QBS Qualifications-Based Selection
Why Value Outweighs Cost in the Selection of Engineering Services
Detailed Workbook for Qualifications-Based Selection containing:
»Step-by-StepProcedures
»Examples
»History
QBS | Qualifications-Based Selection 1
QBS Table of Contents
1.0 INTRODUCTIONS 2
2.0 HOUSE CONCURRENT RESOLUTION NO. 206 3
3.0 HOW DOES QBS WORK? 4
3.1DevelopingtheGeneralScopeofWork 4
3.2EstablishingaSelectionTimeFrame 5
3.3CompilingaListofDesignProfessionals 5
3.4RequestforQualificationDocuments 6
3.5EvaluatingQualificationSubmittals 7
3.6EstablishingaShortlistofFirmstobeInterviewed 8
3.7BriefingHeldwithShortlistedFirms 8
3.8InterviewingtheShortlistedFirms 9
3.9RankingtheFirmsinContentionforSelection 11
3.10NegotiatingaDetailedScopeofWorkwithSelectedFirm 11
3.11NegotiatingaContractwiththeSelectedFirm 11
3.12Post-SelectionCommunicationsEvaluationofProcess 12
3.13AdditionalDiscussion 12
3.14AssociationswithListsofDesignProfessionalFirms 13
4.0 INFORMATION AND EXAMPLE MATERIALS 14
4.1RequestforLettersofQualificationSampleMemo 15
4.2RequirementsforLettersofQualification 16
4.3ScheduleofActivities 17
4.4PreliminaryScopeoftheWork 18
4.5Memo–“NotSelectedforInterview” 19
ForFirmsthatSubmittedLetters/StatementsofQualification
4.6MemotoShortlistedFirmstobeInterviewed/Tourof 20
Facilities/andCriteria
4.7Interview:QuestionsandScoreSheets 22
4.8GroupInterviewEvaluationForm 23
4.9MemotoShortlistedFirmWhenTechnicalProposalisRequested 24
4.10TechnicalProposalScoreSheets 25
4.11GroupTechnicalProposalEvaluationForm 26
4.12MemoforAllDesignProfessionalFirmsThatWereInterviewed 27
4.13ReferenceCheck 28
4.14LettersofQualificationsEvaluation 29
4.15OptionalForm–InterviewScoreSheet 31
4.16Example–Interview:QuestionsandScoreSheets 32
4.17Example–GroupInterviewEvaluationForm 33
QBS | Qualifications-Based Selection 2
1.0 INTRODUCTION AND BACKGROUND
What is QBS?
Qualifications-BasedSelection(QBS)isanobjective,flexibleprocedureforobtainingarchitectural,engineering,surveying,andotherrelatedprofessionaldesignservicesonpublicprojects.Itassistsanownerintheselectionprocessiftheownerdoesnotalreadyhaveaprofessionaldesignconsultant.TheQBSprocessishelpfultofrequentusersofdesignservicesaswellasone-timeuserswithlittleornopastpracticalexperienceinworkingwithdesignprofessionals.QBSprovidesownerswithaselectionprocessthatisstraightforwardandeasytoimplement,isobjectiveandfair,canbewelldocumented,andisopentoaudit.QBShasreceivednationalandstateattentioninthepublicsectorthroughlegislationformanyyears.InOctober,1972,thefederalgovernmentenactedPublicLaw92-582coveringtheselectionofarchitectsandengineersbasedonqualifications.ThisbillhassincebeenknownastheBrooksSelectionBill,asitwasintroducedbyU.S.RepresentativeJackBrooksofTexas.TheQBSCoalitionwasformedin1984.In1987,itundertookthechargebytheMichiganLegislatureinHouseConcurrentResolution#206toprovideadocumentedunderstandingoftheprocess.TheQBSCoalitionforMichiganissupportedbythefollowingassociations:
» ACECOFMICHIGAN » MSPE » AGCOFMICHIGAN » MSPS » AIAOFMICHIGAN » MWEA » APWAOFMICHIGAN » ASCEMICHIGANCHAPTER » ASLAOFMICHIGAN » ESD
Theterm“designprofessional”isusedinthisdocumenttorepresentanyofthedesignprofessionals,orcombinationthereof,includingarchitecture,engineering,surveying,andsupportservices.
“Owner”isusedinthisdocumenttorepresentthepublicuserofdesignprofessionalservices.
TheMichiganQBSdocumenthasbeenpreparedforusebypublicpurchasersofprofessionaldesignservices,andderivesfromexperiencegainedbytheArchitecturalandEngineeringSocietiesinWisconsinandotherstateswithsimilarprograms.Inaddition,thereportandworkbookbytheAmericanInstituteofArchitects,“QualificationsBasedSelection:AProcessfortheSelectionofArchitectsbyPublicOwners”,wasused.TheQBSCoalitionofMichiganhasmodifiedthesedocumentstomakethemapplicableinMichigan.
QBS | Qualifications-Based Selection 3
QBS | Qualifications-Based Selection 4
3.0 HOW DOES QUALIFICATIONS-BASED SELECTION (QBS) WORK?
QBSisafairandrationalprocedurethatfacilitatestheselectionofadesignprofessionalonthebasisofqualificationsandcompetenceinrelationtothescopeandneedsofaparticularproject.Inmostinstances,theQBSprocessshouldincludeallorsomeofthefollowingsteps:
1. Theowneridentifiesthegeneralscopeofwork.2. Theselectionscheduleisestablished.3. Alistofdesignprofessionalfirmsiscompiled.4. Qualificationdocumentsarerequested.5. Qualificationdocumentsareevaluated.6. Ashortlistoffirmstobeinterviewediscomposed.7. Abriefingisheld.8. Interviewsareconducted.9. Firmsarerankedforselection.10. Detailedscopeofworknegotiatedwiththetoprankedfirm.11. Acontractisnegotiatedwiththetoprankedfirm.Ifanagreementcannotbereach, thosenegotiationsareendedandnegotiationsarebegunwiththesecond-ranked firm,andsoondowntheline,untilagreementisreachedandafirmisselected.12. Allfirmsinvolvedreceivepost-selectioncommunicationsandtheprocessis evaluated.
This step-by-step procedure and its variations are detailed in the following sections.
3.1 DEVELOPING THE GENERAL SCOPE OF WORK
Tobegintheselectionprocess,theownermustbrieflyidentifythegeneralscopeandtheparticularneedsoftheproject.Justastheownerneedsinformationaboutthequalificationsandcompetenceofthedesignprofessionalfirms,thefirmsneedtoknowtheprojectrequirementsandgoals.Whenthescopeofworkisproperlydescribedandcommunicated,itsavestime,money,andeffortforboththeownerandthedesignprofessional.Awell-definedscopeofworkallowsthedesignfirmstotailortheirstatementsofqualificationsdirectlytotheprojectrequirements,andprovidestheownerwithauniformbasisforevaluatingtheresponses.
