भारत सरकार Government of India विद् युत मंालय Ministry of Power केीय विद् युत ाविकरण Central Electricity Authority विद् युत शि सिेण और भार पूिाानुमान भाग Power Survey & Load Forecasting Division Quarterly Report on Mock Drill Exercises carried out by Various Establishments of Power Sector (April 2019 to June 2019)

Upload: others

Post on 23-Apr-2020

12 views

Category:

Documents


0 download

TRANSCRIPT

भारत सरकार

Government of India

विद्युत मंत्रालय

Ministry of Power

केन्द्रीय विद्युत प्राविकरण

Central Electricity Authority

विद्युत शक्ति सिेक्षण और भार पूिाानुमान प्रभाग

Power Survey & Load Forecasting Division

Quarterly Report on Mock Drill Exercises carried out by Various

Establishments of Power Sector

(April 2019 to June 2019)

1 | P a g e

Index

Sl.

No.

Content Page.

No.

1. Index 1

2. Background 2

3. Highlights of the report 3

4. Photographs of Mock Drill 4-5

5. Mock Drill Exercise Reported by

5.1 NHPC 6-15

5.2 Damodar Valley Corporation 15-16

5.3 NHDC LTD 16

5.4 Telangana State Power Generation Corporation ltd 16-17

5.5 Spectrum Power Generation Ltd., Kakinada, Andhra Pradesh 17

5.6 The West Bengal Power Development Corporation Limited 17

5.7 CESC Limited 17-18

5.8 Torrent Power Limited 18

5.9 Andhra Pradesh Generation Corporation LTD 19

2 | P a g e

Background:

As per provisions under section 37 of the Disaster Management act

2005, each Ministry or Department of Government of India is required to

prepare a Disaster Management Plan. Accordingly, Ministry of power, in

association with CEA, has prepared Crises and Disaster Management Plan

(CMP) for the power sector in consultation with all stakeholders that provides

a framework and direction to the power sector utilities of the country for all

phases of the disaster management cycle.

The CMP for the power sector provides for undertaking periodic mock

drill exercise in the various area of the power sector considering various crisis

situations like terrorist threats / attack & sabotage, bomb threats & bomb

explosions, strike, fire, accidents due to human error/ equipment

malfunction, cyber-attack etc. to ensure the preparedness of various utilities

in handling the emergent/crisis situations. The plan document also provides

for submission of a quarterly report in this regard by each utility to CEA

indicating the outline of crisis situations, response of the various teams,

observations and effectiveness for handling the emergency situation and

scope for improvements etc.

This report is a compilation of various mock drill exercises undertaken

by various establishments of power sector across the width and breadth of

the country during the period of April to June 2019. It would give us an

insight about our preparedness towards handling untoward incidents and

highlights shortcomings, if any, to prepare our self in better ways. The

experiences gained from these reported mock drill exercises would be very

helpful in updating policy guidelines for crisis management and building

capacity for all the stakeholders to address such events more skilfully.

3 | P a g e

Highlight of the report:

The mock drill exercises reported by various establishments during the

quarter ranges from routine drills to some very specific drills. It has been

observed that routine mock drill exercises such as fire, vehicle accident,

terrorist attacks, anonymous bomb threats, failure of back up supply,

electrocution have been carried out by most of the establishments. Apart from

that, occurrence of some other less frequent mock drill exercises has also been

reported such as flood (Chamera Power Station-II, Himachal Pradesh),

Chlorine Leakage (Sagardighi Thermal Power Project, West Bengal), Acid

Leakage (Southern Generating Station, West Bengal)

A summary of number of mock drill exercises reported by various

establishment is given below:

Sl.

No.

Establishments Number of Mock Drill

Exercises Reported

1. NHPC

93

2. Damodar Valley Corporation

9

3. NHDC LTD

2

4. Telangana State Power Generation

Corporation Ltd

2

5. Spectrum Power Generation Ltd.,

Kakinada, Andhra Pradesh

1

6. The West Bengal Power Development

Corporation Limited

3

7. CESC Limited

10

8. Torrent Power

1

9. Andhra Pradesh Power Generation

Corporation LTD

1

Total

122

4 | P a g e

5 | P a g e

Quarterly Mock Drill Report for the period of April to June 2019

Sl. No

Name of Establishment State Location Scenario Date & Time

Observations/Recommendation /Suggestions/ Activity performed

Name of Organization: NHPC

1. Bairasiul Power Station, Chamba

Himachal Pradesh

Power House Fire 29.06.2019 at 12.15 hrs

System was working satisfactory.

