Public Service Company of ColoradoTransmission Projects Status

Public Service Company of ColoradoTransmission Projects Status

111

CCPGAugust 18, 2016

Transmission Ownership Colorado – 2016

Generation

Name Interconnection Owner Net MW Type ISD

Arapahoe 3 (retired) Arapahoe PSCo -44 Coal 2014

Limon 3 Missile Site 345 kV NextEra 200 Wind 2014

Zuni 2 (retired) Zuni PSCo -65 Coal 2015

3

Golden West Jackson Fuller 230 kV Golden West 250 Wind 2015

Hooper 1 San Luis Valley 230 kV Solar Star 52 Solar (PV) 2015

Comanche Solar Comanche 230 kV Comanche Solar 120 Solar (PV) 2016

Cherokee 3 (retired) Cherokee 115kV PSCo -152 Coal 2016

Cherokee 5,6, 7 Cherokee 115kV PSCo 570 Gas (CC) 2016

Rush Creek Missile Site 345 kV PSCo 600 Wind 2018

Rush Creek Generation Project

►CPUC Rule 3660►600 MW of New Wind Generation►90 Miles of 345 kV Transmission►PSCo-Owned►Interconnect at Missile Site►In-Service Date: 2018►Need Pawnee – Daniels Project►Filed with the Commission on May 13, 2016

►PUC decision made to combine Rush Creek and Pawnee –Daniels Park proceedings

►System Impact Study currently underway

4

44

►CPUC Rule 3660►600 MW of New Wind Generation►90 Miles of 345 kV Transmission►PSCo-Owned►Interconnect at Missile Site►In-Service Date: 2018►Need Pawnee – Daniels Project►Filed with the Commission on May 13, 2016

►PUC decision made to combine Rush Creek and Pawnee –Daniels Park proceedings

►System Impact Study currently underway

Rush Creek Map

5

New Substations

► 2016► Happy Canyon (IREA

Wholesale Load)► Cloverly (Pleasant Valley –

Retail Load)► 2019

► Husky (New Ault)► Graham Creek (New Eaton)

► 2022► Beebe Draw (LaSalle

Replacement)► TBD

► Box Elder Replacement► Reliability:

► Bluestone Valley

► Distribution► Avery (2017)► Moon Gulch (2017)► Thornton (2018)► Barker (2021)

► Conceptual► New Castle (TBD)► Wilson (TBD)

► Need may be replaced by City ofLoveland’s new Foothills substation

► Titan► Formerly Sterling Ranch TBD - 2020

► Dove Valley► Formerly Surrey Ridge TBD - 2020

► High Point► Formerly Pena Station TBD - 2020

► Stock Show► Formerly National Western TBD -

2026► Superior TBD - 2026► Sandy Creek TBD - 2026

► 2016► Happy Canyon (IREA

Wholesale Load)► Cloverly (Pleasant Valley –

Retail Load)► 2019

► Husky (New Ault)► Graham Creek (New Eaton)

► 2022► Beebe Draw (LaSalle

Replacement)► TBD

► Box Elder Replacement► Reliability:

► Bluestone Valley

► Distribution► Avery (2017)► Moon Gulch (2017)► Thornton (2018)► Barker (2021)

► Conceptual► New Castle (TBD)► Wilson (TBD)

► Need may be replaced by City ofLoveland’s new Foothills substation

► Titan► Formerly Sterling Ranch TBD - 2020

► Dove Valley► Formerly Surrey Ridge TBD - 2020

► High Point► Formerly Pena Station TBD - 2020

► Stock Show► Formerly National Western TBD -

2026► Superior TBD - 2026► Sandy Creek TBD - 2026

6

New TransmissionPlanned► 2016

► Rifle – Parachute 230 kV #2► DCP Lucerne 2 – Cloverly 115 kV

► 2018► Rush Creek – Missile Site 345 kV

► 2019► Ault – Cloverly 230/115 kV► Pawnee – Daniels Park 345 kV

► 2021► Gilman – Avon 115 kV

► 2022► Weld – Rosedale 230 kV► Milton – Rosedale 230 kV

Conceptual► San Luis Valley► Glenwood – Rifle Upgrade► Parachute – Cameo 230 kV► Lamar – Front Range► Weld County Expansion (Greeley –

East)► Hayden – Foidel – Gore Pass 230 kV

Loop

Planned► 2016

► Rifle – Parachute 230 kV #2► DCP Lucerne 2 – Cloverly 115 kV

► 2018► Rush Creek – Missile Site 345 kV

► 2019► Ault – Cloverly 230/115 kV► Pawnee – Daniels Park 345 kV

► 2021► Gilman – Avon 115 kV

► 2022► Weld – Rosedale 230 kV► Milton – Rosedale 230 kV

Conceptual► San Luis Valley► Glenwood – Rifle Upgrade► Parachute – Cameo 230 kV► Lamar – Front Range► Weld County Expansion (Greeley –

East)► Hayden – Foidel – Gore Pass 230 kV

Loop

Denver/Boulder

# Project Comments ISD* Drivers1 Moon Gulch

SubstationProposed new Distribution Substation in eitherthe City of Arvada or Jefferson County to servedistribution loads

2017 Distribution

2 Pawnee – DanielsPark 345 kVTransmission Line

Add an additional 345 kV line between thePawnee and Daniels Park substations.