The following are the basic elements that normally will be included in a statement of the scope of work for a project:
» Owner’sname» Descriptionoffunctionandshorthistoryoftheownerorganizationoragency,in
includingthegoalsoreventsthatpromptedtheproject.» Projectnameoridentification.» Projectlocation.» Contactperson.(Thispersonshouldbeidentifiedclearlyastheonlypersontocon
tactforinformationontheproject.)» Identificationandexplanationofinvolvementofselectionpanelorclientgroups,
e.g.boards,foundations,committees,citizensgroups.
QBS | Qualifications-Based Selection 5
» Descriptionsofotherconstructioninprocessorplannedforthesamesitebutnot partofthescopeofwork.» Descriptionsofcompletedstudies,surveys,and/orpreliminaryfeasibilityworkthat arerelevanttotheprojectandavailabletothefirmsthatwillbeshortlistedand interviewed.» Requirementsforfurtherfeasibilityplanningpriortodesignandconstruction.» Projectoutline,including(totheextentknown)theintendedsize,function,and occupancy;andothergeneralanticipatedrequirements,e.g.renovation,demolition, additions,newconstruction;andenergy,landuse,andsiteselectionconsiderations.» Anticipatedscheduleincludingcompletionofdesignwork,beginningof construction,andplannedprojectcompletiondate.» Descriptionofdesignprofessionalselectionprocess,includinginvolvementof groupsmentionedabove.» Additionaloruniquerequirementsorconsiderationssuchasreferenda,anticipated fundingstrategy,andbudgeting.
Additionalitemsmaybeaddedtothislistasappropriatetoprovideguidancetothecompetingfirmsandtomeettheneedsoftheowner.Allservicestobeprovidedbythedesignprofessionalincludingfeasibilitystudies,design,constructioncoordination,budgetdevelopment,andfundingstrategyshouldbespecificallyidentified.
Forms for guidance in preparing a Preliminary Scope of the Work, and examples, are included in the Appendix.
3.2 ESTABLISHING A SELECTION TIME FRAME
Tokeeptheprocessofselectingadesignprofessionalproceedingsmoothly,ownersshouldestablishatimeframeforcompletionoftheselectionprocess.Establishingthetimeframepreventsmisunderstandingandlast-minute“surprises”thatmightdelayorsidetracktheprocess.
Thetimeframeforeachprojectwilldiffer,dependinguponthenatureoftheproject,theconcernsoftheowner,andotherfactors.Insomeinstances,thetourofexistingfacilitiesmaybeprovidedtofirmsbeforeshortlisting.Sometimes,thecomplexityofaprojectcallsforsecondorthirdinterviews,althoughmultipleinterviewsgenerallyshouldbediscouraged.Inanycase,thetimeframeshouldbemodifiedtoensurethatallthesevariablesaretakenintoaccount,andthattheestablishedscheduleisappropriate.
A sample form is included for guidance in developing a time frame.
3.3 COMPILING A LIST OF DESIGN PROFESSIONALS
Howdoestheowneridentifyprofessionaldesignfirmsfromwhichtorequeststatementsofqualifications?Someofthefactorsthatshouldbeconsideredare:
» Thetypeoffirmneeded,e.g.architectural,engineering,surveying,orrelateddesign professionals.» Thereasonablenumberoffirmsthattheownercanevaluate.» Thegeographiclocationsanddistributionofthefirms.
QBS | Qualifications-Based Selection 6
Advertisements for Public Projects
Placingpublicnoticesofprojectsinnewspapersandtradeorprofessionalpublicationsisoftenrequiredbystateandlocallawsorregulations.Suchannouncementswillreachmanyinthedesigncommunity,andwillresultinalargenumberofresponses.Ifthisapproachisused,theadvertisementshouldspecifyinformationtobesubmitted,andtheownermustbepreparedtospendtimeevaluatingtheexpressionsofinteresttonarrowresponsesdowntoaworkablenumberoffirms.
Directories
Mostprofessionalorganizationspublishdirectoriesormakemailinglistsofmemberfirmsavailable.Theseoftencanhelpownersidentifyfirmswithinterestand/orexperienceinspecifictypesofprojects.TheAIA/Michigan,ACEC/Michigan,ASLA/Michigan,theMichiganSocietyofProfessionalEngineers,theMichiganSocietyofProfessionalSurveyors,andmanyotherorganizationsmaintaindirectoriestohelpownerslocatefirms.Directoriesusuallycanbefoundinthereferencesectionofthelocallibrary.Localtelephoneyellowpagesandotherkindsofcommunitybusinessdirectoriesalsocanbeusedtoidentifyprofessionaldesignfirms.
Referrals
Toidentifyfirmsmoreselectively,anownermaywishtocontactotherownerswhohaverecentlyuseddesignprofessionalservicesonsimilarprojects.
Howmanyfirmsshouldbeincludedonthelist?Thereisnoexactformula.Theownershoulddeterminethenumberappropriateforthespecificprojectandcircumstances.
3.4 REQUESTING QUALIFICATION DOCUMENTS
ARequestforQualifications(RFQ)canbeusedtoobtainthenamesandcredentialsofinterestedprofessionalfirms.Publicownersalsomayberequiredtoadvertiseforinterestedprofessionaldesignfirms.Whenthelistoffirmstobeconsiderediscompiled,theownershouldpreparethefollowingmaterialstosendtothefirms:
1. Amemotoallfirmsthatareinvitedtosubmitstatementsofqualifications.The memoshouldlistallfirmsinalphabeticalorder.(Ifthelistislimited,itiscustomary fortheownertoletfirmsknowthenamesofothercompetingfirms.)2. Alistofinformationthatshouldbeincludedwiththefirms’statementsof qualifications.3. Ascheduleofplannedactivities.4. Ascope-of-workstatement.5. Therequirementsforequal-opportunityemployment,minoritybusiness,small business,andwomenownedbusinessparticipation.
QBS | Qualifications-Based Selection 7
Itisessentialthatallfirmsreceivethesamematerialssothatallthefirms’responseswillbebasedonthesameprojectspecificationsandconstraintsand,therefore,canbecomparedfairly.
Theexchangeofinformationbetweentheownerandtheprofessionaldesignfirmsisanimportantinitialphaseintheselectionprocess.Theowner’srepresentative,listedonthememorequestinglettersofqualifications,shouldbepreparedtohandletelephonecallsandalsoshouldbeauthorizedtorespondtoquestions.Ifaquestionfromonefirmrevealsimportantinformationismissingfromthematerialssenttothefirms,allofthefirmsshouldbesuppliedwiththatinformationinwriting.
SampleformsforthisstepintheQBSprocessareincluded.(Thefederalgovernmentstandardforms254/255oftenarerequestedbypublicownersasfirms’statementsofqualifications.Theformsareeasytouseandarefamiliartomostfirms.)