2. Bairasiul Power Station, Chamba

Himachal Pradesh

Main gate Bomb threat 28.04.2019 at 11.00 hrs

Unit in-charge de-briefed to all forcepersonnel and appreciated the workdone by team.

3. Bairasiul Power Station, Chamba

Himachal Pradesh

Unit Line Armed Attack 31.05.2019 at 16.25 hrs

All the functionaries participated incomplete coordination and the drillwas completed successfully.

4. Chamera Power Station-1,Chamba

Himachal Pradesh

Power House Bomb Threat/Terrorist Attack

28.04.2019 at 16:00 hrs

All the functionaries participated incomplete coordination and the drillwas completed successfully.

5. Chamera Power Station-1,Chamba

Himachal Pradesh

Switchyard Failure of Back-up Power

29.06.2019at 15:15 hrs.

Mock drill was completed successfully.

6. Chamera Power Station-1,Chamba

Himachal Pradesh

Unit Line,CISF Bomb Threat/Terrorist Attack

31.05.2019 at 11:10 hrs

Mock drill was completed successfully.

7. Chamera Power Station-1,Chamba

Himachal Pradesh

Sanjpoi Store Electrocution 19.06.2019 at 11:30 hrs

Mock drill was completed successfully.

8. Chamera Power Station-1, Himachal Boat Engine Boat Engine 14.06.2019 Mock drill was completed successfully.

6 | P a g e

Sl. No

Name of Establishment State Location Scenario Date & Time

Observations/Recommendation /Suggestions/ Activity performed

Chamba Pradesh Failure failure at 11:00 hrs

9. Chamera Power Station-1,Chamba

Himachal Pradesh

Switchyard Failure of back Power

31.05.2019 at 11:10 hrs

Mock drill was completed successfully.

10. Chamera Power Station-1,Chamba

Himachal Pradesh

Workshop Fire 11.04.2019at 14:50 hrs

Mock drill was completed successfully.

11. Chamera Power Station-1,Chamba

Himachal Pradesh

Power House Failure of back Power

23.04.2019 at 12:10 hrs

Mock drill was completed successfully.

12. Chamera Power Station-1,Chamba

Himachal Pradesh

Workshop Vehicle Accident

13.06.2019at 11:12 hrs

Mock drill was completed successfully.

13. Chamera Power Station-1,Chamba

Himachal Pradesh

Hospital Fire at Hospital

06.06.2019at 15:45 hrs

Mock drill was completed successfully.

14. Chamera Power Station-1,Chamba

Himachal Pradesh

Dam control Room

Boat Engine failure

14.06.2019 at 11:20 hrs

Mock drill was completed successfully.

15. Chamera Power Station-II,Chamba

Himachal Pradesh

Power Station Failure of backup power

26.04.2019 at 13:25 hrs

All the functionaries participated in complete coordination and the drill was completed successfully.

16. Chamera Power Station-II,Chamba

Himachal Pradesh

Power House Bomb Threat 28.04.2019 at 11:00 hrs

Mock drill was completed successfully.

7 | P a g e

Sl. No

Name of Establishment State Location Scenario Date & Time

Observations/Recommendation /Suggestions/ Activity performed

17. Chamera Power Station-II,Chamba

Himachal Pradesh

Power House Flood 26.04.2019 at 12:00 hrs

Mock drill was completed successfully.

18. Chamera Power Station-II,Chamba

Himachal Pradesh

Control Room, Power Station

Failure of backup power

21.06.2019 at 10:42 hrs

Mock drill was completed successfully.

19. Chamera Power Station-II,Chamba

Himachal Pradesh

DG set Armed Attack 31.05.2019 at 15:55 hrs

Force personnel were suggesteddifferent approaches to tackle suchsituation.

20. Chamera Power Station-II,Chamba

Himachal Pradesh

Chamera-II,Baandh.

Armed attack 29.06.2019 at 12:30 hrs

Mock drill was completed successfully.

21. Chamera Power Station-II,Chamba

Himachal Pradesh

Bagga Bandh Electrocution 21.06.2019 at 13:15 hrs

Mock drill was completed successfully.