2019 Reliability

3 Cherokee-Arvada-Ridge230kVConversion

Convert the existing 115kV line between theCherokee and Ridge substations to a 230kVline.

2016 ReliabilityandDistribution

4 ThorntonSubstation

New substation in Thornton to serve distributionloads. Replaces the Brantner Substationproject.

2017 Distribution44Thornton

Moon Gulch

8*All project in-service dates subject to change

DENVERDENVER

22

33

ThorntonSubstation

New substation in Thornton to serve distributionloads. Replaces the Brantner Substationproject.

5 Barker Substation New Substation in Denver Area to servedistribution load growth in Historic Ballpark Area

2021 Distribution11

44Moon Gulch

55

22

# Project Comments ISD* Drivers

1 Monfort – Cloverly 115 kV Radial load serving 115 kV line to retail Customer facility 2016 Load Growth

2 Avery Substation New distribution substation to serve loads in the area 2017 Distribution

3 Southwest WeldTransmission Project(SWEP)

Participate with Tri-State Project to improve reliability,increase load-serving and resource injection capability

2018 ReliabilityLoad GrowthResource

4 Milton–Rosedale 230 kV New line from Rosedale Substation to Milton SubstationCombined with Weld – Rosedale 230kV line creates 230kVbackbone south of Greeley.

2022 ReliabilityLoad Growth

5 Ault – Cloverly 230/115kVSubs:Husky, Graham Ck.

New line from Ault Substation to Cloverly Substation.Create new substations near PSCo Ault and Eaton to move44 kV loads to higher voltage.

2019 ReliabilityLoad GrowthResource

Foothills/Greeley Area

77

4488

5511

9*All project in-service dates subject to change

Ault – Cloverly 230/115kVSubs:Husky, Graham Ck.

New line from Ault Substation to Cloverly Substation.Create new substations near PSCo Ault and Eaton to move44 kV loads to higher voltage.

ReliabilityLoad GrowthResource

6 Weld – Rosedale 230 kVBeebe Draw Substation(LaSalle Upgrade)

New line from Rosedale Substation to Ault Substation.Build a new 230 kV substation (Beebe Draw) to replace theexisting 44kV La Salle Substation.Combined with Milton – Rosedale 230kV to create 230kVbackbone south of Greeley.

2022 ReliabilityLoad Growth

7 Weld County Expansion High voltage transmission from Ault to Greeley TBD ReliabilityResource

8 Wilson Substation New 115kV substation to serve distribution loads. Thisproject will tap PRPA’s 115kV Horseshoe – Westtransmission line

TBD Distribution

9 Box Elder Replacement Convert 44kV Box Elder Substation to a 115kV substation toservice growing loads in the area. Might tie into SWEP

TBD Load Growth

33Rosedale

664488

99

Current System Future Proposed System

# Project Comments ISD* Drivers

1 Grand Jct 138/115kV Replace 50 MVA TX with 100MVA TX

2016 Reliability

2 Bluestone ValleySubstation

New 230/69 kV transformer atBluestone. New 4 mile 69 kV linefrom Bluestone to Debeque

TBD Reliability

3 Rifle–Parachute 230 kVLine

New, second 230 kV line betweenRifle and Parachute

2016 Load GrowthReliability

4 Hayden – Foidel – GorePass 230kV Loop

loop Hayden-Gore Pass 230kVline into Foidel Creek Substationcreating a Hayden-Foidel Creek230kV Line #2 and a FoidelCreek-Gore Pass 230kV line.

TBD Reliability

44

Western Slope / Mountain Area

8899

11

loop Hayden-Gore Pass 230kVline into Foidel Creek Substationcreating a Hayden-Foidel Creek230kV Line #2 and a FoidelCreek-Gore Pass 230kV line.

5 Glenwood-Rifle 69 to115kV

Replace existing Glenwood-Rifle69 kV transmission system with115 kV system

TBD Reliability

6 Gilman–Avon 115kVLine

New 10-mile 115kV line in EagleCounty for reliability and alternatesource to Holy Cross customers

