public company limited -...
TRANSCRIPT
NAWARAT PATANAKARNPUBLIC COMPANY LIMITED
SET : Opportunity Day, 16 June 2016
www.nawarat.co.th
IR Section T: +662 730 2100 F: +662 751 9484 E: [email protected]
A: 18th-19th Floor, Bangna Towers (A), 2/3 Moo 14, Bangna-Trad Rd, km. 6.5, Bangkaew, Bangplee, Samutprakarn 10540 Thailand
1
Disclaimer
I m p o r t a n t N o t i c e:
The content of the presentation provided by the Nawarat Patanakarn Public Company
Limited (the “Company”) is intended to provide as information for discussion purpose only
and is strictly for private and confidential. Past performance is not indicative of future
performance. Any unauthorised disclosure, use or dissemination, either whole or partial,
is prohibited. It must not be reproduced, copied or made available to others. Some of the
information in this presentation may contain projections or other forward looking
statements regarding future events or future financial performance of countries, markets
or companies. These statements are only predictions and actual events or results may
differ materially. The reader must make his/her own assessment of the relevance,
accuracy and adequacy of the information contained in this presentation and make such
independent investigations as he/she may consider necessary or appropriate for the
purpose of such assessment. Any opinion or estimate contained in this presentation is
made on a general basis and is not to be relied on by the reader as advice. Neither the
Company nor any of its servants or agents have given any consideration to nor have they
or any of them made any investigation of the investment objectives, financial situation or
particular need of the reader, any specific person or group of persons. Accordingly, no
warranty whatsoever is given and no liability whatsoever is accepted for any loss arising
whether directly or indirectly as a result of the reader, any person or group of persons
acting on any information, opinion or estimate contained in this presentation.
2
Q1/2016 Financial Highlights
Q1/2016 Financial Performance (Unit : THB mm)
Construction contract +1,603.7
Rendering of sale and service +89.1
Other Income +10.8
Total revenues +1,703.6
Cost of construction -1,482.2
Cost of sale and service -86.0
SG&A -107.6
Doubtful debts -
Total Expense -1,675.8
Profit (loss) from associates +32.8
Finance cost -48.6
Income Tax -0.8
Net earning +11.2
Non-controlling Interest +3.1
Net earning to Equity Holders +14.3
11
Key Performance Index
Construction Revenue and Growth (Unit:THB mm) Gross Margin
SG&A/Sales Net Margin
13
New Projects Awarded (Unit:THB mm) Backlog Amounts (Unit:THB mm)
D/E ratio Current Ratio
Key Performance Index
11,152 8,387 10,060 10,505 11,381 10,495
445 2,475
1,211 4,144 2,475 2,955
11,597 10,862 11,271 14,649 13,856 13,450
2011 2012 2013 2014 2015 Q1/16
Signed Contract
Unsigned Contract (with high certainty)
14
Current Backlog(Signed Contract)
Item Owner Project Description Start End Total
Value Remaining Project Type
1
Bangkok Metropolitan
Administration [BMA]Drainage System - Bangtoei Canal
Jul-10 May-15 270 11% Infrastructure
2
Bangkok Metropolitan
Administration [BMA]Drainage Tunnel under Bangsue Canal
Sep-13 Aug-16 2,300 53% Tunnel
3Department of Highways [DOH]
Construction of Bypass from Highway No.3
Section 3 Sep-13 Jun-16 1,100 13% Infrastructure
4Private
Construction of Material Trade Building,
Suratthani Sep-13 Feb-15 100 74% Industrial
5Private
Civil and Architectural Work ABP4 CCCP
& ABP5 CCCP, Amata Nakorn Industrial Sep-13 Jul-15 580 0% Industrial
