Purple Line Extension Section 2 Construction Community Meeting August 23, 2018

Upload: others

Post on 03-Jun-2020

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

Purple Line ExtensionSection 2 Construction Community Meeting August 23, 2018

Page 2: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

Agenda

• Wilshire/Rodeo Station

• Advance Utility Relocation

• Demo of former Ace Gallery

• N. Canon Demolition

• MOA City Council final Review

• N. Canon Drive Closure

• Century City/Constellation Station

• Advance Utility Relocation (AUR)

• Demo

• Constellation Bl Launch Box Closure

• #EatShopPlay #Century City

• Business Interruption Fund (BIF)

2

Page 3: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

Purple Line ExtensionProject Alignment

3

> 2.56 miles

Page 4: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

Sections 1, 2 & 3 Status

4

Forecasted Schedule

Section Section 1 Section 2 Section 3

Length 3.92 Miles 2.59 Miles 2.56 Miles

New Stations Wilshire/La Brea

Wilshire/Fairfax

Wilshire/La Cienega

Wilshire/Rodeo

Century City/

Constellation

Westwood/UCLA

Westwood/VA

Hospital

Pre-Construction

Activities

2014 – 2015 2016 – 2018 2018 – 2020

Construction 2015 – 2023 2018 – 2025 2019 – 2026

Operations 2023 2025 2026

*Subject to change. The PLE project team is working to deliver the project consistent with Measure M

Page 5: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

Purple Line ExtensionSection 2 Alignment

5

Page 6: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

Wilshire/Rodeo Station

Page 7: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

Wilshire/Rodeo StationStation Box

Rendering shows length of the underground station box on Wilshire Bl from Canon Dr to Beverly Dr

7

Page 8: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

Wilshire/Rodeo Station Schedule*As of August 2018, subject to change. Pending Council approval.

8

Page 9: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

Advance Utility RelocationOrange = AT&T Yellow= Gas

Page 10: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

SCG and AT&T Utility RelocationCombined Traffic Control * Dates subject to change

• Stage 6 behind K-rail• K-rail to remain 24/7 and work will take place behind it during approved

working hours• North side set up took place on August 15, 2018

10

• Wilshire, two lanes each direction, from west of Beverly to east of Canon

• Medians and parking removed from work zone

• Buses have been relocated outside of work zone

Page 11: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

SCG Utility RelocationStage 6: 12 days / Mon-Fri: 7am-7pm, Sat-Sun: 10am-6pm

11

Page 12: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

SCG Utility RelocationStage 7: 6 days / Mon-Fri: 7am-7pm, Sat-Sun: 10am-6pm

12

K-Rail 24/7

No Left Turns: EB Wilshire to NB Beverly

Page 13: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

SCG and AT&T Utility RelocationStage 8: 6 days / Mon-Fri: 7am-7pm, Sat-Sun: 10am-6pm

K-Rail 24/7

13

Page 14: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

Advance Utility RelocationBehind K-rail

14

Page 15: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

Advance Utility RelocationBehind K-rail

15

Page 16: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

Advance Utility RelocationBehind K-rail

16

Page 17: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

Demolition of 9430 Wilshire BlFormer Ace Gallery, future Construction Staging Yard

17

Page 18: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

Partial Closure of Reeves Park

Reeves Mini Park

• Metro is required to pay the City’s park rental fee for the closure of the park

• Required 30-day notification of the park closure

Wilshire Blvd

Bev

erl

y D

rive

Re

eve

s D

rive

9430 Wilshire Blvd

Reeves Mini Park

Proposed temporary closure area

Page 19: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

Demolition of 9430 Wilshire BlFormer Ace Gallery

Site Address: 9430 Wilshire Bl

Schedule

• Preparation started on July 16, 2018

• Estimated duration of demolition activities: 8-10 weeks

• Work hours: 8am - 6pm

• Portion of park may be closed temporarily

Traffic Impacts

• Sidewalk/partial lane closure along Reeves Dr and Wilshire Bl(intermittently throughout duration of demolition)

