PUBLIC HEARING ON THE PROPOSED
IMPROVEMENTS FOR THE
2020-2021 INFRASTRUCTURE IMPROVEMENTS
City of Springfield, MN
November 12, 2019
Project Area Includes:
• Central Street
• TH 14 to O’Connell Avenue
• Rock Street/Trunk Highway 14
• Park Avenue to Washington Avenue
Existing ConditionsCentral Street
Existing ConditionsCentral Street
Proposed Utility ImprovementsCentral Street
Proposed Utility ImprovementsCentral Street
Proposed Surface ImprovementsCentral Street
Proposed Surface ImprovementsCentral Street
Proposed Surface ImprovementsCentral Street
Proposed Surface ImprovementsCentral Street
Rectangular Rapid Flashing Beacon’sCentral Street
Central Street - Crossing Improvements
Central Street - Crossing Improvements
Central Street - Streetscape Layout
Central Street - Streetscape Layout
Summary of Project Cost
Street Construction $2,949,800
Sanitary Sewer Construction $569,900
Watermain Construction $579,200
Storm Sewer Construction $592,200
TOTAL $4,691,100
Summary of Project Funding
FUNDING SOURCES TOTAL
Local Road Imp. Program- Grant $750,000
Local Partnership Program-Grant $488,060
County Assistance $81,090
PUC – Sanitary Sewer $454,270
PUC - Water $434,420
Storm Sewer $592,180
City Funds $968,780
Assessments $922,300
TOTAL $4,691,100
Special Assessment Policy
IMPROVEMENTS
NEW
CONSTRUCTION
% ASSESSED
RECONSTRUCTION
% ASSESSED
Seal Coat NA 0%
Bituminous OverlayFront LotSide Lot
NA30%15%
Alleys (Bituminous) 100% 100%
Street SurfaceFront LotSide Lot
100% 20%15%
Curb & Gutter 100% 100%
Driveway Approach & Service Walk
100% 100%
Special Assessment Policy
IMPROVEMENTS
NEW
CONSTRUCTION
% ASSESSED
RECONSTRUCTION
% ASSESSED
Boulevard Walk 50% 50%
Storm Sewer 100% 0%
Sanitary MainFront LotSide Lot
100%30%15%
Sanitary Service 100% 100%
Water MainFront LotSide Lot
100%30%15%
Water Service 100% 100%
Preliminary Assessment Rates
ITEM % ASSESSEDESTIMATED
RATES
43’ Residential StreetFront Lot Side Lot
20%15%
$48.00/LF$36.00/LF
Frontage Road
Front Lot 20% $32.00/LF
Concrete Curb & Gutter 100% $22.00/LF
Concrete Driveway 100% $10.00/SF
Concrete Service Walk 100% $8.00/SF
Concrete Boulevard Walk 50% $4.00/SF
Construct Pavers 100% $10.00/SF
Preliminary Assessment Rates
ITEM % ASSESSED
ESTIMATED
RATES
Sanitary Sewer MainFront Lot Side Lot
30%15%
$14.00/LF$7.00/LF
Sanitary Sewer Service 100% $2,100.00/EA
Water MainFront Lot Side Lot
30%15%
$22.00/LF$11.00/LF
Water Service 100% $2,300.00/EA
Proposed Project Schedule
October, 2019November, 2019
March, 2020April, 2020May, 2020
November, 2020
July, 2021September, 2021October, 2021November, 2021April, 2022
Council calls for Hearing on ImprovementHold Hearing on ImprovementCouncil Authorizes Preparation of Plans & SpecificationsCouncil Authorizes Advertisement for BidsBid OpeningCouncil considers bids and awards contractBegin ConstructionSubstantial Completion Including Utility Improvements, Concrete Work & Bituminous Non-wear CourseFinal Completion of all ConstructionCouncil calls for the Hearing on AssessmentHearing on AssessmentCouncil Certifies the Assessment Roll to the CountyFirst Assessment Installment Paid along with Property Taxes.
Questions?