Public Engagement Program
Round 1 Public Open House Storyboards
![Page 2: Public Engagement Program Round 1 Public Open House ... · • Identification of preliminary route. • Finalization of preferred route. • Environmental Assessment of preferred](https://reader034.vdocuments.mx/reader034/viewer/2022050603/5faa6a13fe12e00f8d26f587/html5/thumbnails/2.jpg)
Pointe du Bois Transmission Project Open House
Welcome
pointe_du_bois_storyboards_output.indd 1 13-06-14 2:49 PM
![Page 3: Public Engagement Program Round 1 Public Open House ... · • Identification of preliminary route. • Finalization of preferred route. • Environmental Assessment of preferred](https://reader034.vdocuments.mx/reader034/viewer/2022050603/5faa6a13fe12e00f8d26f587/html5/thumbnails/3.jpg)
Purpose of the Open House
Manitoba Hydro is holding this open house to:
• Shareprojectinformation.
• Provideinformationonsiteselectionandenvironmentalassessmentprocesses.
• Discusscomments,provideanswersandidentifypotentialconcerns.
• CollectinputontheGeneralProjectAreathatwillassistusindevelopingapreferredroutefortheProject.
pointe_du_bois_storyboards_output.indd 2 13-06-14 2:49 PM
![Page 4: Public Engagement Program Round 1 Public Open House ... · • Identification of preliminary route. • Finalization of preferred route. • Environmental Assessment of preferred](https://reader034.vdocuments.mx/reader034/viewer/2022050603/5faa6a13fe12e00f8d26f587/html5/thumbnails/4.jpg)
Need for the Project
• Existing66-kVtransmissionlinesfromPointeduBoistoWinnipeghavereachedtheendoftheirserviceablelife.
• Theproposedprojectreplacestheexisting66-kVlines,improvingsystemreliability.
• OtherrelatedsystemimprovementsthathavebeencompletedwillfacilitatethetransferofenergyfromthisnewtransmissionlinetoWinnipeg.
pointe_du_bois_storyboards_output.indd 3 13-06-14 2:49 PM
![Page 5: Public Engagement Program Round 1 Public Open House ... · • Identification of preliminary route. • Finalization of preferred route. • Environmental Assessment of preferred](https://reader034.vdocuments.mx/reader034/viewer/2022050603/5faa6a13fe12e00f8d26f587/html5/thumbnails/5.jpg)
Project Description
pointe_du_bois_storyboards_output.indd 4 13-06-14 2:49 PM
![Page 6: Public Engagement Program Round 1 Public Open House ... · • Identification of preliminary route. • Finalization of preferred route. • Environmental Assessment of preferred](https://reader034.vdocuments.mx/reader034/viewer/2022050603/5faa6a13fe12e00f8d26f587/html5/thumbnails/6.jpg)
Other Activities
pointe_du_bois_storyboards_output.indd 5 13-06-14 2:49 PM
![Page 7: Public Engagement Program Round 1 Public Open House ... · • Identification of preliminary route. • Finalization of preferred route. • Environmental Assessment of preferred](https://reader034.vdocuments.mx/reader034/viewer/2022050603/5faa6a13fe12e00f8d26f587/html5/thumbnails/7.jpg)
Public Engagement Process
pointe_du_bois_storyboards_output.indd 6 13-06-14 2:49 PM
![Page 8: Public Engagement Program Round 1 Public Open House ... · • Identification of preliminary route. • Finalization of preferred route. • Environmental Assessment of preferred](https://reader034.vdocuments.mx/reader034/viewer/2022050603/5faa6a13fe12e00f8d26f587/html5/thumbnails/8.jpg)
Project Timeline
We are here.
Round 2 - July/August
• Presentpreliminaryroute.
• Identifyanddocumentanyconcernswiththerouteand/ortheproject.
• Considerpotentialproject-basedeffects.
• Identifymitigationmeasures.
•Documentwhatwasheard.
Next Steps
•Confirmationofthepreferredroute.
• SubmissionoftheEnvironmentalAssessmentReport.
• Regulatoryauthoritiesreviewreport.
• Construction.
• Inservicespring/ summer2016.
Round 1 - May/June
• Introducetheproject.
•Describetherouteselectionprocess.
•Outlinetheregulatoryprocessandtimelines.
• Receiveinputtobeutilizedintheselectionoftheroute.
•Documentwhatwasheard.
pointe_du_bois_storyboards_output.indd 7 13-06-14 2:49 PM
![Page 9: Public Engagement Program Round 1 Public Open House ... · • Identification of preliminary route. • Finalization of preferred route. • Environmental Assessment of preferred](https://reader034.vdocuments.mx/reader034/viewer/2022050603/5faa6a13fe12e00f8d26f587/html5/thumbnails/9.jpg)
A site selection process will determine a transmission line route based on technical, ecological, social, land use and economic factors as well as public input.
Site selection process steps include:
• Studyareadelineation.• Identificationofrouteselectionfactors.• Routeselectionfactorscoringandweighting.• Identificationofpreliminaryroute.• Finalizationofpreferredroute.• EnvironmentalAssessmentofpreferredroute.
Site Selection Process
pointe_du_bois_storyboards_output.indd 8 13-06-14 2:49 PM
![Page 10: Public Engagement Program Round 1 Public Open House ... · • Identification of preliminary route. • Finalization of preferred route. • Environmental Assessment of preferred](https://reader034.vdocuments.mx/reader034/viewer/2022050603/5faa6a13fe12e00f8d26f587/html5/thumbnails/10.jpg)
Regulatory Process & Environmental Assessment
The Project will require a Class 2 Licence under The Environment Act (Manitoba).
The Project’s Environmental Assessment Report will be submitted to Manitoba Conservation and Water Stewardship for review and approval.
A public review process will take place following submission.
If Manitoba Conservation and Water Stewardship grants Manitoba Hydro a project licence, construction is anticipated to begin in late 2014.
pointe_du_bois_storyboards_output.indd 9 13-06-14 2:49 PM
![Page 11: Public Engagement Program Round 1 Public Open House ... · • Identification of preliminary route. • Finalization of preferred route. • Environmental Assessment of preferred](https://reader034.vdocuments.mx/reader034/viewer/2022050603/5faa6a13fe12e00f8d26f587/html5/thumbnails/11.jpg)
Regulatory Process & Environmental Assessment
The Environmental Assessment Report includes:
pointe_du_bois_storyboards_output.indd 10 13-06-14 2:50 PM
![Page 12: Public Engagement Program Round 1 Public Open House ... · • Identification of preliminary route. • Finalization of preferred route. • Environmental Assessment of preferred](https://reader034.vdocuments.mx/reader034/viewer/2022050603/5faa6a13fe12e00f8d26f587/html5/thumbnails/12.jpg)
Thank you
Please complete a comment form and leave
it with a Manitoba Hydro representative.
Thank you for attending the Open House
and providing feedback on the proposed
Pointe du Bois Transmission Project.