• Pedestrian protection to be installed

• Partial closure of the alley

•19

Page 20: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

• Work Hours: 8am – 6pm

• Start Date: Immediately following demolition. Anticipate September

• Sound wall installed using soldier piles and prefabricated noise panels

• Sound Wall: 20 feet

• Soundwall will have Public Information Graphics

20

Soundwall Installation

Example of prefab noise panels

Draft Staging Yard layout

Page 21: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

21

Wilshire/RodeoPublic Information Graphics

To be implemented on soundwall, Fall 2018

Page 22: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

22

Noise Control

• Independent Compliance Monitor (ICM)

• All construction personnel will attend Noise Awareness Training provided by Metro

• Moveable noise barriers

• Noise control curtains

• Noise muffling enclosures on stationary equipment

• No idling of heavy equipment when not in use

• No slamming tailgates

• Configure operations to eliminate backing movements

• Maintain equipment to avoid rattling and banging of parts

• Keep noise levels relatively uniform, avoid excessive and impulse noises

• Truck Manager will be onsite to ensure that trucks idle in and out of site to reduce noise levels at the site

Mitigation Measures: Noise

Page 23: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

23

Vibration

• Vibration Monitoring will be implemented

• If vibration approaches FEIS/R threshold, then operations causing higher levels of vibrationwill be minimized

• Vibration exceedance will cause all work activities to stop until corrective measures can beimplemented

Dust

• During demo, water will be used to control fugitive dust

• Use tarped trucks / covered loads

• Hand sweep work area prior to opening work area to traffic

• Implementation of the Mitigation Monitoring Reporting Program (MMRP)

• Dust control during transport, no idling of heavy equipment, maintenance of construction equipment

• Metro’s Green Construction Policy sets rigorous standards for equipment emissions

• Implementation of Best Management Practices (BMPs)

• Street watering, street sweeping, truck wheel track outs, wheel wash

Mitigation Measures: Vibration and Dust

Page 24: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

Air Quality Control Measures

Construction Air Quality Compliance

• Activities must comply with South Coast Air Quality Management District (SCAQMD) Rule 403, the reduction and control of fugitive dust

• Construction equipment is required to be registered with the California Air Resource Board (CARB)

• Use of Tier 4 equipment is required, which reduces emissions by over 95%

• Inspectors and Monitors actively observe daily activities and track compliance

• Report dust concerns to SCAQMD via 800-288-7664

24

Page 25: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

Abatement of N. Canon Properties

Site Address: 9383-9393 and 9395-9399 Wilshire Bl

Schedule

• Abatement - Completed

• Estimated duration of demolition activities: 5 weeks

• Work hours Monday - Friday 8am to 6pm

• Demolition anticipated in September 2018*

25

*Pending City Council Approval

Page 26: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

Memorandum of Agreement (MOA)

26

• Establish conditions and procedures for construction

• Minimize impact to the community

• Establish independent compliance monitor and enforcement process

• Key Elements:

• Work Hours

• Holiday Moratorium

• Business Mitigation Assistance

• Penalties and Fines

Page 27: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

MOA Holiday Moratorium*Pending City of Beverly Hills Council Approval

27

• Each year, Metro will request from COBH the right to workfrom Thanksgiving to New Years

• Requests will be required by each August (annually)

Page 28: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

MOA – Design-BuildBusiness Mitigation Assistance (BMA)

28

• 24/7 Hotline with live-person

• Advertising

• Eat Shop Play Beverly Hills

• Parking Replacement program

• Banners and signage (Aesthetic Treatment)

• Communications, Outreach and Engagement

• Traffic Control Officers

• Marketing

• Lighting

• Public Information Graphics

Page 29: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

Next StepsWilshire/Rodeo Station

29

City Council Approvals*

• MOA Design-Build Consideration – August 21 2018

*Subject to change

Page 30: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

Century City/Constellation Station

30

Page 31: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

Century City/ConstellationStation Box

Rendering shows length of the underground station box on Constellation Bl from Century Park East to Avenue of the Stars

31

Page 32: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

Century City/Constellation Station Schedule

32

*As of August 2018, subject to change.

