“pushing the limits of constructability pushes the limits of stakeholder involvement” case...
TRANSCRIPT
![Page 1: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/1.jpg)
“Pushing the Limits of Constructability Pushes the Limits of Stakeholder
Involvement”
Case Study: Myrtle-Morehead SDIPCity of Charlotte, North Carolina
Presented By:Chip Smith, PE – Woolpert
Kate Labadorf, PE – City of Charlotte Storm Water Services
North Carolina AWWA/WEA2015 Annual Conference
![Page 2: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/2.jpg)
Presentation Outline
• Review of Charlotte’s Flood Control Program• Myrtle-Morehead Project History and Overview• Phase 1 – Construction Reality vs Stakeholder
Issues Resolved During Design• Phase 2 - Constructability Problems &
Stakeholder Issues Still Continue• Lessons Learned• Questions and Answers
![Page 3: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/3.jpg)
City Flood Control Projects
• Drainage system improvements for watersheds up to one square mile
• Typical planning, design and construction duration – 5 to 7 years
• Typical costs range from $500,000 - $10 million
• Annual Funding of $27.8 million• This Project ~ $31 million
![Page 4: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/4.jpg)
Problems: • Road Flooding - 6 Roads• Structure Flooding - 20
structures• Deteriorating Infrastructure
Myrtle/Morehead Project
Parking deck flooding
Metal pipe with holes in bottom
![Page 5: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/5.jpg)
Project History/Existing System Problems
• Project initiated in 2000 due to chronic flooding of Myrtle Square Apartments, Euclid Avenue, Myrtle Avenue, and Lexington Avenue
• Dilworth area was developed around a creek that was piped with various undersized culverts
• Existing culvert is located underneath and behind numerous houses and apartments
• Dilworth area is a designated Historic Area with homes exceeding $1M in value
![Page 6: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/6.jpg)
Project Study Area
Project Area
MOREHEAD STREET
Myrtle Square Condos
Dilworth Historic Area
Drainage Area Outfall
Arlington CondosFlooded Parking Deck
Low Areas
SOUTH BOULE
VARD
![Page 7: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/7.jpg)
Project Design & Constructability Challenges
• Routing a 78” to 90” by-pass culvert through the Dilworth neighborhood streets at depths between 20 and 30 feet
• Tunneling under Morehead Street and replacing 80’ of the 54” water main (NCDOT Encroachment)
• Installing 90” culvert by open cut in McDowell Street (NCDOT Encroachment)
• Installing box culvert by squeezing it between a Public Relations firm and a Duke Over Head Transmission Line
Results in a monumental challenge of project planning & stakeholder involvement !
![Page 8: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/8.jpg)
Culvert By-Pass Alignment
Charlotte Housing Authority
New 9’x6’ RCBC
New 90-Inch RCP
New 78-Inch RCP
New 48-Inch RCP in new Street
![Page 9: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/9.jpg)
Project Area – Urban & Residential
McDowell Avenue Oriole Avenue
![Page 10: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/10.jpg)
Project Area - Residential
Myrtle Avenue
Lexington Avenue
• Narrow Tree Lined Streets
• OH Utilities• On-Street Parking
![Page 11: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/11.jpg)
Project Area - Residential
Myrtle Square Condominiums
Low Area
Existing Culvert in Courtyard
![Page 12: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/12.jpg)
Project Area - Residential
Euclid Avenue “Sump”
![Page 13: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/13.jpg)
Alternatives Considered
• Rehabilitation of Existing System– Results in Less than 2 Year LOS
• Upstream Detention for 10 Year LOS– Required 37 Ac-Ft of Storage
• Numerous Alignments for New Culvert• Other Potential Solutions– Linear Storage– Storm Water Pump Station
![Page 14: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/14.jpg)
Alternatives Considered
Charlotte Housing Authority
Alternative AlignmentsCharlotte Housing
Authority
37 Ac-FtPond
![Page 15: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/15.jpg)
Phase 1 – Under Construction
Wray WardWray Ward
Wray Ward
Wray WardWray Ward
Wray Ward
Dialysis Center
Morehead
PropertiesDuke Endowment HQ
Arts BBQ
Townhouses
![Page 16: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/16.jpg)
Stakeholders
• Property Owner and Businesses
• Charlotte Water – 54-inch WM Replacement and sewer relocation
• CDOT - Multiphase Traffic Control Plans
• Department of Water Quality
• Duke Energy – OH & Duct Banks
• AT&T – Duct Bank Crossing
• Piedmont Natural Gas – Existing & Abandoned Gas Mains
• NCDOT – Encroachment Permit & Design Approval
![Page 17: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/17.jpg)
Impact of Constructability Challenges on Construction Costs
• Only 2 Bidders: $12.15M & $13.04M
• 150 LF of Tunnel 30 feet deep : $3.15M
• Sheeting and Shoring for Deep Open Cut: $600K
• Contaminated Soils and Groundwater: $520K
• 80 LF 54-inch Water Main Replacement: $300K
• Slow construction – 18 months for 1,400 LF : $7.58M
![Page 18: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/18.jpg)
Wray Ward
Existing 9’x6’ RCBC
New 10’x6’ RCBC Adjacent to Existing 9’x6’ RCBC
Existing 9’x6’ RCBC removed to install 2-9’x6’ RCBCs