22. Chamera Power Station-II,Chamba

Himachal Pradesh

Bandh Boat engine failure

08.05.2019at 10:15 hrs

Mock drill was completed successfully.

23. Chamera Power Station-II,Chamba

Himachal Pradesh

CISF Area Accident of Vehicle

31.05.2019 at 04:15 hrs

Mock drill was completed successfully.

24. Chamera Power Station-II,Chamba

Himachal Pradesh

Quarter GuardCISF Unit

To safe guardWeapons of Guard.

31.05.2019at 16:00 hrs

Mock drill was completed successfully.

25. Chamera Power Station-III, Chamba

Himachal Pradesh

Power House Electrocution 27.04.2019at 12:05 hrs

Mock drill was completed successfully.

8 | P a g e

Sl. No

Name of Establishment State Location Scenario Date & Time

Observations/Recommendation /Suggestions/ Activity performed

26. Chamera Power Station-III, Chamba

Himachal Pradesh

Main Gate Failure of backup Power

28.05.2019 at 16:00 hrs

Mock drill was completed successfully.

27. Chamera Power Station-III, Chamba

Himachal Pradesh

Project Site Bomb Threat 28.04.2019 at 16:00 hrs

Mock drill was completed successfully.

28. Chamera Power Station-III, Chamba

Himachal Pradesh

Power House Fire 28.05.2019at 15:30 hrs

Mock drill was completed successfully.

29. Chamera Power Station-III, Chamba

Himachal Pradesh

Inside Power House of CPS-III

Accident of Vehicle

26.06.2019at 12:20 hrs

Mock drill was completed successfully.

30. Chamera Power Station-III, Chamba

Himachal Pradesh

Dharwala colony,CPS-III

Failure of backup Power

10.06.2019 at 12:30 hrs

Mock drill was completed successfully.

31. Chamera Power Station-III, Chamba

Himachal Pradesh

CHEP-III Lines Lothal.

Armed Terrorist attack

31.05.2019at 16:30 hrs

Mock drill was completed successfully.

32. Chamera Power Station-III, Chamba

Himachal Pradesh

Quarter Guard. Armed Terrorist attack

29.06.2019at 16:30 hrs

Mock drill was completed successfully.

33. Chamera Power Station-III, Chamba

Himachal Pradesh

Dam Kharamukh.

Electrocution 27.04.2019at 12:05 hrs

Mock drill was completed successfully.

34. Chutak Power Station Jammu andKashmir

Barrage complex

Firefighting System

11.06.2019at 16:10 hrs

Mock drill was completed successfully.

9 | P a g e

Sl. No

Name of Establishment State Location Scenario Date & Time

Observations/Recommendation /Suggestions/ Activity performed

35. Dhauliganga Power Station, Tapovan Pithoragarh

Uttarakhand

DGPS Administrative Building.

Application ofFireExtinguisher

27.06.2019 at 11:10 hrs

Regular training and awareness to the staff to avoid any fire incident.

36. Dhauliganga Power Station, Tapovan Pithoragarh

Uttarakhand

P/H DG Room, Elagad

Failure ofbackup Power.

08.05.2019 at 16:00 hrs

Mock drill was completed successfully.

37. Dhauliganga Power Station, Tapovan Pithoragarh

Uttarakhand

Line area from river side.

Armed attackon Unit line

28.05.2019 at 14:00 hrs

Mock drill was completed successfully.

38. Dhauliganga Power Station, Tapovan

Uttarakhand

Central store plant area

Bomb Threat 26.06.2019 at 16:00 hrs

Mock drill was completed successfully.

39. Dhauliganga Power Station, Tapovan Pithoragarh

Uttarakhand

Main Gate Bomb Threat 28.04.2019 at 11:00 hrs

Mock drill was completed successfully.

40. Dulhasti Power Station Jammu & Kashmir

Near Field Hostel of DPS.

Armed attack 29.06.2019at 16:00 hrs

Mock drill was completed successfully.

41. Kishanganga Power Station, Bandipora

Jammu andKashmir

Dam site Armed attack 31.05.2019at 11:00 hrs

Practice classes may be increased to enhance coordination.

42. Kishanganga Power Station, Bandipora

Jammu andKashmir

Dam site Armed attack 29.06.2019at 16:00 hrs

Practice classes may be increased to enhance coordination.