Page 33: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

Century City/Constellation AUR Schedule

33

*As of August 2018, subject to change

Page 34: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

Advance Utility Relocation

34

Advanced Utility Relocation

Page 35: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

Advance Utility Relocation Schedule and Work Hours AT&T/DWP

AT&T: thru September, 2018

Work hours: Sunday through Thursday, 8pm to 6am

• Work will occur on Constellation Blvd west of Avenue of the Stars

DWP (Power): Continuous through 2019

• Work hours: Monday through Friday

12am-6am and 12am through 3pm

• Weekends: Friday, 12am through Monday, 8am

• Work will occur east and west of Avenue of the Stars

35

*Dates subject to change

AUR, Constellation Bl west of Avenue of the Stars (before)

Resurfaced (after)

Page 36: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

Century City/Constellation StationConstruction Staging Areas

36

Page 37: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

• Construction of sound wall• Sound Wall: 20 feet• Acceptable Noise Limits:

• Mon-Fri: 7am - 10pm = 75dBA• 10pm - 7am and Weekends:

No more than 5dBA over ambient/background

Construction Staging Areas1940, 1950 & 2040 Century Park East

Page 38: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

Construction Staging AreasProgress

Completed soundwall adjacent to Beverly Hills High School

Page 39: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

39

Site Address: 1940 & 1950 Century Park East

• 1940 Century Park East (formerly the California Bank building)

• 4-story structure with parking garage (3 stories and a basement)

• 1950 Century Park East (parking structure of former AAA building)

• 3 story parking structure

All Demolition activities completed!

Ongoing Activities:

• Backfill of basement at 1940 Century Park East

• Site grading

• Installation of sound wall around perimeter

1940 & 1950 Century Park EastDemolition = COMPLETED

Page 40: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

1940 & 1950 Century Park EastDemolition

40

Page 41: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

41

Full Closure of Constellation Blvd.at Century Park East

*Dates subject to change

Pre-Construction Activities

•Potholing – Completed this week

•Survey – Ongoing

Implementing Traffic Control for Full Closure:

• All traffic control measures will be in place by Monday, Sept. 24 at 6 AM

• Re-striping to begin on Friday, Sept. 21 at 8 PM.

• Implementation of traffic control measures & signal work will be completed throughout weekend.

• Intermittent lane closures will be utilized to assist with installation throughout the weekend

Page 42: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

42

Full Closure of Constellation Blvd.at Century Park East

*Dates subject to change

• No Public Access for Tenants through Driveway• Limited Access for:

• Large Trucks, Deliveries, Construction, Trash, Fedex/UPS (Flaggers will be present for access)

15 Month ClosureAnticipated to begin September 2018

Page 43: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

43

Full Closure of Constellation BlGeneral Detour/Circulation

Page 44: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

Anticipated: October 2018*

• Pile installation includes:

• Rig to drill holes

• Crane to lift piles into holes

• All work occurs behind k-rail (concrete barriers)

• Street will be reduced during operation

• Weekend closures may be needed to install piles across intersections

44

Pile Drilling InstallationStart Date *Dates subject to change

Example of piling work at Wilshire/La Brea

Page 45: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

45

Pile Drilling InstallationExample from Wilshire/La Cienega

Page 46: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

Anticipated: November 2018*• Construction of a concrete deck, curb-to-curb

• Sidewalks will be maintained or pedestrian detours created

• Decking will serve as the temporary street surface

• Traffic will travel on the installed deck panels while the station is constructed underground

• Typical station:

– Approximately 1000 feet long

– Approximately 70 feet wide

– Approximately 75 - 90 feet deep

• Metro will work closely with first responders on emergency access and safety

• Additional activities under decking closures: ground improvements, piling, temporary civil improvements

46

Decking InstallationOverview *Dates subject to change

Asphalt removal on Wilshire Bl near Detroit St

Steel beams welding prior to concrete deck panel installation

Page 47: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

47

Decking example from Wilshire/Fairfax, aerial view of decking progress from roof of the Petersen Automotive Museum

47

Page 48: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

4848

Decking InstallationSet-Up

Page 49: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

Monitoring and Coordination

• COLA/Metro/ TPOG will monitor traffic

• Turn lanes will remain open for use (except for full street closure on weekends)

