QUALITY IN CONSTRUCTION WORKS
DR. K.M. SONICHIEF ENGINEER, CPWD, MUMBAI
![Page 2: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/2.jpg)
QUALITY MOST COMMONLY USED MOST DIFFICULT TO DEFINE PREDICTABLE DEGREE OF
UNIFORMITY, DEPENDABILITY, AT LOW COST SUITED TO THE MARKET (DEMING)
FITNESS FOR USE (JURAN)
23rd October 2016 2Quality in Construction Works -
Dr K M Soni
![Page 3: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/3.jpg)
QUALITY CONFORMANCE TO
REQUIREMENTS (CROSBY) LOSS IMPARTED BY A
PRODUCT TO SOCIETY (TAGUCHI)
CORRECTING AND PREVENTING LOSS , NOT LIVING WITH LOSS (HOSHIN)
23rd October 2016 3Quality in Construction Works -
Dr K M Soni
![Page 4: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/4.jpg)
QUALITY(ISO) Defined as “The totality of
characteristics of an entity that bears on its abil i ty to satisfy stated and implied needs”
23rd October 2016 4Quality in Construction Works -
Dr K M Soni
![Page 5: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/5.jpg)
ENTITY Entity may be a product, process
or even an organization Construction has product as well
as process
23rd October 2016 5Quality in Construction Works -
Dr K M Soni
![Page 6: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/6.jpg)
STATED NEEDS Stated needs may be available in
the form of specif ications, conditions or bil l of quantit ies
23rd October 2016 6Quality in Construction Works -
Dr K M Soni
![Page 7: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/7.jpg)
23rd October 2016 7Quality in Construction Works -
Dr K M Soni
![Page 8: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/8.jpg)
23rd October 2016 8Quality in Construction Works -
Dr K M Soni
![Page 9: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/9.jpg)
23rd October 2016 9Quality in Construction Works -
Dr K M Soni
![Page 10: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/10.jpg)
IMPLIED NEEDS Not defined Sometimes not even expressed Even may be unspoken needs
23rd October 2016 10Quality in Construction Works -
Dr K M Soni
![Page 11: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/11.jpg)
Implied Needs Implied needs are part of the
dimensions of quality. The dimensions of quality for a
product and Service
23rd October 2016 11Quality in Construction Works -
Dr K M Soni
![Page 12: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/12.jpg)
Product Dimensions are performance,
features, reliabil i ty, conformity to specifications /standards, durabil i ty, serviceabil ity, aesthetics and perceived quality.
23rd October 2016 12Quality in Construction Works -
Dr K M Soni
![Page 13: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/13.jpg)
Service Time and timeliness service,
completeness, consistence, courtesy, accessibil i ty and convenience, and responsiveness are the dimensions of quality for a service
23rd October 2016 13Quality in Construction Works -
Dr K M Soni
![Page 14: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/14.jpg)
Works Thus for a construction work, the
dimensions of a product as well as a service are to be considered for a quality work. In fact, product plays a major role during construction and service dimensions play a major role during maintenance
23rd October 2016 14Quality in Construction Works -
Dr K M Soni
![Page 15: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/15.jpg)
https://blog.codinghorror.com/the-iron-stool/23rd October 2016 15
Quality in Construction Works - Dr K M Soni
![Page 16: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/16.jpg)
QUALITY DIFFICULT TO EXPRESS LIKE BEAUTY CUSTOMER ORIENTED
23rd October 2016 16Quality in Construction Works -
Dr K M Soni
![Page 17: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/17.jpg)
QUALITY Is it not achievable? Quality gurus do not agree to the
statement that quality is not achievable.
23rd October 2016 17Quality in Construction Works -
Dr K M Soni
![Page 18: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/18.jpg)
ABOUT QUALITY (CROSBY) Quality is free quality is not: luxury,
unaffordable, intangible therefore not measurable
Quality is not: originated by workers or something that originates in the quality department
23rd October 2016 18Quality in Construction Works -
Dr K M Soni
![Page 19: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/19.jpg)
Basic tenets Quality improvement is everlasting
process Quality philosophy begin at the top QC dept. should believe in zero
defects Quality education and training should
be excellent Mgt. is patience and never ceases its
concern for quality 23rd October 2016 19
Quality in Construction Works - Dr K M Soni
![Page 20: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/20.jpg)
Deming About 85% of all quality problems are
caused by harmful management practices. It has also been stated that consequently, CEO intent on changing the way production workers perform – without changing the obsolete management system – wil l, at best, address only 15% of the problems.
