Activity ID Activity Name Start Finish OriginalDuration
Pump StatioPump Station Improvement Program 01/11/2012 A 09/29/2020 3522
New EPS-New EPS-1 08/01/2018 09/28/2020 790
100259 Pu100259 Pump Station 0010 Upgrade 08/01/2018 09/28/2020 790DesignDesign 08/01/2018 06/29/2019 333
B1000 Design Phase 08/01/2018 06/29/2019 333B1005 Prepare and Submit Design Package 08/01/2018 08/07/2018 7B1010 Engage Design Consultant 08/08/2018 09/04/2018 28B1012 TA Preparation 09/05/2018 09/18/2018 14B1014 TA Approval 09/19/2018 10/28/2018 40B1030 Issue Design NTP 10/29/2018 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/29/2018 06/01/2019 216
30% Des30% Design 10/29/2018 01/16/2019 80B1060 A/E Prepares 30% Construction Documents 10/29/2018 12/17/2018 50
B1100 30% CDs Submittal 12/17/2018 0B1120 30% Review (MDWASD/PSIP Team) 12/18/2018 01/16/2019 30
60% Des60% Design 12/18/2018 01/30/2019 44B1130 A/E Prepares 60% Construction Documents 12/18/2018 01/16/2019 30B1140 60% CDs Submittal 01/16/2019 0B1160 60% Review (MDWASD/PSIP Team) 01/17/2019 01/30/2019 14
90% Des90% Design 01/17/2019 06/01/2019 136B1170 A/E Prepares 90% Construction Documents 01/17/2019 02/25/2019 40B1180 90% CDs Submittal 02/25/2019 0B1190 90% Review (MDWASD/PSIP Team) 02/26/2019 03/27/2019 30B1200 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 03/28/2019 0B1210 90% RER(DERM)/FDEP Permit Review (Pump Station) 03/28/2019 05/11/2019 45B1220 90% RER (Building Dept Permit Submittal (Pump Station) 05/12/2019 0B1230 90% RER (Building Dept) Permit Review (Pump Station) 05/12/2019 06/01/2019 21B1240 90% PWWMD Permit Submittal (Pump Station) 05/12/2019 0B1250 90% PWWMD Permit Review (Pump Station) 05/12/2019 06/01/2019 21B1260 90% CD PM Comments Evaluation Completed 06/01/2019 0
100% De100% Design 06/02/2019 06/29/2019 28B1270 A/E Prepares 100% Construction Documents 06/02/2019 06/15/2019 14B1280 100% CDs Submittal 06/15/2019 0B1290 100% Review (MDWASD/PSIP Team) 06/16/2019 06/29/2019 14B1300 Design Completed 06/29/2019 0
MDWASDMDWASD Procurement 06/29/2019 10/11/2019 104B1305 Procurement Phase 06/29/2019 10/11/2019 104B1310 Submit CDs to MDWASD Procurement Division 06/29/2019 0B1312 Bid Notice Preparation Period 06/30/2019 08/01/2019 33B1314 Bid Notice 08/01/2019 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
06/29/2019, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA ApprovalIssue Design NTP
Final Engineering Report Review & Ap01/16/2019, 30% Design
A/E Prepares 30% Construction Documents
30% CDs Submittal30% Review (MDWASD/PSIP Team)01/30/2019, 60% Design
A/E Prepares 60% Construction Documents60% CDs Submittal60% Review (MDWASD/PSIP Team)
06/01/2019, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)/FDEP Permit Submittal (P
90% RER(DERM)/FDEP Permit Review 90% RER (Building Dept Permit Submit
90% RER (Building Dept) Permit Revie90% PWWMD Permit Submittal (Pump
90% PWWMD Permit Review (Pump 90% CD PM Comments Evaluation C
06/29/2019, 100% Design
A/E Prepares 100% Construction Do100% CDs Submittal100% Review (MDWASD/PSIP TeamDesign Completed
10/11/2019, MDWASD Pro
Procurement PhaseSubmit CDs to MDWASD Procurem
Bid Notice Preparation PeriodBid Notice
Miami Dade Water and Sewer DepartmentProgram and Construction Management Services for theImplementation of a Pump Station Improvement Program
ISD Project No. E13-WASD-02R
PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORTPrint Date: 08/15/2018Data Date: 08/01/2018
Disclaimer: Dates subject to change as program is further developed
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 1 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conferencce 08/02/2019 08/15/2019 14B1320 Pre-Bid Conference 08/16/2019 08/16/2019 1B1328 Bidders Prepare Bids for Submittal 08/17/2019 09/06/2019 21B1330 Bids Submittal 09/06/2019 0B1340 MDWASD/PSIP Team Bids Evaluation 09/07/2019 09/27/2019 21B1350 Recommendation for Award Letter 09/27/2019 0B1355 Contract Award (Purchase Order Approval) 09/28/2019 10/11/2019 14
ConstrucConstruction 08/16/2019 05/31/2020 290B1357 Construction Phase 08/16/2019 05/31/2020 290B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 09/28/2019 10/18/2019 21B1364 Pre-Construction Meeting 10/19/2019 10/19/2019 1B1366 WASD Issues NTP (Pre-Const to NTP) 10/20/2019 12/03/2019 45B1369 WASD Issues NTP (PO to NTP) 10/12/2019 12/03/2019 53B1370 Construction NTP 12/04/2019 0B1390 Construction Operations 12/04/2019 05/31/2020 180B1395 Substantial Completion 05/31/2020 0
DesignerDesigner Construction Support Services 08/16/2019 05/31/2020 290B1397 Designer Construction Support Services 08/16/2019 05/31/2020 290
Project CProject Closeout 05/31/2020 09/28/2020 120B1425 Closeout Phase 05/31/2020 09/28/2020 120B1430 Issue SAC Letter 05/31/2020 0B1450 Final Release of Retainage - Construction Contract 05/31/2020 0B1460 Administrative Closeout 06/01/2020 09/28/2020 120B1470 Project Closed 09/28/2020 0
Basin 0021Basin 0021 09/25/2014 A 10/31/2019 1857
100000 Ba100000 Basin 0021 Infiltration/Inflow Study and Repairs 09/25/2014 A 07/19/2016 A 632InfiltratioInfiltration/Inflow 09/25/2014 A 07/19/2016 A 624
B1000 Infiltration/Inflow Phase 09/25/2014 A 07/19/2016 A 624Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 10/23/2015 A 226
B1005 SSES Phase 09/25/2014 A 10/23/2015 A 226B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 03/04/2015 A 10/23/2015 A 30B1040 Video Review 04/24/2015 A 05/07/2015 A 30
CIPP RepCIPP Repairs 01/15/2016 A 05/06/2016 A 46B1065 CIPP Phase 01/15/2016 A 05/06/2016 A 46B1080 Issue NTP for CIPP Repairs 01/15/2016 A 0B1090 Conduct CIPP Repairs 03/21/2016 A 05/06/2016 A 20
ManholeManhole Repairs 01/15/2016 A 06/09/2016 A 20B1115 Manhole Phase 01/15/2016 A 06/09/2016 A 20B1132 Issue NTP for Manhole Repairs 01/15/2016 A 0B1140 Conduct Manhole Repairs 06/06/2016 A 06/09/2016 A 20
Dig & ReDig & Replace Repairs 11/20/2015 A 07/19/2016 A 45B1160 Dig & Replace Phase 11/20/2015 A 07/19/2016 A 45B1180 Issue NTP for Dig & Replace Repairs 11/20/2015 A 0B1190 Conduct Dig & Replace Repairs 07/13/2016 A 07/19/2016 A 45
Project CProject Closeout 06/10/2016 A 06/10/2016 A 0B1235 Closeout Phase 06/10/2016 A 06/10/2016 A 0B1260 Project Closed 06/10/2016 A 0
100001 Pu100001 Pump Station 0021 Upgrade 10/01/2014 A 03/17/2019 1629
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
MDWASD/PSIP Team Prepare Pre-Bid Conference
Bidders Prepare Bids for SubmBids Submittal
MDWASD/PSIP Team Bids ERecommendation for Award Contract Award (Purchase O
05/31/2
ConstruMDWASD/PSIP Team PrePre-Construction Meeting
WASD Issues NTP (PreWASD Issues NTP (POConstruction NTP
ConstruSubstan05/31/2
Designe
Issue SAFinal Re
10/31/2019, Basin 0021
07/19/2016 A, 100000 Basin 0021 Infiltration/Inflow Study and Repairs07/19/2016 A, Infiltration/Inflow
Infiltration/Inflow Phase10/23/2015 A, Sanitary Sewer Evaluation SurveySSES Phase
Issue NTP to SSES ContractorConduct SSES
Video Review05/06/2016 A, CIPP RepairsCIPP Phase
Issue NTP for CIPP RepairsConduct CIPP Repairs
06/09/2016 A, Manhole RepairsManhole Phase
Issue NTP for Manhole RepairsConduct Manhole Repairs
07/19/2016 A, Dig & Replace Repairs
Dig & Replace PhaseIssue NTP for Dig & Replace Repairs
Conduct Dig & Replace Repairs06/10/2016 A, Project CloseoutCloseout Phase
Project Closed03/17/2019, 100001 Pump Station 0021 U
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 2 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
DesignDesign 10/01/2014 A 10/02/2017 A 1127B1000 Design Phase 10/01/2014 A 10/02/2017 A 1127B1010 WASD Overhead During Planning and Design 10/01/2014 A 10/02/2017 A 1127B1020 Prepare and Submit Design Package 10/01/2014 A 10/02/2014 A 5B1030 Engage Design Consultant 10/03/2014 A 11/04/2014 A 20B1035 TA Preparation 11/05/2014 A 11/05/2014 A 1B1037 TA Approval Process 11/06/2014 A 01/12/2015 A 20B1040 Issue Design NTP 02/02/2015 A 0B1042 WASD/PSIP Prepare Design / Permitting Accelerated Plan 03/23/2016 A 03/29/2016 A 5B1044 TA Rev 1 Preparation 03/30/2016 A 04/21/2016 A 1B1046 TA Rev 1 Approval Process 04/22/2016 A 10/14/2016 A 20B1060 Final Engineering Report Review & Approval (MDWASD/PSIP Te 02/02/2015 A 12/14/2016 A 85
30% Des30% Design 02/03/2015 A 08/29/2016 A 490B1070 A/E Prepares 30% Construction Documents 02/03/2015 A 03/03/2015 A 30B1080 Geotechnical Engineering Services 02/19/2015 A 03/03/2015 A 26B1090 Surveying Services 02/19/2015 A 03/03/2015 A 15B1110 30% CDs Submittal 03/03/2015 A 0B1130 30% Review (MDWASD/PSIP Team) 03/04/2015 A 05/01/2015 A 10B1132 A/E Prepares 30% Construction Documents (Re-Design) 03/23/2016 A 06/22/2016 A 43B1134 30% Review (MDWASD/PSIP Team) (Re-Design) 06/23/2016 A 08/29/2016 A 10
90% Des90% Design 04/20/2015 A 09/29/2017 A 881B1180 A/E Prepares 90% Construction Documents 04/20/2015 A 05/20/2015 A 20B1190 90% CDs Submittal 05/20/2015 A 0B1200 90% Review (MDWASD/PSIP Team) 05/21/2015 A 03/23/2016 A 15B1204 A/E Prepares 90% Construction Documents (Re-Design) 08/30/2016 A 11/02/2016 A 22B1206 90% Review (MDWASD/PSIP Team) (Re-Design) 11/03/2016 A 12/14/2016 A 30B1210 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 02/20/2017 A 0B1220 90% RER(DERM)/FDEP Permit Review (Pump Station) 02/20/2017 A 04/18/2017 A 45B1230 90% Miami - BD Permit Submittal (Pump Station) 04/18/2017 A 0B1240 90% Miami - BD Permit Review (Pump Station) 04/18/2017 A 09/29/2017 A 21B1250 90% Miami - PWD Permit Submittal (Pump Station) 04/18/2017 A 0B1260 90% Miami - PWD Permit Review (Pump Station) 04/18/2017 A 09/29/2017 A 21B1270 90% CD PM Comments Evaluation Completed 09/29/2017 A 0B1272 MDWASD Union Concurrence Process 02/27/2017 A 04/07/2017 A 30
100% De100% Design 09/30/2017 A 10/02/2017 A 31B1280 A/E Prepares 100% Construction Documents 09/30/2017 A 10/02/2017 A 14B1290 100% CDs Submittal 10/02/2017 A 0B1300 100% Review (MDWASD/PSIP Team) 10/02/2017 A 10/02/2017 A 14B1310 Design Completed 10/02/2017 A 0
MDWASDMDWASD Procurement 10/03/2017 A 03/23/2018 A 143B1315 Procurement Phase 10/03/2017 A 03/23/2018 A 143B1320 Submit CDs to MDWASD Procurement Division 10/03/2017 A 0B1323 Bid Notice Preparation Period 10/04/2017 A 10/16/2017 A 33B1325 Bid Notice 10/16/2017 A 0B1327 MDWASD/PSIP Team Prepare for Pre-Bid Conferencce 10/17/2017 A 10/25/2017 A 14B1330 Pre-Bid Conference 10/26/2017 A 10/26/2017 A 1B1335 Bidders Prepare Bids for Submittal 10/27/2017 A 12/10/2017 A 21B1336 Addendum #3 Issued to Changed Sub Trade to Primary Trade 12/11/2017 A 12/13/2017 A 3B1337 2nd Pre-Bid Conference Due to Sub Trade Changed to Primary 12/14/2017 A 12/14/2017 A 1
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
10/02/2017 A, Design
Design PhaseWASD Overhead During Planning and Design
Prepare and Submit Design PackageEngage Design ConsultantTA Preparation
TA Approval ProcessIssue Design NTP
WASD/PSIP Prepare Design / Permitting Accelerated PlanTA Rev 1 Preparation
TA Rev 1 Approval ProcessFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
08/29/2016 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services
30% CDs Submittal30% Review (MDWASD/PSIP Team)
A/E Prepares 30% Construction Documents (Re-Design)30% Review (MDWASD/PSIP Team) (Re-Design)
09/29/2017 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)A/E Prepares 90% Construction Documents (Re-Design)
90% Review (MDWASD/PSIP Team) (Re-Design)90% RER(DERM)/FDEP Permit Submittal (Pump Station)
90% RER(DERM)/FDEP Permit Review (Pump Station)90% Miami - BD Permit Submittal (Pump Station)
90% Miami - BD Permit Review (Pump Station)90% Miami - PWD Permit Submittal (Pump Station)
90% Miami - PWD Permit Review (Pump Station)90% CD PM Comments Evaluation Completed
MDWASD Union Concurrence Process10/02/2017 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal
100% Review (MDWASD/PSIP Team)Design Completed
03/23/2018 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation Period
Bid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferenccePre-Bid Conference
Bidders Prepare Bids for SubmittalAddendum #3 Issued to Changed Sub Trade to Primary Trade2nd Pre-Bid Conference Due to Sub Trade Changed to Primary Trade
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 3 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1338 Bidders Prepare 2nd Bids for Submittal 12/15/2017 A 01/18/2018 A 35B1340 Bids Submittal 01/18/2018 A 0B1350 MDWASD/PSIP Team Bids Evaluation 01/19/2018 A 01/29/2018 A 21B1360 Recommendation for Award Letter 01/29/2018 A 0B1365 Contract Award (Purchase Order Approval) 01/30/2018 A 03/23/2018 A 14
ConstrucConstruction 10/26/2017 A 11/17/2018 419B1370 Construction Phase 10/26/2017 A 11/17/2018 419B1371 Construction Management - PSIP Team 10/26/2017 A 11/17/2018 419B1372 Construction Management - WASD 10/26/2017 A 11/17/2018 419B1373 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 01/30/2018 A 04/17/2018 A 21B1375 Pre-Construction Meeting 04/18/2018 A 04/18/2018 A 1B1376 WASD Issues NTP (Pre-Const to NTP) 04/19/2018 A 05/20/2018 A 45B1378 WASD Issues NTP (PO to NTP) 03/24/2018 A 05/20/2018 A 53B1380 Construction NTP 05/21/2018 A 0B1410 Construction Operations 05/21/2018 A 11/17/2018 179B1415 Substantial Completion 11/17/2018 0
DesignerDesigner Construction Support Services 10/26/2017 A 11/17/2018 388B1420 Designer Construction Support Services 10/26/2017 A 11/17/2018 388
Project CProject Closeout 11/17/2018 03/17/2019 120B1455 Closeout Phase 11/17/2018 03/17/2019 120B1460 Issue SAC Letter 11/17/2018 0B1480 Final Release of Retainage - Construction Contract 11/17/2018 0B1490 Administrative Closeout 11/18/2018 03/17/2019 120B1500 Project Closed 03/17/2019 0
100253 Pu100253 Pump Station 0021 Gravity Sewer 07/31/2017 A 10/31/2019 669DesignDesign 07/31/2017 A 04/17/2018 A 154
B1000 Design Phase 07/31/2017 A 04/17/2018 A 154B1010 WASD Overhead During Planning and Design 07/31/2017 A 04/17/2018 A 154
90% Des90% Design 07/31/2017 A 04/17/2018 A 154B1220 A/E Prepares Performance Specifications 07/31/2017 A 04/17/2018 A 154
MDWASDMDWASD Procurement 08/01/2018 11/12/2018 104B1305 Procurement Phase 08/01/2018 11/12/2018 104B1310 Submit CDs to MDWASD Procurement Division 08/01/2018 0B1312 Bid Notice Preparation Period 08/01/2018 09/02/2018 33B1314 Bid Notice 09/02/2018 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conferencce 09/03/2018 09/16/2018 14B1320 Pre-Bid Conference 09/17/2018 09/17/2018 1B1328 Bidders Prepare Bids for Submittal 09/18/2018 10/08/2018 21B1330 Bids Submittal 10/08/2018 0B1340 MDWASD/PSIP Team Bids Evaluation 10/09/2018 10/29/2018 21B1350 Recommendation for Award Letter 10/29/2018 0B1355 Contract Award (Purchase Order Approval) 10/30/2018 11/12/2018 14
ConstrucConstruction 09/17/2018 07/03/2019 290B1357 Construction Phase 09/17/2018 07/03/2019 290B1358 Construction Management - PSIP Team 09/17/2018 07/03/2019 290B1359 Construction Management - WASD 09/17/2018 07/03/2019 290B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 10/30/2018 11/19/2018 21B1364 Pre-Construction Meeting 11/20/2018 11/20/2018 1B1366 WASD Issues NTP (Pre-Const to NTP) 11/21/2018 01/04/2019 45
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Bidders Prepare 2nd Bids for Submittal
Bids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter
Contract Award (Purchase Order Approval)11/17/2018, Construction
Construction PhaseConstruction Management - PSIP TeamConstruction Management - WASD
MDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Construction NTPConstruction OperationsSubstantial Completion11/17/2018, Designer Construction Support Services
Designer Construction Support Services03/17/2019, Project Closeout
Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction Contract
Administrative CloseoutProject Closed
10/31/2019, 100253 Pum04/17/2018 A, DesignDesign PhaseWASD Overhead During Planning and Design04/17/2018 A, 90% DesignA/E Prepares Performance Specifications
11/12/2018, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferenccePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)
07/03/2019, Construction
Construction PhaseConstruction Management - PSIP TConstruction Management - WASD
MDWASD/PSIP Team Prepare for Pre-Construction MPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 4 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1369 WASD Issues NTP (PO to NTP) 11/13/2018 01/04/2019 53B1370 Construction NTP 01/05/2019 0B1390 Construction Operations 01/05/2019 07/03/2019 180B1395 Substantial Completion 07/03/2019 0
DesignerDesigner Construction Support Services 09/17/2018 07/03/2019 290B1397 Designer Construction Support Services 09/17/2018 07/03/2019 290
Project CProject Closeout 07/03/2019 10/31/2019 120B1425 Closeout Phase 07/03/2019 10/31/2019 120B1450 Final Release of Retainage - Construction Contract 07/03/2019 0B1460 Administrative Closeout 07/04/2019 10/31/2019 120B1470 Project Closed 10/31/2019 0
Basin 0026Basin 0026 02/13/2015 A 11/29/2018 1267
100002 Ba100002 Basin 0026 Infiltration/Inflow Study and Repairs 05/22/2015 A 06/16/2016 A 289InfiltratioInfiltration/Inflow 05/22/2015 A 06/15/2016 A 281
B1000 Infiltration/Inflow Phase 05/22/2015 A 06/15/2016 A 281CIPP RepCIPP Repairs 05/22/2015 A 03/07/2016 A 20
B1065 CIPP Phase 05/22/2015 A 03/07/2016 A 20B1080 Issue NTP for CIPP Repairs 05/22/2015 A 0B1090 Conduct CIPP Repairs 07/09/2015 A 03/07/2016 A 20
ManholeManhole Repairs 03/25/2016 A 06/15/2016 A 112B1115 Manhole Phase 03/25/2016 A 06/15/2016 A 112B1130 Issue NTP for Manhole Repairs 03/25/2016 A 0B1140 Conduct Manhole Repairs 04/11/2016 A 06/15/2016 A 20
Dig & ReDig & Replace Repairs 06/26/2015 A 07/29/2015 A 30B1165 Dig & Replace Phase 06/26/2015 A 07/29/2015 A 30B1180 Issue NTP for Dig & Replace Repairs 06/26/2015 A 0B1190 Conduct Dig & Replace Repairs 07/20/2015 A 07/29/2015 A 30
Project CProject Closeout 06/16/2016 A 06/16/2016 A 0B1235 Closeout Phase 06/16/2016 A 06/16/2016 A 0B1260 Project Closed 06/16/2016 A 0
100240 Pu100240 Pump Station 0026 Upgrade 02/13/2015 A 11/29/2018 1267DesignDesign 02/13/2015 A 05/31/2017 A 783
B1000 Design Phase 02/13/2015 A 05/31/2017 A 783B1005 Prepare and Submit Design Package 02/13/2015 A 06/05/2015 A 5B1010 Engage Design Consultant 02/13/2015 A 06/05/2015 A 20B1020 TA Approval Process 06/19/2015 A 06/30/2015 A 20B1022 TA Rev 1 Approval Process 11/06/2015 A 12/11/2015 A 20B1030 Issue Design NTP 07/02/2015 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 07/02/2015 A 06/09/2016 A 85
30% Des30% Design 07/03/2015 A 09/28/2015 A 91B1060 A/E Prepares 30% Construction Documents 07/03/2015 A 09/11/2015 A 30B1070 Geotechnical Engineering Services 07/03/2015 A 09/11/2015 A 20B1080 Surveying Services 07/03/2015 A 09/11/2015 A 15B1100 30% CDs Submittal 09/14/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 09/15/2015 A 09/28/2015 A 10
90% Des90% Design 09/15/2015 A 04/17/2017 A 645B1170 A/E Prepares 90% Construction Documents 09/15/2015 A 03/24/2016 A 20B1180 90% CDs Submittal 03/24/2016 A 0B1190 90% Review (MDWASD/PSIP Team) 03/25/2016 A 06/09/2016 A 15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
WASD Issues NTP (PO to NTP)
Construction NTPConstruction OperationsSubstantial Completion07/03/2019, Designer Construction
Designer Construction Support Ser10/31/2019, Project Close
Closeout PhaseFinal Release of Retainage - Const
Administrative CloseoutProject Closed
11/29/2018, Basin 0026
06/16/2016 A, 100002 Basin 0026 Infiltration/Inflow Study and Repairs06/15/2016 A, Infiltration/Inflow
Infiltration/Inflow Phase03/07/2016 A, CIPP RepairsCIPP Phase
Issue NTP for CIPP RepairsConduct CIPP Repairs
06/15/2016 A, Manhole RepairsManhole Phase
Issue NTP for Manhole RepairsConduct Manhole Repairs
07/29/2015 A, Dig & Replace RepairsDig & Replace Phase
Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs
06/16/2016 A, Project CloseoutCloseout Phase
Project Closed11/29/2018, 100240 Pump Station 0026 Upgrade
05/31/2017 A, Design
Design PhasePrepare and Submit Design PackageEngage Design Consultant
TA Approval ProcessTA Rev 1 Approval Process
Issue Design NTPFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
09/28/2015 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services
30% CDs Submittal30% Review (MDWASD/PSIP Team)
04/17/2017 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 5 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1192 TA Rev 2 Approval Process 11/10/2016 A 12/21/2016 A 40B1194 A/E Prepares 90% Design for Flow Metter & Specialty Odor Con 11/10/2016 A 01/30/2017 A 40B1200 90% RER (DERM) FDEP Permit Submittal (Pump Station) 06/10/2016 A 0B1210 90% RER (DERM) FDEP Permit Review (Pump Station) 06/10/2016 A 02/24/2017 A 155B1220 90% RER (Building Department) Permit Submittal (Pump Statio 03/09/2017 A 0B1230 90% RER (Building Department) Permit Review (Pump Station) 03/09/2017 A 04/17/2017 A 21B1240 90% PWWMD Permit Submittal (Pump Station) 06/10/2016 A 0B1250 90% PWWMD Permit Review (Pump Station) 06/10/2016 A 02/24/2017 A 15B1260 90% CD PM Comments Evaluation Completed 04/17/2017 A 0B1262 MDWASD Union Concurrence Process 01/27/2017 A 03/07/2017 A 30
100% De100% Design 05/17/2017 A 05/31/2017 A 14B1270 A/E Prepares 100% Construction Documents 05/17/2017 A 05/30/2017 A 10B1280 100% CDs Submittal 05/30/2017 A 0B1290 100% Review (MDWASD/PSIP Team) 05/31/2017 A 05/31/2017 A 10B1300 Design Completed 05/31/2017 A 0
MDWASDMDWASD Procurement 06/01/2017 A 10/19/2017 A 101B1305 Procurement Phase 06/01/2017 A 10/19/2017 A 101B1310 Submit CDs to MDWASD Procurement Division 06/01/2017 A 0B1312 Bid Notice Preparation Period 06/02/2017 A 06/07/2017 A 23B1314 Bid Notice 06/07/2017 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 06/08/2017 A 06/20/2017 A 10B1320 Pre-Bid Conference 06/21/2017 A 06/21/2017 A 1B1328 Bidders Prepare Bids for Submittal 06/22/2017 A 07/24/2017 A 15B1330 Bids Submittal 07/24/2017 A 0B1340 Bids Evaluation (MDWASD/PSIP Team) 07/25/2017 A 08/31/2017 A 15B1350 Recommendation for Award Letter 08/31/2017 A 0B1352 Contract Award (Purchase Order Approval) 09/01/2017 A 10/19/2017 A 10
ConstrucConstruction 06/21/2017 A 08/01/2018 489B1355 Construction Phase 06/21/2017 A 08/01/2018 489B1357 MDAD/PSIP Team Prepare for Pre-Construction Meeting 09/01/2017 A 10/16/2017 A 21B1358 Pre-Construction Meeting 10/17/2017 A 10/17/2017 A 1B1359 WASD Issues NTP (Pre-Const to NTP) 10/18/2017 A 01/28/2018 A 45B1360 Construction NTP 01/29/2018 A 0B1361 WASD Issues NTP (PO to NTP) 10/20/2017 A 01/28/2018 A 53B1390 Construction Operations 01/29/2018 A 08/01/2018 149B1392 Substantial Completion 08/01/2018 0
DesignerDesigner Construction Support Services 06/21/2017 A 04/01/2018 A 274B1480 Designer Construction Support Services 06/21/2017 A 04/01/2018 A 820
Project CProject Closeout 10/31/2017 A 11/29/2018 394B1425 Closeout Phase 10/31/2017 A 11/29/2018 394B1430 Issue SAC Letter 10/31/2017 A 0B1450 Final Release of Retainage - Construction Contract 08/01/2018 0B1460 Administrative Closeout 08/02/2018 11/29/2018 120B1470 Project Closed 11/29/2018 0
Basin 0046Basin 0046 09/25/2014 A 09/28/2020 2031
100003 Ba100003 Basin 0046 Infiltration/Inflow Study and Repairs 09/25/2014 A 08/31/2016 A 723InfiltratioInfiltration/Inflow 09/25/2014 A 08/31/2016 A 723
B1000 Infiltration/Inflow Phase 09/25/2014 A 08/31/2016 A 723Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 06/18/2015 A 136
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
TA Rev 2 Approval ProcessA/E Prepares 90% Design for Flow Metter & Specialty Odor Control
90% RER (DERM) FDEP Permit Submittal (Pump Station)90% RER (DERM) FDEP Permit Review (Pump Station)90% RER (Building Department) Permit Submittal (Pump Station)
90% RER (Building Department) Permit Review (Pump Station)90% PWWMD Permit Submittal (Pump Station)
90% PWWMD Permit Review (Pump Station)90% CD PM Comments Evaluation Completed
MDWASD Union Concurrence Process05/31/2017 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal
100% Review (MDWASD/PSIP Team)Design Completed
10/19/2017 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid Notice
MDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
Bids Evaluation (MDWASD/PSIP Team)Recommendation for Award Letter
Contract Award (Purchase Order Approval)08/01/2018, Construction
Construction PhaseMDAD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)
Construction NTPWASD Issues NTP (PO to NTP)
Construction OperationsSubstantial Completion
04/01/2018 A, Designer Construction Support Services
Designer Construction Support Services11/29/2018, Project Closeout
Closeout PhaseIssue SAC Letter
Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed
08/31/2016 A, 100003 Basin 0046 Infiltration/Inflow Study and Repairs08/31/2016 A, Infiltration/Inflow
Infiltration/Inflow Phase06/18/2015 A, Sanitary Sewer Evaluation Survey
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 6 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1005 SSES Phase 09/25/2014 A 06/18/2015 A 136B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 06/02/2015 A 06/11/2015 A 30B1040 Video Review 06/12/2015 A 06/18/2015 A 30
CIPP RepCIPP Repairs 01/15/2016 A 05/13/2016 A 28B1070 CIPP Phase 01/15/2016 A 05/13/2016 A 28B1090 Issue NTP for CIPP Repairs 01/15/2016 A 0B1100 Conduct CIPP Repairs 05/13/2016 A 05/13/2016 A 28
ManholeManhole Repairs 10/30/2015 A 02/11/2016 A 20B1115 Manhole Phase 10/30/2015 A 02/11/2016 A 20B1130 Issue NTP for Manhole Repairs 10/30/2015 A 0B1140 Conduct Manhole Repairs 01/06/2016 A 02/11/2016 A 20
Dig & ReDig & Replace Repairs 11/20/2015 A 08/31/2016 A 120B1165 Dig & Replace Phase 11/20/2015 A 08/31/2016 A 120B1180 Issue NTP for Dig & Replace Repairs 11/20/2015 A 0B1190 Conduct Dig & Replace Repairs 06/23/2016 A 08/31/2016 A 30
Project CProject Closeout 08/31/2016 A 08/31/2016 A 0B1235 Closeout Phase 08/31/2016 A 08/31/2016 A 0B1260 Project Closed 08/31/2016 A 0
100004 Pu100004 Pump Station 0046(AM) Upgrade 11/03/2015 A 07/26/2020 1700DesignDesign 11/03/2015 A 04/26/2019 1243
B1000 Design Phase 11/03/2015 A 04/26/2019 1243B1010 Prepare and Submit Design Package 11/03/2015 A 11/03/2015 A 5B1020 Engage Design Consultant 11/03/2015 A 11/11/2015 A 20B1021 SOW Received - I/I Repairs Pending To Resume Negotiations 11/12/2015 A 08/01/2018 20B1022 TA Preparation 08/02/2018 08/15/2018 14B1024 TA Approval Process 08/16/2018 09/24/2018 40B1030 Issue Design NTP 09/25/2018 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 09/25/2018 03/29/2019 186
30% Des30% Design 09/25/2018 12/13/2018 80B1060 A/E Prepares 30% Construction Documents 09/25/2018 11/13/2018 50B1100 30% CDs Submittal 11/13/2018 0B1120 30% Review (MDWASD/PSIP Team) 11/14/2018 12/13/2018 30
90% Des90% Design 11/14/2018 03/29/2019 136B1170 A/E Prepares 90% Construction Documents 11/14/2018 12/23/2018 40B1180 90% CDs Submittal 12/23/2018 0B1190 90% Review (MDWASD/PSIP Team) 12/24/2018 01/22/2019 30B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 01/23/2019 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 01/23/2019 03/08/2019 45B1220 90% Miami - BD Permit Submittal 03/09/2019 0B1230 90% Miami - BD Permit Review 03/09/2019 03/29/2019 21B1240 90% Miami - PWD Permit Submittal 03/09/2019 0B1250 90% Miami - PWD Permit Review 03/09/2019 03/29/2019 21B1260 90% CD PM Comments Evaluation Completed 03/29/2019 0
100% De100% Design 03/30/2019 04/26/2019 28B1270 A/E Prepares 100% Construction Documents 03/30/2019 04/12/2019 14B1280 100% CDs Submittal 04/12/2019 0B1290 100% Review (MDWASD/PSIP Team) 04/13/2019 04/26/2019 14B1300 Design Completed 04/26/2019 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
SSES Phase
Issue NTP to SSES ContractorConduct SSESVideo Review
05/13/2016 A, CIPP Repairs
CIPP PhaseIssue NTP for CIPP Repairs
Conduct CIPP Repairs02/11/2016 A, Manhole RepairsManhole Phase
Issue NTP for Manhole RepairsConduct Manhole Repairs
08/31/2016 A, Dig & Replace RepairsDig & Replace Phase
Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs08/31/2016 A, Project CloseoutCloseout Phase
Project Closed07/
04/26/2019, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantSOW Received - I/I Repairs Pending To Resume NegotiationsTA Preparation
TA Approval Process
Issue Design NTPFinal Engineering Report Review & Approva
12/13/2018, 30% Design
A/E Prepares 30% Construction Documents30% CDs Submittal
30% Review (MDWASD/PSIP Team)03/29/2019, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump
90% RER(DERM)FDEP Permit Review (Pum90% Miami - BD Permit Submittal
90% Miami - BD Permit Review90% Miami - PWD Permit Submittal
90% Miami - PWD Permit Review90% CD PM Comments Evaluation Comple
04/26/2019, 100% Design
A/E Prepares 100% Construction Docume100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 7 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
MDWASDMDWASD Procurement 04/26/2019 08/08/2019 104B1305 Procurement Phase 04/26/2019 08/08/2019 104B1310 Submit CDs to MDWASD Procurement Division 04/26/2019 0B1312 Bid Notice Preparation Period 04/27/2019 05/29/2019 33B1314 Bid Notice 05/29/2019 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 05/30/2019 06/12/2019 14B1320 Pre-Bid Conference 06/13/2019 06/13/2019 1B1328 Bidders Prepare Bids for Submittal 06/14/2019 07/04/2019 21B1330 Bids Submittal 07/04/2019 0B1340 MDWASD/PSIP Team Bids Evaluation 07/05/2019 07/25/2019 21B1350 Recommendation for Award Letter 07/25/2019 0B1355 Contract Award (Purchase Order Approval) 07/26/2019 08/08/2019 14
ConstrucConstruction 06/13/2019 03/28/2020 290B1360 Construction Phase 06/13/2019 03/28/2020 290B1364 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 07/26/2019 08/15/2019 21B1366 Pre-Construction Meeting 08/16/2019 08/16/2019 1B1368 WASD Issues NTP (Pre-Const to NTP) 08/17/2019 09/30/2019 45B1370 Construction NTP 10/01/2019 0B1400 Construction Operations 10/01/2019 03/28/2020 180B1402 Substantial Completion 03/28/2020 0
DesignerDesigner Construction Support Services 06/13/2019 03/28/2020 290B1410 Designer Construction Support Services 06/13/2019 03/28/2020 290
Project CProject Closeout 03/28/2020 07/26/2020 120B1445 Closeout Phase 03/28/2020 07/26/2020 120B1450 Issue SAC Letter 03/28/2020 0B1470 Final Release of Retainage - Construction Contract 03/28/2020 0B1480 Administrative Closeout 03/29/2020 07/26/2020 120B1490 Project Closed 07/26/2020 0
100232 FM100232 FM for Pump Station 0046 08/01/2018 09/28/2020 790DesignDesign 08/01/2018 06/29/2019 333
B1000 Design Phase 08/01/2018 06/29/2019 333B1010 Prepare and Submit Design Package 08/01/2018 08/07/2018 7B1020 Engage Design Consultant 08/08/2018 09/04/2018 28B1022 TA Preparation 09/05/2018 09/18/2018 14B1024 TA Approval Process 09/19/2018 10/28/2018 40B1030 Issue Design NTP 10/29/2018 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/29/2018 06/01/2019 216
30% Des30% Design 10/29/2018 01/16/2019 80B1060 A/E Prepares 30% Construction Documents 10/29/2018 12/17/2018 50B1100 30% CDs Submittal 12/17/2018 0B1120 30% Review (MDWASD/PSIP Team) 12/18/2018 01/16/2019 30
60% Des60% Design 12/18/2018 01/30/2019 44B1140 A/E Prepares 60% Construction Documents 12/18/2018 01/16/2019 30B1150 60% CDs Submittal 01/16/2019 0B1170 60% Review (MDWASD/PSIP Team) 01/17/2019 01/30/2019 14
90% Des90% Design 01/17/2019 06/01/2019 136B1180 A/E Prepares 90% Construction Documents 01/17/2019 02/25/2019 40B1190 90% CDs Submittal 02/25/2019 0B1200 90% Review (MDWASD/PSIP Team) 02/26/2019 03/27/2019 30
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
08/08/2019, MDWASD ProcuremProcurement Phase
Submit CDs to MDWASD Procurement DBid Notice Preparation Period
Bid NoticeMDWASD/PSIP Team Prepare for Pr
Pre-Bid ConferenceBidders Prepare Bids for Submittal
Bids SubmittalMDWASD/PSIP Team Bids EvaluRecommendation for Award LetteContract Award (Purchase Order
03/28/2020,
Construction MDWASD/PSIP Team Prepare Pre-Construction Meeting
WASD Issues NTP (Pre-Con
Construction NTPConstruction Substantial C03/28/2020,
Designer Con07/Clo
Issue SAC LeFinal Release
AdmPro
06/29/2019, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval Process
Issue Design NTPFinal Engineering Report Review & Ap
01/16/2019, 30% Design
A/E Prepares 30% Construction Documents30% CDs Submittal
30% Review (MDWASD/PSIP Team)01/30/2019, 60% Design
A/E Prepares 60% Construction Documents60% CDs Submittal60% Review (MDWASD/PSIP Team)
06/01/2019, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 8 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1210 90% PWWMD Permit Submittal (Force Main) 03/28/2019 0B1220 90% PWWMD Permit Review (Force Main) 03/28/2019 04/17/2019 21B1230 90% RER(DERM)FDEP Permit Submittal (Force Main) 03/28/2019 0B1240 90% RER(DERM)FDEP Permit Review (Force Main) 03/28/2019 05/11/2019 45B1250 90% Municipality Permit Submittal (Force Main) 05/12/2019 0B1260 90% Municipality Permit Review (Force Main) 05/12/2019 06/01/2019 21B1270 90% FDOT Permit Submittal (Force Main) 05/12/2019 0B1280 90% FDOT Permit Review (Force Main) 05/12/2019 06/01/2019 21B1290 90% CD PM Comments Evaluation Completed 06/01/2019 0
100% De100% Design 06/02/2019 06/29/2019 28B1300 A/E Prepares 100% Construction Documents 06/02/2019 06/15/2019 14B1310 100% CDs Submittal 06/15/2019 0B1320 100% Review (MDWASD/PSIP Team) 06/16/2019 06/29/2019 14B1330 Design Completed 06/29/2019 0
MDWASDMDWASD Procurement 06/29/2019 10/11/2019 104B1335 Procurement Phase 06/29/2019 10/11/2019 104B1340 Submit CDs to MDWASD Procurement Division 06/29/2019 0B1342 Bid Notice Preparation Period 06/30/2019 08/01/2019 33B1344 Bid Notice 08/01/2019 0B1346 MDWASD/PSIP Team Prepare for Pre-Bid Conference 08/02/2019 08/15/2019 14B1350 Pre-Bid Conference 08/16/2019 08/16/2019 1B1358 Bidders Prepare Bids for Submittal 08/17/2019 09/06/2019 21B1360 Bids Submittal 09/06/2019 0B1370 MDWASD/PSIP Bids Evaluation 09/07/2019 09/27/2019 21B1380 Recommendation for Award letter 09/27/2019 0B1385 Contract Award (Purchase Order Approval) 09/28/2019 10/11/2019 14
ConstrucConstruction 08/16/2019 06/01/2020 290B1390 Construction Phase 08/16/2019 06/01/2020 290B1394 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 09/28/2019 10/18/2019 21B1396 Pre-construction Meeting 10/19/2019 10/19/2019 1B1398 WASD Issues NTP (Pre-Const to NTP) 10/20/2019 12/03/2019 45B1400 Construction NTP 12/04/2019 0B1430 Construction Operations 12/04/2019 05/31/2020 180B1432 Substantial Completion 05/31/2020 0
DesignerDesigner Construction Support Services 08/16/2019 05/31/2020 290B1440 Designer Construction Support Services 08/16/2019 05/31/2020 290
Project CProject Closeout 05/31/2020 09/28/2020 120B1475 Closeout Phase 05/31/2020 09/28/2020 120B1500 Final Release of Retainage - Construction Contract 05/31/2020 0B1510 Administrative Closeout 06/01/2020 09/28/2020 120B1520 Project Closed 09/28/2020 0
Basin 0052Basin 0052 06/24/2016 A 08/05/2016 A 43
100254 Pu100254 Pump Station 0052 Upgrade 06/24/2016 A 08/05/2016 A 43Project CProject Closeout 06/24/2016 A 08/05/2016 A 43
B1425 Closeout Phase 06/24/2016 A 08/05/2016 A 43B1430 Issue SAC Letter 08/05/2016 A 0B1460 Administrative Closeout 06/24/2016 A 08/05/2016 A 31B1470 Project Closed 08/05/2016 A 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
90% PWWMD Permit Submittal (Force Mai90% PWWMD Permit Review (Force Main
90% RER(DERM)FDEP Permit Submittal (F90% RER(DERM)FDEP Permit Review (90% Municipality Permit Submittal (Forc
90% Municipality Permit Review (Forc90% FDOT Permit Submittal (Force Ma
90% FDOT Permit Review (Force Main90% CD PM Comments Evaluation C
06/29/2019, 100% Design
A/E Prepares 100% Construction Do100% CDs Submittal100% Review (MDWASD/PSIP TeamDesign Completed
10/11/2019, MDWASD ProProcurement Phase
Submit CDs to MDWASD ProcuremBid Notice Preparation Period
Bid NoticeMDWASD/PSIP Team Prepare
Pre-Bid ConferenceBidders Prepare Bids for Subm
Bids SubmittalMDWASD/PSIP Bids EvaluaRecommendation for Award Contract Award (Purchase O
06/01/2
ConstruMDWASD/PSIP Team PrePre-construction Meeting
WASD Issues NTP (Pre
Construction NTPConstruSubstan05/31/2
Designe
Final Re
08/05/2016 A, Basin 0052
08/05/2016 A, 100254 Pump Station 0052 Upgrade08/05/2016 A, Project Closeout
Closeout PhaseIssue SAC LetterAdministrative CloseoutProject Closed
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 9 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
Basin 0057Basin 0057 06/13/2012 A 03/01/2020 1762
100005 Ba100005 Basin 0057 Infiltration/Inflow Study and Repairs 05/22/2015 A 10/07/2015 A 254InfiltratioInfiltration/Inflow 05/22/2015 A 10/06/2015 A 20
B1000 Infiltration/Inflow Phase 05/22/2015 A 10/06/2015 A 20CIPP RepCIPP Repairs 05/22/2015 A 10/06/2015 A 20
B1005 CIPP Phase 05/22/2015 A 10/06/2015 A 20B1020 Issue NTP for CIPP Repairs 05/22/2015 A 0B1030 Conduct CIPP Repairs 09/23/2015 A 10/06/2015 A 20
Project CProject Closeout 10/07/2015 A 10/07/2015 A 0B1175 Closeout Phase 10/07/2015 A 10/07/2015 A 0B1200 Project Closed 10/07/2015 A 0
100255 FM100255 FM for Pump Station 0057 08/01/2018 03/01/2020 579DesignDesign 08/01/2018 05/15/2019 288
A1170 Design Phase 08/01/2018 05/15/2019 288A1180 Prepare and Submit Design Package 08/01/2018 08/07/2018 7A1190 Engage Design Consultant 08/08/2018 09/04/2018 28A1193 TA Preparation 09/05/2018 09/18/2018 14A1195 TA Approval Process 09/19/2018 10/28/2018 40A1200 Issue Design NTP 10/29/2018 0A1220 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/29/2018 04/17/2019 171
30% Des30% Design 10/29/2018 01/16/2019 80A1230 A/E Prepares 30% Construction Documents 10/29/2018 12/17/2018 50A1240 30% CDs Submittal 12/17/2018 0A1260 30% Review (MDWASD/PSIP Team) 12/18/2018 01/16/2019 30
60% Des60% Design 12/18/2018 01/30/2019 44A1280 A/E Prepares 60% Construction Documents 12/18/2018 01/16/2019 30A1290 60% CDs Submittal 01/16/2019 0A1300 60% Review (MDWASD/PSIP Team) 01/17/2019 01/30/2019 14
90% Des90% Design 01/17/2019 04/17/2019 91A1310 A/E Prepares 90% Construction Documents 01/17/2019 02/25/2019 40A1320 90% CDs Submittal 02/25/2019 0A1330 90% Review (MDWASD/PSIP Team) 02/26/2019 03/27/2019 30A1345 90% RER (DERM) Permit Submittal (Force Main) 03/27/2019 0A1346 90% RER (DERM) Permit Review (Force Main) 03/28/2019 04/17/2019 21A1350 90% Other/Additional Permit Submittal (Force Main) 03/27/2019 0A1351 90% Other/Additional Permit Review (Force Main) 03/28/2019 04/17/2019 21A1385 90% CD PM Comments Evaluation Completed 04/17/2019 0
100% De100% Design 04/18/2019 05/15/2019 28A1390 A/E Prepares 100% Construction Documents 04/18/2019 05/01/2019 14A1400 100% CDs Submittal 05/01/2019 0A1410 100% Review (MDWASD/PSIP Team) 05/02/2019 05/15/2019 14A1420 Design Completed 05/15/2019 0
MDWASDMDWASD Procurement 05/15/2019 08/27/2019 104A1425 Procurement Phase 05/15/2019 08/27/2019 104A1430 Submit CDs to MDWASD Procurement Division 05/15/2019 0A1434 Bid Notice Preparation Period 05/16/2019 06/17/2019 33A1436 Bid Notice 06/17/2019 0A1438 MDWASD/PSIP Team Prepare for Pre-Bid Conference 06/18/2019 07/01/2019 14A1440 Pre-Bid Conference 07/02/2019 07/02/2019 1
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
03/01/2020, Ba
10/07/2015 A, 100005 Basin 0057 Infiltration/Inflow Study and Repairs10/06/2015 A, Infiltration/Inflow
Infiltration/Inflow Phase10/06/2015 A, CIPP RepairsCIPP Phase
Issue NTP for CIPP RepairsConduct CIPP Repairs10/07/2015 A, Project CloseoutCloseout Phase
Project Closed03/01/2020, 10
05/15/2019, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval ProcessIssue Design NTP
Final Engineering Report Review & Appro01/16/2019, 30% Design
A/E Prepares 30% Construction Documents30% CDs Submittal
30% Review (MDWASD/PSIP Team)01/30/2019, 60% Design
A/E Prepares 60% Construction Documents60% CDs Submittal60% Review (MDWASD/PSIP Team)
04/17/2019, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER (DERM) Permit Submittal (Force
90% RER (DERM) Permit Review (Force M90% Other/Additional Permit Submittal (For
90% Other/Additional Permit Review (Forc90% CD PM Comments Evaluation Comp
05/15/2019, 100% Design
A/E Prepares 100% Construction Docum100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed
08/27/2019, MDWASD Procure
Procurement PhaseSubmit CDs to MDWASD Procurement
Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for PPre-Bid Conference
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 10 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
A1448 Bidders Prepare Bids for Submittal 07/03/2019 07/23/2019 21A1450 Bids Submittal 07/23/2019 0A1455 Bids Evaluation (MDWASD/PSIP Team) 07/24/2019 08/13/2019 21A1460 Recommendation for Award Letter 08/13/2019 0A1465 Contract Award (Purchase Order Approval) 08/14/2019 08/27/2019 14
ConstrucConstruction 07/02/2019 11/03/2019 124A1467 Construction Phase 07/02/2019 11/03/2019 124A1474 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 08/28/2019 09/17/2019 21A1476 Pre-Construction Meeting 09/18/2019 09/18/2019 1A1478 WASD Issues NTP (Pre-Const to NTP) 09/19/2019 11/02/2019 45A1479 WASD Issues NTP (PO to NTP) 08/28/2019 11/02/2019 67A1480 Construction NTP 11/03/2019 0A1500 Construction Operations 11/03/2019 11/03/2019 0A1502 Substantial Completion 11/03/2019 0
DesignerDesigner Construction Support Services 07/02/2019 11/02/2019 124A1508 Designer Construction Support Services 07/02/2019 11/02/2019 124
Project CProject Closeout 11/03/2019 03/01/2020 120A1535 Closeout Phase 11/03/2019 03/01/2020 120A1540 Issue SAC Letter 11/03/2019 0A1547 Final Release of Retainage - Construction Contract 11/03/2019 0A1548 Administrative Closeout 11/03/2019 03/01/2020 120A1550 Project Closed 03/01/2020 0
100256 Pu100256 Pump Station 0057 Upgrade * 06/13/2012 A 10/25/2018 790DesignDesign 06/13/2012 A 06/27/2018 A 7
B1000 Design Phase 06/13/2012 A 06/27/2018 A 7B1002 Remedial Action Plan to SAC Letter Issuance 06/13/2012 A 06/27/2018 A 7
Project CProject Closeout 06/27/2018 A 10/25/2018 673B1425 Closeout Phase 06/27/2018 A 10/25/2018 673B1430 Issue SAC Letter 06/27/2018 A 0B1460 Administrative Closeout 06/28/2018 A 10/25/2018 120B1470 Project Closed 10/25/2018 0
Basin 0065Basin 0065 06/30/2014 A 08/01/2018 1633
100007 Pu100007 Pump Station 0065 Upgrade 06/30/2014 A 08/01/2018 1054Pump StPump Station 0065 Upgrade 08/01/2018 08/01/2018 0
B1380 New Activity 08/01/2018 08/01/2018 0DesignDesign 06/30/2014 A 02/05/2015 A 236
B1495 Design Phase 06/30/2014 A 02/05/2015 A 236B1500 Prepare and Submit Design Package 06/30/2014 A 07/14/2014 A 5B1510 Engage Design Consultant 07/15/2014 A 09/22/2014 A 20B1520 Prepare and Issue TA 08/26/2014 A 09/22/2014 A 10B1530 Issue Design NTP 09/25/2014 A 0B1535 MDWASD MH-to-MH Calculation 10/20/2014 A 12/12/2014 A 10B1540 A/E Develops and Submits Final Engineering Report 09/25/2014 A 01/08/2015 A 41B1550 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/08/2014 A 01/15/2015 A 10
30% Des30% Design 09/26/2014 A 10/13/2014 A 26B1560 A/E Prepares 30% Construction Documents 09/26/2014 A 10/08/2014 A 10B1570 Geotechnical Engineering Services 09/26/2014 A 10/08/2014 A 20B1580 Surveying Services 09/26/2014 A 10/08/2014 A 15B1600 30% CDs Submittal 10/08/2014 A 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Bidders Prepare Bids for SubmittaBids Submittal
Bids Evaluation (MDWASD/PSIPRecommendation for Award LetContract Award (Purchase Orde
11/03/2019, Construction
Construction PhaseMDWASD/PSIP Team PrepaPre-Construction Meeting
WASD Issues NTP (Pre-CWASD Issues NTP (PO to
Construction NTPConstruction OperationsSubstantial Completion11/02/2019, Designer Co
Designer Construction Su03/01/2020, Pro
Closeout PhaseIssue SAC LetterFinal Release of Retainag
Administrative CProject Closed
10/25/2018, 100256 Pump Station 0057 Upgrade *06/27/2018 A, Design
Design PhaseRemedial Action Plan to SAC Letter Issuance
10/25/2018, Project Closeout
Closeout PhaseIssue SAC
Administrative CloseoutProject Closed
08/01/2018, Basin 0065
08/01/2018, 100007 Pump Station 0065 Upgrade08/01/2018, Pump Station 0065 UpgradeNew Activity
02/05/2015 A, DesignDesign Phase
Prepare and Submit Design PackageEngage Design ConsultantPrepare and Issue TA
Issue Design NTPMDWASD MH-to-MH Calculation
A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
10/13/2014 A, 30% DesignA/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services
30% CDs Submittal
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 11 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1620 30% Review (MDWASD/PSIP Team) 10/09/2014 A 10/13/2014 A 1060% Des60% Design 10/09/2014 A 10/31/2014 A 54
B1630 A/E Prepares 60% Construction Documents 10/09/2014 A 10/23/2014 A 30B1640 60% CDs Submittal 10/23/2014 A 0B1660 60% Review (MDWASD/PSIP Team) 10/23/2014 A 10/31/2014 A 10
90% Des90% Design 10/24/2014 A 02/02/2015 A 106B1670 A/E Prepares 90% Construction Documents 10/24/2014 A 11/20/2014 A 20B1680 90% CDs Submittal 11/20/2014 A 0B1690 90% Review (MDWASD/PSIP Team) 11/21/2014 A 12/05/2014 A 15B1710 90% RER(DERM)FDEP Permit Submittal 01/16/2015 A 0B1720 90% RER(DERM)FDEP Permit Review 01/16/2015 A 01/22/2015 A 15B1750 90% Miami - BD Permit Submittal 01/26/2015 A 0B1760 90% Miami - BD Permit Review 01/26/2015 A 02/02/2015 A 15B1765 90% Miami - PWD Permit Submittal 01/26/2015 A 0B1766 90% Miami - PWD Permit Review 01/26/2015 A 02/02/2015 A 15B1770 90% CD PM Comments Evaluation Completed 02/02/2015 A 0
100% De100% Design 02/03/2015 A 02/05/2015 A 12B1780 A/E Prepares 100% Construction Documents 02/03/2015 A 02/04/2015 A 10B1790 100% CDs Submittal 02/04/2015 A 0B1800 100% Review (MDWASD/PSIP Team) 02/05/2015 A 02/05/2015 A 10B1810 Design Completed 02/05/2015 A 0
MDWASDMDWASD Procurement 02/20/2015 A 04/20/2015 A 105B1305 Procurement Phase 02/20/2015 A 04/20/2015 A 105B1310 Submit CDs to MDWASD Procurement Division 02/20/2015 A 0B1312 Bid Notice Preparation Period 02/20/2015 A 02/20/2015 A 33B1314 Bid Notice 02/20/2015 A 0B1316 MDWASD/PSIP Team Prepared for Pre-Bid Conference 02/21/2015 A 03/02/2015 A 14B1320 Pre-Bid Conference 03/03/2015 A 03/03/2015 A 1B1328 Bidders Prepare Bids for Submittal 03/04/2015 A 04/01/2015 A 21B1330 Bids Submittal 04/01/2015 A 0B1340 MDWASD/PSIP Team Bids Evaluation 04/02/2015 A 04/03/2015 A 21B1350 Recommendation for Award Letter 04/02/2015 A 0B1355 Contract Award (Purchase Order Approval) 04/06/2015 A 04/20/2015 A 14
ConstrucConstruction 03/03/2015 A 12/22/2015 A 1172B1360 Construction Phase 03/03/2015 A 12/22/2015 A 1172B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 04/03/2015 A 04/26/2015 A 33B1365 Preconstruction Meeting 04/27/2015 A 04/27/2015 A 1B1367 WASD Issues NTP (Pre-Const to NTP) 04/28/2015 A 05/31/2015 A 45B1368 WASD Issues NTP (PO to NTP) 04/20/2015 A 05/31/2015 A 45B1370 Construction NTP 06/01/2015 A 0B1400 Construction Operations 06/01/2015 A 12/16/2015 A 150B1400 Original Construction Duration 06/01/2015 A 10/29/2015 A 150B1400 Change Order #1 - Inspections 10/30/2015 A 11/20/2015 A 150B1400 Change Order #2 - FPL 11/21/2015 A 12/22/2015 A 150B1402 Substantial Completion 12/16/2015 A 0
DesignerDesigner Construction Support Services 03/03/2015 A 12/16/2015 A 37B1410 Designer Construction Support Services 03/03/2015 A 12/16/2015 A 109
Project CProject Closeout 12/17/2015 A 08/01/2018 944B1445 Closeout Phase 12/17/2015 A 08/01/2018 944
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
30% Review (MDWASD/PSIP Team)10/31/2014 A, 60% DesignA/E Prepares 60% Construction Documents
60% CDs Submittal60% Review (MDWASD/PSIP Team)
02/02/2015 A, 90% DesignA/E Prepares 90% Construction Documents
90% CDs Submittal90% Review (MDWASD/PSIP Team)
90% RER(DERM)FDEP Permit Submittal90% RER(DERM)FDEP Permit Review
90% Miami - BD Permit Submittal90% Miami - BD Permit Review
90% Miami - PWD Permit Submittal90% Miami - PWD Permit Review
90% CD PM Comments Evaluation Completed02/05/2015 A, 100% DesignA/E Prepares 100% Construction Documents
100% CDs Submittal100% Review (MDWASD/PSIP Team)
Design Completed04/20/2015 A, MDWASD ProcurementProcurement Phase
Submit CDs to MDWASD Procurement DivisionBid Notice Preparation Period
Bid NoticeMDWASD/PSIP Team Prepared for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for Submittal
Bids SubmittalMDWASD/PSIP Team Bids Evaluation
Recommendation for Award LetterContract Award (Purchase Order Approval)
12/22/2015 A, ConstructionConstruction Phase
MDWASD/PSIP Team Prepare for Pre-Construction MeetingPreconstruction Meeting
WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Construction NTPConstruction Operations
Original Construction DurationChange Order #1 - Inspections
Change Order #2 - FPL
Substantial Completion12/16/2015 A, Designer Construction Support ServicesDesigner Construction Support Services
08/01/2018, Project CloseoutCloseout Phase
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 12 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1450 Issue SAC Letter 02/04/2016 A 0B1470 Final Release of Retainage - Construction Contract 04/12/2017 A 0B1480 Administrative Closeout 12/17/2015 A 08/01/2018 120B1490 Project Closed 08/01/2018 0
100006 Ba100006 Basin 0065 Infiltration/Inflow Study and Repairs 04/17/2015 A 06/16/2016 A 373InfiltratioInfiltration/Inflow 04/17/2015 A 06/15/2016 A 197
B1000 Infiltration/Inflow Phase 04/17/2015 A 06/15/2016 A 197CIPP RepCIPP Repairs 04/17/2015 A 06/11/2015 A 40
B1065 CIPP Phase 04/17/2015 A 06/11/2015 A 40B1080 Issue NTP for CIPP Repairs 04/17/2015 A 0B1090 Conduct CIPP Repairs 06/10/2015 A 06/11/2015 A 20
ManholeManhole Repairs 10/02/2015 A 06/15/2016 A 20B1115 Manhole Phase 10/02/2015 A 06/15/2016 A 20B1130 Issue NTP for Manhole Repairs 10/02/2015 A 0B1140 Conduct Manhole Repairs 10/13/2015 A 06/15/2016 A 20
Dig & ReDig & Replace Repairs 05/18/2015 A 10/02/2015 A 30B1165 Dig & Replace Phase 05/18/2015 A 10/02/2015 A 30B1180 Issue NTP for Dig & Replace Repairs 05/18/2015 A 0B1190 Conduct Dig & Replace Repairs 09/28/2015 A 10/02/2015 A 30
Project CProject Closeout 06/16/2016 A 06/16/2016 A 0B1235 Closeout Phase 06/16/2016 A 06/16/2016 A 0B1260 Project Closed 06/16/2016 A 0
100231 FM100231 FM for Pump Station 0065 Phase 1 07/14/2014 A 08/01/2018 1619DesignDesign 07/14/2014 A 02/12/2015 A 232
A1565 Design Phase 07/14/2014 A 02/12/2015 A 232A1570 Prepare and Submit Design Package 07/14/2014 A 07/18/2014 A 5A1580 Engage Design Consultant 07/21/2014 A 09/19/2014 A 20A1590 Prepare and Issue TA 09/11/2014 A 10/29/2014 A 20B1600 Issue Design NTP 10/30/2014 A 0B1610 A/E Develops and Submits Final Engineering Report 10/30/2014 A 02/12/2015 A 120B1620 Final Engineering Report Review & Approval (MDWASD/PSIP Te 01/21/2015 A 01/28/2015 A 0
30% Des30% Design 10/30/2014 A 11/10/2014 A 47B1630 A/E Prepares 30% Construction Documents 10/30/2014 A 11/05/2014 A 30B1640 Geotechnical Engineering Services 10/30/2014 A 11/05/2014 A 20B1650 Surveying Services 10/30/2014 A 11/05/2014 A 15B1670 30% CDs Submittal 11/05/2014 A 0B1690 30% Review (MDWASD/PSIP Team) 11/06/2014 A 11/10/2014 A 10
60% Des60% Design 11/07/2014 A 12/11/2014 A 42B1700 A/E Prepares 60% Construction Documents 11/07/2014 A 11/21/2014 A 30B1710 60% CDs Submittal 11/21/2014 A 0B1720 60% Legal Review (MDWASD) 11/24/2014 A 11/24/2014 A 15B1730 60% Review (MDWASD/PSIP Team) 11/24/2014 A 12/11/2014 A 10
90% Des90% Design 11/21/2014 A 02/12/2015 A 82B1740 A/E Prepares 90% Construction Documents 11/24/2014 A 12/22/2014 A 20B1750 90% CDs Submittal 12/22/2014 A 0B1760 90% Review (MDWASD/PSIP Team) 12/23/2014 A 01/02/2015 A 15B1770 90% Legal Review (MDWASD) 12/23/2014 A 12/23/2014 A 15B1780 90% RER(DERM)FDEP Permit Submittal (FM) 01/28/2015 A 0B1790 90% RER(DERM)FDEP Permit Review (FM) 01/28/2015 A 02/12/2015 A 1
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Issue SAC LetterFinal Release of Retainage - Construction Contract
Administrative Closeout
Project Closed06/16/2016 A, 100006 Basin 0065 Infiltration/Inflow Study and Repairs06/15/2016 A, Infiltration/Inflow
Infiltration/Inflow Phase06/11/2015 A, CIPP Repairs
CIPP PhaseIssue NTP for CIPP Repairs
Conduct CIPP Repairs06/15/2016 A, Manhole Repairs
Manhole PhaseIssue NTP for Manhole Repairs
Conduct Manhole Repairs10/02/2015 A, Dig & Replace Repairs
Dig & Replace PhaseIssue NTP for Dig & Replace Repairs
Conduct Dig & Replace Repairs06/16/2016 A, Project Closeout
Closeout PhaseProject Closed
08/01/2018, 100231 FM for Pump Station 0065 Phase 102/12/2015 A, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantPrepare and Issue TAIssue Design NTP
A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
11/10/2014 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services
30% CDs Submittal30% Review (MDWASD/PSIP Team)
12/11/2014 A, 60% Design
A/E Prepares 60% Construction Documents60% CDs Submittal60% Legal Review (MDWASD)60% Review (MDWASD/PSIP Team)
02/12/2015 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% Legal Review (MDWASD)90% RER(DERM)FDEP Permit Submittal (FM)90% RER(DERM)FDEP Permit Review (FM)
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 13 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1820 90% Miami - PWD Permit Submittal (Force Main) 11/21/2014 A 0B1830 90% Miami - PWD Permit Review (Force Main) 11/21/2014 A 11/28/2014 A 5B1840 90% CD PM Comments Evaluation Completed 02/12/2015 A 0
100% De100% Design 02/12/2015 A 02/12/2015 A 0B1880 Design Completed 02/12/2015 A 0
MDWASDMDWASD Procurement 03/18/2015 A 06/01/2015 A 114B1425 Procurement Phase 03/18/2015 A 06/01/2015 A 114B1430 Submit CDs to MDWASD Procurement Division 03/18/2015 A 0B1440 Pre-Bid Conference 04/03/2015 A 0B1450 Bids Submittal 05/04/2015 A 0B1455 MDWASD/PSIP Team Bids Evaluation 05/05/2015 A 05/06/2015 A 20B1460 Contractor Selected 05/06/2015 A 0B1462 Contract Award (Purchase Order Approval) 05/07/2015 A 06/01/2015 A 10
ConstrucConstruction 05/15/2015 A 11/10/2015 A 1295B1465 Construction Phase 05/15/2015 A 11/10/2015 A 1295B1466 Pre Construction Meeting 06/04/2015 A 0B1468 MDWASD/PSIP prepare Notice to Proceed 06/05/2015 A 07/17/2015 A 10B1469 WASD Issues NTP (PO to NTP) 06/02/2015 A 07/19/2015 A 53B1470 Construction NTP 07/20/2015 A 0B1480 Mobilization 05/15/2015 A 07/20/2015 A 10B1490 Permit Approvals 05/15/2015 A 07/20/2015 A 20B1500 Construction Operations 07/20/2015 A 10/21/2015 A 86B1502 Substantial Completion 10/21/2015 A 0
DesignerDesigner Construction Support Services 07/20/2015 A 10/30/2015 A 96B1560 Designer Construction Support Services 07/20/2015 A 10/30/2015 A 96
ConstrucConstruction Close Out 10/22/2015 A 11/10/2015 A 31B1510 Commissioning 10/22/2015 A 11/10/2015 A 15B1520 Punch List 10/22/2015 A 11/10/2015 A 10
Project CProject Closeout 10/22/2015 A 08/01/2018 1004B1535 Closeout Phase 10/22/2015 A 08/01/2018 1004B1540 Issue SAC Letter 02/04/2016 A 0B1547 Final Release of Retainage - Construction Contract 08/04/2017 A 0B1548 Administrative Closeout 10/22/2015 A 08/01/2018 120B1550 Project Closed 08/01/2018 0
100237 FM100237 FM for Pump Station 0065 Phase 2 07/14/2014 A 08/01/2018 1619DesignDesign 07/14/2014 A 09/20/2016 A 817
B1485 Design Phase 07/14/2014 A 09/20/2016 A 817B1490 Prepare and Submit Design Package 07/14/2014 A 07/25/2014 A 5B1500 Engage Design Consultant 07/26/2014 A 04/03/2015 A 20B1510 Prepare and Issue TA 04/04/2015 A 05/01/2015 A 20B1520 Issue Design NTP 05/07/2015 A 0B1530 A/E Develops and Submits Final Engineering Report 05/07/2015 A 08/17/2016 A 160B1540 Final Engineering Report Review & Approval (MDWASD/PSIP Te 05/07/2015 A 06/08/2016 A 85
30% Des30% Design 05/08/2015 A 10/27/2015 A 134B1550 A/E Prepares 30% Construction Documents 05/08/2015 A 06/12/2015 A 60B1560 Geotechnical Engineering Services (Includes GPR) 05/08/2015 A 06/12/2015 A 30B1570 Surveying Services 05/08/2015 A 06/12/2015 A 30B1590 30% CDs Submittal 06/12/2015 A 0B1610 30% Review (MDWASD/PSIP Team) 06/15/2015 A 06/26/2015 A 10
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
90% Miami - PWD Permit Submittal (Force Main)90% Miami - PWD Permit Review (Force Main)90% CD PM Comments Evaluation Completed02/12/2015 A, 100% Design
Design Completed06/01/2015 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement DivisionPre-Bid Conference
Bids SubmittalMDWASD/PSIP Team Bids Evaluation
Contractor SelectedContract Award (Purchase Order Approval)
11/10/2015 A, Construction
Construction PhasePre Construction MeetingMDWASD/PSIP prepare Notice to ProceedWASD Issues NTP (PO to NTP)
Construction NTPMobilizationPermit Approvals
Construction OperationsSubstantial Completion
10/30/2015 A, Designer Construction Support Services
Designer Construction Support Services11/10/2015 A, Construction Close Out
CommissioningPunch List
08/01/2018, Project Closeout
Closeout PhaseIssue SAC Letter
Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed08/01/2018, 100237 FM for Pump Station 0065 Phase 2
09/20/2016 A, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantPrepare and Issue TAIssue Design NTP
A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
10/27/2015 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering Services (Includes GPR)Surveying Services
30% CDs Submittal30% Review (MDWASD/PSIP Team)
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 14 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1612 TA Rev 1 Preparation (Deleted 60% Design) 06/29/2015 A 09/18/2015 A 40B1614 TA Rev 1 Approval Process (Deleted 60% Design) 09/21/2015 A 10/27/2015 A 40
90% Des90% Design 10/28/2015 A 08/17/2016 A 64B1660 A/E Prepares 90% Construction Documents 10/28/2015 A 05/27/2016 A 20B1670 90% CDs Submittal 05/27/2016 A 0
B1680 90% Review (MDWASD/PSIP Team) 05/30/2016 A 06/08/2016 A 15B1700 90% RER(DERM)FDEP Permit Submittal 06/09/2016 A 0B1710 90% RER(DERM)FDEP Permit Review 06/09/2016 A 06/17/2016 A 15B1720 90% FDOT Permit Submittal 06/10/2016 A 0B1730 90% FDOT Permit Review 06/10/2016 A 08/17/2016 A 15B1740 90% Miami - PWD Permit Submittal 06/01/2016 A 0B1750 90% Miami - PWD Permit Review 06/01/2016 A 06/06/2016 A 15B1752 90% Miami - MDT Permit Submittal 07/11/2016 A 0B1754 90% Miami - MDT Permit Review 07/11/2016 A 07/27/2016 A 15B1760 90% CD PM Comments Evaluation Completed 08/17/2016 A 0
100% De100% Design 08/18/2016 A 09/20/2016 A 67B1770 A/E Prepares 100% Construction Documents 08/18/2016 A 09/19/2016 A 10B1780 100% CDs Submittal 09/19/2016 A 0B1790 100% Review (MDWASD/PSIP Team) 09/20/2016 A 09/20/2016 A 5B1800 Design Completed 09/20/2016 A 0
MDWASDMDWASD Procurement 09/21/2016 A 03/15/2017 A 132B1305 Procurement Phase 09/21/2016 A 03/15/2017 A 132B1310 Submit CDs to MDWASD Procurement Division 09/21/2016 A 0B1311 Bid Notice Preparation Period 09/22/2016 A 10/20/2016 A 33B1312 Bid Notice 10/20/2016 A 0B1318 Preparation for Bid Conference 10/21/2016 A 11/09/2016 A 14B1320 Pre-Bid Conference 11/10/2016 A 11/10/2016 A 1B1328 Bidders Prepare Bids for Submittal 11/11/2016 A 12/14/2016 A 21B1330 Bids Submittal 12/14/2016 A 0B1340 MDWASD/PSIP Team Bids Evaluation 12/15/2016 A 01/24/2017 A 21B1350 Recommendation for Award Letter 01/24/2017 A 0B1352 Contract Award (Purchase Order Approval) 01/24/2017 A 03/15/2017 A 14
ConstrucConstruction 11/10/2016 A 02/15/2018 A 769B1355 Construction Phase 11/10/2016 A 01/25/2018 A 769B1356 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 01/25/2017 A 04/05/2017 A 21B1357 Pre-Construction Meeting 04/06/2017 A 04/06/2017 A 1B1359 WASD Issues NTP (Pre-Const to NTP) 04/07/2017 A 07/16/2017 A 45
B1360 Construction NTP 07/17/2017 A 0B1369 WASD Issues NTP (PO to NTP) 03/16/2017 A 07/16/2017 A 53B1390 Construction Operations 07/17/2017 A 01/25/2018 A 149B1390 Original Construction Duration 07/17/2017 A 12/14/2017 A 149B1390 Change Order #1 - Hurricane Irma Delay 12/15/2017 A 01/04/2018 A 149B1390 Change Order #2 - City of Miami Permit Delay 01/05/2018 A 02/15/2018 A 149B1392 Substantial Completion 01/25/2018 A 0
DesignerDesigner Construction Support Services 11/10/2016 A 01/25/2018 A 288B1480 Designer Construction Support Services 11/10/2016 A 01/25/2018 A 288
Project CProject Closeout 01/26/2018 A 08/01/2018 153B1425 Closeout Phase 01/26/2018 A 08/01/2018 153
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
TA Rev 1 Preparation (Deleted 60% Design)TA Rev 1 Approval Process (Deleted 60% Design)
08/17/2016 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal90% RER(DERM)FDEP Permit Review
90% FDOT Permit Submittal90% FDOT Permit Review
90% Miami - PWD Permit Submittal90% Miami - PWD Permit Review
90% Miami - MDT Permit Submittal90% Miami - MDT Permit Review
90% CD PM Comments Evaluation Completed09/20/2016 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal
100% Review (MDWASD/PSIP Team)Design Completed
03/15/2017 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid NoticePreparation for Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter
Contract Award (Purchase Order Approval)02/15/2018 A, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)
Construction NTPWASD Issues NTP (PO to NTP)
Construction OperationsOriginal Construction Duration
Change Order #1 - Hurricane Irma DelayChange Order #2 - City of Miami Permit Delay
Substantial Completion01/25/2018 A, Designer Construction Support Services
Designer Construction Support Services08/01/2018, Project Closeout
Closeout Phase
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 15 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1450 Final Release of Retainage - Construction Contract 08/01/2018 0B1460 Administrative Closeout 01/26/2018 A 08/01/2018 120B1470 Project Closed 08/01/2018 0
Basin 0067Basin 0067 09/25/2014 A 08/01/2018 1535
100009 Pu100009 Pump Station 0067 Upgrade 12/15/2014 A 08/01/2018 1388DesignDesign 12/15/2014 A 09/30/2015 A 276
B1000 Design Phase 12/15/2014 A 09/30/2015 A 276B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 12/15/2014 A 12/17/2014 A 5B1020 Engage Design Consultant 12/18/2014 A 04/10/2015 A 20B1030 Issue Design NTP 04/13/2015 A 0B1040 A/E Develops and Submits Final Engineering Report 04/13/2015 A 09/11/2015 A 90B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 04/13/2015 A 08/20/2015 A 100
30% Des30% Design 04/13/2015 A 06/26/2015 A 46B1060 A/E Prepares 30% Construction Documents 04/13/2015 A 06/05/2015 A 30B1070 Geotechnical Engineering Services 04/15/2015 A 06/05/2015 A 20
B1080 Surveying Services 04/15/2015 A 06/05/2015 A 15B1100 30% CDs Submittal 06/05/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 06/09/2015 A 06/26/2015 A 10
90% Des90% Design 06/08/2015 A 09/11/2015 A 154B1130 A/E Prepares 90% Construction Documents 06/08/2015 A 07/23/2015 A 35B1140 90% CDs Submittal 07/23/2015 A 0B1150 90% Review (MDWASD/PSIP Team) 07/24/2015 A 08/20/2015 A 15B1160 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 08/21/2015 A 0B1170 90% RER(DERM)/FDEP Permit Review (Pump Station) 08/24/2015 A 08/28/2015 A 15B1180 90% Miami - BD Permit Submittal (Pump Station) 08/31/2015 A 0B1190 90% Miami - BD Permit Review (Pump Station) 08/31/2015 A 09/11/2015 A 15B1200 90% Miami - PWD Permit Submittal (Pump Station) 08/31/2015 A 0B1210 90% Miami - PWD Permit Review (Pump Station) 08/31/2015 A 09/11/2015 A 15B1220 90% CD PM Comments Evaluation Completed 09/11/2015 A 0
100% De100% Design 09/14/2015 A 09/30/2015 A 63B1230 A/E Prepares 100% Construction Documents 09/14/2015 A 09/21/2015 A 10B1240 100% CDs Submittal 09/22/2015 A 0B1250 100% Review (MDWASD/PSIP Team) 09/23/2015 A 09/30/2015 A 10B1260 Design Completed 09/30/2015 A 0
MDWASDMDWASD Procurement 10/02/2015 A 04/12/2016 A 72B1265 Procurement Phase 10/02/2015 A 04/12/2016 A 72B1270 Submit CDs to MDWASD Procurement Division 10/02/2015 A 0B1272 Bid Notice Preparation Period 10/05/2015 A 11/02/2015 A 23B1274 Bid Notice 11/03/2015 A 0B1276 MDWASD/PSIP Team Prepare for Pre-Bid Conference 11/04/2015 A 11/16/2015 A 10
B1280 Pre-Bid Conference 11/17/2015 A 11/17/2015 A 1B1288 Bidders Prepare Bids for Submittal 11/18/2015 A 12/16/2015 A 15B1290 Bids Submittal 12/17/2015 A 0B1300 MDWASD/PSIP Team Bids Evaluation 12/18/2015 A 01/05/2016 A 15B1310 Recommendation for Award Letter 01/05/2016 A 0B1315 Contract Award (Purchase Order Approval) 01/06/2016 A 04/12/2016 A 10
ConstrucConstruction 11/17/2015 A 07/18/2017 A 1128B1320 Construction Phase 11/17/2015 A 07/18/2017 A 1128
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed08/01/2018, Basin 0067
08/01/2018, 100009 Pump Station 0067 Upgrade09/30/2015 A, Design
Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book
Engage Design ConsultantIssue Design NTP
A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
06/26/2015 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering Services
Surveying Services30% CDs Submittal30% Review (MDWASD/PSIP Team)
09/11/2015 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)/FDEP Permit Submittal (Pump Station)90% RER(DERM)/FDEP Permit Review (Pump Station)
90% Miami - BD Permit Submittal (Pump Station)90% Miami - BD Permit Review (Pump Station)
90% Miami - PWD Permit Submittal (Pump Station)90% Miami - PWD Permit Review (Pump Station)
90% CD PM Comments Evaluation Completed09/30/2015 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal
100% Review (MDWASD/PSIP Team)Design Completed
04/12/2016 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid Conference
Pre-Bid ConferenceBidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter
Contract Award (Purchase Order Approval)07/18/2017 A, Construction
Construction Phase
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 16 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1324 MDWASD/PSIP Team prepare for Pre-Construction Meeting 01/06/2016 A 01/13/2016 A 15B1325 Pre-Construction Meeting 01/14/2016 A 01/14/2016 A 1B1326 WASD Issues NTP (PO to NTP) 04/13/2016 A 01/02/2017 A 53
B1330 Construction NTP 01/03/2017 A 0B1360 Construction Operations 01/03/2017 A 07/10/2017 A 150B1360 Original Construction Duration 01/03/2017 A 06/02/2017 A 150B1360 Change Order #1 - FPL 06/03/2017 A 06/20/2017 A 150B1360 Change Order #2 - Wet Well Leak 06/21/2017 A 07/18/2017 A 150B1362 Substantial Completion 07/10/2017 A 0
DesignerDesigner Construction Support Services 11/17/2015 A 07/10/2017 A 270B1370 Designer Construction Support Services 11/17/2015 A 07/10/2017 A 270
Project CProject Closeout 07/11/2017 A 08/01/2018 365B1405 Closeout Phase 07/11/2017 A 08/01/2018 365
B1410 Issue SAC Letter 08/01/2018 0B1430 Final Release of Retainage - Construction Contract 08/01/2018 0B1440 Administrative Closeout 07/11/2017 A 08/01/2018 120B1450 Project Closed 08/01/2018 0
100008 Ba100008 Basin 0067 Infiltration/Inflow Study and Repairs 09/25/2014 A 07/30/2015 A 604InfiltratioInfiltration/Inflow 09/25/2014 A 07/29/2015 A 298
B1000 Infiltration/inflow Phase 09/25/2014 A 07/29/2015 A 298Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 07/29/2015 A 298
B1005 SSES Phase 09/25/2014 A 07/29/2015 A 298B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 07/10/2015 A 07/29/2015 A 30
Project CProject Closeout 07/30/2015 A 07/30/2015 A 0B1235 Closeout Phase 07/30/2015 A 07/30/2015 A 0B1260 Project Closed 07/30/2015 A 0
100210 FM100210 FM for Pump Station 0067 11/14/2014 A 08/01/2018 1469DesignDesign 11/14/2014 A 08/18/2015 A 329
B1000 Design Phase 11/14/2014 A 08/18/2015 A 329B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 11/14/2014 A 12/10/2014 A 5B1020 Engage Design Consultant 12/11/2014 A 03/12/2015 A 20B1030 Issue Design NTP 03/12/2015 A 0B1040 A/E Develops and Submits Final Engineering Report 03/12/2015 A 07/29/2015 A 98B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 03/12/2015 A 06/11/2015 A 65
30% Des30% Design 03/13/2015 A 04/22/2015 A 45B1060 A/E Prepares 30% Construction Documents 03/13/2015 A 04/13/2015 A 30B1070 Geotechnical Engineering Services 03/13/2015 A 04/13/2015 A 19B1080 Surveying Services 03/13/2015 A 04/14/2015 A 19B1100 30% CDs Submittal 04/13/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 04/14/2015 A 04/22/2015 A 0
60% Des60% Design 04/14/2015 A 05/19/2015 A 26B1140 A/E Prepares 60% Construction Documents 04/14/2015 A 05/13/2015 A 20B1150 60% CDs Submittal 05/12/2015 A 0
B1170 60% Review (MDWASD/PSIP Team) 05/13/2015 A 05/19/2015 A 790% Des90% Design 04/28/2015 A 07/29/2015 A 106
B1176 90% Miami - PWD Permit Submittal (Force Main) 04/28/2015 A 0B1178 90% Miami - PWD Permit Review (Force Main) 04/28/2015 A 04/28/2015 A 10B1180 A/E Prepares 90% Construction Documents 05/13/2015 A 06/05/2015 A 15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
MDWASD/PSIP Team prepare for Pre-Construction MeetingPre-Construction Meeting
WASD Issues NTP (PO to NTP)
Construction NTPConstruction Operations
Original Construction DurationChange Order #1 - FPL
Change Order #2 - Wet Well Leak
Substantial Completion07/10/2017 A, Designer Construction Support Services
Designer Construction Support Services08/01/2018, Project Closeout
Closeout Phase
Issue SAC LetterFinal Release of Retainage - Construction ContractAdministrative CloseoutProject Closed
07/30/2015 A, 100008 Basin 0067 Infiltration/Inflow Study and Repairs07/29/2015 A, Infiltration/Inflow
Infiltration/inflow Phase07/29/2015 A, Sanitary Sewer Evaluation SurveySSES Phase
Issue NTP to SSES ContractorConduct SSES07/30/2015 A, Project CloseoutCloseout Phase
Project Closed08/01/2018, 100210 FM for Pump Station 0067
08/18/2015 A, Design
Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book
Engage Design ConsultantIssue Design NTP
A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
04/22/2015 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal
30% Review (MDWASD/PSIP Team)05/19/2015 A, 60% Design
A/E Prepares 60% Construction Documents60% CDs Submittal
60% Review (MDWASD/PSIP Team)07/29/2015 A, 90% Design
90% Miami - PWD Permit Submittal (Force Main)90% Miami - PWD Permit Review (Force Main)
A/E Prepares 90% Construction Documents
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 17 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1190 90% CDs Submittal 06/05/2015 A 0B1200 90% Review (MDWASD/PSIP Team) 06/08/2015 A 07/15/2015 A 10B1230 90% RER(DERM)FDEP Permit Submittal (Force Main) 07/16/2015 A 0B1240 90% RER(DERM)FDEP Permit Review (Force Main) 07/16/2015 A 07/29/2015 A 15B1290 90% CD PM Comments Evaluation Completed 07/29/2015 A 0
100% De100% Design 07/30/2015 A 08/18/2015 A 15B1300 A/E Prepares 100% Construction Documents 07/30/2015 A 08/11/2015 A 5B1310 100% CDs Submittal 08/11/2015 A 0B1320 100% Review (MDWASD/PSIP Team) 08/12/2015 A 08/18/2015 A 5B1330 Design Completed 08/18/2015 A 0
MDWASDMDWASD Procurement 08/18/2015 A 01/29/2016 A 120B1335 Procurement Phase 08/18/2015 A 01/29/2016 A 120B1340 Submit CDs to MDWASD Procurement Division 08/18/2015 A 0B1342 Bid Notice Preparation Period 08/19/2015 A 09/24/2015 A 23B1344 Bid Notice 09/25/2015 A 0B1346 MDWASD/PSIP Team Prepare for Pre-Bid Conference 09/28/2015 A 10/06/2015 A 10B1350 Pre-Bid Conference 10/07/2015 A 10/07/2015 A 1B1352 Bidders Prepare Bids for Submittal 10/08/2015 A 11/05/2015 A 15B1360 Bids Submittal 11/06/2015 A 0B1370 MDWASD/PSIP Team Bids Evaluation 11/09/2015 A 12/16/2015 A 15B1380 Recommendation for Award Letter 12/17/2015 A 0B1385 Contract Award (Purchase Order Approval) 12/18/2015 A 01/29/2016 A 10
ConstrucConstruction 10/07/2015 A 09/30/2016 A 1169B1390 Construction Phase 10/07/2015 A 09/30/2016 A 1169B1394 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 12/18/2015 A 01/06/2016 A 15B1396 Pre- Construction Meeting 01/07/2016 A 01/07/2016 A 1B1398 WASD Issues NTP (PO to NTP) 01/30/2016 A 03/01/2016 A 53B1400 Construction NTP 03/02/2016 A 0B1430 Construction Operations 03/02/2016 A 05/20/2016 A 149B1432 Substantial Completion 05/20/2016 A 0
DesignerDesigner Construction Support Services 10/07/2015 A 09/30/2016 A 290B1440 Designer Construction Support Services 10/07/2015 A 09/30/2016 A 290
ConstrucConstruction Close Out 05/23/2016 A 09/30/2016 A 15B1450 Commissioning 05/23/2016 A 09/30/2016 A 15B1460 Punch List 05/23/2016 A 09/30/2016 A 10
Project CProject Closeout 05/23/2016 A 08/01/2018 731B1475 Closeout Phase 05/23/2016 A 08/01/2018 731B1500 Final Release of Retainage - Construction Contract 08/01/2018 0B1510 Administrative Closeout 05/23/2016 A 08/01/2018 120B1520 Project Closed 08/01/2018 0
Basin 0069Basin 0069 09/25/2014 A 12/18/2019 1861
100010 Pu100010 Pump Station 0069 Upgrade 11/14/2014 A 12/18/2019 1861DesignDesign 11/14/2014 A 09/18/2018 1405
B1000 Design Phase 11/14/2014 A 09/18/2018 1405B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 11/14/2014 A 12/19/2014 A 0B1020 Engage Design Consultant 12/22/2014 A 03/24/2015 A 20B1030 Issue Design NTP 03/24/2015 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 03/24/2015 A 08/21/2018 217
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
90% CDs Submittal90% Review (MDWASD/PSIP Team)
90% RER(DERM)FDEP Permit Submittal (Force Main)90% RER(DERM)FDEP Permit Review (Force Main)
90% CD PM Comments Evaluation Completed08/18/2015 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed
01/29/2016 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid Notice
MDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids SubmittalMDWASD/PSIP Team Bids Evaluation
Recommendation for Award LetterContract Award (Purchase Order Approval)
09/30/2016 A, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre- Construction Meeting
WASD Issues NTP (PO to NTP)Construction NTP
Construction OperationsSubstantial Completion
09/30/2016 A, Designer Construction Support Services
Designer Construction Support Services09/30/2016 A, Construction Close Out
CommissioningPunch List
08/01/2018, Project Closeout
Closeout PhaseFinal Release of Retainage - Construction ContractAdministrative CloseoutProject Closed
12/18/2019, Basin 00
12/18/2019, 100010 09/18/2018, Design
Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book
Engage Design ConsultantIssue Design NTP
Final Engineering Report Review & Approval (MDWASD/PSIP
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 18 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
30% Des30% Design 03/25/2015 A 01/18/2018 A 1043B1060 A/E Prepares 30% Construction Documents (Suspended) 03/25/2015 A 06/16/2015 A 30B1070 Geotechnical Engineering Services 03/25/2016 A 06/16/2016 A 20B1080 Surveying Services 03/25/2015 A 05/11/2015 A 15B1082 MDWASD/PSIP Request Feasibility Study 06/17/2015 A 07/17/2015 A 30B1084 DC Prepare Feasibility Study, SOW & Fees for TA 007 Rev 1 07/20/2015 A 08/14/2015 A 30B1086 TA 007 Rev 1 Approval Process 08/14/2015 A 08/25/2015 A 30B1088 DC Prepares Feasibility Study 09/15/2015 A 03/30/2016 A 30B1089 Prepared and Submit Design Package for TA 019 Rev 0 04/01/2016 A 07/22/2016 A 5B1089 Engage Design Consultant for TA 019 Rev 0 07/25/2016 A 10/28/2016 A 20
B1089 TA 019 Rev 0 Preparation 10/31/2016 A 11/17/2016 A 1B1089 TA 019 Rev 0 Approval Process 11/18/2016 A 01/24/2017 A 40B1089 TA 007 Rev 2 Approval Process (Credit TA) 11/18/2016 A 01/24/2017 A 40
B1089 Issue Re-Design NTP 01/30/2017 A 0B1090 A/E Prepares 30% Construction Documents (Re-Design)(On-Ho 01/30/2017 A 03/08/2017 A 50B1092 30% CD On-Hold Until City of Miami - PW Approve Site Layout 03/09/2017 A 11/16/2017 A 50B1094 A/E Prepares 30% Construction Documents (Resume Re-Desig 11/17/2017 A 12/20/2017 A 50B1100 30% CDs Submittal 12/20/2017 A 0B1120 30% Review (MDWASD/PSIP Team) 12/21/2017 A 01/18/2018 A 30
90% Des90% Design 01/19/2018 A 08/21/2018 202B1170 A/E Prepares 90% Construction Documents 01/19/2018 A 03/19/2018 A 40B1180 90% CDs Submittal 03/19/2018 A 0B1190 90% Review (MDWASD/PSIP Team) 03/20/2018 A 04/12/2018 A 30
B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 04/13/2018 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 04/13/2018 A 07/13/2018 A 45B1220 90% Miami - BD Permit Submittal (Pump Station) 07/13/2018 A 0B1230 90% Miami - BD Permit Review (Pump Station) 07/13/2018 A 08/02/2018 21B1240 90% Miami - PWD Permit Submittal (Pump Station) 08/01/2018 0B1250 90% Miami - PWD Permit Review (Pump Station) 08/01/2018 08/21/2018 21B1260 90% CD PM Comments Evaluation Completed 08/21/2018 0
100% De100% Design 08/22/2018 09/18/2018 28B1270 A/E Prepares 100% Construction Documents 08/22/2018 09/04/2018 14B1280 100% CDs Submittal 09/04/2018 0
B1290 100% Review (MDWASD/PSIP Team) 09/05/2018 09/18/2018 14B1300 Design Completed 09/18/2018 0
MDWASDMDWASD Procurement 09/18/2018 12/30/2018 104B1305 Procurement Phase 09/18/2018 12/30/2018 104B1310 Submit CDs to MDWASD Procurement Division 09/18/2018* 0B1312 Bid Notice Preparation Period 09/18/2018 10/20/2018 33B1314 Bid Notice 10/20/2018 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 10/21/2018 11/03/2018 14B1320 Pre-Bid Conference 11/04/2018 11/04/2018 1B1328 Bidders Prepare Bids for Submittal 11/05/2018 11/25/2018 21B1330 Bids Submittal 11/25/2018 0