43. Kishanganga Power Station, Bandipora

Jammu andKashmir

01, NHPC campus

Earth quake 22.06.2019at 11:00 hrs

Practice classes may be increased to enhance coordination.

10 | P a g e

Sl. No

Name of Establishment State Location Scenario Date & Time

Observations/Recommendation /Suggestions/ Activity performed

44. Kishanganga Power Station, Bandipora

Jammu andKashmir

01, NHPC campus

Bomb threat 28.04.2019at 11:00 hrs

Practice classes may be increased to enhance coordination.

45. Loktak Power Station, Churachandpur

Manipur Power House canteen area.

Fire at PowerHouse.

15.06.2019 at 14:00 hrs

Mock drill was completed successfully.

46. Parbati -II, Nagwain Distt Mandi

Himachal Pradesh

Electrical complex, PHEP-II

Electrical shock

06.05.2019at 10:30 hrs

Mock drill was completed successfully.

47. Parbati -II, Nagwain Distt Mandi

Himachal Pradesh

Nagwain complex, PHEP-II

Bomb threat 13.05.2019 at 11:30 hrs

Mock drill was completed successfully.

48. Parbati -II, Nagwain Distt Mandi

Himachal Pradesh

Gammon CMC Workshop

Fire 13.06.2019at 10:00 hrs

Mock drill was completed successfully.

49. Parbati -II, Nagwain Distt Mandi

Himachal Pradesh

Nagwain complex,PHEP-II

Earth quake 29.05.2019at 11:00 hrs

Mock drill was completed successfully.

50. Parbati -III, Behauli, Kullu Himachal Pradesh

Fire in MachineHall

Fire in Machine Hall

12.06.2019 at 11:03 hrs

Mock drill was completed successfully.

51. Parbati -III, Behauli, Kullu Himachal Pradesh

Power House Bomb Threat 28.04.2019 at 11:00 hrs

Mock drill was completed successfully.

52. Parbati -III, Behauli, Kullu Himachal Pradesh

Dam area Armed Attack 31.05.2019 at 16:30 hrs

Mock drill was completed successfully.

11 | P a g e

Sl. No

Name of Establishment State Location Scenario Date & Time

Observations/Recommendation /Suggestions/ Activity performed

53. Parbati -III, Behauli, Kullu Himachal Pradesh

GSS Area Accident of the vehicle

14.06.2019 at 16:00 hrs

Mock drill was completed successfully.

54. Parbati -III, Behauli ,Kullu Himachal Pradesh

GSS Area Electrocution 15.06.2019 at 16:00 hrs

Mock drill was completed successfully.

55. Parbati -III, Behauli, Kullu Himachal Pradesh

Quarter Guard Area

Armed Attack 29.06.2019 at 17:00 hrs

Mock drill was completed successfully.

56. Rangit Power Station Sikkim Rangit Dam Failure of boatengine.

02.05.2019 at 10:30 hrs

Mock drill was completed successfully.

57. Rangit Power Station Sikkim Control Room, ECD

Back-up Power Failure

25.06.2019 at 16:17 hrs

Mock drill was completed successfully.

58. Rangit Power Station Sikkim Control Room, ECD

Electrocution 28.06.2019at 11:00 hrs

Mock drill was completed successfully.

59. Rangit Power Station Sikkim Near Bailey Bridge, Power House

Accident of vehicle

04.06.2019at 11:00 hrs

Mock drill was completed successfully.

60. Salal Power Station, Jyotipuram

Jammu & Kashmir

Bidda DPH. Electrocution 15.06.2019 at 12.10 hrs

Mock drill was completed successfully.

61. Salal Power Station, Jyotipuram

Jammu & Kashmir

Dhyangarh Workshop.

Fire 22.04.2019 at 12:30 hrs

Mock drill was completed successfully.

12 | P a g e

Sl. No

Name of Establishment State Location Scenario Date & Time

Observations/Recommendation /Suggestions/ Activity performed

62. Salal Power Station, Jyotipuram

Jammu & Kashmir

Barrier-I duty Post Jyotipuram

Bomb threat 28.04.2019 at 11:00 hrs

Mock drill was completed successfully.

63. Salal Power Station, Jyotipuram

Jammu & Kashmir

HMWS Dhyangarh.