6Private
Construction of Car Showroom, Office &
Car Park - Nonthaburi Feb-14 Feb-15 300 10% Building
7
Industrial Estate Authority of
Thailand
Flood Wall around Lad Krabang Industrial
Estate Jun-14 Mar-15 520 1% Infrastructure
8Mana Patanakarn Co., Ltd. Construction of "Baranee Park", Romklao
Mar-14 Sep-15 500 55% Building
9MPWT Lao PDR Road Improvement Project, Lao
May-14 Nov-16 600 43% Infrastructure
10Private
Jetty Work of Receiving Terminal Expansion
Project Phase 2, Rayong Jul-14 Mar-16 600 0% Marine
11Private Construction of Hotel, Nakhonratchasima
Jul-14 Sep-16 550 30% Building
12Private Construction of Hotel, Pattaya
Jul-14 Sep-15 400 19% Building
13Private Construction of Flood Wall, Nakhonpathom
Sep-14 Jun-15 200 0% Infrastructure
14Private
BOWIN Combined Cycle Cogeneration
Plant, Amata Nakorn Industrial Estate Sep-14 Jun-16 350 6% Industrial
15Private
Design and Construction of Road and Utility
(Phase 2), Industrial Estate Oct-14 Mar-16 630 18% Infrastructure
16Private
Water Tunnel for Flood Protection System
Phase 1 - Chiangmai Jul-14 Oct-15 90 0% Tunnel
17Private Pagoda - 5th-7th Floor, Chanthaburi
Nov-14 Nov-16 90 40% Building
18Private Ratchaburi Power Plant
Nov-14 Dec-16 1,300 60% Industrial
19Private Oil Business Academy, Ayutthaya
Dec-14 Dec-15 340 0% Building
[last update 31/03/2016] [Unit : Million Baht]
16
Current Backlog(Signed Contract)
Item Owner Project Description Start End Total
Value Remaining Project Type
20Private
Mae Moh Power Plant Units 4-7
Replacement Project, Lampang May-15 Jan-19 2,900 44% Industrial
21
Department of Public Works and
Town & Country Planning [DPT]
Flood Protection System Phase 3 - Omnoi,
Samutsakhon May-15 Sep-17 170 10% Infrastructure
22Private
Manholes and Underground Electrical
Conduits - Light Green MRT Line May-15 Apr-17 1,000 91% Tunnel
23Department of Rural Roads
The Ratchaphruek Road Extension Phase 2
(Section 2) Mar-15 Mar-17 440 80% Infrastructure
24Metropolitan Electricity Authority
The Ratchaphruek Road Extension Phase 2
(Section 2) Mar-15 Mar-17 400 100% Infrastructure
25
Metropolitan Waterworks
Authority
The Ratchaphruek Road Extension Phase 2
(Section 2) Mar-15 Mar-17 35 84% Infrastructure
26TOT Public Co., Ltd.
The Ratchaphruek Road Extension Phase 2
(Section 2) Mar-15 Mar-17 50 100% Infrastructure
27Private
Construction of Car Showroom & Office -
Sainoi Branch Jun-15 Jan-16 110 25% Building
28
Department of Drainage and
SewerageReinforced Concrete Dam - Sawat Canal
Oct-15 Oct-16 100 75% Infrastructure
29Department of Highways
Overpass Crossing Intersection Highway #
3256 with Highway # 3268 Apr-15 Jun-17 370 100% Infrastructure
30Marine Department
Bank Protection Dam in Pasak River Phase 1
(Section 2) Apr-15 Oct-17 560 84% Infrastructure
31
Department of Public Works and
Town & Country Planning [DPT]Flood Protection System, Angthong
Sep-15 Mar-18 340 92% Infrastructure
32
Department of Drainage and
SewerageImprove Drainage System, Sukho Thai Palace
May-15 Nov-15 50 0% Infrastructure
33
Department of Drainage and
Sewerage
Reinforced Concrete Dam - Thawiwatthana
Canal Oct-15 Jul-16 35 50% Infrastructure
34
Department of Drainage and
Sewerage
Improve Cover Pipeline Pumping,
Sukhumvit 42 Sep-15 Dec-15 10 0% Infrastructure
35Port Authority of Thailand
Construction of Laem Chabang Port (Port A)
with Facility Dec-15 Nov-16 1,030 100% Marine
18,420 8,563
36
Electricity Generating Authority
of Thailand [EGAT]Mae Moh Mine, EGAT [NWR-SCBB 50:50]
Mar-09 Feb-18 8,400 23% Earth Work
8,400 1,932
SUB TOTAL===>
Joint Venture
SUB TOTAL===>