3.5 EVALUATING QUALIFICATION SUBMITTALS
Theselectioncommitteeassignedtodevelopashortlistoffirmsshouldevaluatequalificationssubmittedbythefirms.(Itisuptotheownertoensurethatthescreeningcommitteeiscomposedofcompetentindividualswhowillbeabletomakeanintelligentselectiondecision.)Itisrecommendedthattheownerestablishapolicythatqualificationsubmittalsreceivedafterthedeadlinewillnotbeconsidered.
Thenumberoffirmstobeincludedontheshortlistandtheninterviewedmayvarydependingonthesizeandscopeoftheproject.Generally,threetofivefirmsaresufficient.
Asampleevaluationformisprovidedtoassistwithreviewingandshort-listingfirmsbasedontheirqualificationssubmittals.Thisformshouldbetailoredtomeetspecificprojectneeds.
Aformalsoisincludedforcheckingreferencesoffirmstheownerisparticularlyinterestedin.Referencesshouldbecheckedbetweenthetimequalificationssubmittalsarereceivedandthetimetheselectioncommitteemeetstodevelopashortlist.
Allevaluationsshouldprovideequal-opportunityconsiderations.
QBS | Qualifications-Based Selection 8
3.6 ESTABLISHING A SHORTLIST OF FIRMS TO BE INTERVIEWED
Basedonevaluationofqualificationsubmittalsandreferencechecksdiscussedintheprecedingsection,theownercanestablishashortlistofthreetofivefirmstobeinterviewed.Becauseallfirmsthatsubmittedqualificationscommittedtimeandexpensetopursuetheproject,theownershouldcontactthefirmsnotselectedfortheshortlistaswellasthosetobeinterviewed.Thememosenttofirmthatdidnotmaketheshortlistcanexpressthanksandidentifythefirmsthatwillbeinvitedtointerview.
A sample memo is included.
3.7 BRIEFING HELD WITH SHORTLISTED FIRMS
Firmsselectedforinterviewsshouldimmediatelybesentinformationregardinginterviewrequirements.Whatshouldbeincludedinthememotothesefirms?
The following elements should be considered:
1. Abriefingdatefortheshortlistedfirmsshouldbeestablished.Thismayinclude atourofthesite/facilitiesifconsideredappropriate.Thetourprovidesthefirms withanimportantfirst-handlookattheconcernsthatgaverisetotheproject.The briefingalsoprovidesafurtheropportunityforexchangeofinformationaboutthe project.Iftheprojectsiteisvacant,theownermaysimplyprovidemapsand directionstothesite.Iffacilitiesexist,however,thefirmsprobablywillwanttotour themwiththeowner.
Briefingtourscanbehandledindividually(theowner’srepresentativemeetsindividuallywithrepresentativesofcompetingfirms)orinagroup(allinterestedfirmsmeetataspecifictimeandplaceforagroupreviewofthesiteand/orfacility).
2. Alistofinterviewcriteriaandquestions,andanexplanationofthescoringan selectionprocess,shouldbesenttothefirmsontheshortlist.Predetermining selectionscoringcriteriaandspecificareasofownerconcern,andprovidingthat informationtotheshortlistedfirms,willprovidetheinterviewingcommitteewiththe bestpossiblebasisformakingan“applestoapples”comparison.
3. Iftheownerhasfeasibilitystudies,aprojectprogram,orotherbackground informationontheproject,thesematerialsshouldbesubmittedtothefirms,or madeavailabletothemforpurposesofreview.
4. Otherspecificsabouttheinterviewsthemselves,includingthedate,place,time, andthenamesandtitlesofthemembersofthegroupthatwillbeconductingthe interviews,alsoshouldbeincluded.
A sample memo to shortlisted firms is included. The memo, and scoring and evaluation sheets, should be tailored to meet the owner’s criteria, specific priorities, and concerns.
QBS | Qualifications-Based Selection 9
3.8 INTERVIEWING THE SHORTLISTED FIRMS
Purpose
Interviewswiththeshortlistedfirmslettheownercomparethefirms’differentapproachestothedesignprocess,aswellastheirinterpretationsandunderstandingofthespecificprojectrequirements.Theownershouldnotexpectsketchesorotherdesignworkfortheprojectatthistime.Thedesignrequirementsforevensimpleprojectscanbequitecomplex;andatthisstate,thedesignprofessionalwillnotbesufficientlyawareoftheowner’sneedsandrequirementstobeabletoproduceameaningfuldesignsolution.
Theinterviewsallowforevaluationforthepersonalstylesofeachfirm’smanagementandkeypersonnel,andtheircompatibilitywiththepre-identifiedcriteriafortheproject.Itisimperativethatdesignpersonnelassignedtotheproject,aswellaskeyrepresentativesfromthefirm’sconsultants,bepresentattheinterview.Itisalsoessentialfortheprojectuserstobeinvolvedintheinterviews.Directinteractionbetweentheowner/userandthedesignprofessionalisessentialforthedevelopmentofadesignthattrulymeetstheowner’sneeds.
Set-up
Thephysicalset-upfortheinterviewshouldbecomfortable,withgoodacousticsandampleroom.Aseparatewaitingareashouldbeprovidedforotherfirmstobeinterviewed.Equipmentsuchasblackboards,flipcharts,andaudio-visualscreensprobablywillbeusefulifavailable,althoughmostfirmswillbringtheequipmenttheyneed.Sinceequipmentset-uptimemaycausesomedelays,tworoomsshouldbeused,ifpossible.Whileonefirmisbeinginterviewedinthefirstroom,anotherfirmcansetupinthesecondroom.Thisensuresthatimportantinterviewtimeisnotspentcheckingequipment.
Ownersmayelecttointerviewtheshortlistedfirmsinthedesignprofessional’soffice.Thiscanprovidegreaterinsightregardingthefirm’sworksettingaswellasmethods,equipmentandinformationalresources,andkeyteammembersproposedfortheproject.Interviewsmaybeheldinclosedsessionsunlessapplicablestatutesorregulationsrequireanopenpublicmeeting.Insuchcases,thefirmsshouldbenotifiedofthisinadvance.
Some Interviewing Guidelines
The following are suggested guidelines for setting up and conducting the interviews.
» Interviewonlythefirmscommunicatedwithduringtheselectionprocess,toensure thatallinterviewedfirmshavehadequalopportunitytopreparepresentations.
QBS | Qualifications-Based Selection 10
» Scheduleatleast45minutesforeachpresentation,and15minutesbetween interviews.It’simportanttoallowampletimeforthepresentationandquestion- and-answerperiod,andalsoforthecommitteetodiscussthepresentationprivately beforebeginningthenextinterview.
» Scheduleallinterviewsonthesamedayoronconsecutivedays.Thispermitsthe committeetocomparealloftheinterviewedfirmswhileinformationisfreshlyin mind,andensuresconsistentinterviewscoring.
» Theevaluationcriteriafortheinterviewscoringsystemshouldbecommunicatedto allfirmsinadvance.