Bomb threat 29.06.2019 at 16:00 hrs

Mock drill was completed successfully.

64. Salal Power Station, Jyotipuram

Jammu & Kashmir

Switchyard,Dhyangarh.

Armed Attack 31.05.2019 at 16:30 hrs

Mock drill was completed successfully.

65. Sewa –II Power Station Mashka, Kathua

Jammu & Kashmir

Power House Accident of Vehicle

20.06.2019 at 11:00 hrs

Mock drill was completed successfully.

66. Sewa –II Power Station Mashka, Kathua

Jammu & Kashmir

Dam Site Armed Attack 31.05.2019 at 16:30 hrs

Mock drill was completed successfully.

67. Sewa –II Power Station Mashka, Kathua

Jammu & Kashmir

Dam Site Bomb threat 28.04.2019at 11:00 hrs

Mock drill was completed successfully.

68. Sewa –II Power Station Mashka, Kathua

Jammu & Kashmir

Work Shop Fire 01.06.2019at 11:00 hrs

Mock drill was completed successfully.

69. Sewa –II Power Station Mashka, Kathua

Jammu & Kashmir

Power Station Electrocution and failure of backup Power

20.06.2019at 14:30 hrs

Mock drill was completed successfully.

70. Sewa –II Power Station Mashka, Kathua

Jammu & Kashmir

Plant Area Bomb threat 29.06.2019at 16:00 hrs

Mock drill was completed successfully.

13 | P a g e

Sl. No

Name of Establishment State Location Scenario Date & Time

Observations/Recommendation /Suggestions/ Activity performed

71. Tanakpur Power Station,Champawat, Banbassa

Uttarakhand

DPH Barrage Failure of Power backup.

28.06.2019 at 11:32 hrs

Any action should be taken after proper communication between DPH Barrage and DPH Banbassa.

72. Tanakpur Power Station,Champawat, Banbassa

Uttarakhand

Main gate Bomb threat 28.04.2019 at 11:00 hrs

Mock drill was completed successfully.

73. Tanakpur Power Station,Champawat, Banbassa

Uttarakhand

Unit Line. Armed attack 28.05.2019 at 14:00 hrs

Mock drill was completed successfully.

74. Tanakpur Power Station,Champawat, Banbassa

Uttarakhand

Quarter guard. Terrorist armed attack.

26.06.2019 at 16:00 hrs

Mock drill was completed successfully.

75. Teesta-V Power Station, Balutar

Sikkim Zero Point,Balutar

Fire mock drillat zero point.

12.06.2019 at 13:00 hrs

More Seriousness and attentionneeded to be inculcated among theemployees and the workers.

76. Teesta-V Power Station, Balutar

Sikkim Fire Station, Vehicle Accident

28.06.2019 at 15:10 hrs

Seriousness and attention needed to be inculcated among the employees and the workers.

77. Teesta-V Power Station, Balutar

Sikkim Teesta river near Switch yard.

Drowning. 29.06.2019 at 13:00 hrs

The demonstrations were conducted successfully.

78. Teesta-V Power Station, Balutar

Sikkim EMD Dam Failure of backup power

20.06.2019 at 11:40 hrs

The demonstrations were conducted successfully.

79. Teesta-V Power Station, Balutar

Sikkim 11 kV switch yard

Electrocution. 29.06.2019 at 11:55 hrs

Awarness for use of PPEs and first aidhas to be improved.

14 | P a g e

Sl. No

Name of Establishment State Location Scenario Date & Time

Observations/Recommendation /Suggestions/ Activity performed

80. Teesta Low Dam–IV Power Station, Kalijhora, Darjeeling

West Bengal Control Room Failure of backup Power

17.06.2019 at 12:00 hrs

Mock drill was completed successfully.

81. Teesta Low Dam–IV Power Station Kalijhora, Darjeeling

West Bengal Switch Yard Intrusion of unknown Persons

13.05.2019 at 16:00 hrs

Mock drill was completed successfully.

82. Teesta Low Dam–IV Power Station Kalijhora, Darjeeling

West Bengal Near CISF Barrack area

Bomb threat 24.06.2019 at 16:00 hrs

Mock drill was completed successfully.

83. Teesta Low Dam–IV Power Station Kalijhora, Darjeeling

West Bengal Control Room Failure of Backup Power

23.04.2019 at 12:00 hrs

Mock drill was completed successfully.