B1340 MDWASD/PSIP Team Bids Evaluation 11/26/2018 12/16/2018 21B1350 Recommendation for Award Letter 12/16/2018 0B1355 Contract Award (Purchase Order Approval) 12/17/2018 12/30/2018 14
ConstrucConstruction 11/04/2018 08/20/2019 290
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
01/18/2018 A, 30% Design
A/E Prepares 30% Construction Documents (Suspended)Geotechnical Engineering Services
Surveying ServicesMDWASD/PSIP Request Feasibility Study
DC Prepare Feasibility Study, SOW & Fees for TA 007 Rev 1TA 007 Rev 1 Approval Process
DC Prepares Feasibility StudyPrepared and Submit Design Package for TA 019 Rev 0
Engage Design Consultant for TA 019 Rev 0
TA 019 Rev 0 PreparationTA 019 Rev 0 Approval ProcessTA 007 Rev 2 Approval Process (Credit TA)
Issue Re-Design NTPA/E Prepares 30% Construction Documents (Re-Design)(On-Hold)
30% CD On-Hold Until City of Miami - PW Approve Site LayoutA/E Prepares 30% Construction Documents (Resume Re-Design)
30% CDs Submittal30% Review (MDWASD/PSIP Team)
08/21/2018, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)
90% RER(DERM)FDEP Permit Submittal (Pump Station)90% RER(DERM)FDEP Permit Review (Pump Station)90% Miami - BD Permit Submittal (Pump Station)
90% Miami - BD Permit Review (Pump Station)90% Miami - PWD Permit Submittal (Pump Station)
90% Miami - PWD Permit Review (Pump Station)90% CD PM Comments Evaluation Completed
09/18/2018, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal
100% Review (MDWASD/PSIP Team)Design Completed
12/30/2018, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)
08/20/2019, Construction
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 19 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1360 Construction Phase 11/04/2018 08/20/2019 290B1362 MDWASD/PSIP Team prepare for Pre-Construction Meeting 12/17/2018 01/06/2019 21B1365 Pre-Construction Meeting 01/07/2019 01/07/2019 1B1366 WASD Issues NTP (Pre-Const to NTP) 01/08/2019 02/21/2019 45B1368 WASD Issues NTP (PO to NTP) 12/31/2018 02/21/2019 53B1370 Construction NTP 02/22/2019 0B1400 Construction Operations 02/22/2019 08/20/2019 180B1402 Substantial Completion 08/20/2019 0
DesignerDesigner Construction Support Services 11/04/2018 08/20/2019 290B1410 Designer Construction Support Services 11/04/2018 08/20/2019 290
Project CProject Closeout 08/20/2019 12/18/2019 120B1445 Closeout Phase 08/20/2019 12/18/2019 120B1450 Issue SAC Letter 08/20/2019 0B1470 Final Release of Retainage - Construction Contract 08/20/2019 0B1480 Administrative Closeout 08/21/2019 12/18/2019 120B1490 Project Closed 12/18/2019 0
100191 Ba100191 Basin 0069 Infiltration/Inflow Study and Repairs 09/25/2014 A 03/31/2016 A 397InfiltratioInfiltration/Inflow 09/25/2014 A 03/30/2016 A 396
B1000 Infiltration/Inflow Phase 09/25/2014 A 03/30/2016 A 396Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 07/21/2015 A 176
B1005 SSES Phase 09/25/2014 A 07/21/2015 A 176
B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 06/02/2015 A 06/25/2015 A 30B1040 Video Review 06/02/2015 A 07/21/2015 A 30
Dig & ReDig & Replace Repairs 11/20/2015 A 03/30/2016 A 142B1165 Dig & Replace Phase 11/20/2015 A 03/30/2016 A 142B1180 Issue NTP for Dig & Replace Repairs 11/20/2015 A 0B1190 Conduct Dig & Replace Repairs 03/30/2016 A 03/30/2016 A 30
Project CProject Closeout 03/31/2016 A 03/31/2016 A 0B1235 Closeout Phase 03/31/2016 A 03/31/2016 A 0B1260 Project Closed 03/31/2016 A 0
Basin 0076Basin 0076 07/30/2014 A 08/01/2018 1603
100011 Ba100011 Basin 0076 Infiltration/Inflow Study and Repairs 09/25/2014 A 03/09/2016 A 604InfiltratioInfiltration/Inflow 09/25/2014 A 03/08/2016 A 414
B1000 Infiltration/Inflow Phase 09/25/2014 A 03/08/2016 A 414Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 01/05/2015 A 262
B1005 SSES Phase 09/25/2014 A 01/05/2015 A 262B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 11/17/2014 A 12/18/2014 A 30B1031 Smoke Testing 11/17/2014 A 12/18/2014 A 10B1040 Video Review 12/18/2014 A 01/05/2015 A 21
CIPP RepCIPP Repairs 05/22/2015 A 03/08/2016 A 20B1065 CIPP Phase 05/22/2015 A 03/08/2016 A 20B1080 Issue NTP for CIPP Repairs 05/22/2015 A 0B1090 Conduct CIPP Repairs 07/09/2015 A 03/08/2016 A 20
ManholeManhole Repairs 10/02/2015 A 11/05/2015 A 20B1115 Manhole Phase 10/02/2015 A 11/05/2015 A 20B1130 Issue NTP for Manhole Repairs 10/02/2015 A 0B1140 Conduct Manhole Repairs 10/06/2015 A 11/05/2015 A 20
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Construction PhaseMDWASD/PSIP Team prepare for Pre-ConstructioPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Construction NTPConstruction OperationsSubstantial Completion08/20/2019, Designer Construc
Designer Construction Support 12/18/2019, Project C
Closeout PhaseIssue SAC LetterFinal Release of Retainage - Co
Administrative CloseoProject Closed
03/31/2016 A, 100191 Basin 0069 Infiltration/Inflow Study and Repairs03/30/2016 A, Infiltration/Inflow
Infiltration/Inflow Phase07/21/2015 A, Sanitary Sewer Evaluation SurveySSES Phase
Issue NTP to SSES ContractorConduct SSESVideo Review
03/30/2016 A, Dig & Replace RepairsDig & Replace Phase
Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs03/31/2016 A, Project CloseoutCloseout Phase
Project Closed08/01/2018, Basin 0076
03/09/2016 A, 100011 Basin 0076 Infiltration/Inflow Study and Repairs03/08/2016 A, Infiltration/Inflow
Infiltration/Inflow Phase01/05/2015 A, Sanitary Sewer Evaluation SurveySSES Phase
Issue NTP to SSES ContractorConduct SSESSmoke Testing
Video Review03/08/2016 A, CIPP RepairsCIPP Phase
Issue NTP for CIPP RepairsConduct CIPP Repairs
11/05/2015 A, Manhole RepairsManhole Phase
Issue NTP for Manhole RepairsConduct Manhole Repairs
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 20 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
Dig & ReDig & Replace Repairs 05/18/2015 A 01/22/2016 A 30B1165 Dig & Replace Phase 05/18/2015 A 01/22/2016 A 30B1180 Issue NTP for Dig & Replace Repairs 05/18/2015 A 0B1190 Conduct Dig & Replace Repairs 07/06/2015 A 01/22/2016 A 30
Project CProject Closeout 03/09/2016 A 03/09/2016 A 0B1235 Closeout Phase 03/09/2016 A 03/09/2016 A 0B1260 Project Closed 03/09/2016 A 0
100013 Pu100013 Pump Station 0076 Upgrade 07/30/2014 A 08/01/2018 1603DesignDesign 07/30/2014 A 10/27/2015 A 483
B1000 Design Phase 07/30/2014 A 10/27/2015 A 483B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 07/30/2014 A 08/12/2014 A 5B1020 Engage Design Consultant 08/04/2014 A 11/19/2014 A 20B1030 Issue Design NTP 11/20/2014 A 0B1040 A/E Develops and Submits Final Engineering Report 11/20/2014 A 10/23/2015 A 218B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 11/20/2014 A 06/18/2015 A 85
30% Des30% Design 11/20/2014 A 01/16/2015 A 30B1060 A/E Prepares 30% Construction Documents 11/20/2014 A 12/24/2014 A 30B1070 Geotechnical Engineering Services 11/20/2014 A 12/24/2014 A 20B1080 Surveying Services 11/20/2014 A 12/24/2014 A 15B1100 30% CDs Submittal 12/24/2014 A 0B1120 30% Review (MDWASD/PSIP Team) 12/26/2014 A 01/16/2015 A 10
90% Des90% Design 12/26/2014 A 10/23/2015 A 262B1130 A/E Prepares 90% Construction Documents 12/26/2014 A 04/27/2015 A 20B1140 90% CDs Submittal 04/27/2015 A 0B1150 90% Review (MDWASD/PSIP Team) 04/27/2015 A 05/15/2015 A 15B1160 90% RER(DERM)FDEP Permit Submittal (Pump Station) 04/03/2015 A 0B1170 90% RER(DERM)FDEP Permit Review (Pump Station) 04/03/2015 A 05/04/2015 A 15B1180 90% Miami - BD Permit Submittal 05/18/2015 A 0B1190 90% Miami - BD Permit Review 05/18/2015 A 06/12/2015 A 15B1200 90% Miami - PWD Permit Submittal 05/18/2015 A 0B1210 90% Miami - PWD Permit Review 05/18/2015 A 06/12/2015 A 15B1220 90% CD PM Comments Evaluation Completed 06/12/2015 A 0B1221 TA Approval Process - Rev 1 06/09/2015 A 06/18/2015 A 20B1222 A/E Incorporates 90% Construction Documents Revisions 06/19/2015 A 08/25/2015 A 32
B1223 90% RER(DERM)FDEP Permit Reconciliation Period (Pump Sta 08/26/2015 A 10/22/2015 A 15B1224 90% RER(DERM)FDEP Permit Reconciled (Pump Station) 10/23/2015 A 0B1225 90% Miami - BD Permit Reconciliation Period 08/26/2015 A 10/22/2015 A 15B1226 90% Miami - BD Permit Reconciled 10/23/2015 A 0B1227 90% CD Permits Reconciliation Completed 10/23/2015 A 0
100% De100% Design 08/26/2015 A 10/27/2015 A 119B1230 A/E Prepares 100% Construction Documents 08/26/2015 A 10/23/2015 A 10B1240 100% CDs Submittal 10/26/2015 A 0B1250 100% Review (MDWASD/PSIP Team) 10/26/2015 A 10/26/2015 A 10B1260 Design Completed 10/27/2015 A 0
MDWASDMDWASD Procurement 10/28/2015 A 02/19/2016 A 79B1265 Procurement Phase 10/28/2015 A 02/19/2016 A 79B1270 Submit CDs to MDWASD Procurement Division 10/28/2015 A 0B1272 Bid Notice Preparation Period 10/29/2015 A 11/02/2015 A 23B1274 Bid Notice 11/03/2015 A 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
01/22/2016 A, Dig & Replace RepairsDig & Replace Phase
Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs
03/09/2016 A, Project CloseoutCloseout Phase
Project Closed08/01/2018, 100013 Pump Station 0076 Upgrade
10/27/2015 A, Design
Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book
Engage Design ConsultantIssue Design NTP
A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
01/16/2015 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services
30% CDs Submittal30% Review (MDWASD/PSIP Team)
10/23/2015 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)
90% RER(DERM)FDEP Permit Submittal (Pump Station)90% RER(DERM)FDEP Permit Review (Pump Station)90% Miami - BD Permit Submittal
90% Miami - BD Permit Review90% Miami - PWD Permit Submittal
90% Miami - PWD Permit Review90% CD PM Comments Evaluation Completed
TA Approval Process - Rev 1A/E Incorporates 90% Construction Documents Revisions
90% RER(DERM)FDEP Permit Reconciliation Period (Pump Station)90% RER(DERM)FDEP Permit Reconciled (Pump Station)
90% Miami - BD Permit Reconciliation Period90% Miami - BD Permit Reconciled90% CD Permits Reconciliation Completed10/27/2015 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed
02/19/2016 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation Period
Bid Notice
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 21 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1278 MDWASD/PSIP Team Prepare for Pre-Bid Conference 11/04/2015 A 11/16/2015 A 10B1280 Pre-Bid Conference 11/17/2015 A 11/17/2015 A 1B1288 Bidders Prepare Bids for Submittal 11/18/2015 A 12/17/2015 A 15B1290 Bids Submittal 12/17/2015 A 0B1300 MDWASD/PSIP Team Bids Evaluation 12/18/2015 A 01/08/2016 A 15B1310 Recommendation for Award Letter 01/08/2016 A 0B1315 Contract Award (Purchase Order Approval) 01/11/2016 A 02/19/2016 A 10
ConstrucConstruction 11/17/2015 A 07/01/2018 A 1098B1320 Construction Phase 11/17/2015 A 07/01/2018 A 1098B1324 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 01/11/2016 A 01/20/2016 A 15B1326 Pre-Construction Meeting 01/21/2016 A 01/21/2016 A 1
B1328 WASD Issues NTP (PO to NTP) 02/20/2016 A 04/03/2016 A 53B1330 Construction NTP 04/04/2016 A 0B1360 Construction Operations 04/04/2016 A 12/21/2016 A 107B1360 Original Construction Duration 04/04/2016 A 09/01/2016 A 107B1360 Change Order #1 - Tree Permit 09/02/2016 A 12/23/2016 A 107B1362 Substantial Completion 12/21/2016 A 0
DesignerDesigner Construction Support Services 11/17/2015 A 07/01/2018 A 349B1370 Designer Construction Support Services 11/17/2015 A 07/01/2018 A 349
Project CProject Closeout 12/22/2016 A 08/01/2018 617B1405 Closeout Phase 12/22/2016 A 08/01/2018 617B1410 Issue SAC Letter 12/22/2016 A 10/31/2017 A 314B1430 Final Release of Retainage - Construction Contract 08/01/2018 0B1440 Administrative Closeout 12/22/2016 A 08/01/2018 120B1450 Project Closed 08/01/2018 0
Basin 0077Basin 0077 04/04/2018 A 04/04/2018 A 120
100015 Pu100015 Pump Station 0077 Upgrade 04/04/2018 A 04/04/2018 A 120DesignDesign 04/04/2018 A 04/04/2018 A 7
B1000 Design Phase 04/04/2018 A 04/04/2018 A 7
B1012 PS 0077 Swapped With PS 0319 04/04/2018 A 04/04/2018 A 7Project CProject Closeout 04/04/2018 A 04/04/2018 A 120
B1445 Closeout Phase 04/04/2018 A 04/04/2018 A 120B1480 Administrative Closeout 04/04/2018 A 04/04/2018 A 120B1490 Project Closed 04/04/2018 A 0
Basin 0081Basin 0081 12/01/2015 A 08/01/2018 974
100018 Pu100018 Pump Station 0081 Upgrade 12/01/2015 A 08/01/2018 974DesignDesign 12/01/2015 A 12/02/2016 A 249
B1000 Design Phase 12/01/2015 A 12/02/2016 A 249B1010 Prepare and Submit Design Package 12/01/2015 A 12/01/2015 A 5B1020 Engage Design Consultant 12/01/2015 A 12/31/2015 A 20B1022 TA Preparation 01/01/2016 A 01/20/2016 A 1B1024 TA Approval Process 01/21/2016 A 02/26/2016 A 20B1030 Issue Design NTP 03/11/2016 A 0B1040 A/E Develops and Submits Final Engineering Report 03/11/2016 A 07/21/2016 A 115B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 03/11/2016 A 07/21/2016 A 85
30% Des30% Design 03/11/2016 A 06/14/2016 A 63B1060 A/E Prepares 30% Construction Documents 03/11/2016 A 05/24/2016 A 30B1070 Geotechnical Engineering Services 03/11/2016 A 05/24/2016 A 20
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
MDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter
Contract Award (Purchase Order Approval)07/01/2018 A, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
WASD Issues NTP (PO to NTP)Construction NTP
Construction OperationsOriginal Construction Duration
Change Order #1 - Tree Permit
Substantial Completion07/01/2018 A, Designer Construction Support Services
Designer Construction Support Services08/01/2018, Project Closeout
Closeout PhaseIssue SAC Letter
Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed
04/04/2018 A, Basin 0077
04/04/2018 A, 100015 Pump Station 0077 Upgrade04/04/2018 A, Design
Design PhasePS 0077 Swapped With PS 031904/04/2018 A, Project CloseoutCloseout Phase
Administrative CloseoutProject Closed
08/01/2018, Basin 0081
08/01/2018, 100018 Pump Station 0081 Upgrade12/02/2016 A, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval ProcessIssue Design NTP
A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
06/14/2016 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering Services
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 22 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1080 Surveying Services 03/11/2016 A 05/24/2016 A 15B1100 30% CDs Submittal 05/24/2016 A 0B1120 30% Review (MDWASD/PSIP Team) 05/25/2016 A 06/14/2016 A 10
90% Des90% Design 05/25/2016 A 12/02/2016 A 96B1170 A/E Prepares 90% Construction Documents (60% On-Board Re 05/25/2016 A 07/21/2016 A 20B1172 Pump Station Monitoring Period 07/22/2016 A 12/02/2016 A 96
Project CProject Closeout 12/02/2016 A 08/01/2018 609B1445 Closeout Phase 12/02/2016 A 08/01/2018 609B1450 Issue SAC Letter 12/02/2016 A 0B1480 Administrative Closeout 12/05/2016 A 08/01/2018 120B1490 Project Closed 08/01/2018 0
Basin 0102Basin 0102 05/22/2015 A 08/01/2018 1056
100019 Ba100019 Basin 0102 Infiltration/Inflow Study and Repairs 05/22/2015 A 03/18/2016 A 266InfiltratioInfiltration/Inflow 05/22/2015 A 03/17/2016 A 164
B1000 Infiltration/Inflow Phase 05/22/2015 A 03/17/2016 A 164CIPP RepCIPP Repairs 05/22/2015 A 03/10/2016 A 20
B1065 CIPP Phase 05/22/2015 A 03/10/2016 A 20B1080 Issue NTP for CIPP Repairs 05/22/2015 A 0B1090 Conduct CIPP Repairs 07/30/2015 A 03/10/2016 A 20
ManholeManhole Repairs 10/30/2015 A 03/17/2016 A 20B1115 Manhole Phase 10/30/2015 A 03/17/2016 A 20B1130 Issue NTP for Manhole Repairs 10/30/2015 A 0B1140 Conduct Manhole Repairs 02/08/2016 A 03/17/2016 A 20
Dig & ReDig & Replace Repairs 06/26/2015 A 03/10/2016 A 59B1165 Dig & Replace Phase 06/26/2015 A 03/10/2016 A 59B1180 Issue NTP for Dig & Replace Repairs 06/26/2015 A 0B1190 Conduct Dig & Replace Repairs 11/30/2015 A 03/10/2016 A 30
Project CProject Closeout 03/18/2016 A 03/18/2016 A 0B1235 Closeout Phase 03/18/2016 A 03/18/2016 A 0B1260 Project Closed 03/18/2016 A 0
100020 Pu100020 Pump Station 0102 Upgrade 01/15/2016 A 08/01/2018 912DesignDesign 01/15/2016 A 02/17/2017 A 122
B1000 Design Phase 01/15/2016 A 02/17/2017 A 122B1010 Prepare and Submit Design Package 01/15/2016 A 01/27/2016 A 5B1020 Engage Design Consultant 01/27/2016 A 03/24/2016 A 20B1022 TA Preparation 03/25/2016 A 03/25/2016 A 1B1024 TA Approval Process 03/28/2016 A 04/28/2016 A 20B1030 Issue Design NTP 05/16/2016 A 0
30% Des30% Design 05/16/2016 A 02/17/2017 A 30B1060 A/E Prepares 30% Construction Documents 05/16/2016 A 07/18/2016 A 30B1082 30% Design Documents Suspended and Project Cancelled 07/19/2016 A 02/17/2017 A 30
Project CProject Closeout 02/20/2017 A 08/01/2018 518B1445 Closeout Phase 02/20/2017 A 08/01/2018 518B1450 Issue SAC Letter 03/08/2017 A 0B1480 Administrative Closeout 02/20/2017 A 08/01/2018 30B1490 Project Closed 08/01/2018 0
Basin 0105Basin 0105 09/14/2015 A 08/01/2018 1218
100021 Pu100021 Pump Station 0105 Upgrade 09/14/2015 A 08/01/2018 1218
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Surveying Services30% CDs Submittal
30% Review (MDWASD/PSIP Team)12/02/2016 A, 90% Design
A/E Prepares 90% Construction Documents (60% On-Board Review)Pump Station Monitoring Period
08/01/2018, Project Closeout
Closeout PhaseIssue SAC Letter
Administrative CloseoutProject Closed08/01/2018, Basin 0102
03/18/2016 A, 100019 Basin 0102 Infiltration/Inflow Study and Repairs03/17/2016 A, Infiltration/Inflow
Infiltration/Inflow Phase03/10/2016 A, CIPP RepairsCIPP Phase
Issue NTP for CIPP RepairsConduct CIPP Repairs03/17/2016 A, Manhole RepairsManhole Phase
Issue NTP for Manhole RepairsConduct Manhole Repairs03/10/2016 A, Dig & Replace RepairsDig & Replace Phase
Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs03/18/2016 A, Project CloseoutCloseout Phase
Project Closed08/01/2018, 100020 Pump Station 0102 Upgrade
02/17/2017 A, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval ProcessIssue Design NTP
02/17/2017 A, 30% Design
A/E Prepares 30% Construction Documents30% Design Documents Suspended and Project Cancelled
08/01/2018, Project Closeout
Closeout PhaseIssue SAC Letter
Administrative CloseoutProject Closed08/01/2018, Basin 0105
08/01/2018, 100021 Pump Station 0105 Upgrade
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 23 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
DesignDesign 09/14/2015 A 10/10/2016 A 436B1000 Design Phase 09/14/2015 A 10/10/2016 A 436B1010 Prepare and Submit Design Package 09/14/2015 A 09/21/2015 A 5B1020 Engage Design Consultant 09/22/2015 A 11/30/2015 A 20B1022 TA Preparation 12/01/2015 A 12/08/2015 A 1B1024 TA Approval Process 12/09/2015 A 01/28/2016 A 20B1030 Issue Design NTP 12/29/2015 A 0B1040 A/E Develops and Submits Final Engineering Report 12/29/2015 A 10/03/2016 A 110B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 12/29/2015 A 07/06/2016 A 85
30% Des30% Design 12/30/2015 A 03/30/2016 A 71B1060 A/E Prepares 30% Construction Documents 12/30/2015 A 03/15/2016 A 30B1070 Geotechnical Engineering Services 12/30/2015 A 03/15/2016 A 20B1080 Surveying Services 12/30/2015 A 03/15/2016 A 15B1100 30% CDs Submittal 03/15/2016 A 0B1120 30% Review (MDWASD/PSIP Team) 03/16/2016 A 03/30/2016 A 10
90% Des90% Design 03/16/2016 A 09/28/2016 A 182B1170 A/E Prepares 90% Construction Documents 03/16/2016 A 05/27/2016 A 20B1180 90% CDs Submittal 05/27/2016 A 0B1190 90% Review (MDWASD/PSIP Team) 05/31/2016 A 07/06/2016 A 15B1200 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 07/07/2016 A 0
B1210 90% RER(DERM)/FDEP Permit Review (Pump Station) 07/07/2016 A 09/08/2016 A 15B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 09/19/2016 A 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 09/19/2016 A 09/28/2016 A 15B1260 90% CD PM Comments Evaluation Completed 09/28/2016 A 0
100% De100% Design 09/29/2016 A 10/10/2016 A 31B1270 A/E Prepares 100% Construction Documents 09/29/2016 A 10/10/2016 A 10B1280 100% CDs Submittal 10/10/2016 A 0B1290 100% Review (MDWASD/PSIP Team) 09/29/2016 A 10/10/2016 A 10B1300 Design Completed 10/10/2016 A 0
MDWASDMDWASD Procurement 10/11/2016 A 04/06/2017 A 88B1305 Procurement Phase 10/11/2016 A 04/06/2017 A 88
B1310 Submit CDs to MDWASD Procurement Division 10/11/2016 A 0B1312 Bid Notice Preparation Period 10/12/2016 A 11/21/2016 A 23B1314 Bid Notice 11/21/2016 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 11/22/2016 A 12/13/2016 A 9B1320 Pre-Bid Conference 12/14/2016 A 12/14/2016 A 1B1328 Bidders Prepare Bids for Submittal 12/15/2016 A 01/12/2017 A 21B1330 Bids Submittal 01/12/2017 A 0B1340 MDWASD/PSIP Team Bids Evaluation 01/13/2017 A 02/07/2017 A 15B1350 Recommendation for Award Letter 02/07/2017 A 0B1355 Contract Award (Purchase Order Approval) 02/08/2017 A 04/06/2017 A 10
ConstrucConstruction 12/14/2016 A 12/29/2017 A 770B1360 Construction Phase 12/14/2016 A 12/29/2017 A 770B1364 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 02/08/2017 A 04/12/2017 A 15B1366 Pre-Construction Meeting 04/13/2017 A 04/13/2017 A 1B1368 WASD Issues NTP (Pre-Const to NTP) 04/14/2017 A 05/31/2017 A 26B1369 WASD Issues NTP (PO to NTP) 04/06/2017 A 05/31/2017 A 53
B1370 Construction NTP 06/01/2017 A 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
10/10/2016 A, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval ProcessIssue Design NTP
A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
03/30/2016 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal30% Review (MDWASD/PSIP Team)
09/28/2016 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)/FDEP Permit Submittal (Pump Station)
90% RER(DERM)/FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)90% RER(Building Dept) Permit Review (Pump Station)
90% CD PM Comments Evaluation Completed10/10/2016 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal
100% Review (MDWASD/PSIP Team)Design Completed
04/06/2017 A, MDWASD Procurement
Procurement Phase
Submit CDs to MDWASD Procurement DivisionBid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter
Contract Award (Purchase Order Approval)12/29/2017 A, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Construction NTP
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 24 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1400 Construction Operations 06/01/2017 A 12/29/2017 A 151B1400 Original Construction Duration 06/01/2017 A 10/29/2017 A 151B1400 Change Order #1 - Hurricane Irma 10/30/2017 A 11/19/2017 A 151B1402 Substantial Completion 12/29/2017 A 0
DesignerDesigner Construction Support Services 12/14/2016 A 12/29/2017 A 262B1410 Designer Construction Support Services 12/14/2016 A 12/29/2017 A 262
Project CProject Closeout 12/30/2017 A 08/01/2018 243B1445 Closeout Phase 12/30/2017 A 08/01/2018 243B1450 Issue SAC Letter 05/22/2018 A 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 12/30/2017 A 08/01/2018 120B1490 Project Closed 08/01/2018 0
Basin 0109Basin 0109 03/12/2015 A 12/09/2018 1283
100023 Pu100023 Pump Station 0109 Upgrade 03/12/2015 A 12/09/2018 1283DesignDesign 03/12/2015 A 05/31/2017 A 732
B1000 Design Phase 03/12/2015 A 05/31/2017 A 732B1010 Prepare and Submit Design Package 03/12/2015 A 06/23/2015 A 5B1020 Engage Design Consultant 06/24/2015 A 09/16/2015 A 20B1022 TA Preparation 09/17/2015 A 09/17/2015 A 1B1025 TA Approval Process 09/18/2015 A 09/25/2015 A 20B1030 Issue Design NTP 10/01/2015 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/01/2015 A 07/14/2016 A 85
30% Des30% Design 10/01/2015 A 05/27/2016 A 210B1060 A/E Prepares 30% Construction Documents 10/01/2015 A 04/28/2016 A 30B1070 Geotechnical Engineering Services 10/01/2015 A 04/28/2016 A 20B1080 Surveying Services 10/01/2015 A 04/28/2016 A 15B1100 30% CDs Submittal 04/28/2016 A 0B1120 30% Review (MDWASD/PSIP Team) 04/29/2016 A 05/27/2016 A 10
90% Des90% Design 04/29/2016 A 05/12/2017 A 335B1170 A/E Prepares 90% Construction Documents 04/29/2016 A 06/30/2016 A 20B1180 90% CDs Submittal 06/30/2016 A 0B1190 90% Review (MDWASD/PSIP Team) 07/01/2016 A 07/14/2016 A 15B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 07/15/2016 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 07/15/2016 A 03/14/2017 A 45B1211 Flow Metter & Specialty Odor Control Evaluation Period 07/28/2016 A 11/15/2016 A 77B1212 TA Rev 1 Approval Process 11/15/2016 A 12/14/2016 A 40B1214 A/E Prepares 90% Design for Flow Metter & Specialty Odor Con 11/15/2016 A 02/06/2017 A 40B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 03/20/2017 A 0B1230 90% RER(Building Dept) Permit Submittal (Pump Station) 03/20/2017 A 05/12/2017 A 21B1260 90% CD PM Comments Evaluation Completed 05/12/2017 A 0B1262 MDWASD Union Concurrence Process 01/27/2017 A 03/07/2017 A 30
100% De100% Design 05/12/2017 A 05/31/2017 A 45B1270 A/E Prepares 100% Construction Documents 05/12/2017 A 05/30/2017 A 10B1280 100% CDs Submittal 05/30/2017 A 0B1290 100% Review (MDWASD/PSIP Team) 05/31/2017 A 05/31/2017 A 10B1300 Design Completed 05/31/2017 A 0
MDWASDMDWASD Procurement 06/01/2017 A 10/19/2017 A 133B1305 Procurement Phase 06/01/2017 A 10/19/2017 A 133
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Construction OperationsOriginal Construction Duration
Change Order #1 - Hurricane Irma
Substantial Completion12/29/2017 A, Designer Construction Support Services
Designer Construction Support Services08/01/2018, Project Closeout
Closeout PhaseIssue SAC Letter
Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed
12/09/2018, Basin 0109
12/09/2018, 100023 Pump Station 0109 Upgrade05/31/2017 A, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA PreparationTA Approval Process
Issue Design NTPFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
05/27/2016 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal
30% Review (MDWASD/PSIP Team)05/12/2017 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)
90% RER(DERM)FDEP Permit Submittal (Pump Station)90% RER(DERM)FDEP Permit Review (Pump Station)
Flow Metter & Specialty Odor Control Evaluation PeriodTA Rev 1 Approval Process
A/E Prepares 90% Design for Flow Metter & Specialty Odor Control
90% RER(Building Dept) Permit Submittal (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)90% CD PM Comments Evaluation Completed
MDWASD Union Concurrence Process
05/31/2017 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed
10/19/2017 A, MDWASD Procurement
Procurement Phase
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 25 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1310 Submit CDs to MDWASD Procurement Division 06/01/2017 A 0B1314 Bid Notice Preparation Period 06/02/2017 A 06/07/2017 A 23B1316 Bid Notice 06/07/2017 A 0B1318 MDWASD/PSIP Team Prepare for Pre-Bid Conference 06/08/2017 A 06/20/2017 A 10B1320 Pre-Bid Conference 06/21/2017 A 06/21/2017 A 1B1328 Bidders Prepare Bids for Submittal 06/22/2017 A 07/24/2017 A 15B1330 Bids Submittal 07/24/2017 A 0
B1340 MDWASD/PSIP Team Bids Evaluation 07/25/2017 A 08/31/2017 A 15B1350 Recommendation for Award Letter 08/31/2017 A 0B1355 Contract Award (Purchase Order Approval) 09/01/2017 A 10/19/2017 A 10
ConstrucConstruction 06/21/2017 A 08/11/2018 532B1360 Construction Phase 06/21/2017 A 08/11/2018 532B1364 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 09/01/2017 A 10/16/2017 A 15B1366 Pre-Construction Meeting 10/17/2017 A 10/17/2017 A 1B1367 WASD Issues NTP (Pre-Const to NTP) 10/18/2017 A 02/11/2018 A 45B1369 WASD Issues NTP (PO to NTP) 10/20/2017 A 02/11/2018 A 53B1370 Construction NTP 02/12/2018 A 0B1400 Construction Operations 02/12/2018 A 08/11/2018 181B1402 Substantial Completion 08/11/2018 0
DesignerDesigner Construction Support Services 06/21/2017 A 08/11/2018 245B1410 Designer Construction Support Services 06/21/2017 A 08/11/2018 245
Project CProject Closeout 11/09/2017 A 12/09/2018 395B1445 Closeout Phase 11/09/2017 A 12/09/2018 395B1450 Issue SAC Letter 11/09/2017 A 0B1470 Final Release of Retainage - Construction Contract 08/11/2018 0B1480 Administrative Closeout 08/12/2018 12/09/2018 120B1490 Project Closed 12/09/2018 0
Basin 0113Basin 0113 08/01/2014 A 08/01/2018 1598
100024 Ba100024 Basin 0113 Infiltration/Inflow Study and Repairs 04/17/2015 A 10/15/2015 A 328InfiltratioInfiltration/Inflow 04/17/2015 A 10/14/2015 A 136
B1000 Infiltration/inflow Phase 04/17/2015 A 10/14/2015 A 136
CIPP RepCIPP Repairs 04/17/2015 A 07/21/2015 A 23B1005 CIPP Phase 04/17/2015 A 07/21/2015 A 23B1020 Issue NTP for CIPP Repairs 04/17/2015 A 0B1030 Conduct CIPP Repairs 07/21/2015 A 07/21/2015 A 20
ManholeManhole Repairs 10/02/2015 A 10/14/2015 A 20B1055 Manhole Phase 10/02/2015 A 10/14/2015 A 20B1070 Issue NTP for Manhole Repairs 10/02/2015 A 0B1080 Conduct Manhole Repairs 10/14/2015 A 10/14/2015 A 20
Dig & ReDig & Replace Repairs 05/18/2015 A 06/03/2015 A 52B1105 Dig & Replace Phase 05/18/2015 A 06/03/2015 A 52B1120 Issue NTP for Dig & Replace Repairs 05/18/2015 A 0B1130 Conduct Dig & Replace Repairs 06/01/2015 A 06/03/2015 A 30B1140 Punch List 06/03/2015 A 06/03/2015 A 10
Project CProject Closeout 10/15/2015 A 10/15/2015 A 0B1175 Closeout Phase 10/15/2015 A 10/15/2015 A 0B1200 Project Closed 10/15/2015 A 0
100025 Pu100025 Pump Station 0113 Upgrade 08/01/2014 A 08/01/2018 1598
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Submit CDs to MDWASD Procurement DivisionBid Notice Preparation Period
Bid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter
Contract Award (Purchase Order Approval)08/11/2018, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Construction NTPConstruction OperationsSubstantial Completion08/11/2018, Designer Construction Support Services
Designer Construction Support Services12/09/2018, Project Closeout
Closeout PhaseIssue SAC Letter
Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed
08/01/2018, Basin 0113
10/15/2015 A, 100024 Basin 0113 Infiltration/Inflow Study and Repairs10/14/2015 A, Infiltration/Inflow
Infiltration/inflow Phase07/21/2015 A, CIPP RepairsCIPP Phase
Issue NTP for CIPP RepairsConduct CIPP Repairs
10/14/2015 A, Manhole RepairsManhole Phase
Issue NTP for Manhole RepairsConduct Manhole Repairs
06/03/2015 A, Dig & Replace RepairsDig & Replace Phase
Issue NTP for Dig & Replace RepairsConduct Dig & Replace RepairsPunch List
10/15/2015 A, Project CloseoutCloseout Phase
Project Closed08/01/2018, 100025 Pump Station 0113 Upgrade
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 26 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
DesignDesign 08/01/2014 A 06/02/2015 A 306B1000 Design Phase 08/01/2014 A 06/02/2015 A 306B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 08/01/2014 A 08/01/2014 A 5B1020 Engage Design Consultant 08/04/2014 A 11/19/2014 A 20B1030 Issue Design NTP 11/20/2014 A 0B1040 A/E Develops and Submits Final Engineering Report 11/20/2014 A 06/02/2015 A 20
B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 02/09/2015 A 03/26/2015 A 1030% Des30% Design 11/20/2014 A 01/29/2015 A 27
B1060 A/E Prepares 30% Construction Documents 11/20/2014 A 01/19/2015 A 25B1070 Geotechnical Engineering Services 12/03/2014 A 12/29/2014 A 20B1080 Surveying Services 12/03/2014 A 12/29/2014 A 15B1100 30% CDs Submittal 01/19/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 01/20/2015 A 01/29/2015 A 10
90% Des90% Design 01/20/2015 A 06/02/2015 A 98B1170 A/E Prepares 90% Construction Documents 01/20/2015 A 02/24/2015 A 20B1180 90% CDs Submittal 02/24/2015 A 0
B1190 90% Review (MDWASD/PSIP Team) 02/25/2015 A 03/10/2015 A 5B1195 Permit Package Modifications 03/11/2015 A 03/26/2015 A 5B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 03/27/2015 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 03/27/2015 A 04/22/2015 A 5B1220 90% RER (Building Dept) Permit Submittal 05/01/2015 A 0B1230 90% RER (Building Dept) Permit Review 05/01/2015 A 06/02/2015 A 10B1260 90% CD PM Comments Evaluation Completed 06/02/2015 A 0
100% De100% Design 03/11/2015 A 06/02/2015 A 4B1270 A/E Prepares 100% Construction Documents 03/11/2015 A 03/26/2015 A 2B1280 100% CDs Submittal 03/26/2015 A 0
B1290 100% Review (MDWASD/PSIP Team) 03/27/2015 A 05/27/2015 A 2B1300 Design Completed 06/02/2015 A 0
MDWASDMDWASD Procurement 05/05/2015 A 07/27/2015 A 77B1305 Procurement Phase 05/05/2015 A 07/27/2015 A 77B1310 Submit CDs to MDWASD Procurement Division 05/05/2015 A 0B1320 Pre-Bid Conference 05/15/2015 A 0B1322 Adddendum #2 06/11/2015 A 0B1330 Bids Submittal 06/19/2015 A 0B1340 MDWASD/PSIP Team Bids Evaluation 06/22/2015 A 06/29/2015 A 10B1350 Recommendation for Award Letter 06/29/2015 A 0B1355 Contract Award (Purchase Order Approval) 06/29/2015 A 07/27/2015 A 10
ConstrucConstruction 06/30/2015 A 03/29/2016 A 1267B1360 Construction Phase 06/30/2015 A 03/29/2016 A 1267B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 06/30/2015 A 07/10/2015 A 7B1365 Pre-Construction Meeting 07/13/2015 A 07/13/2015 A 1
B1369 WASD Issues NTP (PO to NTP) 07/27/2015 A 07/27/2015 A 53B1370 Construction NTP 07/27/2015 A 0B1400 Construction Operations 07/27/2015 A 02/19/2016 A 106B1400 Original Construction Duration 07/27/2015 A 12/24/2015 A 106B1400 Change Order #1 - Valve Vault, Top Slabs & Hatches Design Ch 12/25/2015 A 01/29/2016 A 106B1400 Change Order #2 - Hatches Design Change 01/30/2016 A 02/19/2016 A 106B1405 Substantial Completion 02/19/2016 A 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
06/02/2015 A, Design
Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book
Engage Design ConsultantIssue Design NTP
A/E Develops and Submits Final Engineering Report
Final Engineering Report Review & Approval (MDWASD/PSIP Team)01/29/2015 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services
30% CDs Submittal30% Review (MDWASD/PSIP Team)
06/02/2015 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)Permit Package Modifications90% RER(DERM)FDEP Permit Submittal (Pump Station)
90% RER(DERM)FDEP Permit Review (Pump Station)90% RER (Building Dept) Permit Submittal
90% RER (Building Dept) Permit Review90% CD PM Comments Evaluation Completed06/02/2015 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal
100% Review (MDWASD/PSIP Team)Design Completed
07/27/2015 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Pre-Bid ConferenceAdddendum #2Bids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter
Contract Award (Purchase Order Approval)03/29/2016 A, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction MeetingWASD Issues NTP (PO to NTP)
Construction NTPConstruction Operations
Original Construction DurationChange Order #1 - Valve Vault, Top Slabs & Hatches Design Change
Change Order #2 - Hatches Design Change
Substantial Completion
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 27 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
DesignerDesigner Construction Support Services 07/13/2015 A 03/29/2016 A 177B1410 Designer Construction Support Services 07/13/2015 A 03/29/2016 A 177
ConstrucConstruction Close Out 02/22/2016 A 03/29/2016 A 15B1420 Commissioning 02/22/2016 A 02/26/2016 A 15
B1430 Punch List 02/22/2016 A 03/29/2016 A 10Project CProject Closeout 09/21/2015 A 08/01/2018 1045
B1445 Closeout Phase 09/21/2015 A 08/01/2018 1045B1450 Issue SAC Letter 09/21/2015 A 0B1470 Final Release of Retainage - Construction Contract 09/12/2016 A 0B1480 Administrative Closeout 02/22/2016 A 08/01/2018 120B1490 Project Closed 08/01/2018 0
Basin 0114Basin 0114 05/22/2015 A 11/29/2018 1228
100026 Ba100026 Basin 0114 Infiltration/Inflow Study and Repairs 05/22/2015 A 11/11/2015 A 68InfiltratioInfiltration/Inflow 05/22/2015 A 11/10/2015 A 20
B1000 Infiltration/Inflow Phase 05/22/2015 A 11/10/2015 A 20CIPP RepCIPP Repairs 05/22/2015 A 11/10/2015 A 20
B1065 CIPP Phase 05/22/2015 A 11/10/2015 A 20B1080 Issue NTP for CIPP Repairs 05/22/2015 A 0B1090 Conduct CIPP Repairs 10/23/2015 A 11/10/2015 A 20
Project CProject Closeout 11/11/2015 A 11/11/2015 A 0B1235 Closeout Phase 11/11/2015 A 11/11/2015 A 0B1260 Project Closed 11/11/2015 A 0
100027 Pu100027 Pump Station 0114 Upgrade 08/28/2015 A 11/29/2018 1228DesignDesign 08/28/2015 A 02/21/2017 A 515
B1000 Design Phase 08/28/2015 A 02/21/2017 A 515B1010 Prepare and Submit Design Package 08/28/2015 A 09/18/2015 A 5B1020 Engage Design Consultant 09/18/2015 A 09/21/2015 A 20
B1024 TA Preparation 09/22/2015 A 09/22/2015 A 1B1025 TA Approval Process 09/23/2015 A 10/08/2015 A 20B1030 Issue Design NTP 10/30/2015 A 0B1032 TA Rev 1 Approval Process 04/07/2016 A 05/02/2016 A 20B1034 Isue Design NTP - TA Rev 1 05/16/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/30/2015 A 08/19/2016 A 105
30% Des30% Design 10/30/2015 A 02/19/2016 A 53B1060 A/E Prepares 30% Construction Documents 10/30/2015 A 12/22/2015 A 30B1070 Geotechnical Engineering Services 10/30/2015 A 12/22/2015 A 20B1080 Surveying Services 10/30/2015 A 12/22/2015 A 15B1100 30% CDs Submittal 12/22/2015 A 0
B1120 30% Review (MDWASD/PSIP Team) 12/23/2015 A 02/19/2016 A 1060% Des60% Design 12/23/2015 A 05/26/2016 A 165
B1130 A/E Prepares 60% Construction Documents 12/23/2015 A 04/19/2016 A 20
B1140 60% CDs Submittal 04/19/2016 A 0B1160 60% Review (MDWASD/PSIP Team) 04/20/2016 A 05/26/2016 A 10
90% Des90% Design 04/19/2016 A 02/21/2017 A 260B1170 A/E Prepares 90% Construction Documents 04/19/2016 A 07/01/2016 A 20B1180 90% CDs Submittal 07/01/2016 A 0B1190 90% Review (MDWASD/PSIP Team) 07/04/2016 A 08/19/2016 A 15B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 09/14/2016 A 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
03/29/2016 A, Designer Construction Support Services
Designer Construction Support Services03/29/2016 A, Construction Close Out
Commissioning
Punch List08/01/2018, Project Closeout
Closeout PhaseIssue SAC Letter
Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed
11/29/2018, Basin 0114
11/11/2015 A, 100026 Basin 0114 Infiltration/Inflow Study and Repairs11/10/2015 A, Infiltration/Inflow
Infiltration/Inflow Phase11/10/2015 A, CIPP RepairsCIPP Phase
Issue NTP for CIPP RepairsConduct CIPP Repairs
11/11/2015 A, Project CloseoutCloseout Phase
Project Closed11/29/2018, 100027 Pump Station 0114 Upgrade
02/21/2017 A, Design
Design PhasePrepare and Submit Design Package
Engage Design Consultant
TA PreparationTA Approval Process
Issue Design NTPTA Rev 1 Approval ProcessIsue Design NTP - TA Rev 1
Final Engineering Report Review & Approval (MDWASD/PSIP Team)02/19/2016 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services
30% CDs Submittal
30% Review (MDWASD/PSIP Team)05/26/2016 A, 60% Design
A/E Prepares 60% Construction Documents
60% CDs Submittal60% Review (MDWASD/PSIP Team)
02/21/2017 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 28 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 09/14/2016 A 11/17/2016 A 15
B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 11/18/2016 A 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 11/18/2016 A 01/12/2017 A 15B1240 90% RER (Class III) Permit Submittal (Pump Station) 09/14/2016 A 0B1250 90% RER (Class III) Permit Review (Pump Station) 09/14/2016 A 11/15/2016 A 15B1260 90% CD PM Comments Evaluation Completed 01/13/2017 A 0B1262 MDWASD Union Concurrence Process 01/20/2017 A 02/21/2017 A 30
100% De100% Design 01/19/2017 A 01/26/2017 A 28B1270 A/E Prepares 100% Construction Documents 01/19/2017 A 01/23/2017 A 10B1280 100% CDs Submittal 01/23/2017 A 0B1290 100% Review (MDWASD/PSIP Team) 01/23/2017 A 01/26/2017 A 10B1300 Design Completed 01/26/2017 A 0
MDWASDMDWASD Procurement 02/21/2017 A 05/22/2017 A 81B1305 Procurement Phase 02/21/2017 A 05/22/2017 A 81B1310 Submit CDs to MDWASD Procurement Division 02/21/2017 A 0B1312 Bid Notice Preparation Period 02/22/2017 A 02/23/2017 A 23B1314 Bid Notice 02/23/2017 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 02/24/2017 A 03/03/2017 A 10B1320 Pre-Bid Conference 03/06/2017 A 03/06/2017 A 1B1328 Bidders Prepare Bids for Submittal 03/07/2017 A 04/07/2017 A 15B1330 Bids Submittal 04/07/2017 A 0B1340 MDWASD/PSIP Team Bids Evaluation 04/10/2017 A 04/17/2017 A 15B1350 Recommendation for Award Letter 04/17/2017 A 0B1355 Contract Award (Purchase Order Approval) 04/18/2017 A 05/22/2017 A 10
ConstrucConstruction 03/06/2017 A 08/01/2018 697B1360 Construction Phase 03/06/2017 A 08/01/2018 697B1364 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 04/18/2017 A 05/24/2017 A 15B1366 Pre-Construction Meeting 05/25/2017 A 05/25/2017 A 1B1368 WASD Issues NTP (Pre-Const to NTP) 05/25/2017 A 08/27/2017 A 45
B1369 WASD Issues NTP (PO to NTP) 05/22/2017 A 08/27/2017 A 97B1370 Construction NTP 08/28/2017 A 0B1400 Construction Operations 08/28/2017 A 08/01/2018 150B1400 Original Construction Duration 08/28/2017 A 01/25/2018 A 150B1400 Change Order #1 - MDPW Permit 01/26/2018 A 06/14/2018 A 150B1402 Substantial Completion 08/01/2018 0
DesignerDesigner Construction Support Services 03/06/2017 A 08/01/2018 235B1410 Designer Construction Support Services 03/06/2017 A 08/01/2018 235
Project CProject Closeout 08/01/2018 11/29/2018 120B1445 Closeout Phase 08/01/2018 11/29/2018 120B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 08/02/2018 11/29/2018 120B1490 Project Closed 11/29/2018 0
Basin 0121Basin 0121 08/01/2018 09/28/2020 790
100029 Pu100029 Pump Station 0121 Upgrade * 08/01/2018 09/28/2020 790DesignDesign 08/01/2018 06/29/2019 333
B1000 Design Phase 08/01/2018 06/29/2019 333B1010 Prepare and Submit Design Package 08/01/2018 08/07/2018 7
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
90% RER(DERM)FDEP Permit Review (Pump Station)
90% RER(Building Dept) Permit Submittal (Pump Station)90% RER(Building Dept) Permit Review (Pump Station)
90% RER (Class III) Permit Submittal (Pump Station)90% RER (Class III) Permit Review (Pump Station)
90% CD PM Comments Evaluation CompletedMDWASD Union Concurrence Process
01/26/2017 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)
Design Completed05/22/2017 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter
Contract Award (Purchase Order Approval)08/01/2018, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Construction NTPConstruction Operations
Original Construction DurationChange Order #1 - MDPW Permit
Substantial Completion08/01/2018, Designer Construction Support Services
Designer Construction Support Services11/29/2018, Project Closeout
Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction Contract
Administrative CloseoutProject Closed
06/29/2019, Design
Design PhasePrepare and Submit Design Package
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 29 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1020 Engage Design Consultant 08/08/2018 09/04/2018 28B1022 TA Preparation 09/05/2018 09/18/2018 14B1024 TA Approval Process 09/19/2018 10/28/2018 40B1030 Issue Design NTP 10/29/2018 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/29/2018 06/01/2019 216
30% Des30% Design 10/29/2018 01/16/2019 80B1060 A/E Prepares 30% Construction Documents 10/29/2018 12/17/2018 50B1100 30% CDs Submittal 12/17/2018 0
B1120 30% Review (MDWASD/PSIP Team) 12/18/2018 01/16/2019 3060% Des60% Design 12/18/2018 01/30/2019 44
B1130 A/E Prepares 60% Construction Documents 12/18/2018 01/16/2019 30B1140 60% CDs Submittal 01/16/2019 0B1160 60% Review (MDWASD/PSIP Team) 01/17/2019 01/30/2019 14
90% Des90% Design 01/17/2019 06/01/2019 136B1170 A/E Prepares 90% Construction Documents 01/17/2019 02/25/2019 40B1180 90% CDs Submittal 02/25/2019 0B1190 90% Review (MDWASD/PSIP Team) 02/26/2019 03/27/2019 30B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 03/28/2019 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 03/28/2019 05/11/2019 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 05/12/2019 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 05/12/2019 06/01/2019 21B1240 90% Municipality Permit Submittal (Pump Station) 05/12/2019 0B1250 90% Municipality Permit Review (Pump Station) 05/12/2019 06/01/2019 21
B1260 90% CD PM Comments Evaluation Completed 06/01/2019 0100% De100% Design 06/02/2019 06/29/2019 28
B1270 A/E Prepares 100% Construction Documents 06/02/2019 06/15/2019 14B1280 100% CDs Submittal 06/15/2019 0B1290 100% Review (MDWASD/PSIP Team) 06/16/2019 06/29/2019 14B1300 Design Completed 06/29/2019 0
MDWASDMDWASD Procurement 06/29/2019 10/11/2019 104B1305 Procurement Phase 06/29/2019 10/11/2019 104B1310 Submit CDs to MDWASD Procurement Division 06/29/2019 0B1312 Bid Notice Preparation Period 06/30/2019 08/01/2019 33B1314 Bid Notice 08/01/2019 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conferencce 08/02/2019 08/15/2019 14B1320 Pre-Bid Conference 08/16/2019 08/16/2019 1B1324 Bidders Prepare Bids for Submittal 08/17/2019 09/06/2019 21
B1330 Bids Submittal 09/06/2019 0B1340 MDWASD/PSIP Team Bids Evaluation 09/07/2019 09/27/2019 21B1350 Recommendation for Award Letter 09/27/2019 0B1355 Contract Award (Purchase Order Approval) 09/28/2019 10/11/2019 14
ConstrucConstruction 08/16/2019 05/31/2020 290B1360 Construction Phase 08/16/2019 05/31/2020 290B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 09/28/2019 10/18/2019 21B1364 Pre-Construction Meeting 10/19/2019 10/19/2019 1B1366 WASD Issues NTP (Pre-Const to NTP) 10/20/2019 12/03/2019 45B1369 WASD Issues NTP (PO to NTP) 10/12/2019 12/03/2019 53B1370 Construction NTP 12/04/2019 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Engage Design ConsultantTA Preparation
TA Approval Process
Issue Design NTPFinal Engineering Report Review & Ap
01/16/2019, 30% Design
A/E Prepares 30% Construction Documents30% CDs Submittal
30% Review (MDWASD/PSIP Team)01/30/2019, 60% Design
A/E Prepares 60% Construction Documents60% CDs Submittal60% Review (MDWASD/PSIP Team)
06/01/2019, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (P
90% RER(DERM)FDEP Permit Review (90% RER(Building Dept) Permit Submit
90% RER(Building Dept) Permit Revie90% Municipality Permit Submittal (Pum
90% Municipality Permit Review (Pum
90% CD PM Comments Evaluation C06/29/2019, 100% Design
A/E Prepares 100% Construction Do100% CDs Submittal100% Review (MDWASD/PSIP TeamDesign Completed
10/11/2019, MDWASD ProProcurement Phase
Submit CDs to MDWASD ProcuremBid Notice Preparation Period
Bid NoticeMDWASD/PSIP Team Prepare
Pre-Bid ConferenceBidders Prepare Bids for Subm
Bids SubmittalMDWASD/PSIP Team Bids ERecommendation for Award Contract Award (Purchase O
05/31/2
ConstruMDWASD/PSIP Team PrePre-Construction Meeting
WASD Issues NTP (PreWASD Issues NTP (PO
Construction NTP
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 30 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1400 Construction Operations 12/04/2019 05/31/2020 180B1402 Substantial Completion 05/31/2020 0
DesignerDesigner Construction Support Services 08/16/2019 05/31/2020 290B1410 Designer Construction Support Services 08/16/2019 05/31/2020 290
Project CProject Closeout 05/31/2020 09/28/2020 120B1445 Closeout Phase 05/31/2020 09/28/2020 120B1450 Issue SAC Letter 05/31/2020 0B1470 Final Release of Retainage - Construction Contract 05/31/2020 0B1480 Administrative Closeout 06/01/2020 09/28/2020 120B1490 Project Closed 09/28/2020 0
Basin 0124Basin 0124 05/22/2015 A 12/02/2018 1244
100030 Ba100030 Basin 0124 Infiltration/Inflow Study and Repairs 05/22/2015 A 11/16/2015 A 212InfiltratioInfiltration/Inflow 05/22/2015 A 11/13/2015 A 20
B1000 Infiltration/Inflow Phase 05/22/2015 A 11/13/2015 A 20CIPP RepCIPP Repairs 05/22/2015 A 11/13/2015 A 20
B1005 CIPP Phase 05/22/2015 A 11/13/2015 A 20B1020 Issue NTP for CIPP Repairs 05/22/2015 A 0B1030 Conduct CIPP Repairs 10/22/2015 A 11/13/2015 A 20
Project CProject Closeout 11/16/2015 A 11/16/2015 A 0B1175 Closeout Phase 11/16/2015 A 11/16/2015 A 0B1200 Project Closed 11/16/2015 A 0
100031 Pu100031 Pump Station 0124 Upgrade 07/30/2015 A 12/02/2018 1244DesignDesign 07/30/2015 A 03/16/2017 A 620
B1000 Design Phase 07/30/2015 A 03/16/2017 A 620B1010 Prepare and Submit Design Package 07/30/2015 A 08/07/2015 A 5
B1020 Engage Design Consultant 08/10/2015 A 09/01/2015 A 15B1022 TA Preparation 09/02/2015 A 09/02/2015 A 1B1025 TA Approval Process 09/03/2015 A 09/25/2015 A 20B1030 Issue Design NTP 10/07/2015 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/07/2015 A 06/21/2016 A 85
30% Des30% Design 10/08/2015 A 01/07/2016 A 72B1060 A/E Prepares 30% Construction Documents 10/08/2015 A 12/03/2015 A 30B1100 30% CDs Submittal 12/03/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 12/04/2015 A 01/07/2016 A 10
60% Des60% Design 12/04/2015 A 05/02/2016 A 99B1130 A/E Prepares 60% Construction Documents 12/04/2015 A 02/09/2016 A 20B1140 60% CDs Submittal 02/09/2016 A 0B1160 60% Review (MDWASD/PSIP Team) 02/10/2016 A 05/02/2016 A 10
90% Des90% Design 02/10/2016 A 03/07/2017 A 387B1170 A/E Prepares 90% Construction Documents 02/10/2016 A 05/02/2016 A 20B1180 90% CDs Submittal 05/02/2016 A 0B1190 90% Review (MDWASD/PSIP Team) 05/03/2016 A 06/21/2016 A 15B1192 Pump Station Layout Under Evaluation 06/22/2016 A 09/12/2016 A 15B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 09/23/2016 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 09/23/2016 A 10/25/2016 A 15B1220 90% Doral - BD Permit Submittal 11/07/2016 A 0B1230 90% Doral - BD Permit Review 11/07/2016 A 01/25/2017 A 15B1240 90% Doral - PWD Permit Submittal 10/27/2016 A 0B1250 90% Doral - PWD Permit Review 10/27/2016 A 11/15/2016 A 15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
ConstruSubstan05/31/2
Designe
Issue SAFinal Re
12/02/2018, Basin 0124
11/16/2015 A, 100030 Basin 0124 Infiltration/Inflow Study and Repairs11/13/2015 A, Infiltration/Inflow
Infiltration/Inflow Phase11/13/2015 A, CIPP RepairsCIPP Phase
Issue NTP for CIPP RepairsConduct CIPP Repairs11/16/2015 A, Project CloseoutCloseout Phase
Project Closed12/02/2018, 100031 Pump Station 0124 Upgrade
03/16/2017 A, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval ProcessIssue Design NTP
Final Engineering Report Review & Approval (MDWASD/PSIP Team)01/07/2016 A, 30% Design
A/E Prepares 30% Construction Documents30% CDs Submittal
30% Review (MDWASD/PSIP Team)05/02/2016 A, 60% Design
A/E Prepares 60% Construction Documents60% CDs Submittal
60% Review (MDWASD/PSIP Team)03/07/2017 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)Pump Station Layout Under Evaluation
90% RER(DERM)FDEP Permit Submittal (Pump Station)90% RER(DERM)FDEP Permit Review (Pump Station)
90% Doral - BD Permit Submittal90% Doral - BD Permit Review
90% Doral - PWD Permit Submittal90% Doral - PWD Permit Review
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 31 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1260 90% CD PM Comments Evaluation Completed 11/16/2016 A 0B1262 MDWASD Union Concurrence Process 01/27/2017 A 03/07/2017 A 30
100% De100% Design 11/17/2016 A 03/16/2017 A 62B1270 A/E Prepares 100% Construction Documents 11/17/2016 A 01/31/2017 A 10B1280 100% CDs Submittal 01/31/2017 A 0B1290 100% Review (MDWASD/PSIP Team) 02/01/2017 A 03/16/2017 A 10B1300 Design Completed 03/16/2017 A 0
MDWASDMDWASD Procurement 03/16/2017 A 07/31/2017 A 115B1305 Procurement Phase 03/16/2017 A 07/31/2017 A 115B1310 Submit CDs to MDWASD Procurement Division 03/16/2017 A 0B1312 Bid Notice Preparation Period 03/17/2017 A 03/23/2017 A 23B1313 Bid Notice 03/23/2017 A 0B1315 Prepare For Pre-Bid Conference 03/24/2017 A 04/03/2017 A 10B1320 Pre-Bid Conference 04/04/2017 A 04/04/2017 A 1B1323 Bidders Prepare Bids For Submittal 04/05/2017 A 05/12/2017 A 15
B1330 Bids Submittal 05/12/2017 A 0B1340 Bids Evaluation (MDWASD/PSIP Team) 05/15/2017 A 05/22/2017 A 15B1350 Recommendation For Award Letter 05/22/2017 A 0B1355 Contract Award (Purchase Order Approval) 05/23/2017 A 07/31/2017 A 10
ConstrucConstruction 04/04/2017 A 08/05/2018 582B1360 Construction Phase 04/04/2017 A 08/04/2018 582B1364 MDWASD/PSIP Team Prepare For Pre-Construction Meeting 05/23/2017 A 07/28/2017 A 21B1366 Pre-Construction Meeting 07/31/2017 A 07/31/2017 A 1B1368 WASD Issues NTP (Pre-Const to NTP) 08/01/2017 A 12/17/2017 A 45B1369 WASD Issues NTP (PO to NTP) 08/01/2017 A 12/17/2017 A 53B1370 Construction NTP 12/18/2017 A 0
B1400 Construction Operations 12/18/2017 A 08/04/2018 150B1400 Original Construction Duration 12/18/2017 A 05/17/2018 A 150B1400 Change Order #1 - FM Shut Down 05/18/2018 A 06/03/2018 A 150B1400 Change Order #2 - FPL (Pending Approval) 06/04/2018 A 08/05/2018 A 150B1402 Substantial Completion 08/04/2018 0
DesignerDesigner Construction Support Services 04/04/2017 A 08/04/2018 274B1410 Designer Construction Support Services 04/04/2017 A 08/04/2018 274
Project CProject Closeout 08/04/2018 12/02/2018 120B1445 Closeout Phase 08/04/2018 12/02/2018 120B1450 Issue SAC Letter 08/04/2018 0
B1470 Final Release of Retainage - Construction Contract 08/04/2018 0B1480 Administrative Closeout 08/05/2018 12/02/2018 120B1490 Project Closed 12/02/2018 0
Basin 0142Basin 0142 09/25/2014 A 09/28/2020 2171
100032 Ba100032 Basin 0142 Infiltration/Inflow Study and Repairs 09/25/2014 A 09/09/2018 1003InfiltratioInfiltration/Inflow 09/25/2014 A 09/09/2018 1421
B1000 Infiltration/Inflow Phase 09/25/2014 A 09/09/2018 1421Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 09/09/2018 1421
B1005 SSES Phase 09/25/2014 A 09/09/2018 1421B1020 Issue NTP to SSES Contractor 09/25/2014 A 0
B1030 Conduct SSES 10/22/2014 A 12/17/2014 A 30B1031 Smoke Testing 10/27/2014 A 10/31/2014 A 10
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
90% CD PM Comments Evaluation CompletedMDWASD Union Concurrence Process03/16/2017 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal
100% Review (MDWASD/PSIP Team)Design Completed
07/31/2017 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation Period
Bid NoticePrepare For Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids For Submittal
Bids SubmittalBids Evaluation (MDWASD/PSIP Team)
Recommendation For Award LetterContract Award (Purchase Order Approval)
08/05/2018, Construction
Construction PhaseMDWASD/PSIP Team Prepare For Pre-Construction MeetingPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Construction NTP
Construction OperationsOriginal Construction DurationChange Order #1 - FM Shut Down
Change Order #2 - FPL (Pending Approval)
Substantial Completion08/04/2018, Designer Construction Support Services
Designer Construction Support Services12/02/2018, Project Closeout
Closeout PhaseIssue SAC Letter
Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed
09/09/2018, 100032 Basin 0142 Infiltration/Inflow Study a09/09/2018, Infiltration/Inflow
Infiltration/Inflow Phase09/09/2018, Sanitary Sewer Evaluation SurveySSES Phase
Issue NTP to SSES Contractor
Conduct SSESSmoke Testing
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 32 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1040 Video Review 10/27/2014 A 01/30/2015 A 30B1290 Issue NTP to SSES Contractor (New I/I) 08/01/2018* 0B1300 Conduct SSES (New I/I) 08/01/2018 08/30/2018 30B1310 Smoke Testing (New I/I) 08/31/2018 09/09/2018 10B1320 Video Review (New I/I) 08/03/2018 09/01/2018 30
Dig & ReDig & Replace Repairs 06/26/2015 A 08/30/2018 1024B1165 Dig & Replace Phase 06/26/2015 A 08/30/2018 1024B1180 Issue NTP for Dig & Replace Repairs 06/26/2015 A 0B1190 Conduct Dig & Replace Repairs 08/17/2015 A 08/28/2015 A 30B1270 Issue NTP for Dig & Replace Repairs (New I/I) 08/01/2018* 0B1280 Conduct Dig & Replace Repairs (New I/I) 08/01/2018 08/30/2018 30
CIPP RepCIPP Repairs 08/01/2018 08/28/2018 20B1070 CIPP Phase 08/01/2018 08/28/2018 20B1090 Issue NTP for CIPP Repairs 08/01/2018* 0B1100 Conduct CIPP Repairs 08/01/2018 08/28/2018 20
ManholeManhole Repairs 08/01/2018 08/28/2018 20B1110 Manhole Phase 08/01/2018 08/28/2018 20B1130 Issue NTP for Manhole Repairs 08/01/2018* 0B1140 Conduct Manhole Repairs 08/01/2018 08/28/2018 20
Project CProject Closeout 08/28/2018 08/28/2018 0B1235 Closeout Phase 08/28/2018 08/28/2018 0B1260 Project Closed 08/28/2018 0
100033 Pu100033 Pump Station 0142 Upgrade * 08/01/2018 09/28/2020 790DesignDesign 08/01/2018 06/29/2019 333
B1000 Design Phase 08/01/2018 06/29/2019 333B1010 Prepare and Submit Design Package 08/01/2018 08/07/2018 7B1020 Engage Design Consultant 08/08/2018 09/04/2018 28B1022 TA Preparation 09/05/2018 09/18/2018 14B1024 TA Approval 09/19/2018 10/28/2018 40B1030 Issue Design NTP 10/29/2018 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/29/2018 06/01/2019 216
30% Des30% Design 10/29/2018 01/16/2019 80B1060 A/E Prepares 30% Construction Documents 10/29/2018 12/17/2018 50B1100 30% CDs Submittal 12/17/2018 0B1120 30% Review (MDWASD/PSIP Team) 12/18/2018 01/16/2019 30
60% Des60% Design 12/18/2018 01/30/2019 44B1130 A/E Prepares 60% Construction Documents 12/18/2018 01/16/2019 30B1140 60% CDs Submittal 01/16/2019 0B1160 60% Review (MDWASD/PSIP Team) 01/17/2019 01/30/2019 14
90% Des90% Design 01/17/2019 06/01/2019 136B1170 A/E Prepares 90% Construction Documents 01/17/2019 02/25/2019 40B1180 90% CDs Submittal 02/25/2019 0B1190 90% Review (MDWASD/PSIP Team) 02/26/2019 03/27/2019 30B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 03/28/2019 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 03/28/2019 05/11/2019 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 05/12/2019 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 05/12/2019 06/01/2019 21B1240 90% Municipality Permit Submittal (Pump Station) 05/12/2019 0B1250 90% Municipality Permit Review (Pump Station) 05/12/2019 06/01/2019 21
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Video ReviewIssue NTP to SSES Contractor (New I/I)
Conduct SSES (New I/I)Smoke Testing (New I/I)Video Review (New I/I)08/30/2018, Dig & Replace RepairsDig & Replace Phase
Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs
Issue NTP for Dig & Replace Repairs (New I/I)Conduct Dig & Replace Repairs (New I/I)08/28/2018, CIPP Repairs
CIPP PhaseIssue NTP for CIPP Repairs
Conduct CIPP Repairs08/28/2018, Manhole Repairs
Manhole PhaseIssue NTP for Manhole Repairs
Conduct Manhole Repairs08/28/2018, Project CloseoutCloseout Phase
Project Closed
06/29/2019, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval
Issue Design NTPFinal Engineering Report Review & Ap
01/16/2019, 30% Design
A/E Prepares 30% Construction Documents30% CDs Submittal
30% Review (MDWASD/PSIP Team)01/30/2019, 60% Design
A/E Prepares 60% Construction Documents60% CDs Submittal60% Review (MDWASD/PSIP Team)
06/01/2019, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (P
90% RER(DERM)FDEP Permit Review (90% RER(Building Dept) Permit Submit
90% RER(Building Dept) Permit Revie90% Municipality Permit Submittal (Pum
90% Municipality Permit Review (Pum
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 33 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1260 90% CD PM Comments Evaluation Completed 06/01/2019 0100% De100% Design 06/02/2019 06/29/2019 28
B1270 A/E Prepares 100% Construction Documents 06/02/2019 06/15/2019 14B1280 100% CDs Submittal 06/15/2019 0B1290 100% Review (MDWASD/PSIP Team) 06/16/2019 06/29/2019 14B1300 Design Completed 06/29/2019 0
MDWASDMDWASD Procurement 06/29/2019 10/11/2019 104B1305 Procurement Phase 06/29/2019 10/11/2019 104B1310 Submit CDs to MDWASD Procurement Division 06/29/2019 0B1312 Bid Notice Preparation Period 06/30/2019 08/01/2019 33B1314 Bid Notice 08/01/2019 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conferencce 08/02/2019 08/15/2019 14B1320 Pre-Bid Conference 08/16/2019 08/16/2019 1B1328 Bidders Prepare Bids for Submittal 08/17/2019 09/06/2019 21B1330 Bids Submittal 09/06/2019 0B1340 MDWASD/PSIP Team Bids Evaluation 09/07/2019 09/27/2019 21B1350 Recommendation for Award Letter 09/27/2019 0B1355 Contract Award (Purchase Order Approval) 09/28/2019 10/11/2019 14
ConstrucConstruction 08/16/2019 05/31/2020 290B1360 Construction Phase 08/16/2019 05/31/2020 290B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 09/28/2019 10/18/2019 21B1364 Pre-Construction Meeting 10/19/2019 10/19/2019 1B1366 WASD Issues NTP (Pre-Const to NTP) 10/20/2019 12/03/2019 45B1369 WASD Issues NTP (PO to NTP) 10/12/2019 12/03/2019 53B1370 Construction NTP 12/04/2019 0B1400 Construction Operations 12/04/2019 05/31/2020 180B1402 Substantial Completion 05/31/2020 0
DesignerDesigner Construction Support Services 08/16/2019 05/31/2020 290B1410 Designer Construction Support Services 08/16/2019 05/31/2020 290
Project CProject Closeout 05/31/2020 09/28/2020 120B1445 Closeout Phase 05/31/2020 09/28/2020 120B1450 Issue SAC Letter 05/31/2020 0B1470 Final Release of Retainage - Construction Contract 05/31/2020 0B1480 Administrative Closeout 06/01/2020 09/28/2020 120B1490 Project Closed 09/28/2020 0
Basin 0144Basin 0144 08/01/2018 09/28/2020 790
100185 Pu100185 Pump Station 0144 Upgrade * 08/01/2018 09/28/2020 790DesignDesign 08/01/2018 06/29/2019 333
B1000 Design Phase 08/01/2018 06/29/2019 333B1010 Prepare and Submit Design Package 08/01/2018 08/07/2018 7B1020 Engage Design Consultant 08/08/2018 09/04/2018 28B1022 TA Preparation 09/05/2018 09/18/2018 14B1024 TA Approval 09/19/2018 10/28/2018 40B1030 Issue Design NTP 10/29/2018 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/29/2018 06/01/2019 216
30% Des30% Design 10/29/2018 01/16/2019 80B1060 A/E Prepares 30% Construction Documents 10/29/2018 12/17/2018 50B1100 30% CDs Submittal 12/17/2018 0B1120 30% Review (MDWASD/PSIP Team) 12/18/2018 01/16/2019 30
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
90% CD PM Comments Evaluation C06/29/2019, 100% Design
A/E Prepares 100% Construction Do100% CDs Submittal100% Review (MDWASD/PSIP TeamDesign Completed
10/11/2019, MDWASD ProProcurement Phase
Submit CDs to MDWASD ProcuremBid Notice Preparation Period
Bid NoticeMDWASD/PSIP Team Prepare
Pre-Bid ConferenceBidders Prepare Bids for Subm
Bids SubmittalMDWASD/PSIP Team Bids ERecommendation for Award Contract Award (Purchase O
05/31/2
ConstruMDWASD/PSIP Team PrePre-Construction Meeting
WASD Issues NTP (PreWASD Issues NTP (PO
Construction NTPConstruSubstan05/31/2
Designe
Issue SAFinal Re
06/29/2019, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval
Issue Design NTPFinal Engineering Report Review & Ap
01/16/2019, 30% Design
A/E Prepares 30% Construction Documents30% CDs Submittal
30% Review (MDWASD/PSIP Team)
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 34 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
60% Des60% Design 12/18/2018 01/30/2019 44B1130 A/E Prepares 60% Construction Documents 12/18/2018 01/16/2019 30B1140 60% CDs Submittal 01/16/2019 0B1160 60% Review (MDWASD/PSIP Team) 01/17/2019 01/30/2019 14
90% Des90% Design 01/17/2019 06/01/2019 136B1170 A/E Prepares 90% Construction Documents 01/17/2019 02/25/2019 40B1180 90% CDs Submittal 02/25/2019 0B1190 90% Review (MDWASD/PSIP Team) 02/26/2019 03/27/2019 30B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 03/28/2019 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 03/28/2019 05/11/2019 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 05/12/2019 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 05/12/2019 06/01/2019 21B1240 90% Municipality Permit Submittal (Pump Station) 05/12/2019 0B1250 90% Municipality Permit Review (Pump Station) 05/12/2019 06/01/2019 21B1260 90% CD PM Comments Evaluation Completed 06/01/2019 0
100% De100% Design 06/02/2019 06/29/2019 28B1270 A/E Prepares 100% Construction Documents 06/02/2019 06/15/2019 14B1280 100% CDs Submittal 06/15/2019 0B1290 100% Review (MDWASD/PSIP Team) 06/16/2019 06/29/2019 14B1300 Design Completed 06/29/2019 0
MDWASDMDWASD Procurement 06/29/2019 10/11/2019 104B1305 Procurement Phase 06/29/2019 10/11/2019 104B1310 Submit CDs to MDWASD Procurement Division 06/29/2019 0B1312 Bid Notice Preparation Period 06/30/2019 08/01/2019 33B1314 Bid Notice 08/01/2019 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conferencce 08/02/2019 08/15/2019 14B1320 Pre-Bid Conference 08/16/2019 08/16/2019 1B1328 Bidders Prepare Bids for Submittal 08/17/2019 09/06/2019 21B1330 Bids Submittal 09/06/2019 0B1340 MDWASD/PSIP Team Bids Evaluation 09/07/2019 09/27/2019 21B1350 Recommendation for Award Letter 09/27/2019 0B1355 Contract Award (Purchase Order Approval) 09/28/2019 10/11/2019 14
ConstrucConstruction 08/16/2019 05/31/2020 290B1360 Construction Phase 08/16/2019 05/31/2020 290B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 09/28/2019 10/18/2019 21B1364 Pre-Construction Meeting 10/19/2019 10/19/2019 1B1366 WASD Issues NTP (Pre-Const to NTP) 10/20/2019 12/03/2019 45B1369 WASD Issues NTP (PO to NTP) 10/12/2019 12/03/2019 53B1370 Construction NTP 12/04/2019 0B1400 Construction Operations 12/04/2019 05/31/2020 180B1402 Substantial Completion 05/31/2020 0
DesignerDesigner Construction Support Services 08/16/2019 05/31/2020 290B1410 Designer Construction Support Services 08/16/2019 05/31/2020 290
Project CProject Closeout 05/31/2020 09/28/2020 120B1445 Closeout Phase 05/31/2020 09/28/2020 120B1450 Issue SAC Letter 05/31/2020 0B1470 Final Release of Retainage - Construction Contract 05/31/2020 0B1480 Administrative Closeout 06/01/2020 09/28/2020 120B1490 Project Closed 09/28/2020 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
01/30/2019, 60% Design
A/E Prepares 60% Construction Documents60% CDs Submittal60% Review (MDWASD/PSIP Team)
06/01/2019, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (P
90% RER(DERM)FDEP Permit Review 90% RER(Building Dept) Permit Submit
90% RER(Building Dept) Permit Revie90% Municipality Permit Submittal (Pum
90% Municipality Permit Review (Pum90% CD PM Comments Evaluation C
06/29/2019, 100% Design
A/E Prepares 100% Construction Do100% CDs Submittal100% Review (MDWASD/PSIP TeamDesign Completed
10/11/2019, MDWASD ProProcurement Phase
Submit CDs to MDWASD ProcuremBid Notice Preparation Period
Bid NoticeMDWASD/PSIP Team Prepare
Pre-Bid ConferenceBidders Prepare Bids for Subm
Bids SubmittalMDWASD/PSIP Team Bids ERecommendation for Award Contract Award (Purchase O
05/31/2
ConstruMDWASD/PSIP Team PrePre-Construction Meeting
WASD Issues NTP (PreWASD Issues NTP (PO
Construction NTPConstruSubstan05/31/2
Designe
Issue SAFinal Re
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 35 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
Basin 0147Basin 0147 07/03/2014 A 08/01/2018 1630
100035 Ba100035 Basin 0147 Infiltration/Inflow Study and Repairs 05/18/2015 A 12/21/2015 A 541InfiltratioInfiltration/Inflow 05/18/2015 A 12/18/2015 A 417
B1000 Infiltration/Inflow Phase 05/18/2015 A 12/18/2015 A 417Sanitary Sanitary Sewer Evaluation Survey 08/19/2015 A 09/24/2015 A 30
B1001 SSES Phase 08/19/2015 A 09/24/2015 A 30B1003 Issue NTP to SSES Contractor 08/19/2015 A 0B1004 Conduct SSES 08/19/2015 A 09/24/2015 A 30
CIPP RepCIPP Repairs 09/17/2015 A 12/18/2015 A 28B1005 CIPP Phase 09/17/2015 A 12/18/2015 A 28B1020 Issue NTP for CIPP Repairs 09/17/2015 A 0B1030 Conduct CIPP Repairs 12/18/2015 A 12/18/2015 A 28
ManholeManhole Repairs 10/02/2015 A 11/11/2015 A 49B1055 Manhole Phase 10/02/2015 A 11/11/2015 A 49B1070 Issue NTP for Manhole Repairs 10/02/2015 A 0B1080 Conduct Manhole Repairs 11/09/2015 A 11/11/2015 A 20
Dig & ReDig & Replace Repairs 05/18/2015 A 12/09/2015 A 30B1105 Dig & Replace Phase 05/18/2015 A 12/09/2015 A 30B1120 Issue NTP for Dig & Replace Repairs 05/18/2015 A 0B1130 Conduct Dig & Replace Repairs 05/26/2015 A 12/09/2015 A 30
Project CProject Closeout 12/21/2015 A 12/21/2015 A 0B1175 Closeout Phase 12/21/2015 A 12/21/2015 A 0B1200 Project Closed 12/21/2015 A 0
100036 Pu100036 Pump Station 0147 Upgrade 07/03/2014 A 08/01/2018 1630DesignDesign 07/03/2014 A 04/27/2016 A 435
B1000 Design Phase 07/03/2014 A 04/27/2016 A 435B1010 Prepare Request for SOW, Fee, Schedule, and Project Book (D 07/03/2014 A 07/03/2014 A 5B1015 Engage Design Consultant (Draft PER) 07/07/2014 A 08/26/2014 A 20B1016 Prepare Request for SOW, Fee, Schedule, and Project Book (A 08/27/2014 A 08/27/2014 A 1B1017 Engage Design Consultant (Approved PER) 08/27/2014 A 11/05/2014 A 20B1020 Issue Design NTP 11/06/2014 A 0B1022 Engage Design Consultant for TA REV 1 07/28/2015 A 03/27/2016 A 20B1024 TA REV 1 Approval Process 03/28/2016 A 04/27/2016 A 20B1030 A/E Develops and Submits Final Engineering Report 11/06/2014 A 06/16/2015 A 20B1040 Final Engineering Report Review & Approval (MDWASD/PSIP Te 03/13/2015 A 03/26/2015 A 10
30% Des30% Design 11/06/2014 A 02/04/2015 A 80B1050 A/E Prepares 30% Construction Documents 11/06/2014 A 01/20/2015 A 30B1060 Geotechnical Engineering Services 11/24/2014 A 01/20/2015 A 25B1070 Surveying Services 11/24/2014 A 12/15/2014 A 15B1090 30% CDs Submittal 01/20/2015 A 0B1110 30% Review (MDWASD/PSIP Team) 01/21/2015 A 02/04/2015 A 10
90% Des90% Design 01/21/2015 A 06/16/2015 A 99B1160 A/E Prepares 90% Construction Documents 01/21/2015 A 03/12/2015 A 20B1170 90% CDs Submittal 03/12/2015 A 0B1180 90% Review (MDWASD/PSIP Team) 03/13/2015 A 03/26/2015 A 5B1190 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 04/06/2015 A 0B1200 90% RER(DERM)/FDEP Permit Review (Pump Station) 04/06/2015 A 05/04/2015 A 5B1210 90% RER (Building Department) Permit Submittal 05/12/2015 A 0B1220 90% RER (Building Department) Permit Review 05/12/2015 A 06/16/2015 A 10
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
08/01/2018, Basin 0147
12/21/2015 A, 100035 Basin 0147 Infiltration/Inflow Study and Repairs12/18/2015 A, Infiltration/Inflow
Infiltration/Inflow Phase09/24/2015 A, Sanitary Sewer Evaluation SurveySSES Phase
Issue NTP to SSES ContractorConduct SSES
12/18/2015 A, CIPP RepairsCIPP Phase
Issue NTP for CIPP RepairsConduct CIPP Repairs
11/11/2015 A, Manhole RepairsManhole Phase
Issue NTP for Manhole RepairsConduct Manhole Repairs
12/09/2015 A, Dig & Replace RepairsDig & Replace Phase
Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs12/21/2015 A, Project CloseoutCloseout Phase
Project Closed08/01/2018, 100036 Pump Station 0147 Upgrade
04/27/2016 A, Design
Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book (Draft PER)
Engage Design Consultant (Draft PER)Prepare Request for SOW, Fee, Schedule, and Project Book (Approved PER)
Engage Design Consultant (Approved PER)Issue Design NTP
Engage Design Consultant for TA REV 1TA REV 1 Approval Process
A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
02/04/2015 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering Services
Surveying Services30% CDs Submittal
30% Review (MDWASD/PSIP Team)06/16/2015 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)90% RER(DERM)/FDEP Permit Submittal (Pump Station)
90% RER(DERM)/FDEP Permit Review (Pump Station)90% RER (Building Department) Permit Submittal
90% RER (Building Department) Permit Review
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 36 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1250 90% CD PM Comments Evaluation Completed 06/16/2015 A 0100% De100% Design 04/06/2015 A 04/08/2016 A 86
B1260 A/E Prepares 100% Construction Documents 04/06/2015 A 06/16/2015 A 10B1270 100% CDs Submittal 06/17/2015 A 0B1280 100% Review (MDWASD/PSIP Team) 05/12/2015 A 06/16/2015 A 10B1290 Design Completed 06/16/2015 A 0B1292 TA REV 1 - Design Modifications - Civil, Structural, Electrical & M 07/28/2015 A 04/08/2016 A 86
MDWASDMDWASD Procurement 04/28/2015 A 08/19/2015 A 258B1295 Procurement Phase 04/28/2015 A 08/19/2015 A 258B1300 Submit CDs to MDWASD Procurement Division 04/28/2015 A 0B1312 Bid Notice Preparation Period 04/29/2015 A 04/29/2015 A 33B1314 Bid Notice 04/30/2015 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conferencce 05/01/2015 A 05/05/2015 A 14B1318 Pre-Bid Conference 05/06/2015 A 05/06/2015 A 1B1319 Bidders Prepare Bids for Submittal 05/07/2015 A 06/18/2015 A 21B1320 Bids Submittal 06/18/2015 A 0B1330 MDWASD/PSIP Team Bids Evaluation 06/18/2015 A 07/10/2015 A 21B1340 Recommendation for Award Letter 07/10/2015 A 0B1345 Contract Award (Purchase Order Approval) 07/13/2015 A 08/19/2015 A 14
ConstrucConstruction 05/06/2015 A 03/31/2017 A 1226B1350 Construction Phase 05/06/2015 A 03/31/2017 A 1226B1354 MDWAS/PSIP Team Prepare for Pre-Construction Meeting 07/13/2015 A 07/24/2015 A 21B1356 Pre-Construction Meeting 07/27/2015 A 07/27/2015 A 1B1357 WASD Issues NTP (Pre-Const to NTP) 08/20/2015 A 06/19/2016 A 45B1358 WASD Issues NTP (PO to NTP) 08/20/2015 A 06/19/2016 A 53B1360 Construction NTP 06/20/2016 A 0B1390 Construction Operations 06/20/2016 A 01/30/2017 A 120B1390 Original Construction Duration 06/20/2016 A 10/18/2016 A 120B1390 Change Order #1 - Scriveners Error 10/19/2016 A 12/17/2016 A 120B1390 Change Order #2 - FPL 12/18/2016 A 01/19/2017 A 120B1390 Change Order #3 - Hurricane Mathew 01/20/2017 A 01/24/2017 A 120B1390 Change Order #4 - FPL 01/25/2017 A 02/22/2017 A 120B1392 Substantial Completion 01/30/2017 A 0
DesignerDesigner Construction Support Services 05/06/2015 A 03/31/2017 A 101B1400 Designer Construction Support Services 05/06/2015 A 03/31/2017 A 101
Project CProject Closeout 12/16/2015 A 08/01/2018 959B1435 Closeout Phase 12/16/2015 A 08/01/2018 959B1440 Issue SAC Letter 12/16/2015 A 0B1460 Final Release of Retainage - Construction Contract 08/01/2018 0B1470 Administrative Closeout 01/31/2017 A 08/01/2018 120B1480 Project Closed 08/01/2018 0
Basin 0149Basin 0149 05/22/2015 A 08/01/2018 1332
100037 Ba100037 Basin 0149 Infiltration/Inflow Study and Repairs 05/22/2015 A 05/16/2016 A 211InfiltratioInfiltration/Inflow 05/22/2015 A 05/13/2016 A 159
B1000 Infiltration/Inflow Phase 05/22/2015 A 05/13/2016 A 159CIPP RepCIPP Repairs 05/22/2015 A 05/13/2016 A 136
B1065 CIPP Phase 05/22/2015 A 05/13/2016 A 136B1080 Issue NTP for CIPP Repairs 05/22/2015 A 0B1090 Conduct CIPP Repairs 11/11/2015 A 05/13/2016 A 20
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
90% CD PM Comments Evaluation Completed04/08/2016 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed
TA REV 1 - Design Modifications - Civil, Structural, Electrical & Mechanical08/19/2015 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation Period
Bid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferenccePre-Bid Conference
Bidders Prepare Bids for Submittal
Bids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter
Contract Award (Purchase Order Approval)03/31/2017 A, Construction
Construction PhaseMDWAS/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)
WASD Issues NTP (PO to NTP)Construction NTP
Construction OperationsOriginal Construction Duration
Change Order #1 - Scriveners ErrorChange Order #2 - FPLChange Order #3 - Hurricane Mathew
Change Order #4 - FPL
Substantial Completion03/31/2017 A, Designer Construction Support Services
Designer Construction Support Services08/01/2018, Project Closeout
Closeout PhaseIssue SAC Letter
Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed08/01/2018, Basin 0149
05/16/2016 A, 100037 Basin 0149 Infiltration/Inflow Study and Repairs05/13/2016 A, Infiltration/Inflow
Infiltration/Inflow Phase05/13/2016 A, CIPP RepairsCIPP Phase
Issue NTP for CIPP RepairsConduct CIPP Repairs
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 37 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
Dig & ReDig & Replace Repairs 09/25/2015 A 01/21/2016 A 30B1165 Dig & Replace Phase 09/25/2015 A 01/21/2016 A 30B1180 Issue NTP for Dig & Replace Repairs 09/25/2015 A 0B1190 Conduct Dig & Replace Repairs 01/21/2016 A 01/21/2016 A 30
Project CProject Closeout 05/16/2016 A 05/16/2016 A 0B1235 Closeout Phase 05/16/2016 A 05/16/2016 A 0B1260 Project Closed 05/16/2016 A 0
100038 Pu100038 Pump Station 0149(AM) Upgrade 10/12/2015 A 08/01/2018 1235DesignDesign 10/12/2015 A 07/31/2017 A 464
B1000 Design Phase 10/12/2015 A 07/31/2017 A 464B1010 Prepare and Submit Design Package 10/12/2015 A 10/12/2015 A 5B1012 Project SACed Evaluation Period 10/13/2015 A 07/31/2017 A 464
Project CProject Closeout 07/31/2017 A 08/01/2018 723B1445 Closeout Phase 07/31/2017 A 08/01/2018 723B1450 Issue SAC Letter 07/31/2017 A 0B1480 Administrative Closeout 08/01/2017 A 08/01/2018 120B1490 Project Closed 08/01/2018 0
Basin 0158Basin 0158 06/05/2015 A 08/01/2018 1297
100039 Ba100039 Basin 0158 Infiltration/Inflow Study and Repairs 11/20/2015 A 04/25/2016 A 92InfiltratioInfiltration/Inflow 11/20/2015 A 04/25/2016 A 20
B1000 Infiltration/Inflow Phase 11/20/2015 A 04/25/2016 A 20Dig & ReDig & Replace Repairs 11/20/2015 A 04/25/2016 A 20
B1105 Dig & Replace Phase 11/20/2015 A 04/25/2016 A 20B1120 Issue NTP for Dig & Replace Repairs 11/20/2015 A 0B1130 Conduct Dig & Replace Repairs 04/21/2016 A 04/25/2016 A 20
Project CProject Closeout 04/25/2016 A 04/25/2016 A 0B1175 Closeout Phase 04/25/2016 A 04/25/2016 A 0B1200 Project Closed 04/25/2016 A 0
100040 Pu100040 Pump Station 0158 Upgrade 06/05/2015 A 08/01/2018 1297DesignDesign 06/05/2015 A 11/18/2016 A 569
B1000 Design Phase 06/05/2015 A 11/18/2016 A 569B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 06/05/2015 A 06/19/2015 A 5B1020 Engage Design Consultant 06/19/2015 A 07/24/2015 A 15B1025 TA Approval Process 07/27/2015 A 08/07/2015 A 15B1030 Issue Design NTP 08/07/2015 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 08/07/2015 A 09/27/2016 A 94