» Whileitisappropriatetoquestionfirmsabouttheirapproachtothedesignofa project,ownersshouldnotaskforanactualdesignsolutionduringtheinterview. Appropriateandresponsivedesignsrequireconsiderablymoreinteractionbetween owneranddesignprofessionalthanispossibleduringtheselectionphase.Pre conceiveddesignsolutionsbroughttothetablebyeitherthedesignprofessional orownerrarelyaddressthetrueneedsoftheowner’sprogram.Considerabletime andeffort,however,maybeexpendedtryingtosalvagepreconceivedideasand makethemfittheprogram.Thisactuallyimpedesprogressandpreventsthe explorationofmoreresponsivesolutionstoidentifieddesignissues.
» Ownersmaywanttoaskhowthefirmsplantodevelopanappropriatelevelof compensationfortheirprofessionalservices.However,compensationamountsare bestresolvedthroughdetaileddiscussionswiththefirmfinallyselected,andonly afterthereisacomprehensiveandmutualunderstandingoftheactualscopeof services.
» Letallfirmsknowwhentheselectiondecisionwillbemade.Itisrecommended that,ifpossible,thedecisionbemadeonthesamedateastheinterviewsafterthe committeehashadampletimetoevaluateallfirms.
» UseofTechnicalProposals.Technicalproposalsshouldberequiredonlywhenthe projectiswelldefined,andifthesignificanceoftheprojectjustifiestheexpense andtimetotheshortlistedfirmsandtheowner.
Theprocesswilladdseveralweeks,andcommensuratecost,thepreparationtimefortheshortlistedfirms.Theowneralsowillrequiretechnically-experiencedstaff,aswellasseveraladditionalweekstoreviewthetechnicalproposals.
Thetechnicalproposalmayberequestedfromshortlistedfirms.Thistechnicalproposalcanbeusedasaforerunnertotheinterviews,orasasubstitutefortheinterview.Thetechnicalproposalshouldberequestedofeachoftheshortlistedfirms.Therequestshouldincludetheareastobeaddressedinthetechnicalproposal.AsamplerequestletterfortheinterviewprocessisincludedintheAppendix.
Thetechnicalproposaltechnique,withoutinterviews,shouldbeusedwhentheownerisfamiliarwiththefirmsandwiththestaffoftheshortlistedfirms.Whentheownerisnotfamiliarwiththefirmsandwishestorequesttechnicalproposals,theproposalsshouldbeinconjunctionwithandpriortointerviews.
QBS | Qualifications-Based Selection 11
3.9 RANKING THE FIRMS IN CONTENTION FOR SELECTION
Anevaluationformthatincludesaweightandascoreforeachcriteria/questionisusefulforevaluating,rankingandfinally,selectingthemostqualifiedfirm.Eachfirmshouldbeevaluatedseparatelybyeachinterviewerduringthepresentationandinterview.Whenalltheinterviewshavebeenconcluded,theheadoftheselectioncommitteeshouldcompiletheindividualscoresheets.Thissystemprovidesadocumentedrecordoftheselectionprocessassupportforthecommittee’sactions.Itisrecommendedthatcommitteememberstakethetimetoachieveaconsensusratherthanjustrankingandselectingbymajorityvote.
A sample evaluation/ranking system is included.
Iftechnicalproposalsareincludedintheprocess,theresultsofthereviewshouldbeincorporatedintheevaluationprocess.Iftechnicalproposalsarerequestedinplaceofinterviews,theheadoftheselectioncommitteeshouldcompiletheindividualscoresheetswhenthereviewofthetechnicalproposalsiscomplete.
3.10 NEGOTIATING A DETAILED SCOPE OF WORK WITH THE SELECTED FIRM
Assoonaspossibleafterselection,theownershouldbeginnegotiationstodevelopadetailedscopeofworkwiththefirmdeemedmostqualified.Normally,itisnotdifficulttoreachanagree-ment,sincetheQBSprocessfacilitatesanearlyunderstandingoftheprojectscopeandrequire-ments.Ifagreementonthescopeofservicescannotbereached,negotiationswiththefirst-rankedfirmshouldbeterminatedandtheownershouldopennegotiationswiththesecond-rankedfirm.
Thisdetailedandcomprehensivescope-of-servicesshouldbedevelopedjointlybytheownerandthetoprankedfirm.Thisisoftenaccomplishedthroughoneormoremeetingsofthedesignprofessionalandtheowner,afterwhichthedesignprofessionalsubmitsaprojectandworkplan.Theworkplanshouldlistconsultantsandtherolesandresponsibilitiesofallmembersofthedesignteam,aswellastheresponsibilitiesoftheowner.
3.11 NEGOTIATING A CONTRACT WITH THE SELECTED FIRM
» Oncethereisagreementontheworkplan,thedesignfirmshouldsubmitits proposalforcompensation,toinitiatefeenegotiations.
» Awrittencontractshouldbeused.Thepartiesmaywishtousethestandardform ofagreementoftheAmericanInstituteofArchitects,ortheEngineers’JointCon tractDocumentsstandardform.Thesecontractsarewidelyused,time-tested,and designedtocoordinatetheneedsoftheowners,contractors,anddesign professionals.
» Theagreementbetweentheowneranddesignprofessionalshouldensurethatboth partieshavethesameexpectationsandunderstandingoftheprojectrequirements.
QBS | Qualifications-Based Selection 12
Whenprojectresponsibilitiesofboththeowneranddesignprofessionalareunderstoodandcompensationisdetermined,anagreementtoenterintoacontracthasbeenreached.Theowner,throughthenormalwrittenprocedureorprocess,authorizescommencementofdesignservicesandthuscompletestheselectionprocess.Again,ifagreementonthecompensationcannotbereached,negotiationswiththefirst-rankedfirmshouldbeterminatedandtheownershouldopennegotiationswiththesecond-rankedfirm.
3.12 POST-SELECTION COMMUNICATIONS
Afterinterviewsand/ortechnicalproposalreviewsandrankingarecompleted,apost-selectionmemoshouldbepreparedandmailedtoallfirmsthatparticipatedintheprocess.Thememoshouldlistallfirmsinalphabeticalorder,andstatebynameinwhatorderthecommitteerankedthefirms.(Itiscustomaryforownerstoprovidethisinformationasacourtesytothefirms.)Asamplepost-selectionmemoisincludedintheAppendix.
Afteracontractisawarded,adebriefingforeachshortlistedfirmshouldbeprovideduponrequest.Thedebriefingwillincludeinformationonrankingandscoringofthatfirm’sproposal.
Theprocessshouldalsobeevaluatedbythegovernmentalunit,foruseinfutureprograms.
3.13 ADDITIONAL DISCUSSION
NothinginthisworkbookisintendedorshouldbereadtoprohibitanymemberoftheQBSCoalitionAssociationsfromsubmittingpricequotationsatanytimeduringthedesignprofessionalselectionprocessortosuggestthattodosoisunethical,unprofessional,orcontrarytopolicy.Norshouldthisworkbookbereadasinanywayprohibitinganybuildingorprojectownerfromrequestingsuchsubmissions.
