Presentation Outline
• Site Setting• Project Background• Coastal Processes Evaluation Summary• Outlet Structure Alternatives Assessment• Recommended Alternative• Next Steps
![Page 3: Public Presentation to the City of Milford, November 14, 2013](https://reader035.vdocuments.mx/reader035/viewer/2022062906/5866829c1a28ab68408b5e58/html5/thumbnails/3.jpg)
Presentation to City of Milford
Site Setting
![Page 4: Public Presentation to the City of Milford, November 14, 2013](https://reader035.vdocuments.mx/reader035/viewer/2022062906/5866829c1a28ab68408b5e58/html5/thumbnails/4.jpg)
Presentation to City of Milford
Site Setting
CHARLES ISLAND
GREAT CREEK TIDE GATEAND OUTLET STRUCTUREGREAT CREEK TIDE GATEAND OUTLET STRUCTURE
PUBLIC BEACHPUBLIC BEACH
GREAT CREEK
PARK ENTRANCEPARK ENTRANCE
LONG ISLAND SOUNDLONG ISLAND SOUNDSILVER SANDSSTATE PARK
SILVER SANDSSTATE PARK
![Page 5: Public Presentation to the City of Milford, November 14, 2013](https://reader035.vdocuments.mx/reader035/viewer/2022062906/5866829c1a28ab68408b5e58/html5/thumbnails/5.jpg)
Presentation to City of Milford
Site Setting
250 FT x 16 FT x 5 FTCONCRETE BOX CULVERT
180 FT LONG TIMBERTRAINING WALLS
TIDE GATE STRUCTURETIDE GATE STRUCTURE
![Page 6: Public Presentation to the City of Milford, November 14, 2013](https://reader035.vdocuments.mx/reader035/viewer/2022062906/5866829c1a28ab68408b5e58/html5/thumbnails/6.jpg)
Presentation to City of Milford
Site Setting
Great Creek and Tide Gate Structure InletGreat Creek and Tide Gate Structure Inlet
![Page 7: Public Presentation to the City of Milford, November 14, 2013](https://reader035.vdocuments.mx/reader035/viewer/2022062906/5866829c1a28ab68408b5e58/html5/thumbnails/7.jpg)
Presentation to City of Milford
Site Setting
Tide Gate Structure (behind tree screen)Tide Gate Structure (behind tree screen)
![Page 8: Public Presentation to the City of Milford, November 14, 2013](https://reader035.vdocuments.mx/reader035/viewer/2022062906/5866829c1a28ab68408b5e58/html5/thumbnails/8.jpg)
Presentation to City of Milford
Site Setting
Tide GatesTide Gates
![Page 9: Public Presentation to the City of Milford, November 14, 2013](https://reader035.vdocuments.mx/reader035/viewer/2022062906/5866829c1a28ab68408b5e58/html5/thumbnails/9.jpg)
Presentation to City of Milford
Site Setting
Great Creek Outlet Structure (looking east)Great Creek Outlet Structure (looking east)
![Page 10: Public Presentation to the City of Milford, November 14, 2013](https://reader035.vdocuments.mx/reader035/viewer/2022062906/5866829c1a28ab68408b5e58/html5/thumbnails/10.jpg)
Presentation to City of Milford
Site Setting
Box Culvert Discharge PointBox Culvert Discharge Point
![Page 11: Public Presentation to the City of Milford, November 14, 2013](https://reader035.vdocuments.mx/reader035/viewer/2022062906/5866829c1a28ab68408b5e58/html5/thumbnails/11.jpg)
Presentation to City of Milford
Site Setting
Great Creek Outlet Structure (looking northwest)Great Creek Outlet Structure (looking northwest)
![Page 12: Public Presentation to the City of Milford, November 14, 2013](https://reader035.vdocuments.mx/reader035/viewer/2022062906/5866829c1a28ab68408b5e58/html5/thumbnails/12.jpg)
Presentation to City of Milford
Project Background
![Page 13: Public Presentation to the City of Milford, November 14, 2013](https://reader035.vdocuments.mx/reader035/viewer/2022062906/5866829c1a28ab68408b5e58/html5/thumbnails/13.jpg)
Presentation to City of Milford
Project Background
• Damage occurred to outlet structure
![Page 14: Public Presentation to the City of Milford, November 14, 2013](https://reader035.vdocuments.mx/reader035/viewer/2022062906/5866829c1a28ab68408b5e58/html5/thumbnails/14.jpg)
Presentation to City of Milford
Project Background
• DEEP temporarily repaired training wall– Tiebacks installed to new sheet pile deadman
![Page 15: Public Presentation to the City of Milford, November 14, 2013](https://reader035.vdocuments.mx/reader035/viewer/2022062906/5866829c1a28ab68408b5e58/html5/thumbnails/15.jpg)
Presentation to City of Milford
Project Background
• Sinkholes continue to form after temporary repairs– Additional repairs made by DEEP
![Page 16: Public Presentation to the City of Milford, November 14, 2013](https://reader035.vdocuments.mx/reader035/viewer/2022062906/5866829c1a28ab68408b5e58/html5/thumbnails/16.jpg)