23rd October 2016 20Quality in Construction Works -
Dr K M Soni
![Page 21: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/21.jpg)
Juran Juran, another quality guru is of
the view that senior managers must personally take charge of leading change related to quality. If they try to delegate that, they wil l not get good results.
23rd October 2016 21Quality in Construction Works -
Dr K M Soni
![Page 22: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/22.jpg)
Ishikawa and Taguchi According to Ishikawa, a Japanese
quality guru, bad quality, meaning wastage, had an effect not only on business creating the waste but also on its customers and on society as a whole. Another Japanese quality guru, Taguchi described quality as the loss imparted to the society from the time a product is shipped and quantif ied as “Loss function”.
23rd October 2016 22Quality in Construction Works -
Dr K M Soni
![Page 23: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/23.jpg)
Quality eras Inspections Quality Control Quality Assurance Total Quality Management
23rd October 2016 23Quality in Construction Works -
Dr K M Soni
![Page 24: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/24.jpg)
Inspections Do not contribute greatly
to reducing the error rate in production.
The problem is addressed after it has arisen.
Thus, even 100 % inspections wil l not mean that all the defects have been removed or rooted out.
23rd October 2016 24Quality in Construction Works -
Dr K M Soni
![Page 25: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/25.jpg)
Quality Control “all those operational techniques and
activit ies that are used to fulf i l l requirements for quality” (ISO). Therefore, emphasis in quality control is on techniques and activit ies. Inspections, monitoring and feedback are carried out in quality control. I t has nothing to do directly with the customer‘s satisfaction. Operational techniques and monitoring also lead to “paper quality” in which the papers assure the quality with or without any consideration of the work.
23rd October 2016 25Quality in Construction Works -
Dr K M Soni
![Page 26: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/26.jpg)
Quality Assurance “all the planned and systematic activit ies,
implemented within the organization for quality management, to provide adequate that a product or service wil l satisfy given requirements for quality.” Therefore, quality assurance is essentially a preventive activity and is therefore to be systematically planned in advance. The activity includes identif ication and planning of the checks, inspection and control of process as a part of quality control.
23rd October 2016 26Quality in Construction Works -
Dr K M Soni
![Page 27: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/27.jpg)
Quality Assurance Quality assurance also means
establishment of a quality system which can demonstrate the requirements. Unfortunately, in many organizations, names have changed from the quality control units to quality assurance units without any change in the working or strategy or even in the atti tude of the quality personnel.
23rd October 2016 27Quality in Construction Works -
Dr K M Soni
![Page 28: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/28.jpg)
http://microjcode.com/quality-assurance-qa/
23rd October 2016 28Quality in Construction Works -
Dr K M Soni
![Page 29: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/29.jpg)
https://quotesgram.com/process-quality-quotes/
23rd October 2016 29Quality in Construction Works -
Dr K M Soni
![Page 30: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/30.jpg)
TQM Whole idea of quality is to reduce
error whether human, machine, method, material or information. This error can be caused at any stage of management and workers and thus, involvement of everyone is essential in TQM.
23rd October 2016 30Quality in Construction Works -
Dr K M Soni
![Page 31: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/31.jpg)
Concept of TQM Question is whether error can be
stopped and the answer is very simple – no as it is natural to make errors. But the errors have to be eliminated and not at later stage but right at the stage it is l ikely to occur or it has occurred by preventing it or correcting it as the case may be. It cannot be passed on to other person or process. Thus, TQM includes self inspection.
23rd October 2016 31Quality in Construction Works -
Dr K M Soni
![Page 32: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/32.jpg)
TQM TQM means “Total” in every product, every process, every job and every person.