Existing 9’x6’ RCBC
Duke Energy OH Transmission Line
Duke & AT&T Duct Banks
![Page 19: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/19.jpg)
![Page 20: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/20.jpg)
New 10’x6’ RCBC Connection @ Sta. 0+00
![Page 21: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/21.jpg)
Duke Energy OH Transmission Line Tower
![Page 22: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/22.jpg)
Required Nighttime/Weekend Work
![Page 23: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/23.jpg)
Wray Ward
Existing 9’x6’ RCBC
New 10’x6’ RCBC Adjacent to Existing 9’x6’ RCBC
Existing 9’x6’ RCBC removed to install 2-9’x6’ RCBCs
Existing 9’x6’ RCBC
Duke Energy OH Transmission Line
Duke & AT&T Duct Banks
![Page 24: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/24.jpg)
Duke Energy Duct Bank Crossing
![Page 25: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/25.jpg)
McDowell Street Junction Box
New Culvert C/LExisting Culvert C/L
New 12 FT x 12 FT Junction Box
![Page 26: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/26.jpg)
12’ x 12’ Junction Box
9’x6’ Downstream
90” Upstream
![Page 27: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/27.jpg)
McDowell Street
New Culvert C/L
![Page 28: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/28.jpg)
Oh No ! Another Utility Coordination
New Fiber Optic Line
New Culvert C/L
![Page 29: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/29.jpg)
McDowell Street – Parking Garage Entrance
![Page 30: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/30.jpg)
McDowell Street – Parking Garage Entrance - October 2015
![Page 31: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/31.jpg)
Tunneling & Water Main Replacement
No Blasting within 10 feet of Water Main
Tunneling Stopped for W.M Replacement
WM Replacement Between Dec. and March
NCDOT Encroachment – Design & Traffic Control
Tunnel Location
![Page 32: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/32.jpg)
12’ SEM Tunnel(Designed by Jacobs Engineering)
![Page 33: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/33.jpg)
54-Inch Water Main Replacement
![Page 34: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/34.jpg)
54-Inch Water Main Replacement
![Page 35: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/35.jpg)
Duke Endowment, Arts BBQ, H&R Block
Arts BBQ
Duke Endowment HQ & Parking Garage
Tunnel Shaft ~ 33 Feet Deep
Only Access
H&R Block
![Page 36: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/36.jpg)
Duke Endowment; Arts BBQ; & H&R Block
![Page 37: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/37.jpg)
Duke Endowment; Arts BBQ; & H&R Block
![Page 38: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/38.jpg)
Oriole Avenue Townhouses
![Page 39: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/39.jpg)
Oriole Avenue Townhouses
![Page 40: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/40.jpg)
Oriole Avenue Townhouses
![Page 41: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/41.jpg)
Oriole Avenue Townhouses
![Page 42: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/42.jpg)
Phase 2 – Final Design
Myrtle Square Apts
New Apts
CHA Redevelopment
90-Inch Pipe ~ 30 Feet Deep
78-Inch Pipe ~ 25 Feet Deep
InterconnectionsMain Driveway
Location Based on Preliminary Re-Development Plans
![Page 43: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/43.jpg)
Phase 2 –Sequence of Construction Prior to 90” & 78” Pipe Installation
1. Relocate Existing Private Utilities to New Location
2. Remove and Replace Existing Sanitary Sewer Mains in conflict with 90” & 78” Pipe
3. Re-instate Sewer Service Laterals to maintain sewer service during construction
4. Install temporary water main to remove existing water main in conflict with 90” & 78” Pipe
![Page 44: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/44.jpg)
Stakeholders
• Property Owners and Businesses• Duke Energy – Overhead Power Service• Cable TV & Telephone – Overhead Serve• Piedmont Natural Gas – Existing & Abandoned
Gas Mains• Charlotte Water – Water and Sewer Service to
Customers• CDOT - Traffic Control Plans
![Page 45: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/45.jpg)
Phase 2 –Sequence of Construction For 90” & 78” Pipe Installation
1. Setup 200’ max road closure2. Trim tree branches to prevent damage3. Install “active” shoring for open cut installation4. Install 90” & 78” Pipe, MH’s, and Street Drainage5. Install Temporary Pavement Restoration6. At Completion of City Block – Install New Water
System and Final Pavement Restoration
![Page 46: “Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina](https://reader036.vdocuments.mx/reader036/viewer/2022062323/5697c0011a28abf838cc22b7/html5/thumbnails/46.jpg)
Lessons Learned1. Improve Bid Advertising for Phase 2– Increase Number of Bidders
2. Additional Construction Location Restrictions– Oriole Street Started Earlier Than Expected– Construction Vehicle Parking, Material Deliveries
3. Stakeholder Involvement Increases During Construction– Significant Utility Coordination During Design – “Tip of Iceberg”– Property Owner Coordination - Unrealistic Requests– Day-to –Day Activities – Garbage Collection; Mail Delivery
4. Costs of “Handcuffing” Contractor– Unrealistic weekend closures
All These Lessons Learned Will Be Applied to Phase 2 !We Are Confident There Will Be Others to Overcome !