Presentation to City of Milford
Project Background
• Tide gate structure inspected– Tide gates functioning properly– Minor repairs recommended
• Borings performed adjacent to the training walls– Dense sand and silt layer identified approx. 15’ deep– Makes driving conventional wooden piles difficult
• Coastal Engineering study performed
![Page 17: Public Presentation to the City of Milford, November 14, 2013](https://reader035.vdocuments.mx/reader035/viewer/2022062906/5866829c1a28ab68408b5e58/html5/thumbnails/17.jpg)
Presentation to City of Milford
Coastal ProcessesEvaluation Summary
![Page 18: Public Presentation to the City of Milford, November 14, 2013](https://reader035.vdocuments.mx/reader035/viewer/2022062906/5866829c1a28ab68408b5e58/html5/thumbnails/18.jpg)
Presentation to City of Milford
Coastal Processes Evaluation Summary
• Evaluate site-specific coastal processes• Improve structural stability of updrift
structure• Improve sediment bypassing• Reduce downdrift beach impacts• Minimize potential for flanking of
downdrift structure• Maintain inlet stability and maintenance• Minimize safety concerns
![Page 19: Public Presentation to the City of Milford, November 14, 2013](https://reader035.vdocuments.mx/reader035/viewer/2022062906/5866829c1a28ab68408b5e58/html5/thumbnails/19.jpg)
Presentation to City of Milford
Coastal Processes Evaluation Summary
1. Data Collection• Sediment samples• Beach profiles• Tidal currents and flux• Tide data• Existing wind and wave data
2. Coastal Processes Analysis and Modeling• Wave Transformation Modeling• Sediment Transport Modeling• Inlet Stability Analysis
3. Alternatives Analysis• Alternatives Considered• Sediment Distribution• Beach Nourishment Performance
![Page 20: Public Presentation to the City of Milford, November 14, 2013](https://reader035.vdocuments.mx/reader035/viewer/2022062906/5866829c1a28ab68408b5e58/html5/thumbnails/20.jpg)
Presentation to City of Milford
Coastal Processes Evaluation Summary
![Page 21: Public Presentation to the City of Milford, November 14, 2013](https://reader035.vdocuments.mx/reader035/viewer/2022062906/5866829c1a28ab68408b5e58/html5/thumbnails/21.jpg)
Presentation to City of Milford
Coastal Processes Evaluation Summary
TideGate(s)Close
After the tide gate(s) close, slowrise in water surface elevation
due to freshwater input
![Page 22: Public Presentation to the City of Milford, November 14, 2013](https://reader035.vdocuments.mx/reader035/viewer/2022062906/5866829c1a28ab68408b5e58/html5/thumbnails/22.jpg)
Presentation to City of Milford
Coastal Processes Evaluation Summary
The Bar
GreatCreekOutlet
CharlesIsland
MilfordHarborChannel
Simulation Cases• Annual Wave Conditions
(MHW, MTL, MLW)• Return Period and Historical
Storms (10-, 50-, 100-yearstorms and Hurricanes Irene[2011] and Gloria [1985])
• Sea Level Rise
![Page 23: Public Presentation to the City of Milford, November 14, 2013](https://reader035.vdocuments.mx/reader035/viewer/2022062906/5866829c1a28ab68408b5e58/html5/thumbnails/23.jpg)
Presentation to City of Milford
Coastal Processes Evaluation Summary
![Page 24: Public Presentation to the City of Milford, November 14, 2013](https://reader035.vdocuments.mx/reader035/viewer/2022062906/5866829c1a28ab68408b5e58/html5/thumbnails/24.jpg)
Presentation to City of Milford
Coastal Processes Evaluation Summary
![Page 25: Public Presentation to the City of Milford, November 14, 2013](https://reader035.vdocuments.mx/reader035/viewer/2022062906/5866829c1a28ab68408b5e58/html5/thumbnails/25.jpg)
Presentation to City of Milford
Coastal Processes Evaluation Summary
Nearshore Circulation- Physically-based representation- Driven by breaking waves in the surf zone- Based on Depth-averaged mass and
momentum- Provides stream function and vorticity
![Page 26: Public Presentation to the City of Milford, November 14, 2013](https://reader035.vdocuments.mx/reader035/viewer/2022062906/5866829c1a28ab68408b5e58/html5/thumbnails/26.jpg)
Presentation to City of Milford
Coastal Processes Evaluation Summary
4 5 6 7
Average annual rate = 14,600 cy/yr to the east (near the outlet)*as long as sand is available