30% Des30% Design 08/07/2015 A 12/01/2015 A 56B1060 A/E Prepares 30% Construction Documents 08/07/2015 A 10/21/2015 A 30B1100 30% CDs Submittal 10/22/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 10/23/2015 A 12/01/2015 A 10
90% Des90% Design 10/23/2015 A 09/27/2016 A 319B1170 A/E Prepares 90% Construction Documents 10/23/2015 A 01/21/2016 A 20B1180 90% CDs Submittal 01/21/2016 A 0B1190 90% Review (MDWASD/PSIP Team) 01/22/2016 A 05/05/2016 A 15B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 04/28/2016 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 04/28/2016 A 06/20/2016 A 15B1220 90% Doral - BD Permit Submittal 04/28/2016 A 0B1230 90% Doral - BD Permit Review 04/28/2016 A 09/27/2016 A 15B1260 90% CD PM Comments Evaluation Completed 09/27/2016 A 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
01/21/2016 A, Dig & Replace RepairsDig & Replace Phase
Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs
05/16/2016 A, Project CloseoutCloseout Phase
Project Closed08/01/2018, 100038 Pump Station 0149(AM) Upgrade
07/31/2017 A, Design
Design PhasePrepare and Submit Design Package
Project SACed Evaluation Period08/01/2018, Project Closeout
Closeout PhaseIssue SAC Letter
Administrative CloseoutProject Closed08/01/2018, Basin 0158
04/25/2016 A, 100039 Basin 0158 Infiltration/Inflow Study and Repairs04/25/2016 A, Infiltration/InflowInfiltration/Inflow Phase04/25/2016 A, Dig & Replace RepairsDig & Replace Phase
Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs04/25/2016 A, Project CloseoutCloseout Phase
Project Closed08/01/2018, 100040 Pump Station 0158 Upgrade
11/18/2016 A, Design
Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book
Engage Design ConsultantTA Approval ProcessIssue Design NTP
Final Engineering Report Review & Approval (MDWASD/PSIP Team)12/01/2015 A, 30% Design
A/E Prepares 30% Construction Documents30% CDs Submittal
30% Review (MDWASD/PSIP Team)09/27/2016 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)
90% RER(DERM)FDEP Permit Review (Pump Station)90% Doral - BD Permit Submittal
90% Doral - BD Permit Review90% CD PM Comments Evaluation Completed
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 38 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
100% De100% Design 09/28/2016 A 11/18/2016 A 78B1270 A/E Prepares 100% Construction Documents 09/28/2016 A 11/18/2016 A 10B1280 100% CDs Submittal 11/18/2016 A 0B1290 100% Review (MDWASD/PSIP Team) 09/28/2016 A 11/18/2016 A 10B1300 Design Completed 11/18/2016 A 0
MDWASDMDWASD Procurement 05/10/2016 A 03/27/2017 A 254B1305 Procurement Phase 05/10/2016 A 03/27/2017 A 254B1310 Submit CDs to MDWASD Procurement Division 05/10/2016 A 0B1312 Bid Notice Preparation Period 05/11/2016 A 05/11/2016 A 23B1314 Bid Notice 05/11/2016 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 05/12/2016 A 05/31/2016 A 10B1320 Pre-Bid Conference 06/01/2016 A 06/01/2016 A 1B1324 Bidders Prepare Bids for Submittal 06/02/2016 A 12/20/2016 A 15B1330 Bids Submittal 12/20/2016 A 0B1340 MDWASD/PSIP Team Bids Evaluation 12/21/2016 A 01/30/2017 A 15B1350 Recommendation for Award Letter 01/30/2017 A 0B1355 Contract Award (Purchase Order Approval) 01/31/2017 A 03/27/2017 A 10
ConstrucConstruction 06/01/2016 A 12/26/2017 A 931B1360 Construction Phase 06/01/2016 A 12/26/2017 A 931B1363 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 01/31/2017 A 03/31/2017 A 21B1365 Pre-Construction Meeting 04/03/2017 A 04/03/2017 A 1B1367 WASD Issues NTP (Pre-Const to NTP) 04/04/2017 A 06/18/2017 A 53B1369 WASD Issues NTP (PO to NTP) 03/28/2017 A 06/18/2017 A 53B1370 Construction NTP 06/19/2017 A 0B1400 Construction Operations 06/19/2017 A 12/26/2017 A 150B1400 Original Construction Duration 06/19/2017 A 11/16/2017 A 150B1400 Change Order #1 - Hurricane Irma 11/17/2017 A 12/07/2017 A 150B1402 Substantial Completion 12/26/2017 A 0
DesignerDesigner Construction Support Services 06/01/2016 A 12/26/2017 A 301B1410 Designer Construction Support Services 06/01/2016 A 12/26/2017 A 301
Project CProject Closeout 12/27/2017 A 08/01/2018 212B1445 Closeout Phase 12/27/2017 A 08/01/2018 212B1450 Issue SAC Letter 07/05/2018 A 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 12/27/2017 A 08/01/2018 120B1490 Project Closed 08/01/2018 0
100239 FM100239 FM for Pump Station 0158 06/09/2015 A 08/01/2018 1283DesignDesign 06/09/2015 A 07/29/2016 A 425
B1000 Design Phase 06/09/2015 A 07/29/2016 A 425B1010 Prepare and Submit Design Package 06/09/2015 A 08/04/2015 A 5B1020 Engage Design Consultant 06/09/2015 A 07/29/2015 A 20B1030 TA Preparation 07/30/2015 A 07/30/2015 A 15B1032 TA Approval Process 07/31/2015 A 08/25/2015 A 20B1040 Issue Design NTP 09/15/2015 A 0B1050 A/E Develops and Submits Final Engineering Report 09/15/2015 A 05/13/2016 A 85B1060 Final Engineering Report Review & Approval (MDWASD/PSIP Te 09/15/2015 A 12/15/2015 A 75
30% Des30% Design 09/15/2015 A 12/15/2015 A 60B1070 A/E Prepares 30% Construction Documents 09/15/2015 A 10/15/2015 A 30B1080 Geotechnical Engineering Services 09/15/2015 A 10/15/2015 A 21
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
11/18/2016 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal
100% Review (MDWASD/PSIP Team)Design Completed
03/27/2017 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid Notice
MDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter
Contract Award (Purchase Order Approval)12/26/2017 A, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Construction NTPConstruction Operations
Original Construction DurationChange Order #1 - Hurricane Irma
Substantial Completion12/26/2017 A, Designer Construction Support Services
Designer Construction Support Services08/01/2018, Project Closeout
Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction ContractAdministrative CloseoutProject Closed08/01/2018, 100239 FM for Pump Station 0158
07/29/2016 A, Design
Design PhasePrepare and Submit Design PackageEngage Design ConsultantTA Preparation
TA Approval ProcessIssue Design NTP
A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)12/15/2015 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering Services
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 39 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1090 Surveying Services 09/15/2015 A 10/15/2015 A 21B1100 30% CDs Submittal 10/16/2015 A 0B1110 30% Review (MDWASD/PSIP Team) 10/19/2015 A 12/15/2015 A 6
90% Des90% Design 10/19/2015 A 05/13/2016 A 224B1150 A/E Prepares 90% Construction Documents 10/19/2015 A 02/08/2016 A 20B1160 90% CDs Submittal 02/08/2016 A 0B1170 90% Review (MDWASD/PSIP Team) 02/09/2016 A 05/05/2016 A 15B1180 90% RER(DERM)/FDEP Permit Submittal (Force Main) 04/27/2016 A 0B1190 90% RER(DERM)/FDEP Permit Review (Force Main) 04/27/2016 A 05/12/2016 A 15B1200 90% Doral - PWD Permit Submittal (Force Main) 04/27/2016 A 0B1210 90% Doral - PWD Permit Review (Force Main) 04/27/2016 A 05/10/2016 A 15B1220 90% CD PM Comments Evaluation Completed 05/13/2016 A 0
100% De100% Design 05/16/2016 A 07/29/2016 A 31B1230 A/E Prepares 100% Construction Documents 05/16/2016 A 07/29/2016 A 10B1240 100% CDs Submittal 07/29/2016 A 0B1250 100% Review (MDWASD/PSIP Team) 05/16/2016 A 07/29/2016 A 10B1260 Design Completed 07/29/2016 A 0
MDWASDMDWASD Procurement 05/10/2016 A 08/16/2016 A 50B1270 Procurement Phase 05/10/2016 A 08/16/2016 A 50B1280 Submit CDs to MDWASD Procurement Division 05/10/2016 A 0B1282 Bid Notice Preparation Period 05/10/2016 A 05/10/2016 A 23B1284 Bid Notice 05/11/2016 A 0B1286 MDWASD/PSIP Team Prepare for Pre-Bid Conference 05/12/2016 A 05/31/2016 A 10B1290 Pre-Bid Conference 06/01/2016 A 06/01/2016 A 1B1298 Bidders Prepare Bids for Submittal 06/02/2016 A 06/14/2016 A 15B1300 Bids Submittal 07/08/2016 A 0B1310 Bids Evaluation (MDWASD/PSIP Team) 06/22/2016 A 07/07/2016 A 15B1320 Recommendation for Award Letter 07/07/2016 A 0B1330 Contract Award (Purchase Order Approval) 07/08/2016 A 08/16/2016 A 10
ConstrucConstruction 06/01/2016 A 12/30/2016 A 901B1340 Construction Phase 06/01/2016 A 12/30/2016 A 901B1344 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 07/08/2016 A 07/28/2016 A 15B1346 Pre-Construction Meeting 07/29/2016 A 07/29/2016 A 1B1348 WASD Issues NTP (PO to NTP) 08/17/2016 A 09/12/2016 A 53B1350 Construction NTP 09/13/2016 A 0B1380 Construction Operations 09/13/2016 A 12/09/2016 A 150B1382 Substantial Completion 12/09/2016 A 0
DesignerDesigner Construction Support Services 06/01/2016 A 12/30/2016 A 321B1480 Designer Construction Support Services 06/01/2016 A 12/30/2016 A 321
ConstrucConstruction Close Out 12/12/2016 A 12/30/2016 A 15B1390 Commissioning 12/12/2016 A 12/30/2016 A 15B1400 Punch List 12/12/2016 A 12/23/2016 A 10
Project CProject Closeout 12/12/2016 A 08/01/2018 598B1420 Closeout Phase 12/12/2016 A 08/01/2018 598B1430 Issue SAC Letter 12/20/2017 A 0B1450 Final Release of Retainage - Construction Contract 08/01/2018 0B1460 Administrative Closeout 12/12/2016 A 08/01/2018 30B1470 Project Closed 08/01/2018 0
Basin 0161Basin 0161 05/18/2015 A 05/18/2015 A 583
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Surveying Services30% CDs Submittal
30% Review (MDWASD/PSIP Team)05/13/2016 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)/FDEP Permit Submittal (Force Main)
90% RER(DERM)/FDEP Permit Review (Force Main)90% Doral - PWD Permit Submittal (Force Main)
90% Doral - PWD Permit Review (Force Main)90% CD PM Comments Evaluation Completed
07/29/2016 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed08/16/2016 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid Notice
MDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid ConferenceBidders Prepare Bids for Submittal
Bids SubmittalBids Evaluation (MDWASD/PSIP Team)Recommendation for Award Letter
Contract Award (Purchase Order Approval)12/30/2016 A, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
WASD Issues NTP (PO to NTP)
Construction NTPConstruction OperationsSubstantial Completion
12/30/2016 A, Designer Construction Support Services
Designer Construction Support Services12/30/2016 A, Construction Close Out
CommissioningPunch List
08/01/2018, Project Closeout
Closeout PhaseIssue SAC Letter
Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed
05/18/2015 A, Basin 0161
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 40 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
100041 Pu100041 Pump Station 0161 Upgrade 05/18/2015 A 05/18/2015 A 583Project CProject Closeout 05/18/2015 A 05/18/2015 A 583
B1445 Closeout Phase 05/18/2015 A 05/18/2015 A 583B1450 Issue SAC Letter 05/18/2015 A 0B1480 Administrative Closeout 05/18/2015 A 05/18/2015 A 30B1490 Project Closed 05/18/2015 A 0
Basin 0163Basin 0163 09/10/2015 A 09/28/2020 1695
100042 Ba100042 Basin 0163 Infiltration/Inflow Study and Repairs 09/10/2015 A 09/25/2015 A 114InfiltratioInfiltration/Inflow 09/10/2015 A 09/24/2015 A 30
B1000 Infiltration/Inflow Phase 09/10/2015 A 09/24/2015 A 30Sanitary Sanitary Sewer Evaluation Survey 09/10/2015 A 09/24/2015 A 30
B1005 SSES Phase 09/10/2015 A 09/24/2015 A 30B1020 Issue NTP to SSES Contractor 09/10/2015 A 0B1030 Conduct SSES 09/10/2015 A 09/24/2015 A 30
Project CProject Closeout 09/25/2015 A 09/25/2015 A 0B1235 Closeout Phase 09/25/2015 A 09/25/2015 A 0B1260 Project Closed 09/25/2015 A 0
100043 Pu100043 Pump Station 0163 Upgrade * 08/01/2018 09/28/2020 790DesignDesign 08/01/2018 06/29/2019 333
B1000 Design Phase 08/01/2018 06/29/2019 333B1010 Prepare and Submit Design Package 08/01/2018 08/07/2018 7B1020 Engage Design Consultant 08/08/2018 09/04/2018 28B1022 TA Preparation 09/05/2018 09/18/2018 14B1024 TA Approval Process 09/19/2018 10/28/2018 40B1030 Issue Design NTP 10/29/2018 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/29/2018 06/01/2019 216
30% Des30% Design 10/29/2018 01/16/2019 80B1060 A/E Prepares 30% Construction Documents 10/29/2018 12/17/2018 50B1100 30% CDs Submittal 12/17/2018 0B1120 30% Review (MDWASD/PSIP Team) 12/18/2018 01/16/2019 30
60% Des60% Design 12/18/2018 01/30/2019 44B1130 A/E Prepares 60% Construction Documents 12/18/2018 01/16/2019 30B1140 60% CDs Submittal 01/16/2019 0B1160 60% Review (MDWASD/PSIP Team) 01/17/2019 01/30/2019 14
90% Des90% Design 01/17/2019 06/01/2019 136B1170 A/E Prepares 90% Construction Documents 01/17/2019 02/25/2019 40B1180 90% CDs Submittal 02/25/2019 0B1190 90% Review (MDWASD/PSIP Team) 02/26/2019 03/27/2019 30B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 03/28/2019 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 03/28/2019 05/11/2019 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 05/12/2019 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 05/12/2019 06/01/2019 21B1240 90% Municipality Permit Submittal (Pump Station) 05/12/2019 0B1250 90% Municipality Permit Review (Pump Station) 05/12/2019 06/01/2019 21B1260 90% CD PM Comments Evaluation Completed 06/01/2019 0
100% De100% Design 06/02/2019 06/29/2019 28B1270 A/E Prepares 100% Construction Documents 06/02/2019 06/15/2019 14B1280 100% CDs Submittal 06/15/2019 0B1290 100% Review (MDWASD/PSIP Team) 06/16/2019 06/29/2019 14
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
05/18/2015 A, 100041 Pump Station 0161 Upgrade05/18/2015 A, Project Closeout
Closeout PhaseIssue SAC Letter
Administrative CloseoutProject Closed
09/25/2015 A, 100042 Basin 0163 Infiltration/Inflow Study and Repairs09/24/2015 A, Infiltration/Inflow
Infiltration/Inflow Phase09/24/2015 A, Sanitary Sewer Evaluation SurveySSES Phase
Issue NTP to SSES ContractorConduct SSES09/25/2015 A, Project CloseoutCloseout Phase
Project Closed
06/29/2019, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval Process
Issue Design NTPFinal Engineering Report Review & Ap
01/16/2019, 30% Design
A/E Prepares 30% Construction Documents30% CDs Submittal
30% Review (MDWASD/PSIP Team)01/30/2019, 60% Design
A/E Prepares 60% Construction Documents60% CDs Submittal60% Review (MDWASD/PSIP Team)
06/01/2019, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (P
90% RER(DERM)FDEP Permit Review (90% RER(Building Dept) Permit Submit
90% RER(Building Dept) Permit Revie90% Municipality Permit Submittal (Pum
90% Municipality Permit Review (Pum90% CD PM Comments Evaluation C
06/29/2019, 100% Design
A/E Prepares 100% Construction Do100% CDs Submittal100% Review (MDWASD/PSIP Team
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 41 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1300 Design Completed 06/29/2019 0MDWASDMDWASD Procurement 06/29/2019 10/11/2019 104
B1305 Procurement Phase 06/29/2019 10/11/2019 104B1310 Submit CDs to MDWASD Procurement Division 06/29/2019 0B1312 Bid Notice Preparation Period 06/30/2019 08/01/2019 33B1314 Bid Notice 08/01/2019 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 08/02/2019 08/15/2019 14B1320 Pre-Bid Conference 08/16/2019 08/16/2019 1B1322 Bidders Prepare Bids for Submittal 08/17/2019 09/06/2019 21B1330 Bids Submittal 09/06/2019 0B1340 MDWASD/PSIP Team Bids Evaluation 09/07/2019 09/27/2019 21B1350 Recommendation for Award Letter 09/27/2019 0B1355 Contract Award (Purchase Order Approval) 09/28/2019 10/11/2019 14
ConstrucConstruction 08/16/2019 05/31/2020 290B1360 Construction Phase 08/16/2019 05/31/2020 290B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 09/28/2019 10/18/2019 21B1364 Pre-Construction Meeting 10/19/2019 10/19/2019 1B1366 WASD Issues NTP (Pre-Const to NTP) 10/20/2019 12/03/2019 45B1369 WASD Issues NTP (PO to NTP) 10/12/2019 12/03/2019 53B1370 Construction NTP 12/04/2019 0B1400 Construction Operations 12/04/2019 05/31/2020 180B1402 Substantial Completion 05/31/2020 0
DesignerDesigner Construction Support Services 08/16/2019 05/31/2020 290B1410 Designer Construction Support Services 08/16/2019 05/31/2020 290
Project CProject Closeout 05/31/2020 09/28/2020 120B1445 Closeout Phase 05/31/2020 09/28/2020 120B1450 Issue SAC Letter 05/31/2020 0B1470 Final Release of Retainage - Construction Contract 05/31/2020 0B1480 Administrative Closeout 06/01/2020 09/28/2020 120B1490 Project Closed 09/28/2020 0
100235 FM100235 FM for Pump Station 0163 * 08/01/2017 A 11/20/2019 761DesignDesign 08/01/2017 A 08/20/2018 320
B1000 Design Phase 08/01/2017 A 08/20/2018 320B1010 Prepare and Submit Design Package 08/01/2017 A 08/01/2017 A 7B1020 Engage Design Consultant 08/02/2017 A 10/02/2017 A 28B1022 TA Preparation 10/03/2017 A 10/16/2017 A 14B1024 TA Approval Process 10/17/2017 A 12/20/2017 A 40B1030 Issue Design NTP 12/22/2017 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 12/22/2017 A 04/13/2018 A 186
30% Des30% Design 12/22/2017 A 02/15/2018 A 120B1060 A/E Prepares 30% Construction Documents 12/22/2017 A 02/05/2018 A 50B1100 30% CDs Submittal 02/05/2018 A 0B1120 30% Review (MDWASD/PSIP Team) 02/06/2018 A 02/15/2018 A 30
90% Des90% Design 02/02/2018 A 07/25/2018 A 174B1180 A/E Prepares 90% Construction Documents 02/06/2018 A 03/14/2018 A 40B1190 90% CDs Submittal 03/14/2018 A 0B1200 90% Review (MDWASD/PSIP Team) 03/15/2018 A 04/09/2018 A 30B1210 90% PWWMD Permit Submittal (Force Main) 02/02/2018 A 0B1220 90% PWWMD Permit Review (Force Main) 02/02/2018 A 02/06/2018 A 21
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Design Completed10/11/2019, MDWASD ProProcurement Phase
Submit CDs to MDWASD ProcuremBid Notice Preparation Period
Bid NoticeMDWASD/PSIP Team Prepare
Pre-Bid ConferenceBidders Prepare Bids for Subm
Bids SubmittalMDWASD/PSIP Team Bids ERecommendation for Award Contract Award (Purchase O
05/31/2
ConstruMDWASD/PSIP Team PrePre-Construction Meeting
WASD Issues NTP (PreWASD Issues NTP (PO
Construction NTPConstruSubstan05/31/2
Designe
Issue SAFinal Re
11/20/2019, 100235 FM08/20/2018, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval ProcessIssue Design NTP
Final Engineering Report Review & Approval (MDWASD/PSIP Team)02/15/2018 A, 30% Design
A/E Prepares 30% Construction Documents30% CDs Submittal
30% Review (MDWASD/PSIP Team)07/25/2018 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)
90% PWWMD Permit Submittal (Force Main)90% PWWMD Permit Review (Force Main)
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 42 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1230 90% RER(DERM)FDEP Permit Submittal (Force Main) 04/16/2018 A 0B1240 90% RER(DERM)FDEP Permit Review (Force Main) 04/16/2018 A 07/25/2018 A 45B1290 90% CD PM Comments Evaluation Completed 04/13/2018 A 0
100% De100% Design 07/26/2018 A 08/20/2018 30B1300 A/E Prepares 100% Construction Documents 07/26/2018 A 08/06/2018 14B1310 100% CDs Submittal 08/06/2018 0B1320 100% Review (MDWASD/PSIP Team) 08/07/2018 08/20/2018 14B1330 Design Completed 08/20/2018 0
MDWASDMDWASD Procurement 08/20/2018 12/02/2018 104B1335 Procurement Phase 08/20/2018 12/02/2018 104B1340 Submit CDs to MDWASD Procurement Division 08/20/2018 0B1342 Bid Notice Preparation Period 08/21/2018 09/22/2018 33B1344 Bid Notice 09/22/2018 0B1346 MDWASD/PSIP Team Prepare for Pre-Bid Conference 09/23/2018 10/06/2018 14B1350 Pre-Bid Conference 10/07/2018 10/07/2018 1B1352 Bidders Prepare Bids for Submittal 10/08/2018 10/28/2018 21B1360 Bids Submittal 10/28/2018 0B1370 MDWASD/PSIP Team Bids Evaluation 10/29/2018 11/18/2018 21B1380 Recommendation for Award Letter 11/18/2018 0B1385 Contract Award (Purchase Order Approval) 11/19/2018 12/02/2018 14
ConstrucConstruction 10/07/2018 07/23/2019 290B1390 Construction Phase 10/07/2018 07/23/2019 290B1392 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 11/19/2018 12/09/2018 21B1394 Pre-Construction Meeting 12/10/2018 12/10/2018 1B1396 WASD Issues NTP (Pre-Const to NTP) 12/11/2018 01/24/2019 45B1398 WASD Issues NTP (PO to NTP) 12/03/2018 01/24/2019 53B1400 Construction NTP 01/25/2019 0B1430 Construction Operations 01/25/2019 07/23/2019 180B1432 Substantial Completion 07/23/2019 0
DesignerDesigner Construction Support Services 10/07/2018 07/23/2019 290B1440 Designer Construction Support Services 10/07/2018 07/23/2019 290
Project CProject Closeout 07/23/2019 11/20/2019 120B1475 Closeout Phase 07/23/2019 11/20/2019 120B1500 Final Release of Retainage - Construction Contract 07/23/2019 0B1510 Administrative Closeout 07/24/2019 11/20/2019 120B1520 Project Closed 11/20/2019 0
Basin 0167Basin 0167 01/14/2016 A 08/01/2018 1263
100044 Pu100044 Pump Station 0167 Upgrade 01/14/2016 A 08/01/2018 1263DesignDesign 01/14/2016 A 10/20/2017 A 625
B1000 Design Phase 01/14/2016 A 10/20/2017 A 625B1010 Prepare and Submit Design Package 01/14/2016 A 02/23/2016 A 5B1020 Engage Design Consultant 02/23/2016 A 09/14/2016 A 20B1022 TA Preparation 09/15/2016 A 09/15/2016 A 1B1024 TA Approval Process 09/16/2016 A 10/21/2016 A 20B1030 Issue Design NTP 10/26/2016 A 0
30% Des30% Design 10/26/2016 A 10/20/2017 A 386B1060 A/E Prepares 30% Construction Documents 10/26/2016 A 04/04/2017 A 50B1100 30% CDs Submittal 04/04/2017 A 0B1102 SAC Determination Period 04/05/2017 A 10/20/2017 A 198
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
90% RER(DERM)FDEP Permit Submittal (Force Main)90% RER(DERM)FDEP Permit Review (Force Main)
90% CD PM Comments Evaluation Completed08/20/2018, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed
12/02/2018, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)
07/23/2019, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction Pre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Construction NTPConstruction OperationsSubstantial Completion07/23/2019, Designer Constructio
Designer Construction Support Se11/20/2019, Project Clo
Closeout PhaseFinal Release of Retainage - Con
Administrative CloseoutProject Closed
08/01/2018, Basin 0167
08/01/2018, 100044 Pump Station 0167 Upgrade10/20/2017 A, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval ProcessIssue Design NTP
10/20/2017 A, 30% Design
A/E Prepares 30% Construction Documents30% CDs Submittal
SAC Determination Period
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 43 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
Project CProject Closeout 10/20/2017 A 08/01/2018 664B1445 Closeout Phase 10/20/2017 A 08/01/2018 664B1450 Issue SAC Letter 10/20/2017 A 0B1480 Administrative Closeout 10/21/2017 A 08/01/2018 120B1490 Project Closed 08/01/2018 0
Basin 0173Basin 0173 09/25/2014 A 11/29/2019 1881
100045-2 B100045-2 Basin 0173 Infiltration/Inflow Study and Repairs 09/25/2014 A 07/22/2015 A 604InfiltratioInfiltration/Inflow 09/25/2014 A 07/21/2015 A 298
B1000 Infiltration/Inflow Phase 09/25/2014 A 07/21/2015 A 298Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 07/21/2015 A 298
B1005 SSES Phase 09/25/2014 A 07/21/2015 A 298B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 06/25/2015 A 07/21/2015 A 30
Project CProject Closeout 07/22/2015 A 07/22/2015 A 0B1235 Closeout Phase 07/22/2015 A 07/22/2015 A 0B1260 Project Closed 07/22/2015 A 0
100046 Pu100046 Pump Station 0173 Upgrade 04/20/2015 A 11/29/2019 1685DesignDesign 04/20/2015 A 08/29/2018 1228
B1000 Design Phase 04/20/2015 A 08/29/2018 1228B1010 Prepare and Submit Design Package 04/20/2015 A 04/24/2015 A 5B1020 Engage Design Consultant 04/27/2015 A 06/05/2015 A 20B1022 TA Preparation 06/18/2015 A 06/18/2015 A 1B1025 TA Approval Process 06/19/2015 A 06/25/2015 A 20B1030 Issue Design NTP 08/05/2015 A 0B1032 Prepare and Submit Design Package - Re-Design 03/21/2016 A 03/21/2016 A 5B1034 Engage Design Consultant - Re-Design 03/21/2016 A 04/28/2016 A 20B1036 TA Rev 1 Preparation - Re-Design 04/29/2016 A 09/22/2016 A 1B1038 TA Rev 1 Approval Process - Re-Design 09/26/2016 A 11/16/2016 A 20B1039 Issue Re-Design NTP 11/21/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 08/05/2015 A 08/01/2018 86
30% Des30% Design 08/05/2015 A 02/24/2017 A 558B1100 A/E Prepares 30% Construction Documents 08/05/2015 A 09/16/2015 A 30B1110 Geotechnical Engineering Services 08/05/2015 A 09/16/2015 A 20B1120 Surveying Services 08/05/2015 A 09/16/2015 A 15B1140 30% CDs Submittal 09/17/2015 A 0B1160 30% Review (MDWASD/PSIP Team) 09/18/2015 A 10/13/2015 A 10B1162 A/E Prepares 30% Construction Documents - Re-Design 11/21/2016 A 01/13/2017 A 36B1164 30% CDs Submittal - Re-Design 01/13/2017 A 0B1166 30% Review (MDWASD/PSIP Team) - Re-Design 01/13/2017 A 02/24/2017 A 10
90% Des90% Design 10/14/2015 A 08/01/2018 1003B1170 A/E Prepares 90% Construction Documents 10/14/2015 A 11/24/2015 A 20B1180 90% CDs Submittal 11/24/2015 A 0B1190 90% Review (MDWASD/PSIP Team) 11/25/2015 A 03/18/2016 A 15B1192 A/E Prepares 90% Construction Documents - Re-Design 02/27/2017 A 08/11/2017 A 40B1194 90% CDs Submittal - Re-Design 08/11/2017 A 0B1196 90% Review (MDWASD/PSIP Team) - Re-Design 08/14/2017 A 10/09/2017 A 30B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 11/20/2017 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 11/20/2017 A 03/13/2018 A 45B1220 90% Doral - BD Permit Submittal 03/26/2018 A 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
08/01/2018, Project Closeout
Closeout PhaseIssue SAC Letter
Administrative CloseoutProject Closed
11/29/2019, Basin 017
07/22/2015 A, 100045-2 Basin 0173 Infiltration/Inflow Study and Repairs07/21/2015 A, Infiltration/Inflow
Infiltration/Inflow Phase07/21/2015 A, Sanitary Sewer Evaluation SurveySSES Phase
Issue NTP to SSES ContractorConduct SSES07/22/2015 A, Project CloseoutCloseout Phase
Project Closed11/29/2019, 100046 P
08/29/2018, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA PreparationTA Approval Process
Issue Design NTPPrepare and Submit Design Package - Re-Design
Engage Design Consultant - Re-DesignTA Rev 1 Preparation - Re-Design
TA Rev 1 Approval Process - Re-DesignIssue Re-Design NTP
Final Engineering Report Review & Approval (MDWASD/PSIP 02/24/2017 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal
30% Review (MDWASD/PSIP Team)A/E Prepares 30% Construction Documents - Re-Design
30% CDs Submittal - Re-Design30% Review (MDWASD/PSIP Team) - Re-Design
08/01/2018, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)A/E Prepares 90% Construction Documents - Re-Design90% CDs Submittal - Re-Design
90% Review (MDWASD/PSIP Team) - Re-Design90% RER(DERM)FDEP Permit Submittal (Pump Station)
90% RER(DERM)FDEP Permit Review (Pump Station)90% Doral - BD Permit Submittal
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 44 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1230 90% Doral - BD Permit Review 03/26/2018 A 08/01/2018 21B1240 90% Doral - PWD Permit Submittal 10/23/2015 A 0B1250 90% Doral - PWD Permit Review 10/23/2015 A 10/30/2015 A 15B1260 90% CD PM Comments Evaluation Completed 08/01/2018 0B1262 MDWASD Union Concurrence Process 08/25/2017 A 09/28/2017 A 30
100% De100% Design 08/02/2018 08/29/2018 28B1270 A/E Prepares 100% Construction Documents 08/02/2018 08/15/2018 14B1280 100% CDs Submittal 08/15/2018 0B1290 100% Review (MDWASD/PSIP Team) 08/16/2018 08/29/2018 14B1300 Design Completed 08/29/2018 0
MDWASDMDWASD Procurement 08/29/2018 12/11/2018 104B1305 Procurement Phase 08/29/2018 12/11/2018 104B1310 Submit CDs to MDWASD Procurement Division 08/29/2018 0B1312 Bid Notice Preparation Period 08/30/2018 10/01/2018 33B1314 Bid Notice 10/01/2018 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 10/02/2018 10/15/2018 14B1320 Pre-Bid Conference 10/16/2018 10/16/2018 1B1328 Bidders prepare Bids for Submittal 10/17/2018 11/06/2018 21B1330 Bids Submittal 11/06/2018 0B1340 MDWASD/PSIP Team Bids Evaluation 11/07/2018 11/27/2018 21B1350 Recommendation for Award Letter 11/27/2018 0B1355 Contract Award (Purchase Order Approval) 11/28/2018 12/11/2018 14
ConstrucConstruction 10/16/2018 08/01/2019 290B1360 Construction Phase 10/16/2018 08/01/2019 290B1364 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 11/28/2018 12/18/2018 21B1365 Pre-Construction Meeting 12/19/2018 12/19/2018 1B1367 WASD Issues NTP (Pre-Const to NTP) 12/20/2018 02/02/2019 45B1369 WASD Issues NTP (PO to NTP) 12/12/2018 02/02/2019 53B1370 Construction NTP 02/03/2019 0B1400 Construction Operations 02/03/2019 08/01/2019 180B1402 Substantial Completion 08/01/2019 0
DesignerDesigner Construction Support Services 10/16/2018 08/01/2019 290B1410 Designer Construction Support Services 10/16/2018 08/01/2019 290
Project CProject Closeout 08/01/2019 11/29/2019 120B1445 Closeout Phase 08/01/2019 11/29/2019 120B1450 Issue SAC Letter 08/01/2019 0B1470 Final Release of Retainage - Construction Contract 08/01/2019 0B1480 Administrative Closeout 08/02/2019 11/29/2019 120B1490 Project Closed 11/29/2019 0
Basin 0194Basin 0194 04/08/2015 A 04/08/2015 A 1499
100047 FM100047 FM for Pump Station 0194 04/08/2015 A 04/08/2015 A 1499Project CProject Closeout 04/08/2015 A 04/08/2015 A 1499
A1535 Closeout Phase 04/08/2015 A 04/08/2015 A 1499A1540 Issue SAC Letter 04/08/2015 A 0A1548 Administrative Closeout 04/08/2015 A 04/08/2015 A 15A1550 Project Closed 04/08/2015 A 04/08/2015 A 10
Basin 0196Basin 0196 05/22/2015 A 09/29/2020 1794
100048-2 B100048-2 Basin 0196 Infiltration/Inflow Study and Repairs 05/22/2015 A 03/14/2016 A 212InfiltratioInfiltration/Inflow 05/22/2015 A 03/11/2016 A 121
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
90% Doral - BD Permit Review90% Doral - PWD Permit Submittal90% Doral - PWD Permit Review
90% CD PM Comments Evaluation CompletedMDWASD Union Concurrence Process
08/29/2018, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed
12/11/2018, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)
08/01/2019, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-ConstructionPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Construction NTPConstruction OperationsSubstantial Completion08/01/2019, Designer Constructi
Designer Construction Support S11/29/2019, Project Clo
Closeout PhaseIssue SAC LetterFinal Release of Retainage - Con
Administrative CloseouProject Closed
04/08/2015 A, Basin 0194
04/08/2015 A, 100047 FM for Pump Station 019404/08/2015 A, Project Closeout
Closeout PhaseIssue SAC Letter
Administrative CloseoutProject Closed
03/14/2016 A, 100048-2 Basin 0196 Infiltration/Inflow Study and Repairs03/11/2016 A, Infiltration/Inflow
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 45 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1000 Infiltration/Inflow Phase 05/22/2015 A 03/11/2016 A 121CIPP RepCIPP Repairs 05/22/2015 A 03/11/2016 A 20
B1005 CIPP Phase 05/22/2015 A 03/11/2016 A 20B1020 Issue NTP for CIPP Repairs 05/22/2015 A 0B1030 Conduct CIPP Repairs 07/22/2015 A 03/11/2016 A 20
Dig & ReDig & Replace Repairs 11/20/2015 A 02/23/2016 A 30B1105 Dig & Replace Phase 11/20/2015 A 02/23/2016 A 30B1120 Issue NTP for Dig & Replace Repairs 11/20/2015 A 0B1130 Conduct Dig & Replace Repairs 01/05/2016 A 02/23/2016 A 30
Project CProject Closeout 03/14/2016 A 03/14/2016 A 0B1175 Closeout Phase 03/14/2016 A 03/14/2016 A 0B1200 Project Closed 03/14/2016 A 0
100049 Pu100049 Pump Station 0196 Upgrade 08/01/2018 09/29/2020 791DesignDesign 08/01/2018 06/29/2019 333
B1000 Design Phase 08/01/2018 06/29/2019 333B1010 Prepare and Submit Design Package 08/01/2018 08/07/2018 7B1020 Engage Design Consultant 08/08/2018 09/04/2018 28B1022 TA Preparation 09/05/2018 09/18/2018 14B1024 TA Approval Process 09/19/2018 10/28/2018 40B1030 Issue Design NTP 10/29/2018 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/29/2018 06/01/2019 216
30% Des30% Design 10/29/2018 01/16/2019 80B1060 A/E Prepares 30% Construction Documents 10/29/2018 12/17/2018 50B1100 30% CDs Submittal 12/17/2018 0B1120 30% Review (MDWASD/PSIP Team) 12/18/2018 01/16/2019 30
60% Des60% Design 12/18/2018 01/30/2019 44B1130 A/E Prepares 60% Construction Documents 12/18/2018 01/16/2019 30B1140 60% CDs Submittal 01/16/2019 0B1160 60% Review (MDWASD/PSIP Team) 01/17/2019 01/30/2019 14
90% Des90% Design 01/17/2019 06/01/2019 136B1170 A/E Prepares 90% Construction Documents 01/17/2019 02/25/2019 40B1180 90% CDs Submittal 02/25/2019 0B1190 90% Review (MDWASD/PSIP Team) 02/26/2019 03/27/2019 30B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 03/28/2019 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 03/28/2019 05/11/2019 45B1220 90% RER (Building Department) Permit Submittal 05/12/2019 0B1230 90% RER (Building Department) Permit Review 05/12/2019 06/01/2019 21B1240 90% Municipality Permit Submittal (Pump Station) 05/12/2019 0B1250 90% Municipality Permit Review (Pump Station) 05/12/2019 06/01/2019 21B1260 90% CD PM Comments Evaluation Completed 06/01/2019 0
100% De100% Design 06/02/2019 06/29/2019 28B1270 A/E Prepares 100% Construction Documents 06/02/2019 06/15/2019 14B1280 100% CDs Submittal 06/15/2019 0B1290 100% Review (MDWASD/PSIP Team) 06/16/2019 06/29/2019 14B1300 Design Completed 06/29/2019 0
MDWASDMDWASD Procurement 06/30/2019 10/12/2019 104B1305 Procurement Phase 06/30/2019 10/12/2019 104B1310 Submit CDs to MDWASD Procurement Division 06/30/2019 0B1312 Bid Notice Preparation Period 07/01/2019 08/02/2019 33
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Infiltration/Inflow Phase03/11/2016 A, CIPP RepairsCIPP Phase
Issue NTP for CIPP RepairsConduct CIPP Repairs
02/23/2016 A, Dig & Replace RepairsDig & Replace Phase
Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs
03/14/2016 A, Project CloseoutCloseout Phase
Project Closed
06/29/2019, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval Process
Issue Design NTPFinal Engineering Report Review & Ap
01/16/2019, 30% Design
A/E Prepares 30% Construction Documents30% CDs Submittal
30% Review (MDWASD/PSIP Team)01/30/2019, 60% Design
A/E Prepares 60% Construction Documents60% CDs Submittal60% Review (MDWASD/PSIP Team)
06/01/2019, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (P
90% RER(DERM)FDEP Permit Review (90% RER (Building Department) Permit
90% RER (Building Department) Perm90% Municipality Permit Submittal (Pum
90% Municipality Permit Review (Pum90% CD PM Comments Evaluation C
06/29/2019, 100% Design
A/E Prepares 100% Construction Do100% CDs Submittal100% Review (MDWASD/PSIP TeamDesign Completed
10/12/2019, MDWASD ProProcurement Phase
Submit CDs to MDWASD ProcuremBid Notice Preparation Period
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 46 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1314 Bid Notice 08/02/2019 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 08/03/2019 08/16/2019 14B1320 Pre-Bid Conference 08/17/2019 08/17/2019 1B1322 Bidders Prepare Bids for Submittal 08/18/2019 09/07/2019 21B1330 Bids Submittal 09/07/2019 0B1340 MDWASD/PSIP Team Bids Evaluation 09/08/2019 09/28/2019 21B1350 Recommendation for Award Letter 09/28/2019 0B1355 Contract Award (Purchase Order Approval) 09/29/2019 10/12/2019 14
ConstrucConstruction 08/17/2019 06/01/2020 290B1360 Construction Phase 08/17/2019 06/01/2020 290B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 09/29/2019 10/19/2019 21B1364 Pre-Construction Meeting 10/20/2019 10/20/2019 1B1366 WASD Issues NTP (Pre-Const to NTP) 10/21/2019 12/04/2019 45B1369 WASD Issues NTP (PO to NTP) 10/13/2019 12/04/2019 53B1370 Construction NTP 12/05/2019 0B1400 Construction Operations 12/05/2019 06/01/2020 180B1402 Substantial Completion 06/01/2020 0
DesignerDesigner Construction Support Services 08/17/2019 06/01/2020 290B1410 Designer Construction Support Services 08/17/2019 06/01/2020 290
Project CProject Closeout 06/01/2020 09/29/2020 120B1445 Closeout Phase 06/01/2020 09/29/2020 120B1450 Issue SAC Letter 06/01/2020 0B1470 Final Release of Retainage - Construction Contract 06/01/2020 0B1480 Administrative Closeout 06/02/2020 09/29/2020 120B1490 Project Closed 09/29/2020 0
Basin 0201Basin 0201 05/21/2014 A 08/01/2016 A 1535
100050-2 B100050-2 Basin 0201 Infiltration/Inflow Study and Repairs 09/25/2014 A 08/03/2015 A 604InfiltratioInfiltration/Inflow 09/25/2014 A 07/31/2015 A 466
B1000 Infiltration/Inflow Phase 09/25/2014 A 07/31/2015 A 466Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 05/15/2015 A 156
B1005 SSES Phase 09/25/2014 A 05/15/2015 A 156B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct Flow Isolation & SSES 10/28/2014 A 04/16/2015 A 30B1040 Video Review 12/05/2014 A 05/15/2015 A 30
CIPP RepCIPP Repairs 04/17/2015 A 07/30/2015 A 38B1065 CIPP Phase 04/17/2015 A 07/30/2015 A 38B1080 Issue NTP for CIPP Repairs 04/17/2015 A 0B1090 Conduct CIPP Repairs 05/26/2015 A 06/11/2015 A 20B1100 Punch List 06/12/2015 A 07/30/2015 A 10
Dig & ReDig & Replace Repairs 05/18/2015 A 07/31/2015 A 30B1165 Dig & Replace Phase 05/18/2015 A 07/31/2015 A 30B1180 Issue NTP for Dig & Replace Repairs 05/18/2015 A 0B1190 Conduct Dig & Replace Repairs 07/30/2015 A 07/31/2015 A 30
Project CProject Closeout 08/03/2015 A 08/03/2015 A 0B1235 Closeout Phase 08/03/2015 A 08/03/2015 A 0B1260 Project Closed 08/03/2015 A 0
100051 Pu100051 Pump Station 0201 Upgrade 05/21/2014 A 08/01/2016 A 1523100% De100% Design 09/02/2014 A 09/02/2014 A 0
B1260 Design Completed 09/02/2014 A 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Bid NoticeMDWASD/PSIP Team Prepare
Pre-Bid ConferenceBidders Prepare Bids for Subm
Bids SubmittalMDWASD/PSIP Team Bids ERecommendation for Award Contract Award (Purchase
06/01/2
ConstruMDWASD/PSIP Team PrePre-Construction Meeting
WASD Issues NTP (PreWASD Issues NTP (PO
Construction NTPConstruSubstan06/01/2
Designe
Issue SAFinal Re
08/01/2016 A, Basin 0201
08/03/2015 A, 100050-2 Basin 0201 Infiltration/Inflow Study and Repairs07/31/2015 A, Infiltration/Inflow
Infiltration/Inflow Phase05/15/2015 A, Sanitary Sewer Evaluation Survey
SSES PhaseIssue NTP to SSES Contractor
Conduct Flow Isolation & SSESVideo Review
07/30/2015 A, CIPP Repairs
CIPP PhaseIssue NTP for CIPP Repairs
Conduct CIPP RepairsPunch List07/31/2015 A, Dig & Replace Repairs
Dig & Replace PhaseIssue NTP for Dig & Replace Repairs
Conduct Dig & Replace Repairs08/03/2015 A, Project Closeout
Closeout PhaseProject Closed
08/01/2016 A, 100051 Pump Station 0201 Upgrade09/02/2014 A, 100% Design
Design Completed
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 47 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
MDWASDMDWASD Procurement 05/21/2014 A 12/22/2014 A 346B1265 Procurement Phase 05/21/2014 A 12/22/2014 A 346B1270 Submit CDs to MDWASD Procurement Division 05/21/2014 A 0B1273 Bid Notice Preparation Period 05/22/2014 A 09/02/2014 A 23B1275 Bid Notice 09/03/2014 A 0B1277 MDWASD/PSIP Team Prepare for Pre-Bid Conferencce 09/04/2014 A 09/16/2014 A 10B1280 Pre-Bid Conference 09/17/2014 A 0B1285 Bidders Prepare Bids for Submittal 09/18/2014 A 10/06/2014 A 15B1290 Bids Submittal 10/07/2014 A 0B1300 MDWASD/PSIP Team Bids Evaluation 10/08/2014 A 11/05/2014 A 5B1310 Recommendation for Award Letter 11/06/2014 A 0B1312 Contract Award (Purchase Order Approval) 11/07/2014 A 12/22/2014 A 0
ConstrucConstruction 12/16/2014 A 09/05/2015 A 1381B1320 Construction Phase 12/16/2014 A 09/05/2015 A 1381B1323 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 12/23/2014 A 01/28/2015 A 15B1326 Pre-Construction Meeting 01/28/2015 A 0B1328 Permit Approvals 12/16/2014 A 03/27/2015 A 20B1329 WASD Issues NTP (PO to NTP) 12/23/2014 A 03/08/2015 A 53B1330 Construction NTP 03/09/2015 A 0B1340 Mobilization 03/09/2015 A 03/27/2015 A 30B1350 Construction Operations 03/09/2015 A 09/04/2015 A 121B1350 Original Construction Duration 03/09/2015 A 07/07/2015 A 121B1350 Change order #1 - Pump Delevery 07/08/2015 A 08/26/2015 A 121B1350 Change order #2 - Impeller Changes 08/27/2015 A 09/05/2015 A 121B1362 Substantial Completion 09/04/2015 A 0
DesignerDesigner Construction Support Services 03/09/2015 A 09/04/2015 A 140B1370 Designer Construction Support Services 03/09/2015 A 09/04/2015 A 140
ConstrucConstruction Close Out 08/06/2015 A 09/04/2015 A 15B1380 Commissioning 08/06/2015 A 09/04/2015 A 15B1390 Punch List 08/06/2015 A 09/04/2015 A 10
Project CProject Closeout 09/07/2015 A 08/01/2016 A 334B1405 Closeout Phase 09/07/2015 A 08/01/2016 A 334B1408 SAC Letter Issuance Period 09/07/2015 A 10/20/2015 A 30B1410 Issue SAC Letter 10/21/2015 A 0B1428 Final Release of Retainage Period 09/07/2015 A 05/06/2016 A 10B1430 Final Release of Retainage - Construction Contract 05/06/2016 A 0B1440 Administrative Closeout 09/07/2015 A 08/01/2016 A 30B1450 Project Closed 08/01/2016 A 0
Basin 0215Basin 0215 10/03/2017 A 12/05/2019 765
100052 Pu100052 Pump Station 0215 Upgrade 10/03/2017 A 12/05/2019 765DesignDesign 10/03/2017 A 09/04/2018 308
B1000 Design Phase 10/03/2017 A 09/04/2018 308B1010 Prepare and Submit Design Package 10/03/2017 A 10/03/2017 A 7B1020 Engage Design Consultant 10/04/2017 A 10/27/2017 A 28B1022 TA Preparation 10/28/2017 A 12/12/2017 A 14B1024 TA Approval Process 12/13/2017 A 02/02/2018 A 40B1030 Issue Design NTP 02/05/2018 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 02/05/2018 A 08/07/2018 186
30% Des30% Design 02/05/2018 A 04/23/2018 A 55
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
12/22/2014 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid Notice
MDWASD/PSIP Team Prepare for Pre-Bid ConferenccePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter
Contract Award (Purchase Order Approval)09/05/2015 A, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction Meeting
Pre-Construction MeetingPermit Approvals
WASD Issues NTP (PO to NTP)
Construction NTPMobilization
Construction OperationsOriginal Construction Duration
Change order #1 - Pump DeleveryChange order #2 - Impeller Changes
Substantial Completion09/04/2015 A, Designer Construction Support Services
Designer Construction Support Services09/04/2015 A, Construction Close Out
CommissioningPunch List
08/01/2016 A, Project Closeout
Closeout PhaseSAC Letter Issuance PeriodIssue SAC Letter
Final Release of Retainage Period
Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed
12/05/2019, Basin 021
12/05/2019, 100052 P09/04/2018, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval Process
Issue Design NTPFinal Engineering Report Review & Approval (MDWASD/PSIP
04/23/2018 A, 30% Design
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 48 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1060 A/E Prepares 30% Construction Documents 02/05/2018 A 04/06/2018 A 50B1100 30% CDs Submittal 04/06/2018 A 0B1120 30% Review (MDWASD/PSIP Team) 04/07/2018 A 04/23/2018 A 18
90% Des90% Design 04/25/2018 A 08/07/2018 113B1170 A/E Prepares 90% Construction Documents 04/25/2018 A 05/22/2018 A 29B1180 90% CDs Submittal 05/22/2018 A 0B1190 90% Review (MDWASD/PSIP Team) 05/23/2018 A 06/05/2018 A 16B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 06/06/2018 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 06/06/2018 A 07/17/2018 A 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 07/18/2018 A 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 07/18/2018 A 08/07/2018 21B1260 90% CD PM Comments Evaluation Completed 08/07/2018 0
100% De100% Design 08/08/2018 09/04/2018 28B1270 A/E Prepares 100% Construction Documents 08/08/2018 08/21/2018 14B1280 100% CDs Submittal 08/21/2018 0B1290 100% Review (MDWASD/PSIP Team) 08/22/2018 09/04/2018 14B1300 Design Completed 09/04/2018 0
MDWASDMDWASD Procurement 09/04/2018 12/17/2018 104B1305 Procurement Phase 09/04/2018 12/17/2018 104B1310 Submit CDs to MDWASD Procurement Division 09/04/2018 0B1312 Bid Notice Preparation Period 09/05/2018 10/07/2018 33B1314 Bid Notice 10/07/2018 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 10/08/2018 10/21/2018 14B1320 Pre-Bid Conference 10/22/2018 10/22/2018 1B1322 Bidders Prepare Bids for Submittal 10/23/2018 11/12/2018 21B1330 Bids Submittal 11/12/2018 0B1340 MDWASD/PSIP Team Bids Evaluation 11/13/2018 12/03/2018 21B1350 Recommendation for Award Letter 12/03/2018 0B1355 Contract Award (Purchase Order Approval) 12/04/2018 12/17/2018 14
ConstrucConstruction 10/22/2018 08/07/2019 290B1360 Construction Phase 10/22/2018 08/07/2019 290B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 12/04/2018 12/24/2018 21B1364 Pre-Construction Meeting 12/25/2018 12/25/2018 1B1366 WASD Issues NTP (Pre-Const to NTP) 12/26/2018 02/08/2019 45B1368 WASD Issues NTP (PO to NTP) 12/18/2018 02/08/2019 53B1370 Construction NTP 02/09/2019 0B1400 Construction Operations 02/09/2019 08/07/2019 180B1402 Substantial Completion 08/07/2019 0
DesignerDesigner Construction Support Services 10/22/2018 08/07/2019 290B1410 Designer Construction Support Services 10/22/2018 08/07/2019 290
Project CProject Closeout 08/07/2019 12/05/2019 120B1445 Closeout Phase 08/07/2019 12/05/2019 120B1450 Issue SAC Letter 08/07/2019 0B1470 Final Release of Retainage - Construction Contract 08/07/2019 0B1480 Administrative Closeout 08/08/2019 12/05/2019 120B1490 Project Closed 12/05/2019 0
Basin 0309Basin 0309 01/11/2012 A 08/01/2018 1225
100053 Pu100053 Pump Station 0309 Upgrade 01/11/2012 A 08/01/2018 1225DesignDesign 01/11/2012 A 09/25/2017 A 1225
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
A/E Prepares 30% Construction Documents30% CDs Submittal
30% Review (MDWASD/PSIP Team)08/07/2018, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)
90% RER(DERM)FDEP Permit Submittal (Pump Station)90% RER(DERM)FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)90% RER(Building Dept) Permit Review (Pump Station)90% CD PM Comments Evaluation Completed
09/04/2018, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed
12/17/2018, MDWASD ProcurementProcurement Phase
Submit CDs to MDWASD Procurement DivisionBid Notice Preparation Period
Bid NoticeMDWASD/PSIP Team Prepare for Pre-Bid Conference
Pre-Bid ConferenceBidders Prepare Bids for Submittal
Bids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)
08/07/2019, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-ConstructionPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Construction NTPConstruction OperationsSubstantial Completion08/07/2019, Designer Construct
Designer Construction Support S12/05/2019, Project ClCloseout Phase
Issue SAC LetterFinal Release of Retainage - Co
Administrative CloseouProject Closed
08/01/2018, Basin 0309
08/01/2018, 100053 Pump Station 0309 Upgrade09/25/2017 A, Design
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 49 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1000 Design Phase 01/11/2012 A 09/25/2017 A 1225B1028 Initial Moratorium 01/11/2012 A 05/19/2014 A 860B1030 Remedial Action Plan (RAP) 05/20/2014 A 09/25/2017 A 1225
Project CProject Closeout 11/12/2017 A 08/01/2018 489B1445 Closeout Phase 11/12/2017 A 08/01/2018 489B1450 Issue SAC Letter 11/12/2017 A 0B1480 Administrative Closeout 11/13/2017 A 08/01/2018 120B1490 Project Closed 08/01/2018 0
New EPS-New EPS-2 08/01/2018 09/28/2020 790
100260 Pu100260 Pump Station 0319 Upgrade 08/01/2018 09/28/2020 790DesignDesign 08/01/2018 06/29/2019 333
B1000 Design Phase 08/01/2018 06/29/2019 333B1005 Prepare and Submit Design Package 08/01/2018 08/07/2018 7B1010 Engage Design Consultant 08/08/2018 09/04/2018 28B1012 TA Preparation 09/05/2018 09/18/2018 14B1014 TA Approval 09/19/2018 10/28/2018 40B1030 Issue Design NTP 10/29/2018 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/29/2018 06/01/2019 216
30% Des30% Design 10/29/2018 01/16/2019 80B1060 A/E Prepares 30% Construction Documents 10/29/2018 12/17/2018 50B1100 30% CDs Submittal 12/17/2018 0B1120 30% Review (MDWASD/PSIP Team) 12/18/2018 01/16/2019 30
60% Des60% Design 12/18/2018 01/30/2019 44B1130 A/E Prepares 60% Construction Documents 12/18/2018 01/16/2019 30B1140 60% CDs Submittal 01/16/2019 0B1160 60% Review (MDWASD/PSIP Team) 01/17/2019 01/30/2019 14
90% Des90% Design 01/17/2019 06/01/2019 136B1170 A/E Prepares 90% Construction Documents 01/17/2019 02/25/2019 40B1180 90% CDs Submittal 02/25/2019 0B1190 90% Review (MDWASD/PSIP Team) 02/26/2019 03/27/2019 30B1200 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 03/28/2019 0B1210 90% RER(DERM)/FDEP Permit Review (Pump Station) 03/28/2019 05/11/2019 45B1220 90% RER (Building Dept Permit Submittal (Pump Station) 05/12/2019 0B1230 90% RER (Building Dept) Permit Review (Pump Station) 05/12/2019 06/01/2019 21B1240 90% PWWMD Permit Submittal (Pump Station) 05/12/2019 0B1250 90% PWWMD Permit Review (Pump Station) 05/12/2019 06/01/2019 21B1260 90% CD PM Comments Evaluation Completed 06/01/2019 0
100% De100% Design 06/02/2019 06/29/2019 28B1270 A/E Prepares 100% Construction Documents 06/02/2019 06/15/2019 14B1280 100% CDs Submittal 06/15/2019 0B1290 100% Review (MDWASD/PSIP Team) 06/16/2019 06/29/2019 14B1300 Design Completed 06/29/2019 0
MDWASDMDWASD Procurement 06/29/2019 10/11/2019 104B1305 Procurement Phase 06/29/2019 10/11/2019 104B1310 Submit CDs to MDWASD Procurement Division 06/29/2019 0B1312 Bid Notice Preparation Period 06/30/2019 08/01/2019 33B1314 Bid Notice 08/01/2019 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conferencce 08/02/2019 08/15/2019 14B1320 Pre-Bid Conference 08/16/2019 08/16/2019 1
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Design PhaseInitial Moratorium
Remedial Action Plan (RAP)08/01/2018, Project CloseoutCloseout Phase
Issue SAC LetterAdministrative CloseoutProject Closed
06/29/2019, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA ApprovalIssue Design NTP
Final Engineering Report Review & Ap01/16/2019, 30% Design
A/E Prepares 30% Construction Documents30% CDs Submittal
30% Review (MDWASD/PSIP Team)01/30/2019, 60% Design
A/E Prepares 60% Construction Documents60% CDs Submittal60% Review (MDWASD/PSIP Team)
06/01/2019, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)/FDEP Permit Submittal (P
90% RER(DERM)/FDEP Permit Review 90% RER (Building Dept Permit Submit
90% RER (Building Dept) Permit Revie90% PWWMD Permit Submittal (Pump
90% PWWMD Permit Review (Pump 90% CD PM Comments Evaluation C
06/29/2019, 100% Design
A/E Prepares 100% Construction Do100% CDs Submittal100% Review (MDWASD/PSIP TeamDesign Completed
10/11/2019, MDWASD Pro
Procurement PhaseSubmit CDs to MDWASD Procurem
Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare Pre-Bid Conference
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 50 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1328 Bidders Prepare Bids for Submittal 08/17/2019 09/06/2019 21B1330 Bids Submittal 09/06/2019 0B1340 MDWASD/PSIP Team Bids Evaluation 09/07/2019 09/27/2019 21B1350 Recommendation for Award Letter 09/27/2019 0B1355 Contract Award (Purchase Order Approval) 09/28/2019 10/11/2019 14
ConstrucConstruction 08/16/2019 05/31/2020 290B1357 Construction Phase 08/16/2019 05/31/2020 290B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 09/28/2019 10/18/2019 21B1364 Pre-Construction Meeting 10/19/2019 10/19/2019 1B1366 WASD Issues NTP (Pre-Const to NTP) 10/20/2019 12/03/2019 45B1369 WASD Issues NTP (PO to NTP) 10/12/2019 12/03/2019 53B1370 Construction NTP 12/04/2019 0B1390 Construction Operations 12/04/2019 05/31/2020 180B1395 Substantial Completion 05/31/2020 0
DesignerDesigner Construction Support Services 08/16/2019 05/31/2020 290B1397 Designer Construction Support Services 08/16/2019 05/31/2020 290
Project CProject Closeout 05/31/2020 09/28/2020 120B1425 Closeout Phase 05/31/2020 09/28/2020 120B1430 Issue SAC Letter 05/31/2020 0B1450 Final Release of Retainage - Construction Contract 05/31/2020 0B1460 Administrative Closeout 06/01/2020 09/28/2020 120B1470 Project Closed 09/28/2020 0
Basin 0331Basin 0331 09/25/2014 A 08/01/2018 1521
100054-2 B100054-2 Basin 0331 Infiltration/Inflow Study and Repairs 09/25/2014 A 05/16/2016 A 632InfiltratioInfiltration/Inflow 09/25/2014 A 05/13/2016 A 518
B1000 Infiltration/Inflow Phase 09/25/2014 A 05/13/2016 A 518Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 06/19/2015 A 212
B1005 SSES Phase 09/25/2014 A 06/19/2015 A 212B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 03/20/2015 A 06/04/2015 A 30B1040 Video Review 06/05/2015 A 06/19/2015 A 30
CIPP RepCIPP Repairs 09/17/2015 A 05/13/2016 A 49B1065 CIPP Phase 09/17/2015 A 05/13/2016 A 49B1080 Issue NTP for CIPP Repairs 09/17/2015 A 0B1090 Conduct CIPP Repairs 11/23/2015 A 05/13/2016 A 20
ManholeManhole Repairs 10/30/2015 A 03/10/2016 A 47B1115 Manhole Phase 10/30/2015 A 03/10/2016 A 47B1130 Issue NTP for Manhole Repairs 10/30/2015 A 0B1140 Conduct Manhole Repairs 03/07/2016 A 03/10/2016 A 20
Project CProject Closeout 05/16/2016 A 05/16/2016 A 0B1235 Closeout Phase 05/16/2016 A 05/16/2016 A 0B1260 Project Closed 05/16/2016 A 0
100222 Pu100222 Pump Station 0331 Upgrade 10/08/2014 A 08/01/2018 1415DesignDesign 10/08/2014 A 06/17/2016 A 515
B1000 Design Phase 10/08/2014 A 06/17/2016 A 515B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 10/08/2014 A 10/08/2014 A 5B1020 Engage Design Consultant 10/09/2014 A 02/02/2015 A 20B1030 Issue Design NTP 02/03/2015 A 0B1032 TA Rev 1 Approval Process 03/21/2016 A 05/12/2016 A 20
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Bidders Prepare Bids for SubmBids Submittal
MDWASD/PSIP Team Bids ERecommendation for Award Contract Award (Purchase O
05/31/2
ConstruMDWASD/PSIP Team PrePre-Construction Meeting
WASD Issues NTP (PreWASD Issues NTP (POConstruction NTP
ConstruSubstan05/31/2
Designe
Issue SAFinal Re
08/01/2018, Basin 0331
05/16/2016 A, 100054-2 Basin 0331 Infiltration/Inflow Study and Repairs05/13/2016 A, Infiltration/Inflow
Infiltration/Inflow Phase06/19/2015 A, Sanitary Sewer Evaluation SurveySSES Phase
Issue NTP to SSES ContractorConduct SSESVideo Review
05/13/2016 A, CIPP RepairsCIPP Phase
Issue NTP for CIPP RepairsConduct CIPP Repairs
03/10/2016 A, Manhole RepairsManhole Phase
Issue NTP for Manhole RepairsConduct Manhole Repairs
05/16/2016 A, Project CloseoutCloseout Phase
Project Closed08/01/2018, 100222 Pump Station 0331 Upgrade
06/17/2016 A, Design
Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book
Engage Design ConsultantIssue Design NTP
TA Rev 1 Approval Process
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 51 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1040 A/E Develops and Submits Final Engineering Report 02/03/2015 A 05/04/2016 A 125B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 02/03/2015 A 03/09/2016 A 85
30% Des30% Design 02/03/2015 A 10/27/2015 A 251B1060 A/E Prepares 30% Construction Documents 02/03/2015 A 03/19/2015 A 30B1070 Geotechnical Engineering Services 02/03/2015 A 03/31/2015 A 20B1080 Surveying Services 02/03/2015 A 03/31/2015 A 15B1082 A/E & MDWASD/PSIP Team and Town of Miami Lakes Easeme 03/23/2015 A 07/21/2015 A 20B1084 A/E Prepares 30% Construction Documents (Resume Design) 07/22/2015 A 09/25/2015 A 11B1100 30% CDs Submittal 09/28/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 09/29/2015 A 10/27/2015 A 10
90% Des90% Design 09/29/2015 A 05/04/2016 A 220B1170 A/E Prepares 90% Construction Documents 09/29/2015 A 12/23/2015 A 26B1180 90% CDs Submittal 12/23/2015 A 0B1190 90% Review (MDWASD/PSIP Team) 12/24/2015 A 03/09/2016 A 10B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 03/09/2016 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 03/09/2016 A 03/14/2016 A 15B1240 90% Miami Lakes - BD Permit Submittal (Pump Station) 03/23/2016 A 0B1250 90% Miami Lakes - BD Permit Review (Pump Station) 03/23/2016 A 05/04/2016 A 15B1260 90% CD PM Comments Evaluation Completed 05/04/2016 A 0
100% De100% Design 05/05/2016 A 06/17/2016 A 29B1270 A/E Prepares 100% Construction Documents 05/05/2016 A 06/17/2016 A 11B1280 100% CDs Submittal 06/17/2016 A 0B1290 100% Review (MDWASD/PSIP Team) 05/05/2016 A 06/17/2016 A 10B1300 Design Completed 06/17/2016 A 0
MDWASDMDWASD Procurement 04/05/2016 A 07/12/2016 A 77B1305 Procurement Phase 04/05/2016 A 07/12/2016 A 77B1310 Submit CDs to MDWASD Procurement Division 04/05/2016 A 0B1312 Bid Notice Preparation Period 04/06/2016 A 04/14/2016 A 23B1314 Bid Notice 04/15/2016 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 04/18/2016 A 04/21/2016 A 10B1320 Pre-Bid Conference 04/22/2016 A 04/22/2016 A 1B1328 Bidders Prepare Bids for Submittal 04/25/2016 A 05/26/2016 A 15B1330 Bids Submittal 05/27/2016 A 0B1340 MDWASD/PSIP Team Bids Evaluation 05/30/2016 A 06/08/2016 A 15B1350 Recommendation for Award Letter 06/08/2016 A 0B1355 Contract Award (Purchase Order Approval) 06/09/2016 A 07/12/2016 A 10
ConstrucConstruction 04/22/2016 A 11/17/2017 A 915B1360 Construction Phase 04/22/2016 A 11/17/2017 A 915B1364 MDAD/PSIP Team Prepare for Pre-Construction Meeting 06/09/2016 A 07/07/2016 A 15B1365 Pre-Construction Meeting 07/08/2016 A 07/08/2016 A 1B1369 WASD Issues NTP (PO to NTP) 07/13/2016 A 07/31/2016 A 53B1370 Construction NTP 08/01/2016 A 0B1400 Construction Operations 08/01/2016 A 11/17/2017 A 278B1400 Original Construction Duration 08/01/2016 A 12/29/2016 A 278B1400 Change Order #1 - FPL 12/30/2016 A 02/14/2017 A 278B1400 Change Order #2 - Diving Plan Approval & Hurricane Irma 02/15/2017 A 05/06/2017 A 278B1400 Change Order #3 - FPL 05/07/2017 A 10/11/2017 A 278B1402 Substantial Completion 11/17/2017 A 0
DesignerDesigner Construction Support Services 04/22/2016 A 11/17/2017 A 263
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
10/27/2015 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services
A/E & MDWASD/PSIP Team and Town of Miami Lakes Easement NegotiationsA/E Prepares 30% Construction Documents (Resume Design)30% CDs Submittal
30% Review (MDWASD/PSIP Team)05/04/2016 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)90% RER(DERM)FDEP Permit Review (Pump Station)90% Miami Lakes - BD Permit Submittal (Pump Station)
90% Miami Lakes - BD Permit Review (Pump Station)90% CD PM Comments Evaluation Completed
06/17/2016 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed
07/12/2016 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)
11/17/2017 A, Construction
Construction PhaseMDAD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction MeetingWASD Issues NTP (PO to NTP)
Construction NTPConstruction Operations
Original Construction DurationChange Order #1 - FPL
Change Order #2 - Diving Plan Approval & Hurricane IrmaChange Order #3 - FPL
Substantial Completion11/17/2017 A, Designer Construction Support Services
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 52 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1410 Designer Construction Support Services 04/22/2016 A 11/17/2017 A 263Project CProject Closeout 11/18/2017 A 08/01/2018 212
B1445 Closeout Phase 11/18/2017 A 08/01/2018 212B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 11/18/2017 A 08/01/2018 120B1490 Project Closed 08/01/2018 0
Basin 0334Basin 0334 06/02/2014 A 08/01/2018 1646
100056 FM100056 FM for Pump Station 0334 06/23/2014 A 05/21/2015 A 386100% De100% Design 07/10/2014 A 07/10/2014 A 0
B1290 Design Completed 07/10/2014 A 0MDWASDMDWASD Procurement 06/23/2014 A 10/02/2014 A 167
B1295 Procurement Phase 06/23/2014 A 10/02/2014 A 167B1300 Submit CDs to MDWASD Procurement Division 06/23/2014 A 0B1310 Pre-Bid Conference 07/15/2014 A 0B1320 Bids Submittal 09/03/2014 A 0B1330 MDWASD Bids Evaluation 09/04/2014 A 10/02/2014 A 10B1340 Contractor Selected 09/04/2014 A 0
ConstrucConstruction 10/03/2014 A 05/21/2015 A 173B1350 Construction Phase 10/03/2014 A 05/21/2015 A 173B1360 Construction NTP 02/02/2015 A 0B1370 Mobilization 02/02/2015 A 02/09/2015 A 40B1380 Permit Approvals 10/03/2014 A 02/01/2015 A 20B1390 Construction Operations 02/02/2015 A 05/20/2015 A 128B1392 Substantial Completion 05/20/2015 A 0
DesignerDesigner Construction Services 02/02/2015 A 05/21/2015 A 130B1400 Designer Construction Support Services 02/02/2015 A 05/21/2015 A 130
ConstrucConstruction Close Out 05/21/2015 A 05/21/2015 A 10B1420 Punch List 05/21/2015 A 05/21/2015 A 10
100057 Pu100057 Pump Station 0334 Upgrade 06/02/2014 A 08/01/2018 1646DesignDesign 06/17/2014 A 06/17/2014 A 0
B1250 Design Phase 06/17/2014 A 06/17/2014 A 0100% De100% Design 06/17/2014 A 06/17/2014 A 0
B1260 Design Completed 06/17/2014 A 0MDWASDMDWASD Procurement 06/02/2014 A 10/07/2014 A 112
B1265 Procurement Phase 06/02/2014 A 10/07/2014 A 112B1270 Submit CDs to MDWASD Procurement Division 06/02/2014 A 0B1280 Pre-Bid Conference 07/02/2014 A 0B1290 Bids Submittal 07/10/2014 A 0B1300 MDWASD Bid Evaluation 07/11/2014 A 08/14/2014 A 10B1310 Recommendation for Award Letter 08/14/2014 A 0B1460 Contract Award (Purchase Order Approval) 08/14/2014 A 10/07/2014 A 0
ConstrucConstruction 08/15/2014 A 10/31/2016 A 1416B1320 Construction Phase 08/15/2014 A 10/31/2016 A 1416B1328 WASD Issues NTP (PO to NTP) 10/08/2014 A 02/04/2015 A 53B1330 Construction NTP 02/05/2015 A 0B1340 Mobilization 02/05/2015 A 02/26/2015 A 40B1350 Permit Approvals 08/15/2014 A 02/26/2015 A 20B1360 Construction Operations 02/06/2015 A 12/30/2015 A 126
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Designer Construction Support Services08/01/2018, Project Closeout
Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction ContractAdministrative CloseoutProject Closed08/01/2018, Basin 0334
05/21/2015 A, 100056 FM for Pump Station 033407/10/2014 A, 100% Design
Design Completed10/02/2014 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Pre-Bid ConferenceBids Submittal
MDWASD Bids EvaluationContractor Selected
05/21/2015 A, Construction
Construction PhaseConstruction NTP
MobilizationPermit Approvals
Construction OperationsSubstantial Completion
05/21/2015 A, Designer Construction Services
Designer Construction Support Services05/21/2015 A, Construction Close Out
Punch List08/01/2018, 100057 Pump Station 0334 Upgrade
06/17/2014 A, Design
Design Phase06/17/2014 A, 100% Design
Design Completed10/07/2014 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Pre-Bid ConferenceBids Submittal
MDWASD Bid EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)
10/31/2016 A, Construction
Construction PhaseWASD Issues NTP (PO to NTP)
Construction NTPMobilization
Permit ApprovalsConstruction Operations
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 53 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1360 Original Construction Duration 02/06/2015 A 08/04/2015 A 126B1360 Change Order #1 - Shop Drawing Approval 08/05/2015 A 11/06/2015 A 126B1360 Change Order #2 - Sheet Pilling, FPL, Weather 11/07/2015 A 12/24/2015 A 126B1362 Substantial Completion 12/30/2015 A 0
DesignerDesigner Construction Support Services 02/05/2015 A 10/31/2016 A 130B1370 Designer Construction Support Services 02/05/2015 A 10/31/2016 A 130
ConstrucConstruction Close Out 12/31/2015 A 10/31/2016 A 15B1380 Commissioning 12/31/2015 A 02/29/2016 A 15B1390 Punch List 12/31/2015 A 10/31/2016 A 10
Project CProject Closeout 12/31/2015 A 08/01/2018 944B1405 Closeout Phase 12/31/2015 A 08/01/2018 944B1410 Issue SAC Letter 02/11/2016 A 0B1430 Final Release of Retainage - Construction Contract 08/01/2018 0B1440 Administrative Closeout 12/31/2015 A 08/01/2018 120B1450 Project Closed 08/01/2018 0
100055 Ba100055 Basin 0334 Infiltration/Inflow Study and Repairs 04/17/2015 A 11/12/2015 A 412InfiltratioInfiltration/Inflow 04/17/2015 A 11/11/2015 A 345
B1000 Infiltration/Inflow Phase 04/17/2015 A 11/11/2015 A 345CIPP RepCIPP Repairs 04/17/2015 A 07/22/2015 A 86
B1070 CIPP Phase 04/17/2015 A 07/22/2015 A 86B1090 Issue NTP for CIPP Repairs 04/17/2015 A 0B1100 Conduct CIPP Repairs 06/15/2015 A 07/22/2015 A 86
ManholeManhole Repairs 10/02/2015 A 11/11/2015 A 117B1110 Manhole Phase 10/02/2015 A 11/11/2015 A 117B1130 Issue NTP for Manhole Repairs 10/02/2015 A 0B1140 Conduct Manhole Repairs 11/11/2015 A 11/11/2015 A 117
Dig & ReDig & Replace Repairs 05/18/2015 A 10/07/2015 A 30B1160 Dig & Replace Phase 05/18/2015 A 10/07/2015 A 30B1180 Issue NTP for Dig & Replace Repairs 05/18/2015 A 0B1190 Conduct Dig & Replace Repairs 10/07/2015 A 10/07/2015 A 30
Project CProject Closeout 11/12/2015 A 11/12/2015 A 0B1250 Closeout Phase 11/12/2015 A 11/12/2015 A 0B1280 Project Closed 11/12/2015 A 0
New EPS-New EPS-3 08/01/2018 09/28/2020 790
100261 Pu100261 Pump Station 0335 Upgrade 08/01/2018 09/28/2020 790DesignDesign 08/01/2018 06/29/2019 333
B1000 Design Phase 08/01/2018 06/29/2019 333B1005 Prepare and Submit Design Package 08/01/2018 08/07/2018 7B1010 Engage Design Consultant 08/08/2018 09/04/2018 28B1012 TA Preparation 09/05/2018 09/18/2018 14B1014 TA Approval 09/19/2018 10/28/2018 40B1030 Issue Design NTP 10/29/2018 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/29/2018 06/01/2019 216
30% Des30% Design 10/29/2018 01/16/2019 80B1060 A/E Prepares 30% Construction Documents 10/29/2018 12/17/2018 50B1100 30% CDs Submittal 12/17/2018 0B1120 30% Review (MDWASD/PSIP Team) 12/18/2018 01/16/2019 30
60% Des60% Design 12/18/2018 01/30/2019 44B1130 A/E Prepares 60% Construction Documents 12/18/2018 01/16/2019 30
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Original Construction DurationChange Order #1 - Shop Drawing Approval
Change Order #2 - Sheet Pilling, FPL, Weather
Substantial Completion10/31/2016 A, Designer Construction Support Services
Designer Construction Support Services10/31/2016 A, Construction Close Out
CommissioningPunch List
08/01/2018, Project Closeout
Closeout PhaseIssue SAC Letter
Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed
11/12/2015 A, 100055 Basin 0334 Infiltration/Inflow Study and Repairs11/11/2015 A, Infiltration/InflowInfiltration/Inflow Phase
07/22/2015 A, CIPP RepairsCIPP Phase
Issue NTP for CIPP RepairsConduct CIPP Repairs
11/11/2015 A, Manhole RepairsManhole Phase
Issue NTP for Manhole RepairsConduct Manhole Repairs
10/07/2015 A, Dig & Replace RepairsDig & Replace Phase
Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs
11/12/2015 A, Project CloseoutCloseout Phase
Project Closed
06/29/2019, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA ApprovalIssue Design NTP
Final Engineering Report Review & Ap01/16/2019, 30% Design
A/E Prepares 30% Construction Documents30% CDs Submittal
30% Review (MDWASD/PSIP Team)01/30/2019, 60% Design
A/E Prepares 60% Construction Documents
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 54 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1140 60% CDs Submittal 01/16/2019 0B1160 60% Review (MDWASD/PSIP Team) 01/17/2019 01/30/2019 14
90% Des90% Design 01/17/2019 06/01/2019 136B1170 A/E Prepares 90% Construction Documents 01/17/2019 02/25/2019 40B1180 90% CDs Submittal 02/25/2019 0B1190 90% Review (MDWASD/PSIP Team) 02/26/2019 03/27/2019 30B1200 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 03/28/2019 0B1210 90% RER(DERM)/FDEP Permit Review (Pump Station) 03/28/2019 05/11/2019 45B1220 90% RER (Building Dept Permit Submittal (Pump Station) 05/12/2019 0B1230 90% RER (Building Dept) Permit Review (Pump Station) 05/12/2019 06/01/2019 21B1240 90% PWWMD Permit Submittal (Pump Station) 05/12/2019 0B1250 90% PWWMD Permit Review (Pump Station) 05/12/2019 06/01/2019 21B1260 90% CD PM Comments Evaluation Completed 06/01/2019 0
100% De100% Design 06/02/2019 06/29/2019 28B1270 A/E Prepares 100% Construction Documents 06/02/2019 06/15/2019 14B1280 100% CDs Submittal 06/15/2019 0B1290 100% Review (MDWASD/PSIP Team) 06/16/2019 06/29/2019 14B1300 Design Completed 06/29/2019 0
MDWASDMDWASD Procurement 06/29/2019 10/11/2019 104B1305 Procurement Phase 06/29/2019 10/11/2019 104B1310 Submit CDs to MDWASD Procurement Division 06/29/2019 0B1312 Bid Notice Preparation Period 06/30/2019 08/01/2019 33B1314 Bid Notice 08/01/2019 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conferencce 08/02/2019 08/15/2019 14B1320 Pre-Bid Conference 08/16/2019 08/16/2019 1B1328 Bidders Prepare Bids for Submittal 08/17/2019 09/06/2019 21B1330 Bids Submittal 09/06/2019 0B1340 MDWASD/PSIP Team Bids Evaluation 09/07/2019 09/27/2019 21B1350 Recommendation for Award Letter 09/27/2019 0B1355 Contract Award (Purchase Order Approval) 09/28/2019 10/11/2019 14
ConstrucConstruction 08/16/2019 05/31/2020 290B1357 Construction Phase 08/16/2019 05/31/2020 290B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 09/28/2019 10/18/2019 21B1364 Pre-Construction Meeting 10/19/2019 10/19/2019 1B1366 WASD Issues NTP (Pre-Const to NTP) 10/20/2019 12/03/2019 45B1369 WASD Issues NTP (PO to NTP) 10/12/2019 12/03/2019 53B1370 Construction NTP 12/04/2019 0B1390 Construction Operations 12/04/2019 05/31/2020 180B1395 Substantial Completion 05/31/2020 0
DesignerDesigner Construction Support Services 08/16/2019 05/31/2020 290B1397 Designer Construction Support Services 08/16/2019 05/31/2020 290
Project CProject Closeout 05/31/2020 09/28/2020 120B1425 Closeout Phase 05/31/2020 09/28/2020 120B1430 Issue SAC Letter 05/31/2020 0B1450 Final Release of Retainage - Construction Contract 05/31/2020 0B1460 Administrative Closeout 06/01/2020 09/28/2020 120B1470 Project Closed 09/28/2020 0
Basin 0336Basin 0336 09/25/2014 A 01/11/2019 1322
100058 Pu100058 Pump Station 0336 Upgrade 01/11/2016 A 01/11/2019 1106
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
60% CDs Submittal60% Review (MDWASD/PSIP Team)
06/01/2019, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)/FDEP Permit Submittal (P
90% RER(DERM)/FDEP Permit Review 90% RER (Building Dept Permit Submit
90% RER (Building Dept) Permit Revie90% PWWMD Permit Submittal (Pump
90% PWWMD Permit Review (Pump 90% CD PM Comments Evaluation C
06/29/2019, 100% Design
A/E Prepares 100% Construction Do100% CDs Submittal100% Review (MDWASD/PSIP TeamDesign Completed
10/11/2019, MDWASD Pro
Procurement PhaseSubmit CDs to MDWASD Procurem
Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare Pre-Bid Conference
Bidders Prepare Bids for SubmBids Submittal
MDWASD/PSIP Team Bids ERecommendation for Award Contract Award (Purchase O
05/31/2
ConstruMDWASD/PSIP Team PrePre-Construction Meeting
WASD Issues NTP (PreWASD Issues NTP (POConstruction NTP
ConstruSubstan05/31/2
Designe
Issue SAFinal Re
01/11/2019, Basin 0336
01/11/2019, 100058 Pump Station 0336 Upgrad
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 55 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
DesignDesign 01/11/2016 A 08/16/2017 A 591B1000 Design Phase 01/11/2016 A 08/16/2017 A 591B1010 Prepare and Submit Design Package 01/11/2016 A 01/11/2016 A 5B1020 Engage Design Consultant 01/11/2016 A 01/22/2016 A 20B1022 TA Preparation 01/25/2016 A 01/25/2016 A 1B1024 TA Approval Process 01/26/2016 A 04/04/2016 A 20B1030 Issue Design NTP 04/26/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 04/26/2016 A 11/07/2016 A 85
30% Des30% Design 04/27/2016 A 06/16/2016 A 46B1060 A/E Prepares 30% Construction Documents 04/27/2016 A 04/29/2016 A 30B1070 Geotechnical Engineering Services 04/27/2016 A 04/29/2016 A 20B1080 Surveying Services 04/27/2016 A 04/29/2016 A 15B1100 30% CDs Submittal 04/29/2016 A 0B1120 30% Review (MDWASD/PSIP Team) 05/02/2016 A 06/16/2016 A 10
90% Des90% Design 05/02/2016 A 06/28/2017 A 457B1170 A/E Prepares 90% Construction Documents 05/02/2016 A 09/19/2016 A 20B1180 90% CDs Submittal 09/19/2016 A 0B1190 90% Review (MDWASD/PSIP Team) 09/20/2016 A 11/07/2016 A 15B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 03/10/2017 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 03/01/2017 A 05/30/2017 A 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 05/30/2017 A 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 05/30/2017 A 05/31/2017 A 21B1240 90% Miami Lakes - BD Permit Submittal (Pump Station) 06/05/2017 A 0B1250 90% Miami Lakes - BD Permit Review (Pump Station) 06/05/2017 A 06/28/2017 A 21B1260 90% CD PM Comments Evaluation Completed 06/28/2017 A 0B1262 MDWASD Union Concurrence Process 04/26/2017 A 06/20/2017 A 30
100% De100% Design 06/29/2017 A 08/16/2017 A 44B1270 A/E Prepares 100% Construction Documents 06/29/2017 A 08/14/2017 A 10B1280 100% CDs Submittal 08/14/2017 A 0B1290 100% Review (MDWASD/PSIP Team) 08/14/2017 A 08/16/2017 A 10B1300 Design Completed 08/16/2017 A 0
MDWASDMDWASD Procurement 08/16/2017 A 12/19/2017 A 112B1305 Procurement Phase 08/16/2017 A 12/19/2017 A 112B1310 Submit CDs to MDWASD Procurement Division 08/16/2017 A 0B1312 Bid Notice Preparation Period 08/17/2017 A 08/23/2017 A 33B1314 Bid Notice 08/23/2017 A 0B1316 MDADWAD/PSIP Team Prepare for Pre-Bid Conference 08/24/2017 A 09/26/2017 A 14B1320 Pre-Bid Conference 09/27/2017 A 09/27/2017 A 1B1328 Bidders Prepare Bids for Submittal 09/28/2017 A 10/30/2017 A 21B1330 Bids Submittal 10/31/2017 A 0B1340 MDWASD/PSIP Team Bids Evaluation 11/01/2017 A 11/14/2017 A 21B1350 Recommendation for Award Letter 11/14/2017 A 0B1355 Contract Award (Purchase Order Approval) 11/15/2017 A 12/19/2017 A 14
ConstrucConstruction 09/27/2017 A 09/13/2018 468B1360 Construction Phase 09/27/2017 A 09/13/2018 468B1364 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 11/15/2017 A 01/18/2018 A 21B1366 Pre-Construction Meeting 01/19/2018 A 01/19/2018 A 1B1368 WASD Issues NTP (Pre-Const to NTP) 01/20/2018 A 04/15/2018 A 45B1369 WASD Issues NTP (PO to NTP) 12/19/2017 A 04/15/2018 A 53
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
08/16/2017 A, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval ProcessIssue Design NTP
Final Engineering Report Review & Approval (MDWASD/PSIP Team)06/16/2016 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services
30% CDs Submittal30% Review (MDWASD/PSIP Team)
06/28/2017 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)
90% RER(DERM)FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)90% RER(Building Dept) Permit Review (Pump Station)
90% Miami Lakes - BD Permit Submittal (Pump Station)90% Miami Lakes - BD Permit Review (Pump Station)
90% CD PM Comments Evaluation CompletedMDWASD Union Concurrence Process
08/16/2017 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal
100% Review (MDWASD/PSIP Team)Design Completed
12/19/2017 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation Period
Bid NoticeMDADWAD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter
Contract Award (Purchase Order Approval)09/13/2018, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 56 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1370 Construction NTP 04/16/2018 A 0B1400 Construction Operations 04/16/2018 A 09/13/2018 149B1402 Substantial Completion 09/13/2018 0
DesignerDesigner Construction Support Services 09/27/2017 A 09/13/2018 290B1410 Designer Construction Support Services 09/27/2017 A 09/13/2018 290
Project CProject Closeout 11/13/2017 A 01/11/2019 162B1445 Closeout Phase 11/13/2017 A 01/11/2019 162B1450 Issue SAC Letter 11/13/2017 A 0B1470 Final Release of Retainage - Construction Contract 09/13/2018 0B1480 Administrative Closeout 09/14/2018 01/11/2019 120B1490 Project Closed 01/11/2019 0
100200 Ba100200 Basin 0336 Infiltration/Inflow Study and Repairs 09/25/2014 A 07/29/2015 A 336InfiltratioInfiltration/Inflow 09/25/2014 A 07/28/2015 A 61
B1000 Infiltration/Inflow Phase 09/25/2014 A 07/28/2015 A 61Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 07/28/2015 A 61
B1005 SSES Phase 09/25/2014 A 07/28/2015 A 61B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 07/10/2015 A 07/28/2015 A 30
Project CProject Closeout 07/29/2015 A 07/29/2015 A 0B1235 Closeout Phase 07/29/2015 A 07/29/2015 A 0B1260 Project Closed 07/29/2015 A 0
Basin 0356Basin 0356 09/05/2014 A 02/20/2019 1614
100219 Pu100219 Pump Station 0356 Upgrade 09/05/2014 A 02/20/2019 1614DesignDesign 09/05/2014 A 01/12/2016 A 378
B1000 Design Phase 09/05/2014 A 01/12/2016 A 378B1010 Prepare and Submit Design Package 09/05/2014 A 09/10/2014 A 5B1020 Engage Design Consultant 09/05/2014 A 11/04/2014 A 20B1022 TA Approval Process 11/05/2014 A 01/12/2015 A 20B1030 Issue Design NTP 02/02/2015 A 0B1032 Engage Design Consultant for TA Rev 1 07/03/2015 A 07/23/2015 A 20B1034 TA Rev 1 Approval Process 07/24/2015 A 07/31/2015 A 20B1036 Issue Design NTP for TA Rev 1 08/05/2015 A 0B1040 A/E Develops and Submits Final Engineering Report 02/02/2015 A 01/12/2016 A 125B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 02/02/2015 A 08/05/2015 A 85
30% Des30% Design 02/03/2015 A 06/01/2015 A 52B1060 A/E Prepares 30% Construction Documents 02/03/2015 A 03/02/2015 A 30B1070 Geotechnical Engineering Services 02/03/2015 A 02/18/2015 A 20B1080 Surveying Services 02/03/2015 A 02/18/2015 A 15B1100 30% CDs Submittal 03/02/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 03/03/2015 A 06/01/2015 A 10
90% Des90% Design 03/03/2015 A 01/12/2016 A 217B1170 A/E Prepares 90% Construction Documents 03/03/2015 A 07/02/2015 A 20B1180 90% CDs Submittal 07/02/2015 A 0B1190 90% Review (MDWASD/PSIP Team) 07/03/2015 A 10/16/2015 A 15B1192 A/E Incorporates TA Rev 1 - 30%, 90% & 100% Revisions 08/05/2015 A 10/16/2015 A 64B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 10/19/2015 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 10/20/2015 A 12/21/2015 A 15B1220 90% PWWMD Permit Submittal (Pump Station) 11/02/2015 A 0B1230 90% PWWMD Permit Review (Pump Station) 11/03/2015 A 11/03/2015 A 15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Construction NTPConstruction OperationsSubstantial Completion09/13/2018, Designer Construction Support Services