23rd October 2016 32Quality in Construction Works -
Dr K M Soni
![Page 33: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/33.jpg)
https://www.linkedin.com/pulse/customer-focus-tqm-paul-weenink23rd October 2016 33
Quality in Construction Works - Dr K M Soni
![Page 34: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/34.jpg)
TQM TQM is also a philosophy based
on the quest for progress and continuous improvement. In Japanese, process of continuous improvement has been termed as Kaizen.
23rd October 2016 34Quality in Construction Works -
Dr K M Soni
![Page 35: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/35.jpg)
Waste Analysis In quality improvement, waste and total cost
must reduce. Quality improvement can only result from planned management action. Importance of TQM can be understood from the statement of Crosby’s four eras of quality as organizations adopting inspections only say, “We don’t know why we have quality problems” while in TQM, they say,”We know why we don’t have quality problems”.
23rd October 2016 35Quality in Construction Works -
Dr K M Soni
![Page 36: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/36.jpg)
https://www.pinterest.com/pin/368239707006749600/23rd October 2016 36
Quality in Construction Works - Dr K M Soni
![Page 37: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/37.jpg)
TQM TEAMWORK PARTICIPATORY APPROACH CUSTOMER ORIENTED ZERO DEFECTS
23rd October 2016 37Quality in Construction Works -
Dr K M Soni
![Page 38: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/38.jpg)
http://kalyan-city.blogspot.in/2012/04/how-to-implement-total-quality.html
23rd October 2016 38Quality in Construction Works -
Dr K M Soni
![Page 39: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/39.jpg)
TQM BELIEFS PEOPLE ARE UNTAPPED
RESOURCES PEOPLE WHO DO THE WORK
ARE IN THE BEST POSITION TO IMPROVE ORGANIZATIONAL PROCESS
CONTINUAL IMPROVEMENT
23rd October 2016 39Quality in Construction Works -
Dr K M Soni
![Page 40: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/40.jpg)
Contd. Values drive behaviour Prevention as opposed to
detection Organization wide involvement
and commitment
23rd October 2016 40Quality in Construction Works -
Dr K M Soni
![Page 41: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/41.jpg)
Crosby 14 steps Crosby has described fourteen step
programme to achieve quality as management commitment, quality improvement teams, quality measurement, cost of quality evaluation, quality awareness, corrective action, zero defects planning, supervisory training, zero-defects day, goal sett ing, errors cause removal, recognit ion, quality councils and ‘do it al l over again’.
23rd October 2016 41Quality in Construction Works -
Dr K M Soni
![Page 42: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/42.jpg)
Deming’s 14 Points create constancy of purpose, adopt new
philosophy, cease dependence on mass inspections, end the practice of awarding business on the price tag only, improve constantly and forever the system of production and service, inst itute training, inst itute leadership, drive out fear, break down barriers between staff areas, eliminate slogans, exhortations, and targets for the workforce, eliminate numerical quotas, remove barriers to pride of workmanship, inst itute a vigorous program of education and training and take action to accomplish the transformation. 23rd October 2016 42
Quality in Construction Works - Dr K M Soni
![Page 43: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/43.jpg)
QUALITY, QUANTITY AND SPEED IS IT POSSIBLE TO ACHIEVE
ALL THREE? IT IS SAID TO OPT FOR TWO
OUT OF THREE. WHICH TWO?
23rd October 2016 43Quality in Construction Works -
Dr K M Soni
![Page 44: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/44.jpg)
QUALITY Vs Mechanization Mechanization is defined as the use of
machines to replace manual labour or animals and can also refer to the use of powered machinery to help a human operator in some task. The use of hand operated tools is not the part of the mechanization but it is really a matter of concern that even these tools are not the part of every construction process.
23rd October 2016 44Quality in Construction Works -
Dr K M Soni
![Page 45: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/45.jpg)
Benefits of Mechanization improvement in productivity,
quality, speed, construction technology advancement, industrial technology advancement, economy due to scale of work, employment potential etc. &
23rd October 2016 45Quality in Construction Works -
Dr K M Soni
![Page 46: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/46.jpg)
Mechanization Mechanization helps in the quality of
product and in improving process capabil i ty to improve the process to provide a major contribution in TQM.