TheQBSCoalitiondoes,however,advocatethatpublicownersvoluntarilyadoptthequalifications-basedapproachtodesignprofessionalselectiondescribedinthisworkbook.Thisworkbookisnotwrittenforprivate,nongovernmentalowners.
QBS | Qualifications-Based Selection 13
3.14 LISTS OF DESIGN PROFESSIONAL FIRMS ARE AVAILABLE FROM THE FOLLOWING ASSOCIATIONS:
ACEC of Michigan AGC of MichiganAmericanCouncilofEngineering AssociatedGeneralContractors(Michigan)Companies(Michigan) 2323N.LarchSt.215N.Walnut Lansing,MI48906Lansing,MI48933 (517)371-1550(517)332-2066
AIA of Michigan APWAAmericanInstituteofArchitects AmericanPublicWorskAssociationofMichigan ofMichigan553E.Jefferson VanBurenCountyDetroit,MI48226 POBox156(313)965-4100 Lawrence,MI49064 (269)674-8011
ASCE ASLA of MichiganAmericanSocietyofCivil AmericanSocietyofLandscapeArchitectsEngineers,MichiganChapter ofMichigan215N.Walnut 1026N.WashingtonAve.Lansing,MI48933 Lansing,MI48906(517) 332-2066 (517) 485-4115
AWWA ESDAmericanWaterWorks EngineeringSocietyofDetroitAssociationofMichigan 20700CivicCenterDr.,Ste.450P.O.Box609 Southfield,MI48076GrandLedge,MI48837 (248) 356-0736Telephone:(517) 627-0913
MSPE MSPSMichiganSocietyofProfessional MichiganSocietyofProfessionalSurveyorsEngineers 220MuseumDr.215N.Walnut Lansing,MI48933POBox15276 (517)484-2413Lansing,MI48901(517)487-0635
MWEAMichiganWaterEnvironmentalAssociationPOBox397Bath,MI48808
QBS | Qualifications-Based Selection 14
(517)641-7377
4.0 INFORMATION AND EXAMPLE MATERIALS
Theformsandmaterialsincludedaredesignedtoprovidebasicformatsthatcanbeadjustedtomeetspecificprojectneeds.TheMichiganQualifications-BasedSelectionCoalitionwillhelptheownerdevelopasetofmaterialstogettheselectionprocessstarted.
Memos and materials to be mailed to the firms involved
1. Requestforlettersofqualificationsandenclosures: » Requirementsforlettersofqualifications. » Scheduleofactivitiesfortheselectiontimeframe. » Apreliminaryscopeofthework.2. Memotofirmsthatsubmittedletterofqualificationsbutwerenotselectedforan interview.3. Memotoshortlistedfirmsforinformationoninterviewandsitevisitations,withen closures: » Interviewquestionsandscoresheetsforrankingfirms. » Groupinterviewevaluationforms.4. Memotoshortlistedfirmswhentechnicalproposalisrequested,withenclosures: » Reviewquestionsandscoresheetsforrankingfirms.5. Memotoallfirmsthatwereinterviewed.
Forms and information for use by the owner during the screening and interview process
6. Alternativeinterviewscoresheetforrankingshortlistedfirms.7. Rankingformforevaluationofthelettersofqualificationreceived.8. Formforcheckingthereferencesoffirmsunderconsideration.
QBS | Qualifications-Based Selection 15
4.1 REQUEST FOR LETTERS OF QUALIFICATION SAMPLE MEMO
TO:_________________________________________________________________________ Listnameoffirm
FROM:______________________________________________________________________ Owner
_________________________________ ________________________________________Individual Title
RE: Request for Statements of Qualification
YourfirmisinvitedtosubmityourStatementsofQualificationtobecomeeligibleforapossibleinterviewforprofessionaldesign*servicesrelatedtodesignandconstructionrequirementsforthe
____________________________________________________________________________Owner
Thisproject’s_________________________________________________________________ Description
Preliminaryrequirementsarebasedonstudiesperformedbythe ___________________ Nameofcommitteeorgroup
Attached to this memo are:
1. AlistofmaterialsandinformationthatshouldbeincludedwithyourStatementsof Qualification.2. Ageneraldefinitionofthepreliminaryscopeofthework.3. Ascheduleofdatesandrequirementsfortheselectionprocess.
Forfirmsthatareselectedforaninterview,atourofthefacilityandsitewillbearranged.(This sentence is optional)
YourlettersandStatementsofQualificationwith __________ copiesshouldbeforwardedtothefollowingaddress,andshouldbereceivednolaterthan5p.m.on_____________ Dayandtime
TO:______________________________ _______________________________________ Name Title
___________________________________________________________________________ Address
*Note: May use “architectural,” “engineering,” or “land surveyors” in place of “design professional,” where appropriate
QBS | Qualifications-Based Selection 16
4.2 REQUIREMENTS FOR LETTERS OF QUALIFICATION
_____________________________________________________________________________________ Owner
___________________________________________________________________________________Project
YourLettersofQualificationshouldincludethefollowinginformation:
1. Name,address,andbriefhistoryoffirm.2. Resumesofkeypersonneltobeassignedtothisproject.3. Relatedexperienceduringthelasttwoyears.(Oncomplexanduniqueprojects, maybeextendedbeyond2years.) ForExample: a.Includeprojectswhereprofessionaldesignservicesrelatedtodesignwork wereperformed. b. Includeexamplesofotherprojectsthataresimilarinscopetothisone. c. Includeexamplesofprojectbudgeting,costestimatingandresults. Includethenameoftheproject,acontactperson,anddollaramountforeach example.4. Youareinvitedtoincludeamaximumofonepage(mayallowmore)ofinformation notincludedaboveifyoufeelitmaybeusefulandapplicabletothisproject.
QBS | Qualifications-Based Selection 17
4.3 SCHEDULE OF ACTIVITIES
Thefollowingschedulehasbeenestablishedby: ________________________________________ Owner
FOR:_______________________________________________________________________________ Project
___________ 1.Identificationofneedsfinalizedbytheowner.AscopeofworkingeneraltermsDate developed.
___________ 2.IdentificationbyownerofinterestedandpotentialprofessionaldesignfirmstoDate receivememorequestingLettersandStatementsofQualification.
___________ 3.MemorequestingLettersandStatementsofQualificationmailedtointerestedDate andinvitedfirms.
___________ 4.LettersandStatementsofQualificationdue.(Allowminimumof10daysforDate firmstosubmitmaterials)Note:Beforethenextactiondate,references shouldbereviewed.
___________ 5.Developshortlistof3-5firmsselectedforinterviews.SelectionshouldbeDate basedonqualifications,references,andcompatibilitywithowner’sproject.