![Page 27: Public Presentation to the City of Milford, November 14, 2013](https://reader035.vdocuments.mx/reader035/viewer/2022062906/5866829c1a28ab68408b5e58/html5/thumbnails/27.jpg)
Presentation to City of Milford
AlternativesAssessment
![Page 28: Public Presentation to the City of Milford, November 14, 2013](https://reader035.vdocuments.mx/reader035/viewer/2022062906/5866829c1a28ab68408b5e58/html5/thumbnails/28.jpg)
Presentation to City of Milford
Alternatives Assessment
• No action• Replacement in kind• Removal of training walls• Shortening of training walls• Tapering the elevation of training walls• Culvert extension• Culvert extension with training wall shortening• New outlet structure
![Page 29: Public Presentation to the City of Milford, November 14, 2013](https://reader035.vdocuments.mx/reader035/viewer/2022062906/5866829c1a28ab68408b5e58/html5/thumbnails/29.jpg)
Presentation to City of Milford
Alternatives Assessment
• Balance of inlet stability and sediment bypassing
• Criteria Evaluated– Inlet stability– Downdrift beach– Cost– Service Life– Maintenance requirements– Safety– Modular design
![Page 30: Public Presentation to the City of Milford, November 14, 2013](https://reader035.vdocuments.mx/reader035/viewer/2022062906/5866829c1a28ab68408b5e58/html5/thumbnails/30.jpg)
Presentation to City of Milford
Training Wall Adjustments
Evaluated a range of reductionsReduce length by 30 feet and/or taper slope over 100 feetAllows an additional 1,500-1,800 yd3/yr to naturally bypassMaintains stability of outlet
![Page 31: Public Presentation to the City of Milford, November 14, 2013](https://reader035.vdocuments.mx/reader035/viewer/2022062906/5866829c1a28ab68408b5e58/html5/thumbnails/31.jpg)
Presentation to City of Milford
Culvert ExtensionExtend culvert and reduce training wallsAllows an additional 3,800 yd3/yr to naturally bypassMaintains stability of outlet
![Page 32: Public Presentation to the City of Milford, November 14, 2013](https://reader035.vdocuments.mx/reader035/viewer/2022062906/5866829c1a28ab68408b5e58/html5/thumbnails/32.jpg)
Presentation to City of Milford
RecommendedAlternative
![Page 33: Public Presentation to the City of Milford, November 14, 2013](https://reader035.vdocuments.mx/reader035/viewer/2022062906/5866829c1a28ab68408b5e58/html5/thumbnails/33.jpg)
Presentation to City of Milford
Recommended Alternative
• Configuration based on Coastal Study– Shorten training walls by 30 feet– Extend box culvert to increase sediment transport
• Various training wall options explored1. Timber piles and lagging – Piles difficult to drive through
confining layer2. Steel sheet piling – Least aesthetically pleasing and difficult to
modify after installation3. Precast concrete piles and panels – Most expensive option
and difficult to modify after installation4. Steel piles with timber lagging – Deemed best compromise
on pile drivability, flexibility, aesthetics, and cost
![Page 34: Public Presentation to the City of Milford, November 14, 2013](https://reader035.vdocuments.mx/reader035/viewer/2022062906/5866829c1a28ab68408b5e58/html5/thumbnails/34.jpg)
Presentation to City of Milford
Recommended Alternative
Existing Great Creek Outlet StructureExisting Great Creek Outlet Structure
![Page 35: Public Presentation to the City of Milford, November 14, 2013](https://reader035.vdocuments.mx/reader035/viewer/2022062906/5866829c1a28ab68408b5e58/html5/thumbnails/35.jpg)
Presentation to City of Milford
Recommended Alternative
Proposed Great Creek Outlet StructureProposed Great Creek Outlet Structure
![Page 36: Public Presentation to the City of Milford, November 14, 2013](https://reader035.vdocuments.mx/reader035/viewer/2022062906/5866829c1a28ab68408b5e58/html5/thumbnails/36.jpg)
Presentation to City of Milford
Next Steps
![Page 37: Public Presentation to the City of Milford, November 14, 2013](https://reader035.vdocuments.mx/reader035/viewer/2022062906/5866829c1a28ab68408b5e58/html5/thumbnails/37.jpg)
Presentation to City of Milford
Next Steps
• Obtain State permits from the DEEP Office of the LongIsland Sound Programs (OLISP)– Project requires a Certificate of Permission (COP)
• Prepare Construction Documents• Solicit bids for proposed work• Hire a contractor• Begin construction
– May be restricted from working during certain times of year