Designer Construction Support Services01/11/2019, Project Closeout
Closeout PhaseIssue SAC Letter
Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed
07/29/2015 A, 100200 Basin 0336 Infiltration/Inflow Study and Repairs07/28/2015 A, Infiltration/Inflow
Infiltration/Inflow Phase07/28/2015 A, Sanitary Sewer Evaluation SurveySSES Phase
Issue NTP to SSES ContractorConduct SSES
07/29/2015 A, Project CloseoutCloseout Phase
Project Closed02/20/2019, Basin 0356
02/20/2019, 100219 Pump Station 0356 Upg01/12/2016 A, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Approval Process
Issue Design NTPEngage Design Consultant for TA Rev 1
TA Rev 1 Approval ProcessIssue Design NTP for TA Rev 1
A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
06/01/2015 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services
30% CDs Submittal30% Review (MDWASD/PSIP Team)
01/12/2016 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)A/E Incorporates TA Rev 1 - 30%, 90% & 100% Revisions
90% RER(DERM)FDEP Permit Submittal (Pump Station)90% RER(DERM)FDEP Permit Review (Pump Station)
90% PWWMD Permit Submittal (Pump Station)90% PWWMD Permit Review (Pump Station)
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 57 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1240 90% RER (Building Dept) Permit Submittal (Pump Station) 12/29/2015 A 0B1250 90% RER (Building Dept) Permit Review (Pump Station) 12/30/2015 A 01/12/2016 A 15B1260 90% CD PM Comments Evaluation Completed 01/12/2016 A 0
100% De100% Design 01/08/2016 A 01/12/2016 A 24B1270 A/E Prepares 100% Construction Documents 01/12/2016 A 01/12/2016 A 10B1280 100% CDs Submittal 01/12/2016 A 0B1290 100% Review (MDWASD/PSIP Team) 01/12/2016 A 01/12/2016 A 10B1300 Design Completed 01/08/2016 A 0
MDWASDMDWASD Procurement 01/08/2016 A 12/28/2018 1051B1305 Procurement Phase 01/08/2016 A 12/28/2018 1051B1310 Submit CDs to MDWASD Procurement Division 01/08/2016 A 0B1312 Bid Notice Preparation Period 01/08/2016 A 01/08/2016 A 23B1314 Bid Notice 01/08/2016 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 01/11/2016 A 02/10/2016 A 10B1320 Pre-Bid Conference 02/11/2016 A 02/11/2016 A 1B1328 Bidders Prepare Bids for Submittal 02/12/2016 A 03/28/2016 A 15B1330 Bids Submittal 03/28/2016 A 0B1340 MDWASD/PSIP Team Bids Evaluation 03/29/2016 A 04/01/2016 A 15B1350 Recommendation for Award Letter 04/01/2016 A 0B1355 Contract Award (Purchase Order Approval) 04/04/2016 A 05/05/2016 A 10B1355 Submit CDs to MDWASD Procurement Division 09/15/2018 0B1355 Bid Notice Preparation Period 09/16/2018 10/18/2018 33B1355 Bid Notice 10/18/2018 0B1355 MDWASD/PSIP Team Prepare for Pre-Bid Conference 10/19/2018 11/01/2018 14B1355 Pre-Bid Conference 11/02/2018 11/02/2018 1B1355 Bidders Prepare Bids for Submittal 11/03/2018 11/23/2018 21B1355 Bids Submittal 11/23/2018 0B1355 MDWASD/PSIP Team Bids Evaluation 11/24/2018 12/14/2018 21B1355 Recommendation for Award Letter 12/14/2018 0B1355 Contract Award (Purchase Order Approval) 12/15/2018 12/28/2018 14
ConstrucConstruction 04/04/2016 A 02/20/2019 1144B1360 Construction Phase 04/04/2016 A 02/19/2019 1144B1364 MDAD/PSIP Team Prepare for Pre-Construction Meeting 04/04/2016 A 04/26/2016 A 15B1365 Pre-Construction Meeting 04/29/2016 A 04/29/2016 A 1B1370 Construction NTP 06/06/2016 A 0B1400 Construction Operations 06/06/2016 A 01/20/2017 A 186B1400 WASD Terminate Contract 01/20/2017 A 01/20/2017 A 1B1400 WASD/PSIP Team Re-Package Resolution Period 01/23/2017 A 08/29/2017 A 219B1400 Finalize Project Closeout with Maxon Groupe (Contractor) 08/30/2017 A 08/01/2018 275B1400 A/E Prepared SOW to Re-Package Contract Documents 08/30/2017 A 05/08/2018 A 215B1400 TA Approval Process 05/09/2018 A 08/01/2018 40B1400 A/E Re-Package Contract Documents 08/02/2018 09/15/2018 45B1400 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 12/15/2018 01/04/2019 21B1400 Pre-Construction Meeting 01/05/2019 01/05/2019 1B1400 WASD Issues NTP (Pre-Const to NTP) 01/06/2019 02/19/2019 45B1400 WASD Issues NTP (PO to NTP) 12/29/2018 02/19/2019 53B1400 Construction NTP 02/20/2019 0B1402 Substantial Completion 08/01/2018 0
DesignerDesigner Construction Support Services 06/06/2016 A 08/01/2018 180
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
90% RER (Building Dept) Permit Submittal (Pump Station)90% RER (Building Dept) Permit Review (Pump Station)90% CD PM Comments Evaluation Completed01/12/2016 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed
12/28/2018, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid Notice
MDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter
Contract Award (Purchase Order Approval)Submit CDs to MDWASD Procurement Division
Bid Notice Preparation Period
Bid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for Submittal
Bids SubmittalMDWASD/PSIP Team Bids Evaluation
Recommendation for Award LetterContract Award (Purchase Order Approval)
02/20/2019, Construction
Construction PhaseMDAD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
Construction NTPConstruction Operations
WASD Terminate ContractWASD/PSIP Team Re-Package Resolution Period
Finalize Project Closeout with Maxon Groupe (Contractor)A/E Prepared SOW to Re-Package Contract Documents
TA Approval ProcessA/E Re-Package Contract Documents
MDWASD/PSIP Team Prepare for Pre-ConstructioPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Construction NTPSubstantial Completion08/01/2018, Designer Construction Support Services
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 58 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1410 Designer Construction Support Services 06/06/2016 A 08/01/2018 180Project CProject Closeout 08/01/2018 11/28/2018 120
B1445 Closeout Phase 08/01/2018 11/28/2018 120B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 08/01/2018 11/28/2018 120B1490 Project Closed 11/28/2018 0
Basin 0369Basin 0369 05/01/2014 A 04/28/2017 A 1095
100060 Pu100060 Pump Station 0369 Upgrade 05/01/2014 A 04/28/2017 A 1095PlanningPlanning 05/01/2014 A 01/09/2017 A 19
B0900 Planning Phase 05/01/2014 A 01/09/2017 A 19B0940 Develop Remedial Action Plan (RAP) 05/01/2014 A 05/19/2014 A 7B0950 Develop Preliminary Engineering Report (PER) 01/05/2015 A 10/26/2015 A 10B0960 Recommended Action Memo (RAM) 08/10/2016 A 01/09/2017 A 10
Project CProject Closeout 02/14/2017 A 04/28/2017 A 87B1445 Closeout Phase 02/14/2017 A 04/28/2017 A 87B1450 Issue SAC Letter 02/14/2017 A 0B1480 Administrative Closeout 04/03/2017 A 04/28/2017 A 30B1490 Project Closed 04/28/2017 A 0
Basin 0386Basin 0386 04/07/2014 A 04/28/2017 A 1085
100062 Pu100062 Pump Station 0386 Upgrade 04/07/2014 A 04/28/2017 A 1085PlanningPlanning 04/07/2014 A 01/09/2017 A 19
B0900 Planning Phase 04/07/2014 A 01/09/2017 A 19B0940 Develop Remedial Action Plan (RAP) 04/07/2014 A 05/20/2014 A 7B0960 Recommended Action Memo (RAM) 05/25/2016 A 01/09/2017 A 10
Project CProject Closeout 01/10/2017 A 04/28/2017 A 77B1445 Closeout Phase 01/10/2017 A 04/28/2017 A 77B1450 Issue SAC Letter 02/14/2017 A 0B1480 Administrative Closeout 01/10/2017 A 04/28/2017 A 30B1490 Project Closed 04/28/2017 A 0
Basin 0394Basin 0394 04/06/2015 A 08/01/2018 1247
100064 FM100064 FM for Pump Station 0394 04/06/2015 A 08/01/2018 1247DesignDesign 04/06/2015 A 06/21/2016 A 396
B1000 Design Phase 04/06/2015 A 06/21/2016 A 396B1010 Prepare and Submit Design Package 04/06/2015 A 04/08/2015 A 5B1020 Engage Design Consultant 04/09/2015 A 07/16/2015 A 20B1025 TA Approval Process 07/17/2015 A 08/07/2015 A 20B1030 Issue Design NTP 08/07/2015 A 0B1040 A/E Develops and Submits Final Engineering Report 08/07/2015 A 05/16/2016 A 125B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 08/07/2015 A 05/17/2016 A 125
30% Des30% Design 08/07/2015 A 02/12/2016 A 214B1060 A/E Prepares 30% Construction Documents 08/07/2015 A 02/01/2016 A 30B1070 Geotechnical Engineering Services 08/07/2015 A 11/20/2015 A 20B1080 Surveying Services 08/07/2015 A 11/20/2015 A 15B1100 30% CDs Submittal 02/01/2016 A 0B1120 30% Review (MDWASD/PSIP Team) 02/02/2016 A 02/12/2016 A 10
60% Des60% Design 02/02/2016 A 04/06/2016 A 29B1140 A/E Prepares 60% Construction Documents 02/02/2016 A 03/24/2016 A 20
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Designer Construction Support Services11/28/2018, Project Closeout
Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction Contract
Administrative CloseoutProject Closed
04/28/2017 A, Basin 0369
04/28/2017 A, 100060 Pump Station 0369 Upgrade01/09/2017 A, PlanningPlanning Phase
Develop Remedial Action Plan (RAP)Develop Preliminary Engineering Report (PER)
Recommended Action Memo (RAM)04/28/2017 A, Project CloseoutCloseout Phase
Issue SAC LetterAdministrative Closeout
Project Closed04/28/2017 A, Basin 0386
04/28/2017 A, 100062 Pump Station 0386 Upgrade01/09/2017 A, PlanningPlanning Phase
Develop Remedial Action Plan (RAP)Recommended Action Memo (RAM)
04/28/2017 A, Project CloseoutCloseout Phase
Issue SAC LetterAdministrative Closeout
Project Closed08/01/2018, Basin 0394
08/01/2018, 100064 FM for Pump Station 039406/21/2016 A, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Approval ProcessIssue Design NTP
A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
02/12/2016 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services
30% CDs Submittal30% Review (MDWASD/PSIP Team)
04/06/2016 A, 60% Design
A/E Prepares 60% Construction Documents
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 59 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1150 60% CDs Submittal 03/24/2016 A 0B1170 60% Review (MDWASD/PSIP Team) 03/25/2016 A 04/06/2016 A 10
90% Des90% Design 03/25/2016 A 05/17/2016 A 82B1180 A/E Prepares 90% Construction Documents 03/25/2016 A 05/06/2016 A 20B1190 90% CDs Submittal 05/06/2016 A 0B1200 90% Review (MDWASD/PSIP Team) 05/09/2016 A 05/17/2016 A 15B1230 90% RER(DERM)FDEP Permit Submittal (Force Main) 04/07/2016 A 0B1240 90% RER(DERM)FDEP Permit Review (Force Main) 04/07/2016 A 05/16/2016 A 15B1242 90% PWWMD Permit Submittal (Force Main) 04/07/2016 A 0B1244 90% PWWMD Permit Review (Force Main) 04/07/2016 A 04/08/2016 A 15B1290 90% CD PM Comments Evaluation Completed 05/16/2016 A 0
100% De100% Design 05/17/2016 A 06/21/2016 A 26B1300 A/E Prepares 100% Construction Documents 05/17/2016 A 05/18/2016 A 10B1310 100% CDs Submittal 05/19/2016 A 0B1320 100% Review (MDWASD/PSIP Team) 05/20/2016 A 06/20/2016 A 10B1330 Design Completed 06/21/2016 A 0
MDWASDMDWASD Procurement 05/18/2016 A 08/09/2016 A 54B1335 Procurement Phase 05/18/2016 A 08/09/2016 A 54B1340 Submit CDs to MDWASD Procurement Division 05/18/2016 A 0B1342 Bid Notice Preparation Period 05/19/2016 A 05/19/2016 A 23B1344 Bid Notice 05/19/2016 A 0B1346 MDWASD/PSIP Team Prepare for Pre-Bid Conference 05/20/2016 A 05/26/2016 A 10B1350 Pre-Bid Conference 05/27/2016 A 05/27/2016 A 1B1358 Bidders Prepare Bids for Submittal 05/30/2016 A 06/29/2016 A 15B1360 Bids Submittal 06/29/2016 A 0B1370 MDWASD/PSIP Team Bids Evaluation 06/30/2016 A 07/07/2016 A 15B1380 Recommendation for Award Letter 07/07/2016 A 0B1385 Contract Award (Purchase Order Approval) 07/08/2016 A 08/09/2016 A 10
ConstrucConstruction 05/27/2016 A 01/11/2017 A 897B1390 Construction Phase 05/27/2016 A 01/11/2017 A 897B1394 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 07/08/2016 A 07/18/2016 A 15B1396 Pre-Construction Meeting 07/19/2016 A 07/19/2016 A 1B1398 WASD Issues NTP (PO to NTP) 08/10/2016 A 08/28/2016 A 53B1400 Construction NTP 08/29/2016 A 0B1430 Construction Operations 08/29/2016 A 01/06/2017 A 99B1430 Original Construction Duration 08/29/2016 A 12/07/2016 A 99B1430 Change Order #1 - Hurricane Mathew Preparation 12/08/2016 A 12/12/2016 A 99B1430 Change Order #4 - Additional Scope 12/13/2016 A 01/11/2017 A 99B1432 Substantial Completion 01/06/2017 A 0
DesignerDesigner Construction Support Services 05/27/2016 A 01/06/2017 A 275B1440 Designer Construction Support Services 05/27/2016 A 01/06/2017 A 275
Project CProject Closeout 01/09/2017 A 08/01/2018 570B1475 Closeout Phase 01/09/2017 A 08/01/2018 570B1480 Issue SAC Letter 08/01/2018 0B1500 Final Release of Retainage - Construction Contract 08/01/2018 0B1510 Administrative Closeout 01/09/2017 A 08/01/2018 120B1520 Project Closed 08/01/2018 0
100065 Pu100065 Pump Station 0394(AM) Upgrade 09/02/2015 A 08/01/2018 1205DesignDesign 11/30/2015 A 11/30/2015 A 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
60% CDs Submittal60% Review (MDWASD/PSIP Team)
05/17/2016 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Force Main)90% RER(DERM)FDEP Permit Review (Force Main)
90% PWWMD Permit Submittal (Force Main)90% PWWMD Permit Review (Force Main)
90% CD PM Comments Evaluation Completed06/21/2016 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal
100% Review (MDWASD/PSIP Team)Design Completed08/09/2016 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid Notice
MDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter
Contract Award (Purchase Order Approval)01/11/2017 A, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
WASD Issues NTP (PO to NTP)Construction NTP
Construction OperationsOriginal Construction DurationChange Order #1 - Hurricane Mathew Preparation
Change Order #4 - Additional Scope
Substantial Completion01/06/2017 A, Designer Construction Support Services
Designer Construction Support Services08/01/2018, Project Closeout
Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction ContractAdministrative CloseoutProject Closed08/01/2018, 100065 Pump Station 0394(AM) Upgrade
11/30/2015 A, Design
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 60 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1000 Design Phase 11/30/2015 A 11/30/2015 A 0100% De100% Design 11/30/2015 A 11/30/2015 A 0
B1260 Design Completed 11/30/2015 A 0MDWASDMDWASD Procurement 09/02/2015 A 12/09/2015 A 337
B1265 Procurement Phase 09/02/2015 A 12/09/2015 A 337B1270 Submit CDs to MDWASD Procurement Division 09/02/2015 A 0B1274 Bid Notice Preparation Period 09/02/2015 A 09/14/2015 A 23B1276 Bid Notice 09/15/2015 A 0B1278 MDWASD/PSIP Team Prepare for Pre-Bid Conference 09/16/2015 A 09/24/2015 A 10B1280 Pre-Bid Conference 09/25/2015 A 09/25/2015 A 1B1282 Bidders Prepare Bids for Submittal 09/28/2015 A 10/23/2015 A 15B1290 Bids Submittal 10/26/2015 A 0B1300 MDWASD/PSIP Team Bids Evaluation 10/26/2015 A 10/29/2015 A 15B1310 Recommendation for Award Letter 10/29/2015 A 0B1315 Contract Award (Purchase Order Approval) 10/30/2015 A 12/09/2015 A 10
ConstrucConstruction 09/25/2015 A 06/09/2016 A 1114B1320 Construction Phase 09/25/2015 A 06/09/2016 A 1114B1324 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 10/30/2015 A 01/07/2016 A 15B1326 Pre- Construction Meeting 01/08/2016 A 01/08/2016 A 1B1328 WASD Issues NTP (PO to NTP) 12/10/2015 A 01/10/2016 A 53B1330 Construction NTP 01/11/2016 A 0B1360 Construction Operations 01/11/2016 A 05/19/2016 A 120B1360 Original Construction Duration 01/11/2016 A 05/10/2016 A 120B1360 Change Order #1 - Rejected HOMA Pumps 05/11/2016 A 06/09/2016 A 120B1362 Substantial Completion 05/19/2016 A 0
DesignerDesigner Construction Support Services 09/25/2015 A 05/19/2016 A 192B1370 Designer Construction Support Services 09/25/2015 A 05/19/2016 A 192
ConstrucConstruction Close Out 05/19/2016 A 05/19/2016 A 21B1380 Commissioning 05/19/2016 A 05/19/2016 A 21B1390 Punch List 05/19/2016 A 05/19/2016 A 14
Project CProject Closeout 05/20/2016 A 08/01/2018 759B1405 Closeout Phase 05/20/2016 A 08/01/2018 759B1410 Issue SAC Letter 03/22/2017 A 0B1430 Final Release of Retainage - Construction Contract 02/18/2017 A 0B1440 Administrative Closeout 05/20/2016 A 08/01/2018 120B1450 Project Closed 08/01/2018 0
100248-2 B100248-2 Basin 0394 Infiltration/Inflow Study and Repairs 10/30/2015 A 03/15/2016 A 215InfiltratioInfiltration/Inflow 10/30/2015 A 03/14/2016 A 20
B1000 Infiltration/Inflow Phase 10/30/2015 A 03/14/2016 A 20ManholeManhole Repairs 10/30/2015 A 03/14/2016 A 20
B1110 Manhole Phase 10/30/2015 A 03/14/2016 A 20B1130 Issue NTP for Manhole Repairs 10/30/2015 A 0B1140 Conduct Manhole Repairs 03/14/2016 A 03/14/2016 A 20
Project CProject Closeout 03/15/2016 A 03/15/2016 A 0B1250 Closeout Phase 03/15/2016 A 03/15/2016 A 0B1280 Project Closed 03/15/2016 A 0
Basin 0399Basin 0399 06/12/2014 A 08/01/2018 1682
100066-2 B100066-2 Basin 0399 Infiltration/Inflow Study and Repairs 09/25/2014 A 06/10/2016 A 604InfiltratioInfiltration/Inflow 09/25/2014 A 06/09/2016 A 517
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Design Phase11/30/2015 A, 100% Design
Design Completed12/09/2015 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid Notice
MDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter
Contract Award (Purchase Order Approval)06/09/2016 A, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre- Construction Meeting
WASD Issues NTP (PO to NTP)
Construction NTPConstruction Operations
Original Construction DurationChange Order #1 - Rejected HOMA Pumps
Substantial Completion05/19/2016 A, Designer Construction Support Services
Designer Construction Support Services05/19/2016 A, Construction Close Out
CommissioningPunch List
08/01/2018, Project Closeout
Closeout PhaseIssue SAC Letter
Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed
03/15/2016 A, 100248-2 Basin 0394 Infiltration/Inflow Study and Repairs03/14/2016 A, Infiltration/Inflow
Infiltration/Inflow Phase03/14/2016 A, Manhole Repairs
Manhole PhaseIssue NTP for Manhole Repairs
Conduct Manhole Repairs03/15/2016 A, Project Closeout
Closeout PhaseProject Closed
08/01/2018, Basin 0399
06/10/2016 A, 100066-2 Basin 0399 Infiltration/Inflow Study and Repairs06/09/2016 A, Infiltration/Inflow
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 61 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1000 Infiltration/Inflow Phase 09/25/2014 A 06/09/2016 A 517Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 05/14/2015 A 254
B1005 SSES Phase 09/25/2014 A 05/14/2015 A 254B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 03/02/2015 A 04/17/2015 A 30B1040 Video Review 04/07/2015 A 05/14/2015 A 30
CIPP RepCIPP Repairs 04/17/2015 A 07/27/2015 A 20B1065 CIPP Phase 04/17/2015 A 07/27/2015 A 20B1180 Issue NTP for CIPP Repairs 04/17/2015 A 0B1190 Conduct CIPP Repairs 06/08/2015 A 07/27/2015 A 20
ManholeManhole Repairs 10/02/2015 A 06/09/2016 A 104B1115 Manhole Phase 10/02/2015 A 06/09/2016 A 104B1130 Issue NTP for Manhole Repairs 10/02/2015 A 0B1140 Conduct Manhole Repairs 12/21/2015 A 06/09/2016 A 20
Project CProject Closeout 06/10/2016 A 06/10/2016 A 0B1235 Closeout Phase 06/10/2016 A 06/10/2016 A 0B1260 Project Closed 06/10/2016 A 0
100067 Pu100067 Pump Station 0399 Upgrade 06/12/2014 A 08/01/2018 1682DesignDesign 06/12/2014 A 04/29/2015 A 350
B1000 Design Phase 06/12/2014 A 04/29/2015 A 350B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 06/12/2014 A 06/17/2014 A 5B1020 Engage Design Consultant 06/18/2014 A 08/26/2014 A 20B1030 Issue Design NTP 09/17/2014 A 0B1040 A/E Develops and Submits Final Engineering Report 09/17/2014 A 04/29/2015 A 20B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 11/26/2014 A 01/26/2015 A 10
30% Des30% Design 09/18/2014 A 10/30/2014 A 54B1060 A/E Prepares 30% Construction Documents 09/18/2014 A 10/17/2014 A 30B1070 Geotechnical Engineering Services 10/03/2014 A 10/21/2014 A 31B1080 Surveying Services 10/03/2014 A 10/21/2014 A 21B1100 30% CDs Submittal 10/17/2014 A 0B1120 30% Review (MDWASD/PSIP Team) 10/17/2014 A 10/30/2014 A 10
90% Des90% Design 10/20/2014 A 04/29/2015 A 117B1170 A/E Prepares 90% Construction Documents 10/20/2014 A 11/25/2014 A 20B1180 90% CDs Submittal 11/25/2014 A 0B1190 90% Review (MDWASD/PSIP Team) 11/26/2014 A 01/06/2015 A 15B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 01/27/2015 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 01/27/2015 A 02/20/2015 A 15B1220 90% RER (Building Department) Permit Submittal 03/02/2015 A 0B1230 90% RER (Building Department) Permit Review 03/02/2015 A 04/29/2015 A 15B1260 90% CD PM Comments Evaluation Completed 04/29/2015 A 0
100% De100% Design 01/07/2015 A 03/26/2015 A 13B1270 A/E Prepares 100% Construction Documents 01/07/2015 A 03/24/2015 A 10B1280 100% CDs Submittal 03/24/2015 A 0B1290 100% Review (MDWASD/PSIP Team) 03/25/2015 A 03/26/2015 A 10B1300 Design Completed 03/26/2015 A 0
MDWASDMDWASD Procurement 04/01/2015 A 06/17/2015 A 113B1305 Procurement Phase 04/01/2015 A 06/17/2015 A 113B1310 Submit CDs to MDWASD Procurement Division 04/01/2015 A 0B1320 Pre-Bid Conference 04/09/2015 A 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Infiltration/Inflow Phase05/14/2015 A, Sanitary Sewer Evaluation SurveySSES Phase
Issue NTP to SSES ContractorConduct SSES
Video Review07/27/2015 A, CIPP RepairsCIPP Phase
Issue NTP for CIPP RepairsConduct CIPP Repairs
06/09/2016 A, Manhole RepairsManhole Phase
Issue NTP for Manhole RepairsConduct Manhole Repairs06/10/2016 A, Project CloseoutCloseout Phase
Project Closed08/01/2018, 100067 Pump Station 0399 Upgrade
04/29/2015 A, Design
Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book
Engage Design ConsultantIssue Design NTP
A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
10/30/2014 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services
30% CDs Submittal30% Review (MDWASD/PSIP Team)
04/29/2015 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)
90% RER(DERM)FDEP Permit Submittal (Pump Station)90% RER(DERM)FDEP Permit Review (Pump Station)90% RER (Building Department) Permit Submittal
90% RER (Building Department) Permit Review90% CD PM Comments Evaluation Completed
03/26/2015 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal
100% Review (MDWASD/PSIP Team)Design Completed
06/17/2015 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement DivisionPre-Bid Conference
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 62 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1330 Bids Submittal 05/15/2015 A 0B1340 MDWASD/PSIP Team Bids Evaluation 05/18/2015 A 05/27/2015 A 30B1350 Recommendation for Award Letter 05/27/2015 A 0B1355 Contract Award (Purchase Order Approval) 05/28/2015 A 06/17/2015 A 15
ConstrucConstruction 04/09/2015 A 08/11/2016 A 1283B1360 Construction Phase 04/09/2015 A 08/11/2016 A 1283B1362 MDWASD/PSIP Team prepare for Pre-Construction meeting 05/29/2015 A 06/17/2015 A 15B1365 Pre-Construction Meeting 06/18/2015 A 06/18/2015 A 1B1369 WASD Issues NTP (PO to NTP) 06/18/2015 A 07/12/2015 A 53B1370 Construction NTP 07/13/2015 A 0B1400 Construction Operations 07/13/2015 A 12/18/2015 A 92B1400 Original Construction Duration 07/13/2015 A 11/20/2015 A 92B1400 Change Order #1 - FPL 11/21/2015 A 12/18/2015 A 92B1402 Substantial Completion 12/18/2015 A 0
DesignerDesigner Construction Support Services 04/09/2015 A 08/11/2016 A 95B1410 Designer Construction Support Services 04/09/2015 A 08/11/2016 A 95
ConstrucConstruction Close Out 12/21/2015 A 03/29/2016 A 15B1420 Commissioning 12/21/2015 A 03/29/2016 A 15B1430 Punch List 12/21/2015 A 03/29/2016 A 10
Project CProject Closeout 09/21/2015 A 08/01/2018 1045B1445 Closeout Phase 09/21/2015 A 08/01/2018 1045B1450 Issue SAC Letter 09/21/2015 A 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 12/21/2015 A 08/01/2018 120B1490 Project Closed 08/01/2018 0
Basin 0407Basin 0407 09/25/2014 A 01/05/2020 1883
100068 Pu100068 Pump Station 0407 Upgrade 12/29/2014 A 01/05/2020 1715DesignDesign 12/29/2014 A 10/04/2018 1257
B1000 Design Phase 12/29/2014 A 10/04/2018 1257B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 12/29/2014 A 01/05/2015 A 5B1020 Engage Design Consultant 01/06/2015 A 05/05/2015 A 20B1030 Issue Design NTP 05/05/2015 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 05/05/2015 A 09/14/2018 85
30% Des30% Design 05/06/2015 A 08/24/2015 A 95B1060 A/E Prepares 30% Construction Documents 05/06/2015 A 08/11/2015 A 30B1070 Geotechnical Engineering Services 05/06/2015 A 08/11/2015 A 20B1080 Surveying Services 05/06/2015 A 08/11/2015 A 15B1100 30% CDs Submittal 08/11/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 08/11/2015 A 08/24/2015 A 10
90% Des90% Design 08/11/2015 A 09/14/2018 1088B1170 A/E Prepares 90% Construction Documents 08/11/2015 A 10/30/2015 A 20B1172 90% CD On-Hold Until Pump Station Relocation Resolution 10/30/2015 A 08/01/2018 100B1180 90% CDs Submittal 08/01/2018 0B1190 90% Review (MDWASD/PSIP Team) 08/01/2018 08/15/2018 15B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 08/16/2018 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 08/16/2018 08/30/2018 15B1220 90% RER (Building Department) Permit Submittal 08/31/2018 0B1230 90% RER (Building Department) Permit Review 08/31/2018 09/14/2018 15B1260 90% CD PM Comments Evaluation Completed 09/14/2018 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Bids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)
08/11/2016 A, Construction
Construction PhaseMDWASD/PSIP Team prepare for Pre-Construction meetingPre-Construction Meeting
WASD Issues NTP (PO to NTP)
Construction NTPConstruction Operations
Original Construction DurationChange Order #1 - FPL
Substantial Completion08/11/2016 A, Designer Construction Support Services
Designer Construction Support Services03/29/2016 A, Construction Close Out
CommissioningPunch List
08/01/2018, Project Closeout
Closeout PhaseIssue SAC Letter
Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed
01/05/2020, Basin 0
01/05/2020, 10006810/04/2018, Design
Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book
Engage Design ConsultantIssue Design NTP
Final Engineering Report Review & Approval (MDWASD/PS08/24/2015 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal30% Review (MDWASD/PSIP Team)
09/14/2018, 90% Design
A/E Prepares 90% Construction Documents90% CD On-Hold Until Pump Station Relocation Resolution
90% CDs Submittal90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)90% RER(DERM)FDEP Permit Review (Pump Station)90% RER (Building Department) Permit Submittal90% RER (Building Department) Permit Review90% CD PM Comments Evaluation Completed
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 63 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
100% De100% Design 09/15/2018 10/04/2018 20B1270 A/E Prepares 100% Construction Documents 09/15/2018 09/24/2018 10B1280 100% CDs Submittal 09/24/2018 0B1290 100% Review (MDWASD/PSIP Team) 09/25/2018 10/04/2018 10B1300 Design Completed 10/04/2018 0
MDWASDMDWASD Procurement 10/04/2018 01/15/2019 104B1305 Procurement Phase 10/04/2018 01/15/2019 104B1310 Submit CDs to MDWASD Procurement Division 10/04/2018 0B1312 Bid Notice Preparation Period 10/04/2018 11/05/2018 33B1314 Bid Notice 11/05/2018 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 11/06/2018 11/19/2018 14B1320 Pre-Bid Conference 11/20/2018 11/20/2018 1B1328 Bidders Prepare Bids for Submittal 11/21/2018 12/11/2018 21B1330 Bids Submittal 12/11/2018 0B1340 MDWASD/PSIP Team Bids Evaluation 12/12/2018 01/01/2019 21B1350 Recommendation for Award Letter 01/01/2019 0B1355 Contract Award (Purchase Order Approval) 01/02/2019 01/15/2019 14
ConstrucConstruction 11/20/2018 09/07/2019 292B1360 Construction Phase 11/20/2018 09/07/2019 292B1364 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 01/02/2019 01/24/2019 23B1366 Pre-Construction Meeting 01/25/2019 01/25/2019 1B1368 WASD Issues NTP (Pre-Const to NTP) 01/26/2019 03/11/2019 45B1369 WASD Issues NTP (PO to NTP) 01/16/2019 03/11/2019 55B1370 Construction NTP 03/12/2019 0B1400 Construction Operations 03/12/2019 09/07/2019 180B1402 Substantial Completion 09/07/2019 0
DesignerDesigner Construction Support Services 11/20/2018 09/07/2019 292B1410 Designer Construction Support Services 11/20/2018 09/07/2019 292
Project CProject Closeout 09/07/2019 01/05/2020 120B1445 Closeout Phase 09/07/2019 01/05/2020 120B1450 Issue SAC Letter 09/07/2019 0B1470 Final Release of Retainage - Construction Contract 09/07/2019 0B1480 Administrative Closeout 09/08/2019 01/05/2020 120B1490 Project Closed 01/05/2020 0
100190-2 B100190-2 Basin 0407 Infiltration/Inflow Study and Repairs 09/25/2014 A 07/28/2015 A 569InfiltratioInfiltration/Inflow 09/25/2014 A 07/27/2015 A 263
B1000 Infiltration/Inflow Phase 09/25/2014 A 07/27/2015 A 263Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 07/27/2015 A 263
B1005 SSES Phase 09/25/2014 A 07/27/2015 A 263B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 07/06/2015 A 07/27/2015 A 30
Project CProject Closeout 07/28/2015 A 07/28/2015 A 0B1235 Closeout Phase 07/28/2015 A 07/28/2015 A 0B1260 Project Closed 07/28/2015 A 0
100223 FM100223 FM for Pump Station 0407 12/29/2014 A 03/09/2019 1413DesignDesign 12/29/2014 A 09/10/2018 1233
B1000 Design Phase 12/29/2014 A 09/10/2018 1233B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 12/29/2014 A 01/05/2015 A 5B1020 Engage Design Consultant 01/06/2015 A 05/05/2015 A 20
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
10/04/2018, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed
01/15/2019, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)
09/07/2019, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-ConstructPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Construction NTPConstruction OperationsSubstantial Completion09/07/2019, Designer Constru
Designer Construction Suppo01/05/2020, Project
Closeout PhaseIssue SAC LetterFinal Release of Retainage - C
Administrative CloseProject Closed
07/28/2015 A, 100190-2 Basin 0407 Infiltration/Inflow Study and Repairs07/27/2015 A, Infiltration/Inflow
Infiltration/Inflow Phase07/27/2015 A, Sanitary Sewer Evaluation SurveySSES Phase
Issue NTP to SSES ContractorConduct SSES07/28/2015 A, Project CloseoutCloseout Phase
Project Closed03/09/2019, 100223 FM for Pump Station 0
09/10/2018, Design
Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book
Engage Design Consultant
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 64 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1030 Issue Design NTP 05/05/2015 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 05/05/2015 A 10/30/2015 A 10
30% Des30% Design 05/06/2015 A 08/24/2015 A 107B1060 A/E Prepares 30% Construction Documents 05/06/2015 A 08/11/2015 A 30B1070 Geotechnical Engineering Services 05/06/2015 A 08/11/2015 A 20B1080 Surveying Services 05/06/2015 A 08/11/2015 A 15B1100 30% CDs Submittal 08/11/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 08/11/2015 A 08/24/2015 A 10
90% Des90% Design 08/11/2015 A 08/21/2018 1064B1180 A/E Prepares 90% Construction Documents 08/11/2015 A 10/22/2015 A 20B1190 90% CDs Submittal 10/22/2015 A 0B1200 90% Review (MDWASD/PSIP Team) 10/23/2015 A 10/30/2015 A 15B1202 90% Design Review On-Hold Until Pump Station Relocation Res 10/30/2015 A 08/01/2018 100B1230 90% RER(DERM)FDEP Permit Submittal (Force Main) 08/02/2018 0B1240 90% RER(DERM)FDEP Permit Review (Force Main) 08/02/2018 08/11/2018 10B1250 90% PWWMD Permit Submittal (Force Main) 08/12/2018 0B1260 90% PWWMD Permit Review (Force Main) 08/12/2018 08/21/2018 10B1290 90% CD PM Comments Evaluation Completed 08/21/2018 0
100% De100% Design 08/22/2018 09/10/2018 20B1300 A/E Prepares 100% Construction Documents 08/22/2018 08/31/2018 10B1310 100% CDs Submittal 08/31/2018 0B1320 100% Review (MDWASD/PSIP Team) 09/01/2018 09/10/2018 10B1330 Design Completed 09/10/2018 0
MDWASDMDWASD Procurement 09/10/2018 11/23/2018 74B1335 Procurement Phase 09/10/2018 11/23/2018 74B1340 Submit CDs to MDWASD Procurement Division 09/10/2018 0B1342 Bid Notice Preparation Period 09/11/2018 10/03/2018 23B1344 Bid Notice 10/03/2018 0B1346 MDWASD/PSIP Team Prepare for Pre-Bid Conference 10/04/2018 10/13/2018 10B1350 Pre-Bid Conference 10/14/2018 10/14/2018 1B1358 Bidders Prepare Bids for Submittal 10/15/2018 10/29/2018 15B1360 Bids Submittal 10/29/2018 0B1370 MDWASD/PSIP Team Bids Evaluation 10/30/2018 11/13/2018 15B1380 Recommendation for Award Letter 11/13/2018 0B1385 Contract Award (Purchase Order Approval) 11/14/2018 11/23/2018 10
ConstrucConstruction 10/14/2018 02/07/2019 117B1390 Construction Phase 10/14/2018 02/07/2019 117B1394 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 11/24/2018 12/08/2018 15B1396 Pre-Construction Meeting 12/09/2018 12/09/2018 1B1398 WASD Issues NTP (PO to NTP) 11/24/2018 12/09/2018 16B1400 Construction NTP 12/10/2018 0B1430 Construction Operations 12/10/2018 02/07/2019 60B1432 Substantial Completion 02/07/2019 0
DesignerDesigner Construction Support Services 10/14/2018 02/07/2019 117B1440 Designer Construction Support Services 10/14/2018 02/07/2019 117
Project CProject Closeout 02/07/2019 03/09/2019 30B1475 Closeout Phase 02/07/2019 03/09/2019 30B1480 Issue SAC Letter 02/07/2019 0B1500 Final Release of Retainage - Construction Contract 02/07/2019 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Issue Design NTPFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
08/24/2015 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal30% Review (MDWASD/PSIP Team)
08/21/2018, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)
90% Design Review On-Hold Until Pump Station Relocation Re
90% RER(DERM)FDEP Permit Submittal (Force Main)90% RER(DERM)FDEP Permit Review (Force Main)90% PWWMD Permit Submittal (Force Main)90% PWWMD Permit Review (Force Main)90% CD PM Comments Evaluation Completed
09/10/2018, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed
11/23/2018, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation Period
Bid NoticeMDWASD/PSIP Team Prepare for Pre-Bid Conference
Pre-Bid ConferenceBidders Prepare Bids for Submittal
Bids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)
02/07/2019, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction Pre-Construction MeetingWASD Issues NTP (PO to NTP)
Construction NTPConstruction OperationsSubstantial Completion02/07/2019, Designer Construction Support Se
Designer Construction Support Services03/09/2019, Project Closeout
Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction Cont
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 65 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1510 Administrative Closeout 02/08/2019 03/09/2019 30B1520 Project Closed 03/09/2019 0
Basin 0408Basin 0408 09/25/2014 A 08/01/2018 1628
100070 Pu100070 Pump Station 0408(AM) Upgrade 01/12/2015 A 08/01/2018 1138DesignDesign 01/12/2015 A 05/19/2016 A 351
B1000 Design Phase 01/12/2015 A 05/19/2016 A 351B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 01/12/2015 A 03/04/2015 A 5B1020 Engage Design Consultant 03/05/2015 A 07/16/2015 A 15B1025 TA Approval Process 07/17/2015 A 08/07/2015 A 20B1030 Issue Design NTP 08/07/2015 A 0
30% Des30% Design 08/07/2015 A 10/30/2015 A 59B1060 A/E Prepares 30% Construction Documents 08/07/2015 A 10/22/2015 A 30B1070 Geotechnical Engineering Services 08/07/2015 A 10/22/2015 A 20B1080 Surveying Services 08/07/2015 A 10/22/2015 A 15B1100 30% CDs Submittal 10/22/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 10/23/2015 A 10/30/2015 A 10
60% Des60% Design 10/23/2015 A 05/19/2016 A 100B1130 A/E Prepares 60% Construction Documents 10/23/2015 A 10/30/2015 A 20B1132 60% CD On-Hold Until Pump Station Relocation Resolution 10/30/2015 A 05/19/2016 A 100
Project CProject Closeout 05/19/2016 A 08/01/2018 1157B1445 Closeout Phase 05/19/2016 A 08/01/2018 1157B1450 Issue SAC Letter 05/19/2016 A 0B1480 Administrative Closeout 05/20/2016 A 08/01/2018 120B1490 Project Closed 08/01/2018 0
100201-2 B100201-2 Basin 0408 Infiltration/Inflow Study and Repairs 09/25/2014 A 07/28/2015 A 336InfiltratioInfiltration/Inflow 09/25/2014 A 07/27/2015 A 111
B1000 Infiltration/Inflow Phase 09/25/2014 A 07/27/2015 A 111Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 07/27/2015 A 111
B1005 SSES Phase 09/25/2014 A 07/27/2015 A 111B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 07/06/2015 A 07/27/2015 A 30
Project CProject Closeout 07/28/2015 A 07/28/2015 A 0B1235 Closeout Phase 07/28/2015 A 07/28/2015 A 0B1260 Project Closed 07/28/2015 A 0
100063 FM100063 FM for Pump Station 0408 01/26/2015 A 08/01/2018 1275DesignDesign 01/26/2015 A 05/19/2016 A 331
B1000 Design Phase 01/26/2015 A 05/19/2016 A 331B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 01/26/2015 A 02/27/2015 A 5B1015 MDWASD to Issue PCTS Number to Project 03/03/2015 A 04/03/2015 A 21B1020 Engage Design Consultant 04/06/2015 A 07/16/2015 A 25B1030 Prepare and Issue TA 07/17/2015 A 08/06/2015 A 20B1040 Issue Design NTP 08/07/2015 A 0
30% Des30% Design 08/07/2015 A 05/19/2016 A 136B1070 A/E Prepares 30% Construction Documents 08/07/2015 A 10/30/2015 A 30B1080 Geotechnical Engineering Services 08/07/2015 A 10/30/2015 A 20B1090 Surveying Services 08/07/2015 A 10/30/2015 A 15B1092 30% CD On-Hold Until Pump Station Relocation Resolution 10/30/2015 A 05/19/2016 A 100
Project CProject Closeout 05/19/2016 A 08/01/2018 804B1420 Closeout Phase 05/19/2016 A 08/01/2018 804
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Administrative CloseoutProject Closed
08/01/2018, Basin 0408
08/01/2018, 100070 Pump Station 0408(AM) Upgrade05/19/2016 A, Design
Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book
Engage Design ConsultantTA Approval ProcessIssue Design NTP
10/30/2015 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal30% Review (MDWASD/PSIP Team)
05/19/2016 A, 60% Design
A/E Prepares 60% Construction Documents60% CD On-Hold Until Pump Station Relocation Resolution
08/01/2018, Project Closeout
Closeout PhaseIssue SAC Letter
Administrative CloseoutProject Closed
07/28/2015 A, 100201-2 Basin 0408 Infiltration/Inflow Study and Repairs07/27/2015 A, Infiltration/Inflow
Infiltration/Inflow Phase07/27/2015 A, Sanitary Sewer Evaluation SurveySSES Phase
Issue NTP to SSES ContractorConduct SSES
07/28/2015 A, Project CloseoutCloseout Phase
Project Closed08/01/2018, 100063 FM for Pump Station 0408
05/19/2016 A, Design
Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book
MDWASD to Issue PCTS Number to Project
Engage Design ConsultantPrepare and Issue TAIssue Design NTP
05/19/2016 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services
30% CD On-Hold Until Pump Station Relocation Resolution08/01/2018, Project Closeout
Closeout Phase
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 66 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1430 Issue SAC Letter 05/19/2016 A 0B1460 Administrative Closeout 05/20/2016 A 08/01/2018 120B1470 Project Closed 08/01/2018 0
Basin 0431Basin 0431 04/15/2014 A 08/01/2018 1667
100072 Pu100072 Pump Station 0431 Upgrade 04/15/2014 A 08/01/2018 1667DesignDesign 04/15/2014 A 04/21/2016 A 400
B1000 Design Phase 04/15/2014 A 04/21/2016 A 400B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 04/15/2014 A 04/15/2014 A 5B1020 Engage Design Consultant 04/16/2014 A 09/17/2014 A 15B1022 TA Rev 1 - Approval Process 01/19/2016 A 04/21/2016 A 20B1030 Issue Design NTP 09/18/2014 A 0B1040 A/E Develops and Submits Final Engineering Report 09/19/2014 A 11/21/2014 A 20B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 11/24/2014 A 04/07/2015 A 10
30% Des30% Design 09/18/2014 A 10/30/2014 A 30B1060 A/E Prepares 30% Construction Documents 09/18/2014 A 10/20/2014 A 30B1070 Geotechnical Engineering Services 10/02/2014 A 10/16/2014 A 20B1080 Surveying Services 10/09/2014 A 10/16/2014 A 15B1090 30% CDs Submittal 10/20/2014 A 0B1100 30% Review (MDWASD/PSIP Team) 10/21/2014 A 10/30/2014 A 10
90% Des90% Design 10/21/2014 A 05/21/2015 A 210B1150 A/E Prepares 90% Construction Documents 10/21/2014 A 11/21/2014 A 20B1160 90% CDs Submittal 11/21/2014 A 0B1170 90% Review (MDWASD/PSIP Team) 11/24/2014 A 12/11/2014 A 15B1180 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 03/06/2015 A 0B1190 90% RER(DERM)/FDEP Permit Review (Pump Station) 03/06/2015 A 04/07/2015 A 15B1200 90% RER (Building Dept) Permit Submittal 04/22/2015 A 0B1210 90% RER (Building Dept) Permit Review 04/22/2015 A 05/21/2015 A 15B1240 90% CD PM Comments Evaluation Completed 05/21/2015 A 0
100% De100% Design 12/11/2014 A 05/21/2015 A 98B1250 A/E Prepares 100% Construction Documents 12/11/2014 A 01/23/2015 A 10B1260 100% CDs Submittal 01/23/2015 A 0B1270 100% Review (MDWASD/PSIP Team) 01/26/2015 A 03/05/2015 A 10B1280 Design Completed 05/21/2015 A 0
MDWASDMDWASD Procurement 04/24/2015 A 08/18/2015 A 202B1285 Procurement Phase 04/24/2015 A 08/18/2015 A 202B1290 Submit CDs to MDWASD Procurement Division 04/24/2015 A 0B1292 Bid Notice Preparation Period 04/27/2015 A 04/30/2015 A 23B1294 Bid Notice 04/30/2015 A 0B1296 MDWASD/PSIP Team Prepare for Pre-Bid Conference 05/01/2015 A 05/05/2015 A 10B1300 Pre-Bid Conference 05/06/2015 A 05/06/2015 A 1B1302 Bidders Prepare Bids for Submittal 05/07/2015 A 05/28/2015 A 15B1310 Bids Submittal 05/28/2015 A 0B1320 MDWASD/PSIP Team Bids Evaluation 05/29/2015 A 06/25/2015 A 15B1330 Recommendation for Award Letter 06/25/2015 A 0B1335 Contract Award (Purchase Order Approval) 06/26/2015 A 08/18/2015 A 10
ConstrucConstruction 05/06/2015 A 12/16/2016 A 1240B1340 Construction Phase 05/06/2015 A 12/16/2016 A 1240B1344 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 06/26/2015 A 07/27/2015 A 15B1346 Pre-Construction Meeting 07/28/2015 A 07/28/2015 A 1
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Issue SAC LetterAdministrative CloseoutProject Closed08/01/2018, Basin 0431
08/01/2018, 100072 Pump Station 0431 Upgrade04/21/2016 A, Design
Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book
Engage Design ConsultantTA Rev 1 - Approval Process
Issue Design NTPA/E Develops and Submits Final Engineering Report
Final Engineering Report Review & Approval (MDWASD/PSIP Team)10/30/2014 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services
30% CDs Submittal30% Review (MDWASD/PSIP Team)
05/21/2015 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)/FDEP Permit Submittal (Pump Station)
90% RER(DERM)/FDEP Permit Review (Pump Station)90% RER (Building Dept) Permit Submittal
90% RER (Building Dept) Permit Review90% CD PM Comments Evaluation Completed
05/21/2015 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)
Design Completed08/18/2015 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation Period
Bid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter
Contract Award (Purchase Order Approval)12/16/2016 A, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 67 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1348 WASD Issues NTP (PO to NTP) 08/19/2015 A 09/01/2015 A 53B1350 Construction NTP 09/02/2015 A 0B1380 Construction Operations 09/02/2015 A 12/16/2016 A 105B1380 Original Construction Duration 09/02/2015 A 01/30/2016 A 105B1380 Change Order #1 - Shop Drawing Processing 01/31/2016 A 07/18/2016 A 105B1380 Change Order #2 - Contractor's Delays 07/19/2016 A 08/18/2016 A 105B1380 Change Order #3 - Multiple Issues 08/19/2016 A 11/28/2016 A 105B1382 Substantial Completion 12/16/2016 A 0
DesignerDesigner Construction Support Services 05/06/2015 A 12/16/2016 A 198B1390 Designer Construction Support Services 05/06/2015 A 12/16/2016 A 198
Project CProject Closeout 09/21/2015 A 08/01/2018 1045B1425 Closeout Phase 09/21/2015 A 08/01/2018 1045B1430 Issue SAC Letter 09/21/2015 A 0B1450 Final Release of Retainage - Construction Contract 08/01/2018 0B1460 Administrative Closeout 12/19/2016 A 08/01/2018 120B1470 Project Closed 08/01/2018 0
100202-2 B100202-2 Basin 0431 Infiltration/Inflow Study and Repairs 09/25/2014 A 01/29/2016 A 576InfiltratioInfiltration/Inflow 09/25/2014 A 01/28/2016 A 414
B1000 Infiltration/Inflow Phase 09/25/2014 A 01/28/2016 A 414Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 04/16/2015 A 234
B1005 SSES Phase 09/25/2014 A 04/16/2015 A 234B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct Flow Isolation & SSES 11/12/2014 A 03/02/2015 A 30B1031 Smoke Test 02/02/2015 A 02/05/2015 A 10B1040 Video Review 02/16/2015 A 04/16/2015 A 30
CIPP RepCIPP Repairs 11/30/2015 A 01/28/2016 A 20B1065 CIPP Phase 11/30/2015 A 01/28/2016 A 20B1080 Issue NTP for CIPP Repairs 11/30/2015 A 0B1090 Conduct CIPP Repairs 11/30/2015 A 01/28/2016 A 20
Project CProject Closeout 01/29/2016 A 01/29/2016 A 0B1235 Closeout Phase 01/29/2016 A 01/29/2016 A 0B1260 Project Closed 01/29/2016 A 0
100236 FM100236 FM for Pump Station 0431 07/14/2014 A 08/01/2018 1619DesignDesign 07/14/2014 A 05/07/2015 A 301
B1000 Design Phase 07/14/2014 A 05/07/2015 A 301B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 07/14/2014 A 07/18/2014 A 5B1020 Engage Design Consultant 07/21/2014 A 10/02/2014 A 20B1025 Prepare and Issue TA 09/19/2014 A 12/11/2014 A 10B1030 Issue Design NTP 12/11/2014 A 0B1040 A/E Develops and Submits Final Engineering Report 12/11/2014 A 05/05/2015 A 60B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 12/24/2014 A 04/08/2015 A 10
30% Des30% Design 12/12/2014 A 02/18/2015 A 73B1060 A/E Prepares 30% Construction Documents 12/12/2014 A 02/11/2015 A 20B1070 Geotechnical Engineering Services 12/12/2014 A 02/11/2015 A 15B1080 Surveying Services 12/12/2014 A 02/11/2015 A 15B1100 30% CDs Submittal 02/11/2015 A 0B1120 30% Review (MDWASD/PSIP Team ) 02/12/2015 A 02/18/2015 A 10
90% Des90% Design 02/12/2015 A 05/05/2015 A 84B1140 A/E Prepares 90% Construction Documents 02/12/2015 A 03/23/2015 A 15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
WASD Issues NTP (PO to NTP)
Construction NTPConstruction Operations
Original Construction DurationChange Order #1 - Shop Drawing Processing
Change Order #2 - Contractor's DelaysChange Order #3 - Multiple Issues
Substantial Completion12/16/2016 A, Designer Construction Support Services
Designer Construction Support Services08/01/2018, Project Closeout
Closeout PhaseIssue SAC Letter
Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed
01/29/2016 A, 100202-2 Basin 0431 Infiltration/Inflow Study and Repairs01/28/2016 A, Infiltration/Inflow
Infiltration/Inflow Phase04/16/2015 A, Sanitary Sewer Evaluation SurveySSES Phase
Issue NTP to SSES ContractorConduct Flow Isolation & SSES
Smoke Test
Video Review01/28/2016 A, CIPP RepairsCIPP Phase
Issue NTP for CIPP RepairsConduct CIPP Repairs01/29/2016 A, Project CloseoutCloseout Phase
Project Closed08/01/2018, 100236 FM for Pump Station 0431
05/07/2015 A, Design
Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book
Engage Design ConsultantPrepare and Issue TAIssue Design NTP
A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
02/18/2015 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal30% Review (MDWASD/PSIP Team )
05/05/2015 A, 90% Design
A/E Prepares 90% Construction Documents
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 68 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1150 90% CDs Submittal 03/23/2015 A 0B1160 90% Review (MDWASD/PSIP Team) 03/24/2015 A 04/08/2015 A 5B1170 90% RER(DERM)/FDEP Permit Submittal (Force Main) 04/21/2015 A 0B1180 90% RER(DERM)/FDEP Permit Review (Force Main) 04/21/2015 A 04/28/2015 A 5B1190 90% PWWMD Permit Submittal (Force Main) 04/22/2015 A 0B1200 90% PWWMD Permit Review (Force Main) 04/22/2015 A 05/05/2015 A 10B1250 90% CD PM Comments Evaluation Completed 05/05/2015 A 0
100% De100% Design 05/07/2015 A 05/07/2015 A 46B1260 A/E Prepares 100% Construction Documents 05/07/2015 A 05/07/2015 A 5B1270 100% CDs Submittal 05/07/2015 A 0B1280 100% Review (MDWASD/PSIP Team) 05/07/2015 A 05/07/2015 A 5B1290 Design Completed 05/07/2015 A 0
MDWASDMDWASD Procurement 05/01/2015 A 10/13/2015 A 178B1295 Procurement Phase 05/01/2015 A 10/13/2015 A 178B1300 Submit CDs to MDWASD Procurement Division 05/01/2015 A 0B1310 Pre-Bid Conference 05/27/2015 A 0B1320 Bids Submittal 06/18/2015 A 0B1330 Bids Evaluation (MDWASD/PSIP Team) 06/19/2015 A 08/10/2015 A 30B1332 MDWASD Issued Notice of Cancellation - Project To Be Re-Bid 08/11/2015 A 08/11/2015 A 30B1333 Re-Bid Notice Preparation Period 08/12/2015 A 08/12/2015 A 30B1334 Re-Bid Notice 08/12/2015 A 0B1335 MDWASD/PSIP Team Prepare for Re-Bid Conference 08/13/2015 A 08/25/2015 A 10B1336 Re-Bid Conference 08/26/2015 A 08/26/2015 A 1B1337 Bidders Prepare for Re-Bids Submittal 08/27/2015 A 09/15/2015 A 15B1338 Re-Bids Submittal 09/16/2015 A 0B1339 Re-Bids Evaluation (MDWASD/PSIP Team) 09/17/2015 A 09/18/2015 A 15B1340 Recommendation for Award Letter 09/21/2015 A 0B1345 Contract Award (Purchase Order Approval) 09/22/2015 A 10/13/2015 A 10
ConstrucConstruction 05/27/2015 A 07/29/2016 A 1175B1350 Construction Phase 05/27/2015 A 07/29/2016 A 1175B1354 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 09/22/2015 A 10/29/2015 A 15B1356 Pre-Construction Meeting 10/30/2015 A 10/30/2015 A 1B1357 WASD Issues NTP (Pre-Const to NTP) 11/02/2015 A 01/31/2016 A 15B1358 WASD Issues NTP (PO to NTP) 10/14/2015 A 01/31/2016 A 53B1360 Construction NTP 02/01/2016 A 0B1390 Construction Operations 02/01/2016 A 04/29/2016 A 63B1392 Substantial Completion 04/29/2016 A 0
DesignerDesigner Construction Services 05/27/2015 A 07/29/2016 A 152B1400 Designer Construction Support Services 05/27/2015 A 07/29/2016 A 152
ConstrucConstruction Close Out 05/02/2016 A 07/29/2016 A 10B1420 Punch List 05/02/2016 A 07/29/2016 A 10
Project CProject Closeout 05/02/2016 A 08/01/2018 792B1435 Closeout Phase 05/02/2016 A 08/01/2018 792B1460 Final Release of Retainage - Construction Contract 05/30/2017 A 0B1470 Administrative Closeout 05/02/2016 A 08/01/2018 120B1480 Project Closed 08/01/2018 0
Basin 0435Basin 0435 08/07/2014 A 08/01/2018 1651
100073 Pu100073 Pump Station 0435 Upgrade 08/07/2014 A 08/01/2018 1651DesignDesign 08/07/2014 A 09/30/2015 A 478
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
90% CDs Submittal90% Review (MDWASD/PSIP Team)90% RER(DERM)/FDEP Permit Submittal (Force Main)90% RER(DERM)/FDEP Permit Review (Force Main)90% PWWMD Permit Submittal (Force Main)90% PWWMD Permit Review (Force Main)90% CD PM Comments Evaluation Completed05/07/2015 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed
10/13/2015 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Pre-Bid ConferenceBids Submittal
Bids Evaluation (MDWASD/PSIP Team)MDWASD Issued Notice of Cancellation - Project To Be Re-BidRe-Bid Notice Preparation Period
Re-Bid NoticeMDWASD/PSIP Team Prepare for Re-Bid ConferenceRe-Bid Conference
Bidders Prepare for Re-Bids Submittal
Re-Bids SubmittalRe-Bids Evaluation (MDWASD/PSIP Team)
Recommendation for Award LetterContract Award (Purchase Order Approval)
07/29/2016 A, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Construction NTPConstruction OperationsSubstantial Completion
07/29/2016 A, Designer Construction Services
Designer Construction Support Services07/29/2016 A, Construction Close Out
Punch List08/01/2018, Project Closeout
Closeout PhaseFinal Release of Retainage - Construction Contract
Administrative CloseoutProject Closed08/01/2018, Basin 0435
08/01/2018, 100073 Pump Station 0435 Upgrade09/30/2015 A, Design
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 69 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1000 Design Phase 08/07/2014 A 09/30/2015 A 478B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 08/07/2014 A 08/08/2014 A 5B1020 Engage Design Consultant 08/11/2014 A 01/15/2015 A 20B1030 Issue Design NTP 01/19/2015 A 0B1040 A/E Develops and Submits Final Engineering Report 01/16/2015 A 09/17/2015 A 175B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 01/16/2015 A 04/20/2015 A 85
30% Des30% Design 02/02/2015 A 04/24/2015 A 72B1060 A/E Prepares 30% Construction Documents 03/16/2015 A 04/24/2015 A 30B1070 Geotechnical Engineering Services 02/02/2015 A 03/06/2015 A 20B1080 Surveying Services 02/02/2015 A 03/06/2015 A 15B1100 30% CDs Submittal 03/06/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 03/09/2015 A 03/23/2015 A 7
90% Des90% Design 03/09/2015 A 09/17/2015 A 205B1170 A/E Prepares 90% Construction Documents 03/09/2015 A 04/13/2015 A 30B1180 90% CDs Submittal 04/13/2015 A 0B1190 90% Review (MDWASD/PSIP Team) 04/14/2015 A 04/20/2015 A 15B1200 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 06/25/2015 A 0B1210 90% RER(DERM)/FDEP Permit Review (Pump Station) 06/26/2015 A 08/20/2015 A 15B1236 90% RER (Building Dept) Permit Submittal (Pump Station) 08/25/2015 A 0B1238 90% RER (Building Dept) Permit Review (Pump Station) 08/25/2015 A 09/11/2015 A 15B1240 90% Aventura - BD Permit Submittal (Pump Station) 08/24/2015 A 0B1250 90% Aventura - BD Permit Review (Pump Station) 08/25/2015 A 09/17/2015 A 15B1260 90% CD PM Comments Evaluation Completed 09/17/2015 A 0
100% De100% Design 09/18/2015 A 09/30/2015 A 13B1270 A/E Prepares 100% Construction Documents 09/18/2015 A 09/28/2015 A 10B1280 100% CDs Submittal 09/29/2015 A 0B1290 100% Review (MDWASD/PSIP Team) 09/30/2015 A 09/30/2015 A 10B1300 Design Completed 09/30/2015 A 0
MDWASDMDWASD Procurement 09/30/2015 A 03/08/2016 A 85B1305 Procurement Phase 09/30/2015 A 03/08/2016 A 85B1310 Submit CDs to MDWASD Procurement Division 09/30/2015 A 0B1312 Bid Notice Preparation Period 09/30/2015 A 10/07/2015 A 23B1314 Bid Notice 10/08/2015 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 10/09/2015 A 10/19/2015 A 10B1320 Pre-Bid Conference 10/20/2015 A 10/20/2015 A 1B1328 Bidders Prepare Bids for Submittal 10/21/2015 A 11/19/2015 A 15B1330 Bids Submittal 11/19/2015 A 0B1340 MDWASD/PSIP Team Bids Evaluation 11/20/2015 A 12/07/2015 A 15B1350 Recommendation for Award Letter 12/07/2015 A 0B1355 Contract Award (Purchase Order Approval) 12/08/2015 A 03/08/2016 A 10
ConstrucConstruction 10/20/2015 A 10/31/2016 A 1182B1360 Construction Phase 10/20/2015 A 10/31/2016 A 1182B1364 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 12/08/2015 A 01/04/2016 A 15B1366 Pre-Construction Meeting 01/05/2016 A 01/05/2016 A 1B1368 WASD Issues NTP (PO to NTP) 03/09/2016 A 03/13/2016 A 55B1370 Construction NTP 03/14/2016 A 0B1400 Construction Operations 03/14/2016 A 06/21/2016 A 107B1402 Substantial Completion 06/21/2016 A 0
DesignerDesigner Construction Support Services 10/20/2015 A 10/31/2016 A 295
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book
Engage Design ConsultantIssue Design NTP
A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
04/24/2015 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services
30% CDs Submittal30% Review (MDWASD/PSIP Team)
09/17/2015 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)/FDEP Permit Submittal (Pump Station)
90% RER(DERM)/FDEP Permit Review (Pump Station)90% RER (Building Dept) Permit Submittal (Pump Station)90% RER (Building Dept) Permit Review (Pump Station)
90% Aventura - BD Permit Submittal (Pump Station)90% Aventura - BD Permit Review (Pump Station)90% CD PM Comments Evaluation Completed09/30/2015 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed
03/08/2016 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation Period
Bid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter
Contract Award (Purchase Order Approval)10/31/2016 A, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
WASD Issues NTP (PO to NTP)Construction NTP
Construction OperationsSubstantial Completion
10/31/2016 A, Designer Construction Support Services
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 70 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1410 Designer Construction Support Services 10/20/2015 A 10/31/2016 A 295ConstrucConstruction Close Out 06/22/2016 A 10/31/2016 A 15
B1420 Commissioning 06/22/2016 A 10/31/2016 A 15B1430 Punch List 06/22/2016 A 08/22/2016 A 10
Project CProject Closeout 06/22/2016 A 08/01/2018 719B1445 Closeout Phase 06/22/2016 A 08/01/2018 719B1450 Issue SAC Letter 02/14/2017 A 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 06/22/2016 A 08/01/2018 120B1490 Project Closed 08/01/2018 0
Basin 0439Basin 0439 09/18/2014 A 08/01/2018 1535
100075 Pu100075 Pump Station 0439 Upgrade 09/18/2014 A 08/01/2018 1535DesignDesign 09/18/2014 A 07/18/2016 A 677
B1000 Design Phase 09/18/2014 A 07/18/2016 A 677B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 09/18/2014 A 09/19/2014 A 5B1020 Engage Design Consultant 10/07/2014 A 01/07/2015 A 20B1030 Issue Design NTP 01/07/2015 A 0B1040 A/E Develops and Submits Final Engineering Report 01/07/2015 A 06/08/2016 A 185B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 01/07/2015 A 03/18/2016 A 85
30% Des30% Design 01/08/2015 A 12/02/2015 A 312B1060 A/E Prepares 30% Construction Documents 01/08/2015 A 02/18/2015 A 30B1070 Geotechnical Engineering Services 01/08/2015 A 01/14/2015 A 20B1080 Surveying Services 01/08/2015 A 01/15/2015 A 15B1090 Engage VE Consultant 01/08/2015 A 01/08/2015 A 10B1100 30% CDs Submittal 02/18/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 02/19/2015 A 03/04/2015 A 10B1122 A/E Prepares 30% Construction Documents (Re-Design) 09/29/2015 A 11/05/2015 A 26B1124 30% CDs Submittal (Re-Design) 11/06/2015 A 0B1126 30% Review (MDWASD/PSIP Team) (Re-Design) 11/09/2015 A 12/02/2015 A 10
90% Des90% Design 02/19/2015 A 06/08/2016 A 487B1170 A/E Prepares 90% Construction Documents 02/19/2015 A 03/26/2015 A 20B1180 90% CDs Submittal 03/26/2015 A 0B1190 90% Review (MDWASD/PSIP Team) 03/27/2015 A 04/28/2015 A 15B1193 PSIP Revision to PER (VFD Removal/Pump Change) 04/29/2015 A 09/02/2015 A 15B1195 TA Rev 1 - Approval Process (VFD Removal/Pump Change) 09/03/2015 A 09/23/2015 A 20B1196 90% Plans Revision (VFD Removal/Pump Change) 11/09/2015 A 01/12/2016 A 26B1197 90% Plans Revision Review (MDWASD/PSIP Team) 01/13/2016 A 03/18/2016 A 15B1200 90% RER (DERM)FDEP Permit Submittal (Pump Station) 04/07/2016 A 0B1210 90% RER (DERM)FDEP Permit Review (Pump Station) 04/08/2016 A 05/16/2016 A 15B1212 90% RER (Building Dept) Permit Submittal (Pump Station) 05/23/2016 A 0B1214 90% RER (Building Dept) Permit Review (Pump Station) 05/23/2016 A 06/01/2016 A 15B1220 90% Aventura - BD Permit Submittal 05/20/2016 A 0B1230 90% Aventura - BD Permit Review 05/20/2016 A 06/08/2016 A 15B1260 90% CD PM Comments Evaluation Completed 06/08/2016 A 0
100% De100% Design 06/09/2016 A 07/18/2016 A 43B1270 A/E Prepares 100% Construction Documents 06/09/2016 A 07/18/2016 A 10B1280 100% CDs Submittal 07/18/2016 A 0B1290 100% Review (MDWASD/PSIP Team) 06/09/2016 A 07/18/2016 A 10B1300 Design Completed 07/18/2016 A 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Designer Construction Support Services10/31/2016 A, Construction Close Out
CommissioningPunch List
08/01/2018, Project Closeout
Closeout PhaseIssue SAC Letter
Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed08/01/2018, Basin 0439
08/01/2018, 100075 Pump Station 0439 Upgrade07/18/2016 A, Design
Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book
Engage Design ConsultantIssue Design NTP
A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
12/02/2015 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying ServicesEngage VE Consultant
30% CDs Submittal30% Review (MDWASD/PSIP Team)
A/E Prepares 30% Construction Documents (Re-Design)30% CDs Submittal (Re-Design)
30% Review (MDWASD/PSIP Team) (Re-Design)06/08/2016 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)PSIP Revision to PER (VFD Removal/Pump Change)
TA Rev 1 - Approval Process (VFD Removal/Pump Change)90% Plans Revision (VFD Removal/Pump Change)
90% Plans Revision Review (MDWASD/PSIP Team)90% RER (DERM)FDEP Permit Submittal (Pump Station)
90% RER (DERM)FDEP Permit Review (Pump Station)90% RER (Building Dept) Permit Submittal (Pump Station)90% RER (Building Dept) Permit Review (Pump Station)90% Aventura - BD Permit Submittal90% Aventura - BD Permit Review90% CD PM Comments Evaluation Completed
07/18/2016 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal
100% Review (MDWASD/PSIP Team)Design Completed
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 71 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
MDWASDMDWASD Procurement 05/11/2016 A 08/19/2016 A 65B1305 Procurement Phase 05/11/2016 A 08/19/2016 A 65B1310 Submit CDs to MDWASD Procurement Division 05/11/2016 A 0B1312 Bid Notice Preparation Period 05/12/2016 A 05/24/2016 A 23B1314 Bid Notice 05/25/2016 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 05/26/2016 A 06/20/2016 A 10B1320 Pre-Bid Conference 06/21/2016 A 06/21/2016 A 1B1328 Bidders Prepare Bids for Submittal 06/22/2016 A 06/24/2016 A 15B1330 Bids Submittal 06/24/2016 A 0B1340 MDWASD/PSIP Team Bids Evaluation 06/27/2016 A 07/11/2016 A 15B1350 Recommendation for Award Letter 07/11/2016 A 0B1355 Contract Award (Purchase Order Approval) 07/12/2016 A 08/19/2016 A 10
ConstrucConstruction 06/21/2016 A 02/21/2017 A 930B1360 Construction Phase 06/21/2016 A 02/21/2017 A 930B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 07/12/2016 A 07/20/2016 A 15B1364 Pre-Construction Meeting 07/21/2016 A 07/21/2016 A 1B1369 WASD Issues NTP (PO to NTP) 08/20/2016 A 08/28/2016 A 53B1370 Construction NTP 08/29/2016 A 0B1400 Construction Operations 08/29/2016 A 02/21/2017 A 86B1400 Original Construction Duration 08/29/2016 A 12/27/2016 A 86B1400 Change Order #1 - Contractual Duration, Wet Well Hatcg Shopd 12/28/2016 A 02/16/2017 A 86B1402 Substantial Completion 02/21/2017 A 0
DesignerDesigner Construction Support Services 06/21/2016 A 02/21/2017 A 275B1410 Designer Construction Support Services 06/21/2016 A 02/21/2017 A 275
Project CProject Closeout 08/05/2016 A 08/01/2018 726B1445 Closeout Phase 08/05/2016 A 08/01/2018 726B1450 Issue SAC Leter 08/05/2016 A 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 02/22/2017 A 08/01/2018 120B1490 Project Closed 08/01/2018 0
Basin 0440Basin 0440 09/25/2014 A 03/21/2019 1445
100076-2 B100076-2 Basin 0440 Infiltration/Inflow Study and Repairs 09/25/2014 A 06/09/2016 A 463InfiltratioInfiltration/Inflow 09/25/2014 A 06/08/2016 A 451
B1000 Infiltration/Inflow Phase 09/25/2014 A 06/08/2016 A 451Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 10/23/2015 A 115
B1005 SSES Phase 09/25/2014 A 10/23/2015 A 115B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 06/22/2015 A 10/23/2015 A 30
Dig & ReDig & Replace Repairs 06/26/2015 A 06/08/2016 A 196B1165 Dig & Replace Phase 06/26/2015 A 06/08/2016 A 196B1180 Issue NTP for Dig & Replace Repairs 06/26/2015 A 0B1190 Conduct Dig & Replace Repairs 06/08/2016 A 06/08/2016 A 30
Project CProject Closeout 06/09/2016 A 06/09/2016 A 0B1235 Closeout Phase 06/09/2016 A 06/09/2016 A 0B1260 Project Closed 06/09/2016 A 0
100077 Pu100077 Pump Station 0440 Upgrade Phase 1 06/29/2015 A 08/01/2018 1128DesignDesign 06/29/2015 A 08/16/2016 A 381
B1000 Design Phase 06/29/2015 A 08/16/2016 A 381B1010 Prepare and Submit Design Package 06/29/2015 A 07/15/2015 A 5
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
08/19/2016 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid ConferenceBidders Prepare Bids for SubmittalBids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter
Contract Award (Purchase Order Approval)02/21/2017 A, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
WASD Issues NTP (PO to NTP)
Construction NTPConstruction Operations
Original Construction DurationChange Order #1 - Contractual Duration, Wet Well Hatcg Shopdrawing Approval
Substantial Completion02/21/2017 A, Designer Construction Support Services
Designer Construction Support Services08/01/2018, Project Closeout
Closeout PhaseIssue SAC Leter
Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed
03/21/2019, Basin 0440
06/09/2016 A, 100076-2 Basin 0440 Infiltration/Inflow Study and Repairs06/08/2016 A, Infiltration/Inflow
Infiltration/Inflow Phase10/23/2015 A, Sanitary Sewer Evaluation SurveySSES Phase
Issue NTP to SSES ContractorConduct SSES
06/08/2016 A, Dig & Replace RepairsDig & Replace Phase
Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs06/09/2016 A, Project CloseoutCloseout Phase
Project Closed08/01/2018, 100077 Pump Station 0440 Upgrade Phase 1
08/16/2016 A, Design
Design PhasePrepare and Submit Design Package
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 72 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1020 Engage Design Consultant 06/29/2015 A 09/17/2015 A 20B1021 TA Preparation 09/18/2015 A 09/18/2015 A 1B1022 TA Approval Process 09/21/2015 A 09/25/2015 A 20B1030 Issue Design NTP 10/08/2015 A 0B1040 A/E Develops and Submits Final Engineering Report 10/08/2015 A 05/02/2016 A 101B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/08/2015 A 05/02/2016 A 86
30% Des30% Design 10/09/2015 A 12/23/2015 A 62B1060 A/E Prepares 30% Construction Documents 10/09/2015 A 12/09/2015 A 30B1070 Geotechnical Engineering Services 10/09/2015 A 12/09/2015 A 20B1080 Surveying Services 10/09/2015 A 12/09/2015 A 15B1100 30% CDs Submittal 12/09/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 12/10/2015 A 12/23/2015 A 10
90% Des90% Design 12/10/2015 A 08/16/2016 A 43B1170 A/E Prepares 90% Construction Documents 12/10/2015 A 04/06/2016 A 20B1180 90% CDs Submittal 04/06/2016 A 0B1190 90% Review (MDWASD/PSIP Team) 04/07/2016 A 05/02/2016 A 15B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 06/13/2016 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 06/13/2016 A 08/16/2016 A 15
Project CProject Closeout 09/09/2016 A 08/01/2018 762B1445 Closeout Phase 09/09/2016 A 08/01/2018 762B1448 Project Cancellation Approval Process 09/09/2016 A 09/20/2016 A 15B1480 Administrative Closeout 09/21/2016 A 08/01/2018 30B1490 Project Closed 08/01/2018 0
100245 Pu100245 Pump Station 0440 Upgrade Phase 2 10/30/2015 A 03/21/2019 1239Land AcqLand Acquisition 05/23/2016 A 05/04/2018 A 119
B0900 Land Acquisition Phase 05/23/2016 A 05/04/2018 A 119DesignDesign 10/30/2015 A 05/23/2018 A 946
B1000 Design Phase 10/30/2015 A 05/23/2018 A 946B1005 Prepare and Submit Design Package 10/30/2015 A 10/30/2015 A 5B1010 Engage Design Consultant 10/30/2015 A 01/27/2016 A 20B1018 TA Preparation 01/28/2016 A 01/28/2016 A 1B1020 TA Approval Process 01/29/2016 A 04/04/2016 A 20B1030 Issue Design NTP 04/14/2016 A 0B1031 WASD/PSIP Team Engage Design Consultant After 30% Subm 05/23/2016 A 12/01/2016 A 20B1032 TA Rev 1 Preparation 12/02/2016 A 12/02/2016 A 1B1034 TA Rev 1 Approval Process 12/05/2016 A 04/03/2017 A 40B1036 Issue 90% Design NTP 04/17/2017 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 04/14/2016 A 05/23/2018 A 85
30% Des30% Design 04/14/2016 A 06/20/2016 A 33B1060 A/E Prepares 30% Construction Documents 04/14/2016 A 05/20/2016 A 30B1070 Geotechnical Engineering Services 04/14/2016 A 05/20/2016 A 20B1080 Surveying Services 04/14/2016 A 05/20/2016 A 15B1100 30% CDs Submittal 05/20/2016 A 0B1120 30% Review (MDWASD/PSIP Team) 05/23/2016 A 06/20/2016 A 10
90% Des90% Design 04/17/2017 A 05/23/2018 A 424B1170 A/E Prepares 90% Construction Documents 04/17/2017 A 06/30/2017 A 40B1180 90% CDs Submittal 06/30/2017 A 0B1190 90% Review (MDWASD/PSIP Team) 07/03/2017 A 08/14/2017 A 30B1200 90% RER (DERM) FDEP Permit Submittal 10/02/2017 A 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Engage Design ConsultantTA PreparationTA Approval Process
Issue Design NTPA/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
12/23/2015 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal30% Review (MDWASD/PSIP Team)
08/16/2016 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)
90% RER(DERM)FDEP Permit Review (Pump Station)08/01/2018, Project Closeout
Closeout PhaseProject Cancellation Approval Process
Administrative CloseoutProject Closed
03/21/2019, 100245 Pump Station 0440 U05/04/2018 A, Land Acquisition
Land Acquisition Phase05/23/2018 A, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval ProcessIssue Design NTP
WASD/PSIP Team Engage Design Consultant After 30% SubmittalTA Rev 1 Preparation
TA Rev 1 Approval Process
Issue 90% Design NTPFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
06/20/2016 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal
30% Review (MDWASD/PSIP Team)05/23/2018 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER (DERM) FDEP Permit Submittal
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 73 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1210 90% RER (DERM) FDEP Permit Review 10/02/2017 A 03/30/2018 A 45B1220 90% Miami Garden (Building Dept) Permit Submittal 04/04/2018 A 0B1230 90% Miami Garden (Building Dept) Permit Review 04/04/2018 A 05/23/2018 A 21B1260 90% CD PM Comments Evaluation Completed 05/23/2018 A 0B1262 MDWASD Union Concurrence Process 07/06/2017 A 07/31/2017 A 30
100% De100% Design 05/02/2018 A 05/04/2018 A 28B1270 A/E Prepares 100% Construction Documents 05/02/2018 A 05/04/2018 A 14B1280 100% CDs Submittal 05/04/2018 A 0B1290 100% Review (MDWASD/PSIP Team) 05/04/2018 A 05/04/2018 A 14B1300 Design Completed 05/04/2018 A 0
MDWASDMDWASD Procurement 06/08/2018 A 10/05/2018 127B1305 Procurement Phase 06/08/2018 A 10/05/2018 127B1310 Submit CDs to MDWASD Procurement Division 06/08/2018 A 0B1312 Bid Notice Preparation Period 06/09/2018 A 06/28/2018 A 33B1313 Bid Notice 06/28/2018 A 0B1315 MDWASD/PSIP Team Prepare for Pre-Bid Conferencce 06/29/2018 A 07/16/2018 A 14B1320 Pre-Bid Conference 07/17/2018 A 07/17/2018 A 1B1323 Bidders Prepare Bids for Submittal 07/18/2018 A 08/31/2018 21B1324 FPL Feeder Route Resolution 06/08/2018 A 08/31/2018 21B1330 Bids Submittal 08/31/2018 0B1340 MDWASD/PSIP Team Bids Evaluation 09/01/2018 09/21/2018 21B1350 Recommendation for Award Letter 09/21/2018 0B1355 Contract Award (Purchase Order Approval) 09/22/2018 10/05/2018 14B1480 Bidders Prepare Bids for Submittal 07/18/2018 A 08/17/2018 21
ConstrucConstruction 07/17/2018 A 11/22/2018 119B1357 Construction Phase 07/17/2018 A 11/22/2018 119B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 09/22/2018 10/06/2018 15B1365 Pre-Construction Meeting 10/07/2018 10/07/2018 1B1366 WASD Issues NTP (Pre-Const to NTP) 10/08/2018 11/21/2018 45B1368 WASD Issues NTP (PO to NTP) 10/06/2018 11/21/2018 47B1369 Construction NTP 11/22/2018 0B1390 Construction Operations 11/22/2018 11/22/2018 0B1395 Substantial Completion 11/22/2018 0
DesignerDesigner Construction Support Services 07/17/2018 A 11/21/2018 104B1397 Designer Construction Support Services 07/17/2018 A 11/21/2018 104
Project CProject Closeout 08/05/2016 A 03/21/2019 958B1425 Closeout Phase 08/05/2016 A 03/21/2019 958B1430 Issue SAC Letter 08/05/2016 A 0B1450 Final Release of Retainage - Construction Contract 11/22/2018 0B1460 Administrative Closeout 11/22/2018 03/21/2019 120B1470 Project Closed 03/21/2019 0
Basin 0442Basin 0442 04/19/2016 A 12/13/2019 1188
100078 Pu100078 Pump Station 0442 Upgrade 04/19/2016 A 12/13/2019 1188DesignDesign 04/19/2016 A 09/18/2018 737
B1000 Design Phase 04/19/2016 A 09/18/2018 737B1010 Prepare and Submit Design Package 04/19/2016 A 04/22/2016 A 5B1020 Engage Design Consultant 04/22/2016 A 09/13/2016 A 20B1022 TA Preparation 09/14/2016 A 09/14/2016 A 1B1024 TA Approval Process 09/15/2016 A 11/15/2016 A 20
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
90% RER (DERM) FDEP Permit Review90% Miami Garden (Building Dept) Permit Submittal
90% Miami Garden (Building Dept) Permit Review90% CD PM Comments Evaluation Completed
MDWASD Union Concurrence Process05/04/2018 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal
100% Review (MDWASD/PSIP Team)Design Completed
10/05/2018, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferenccePre-Bid Conference
Bidders Prepare Bids for SubmittalFPL Feeder Route Resolution
Bids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)
Bidders Prepare Bids for Submittal11/22/2018, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)
WASD Issues NTP (PO to NTP)Construction NTPConstruction OperationsSubstantial Completion11/21/2018, Designer Construction Support Services
Designer Construction Support Services03/21/2019, Project Closeout
Closeout PhaseIssue SAC Letter
Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed
12/13/2019, Basin 04
12/13/2019, 100078 09/18/2018, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval Process
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 74 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1030 Issue Design NTP 11/18/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 11/18/2016 A 08/21/2018 65
30% Des30% Design 11/18/2016 A 05/08/2017 A 107B1060 A/E Prepares 30% Construction Documents 11/18/2016 A 02/09/2017 A 50B1100 30% CDs Submittal 02/09/2017 A 0B1120 30% Review (MDWASD/PSIP Team) 02/10/2017 A 05/08/2017 A 30
90% Des90% Design 02/10/2017 A 08/21/2018 567B1170 A/E Prepares 90% Construction Documents 02/10/2017 A 06/30/2017 A 40B1180 90% CDs Submittal 06/30/2017 A 0B1190 90% Review (MDWASD/PSIP Team) 07/03/2017 A 07/25/2017 A 30B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 08/28/2017 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 08/28/2017 A 02/22/2018 A 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 02/22/2018 A 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 02/22/2018 A 08/01/2018 21B1240 90% Miami Gardens - PWD Permit Submittal (Pump Station) 08/01/2018 0B1250 90% Miami Gardens - PWD Permit Review (Pump Station) 08/01/2018 08/21/2018 21B1252 90% Miami Gardens - BD Permit Submittal (Pump Station) 08/01/2018 0B1254 90% Miami Gardens - BD Permit Review (Pump Station) 08/01/2018 08/21/2018 21B1260 90% CD PM Comments Evaluation Completed 08/21/2018 0B1262 MDWASD Union Concurrence Process 07/06/2017 A 07/31/2017 A 30
100% De100% Design 08/22/2018 09/18/2018 28B1270 A/E Prepares 100% Construction Documents 08/22/2018 09/04/2018 14B1280 100% CDs Submittal 09/04/2018 0B1290 100% Review (MDWASD/PSIP Team) 09/05/2018 09/18/2018 14B1300 Design Completed 09/18/2018 0
MDWASDMDWASD Procurement 09/18/2018 12/31/2018 104B1305 Procurement Phase 09/18/2018 12/31/2018 104B1310 Submit CDs to MDWASD Procurement Division 09/18/2018 0B1312 Bid Notice Preparation Period 09/19/2018 10/21/2018 33B1314 Bid Notice 10/21/2018 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 10/22/2018 11/04/2018 14B1320 Pre-Bid Conference 11/05/2018 11/05/2018 1B1322 Bidders Prepare Bids for Submittal 11/06/2018 11/26/2018 21B1330 Bids Submittal 11/26/2018 0B1340 MDWASD/PSIP Team Bids Evaluation 11/27/2018 12/17/2018 21B1350 Recommendation for Award Letter 12/17/2018 0B1355 Contract Award (Purchase Order Approval) 12/18/2018 12/31/2018 14
ConstrucConstruction 11/05/2018 08/15/2019 284B1360 Construction Phase 11/05/2018 08/15/2019 284B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 12/18/2018 01/01/2019 15B1364 Pre-Construction Meeting 01/02/2019 01/02/2019 1B1366 WASD Issues NTP (Pre-Const to NTP) 01/03/2019 02/16/2019 45B1368 WASD Issues NTP (PO to NTP) 01/01/2019 02/16/2019 47B1370 Construction NTP 02/17/2019 0B1400 Construction Operations 02/17/2019 08/15/2019 180B1402 Substantial Completion 08/15/2019 0
DesignerDesigner Construction Support Services 11/05/2018 08/15/2019 284B1410 Designer Construction Support Services 11/05/2018 08/15/2019 284
Project CProject Closeout 08/15/2019 12/13/2019 120
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Issue Design NTPFinal Engineering Report Review & Approval (MDWASD/PSIP
05/08/2017 A, 30% Design
A/E Prepares 30% Construction Documents30% CDs Submittal
30% Review (MDWASD/PSIP Team)08/21/2018, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)
90% RER(DERM)FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)
90% RER(Building Dept) Permit Review (Pump Station)90% Miami Gardens - PWD Permit Submittal (Pump Station)
90% Miami Gardens - PWD Permit Review (Pump Station)90% Miami Gardens - BD Permit Submittal (Pump Station)
90% Miami Gardens - BD Permit Review (Pump Station)90% CD PM Comments Evaluation Completed
MDWASD Union Concurrence Process09/18/2018, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed
12/31/2018, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)
08/15/2019, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-ConstructioPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Construction NTPConstruction OperationsSubstantial Completion08/15/2019, Designer Construc
Designer Construction Support 12/13/2019, Project C
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 75 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1445 Closeout Phase 08/15/2019 12/13/2019 120B1450 Issue SAC Letter 08/15/2019 0B1470 Final Release of Retainage - Construction Contract 08/15/2019 0B1480 Administrative Closeout 08/16/2019 12/13/2019 120B1490 Project Closed 12/13/2019 0
Basin 0449Basin 0449 05/14/2014 A 08/01/2018 1680
100082 Pu100082 Pump Station 0449 Upgrade (PS 460) 05/14/2014 A 01/05/2015 A 19PlanningPlanning 05/14/2014 A 01/05/2015 A 19
B0900 Planning Phase 05/14/2014 A 01/05/2015 A 19B0940 Develop Remedial Action Plan (RAP) 05/14/2014 A 05/22/2014 A 7B0950 Develop Preliminary Engineering Report (PER) 05/15/2014 A 01/05/2015 A 10
100080 FM100080 FM for Pump Station 0449 (PS 460) 05/14/2014 A 01/05/2015 A 19PlanningPlanning 05/14/2014 A 01/05/2015 A 19