___________ 6.Memomailedtoshortlistedfirmsadvisingdateforinterviewsandpre-interviewDate tourortoursofsiteand/orfacilities,alongwithcriteriatobereviewedduring theinterview.
___________ 7.Memomailedtoallfirms,excludingshortlistedfirms,informingthemoffirmsDate tobeinterviewedandexpressingappreciationfortheirinterest.
___________ 8.Tourortoursoffacilitiesat(time)and(location).(ShouldbescheduledatDate least20daysbeforeinterviews,toallowforpreparation.)
___________ 9.Scheduledinterviewsforshortlistedfirms,attimesandlocationspreviouslyDate communicated.Thebestfirmfortheprojecttobeselected,basedon qualifications.
___________ 10.Contractwithselectedfirmnegotiatedandimplemented.Date
___________ 11.Memomailedtoallfirmsinterviewed,indicatingresultsofinterviewsandDate expressingappreciationfortheirinvolvement.
___________ 12.Post-selectionrequirements.(Publichearings,etc.) Date
QBS | Qualifications-Based Selection 18
4.4 PRELIMINARY SCOPE OF THE WORK
(The development of a scope of work for each project should include the following information in general terms, and should be limited to one page.)
____________________________________________________________________________________ Owner
____________________________________________________________________________________ ProjectName
_________________________________________ ________________________________________ ProjectLocation ContactPerson
Identificationandinvolvementofgroups(Example:Boards,committees,citizen’sgroups,etc.):
_____________________________________________________________________________________
_____________________________________________________________________________________
Descriptionofstudies,surveys,andpreliminaryfeasibilityworkrelevanttoproject,andusefulandavailabletofirmsthatwillbeshortlisted.
Requirementsforfurtherfeasibilityplanningbeforedevelopmentofplansordesignwork.
Projectoutlineandgeneralanticipatedrequirements.(Example: demolition, renovation, new con-struction, land use, environmental, waste management, etc.)
Anticipated time frame:
ProjectedStart:_____________________________PlannedFinish: ____________________________
Approvalprocess/involvementofgroups.
Other requirements:
Referendums,publichearings,etc.
QBS | Qualifications-Based Selection 19
4.5 MEMO – FOR FIRMS THAT SUBMITTED LETTERS/STATEMENTS OF QUALIFICATION – NOT SELECTED FOR INTERVIEW
TO:(List firms in alphabetical order.) (All firms not asked to interview or tour facilities.)
FROM:________________________________________________________________________________ Owner
____________________________________________________________________________________Individual Title
____________________________________________________________________________________Address
RE: Status of Selection Process
____________________________________________________________________________________Project
The_________________________________________________________________________________ Nameofcommitteeorgroup
expressesitsappreciationtoyouandyourfirmforsubmittingyourLettersofQualification.
Aftercarefulconsiderationofallfirmsthatsubmittedqualifications,the_______________________ Committeeboardorstaffunit
decidedtointerviewthefollowingfirms:(List firms in alphabetical order)
1.2.3.4.5.
Althoughyourfirmwasnotselectedforaninterview,weappreciateyourinterestinourproject,andtheresourcesspentonthepreparationofyourproposal.
QBS | Qualifications-Based Selection 20
4.6 MEMO TO SHORTLISTED FIRMS TO BE INTERVIEWED/TOUR OF FACILITIES/AND CRITERIA
TO:(List professional design firms in alphabetical order)
FROM:______________________________________________________________________________ Owner
____________________________________________________________________________________Individual Title
____________________________________________________________________________________Project
RE: Interview Schedule and Requirements
Thefirmslistedabovehavebeenshortlistedandwillbeinterviewedfortheprofessionaldesignservicesrelatedtotheworknecessarytoimplementthisproject.(Specifystudy,design,other)
Attached to this memo are the following:
1.AnInterviewScoreSheet,whichwillbeusedbythe_____________________________ duringtheinterviewsession. Interviewinggrouporindividual
2.Evaluationform,whichthepersoninchargewillusetocompileevaluationscores. 3.Copiesof__________________________________________________________________ Nameofstudiesorreport
compiledby ____________________________________ ,foryourinformationandreview. Nameofgroup
Eachfirmwillbeallowed45minutestopresentqualificationsandtoanswerquestions.Theinterviewerswillschedule15minutesbetweeninterviewsforinformaldiscussionofinformationpresentedduringtheprecedinginterview.Atthecompletionoftheinterviews,theinterviewerswillrankthefirmsinterviewedinaccordancewiththeirdeterminationofwhichfirmismostcompetentandcompatibletodothework.Thefirmdeemedtobemostqualifiedwillthenenterintonegotiationsforacontracttoprovidethenecessarydesignservices.Ifcontracttermscannotbereached,thefirmrankedsecondwillbeinvitedinforcontractnegotiations.
Interviewswillbeheldon______________________________________________________________ Date
Thelocationis _______________________________________________________________________ Nameofbuilding
____________________________________________________________________________________Address
Form Continued on Next Page
QBS | Qualifications-Based Selection 21
Form Continued....
Theorderandtimeofinterviewsis:
FirmA________Time FirmB________Time FirmC________Time FirmD________Time FirmE________Time
Abriefingandtourofthesiteand/orfacilitywillbearrangedfor__________________.Pleasehaveyourfirm’srepresentativemakearrangementstobepresent.
QBS | Qualifications-Based Selection 22
4.7 EXAMPLE – THE INTERVIEW: QUESTIONS AND SCORE SHEETS
Owner______________________________ Project______________________________________
(Firmsinvitedtointerviewforthecaptionedprojectshouldbepreparedtoaddressthefollowingissuesduringthecourseoftheirinterview.Questionscanbeexpandedonasappropriate.)
CATEGORIES RATING WEIGHT TOTAL
1.Relatedprojectexperience _________x_________=_________2.Firm’sabilityandcapacitytoperformthework »Keypersonnelassignedtothisproject _________x _________=_________3.Graspoftheprojectrequirements »Studies »Design »Other _________x_________=_________4.Methodtobeusedtofulfilltherequired services,includingdesignphase _________x_________=_________5.Managementapproachfortechnical requirements.Examples: »CostControls »Designandconstructionphaseinvolvement _________x_________=_________6.Useofconsultantsthatmayworkontheproject »Discussin-houseresources »Outsidesources _________x_________=_________7.Timescheduleplannedforthisproject »Availability _________x_________=_________8.Firm’sexperienceandmethodsusedfor: »Budgetingandfinancialcontrols »Determiningfeeandcompensation _________x_________=_________ GRANDTOTAL=_________
Instruction for the Interviewers
Duringtheinterview,rateeachfirmonascaleof1-5,with5beinghighest,ineachoftheeightcategories.Enterthenumberunder“Rating”.Atthecompletionoftheinterview,multiplyingtheratingbythepre-determinedweightforeachcategory,andenterthetotal.Addalltotalstoestab-lishthegrandtotal.Thepersoninchargewillcombineallofthetotalsforthoseparticipatingintheinterviewsession.Thepreassignedweightsareestablishedwithamaximumof10pointsforeachcategory.Amaximumof400pointsmaybeawarded,assumingallcategorieswereweightedat10,andthefirmreceivedthemaximum5ratingoneachcategory.