• Access to driveways & entrances will be maintained (except for weekends)

• Access for Emergency Vehicles & First Responders will be maintained

49

Page 50: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

• Work primarily occurs underground beneath concrete decking

• Surface activities include:• Deliveries• Soil removal• Concrete pumping

• Material delivery and hauling occurs day/night

50

Station Construction24/7 Underground

Example of underground station construction

Page 51: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

Santa Monica Bus Layover

51

Scheduled to start early Fall 2018

Page 52: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

Tree Removal and Replacement• Estimate 15 trees need to be removed in public Right-

of-Way• 8 at Constellation Bl- removed• 7 at Santa Monica Bl

• Trees evaluated for relocation potential• Potential tree relocations

• 9 at Constellation Bl• 21at Santa Monica Bl

Platanus x acerfolia – London planetree, along south side of Constellation Bl

Ficus rubiginosa – Rusty leaf fig, at NE corner of Constellation Bl and Avenue of the Stars

Page 53: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

Tree Removal and ReplacementLandscape Plan Overview

• Metro will replace all trees 2:1

• Design-Builder responsible for landscape plan• Reviewed existing plan to ensure all trees

need to be removed

• Landscape palette dictated by existing palette and City requirements

• Workshops will be hosted by Design-Builder for community input

• City of Los Angeles has agreed to 36” box trees

• New irrigation, controllers and lighting for affected areas (Santa Monica Bl) Quercus agrifolia – Coastal live oak,

Santa Monica Bl

53

Page 54: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

Tree Removal and Replacement Constellation Bl

Note: To satisfy 2:1 ratio, additional tree replacements for Constellation Bl tree removals will be located at Santa Monica Bl

54

Page 55: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

Tree Removal and Replacement Santa Monica Bl

Page 56: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

Landscape Exhibit: Tree Replacement at Avenue of the Stars/Constellation Bl

Platanus x acerfolia –London planetree1

56

1TYP

Page 57: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

57

Lunch Pop-Up When: September 20, 11:30 am-1:30 pmWhere: Century Park

Come by the Eat Shop Play Pop-Up for information on the Constellation Blvd, closure

and to receive special prizes! Free TAP card giveaway at participating business.

Ask for yours today!

Page 58: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

Helping local businesses as we build.Update as of 8/10/18

Page 59: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

BIF Information and Eligibility

> Financial assistance to small “mom & pop” businesses with 25 or fewer employees directly impacted by Metro Rail construction along three project areas

> Businesses must be located immediately adjacent to the rail corridor and meet other eligibility requirements

> Grant amount determined by loss of business revenue related to period of construction disruption

> To date, 730 grants have been awarded with a total value of more than $16.4 million along all three projects

Page 60: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

BIF Grant Award Update

> Purple Line Extension, Section 1

> BIF Grants Awarded: 176

> BIF Grant Amount Awarded: $4,394,161.83

> Number of small businesses awarded: 69

> BIF Business Advisor: Brian Lazo

> Pacific Coast Regional Small Business Development Corporation (PCR)

> Phone: 213.739.2999

Page 61: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

BIF Grant Award Update

> Purple Line Extension, Section 2

> BIF Grants Awarded: 14

> BIF Grant Amount Awarded: $395,024.90

> Number of small businesses awarded: 13

> BIF Business Advisor: Darrell Smith

> Pacific Coast Regional Small Business Development Corporation (PCR)

> Phone: 213.739.2999

Page 62: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

Update on La Cienega and Rodeo Stations

Wednesday, September 5, 2018

6:30pm – 8pm

Beverly Hills City HallMunicipal Gallery

455 N. Rexford Drive

Beverly Hills, CA 90210

62

Next Community MeetingBeverly Hills

Page 63: Purple Line Extension - media.metro.netmedia.metro.net/projects_studies/westside/images/presentations-ple... · • Construction of a concrete deck, curb-to-curb • Sidewalks will

Section 2: Construction Community Meeting

Thursday, November 13, 2018

6:30pm – 8pm

Century Park Towers2029 Century Park EastLos Angeles, CA 90067

*Parking will be validated

63

Next Community MeetingSection 2