quarterly progress report staff updating & review meeting netherlands leprosy relief, india...
TRANSCRIPT
Quarterly Progress Report
Staff Updating & Review meetingNetherlands Leprosy Relief, India
DHANBAD, 7-8 July 2010
Presented by LPA--Dr. R. N. Sinha
NLR Bihar
Gantt. Chart showingQuarterly Progress Report
S.N.
Activities Jan Feb Mar Apr May Jun
1 Workshop on supervision of supervisors
Planned 0 01 0 01 02 0
Performed 0 01 0 01 0 01
2 ½ day sensitization training of U AWWs
Planned 01 03 0 0 0 01
Performed 01 03 0 0 0 0
3 ½ day training of trainee ANMs of PatnaAnd Bhoj Pur ANMT School
Planned 0 0 0 0 02 (P ) 01 ( Bh )
Performed 0 0 0 0 01 ( Bh )
0
4 Self Care practices in two PHCs
Planned 0 0 02 0 0 0
Performed 0 0 0 01 0 01
Activities Completion Report 20101st & 2nd Quarter
Result Based Activities Allocated Budget for the quarter
Batches Planed
Batches Done
Total Expenditure
Result-1 Supervision system improved.
Workshop on supervision for supervisors x 4 districts.
69,638.00 04 03 36,181
Do x 1 district ( Patna )
- - - -
Result-2 Early case detection improved.
½ day sensitization of Urban AWWsX 5 districts
13000.00 05 04 8960.00
½ day sensitization of trainee ANMs of Patna and Bhoj Pur.
55000.00 + 23000.00=78000.00
03 ANMTSchool
02 11065.00 + 8960.00= 20025.00
Activities Completion Report 20101st & 2nd Quarter Cont…
Result Based Activities Allocated Budget for the quarter
Batches Planed
Batches Done
Total Expenditure
Result-3 DPMR Services improved
Self care practices in 2 PHCs ( one each from Patna & Nawada )
62640.00 02 02 37526.00
Expansion of SCG & Continuing of old projects
24500.00 04+05=09
09 28492.00
Activities not performed
Name of the Activity- 1.Workshop on supervision of supervisors of Aurangabad district-01
batch. 2. UAWWs training of Aurangabad.
Reasons for non-completion- Due to marriage seasons, venue and
vehicle could not be arranged.
Comments Difficulties faced – No due involvement of DN in NLR planned activities.
Different calendar of NLR and DN.
Expectations from District/State/NLR
NLR activities to be included in District action plan. State should issue instructions in this regard. NLR must inform state about the activities.
Gantt chart for July’10 to Dec’10
Result- Early case detection improved
S.n. Activity July Aug Sept OCT Nov Dec
1 Sensitization training of Trainee ANMs Of ANMT School (a) GGS Patna (b) Barha ( Patna )
Done
█2. Sensitization training of
Urban AWWsOf Aurangabad district
█
3. Sensitization training of Cont ANMsBhoj Pur
█4. Buxar Sensitization training
of ANMs █
Gantt chart for July’10 to Dec’10 Result- Supervision
system improved.S.n. Activity July Aug Sept OCT Nov Dec
1 Workshop on supervision of supervisors-Patna district
█
2. Workshop on supervision of supervisors-Aurangabad district
█
Result- Programme management improved
1 Decentralised Planning and management training of DN of wholeBihar.
█
Re