B0900 Planning Phase 05/14/2014 A 01/05/2015 A 19B0940 Develop Remedial Action Plan (RAP) 05/14/2014 A 05/22/2014 A 7B0950 Develop Preliminary Engineering Report (PER) 05/23/2014 A 01/05/2015 A 10
100083 Pu100083 Pump Station 0449 Upgrade 07/30/2014 A 08/01/2018 1601DesignDesign 07/30/2014 A 05/26/2016 A 728
B1000 Design Phase 07/30/2014 A 05/26/2016 A 728B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 07/30/2014 A 08/07/2014 A 5B1020 Engage Design Consultant 08/08/2014 A 11/19/2014 A 20B1030 Issue Design NTP 11/20/2014 A 0B1040 A/E Develops and Submits Final Engineering Report 11/20/2014 A 05/09/2016 A 279B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 11/20/2014 A 11/27/2015 A 228
30% Des30% Design 11/20/2014 A 02/13/2015 A 56B1060 A/E Prepares 30% Construction Documents 11/20/2014 A 01/21/2015 A 30B1070 Geotechnical Engineering Services 11/20/2014 A 01/21/2015 A 20B1080 Surveying Services 11/20/2014 A 01/21/2015 A 15B1100 30% CDs Submittal 01/21/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 01/22/2015 A 02/13/2015 A 10
60% Des60% Design 01/22/2015 A 02/13/2015 A 24B1130 A/E Prepares 60% Construction Documents (Progress Set) 01/22/2015 A 02/13/2015 A 20B1140 60% CDs Submittal (Progress Set) 02/13/2015 A 0B1160 60% On-Board Review (Progress Set) 02/13/2015 A 02/13/2015 A 10
90% Des90% Design 02/16/2015 A 05/09/2016 A 487B1170 A/E Prepares 90% Construction Documents 02/16/2015 A 06/15/2015 A 20B1171 FM 0449 - TA Rev 1 Submission and Approval 02/18/2015 A 04/03/2015 A 20B1172 FM 0449 - Add FM to Project 04/06/2015 A 05/29/2015 A 20B1180 90% CDs Submittal 06/15/2015 A 0B1190 90% Review (MDWASD/PSIP Team) 06/15/2015 A 11/27/2015 A 15B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 11/30/2015 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 11/30/2015 A 03/01/2016 A 15B1220 90% Miami Gardens - BD Permit Submittal 03/02/2016 A 0B1230 90% Miami Gardens - BD Permit Review 03/02/2016 A 05/09/2016 A 15B1260 90% CD PM Comments Evaluation Completed 05/09/2016 A 0
100% De100% Design 05/10/2016 A 05/26/2016 A 28B1270 A/E Prepares 100% Construction Documents 05/10/2016 A 05/26/2016 A 10B1280 100% CDs Submittal 05/26/2016 A 0B1290 100% Review (MDWASD/PSIP Team) 05/10/2016 A 05/26/2016 A 10
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Closeout PhaseIssue SAC LetterFinal Release of Retainage - Co
Administrative CloseoProject Closed
08/01/2018, Basin 0449
01/05/2015 A, 100082 Pump Station 0449 Upgrade (PS 460)01/05/2015 A, PlanningPlanning Phase
Develop Remedial Action Plan (RAP)Develop Preliminary Engineering Report (PER)01/05/2015 A, 100080 FM for Pump Station 0449 (PS 460)01/05/2015 A, PlanningPlanning Phase
Develop Remedial Action Plan (RAP)Develop Preliminary Engineering Report (PER)
08/01/2018, 100083 Pump Station 0449 Upgrade05/26/2016 A, Design
Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book
Engage Design ConsultantIssue Design NTP
A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
02/13/2015 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services
30% CDs Submittal30% Review (MDWASD/PSIP Team)02/13/2015 A, 60% Design
A/E Prepares 60% Construction Documents (Progress Set)60% CDs Submittal (Progress Set)60% On-Board Review (Progress Set)
05/09/2016 A, 90% Design
A/E Prepares 90% Construction DocumentsFM 0449 - TA Rev 1 Submission and Approval
FM 0449 - Add FM to Project90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)
90% RER(DERM)FDEP Permit Review (Pump Station)90% Miami Gardens - BD Permit Submittal90% Miami Gardens - BD Permit Review
90% CD PM Comments Evaluation Completed05/26/2016 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal
100% Review (MDWASD/PSIP Team)
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 76 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1300 Design Completed 05/26/2016 A 0MDWASDMDWASD Procurement 03/02/2016 A 07/06/2016 A 97
B1305 Procurement Phase 03/02/2016 A 07/06/2016 A 97B1310 Submit CDs to MDWASD Procurement Division 03/02/2016 A 0B1312 Bid Notice Preparation Period 03/03/2016 A 03/15/2016 A 23B1314 Bid Notice 03/15/2016 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 03/16/2016 A 04/05/2016 A 10B1320 Pre-Bid Conference 04/06/2016 A 04/06/2016 A 1B1322 Bidders Prepare Bids for Submittal 04/07/2016 A 05/13/2016 A 15B1330 Bids Submittal 05/16/2016 A 0B1340 MDWASD/PSIP Team Bids Evaluation 05/13/2016 A 05/24/2016 A 15B1350 Recommendation for Award Letter 05/25/2016 A 0B1355 Contract Award (Purchase Order Approval) 05/26/2016 A 07/06/2016 A 10
ConstrucConstruction 04/06/2016 A 01/18/2017 A 960B1360 Construction Phase 04/06/2016 A 01/18/2017 A 960B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 05/26/2016 A 07/06/2016 A 15B1365 Pre-Construction Meeting 07/07/2016 A 07/07/2016 A 1B1366 TA Rev 2 - Approval Process 07/11/2016 A 09/28/2016 A 20B1369 WASD Issues NTP (PO to NTP) 07/07/2016 A 07/31/2016 A 53B1370 Construction NTP 08/01/2016 A 0B1400 Construction Operations 08/01/2016 A 12/28/2016 A 107B1402 Substantial Completion 12/28/2016 A 0
DesignerDesigner Construction Support Services 04/06/2016 A 01/18/2017 A 275B1410 Designer Construction Support Services 04/06/2016 A 01/18/2017 A 275
ConstrucConstruction Close Out 12/29/2016 A 01/18/2017 A 15B1420 Commissioning 12/29/2016 A 01/18/2017 A 15B1430 Punch List 12/29/2016 A 01/11/2017 A 10
Project CProject Closeout 08/05/2016 A 08/01/2018 726B1445 Closeout Phase 08/05/2016 A 08/01/2018 726B1450 Issue SAC Letter 08/05/2016 A 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 12/29/2016 A 08/01/2018 120B1490 Project Closed 08/01/2018 0
Basin 0456Basin 0456 09/25/2014 A 02/02/2020 1946
100084 Pu100084 Pump Station 0456 Upgrade 01/08/2018 A 04/30/2019 485DesignDesign 01/08/2018 A 08/31/2018 243
B1000 Design Phase 01/08/2018 A 08/31/2018 243B1010 Prepare and Submit Design Package 01/08/2018 A 01/08/2018 A 7B1020 Engage Design Consultant 01/09/2018 A 02/05/2018 A 28B1022 TA Preparation 02/06/2018 A 02/07/2018 A 7B1024 TA Approval Process 02/08/2018 A 03/17/2018 A 20B1030 Issue Design NTP 03/26/2018 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 03/26/2018 A 08/17/2018 80
30% Des30% Design 03/26/2018 A 08/01/2018 149B1060 A/E Prepares 30% Construction Documents 03/26/2018 A 05/15/2018 A 21B1100 30% CDs Submittal 05/15/2018 A 0B1120 30% Review (MDWASD/PSIP Team) 08/01/2018 08/01/2018 1
90% Des90% Design 03/26/2018 A 08/17/2018 108B1170 A/E Prepares 90% Construction Documents 03/26/2018 A 05/15/2018 A 22
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Design Completed07/06/2016 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids SubmittalMDWASD/PSIP Team Bids Evaluation
Recommendation for Award LetterContract Award (Purchase Order Approval)
01/18/2017 A, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
TA Rev 2 - Approval ProcessWASD Issues NTP (PO to NTP)
Construction NTPConstruction OperationsSubstantial Completion
01/18/2017 A, Designer Construction Support Services
Designer Construction Support Services01/18/2017 A, Construction Close Out
CommissioningPunch List
08/01/2018, Project Closeout
Closeout PhaseIssue SAC Letter
Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed
02/02/2020, Basin
04/30/2019, 100084 Pump Station 04508/31/2018, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval Process
Issue Design NTPFinal Engineering Report Review & Approval (MDWASD/PSIP
08/01/2018, 30% Design
A/E Prepares 30% Construction Documents30% CDs Submittal
30% Review (MDWASD/PSIP Team)08/17/2018, 90% Design
A/E Prepares 90% Construction Documents
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 77 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1180 90% CDs Submittal 05/15/2018 A 0B1190 90% Review (MDWASD/PSIP Team) 05/16/2018 A 06/14/2018 A 7B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 06/15/2018 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 06/15/2018 A 08/02/2018 15B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 08/03/2018 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 08/03/2018 08/17/2018 15B1260 90% CD PM Comments Evaluation Completed 08/17/2018 0
100% De100% Design 08/18/2018 08/31/2018 14B1270 A/E Prepares 100% Construction Documents 08/18/2018 08/24/2018 7B1280 100% CDs Submittal 08/24/2018 0B1290 100% Review (MDWASD/PSIP Team) 08/25/2018 08/31/2018 7B1300 Design Completed 08/31/2018 0
MDWASDMDWASD Procurement 08/31/2018 10/27/2018 57B1305 Procurement Phase 08/31/2018 10/27/2018 57B1310 Submit CDs to MDWASD Procurement Division 08/31/2018 0B1312 Bid Notice Preparation Period 09/01/2018 09/20/2018 20B1314 Bid Notice 09/20/2018 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conferencce 09/21/2018 09/27/2018 7B1320 Pre-Bid Conference 09/28/2018 09/28/2018 1B1328 Bidders Prepare Bids for Submittal 09/29/2018 10/13/2018 15B1330 Bids Submittal 10/13/2018 0B1340 MDWASD/PSIP Team Bids Evaluation 10/14/2018 10/20/2018 7B1350 Recommendation for Award Letter 10/20/2018 0B1355 Contract Award (Purchase Order Approval) 10/21/2018 10/27/2018 7
ConstrucConstruction 09/28/2018 12/31/2018 95B1360 Construction Phase 09/28/2018 12/31/2018 95B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 10/21/2018 11/10/2018 21B1364 Pre-Construction Meeting 11/11/2018 11/11/2018 1B1366 WASD Issues NTP (Pre-Const to NTP) 11/12/2018 11/25/2018 14B1368 WASD Issues NTP (PO to NTP) 10/28/2018 11/25/2018 29B1370 Construction NTP 11/26/2018 0B1400 Construction Operations 11/26/2018 12/31/2018 36B1402 Substantial Completion 12/31/2018 0
DesignerDesigner Construction Support Services 09/28/2018 12/31/2018 95B1410 Designer Construction Support Services 09/28/2018 12/31/2018 95
Project CProject Closeout 12/31/2018 04/30/2019 120B1445 Closeout Phase 12/31/2018 04/30/2019 120B1450 Issue SAC Letter 12/31/2018 0B1470 Final Release of Retainage - Construction Contract 12/31/2018 0B1480 Administrative Closeout 01/01/2019 04/30/2019 120B1490 Project Closed 04/30/2019 0
100085 Pu100085 Pump Station 0456 Upgrade (PS 0454 Generator) 12/14/2017 A 02/02/2020 780DesignDesign 08/01/2018 06/08/2019 312
B1000 Design Phase 08/01/2018 06/08/2019 312B1010 Prepare and Submit Design Package 08/01/2018* 08/05/2018 5B1020 Engage Design Consultant 08/06/2018 08/25/2018 20B1022 TA Preparation 08/26/2018 08/26/2018 1B1024 TA Approval Process 08/27/2018 10/05/2018 40B1030 Issue Design NTP 10/06/2018 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
90% CDs Submittal90% Review (MDWASD/PSIP Team)
90% RER(DERM)FDEP Permit Submittal (Pump Station)90% RER(DERM)FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)90% RER(Building Dept) Permit Review (Pump Station)90% CD PM Comments Evaluation Completed08/31/2018, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed
10/27/2018, MDWASD ProcurementProcurement Phase
Submit CDs to MDWASD Procurement DivisionBid Notice Preparation Period
Bid NoticeMDWASD/PSIP Team Prepare for Pre-Bid Conferencce
Pre-Bid ConferenceBidders Prepare Bids for Submittal
Bids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)
12/31/2018, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MPre-Construction MeetingWASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Construction NTPConstruction OperationsSubstantial Completion12/31/2018, Designer Construction Support Servic
Designer Construction Support Services04/30/2019, Project CloseoutCloseout Phase
Issue SAC LetterFinal Release of Retainage - Construction Contrac
Administrative CloseoutProject Closed
02/02/2020, 100006/08/2019, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval Process
Issue Design NTP
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 78 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/06/2018 05/09/2019 21630% Des30% Design 10/06/2018 12/24/2018 80
B1060 A/E Prepares 30% Construction Documents 10/06/2018 11/24/2018 50B1090 30% CDs Submittal 11/24/2018 0B1100 30% Review (MDWASD/PSIP Team) 11/25/2018 12/24/2018 30
60% Des60% Design 11/25/2018 01/03/2019 40B1110 A/E Prepares 60% Construction Documents 11/25/2018 12/24/2018 30B1120 60% CDs Submittal 12/24/2018 0B1140 60% Review (MDWASD/PSIP Team) 12/25/2018 01/03/2019 10
90% Des90% Design 12/25/2018 06/08/2019 166B1150 A/E Prepares 90% Construction Documents 12/25/2018 02/02/2019 40B1160 90% CDs Submittal 02/02/2019 0B1170 90% Review (MDWASD/PSIP Team) 02/03/2019 03/04/2019 30B1180 90% RER(DERM)FDEP Permit Submittal (Pump Station) 03/05/2019 0B1190 90% RER(DERM)FDEP Permit Review (Pump Station) 03/05/2019 04/18/2019 45B1200 90% RER(Building Dept) Permit Submittal (Pump Station) 04/19/2019 0B1210 90% RER(Building Dept) Permit Review (Pump Station) 04/19/2019 05/09/2019 21B1220 90% Municipality Permit Submittal (Pump Station) 04/19/2019 0B1230 90% Municipality Permit Review (Pump Station) 04/19/2019 05/03/2019 15B1240 90% CD PM Comments Evaluation Completed 05/09/2019 0B1242 MDWASD Union Concurrence Process 05/10/2019 06/08/2019 30
100% De100% Design 05/10/2019 05/29/2019 20B1250 A/E Prepares 100% Construction Documents 05/10/2019 05/19/2019 10B1260 100% CDs Submittal 05/19/2019 0B1270 100% Review (MDWASD/PSIP Team) 05/20/2019 05/29/2019 10B1280 Design Completed 05/29/2019 0
MDWASDMDWASD Procurement 06/08/2019 08/21/2019 74B1285 Procurement Phase 06/08/2019 08/21/2019 74B1290 Submit CDs to MDWASD Procurement Division 06/08/2019 0B1292 Bid Notice Preparation Period 06/09/2019 07/01/2019 23B1294 Bid Notice 07/01/2019 0B1296 MDWASD/PSIP Team Prepare for Pre-Bid Conferencce 07/02/2019 07/11/2019 10B1300 Pre-Bid Conference 07/12/2019 07/12/2019 1B1302 Bidders Prepare Bids for Submittal 07/13/2019 07/27/2019 15B1310 Bids Submittal 07/27/2019 0B1320 MDWASD/PSIP Team Bids Evaluation 07/28/2019 08/11/2019 15B1330 Recommendation for Award Letter 08/11/2019 0B1335 Contract Award (Purchase Order Approval) 08/12/2019 08/21/2019 10
ConstrucConstruction 07/12/2019 01/13/2020 186B1340 Construction Phase 07/12/2019 01/13/2020 186B1342 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 08/12/2019 08/26/2019 15B1344 Pre-Construction Meeting 08/27/2019 08/27/2019 1B1350 Construction NTP 08/28/2019 0B1380 Construction Operations 08/28/2019 01/03/2020 129B1382 Substantial Completion 01/03/2020 0
DesignerDesigner Construction Support Services 07/12/2019 01/13/2020 186B1390 Designer Construction Support Services 07/12/2019 01/13/2020 186
ConstrucConstruction Close Out 01/04/2020 01/13/2020 10B1400 Commissioning 01/04/2020 01/08/2020 5
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Final Engineering Report Review & App12/24/2018, 30% Design
A/E Prepares 30% Construction Documents30% CDs Submittal
30% Review (MDWASD/PSIP Team)01/03/2019, 60% Design
A/E Prepares 60% Construction Documents60% CDs Submittal60% Review (MDWASD/PSIP Team)
06/08/2019, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pu
90% RER(DERM)FDEP Permit Review (P90% RER(Building Dept) Permit Submitta
90% RER(Building Dept) Permit Review 90% Municipality Permit Submittal (Pump90% Municipality Permit Review (Pump 90% CD PM Comments Evaluation Com
MDWASD Union Concurrence Proces05/29/2019, 100% Design
A/E Prepares 100% Construction Docu100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed
08/21/2019, MDWASD ProcureProcurement Phase
Submit CDs to MDWASD ProcuremeBid Notice Preparation Period
Bid NoticeMDWASD/PSIP Team Prepare for
Pre-Bid ConferenceBidders Prepare Bids for Submitt
Bids SubmittalMDWASD/PSIP Team Bids EvalRecommendation for Award LetContract Award (Purchase Orde
01/13/2020, Constr
Construction PhaseMDWASD/PSIP Team PreparePre-Construction Meeting
Construction NTPConstruction OperatSubstantial Complet01/13/2020, Design
Designer Construct01/13/2020, Constr
Commissioning
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 79 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1410 Punch List 01/04/2020 01/13/2020 10Project CProject Closeout 12/14/2017 A 02/02/2020 780
B1425 Closeout Phase 12/14/2017 A 02/02/2020 780B1430 Issue SAC Letter 12/14/2017 A 0B1450 Final Release of Retainage - Construction Contract 01/13/2020 0B1460 Administrative Closeout 01/04/2020 02/02/2020 30B1470 Project Closed 02/02/2020 0
100187 Ba100187 Basin 0456 Infiltration/Inflow Study and Repairs 09/25/2014 A 09/04/2015 A 604InfiltratioInfiltration/Inflow 09/25/2014 A 09/03/2015 A 331
B1000 Infiltration/Inflow Phase 09/25/2014 A 09/03/2015 A 331Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 09/03/2015 A 331
B1005 SSES Phase 09/25/2014 A 09/03/2015 A 331B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 07/30/2015 A 09/03/2015 A 30
Project CProject Closeout 09/04/2015 A 09/04/2015 A 0B1235 Closeout Phase 09/04/2015 A 09/04/2015 A 0B1260 Project Closed 09/04/2015 A 0
Basin 0473Basin 0473 12/09/2015 A 08/01/2018 1067
100086 Pu100086 Pump Station 0473(AM) Upgrade 12/09/2015 A 08/01/2018 1067DesignDesign 12/09/2015 A 12/15/2016 A 393
B1000 Design Phase 12/09/2015 A 12/15/2016 A 393B1010 Prepare and Submit Design Package 12/09/2015 A 12/16/2015 A 5B1020 Engage Design Consultant 12/17/2015 A 12/28/2015 A 20B1022 TA Preparation 12/29/2015 A 12/29/2015 A 1B1024 TA Approval Process 12/30/2015 A 01/14/2016 A 20B1030 Issue Design NTP 01/27/2016 A 0B1040 A/E Develops and Submits Final Engineering Report 01/27/2016 A 12/07/2016 A 115B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 01/27/2016 A 08/25/2016 A 85
30% Des30% Design 01/27/2016 A 04/25/2016 A 52B1060 A/E Prepares 30% Construction Documents 01/27/2016 A 03/15/2016 A 30B1070 Geotechnical Engineering Services 01/27/2016 A 03/15/2016 A 20B1080 Surveying Services 01/27/2016 A 03/15/2016 A 15B1100 30% CDs Submittal 03/15/2016 A 0B1120 30% Review (MDWASD/PSIP Team) 03/15/2016 A 04/25/2016 A 10
60% Des60% Design 03/16/2016 A 06/20/2016 A 99B1130 A/E Prepares 60% Construction Documents 03/16/2016 A 05/24/2016 A 20B1140 60% CDs Submittal 05/24/2016 A 0B1160 60% Review (MDWASD/PSIP Team) 05/25/2016 A 06/20/2016 A 10
90% Des90% Design 05/25/2016 A 12/07/2016 A 190B1170 A/E Prepares 90% Construction Documents 05/25/2016 A 07/22/2016 A 20B1180 90% CDs Submittal 07/22/2016 A 0B1190 90% Review (MDWASD/PSIP Team) 07/25/2016 A 09/14/2016 A 15B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 09/26/2016 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 09/26/2016 A 11/30/2016 A 15B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 11/09/2016 A 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 11/09/2016 A 12/07/2016 A 15B1260 90% CD PM Comments Evaluation Completed 12/07/2016 A 0
100% De100% Design 12/08/2016 A 12/15/2016 A 28B1270 A/E Prepares 100% Construction Documents 12/08/2016 A 12/13/2016 A 10
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Punch List02/02/2020, ProjeCloseout Phase
Issue SAC LetterFinal Release of Re
Administrative CloProject Closed
09/04/2015 A, 100187 Basin 0456 Infiltration/Inflow Study and Repairs09/03/2015 A, Infiltration/Inflow
Infiltration/Inflow Phase09/03/2015 A, Sanitary Sewer Evaluation SurveySSES Phase
Issue NTP to SSES ContractorConduct SSES09/04/2015 A, Project CloseoutCloseout Phase
Project Closed08/01/2018, Basin 0473
08/01/2018, 100086 Pump Station 0473(AM) Upgrade12/15/2016 A, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval ProcessIssue Design NTP
A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
04/25/2016 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal
30% Review (MDWASD/PSIP Team)06/20/2016 A, 60% Design
A/E Prepares 60% Construction Documents60% CDs Submittal60% Review (MDWASD/PSIP Team)
12/07/2016 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)
90% RER(DERM)FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)
90% RER(Building Dept) Permit Review (Pump Station)90% CD PM Comments Evaluation Completed12/15/2016 A, 100% Design
A/E Prepares 100% Construction Documents
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 80 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1280 100% CDs Submittal 12/13/2016 A 0B1290 100% Review (MDWASD/PSIP Team) 12/13/2016 A 12/15/2016 A 10B1300 Design Completed 12/15/2016 A 0
MDWASDMDWASD Procurement 12/15/2016 A 03/27/2017 A 57B1305 Procurement Phase 12/15/2016 A 03/27/2017 A 57B1310 Submit CDs to MDWASD Procurement Division 12/15/2016 A 0B1312 Bid Notice Preparation Period 12/16/2016 A 12/20/2016 A 23B1314 Bid Notice 12/20/2016 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 12/21/2016 A 01/09/2017 A 10B1320 Pre-Bid Conference 01/10/2017 A 01/10/2017 A 1B1328 Bidders Prepare Bids for Submittal 01/11/2017 A 01/30/2017 A 14B1330 Bids Submittal 01/30/2017 A 0B1340 MDWASD/PSIP Team Bids Evaluation 01/31/2017 A 02/16/2017 A 15B1350 Recommendation for Award Letter 02/17/2017 A 0B1355 Contract Award (Purchase Order Approval) 02/20/2017 A 03/27/2017 A 10
ConstrucConstruction 01/10/2017 A 01/18/2018 A 669B1360 Construction Phase 01/10/2017 A 01/18/2018 A 669B1364 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 02/20/2017 A 03/31/2017 A 15B1366 Pre-Construction Meeting 04/03/2017 A 04/03/2017 A 1B1368 WASD Issues NTP (Pre-Const to NTP) 04/03/2017 A 06/23/2017 A 59B1369 WASD Issues NTP (PO to NTP) 03/27/2017 A 06/23/2017 A 29B1370 Construction NTP 06/26/2017 A 0B1400 Construction Operations 06/26/2017 A 01/18/2018 A 108B1400 Original Construction Duration 06/26/2017 A 11/23/2017 A 108B1400 Change Order #1 - Hurricane Irma 11/24/2017 A 12/14/2017 A 108B1402 Substantial Completion 01/18/2018 A 0
DesignerDesigner Construction Support Services 01/10/2017 A 01/18/2018 A 253B1410 Designer Construction Support Services 01/10/2017 A 01/18/2018 A 253
Project CProject Closeout 12/14/2017 A 08/01/2018 230B1445 Closeout Phase 12/14/2017 A 08/01/2018 230B1450 Issue SAC Letter 12/14/2017 A 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 01/19/2018 A 08/01/2018 120B1490 Project Closed 08/01/2018 0
Basin 0480Basin 0480 11/05/2015 A 09/26/2019 1421
100087 Pu100087 Pump Station 0480 Upgrade 11/05/2015 A 09/26/2019 1421DesignDesign 11/05/2015 A 07/17/2018 A 1027
B1000 Design Phase 11/05/2015 A 07/17/2018 A 1027B1010 Prepare and Submit Design Package 11/05/2015 A 11/06/2015 A 5B1020 Engage Design Consultant 11/06/2015 A 03/18/2016 A 20B1022 TA Preparation 03/21/2016 A 03/21/2016 A 1B1024 TA Approval Process 03/22/2016 A 04/27/2016 A 20B1030 Issue Design NTP 05/13/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 05/13/2016 A 06/20/2018 A 65
30% Des30% Design 05/16/2016 A 08/17/2017 A 457B1060 A/E Prepares 30% Construction Documents 05/16/2016 A 07/05/2016 A 30B1070 Geotechnical Engineering Services 05/16/2016 A 07/05/2016 A 20B1080 Surveying Services 05/16/2016 A 07/05/2016 A 15B1100 30% CDs Submittal 07/05/2016 A 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
100% CDs Submittal100% Review (MDWASD/PSIP Team)
Design Completed03/27/2017 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid Notice
MDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter
Contract Award (Purchase Order Approval)01/18/2018 A, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Construction NTPConstruction Operations
Original Construction DurationChange Order #1 - Hurricane Irma
Substantial Completion01/18/2018 A, Designer Construction Support Services
Designer Construction Support Services08/01/2018, Project Closeout
Closeout PhaseIssue SAC Letter
Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed
09/26/2019, Basin 0480
09/26/2019, 100087 Pump07/17/2018 A, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval ProcessIssue Design NTP
Final Engineering Report Review & Approval (MDWASD/PSIP Tea08/17/2017 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 81 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1120 30% Review (MDWASD/PSIP Team) 07/06/2016 A 09/09/2016 A 10B1122 Design Consultant Prepares SOW for New FDOT Requirement 09/12/2016 A 04/17/2017 A 20B1124 TA Rev 1 Preparation 04/18/2017 A 04/18/2017 A 1B1126 TA Rev 1 Approval Process 04/19/2017 A 05/17/2017 A 40B1128 A/E Prepares 30% Construction Documents (Re-Design) 06/02/2017 A 07/17/2017 A 22B1130 30% CDs Submittal (Re-Design) 07/17/2017 A 0B1132 30% Review (MDWASD/PSIP Team) (Re-Design) 07/18/2017 A 08/17/2017 A 30
90% Des90% Design 07/18/2017 A 06/20/2018 A 414B1170 A/E Prepares 90% Construction Documents 07/18/2017 A 10/02/2017 A 40B1180 90% CDs Submittal 10/02/2017 A 0B1190 90% Review (MDWASD/PSIP Team) 10/03/2017 A 10/30/2017 A 30B1200 90% RER(DERM)FDEP Permit Submittal 11/22/2017 A 0B1210 90% RER(DERM)FDEP Permit Review 11/22/2017 A 02/23/2018 A 45B1220 90% RER(Building Dept) Permit Submittal 03/27/2018 A 0B1230 90% RER(Building Dept) Permit Review 03/27/2018 A 04/11/2018 A 21B1240 90% Aventura - PWD Permit Submittal 03/26/2018 A 0B1250 90% Aventura - PWD Permit Review 03/26/2018 A 06/20/2018 A 21B1252 90% Aventura - BD Permit Submittal 03/26/2018 A 0B1254 90% Aventura - BD Permit Review 03/26/2018 A 03/27/2018 A 21B1256 90% FDOT Permit Submittal 12/19/2017 A 0B1258 90% FDOT Permit Review 12/19/2017 A 02/08/2018 A 21B1260 90% CD PM Comments Evaluation Completed 06/20/2018 A 0
100% De100% Design 06/20/2018 A 07/17/2018 A 28B1270 A/E Prepares 100% Construction Documents 06/20/2018 A 07/17/2018 A 14B1280 100% CDs Submittal 07/17/2018 A 0B1290 100% Review (MDWASD/PSIP Team) 07/13/2018 A 07/16/2018 A 14B1300 Design Completed 07/17/2018 A 0
MDWASDMDWASD Procurement 07/17/2018 A 10/08/2018 61B1305 Procurement Phase 07/17/2018 A 10/08/2018 61B1310 Submit CDs to MDWASD Procurement Division 07/17/2018 A 0B1312 Bid Notice Preparation Period 07/18/2018 A 07/30/2018 A 33B1314 Bid Notice 07/30/2018 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 07/31/2018 A 08/08/2018 14B1320 Pre-Bid Conference 08/09/2018 08/09/2018 1B1322 Bidders Prepare Bids for Submittal 08/10/2018 09/03/2018 25B1330 Bids Submittal 09/03/2018 0B1340 MDWASD/PSIP Team Bids Evaluation 09/04/2018 09/24/2018 21B1350 Recommendation for Award Letter 09/24/2018 0B1355 Contract Award (Purchase Order Approval) 09/25/2018 10/08/2018 14
ConstrucConstruction 08/09/2018 05/29/2019 294B1360 Construction Phase 08/09/2018 05/29/2019 294B1364 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 09/25/2018 10/15/2018 21B1366 Pre-Construction Meeting 10/16/2018 10/16/2018 1B1368 WASD Issues NTP (Pre-Const to NTP) 10/17/2018 11/30/2018 45B1369 WASD Issues NTP (PO to NTP) 10/09/2018 11/30/2018 53B1370 Construction NTP 12/01/2018 0B1400 Construction Operations 12/01/2018 05/29/2019 180B1402 Substantial Completion 05/29/2019 0
DesignerDesigner Construction Support Services 08/09/2018 05/29/2019 294
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
30% Review (MDWASD/PSIP Team)Design Consultant Prepares SOW for New FDOT RequirementTA Rev 1 Preparation
TA Rev 1 Approval ProcessA/E Prepares 30% Construction Documents (Re-Design)
30% CDs Submittal (Re-Design)30% Review (MDWASD/PSIP Team) (Re-Design)
06/20/2018 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal
90% RER(DERM)FDEP Permit Review90% RER(Building Dept) Permit Submittal90% RER(Building Dept) Permit Review
90% Aventura - PWD Permit Submittal90% Aventura - PWD Permit Review
90% Aventura - BD Permit Submittal90% Aventura - BD Permit Review
90% FDOT Permit Submittal90% FDOT Permit Review
90% CD PM Comments Evaluation Completed07/17/2018 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal
100% Review (MDWASD/PSIP Team)Design Completed
10/08/2018, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid Notice
MDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)
05/29/2019, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeePre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Construction NTPConstruction OperationsSubstantial Completion05/29/2019, Designer Construction Su
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 82 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1410 Designer Construction Support Services 08/09/2018 05/29/2019 294Project CProject Closeout 05/29/2019 09/26/2019 120
B1445 Closeout Phase 05/29/2019 09/26/2019 120B1450 Issue SAC Letter 05/29/2019 0B1470 Final Release of Retainage - Construction Contract 05/29/2019 0B1480 Administrative Closeout 05/30/2019 09/26/2019 120B1490 Project Closed 09/26/2019 0
Basin 0487Basin 0487 05/02/2016 A 08/01/2018 822
100088 Pu100088 Pump Station 0487 Upgrade 05/02/2016 A 08/01/2018 822DesignDesign 05/02/2016 A 03/23/2017 A 376
B1000 Design Phase 05/02/2016 A 03/23/2017 A 376B1010 Prepare and Submit Design Package 05/02/2016 A 05/06/2016 A 5B1020 Engage Design Consultant 05/06/2016 A 09/29/2016 A 20B1022 TA Preparation 09/30/2016 A 09/30/2016 A 1B1024 TA Approval Process 10/03/2016 A 11/30/2016 A 40B1030 Issue Design NTP 12/09/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 12/09/2016 A 02/07/2017 A 65
30% Des30% Design 12/12/2016 A 03/23/2017 A 131B1060 A/E Prepares 30% Construction Documents 12/12/2016 A 02/07/2017 A 50B1062 Station Monitoring and SAC Process 02/08/2017 A 03/23/2017 A 40
Project CProject Closeout 03/23/2017 A 08/01/2018 496B1445 Closeout Phase 03/23/2017 A 08/01/2018 496B1450 Issue SAC Letter 03/23/2017 A 0B1480 Administrative Closeout 03/23/2017 A 08/01/2018 30B1490 Project Closed 08/01/2018 0
Basin 0494Basin 0494 01/14/2016 A 12/08/2018 1052
100090 Pu100090 Pump Station 0494 Upgrade 01/14/2016 A 12/08/2018 1052DesignDesign 01/14/2016 A 06/07/2017 A 548
B1000 Design Phase 01/14/2016 A 06/07/2017 A 548B1010 Prepare and Submit Design Package 01/14/2016 A 01/29/2016 A 5B1020 Engage Design Consultant 01/29/2016 A 04/26/2016 A 20B1022 TA Preparation 04/27/2016 A 04/27/2016 A 1B1024 TA Approval Process 04/28/2016 A 06/01/2016 A 20B1030 Issue Design NTP 06/13/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 06/13/2016 A 06/07/2017 A 65
30% Des30% Design 06/14/2016 A 09/29/2016 A 105B1060 A/E Prepares 30% Construction Documents 06/14/2016 A 09/01/2016 A 30B1100 30% CDs Submittal 09/01/2016 A 0B1120 30% Review (MDWASD/PSIP Team) 09/02/2016 A 09/29/2016 A 10
90% Des90% Design 09/05/2016 A 06/07/2017 A 331B1130 A/E Prepares 90% Construction Documents 09/05/2016 A 01/17/2017 A 40B1140 90% CDs Submittal 01/17/2017 A 0B1150 90% Review (MDWASD/PSIP Team) 01/18/2017 A 02/07/2017 A 30B1160 90% RER(DERM)FDEP Permit Submittal (Pump Station) 03/24/2017 A 0B1170 90% RER(DERM)FDEP Permit Review (Pump Station) 03/24/2017 A 04/04/2017 A 45B1180 90% RER(Building Dept) Permit Submittal (Pump Station) 05/15/2017 A 0B1190 90% RER(Building Dept) Permit Review (Pump Station) 05/15/2017 A 06/07/2017 A 21B1200 90% Golden Beach - BD Permit Submittal (Pump Station) 04/05/2017 A 0B1210 90% Golden Beach - BD Permit Review (Pump Station) 04/05/2017 A 05/23/2017 A 21
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Designer Construction Support Service09/26/2019, Project Closeou
Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construc
Administrative CloseoutProject Closed
08/01/2018, Basin 0487
08/01/2018, 100088 Pump Station 0487 Upgrade03/23/2017 A, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval ProcessIssue Design NTP
Final Engineering Report Review & Approval (MDWASD/PSIP Team)03/23/2017 A, 30% Design
A/E Prepares 30% Construction DocumentsStation Monitoring and SAC Process
08/01/2018, Project Closeout
Closeout PhaseIssue SAC Letter
Administrative CloseoutProject Closed
12/08/2018, Basin 0494
12/08/2018, 100090 Pump Station 0494 Upgrade06/07/2017 A, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval ProcessIssue Design NTP
Final Engineering Report Review & Approval (MDWASD/PSIP Team)09/29/2016 A, 30% Design
A/E Prepares 30% Construction Documents30% CDs Submittal
30% Review (MDWASD/PSIP Team)06/07/2017 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)90% RER(DERM)FDEP Permit Review (Pump Station)
90% RER(Building Dept) Permit Submittal (Pump Station)90% RER(Building Dept) Permit Review (Pump Station)90% Golden Beach - BD Permit Submittal (Pump Station)90% Golden Beach - BD Permit Review (Pump Station)
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 83 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1212 90% Golden Beach - PWD Permit Submittal (Pump Station) 04/05/2017 A 0B1214 90% Golden Beach - PWD Permit Review (Pump Station) 04/05/2017 A 05/23/2017 A 21B1220 90% CD PM Comments Evaluation Completed 06/07/2017 A 0B1222 MDWASD Union Concurrence Process 03/07/2017 A 04/07/2017 A 30
100% De100% Design 04/07/2017 A 04/14/2017 A 26B1230 A/E Prepares 100% Construction Documents 04/07/2017 A 04/13/2017 A 10B1240 100% CDs Submittal 04/13/2017 A 0B1250 100% Review (MDWASD/PSIP Team) 04/14/2017 A 04/14/2017 A 10B1260 Design Completed 04/14/2017 A 0
MDWASDMDWASD Procurement 04/14/2017 A 08/14/2017 A 75B1265 Procurement Phase 04/14/2017 A 08/14/2017 A 75B1270 Submit CDs to MDWASD Procurement Division 04/14/2017 A 0B1272 Bid Notice Preparation Period 04/17/2017 A 05/10/2017 A 23B1274 Bid Notice 05/10/2017 A 0B1276 MDWASD/PSIP Team Prepare for Pre-Bid Conference 05/11/2017 A 05/22/2017 A 10B1280 Pre-Bid Conference 05/23/2017 A 05/23/2017 A 1B1282 Bidders Prepare Bids for Submittal 05/24/2017 A 06/20/2017 A 15B1290 Bids Submittal 06/20/2017 A 0B1300 MDWASD/PSIP Team Bids Evaluation 06/21/2017 A 07/24/2017 A 15B1310 Recommendation for Award Letter 07/24/2017 A 0B1315 Contract Award (Purchase Order Approval) 07/25/2017 A 08/14/2017 A 10
ConstrucConstruction 05/23/2017 A 08/10/2018 551B1320 Construction Phase 05/23/2017 A 08/10/2018 551B1322 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 07/25/2017 A 08/21/2017 A 15B1324 Pre-Construction Meeting 08/22/2017 A 08/22/2017 A 1B1326 WASD Issues NTP (Pre-Const to NTP) 08/23/2017 A 03/11/2018 A 132B1328 WASD Issues NTP (PO to NTP) 08/15/2017 A 03/11/2018 A 53B1330 Construction NTP 03/12/2018 A 0B1360 Construction Operations 03/12/2018 A 08/10/2018 119B1362 Substantial Completion 08/10/2018 0
DesignerDesigner Construction Support Services 05/23/2017 A 08/10/2018 260B1370 Designer Construction Support Services 05/23/2017 A 08/10/2018 260
Project CProject Closeout 08/10/2018 12/08/2018 120B1405 Closeout Phase 08/10/2018 12/08/2018 120B1410 Issue SAC Letter 08/10/2018 0B1430 Final Release of Retainage - Construction Contract 08/10/2018 0B1440 Administrative Closeout 08/11/2018 12/08/2018 120B1450 Project Closed 12/08/2018 0
Basin 0495Basin 0495 06/16/2014 A 08/01/2018 1696
100091 Pu100091 Pump Station 0495 Upgrade 06/16/2014 A 08/01/2018 1198DesignDesign 06/16/2014 A 08/01/2016 A 333
B1000 Design Phase 06/16/2014 A 08/01/2016 A 333B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 06/16/2014 A 06/19/2014 A 5B1020 Engage Design Consultant 06/20/2014 A 09/16/2014 A 15B1030 Issue Design NTP 09/17/2014 A 0B1032 TA Rev 2 - Approval Process 06/02/2016 A 08/01/2016 A 15B1040 A/E Develops and Submits Final Engineering Report 09/17/2014 A 04/23/2015 A 20B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 09/17/2014 A 01/07/2015 A 0
30% Des30% Design 09/18/2014 A 10/30/2014 A 30
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
90% Golden Beach - PWD Permit Submittal (Pump Station)90% Golden Beach - PWD Permit Review (Pump Station)
90% CD PM Comments Evaluation CompletedMDWASD Union Concurrence Process04/14/2017 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal
100% Review (MDWASD/PSIP Team)Design Completed08/14/2017 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid Notice
MDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)
08/10/2018, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Construction NTPConstruction OperationsSubstantial Completion08/10/2018, Designer Construction Support Services
Designer Construction Support Services12/08/2018, Project Closeout
Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction Contract
Administrative CloseoutProject Closed
08/01/2018, Basin 0495
08/01/2018, 100091 Pump Station 0495 Upgrade08/01/2016 A, Design
Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book
Engage Design ConsultantIssue Design NTP
TA Rev 2 - Approval Process
A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
10/30/2014 A, 30% Design
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 84 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1060 A/E Prepares 30% Construction Documents 09/18/2014 A 10/16/2014 A 30B1070 Geotechnical Engineering Services 10/03/2014 A 10/16/2014 A 30B1080 Surveying Services 10/03/2014 A 10/23/2014 A 23B1100 30% CDs Submittal 10/17/2014 A 0B1120 30% Review (MDWASD/PSIP Team) 10/17/2014 A 10/30/2014 A 10
90% Des90% Design 10/17/2014 A 04/23/2015 A 144B1170 A/E Prepares 90% Construction Documents 10/17/2014 A 11/25/2014 A 20B1180 90% CDs Submittal 11/25/2014 A 0B1190 90% Review (MDWASD/PSIP Team) 11/26/2014 A 01/07/2015 A 15B1195 Revision - FPL Issues 01/26/2015 A 02/11/2015 A 5B1200 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 02/12/2015 A 0B1210 90% RER(DERM)/FDEP Permit Review (Pump Station) 02/12/2015 A 03/11/2015 A 15B1220 90% Golden Beach - BD Permit Submittal 03/03/2015 A 0B1230 90% Golden Beach - BD Permit Review 03/03/2015 A 04/23/2015 A 15B1240 90% Golden Beach - PWD Permit Submittal 03/03/2015 A 0B1250 90% Golden Beach - PWD Permit Review 03/03/2015 A 04/23/2015 A 15B1260 90% CD PM Comments Evaluation Completed 04/23/2015 A 0
100% De100% Design 02/12/2015 A 04/30/2015 A 25B1270 A/E Prepares 100% Construction Documents 02/12/2015 A 03/30/2015 A 10B1280 100% CDs Submittal 03/30/2015 A 0B1290 100% Review (MDWASD/PSIP Team) 03/30/2015 A 04/30/2015 A 10B1300 Design Completed 04/30/2015 A 0
MDWASDMDWASD Procurement 04/07/2015 A 07/14/2015 A 98B1305 Procurement Phase 04/07/2015 A 07/14/2015 A 98B1310 Submit CDs to MDWASD Procurement Division 04/07/2015 A 0B1312 Bid Notice Preparation Period 04/08/2015 A 04/27/2015 A 23B1314 Bid Notice 04/28/2015 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 04/29/2015 A 05/11/2015 A 10B1320 Pre-Bid Conference 05/12/2015 A 05/12/2015 A 1B1322 Bidders Prepare Bids for Submittal 05/13/2015 A 06/09/2015 A 15B1330 Bids Submittal 06/10/2015 A 0B1340 MDWASD/PSIP Team Bids Evaluation 06/11/2015 A 06/16/2015 A 15B1350 Recommendation for Award Letter 06/17/2015 A 0B1355 Contract Award (Purchase Order Approval) 06/18/2015 A 07/14/2015 A 10
ConstrucConstruction 05/12/2015 A 09/30/2016 A 1301B1360 Construction Phase 05/12/2015 A 09/30/2016 A 1301B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 06/18/2015 A 07/08/2015 A 15B1365 Pre-Construction Meeting 07/09/2015 A 07/09/2015 A 1B1368 WASD Issues NTP (PO to NTP) 07/14/2015 A 07/14/2015 A 53B1370 Construction NTP 07/14/2015 A 0B1400 Construction Operations 07/14/2015 A 11/17/2015 A 85B1400 Original Construction Duration 07/14/2015 A 11/11/2015 A 85B1400 Change Order #1 - FPL 11/12/2015 A 11/28/2015 A 85B1402 Substantial Completion 11/17/2015 A 0
DesignerDesigner Construction Support Services 05/12/2015 A 09/30/2016 A 143B1410 Designer Construction Support Services 05/12/2015 A 09/30/2016 A 143
ConstrucConstruction Close Out 11/18/2015 A 06/27/2016 A 15B1420 Commissioning 11/18/2015 A 12/10/2015 A 15B1430 Punch List 11/18/2015 A 06/27/2016 A 10
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services
30% CDs Submittal30% Review (MDWASD/PSIP Team)
04/23/2015 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)Revision - FPL Issues90% RER(DERM)/FDEP Permit Submittal (Pump Station)
90% RER(DERM)/FDEP Permit Review (Pump Station)90% Golden Beach - BD Permit Submittal
90% Golden Beach - BD Permit Review90% Golden Beach - PWD Permit Submittal
90% Golden Beach - PWD Permit Review90% CD PM Comments Evaluation Completed04/30/2015 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal
100% Review (MDWASD/PSIP Team)Design Completed
07/14/2015 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid Notice
MDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter
Contract Award (Purchase Order Approval)09/30/2016 A, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction MeetingWASD Issues NTP (PO to NTP)Construction NTP
Construction OperationsOriginal Construction DurationChange Order #1 - FPL
Substantial Completion09/30/2016 A, Designer Construction Support Services
Designer Construction Support Services06/27/2016 A, Construction Close Out
CommissioningPunch List
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 85 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
Project CProject Closeout 11/18/2015 A 08/01/2018 678B1445 Closeout Phase 11/18/2015 A 08/01/2018 952B1450 Issue SAC Letter 12/23/2015 A 0B1470 Final Release of Retainage - Construction Contract 11/21/2016 A 0B1480 Administrative Closeout 11/18/2015 A 08/01/2018 120B1490 Project Closed 08/01/2018 0
100188-2 B100188-2 Basin 0495 Infiltration/Inflow Study and Repairs 04/17/2015 A 11/26/2015 A 390InfiltratioInfiltration/Inflow 04/17/2015 A 11/25/2015 A 173
B1000 Infiltration/Inflow Phase 04/17/2015 A 11/25/2015 A 173CIPP RepCIPP Repairs 04/17/2015 A 07/27/2015 A 107
B1065 CIPP Phase 04/17/2015 A 07/27/2015 A 107B1080 Issue NTP for CIPP Repairs 04/17/2015 A 0B1090 Conduct CIPP Repairs 07/27/2015 A 07/27/2015 A 20
ManholeManhole Repairs 10/02/2015 A 11/25/2015 A 20B1115 Manhole Phase 10/02/2015 A 11/25/2015 A 20B1130 Issue NTP for Manhole Repairs 10/02/2015 A 0B1140 Conduct Manhole Repairs 10/14/2015 A 11/25/2015 A 20
Project CProject Closeout 11/26/2015 A 11/26/2015 A 0B1235 Closeout Phase 11/26/2015 A 11/26/2015 A 0B1260 Project Closed 11/26/2015 A 0
Basin 0500Basin 0500 07/02/2014 A 08/01/2018 1631
100093 Pu100093 Pump Station 0500 Upgrade 07/02/2014 A 08/01/2018 1631DesignDesign 07/02/2014 A 04/30/2015 A 303
B1000 Design Phase 07/02/2014 A 04/30/2015 A 303B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 07/02/2014 A 07/28/2014 A 5B1020 Engage Design Consultant 07/29/2014 A 10/23/2014 A 15B1030 Issue Design NTP 10/24/2014 A 0B1040 A/E Develops and Submits Final Engineering Report 10/27/2014 A 01/14/2015 A 20B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 12/29/2014 A 02/11/2015 A 1
30% Des30% Design 10/27/2014 A 12/02/2014 A 57B1060 A/E Prepares 30% Construction Documents 10/27/2014 A 11/11/2014 A 30B1070 Geotechnical Engineering Services 10/27/2014 A 11/11/2014 A 20B1080 Surveying Services 10/27/2014 A 11/11/2014 A 15B1100 30% CDs Submittal 11/11/2014 A 0B1120 30% Review (MDWASD/PSIP Team) 11/12/2014 A 12/02/2014 A 10
90% Des90% Design 11/12/2014 A 04/30/2015 A 99B1170 A/E Prepares 90% Construction Documents 11/12/2014 A 12/26/2014 A 20B1180 90% CDs Submittal 12/26/2014 A 0B1190 90% Review (MDWASD/PSIP Team) 12/29/2014 A 01/14/2015 A 15B1200 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 02/17/2015 A 0B1210 90% RER(DERM)/FDEP Permit Review (Pump Station) 02/17/2015 A 03/12/2015 A 5B1220 90% RER (Building Dept) Permit Submittal 03/20/2015 A 0B1230 90% RER (Building Dept) Permit Review 03/20/2015 A 04/30/2015 A 5B1240 90% PWWMD Permit Submittal (Pump Station) 11/14/2014 A 0B1250 90% PWWMD Permit Review (Pump Station) 11/12/2014 A 11/20/2014 A 5B1260 90% CD PM Comments Evaluation Completed 04/30/2015 A 0
100% De100% Design 01/15/2015 A 04/30/2015 A 64B1270 A/E Prepares 100% Construction Documents 01/15/2015 A 01/23/2015 A 10B1280 100% CDs Submittal 01/23/2015 A 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
08/01/2018, Project Closeout
Closeout PhaseIssue SAC Letter
Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed
11/26/2015 A, 100188-2 Basin 0495 Infiltration/Inflow Study and Repairs11/25/2015 A, Infiltration/Inflow
Infiltration/Inflow Phase07/27/2015 A, CIPP RepairsCIPP Phase
Issue NTP for CIPP RepairsConduct CIPP Repairs
11/25/2015 A, Manhole RepairsManhole Phase
Issue NTP for Manhole RepairsConduct Manhole Repairs11/26/2015 A, Project CloseoutCloseout Phase
Project Closed08/01/2018, Basin 0500
08/01/2018, 100093 Pump Station 0500 Upgrade04/30/2015 A, Design
Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book
Engage Design ConsultantIssue Design NTP
A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
12/02/2014 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services
30% CDs Submittal30% Review (MDWASD/PSIP Team)
04/30/2015 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)
90% RER(DERM)/FDEP Permit Submittal (Pump Station)90% RER(DERM)/FDEP Permit Review (Pump Station)
90% RER (Building Dept) Permit Submittal90% RER (Building Dept) Permit Review
90% PWWMD Permit Submittal (Pump Station)90% PWWMD Permit Review (Pump Station)
90% CD PM Comments Evaluation Completed04/30/2015 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 86 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1290 100% Review (MDWASD/PSIP Team) 01/24/2015 A 02/11/2015 A 5B1300 Design Completed 04/30/2015 A 0
MDWASDMDWASD Procurement 03/18/2015 A 07/23/2015 A 109B1305 Procurement Phase 03/18/2015 A 07/23/2015 A 109B1310 Submit CDs to MDWASD Procurement Division 03/18/2015 A 0B1320 Pre-Bid Conference 04/07/2015 A 04/07/2015 A 1B1330 Bids Submittal 05/05/2015 A 0B1340 MDWASD/PSIP Team Bids Evaluation 05/06/2015 A 05/14/2015 A 30B1350 Recommendation for Award Letter 05/15/2015 A 0B1355 Contract Award (Purchase Order Approval) 05/18/2015 A 07/23/2015 A 15
ConstrucConstruction 04/07/2015 A 07/08/2016 A 1290B1360 Construction Phase 04/07/2015 A 07/08/2016 A 1290B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 05/18/2015 A 06/09/2015 A 0B1365 Pre-Construction Meeting 06/10/2015 A 06/10/2015 A 1B1368 WASD Issues NTP (PO to NTP) 07/24/2015 A 07/26/2015 A 53B1369 Permits / Shop Drawings / Material Orders 06/11/2015 A 11/20/2015 A 15B1370 Construction NTP 07/27/2015 A 0B1400 Construction Operations 07/27/2015 A 12/23/2015 A 106B1402 Substantial Completion 12/23/2015 A 0
DesignerDesigner Construction Support Services 04/07/2015 A 07/08/2016 A 160B1410 Designer Construction Support Services 04/07/2015 A 07/08/2016 A 160
ConstrucConstruction Close Out 12/24/2015 A 02/29/2016 A 15B1420 Commissioning 12/24/2015 A 02/29/2016 A 15B1430 Punch List 12/24/2015 A 02/29/2016 A 10
Project CProject Closeout 12/24/2015 A 08/01/2018 944B1445 Closeout Phase 12/24/2015 A 08/01/2018 944B1450 Issue SAC Letter 01/26/2016 A 0B1470 Final Release of Retainage - Construction Contract 12/23/2016 A 0B1480 Administrative Closeout 12/24/2015 A 08/01/2018 120B1490 Project Closed 08/01/2018 0
100092-2 B100092-2 Basin 0500 Infiltration/Inflow Study and Repairs 09/25/2014 A 09/04/2015 A 609InfiltratioInfiltration/Inflow 09/25/2014 A 09/03/2015 A 338
B1260 Infiltration/Inflow Phase 09/25/2014 A 09/03/2015 A 338Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 12/31/2014 A 274
B0995 SSES Phase 09/25/2014 A 12/31/2014 A 274B1010 Issue NTP to SSES Contractor 09/25/2014 A 0B1020 Conduct SSES 09/29/2014 A 10/17/2014 A 30B1021 Suspect Laterals/Smoke Test Defect Investigations 10/16/2014 A 10/17/2014 A 10B1030 Video Review 10/20/2014 A 12/31/2014 A 30
CIPP RepCIPP Repairs 04/17/2015 A 07/20/2015 A 33B1055 CIPP Phase 04/17/2015 A 07/20/2015 A 33B1070 Issue NTP for CIPP Repairs 04/17/2015 A 0B1080 Conduct CIPP Repairs 06/18/2015 A 07/20/2015 A 20
ManholeManhole Repairs 07/14/2015 A 09/03/2015 A 20B1005 Manhole Phase 07/14/2015 A 09/03/2015 A 20B1120 Issue NTP for Manhole Repairs 07/14/2015 A 0B1130 Conduct Manhole Repairs 08/17/2015 A 09/03/2015 A 20
Dig & ReDig & Replace Repairs 05/18/2015 A 07/01/2015 A 30B1155 Dig & Replace Phase 05/18/2015 A 07/01/2015 A 30
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
100% Review (MDWASD/PSIP Team)Design Completed
07/23/2015 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Pre-Bid ConferenceBids SubmittalMDWASD/PSIP Team Bids Evaluation
Recommendation for Award LetterContract Award (Purchase Order Approval)
07/08/2016 A, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
WASD Issues NTP (PO to NTP)
Permits / Shop Drawings / Material OrdersConstruction NTP
Construction OperationsSubstantial Completion
07/08/2016 A, Designer Construction Support Services
Designer Construction Support Services02/29/2016 A, Construction Close Out
CommissioningPunch List
08/01/2018, Project Closeout
Closeout PhaseIssue SAC Letter
Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed
09/04/2015 A, 100092-2 Basin 0500 Infiltration/Inflow Study and Repairs09/03/2015 A, Infiltration/Inflow
Infiltration/Inflow Phase12/31/2014 A, Sanitary Sewer Evaluation SurveySSES Phase
Issue NTP to SSES ContractorConduct SSESSuspect Laterals/Smoke Test Defect Investigations
Video Review07/20/2015 A, CIPP RepairsCIPP Phase
Issue NTP for CIPP RepairsConduct CIPP Repairs
09/03/2015 A, Manhole RepairsManhole Phase
Issue NTP for Manhole RepairsConduct Manhole Repairs
07/01/2015 A, Dig & Replace RepairsDig & Replace Phase
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 87 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1170 Issue NTP for Dig & Replace Repairs 05/18/2015 A 0B1180 Conduct Dig & Replace Repairs 06/22/2015 A 07/01/2015 A 30
Project CProject Closeout 09/04/2015 A 09/04/2015 A 0B1225 Closeout Phase 09/04/2015 A 09/04/2015 A 0B1250 Project Closed 09/04/2015 A 0
100213 FM100213 FM for Pump Station 0500 07/02/2014 A 07/17/2017 A 1631DesignDesign 07/02/2014 A 03/24/2015 A 283
B1000 Design Phase 07/02/2014 A 03/24/2015 A 283B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 07/02/2014 A 08/01/2014 A 5B1020 Engage Design Consultant 08/04/2014 A 11/05/2014 A 20B1030 Issue Design NTP 11/05/2014 A 0B1040 A/E Develops and Submits Final Engineering Report 11/06/2014 A 01/26/2015 A 20B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 01/27/2015 A 01/30/2015 A 2
30% Des30% Design 11/06/2014 A 12/04/2014 A 97B1060 A/E Prepares 30% Construction Documents 11/06/2014 A 11/24/2014 A 30B1070 Geotechnical Engineering Services 11/06/2014 A 11/24/2014 A 20B1080 Surveying Services 11/06/2014 A 11/24/2014 A 15B1100 30% CDs Submittal 11/24/2014 A 0B1120 30% Review (MDWASD/PSIP Team) 11/24/2014 A 12/04/2014 A 10
90% Des90% Design 11/25/2014 A 03/13/2015 A 66B1180 A/E Prepares 90% Construction Documents 12/16/2014 A 01/30/2015 A 15B1190 90% CDs Submittal 01/30/2015 A 0B1200 90% Review (MDWASD/PSIP Team) 02/02/2015 A 02/13/2015 A 15B1230 90% RER(DERM)FDEP Permit Submittal (Force Main) 03/06/2015 A 0B1240 90% RER(DERM)FDEP Permit Review (Force Main) 03/06/2015 A 03/11/2015 A 5B1250 90% PWWMD Permit Submittal (Force Main) 11/25/2014 A 0B1260 90% PWWMD Permit Review (Force Main) 11/25/2014 A 12/02/2014 A 5B1290 90% CD PM Comments Evaluation Completed 03/13/2015 A 0
100% De100% Design 02/14/2015 A 03/24/2015 A 37B1300 A/E Prepares 100% Construction Documents 02/14/2015 A 03/20/2015 A 2B1310 100% CDs Submittal 03/20/2015 A 0B1320 100% Review (MDWASD/PSIP Team) 03/23/2015 A 03/24/2015 A 4B1330 Design Completed 03/24/2015 A 0
MDWASDMDWASD Procurement 03/25/2015 A 07/14/2015 A 95B1335 Procurement Phase 03/25/2015 A 07/14/2015 A 95B1340 Submit CDs to MDWASD Procurement Division 03/25/2015 A 0B1350 Pre-Bid Conference 04/14/2015 A 04/14/2015 A 1B1360 Bids Submittal 05/18/2015 A 0B1370 MDWASD/PSIP Team Bids Evaluation 05/19/2015 A 05/22/2015 A 20B1380 Recommendation for Award Letter 05/22/2015 A 0B1385 Contract Award (Purchase Order Approval) 05/22/2015 A 07/14/2015 A 15
ConstrucConstruction 04/14/2015 A 02/06/2017 A 1276B1390 Construction Phase 04/14/2015 A 02/06/2017 A 1276B1394 MDWASD/PSIP Prepare for Pre-Construction Meeting 05/25/2015 A 06/17/2015 A 30B1396 Pre-Construction Meeting 06/18/2015 A 06/18/2015 A 1B1398 Permits / Shop Drawings / Material Orders 06/19/2015 A 11/20/2015 A 30B1399 WASD Issues NTP (PO to NTP) 07/15/2015 A 08/31/2015 A 53B1400 Construction NTP 09/01/2015 A 0B1430 Construction Operations 09/01/2015 A 12/17/2015 A 85
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs
09/04/2015 A, Project CloseoutCloseout Phase
Project Closed07/17/2017 A, 100213 FM for Pump Station 0500
03/24/2015 A, Design
Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book
Engage Design ConsultantIssue Design NTP
A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
12/04/2014 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services
30% CDs Submittal30% Review (MDWASD/PSIP Team)
03/13/2015 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)
90% RER(DERM)FDEP Permit Submittal (Force Main)90% RER(DERM)FDEP Permit Review (Force Main)
90% PWWMD Permit Submittal (Force Main)90% PWWMD Permit Review (Force Main)
90% CD PM Comments Evaluation Completed03/24/2015 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed
07/14/2015 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement DivisionPre-Bid Conference
Bids SubmittalMDWASD/PSIP Team Bids Evaluation
Recommendation for Award LetterContract Award (Purchase Order Approval)
02/06/2017 A, Construction
Construction PhaseMDWASD/PSIP Prepare for Pre-Construction MeetingPre-Construction Meeting
Permits / Shop Drawings / Material OrdersWASD Issues NTP (PO to NTP)
Construction NTPConstruction Operations
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 88 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1432 Substantial Completion 12/17/2015 A 0DesignerDesigner Construction Support Services 04/14/2015 A 02/06/2017 A 128
B1440 Designer Construction Support Services 04/14/2015 A 02/06/2017 A 128ConstrucConstruction Close Out 12/18/2015 A 02/29/2016 A 15
B1450 Commissioning 12/18/2015 A 12/31/2015 A 15B1460 Punch List 12/18/2015 A 02/29/2016 A 10
Project CProject Closeout 12/17/2015 A 07/17/2017 A 550B1475 Closeout Phase 12/17/2015 A 07/17/2017 A 550B1478 SAC Letter Issuance Period 12/17/2015 A 01/26/2016 A 26B1480 Issue SAC Letter 01/26/2016 A 0B1500 Final Release of Retainage - Construction Contract 05/27/2016 A 0B1510 Administrative Closeout 12/18/2015 A 07/17/2017 A 30B1520 Project Closed 07/17/2017 A 0
Basin 0502Basin 0502 09/25/2014 A 08/01/2018 1506
100094 Pu100094 Pump Station 0502 Upgrade 10/10/2014 A 08/01/2018 1437DesignDesign 10/10/2014 A 06/22/2015 A 179
B1000 Design Phase 10/10/2014 A 06/22/2015 A 179B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 10/10/2014 A 10/13/2014 A 5B1020 Engage Design Consultant 10/14/2014 A 01/08/2015 A 20B1030 Issue Design NTP 01/08/2015 A 0B1040 A/E Develops and Submits Final Engineering Report 01/08/2015 A 05/29/2015 A 20B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 04/30/2015 A 05/14/2015 A 10
30% Des30% Design 01/09/2015 A 02/24/2015 A 72B1060 A/E Prepares 30% Construction Documents 01/09/2015 A 02/12/2015 A 30B1070 Geotechnical Engineering Services 01/26/2015 A 02/12/2015 A 20B1080 Surveying Services 01/26/2015 A 02/12/2015 A 15B1100 30% CDs Submittal 02/12/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 02/13/2015 A 02/24/2015 A 10
90% Des90% Design 02/13/2015 A 06/12/2015 A 124B1170 A/E Prepares 90% Construction Documents 02/13/2015 A 04/29/2015 A 35B1180 90% CDs Submittal 04/29/2015 A 0B1190 90% Review (MDWASD/PSIP Team) 04/30/2015 A 05/14/2015 A 10B1200 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 05/29/2015 A 0B1210 90% RER(DERM)/FDEP Permit Review (Pump Station) 05/20/2015 A 06/04/2015 A 5B1220 90% RER (Building Dept) Permit Submittal 06/10/2015 A 0B1230 90% RER (Building Dept) Permit Review 06/11/2015 A 06/12/2015 A 10B1260 90% CD PM Comments Evaluation Completed 06/12/2015 A 0
100% De100% Design 05/30/2015 A 06/22/2015 A 11B1270 A/E Prepares 100% Construction Documents 05/30/2015 A 06/22/2015 A 5B1280 100% CDs Submittal 06/22/2015 A 0B1290 100% Review (MDWASD/PSIP Team) 06/22/2015 A 06/22/2015 A 5B1300 Design Completed 06/22/2015 A 0
MDWASDMDWASD Procurement 06/23/2015 A 08/05/2015 A 64B1305 Procurement Phase 06/23/2015 A 08/05/2015 A 64B1310 Submit CDs to MDWASD Procurement Division 06/23/2015 A 0B1312 Bid Notice Preparation Period 06/23/2015 A 06/23/2015 A 23B1314 Bid Notice 06/23/2015 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 06/24/2015 A 06/29/2015 A 10B1320 Pre-Bid Conference 06/30/2015 A 06/30/2015 A 1
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Substantial Completion02/06/2017 A, Designer Construction Support Services
Designer Construction Support Services02/29/2016 A, Construction Close Out
CommissioningPunch List
07/17/2017 A, Project Closeout
Closeout PhaseSAC Letter Issuance Period
Issue SAC LetterFinal Release of Retainage - Construction Contract
Administrative CloseoutProject Closed
08/01/2018, Basin 0502
08/01/2018, 100094 Pump Station 0502 Upgrade06/22/2015 A, Design
Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book
Engage Design ConsultantIssue Design NTP
A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
02/24/2015 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services
30% CDs Submittal30% Review (MDWASD/PSIP Team)06/12/2015 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)/FDEP Permit Submittal (Pump Station)
90% RER(DERM)/FDEP Permit Review (Pump Station)90% RER (Building Dept) Permit Submittal
90% RER (Building Dept) Permit Review90% CD PM Comments Evaluation Completed06/22/2015 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal
100% Review (MDWASD/PSIP Team)Design Completed
08/05/2015 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation Period
Bid NoticeMDWASD/PSIP Team Prepare for Pre-Bid Conference
Pre-Bid Conference
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 89 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1322 Bidders Prepare Bids for Submittal 07/01/2015 A 07/20/2015 A 15B1330 Bids Submittal 07/21/2015 A 0B1340 MDWASD/PSIP Team Bids Evaluation 07/22/2015 A 07/22/2015 A 15B1350 Recommendation for Award Letter 07/22/2015 A 0B1355 Contract Award (Purchase Order Approval) 07/23/2015 A 08/05/2015 A 10
ConstrucConstruction 06/30/2015 A 04/28/2017 A 1226B1360 Construction Phase 06/30/2015 A 04/28/2017 A 1226B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 07/23/2015 A 09/09/2015 A 15B1365 Pre-Construction Meeting 09/10/2015 A 09/10/2015 A 1B1366 WASD Issues NTP (Pre-Const to NTP) 09/11/2015 A 04/10/2016 A 15B1368 WASD Issues NTP (PO to NTP) 08/06/2015 A 04/10/2016 A 53B1370 Construction NTP 04/11/2016 A 0B1400 Construction Operations 04/11/2016 A 03/02/2017 A 108B1400 Original Construction Duration 04/11/2016 A 09/08/2016 A 108B1400 Change Order #1 - FPL 09/09/2016 A 09/30/2016 A 108B1400 Change Order #2 - Hurricane Mathew 10/01/2016 A 10/05/2016 A 108B1400 Change Order #3 - Bypass, Sheet Pilling Contractor, FPL 10/06/2016 A 12/13/2016 A 108B1400 Change Order #4 - Contractual Duration Discrepancy 12/14/2016 A 03/02/2017 A 108B1402 Substantial Completion 03/09/2017 A 0
DesignerDesigner Construction Support Services 06/30/2015 A 04/28/2017 A 217B1410 Designer Construction Support Services 06/30/2015 A 04/28/2017 A 217
ConstrucConstruction Close Out 03/09/2017 A 04/28/2017 A 10B1420 Commissioning 03/09/2017 A 03/09/2017 A 5B1430 Punch List 03/10/2017 A 04/28/2017 A 10
Project CProject Closeout 03/10/2017 A 08/01/2018 518B1445 Closeout Phase 03/10/2017 A 08/01/2018 518B1450 Issue SAC Letter 05/16/2018 A 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 03/10/2017 A 08/01/2018 120B1490 Project Closed 08/01/2018 0
100189-2 B100189-2 Basin 0502 Infiltration/Inflow Study and Repairs 09/25/2014 A 02/24/2016 A 575InfiltratioInfiltration/Inflow 09/25/2014 A 02/23/2016 A 486
B1000 Infiltration/Inflow Phase 09/25/2014 A 02/23/2016 A 486Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 04/01/2015 A 233
B1005 SSES Phase 09/25/2014 A 04/01/2015 A 233B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 01/20/2015 A 02/27/2015 A 30B1031 Suspect Lateral/Smoke Test Defect Investigations 01/20/2015 A 01/23/2015 A 10B1040 Video Review 02/20/2015 A 04/01/2015 A 30
CIPP RepCIPP Repairs 05/22/2015 A 08/05/2015 A 20B1065 CIPP Phase 05/22/2015 A 08/05/2015 A 20B1080 Issue NTP for CIPP Repairs 05/22/2015 A 0B1090 Conduct CIPP Repairs 07/29/2015 A 08/05/2015 A 20
Dig & ReDig & Replace Repairs 11/20/2015 A 02/23/2016 A 30B1165 Dig & Replace Phase 11/20/2015 A 02/23/2016 A 30B1180 Issue NTP for Dig & Replace Repairs 11/20/2015 A 0B1190 Conduct Dig & Replace Repairs 02/18/2016 A 02/23/2016 A 30
Project CProject Closeout 02/24/2016 A 02/24/2016 A 0B1235 Closeout Phase 02/24/2016 A 02/24/2016 A 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Bidders Prepare Bids for Submittal
Bids SubmittalMDWASD/PSIP Team Bids Evaluation
Recommendation for Award LetterContract Award (Purchase Order Approval)
04/28/2017 A, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)
WASD Issues NTP (PO to NTP)Construction NTP
Construction OperationsOriginal Construction Duration
Change Order #1 - FPLChange Order #2 - Hurricane Mathew
Change Order #3 - Bypass, Sheet Pilling Contractor, FPLChange Order #4 - Contractual Duration Discrepancy
Substantial Completion04/28/2017 A, Designer Construction Support Services
Designer Construction Support Services04/28/2017 A, Construction Close Out
CommissioningPunch List
08/01/2018, Project Closeout
Closeout PhaseIssue SAC Letter
Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed
02/24/2016 A, 100189-2 Basin 0502 Infiltration/Inflow Study and Repairs02/23/2016 A, Infiltration/Inflow
Infiltration/Inflow Phase04/01/2015 A, Sanitary Sewer Evaluation SurveySSES Phase
Issue NTP to SSES ContractorConduct SSES
Suspect Lateral/Smoke Test Defect Investigations
Video Review08/05/2015 A, CIPP RepairsCIPP Phase
Issue NTP for CIPP RepairsConduct CIPP Repairs
02/23/2016 A, Dig & Replace RepairsDig & Replace Phase
Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs02/24/2016 A, Project CloseoutCloseout Phase
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 90 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1260 Project Closed 02/24/2016 A 0
Basin 0503Basin 0503 09/25/2014 A 09/18/2015 A 921
100095-3 B100095-3 Basin 0503 Infiltration/Inflow Study and Repairs 09/25/2014 A 07/24/2015 A 541InfiltratioInfiltration/Inflow 09/25/2014 A 07/23/2015 A 275
B1000 Infiltration/Inflow Phase 09/25/2014 A 07/23/2015 A 275Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 05/25/2015 A 30
B1005 SSES Phase 09/25/2014 A 05/25/2015 A 30B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 04/26/2015 A 05/25/2015 A 30
Dig & ReDig & Replace Repairs 05/18/2015 A 07/23/2015 A 30B1165 Dig & Replace Phase 05/18/2015 A 07/23/2015 A 30B1180 Issue NTP for Dig & Replace Repairs 05/18/2015 A 0B1190 Conduct Dig & Replace Repairs 07/21/2015 A 07/23/2015 A 30
Project CProject Closeout 07/24/2015 A 07/24/2015 A 0B1235 Closeout Phase 07/24/2015 A 07/24/2015 A 0B1260 Project Closed 07/24/2015 A 0
100225 Pu100225 Pump Station 0503 Upgrade 09/18/2015 A 09/18/2015 A 636Project CProject Closeout 09/18/2015 A 09/18/2015 A 636
B1445 Closeout Phase 09/18/2015 A 09/18/2015 A 636B1450 Issue SAC Letter 09/18/2015 A 0B1480 Administrative Closeout 09/18/2015 A 09/18/2015 A 5B1490 Project Closed 09/18/2015 A 0
Basin 0506Basin 0506 01/05/2016 A 11/08/2018 1057
100096 Pu100096 Pump Station 0506 Upgrade 01/05/2016 A 11/08/2018 1057DesignDesign 01/05/2016 A 03/06/2017 A 428
B1000 Design Phase 01/05/2016 A 03/06/2017 A 428B1010 Prepare and Submit Design Package 01/05/2016 A 01/05/2016 A 5B1020 Engage Design Consultant 01/05/2016 A 02/26/2016 A 20B1022 TA Preparation 02/29/2016 A 02/29/2016 A 1B1024 TA Approval Process 03/01/2016 A 03/16/2016 A 20B1030 Issue Design NTP 03/28/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 03/28/2016 A 11/02/2016 A 85
30% Des30% Design 03/28/2016 A 07/15/2016 A 104B1060 A/E Prepares 30% Construction Documents 03/28/2016 A 06/28/2016 A 30B1070 Geotechnical Engineering Services 03/28/2016 A 06/28/2016 A 20B1080 Surveying Services 03/28/2016 A 06/28/2016 A 15B1100 30% CDs Submittal 06/28/2016 A 0B1120 30% Review (MDWASD/PSIP Team) 06/29/2016 A 07/15/2016 A 10
90% Des90% Design 06/29/2016 A 02/21/2017 A 275B1170 A/E Prepares 90% Construction Documents 06/29/2016 A 09/26/2016 A 40B1180 90% CDs Submittal 09/26/2016 A 0B1190 90% Review (MDWASD/PSIP Team) 09/27/2016 A 11/02/2016 A 30B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 11/03/2016 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 11/03/2016 A 12/13/2016 A 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 01/04/2017 A 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 01/04/2017 A 01/24/2017 A 21B1260 90% CD PM Comments Evaluation Completed 01/25/2017 A 0B1262 MDWASD Union Concurrence Process 01/25/2017 A 02/21/2017 A 30
100% De100% Design 01/26/2017 A 03/06/2017 A 10
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Project Closed09/18/2015 A, Basin 0503
07/24/2015 A, 100095-3 Basin 0503 Infiltration/Inflow Study and Repairs07/23/2015 A, Infiltration/Inflow
Infiltration/Inflow Phase05/25/2015 A, Sanitary Sewer Evaluation SurveySSES Phase
Issue NTP to SSES ContractorConduct SSES
07/23/2015 A, Dig & Replace RepairsDig & Replace Phase
Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs
07/24/2015 A, Project CloseoutCloseout Phase
Project Closed09/18/2015 A, 100225 Pump Station 0503 Upgrade09/18/2015 A, Project Closeout
Closeout PhaseIssue SAC Letter
Administrative CloseoutProject Closed
11/08/2018, Basin 0506
11/08/2018, 100096 Pump Station 0506 Upgrade03/06/2017 A, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA PreparationTA Approval ProcessIssue Design NTP
Final Engineering Report Review & Approval (MDWASD/PSIP Team)07/15/2016 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal30% Review (MDWASD/PSIP Team)
02/21/2017 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)
90% RER(DERM)FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)
90% RER(Building Dept) Permit Review (Pump Station)90% CD PM Comments Evaluation Completed
MDWASD Union Concurrence Process03/06/2017 A, 100% Design
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 91 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1270 A/E Prepares 100% Construction Documents 01/26/2017 A 03/01/2017 A 10B1280 100% CDs Submittal 03/01/2017 A 0B1290 100% Review (MDWASD/PSIP Team) 03/02/2017 A 03/06/2017 A 2B1300 Design Completed 03/06/2017 A 0
MDWASDMDWASD Procurement 03/07/2017 A 05/31/2017 A 79B1305 Procurement Phase 03/07/2017 A 05/31/2017 A 79B1310 Submit CDs to MDWASD Procurement Division 03/07/2017 A 0B1312 Bid Notice Preparation Period 03/08/2017 A 03/16/2017 A 23B1314 Bid Notice 03/16/2017 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 03/17/2017 A 03/22/2017 A 10B1320 Pre-Bid Conference 03/23/2017 A 03/23/2017 A 1B1328 Bidders Prepare Bids for Submittal 03/24/2017 A 04/20/2017 A 15B1330 Bids Submittal 04/20/2017 A 0B1340 MDWASD/PSIP Team Bids Evaluation 04/21/2017 A 04/26/2017 A 15B1350 Recommendation for Award Letter 04/26/2017 A 0B1355 Contract Award (Purchase Order Approval) 04/27/2017 A 05/31/2017 A 10
ConstrucConstruction 03/23/2017 A 07/11/2018 A 639B1360 Construction Phase 03/23/2017 A 07/11/2018 A 639B1364 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 04/27/2017 A 06/09/2017 A 15B1366 Pre-Construction Meeting 06/12/2017 A 06/12/2017 A 1B1368 WASD Issues NTP (Pre-Const to NTP) 06/13/2017 A 08/27/2017 A 24B1369 WASD Issues NTP (PO to NTP) 06/01/2017 A 08/27/2017 A 53B1370 Construction NTP 08/28/2017 A 0B1400 Construction Operations 08/28/2017 A 07/11/2018 A 150B1402 Substantial Completion 07/11/2018 A 0
DesignerDesigner Construction Support Services 03/23/2017 A 07/11/2018 A 260B1410 Designer Construction Support Services 03/23/2017 A 07/11/2018 A 778
Project CProject Closeout 07/12/2018 A 11/08/2018 120B1445 Closeout Phase 07/12/2018 A 11/08/2018 120B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 07/12/2018 A 11/08/2018 120B1490 Project Closed 11/08/2018 0
Basin 0527Basin 0527 09/21/2015 A 09/21/2015 A 838
100226 Pu100226 Pump Station 0527 Upgrade 09/21/2015 A 09/21/2015 A 838Project CProject Closeout 09/21/2015 A 09/21/2015 A 838
B1445 Closeout Phase 09/21/2015 A 09/21/2015 A 838B1450 Issue SAC Letter 09/21/2015 A 0B1480 Administrative Closeout 09/21/2015 A 09/21/2015 A 5B1490 Project Closed 09/21/2015 A 09/21/2015 A 10
Basin 0530Basin 0530 04/29/2016 A 11/30/2018 996
100098 Pu100098 Pump Station 0530 Upgrade 04/29/2016 A 11/30/2018 996DesignDesign 04/29/2016 A 07/17/2017 A 464
B1000 Design Phase 04/29/2016 A 07/17/2017 A 464B1010 Prepare and Submit Design Package 04/29/2016 A 05/10/2016 A 5B1020 Engage Design Consultant 05/10/2016 A 07/15/2016 A 20B1022 TA Preparation 07/18/2016 A 07/18/2016 A 1B1024 TA Approval Process 07/19/2016 A 10/21/2016 A 40
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed
05/31/2017 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation Period
Bid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter
Contract Award (Purchase Order Approval)07/11/2018 A, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Construction NTPConstruction OperationsSubstantial Completion07/11/2018 A, Designer Construction Support Services
Designer Construction Support Services11/08/2018, Project Closeout
Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction Contract
Administrative CloseoutProject Closed
09/21/2015 A, Basin 0527
09/21/2015 A, 100226 Pump Station 0527 Upgrade09/21/2015 A, Project Closeout
Closeout PhaseIssue SAC Letter
Administrative CloseoutProject Closed
11/30/2018, Basin 0530
11/30/2018, 100098 Pump Station 0530 Upgrade07/17/2017 A, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval Process
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 92 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1030 Issue Design NTP 11/03/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 11/03/2016 A 06/26/2017 A 65
30% Des30% Design 11/03/2016 A 02/13/2017 A 100B1060 A/E Prepares 30% Construction Documents 11/03/2016 A 01/30/2017 A 50B1100 30% CDs Submittal 01/30/2017 A 0B1120 30% Review (MDWASD/PSIP Team) 01/31/2017 A 02/13/2017 A 30
90% Des90% Design 01/31/2017 A 06/26/2017 A 209B1170 A/E Prepares 90% Construction Documents 01/31/2017 A 03/24/2017 A 40B1180 90% CDs Submittal 03/24/2017 A 0B1190 90% Review (MDWASD/PSIP Team) 03/27/2017 A 05/05/2017 A 30B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 05/15/2017 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 05/15/2017 A 06/09/2017 A 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 06/12/2017 A 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 06/12/2017 A 06/26/2017 A 21B1260 90% CD PM Comments Evaluation Completed 06/26/2017 A 0B1262 MDWASD Union Concurrence Process 04/26/2017 A 06/20/2017 A 30
100% De100% Design 06/27/2017 A 07/17/2017 A 14B1270 A/E Prepares 100% Construction Documents 06/27/2017 A 07/10/2017 A 10B1280 100% CDs Submittal 07/10/2017 A 0B1290 100% Review (MDWASD/PSIP Team) 07/11/2017 A 07/17/2017 A 10B1300 Design Completed 07/17/2017 A 0
MDWASDMDWASD Procurement 07/18/2017 A 11/16/2017 A 118B1305 Procurement Phase 07/18/2017 A 11/16/2017 A 118B1310 Submit CDs to MDWASD Procurement Division 07/18/2017 A 0B1312 Bid Notice Preparation Period 07/19/2017 A 08/10/2017 A 33B1313 Bid Notice 08/10/2017 A 0B1315 MDWASD/PSIP Team Prepare for Pre-Bid Conferencce 08/11/2017 A 08/21/2017 A 14B1320 Pre-Bid Conference 08/22/2017 A 08/22/2017 A 1B1323 Bidders Prepare Bids for Submittal 08/23/2017 A 10/19/2017 A 21B1330 Bids Submittal 10/19/2017 A 0B1340 MDWASD/PSIP Team Bids Evaluation 10/20/2017 A 10/31/2017 A 21B1350 Recommendation for Award Letter 10/31/2017 A 0B1355 Contract Award (Purchase Order Approval) 11/01/2017 A 11/16/2017 A 14
ConstrucConstruction 08/22/2017 A 08/02/2018 506B1360 Construction Phase 08/22/2017 A 08/02/2018 506B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 11/01/2017 A 11/30/2017 A 21B1365 Pre-Construction Meeting 12/01/2017 A 12/01/2017 A 1B1366 WASD Issues NTP (Pre-Const to NTP) 12/02/2017 A 03/04/2018 A 45B1369 WASD Issues NTP (PO to NTP) 11/17/2017 A 03/04/2018 A 53B1370 Construction NTP 03/05/2018 A 0B1400 Construction Operations 03/05/2018 A 08/02/2018 151B1402 Substantial Completion 08/02/2018 0
DesignerDesigner Construction Support Services 08/22/2017 A 08/02/2018 260B1410 Designer Construction Support Services 08/22/2017 A 08/02/2018 260
Project CProject Closeout 08/01/2018 11/30/2018 122B1445 Closeout Phase 08/01/2018 11/30/2018 122B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 08/02/2018 0B1480 Administrative Closeout 08/03/2018 11/30/2018 120
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Issue Design NTPFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
02/13/2017 A, 30% Design
A/E Prepares 30% Construction Documents30% CDs Submittal30% Review (MDWASD/PSIP Team)
06/26/2017 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)90% RER(DERM)FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)90% RER(Building Dept) Permit Review (Pump Station)90% CD PM Comments Evaluation Completed
MDWASD Union Concurrence Process07/17/2017 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed
11/16/2017 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid Notice
MDWASD/PSIP Team Prepare for Pre-Bid ConferenccePre-Bid Conference
Bidders Prepare Bids for SubmittalBids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)
08/02/2018, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Construction NTPConstruction OperationsSubstantial Completion08/02/2018, Designer Construction Support Services
Designer Construction Support Services11/30/2018, Project Closeout
Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction Contract
Administrative Closeout
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 93 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1490 Project Closed 11/30/2018 0
Basin 0542Basin 0542 11/10/2015 A 08/03/2018 1135
100100 Pu100100 Pump Station 0542 Upgrade 11/10/2015 A 08/03/2018 1135DesignDesign 11/10/2015 A 02/24/2017 A 571
B1000 Design Phase 11/10/2015 A 02/24/2017 A 571B1010 Prepare and Submit Design Package 11/10/2015 A 11/10/2015 A 5B1020 Engage Design Consultant 11/10/2015 A 12/25/2015 A 20B1022 TA Preparation 12/28/2015 A 12/28/2015 A 1B1024 TA Approval Process 12/29/2015 A 01/15/2016 A 20B1030 Issue Design NTP 01/15/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 01/15/2016 A 01/20/2017 A 65
30% Des30% Design 01/18/2016 A 05/24/2016 A 52B1060 A/E Prepares 30% Construction Documents 01/18/2016 A 05/04/2016 A 30B1070 Geotechnical Engineering Services 01/18/2016 A 05/04/2016 A 20B1080 Surveying Services 01/18/2016 A 05/04/2016 A 15B1100 30% CDs Submittal 05/04/2016 A 0B1120 30% Review (MDWASD/PSIP Team) 05/05/2016 A 05/24/2016 A 10
90% Des90% Design 05/05/2016 A 02/22/2017 A 365B1170 A/E Prepares 90% Construction Documents 05/05/2016 A 06/24/2016 A 20B1180 90% CDs Submittal 06/24/2016 A 0B1190 90% Review (MDWASD/PSIP Team) 06/27/2016 A 11/07/2016 A 15B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 01/09/2017 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 01/09/2017 A 01/11/2017 A 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 01/04/2017 A 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 01/04/2017 A 01/19/2017 A 21B1260 90% CD PM Comments Evaluation Completed 01/20/2017 A 0B1262 MDWASD Union Concurrence Process 01/25/2017 A 02/22/2017 A 30
100% De100% Design 01/23/2017 A 02/24/2017 A 28B1270 A/E Prepares 100% Construction Documents 01/23/2017 A 02/24/2017 A 10B1280 100% CDs Submittal 02/24/2017 A 0B1290 100% Review (MDWASD/PSIP Team) 02/24/2017 A 02/24/2017 A 10B1300 Design Completed 02/24/2017 A 0
MDWASDMDWASD Procurement 02/24/2017 A 06/08/2017 A 75B1305 Procurement Phase 02/24/2017 A 06/08/2017 A 75B1310 Submit CDs to MDWASD Procurement Division 02/24/2017 A 0B1312 Bid Notice Preparation Period 02/27/2017 A 03/06/2017 A 23B1314 Bid Notice 03/06/2017 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 03/07/2017 A 03/13/2017 A 10B1320 Pre-Bid Conference 03/14/2017 A 03/14/2017 A 1B1328 Bidders Prepare Bids for Submittal 03/15/2017 A 04/25/2017 A 15B1330 Bids Submittal 04/25/2017 A 0B1340 MDWASD/PSIP Team Bids Evaluation 04/26/2017 A 05/10/2017 A 15B1350 Recommendation for Award Letter 05/10/2017 A 0B1355 Contract Award (Purchase Order Approval) 05/11/2017 A 06/08/2017 A 10
ConstrucConstruction 03/14/2017 A 04/13/2018 A 615B1360 Construction Phase 03/14/2017 A 04/05/2018 A 615B1364 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 05/11/2017 A 07/12/2017 A 15B1366 Pre-Construction Meeting 07/13/2017 A 07/13/2017 A 1B1368 WASD Issues NTP (Pre-Const to NTP) 07/14/2017 A 08/27/2017 A 1
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Project Closed08/03/2018, Basin 0542
08/03/2018, 100100 Pump Station 0542 Upgrade02/24/2017 A, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval ProcessIssue Design NTP
Final Engineering Report Review & Approval (MDWASD/PSIP Team)05/24/2016 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services
30% CDs Submittal30% Review (MDWASD/PSIP Team)
02/22/2017 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)
90% RER(DERM)FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)