84.TLD-III Power StationRambi, Darjeeling

West Bengal Store complex, sector-A

Armed attack 24.06.2019at 17:00 hrs

Mock drill was completed successfully.

85. TLD-III Power StationRambi, Darjeeling

West Bengal Canteen,Dam Gate-2,Silt Lab

Armed attack 16.05.2019at 16:20 hrs

Mock drill was completed successfully.

86. Uri - I Power Station, Mohura, Baramulla

Jammu & Kashmir

Barrage area Power backup failure.

29.06.2019 at 11:30 hrs

Mock drill was completed successfully.

87. Uri - I Power Station, Mohura, Baramulla

Jammu & Kashmir

Power house Fire 29.06.2019 at 12:15 hrs

Mock drill was completed successfully.

88. Uri - I Power Station, Mohura, Baramulla

Jammu & Kashmir

CISF UNIT Bomb threat 28.04.2019 at 11:00 hrs

Mock drill was completed successfully.

15 | P a g e

Sl. No

Name of Establishment State Location Scenario Date & Time

Observations/Recommendation /Suggestions/ Activity performed

89. Uri - I Power Station, Mohura, Baramulla

Jammu & Kashmir

Pringal Out post

Armed attack 29.06.2019 at 16:00 hrs

Mock drill was completed successfully.

90. Uri - I Power Station, Mohura, Baramulla

Jammu & Kashmir

Unit /BN Armed attack 31.05.2019 at 16:30 hrs

Mock drill was completed successfully.

91. Uri - II Power Station, Mohura, Baramulla

Jammu & Kashmir

Near Badminton court, Nowpora

Fire at vital location.

11.06.2019at 11:00 hrs

Mock drill was completed successfully.

92. Uri - II Power Station, Mohura, Baramulla

Jammu & Kashmir

Dam approach gate area.

Terrorist armed attack.

31.05.2019at 16:30 hrs.

Mock drill was completed successfully.

93. Uri - II Power Station, Mohura, Baramulla

Jammu & Kashmir

Nursery school Fire at vital location.

14.06.2019at 16:00 hrs

Mock drill was completed successfully.

Name of the Plant: Damodar Valley Corporation

94. Bokaro Thermal Power station

Jharkhand Bokaro Thermal

To neutralizetoxic fumes ofChlorine

15.04.2019 All the functionaries participated in complete coordination and the drill was completed successfully.

95. Bokaro Thermal Power station

Jharkhand Bokaro Thermal

Fire Call 17.04.2019 All the functionaries participated in complete coordination and the drill was completed successfully.

96. Bokaro Thermal Power station

Jharkhand Bokaro Thermal

Anti-social element attack

23.04.2019 All the functionaries participated in complete coordination and the drill was completed successfully.

16 | P a g e

Sl. No

Name of Establishment State Location Scenario Date & Time

Observations/Recommendation /Suggestions/ Activity performed

97. Bokaro Thermal Power station

Jharkhand Bokaro Thermal

Fire call 13.05.2019 All the functionaries participated in complete coordination and the drill was completed successfully.

98. Bokaro Thermal Power station

Jharkhand Bokaro Thermal

Fire Call 22.05.2019 All the functionaries participated in complete coordination and the drill was completed successfully.

99. Bokaro Thermal Power station

Jharkhand Bokaro Thermal

Anti-social element attack

20.05.2019 All the functionaries participated in complete coordination and the drill was completed successfully.

100. Bokaro Thermal Power station

Jharkhand Bokaro Thermal

Fire call 15.06.2019 All the functionaries participated in complete coordination and the drill was completed successfully.

101. Bokaro Thermal Power station

Jharkhand Bokaro Thermal

Fire Call 28.06.2019 All the functionaries participated in complete coordination and the drill was completed successfully.

102. Bokaro Thermal Power station

Jharkhand Bokaro Thermal

Anti-social element attack

20.05.2019 All the functionaries participated in complete coordination and the drill was completed successfully.

Name of Organization: NHDC LTD

103. Indira Sagar Power Station, Narmada Nagar

Madhya Pradesh

Parking Area near Access Tunnel

Fire 08.05.2019 at 15:35 hrs

Mock Drill of different nature to be carried out next time.