QBS | Qualifications-Based Selection 23
4.8 GROUP INTERVIEW PROPOSAL EVALUATION FORM
(For use by the person in charge of the interviews to compile all scores of professional design firms participating in the interview process.)
Note:
Enterthegrandtotalforeachfirm,asrecordedbyeachinterviewerontheInterviewScoreSheet.Afterallentriesaremadeandtotaled,dividethecombinedgrouptotalforeachfirmby400forthemaximumpossiblescore.
Combined Group TotalsInterviewer 1
Interviewer 2
Interviewer 3
Interviewer 4
Interviewer 5
--------------------
--------------------
--------------------
--------------------
Grand Totals
QBS | Qualifications-Based Selection 24
4.9 MEMO TO SHORTLISTED FIRMS WHEN TECHNICAL PROPOSAL IS REQUESTED
TO:(List professional design firms in alphabetical order)
FROM:______________________________________________________________________________ Owner
____________________________________________________________________________________ Individual Title
____________________________________________________________________________________ Project
RE: Technical Proposal Request
Thefirmslistedabovehavebeenshortlisted.Technicalproposalsarerequestedforprofessionaldesignservicesrelatedtotheworknecessarytoimplementthisproject.(Specifystudy,designorother)
Attached are:
1.ATechnicalProposalScoreSheet,whichwillbeusedbythe______________________________ Reviewgrouporindividual
2.Evaluationform,foruseofthepersonincharge,tocompiletheevaluationscores.
3.Copiesof _________________________________________________________________________ Nameofstudiesorreports
compiledby___________________________________________,foryourinformationandreview. Nameofgroup
Technicalproposalsaredueon_______________at______________,andshouldbeaddressedto: Date Time
__________________________________________________.__________copiesaretobesubmitted.
Abriefingandtourofthesiteand/orfacilitywillbearrangedfor_____________________________. Date
Pleasehaveyourfirm’srepresentativemakearrangementstobepresent.
QBS | Qualifications-Based Selection 25
Owner______________________________ Project______________________________________
4.10 Technical proposals should address the following issues.
CATEGORIES RATING WEIGHT TOTAL
1.Relatedprojectexperience _________x_________=_________
2.Firm’sabilityandcapacitytoperformthework »Keypersonnelassignedtothisproject »Responsibleofficer _________x _________=_________
3.Issuesofspecialconcern _________x_________=_________
4.Technicalapproachtowork _________x_________=_________
5.Managementapproachfortechnicalrequirements. Examples: »CostControls »Designandconstructionphaseinvolvement _________x_________=_________
6.Useofconsultantsthatmayworkontheproject »In-houseresources »Outsidesources _________x_________=_________
7.Timescheduleplannedforthisproject »Availability _________x_________=_________
8.Firm’sexperienceandmethodsusedfor: »Budgetingandfinancialcontrols »Determiningfeeandcompensation _________x_________=_________ GRANDTOTAL=_________
Instructions for the Reviewers
Duringtheinterview,rateeachfirmonascaleof1-5,with5beingthehighest,ineachoftheeightcategories.Enterthenumberunder“Rating”.Atthecompletionofthereview,multiplytheratingbythepredeterminedweightforeachcategory,andenterthetotal.Addalltotalstoestablishthegrandtotal.Thepersoninchargewillcombineallofthetotalsforthoseparticipating.Thepreas-signedweightsareestablishedwithamaximumof10pointsforeachcategory.Amaximumof400pointsmaybeawarded,assumingallcategorieswereweighedat10andthefirmreceivedthemaximum5ratingoneachcategory.
QBS | Qualifications-Based Selection 26
4.11 GROUP TECHNICAL PROPOSAL EVALUATION FORM
(For use by the person in charge of the interviews, to compile all scores of professional design firms participating in the interview process.)
Note:
Enterthegrandtotalforeachfirm,asrecordedbyeachinterviewerontheinterviewscoresheet.Afterallentriesaremadeandtotaled,dividethecombinedgrouptotalforeachfirmby400forthemaximumpossiblescore.
Combined Group TotalsFirm A Firm B Firm C Firm D Firm E
Interviewer 1
Interviewer 2
Interviewer 3
Interviewer 4
Interviewer 5
--------------------
--------------------
--------------------
--------------------
Grand Totals
Dividegrouptotalsby400foracompositescoretodeterminethemostqualifiedfirm.(Based on eight categories.)
QBS | Qualifications-Based Selection 27
4.12 MEMO FOR ALL PROFESSIONAL DESIGN FIRMS THAT WERE INTERVIEWED
TO:(List professional design firms in alphabetical order)
FROM:______________________________________________________________________________ Owner
____________________________________________________________________________________Individual Title
____________________________________________________________________________________(Address)
RE: Status of Selection Process
____________________________________________________________________________________ProjectName
The_______________________________________hascompletedtheselectionprocessfor Owner
Professionalservicesfortheabovenamedproject.
Ithasbeenourobjectivetoselectthemostqualifiedfirmtoperformthisservice.Theresultsofthe
______________________________decision,ranksthefirmsinterviewedinthefollowingorder:Interviewers
Firm#1_____________________________________________________________________________ Name
Firm#2_____________________________________________________________________________ Name
Firm#3_____________________________________________________________________________ Name
Firm#4 ____________________________________________________________________________ Name
Firm#5_____________________________________________________________________________ Name
Wehavenowenteredintocontractdiscussionsandnegotiationswith______________________. Firm#1
The_________________________________________expresstheirappreciationforyourtime, Interviewers
effortandinterestonourbehalf.
QBS | Qualifications-Based Selection 28
4.13 THE REFERENCE CHECK
Owner________________________________ProjectDescription_____________________________
ProfessionalDesignFirm_____________________________onwhichthereferencecheckisbeingconducted.
Reference Information:
Owner______________________________ProjectReferenced_______________________________
Address_____________________________PersonContacted________________________________
Phone_______________________________
(Based on references provided in firm’s Letters of Qualification or through networking with other owners who have worked with the firm.)
5 4 3 2 1Sample Questions Asked Exe. Good Avg. Fair Poor
1.Whatisyouproject?
2.Whenwasitcompleted?
3.Didthefirmabovedothework?
4.Whatdidtheydoforyou?Designwork,studies,construction,
coordination,other(specify)____________________________
5.Whowasthestaffpersonassignedtoworkwithyouonthis
project?_____________________________________________
Wereyousatisfiedwithhis/herwork?__________________
6.Wastheprojectstartedatschedule?
7.Wastheprojectcompletedasplanned?
8.Werethebudget,costcontrol,andfinancialadministration
withintheplannedcontrolsandlimitations?