Mechanization thus helps in improving the quality by way of three reasons which are the basic components in civi l engineering construction i.e. labour, product (material) and process (method of construction).
23rd October 2016 46Quality in Construction Works -
Dr K M Soni
![Page 47: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/47.jpg)
Mechanization Ultimately mechanization helps in
productivity and also brings down the cost due to reduction in poor quality costs. It ensures the dimensions of the quality and thus enhances customer satisfaction
23rd October 2016 47Quality in Construction Works -
Dr K M Soni
![Page 48: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/48.jpg)
Continuous Improvement
TQM is not one time concept and is based on continuous improvement. Hence continuous improvement is essential in product, process, and management.
Education and training are very important for continuous improvement process.
23rd October 2016 48Quality in Construction Works -
Dr K M Soni
![Page 49: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/49.jpg)
TQM Therefore, the management has to believe
f irst in TQM concept that the same is possible and then make sure that education and training is imparted to all their employees. Early in the process, all levels of management must be trained to implement their part of the quality improvement programme. Continuous improvement helps in customer delight i.e. the state in which customer gets more than what he expects for satisfaction.
23rd October 2016 49Quality in Construction Works -
Dr K M Soni
![Page 50: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/50.jpg)
Personnel in civi l works Architects Engineers Contractors Accountants Clients Suppliers
23rd October 2016 50Quality in Construction Works -
Dr K M Soni
![Page 51: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/51.jpg)
TQM TOTAL, QUALITY,
MANAGEMENT IN ALL PERSONNEL INVOLVED IN A CIVIL WORK
IS IT POSSIBLE? HOW?
23rd October 2016 51Quality in Construction Works -
Dr K M Soni
![Page 52: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/52.jpg)
QUALITY IN (T,Q,M) ARCHITECTS ENGINEERS CONSULTANTS CONTRACTORS QUALITY MANAGERS SUPPLIERS
23rd October 2016 52Quality in Construction Works -
Dr K M Soni
![Page 53: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/53.jpg)
ACCIDENTS ARE CAUSED BY UNSAFE ACT: ATTRIBUTED TO
INDIVIDUAL UNSAFE CONDITIONS:
ATTRIBUTED TO ENGINEERING – ENGINEERS/MANAGEMENT RESPONSIBILITY
23rd October 2016 53Quality in Construction Works -
Dr K M Soni
![Page 54: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/54.jpg)
SAFETY AND QUALITY COMPLEMENTARY SAFE STRUCTURE SAFE MATERIALS SAFE CONSTRUCTION SAFE ENVIRONMENT
23rd October 2016 54Quality in Construction Works -
Dr K M Soni
![Page 55: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/55.jpg)
APPROACH TOWARDS SAFETY SWAMP : SAFETY WITHOUT
ANY MANAGEMENT PROCESS (16%)
NORM : THE NATURALLY OCCURING REACTIVE MANAGEMENT – RELUCTANT COMPLIERS (77%)
WORLD CLASS: WHERE MOST ARE READY TO COMPLY (7%)
23rd October 2016 55Quality in Construction Works -
Dr K M Soni
![Page 56: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/56.jpg)
SAFETY COST DIRECT COST
MEDICAL CARE COMPENSATION LOSS OF PROPERTY/EQUIPMENT REPLACEMENT COST
INDIRECT COST LOSS OF PRODUCTION COST OF TIME SPENT ON
INVESTIGATION COST OF TIME SPENT WITH
REGULATORY AUTHORITIES23rd October 2016 56Quality in Construction Works -
Dr K M Soni
![Page 57: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/57.jpg)
CONTRACT AND QUALITY QUALITY IN CONTRACT
DOCUMENT SAFETY IN CONTRACT
DOCUMENT NOTHING COMES FREE” – PAY
FOR IT, ULTIMATELY IT MAY BE REWARDING
23rd October 2016 57Quality in Construction Works -
Dr K M Soni
![Page 58: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/58.jpg)
QUALITY IS NOT ABSOLUTE SPECIFICATIONS THAT CONCERNS ONLY TO
WORKERS OR ENGINEERS
23rd October 2016 58Quality in Construction Works -