[last update 31/03/2016] [Unit : Million Baht]
17
Current Backlog (Unsigned Contract)
Item Owner Project Description Start End Total
Value Remaining Project Type
1
Department of Drainage and
Sewerage
Improve Drainage System, Chitralada Villa
Royal Residence
180
Day 55 100% Infrastructure
2Metropolitan Electricity Authority
Underground Power Transmission Lines,
Khlong Phra Khanong
600
Day 375 100% Tunnel
3Metropolitan Electricity Authority
Manholes and Underground Electrical
Conduits, Chulalongkorn Hospital
700
Day 140 100% Tunnel
4Metropolitan Electricity Authority
Manholes and Underground Electrical
Conduits, Ramintra Road
840
Day 240 100% Tunnel
5
Department of Drainage and
Sewerage
Improve Drainage System, Chitralada Villa
Royal Residence (Project 2)
240
Day 15 100% Infrastructure
6Expressway Authority of Thailand
Build and Reconstruction a connecting route
to Expressway Kanchanaphisek
720
Day 440 100% Infrastructure
7Department of Highways
Construction of railway overpass of train
route of Don Si Non - Ban Pho district
780
Day 180 100% Infrastructure
8Private
ABPR3 - 123MW Combined Cycle
Cogeneration Plant, Rayong
720
Day 340 100% Industrial
9Department of Highways
Roadway Extension from Highway No.7
Route of Bangkok - Ban Chang
930
Day 730 100% Infrastructure
10Department of Rural Roads
Roadway Overpass the Highway No.7
(Km.107+200), Sriracha
810
Day 270 100% Infrastructure
11Department of Rural Roads
Railway Overpass the Train Route No.1012,
Nakhon Pathom
720
Day 170 100% Infrastructure
2,955 2,955
29,775 13,450
[Unit : Million Baht] [last update 31/03/2016]
Note
- Joint Venture [JV] Project are Presented Only NWR's Portion
- Total Value is Roundup
SUB TOTAL===>
GRAND TOTAL===>
18
Backlog Type & Expected Gross Margin
Future projects are to be focused on high-margin worksin which the company has competitive edge
Expected Gross Margin By Project Type Total Backlog Composition by Project Types
Higher Company's expertise &Core focus of '15 & '16
Marine
Tunnel
Industrial
Infrastructure
Building
Lower Earth Work
19
New Projects Awardedin 2016
Project Owner Contract Value Type
(THB mm)
1. Power Plant 2 * 110 MW Private 587 Industrial
2. Motor Way DOH 785 Infrastructure
3. Flood Protection DPT 280 Infrastructure
4. Highway DRR 299 Infrastructure
5. Power Plant EGAT 2,000 Industrial
6. Airport DOA 1,313 Infrastructure
TOTAL 5,264
22
New Business - Property Development
ISSI CondominiumThe Issara Ladprao
Based on its success from CIN, the Company will selectively invest in more property projects that provide both attractive margins and synergies with its current business
• Modern high end condominium on ladprao road
• JV with Charn Issara Development PCL (CI:NWR 60:40)
• Project revenue ~ THB 2,700 mm
• Total 561 units
• Modern condominium on Suksawat road
• JV with Charn Issara Development PCL (CI:NWR 60:40)
• Project revenue ~THB 1,900 mm
• Total 892 units
• Unit area: 21-55 m2
32
New Business - Property Development
Baranee ParkVilla Baranee
• The housing project on Rangsit Klong 3 Road
• 100% owned by NWR
• Expected project revenue ~ THB 630 mm
• Total 198 units
• Total land 35-3-1 rais
• The housing project on Romklao Road
• A subsidiary 99% owned by NWR (Mana
Patanakarn Company Limited)
• Expected project revenue ~ THB 900 mm
• Total 94 plots
• Total land 22 rais
33
New Business - Property Development
Aspen Condo Lasalle
• Low rise condominium on Lasalle road
• A subsidiary 99% owned by NWR (Mana
Patanakarn Company Limited)
• Expected project revenue ~ THB 780 mm
• Total 425 units
• Total land 3-3-78.1 rais
34