9.Didthefirmand(you)theownerworkwellasateamasit
relatedtotheproject?
10.Didthefirmspersonnelworkwellwiththecommittee/
boardsandstaffonalltheproject’sspecificrequirements?
11.Whatisyouroverallevaluationofthefirmbasedonyour
experience?
GRAND TOTAL ________
Multiplynumberofquestionsby5formaximumscoreasappropriate.Addeachfirm’sscorefollowingthereferencecheck,andthentransfertotheLettersofQualificationEvaluationFormasalineitemonthatfirm’sevaluationsheet.
QBS | Qualifications-Based Selection 29
4.14 LETTERS OF QUALIFICATION EVALUATION
To the following model, you should add or delete questions as appropriate for your specific situa-tion. It is suggested that the weights and values assigned be on the same scale as those used for interviewing shortlisted firms which you will do later.
Highest numbers: most value / Rating columns: 1-5 points / Weight columns; 1-10, depending on importance to the project.
A form at the bottom of this page is provided for the person in charge of the review group to use, to summarize the results of the process, to narrow the number of firms that submitted qualifications down to the number desired for a shortlist (firms to be interviewed).
Qualifications Evaluation
Owner _______________________________________________________________________________ContactPerson________________________________________________________________________ProjectDescription ____________________________________________________________________ProfessionalDesignFirm_______________________________________________________________Address______________________________________________________________________________City_______________________________________State_________________Zip________________Phone____________________________ContactPerson_____________________________________
RATING WEIGHT=TOTAL1)Firm’shistoryandresourcecapabilitytoperform requiredservices ________x________=_______2)Evaluationofassignedpersonnel ________x________=_______3)Relatedexperience(asappropriate) ________x________=_______ » DesignServices » ConstructionCoordination » Demolition » Studies »Other______________________________________ ________x________=_______4)Budget,costcontrolsexperience,andresults ________x________=_______5)Familiaritywithlocalarea–geographyandfacilities ________x________=_______6)Abilitytorelateprojectrequirements ________x________=_______7)Analysisofsubjectivestatements(onepage)
applicabletotheprojectasrequiredontheRFQ ________x________=_______8)Referencecheck(evaluationtransferfromreference
checkform) ________x________=_______ GRAND TOTAL _______________
Form Continued on Next Page
QBS | Qualifications-Based Selection 30
Form Continued...
NameofReviewer_____________________________________________________________________
Qualifications Evaluation Summary
(To be used by the Review Group person in charge, to compile the evaluation results of all Letters of Qualification submitted. Note: Enter the Grand Total for each firm’s qualifications (from the respec-tive evaluation sheets for comparative purposes) to select three to five most qualified firms to be interviewed.)
Firms 1 2 3 4 5 6 7 8 9 10Reviewer 1
Reviewer 2
Reviewer 3
Reviewer ___
Reviewer ___
Reviewer ___
Divide the totals by the maximum composite score possible. Rating X Maximum weight. Example: 8 questions X 5 rating = 40 X 10 weight = maximum points. List the top-ranked firm as the short-listed firms to be interviewed.
QBS | Qualifications-Based Selection 31
4.15 OPTIONAL FORM
To:_________________________________________________________________________________ InterviewingGroup
Owner:______________________________________________________________________________
Interview Score Sheet
Issue Possible Points
Points Awarded
1.Similarprojectexperience 10
2.Discussionofthefirm’scapacitytoperformthework 10
3.Adiscussionofthefirm’sunderstandingoftheprojectneeds 20
4.Discussionofthemethodsthefirmproposestouseinprovidingtherequiredservices.
10
5.Adiscussionofconsultantsthatmaybeworkingwiththefirmontheproject.
10
6.Discussionofhowthefirmwillhandletheplanning,designandconstructionphasesoftheproject.Discussdesignapproach,constructioncostcontrols,andinvolvementinthedesignandimplantationphasesofthework.
30
7.Discussionoftimeschedulethefirmproposestocompletethenecessarypreliminarywork,aswellasatimeschedulefortheentireproject.
10
Notes: 100
QBS | Qualifications-Based Selection 32
4.16 EXAMPLE – THE INTERVIEW: QUESTIONS AND SCORE SHEETS
Owner____Hickory Valley Township_______Project____Landfill Monitoring Wells______________(Firms invited to interview for the captioned project should be prepared to address the following is-sues during the course of their interview. Questions can be expanded on as appropriate.)
Categories Rating x Weight = Total1.Relatedprojectexperience 3 8 24
2.Firmsabilityandcapacitytoperformthework
»Keypersonnelassignedtothisproject
5 8 40
3.Graspoftheprojectrequirements
»Studies
»Design
»Other
4 10 40
4.Methodtobeusedtofulfilltherequiredservices,
includingdesignphase
4 8 32
5.Managementapproachfortechnicalrequirements
examples:
»CostControls
»Design&constructionphaseinvolvement
3 7 21
6.Useofconsultantsthatmayworkontheproject
»DiscussIn-HouseResources
»OutsideResources
3 5 15
7.Timescheduleplannedforthisproject
»Availability
5 5 25
8.Firmsexperienceandmethodsusedfor:
»Budgetingandfinancialcontrols
»Determiningfeeandcompensation
4 10 40
Grand Total 237
Instructions for the Interviewers
Duringtheinterview,rateeachfirmonascaleof1-5,with5beinghighest,ineachoftheeightcategories.Enterthenumberunder“Rating”.Atthecompletionoftheinterview,multiplytherat-ingbythepredeterminedweightforeachcategory,andenterthetotal.AddalltotalstoestablishtheGrandTotal.Thepersoninchargewillcombineallofthetotalsforthoseparticipatingintheinterviewsession.Thepreassignedweightsareestablishedwithamaximumof10pointsforeachcategory.Amaximumof400pointsmaybeawarded,assumingallcategorieswereweightedat10,andthefirmreceivedthemaximum5ratingoneachcategory.
INTERVIEWER: Mr. Hazelton Firm: A
QBS | Qualifications-Based Selection 33
4.17 GROUP TECHNICAL PROPOSAL EVALUATION FORM
(For use by the person in charge of the interviews to compile all scores of professional design firms participating in the interview process.)
Note:
Enterthegrandtotalforeachfirm,asrecordedbyeachinterviewerontheInterviewScoreSheet.Afterallentriesaremadeandtotaled,dividethecombinedgrouptotalforeachfirmby400forthemaximumpossiblescore.
Combined Group TotalsInterviewer 1 237 314 390
Interviewer 2 340 275 370
Interviewer 3 310 290 370
Interviewer 4 257 330 302
Interviewer 5 290 300 340
-------------------
-------------------
-------------------
-------------------
Grand Totals 1434 1509 1772
Dividegrouptotalsby400foracompositescoretodeterminethemostqualifiedfirm.
BlackhawkSchoolDistrict–ElementarySchoolAddition
FirmC=4.38 FirmB=3.77
FirmA=3.58