Dr K M Soni
![Page 59: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/59.jpg)
QUALITY IS RELATIVE TERM THAT SATISFIES CUSTOMER NEEDS STARTS FROM TOP PLAN, DO, CHECK, ACT CYCLE FUNCTION OF DURABILITY, SAFETY,
CONTRACT DOCUMENT, HRD, MECHANIZATION
RELATED TO QUANTITY AND SPEED
23rd October 2016 59Quality in Construction Works -
Dr K M Soni
![Page 60: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/60.jpg)
QUALITY CANNOT BE ACHIEVED ONLY THROUGH INSPECTIONS/QC/QA WITHOUT CONTRACTOR’
INVOLVEMENT STIPULATION OF MEN, MATERIAL,
METHODS, SAFETY, AND OTHER FACTORS AFFECT QUALITY IN CONTRACT DOCUMENT
ACCEPTANCE OF LOWEST BID IF BELOW MR
HIGH WASTAGE23rd October 2016 60Quality in Construction Works -
Dr K M Soni
![Page 61: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/61.jpg)
QUALITY CAN BE ACHIVED THROUGH T – TOTAL INVOLVEMENT Q – QUALITY/CONTINUOUS
IMPROVEMENT OF SERVICE TO CUSTOMERS, PERSONNEL AND SYSTEM
M – MANAGEMENT : MANAGING THE RESOURCES WITH ZERO WASTAGE
23rd October 2016 61Quality in Construction Works -
Dr K M Soni
![Page 62: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/62.jpg)
THEREFORE, QUALITY IS AN OUTCOME OF A TEAMWORK
23rd October 2016 62Quality in Construction Works -
Dr K M Soni
![Page 63: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/63.jpg)
QUALITY ASSURANCE IN CPWD HAS A MINMUM QA PLAN FOR
ALL THE WORKS ABOVE THE TENDERING LIMITS OF CLASS V CONTRACTORS
23rd October 2016 63Quality in Construction Works -
Dr K M Soni
![Page 64: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/64.jpg)
BASIC PARAMETERS Lot size, number of required tests and
frequency of testing defined Machinery and T & P required to be
deployed by the contractor at site with a time schedule for their availabil i ty.
Testing equipments to be arranged by the contractor along with requirement of sett ing up field laboratory.
23rd October 2016 64Quality in Construction Works -
Dr K M Soni
![Page 65: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/65.jpg)
Contd. Acceptance criterion for various items
of work, materials, workmanship and process indicating the codes, specif ications and standards applicable.
Shuttering schedule showing the quantity of shuttering to be brought at site either in one lot or at different stages of work as per the requirements of the work.
23rd October 2016 65Quality in Construction Works -
Dr K M Soni
![Page 66: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/66.jpg)
Contd. Responsibil i ty of the contractor to
maintain all the registers of tests carried out at site or in outside laboratories.
Method of taking samples in presence of departmental engineers.
Cost of samples and tests to be borne.
23rd October 2016 66Quality in Construction Works -
Dr K M Soni
![Page 67: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/67.jpg)
Contd. Witnessing of tests to be carried
out in f ield lab. Submission of copy of the test
registers before making payments to the contractor.
Procedure of maintenance of Material at Site (MAS) Register.
23rd October 2016 67Quality in Construction Works -
Dr K M Soni
![Page 68: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/68.jpg)
Responsibil i ty Field engineers Overall responsibil i ty with
Superintending Engineer
23rd October 2016 68Quality in Construction Works -
Dr K M Soni
![Page 69: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/69.jpg)
Quality management teams AT CIRCLE LEVEL AT REGIONAL LEVEL AT CENTRAL LEVEL
23rd October 2016 69Quality in Construction Works -
Dr K M Soni
![Page 70: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/70.jpg)
EMPHASIS ON MATERIALS PROCESS
23rd October 2016 70Quality in Construction Works -
Dr K M Soni
![Page 71: Quality in Construction](https://reader034.vdocuments.mx/reader034/viewer/2022042515/587469a71a28abab198b7873/html5/thumbnails/71.jpg)
23rd October 2016 71Quality in Construction Works -
Dr K M Soni