90% RER(Building Dept) Permit Review (Pump Station)90% CD PM Comments Evaluation Completed
MDWASD Union Concurrence Process02/24/2017 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal
100% Review (MDWASD/PSIP Team)Design Completed
06/08/2017 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid Notice
MDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids SubmittalMDWASD/PSIP Team Bids Evaluation
Recommendation for Award LetterContract Award (Purchase Order Approval)
04/13/2018 A, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 94 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1369 WASD Issues NTP (PO to NTP) 06/09/2017 A 08/27/2017 A 53B1370 Construction NTP 08/28/2017 A 0B1400 Construction Operations 08/28/2017 A 04/05/2018 A 149B1400 Original Construction Duration 08/28/2017 A 01/25/2018 A 149B1400 Change Order #1 - Hurricane Irma 01/26/2018 A 02/15/2018 A 149B1400 Change Order #2 - FPL 02/16/2018 A 04/13/2018 A 149B1402 Substantial Completion 04/05/2018 A 0
DesignerDesigner Construction Support Services 03/14/2017 A 04/05/2018 A 260B1410 Designer Construction Support Services 03/14/2017 A 04/05/2018 A 778
Project CProject Closeout 04/06/2018 A 08/03/2018 124B1445 Closeout Phase 04/06/2018 A 08/03/2018 124B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 04/06/2018 A 08/03/2018 120B1490 Project Closed 08/03/2018 0
Basin 0560Basin 0560 11/06/2015 A 08/18/2019 1382
100101 Pu100101 Pump Station 0560 Upgrade 11/06/2015 A 08/18/2019 1382DesignDesign 11/06/2015 A 12/23/2016 A 434
B1000 Design Phase 11/06/2015 A 12/23/2016 A 434B1010 Prepare and Submit Design Package 11/06/2015 A 11/19/2015 A 5B1020 Engage Design Consultant 11/20/2015 A 12/28/2015 A 20B1022 TA Preparation 12/29/2015 A 12/29/2015 A 1B1024 TA Approval Process 12/14/2015 A 01/15/2016 A 20B1030 Issue Design NTP 01/20/2016 A 0B1040 A/E Develops and Submits Final Engineering Report 01/20/2016 A 12/15/2016 A 115B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 01/20/2016 A 08/25/2016 A 85
30% Des30% Design 01/20/2016 A 04/19/2016 A 87B1060 A/E Prepares 30% Construction Documents 01/20/2016 A 03/07/2016 A 30B1070 Geotechnical Engineering Services 01/20/2016 A 03/07/2016 A 20B1080 Surveying Services 01/20/2016 A 03/07/2016 A 15B1100 30% CDs Submittal 03/07/2016 A 0B1120 30% Review (MDWASD/PSIP Team) 03/08/2016 A 04/19/2016 A 10
60% Des60% Design 03/08/2016 A 06/23/2016 A 69B1130 A/E Prepares 60% Construction Documents 03/08/2016 A 05/24/2016 A 20B1140 60% CDs Submittal 05/24/2016 A 0B1160 60% Review (MDWASD/PSIP Team) 05/25/2016 A 06/23/2016 A 10
90% Des90% Design 05/25/2016 A 12/15/2016 A 197B1170 A/E Prepares 90% Construction Documents 05/25/2016 A 07/29/2016 A 20B1180 90% CDs Submittal 07/29/2016 A 0B1190 90% Review (MDWASD/PSIP Team) 08/01/2016 A 09/14/2016 A 30B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 09/26/2016 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 09/26/2016 A 11/02/2016 A 15B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 11/09/2016 A 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 11/09/2016 A 12/15/2016 A 15B1260 90% CD PM Comments Evaluation Completed 12/15/2016 A 0
100% De100% Design 12/16/2016 A 12/23/2016 A 28B1270 A/E Prepares 100% Construction Documents 12/16/2016 A 12/22/2016 A 10B1280 100% CDs Submittal 12/22/2016 A 0B1290 100% Review (MDWASD/PSIP Team) 12/22/2016 A 12/23/2016 A 10
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
WASD Issues NTP (PO to NTP)
Construction NTPConstruction Operations
Original Construction DurationChange Order #1 - Hurricane Irma
Change Order #2 - FPL
Substantial Completion04/05/2018 A, Designer Construction Support Services
Designer Construction Support Services08/03/2018, Project Closeout
Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction ContractAdministrative CloseoutProject Closed
08/18/2019, Basin 0560
08/18/2019, 100101 Pump Sta12/23/2016 A, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA PreparationTA Approval ProcessIssue Design NTP
A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
04/19/2016 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services
30% CDs Submittal30% Review (MDWASD/PSIP Team)
06/23/2016 A, 60% Design
A/E Prepares 60% Construction Documents60% CDs Submittal
60% Review (MDWASD/PSIP Team)12/15/2016 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)
90% RER(DERM)FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)
90% RER(Building Dept) Permit Review (Pump Station)90% CD PM Comments Evaluation Completed12/23/2016 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 95 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1300 Design Completed 12/23/2016 A 0MDWASDMDWASD Procurement 12/23/2016 A 08/30/2018 596
B1305 Procurement Phase 12/23/2016 A 08/30/2018 596B1310 Submit CDs to MDWASD Procurement Division 12/23/2016 A 0B1312 Bid Notice Preparation Period 12/26/2016 A 01/24/2017 A 23B1314 Bid Notice 01/24/2017 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 01/25/2017 A 02/01/2017 A 10B1320 Pre-Bid Conference 02/02/2017 A 02/02/2017 A 1B1328 Bidders Prepare Bids for Submittal 02/03/2017 A 02/28/2017 A 15B1330 Bids Submittal 02/28/2017 A 0B1340 MDWASD/PSIP Team Bids Evaluation 03/01/2017 A 03/08/2017 A 6B1350 Recommendation for Award Letter 03/08/2017 A 0B1355 Contract Award (Purchase Order Approval) 03/09/2017 A 04/07/2017 A 10B1355 Submit CDs to MDWASD Procurement Division 05/18/2018 A 0B1355 Bid Notice Preparation Period 05/19/2018 A 06/13/2018 A 33B1355 Bid Notice 06/13/2018 A 0B1355 MDWASD/PSIP Team Prepare for Pre-Bid Conference 06/14/2018 A 06/25/2018 A 14B1355 Pre-Bid Conference 06/26/2018 A 06/26/2018 A 1B1355 Bidders Prepare Bids for Submittal 06/27/2018 A 07/26/2018 A 21B1355 Bids Submittal 07/26/2018 A 0B1355 MDWASD/PSIP Team Bids Evaluation 07/27/2018 A 08/16/2018 21B1355 Recommendation for Award Letter 08/16/2018 0B1355 Contract Award (Purchase Order Approval) 08/17/2018 08/30/2018 14
ConstrucConstruction 03/09/2017 A 04/20/2019 808B1360 Construction Phase 03/09/2017 A 04/20/2019 808B1364 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 03/09/2017 A 04/11/2017 A 15B1366 Pre-Construction Meeting 04/12/2017 A 04/12/2017 A 1B1368 WASD Issues NTP Period 04/13/2017 A 05/19/2017 A 45B1370 Construction NTP 05/22/2017 A 0B1400 Construction Operations 05/22/2017 A 08/09/2017 A 151B1400 WASD Terminate Contract 08/10/2017 A 08/10/2017 A 1B1400 WASD/PSIP Team Re-Package Resolution Period 08/11/2017 A 08/29/2017 A 160B1400 Finalize Project Closeout with A Green World (Contractor) 08/30/2017 A 08/01/2018 275B1400 A/E Prepared SOW to Re-Package Contract Documents 08/30/2017 A 03/15/2018 A 198B1400 TA Approval Process 03/16/2018 A 05/08/2018 A 40B1400 A/E Re-Package Contract Documents 05/09/2018 A 05/18/2018 A 10B1400 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 08/17/2018 09/06/2018 21B1400 Pre-Construction Meeting 09/07/2018 09/07/2018 1B1400 WASD Issues NTP (Pre-Const to NTP) 09/08/2018 10/22/2018 45B1400 WASD Issues NTP (PO to NTP) 08/31/2018 10/22/2018 53B1400 Construction NTP 10/23/2018 0B1400 Construction Operations 10/23/2018 04/20/2019 180B1402 Substantial Completion 04/20/2019 0
DesignerDesigner Construction Support Services 05/22/2017 A 04/20/2019 267B1410 Designer Construction Support Services 05/22/2017 A 04/20/2019 267
Project CProject Closeout 08/01/2018 08/18/2019 383B1445 Closeout Phase 08/01/2018 08/18/2019 383B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 04/20/2019 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Design Completed08/30/2018, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter
Contract Award (Purchase Order Approval)Submit CDs to MDWASD Procurement Division
Bid Notice Preparation Period
Bid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for Submittal
Bids SubmittalMDWASD/PSIP Team Bids Evaluation
Recommendation for Award LetterContract Award (Purchase Order Approval)
04/20/2019, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
WASD Issues NTP PeriodConstruction NTP
Construction OperationsWASD Terminate Contract
WASD/PSIP Team Re-Package Resolution PeriodFinalize Project Closeout with A Green World (Contractor)
A/E Prepared SOW to Re-Package Contract DocumentsTA Approval ProcessA/E Re-Package Contract Documents
MDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Construction NTPConstruction Operations
Substantial Completion04/20/2019, Designer Construction Supp
Designer Construction Support Services08/18/2019, Project Closeout
Closeout PhaseIssue SAC Letter
Final Release of Retainage - Construction
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 96 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1480 Administrative Closeout 04/21/2019 08/18/2019 120B1490 Project Closed 08/18/2019 0
Basin 0592Basin 0592 09/17/2012 A 08/03/2018 2938
100103 FM100103 FM for Pump Station 0592 09/18/2015 A 08/01/2018 1143DesignDesign 09/18/2015 A 11/01/2016 A 607
B1000 Design Phase 09/18/2015 A 11/01/2016 A 607B1010 Prepare and Submit Design Package 09/18/2015 A 10/19/2015 A 5B1020 Engage Design Consultant 10/20/2015 A 11/12/2015 A 20B1022 TA Preparation 11/12/2015 A 11/12/2015 A 1B1024 TA Approval Provess 11/13/2015 A 12/11/2015 A 20B1030 Issue Design NTP 12/30/2015 A 0B1040 A/E Develops and Submits Final Engineering Report 12/30/2015 A 10/24/2016 A 105B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 12/30/2015 A 08/09/2016 A 85
30% Des30% Design 12/30/2015 A 02/25/2016 A 69B1060 A/E Prepares 30% Construction Documents 12/31/2015 A 02/08/2016 A 30B1070 Geotechnical Engineering Services 12/30/2015 A 02/08/2016 A 20B1080 Surveying Services 12/30/2015 A 02/08/2016 A 15B1100 30% CDs Submittal 02/08/2016 A 0B1120 30% Review (MDWASD/PSIP Team) 02/09/2016 A 02/25/2016 A 10
60% Des60% Design 02/09/2016 A 04/04/2016 A 44B1140 A/E Prepares 60% Construction Documents 02/09/2016 A 03/28/2016 A 20B1150 60% CDs Submittal 03/28/2016 A 0B1170 60% Review (MDWASD/PSIP Team) 03/29/2016 A 04/04/2016 A 10
90% Des90% Design 03/29/2016 A 10/24/2016 A 225B1180 A/E Prepares 90% Construction Documents 03/29/2016 A 06/27/2016 A 20B1190 90% CDs Submittal 06/27/2016 A 0B1200 90% Review (MDWASD/PSIP Team) 06/28/2016 A 08/09/2016 A 15B1202 90% CSX Permit Submittal (Force Main) 06/28/2016 A 0B1204 90% CSX Permit Review (Force Main) 06/28/2016 A 10/03/2016 A 15B1210 90% PWWMD Permit Submittal (Force Main) 07/13/2016 A 0B1220 90% PWWMD Permit Review (Force Main) 07/13/2016 A 07/29/2016 A 15B1230 90% RER(DERM)FDEP Permit Submittal (Force Main) 09/15/2016 A 0B1240 90% RER(DERM)FDEP Permit Review (Force Main) 09/15/2016 A 10/24/2016 A 15B1290 90% CD PM Comments Evaluation Completed 10/24/2016 A 0
100% De100% Design 10/25/2016 A 11/01/2016 A 57B1300 A/E Prepares 100% Construction Documents 10/25/2016 A 11/01/2016 A 10B1310 100% CDs Submittal 11/01/2016 A 0B1320 100% Review (MDWASD/PSIP Team) 10/25/2016 A 11/01/2016 A 10B1330 Design Completed 11/01/2016 A 0
MDWASDMDWASD Procurement 11/08/2016 A 03/17/2017 A 103B1335 Procurement Phase 11/08/2016 A 03/17/2017 A 103B1340 Submit CDs to MDWASD Procurement Division 11/08/2016 A 0B1342 Bid Notice Preparation Period 11/09/2016 A 11/17/2016 A 33B1344 Bid Notice 11/17/2016 A 0B1346 MDWASD/PSIP Prepare for Pre-Bid Conference 11/18/2016 A 11/28/2016 A 14B1350 Pre-Bid Conference 11/29/2016 A 11/29/2016 A 1B1358 Bidders Prepare Bids for Submittal 11/30/2016 A 01/13/2017 A 21B1360 Bids Submittal 01/13/2017 A 0B1370 MDWASD/PSIP Team Bids Evaluation 01/16/2017 A 02/17/2017 A 21
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Administrative CloseoutProject Closed
08/03/2018, Basin 0592
08/01/2018, 100103 FM for Pump Station 059211/01/2016 A, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval ProvessIssue Design NTP
A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
02/25/2016 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal30% Review (MDWASD/PSIP Team)
04/04/2016 A, 60% Design
A/E Prepares 60% Construction Documents60% CDs Submittal60% Review (MDWASD/PSIP Team)
10/24/2016 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% CSX Permit Submittal (Force Main)
90% CSX Permit Review (Force Main)90% PWWMD Permit Submittal (Force Main)90% PWWMD Permit Review (Force Main)
90% RER(DERM)FDEP Permit Submittal (Force Main)90% RER(DERM)FDEP Permit Review (Force Main)90% CD PM Comments Evaluation Completed11/01/2016 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal
100% Review (MDWASD/PSIP Team)Design Completed
03/17/2017 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation Period
Bid NoticeMDWASD/PSIP Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids Evaluation
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 97 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1380 Recommendation for Award Letter 02/17/2017 A 0B1385 Contract Award (Purchase Order Approval) 02/20/2017 A 03/17/2017 A 14
ConstrucConstruction 11/29/2016 A 01/30/2018 A 747B1390 Construction Phase 11/29/2016 A 01/30/2018 A 747B1394 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 02/20/2017 A 04/04/2017 A 21B1396 Pre-Construction meeting 04/05/2017 A 04/05/2017 A 1B1398 WASD Issues NTP (Pre-Const to NTP) 04/05/2017 A 06/18/2017 A 45B1399 WASD Issues NTP (PO to NTP) 03/18/2017 A 06/18/2017 A 53B1400 Construction NTP 06/19/2017 A 0B1430 Construction Operations 06/19/2017 A 01/30/2018 A 241B1432 Substantial Completion 01/30/2018 A 0
DesignerDesigner Construction Support Services 11/29/2016 A 01/30/2018 A 277B1440 Designer Construction Support Services 11/29/2016 A 01/30/2018 A 277
Project CProject Closeout 01/31/2018 A 08/01/2018 201B1475 Closeout Phase 01/31/2018 A 08/01/2018 201B1500 Final Release of Retainage - Construction Contract 08/01/2018 0B1510 Administrative Closeout 01/31/2018 A 08/01/2018 120B1520 Project Closed 08/01/2018 0
100227 Pu100227 Pump Station 0592 Upgrade 09/17/2012 A 08/03/2018 2057DesignDesign 09/17/2012 A 04/05/2018 A 2027
B1000 Design Phase 09/17/2012 A 04/05/2018 A 2027B1012 Remedial Action Plan to SAC Issuance Letter 09/17/2012 A 04/05/2018 A 2027
ConstrucConstruction 08/01/2018 08/01/2018 0B1360 Construction Phase 08/01/2018 08/01/2018 0
Project CProject Closeout 04/05/2018 A 08/03/2018 820B1445 Closeout Phase 04/05/2018 A 08/03/2018 820B1450 Issue SAC Letter 04/05/2018 A 0B1480 Administrative Closeout 04/06/2018 A 08/03/2018 120B1490 Project Closed 08/03/2018 0
Basin 0596Basin 0596 05/11/2016 A 11/29/2019 1398
100104 Pu100104 Pump Station 0596 Upgrade 05/11/2016 A 11/29/2019 1398DesignDesign 05/11/2016 A 08/29/2018 941
B1000 Design Phase 05/11/2016 A 08/29/2018 941B1010 Prepare and Submit Design Package 05/11/2016 A 05/17/2016 A 7B1020 Engage Design Consultant 05/18/2016 A 07/19/2017 A 20B1022 TA Preparation 06/20/2017 A 06/20/2017 A 1B1024 TA Approval Process 06/21/2017 A 08/09/2017 A 40B1030 Issue Design NTP 09/21/2017 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 09/21/2017 A 08/01/2018 186
30% Des30% Design 09/22/2017 A 01/26/2018 A 102B1060 A/E Prepares 30% Construction Documents 09/22/2017 A 01/11/2018 A 50B1100 30% CDs Submittal 01/11/2018 A 0B1120 30% Review (MDWASD/PSIP Team) 01/12/2018 A 01/26/2018 A 30
90% Des90% Design 01/29/2018 A 08/01/2018 154B1170 A/E Prepares 90% Construction Documents 01/29/2018 A 03/22/2018 A 40B1180 90% CDs Submittal 03/22/2018 A 0B1190 90% Review (MDWASD/PSIP Team) 03/23/2018 A 05/18/2018 A 30B1200 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 05/21/2018 A 0B1210 90% RER(DERM)/FDEP Permit Review (Pump Station) 05/21/2018 A 06/25/2018 A 45
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Recommendation for Award LetterContract Award (Purchase Order Approval)
01/30/2018 A, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction meeting
WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Construction NTPConstruction OperationsSubstantial Completion01/30/2018 A, Designer Construction Support Services
Designer Construction Support Services08/01/2018, Project Closeout
Closeout PhaseFinal Release of Retainage - Construction ContractAdministrative CloseoutProject Closed08/03/2018, 100227 Pump Station 0592 Upgrade
04/05/2018 A, Design
Design PhaseRemedial Action Plan to SAC Issuance Letter
08/01/2018, Construction
Construction Phase08/03/2018, Project CloseoutCloseout Phase
Issue SAC LetterAdministrative Closeout
Project Closed11/29/2019, Basin 059
11/29/2019, 100104 P08/29/2018, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval ProcessIssue Design NTP
Final Engineering Report Review & Approval (MDWASD/PSIP 01/26/2018 A, 30% Design
A/E Prepares 30% Construction Documents30% CDs Submittal30% Review (MDWASD/PSIP Team)
08/01/2018, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)/FDEP Permit Submittal (Pump Station)
90% RER(DERM)/FDEP Permit Review (Pump Station)
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 98 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 06/28/2018 A 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 06/28/2018 A 08/01/2018 21B1260 90% CD PM Comments Evaluation Completed 08/01/2018 0
100% De100% Design 08/02/2018 08/29/2018 28B1270 A/E Prepares 100% Construction Documents 08/02/2018 08/15/2018 14B1280 100% CDs Submittal 08/15/2018 0B1290 100% Review (MDWASD/PSIP Team) 08/16/2018 08/29/2018 14B1300 Design Completed 08/29/2018 0
MDWASDMDWASD Procurement 08/29/2018 12/11/2018 104B1305 Procurement Phase 08/29/2018 12/11/2018 104B1310 Submit CDs to MDWASD Procurement Division 08/29/2018* 0B1312 Bid Notice Preparation Period 08/30/2018 10/01/2018 33B1314 Bid Notice 10/01/2018 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 10/02/2018 10/15/2018 14B1320 Pre-Bid Conference 10/16/2018 10/16/2018 1B1322 Bidders Prepare Bids for Submittal 10/17/2018 11/06/2018 21B1330 Bids Submittal 11/06/2018 0B1340 MDWASD/PSIP Team Bids Evaluation 11/07/2018 11/27/2018 21B1350 Recommendation for Award Letter 11/27/2018 0B1355 Contract Award (Purchase Order Approval) 11/28/2018 12/11/2018 14
ConstrucConstruction 10/16/2018 08/01/2019 290B1360 Construction Phase 10/16/2018 08/01/2019 290B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 11/28/2018 12/18/2018 21B1364 Pre-Construction Meeting 12/19/2018 12/19/2018 1B1366 WASD Issues NTP (Pre-Const to NTP) 12/20/2018 02/02/2019 45B1369 WASD Issues NTP (PO to NTP) 12/12/2018 02/02/2019 53B1370 Construction NTP 02/03/2019 0B1400 Construction Operations 02/03/2019 08/01/2019 180B1402 Substantial Completion 08/01/2019 0
DesignerDesigner Construction Support Services 10/16/2018 08/01/2019 290B1410 Designer Construction Support Services 10/16/2018 08/01/2019 290
Project CProject Closeout 08/01/2018 11/29/2019 486B1445 Closeout Phase 08/01/2018 11/29/2019 486B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 08/01/2019 0B1480 Administrative Closeout 08/02/2019 11/29/2019 120B1490 Project Closed 11/29/2019 0
Basin 0604Basin 0604 07/07/2014 A 08/01/2018 1658
100106 FM100106 FM for Pump Station 0604 07/16/2014 A 08/01/2018 1615DesignDesign 07/16/2014 A 05/18/2015 A 326
B1000 Design Phase 07/16/2014 A 05/18/2015 A 326B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 07/16/2014 A 07/23/2014 A 5B1020 Engage Design Consultant 07/24/2014 A 11/05/2014 A 20B1030 Issue Design NTP 11/05/2014 A 0B1040 A/E Develops and Submits Final Engineering Report 11/05/2014 A 05/05/2015 A 20B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 03/23/2015 A 04/08/2015 A 10
30% Des30% Design 11/06/2014 A 02/18/2015 A 61B1060 A/E Prepares 30% Construction Documents 11/06/2014 A 02/11/2015 A 30B1070 Geotechnical Engineering Services 11/06/2014 A 02/11/2015 A 20
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
90% RER(Building Dept) Permit Submittal (Pump Station)90% RER(Building Dept) Permit Review (Pump Station)90% CD PM Comments Evaluation Completed
08/29/2018, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed
12/11/2018, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)
08/01/2019, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-ConstructionPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Construction NTPConstruction OperationsSubstantial Completion08/01/2019, Designer Constructi
Designer Construction Support S11/29/2019, Project CloCloseout Phase
Issue SAC LetterFinal Release of Retainage - Con
Administrative CloseouProject Closed
08/01/2018, Basin 0604
08/01/2018, 100106 FM for Pump Station 060405/18/2015 A, Design
Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book
Engage Design ConsultantIssue Design NTP
A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
02/18/2015 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering Services
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 99 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1080 Surveying Services 11/06/2014 A 02/11/2015 A 15B1100 30% CDs Submittal 02/11/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 02/12/2015 A 02/18/2015 A 10
90% Des90% Design 02/12/2015 A 05/05/2015 A 85B1140 A/E Prepares 90% Construction Documents 02/12/2015 A 03/23/2015 A 20B1150 90% CDs Submittal 03/23/2015 A 0B1160 90% Review (MDWASD/PSIP Team) 03/24/2015 A 04/08/2015 A 5B1170 90% PWWMD Permit Submittal 04/22/2015 A 0B1180 90% PWWMD Permit Review 04/22/2015 A 05/05/2015 A 10B1190 90% RER(DERM)FDEP Permit Submittal (Force Main) 04/10/2015 A 0B1200 90% RER(DERM)FDEP Permit Review (Force Main) 04/10/2015 A 04/29/2015 A 5B1250 90% CD PM Comments Evaluation Completed 05/05/2015 A 0
100% De100% Design 05/06/2015 A 05/18/2015 A 14B1260 A/E Prepares 100% Construction Documents 05/06/2015 A 05/13/2015 A 5B1270 100% CDs Submittal 05/13/2015 A 0B1280 100% Review (MDWASD/PSIP Team) 05/14/2015 A 05/18/2015 A 5B1290 Design Completed 05/18/2015 A 0
MDWASDMDWASD Procurement 04/23/2015 A 07/27/2015 A 111B1295 Procurement Phase 04/23/2015 A 07/27/2015 A 111B1300 Submit CDs to MDWASD Procurement Division 04/23/2015 A 0B1310 Pre-Bid Conference 05/12/2015 A 0B1320 Bids Submittal 06/15/2015 A 0B1330 MDWASD/PSIP Team Bids Evaluation 06/16/2015 A 06/19/2015 A 20B1340 Recommendation for Award Letter 06/19/2015 A 0B1345 Contract Award (Purchase Order Approval) 06/22/2015 A 07/27/2015 A 10
ConstrucConstruction 05/12/2015 A 12/15/2015 A 1226B1350 Construction Phase 05/12/2015 A 12/15/2015 A 1226B1354 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 06/22/2015 A 07/24/2015 A 15B1356 Pre-Construction Meeting 07/27/2015 A 07/27/2015 A 1B1358 Permits / Shop Drawings / Material Orders 07/27/2015 A 11/20/2015 A 15B1359 WASD Issues NTP (PO to NTP) 07/28/2015 A 08/09/2015 A 53B1360 Construction NTP 08/10/2015 A 0B1390 Construction Operations 08/10/2015 A 12/15/2015 A 100B1392 Substantial Completion 12/15/2015 A 0
DesignerDesigner Construction Services 05/12/2015 A 12/15/2015 A 175B1400 Designer Construction Support Services 05/12/2015 A 12/15/2015 A 175
ConstrucConstruction Close Out 12/01/2015 A 12/15/2015 A 15B1410 Commissioning 12/01/2015 A 12/15/2015 A 15B1420 Punch List 12/01/2015 A 12/15/2015 A 10
Project CProject Closeout 12/16/2015 A 08/01/2018 944B1435 Closeout Phase 12/16/2015 A 08/01/2018 944B1460 Final Release of Retainage - Construction Contract 03/07/2017 A 0B1470 Administrative Closeout 12/16/2015 A 08/01/2018 120B1480 Project Closed 08/01/2018 0
100105-2 B100105-2 Basin 0604 Infiltration/Inflow Study and Repairs 09/25/2014 A 10/06/2015 A 609InfiltratioInfiltration/Inflow 09/25/2014 A 10/05/2015 A 429
B1000 Infiltration/Inflow Phase 09/25/2014 A 10/05/2015 A 429Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 12/19/2014 A 274
B1005 SSES Phase 09/25/2014 A 12/19/2014 A 274
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Surveying Services30% CDs Submittal
30% Review (MDWASD/PSIP Team)05/05/2015 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)
90% PWWMD Permit Submittal90% PWWMD Permit Review
90% RER(DERM)FDEP Permit Submittal (Force Main)90% RER(DERM)FDEP Permit Review (Force Main)90% CD PM Comments Evaluation Completed05/18/2015 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal
100% Review (MDWASD/PSIP Team)Design Completed
07/27/2015 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement DivisionPre-Bid Conference
Bids SubmittalMDWASD/PSIP Team Bids Evaluation
Recommendation for Award LetterContract Award (Purchase Order Approval)
12/15/2015 A, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
Permits / Shop Drawings / Material OrdersWASD Issues NTP (PO to NTP)
Construction NTPConstruction OperationsSubstantial Completion
12/15/2015 A, Designer Construction Services
Designer Construction Support Services12/15/2015 A, Construction Close Out
CommissioningPunch List
08/01/2018, Project Closeout
Closeout PhaseFinal Release of Retainage - Construction Contract
Administrative CloseoutProject Closed
10/06/2015 A, 100105-2 Basin 0604 Infiltration/Inflow Study and Repairs10/05/2015 A, Infiltration/Inflow
Infiltration/Inflow Phase12/19/2014 A, Sanitary Sewer Evaluation SurveySSES Phase
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 100 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 10/10/2014 A 12/05/2014 A 30B1031 Smoke Testing 10/21/2014 A 10/21/2014 A 10B1040 Video Review 12/08/2014 A 12/19/2014 A 30
CIPP RepCIPP Repairs 04/17/2015 A 06/17/2015 A 33B1065 CIPP Phase 04/17/2015 A 06/17/2015 A 33B1080 Issue NTP for CIPP Repairs 04/17/2015 A 0B1090 Conduct CIPP Repairs 06/17/2015 A 06/17/2015 A 20
ManholeManhole Repairs 07/15/2015 A 10/05/2015 A 20B1115 Manhole Phase 07/15/2015 A 10/05/2015 A 20B1130 Issue NTP for Manhole Repairs 07/15/2015 A 0B1140 Conduct Manhole Repairs 09/30/2015 A 10/05/2015 A 20
Dig & ReDig & Replace Repairs 06/26/2015 A 09/18/2015 A 30B1165 Dig & Replace Phase 06/26/2015 A 09/18/2015 A 30B1180 Issue NTP for Dig & Replace Repairs 06/26/2015 A 0B1190 Conduct Dig & Replace Repairs 09/14/2015 A 09/18/2015 A 30
Project CProject Closeout 10/06/2015 A 10/06/2015 A 0B1235 Closeout Phase 10/06/2015 A 10/06/2015 A 0B1260 Project Closed 10/06/2015 A 0
100107 Pu100107 Pump Station 0604 Upgrade 07/07/2014 A 08/01/2018 1658DesignDesign 07/07/2014 A 04/21/2016 A 403
B1000 Design Phase 07/07/2014 A 04/21/2016 A 403B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 07/07/2014 A 07/14/2014 A 5B1020 Engage Design Consultant 07/14/2014 A 10/08/2014 A 20B1030 Issue Design NTP 10/08/2014 A 0B1032 TA Rev 1 - Approval Process 01/19/2016 A 04/21/2016 A 20B1040 A/E Develops and Submits Final Engineering Report 10/08/2014 A 07/28/2015 A 20B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/08/2014 A 02/17/2015 A 10
30% Des30% Design 09/10/2014 A 11/26/2014 A 45B1060 A/E Prepares 30% Construction Documents 09/10/2014 A 11/17/2014 A 30B1070 Geotechnical Engineering Services 10/20/2014 A 10/24/2014 A 20B1080 Surveying Services 10/17/2014 A 11/14/2014 A 15B1100 30% CDs Submittal 11/17/2014 A 0B1120 30% Review (MDWASD/PSIP Team) 11/18/2014 A 11/26/2014 A 10
90% Des90% Design 11/18/2014 A 07/28/2015 A 189B1170 A/E Prepares 90% Construction Documents 11/18/2014 A 01/28/2015 A 20B1180 90% CDs Submittal 01/28/2015 A 0B1190 90% Review (MDWASD/PSIP Team) 01/29/2015 A 02/17/2015 A 15B1191 Design Consultant Preparing Permit Packages 02/23/2015 A 03/04/2015 A 10B1200 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 03/06/2015 A 0B1210 90% RER(DERM)/FDEP Permit Review (Pump Station) 03/06/2015 A 06/24/2015 A 15B1220 90% RER (Building Dept) Permit Submittal 06/25/2015 A 0B1230 90% RER (Building Dept) Permit Review 06/25/2015 A 07/28/2015 A 15B1260 90% CD PM Comments Evaluation Completed 07/28/2015 A 0
100% De100% Design 07/29/2015 A 08/07/2015 A 18B1270 A/E Prepares 100% Construction Documents 07/29/2015 A 08/07/2015 A 10B1280 100% CDs Submittal 08/07/2015 A 0B1290 100% Review (MDWASD/PSIP Team) 08/07/2015 A 08/07/2015 A 10B1300 Design Completed 08/07/2015 A 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Issue NTP to SSES ContractorConduct SSES
Smoke Testing
Video Review06/17/2015 A, CIPP RepairsCIPP Phase
Issue NTP for CIPP RepairsConduct CIPP Repairs
10/05/2015 A, Manhole RepairsManhole Phase
Issue NTP for Manhole RepairsConduct Manhole Repairs
09/18/2015 A, Dig & Replace RepairsDig & Replace Phase
Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs10/06/2015 A, Project CloseoutCloseout Phase
Project Closed08/01/2018, 100107 Pump Station 0604 Upgrade
04/21/2016 A, Design
Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book
Engage Design ConsultantIssue Design NTP
TA Rev 1 - Approval Process
A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
11/26/2014 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering Services
Surveying Services30% CDs Submittal
30% Review (MDWASD/PSIP Team)07/28/2015 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)Design Consultant Preparing Permit Packages90% RER(DERM)/FDEP Permit Submittal (Pump Station)
90% RER(DERM)/FDEP Permit Review (Pump Station)90% RER (Building Dept) Permit Submittal
90% RER (Building Dept) Permit Review90% CD PM Comments Evaluation Completed08/07/2015 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 101 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
MDWASDMDWASD Procurement 04/28/2015 A 08/11/2015 A 204B1305 Procurement Phase 04/28/2015 A 08/11/2015 A 204B1310 Submit CDs to MDWASD Procurement Division 04/28/2015 A 0B1312 Bid Notice Preparation Period 04/29/2015 A 05/05/2015 A 23B1314 Bid Notice 05/06/2015 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conferencce 05/07/2015 A 05/14/2015 A 10B1320 Pre-Bid Conference 05/15/2015 A 05/15/2015 A 1B1328 Bidders Prepare Bids for Submittal 05/18/2015 A 07/16/2015 A 15B1330 Bids Submittal 07/17/2015 A 0B1340 MDWASD/PSIP Team Bids Evaluation 07/20/2015 A 07/22/2015 A 15B1350 Recommendation for Award Letter 07/22/2015 A 0B1355 Contract Award (Purchase Order Approval) 07/23/2015 A 08/11/2015 A 10
ConstrucConstruction 05/15/2015 A 01/24/2017 A 1258B1360 Construction Phase 05/15/2015 A 01/24/2017 A 1258B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 07/23/2015 A 07/27/2015 A 15B1365 Pre-Construction Meeting 07/28/2015 A 07/28/2015 A 1B1369 WASD Issues NTP (PO to NTP) 08/12/2015 A 08/16/2015 A 53B1370 Construction NTP 08/17/2015 A 0B1400 Construction Operations 08/17/2015 A 03/02/2016 A 104B1400 Original Construction Duration 08/17/2015 A 01/09/2016 A 104B1400 Change Order #1 - Electrical Revisions, Shopdrawing Approval 01/10/2016 A 02/26/2016 A 104B1400 Change Order #2 - FPL 02/27/2016 A 03/02/2016 A 104B1402 Substantial Completion 03/02/2016 A 0
DesignerDesigner Construction Support Services 05/15/2015 A 01/24/2017 A 114B1410 Designer Construction Support Services 05/15/2015 A 01/24/2017 A 114
ConstrucConstruction Close Out 03/03/2016 A 08/31/2016 A 15B1420 Commissioning 03/03/2016 A 08/31/2016 A 15B1430 Punch List 03/03/2016 A 06/30/2016 A 10
Project CProject Closeout 03/03/2016 A 08/01/2018 853B1445 Closeout Phase 03/03/2016 A 08/01/2018 853B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 08/23/2016 A 0B1480 Administrative Closeout 03/03/2016 A 08/01/2018 30B1490 Project Closed 08/01/2018 0
Basin 0607Basin 0607 05/19/2014 A 05/31/2017 A 1637
100109 Pu100109 Pump Station 0607 Upgrade 05/19/2014 A 05/31/2017 A 1637100% De100% Design 06/23/2014 A 06/23/2014 A 0
B1300 Design Completed 06/23/2014 A 0MDWASDMDWASD Procurement 05/19/2014 A 09/24/2014 A 173
B1305 Procurement Phase 05/19/2014 A 09/24/2014 A 173B1310 Submit CDs to MDWASD Procurement Division 05/19/2014 A 0B1312 Bid Notice Preparation Period 05/20/2014 A 06/30/2014 A 23B1313 Bid Notice 06/30/2014 A 0B1315 MDWASD/PSIP Team Prepare for Pre-Bid Conferencce 07/01/2014 A 07/16/2014 A 10B1320 Pre-Bid Conference 07/16/2014 A 0B1323 Bidders Prepare Bids for Submittal 07/17/2014 A 07/24/2014 A 15B1330 Bids Submittal 07/24/2014 A 0B1340 MDWASD/PSIP Team Bids Evaluation 07/25/2014 A 08/13/2014 A 10B1350 Recommendation for Award Letter 08/14/2014 A 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
08/11/2015 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation Period
Bid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferenccePre-Bid Conference
Bidders Prepare Bids for SubmittalBids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)
01/24/2017 A, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
WASD Issues NTP (PO to NTP)
Construction NTPConstruction Operations
Original Construction DurationChange Order #1 - Electrical Revisions, Shopdrawing ApprovalChange Order #2 - FPL
Substantial Completion01/24/2017 A, Designer Construction Support Services
Designer Construction Support Services08/31/2016 A, Construction Close Out
CommissioningPunch List
08/01/2018, Project Closeout
Closeout PhaseIssue SAC Letter
Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed
05/31/2017 A, Basin 0607
05/31/2017 A, 100109 Pump Station 0607 Upgrade06/23/2014 A, 100% Design
Design Completed09/24/2014 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferenccePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 102 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1352 Contract Award (Purchase Order Approval) 08/15/2014 A 09/24/2014 A 10ConstrucConstruction 09/24/2014 A 11/30/2015 A 1523
B1360 Construction Phase 09/24/2014 A 11/30/2015 A 1523B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 09/25/2014 A 10/07/2014 A 15B1365 Pre-Construction Meeting 10/07/2014 A 0B1369 WASD Issues NTP (PO to NTP) 09/25/2014 A 12/07/2014 A 53B1370 Construction NTP 12/08/2014 A 0B1380 Mobilization 01/12/2015 A 05/22/2015 A 40B1390 Permit Approvals 09/24/2014 A 12/07/2014 A 20B1400 Construction Operations 12/08/2014 A 10/14/2015 A 249B1400 Original Construction Duration 12/08/2014 A 06/06/2015 A 249B1400 Change Order #1 - Re-Design of Pipe Diameter 06/07/2015 A 08/13/2015 A 249B1400 Change Order #2 - Additional Wet Well Repairs, Tropical Stor W 08/14/2015 A 10/14/2015 A 249B1402 Substantial Completion 10/14/2015 A 0
DesignerDesigner Construction Support Services 12/08/2014 A 11/30/2015 A 140B1410 Designer Construction Support Services 12/08/2014 A 11/30/2015 A 140
ConstrucConstruction Close Out 10/15/2015 A 11/30/2015 A 15B1420 Commissioning 10/15/2015 A 11/30/2015 A 15B1430 Punch List 10/15/2015 A 11/30/2015 A 10
Project CProject Closeout 10/15/2015 A 05/31/2017 A 853B1445 Closeout Phase 10/15/2015 A 05/31/2017 A 853B1450 Issue SAC Letter 11/30/2015 A 0B1470 Final Release of Retainage - Construction Contract 10/31/2016 A 0B1480 Administrative Closeout 10/15/2015 A 05/31/2017 A 120B1490 Project Closed 05/31/2017 A 0
100108-2 B100108-2 Basin 0607 Infiltration/Inflow Study and Repairs 09/25/2014 A 03/10/2016 A 609InfiltratioInfiltration/Inflow 09/25/2014 A 03/09/2016 A 431
B1000 Infiltration/Inflow Phase 09/25/2014 A 03/09/2016 A 431Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 12/31/2014 A 267
B1005 SSES Phase 09/25/2014 A 12/31/2014 A 267B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 10/15/2014 A 12/18/2014 A 30B1031 Smoke Testing 11/06/2014 A 11/12/2014 A 10B1040 Video Review 11/03/2014 A 12/31/2014 A 30
CIPP RepCIPP Repairs 04/17/2015 A 03/09/2016 A 34B1065 CIPP Phase 04/17/2015 A 03/09/2016 A 34B1080 Issue NTP for CIPP Repairs 04/17/2015 A 0B1090 Conduct CIPP Repairs 05/27/2015 A 03/09/2016 A 20
ManholeManhole Repairs 07/15/2015 A 11/09/2015 A 111B1115 Manhole Phase 07/15/2015 A 11/09/2015 A 111B1130 Issue NTP for Manhole Repairs 07/15/2015 A 0B1140 Conduct Manhole Repairs 08/26/2015 A 11/09/2015 A 20
Dig & ReDig & Replace Repairs 05/18/2015 A 06/19/2015 A 30B1165 Dig & Replace Phase 05/18/2015 A 06/19/2015 A 30B1180 Issue NTP for Dig & Replace Repairs 05/18/2015 A 0B1190 Conduct Dig & Replace Repairs 06/11/2015 A 06/19/2015 A 30
Project CProject Closeout 03/10/2016 A 03/10/2016 A 0B1235 Closeout Phase 03/10/2016 A 03/10/2016 A 0B1260 Project Closed 03/10/2016 A 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Contract Award (Purchase Order Approval)11/30/2015 A, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
WASD Issues NTP (PO to NTP)
Construction NTPMobilization
Permit ApprovalsConstruction Operations
Original Construction DurationChange Order #1 - Re-Design of Pipe Diameter
Change Order #2 - Additional Wet Well Repairs, Tropical Stor Weather Preparation
Substantial Completion11/30/2015 A, Designer Construction Support Services
Designer Construction Support Services11/30/2015 A, Construction Close Out
CommissioningPunch List
05/31/2017 A, Project Closeout
Closeout PhaseIssue SAC Letter
Final Release of Retainage - Construction ContractAdministrative Closeout
Project Closed03/10/2016 A, 100108-2 Basin 0607 Infiltration/Inflow Study and Repairs03/09/2016 A, Infiltration/Inflow
Infiltration/Inflow Phase12/31/2014 A, Sanitary Sewer Evaluation Survey
SSES PhaseIssue NTP to SSES Contractor
Conduct SSESSmoke Testing
Video Review03/09/2016 A, CIPP Repairs
CIPP PhaseIssue NTP for CIPP Repairs
Conduct CIPP Repairs11/09/2015 A, Manhole Repairs
Manhole PhaseIssue NTP for Manhole Repairs
Conduct Manhole Repairs06/19/2015 A, Dig & Replace Repairs
Dig & Replace PhaseIssue NTP for Dig & Replace Repairs
Conduct Dig & Replace Repairs03/10/2016 A, Project Closeout
Closeout PhaseProject Closed
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 103 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
Basin 0609Basin 0609 03/28/2014 A 08/01/2018 1759
100111 FM100111 FM for Pump Station 0609 03/28/2014 A 11/25/2014 A 24PlanningPlanning 03/28/2014 A 11/25/2014 A 24
B0900 Planning Phase 03/28/2014 A 11/25/2014 A 24B0940 Develop Remedial Action Plan (RAP) 03/28/2014 A 05/22/2014 A 10B0950 Develop Preliminary Engineering Report (PER) 05/23/2014 A 11/25/2014 A 10
100110-2 B100110-2 Basin 0609 Infiltration/Inflow Study and Repairs 04/17/2015 A 10/01/2015 A 372InfiltratioInfiltration/Inflow 04/17/2015 A 09/30/2015 A 209
B1000 Infiltration/Inflow Phase 04/17/2015 A 09/30/2015 A 209CIPP RepCIPP Repairs 04/17/2015 A 07/20/2015 A 40
B1005 CIPP Phase 04/17/2015 A 07/20/2015 A 40B1020 Issue NTP for CIPP Repairs 04/17/2015 A 0B1030 Conduct CIPP Repairs 06/19/2015 A 07/20/2015 A 20
ManholeManhole Repairs 07/15/2015 A 09/30/2015 A 140B1055 Manhole Phase 07/15/2015 A 09/30/2015 A 140B1070 Issue NTP for Manhole Repairs 07/15/2015 A 0B1080 Conduct Manhole Repairs 09/30/2015 A 09/30/2015 A 20
Dig & ReDig & Replace Repairs 05/18/2015 A 06/19/2015 A 30B1105 Dig & Replace Phase 05/18/2015 A 06/19/2015 A 30B1120 Issue NTP for Dig & Replace Repairs 05/18/2015 A 0B1130 Conduct Dig & Replace Repairs 06/03/2015 A 06/19/2015 A 30
Project CProject Closeout 10/01/2015 A 10/01/2015 A 0B1175 Closeout Phase 10/01/2015 A 10/01/2015 A 0B1200 Project Closed 10/01/2015 A 0
100228 Pu100228 Pump Station 0609 Upgrade 08/28/2014 A 08/01/2018 1606DesignDesign 08/28/2014 A 05/28/2015 A 307
B1000 Design Phase 08/28/2014 A 05/28/2015 A 307B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 08/28/2014 A 09/02/2014 A 5B1020 Engage Design Consultant 09/03/2014 A 11/05/2014 A 20B1030 Issue Design NTP 11/06/2014 A 0B1040 A/E Develops and Submits Final Engineering Report 11/06/2014 A 05/04/2015 A 20B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 02/26/2015 A 04/06/2015 A 10
30% Des30% Design 11/06/2014 A 01/23/2015 A 80B1060 A/E Prepares 30% Construction Documents 11/06/2014 A 01/08/2015 A 30B1070 Geotechnical Engineering Services 11/19/2014 A 01/08/2015 A 20B1080 Surveying Services 11/19/2014 A 12/08/2014 A 15B1100 30% CDs Submittal 01/08/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 01/09/2015 A 01/23/2015 A 10
90% Des90% Design 01/09/2015 A 05/22/2015 A 127B1170 A/E Prepares 90% Construction Documents 01/09/2015 A 02/25/2015 A 20B1180 90% CDs Submittal 02/25/2015 A 0B1190 90% Review (MDWASD/PSIP Team) 02/26/2015 A 03/05/2015 A 15B1200 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 03/06/2015 A 0B1210 90% RER(DERM)/FDEP Permit Review (Pump Station) 03/06/2015 A 04/06/2015 A 15B1220 90% Cutler Bay - BD Permit Submittal 04/10/2015 A 0B1230 90% Cutller Bay - BD Permit Review 04/10/2015 A 05/22/2015 A 15B1240 90% RER (Building Dept) Permit Submittal 04/21/2015 A 0B1250 90% RER (Building Dept) Permit Review 04/21/2015 A 05/04/2015 A 15B1260 90% CD PM Comments Evaluation Completed 05/04/2015 A 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
08/01/2018, Basin 0609
11/25/2014 A, 100111 FM for Pump Station 060911/25/2014 A, Planning
Planning PhaseDevelop Remedial Action Plan (RAP)
Develop Preliminary Engineering Report (PER)10/01/2015 A, 100110-2 Basin 0609 Infiltration/Inflow Study and Repairs09/30/2015 A, Infiltration/Inflow
Infiltration/Inflow Phase07/20/2015 A, CIPP RepairsCIPP Phase
Issue NTP for CIPP RepairsConduct CIPP Repairs
09/30/2015 A, Manhole RepairsManhole Phase
Issue NTP for Manhole RepairsConduct Manhole Repairs
06/19/2015 A, Dig & Replace RepairsDig & Replace Phase
Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs
10/01/2015 A, Project CloseoutCloseout Phase
Project Closed08/01/2018, 100228 Pump Station 0609 Upgrade
05/28/2015 A, Design
Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book
Engage Design ConsultantIssue Design NTP
A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
01/23/2015 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering Services
Surveying Services30% CDs Submittal
30% Review (MDWASD/PSIP Team)05/22/2015 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)90% RER(DERM)/FDEP Permit Submittal (Pump Station)
90% RER(DERM)/FDEP Permit Review (Pump Station)90% Cutler Bay - BD Permit Submittal
90% Cutller Bay - BD Permit Review90% RER (Building Dept) Permit Submittal
90% RER (Building Dept) Permit Review90% CD PM Comments Evaluation Completed
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 104 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
100% De100% Design 03/06/2015 A 05/28/2015 A 12B1270 A/E Prepares 100% Construction Documents 03/06/2015 A 05/22/2015 A 10B1280 100% CDs Submittal 05/22/2015 A 0B1290 100% Review (MDWASD/PSIP Team) 05/23/2015 A 05/28/2015 A 10B1300 Design Completed 05/28/2015 A 0
MDWASDMDWASD Procurement 04/28/2015 A 08/26/2015 A 117B1305 Procurement Phase 04/28/2015 A 08/26/2015 A 117B1310 Submit CDs to MDWASD Procurement Division 04/28/2015 A 0B1320 Pre-Bid Conference 05/06/2015 A 05/06/2015 A 1B1330 Bids Submittal 05/28/2015 A 0B1340 MDWASD/PSIP Team Bids Evaluation 05/29/2015 A 07/09/2015 A 15B1350 Recommendation for Award Letter 07/09/2015 A 0B1355 Contract Award (Purchase Order Approval) 07/10/2015 A 08/26/2015 A 10
ConstrucConstruction 05/06/2015 A 10/03/2016 A 1258B1360 Construction Phase 05/06/2015 A 10/03/2016 A 1258B1364 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 07/10/2015 A 07/27/2015 A 15B1366 Pre-Construction Meeting 07/28/2015 A 07/28/2015 A 1B1369 WASD Issues NTP (PO to NTP) 08/27/2015 A 09/01/2015 A 53B1370 Construction NTP 09/02/2015 A 0B1400 Construction Operations 09/02/2015 A 01/19/2016 A 71B1402 Substantial Completion 01/19/2016 A 0
DesignerDesigner Construction Support Services 05/06/2015 A 10/03/2016 A 127B1410 Designer Construction Support Services 05/06/2015 A 10/03/2016 A 127
ConstrucConstruction Close Out 01/19/2016 A 08/31/2016 A 15B1420 Commissioning 01/19/2016 A 01/28/2016 A 15B1430 Punch List 01/20/2016 A 08/31/2016 A 10
Project CProject Closeout 09/21/2015 A 08/01/2018 1045B1445 Closeout Phase 09/21/2015 A 08/01/2018 1045B1450 Issue SAC Letter 09/21/2015 A 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 01/20/2016 A 08/01/2018 30B1490 Project Closed 08/01/2018 0
Basin 0613Basin 0613 05/12/2014 A 08/01/2018 1901
100113 Pu100113 Pump Station 0613 Upgrade 05/12/2014 A 08/01/2018 1106DesignDesign 05/12/2014 A 12/04/2015 A 47
B1000 Design Phase 05/12/2014 A 12/04/2015 A 47B1002 RAP - Remedial Action Plan 05/12/2014 A 05/12/2014 A 1B1004 PER - Preliminary Engineer Report 10/19/2015 A 12/04/2015 A 47
Project CProject Closeout 12/05/2015 A 08/01/2018 1106B1445 Closeout Phase 12/05/2015 A 08/01/2018 1106B1447 SAC Letter Execution Period 12/05/2015 A 08/28/2017 A 616B1450 Issue SAC Letter 08/28/2017 A 0B1480 Administrative Closeout 08/29/2017 A 08/01/2018 120B1490 Project Closed 08/01/2018 0
100112 FM100112 FM for Pump Station 0613 05/12/2014 A 08/01/2018 911DesignDesign 05/12/2014 A 12/04/2015 A 47
B1000 Design Phase 05/12/2014 A 12/04/2015 A 47B1002 RAP - Remedial Action Plan 05/12/2014 A 05/12/2014 A 1B1004 PER - Preliminary Engineer Report 10/19/2015 A 12/04/2015 A 47
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
05/28/2015 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed
08/26/2015 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement DivisionPre-Bid Conference
Bids SubmittalMDWASD/PSIP Team Bids Evaluation
Recommendation for Award LetterContract Award (Purchase Order Approval)
10/03/2016 A, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
WASD Issues NTP (PO to NTP)
Construction NTPConstruction OperationsSubstantial Completion
10/03/2016 A, Designer Construction Support Services
Designer Construction Support Services08/31/2016 A, Construction Close Out
CommissioningPunch List
08/01/2018, Project Closeout
Closeout PhaseIssue SAC Letter
Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed08/01/2018, Basin 0613
08/01/2018, 100113 Pump Station 0613 Upgrade12/04/2015 A, Design
Design PhaseRAP - Remedial Action Plan
PER - Preliminary Engineer Report08/01/2018, Project CloseoutCloseout Phase
SAC Letter Execution Period
Issue SAC LetterAdministrative CloseoutProject Closed08/01/2018, 100112 FM for Pump Station 0613
12/04/2015 A, Design
Design PhaseRAP - Remedial Action Plan
PER - Preliminary Engineer Report
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 105 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
Project CProject Closeout 08/29/2017 A 08/01/2018 667B1475 Closeout Phase 08/29/2017 A 08/01/2018 667B1510 Administrative Closeout 08/29/2017 A 08/01/2018 120B1520 Project Closed 08/01/2018 0
100249-2 B100249-2 Basin 0613 Infiltration/Inflow Study and Repairs 06/26/2015 A 03/03/2016 A 43InfiltratioInfiltration/Inflow 06/26/2015 A 03/02/2016 A 30
B1000 Infiltration/Inflow Phase 06/26/2015 A 03/02/2016 A 30Dig & ReDig & Replace Repairs 06/26/2015 A 03/02/2016 A 30
B1160 Dig & Replace Phase 06/26/2015 A 03/02/2016 A 30B1180 Issue NTP for Dig & Replace Repairs 06/26/2015 A 0B1190 Conduct Dig & Replace Repairs 03/02/2016 A 03/02/2016 A 30
Project CProject Closeout 03/03/2016 A 03/03/2016 A 0B1250 Closeout Phase 03/03/2016 A 03/03/2016 A 0B1280 Project Closed 03/03/2016 A 0
Basin 0614Basin 0614 09/25/2014 A 08/01/2018 1455
100114 Pu100114 Pump Station 0614 Upgrade 10/07/2014 A 08/01/2018 1455DesignDesign 10/07/2014 A 06/08/2016 A 1028
B1000 Design Phase 10/07/2014 A 06/08/2016 A 1028B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 10/07/2014 A 10/08/2014 A 5B1020 Engage Design Consultant 10/09/2014 A 01/22/2015 A 20B1030 Issue Design NTP 01/23/2015 A 0B1040 A/E Develops and Submits Final Engineering Report 01/23/2015 A 05/10/2016 A 20B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 01/23/2015 A 06/05/2015 A 10
30% Des30% Design 01/23/2015 A 03/26/2015 A 58B1060 A/E Prepares 30% Construction Documents 01/23/2015 A 02/20/2015 A 30B1070 Geotechnical Engineering Services 01/23/2015 A 02/06/2015 A 20B1080 Surveying Services 01/23/2015 A 02/06/2015 A 15B1100 30% CDs Submittal 02/20/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 02/23/2015 A 03/26/2015 A 10
90% Des90% Design 02/23/2015 A 05/10/2016 A 418B1170 A/E Prepares 90% Construction Documents 02/23/2015 A 04/08/2015 A 20B1180 90% CDs Submittal 04/08/2015 A 0B1190 90% Review (MDWASD/PSIP Team) 04/09/2015 A 10/16/2015 A 15B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 10/19/2015 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 10/20/2015 A 03/18/2016 A 15B1220 90% RER (Building Department) Permit Submittal 01/07/2016 A 0B1230 90% RER (Building Department) Permit Review 01/08/2016 A 05/10/2016 A 15B1240 90% PWWMD Permit Submittal 11/02/2015 A 0B1250 90% PWWMD Permit Review 11/03/2015 A 11/04/2015 A 15B1260 90% CD PM Comments Evaluation Completed 05/10/2016 A 0
100% De100% Design 05/11/2016 A 06/08/2016 A 26B1270 A/E Prepares 100% Construction Documents 05/11/2016 A 06/08/2016 A 10B1280 100% CDs Submittal 06/08/2016 A 0B1290 100% Review (MDWASD/PSIP Team) 05/11/2016 A 06/08/2016 A 10B1300 Design Completed 06/08/2016 A 0
MDWASDMDWASD Procurement 01/08/2016 A 07/07/2016 A 180B1305 Procurement Phase 01/08/2016 A 07/07/2016 A 180B1310 Submit CDs to MDWASD Procurement Division 01/08/2016 A 0B1312 Bid Notice Preparation Period 01/08/2016 A 01/08/2016 A 23
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
08/01/2018, Project CloseoutCloseout Phase
Administrative CloseoutProject Closed
03/03/2016 A, 100249-2 Basin 0613 Infiltration/Inflow Study and Repairs03/02/2016 A, Infiltration/Inflow
Infiltration/Inflow Phase03/02/2016 A, Dig & Replace Repairs
Dig & Replace PhaseIssue NTP for Dig & Replace Repairs
Conduct Dig & Replace Repairs03/03/2016 A, Project Closeout
Closeout PhaseProject Closed
08/01/2018, Basin 0614
08/01/2018, 100114 Pump Station 0614 Upgrade06/08/2016 A, Design
Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book
Engage Design ConsultantIssue Design NTP
A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
03/26/2015 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal
30% Review (MDWASD/PSIP Team)05/10/2016 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)
90% RER(DERM)FDEP Permit Review (Pump Station)90% RER (Building Department) Permit Submittal
90% RER (Building Department) Permit Review90% PWWMD Permit Submittal
90% PWWMD Permit Review90% CD PM Comments Evaluation Completed06/08/2016 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal
100% Review (MDWASD/PSIP Team)Design Completed07/07/2016 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation Period
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 106 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1314 Bid Notice 01/08/2016 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 01/11/2016 A 02/10/2016 A 10B1320 Pre-Bid Conference 02/11/2016 A 02/11/2016 A 1B1322 Bidders Prepare Bids for Submittal 02/12/2016 A 03/09/2016 A 15B1330 Bids Submittal 03/10/2016 A 0B1340 MDWASD/PSIP Team Bids Evaluation 03/11/2016 A 05/23/2016 A 15B1350 Recommendation for Award Letter 05/23/2016 A 0B1355 Contract Award (Purchase Order Approval) 05/24/2016 A 07/07/2016 A 10
ConstrucConstruction 02/11/2016 A 09/21/2017 A 935B1360 Construction Phase 02/11/2016 A 09/21/2017 A 935B1364 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 05/24/2016 A 06/07/2016 A 15B1366 Pre-Construction Meeting 06/08/2016 A 06/08/2016 A 1B1369 WASD Issues NTP (PO to NTP) 07/08/2016 A 08/28/2016 A 53B1370 Construction NTP 08/29/2016 A 0B1400 Construction Operations 08/29/2016 A 05/20/2017 A 107B1400 Original Construction Duration 08/29/2016 A 01/26/2017 A 107B1400 Change Order #? - Unidentifiable Time Extension 01/27/2017 A 05/16/2017 A 107B1400 Change Order #1 - PW Permit & FPL 05/17/2017 A 09/21/2017 A 107B1402 Substantial Completion 05/20/2017 A 0
DesignerDesigner Construction Support Services 02/11/2016 A 06/30/2017 A 189B1410 Designer Construction Support Services 02/11/2016 A 06/30/2017 A 189
ConstrucConstruction Close Out 05/10/2017 A 06/30/2017 A 10B1420 Commissioning 05/10/2017 A 05/13/2017 A 5B1430 Punch List 05/22/2017 A 06/30/2017 A 10
Project CProject Closeout 05/22/2017 A 08/01/2018 395B1445 Closeout Phase 05/22/2017 A 08/01/2018 395B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 05/22/2017 A 08/01/2018 120B1490 Project Closed 08/01/2018 0
100205-2 B100205-2 Basin 0614 Infiltration/Inflow Study and Repairs 09/25/2014 A 07/15/2015 A 352InfiltratioInfiltration/Inflow 09/25/2014 A 07/14/2015 A 112
B1000 Infiltration/Inflow Phase 09/25/2014 A 07/14/2015 A 112Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 07/14/2015 A 112
B1005 SSES Phase 09/25/2014 A 07/14/2015 A 112B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 06/17/2015 A 06/19/2015 A 30B1040 Video Review 06/17/2015 A 07/14/2015 A 30
Project CProject Closeout 07/15/2015 A 07/15/2015 A 0B1235 Closeout Phase 07/15/2015 A 07/15/2015 A 0B1260 Project Closed 07/15/2015 A 0
Basin 0638Basin 0638 11/20/2015 A 12/20/2019 1390
100115 Pu100115 Pump Station 0638 Upgrade 07/17/2017 A 12/20/2019 810DesignDesign 07/17/2017 A 09/19/2018 353
B1000 Design Phase 07/17/2017 A 09/19/2018 353B1010 Prepare and Submit Design Package 07/17/2017 A 07/17/2017 A 7B1020 Engage Design Consultant 07/18/2017 A 10/09/2017 A 28B1022 TA Preparation 10/10/2017 A 10/10/2017 A 14B1024 TA Approval Process 10/11/2017 A 01/16/2018 A 40
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Bid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)
09/21/2017 A, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
WASD Issues NTP (PO to NTP)
Construction NTPConstruction Operations
Original Construction DurationChange Order #? - Unidentifiable Time Extension
Change Order #1 - PW Permit & FPL
Substantial Completion06/30/2017 A, Designer Construction Support Services
Designer Construction Support Services06/30/2017 A, Construction Close Out
CommissioningPunch List
08/01/2018, Project Closeout
Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction ContractAdministrative CloseoutProject Closed
07/15/2015 A, 100205-2 Basin 0614 Infiltration/Inflow Study and Repairs07/14/2015 A, Infiltration/Inflow
Infiltration/Inflow Phase07/14/2015 A, Sanitary Sewer Evaluation SurveySSES Phase
Issue NTP to SSES ContractorConduct SSESVideo Review
07/15/2015 A, Project CloseoutCloseout Phase
Project Closed12/20/2019, Basin 06
12/20/2019, 100115 09/19/2018, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval Process
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 107 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1030 Issue Design NTP 01/16/2018 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 01/16/2018 A 08/22/2018 186
30% Des30% Design 10/11/2017 A 02/16/2018 A 95B1060 A/E Prepares 30% Construction Documents 10/11/2017 A 01/05/2018 A 50B1100 30% CDs Submittal 01/05/2018 A 0B1120 30% Review (MDWASD/PSIP Team) 01/06/2018 A 02/16/2018 A 30
90% Des90% Design 02/17/2018 A 08/22/2018 168B1170 A/E Prepares 90% Construction Documents 02/17/2018 A 03/30/2018 A 40B1180 90% CDs Submittal 03/30/2018 A 0B1190 90% Review (MDWASD/PSIP Team) 03/31/2018 A 05/31/2018 A 30B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 06/04/2018 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 06/04/2018 A 08/01/2018 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 08/02/2018 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 08/02/2018 08/22/2018 21B1260 90% CD PM Comments Evaluation Completed 08/22/2018 0
100% De100% Design 08/23/2018 09/19/2018 28B1270 A/E Prepares 100% Construction Documents 08/23/2018 09/05/2018 14B1280 100% CDs Submittal 09/05/2018 0B1290 100% Review (MDWASD/PSIP Team) 09/06/2018 09/19/2018 14B1300 Design Completed 09/19/2018 0
MDWASDMDWASD Procurement 09/19/2018 01/01/2019 104B1305 Procurement Phase 09/19/2018 01/01/2019 104B1310 Submit CDs to MDWASD Procurement Division 09/19/2018 0B1312 Bid Notice Preparation Period 09/20/2018 10/22/2018 33B1314 Bid Notice 10/22/2018 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 10/23/2018 11/05/2018 14B1320 Pre-Bid Conference 11/06/2018 11/06/2018 1B1322 Bidders Prepare Bids for Submittal 11/07/2018 11/27/2018 21B1330 Bids Submittal 11/27/2018 0B1340 MDWASD/PSIP Team Bids Evaluation 11/28/2018 12/18/2018 21B1350 Recommendation for Award Letter 12/18/2018 0B1355 Contract Award (Purchase Order Approval) 12/19/2018 01/01/2019 14
ConstrucConstruction 11/06/2018 08/22/2019 290B1360 Construction Phase 11/06/2018 08/22/2019 290B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 12/19/2018 01/08/2019 21B1364 Pre-Construction Meeting 01/09/2019 01/09/2019 1B1366 WASD Issues NTP (Pre-Const to NTP) 01/10/2019 02/23/2019 45B1369 WASD Issues NTP (PO to NTP) 01/02/2019 02/23/2019 53B1370 Construction NTP 02/24/2019 0B1400 Construction Operations 02/24/2019 08/22/2019 180B1402 Substantial Completion 08/22/2019 0
DesignerDesigner Construction Support Services 11/06/2018 08/22/2019 290B1410 Designer Construction Support Services 11/06/2018 08/22/2019 290
Project CProject Closeout 08/01/2018 12/20/2019 507B1445 Closeout Phase 08/01/2018 12/20/2019 507B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 08/22/2019 0B1480 Administrative Closeout 08/23/2019 12/20/2019 120B1490 Project Closed 12/20/2019 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Issue Design NTPFinal Engineering Report Review & Approval (MDWASD/PSIP
02/16/2018 A, 30% Design
A/E Prepares 30% Construction Documents30% CDs Submittal
30% Review (MDWASD/PSIP Team)08/22/2018, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)
90% RER(DERM)FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)
90% RER(Building Dept) Permit Review (Pump Station)90% CD PM Comments Evaluation Completed
09/19/2018, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed
01/01/2019, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)
08/22/2019, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-ConstructioPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Construction NTPConstruction OperationsSubstantial Completion08/22/2019, Designer Construc
Designer Construction Support 12/20/2019, Project C
Closeout PhaseIssue SAC Letter
Final Release of Retainage - CAdministrative CloseoProject Closed
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 108 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
100206-2 B100206-2 Basin 0638 Infiltration/Inflow Study and Repairs 11/20/2015 A 03/08/2016 A 92InfiltratioInfiltration/Inflow 11/20/2015 A 03/07/2016 A 43
B1000 Infiltration/Inflow Phase 11/20/2015 A 03/07/2016 A 43Dig & ReDig & Replace Repairs 11/20/2015 A 03/07/2016 A 43
B1165 Dig & Replace Phase 11/20/2015 A 03/07/2016 A 43B1180 Issue NTP for Dig & Replace Repairs 11/20/2015 A 0B1190 Conduct Dig & Replace Repairs 03/04/2016 A 03/07/2016 A 30
Project CProject Closeout 03/08/2016 A 03/08/2016 A 0B1235 Closeout Phase 03/08/2016 A 03/08/2016 A 0B1260 Project Closed 03/08/2016 A 0
Basin 0645Basin 0645 09/18/2012 A 08/01/2018 1987
100117 Pu100117 Pump Station 0645 Upgrade 09/18/2012 A 08/01/2018 1987DesignDesign 09/18/2012 A 02/25/2018 A 1987
B1000 Design Phase 09/18/2012 A 02/25/2018 A 1987B1005 Remedial Action Plan to SAC Letter Issuance 09/18/2012 A 02/25/2018 A 1987
Project CProject Closeout 02/26/2018 A 08/01/2018 667B1445 Closeout Phase 02/26/2018 A 08/01/2018 667B1450 Issue SAC Letter 02/26/2018 A 0B1480 Administrative Closeout 02/26/2018 A 08/01/2018 120B1490 Project Closed 08/01/2018 0
Basin 0648Basin 0648 09/25/2014 A 08/01/2018 1836
100118 Ba100118 Basin 0648 Infiltration/Inflow Study and Repairs 09/25/2014 A 06/18/2015 A 563InfiltratioInfiltration/Inflow 09/25/2014 A 06/17/2015 A 241
B1000 Infiltration/Inflow Phase 09/25/2014 A 06/17/2015 A 241Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 06/17/2015 A 241
B1005 SSES Phase 09/25/2014 A 06/17/2015 A 241B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 05/26/2015 A 06/03/2015 A 30B1040 Video Review 06/04/2015 A 06/17/2015 A 30
Project CProject Closeout 06/18/2015 A 06/18/2015 A 0B1235 Closeout Phase 06/18/2015 A 06/18/2015 A 0B1260 Project Closed 06/18/2015 A 0
100119 Pu100119 Pump Station 0648 Upgrade 06/27/2016 A 08/01/2018 1196DesignDesign 06/27/2016 A 11/17/2017 A 240
B1000 Design Phase 06/27/2016 A 11/17/2017 A 240B1010 Prepare and Submit Design Package 06/27/2016 A 08/17/2016 A 5B1020 Engage Design Consultant 08/18/2016 A 11/10/2016 A 20B1021 SAC Determination Period 11/11/2016 A 11/17/2017 A 166
Project CProject Closeout 11/17/2017 A 08/01/2018 739B1445 Closeout Phase 11/17/2017 A 08/01/2018 739B1450 Issue SAC Letter 11/17/2017 A 0B1480 Administrative Closeout 11/18/2017 A 08/01/2018 120B1490 Project Closed 08/01/2018 0
Basin 0669Basin 0669 11/20/2015 A 09/27/2020 1694
100120 Ba100120 Basin 0669 Infiltration/Inflow Study and Repairs 11/20/2015 A 06/14/2016 A 144InfiltratioInfiltration/Inflow 11/20/2015 A 06/13/2016 A 144
B1000 Infiltration/Inflow Phase 11/20/2015 A 06/13/2016 A 144CIPP RepCIPP Repairs 01/15/2016 A 05/04/2016 A 113
B1065 CIPP Phase 01/15/2016 A 05/04/2016 A 113
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
03/08/2016 A, 100206-2 Basin 0638 Infiltration/Inflow Study and Repairs03/07/2016 A, Infiltration/Inflow
Infiltration/Inflow Phase03/07/2016 A, Dig & Replace RepairsDig & Replace Phase
Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs03/08/2016 A, Project CloseoutCloseout Phase
Project Closed08/01/2018, Basin 0645
08/01/2018, 100117 Pump Station 0645 Upgrade02/25/2018 A, Design
Design PhaseRemedial Action Plan to SAC Letter Issuance
08/01/2018, Project CloseoutCloseout Phase
Issue SAC LetterAdministrative CloseoutProject Closed08/01/2018, Basin 0648
06/18/2015 A, 100118 Basin 0648 Infiltration/Inflow Study and Repairs06/17/2015 A, Infiltration/Inflow
Infiltration/Inflow Phase06/17/2015 A, Sanitary Sewer Evaluation SurveySSES Phase
Issue NTP to SSES ContractorConduct SSESVideo Review06/18/2015 A, Project CloseoutCloseout Phase
Project Closed08/01/2018, 100119 Pump Station 0648 Upgrade
11/17/2017 A, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantSAC Determination Period
08/01/2018, Project Closeout
Closeout PhaseIssue SAC Letter
Administrative CloseoutProject Closed
06/14/2016 A, 100120 Basin 0669 Infiltration/Inflow Study and Repairs06/13/2016 A, Infiltration/Inflow
Infiltration/Inflow Phase05/04/2016 A, CIPP RepairsCIPP Phase
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 109 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1080 Issue NTP for CIPP Repairs 01/15/2016 A 0B1090 Conduct CIPP Repairs 05/04/2016 A 05/04/2016 A 28
ManholeManhole Repairs 03/25/2016 A 06/13/2016 A 105B1115 Manhole Phase 03/25/2016 A 06/13/2016 A 105B1130 Issue NTP for Manhole Repairs 03/25/2016 A 0B1140 Conduct Manhole Repairs 04/18/2016 A 06/13/2016 A 20
Dig & ReDig & Replace Repairs 11/20/2015 A 04/07/2016 A 144B1165 Dig & Replace Phase 11/20/2015 A 04/07/2016 A 144B1180 Issue NTP for Dig & Replace Repairs 11/20/2015 A 0B1190 Conduct Dig & Replace Repairs 03/16/2016 A 04/07/2016 A 30
Project CProject Closeout 06/14/2016 A 06/14/2016 A 0B1235 Closeout Phase 06/14/2016 A 06/14/2016 A 0B1260 Project Closed 06/14/2016 A 0
100121 Pu100121 Pump Station 0669 Upgrade * 08/01/2018 09/27/2020 789DesignDesign 08/01/2018 06/29/2019 333
B1000 Design Phase 08/01/2018 06/29/2019 333B1010 Prepare and Submit Design Package 08/01/2018 08/07/2018 7B1020 Engage Design Consultant 08/08/2018 09/04/2018 28B1022 TA Preparation 09/05/2018 09/18/2018 14B1024 TA Approval Process 09/19/2018 10/28/2018 40B1030 Issue Design NTP 10/29/2018 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/29/2018 06/01/2019 216
30% Des30% Design 10/29/2018 01/16/2019 80B1060 A/E Prepares 30% Construction Documents 10/29/2018 12/17/2018 50B1100 30% CDs Submittal 12/17/2018 0B1120 30% Review (MDWASD/PSIP Team) 12/18/2018 01/16/2019 30
60% Des60% Design 12/18/2018 01/30/2019 44B1130 A/E Prepares 60% Construction Documents 12/18/2018 01/16/2019 30B1140 60% CDs Submittal 01/16/2019 0B1160 60% Review (MDWASD/PSIP Team) 01/17/2019 01/30/2019 14
90% Des90% Design 01/17/2019 06/01/2019 136B1170 A/E Prepares 90% Construction Documents 01/17/2019 02/25/2019 40B1180 90% CDs Submittal 02/25/2019 0B1190 90% Review (MDWASD/PSIP Team) 02/26/2019 03/27/2019 30B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 03/28/2019 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 03/28/2019 05/11/2019 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 05/12/2019 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 05/12/2019 06/01/2019 21B1240 90% Municipality Permit Submittal (Pump Station) 05/12/2019 0B1250 90% Municipality Permit Review (Pump Station) 05/12/2019 06/01/2019 21B1260 90% CD PM Comments Evaluation Completed 06/01/2019 0
100% De100% Design 06/02/2019 06/29/2019 28B1270 A/E Prepares 100% Construction Documents 06/02/2019 06/15/2019 14B1280 100% CDs Submittal 06/15/2019 0B1290 100% Review (MDWASD/PSIP Team) 06/16/2019 06/29/2019 14B1300 Design Completed 06/29/2019 0
MDWASDMDWASD Procurement 06/29/2019 10/10/2019 104B1305 Procurement Phase 06/29/2019 10/10/2019 104B1310 Submit CDs to MDWASD Procurement Division 06/29/2019 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Issue NTP for CIPP RepairsConduct CIPP Repairs
06/13/2016 A, Manhole RepairsManhole Phase
Issue NTP for Manhole RepairsConduct Manhole Repairs
04/07/2016 A, Dig & Replace RepairsDig & Replace Phase
Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs
06/14/2016 A, Project CloseoutCloseout Phase
Project Closed
06/29/2019, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval Process
Issue Design NTPFinal Engineering Report Review & Ap
01/16/2019, 30% Design
A/E Prepares 30% Construction Documents30% CDs Submittal
30% Review (MDWASD/PSIP Team)01/30/2019, 60% Design
A/E Prepares 60% Construction Documents60% CDs Submittal60% Review (MDWASD/PSIP Team)
06/01/2019, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (P
90% RER(DERM)FDEP Permit Review (90% RER(Building Dept) Permit Submit
90% RER(Building Dept) Permit Revie90% Municipality Permit Submittal (Pum
90% Municipality Permit Review (Pum90% CD PM Comments Evaluation C
06/29/2019, 100% Design
A/E Prepares 100% Construction Do100% CDs Submittal100% Review (MDWASD/PSIP TeamDesign Completed
10/10/2019, MDWASD ProProcurement Phase
Submit CDs to MDWASD Procurem
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 110 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1312 Bid Notice Preparation period 06/29/2019 07/31/2019 33B1314 Bid Notice 07/31/2019 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 08/01/2019 08/14/2019 14B1320 Pre-Bid Conference 08/15/2019 08/15/2019 1B1322 Bidders Prepare Bids for Submittal 08/16/2019 09/05/2019 21B1330 Bids Submittal 09/05/2019 0B1340 MDWASD/PSIP Team Bids Evaluation 09/06/2019 09/26/2019 21B1350 Recommendation for Award Letter 09/26/2019 0B1355 Contract Award (Purchase Order Approval) 09/27/2019 10/10/2019 14
ConstrucConstruction 08/15/2019 05/30/2020 290B1360 Construction Phase 08/15/2019 05/30/2020 290B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 09/27/2019 10/17/2019 21B1364 Pre-Construction Meeting 10/18/2019 10/18/2019 1B1366 WASD Issues NTP (Pre-Const to NTP) 10/19/2019 12/02/2019 45B1369 WASD Issues NTP (PO to NTP) 10/11/2019 12/02/2019 53B1370 Construction NTP 12/03/2019 0B1400 Construction Operations 12/03/2019 05/30/2020 180B1402 Substantial Completion 05/30/2020 0
DesignerDesigner Construction Support Services 08/15/2019 05/30/2020 290B1410 Designer Construction Support Services 08/15/2019 05/30/2020 290
Project CProject Closeout 08/01/2018 09/27/2020 789B1445 Closeout Phase 08/01/2018 09/27/2020 789B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 05/30/2020 0B1480 Administrative Closeout 05/31/2020 09/27/2020 120B1490 Project Closed 09/27/2020 0
Basin 0672Basin 0672 12/07/2015 A 02/22/2019 1177
100122 Pu100122 Pump Station 0672 Upgrade 12/07/2015 A 02/22/2019 1177DesignDesign 12/07/2015 A 07/14/2017 A 620
B1000 Design Phase 12/07/2015 A 07/14/2017 A 620B1010 Prepare and Submit Design Package 12/07/2015 A 12/07/2015 A 5B1020 Engage Design Consultant 12/07/2015 A 01/12/2016 A 20B1022 TA Preparation 01/13/2016 A 01/13/2016 A 1B1024 TA Approval Process 01/14/2016 A 04/04/2016 A 20B1030 Issue Design NTP 04/14/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 04/14/2016 A 09/29/2016 A 85
30% Des30% Design 04/14/2016 A 05/18/2016 A 52B1060 A/E Prepares 30% Construction Documents 04/14/2016 A 04/27/2016 A 30B1070 Geotechnical Engineering Services 04/14/2016 A 04/27/2016 A 20B1080 Surveying Services 04/14/2016 A 04/27/2016 A 15B1100 30% CDs Submittal 04/27/2016 A 0B1120 30% Review (MDWASD/PSIP Team) 04/28/2016 A 05/18/2016 A 10
90% Des90% Design 04/28/2016 A 05/30/2017 A 417B1170 A/E Prepares 90% Construction Documents 04/28/2016 A 08/17/2016 A 20B1180 90% CDs Submittal 08/17/2016 A 0B1190 90% Review (MDWASD/PSIP Team) 08/18/2016 A 09/29/2016 A 15B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 12/06/2016 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 12/06/2016 A 04/04/2017 A 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 04/18/2017 A 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Bid Notice Preparation period
Bid NoticeMDWASD/PSIP Team Prepare
Pre-Bid ConferenceBidders Prepare Bids for Subm
Bids SubmittalMDWASD/PSIP Team Bids ERecommendation for Award Contract Award (Purchase O
05/30/20
ConstrucMDWASD/PSIP Team PrePre-Construction Meeting
WASD Issues NTP (PreWASD Issues NTP (PO
Construction NTPConstrucSubstan05/30/20
Designe
Issue SAC LetterFinal Re
02/22/2019, Basin 0672
02/22/2019, 100122 Pump Station 0672 Upg07/14/2017 A, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval ProcessIssue Design NTP
Final Engineering Report Review & Approval (MDWASD/PSIP Team)05/18/2016 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services
30% CDs Submittal30% Review (MDWASD/PSIP Team)
05/30/2017 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)
90% RER(DERM)FDEP Permit Submittal (Pump Station)90% RER(DERM)FDEP Permit Review (Pump Station)
90% RER(Building Dept) Permit Submittal (Pump Station)
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 111 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1230 90% RER(Building Dept) Permit Review (Pump Station) 04/18/2017 A 05/12/2017 A 21B1240 90% PWWMD Permit Submittal (Pump Station) 05/22/2017 A 0B1250 90% PWWMD Permit Review (Pump Station) 05/22/2017 A 05/30/2017 A 21B1260 90% CD PM Comments Evaluation Completed 05/30/2017 A 0B1262 MDWASD Union Concurrence Process 02/27/2017 A 04/07/2017 A 30
100% De100% Design 05/31/2017 A 07/14/2017 A 75B1270 A/E Prepares 100% Construction Documents 05/31/2017 A 07/14/2017 A 10B1280 100% CDs Submittal 07/14/2017 A 0B1290 100% Review (MDWASD/PSIP Team) 07/14/2017 A 07/14/2017 A 10B1300 Design Completed 07/14/2017 A 0
MDWASDMDWASD Procurement 07/14/2017 A 01/02/2018 A 101B1305 Procurement Phase 07/14/2017 A 01/02/2018 A 101B1310 Submit CDs to MDWASD Procurement Division 07/14/2017 A 0B1312 Bid Notice Preparation Period 07/17/2017 A 08/10/2017 A 33B1314 Bid Notice 08/10/2017 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 08/11/2017 A 08/21/2017 A 14B1320 Pre-Bid Conference 08/22/2017 A 08/22/2017 A 1B1328 Bidders Prepare Bids for Submittal 09/25/2017 A 10/19/2017 A 21B1330 Bids Submittal 10/19/2017 A 0B1340 MDWASD/PSIP Team Bids Evaluation 10/20/2017 A 11/17/2017 A 21B1350 Recommendation for Award letter 11/17/2017 A 0B1355 Contract Award (Purchase Order Approval) 11/18/2017 A 01/02/2018 A 14
ConstrucConstruction 08/22/2017 A 10/25/2018 507B1360 Construction Phase 08/22/2017 A 10/25/2018 507B1364 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 11/18/2017 A 01/21/2018 A 21B1366 Pre-Construction Meeting 01/22/2018 A 01/22/2018 A 1B1368 WASD Issues NTP (Pre-Const to NTP) 01/23/2018 A 05/27/2018 A 45B1369 WASD Issues NTP (PO to NTP) 01/03/2018 A 05/27/2018 A 53B1370 Construction NTP 05/28/2018 A 0B1400 Construction Operations 05/28/2018 A 10/25/2018 151B1402 Substantial Completion 10/25/2018 0
DesignerDesigner Construction Support Services 08/22/2017 A 10/25/2018 246B1410 Designer Construction Support Services 08/22/2017 A 10/25/2018 246
Project CProject Closeout 08/01/2018 02/22/2019 206B1445 Closeout Phase 08/01/2018 02/22/2019 206B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 10/25/2018 0B1480 Administrative Closeout 10/26/2018 02/22/2019 120B1490 Project Closed 02/22/2019 0
Basin 0675Basin 0675 09/25/2014 A 11/01/2019 1646
100123 Pu100123 Pump Station 0675 Upgrade 01/14/2016 A 11/01/2019 1369DesignDesign 01/14/2016 A 08/01/2018 912
B1000 Design Phase 01/14/2016 A 08/01/2018 912B1010 Prepare and Submit Design Package 01/14/2016 A 01/14/2016 A 5B1020 Engage Design Consultant 01/14/2016 A 04/01/2016 A 20B1022 TA Preparation 04/04/2016 A 04/15/2016 A 1B1024 TA Approval Process 04/18/2016 A 01/10/2017 A 40B1030 Issue Design NTP 01/13/2017 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 01/13/2017 A 01/26/2018 A 65
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
90% RER(Building Dept) Permit Review (Pump Station)90% PWWMD Permit Submittal (Pump Station)
90% PWWMD Permit Review (Pump Station)90% CD PM Comments Evaluation Completed
MDWASD Union Concurrence Process07/14/2017 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal
100% Review (MDWASD/PSIP Team)Design Completed
01/02/2018 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award letter
Contract Award (Purchase Order Approval)10/25/2018, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Construction NTPConstruction OperationsSubstantial Completion10/25/2018, Designer Construction Support Services
Designer Construction Support Services02/22/2019, Project Closeout
Closeout PhaseIssue SAC Letter
Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed
11/01/2019, Basin 0675
11/01/2019, 100123 Pum08/01/2018, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval ProcessIssue Design NTP
Final Engineering Report Review & Approval (MDWASD/PSIP Team)
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 112 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
30% Des30% Design 01/13/2017 A 06/07/2017 A 151B1060 A/E Prepares 30% Construction Documents 01/13/2017 A 05/04/2017 A 50B1100 30% CDs Submittal 05/04/2017 A 0B1120 30% Review (MDWASD/PSIP Team) 05/05/2017 A 05/05/2017 A 30B1122 Project On-Hold Until Property Limits/Easments Have Been Esta 05/05/2017 A 06/07/2017 A 30
90% Des90% Design 06/08/2017 A 01/26/2018 A 200B1170 A/E Prepares 90% Construction Documents 06/08/2017 A 07/05/2017 A 40B1180 90% CDs Submittal 07/05/2017 A 0B1190 90% Review (MDWASD/PSIP Team) 07/06/2017 A 07/26/2017 A 30B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 08/29/2017 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 08/29/2017 A 11/29/2017 A 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 11/30/2017 A 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 11/30/2017 A 01/26/2018 A 21B1260 90% CD PM Comments Evaluation Completed 01/26/2018 A 0B1262 MDWASD Union Concurrence Process 07/06/2017 A 07/31/2017 A 30
100% De100% Design 01/29/2018 A 08/01/2018 212B1270 A/E Prepares 100% Construction Documents 01/29/2018 A 02/22/2018 A 14B1280 100% CDs Submittal 02/22/2018 A 0B1282 TA Rev 2 Preparation 02/23/2018 A 05/08/2018 A 14B1284 TA Rev 2 Approval Process 05/09/2018 A 06/20/2018 A 40B1290 100% Review (MDWASD/PSIP Team) 06/21/2018 A 08/01/2018 14B1300 Design Completed 08/01/2018 0
MDWASDMDWASD Procurement 08/01/2018 11/13/2018 104B1305 Procurement Phase 08/01/2018 11/13/2018 104B1310 Submit CDs to MDWASD Procurement Division 08/01/2018 0B1312 Bid Notice Preparation Period 08/02/2018 09/03/2018 33B1314 Bid Notice 09/03/2018 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 09/04/2018 09/17/2018 14B1320 Pre-Bid Conference 09/18/2018 09/18/2018 1B1322 Bidders Prepare Bids for Submittal 09/19/2018 10/09/2018 21B1330 Bids Submittal 10/09/2018 0B1340 MDWASD/PSIP Team Bids Evaluation 10/10/2018 10/30/2018 21B1350 Recommendation for Award Letter 10/30/2018 0B1355 Contract Award (Purchase Order Approval) 10/31/2018 11/13/2018 14
ConstrucConstruction 09/18/2018 07/05/2019 290B1360 Construction Phase 09/18/2018 07/05/2019 290B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 10/31/2018 11/20/2018 21B1364 Pre-Construction Meeting 11/21/2018 11/21/2018 1B1366 WASD Issues NTP (Pre-Const to NTP) 11/22/2018 01/05/2019 45B1369 WASD Issues NTP (PO to NTP) 11/14/2018 01/05/2019 53B1370 Construction NTP 01/06/2019 0B1400 Construction Operations 01/06/2019 07/04/2019 180B1402 Substantial Completion 07/04/2019 0
DesignerDesigner Construction Support Services 09/18/2018 07/04/2019 290B1410 Designer Construction Support Services 09/18/2018 07/04/2019 290
Project CProject Closeout 08/01/2018 11/01/2019 458B1445 Closeout Phase 08/01/2018 11/01/2019 458B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 07/04/2019 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
06/07/2017 A, 30% Design
A/E Prepares 30% Construction Documents30% CDs Submittal
30% Review (MDWASD/PSIP Team)Project On-Hold Until Property Limits/Easments Have Been Established
01/26/2018 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)
90% RER(DERM)FDEP Permit Submittal (Pump Station)90% RER(DERM)FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)
90% RER(Building Dept) Permit Review (Pump Station)90% CD PM Comments Evaluation Completed