2021 Reliability

7 Parachute – Cameo230kV Line

New 230 kV line from theParachute substation to Cameosubstation

TBD Reliability

8 New Castle Substation Construct a new 115 kVsubstation to service Distributionloads in New Castle

TBD Distribution

9 Wolcott Reactor Install 40 MVAR reactor atWolcott.

2017 Reliability

3322

*All project in-service dates subject to change

55

11

6677

8899

Rifle – Parachute 230kV Project Line #2

►Purpose►Serve anticipated load growth (electric-driven

compressors) in the Piceance Basin►Description

►20 mile 230kV line►Electrically parallel to existing 230kV line

►Status►Filed CPCN in Dec 2012►CPCN Granted Feb 2013►ISD - 2016

►Purpose►Serve anticipated load growth (electric-driven

compressors) in the Piceance Basin►Description

►20 mile 230kV line►Electrically parallel to existing 230kV line

►Status►Filed CPCN in Dec 2012►CPCN Granted Feb 2013►ISD - 2016

12

Rifle -Parachute 230kV Line #2 Location Map

13

11

# Project Comments ISD* Drivers

1 IREA HappyCanyon

Construct a new 115 kV substationfor IREA

2016 WholesaleCustomer

South Denver/CO Springs Area

14*All project in-service dates subject to change

PSCo Public PolicySenate Bill 07-100

►Designate “Energy Resource Zones (ERZ)”►Develop plans for the construction or expansion of

transmission facilities necessary to deliver electric powerconsistent with the timing of the development of beneficialenergy resources located in or near such zones

►Consider how transmission can be provided to encouragelocal ownership of renewable energy facilities

►Submit proposed plans, designations, and applications forcertificates of public convenience and necessity to thecommission

15

1515

►Designate “Energy Resource Zones (ERZ)”►Develop plans for the construction or expansion of

transmission facilities necessary to deliver electric powerconsistent with the timing of the development of beneficialenergy resources located in or near such zones

►Consider how transmission can be provided to encouragelocal ownership of renewable energy facilities

►Submit proposed plans, designations, and applications forcertificates of public convenience and necessity to thecommission

Senate Bill 100 Project ListItem Project Zone In Service Date* Project Status

Planned

1. Missile Site 230kVSwitching Station

2 Nov 2010 In ServiceNo CPCN Required

2. Midway-Waterton 345kVTransmission Project

3,4,5 Jun 2011 In ServiceCPCN: July 2009

3. Missile Site 345kVSwitching Station

2 October 2012 In serviceCPCN: June 2010

4. Pawnee-Smoky Hill 345kVTransmission Project

1 June 2013 IN ServiceCPCN: Feb 2009

5. Pawnee-Daniels Park 345kVTransmission Project

1 2019 CPCN: April 2015

16*All project in-service dates subject to change

5. Pawnee-Daniels Park 345kVTransmission Project

1 2019 CPCN: April 2015

Conceptual

6. Lamar-Front Range 345kVTransmission Project

2, 3 TBD Studies Complete.No plans for full build-out at this time

7. Lamar-Vilas 230kVTransmission Project

3 TBD See Lamar – Front Range

8. Weld County Expansion Project 1 TBD Studies Ongoing

9. San Luis Valley 4 2022 OngoingCCPG – SLV Subcommittee

Pawnee to Daniels Park► Cost $178million► Purpose:

► Resource Accommodation,SB 07-100

► Infrastructure:► 124-mile transmission from

Pawnee Substation toDaniels Park Substation andfrom Smoky Hill Substationto Daniels Park Substation

► CPCN Approved► PSCo filed “Petition for

Variance” for ISD of Fall 2019► PUC Decision:

► Project combined with RushCreek

► Local Permitting Underway

17

► Cost $178million► Purpose:

► Resource Accommodation,SB 07-100

► Infrastructure:► 124-mile transmission from

Pawnee Substation toDaniels Park Substation andfrom Smoky Hill Substationto Daniels Park Substation

► CPCN Approved► PSCo filed “Petition for

Variance” for ISD of Fall 2019► PUC Decision:

► Project combined with RushCreek

► Local Permitting Underway

PSCo Regulatory ActivitiesRule 3627

PSCo Regulatory ActivitiesRule 3627

18

PSCo Regulatory ActivitiesRule 3627

PSCo Regulatory ActivitiesRule 3627

Zinn Photography/Courtesy of SunEdison

CPUC Rule 3627► Requires Regulated Utilities to File Transmission Report

► 10-Year Plan, 20-Year Scenario; 2-year cycle► Black Hills, Tri-State, Public Service

► Use CCPG as Forum► Proactive Stakeholder Participation► Report Filed February 2016► Proceeding Consolidated with SB07-100► Comments Received from OCC and IEA► ALJ Assigned; Ruled that Evidentiary Hearing Necessary► Schedule: ??► Goal: Ruling of Adequacy

► Requires Regulated Utilities to File Transmission Report► 10-Year Plan, 20-Year Scenario; 2-year cycle► Black Hills, Tri-State, Public Service

► Use CCPG as Forum► Proactive Stakeholder Participation► Report Filed February 2016► Proceeding Consolidated with SB07-100► Comments Received from OCC and IEA► ALJ Assigned; Ruled that Evidentiary Hearing Necessary► Schedule: ??► Goal: Ruling of Adequacy

19

20

6700

6800

6900

7000

PSCo Peak Demand

21

6300

6400

6500

6600

2010 2011 2012 2013 2014 2015 2016 2017

PSCo Peak Demand

Patrick Corrigan(303) 571-2747

[email protected] Green

(303) [email protected]