104. Omkareshwar Power Station, Khandwa

Madhya Pradesh

Power House Fire 21.06.2019 at 16.15 hrs

Mock drill was completed successfully.

17 | P a g e

Sl. No

Name of Establishment State Location Scenario Date & Time

Observations/Recommendation /Suggestions/ Activity performed

Name of Organization: Telangana State Power Generation Corporation ltd

105. K.T.P.S(O&M), PalonchaKhammam

Telangana New Canteen-KTPS/VII Stage.

Fire 15.06.2019 at 10:30 hrs

Mock drill was completed successfully.

106. RTS-B, Ramagundam Telangana Near Cooling tower.

Fire 28.06.2019 at 16.00 hrs.

Mock Drill was conducted satisfactorily.

Name of Organization: Spectrum Power Generation Ltd., Kakinada, Andhra Pradesh

107. Spectrum Power Gas Power Plant, Kakinada

Andhra Pradesh

Unit Transformer #1

Fire 26.06.2019 at 11:55 hrs

Mock Drill was conductedsatisfactorily.

Name of Organization: The West Bengal Power Development Corporation Limited

108. Sagardighi Thermal PowerProject

West Bengal Stg.II-RW Plant Chlorination Unit.

Chlorine Leakage.

21.06.2019 at16:15 hrs

Such drills should be done at allhazardous operation.

109. Bakreswar Thermal PowerProject

West Bengal In front of PlantTechnical Building.

Fire 28.04.2019 at 10:00 hrs

All unwanted materials shall have tobe shifted to scrap yard.

110. Santaldih Thermal Power Project

West Bengal CHP Technical Building.

Fire 17.06.2019 at 16:30 hrs

Mock Drill was conductedsatisfactorily.

18 | P a g e

Sl. No

Name of Establishment State Location Scenario Date & Time

Observations/Recommendation /Suggestions/ Activity performed

Name of Organization: CESC Limited

111. Budge Budge generating Station

West Bengal Rail gate Intrusion of unauthorizedPersonnel.

18.06.2019 at 13:30 hrs

Performance of the Emergencyresponse was found satisfactory.

112. Southern Generating Station

West Bengal DM Plant Acid leakage. 19.06.2019 Pressure in water spray line was notadequate. Difficulty in Mobilecommunication from DM Plant isnoted.

113. Titagarh Generating Station

West Bengal Burner front area.

Fire 23.04.2019 at 16:00 hrs

Mock Drill was conductedsatisfactorily

114. Titagarh Generating Station

West Bengal Ash gate. Armed Intruders

18.06.2019at 15:00 hrs

CCTV coverage & minimizing no ofentry points to the plant arerecommended.

115. CESC Hose, Corporate Office Building.

West Bengal Main gate. Mob control 24.06.2019at 14:00 hrs

Suitable training for Security staff oncrowd management is required.

116. Bantala 220Kv BBGS-EM SS Circuit.

West Bengal Near tower location no 304.

Potable Inflatable Tower lights

20.06.2019 Mock drill for these tower lights arebeing done quarterly.

117. BBD Bag Sub Station West Bengal Project Site Fire Drill 04.06.2019 Mock Drill was conductedsatisfactorily

118. Belur Receiving Station West Bengal Project Site Fire Drill 05.04.2019 Mock Drill was conducted

19 | P a g e

Sl. No

Name of Establishment State Location Scenario Date & Time

Observations/Recommendation /Suggestions/ Activity performed

at 15:00 hrs satisfactorily

119. Park Lane Sub Station West Bengal Project Site Fire Drill 24.04.2019at 15:00 hrs

Mock Drill was conductedsatisfactorily

120. New Cossipore Sub Station

West Bengal Project Site Fire Drill 07.05.2019 at 15:00 hrs

Mock Drill was conductedsatisfactorily

Name of Organization: Torrent Power Limited

121. Torrent Power Limited,Sabarmati,Ahmedabad

Gujarat Garden gate area

Sighting of Unknownperson

22.06.2019at 02:15 hrs

Mock Drill was conductedsatisfactorily

Name of Organization: Andhra Pradesh Power Generation Corporation LTD

122. Rayalaseema ThermalPower Project

Andhra Pradesh

Near unit-V Boiler/stage-III/RTPP

Fire 23.04.201910:45 hrs

The maintenance of fire extinguishers are to be improved.

***************

20 | P a g e