MDWASD Union Concurrence Process08/01/2018, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal
TA Rev 2 PreparationTA Rev 2 Approval Process
100% Review (MDWASD/PSIP Team)Design Completed
11/13/2018, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)
07/05/2019, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Construction NTPConstruction OperationsSubstantial Completion07/04/2019, Designer Construction
Designer Construction Support Ser11/01/2019, Project Close
Closeout PhaseIssue SAC Letter
Final Release of Retainage - Const
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 113 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1480 Administrative Closeout 07/05/2019 11/01/2019 120B1490 Project Closed 11/01/2019 0
100193 Ba100193 Basin 0675 Infiltration/Inflow Study and Repairs 09/25/2014 A 05/27/2015 A 397InfiltratioInfiltration/Inflow 09/25/2014 A 05/26/2015 A 38
B1000 Infiltration/Inflow Phase 09/25/2014 A 05/26/2015 A 38Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 05/26/2015 A 38
B1005 SSES Phase 09/25/2014 A 05/26/2015 A 38B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 04/10/2015 A 04/30/2015 A 30B1040 Video Review 05/12/2015 A 05/26/2015 A 30
Project CProject Closeout 05/27/2015 A 05/27/2015 A 0B1235 Closeout Phase 05/27/2015 A 05/27/2015 A 0B1260 Project Closed 05/27/2015 A 0
Basin 0688Basin 0688 11/10/2014 A 08/01/2018 1444
100125 Pu100125 Pump Station 0688 Upgrade 11/10/2014 A 08/01/2018 1444DesignDesign 11/10/2014 A 04/25/2016 A 529
B1000 Design Phase 11/10/2014 A 04/25/2016 A 529B1010 Prepare and Submit Design Package 11/10/2014 A 11/24/2014 A 5B1020 Engage Design Consultant 11/25/2014 A 03/23/2015 A 20B1022 TA Approval Process 03/24/2015 A 04/30/2015 A 20B1030 Issue Design NTP 05/07/2015 A 0B1040 A/E Develops and Submits Final Engineering Report 05/07/2015 A 03/30/2016 A 125B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 05/07/2015 A 11/18/2015 A 10
30% Des30% Design 05/08/2015 A 07/28/2015 A 74B1060 A/E Prepares 30% Construction Documents 05/08/2015 A 07/13/2015 A 30B1070 Geotechnical Engineering Services 05/08/2015 A 07/13/2015 A 20B1080 Surveying Services 05/08/2015 A 07/13/2015 A 15B1100 30% CDs Submittal 07/13/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 07/14/2015 A 07/28/2015 A 10
60% Des60% Design 07/14/2015 A 09/08/2015 A 84B1130 A/E Prepares 60% Construction Documents 07/14/2015 A 08/07/2015 A 20B1140 60% CDs Submittal 08/07/2015 A 0B1160 60% Review (MDWASD/PSIP Team) 08/11/2015 A 09/08/2015 A 10
90% Des90% Design 08/11/2015 A 03/30/2016 A 218B1170 A/E Prepares 90% Construction Documents 08/11/2015 A 10/23/2015 A 20B1180 90% CDs Submittal 10/23/2015 A 0B1190 90% Review (MDWASD/PSIP Team) 10/26/2015 A 11/18/2015 A 15B1200 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 01/27/2016 A 0B1210 90% RER(DERM)/FDEP Permit Review (Pump Station) 01/27/2016 A 03/25/2016 A 15B1220 90% RER (Building Dept) Permit Submittal 03/15/2016 A 0B1230 90% RER (Building Dept) Permit Review 03/15/2016 A 03/30/2016 A 15B1260 90% CD PM Comments Evaluation Completed 03/30/2016 A 0
100% De100% Design 03/30/2016 A 04/25/2016 A 74B1270 A/E Prepares 100% Construction Documents 03/30/2016 A 04/25/2016 A 10B1280 100% CDs Submittal 04/25/2016 A 0B1290 100% Review (MDWASD/PSIP Team) 03/30/2016 A 04/25/2016 A 10B1300 Design Completed 04/25/2016 A 0
MDWASDMDWASD Procurement 03/02/2016 A 05/02/2016 A 55B1305 Procurement Phase 03/02/2016 A 05/02/2016 A 55
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Administrative CloseoutProject Closed
05/27/2015 A, 100193 Basin 0675 Infiltration/Inflow Study and Repairs05/26/2015 A, Infiltration/Inflow
Infiltration/Inflow Phase05/26/2015 A, Sanitary Sewer Evaluation SurveySSES Phase
Issue NTP to SSES ContractorConduct SSESVideo Review
05/27/2015 A, Project CloseoutCloseout Phase
Project Closed08/01/2018, Basin 0688
08/01/2018, 100125 Pump Station 0688 Upgrade04/25/2016 A, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Approval Process
Issue Design NTPA/E Develops and Submits Final Engineering Report
Final Engineering Report Review & Approval (MDWASD/PSIP Team)07/28/2015 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal30% Review (MDWASD/PSIP Team)
09/08/2015 A, 60% Design
A/E Prepares 60% Construction Documents60% CDs Submittal
60% Review (MDWASD/PSIP Team)03/30/2016 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)/FDEP Permit Submittal (Pump Station)90% RER(DERM)/FDEP Permit Review (Pump Station)
90% RER (Building Dept) Permit Submittal90% RER (Building Dept) Permit Review90% CD PM Comments Evaluation Completed
04/25/2016 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal
100% Review (MDWASD/PSIP Team)Design Completed
05/02/2016 A, MDWASD Procurement
Procurement Phase
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 114 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1310 Submit CDs to MDWASD Procurement Division 03/02/2016 A 0B1312 Bid Notice Preparation Period 03/03/2016 A 03/07/2016 A 23B1314 Bid Notice 03/07/2016 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 03/08/2016 A 03/16/2016 A 10B1320 Pre-Bid Conference 03/17/2016 A 03/17/2016 A 1B1328 Bidders Prepare Bids for Submittal 03/21/2016 A 04/05/2016 A 15B1330 Bids Submittal 04/06/2016 A 0B1340 MDWASD/PSIP Team Bids Evaluation 04/07/2016 A 04/12/2016 A 15B1350 Recommendation for Award Letter 04/12/2016 A 0B1355 Contract Award (Purchase Order Approval) 04/13/2016 A 05/02/2016 A 10
ConstrucConstruction 03/17/2016 A 02/28/2017 A 936B1360 Construction Phase 03/17/2016 A 02/28/2017 A 936B1364 MDWASD/PSIP Team Prepare for Pre-Construction meeting 04/13/2016 A 04/22/2016 A 15B1366 Pre-Construction Meeting 04/25/2016 A 04/25/2016 A 1B1369 WASD Issues NTP (PO to NTP) 05/03/2016 A 07/19/2016 A 53B1370 Construction NTP 07/20/2016 A 0B1400 Construction Operations 07/20/2016 A 12/28/2016 A 180B1402 Substantial Completion 12/28/2016 A 0
DesignerDesigner Construction Support Services 03/17/2016 A 02/28/2017 A 249B1410 Designer Construction Support Services 03/17/2016 A 02/28/2017 A 249
ConstrucConstruction Close Out 12/29/2016 A 02/28/2017 A 10B1420 Commissioning 12/29/2016 A 01/05/2017 A 5B1430 Punch List 12/29/2016 A 02/28/2017 A 10
Project CProject Closeout 12/29/2016 A 08/01/2018 562B1445 Closeout Phase 12/29/2016 A 08/01/2018 562B1448 SAC Letter Issuance Period 12/29/2016 A 06/14/2017 A 167B1450 Issue SAC Letter 06/22/2017 A 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 12/29/2016 A 08/01/2018 120B1490 Project Closed 08/01/2018 0
100246 Ba100246 Basin 0688 Infiltration/Inflow Study and Repairs 05/22/2015 A 10/23/2015 A 376InfiltratioInfiltration/Inflow 05/22/2015 A 10/22/2015 A 154
B1000 Infiltration/Inflow Phase 05/22/2015 A 10/22/2015 A 154CIPP RepCIPP Repairs 05/22/2015 A 10/22/2015 A 154
B1070 CIPP Phase 05/22/2015 A 10/22/2015 A 154B1090 Issue NTP for CIPP Repairs 05/22/2015 A 0B1100 Conduct CIPP Repairs 10/21/2015 A 10/22/2015 A 2
Project CProject Closeout 10/23/2015 A 10/23/2015 A 0B1250 Closeout Phase 10/23/2015 A 10/23/2015 A 0B1280 Project Closed 10/23/2015 A 0
Basin 0698Basin 0698 09/25/2014 A 05/19/2019 1620
100126 Ba100126 Basin 0698 Infiltration/Inflow Study and Repairs 09/25/2014 A 06/02/2016 A 567InfiltratioInfiltration/Inflow 09/25/2014 A 06/01/2016 A 439
B1000 Infiltration/Inflow Phase 09/25/2014 A 06/01/2016 A 439Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 10/23/2015 A 235
B1005 SSES Phase 09/25/2014 A 10/23/2015 A 235B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 12/15/2014 A 10/23/2015 A 30
CIPP RepCIPP Repairs 01/15/2016 A 06/01/2016 A 20
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Submit CDs to MDWASD Procurement DivisionBid Notice Preparation Period
Bid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter
Contract Award (Purchase Order Approval)02/28/2017 A, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction meetingPre-Construction Meeting
WASD Issues NTP (PO to NTP)
Construction NTPConstruction Operations
Substantial Completion02/28/2017 A, Designer Construction Support Services
Designer Construction Support Services02/28/2017 A, Construction Close Out
CommissioningPunch List
08/01/2018, Project Closeout
Closeout PhaseSAC Letter Issuance Period
Issue SAC LetterFinal Release of Retainage - Construction ContractAdministrative CloseoutProject Closed
10/23/2015 A, 100246 Basin 0688 Infiltration/Inflow Study and Repairs10/22/2015 A, Infiltration/Inflow
Infiltration/Inflow Phase10/22/2015 A, CIPP Repairs
CIPP PhaseIssue NTP for CIPP Repairs
Conduct CIPP Repairs10/23/2015 A, Project Closeout
Closeout PhaseProject Closed
05/19/2019, Basin 0698
06/02/2016 A, 100126 Basin 0698 Infiltration/Inflow Study and Repairs06/01/2016 A, Infiltration/Inflow
Infiltration/Inflow Phase10/23/2015 A, Sanitary Sewer Evaluation SurveySSES Phase
Issue NTP to SSES ContractorConduct SSES
06/01/2016 A, CIPP Repairs
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 115 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1065 CIPP Phase 01/15/2016 A 06/01/2016 A 20B1080 Issue NTP for CIPP Repairs 01/15/2016 A 0B1090 Conduct CIPP Repairs 02/19/2016 A 06/01/2016 A 20
ManholeManhole Repairs 10/30/2015 A 03/24/2016 A 20B1115 Manhole Phase 10/30/2015 A 03/24/2016 A 20B1130 Issue NTP for Manhole Repairs 10/30/2015 A 0B1140 Conduct Manhole Repairs 11/16/2015 A 03/24/2016 A 20
Dig & ReDig & Replace Repairs 09/25/2015 A 02/26/2016 A 30B1165 Dig & Replace Phase 09/25/2015 A 02/26/2016 A 30B1180 Issue NTP for Dig & Replace Repairs 09/25/2015 A 0B1190 Conduct Dig & Replace Repairs 10/05/2015 A 02/26/2016 A 30
Project CProject Closeout 06/02/2016 A 06/02/2016 A 0B1235 Closeout Phase 06/02/2016 A 06/02/2016 A 0B1260 Project Closed 06/02/2016 A 0
100128 Pu100128 Pump Station 0698(AM) Upgrade 10/10/2014 A 05/19/2019 1519DesignDesign 10/10/2014 A 12/13/2017 A 1013
B1000 Design Phase 10/10/2014 A 12/13/2017 A 1013B1010 Prepare and Submit Design Package 10/10/2014 A 10/13/2014 A 5B1020 Engage Design Consultant 10/14/2014 A 03/24/2015 A 20B1030 Issue Design NTP 03/24/2015 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 03/24/2015 A 11/30/2017 A 209
30% Des30% Design 03/25/2015 A 07/13/2016 A 441B1060 A/E Prepares 30% Construction Documents 03/25/2015 A 06/08/2015 A 30B1070 Geotechnical Engineering Services 03/25/2015 A 06/08/2015 A 20B1080 Surveying Services 03/25/2015 A 06/08/2015 A 15B1100 30% CDs Submittal 06/08/2015 A 0B1102 PSIP Prepare PER to Re-Design 30% CDs 06/09/2015 A 10/14/2015 A 10B1104 Prepare Request for SOW, Fee to Re-Design 30% CDs 10/15/2015 A 12/15/2015 A 10B1106 TA Rev 1 Approval Process to Re-Design 30% CDs 12/16/2015 A 01/20/2016 A 10B1108 A/E Re-Design 30% Contract Documents 01/28/2016 A 04/28/2016 A 30B1120 30% Re-Design Review (MDWASD/PSIP Team) 04/29/2016 A 07/13/2016 A 10
60% Des60% Design 04/29/2016 A 03/23/2017 A 72B1128 TA Rev 2 Approval Process 12/19/2016 A 02/01/2017 A 40B1130 A/E Prepares 60% Construction Documents 04/29/2016 A 02/01/2017 A 30B1140 60% CDs Submittal 02/01/2017 A 0B1160 60% Review (MDWASD/PSIP Team) 02/02/2017 A 03/23/2017 A 10
90% Des90% Design 03/24/2017 A 11/30/2017 A 208B1170 A/E Prepares 90% Construction Documents 03/24/2017 A 06/27/2017 A 40B1180 90% CDs Submittal 06/27/2017 A 0B1190 90% Review (MDWASD/PSIP Team) 06/28/2017 A 08/11/2017 A 30B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 08/14/2017 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 08/14/2017 A 09/28/2017 A 45B1220 90% RER (Building Dept) Permit Submittal 10/20/2017 A 0B1230 90% RER (Building Dept) Permit Review 10/20/2017 A 11/30/2017 A 21B1260 90% CD PM Comments Evaluation Completed 11/30/2017 A 0B1262 MDWASD Union Concurrence Process 06/28/2017 A 07/17/2017 A 30
100% De100% Design 12/01/2017 A 12/13/2017 A 28B1270 A/E Prepares 100% Construction Documents 12/01/2017 A 12/13/2017 A 14B1280 100% CDs Submittal 12/13/2017 A 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
CIPP Phase
Issue NTP for CIPP RepairsConduct CIPP Repairs
03/24/2016 A, Manhole RepairsManhole Phase
Issue NTP for Manhole RepairsConduct Manhole Repairs
02/26/2016 A, Dig & Replace RepairsDig & Replace Phase
Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs
06/02/2016 A, Project CloseoutCloseout Phase
Project Closed05/19/2019, 100128 Pump Station 06
12/13/2017 A, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantIssue Design NTP
Final Engineering Report Review & Approval (MDWASD/PSIP Team)07/13/2016 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services
30% CDs SubmittalPSIP Prepare PER to Re-Design 30% CDs
Prepare Request for SOW, Fee to Re-Design 30% CDsTA Rev 1 Approval Process to Re-Design 30% CDs
A/E Re-Design 30% Contract Documents30% Re-Design Review (MDWASD/PSIP Team)
03/23/2017 A, 60% DesignTA Rev 2 Approval Process
A/E Prepares 60% Construction Documents60% CDs Submittal
60% Review (MDWASD/PSIP Team)11/30/2017 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)
90% RER(DERM)FDEP Permit Review (Pump Station)90% RER (Building Dept) Permit Submittal
90% RER (Building Dept) Permit Review90% CD PM Comments Evaluation Completed
MDWASD Union Concurrence Process12/13/2017 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 116 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1290 100% Review (MDWASD/PSIP Team) 12/13/2017 A 12/13/2017 A 14B1300 Design Completed 12/13/2017 A 0
MDWASDMDWASD Procurement 12/13/2017 A 04/13/2018 A 88B1305 Procurement Phase 12/13/2017 A 04/13/2018 A 88B1310 Submit CDs to MDWASD Procurement Division 12/13/2017 A 0B1312 Bid Notice Preparation Period 12/14/2017 A 12/18/2017 A 33B1314 Bid Notice 12/18/2017 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 12/19/2017 A 01/11/2018 A 14B1320 Pre-Bid Conference 01/12/2018 A 01/12/2018 A 1B1328 Bidders Prepare Bids for Submittal 01/13/2018 A 02/20/2018 A 21B1330 Bids Submittal 02/20/2018 A 0B1340 MDWASD/PSIP Team Bids Evaluation 02/21/2018 A 03/12/2018 A 21B1350 Recommendation for Award Letter 03/12/2018 A 0B1355 Contract Award (Purchase Order Approval) 03/13/2018 A 04/13/2018 A 14
ConstrucConstruction 01/12/2018 A 01/19/2019 382B1360 Construction Phase 01/12/2018 A 01/19/2019 382B1364 MDWASD/PSIP Team Prepare for Pre-Construction meeting 03/13/2018 A 05/09/2018 A 21B1365 Pre-Construction Meeting 05/10/2018 A 05/10/2018 A 1B1366 WASD Issues NTP (Pre-Const to NTP) 05/11/2018 A 07/22/2018 A 45B1369 WASD Issues NTP (PO to NTP) 04/13/2018 A 07/22/2018 A 53B1370 Construction NTP 07/23/2018 A 0B1400 Construction Operations 07/23/2018 A 01/19/2019 181B1402 Substantial Completion 01/19/2019 0
DesignerDesigner Construction Support Services 01/12/2018 A 01/19/2019 290B1410 Designer Construction Support Services 01/12/2018 A 01/19/2019 290
Project CProject Closeout 07/05/2018 A 05/19/2019 323B1445 Closeout Phase 07/05/2018 A 05/19/2019 323B1450 Issue SAC Letter 07/05/2018 A 0B1470 Final Release of Retainage - Construction Contract 01/19/2019 0B1480 Administrative Closeout 01/20/2019 05/19/2019 120B1490 Project Closed 05/19/2019 0
Basin 0700Basin 0700 02/12/2013 A 08/01/2018 1808
100129 Pu100129 Pump Station 0700 Upgrade 02/12/2013 A 08/01/2018 1808DesignDesign 02/12/2013 A 01/24/2018 A 1808
B1000 Design Phase 02/12/2013 A 01/24/2018 A 1808B1005 Remedial Action Plan Submittal to SAC Letter Issuance 02/12/2013 A 01/24/2018 A 1808
Project CProject Closeout 01/24/2018 A 08/01/2018 642B1445 Closeout Phase 01/24/2018 A 08/01/2018 642B1450 Issue SAC Letter 01/24/2018 A 0B1480 Administrative Closeout 01/25/2018 A 08/01/2018 120B1490 Project Closed 08/01/2018 0
Basin 0723Basin 0723 01/14/2016 A 08/17/2018 1083
100130 Pu100130 Pump Station 0723 Upgrade 01/14/2016 A 08/17/2018 1083DesignDesign 01/14/2016 A 03/27/2017 A 452
B1000 Design Phase 01/14/2016 A 03/27/2017 A 452B1010 Prepare and Submit Design Package 01/14/2016 A 01/15/2016 A 5B1020 Engage Design Consultant 01/15/2016 A 02/17/2016 A 20B1022 TA Preparation 02/22/2016 A 02/22/2016 A 1B1024 TA Approval Process 03/08/2016 A 04/21/2016 A 20
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
100% Review (MDWASD/PSIP Team)Design Completed
04/13/2018 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter
Contract Award (Purchase Order Approval)01/19/2019, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction meetingPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Construction NTPConstruction OperationsSubstantial Completion01/19/2019, Designer Construction Support Serv
Designer Construction Support Services05/19/2019, Project Closeout
Closeout PhaseIssue SAC Letter
Final Release of Retainage - Construction ContraAdministrative CloseoutProject Closed
08/01/2018, Basin 0700
08/01/2018, 100129 Pump Station 0700 Upgrade01/24/2018 A, Design
Design PhaseRemedial Action Plan Submittal to SAC Letter Issuance
08/01/2018, Project CloseoutCloseout Phase
Issue SAC LetterAdministrative Closeout
Project Closed08/17/2018, Basin 0723
08/17/2018, 100130 Pump Station 0723 Upgrade03/27/2017 A, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval Process
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 117 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1030 Issue Design NTP 04/25/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 04/25/2016 A 03/14/2017 A 85
30% Des30% Design 04/25/2016 A 07/11/2016 A 42B1060 A/E Prepares 30% Construction Documents 04/25/2016 A 06/08/2016 A 30B1070 Geotechnical Engineering Services 05/04/2016 A 06/08/2016 A 20B1080 Surveying Services 05/04/2016 A 06/08/2016 A 15B1100 30% CDs Submittal 06/08/2016 A 0B1120 30% Review (MDWASD/PSIP Team) 06/08/2016 A 07/11/2016 A 10
60% Des60% Design 06/09/2016 A 09/02/2016 A 72B1130 A/E Prepares 60% Construction Documents 06/09/2016 A 08/08/2016 A 20B1140 60% CDs Submittal 08/08/2016 A 0B1160 60% Review (MDWASD/PSIP Team) 08/09/2016 A 09/02/2016 A 10
90% Des90% Design 06/09/2016 A 03/14/2017 A 214B1170 A/E Prepares 90% Construction Documents 08/09/2016 A 09/30/2016 A 20B1180 90% CDs Submittal 09/30/2016 A 0B1190 90% Review (MDWASD/PSIP Team) 10/03/2016 A 10/26/2016 A 15B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 11/21/2016 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 11/21/2016 A 01/31/2017 A 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 02/07/2017 A 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 02/07/2017 A 03/14/2017 A 21B1240 90% PWWMD Permit Submittal (Pump Station) 06/09/2016 A 0B1250 90% PWWMD Permit Review (Pump Station) 06/09/2016 A 07/06/2016 A 15B1260 90% CD PM Comments Evaluation Completed 03/14/2017 A 0B1262 MDWASD Union Concurrence Process 01/27/2017 A 03/07/2017 A 30
100% De100% Design 03/14/2017 A 03/27/2017 A 26B1270 A/E Prepares 100% Construction Documents 03/14/2017 A 03/27/2017 A 10B1280 100% CDs Submittal 03/27/2017 A 0B1290 100% Review (MDWASD/PSIP Team) 03/27/2017 A 03/27/2017 A 10B1300 Design Completed 03/27/2017 A 0
MDWASDMDWASD Procurement 03/27/2017 A 08/09/2017 A 66B1305 Procurement Phase 03/27/2017 A 08/09/2017 A 66B1310 Submit CDs to MDWASD Procurement Division 03/27/2017 A 0B1312 Bid Notice Preparation Period 03/28/2017 A 03/31/2017 A 23B1314 Bid Notice 03/31/2017 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Confefence 04/03/2017 A 04/03/2017 A 10B1320 Pre-Bid Conference 04/04/2017 A 04/04/2017 A 1B1322 Bidders Prepare Bids for Submittal 04/05/2017 A 05/02/2017 A 15B1330 Bids Submittal 05/02/2017 A 0B1340 MDWASD/PSIP Team Bids Evaluation 05/03/2017 A 05/23/2017 A 15B1350 Recommendation for Award Letter 05/23/2017 A 0B1355 Contract Award (Purchase Order Approval) 05/24/2017 A 08/09/2017 A 10
ConstrucConstruction 04/04/2017 A 04/19/2018 A 618B1360 Construction Phase 04/04/2017 A 04/19/2018 A 618B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 05/24/2017 A 08/22/2017 A 15B1364 Pre-Construction Meeting 08/23/2017 A 08/23/2017 A 1B1366 WASD Issues NTP (Pre-Const to NTP) 08/24/2017 A 09/01/2017 A 12B1369 WASD Issues NTP (PO to NTP) 08/10/2017 A 09/03/2017 A 53B1370 Construction NTP 09/04/2017 A 0B1400 Construction Operations 09/04/2017 A 04/19/2018 A 150
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Issue Design NTPFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
07/11/2016 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal
30% Review (MDWASD/PSIP Team)09/02/2016 A, 60% Design
A/E Prepares 60% Construction Documents60% CDs Submittal60% Review (MDWASD/PSIP Team)
03/14/2017 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)
90% RER(DERM)FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)
90% RER(Building Dept) Permit Review (Pump Station)90% PWWMD Permit Submittal (Pump Station)
90% PWWMD Permit Review (Pump Station)90% CD PM Comments Evaluation Completed
MDWASD Union Concurrence Process03/27/2017 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal
100% Review (MDWASD/PSIP Team)Design Completed
08/09/2017 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid Notice
MDWASD/PSIP Team Prepare for Pre-Bid ConfefencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter
Contract Award (Purchase Order Approval)04/19/2018 A, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction MeetingWASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Construction NTPConstruction Operations
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 118 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1400 Original Construction Duration 09/04/2017 A 02/01/2018 A 150B1400 Change Order #1 - Hurricane Irma 02/02/2018 A 02/22/2018 A 150B1402 Substantial Completion 04/19/2018 A 0
DesignerDesigner Construction Support Services 04/04/2017 A 04/19/2018 A 260B1410 Designer Construction Support Services 04/04/2017 A 04/19/2018 A 778
Project CProject Closeout 04/20/2018 A 08/17/2018 120B1445 Closeout Phase 04/20/2018 A 08/17/2018 120B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 04/20/2018 A 08/17/2018 120B1490 Project Closed 08/17/2018 0
Basin 0724Basin 0724 09/25/2014 A 09/28/2020 2136
100131 Ba100131 Basin 0724 Infiltration/Inflow Study and Repairs 09/25/2014 A 05/13/2016 A 647InfiltratioInfiltration/Inflow 09/25/2014 A 05/13/2016 A 615
B1000 Infiltration/Inflow Phase 09/25/2014 A 05/13/2016 A 615Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 10/23/2015 A 213
B1005 SSES Phase 09/25/2014 A 10/23/2015 A 213B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 04/24/2015 A 10/23/2015 A 30
Dig & ReDig & Replace Repairs 11/20/2015 A 05/13/2016 A 30B1165 Dig & Replace Phase 11/20/2015 A 05/13/2016 A 30B1180 Issue NTP for Dig & Replace Repairs 11/20/2015 A 0B1190 Conduct Dig & Replace Repairs 04/14/2016 A 05/13/2016 A 30
Project CProject Closeout 05/13/2016 A 05/13/2016 A 0B1235 Closeout Phase 05/13/2016 A 05/13/2016 A 0B1260 Project Closed 05/13/2016 A 0
100132 Pu100132 Pump Station 0724 Upgrade * 08/01/2018 09/28/2020 564DesignDesign 08/01/2018 06/29/2019 333
B1000 Design Phase 08/01/2018 06/29/2019 333B1010 Prepare and Submit Design Package 08/01/2018 08/07/2018 7B1020 Engage Design Consultant 08/08/2018 09/04/2018 28B1022 TA Preparation 09/05/2018 09/18/2018 14B1024 TA Approval Process 09/19/2018 10/28/2018 40B1030 Issue Design NTP 10/29/2018 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/29/2018 06/01/2019 216
30% Des30% Design 10/29/2018 01/16/2019 80B1060 A/E Prepares 30% Construction Documents 10/29/2018 12/17/2018 50B1100 30% CDs Submittal 12/17/2018 0B1120 30% Review (MDWASD/PSIP Team) 12/18/2018 01/16/2019 30
60% Des60% Design 12/18/2018 01/30/2019 44B1130 A/E Prepares 60% Construction Documents 12/18/2018 01/16/2019 30B1140 60% CDs Submittal 01/16/2019 0B1160 60% Review (MDWASD/PSIP Team) 01/17/2019 01/30/2019 14
90% Des90% Design 01/17/2019 06/01/2019 136B1170 A/E Prepares 90% Construction Documents 01/17/2019 02/25/2019 40B1180 90% CDs Submittal 02/25/2019 0B1190 90% Review (MDWASD/PSIP Team) 02/26/2019 03/27/2019 30B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 03/28/2019 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 03/28/2019 05/11/2019 45
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Original Construction DurationChange Order #1 - Hurricane Irma
Substantial Completion04/19/2018 A, Designer Construction Support Services
Designer Construction Support Services08/17/2018, Project Closeout
Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction ContractAdministrative CloseoutProject Closed
05/13/2016 A, 100131 Basin 0724 Infiltration/Inflow Study and Repairs05/13/2016 A, Infiltration/Inflow
Infiltration/Inflow Phase10/23/2015 A, Sanitary Sewer Evaluation SurveySSES Phase
Issue NTP to SSES ContractorConduct SSES
05/13/2016 A, Dig & Replace RepairsDig & Replace Phase
Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs05/13/2016 A, Project CloseoutCloseout Phase
Project Closed
06/29/2019, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval Process
Issue Design NTPFinal Engineering Report Review & Ap
01/16/2019, 30% Design
A/E Prepares 30% Construction Documents30% CDs Submittal
30% Review (MDWASD/PSIP Team)01/30/2019, 60% Design
A/E Prepares 60% Construction Documents60% CDs Submittal60% Review (MDWASD/PSIP Team)
06/01/2019, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (P
90% RER(DERM)FDEP Permit Review (
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 119 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 05/12/2019 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 05/12/2019 06/01/2019 21B1240 90% Municipality Permit Submittal (Pump Station) 05/12/2019 0B1250 90% Municipality Permit Review (Pump Station) 05/12/2019 06/01/2019 21B1260 90% CD PM Comments Evaluation Completed 06/01/2019 0
100% De100% Design 06/02/2019 06/29/2019 28B1270 A/E Prepares 100% Construction Documents 06/02/2019 06/15/2019 14B1280 100% CDs Submittal 06/15/2019 0B1290 100% Review (MDWASD/PSIP Team) 06/16/2019 06/29/2019 14B1300 Design Completed 06/29/2019 0
MDWASDMDWASD Procurement 06/29/2019 10/11/2019 104B1305 Procurement Phase 06/29/2019 10/11/2019 104B1310 Submit CDs to MDWASD Procurement Division 06/29/2019 0B1312 Bid Notice Preparation Period 06/30/2019 08/01/2019 33B1314 Bid Notice 08/01/2019 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 08/02/2019 08/15/2019 14B1320 Pre-Bid Conference 08/16/2019 08/16/2019 1B1322 Bidders Prepare Bids for Submittal 08/17/2019 09/06/2019 21B1330 Bids Submittal 09/06/2019 0B1340 MDWASD/PSIP Team Bids Evaluation 09/07/2019 09/27/2019 21B1350 Recommendation for Award Letter 09/27/2019 0B1355 Contract Award (Purchase Order Approval) 09/28/2019 10/11/2019 14
ConstrucConstruction 08/16/2019 05/31/2020 290B1360 Construction Phase 08/16/2019 05/31/2020 290B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 09/28/2019 10/18/2019 21B1364 Pre-Construction Meeting 10/19/2019 10/19/2019 1B1366 WASD Issues NTP (Pre-Const to NTP) 10/20/2019 12/03/2019 45B1369 WASD Issues NTP (PO to NTP) 10/12/2019 12/03/2019 53B1370 Construction NTP 12/04/2019 0B1400 Construction Operations 12/04/2019 05/31/2020 180B1402 Substantial Completion 05/31/2020 0
DesignerDesigner Construction Support Services 08/16/2019 05/31/2020 290B1410 Designer Construction Support Services 08/16/2019 05/31/2020 290
Project CProject Closeout 08/01/2018 09/28/2020 564B1445 Closeout Phase 08/01/2018 09/28/2020 790B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 05/31/2020 0B1480 Administrative Closeout 06/01/2020 09/28/2020 120B1490 Project Closed 09/28/2020 0
Basin 0742Basin 0742 11/20/2015 A 08/18/2019 1294
100133 Ba100133 Basin 0742 Infiltration/Inflow Study and Repairs 11/20/2015 A 05/11/2016 A 156InfiltratioInfiltration/Inflow 11/20/2015 A 05/10/2016 A 144
B1000 Infiltration/Inflow Phase 11/20/2015 A 05/10/2016 A 144Dig & ReDig & Replace Repairs 11/20/2015 A 05/10/2016 A 144
B1165 Dig & Replace Phase 11/20/2015 A 05/10/2016 A 144B1180 Issue NTP for Dig & Replace Repairs 11/20/2015 A 0B1190 Conduct Dig & Replace Repairs 04/08/2016 A 05/10/2016 A 30
Project CProject Closeout 05/11/2016 A 05/11/2016 A 0B1235 Closeout Phase 05/11/2016 A 05/11/2016 A 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
90% RER(Building Dept) Permit Submit90% RER(Building Dept) Permit Revie
90% Municipality Permit Submittal (Pum90% Municipality Permit Review (Pum90% CD PM Comments Evaluation C
06/29/2019, 100% Design
A/E Prepares 100% Construction Do100% CDs Submittal100% Review (MDWASD/PSIP TeamDesign Completed
10/11/2019, MDWASD ProProcurement Phase
Submit CDs to MDWASD ProcuremBid Notice Preparation Period
Bid NoticeMDWASD/PSIP Team Prepare
Pre-Bid ConferenceBidders Prepare Bids for Subm
Bids SubmittalMDWASD/PSIP Team Bids ERecommendation for Award Contract Award (Purchase O
05/31/2
ConstruMDWASD/PSIP Team PrePre-Construction Meeting
WASD Issues NTP (PreWASD Issues NTP (PO
Construction NTPConstruSubstan05/31/2
Designe
Issue SAC LetterFinal Re
08/18/2019, Basin 0742
05/11/2016 A, 100133 Basin 0742 Infiltration/Inflow Study and Repairs05/10/2016 A, Infiltration/InflowInfiltration/Inflow Phase05/10/2016 A, Dig & Replace RepairsDig & Replace Phase
Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs05/11/2016 A, Project CloseoutCloseout Phase
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 120 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1260 Project Closed 05/11/2016 A 0
100134 Pu100134 Pump Station 0742 Upgrade 01/14/2016 A 08/18/2019 1294DesignDesign 01/14/2016 A 04/23/2018 A 819
B1000 Design Phase 01/14/2016 A 04/23/2018 A 819B1010 Prepare and Submit Design Package 01/14/2016 A 01/14/2016 A 5B1020 Engage Design Consultant 01/14/2016 A 04/01/2016 A 20B1022 TA Preparation 04/04/2016 A 04/15/2016 A 1B1024 TA Approval Process 04/18/2016 A 09/28/2016 A 20B1030 Issue Design NTP 09/30/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 09/30/2016 A 03/30/2018 A 85
30% Des30% Design 09/30/2016 A 06/13/2017 A 170B1060 A/E Prepares 30% Construction Documents 09/30/2016 A 01/17/2017 A 50B1100 30% CDs Submittal 01/17/2017 A 0B1120 30% Review (MDWASD/PSIP Team) 01/18/2017 A 03/17/2017 A 30B1122 Project On-Hold, Pending Construction Staging Area Approval 03/17/2017 A 06/13/2017 A 63
90% Des90% Design 06/13/2017 A 03/30/2018 A 282B1170 A/E Prepares 90% Construction Documents 06/13/2017 A 07/14/2017 A 40B1180 90% CDs Submittal 07/14/2017 A 0B1190 90% Review (MDWASD/PSIP Team) 07/17/2017 A 10/09/2017 A 30B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 11/22/2017 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 11/22/2017 A 02/21/2018 A 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 02/22/2018 A 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 02/22/2018 A 03/30/2018 A 21B1260 90% CD PM Comments Evaluation Completed 03/30/2018 A 0B1262 MDWASD Union Concurrence Process 07/27/2017 A 08/17/2017 A 30
100% De100% Design 04/01/2018 A 04/23/2018 A 30B1270 A/E Prepares 100% Construction Documents 04/01/2018 A 04/13/2018 A 14B1280 100% CDs Submittal 04/13/2018 A 0B1290 100% Review (MDWASD/PSIP Team) 04/15/2018 A 04/23/2018 A 14B1300 Design Completed 04/23/2018 A 0
MDWASDMDWASD Procurement 04/08/2018 A 08/30/2018 91B1305 Procurement Phase 04/08/2018 A 08/30/2018 91B1310 Submit CDs to MDWASD Procurement Division 05/07/2018 A 0B1312 Bid Notice Preparation Period 04/08/2018 A 05/15/2018 A 33B1314 Bid Notice 05/15/2018 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 05/16/2018 A 05/28/2018 A 14B1320 Pre-Bid Conference 05/29/2018 A 05/29/2018 A 1B1322 Bidders Prepare Bids for Submittal 05/30/2018 A 07/26/2018 A 21B1330 Bids Submittal 07/26/2018 A 0B1340 MDWASD/PSIP Team Bids Evaluation 07/27/2018 A 08/16/2018 21B1350 Recommendation for Award Letter 08/16/2018 0B1355 Contract Award (Purchase Order Approval) 08/17/2018 08/30/2018 14
ConstrucConstruction 05/29/2018 A 04/20/2019 290B1360 Construction Phase 05/29/2018 A 04/20/2019 290B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 08/17/2018 09/06/2018 21B1364 Pre-Construction Meeting 09/07/2018 09/07/2018 1B1366 WASD Issues NTP (Pre-Const to NTP) 09/08/2018 10/22/2018 45B1369 WASD Issues NTP (PO to NTP) 08/31/2018 10/22/2018 53B1370 Construction NTP 10/23/2018 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Project Closed08/18/2019, 100134 Pump Sta
04/23/2018 A, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval ProcessIssue Design NTP
Final Engineering Report Review & Approval (MDWASD/PSIP Team)06/13/2017 A, 30% Design
A/E Prepares 30% Construction Documents30% CDs Submittal
30% Review (MDWASD/PSIP Team)Project On-Hold, Pending Construction Staging Area Approval
03/30/2018 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)
90% RER(DERM)FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)
90% RER(Building Dept) Permit Review (Pump Station)90% CD PM Comments Evaluation Completed
MDWASD Union Concurrence Process04/23/2018 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed
08/30/2018, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid Notice
MDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)
04/20/2019, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Construction NTP
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 121 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1400 Construction Operations 10/23/2018 04/20/2019 180B1402 Substantial Completion 04/20/2019 0
DesignerDesigner Construction Support Services 05/29/2018 A 04/20/2019 290B1410 Designer Construction Support Services 05/29/2018 A 04/20/2019 290
Project CProject Closeout 08/01/2018 08/18/2019 383B1445 Closeout Phase 08/01/2018 08/18/2019 383B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 04/20/2019 0B1480 Administrative Closeout 04/21/2019 08/18/2019 120B1490 Project Closed 08/18/2019 0
Basin 0743Basin 0743 08/04/2014 A 08/01/2018 1554
100135 Ba100135 Basin 0743 Infiltration/Inflow Study and Repairs 05/22/2015 A 05/06/2016 A 297InfiltratioInfiltration/Inflow 05/22/2015 A 05/05/2016 A 237
B1000 Infiltration/Inflow Phase 05/22/2015 A 05/05/2016 A 237CIPP RepCIPP Repairs 05/22/2015 A 07/28/2015 A 20
B1065 CIPP Phase 05/22/2015 A 07/28/2015 A 20B1080 Issue NTP for CIPP Repairs 05/22/2015 A 0B1090 Conduct CIPP Repairs 07/27/2015 A 07/28/2015 A 20
ManholeManhole Repairs 10/30/2015 A 03/17/2016 A 20B1115 Manhole Phase 10/30/2015 A 03/17/2016 A 20B1130 Issue NTP for Manhole Repairs 10/30/2015 A 0B1140 Conduct Manhole Repairs 03/17/2016 A 03/17/2016 A 20
Dig & ReDig & Replace Repairs 06/26/2015 A 05/05/2016 A 30B1165 Dig & Replace Phase 06/26/2015 A 05/05/2016 A 30B1180 Issue NTP for Dig & Replace Repairs 06/26/2015 A 0B1190 Conduct Dig & Replace Repairs 08/04/2015 A 05/05/2016 A 30
Project CProject Closeout 05/06/2016 A 05/06/2016 A 0B1235 Closeout Phase 05/06/2016 A 05/06/2016 A 0B1260 Project Closed 05/06/2016 A 0
100218 Pu100218 Pump Station 0743(AM) Upgrade 08/04/2014 A 08/01/2018 1479DesignDesign 08/04/2014 A 07/10/2015 A 496
B1000 Design Phase 08/04/2014 A 07/10/2015 A 496B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 08/04/2014 A 08/06/2014 A 5B1020 Engage Design Consultant 08/07/2014 A 11/04/2014 A 20B1030 Issue Design NTP 11/05/2014 A 0B1040 A/E Develops and Submits Final Engineering Report 11/05/2014 A 07/10/2015 A 17B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 11/05/2014 A 02/27/2015 A 10
30% Des30% Design 11/05/2014 A 01/08/2015 A 30B1060 A/E Prepares 30% Construction Documents 11/05/2014 A 12/24/2014 A 30B1070 Geotechnical Engineering Services 11/05/2014 A 12/24/2014 A 20B1080 Surveying Services 11/05/2014 A 12/24/2014 A 15B1100 30% CDs Submittal 12/24/2014 A 0B1120 30% Review (MDWASD/PSIP Team) 12/26/2014 A 01/08/2015 A 10
90% Des90% Design 12/26/2014 A 07/10/2015 A 135B1170 A/E Prepares 90% Construction Documents 12/26/2014 A 02/18/2015 A 20B1180 90% CDs Submittal 02/18/2015 A 0B1190 90% Review (MDWASD/PSIP Team) 02/18/2015 A 02/27/2015 A 15B1195 Permit Set Modifications 03/02/2015 A 03/05/2015 A 10B1200 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 03/06/2015 A 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Construction OperationsSubstantial Completion04/20/2019, Designer Construction Supp
Designer Construction Support Services08/18/2019, Project Closeout
Closeout PhaseIssue SAC Letter
Final Release of Retainage - ConstructionAdministrative CloseoutProject Closed
08/01/2018, Basin 0743
05/06/2016 A, 100135 Basin 0743 Infiltration/Inflow Study and Repairs05/05/2016 A, Infiltration/Inflow
Infiltration/Inflow Phase07/28/2015 A, CIPP RepairsCIPP Phase
Issue NTP for CIPP RepairsConduct CIPP Repairs
03/17/2016 A, Manhole RepairsManhole Phase
Issue NTP for Manhole RepairsConduct Manhole Repairs
05/05/2016 A, Dig & Replace RepairsDig & Replace Phase
Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs05/06/2016 A, Project CloseoutCloseout Phase
Project Closed08/01/2018, 100218 Pump Station 0743(AM) Upgrade
07/10/2015 A, Design
Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book
Engage Design ConsultantIssue Design NTP
A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
01/08/2015 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services
30% CDs Submittal30% Review (MDWASD/PSIP Team)
07/10/2015 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)Permit Set Modifications
90% RER(DERM)/FDEP Permit Submittal (Pump Station)
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 122 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1210 90% RER(DERM)/FDEP Permit Review (Pump Station) 03/06/2015 A 04/07/2015 A 5B1220 90% RER (Building Dept) Permit Submittal 04/22/2015 A 0B1230 90% RER (Building Dept) Permit Review 04/22/2015 A 06/09/2015 A 10B1240 90% PWWMD Permit Submittal 07/01/2015 A 0B1250 90% PWWMD Permit Review 07/01/2015 A 07/10/2015 A 5B1260 90% CD PM Comments Evaluation Completed 07/10/2015 A 0
100% De100% Design 07/10/2015 A 07/10/2015 A 43B1270 A/E Prepares 100% Construction Documents 07/10/2015 A 07/10/2015 A 5B1280 100% CDs Submittal 07/10/2015 A 0B1290 100% Review (MDWASD/PSIP Team) 07/10/2015 A 07/10/2015 A 5B1300 Design Completed 07/10/2015 A 0
MDWASDMDWASD Procurement 04/17/2015 A 10/07/2015 A 123B1305 Procurement Phase 04/17/2015 A 10/07/2015 A 123B1310 Submit CDs to MDWASD Procurement Division 04/17/2015 A 0B1312 Bid Notice Preparation Period 04/20/2015 A 04/29/2015 A 0B1314 Bid Notice 04/30/2015 A 0B1316 MDWASD/PSIP Team Prepared for Pre-Bid Conference 05/01/2015 A 05/05/2015 A 0B1320 Pre-Bid Conference 05/06/2015 A 05/06/2015 A 0B1322 Bidders Prepare Bids for Submittal 05/07/2015 A 07/01/2015 A 0B1330 Bids Submittal 07/02/2015 A 0B1340 MDWASD/PSIP Team Bids Evaluation 07/03/2015 A 07/17/2015 A 15B1350 Recommendation for Award Letter 07/17/2015 A 0B1355 Contract Award (Purchase Order Approval) 07/20/2015 A 10/07/2015 A 10
ConstrucConstruction 05/06/2015 A 03/03/2017 A 1219B1360 Construction Phase 05/06/2015 A 03/03/2017 A 1219B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 07/20/2015 A 08/18/2015 A 15B1365 Pre-Construction Meeting 08/19/2015 A 0B1366 Awaiting Resolution of FPL Issues & MDWASD Electrtical Stand 08/19/2015 A 01/22/2016 A 15B1369 WASD Issues NTP (PO to NTP) 10/08/2015 A 01/24/2016 A 53B1370 Construction NTP 01/25/2016 A 0B1400 Construction Operations 01/25/2016 A 11/15/2016 A 107B1400 Original Construction Duration 01/25/2016 A 06/23/2016 A 107B1400 Change Order #1 - FPL 06/24/2016 A 08/31/2016 A 107B1400 Change Order #2 - Contractual Duration Discrepancies 09/01/2016 A 11/15/2016 A 107B1402 Substantial Completion 11/15/2016 A 0
DesignerDesigner Construction Support Services 05/06/2015 A 03/03/2017 A 226B1410 Designer Construction Support Services 05/06/2015 A 03/03/2017 A 226
ConstrucConstruction Close Out 11/16/2016 A 03/03/2017 A 10B1420 Commissioning 11/16/2016 A 03/03/2017 A 5B1430 Punch List 11/16/2016 A 03/03/2017 A 10
Project CProject Closeout 11/16/2016 A 08/01/2018 624B1445 Closeout Phase 11/16/2016 A 08/01/2018 624B1450 Issue SAC Letter 03/20/2018 A 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 11/16/2016 A 08/01/2018 120B1490 Project Closed 08/01/2018 0
100214 FM100214 FM for Pump Station 0743 08/18/2014 A 08/01/2018 1554DesignDesign 08/18/2014 A 07/23/2015 A 549
B1000 Design Phase 08/18/2014 A 07/23/2015 A 549
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
90% RER(DERM)/FDEP Permit Review (Pump Station)90% RER (Building Dept) Permit Submittal
90% RER (Building Dept) Permit Review90% PWWMD Permit Submittal90% PWWMD Permit Review90% CD PM Comments Evaluation Completed07/10/2015 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal
100% Review (MDWASD/PSIP Team)Design Completed
10/07/2015 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation Period
Bid NoticeMDWASD/PSIP Team Prepared for Pre-Bid Conference
Pre-Bid ConferenceBidders Prepare Bids for Submittal
Bids SubmittalMDWASD/PSIP Team Bids Evaluation
Recommendation for Award LetterContract Award (Purchase Order Approval)
03/03/2017 A, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction Meeting
Pre-Construction MeetingAwaiting Resolution of FPL Issues & MDWASD Electrtical StandardWASD Issues NTP (PO to NTP)
Construction NTPConstruction Operations
Original Construction DurationChange Order #1 - FPL
Change Order #2 - Contractual Duration Discrepancies
Substantial Completion03/03/2017 A, Designer Construction Support Services
Designer Construction Support Services03/03/2017 A, Construction Close Out
CommissioningPunch List
08/01/2018, Project Closeout
Closeout PhaseIssue SAC Letter
Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed08/01/2018, 100214 FM for Pump Station 0743
07/23/2015 A, Design
Design Phase
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 123 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 08/18/2014 A 09/05/2014 A 5B1020 Engage Design Consultant 09/08/2014 A 12/05/2014 A 20B1030 Issue Design NTP 12/05/2014 A 0B1040 A/E Develops and Submits Final Engineering Report 12/05/2014 A 07/23/2015 A 20B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 12/05/2014 A 03/30/2015 A 10
30% Des30% Design 12/08/2014 A 03/25/2015 A 30B1060 A/E Prepares 30% Construction Documents 12/08/2014 A 02/17/2015 A 30B1070 Geotechnical Engineering Services 12/08/2014 A 02/17/2015 A 20B1080 Surveying Services 12/08/2014 A 02/17/2015 A 15B1100 30% CDs Submittal 02/17/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 02/18/2015 A 03/25/2015 A 0
60% Des60% Design 02/18/2015 A 03/04/2015 A 15B1140 A/E Prepares 60% Construction Documents (Progress Set) 02/18/2015 A 03/04/2015 A 15B1150 60% CDs Submittal (Progress Set) 03/04/2015 A 0B1170 60% Review (On-Board Review) 03/04/2015 A 03/04/2015 A 1
90% Des90% Design 03/05/2015 A 07/23/2015 A 116B1180 A/E Prepares 90% Construction Documents 03/05/2015 A 03/27/2015 A 0B1190 90% CDs Submittal 03/27/2015 A 0B1200 90% Review (MDWASD/PSIP Team) 03/25/2015 A 03/30/2015 A 5B1230 90% RER(DERM)FDEP Permit Submittal (Force Main) 07/14/2015 A 0B1240 90% RER(DERM)FDEP Permit Review (Force Main) 07/14/2015 A 07/22/2015 A 5B1250 90% PWWMD Permit Submittal (Force Main) 07/16/2015 A 0B1260 90% PWWMD Permit Review (Force Main) 07/16/2015 A 07/23/2015 A 10B1290 90% CD PM Comments Evaluation Completed 07/23/2015 A 0
100% De100% Design 03/31/2015 A 07/22/2015 A 123B1300 A/E Prepares 100% Construction Documents 03/31/2015 A 07/22/2015 A 5B1310 100% CDs Submittal 07/22/2015 A 0B1320 100% Review (MDWASD/PSIP Team) 07/22/2015 A 07/22/2015 A 5B1330 Design Completed 07/22/2015 A 0
MDWASDMDWASD Procurement 08/13/2015 A 03/04/2016 A 109B1335 Procurement Phase 08/13/2015 A 03/04/2016 A 109B1340 Submit CDs to MDWASD Procurement Division 08/13/2015 A 0B1342 Bid Notice Preparation Period 08/14/2015 A 09/18/2015 A 23B1344 Bid Notice 09/21/2015 A 0B1346 MDWASD/PSIP Team Preparation for Pre-Bid Conference 09/22/2015 A 10/07/2015 A 10B1350 Pre-Bid Conference 10/08/2015 A 10/08/2015 A 1B1358 Bidders Prepare Bids for Submittal 10/09/2015 A 10/27/2015 A 15B1360 Bids Submittal 10/28/2015 A 0B1370 MDWASD/PSIP Team Bids Evaluation 10/29/2015 A 12/08/2015 A 15B1380 Recommendation for Award Letter 12/08/2015 A 0B1385 Contract Award (Purchase Order Approval) 12/09/2015 A 03/04/2016 A 10
ConstrucConstruction 10/08/2015 A 02/02/2017 A 1160B1390 Construction Phase 10/08/2015 A 12/04/2016 A 1160B1392 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 12/09/2015 A 01/06/2016 A 15B1394 Pre-Construction Meeting 01/07/2016 A 01/07/2016 A 1B1396 WASD Issues NTP (PO to NTP) 03/05/2016 A 03/13/2016 A 53B1400 Construction NTP 03/14/2016 A 0B1430 Construction Operations 03/14/2016 A 11/04/2016 A 104B1430 Original Contruction Duration 03/14/2016 A 08/07/2016 A 104
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Prepare Request for SOW, Fee, Schedule, and Project BookEngage Design ConsultantIssue Design NTP
A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)03/25/2015 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal
30% Review (MDWASD/PSIP Team)03/04/2015 A, 60% Design
A/E Prepares 60% Construction Documents (Progress Set)60% CDs Submittal (Progress Set)
60% Review (On-Board Review)07/23/2015 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)
90% RER(DERM)FDEP Permit Submittal (Force Main)90% RER(DERM)FDEP Permit Review (Force Main)90% PWWMD Permit Submittal (Force Main)90% PWWMD Permit Review (Force Main)90% CD PM Comments Evaluation Completed07/22/2015 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal
100% Review (MDWASD/PSIP Team)Design Completed
03/04/2016 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Preparation for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter
Contract Award (Purchase Order Approval)02/02/2017 A, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
WASD Issues NTP (PO to NTP)Construction NTP
Construction OperationsOriginal Contruction Duration
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 124 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1430 Change Order #1 - Pipe & Roadway Restoration 08/08/2016 A 11/05/2016 A 104B1432 Substantial Completion 02/02/2017 A 0
DesignerDesigner Construction Support Services 10/08/2015 A 12/04/2016 A 267B1440 Designer Construction Support Services 10/08/2015 A 12/04/2016 A 267
ConstrucConstruction Close Out 11/07/2016 A 12/04/2016 A 10B1460 Punch List 11/07/2016 A 12/04/2016 A 10
Project CProject Closeout 11/07/2016 A 08/01/2018 547B1475 Closeout Phase 11/07/2016 A 08/01/2018 547B1500 Final Release of Retainage - Construction Contract 11/07/2017 A 0B1510 Administrative Closeout 11/07/2016 A 08/01/2018 120B1520 Project Closed 08/01/2018 0
Basin 0773Basin 0773 12/17/2012 A 08/01/2018 1901
100137 Pu100137 Pump Station 0773 Upgrade 12/17/2012 A 08/01/2018 1901DesignDesign 12/17/2012 A 03/02/2018 A 1901
B1000 Design Phase 12/17/2012 A 03/02/2018 A 1901B1005 Remedial Action Plan to SAC Letter Issuance 12/17/2012 A 03/02/2018 A 1901
Project CProject Closeout 03/02/2018 A 08/01/2018 152B1445 Closeout Phase 03/02/2018 A 08/01/2018 152B1450 Issue SAC Letter 03/02/2018 A 0B1480 Administrative Closeout 03/03/2018 A 08/01/2018 120B1490 Project Closed 08/01/2018 0
100229 FM100229 FM for Pump Station 0773 12/17/2012 A 08/01/2018 1901DesignDesign 12/17/2012 A 03/02/2018 A 1901
B1000 Design Phase 12/17/2012 A 03/02/2018 A 1901B1005 Remedial Action Plan to SAC Letter Issuance 12/17/2012 A 03/02/2018 A 1901
Project CProject Closeout 03/03/2018 A 08/01/2018 697B1475 Closeout Phase 03/03/2018 A 08/01/2018 697B1510 Administrative Closeout 03/03/2018 A 08/01/2018 120B1520 Project Closed 08/01/2018 0
Basin 0785Basin 0785 06/26/2015 A 01/22/2016 A 1000
100138 Ba100138 Basin 0785 Infiltration/Inflow Study and Repairs 06/26/2015 A 01/22/2016 A 246InfiltratioInfiltration/Inflow 06/26/2015 A 01/21/2016 A 30
B1000 Infiltration/Inflow Phase 06/26/2015 A 01/21/2016 A 30Dig & ReDig & Replace Repairs 06/26/2015 A 01/21/2016 A 30
B1165 Dig & Replace Phase 06/26/2015 A 01/21/2016 A 30B1180 Issue NTP for Dig & Replace Repairs 06/26/2015 A 0B1190 Conduct Dig & Replace Repairs 07/09/2015 A 01/21/2016 A 30
Project CProject Closeout 01/22/2016 A 01/22/2016 A 0B1235 Closeout Phase 01/22/2016 A 01/22/2016 A 0B1260 Project Closed 01/22/2016 A 0
100139 Pu100139 Pump Station 0785 Upgrade 07/02/2015 A 07/02/2015 A 1000Project CProject Closeout 07/02/2015 A 07/02/2015 A 1000
B1445 Closeout Phase 07/02/2015 A 07/02/2015 A 1000B1450 Issue SAC Letter 07/02/2015 A 0B1480 Administrative Closeout 07/02/2015 A 07/02/2015 A 5B1490 Project Closed 07/02/2015 A 07/02/2015 A 10
Basin 0794Basin 0794 09/25/2014 A 08/01/2018 1477
100140 Ba100140 Basin 0794 Infiltration/Inflow Study and Repairs 09/25/2014 A 07/13/2015 A 546InfiltratioInfiltration/Inflow 09/25/2014 A 07/10/2015 A 240
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Change Order #1 - Pipe & Roadway Restoration
Substantial Completion12/04/2016 A, Designer Construction Support Services
Designer Construction Support Services12/04/2016 A, Construction Close Out
Punch List08/01/2018, Project Closeout
Closeout PhaseFinal Release of Retainage - Construction Contract
Administrative CloseoutProject Closed08/01/2018, Basin 0773
08/01/2018, 100137 Pump Station 0773 Upgrade03/02/2018 A, Design
Design PhaseRemedial Action Plan to SAC Letter Issuance
08/01/2018, Project CloseoutCloseout Phase
Issue SAC LetterAdministrative CloseoutProject Closed08/01/2018, 100229 FM for Pump Station 0773
03/02/2018 A, Design
Design PhaseRemedial Action Plan to SAC Letter Issuance
08/01/2018, Project CloseoutCloseout Phase
Administrative CloseoutProject Closed
01/22/2016 A, Basin 0785
01/22/2016 A, 100138 Basin 0785 Infiltration/Inflow Study and Repairs01/21/2016 A, Infiltration/Inflow
Infiltration/Inflow Phase01/21/2016 A, Dig & Replace RepairsDig & Replace Phase
Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs01/22/2016 A, Project CloseoutCloseout Phase
Project Closed07/02/2015 A, 100139 Pump Station 0785 Upgrade07/02/2015 A, Project Closeout
Closeout PhaseIssue SAC Letter
Administrative CloseoutProject Closed
08/01/2018, Basin 0794
07/13/2015 A, 100140 Basin 0794 Infiltration/Inflow Study and Repairs07/10/2015 A, Infiltration/Inflow
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 125 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1000 Infiltration/Inflow Phase 09/25/2014 A 07/10/2015 A 240Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 07/10/2015 A 240
B1005 SSES Phase 09/25/2014 A 07/10/2015 A 240B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 06/22/2015 A 07/10/2015 A 30
Project CProject Closeout 07/13/2015 A 07/13/2015 A 0B1235 Closeout Phase 07/13/2015 A 07/13/2015 A 0B1260 Project Closed 07/13/2015 A 0
100141 Pu100141 Pump Station 0794(AM) Upgrade 12/31/2014 A 08/01/2018 1440DesignDesign 12/31/2014 A 07/28/2016 A 662
B1000 Design Phase 12/31/2014 A 07/28/2016 A 662B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 12/31/2014 A 01/07/2015 A 5B1020 Engage Design Consultant 01/08/2015 A 04/14/2015 A 20B1030 Issue Design NTP 04/15/2015 A 0B1040 A/E Develops and Submits Final Engineering Report 04/15/2015 A 07/20/2016 A 73B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 04/15/2015 A 03/30/2016 A 32B1052 TA Rev 1 - Preparation of FPL and WASD Easements 06/30/2015 A 07/29/2015 A 20B1054 TA Rev 1 - FPL and WASD Easements Approval Process 07/30/2015 A 08/14/2015 A 20
30% Des30% Design 04/15/2015 A 06/08/2016 A 73B1060 A/E Prepares 30% Construction Documents 04/15/2015 A 06/08/2015 A 30B1070 Geotechnical Engineering Services 04/15/2015 A 06/08/2015 A 15B1080 Surveying Services 04/15/2015 A 06/08/2015 A 15B1100 30% CDs Submittal 06/12/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 06/15/2015 A 06/26/2015 A 10B1122 DC Prepares Legal Description & Location of FPL & MDWASD E 08/17/2015 A 08/31/2015 A 20B1124 Approval and Recording of FPL & MDWASD Easements 09/01/2015 A 06/08/2016 A 20
90% Des90% Design 02/09/2016 A 07/20/2016 A 181B1170 A/E Prepares 90% Construction Documents 02/09/2016 A 02/23/2016 A 20B1180 90% CDs Submittal 02/23/2016 A 0B1190 90% Review (MDWASD/PSIP Team) 02/24/2016 A 03/30/2016 A 15B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 04/19/2016 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 04/19/2016 A 06/20/2016 A 15B1220 90% RER (Building Department) Permit Submittal 06/24/2016 A 0B1230 90% RER (Building Department) Permit Review 06/24/2016 A 07/20/2016 A 15B1240 90% PWWMD Permit Submittal 03/07/2016 A 0B1250 90% PWWMD Permit Review 03/07/2016 A 03/30/2016 A 15B1260 90% CD PM Comments Evaluation Completed 07/20/2016 A 0
100% De100% Design 07/21/2016 A 07/28/2016 A 92B1270 A/E Prepares 100% Construction Documents 07/21/2016 A 07/28/2016 A 10B1280 100% CDs Submittal 07/28/2016 A 0B1290 100% Review (MDWASD/PSIP Team) 07/21/2016 A 07/28/2016 A 10B1300 Design Completed 07/28/2016 A 0
MDWASDMDWASD Procurement 07/29/2016 A 11/07/2016 A 59B1305 Procurement Phase 07/29/2016 A 11/07/2016 A 59B1310 Submit CDs to MDWASD Procurement Division 07/29/2016 A 0B1312 Bid Notice Preparation Period 07/29/2016 A 08/02/2016 A 23B1314 Bid Notice 08/02/2016 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 08/03/2016 A 08/11/2016 A 7B1320 Pre-Bid Conference 08/12/2016 A 08/12/2016 A 1
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Infiltration/Inflow Phase07/10/2015 A, Sanitary Sewer Evaluation SurveySSES Phase
Issue NTP to SSES ContractorConduct SSES07/13/2015 A, Project CloseoutCloseout Phase
Project Closed08/01/2018, 100141 Pump Station 0794(AM) Upgrade
07/28/2016 A, Design
Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book
Engage Design ConsultantIssue Design NTP
A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
TA Rev 1 - Preparation of FPL and WASD EasementsTA Rev 1 - FPL and WASD Easements Approval Process
06/08/2016 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal30% Review (MDWASD/PSIP Team)
DC Prepares Legal Description & Location of FPL & MDWASD Easement.Approval and Recording of FPL & MDWASD Easements
07/20/2016 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)
90% RER(DERM)FDEP Permit Review (Pump Station)90% RER (Building Department) Permit Submittal
90% RER (Building Department) Permit Review90% PWWMD Permit Submittal
90% PWWMD Permit Review90% CD PM Comments Evaluation Completed07/28/2016 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal
100% Review (MDWASD/PSIP Team)Design Completed11/07/2016 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 126 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1328 Bidders Prepare Bids for Submittal 08/15/2016 A 08/30/2016 A 12B1330 Bids Submittal 08/30/2016 A 0B1340 MDWASD/PSIP Team Bids Evaluation 08/31/2016 A 09/08/2016 A 15B1350 Recommendation for Award Letter 09/08/2016 A 0B1355 Contract Award (Purchase Order Approval) 09/09/2016 A 11/07/2016 A 10
ConstrucConstruction 08/12/2016 A 03/15/2018 A 859B1360 Construction Phase 08/12/2016 A 03/15/2018 A 859B1362 MDWASD/PSIP Team Prepare for Pre-Construction meeting 09/09/2016 A 11/14/2016 A 15B1364 Pre-Construction Meeting 11/15/2016 A 11/15/2016 A 1B1369 WASD Issues NTP (PO to NTP) 11/08/2016 A 11/27/2016 A 53B1370 Construction NTP 11/28/2016 A 0B1400 Construction Operations 11/28/2016 A 03/15/2018 A 150B1400 Original Constrcution Duration 11/28/2016 A 04/27/2017 A 150B1400 Change Order #1 - FPL 04/28/2017 A 07/26/2017 A 150B1400 Change Order #2 - Hurricane Irma 07/27/2017 A 08/16/2017 A 150B1400 Change Order #3 - FPL 08/17/2017 A 02/16/2018 A 150B1402 Substantial Completion 03/15/2018 A 0
DesignerDesigner Construction Support Services 08/12/2016 A 03/15/2018 A 272B1410 Designer Construction Support Services 08/12/2016 A 03/15/2018 A 814
Project CProject Closeout 03/16/2018 A 08/01/2018 120B1445 Closeout Phase 03/16/2018 A 08/01/2018 120B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 03/16/2018 A 08/01/2018 120B1490 Project Closed 08/01/2018 0
100074 FM100074 FM for Pump Station 0794 01/12/2015 A 08/01/2018 1437DesignDesign 01/12/2015 A 10/16/2015 A 333
B1005 Design Phase 01/12/2015 A 10/16/2015 A 333B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 01/12/2015 A 01/16/2015 A 5B1020 Engage Design Consultant 01/19/2015 A 04/08/2015 A 30B1030 TA Approval Process 04/09/2015 A 04/30/2015 A 20B1040 Issue Design NTP 05/01/2015 A 0B1050 A/E Develops and Submits Final Engineering Report 05/01/2015 A 09/29/2015 A 86B1060 Final Engineering Report Review & Approval (MDWASD/PSIP Te 05/14/2015 A 09/29/2015 A 10
30% Des30% Design 05/01/2015 A 06/19/2015 A 54B1070 A/E Prepares 30% Construction Documents 05/01/2015 A 06/09/2015 A 25B1080 Geotechnical Engineering Services 05/01/2015 A 06/09/2015 A 15B1090 Surveying Services 05/01/2015 A 06/09/2015 A 15B1100 30% CDs Submittal 06/09/2015 A 0B1110 30% Review (MDWASD/PSIP Team) 06/10/2015 A 06/19/2015 A 6
90% Des90% Design 06/09/2015 A 10/08/2015 A 113B1150 A/E Prepares 90% Construction Documents 06/09/2015 A 06/29/2015 A 15B1152 90% Construction Documents Awaiting MDWASD/FPL Easemen 06/30/2015 A 07/28/2015 A 15B1154 A/E Prepares 90% Construction Documents (Resume Design) 07/29/2015 A 08/20/2015 A 15B1160 90% CDs Submittal 08/20/2015 A 0B1170 90% Review (MDWASD/PSIP Team) 08/21/2015 A 09/29/2015 A 15B1180 90% RER(DERM)FDEP Permit Submittal (Force Main) 09/29/2015 A 0B1190 90% RER(DERM)FDEP Permit Review (Force Main) 09/29/2015 A 10/08/2015 A 5B1200 90% PWWMD Permit Submittal (Force Main) 07/27/2015 A 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Bidders Prepare Bids for SubmittalBids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter
Contract Award (Purchase Order Approval)03/15/2018 A, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction meetingPre-Construction MeetingWASD Issues NTP (PO to NTP)
Construction NTPConstruction Operations
Original Constrcution DurationChange Order #1 - FPL
Change Order #2 - Hurricane IrmaChange Order #3 - FPL
Substantial Completion03/15/2018 A, Designer Construction Support Services
Designer Construction Support Services08/01/2018, Project Closeout
Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction ContractAdministrative CloseoutProject Closed08/01/2018, 100074 FM for Pump Station 0794
10/16/2015 A, Design
Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book
Engage Design ConsultantTA Approval ProcessIssue Design NTP
A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
06/19/2015 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal30% Review (MDWASD/PSIP Team)
10/08/2015 A, 90% Design
A/E Prepares 90% Construction Documents90% Construction Documents Awaiting MDWASD/FPL Easement ResolutionA/E Prepares 90% Construction Documents (Resume Design)
90% CDs Submittal90% Review (MDWASD/PSIP Team)
90% RER(DERM)FDEP Permit Submittal (Force Main)90% RER(DERM)FDEP Permit Review (Force Main)90% PWWMD Permit Submittal (Force Main)
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 127 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1210 90% PWWMD Permit Review (Force Main) 07/27/2015 A 08/12/2015 A 15B1220 90% CD PM Comments Evaluation Completed 09/29/2015 A 0
100% De100% Design 09/30/2015 A 10/16/2015 A 17B1230 A/E Prepares 100% Construction Documents 09/30/2015 A 10/15/2015 A 6B1240 100% CDs Submittal 10/15/2015 A 0B1250 100% Review (MDWASD/PSIP Team) 10/15/2015 A 10/16/2015 A 5B1260 Design Completed 10/16/2015 A 0
MDWASDMDWASD Procurement 10/16/2015 A 03/07/2016 A 84B1270 Procurement Phase 10/16/2015 A 03/07/2016 A 84B1280 Submit CDs to MDWASD Procurement Division 10/16/2015 A 0B1282 Bid Notice Preparation Period 10/19/2015 A 11/17/2015 A 23B1284 Bid Notice 11/17/2015 A 0B1286 MDWASD/PSIP Team Prepare for Pre-Bid Conference 11/18/2015 A 12/02/2015 A 10B1290 Pre-Bid Conference 12/03/2015 A 12/03/2015 A 1B1298 Bidders Prepare Bids for Submittal 12/04/2015 A 12/17/2015 A 15B1300 Bids Submittal 12/17/2015 A 0B1310 Bids Evaluation (MDWASD/PSIP Team) 12/18/2015 A 01/29/2016 A 15B1320 Recommendation for Award Letter 01/29/2016 A 0B1330 Contract Award (Purchase Order Approval) 02/01/2016 A 03/07/2016 A 10
ConstrucConstruction 12/03/2015 A 07/26/2016 A 1112B1340 Construction Phase 12/03/2015 A 07/26/2016 A 1112B1342 MDWASD/PSIP Team Prepare for Pre-Construction meeting 02/01/2016 A 02/25/2016 A 15B1344 Pre-Construction Meeting 02/26/2016 A 02/26/2016 A 1B1346 WASD Issues NTP (PO to NTP) 03/08/2016 A 03/27/2016 A 53B1350 Construction NTP 03/28/2016 A 0B1380 Construction Operations 03/28/2016 A 06/03/2016 A 120B1382 Substantial Completion 06/03/2016 A 0
DesignerDesigner Construction Support Services 12/03/2015 A 07/26/2016 A 272B1480 Designer Construction Support Services 12/03/2015 A 07/26/2016 A 272
ConstrucConstruction Close Out 06/06/2016 A 06/24/2016 A 15B1390 Commissioning 06/06/2016 A 06/24/2016 A 15B1400 Punch List 06/06/2016 A 06/24/2016 A 10
Project CProject Closeout 06/06/2016 A 08/01/2018 737B1420 Closeout Phase 06/06/2016 A 08/01/2018 737B1450 Final Release of Retainage - Construction Contract 05/30/2017 A 0B1460 Administrative Closeout 06/06/2016 A 08/01/2018 30B1470 Project Closed 08/01/2018 0
Basin 0815Basin 0815 05/01/2014 A 08/01/2018 1541
100142 Ba100142 Basin 0815 Infiltration/Inflow Study and Repairs 09/25/2014 A 05/27/2015 A 542InfiltratioInfiltration/Inflow 09/25/2014 A 05/26/2015 A 193
B1000 Infiltration/Inflow Phase 09/25/2014 A 05/26/2015 A 193Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 05/26/2015 A 193
B1005 SSES Phase 09/25/2014 A 05/26/2015 A 193B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 04/22/2015 A 05/15/2015 A 30B1040 Video Review 05/12/2015 A 05/26/2015 A 30
Project CProject Closeout 05/27/2015 A 05/27/2015 A 0B1235 Closeout Phase 05/27/2015 A 05/27/2015 A 0B1260 Project Closed 05/27/2015 A 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
90% PWWMD Permit Review (Force Main)90% CD PM Comments Evaluation Completed
10/16/2015 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed
03/07/2016 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid ConferenceBidders Prepare Bids for SubmittalBids Submittal
Bids Evaluation (MDWASD/PSIP Team)Recommendation for Award Letter
Contract Award (Purchase Order Approval)07/26/2016 A, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction meeting
Pre-Construction MeetingWASD Issues NTP (PO to NTP)
Construction NTPConstruction OperationsSubstantial Completion07/26/2016 A, Designer Construction Support Services
Designer Construction Support Services06/24/2016 A, Construction Close Out
CommissioningPunch List
08/01/2018, Project Closeout
Closeout PhaseFinal Release of Retainage - Construction Contract
Administrative CloseoutProject Closed08/01/2018, Basin 0815
05/27/2015 A, 100142 Basin 0815 Infiltration/Inflow Study and Repairs05/26/2015 A, Infiltration/Inflow
Infiltration/Inflow Phase05/26/2015 A, Sanitary Sewer Evaluation SurveySSES Phase
Issue NTP to SSES ContractorConduct SSESVideo Review05/27/2015 A, Project CloseoutCloseout Phase
Project Closed
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 128 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
100143 Pu100143 Pump Station 0815 Upgrade 05/01/2014 A 08/01/2018 1541PlanningPlanning 05/01/2014 A 01/09/2017 A 19
B0900 Planning Phase 05/01/2014 A 01/09/2017 A 19B0940 Develop Remedial Action Plan (RAP) 05/01/2014 A 05/19/2014 A 7B0950 Develop Preliminary Engineering Report (PER) 05/22/2014 A 01/04/2016 A 10B0960 Recommended Action Memo (RAM) 02/03/2016 A 01/09/2017 A 10
Project CProject Closeout 02/15/2017 A 08/01/2018 532B1445 Closeout Phase 02/15/2017 A 08/01/2018 532B1450 Issue SAC Letter 02/15/2017 A 0B1480 Administrative Closeout 02/16/2017 A 08/01/2018 30B1490 Project Closed 08/01/2018 0
Basin 0819Basin 0819 08/11/2014 A 08/01/2018 1458
100145 Pu100145 Pump Station 0819 Upgrade 08/11/2014 A 08/01/2018 1458DesignDesign 08/11/2014 A 02/09/2016 A 438
B1000 Design Phase 08/11/2014 A 02/09/2016 A 438B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 08/11/2014 A 08/15/2014 A 5B1020 Engage Design Consultant 08/15/2014 A 01/07/2015 A 35B1022 TA Rev 00 - Approval Process 11/24/2014 A 12/30/2014 A 20B1024 TA Rev 01 - Approval Process 05/19/2015 A 05/27/2015 A 20B1026 TA Rev 02 - Approval Process 12/09/2015 A 01/20/2016 A 20B1030 Issue Design NTP 01/07/2015 A 0B1040 A/E Develops and Submits Final Engineering Report 01/07/2015 A 01/21/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 01/07/2015 A 07/01/2015 A 10
30% Des30% Design 01/08/2015 A 03/12/2015 A 48B1060 A/E Prepares 30% Construction Documents 01/08/2015 A 02/20/2015 A 30B1070 Geotechnical Engineering Services 01/08/2015 A 02/20/2015 A 20B1080 Surveying Services 01/08/2015 A 02/20/2015 A 15B1100 30% CDs Submittal 02/20/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 02/20/2015 A 03/12/2015 A 10
60% Des60% Design 02/20/2015 A 04/29/2015 A 42B1130 A/E Prepares 60% Construction Documents 02/20/2015 A 04/10/2015 A 30B1140 60% CDs Submittal 04/10/2015 A 0B1160 60% Review (MDWASD/PSIP Team) 04/13/2015 A 04/29/2015 A 10
90% Des90% Design 04/14/2015 A 01/20/2016 A 309B1170 A/E Prepares 90% Construction Documents 04/14/2015 A 06/15/2015 A 20B1180 90% CDs Submittal 06/15/2015 A 0B1190 90% Review (MDWASD/PSIP Team) 06/16/2015 A 10/19/2015 A 15B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 10/20/2015 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 10/21/2015 A 11/10/2015 A 15B1220 90% RER (Building Dept) Permit Submittal 11/25/2015 A 0B1230 90% RER (Building Dept) Permit Review 11/26/2015 A 01/19/2016 A 15B1260 90% CD PM Comments Evaluation Completed 01/20/2016 A 0
100% De100% Design 01/22/2016 A 02/09/2016 A 24B1270 A/E Prepares 100% Construction Documents 01/22/2016 A 02/09/2016 A 10B1280 100% CDs Submittal 02/09/2016 A 0B1290 100% Review (MDWASD/PSIP Team) 02/09/2016 A 02/09/2016 A 1B1300 Design Completed 02/09/2016 A 0
MDWASDMDWASD Procurement 02/09/2016 A 04/25/2016 A 125B1305 Procurement Phase 02/09/2016 A 04/25/2016 A 125
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
08/01/2018, 100143 Pump Station 0815 Upgrade01/09/2017 A, PlanningPlanning Phase
Develop Remedial Action Plan (RAP)Develop Preliminary Engineering Report (PER)
Recommended Action Memo (RAM)08/01/2018, Project CloseoutCloseout Phase
Issue SAC LetterAdministrative Closeout
Project Closed08/01/2018, Basin 0819
08/01/2018, 100145 Pump Station 0819 Upgrade02/09/2016 A, Design
Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book
Engage Design ConsultantTA Rev 00 - Approval Process
TA Rev 01 - Approval ProcessTA Rev 02 - Approval Process
Issue Design NTPA/E Develops and Submits Final Engineering Report
Final Engineering Report Review & Approval (MDWASD/PSIP Team)03/12/2015 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services
30% CDs Submittal30% Review (MDWASD/PSIP Team)04/29/2015 A, 60% Design
A/E Prepares 60% Construction Documents60% CDs Submittal
60% Review (MDWASD/PSIP Team)01/20/2016 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)90% RER(DERM)FDEP Permit Review (Pump Station)90% RER (Building Dept) Permit Submittal
90% RER (Building Dept) Permit Review90% CD PM Comments Evaluation Completed
02/09/2016 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed
04/25/2016 A, MDWASD Procurement
Procurement Phase
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 129 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1310 Submit CDs to MDWASD Procurement Division 02/09/2016 A 0B1312 Bid Notice Preparation Period 02/09/2016 A 02/17/2016 A 23B1314 Bid Notice 02/17/2016 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 02/18/2016 A 02/22/2016 A 10B1320 Pre-Bid Conference 02/23/2016 A 02/23/2016 A 1B1328 Bidders Prepare Bids for Submittal 02/24/2016 A 03/28/2016 A 15B1330 Bids Submittal 03/28/2016 A 0B1340 MDWASD/PSIP Team Bids Evaluation 03/29/2016 A 04/01/2016 A 15B1350 Recommendation for Award Letter 04/01/2016 A 0B1355 Contract Award (Purchase Order Approval) 04/04/2016 A 04/25/2016 A 10
ConstrucConstruction 02/23/2016 A 10/26/2017 A 999B1360 Construction Phase 02/23/2016 A 10/26/2017 A 999B1362 MDWASD/PSIP Team Prepare for Pre-Construction meeting 04/04/2016 A 04/21/2016 A 15B1364 Pre-Construction Meeting 04/22/2016 A 04/22/2016 A 1B1369 WASD Issues NTP (PO to NTP) 04/26/2016 A 06/19/2016 A 53B1370 Construction NTP 06/20/2016 A 0B1400 Construction Operations 06/20/2016 A 10/26/2017 A 150B1400 Original Construction Duration 06/20/2016 A 11/17/2016 A 150B1400 Change Order #1 - Miami Dade Bldg. Dept. Re-Permitting 11/18/2016 A 02/11/2017 A 150B1400 Change Order #2 - WASD Shut Down FM & FPL 02/12/2017 A 04/20/2017 A 150B1400 Change Order #3 - Hurricane Irma 04/21/2017 A 05/11/2017 A 150B1402 Substantial Completion 10/26/2017 A 0
DesignerDesigner Construction Support Services 02/23/2016 A 10/26/2017 A 291B1410 Designer Construction Support Services 02/23/2016 A 10/26/2017 A 291
Project CProject Closeout 10/27/2017 A 08/01/2018 273B1445 Closeout Phase 10/27/2017 A 08/01/2018 273B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 10/27/2017 A 08/01/2018 120B1490 Project Closed 08/01/2018 0
100250 Ba100250 Basin 0819 Infiltration/Inflow Study and Repairs 05/22/2015 A 10/13/2015 A 29InfiltratioInfiltration/Inflow 05/22/2015 A 10/12/2015 A 20
B1000 Infiltration/Inflow Phase 05/22/2015 A 10/12/2015 A 20CIPP RepCIPP Repairs 05/22/2015 A 10/12/2015 A 20
B1070 CIPP Phase 05/22/2015 A 10/12/2015 A 20B1090 Issue NTP for CIPP Repairs 05/22/2015 A 0B1100 Conduct CIPP Repairs 10/12/2015 A 10/12/2015 A 20
Project CProject Closeout 10/13/2015 A 10/13/2015 A 0B1250 Closeout Phase 10/13/2015 A 10/13/2015 A 0B1280 Project Closed 10/13/2015 A 0
Basin 0836Basin 0836 10/02/2015 A 08/01/2018 1035
100146 Pu100146 Pump Station 0836 Upgrade 10/02/2015 A 08/01/2018 1035DesignDesign 10/02/2015 A 11/11/2016 A 458
B1000 Design Phase 10/02/2015 A 11/11/2016 A 458B1010 Prepare & Submit Design Package 10/02/2015 A 11/04/2015 A 5B1020 Engage Design Consultant 11/05/2015 A 12/04/2015 A 20B1022 TA Preparation 12/07/2015 A 12/07/2015 A 1B1024 TA Approval Process 12/08/2015 A 12/18/2015 A 20B1030 Issue Design NTP 01/06/2016 A 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Submit CDs to MDWASD Procurement DivisionBid Notice Preparation Period
Bid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter
Contract Award (Purchase Order Approval)10/26/2017 A, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction meetingPre-Construction Meeting
WASD Issues NTP (PO to NTP)
Construction NTPConstruction Operations
Original Construction DurationChange Order #1 - Miami Dade Bldg. Dept. Re-Permitting
Change Order #2 - WASD Shut Down FM & FPLChange Order #3 - Hurricane Irma
Substantial Completion10/26/2017 A, Designer Construction Support Services
Designer Construction Support Services08/01/2018, Project Closeout
Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction ContractAdministrative CloseoutProject Closed
10/13/2015 A, 100250 Basin 0819 Infiltration/Inflow Study and Repairs10/12/2015 A, Infiltration/Inflow
Infiltration/Inflow Phase10/12/2015 A, CIPP Repairs
CIPP PhaseIssue NTP for CIPP Repairs
Conduct CIPP Repairs10/13/2015 A, Project Closeout
Closeout PhaseProject Closed
08/01/2018, Basin 0836
08/01/2018, 100146 Pump Station 0836 Upgrade11/11/2016 A, Design
Design PhasePrepare & Submit Design Package
Engage Design ConsultantTA PreparationTA Approval Process
Issue Design NTP
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 130 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1040 A/E Develops and Submits Final Engineering Report 01/06/2016 A 11/11/2016 A 110B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 01/06/2016 A 06/23/2016 A 85
30% Des30% Design 01/06/2016 A 04/08/2016 A 66B1060 A/E Prepares 30% Construction Documents 01/06/2016 A 03/25/2016 A 30B1080 Surveying Services 01/06/2016 A 02/11/2016 A 15B1100 30% CDs Submittal 03/25/2016 A 0B1120 30% Review (MDWASD/PSIP Team) 03/28/2016 A 04/08/2016 A 10
90% Des90% Design 03/28/2016 A 10/26/2016 A 138B1170 A/E Prepares 90% Construction Documents 03/28/2016 A 06/14/2016 A 20B1180 90% CDs Submittal 06/14/2016 A 0B1190 90% Review (MDWASD/PSIP Team) 06/15/2016 A 07/14/2016 A 15B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 07/15/2016 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 07/15/2016 A 09/30/2016 A 15B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 10/18/2016 A 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 10/18/2016 A 10/26/2016 A 15B1260 90% CD PM Comments Evaluation Completed 10/26/2016 A 0
100% De100% Design 10/27/2016 A 11/09/2016 A 32B1270 A/E Prepares 100% Construction Documents 10/27/2016 A 11/09/2016 A 10B1280 100% CDs Submittal 11/09/2016 A 0B1290 100% Review (MDWASD/PSIP Team) 10/27/2016 A 11/09/2016 A 10B1300 Design Completed 11/09/2016 A 0
MDWASDMDWASD Procurement 11/14/2016 A 04/06/2017 A 88B1305 Procurement Phase 11/14/2016 A 04/06/2017 A 88B1310 Submit CDs to MDWASD Procurement Division 11/14/2016 A 0B1312 Bid Notice Preparation Period 11/15/2016 A 11/29/2016 A 11B1314 Bid Notice 11/29/2016 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 11/30/2016 A 12/13/2016 A 10B1320 Pre-Bid Conference 12/14/2016 A 12/14/2016 A 1B1322 Bidders Prepare Bids for Submittal 12/15/2016 A 01/12/2017 A 21B1330 Bids Submittal 01/12/2017 A 0B1340 MDWASD/PSIP Team Bids Evaluation 01/13/2017 A 01/31/2017 A 15B1350 Recommendation for Award Letter 01/31/2017 A 0B1355 Contract Award (Purchase Order Approval) 02/01/2017 A 04/06/2017 A 10
ConstrucConstruction 12/14/2016 A 12/27/2017 A 375B1360 Construction Phase 12/14/2016 A 12/27/2017 A 375B1364 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 02/01/2017 A 03/14/2017 A 15B1366 Pre-Construction Meeting 03/15/2017 A 03/15/2017 A 1B1368 WASD Issues NTP (Pre-Const to NTP) 03/16/2017 A 07/21/2017 A 91B1369 WASD Issues NTP (PO to NTP) 04/06/2017 A 07/21/2017 A 91B1370 Construction NTP 07/24/2017 A 0B1400 Construction Operations 07/24/2017 A 12/27/2017 A 153B1402 Substantial Completion 12/27/2017 A 0
DesignerDesigner Construction Support Services 12/14/2016 A 12/26/2017 A 262B1410 Designer Construction Support Services 12/14/2016 A 12/26/2017 A 262
Project CProject Closeout 12/28/2017 A 08/01/2018 202B1445 Closeout Phase 12/28/2017 A 08/01/2018 202B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 12/28/2017 A 08/01/2018 120
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
04/08/2016 A, 30% Design
A/E Prepares 30% Construction DocumentsSurveying Services
30% CDs Submittal30% Review (MDWASD/PSIP Team)
10/26/2016 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)
90% RER(DERM)FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)90% RER(Building Dept) Permit Review (Pump Station)90% CD PM Comments Evaluation Completed11/09/2016 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal
100% Review (MDWASD/PSIP Team)Design Completed
04/06/2017 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter
Contract Award (Purchase Order Approval)12/27/2017 A, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Construction NTPConstruction OperationsSubstantial Completion
12/26/2017 A, Designer Construction Support Services
Designer Construction Support Services08/01/2018, Project Closeout
Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction ContractAdministrative Closeout
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 131 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1490 Project Closed 08/01/2018 0
Basin 0840Basin 0840 05/04/2016 A 11/29/2018 929
100147 Pu100147 Pump Station 0840 (AM) Upgrade 05/04/2016 A 11/29/2018 929DesignDesign 05/04/2016 A 12/18/2017 A 601
B1000 Design Phase 05/04/2016 A 12/18/2017 A 601B1010 Prepare and Submit Design Package 05/04/2016 A 05/04/2016 A 5B1020 Engage Design Consultant 05/04/2016 A 06/28/2016 A 20B1022 TA Preparation 06/29/2016 A 07/14/2016 A 1B1024 TA Approval Process 07/15/2016 A 09/21/2016 A 20B1030 Issue Design NTP 09/27/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 09/27/2016 A 11/22/2017 A 103
30% Des30% Design 09/27/2016 A 01/19/2017 A 121B1060 A/E Prepares 30% Construction Documents 09/27/2016 A 12/20/2016 A 50B1100 30% CDs Submittal 12/20/2016 A 0B1120 30% Review (MDWASD/PSIP Team) 12/21/2016 A 01/19/2017 A 30
90% Des90% Design 12/21/2016 A 11/22/2017 A 364B1170 A/E Prepares 90% Construction Documents 12/21/2016 A 05/01/2017 A 62B1180 90% CDs Submittal 05/01/2017 A 0B1190 90% Review (MDWASD/PSIP Team) 05/02/2017 A 05/22/2017 A 30B1191 PSIP Prepared Memorandum with Recommendation for WASD 03/29/2017 A 04/16/2017 A 60B1192 TA Rev 1 Preparation 04/17/2017 A 04/17/2017 A 1B1193 TA Rev 1 Approval Process 04/18/2017 A 05/31/2017 A 40B1200 90% RER(DERM)/FDEP Permit Submittal (Force Main) 07/17/2017 A 0B1210 90% RER(DERM)/FDEP Permit Review (Force Main) 07/17/2017 A 11/22/2017 A 45B1260 90% CD PM Comments Evaluation Completed 11/22/2017 A 0B1262 MDWASD Union Concurrence Process 06/28/2017 A 07/17/2017 A 30
100% De100% Design 11/23/2017 A 12/18/2017 A 24B1270 A/E Prepares 100% Construction Documents 11/23/2017 A 12/18/2017 A 14B1280 100% CDs Submittal 12/18/2017 A 0B1290 100% Review (MDWASD/PSIP Team) 12/18/2017 A 12/18/2017 A 14B1300 Design Completed 12/18/2017 A 0
MDWASDMDWASD Procurement 12/19/2017 A 05/15/2018 A 96B1305 Procurement Phase 12/19/2017 A 05/15/2018 A 96B1310 Submit CDs to MDWASD Procurement Division 12/19/2017 A 0B1312 Bid Notice Preparation Period 12/20/2017 A 01/18/2018 A 33B1314 Bid Notice 01/18/2018 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conferencce 01/19/2018 A 01/29/2018 A 14B1320 Pre-Bid Conference 01/30/2018 A 01/30/2018 A 1B1324 Bidders Prepare Bids for Submittal 01/31/2018 A 03/02/2018 A 21B1330 Bids Submittal 03/02/2018 A 0B1340 MDWASD/PSIP Team Bids Evaluation 03/03/2018 A 03/29/2018 A 21B1350 Recommendation for Award Letter 03/29/2018 A 0B1355 Contract Award (Purchase Order Approval) 03/30/2018 A 05/15/2018 A 14
ConstrucConstruction 01/30/2018 A 08/02/2018 317B1360 Construction Phase 01/30/2018 A 08/02/2018 317B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 03/30/2018 A 05/09/2018 A 33B1365 Pre-Construction Meeting 05/10/2018 A 05/10/2018 A 1B1366 WASD Issues NTP (Pre-Const to NTP) 05/11/2018 A 08/01/2018 38B1369 WASD Issues NTP (PO to NTP) 05/15/2018 A 08/01/2018 53
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Project Closed11/29/2018, Basin 0840
11/29/2018, 100147 Pump Station 0840 (AM) Upgr12/18/2017 A, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval ProcessIssue Design NTP
Final Engineering Report Review & Approval (MDWASD/PSIP Team)01/19/2017 A, 30% Design
A/E Prepares 30% Construction Documents30% CDs Submittal
30% Review (MDWASD/PSIP Team)11/22/2017 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)PSIP Prepared Memorandum with Recommendation for WASD ApprovalTA Rev 1 Preparation
TA Rev 1 Approval Process
90% RER(DERM)/FDEP Permit Submittal (Force Main)90% RER(DERM)/FDEP Permit Review (Force Main)
90% CD PM Comments Evaluation CompletedMDWASD Union Concurrence Process
12/18/2017 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal
100% Review (MDWASD/PSIP Team)Design Completed
05/15/2018 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferenccePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter
Contract Award (Purchase Order Approval)08/02/2018, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 132 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1370 Construction NTP 08/02/2018 0B1400 Construction Operations 08/02/2018 08/02/2018 0B1402 Substantial Completion 08/02/2018 0
DesignerDesigner Construction Support Services 01/30/2018 A 08/01/2018 302B1410 Designer Construction Support Services 01/30/2018 A 08/01/2018 302
Project CProject Closeout 08/02/2018 11/29/2018 120B1445 Closeout Phase 08/02/2018 11/29/2018 120B1450 Issue SAC Letter 08/02/2018 0B1470 Final Release of Retainage - Construction Contract 08/02/2018 0B1480 Administrative Closeout 08/02/2018 11/29/2018 120B1490 Project Closed 11/29/2018 0
Basin 0842Basin 0842 04/02/2014 A 08/01/2018 1682
100149 Pu100149 Pump Station 0842 Upgrade 04/02/2014 A 08/01/2018 1682DesignDesign 04/02/2014 A 06/12/2015 A 411
B1000 Design Phase 04/02/2014 A 06/12/2015 A 411B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 04/02/2014 A 04/02/2014 A 5B1020 Engage Design Consultant 04/03/2014 A 11/19/2014 A 20B1030 Issue Design NTP 11/20/2014 A 0B1040 A/E Develops and Submits Final Engineering Report 11/20/2014 A 05/29/2015 A 20B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 11/20/2014 A 03/25/2015 A 5
30% Des30% Design 11/20/2014 A 01/23/2015 A 128B1060 A/E Prepares 30% Construction Documents 11/20/2014 A 01/14/2015 A 30B1070 Geotechnical Engineering Services 11/20/2014 A 12/16/2014 A 20B1080 Surveying Services 11/20/2014 A 12/17/2014 A 15B1090 30% CDs Submittal 01/14/2015 A 0B1100 30% Review (MDWASD/PSIP Team) 01/15/2015 A 01/23/2015 A 10
90% Des90% Design 01/15/2015 A 06/05/2015 A 86B1110 A/E Prepares 90% Construction Documents 01/15/2015 A 03/06/2015 A 20B1120 90% CDs Submittal 03/06/2015 A 0B1130 90% Review (MDWASD/PSIP Team) 03/09/2015 A 03/25/2015 A 15B1131 Permit Set Revisions 03/26/2015 A 04/10/2015 A 5B1140 90% RER(DERM)FDEP Permit Submittal (Pump Station) 04/13/2015 A 0B1150 90% RER(DERM)FDEP Permit Review (Pump Station) 04/13/2015 A 04/20/2015 A 15B1160 90% RER (Building Department) Permit Submittal 04/23/2015 A 0B1170 90% RER (Building Department) Permit Review 04/23/2015 A 06/05/2015 A 15B1200 90% CD PM Comments Evaluation Completed 06/05/2015 A 0
100% De100% Design 03/26/2015 A 06/12/2015 A 12B1210 A/E Prepares 100% Construction Documents 03/26/2015 A 04/10/2015 A 10B1220 100% CDs Submittal 04/10/2015 A 0B1230 100% Review (MDWASD/PSIP Team) 04/13/2015 A 04/24/2015 A 10B1240 Design Completed 06/12/2015 A 0
MDWASDMDWASD Procurement 05/01/2015 A 07/24/2015 A 64B1245 Procurement Phase 05/01/2015 A 07/24/2015 A 64B1250 Submit CDs to MDWASD Procurement Division 05/01/2015 A 0B1260 Pre-Bid Conference 05/15/2015 A 0B1270 Bids Submittal 06/19/2015 A 0B1280 MDWASD/PSIP Team Bids Evaluation 06/22/2015 A 06/23/2015 A 15B1290 Recommendation for Award Letter 06/23/2015 A 0B1295 Contract Award (Purchase Order Approval) 06/23/2015 A 07/24/2015 A 10
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Construction NTPConstruction OperationsSubstantial Completion08/01/2018, Designer Construction Support Services
Designer Construction Support Services11/29/2018, Project CloseoutCloseout Phase
Issue SAC LetterFinal Release of Retainage - Construction Contract
Administrative CloseoutProject Closed
08/01/2018, Basin 0842
08/01/2018, 100149 Pump Station 0842 Upgrade06/12/2015 A, Design
Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book
Engage Design ConsultantIssue Design NTP
A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
01/23/2015 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services
30% CDs Submittal30% Review (MDWASD/PSIP Team)
06/05/2015 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)Permit Set Revisions90% RER(DERM)FDEP Permit Submittal (Pump Station)90% RER(DERM)FDEP Permit Review (Pump Station)90% RER (Building Department) Permit Submittal
90% RER (Building Department) Permit Review90% CD PM Comments Evaluation Completed06/12/2015 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal
100% Review (MDWASD/PSIP Team)Design Completed
07/24/2015 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Pre-Bid ConferenceBids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter
Contract Award (Purchase Order Approval)
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 133 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
ConstrucConstruction 05/15/2015 A 08/19/2016 A 1251B1300 Construction Phase 05/15/2015 A 08/19/2016 A 1251B1302 MDWASD / PSIP Team Prepare for Pre-Construction Meeting 06/24/2015 A 07/10/2015 A 15B1304 Pre-Construction Meeting 07/13/2015 A 07/13/2015 A 1B1306 Permits / Shop Drawings / Material Orders 07/14/2015 A 11/20/2015 A 15B1308 WASD Issues NTP (PO to NTP) 07/25/2015 A 08/02/2015 A 53B1310 Construction NTP 08/03/2015 A 0B1340 Construction Operations 08/03/2015 A 02/05/2016 A 107B1340 Original Construction Duration 08/03/2015 A 12/31/2015 A 107B1340 Change Order #1 - Utility Conflict Impeding Wet Well Installation 01/01/2016 A 01/21/2016 A 107B1342 Substantial Completion 02/05/2016 A 0
DesignerDesigner Construction Services 05/15/2015 A 08/19/2016 A 146B1350 Designer Construction Support Services 05/15/2015 A 08/19/2016 A 146
ConstrucConstruction Close Out 02/08/2016 A 07/21/2016 A 15B1360 Commissioning 02/08/2016 A 07/21/2016 A 15B1370 Punch List 02/08/2016 A 07/21/2016 A 10
Project CProject Closeout 09/23/2015 A 08/01/2018 1043B1385 Closeout Phase 09/23/2015 A 08/01/2018 1043B1390 Issue SAC Letter 09/23/2015 A 0B1392 Contracctor Prepare Remedial Action Plan - Property Encroachm 02/08/2016 A 07/21/2016 A 30B1420 Final Release of Retainage - Construction Contract 02/23/2017 A 0B1422 Administrative Closeout 02/08/2016 A 08/01/2018 120B1430 Project Closed 08/01/2018 0
100243 Ba100243 Basin 0842 Infiltration/Inflow Study and Repairs 05/22/2015 A 07/28/2015 A 29InfiltratioInfiltration/Inflow 05/22/2015 A 07/28/2015 A 29
B1000 Infiltration/Inflow Phase 05/22/2015 A 07/28/2015 A 29CIPP RepCIPP Repairs 05/22/2015 A 07/28/2015 A 29
B1070 CIPP Phase 05/22/2015 A 07/28/2015 A 29B1090 Issue NTP for CIPP Repairs 05/22/2015 A 0B1100 Conduct CIPP Repairs 07/28/2015 A 07/28/2015 A 29
Project CProject Closeout 07/28/2015 A 07/28/2015 A 0B1250 Closeout Phase 07/28/2015 A 07/28/2015 A 0B1280 Project Closed 07/28/2015 A 0
Basin 0843Basin 0843 01/14/2016 A 08/31/2018 942
100150 Pu100150 Pump Station 0843 Upgrade 01/14/2016 A 08/31/2018 942DesignDesign 01/14/2016 A 05/02/2017 A 487
B1000 Design Phase 01/14/2016 A 05/02/2017 A 487B1010 Prepare and Submit Design Package 01/14/2016 A 01/14/2016 A 5B1020 Engage Design Consultant 01/15/2016 A 04/22/2016 A 20B1022 TA Preparation 04/25/2016 A 04/25/2016 A 1B1024 TA Approval Process 04/26/2016 A 06/01/2016 A 20B1030 Issue Design NTP 06/07/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 06/07/2016 A 04/21/2017 A 85
30% Des30% Design 06/07/2016 A 09/29/2016 A 134B1060 A/E Prepares 30% Construction Documents 06/08/2016 A 08/17/2016 A 30B1070 Geotechnical Engineering Services 06/07/2016 A 08/17/2016 A 20B1080 Surveying Services 06/08/2016 A 08/17/2016 A 15B1100 30% CDs Submittal 08/18/2016 A 0B1120 30% Review (MDWASD/PSIP Team) 08/19/2016 A 09/29/2016 A 10
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
08/19/2016 A, Construction
Construction PhaseMDWASD / PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
Permits / Shop Drawings / Material OrdersWASD Issues NTP (PO to NTP)
Construction NTPConstruction Operations
Original Construction DurationChange Order #1 - Utility Conflict Impeding Wet Well Installation
Substantial Completion08/19/2016 A, Designer Construction Services
Designer Construction Support Services07/21/2016 A, Construction Close Out
CommissioningPunch List
08/01/2018, Project Closeout
Closeout PhaseIssue SAC Letter
Contracctor Prepare Remedial Action Plan - Property Encroachment
Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed
07/28/2015 A, 100243 Basin 0842 Infiltration/Inflow Study and Repairs07/28/2015 A, Infiltration/InflowInfiltration/Inflow Phase07/28/2015 A, CIPP Repairs
CIPP PhaseIssue NTP for CIPP Repairs
Conduct CIPP Repairs07/28/2015 A, Project Closeout
Closeout PhaseProject Closed
08/31/2018, Basin 0843
08/31/2018, 100150 Pump Station 0843 Upgrade05/02/2017 A, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval ProcessIssue Design NTP
Final Engineering Report Review & Approval (MDWASD/PSIP Team)09/29/2016 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services
30% CDs Submittal30% Review (MDWASD/PSIP Team)
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 134 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
60% Des60% Design 09/30/2016 A 11/08/2016 A 34B1130 A/E Prepares 60% Construction Documents 09/30/2016 A 10/21/2016 A 20B1140 60% CDs Submittal 10/21/2016 A 0B1160 60% Review (MDWASD/PSIP Team) 10/24/2016 A 11/08/2016 A 10
90% Des90% Design 10/24/2016 A 04/21/2017 A 214B1170 A/E Prepares 90% Construction Documents 10/24/2016 A 11/30/2016 A 20B1180 90% CDs Submittal 11/30/2016 A 0B1190 90% Review (MDWASD/PSIP Team) 12/01/2016 A 12/23/2016 A 15B1200 90% RER(DERM)FDEP Permit Submittal 01/31/2017 A 0B1210 90% RER(DERM)FDEP Permit Review 01/31/2017 A 04/07/2017 A 45B1220 90% RER(Building Dept) Permit Submittal 04/12/2017 A 0B1230 90% RER(Building Dept) Permit Review 04/12/2017 A 04/21/2017 A 21B1260 90% CD PM Comments Evaluation Completed 04/21/2017 A 0B1262 MDWASD Union Concurrence Process 01/27/2017 A 03/07/2017 A 30
100% De100% Design 04/24/2017 A 05/02/2017 A 30B1270 A/E Prepares 100% Construction Documents 04/24/2017 A 05/01/2017 A 10B1280 100% CDs Submittal 05/01/2017 A 0B1290 100% Review (MDWASD/PSIP Team) 05/02/2017 A 05/02/2017 A 1B1300 Design Completed 05/02/2017 A 0
MDWASDMDWASD Procurement 05/02/2017 A 08/24/2017 A 55B1305 Procurement Phase 05/02/2017 A 08/24/2017 A 55B1310 Submit CDs to MDWASD Procurement Division 05/02/2017 A 0B1312 Bid Notice Preparation Period 05/03/2017 A 05/11/2017 A 23B1314 Bid Notice 05/11/2017 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 05/12/2017 A 05/22/2017 A 10B1320 Pre-Bid Conference 05/23/2017 A 05/23/2017 A 1B1322 Bidders Prepare Bids for Submittal 05/24/2017 A 06/23/2017 A 15B1330 Bids Submittal 06/23/2017 A 0B1340 MDWASD/PSIP Team Bids Evaluation 06/26/2017 A 07/17/2017 A 15B1350 Recommendation for Award Letter 07/17/2017 A 0B1355 Contract Award (Purchase Order Approval) 07/18/2017 A 08/24/2017 A 10
ConstrucConstruction 05/23/2017 A 08/01/2018 426B1360 Construction Phase 05/23/2017 A 08/01/2018 426B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 07/18/2017 A 10/10/2017 A 15B1364 Pre-Construction Meeting 10/11/2017 A 10/11/2017 A 1B1366 WASD Issues NTP (Pre-Const to NTP) 10/12/2017 A 01/01/2018 A 45B1368 WASD Issues NTP (PO to NTP) 08/24/2017 A 01/01/2018 A 45B1370 Construction NTP 01/02/2018 A 0B1400 Construction Operations 01/02/2018 A 08/01/2018 190B1402 Substantial Completion 08/01/2018 0
DesignerDesigner Construction Support Services 05/23/2017 A 08/01/2018 260B1410 Designer Construction Support Services 05/23/2017 A 08/01/2018 260
Project CProject Closeout 08/01/2018 08/31/2018 31B1445 Closeout Phase 08/01/2018 08/31/2018 31B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 08/02/2018 08/31/2018 30B1490 Project Closed 08/31/2018 0
Basin 0853Basin 0853 03/19/2014 A 08/01/2018 1581
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
11/08/2016 A, 60% Design
A/E Prepares 60% Construction Documents60% CDs Submittal60% Review (MDWASD/PSIP Team)
04/21/2017 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal
90% RER(DERM)FDEP Permit Review90% RER(Building Dept) Permit Submittal90% RER(Building Dept) Permit Review90% CD PM Comments Evaluation Completed
MDWASD Union Concurrence Process05/02/2017 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal
100% Review (MDWASD/PSIP Team)Design Completed
08/24/2017 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid Notice
MDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter
Contract Award (Purchase Order Approval)08/01/2018, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Construction NTPConstruction OperationsSubstantial Completion08/01/2018, Designer Construction Support Services
Designer Construction Support Services08/31/2018, Project Closeout
Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction Contract
Administrative CloseoutProject Closed
08/01/2018, Basin 0853
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 135 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
100151 Ba100151 Basin 0853 Infiltration/Inflow Study and Repairs 06/26/2015 A 11/25/2015 A 240InfiltratioInfiltration/Inflow 06/26/2015 A 11/24/2015 A 30
B1000 Infiltration/Inflow Phase 06/26/2015 A 11/24/2015 A 30Dig & ReDig & Replace Repairs 06/26/2015 A 11/24/2015 A 30
B1165 Dig & Replace Phase 06/26/2015 A 11/24/2015 A 30B1180 Issue NTP for Dig & Replace Repairs 06/26/2015 A 0B1190 Conduct Dig & Replace Repairs 11/24/2015 A 11/24/2015 A 30
Project CProject Closeout 11/25/2015 A 11/25/2015 A 0B1235 Closeout Phase 11/25/2015 A 11/25/2015 A 0B1260 Project Closed 11/25/2015 A 0
100152 Pu100152 Pump Station 0853 Upgrade 03/19/2014 A 08/01/2018 792DesignDesign 03/19/2014 A 12/04/2017 A 63
B1000 Design Phase 03/19/2014 A 12/04/2017 A 63B1012 RAP - Remedial Action Plan 03/19/2014 A 05/20/2014 A 63B1014 SAC Period 05/21/2014 A 12/04/2017 A 63
Project CProject Closeout 12/06/2017 A 08/01/2018 792B1445 Closeout Phase 12/06/2017 A 08/01/2018 792B1450 Issue SAC Letter 12/29/2017 A 0B1480 Administrative Closeout 12/06/2017 A 08/01/2018 120B1490 Project Closed 08/01/2018 0
Basin 0860Basin 0860 09/25/2014 A 08/01/2018 1535
100153 Ba100153 Basin 0860 Infiltration/Inflow Study and Repairs 09/25/2014 A 04/22/2016 A 632InfiltratioInfiltration/Inflow 09/25/2014 A 04/21/2016 A 624
B1000 Infiltration/Inflow Phase 09/25/2014 A 04/21/2016 A 624Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 07/16/2015 A 282
B1005 SSES Phase 09/25/2014 A 07/16/2015 A 282B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 06/17/2015 A 07/16/2015 A 30
ManholeManhole Repairs 03/25/2016 A 04/21/2016 A 112B1115 Manhole Phase 03/25/2016 A 04/21/2016 A 112B1130 Issue NTP for Manhole Repairs 03/25/2016 A 0B1140 Conduct Manhole Repairs 04/13/2016 A 04/21/2016 A 20
Project CProject Closeout 04/22/2016 A 04/22/2016 A 0B1235 Closeout Phase 04/22/2016 A 04/22/2016 A 0B1260 Project Closed 04/22/2016 A 0
100154 Pu100154 Pump Station 0860 Upgrade 12/08/2014 A 08/01/2018 1458DesignDesign 12/08/2014 A 02/09/2016 A 456
B1000 Design Phase 12/08/2014 A 02/09/2016 A 456B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 12/08/2014 A 12/19/2014 A 5B1020 Engage Design Consultant 12/22/2014 A 03/24/2015 A 20B1030 Issue Design NTP 03/24/2015 A 0B1040 A/E Develops and Submits Final Engineering Report 03/24/2015 A 02/02/2016 A 125B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 03/24/2015 A 12/21/2015 A 10
30% Des30% Design 03/25/2015 A 06/15/2015 A 87B1060 A/E Prepares 30% Construction Documents 03/25/2015 A 06/08/2015 A 30B1070 Geotechnical Engineering Services 03/25/2015 A 06/08/2015 A 20B1080 Surveying Services 03/25/2015 A 06/08/2015 A 15B1100 30% CDs Submittal 06/08/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 06/09/2015 A 06/15/2015 A 10
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
11/25/2015 A, 100151 Basin 0853 Infiltration/Inflow Study and Repairs11/24/2015 A, Infiltration/Inflow
Infiltration/Inflow Phase11/24/2015 A, Dig & Replace RepairsDig & Replace Phase
Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs11/25/2015 A, Project CloseoutCloseout Phase
Project Closed08/01/2018, 100152 Pump Station 0853 Upgrade
12/04/2017 A, Design
Design PhaseRAP - Remedial Action Plan
SAC Period08/01/2018, Project CloseoutCloseout Phase
Issue SAC LetterAdministrative CloseoutProject Closed08/01/2018, Basin 0860
04/22/2016 A, 100153 Basin 0860 Infiltration/Inflow Study and Repairs04/21/2016 A, Infiltration/Inflow
Infiltration/Inflow Phase07/16/2015 A, Sanitary Sewer Evaluation SurveySSES Phase
Issue NTP to SSES ContractorConduct SSES
04/21/2016 A, Manhole RepairsManhole Phase
Issue NTP for Manhole RepairsConduct Manhole Repairs04/22/2016 A, Project CloseoutCloseout Phase
Project Closed08/01/2018, 100154 Pump Station 0860 Upgrade
02/09/2016 A, Design
Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book
Engage Design ConsultantIssue Design NTP
A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
06/15/2015 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal30% Review (MDWASD/PSIP Team)
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 136 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
90% Des90% Design 06/09/2015 A 02/02/2016 A 253B1170 A/E Prepares 90% Construction Documents 06/09/2015 A 09/24/2015 A 20B1180 90% CDs Submittal 09/25/2015 A 0B1190 90% Review (MDWASD/PSIP Team) 09/28/2015 A 12/21/2015 A 15B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 12/22/2015 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 12/23/2015 A 01/07/2016 A 15B1220 90% RER (Building Dept) Permit Submittal 01/08/2016 A 0B1230 90% RER (Building Dept) Permit Review 01/08/2016 A 02/02/2016 A 15B1260 90% CD PM Comments Evaluation Completed 02/02/2016 A 0
100% De100% Design 02/03/2016 A 02/09/2016 A 28B1270 A/E Prepares 100% Construction Documents 02/03/2016 A 02/05/2016 A 10B1280 100% CDs Submittal 02/05/2016 A 0B1290 100% Review (MDWASD/PSIP Team) 02/08/2016 A 02/09/2016 A 10B1300 Design Completed 02/09/2016 A 0
MDWASDMDWASD Procurement 02/10/2016 A 06/21/2016 A 111B1305 Procurement Phase 02/10/2016 A 06/21/2016 A 111B1310 Submit CDs to MDWASD Procurement Division 02/10/2016 A 0B1312 Bid Notice Preparation Period 02/11/2016 A 03/11/2016 A 23B1314 Bid Notice 03/11/2016 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 03/14/2016 A 03/22/2016 A 10B1320 Pre-Bid Conference 03/22/2016 A 03/22/2016 A 1B1328 Bidders Prepare Bids for Submittal 03/23/2016 A 04/08/2016 A 15B1330 Bids Submittal 04/11/2016 A 0B1340 MDWASD/PSIP Team Bids Evaluation 04/12/2016 A 04/22/2016 A 15B1350 Recommendation for Award Letter 04/22/2016 A 0B1355 Contract Award (Purchase Order Approval) 04/25/2016 A 06/21/2016 A 10
ConstrucConstruction 03/22/2016 A 07/11/2017 A 995B1360 Construction Phase 03/22/2016 A 07/11/2017 A 995B1362 MDWASD/PSIP Team Prepare for Pre-Construction meeting 04/25/2016 A 05/04/2016 A 15B1364 Pre-Construction Meeting 05/05/2016 A 05/05/2016 A 1B1369 WASD Issues NTP (PO to NTP) 06/22/2016 A 08/21/2016 A 53B1370 Construction NTP 08/22/2016 A 0B1400 Construction Operations 08/22/2016 A 07/11/2017 A 120B1400 Original Construction Duration 08/22/2016 A 12/20/2016 A 120B1400 Change Order #1 - Bid Plans Error Relocating FPL Equipment 12/21/2016 A 04/19/2017 A 120B1400 Change Order #2 - Use of Commercial Diving Company 04/20/2017 A 05/03/2017 A 120B1400 Change Order #3 - Unforeseen FPL Utility 05/04/2017 A 05/08/2017 A 120B1400 Change Order #4 - Inoperable Pump Station Plug Valve 05/09/2017 A 05/29/2017 A 120B1400 Change Order #5 - FPL 05/30/2017 A 07/02/2017 A 120B1400 Change Order #6 - Unforeseen Weather Condition 07/03/2017 A 07/09/2017 A 120B1402 Substantial Completion 07/11/2017 A 0
DesignerDesigner Construction Support Services 03/22/2016 A 07/11/2017 A 275B1410 Designer Construction Support Services 03/22/2016 A 07/11/2017 A 275
Project CProject Closeout 07/12/2017 A 08/01/2018 366B1445 Closeout Phase 07/12/2017 A 08/01/2018 366B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 07/12/2017 A 08/01/2018 120B1490 Project Closed 08/01/2018 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
02/02/2016 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)90% RER(DERM)FDEP Permit Review (Pump Station)
90% RER (Building Dept) Permit Submittal90% RER (Building Dept) Permit Review
90% CD PM Comments Evaluation Completed02/09/2016 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal
100% Review (MDWASD/PSIP Team)Design Completed
06/21/2016 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)
07/11/2017 A, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction meetingPre-Construction Meeting
WASD Issues NTP (PO to NTP)
Construction NTPConstruction Operations
Original Construction DurationChange Order #1 - Bid Plans Error Relocating FPL EquipmentChange Order #2 - Use of Commercial Diving CompanyChange Order #3 - Unforeseen FPL Utility
Change Order #4 - Inoperable Pump Station Plug ValveChange Order #5 - FPLChange Order #6 - Unforeseen Weather Condition
Substantial Completion07/11/2017 A, Designer Construction Support Services
Designer Construction Support Services08/01/2018, Project Closeout
Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction ContractAdministrative CloseoutProject Closed
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 137 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
Basin 0870Basin 0870 07/06/2015 A 10/24/2018 1178
100155 Pu100155 Pump Station 0870 Upgrade 07/06/2015 A 10/24/2018 1178DesignDesign 07/06/2015 A 02/22/2017 A 555
B1000 Design Phase 07/06/2015 A 02/22/2017 A 555B1010 Prepare and Submit Design Package 07/06/2015 A 07/06/2015 A 5B1020 Engage Design Consultant 07/06/2015 A 09/21/2015 A 20B1022 TA Preparation 09/22/2015 A 09/22/2015 A 1B1024 TA Approval Process 09/23/2015 A 10/27/2015 A 20B1030 Issue Design NTP 10/30/2015 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/30/2015 A 08/25/2016 A 110
30% Des30% Design 10/30/2015 A 01/04/2016 A 52B1060 A/E Prepares 30% Construction Documents 10/30/2015 A 12/21/2015 A 30B1070 Geotechnical Engineering Services 10/30/2015 A 12/21/2015 A 29B1080 Surveying Services 10/30/2015 A 12/21/2015 A 18B1100 30% CDs Submittal 12/21/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 12/22/2015 A 01/04/2016 A 10
60% Des60% Design 12/22/2015 A 03/30/2016 A 105B1130 A/E Prepares 60% Construction Documents 12/22/2015 A 03/04/2016 A 20B1140 60% CDs Submittal 03/04/2016 A 0B1160 60% Review (MDWASD/PSIP Team) 03/07/2016 A 03/30/2016 A 10
90% Des90% Design 03/07/2016 A 02/22/2017 A 311B1170 A/E Prepares 90% Construction Documents 03/07/2016 A 07/29/2016 A 20B1180 90% CDs Submittal 07/29/2016 A 0B1190 90% Review (MDWASD/PSIP Team) 07/29/2016 A 08/25/2016 A 15B1200 90% RER(DERM)FDEP Permit Submittal 10/11/2016 A 0B1210 90% RER(DERM)FDEP Permit Review 10/11/2016 A 11/22/2016 A 15B1220 90% RER(Building Dept) Permit Submittal 12/01/2016 A 0B1230 90% RER(Building Dept) Permit Review 12/01/2016 A 12/16/2016 A 15B1240 90% PWWMD Permit Submittal 12/16/2016 A 0B1250 90% PWWMD Permit Review 12/16/2016 A 01/09/2017 A 15B1260 90% CD PM Comments Evaluation Completed 01/09/2017 A 0B1262 MDWASD Union Concurrence Process 01/10/2017 A 02/22/2017 A 30
100% De100% Design 01/10/2017 A 01/11/2017 A 2B1270 A/E Prepares 100% Construction Documents 01/10/2017 A 01/10/2017 A 1B1280 100% CDs Submittal 01/10/2017 A 0B1290 100% Review (MDWASD/PSIP Team) 01/11/2017 A 01/11/2017 A 1B1300 Design Completed 01/11/2017 A 0
MDWASDMDWASD Procurement 02/22/2017 A 07/25/2017 A 116B1305 Procurement Phase 02/22/2017 A 07/25/2017 A 116B1310 Submit CDs to MDWASD Procurement Division 02/22/2017 A 0B1312 Bid Notice Preparation Period 02/23/2017 A 03/02/2017 A 23B1314 Bid Notice 03/02/2017 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 03/03/2017 A 03/08/2017 A 10B1320 Pre-Bid Conference 03/09/2017 A 03/09/2017 A 1B1328 Bidders Prepare Bids for Submittal 03/10/2017 A 04/06/2017 A 15B1330 Bids Submittal 04/06/2017 A 0B1340 MDWASD/PSIP Team Bids Evaluation 04/07/2017 A 04/25/2017 A 15B1350 Recommendation for Award Letter 04/25/2017 A 0B1355 Contract Award (Purchase Order Approval) 04/26/2017 A 07/25/2017 A 10
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
10/24/2018, Basin 0870
10/24/2018, 100155 Pump Station 0870 Upgrade02/22/2017 A, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval ProcessIssue Design NTP
Final Engineering Report Review & Approval (MDWASD/PSIP Team)01/04/2016 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services
30% CDs Submittal30% Review (MDWASD/PSIP Team)03/30/2016 A, 60% Design
A/E Prepares 60% Construction Documents60% CDs Submittal
60% Review (MDWASD/PSIP Team)02/22/2017 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal
90% RER(DERM)FDEP Permit Review90% RER(Building Dept) Permit Submittal90% RER(Building Dept) Permit Review90% PWWMD Permit Submittal
90% PWWMD Permit Review90% CD PM Comments Evaluation Completed
MDWASD Union Concurrence Process01/11/2017 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed
07/25/2017 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation Period
Bid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter
Contract Award (Purchase Order Approval)
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 138 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
ConstrucConstruction 03/09/2017 A 06/26/2018 A 417B1360 Construction Phase 03/09/2017 A 06/26/2018 A 417B1364 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 04/26/2017 A 06/23/2017 A 15B1366 Pre-Construction Meeting 06/27/2017 A 06/27/2017 A 1B1368 WASD Issues NTP (Pre-Const to NTP) 06/27/2017 A 07/28/2017 A 4B1369 WASD Issues NTP (PO to NTP) 07/25/2017 A 07/28/2017 A 45B1370 Construction NTP 07/31/2017 A 0B1400 Construction Operations 07/31/2017 A 06/26/2018 A 150B1400 Original Construction Duration 07/31/2017 A 12/28/2017 A 150B1400 Change order #1 - Hurricane Irma and FPL 12/29/2017 A 03/01/2018 A 150B1400 Change order #2 - Miami Dade Public Work Dept. MOT Permit A 03/02/2018 A 05/24/2018 A 150B1402 Substantial Completion 06/26/2018 A 0
DesignerDesigner Construction Support Services 03/09/2017 A 06/26/2018 A 260B1410 Designer Construction Support Services 03/09/2017 A 06/26/2018 A 260
Project CProject Closeout 11/12/2017 A 10/24/2018 145B1445 Closeout Phase 11/12/2017 A 10/24/2018 145B1450 Issue SAC Letter 11/12/2017 A 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 06/27/2018 A 10/24/2018 120B1490 Project Closed 10/24/2018 0
Basin 0871Basin 0871 09/18/2015 A 09/18/2015 A 1277
100157 Pu100157 Pump Station 0871 Upgrade 09/18/2015 A 09/18/2015 A 1277Project CProject Closeout 09/18/2015 A 09/18/2015 A 1277
B1445 Closeout Phase 09/18/2015 A 09/18/2015 A 1277B1450 Issue SAC Letter 09/18/2015 A 0B1480 Administrative Closeout 09/18/2015 A 09/18/2015 A 5B1490 Project Closed 09/18/2015 A 0
Basin 0877Basin 0877 08/15/2012 A 08/01/2018 2791
100158 Ba100158 Basin 0877 Infiltration/Inflow Study and Repairs 11/20/2015 A 06/01/2016 A 163InfiltratioInfiltration/Inflow 11/20/2015 A 05/31/2016 A 151
B1000 Infiltration/Inflow Phase 11/20/2015 A 05/31/2016 A 151Dig & ReDig & Replace Repairs 11/20/2015 A 05/31/2016 A 151
B1165 Dig & Replace Phase 11/20/2015 A 05/31/2016 A 151B1180 Issue NTP for Dig & Replace Repairs 11/20/2015 A 0B1190 Conduct Dig & Replace Repairs 04/21/2016 A 05/31/2016 A 30
Project CProject Closeout 06/01/2016 A 06/01/2016 A 0B1235 Closeout Phase 06/01/2016 A 06/01/2016 A 0B1260 Project Closed 06/01/2016 A 0
100159 Pu100159 Pump Station 0877 Upgrade 08/15/2012 A 08/01/2018 2032DesignDesign 08/15/2012 A 03/21/2018 A 2032
B1000 Design Phase 08/15/2012 A 03/21/2018 A 2032B1005 Remedial Action Plan to SAC Letter Issuance 08/15/2012 A 03/21/2018 A 2032
Project CProject Closeout 03/21/2018 A 08/01/2018 146B1445 Closeout Phase 03/21/2018 A 08/01/2018 146B1450 Issue SAC Letter 03/21/2018 A 0B1480 Administrative Closeout 03/22/2018 A 08/01/2018 120B1490 Project Closed 08/01/2018 0
Basin 0897Basin 0897 09/25/2014 A 08/01/2018 1402
100160 Ba100160 Basin 0897 Infiltration/Inflow Study and Repairs 09/25/2014 A 06/12/2015 A 372
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
06/26/2018 A, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Construction NTPConstruction Operations
Original Construction DurationChange order #1 - Hurricane Irma and FPL
Change order #2 - Miami Dade Public Work Dept. MOT Permit Appr
Substantial Completion06/26/2018 A, Designer Construction Support Services
Designer Construction Support Services10/24/2018, Project Closeout
Closeout PhaseIssue SAC Letter
Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed
09/18/2015 A, Basin 0871
09/18/2015 A, 100157 Pump Station 0871 Upgrade09/18/2015 A, Project Closeout
Closeout PhaseIssue SAC Letter
Administrative CloseoutProject Closed
08/01/2018, Basin 0877
06/01/2016 A, 100158 Basin 0877 Infiltration/Inflow Study and Repairs05/31/2016 A, Infiltration/InflowInfiltration/Inflow Phase05/31/2016 A, Dig & Replace RepairsDig & Replace Phase
Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs06/01/2016 A, Project CloseoutCloseout Phase
Project Closed08/01/2018, 100159 Pump Station 0877 Upgrade
03/21/2018 A, Design
Design PhaseRemedial Action Plan to SAC Letter Issuance
08/01/2018, Project CloseoutCloseout Phase
Issue SAC LetterAdministrative CloseoutProject Closed08/01/2018, Basin 0897
06/12/2015 A, 100160 Basin 0897 Infiltration/Inflow Study and Repairs
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 139 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
InfiltratioInfiltration/Inflow 09/25/2014 A 06/11/2015 A 223B1000 Infiltration/Inflow Phase 09/25/2014 A 06/11/2015 A 223
Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 06/11/2015 A 223B1005 SSES Phase 09/25/2014 A 06/11/2015 A 223B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 05/15/2015 A 05/27/2015 A 30B1040 Video Review 05/28/2015 A 06/11/2015 A 30
Project CProject Closeout 06/12/2015 A 06/12/2015 A 0B1235 Closeout Phase 06/12/2015 A 06/12/2015 A 0B1260 Project Closed 06/12/2015 A 0
100162 Pu100162 Pump Station 0897 Upgrade 02/16/2015 A 08/01/2018 1395DesignDesign 02/16/2015 A 05/31/2016 A 859
B1000 Design Phase 02/16/2015 A 05/31/2016 A 859B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 02/16/2015 A 02/20/2015 A 5B1020 Engage Design Consultant 02/23/2015 A 05/01/2015 A 20B1030 Issue Design NTP 05/05/2015 A 0B1040 A/E Develops and Submits Final Engineering Report 05/05/2015 A 10/28/2015 A 125B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 05/05/2015 A 10/19/2015 A 103
30% Des30% Design 05/05/2015 A 08/28/2015 A 95B1060 A/E Prepares 30% Construction Documents 05/06/2015 A 08/10/2015 A 30B1070 Geotechnical Engineering Services 05/05/2015 A 05/26/2015 A 20B1080 Surveying Services 05/05/2015 A 06/03/2015 A 15B1100 30% CDs Submittal 08/10/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 08/11/2015 A 08/28/2015 A 10
90% Des90% Design 08/11/2015 A 01/29/2016 A 161B1170 A/E Prepares 90% Construction Documents 08/11/2015 A 09/23/2015 A 20B1180 90% CDs Submittal 09/24/2015 A 0B1190 90% Review (MDWASD/PSIP Team) 09/25/2015 A 11/25/2015 A 15B1200 90% RER (DERM)FDEP Permit Submittal (Pump Station) 12/10/2015 A 0B1210 90% RER (DERM)FDEP Permit Review (Pump Station) 12/10/2015 A 01/13/2016 A 15B1220 90% RER (Building Dept.) Permit Submittal (Pump Station) 01/22/2016 A 0B1230 90% RER (Building Dept.) Permit Review (Pump Station) 01/22/2016 A 01/29/2016 A 15B1240 90% PWWMD Permit Submittal (Pump Station) 09/21/2015 A 0B1250 90% PWWMD Permit Review (Pump Station) 09/21/2015 A 10/05/2015 A 15B1260 90% CD PM Comments Evaluation Completed 01/29/2016 A 0
100% De100% Design 01/29/2016 A 05/31/2016 A 136B1270 A/E Prepares 100% Construction Documents 01/29/2016 A 05/31/2016 A 10B1280 100% CDs Submittal 05/31/2016 A 0B1290 100% Review (MDWASD/PSIP Team) 02/08/2016 A 05/31/2016 A 10B1300 Design Completed 05/31/2016 A 0
MDWASDMDWASD Procurement 02/08/2016 A 07/01/2016 A 110B1305 Procurement Phase 02/08/2016 A 07/01/2016 A 110B1310 Submit CDs to MDWASD Procurement Division 02/08/2016 A 0B1312 Bid Notice Preparation Period 02/09/2016 A 03/11/2016 A 23B1314 Bid Notice 03/11/2016 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 03/14/2016 A 03/21/2016 A 10B1320 Pre-Bid Conference 03/22/2016 A 03/22/2016 A 1B1322 Bidders Prepare Bids for Submittal 03/23/2016 A 04/18/2016 A 15B1330 Bids Submittal 04/18/2016 A 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
06/11/2015 A, Infiltration/Inflow
Infiltration/Inflow Phase06/11/2015 A, Sanitary Sewer Evaluation SurveySSES Phase
Issue NTP to SSES ContractorConduct SSESVideo Review
06/12/2015 A, Project CloseoutCloseout Phase
Project Closed08/01/2018, 100162 Pump Station 0897 Upgrade
05/31/2016 A, Design
Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book
Engage Design ConsultantIssue Design NTP
A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
08/28/2015 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services
30% CDs Submittal30% Review (MDWASD/PSIP Team)
01/29/2016 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER (DERM)FDEP Permit Submittal (Pump Station)
90% RER (DERM)FDEP Permit Review (Pump Station)90% RER (Building Dept.) Permit Submittal (Pump Station)90% RER (Building Dept.) Permit Review (Pump Station)
90% PWWMD Permit Submittal (Pump Station)90% PWWMD Permit Review (Pump Station)
90% CD PM Comments Evaluation Completed05/31/2016 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal
100% Review (MDWASD/PSIP Team)Design Completed07/01/2016 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 140 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1340 MDWASD/PSIP Team Bids Evaluation 04/19/2016 A 05/31/2016 A 15B1350 Recommendation for Award Letter 05/31/2016 A 0B1355 Contract Award (Purchase Order Approval) 06/01/2016 A 07/01/2016 A 10
ConstrucConstruction 03/22/2016 A 03/30/2017 A 994B1360 Construction Phase 03/22/2016 A 03/30/2017 A 994B1364 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 06/01/2016 A 06/14/2016 A 15B1366 Pre-Construction Meeting 06/15/2016 A 06/15/2016 A 1B1368 WASD Issues NTP (PO to NTP) 07/02/2016 A 11/13/2016 A 53B1369 FPL De-Energizes Overhead Lines 07/04/2016 A 11/08/2016 A 15B1370 Construction NTP 11/14/2016 A 0B1400 Construction Operations 11/14/2016 A 03/30/2017 A 129B1402 Substantial Completion 03/30/2017 A 0
DesignerDesigner Construction Support Services 03/22/2016 A 03/30/2017 A 275B1410 Designer Construction Support Services 03/22/2016 A 03/30/2017 A 275
Project CProject Closeout 03/31/2017 A 08/01/2018 394B1445 Closeout Phase 03/31/2017 A 08/01/2018 394B1450 Issue SAC Letter 05/09/2018 A 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 03/31/2017 A 08/01/2018 120B1490 Project Closed 08/01/2018 0
100161 FM100161 FM for Pump Station 0897 02/16/2015 A 08/01/2018 1402DesignDesign 02/16/2015 A 12/02/2015 A 298
B1000 Design Phase 02/16/2015 A 12/02/2015 A 298B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 02/16/2015 A 02/20/2015 A 5B1020 Engage Design Consultant 02/23/2015 A 05/20/2015 A 20B1025 TA Approval Process 05/21/2015 A 06/08/2015 A 20B1030 Issue Design NTP 06/11/2015 A 0B1040 A/E Develops and Submits Final Engineering Report 06/11/2015 A 10/28/2015 A 125B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 06/11/2015 A 10/02/2015 A 10
30% Des30% Design 06/11/2015 A 08/12/2015 A 80B1060 A/E Prepares 30% Construction Documents 06/11/2015 A 07/16/2015 A 30B1070 Geotechnical Engineering Services 06/11/2015 A 07/01/2015 A 29B1080 Surveying Services 06/11/2015 A 07/01/2015 A 22B1100 30% CDs Submittal 07/17/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 07/20/2015 A 07/24/2015 A 10B1130 30% Public Works Dry-Run Permit Submittal (Force Main) 07/27/2015 A 08/12/2015 A 30
90% Des90% Design 07/20/2015 A 10/28/2015 A 43B1180 A/E Prepares 90% Construction Documents 07/20/2015 A 08/17/2015 A 20B1190 90% CDs Submittal 08/18/2015 A 0B1200 90% Review (MDWASD/PSIP Team) 08/19/2015 A 10/02/2015 A 15B1210 90% PWWMD Permit Submittal (Force Main) 07/27/2015 A 0B1220 90% PWWMD Permit Review (Force Main) 07/27/2015 A 08/12/2015 A 15B1230 90% RER(DERM)FDEP Permit Submittal (Force Main) 10/05/2015 A 0B1240 90% RER(DERM)FDEP Permit Review (Force Main) 10/05/2015 A 10/28/2015 A 15B1290 90% CD PM Comments Evaluation Completed 10/28/2015 A 0
100% De100% Design 10/28/2015 A 12/02/2015 A 25B1300 A/E Prepares 100% Construction Documents 10/28/2015 A 11/30/2015 A 10B1310 100% CDs Submittal 11/30/2015 A 0B1320 100% Review (MDWASD/PSIP Team) 12/01/2015 A 12/02/2015 A 10
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter
Contract Award (Purchase Order Approval)03/30/2017 A, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
WASD Issues NTP (PO to NTP)FPL De-Energizes Overhead Lines
Construction NTPConstruction Operations
Substantial Completion03/30/2017 A, Designer Construction Support Services
Designer Construction Support Services08/01/2018, Project Closeout
Closeout PhaseIssue SAC Letter
Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed08/01/2018, 100161 FM for Pump Station 0897
12/02/2015 A, Design
Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book
Engage Design ConsultantTA Approval ProcessIssue Design NTP
A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
08/12/2015 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services
30% CDs Submittal30% Review (MDWASD/PSIP Team)
30% Public Works Dry-Run Permit Submittal (Force Main)10/28/2015 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% PWWMD Permit Submittal (Force Main)
90% PWWMD Permit Review (Force Main)90% RER(DERM)FDEP Permit Submittal (Force Main)90% RER(DERM)FDEP Permit Review (Force Main)90% CD PM Comments Evaluation Completed
12/02/2015 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 141 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1330 Design Completed 12/02/2015 A 0MDWASDMDWASD Procurement 12/03/2015 A 06/21/2016 A 111
B1335 Procurement Phase 12/03/2015 A 06/21/2016 A 111B1340 Submit CDs to MDWASD Procurement Division 12/03/2015 A 0B1344 Bid Notice Preparation Period 12/04/2015 A 12/17/2015 A 23B1346 Bid Notice 12/17/2015 A 0B1348 MDWASD/PSIP Team Prepare for Pre-Bid Conference 12/17/2015 A 01/20/2016 A 10B1350 Pre-Bid Conference 01/21/2016 A 01/21/2016 A 1B1358 Bidders Prepare Bids for Submittal 01/22/2016 A 02/17/2016 A 15B1360 Bids Submittal 02/17/2016 A 0B1370 MDWASD/PSIP Team Bids Evaluation 02/18/2016 A 03/01/2016 A 15B1380 Recommendation for Award Letter 03/01/2016 A 0B1385 Contract Award (Purchase Order Approval) 03/02/2016 A 06/21/2016 A 10
ConstrucConstruction 01/21/2016 A 10/03/2016 A 992B1390 Construction Phase 01/21/2016 A 10/03/2016 A 992B1394 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 03/02/2016 A 04/11/2016 A 15B1396 Pre-Construction Meeting 04/12/2016 A 04/12/2016 A 1B1398 WASD Issues NTP (PO to NTP) 06/21/2016 A 06/22/2016 A 53B1400 Construction NTP 06/22/2016 A 0B1430 Construction Operations 06/22/2016 A 08/28/2016 A 107B1432 Substantial Completion 08/28/2016 A 0
DesignerDesigner Construction Support Services 01/21/2016 A 10/03/2016 A 141B1440 Designer Construction Support Services 01/21/2016 A 10/03/2016 A 141
ConstrucConstruction Close Out 08/15/2016 A 08/31/2016 A 15B1450 Commissioning 08/15/2016 A 08/31/2016 A 15B1460 Punch List 08/15/2016 A 08/31/2016 A 10
Project CProject Closeout 08/15/2016 A 08/01/2018 622B1475 Closeout Phase 08/15/2016 A 08/01/2018 622B1500 Final Release of Retainage - Construction Contract 04/12/2017 A 0B1510 Administrative Closeout 08/15/2016 A 08/01/2018 120B1520 Project Closed 08/01/2018 0
Basin 0898Basin 0898 09/18/2012 A 08/01/2018 1736
100164 Pu100164 Pump Station 0898 Upgrade 09/18/2012 A 08/01/2018 1736DesignDesign 09/18/2012 A 12/18/2017 A 1723
B1000 Design Phase 09/18/2012 A 12/18/2017 A 1723B1012 RAP Submittal 09/18/2012 A 0B1014 I/I Repairs and Monitoring Period 04/01/2013 A 12/18/2017 A 1723
Project CProject Closeout 12/19/2017 A 08/01/2018 802B1445 Closeout Phase 12/19/2017 A 08/01/2018 802B1450 Issue SAC Letter 12/19/2017 A 0B1480 Administrative Closeout 12/20/2017 A 08/01/2018 120B1490 Project Closed 08/01/2018 0
Basin 1002Basin 1002 09/25/2014 A 01/23/2020 1662
100165 Pu100165 Pump Station 1002 Upgrade 12/17/2015 A 01/23/2020 1452DesignDesign 12/17/2015 A 10/23/2018 995
B1000 Design Phase 12/17/2015 A 10/23/2018 995B1010 Prepare and Submit Design Package 12/17/2015 A 12/28/2015 A 5B1020 Engage Design Consultant 12/28/2015 A 04/01/2016 A 20B1022 TA Preparation 04/04/2016 A 04/15/2016 A 1
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Design Completed06/21/2016 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation Period
Bid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter
Contract Award (Purchase Order Approval)10/03/2016 A, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
WASD Issues NTP (PO to NTP)Construction NTP
Construction OperationsSubstantial Completion
10/03/2016 A, Designer Construction Support Services
Designer Construction Support Services08/31/2016 A, Construction Close Out
CommissioningPunch List
08/01/2018, Project Closeout
Closeout PhaseFinal Release of Retainage - Construction Contract
Administrative CloseoutProject Closed08/01/2018, Basin 0898
08/01/2018, 100164 Pump Station 0898 Upgrade12/18/2017 A, Design
Design PhaseRAP Submittal
I/I Repairs and Monitoring Period08/01/2018, Project CloseoutCloseout Phase
Issue SAC LetterAdministrative CloseoutProject Closed
01/23/2020, Basin
01/23/2020, 1001610/23/2018, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 142 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1024 TA Approval Process 04/18/2016 A 09/21/2016 A 20B1030 Issue Design NTP 09/28/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 09/28/2016 A 10/09/2018 85
30% Des30% Design 09/28/2016 A 09/04/2018 702B1060 A/E Prepares 30% Construction Documents 09/28/2016 A 01/24/2017 A 50B1100 30% CDs Submittal 01/24/2017 A 0B1102 Project On-Hold Due to Re-Design 01/25/2017 A 03/17/2017 A 52B1104 Engage Design Consultant (Re-Design) 03/20/2017 A 08/14/2017 A 28B1106 TA-Rev 1 Preparation 08/15/2017 A 08/15/2017 A 14B1108 TA-Rev 1 Approval Process 08/16/2017 A 11/29/2017 A 40B1109 WASD/PSIP/Design Consultant in Consultation for easement E 11/30/2017 A 05/21/2018 A 50B1110 A/E Prepares 30% Construction Documents (Re-Design) 05/22/2018 A 07/18/2018 A 50B1112 30% CDs Submittal (Re-Design) 07/18/2018 A 0B1114 TA-Rev 2 Approval Process 07/27/2018 A 09/04/2018 40B1120 30% Review (MDWASD/PSIP Team) (Re-Design) 07/19/2018 A 08/10/2018 10
90% Des90% Design 08/11/2018 10/09/2018 60B1170 A/E Prepares 90% Construction Documents 08/11/2018 08/25/2018 15B1180 90% CDs Submittal 08/25/2018 0B1190 90% Review (MDWASD/PSIP Team) 08/26/2018 09/09/2018 15B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 09/10/2018 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 09/10/2018 09/24/2018 15B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 09/25/2018 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 09/25/2018 10/09/2018 15B1260 90% CD PM Comments Evaluation Completed 10/09/2018 0
100% De100% Design 10/10/2018 10/23/2018 14B1270 A/E Prepares 100% Construction Documents 10/10/2018 10/16/2018 7B1280 100% CDs Submittal 10/16/2018 0B1290 100% Review (MDWASD/PSIP Team) 10/17/2018 10/23/2018 7B1300 Design Completed 10/23/2018 0
MDWASDMDWASD Procurement 10/23/2018 02/04/2019 104B1305 Procurement Phase 10/23/2018 02/04/2019 104B1310 Submit CDs to MDWASD Procurement Division 10/23/2018 0B1312 Bid Notice Preparation Period 10/24/2018 11/25/2018 33B1314 Bid Notice 11/25/2018 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 11/26/2018 12/09/2018 14B1320 Pre-Bid Conference 12/10/2018 12/10/2018 1B1328 Bidders Prepare Bids for Submittal 12/11/2018 12/31/2018 21B1330 Bids Submittal 12/31/2018 0B1340 MDWASD/PSIP Team Bids Evaluation 01/01/2019 01/21/2019 21B1350 Recommendation for Award Letter 01/21/2019 0B1355 Contract Award (Purchase Order Approval) 01/22/2019 02/04/2019 14
ConstrucConstruction 12/10/2018 09/25/2019 290B1360 Construction Phase 12/10/2018 09/25/2019 290B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 01/22/2019 02/11/2019 21B1364 Pre-Construction Meeting 02/12/2019 02/12/2019 1B1366 WASD Issues NTP (Pre-Const to NTP) 02/13/2019 03/29/2019 45B1368 WASD Issues NTP (PO to NTP) 02/05/2019 03/29/2019 53B1370 Construction NTP 03/30/2019 0B1400 Construction Operations 03/30/2019 09/25/2019 180
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
TA Approval ProcessIssue Design NTP
Final Engineering Report Review & Approval (MDWASD/P09/04/2018, 30% Design
A/E Prepares 30% Construction Documents30% CDs Submittal
Project On-Hold Due to Re-DesignEngage Design Consultant (Re-Design)TA-Rev 1 Preparation
TA-Rev 1 Approval ProcessWASD/PSIP/Design Consultant in Consultation for easement Encroa
A/E Prepares 30% Construction Documents (Re-Design)30% CDs Submittal (Re-Design)
TA-Rev 2 Approval Process
30% Review (MDWASD/PSIP Team) (Re-Design)10/09/2018, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)90% RER(DERM)FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)90% RER(Building Dept) Permit Review (Pump Station)90% CD PM Comments Evaluation Completed10/23/2018, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed
02/04/2019, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferenPre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)
09/25/2019, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-ConstruPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Construction NTPConstruction Operations
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 143 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1402 Substantial Completion 09/25/2019 0DesignerDesigner Construction Support Services 12/10/2018 09/25/2019 290
B1410 Designer Construction Support Services 12/10/2018 09/25/2019 290Project CProject Closeout 09/25/2019 01/23/2020 120
B1445 Closeout Phase 09/25/2019 01/23/2020 120B1450 Issue SAC Letter 09/25/2019 0B1470 Final Release of Retainage - Construction Contract 09/25/2019 0B1480 Administrative Closeout 09/26/2019 01/23/2020 120B1490 Project Closed 01/23/2020 0
100196 Ba100196 Basin 1002 Infiltration/Inflow Study and Repairs 09/25/2014 A 10/26/2015 A 330InfiltratioInfiltration/Inflow 09/25/2014 A 10/23/2015 A 57
B1000 Infiltration/Inflow Phase 09/25/2014 A 10/23/2015 A 57Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 10/23/2015 A 57
B1005 SSES Phase 09/25/2014 A 10/23/2015 A 57B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 07/30/2015 A 10/23/2015 A 30
Project CProject Closeout 10/26/2015 A 10/26/2015 A 0B1235 Closeout Phase 10/26/2015 A 10/26/2015 A 0B1260 Project Closed 10/26/2015 A 0
Basin 1004Basin 1004 04/22/2015 A 04/22/2015 A 933
100234 FM100234 FM for Pump Station 1004 04/22/2015 A 04/22/2015 A 933Project CProject Closeout 04/22/2015 A 04/22/2015 A 933
B1475 Closeout Phase 04/22/2015 A 04/22/2015 A 933B1480 Issue SAC Letter 04/22/2015 A 0B1510 Administrative Closeout 04/22/2015 A 04/22/2015 A 15B1520 Project Closed 04/22/2015 A 04/22/2015 A 10
Basin 1008Basin 1008 07/27/2017 A 12/20/2019 802
100167 Pu100167 Pump Station 1008 Upgrade 07/27/2017 A 12/20/2019 802DesignDesign 07/27/2017 A 09/19/2018 345
B1000 Design Phase 07/27/2017 A 09/19/2018 345B1010 Prepare and Submit Design Package 07/27/2017 A 07/27/2017 A 7B1020 Engage Design Consultant 07/28/2017 A 10/09/2017 A 28B1022 TA Preparation 10/10/2017 A 10/10/2017 A 14B1024 TA Approval Process 10/11/2017 A 12/20/2017 A 40B1030 Issue Design NTP 12/22/2017 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 12/22/2017 A 08/22/2018 186
30% Des30% Design 12/22/2017 A 02/12/2018 A 100B1060 A/E Prepares 30% Construction Documents 12/22/2017 A 01/11/2018 A 50B1100 30% CDs Submittal 01/11/2018 A 0B1120 30% Review (MDWASD/PSIP Team) 01/12/2018 A 02/12/2018 A 30
90% Des90% Design 01/12/2018 A 08/22/2018 175B1170 A/E Prepares 90% Construction Documents 01/12/2018 A 03/26/2018 A 40B1180 90% CDs Submittal 03/26/2018 A 0B1190 90% Review (MDWASD/PSIP Team) 03/27/2018 A 04/24/2018 A 30B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 06/12/2018 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 06/12/2018 A 08/01/2018 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 08/02/2018 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 08/02/2018 08/22/2018 21B1260 90% CD PM Comments Evaluation Completed 08/22/2018 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Substantial Completion09/25/2019, Designer Const
Designer Construction Supp01/23/2020, Projec
Closeout PhaseIssue SAC LetterFinal Release of Retainage -
Administrative ClosProject Closed
10/26/2015 A, 100196 Basin 1002 Infiltration/Inflow Study and Repairs10/23/2015 A, Infiltration/Inflow
Infiltration/Inflow Phase10/23/2015 A, Sanitary Sewer Evaluation SurveySSES Phase
Issue NTP to SSES ContractorConduct SSES10/26/2015 A, Project CloseoutCloseout Phase
Project Closed04/22/2015 A, Basin 1004
04/22/2015 A, 100234 FM for Pump Station 100404/22/2015 A, Project Closeout
Closeout PhaseIssue SAC Letter
Administrative CloseoutProject Closed
12/20/2019, Basin 10
12/20/2019, 100167 09/19/2018, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval ProcessIssue Design NTP
Final Engineering Report Review & Approval (MDWASD/PSIP02/12/2018 A, 30% Design
A/E Prepares 30% Construction Documents30% CDs Submittal30% Review (MDWASD/PSIP Team)
08/22/2018, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)
90% RER(DERM)FDEP Permit Submittal (Pump Station)90% RER(DERM)FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)
90% RER(Building Dept) Permit Review (Pump Station)90% CD PM Comments Evaluation Completed
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 144 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
100% De100% Design 08/23/2018 09/19/2018 28B1270 A/E Prepares 100% Construction Documents 08/23/2018 09/05/2018 14B1280 100% CDs Submittal 09/05/2018 0B1290 100% Review (MDWASD/PSIP Team) 09/06/2018 09/19/2018 14B1300 Design Completed 09/19/2018 0
MDWASDMDWASD Procurement 09/19/2018 01/01/2019 104B1305 Procurement Phase 09/19/2018 01/01/2019 104B1310 Submit CDs to MDWASD Procurement Division 09/19/2018 0B1312 Bid Notice Preparation Period 09/20/2018 10/22/2018 33B1314 Bid Notice 10/22/2018 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conferencce 10/23/2018 11/05/2018 14B1320 Pre-Bid Conference 11/06/2018 11/06/2018 1B1328 Bidders Prepare Bids for Submittal 11/07/2018 11/27/2018 21B1330 Bids Submittal 11/27/2018 0B1340 MDWASD/PSIP Team Bids Evaluation 11/28/2018 12/18/2018 21B1350 Recommendation for Award Letter 12/18/2018 0B1355 Contract Award (Purchase Order Approval) 12/19/2018 01/01/2019 14
ConstrucConstruction 11/06/2018 08/22/2019 290B1360 Construction Phase 11/06/2018 08/22/2019 290B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 12/19/2018 01/08/2019 21B1364 Pre-Construction Meeting 01/09/2019 01/09/2019 1B1366 WASD Issues NTP (Pre-Const to NTP) 01/10/2019 02/23/2019 45B1368 WASD Issues NTP (PO to NTP) 01/02/2019 02/23/2019 53B1370 Construction NTP 02/24/2019 0B1400 Construction Operations 02/24/2019 08/22/2019 180B1402 Substantial Completion 08/22/2019 0
DesignerDesigner Construction Support Services 11/06/2018 08/22/2019 290B1410 Designer Construction Support Services 11/06/2018 08/22/2019 290
Project CProject Closeout 08/22/2019 12/20/2019 120B1445 Closeout Phase 08/22/2019 12/20/2019 120B1450 Issue SAC Letter 08/22/2019 0B1470 Final Release of Retainage - Construction Contract 08/22/2019 0B1480 Administrative Closeout 08/23/2019 12/20/2019 120B1490 Project Closed 12/20/2019 0
Basin 1020Basin 1020 05/29/2015 A 12/28/2019 1854
100168 Pu100168 Pump Station 1020 Upgrade 06/04/2018 A 12/28/2019 576DesignDesign 06/04/2018 A 11/26/2018 179
B1000 Design Phase 06/04/2018 A 11/26/2018 179B1010 Prepare and Submit Design Package 06/04/2018 A 06/04/2018 A 7B1020 Engage Design Consultant 06/05/2018 A 06/23/2018 A 28B1022 TA Preparation 06/24/2018 A 06/24/2018 A 14B1024 TA Approval Process 06/25/2018 A 08/01/2018 40B1030 Issue Design NTP 08/02/2018 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 08/02/2018 11/12/2018 103
30% Des30% Design 08/02/2018 08/23/2018 22B1060 A/E Prepares 30% Construction Documents 08/02/2018 08/16/2018 15B1100 30% CDs Submittal 08/16/2018 0B1120 30% Review (MDWASD/PSIP Team) 08/17/2018 08/23/2018 7
90% Des90% Design 08/17/2018 11/12/2018 88
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
09/19/2018, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed
01/01/2019, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferenccePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)
08/22/2019, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-ConstructioPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Construction NTPConstruction OperationsSubstantial Completion08/22/2019, Designer Construc
Designer Construction Support 12/20/2019, Project C
Closeout PhaseIssue SAC LetterFinal Release of Retainage - C
Administrative CloseoProject Closed12/28/2019, Basin 1
12/28/2019, 10016811/26/2018, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval Process
Issue Design NTPFinal Engineering Report Review & Approval (MDWAS
08/23/2018, 30% Design
A/E Prepares 30% Construction Documents30% CDs Submittal30% Review (MDWASD/PSIP Team)
11/12/2018, 90% Design
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 145 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1170 A/E Prepares 90% Construction Documents 08/17/2018 08/31/2018 15B1180 90% CDs Submittal 08/31/2018 0B1190 90% Review (MDWASD/PSIP Team) 09/01/2018 09/07/2018 7B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 09/08/2018 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 09/08/2018 10/22/2018 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 10/23/2018 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 10/23/2018 11/12/2018 21B1260 90% CD PM Comments Evaluation Completed 11/12/2018 0
100% De100% Design 11/13/2018 11/26/2018 14B1270 A/E Prepares 100% Construction Documents 11/13/2018 11/19/2018 7B1280 100% CDs Submittal 11/19/2018 0B1290 100% Review (MDWASD/PSIP Team) 11/20/2018 11/26/2018 7B1300 Design Completed 11/26/2018 0
MDWASDMDWASD Procurement 11/26/2018 03/10/2019 104B1305 Procurement Phase 11/26/2018 03/10/2019 104B1310 Submit CDs to MDWASD Procurement Division 11/26/2018 0B1312 Bid Notice Preparation Period 11/27/2018 12/29/2018 33B1314 Bid Notice 12/29/2018 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conferencce 12/30/2018 01/12/2019 14B1320 Pre-Bid Conference 01/13/2019 01/13/2019 1B1328 Bidders Prepare Bids for Submittal 01/14/2019 02/03/2019 21B1330 Bids Submittal 02/03/2019 0B1340 MDWASD/PSIP Team Bids Evaluation 02/04/2019 02/24/2019 21B1350 Recommendation for Award Letter 02/24/2019 0B1355 Contract Award (Purchase Order Approval) 02/25/2019 03/10/2019 14
ConstrucConstruction 01/13/2019 08/30/2019 230B1360 Construction Phase 01/13/2019 08/30/2019 230B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 02/25/2019 03/17/2019 21B1364 Pre-Construction Meeting 03/18/2019 03/18/2019 1B1366 WASD Issues NTP (Pre-Const to NTP) 03/19/2019 05/02/2019 45B1368 WASD Issues NTP (PO to NTP) 03/11/2019 05/02/2019 53B1370 Construction NTP 05/03/2019 0B1400 Construction Operations 05/03/2019 08/30/2019 120B1402 Substantial Completion 08/30/2019 0
DesignerDesigner Construction Support Services 01/13/2019 08/30/2019 230B1410 Designer Construction Support Services 01/13/2019 08/30/2019 230
Project CProject Closeout 08/30/2019 12/28/2019 120B1445 Closeout Phase 08/30/2019 12/28/2019 120B1450 Issue SAC Letter 08/30/2019 0B1470 Final Release of Retainage - Construction Contract 08/30/2019 0B1480 Administrative Closeout 08/31/2019 12/28/2019 120B1490 Project Closed 12/28/2019 0
100198 Ba100198 Basin 1020 Infiltration/Inflow Study and Repairs 05/29/2015 A 06/17/2016 A 548InfiltratioInfiltration/Inflow 05/29/2015 A 06/16/2016 A 275
B1000 Infiltration/Inflow Phase 05/29/2015 A 06/16/2016 A 275Sanitary Sanitary Sewer Evaluation Survey 05/29/2015 A 08/13/2015 A 30
B1005 SSES Phase 05/29/2015 A 08/13/2015 A 30B1020 Issue NTP to SSES Contractor 05/29/2015 A 0B1030 Conduct SSES 05/29/2015 A 08/13/2015 A 30
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)
90% RER(DERM)FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Statio
90% RER(Building Dept) Permit Review (Pump Station90% CD PM Comments Evaluation Completed11/26/2018, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed
03/10/2019, MDWASD ProcurementProcurement Phase
Submit CDs to MDWASD Procurement DivisionBid Notice Preparation Period
Bid NoticeMDWASD/PSIP Team Prepare for Pre-Bid Confer
Pre-Bid ConferenceBidders Prepare Bids for Submittal
Bids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)
08/30/2019, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-ConsPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Construction NTPConstruction OperationsSubstantial Completion08/30/2019, Designer Constru
Designer Construction Suppor12/28/2019, Project Closeout Phase
Issue SAC LetterFinal Release of Retainage - C
Administrative CloseProject Closed
06/17/2016 A, 100198 Basin 1020 Infiltration/Inflow Study and Repairs06/16/2016 A, Infiltration/Inflow
Infiltration/Inflow Phase08/13/2015 A, Sanitary Sewer Evaluation SurveySSES Phase
Issue NTP to SSES ContractorConduct SSES
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 146 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
Dig & ReDig & Replace Repairs 11/20/2015 A 06/16/2016 A 30B1160 Dig & Replace Phase 11/20/2015 A 06/16/2016 A 30B1180 Issue NTP for Dig & Replace Repairs 11/20/2015 A 0B1190 Conduct Dig & Replace Repairs 06/16/2016 A 06/16/2016 A 30
Project CProject Closeout 06/17/2016 A 06/17/2016 A 0B1235 Closeout Phase 06/17/2016 A 06/17/2016 A 0B1260 Project Closed 06/17/2016 A 0
Basin 1021Basin 1021 08/15/2012 A 09/28/2020 905
100238 FM100238 FM for Pump Station 1021 08/01/2018 09/28/2020 790DesignDesign 08/01/2018 06/29/2019 333
B1000 Design Phase 08/01/2018 06/29/2019 333B1010 Prepare and Submit Design Package 08/01/2018 08/07/2018 7B1020 Engage Design Consultant 08/08/2018 09/04/2018 28B1030 TA Preparation 09/05/2018 09/18/2018 14B1032 TA Approval Process 09/19/2018 10/28/2018 40B1040 Issue Design NTP 10/29/2018 0B1060 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/29/2018 06/01/2019 216
30% Des30% Design 10/29/2018 01/16/2019 80B1070 A/E Prepares 30% Construction Documents 10/29/2018 12/17/2018 50B1110 30% CDs Submittal 12/17/2018 0B1130 30% Review (MDWASD/PSIP Team) 12/18/2018 01/16/2019 30
60% Des60% Design 12/18/2018 01/30/2019 44B1150 A/E Prepares 60% Construction Documents 12/18/2018 01/16/2019 30B1160 60% CDs Submittal 01/16/2019 0B1180 60% Review (MDWASD/PSIP Team) 01/17/2019 01/30/2019 14
90% Des90% Design 01/17/2019 06/01/2019 136B1190 A/E Prepares 90% Construction Documents 01/17/2019 02/25/2019 40B1200 90% CDs Submittal 02/25/2019 0B1210 90% Review (MDWASD/PSIP Team) 02/26/2019 03/27/2019 30B1220 90% PWWMD Permit Submittal (Force Main) 03/28/2019 0B1230 90% PWWMD Permit Review (Force Main) 03/28/2019 04/17/2019 21B1240 90% RER(DERM)/FDEP Permit Submittal (Force Main) 03/28/2019 0B1250 90% RER(DERM)/FDEP Permit Review (Force Main) 03/28/2019 05/11/2019 45B1260 90% Municipality Permit Submittal (Force Main) 05/12/2019 0B1270 90% Municipality Permit Review (Force Main) 05/12/2019 06/01/2019 21B1280 90% FDOT Permit Submittal (Force Main) 05/12/2019 0B1290 90% FDOT Permit Review (Force Main) 05/12/2019 06/01/2019 21B1300 90% CD PM Comments Evaluation Completed 06/01/2019 0
100% De100% Design 06/02/2019 06/29/2019 28B1310 A/E Prepares 100% Construction Documents 06/02/2019 06/15/2019 14B1320 100% CDs Submittal 06/15/2019 0B1330 100% Review (MDWASD/PSIP Team) 06/16/2019 06/29/2019 14B1340 Design Completed 06/29/2019 0
MDWASDMDWASD Procurement 06/29/2019 10/11/2019 104B1345 Procurement Phase 06/29/2019 10/11/2019 104B1350 Submit CDs to MDWASD Procurement Division 06/29/2019 0B1356 Bid Notice Preparation Period 06/30/2019 08/01/2019 33B1357 Bid Notice 08/01/2019 0B1358 MDWASD/PSIP Team Prepare for Pre-Bid Conferencce 08/02/2019 08/15/2019 14
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
06/16/2016 A, Dig & Replace Repairs
Dig & Replace PhaseIssue NTP for Dig & Replace Repairs
Conduct Dig & Replace Repairs06/17/2016 A, Project CloseoutCloseout Phase
Project Closed
06/29/2019, DesignDesign Phase
Prepare and Submit Design PackageEngage Design ConsultantTA Preparation
TA Approval Process
Issue Design NTPFinal Engineering Report Review & Ap
01/16/2019, 30% DesignA/E Prepares 30% Construction Documents
30% CDs Submittal30% Review (MDWASD/PSIP Team)01/30/2019, 60% Design
A/E Prepares 60% Construction Documents
60% CDs Submittal60% Review (MDWASD/PSIP Team)
06/01/2019, 90% DesignA/E Prepares 90% Construction Documents
90% CDs Submittal90% Review (MDWASD/PSIP Team)
90% PWWMD Permit Submittal (Force Mai90% PWWMD Permit Review (Force Main
90% RER(DERM)/FDEP Permit Submittal (F90% RER(DERM)/FDEP Permit Review
90% Municipality Permit Submittal (Forc90% Municipality Permit Review (Forc
90% FDOT Permit Submittal (Force Ma90% FDOT Permit Review (Force Main
90% CD PM Comments Evaluation C06/29/2019, 100% Design
A/E Prepares 100% Construction Do
100% CDs Submittal100% Review (MDWASD/PSIP Team
Design Completed10/11/2019, MDWASD ProProcurement Phase
Submit CDs to MDWASD ProcuremBid Notice Preparation Period
Bid NoticeMDWASD/PSIP Team Prepare
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 147 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1360 Pre-Bid Conference 08/16/2019 08/16/2019 1B1362 Bidders Prepare Bids for Submittal 08/17/2019 09/06/2019 21B1370 Bids Submittal 09/06/2019 0B1380 MDWASD/PSIP Team Bids Evaluation 09/07/2019 09/27/2019 21B1390 Recommendation for Award Letter 09/27/2019 0B1392 Contract Award (Purchase Order Approval) 09/28/2019 10/11/2019 14
ConstrucConstruction 08/16/2019 05/31/2020 290B1395 Construction Phase 08/16/2019 05/31/2020 290B1396 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 09/28/2019 10/18/2019 21B1397 Pre-Construction Meeting 10/19/2019 10/19/2019 1B1398 WASD Issues NTP (Pre-Const to NTP) 10/20/2019 12/03/2019 45B1399 WASD Issues NTP (PO to NTP) 10/12/2019 12/03/2019 53B1400 Construction NTP 12/04/2019 0B1430 Construction Operations 12/04/2019 05/31/2020 180B1432 Substantial Completion 05/31/2020 0
DesignerDesigner Construction Support Services 08/16/2019 05/31/2020 290B1440 Designer Construction Support Services 08/16/2019 05/31/2020 290
Project CProject Closeout 05/31/2020 09/28/2020 120B1475 Closeout Phase 05/31/2020 09/28/2020 120B1500 Final Release of Retainage - Construction Contract 05/31/2020 0B1510 Administrative Closeout 06/01/2020 09/28/2020 120B1520 Project Closed 09/28/2020 0
100258 Pu100258 Pump Station 1021 Upgrade 08/15/2012 A 08/03/2018 783DesignDesign 08/15/2012 A 04/05/2018 A 28
B1000 Design Phase 08/15/2012 A 04/05/2018 A 28B1016 Remedial Action Plan to SAC Letter Issuance 08/15/2012 A 04/05/2018 A 28
Project CProject Closeout 04/05/2018 A 08/03/2018 665B1425 Closeout Phase 04/05/2018 A 08/03/2018 665B1430 Issue SAC Letter 04/05/2018 A 0B1460 Administrative Closeout 04/06/2018 A 08/03/2018 120B1470 Project Closed 08/03/2018 0
Basin 1022Basin 1022 04/22/2014 A 01/12/2020 1718
100170 Pu100170 Pump Station 1022(AM) Upgrade 03/14/2016 A 01/12/2020 1399DesignDesign 03/14/2016 A 10/12/2018 942
B1000 Design Phase 03/14/2016 A 10/12/2018 942B1010 Prepare and Submit Design Package 03/14/2016 A 03/14/2016 A 5B1020 Engage Design Consultant 03/14/2016 A 08/10/2016 A 20B1020 FPL/WASD Easements Negotiation Period (Approved PER) 08/11/2016 A 02/01/2017 A 60B1020 Engage Design Consultant (Design TA) 02/01/2017 A 02/28/2017 A 20B1022 TA Preparation 02/28/2017 A 02/28/2017 A 1B1024 TA Approval Process 02/28/2017 A 04/03/2017 A 40B1030 Issue Design NTP 04/06/2017 A 0B1032 Surveying Services for Easements - Recording - Conceptual De 04/06/2017 A 11/02/2017 A 110B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 08/01/2018 09/14/2018 45
30% Des30% Design 11/03/2017 A 01/22/2018 A 80B1060 A/E Prepares 30% Construction Documents 11/03/2017 A 12/11/2017 A 50B1100 30% CDs Submittal 12/11/2017 A 0B1120 30% Review (MDWASD/PSIP Team) 12/12/2017 A 01/22/2018 A 30
90% Des90% Design 01/23/2018 A 09/14/2018 226
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Pre-Bid ConferenceBidders Prepare Bids for Subm
Bids SubmittalMDWASD/PSIP Team Bids E
Recommendation for Award Contract Award (Purchase O
05/31/2Constru
MDWASD/PSIP Team PrePre-Construction Meeting
WASD Issues NTP (PreWASD Issues NTP (PO
Construction NTPConstru
Substan05/31/2Designe
Final Re
08/03/2018, 100258 Pump Station 1021 Upgrade04/05/2018 A, Design
Design PhaseRemedial Action Plan to SAC Letter Issuance
08/03/2018, Project Closeout
Closeout PhaseIssue SAC Letter
Administrative CProject Closed
01/12/2020, Basin
01/12/2020, 1001710/12/2018, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantFPL/WASD Easements Negotiation Period (Approved PER)
Engage Design Consultant (Design TA)TA Preparation
TA Approval ProcessIssue Design NTP
Surveying Services for Easements - Recording - Conceptual DesignFinal Engineering Report Review & Approval (MDWASD/PS
01/22/2018 A, 30% Design
A/E Prepares 30% Construction Documents30% CDs Submittal
30% Review (MDWASD/PSIP Team)09/14/2018, 90% Design
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 148 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1170 A/E Prepares 90% Construction Documents 01/23/2018 A 03/21/2018 A 40B1180 90% CDs Submittal 03/21/2018 A 0B1190 90% Review (MDWASD/PSIP Team) 03/22/2018 A 07/10/2018 A 30B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 07/11/2018 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 07/11/2018 A 08/24/2018 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 08/25/2018 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 08/25/2018 09/14/2018 21B1260 90% CD PM Comments Evaluation Completed 09/14/2018 0
100% De100% Design 09/15/2018 10/12/2018 28B1270 A/E Prepares 100% Construction Documents 09/15/2018 09/28/2018 14B1280 100% CDs Submittal 09/28/2018 0B1290 100% Review (MDWASD/PSIP Team) 09/29/2018 10/12/2018 14B1300 Design Completed 10/12/2018 0
MDWASDMDWASD Procurement 10/12/2018 01/24/2019 104B1305 Procurement Phase 10/12/2018 01/24/2019 104B1310 Submit CDs to MDWASD Procurement Division 10/12/2018 0B1312 Bid Notice Preparation Period 10/13/2018 11/14/2018 33B1314 Bid Notice 11/14/2018 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 11/15/2018 11/28/2018 14B1320 Pre-Bid Conference 11/29/2018 11/29/2018 1B1322 Bidders Prepare Bids for Submittal 11/30/2018 12/20/2018 21B1330 Bids Submittal 12/20/2018 0B1340 MDWASD/PSIP Team Bids Evaluation 12/21/2018 01/10/2019 21B1350 Recommendation for Award Letter 01/10/2019 0B1355 Contract Award (Purchase Order Approval) 01/11/2019 01/24/2019 14
ConstrucConstruction 11/29/2018 09/14/2019 290B1360 Construction Phase 11/29/2018 09/14/2019 290B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 01/11/2019 01/31/2019 21B1364 Pre-Construction Meeting 02/01/2019 02/01/2019 1B1366 WASD Issues NTP (Pre-Const to NTP) 02/02/2019 03/18/2019 45B1368 WASD Issues NTP (PO to NTP) 01/25/2019 03/18/2019 53B1370 Construction NTP 03/19/2019 0B1400 Construction Operations 03/19/2019 09/14/2019 180B1402 Substantial Completion 09/14/2019 0
DesignerDesigner Construction Support Services 11/29/2018 09/14/2019 290B1410 Designer Construction Support Services 11/29/2018 09/14/2019 290
Project CProject Closeout 09/14/2019 01/12/2020 120B1445 Closeout Phase 09/14/2019 01/12/2020 120B1450 Issue SAC Letter 09/14/2019 0B1470 Final Release of Retainage - Construction Contract 09/14/2019 0B1480 Administrative Closeout 09/15/2019 01/12/2020 120B1490 Project Closed 01/12/2020 0
100169 FM100169 FM for Pump Station 1022 04/22/2014 A 06/08/2016 A 12PlanningPlanning 04/22/2014 A 06/08/2016 A 12
B0900 Planning Phase 04/22/2014 A 06/08/2016 A 12B0940 Develop Remedial Action Plan (RAP) 04/22/2014 A 05/22/2014 A 5B0950 Develop Preliminary Engineer Report (PER) 09/08/2015 A 06/08/2016 A 5
100199 Ba100199 Basin 1022 Infiltration/Inflow Study and Repairs 09/25/2014 A 05/20/2015 A 397InfiltratioInfiltration/Inflow 09/25/2014 A 05/19/2015 A 109
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)
90% RER(DERM)FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)
90% RER(Building Dept) Permit Review (Pump Station)90% CD PM Comments Evaluation Completed
10/12/2018, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed
01/24/2019, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencPre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)
09/14/2019, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-ConstrucPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Construction NTPConstruction OperationsSubstantial Completion09/14/2019, Designer Constr
Designer Construction Suppo01/12/2020, Projec
Closeout PhaseIssue SAC LetterFinal Release of Retainage -
Administrative CloseProject Closed
06/08/2016 A, 100169 FM for Pump Station 102206/08/2016 A, PlanningPlanning Phase
Develop Remedial Action Plan (RAP)Develop Preliminary Engineer Report (PER)
05/20/2015 A, 100199 Basin 1022 Infiltration/Inflow Study and Repairs05/19/2015 A, Infiltration/Inflow
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 149 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1000 Infiltration/Inflow Phase 09/25/2014 A 05/19/2015 A 109Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 05/19/2015 A 109
B1005 SSES Phase 09/25/2014 A 05/19/2015 A 109B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 04/17/2015 A 05/06/2015 A 30B1040 Video Review 05/05/2015 A 05/19/2015 A 30
Project CProject Closeout 05/20/2015 A 05/20/2015 A 0B1235 Closeout Phase 05/20/2015 A 05/20/2015 A 0B1260 Project Closed 05/20/2015 A 0
Basin 1026Basin 1026 01/14/2016 A 08/02/2019 1261
100171 Pu100171 Pump Station 1026 Upgrade 01/14/2016 A 08/02/2019 1261DesignDesign 01/14/2016 A 03/25/2018 A 770
B1000 Design Phase 01/14/2016 A 03/25/2018 A 770B1010 Prepare and Submit Design Package 01/14/2016 A 02/19/2016 A 5B1020 Engage Design Consultant 02/19/2016 A 05/16/2016 A 20B1022 TA Preparation 05/17/2016 A 05/17/2016 A 1B1024 TA Approval Process 05/18/2016 A 11/08/2016 A 20B1030 Issue Design NTP 11/15/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 11/15/2016 A 02/15/2018 A 85
30% Des30% Design 11/15/2016 A 02/17/2017 A 115B1060 A/E Prepares 30% Construction Documents 11/15/2016 A 01/19/2017 A 50B1100 30% CDs Submittal 01/19/2017 A 0B1120 30% Review (MDWASD/PSIP Team) 01/20/2017 A 02/17/2017 A 30
90% Des90% Design 02/20/2017 A 02/15/2018 A 393B1170 A/E Prepares 90% Construction Documents 02/20/2017 A 07/14/2017 A 40B1180 90% CDs Submittal 07/14/2017 A 0B1190 90% Review (MDWASD/PSIP Team) 07/17/2017 A 08/10/2017 A 30B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 10/11/2017 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 10/11/2017 A 12/19/2017 A 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 12/27/2017 A 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 12/27/2017 A 02/15/2018 A 21B1260 90% CD PM Comments Evaluation Completed 02/15/2018 A 0B1262 MDWASD Union Concurrence Process 07/27/2017 A 08/17/2017 A 30
100% De100% Design 02/16/2018 A 03/25/2018 A 28B1270 A/E Prepares 100% Construction Documents 02/16/2018 A 03/15/2018 A 14B1280 100% CDs Submittal 03/15/2018 A 0B1290 100% Review (MDWASD/PSIP Team) 03/16/2018 A 03/25/2018 A 14B1300 Design Completed 03/25/2018 A 0
MDWASDMDWASD Procurement 03/26/2018 A 08/01/2018 108B1305 Procurement Phase 03/26/2018 A 08/01/2018 108B1310 Submit CDs to MDWASD Procurement Division 03/26/2018 A 0B1312 Bid Notice Preparation Period 03/27/2018 A 04/06/2018 A 33B1314 Bid Notice 04/06/2018 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 04/07/2018 A 05/15/2018 A 21B1320 Pre-Bid Conference 04/16/2018 A 04/16/2018 A 1B1322 Bidders Prepare Bids for Submittal 04/17/2018 A 05/31/2018 A 21B1330 Bids Submittal 05/31/2018 A 0B1340 MDWASD/PSIP Team Bids Evaluation 06/01/2018 A 06/26/2018 A 21B1350 Recommendation for Award Letter 06/26/2018 A 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Infiltration/Inflow Phase05/19/2015 A, Sanitary Sewer Evaluation SurveySSES Phase
Issue NTP to SSES ContractorConduct SSESVideo Review
05/20/2015 A, Project CloseoutCloseout Phase
Project Closed08/02/2019, Basin 1026
08/02/2019, 100171 Pump Stat03/25/2018 A, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval ProcessIssue Design NTP
Final Engineering Report Review & Approval (MDWASD/PSIP Team)02/17/2017 A, 30% Design
A/E Prepares 30% Construction Documents30% CDs Submittal30% Review (MDWASD/PSIP Team)
02/15/2018 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)
90% RER(DERM)FDEP Permit Submittal (Pump Station)90% RER(DERM)FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)
90% RER(Building Dept) Permit Review (Pump Station)90% CD PM Comments Evaluation Completed
MDWASD Union Concurrence Process03/25/2018 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed
08/01/2018, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation Period
Bid NoticeMDWASD/PSIP Team Prepare for Pre-Bid Conference
Pre-Bid ConferenceBidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 150 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1355 Contract Award (Purchase Order Approval) 06/27/2018 A 08/01/2018 14ConstrucConstruction 04/16/2018 A 04/04/2019 327
B1360 Construction Phase 04/16/2018 A 04/04/2019 327B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 08/01/2018 08/21/2018 21B1364 Pre-Construction Meeting 08/22/2018 08/22/2018 1B1366 WASD Issues NTP (Pre-Const to NTP) 08/23/2018 10/06/2018 45B1368 WASD Issues NTP (PO to NTP) 08/02/2018 10/06/2018 66B1370 Construction NTP 10/07/2018 0B1400 Construction Operations 10/07/2018 04/04/2019 180B1402 Substantial Completion 04/04/2019 0
DesignerDesigner Construction Support Services 04/16/2018 A 04/04/2019 290B1410 Designer Construction Support Services 04/16/2018 A 04/04/2019 290
Project CProject Closeout 04/04/2019 08/02/2019 120B1445 Closeout Phase 04/04/2019 08/02/2019 120B1450 Issue SAC Letter 04/04/2019 0B1470 Final Release of Retainage - Construction Contract 04/04/2019 0B1480 Administrative Closeout 04/05/2019 08/02/2019 120B1490 Project Closed 08/02/2019 0
Basin 1056Basin 1056 11/17/2015 A 10/30/2018 1002
100172 Pu100172 Pump Station 1056 Upgrade 11/17/2015 A 10/30/2018 1002DesignDesign 11/17/2015 A 06/26/2017 A 575
B1000 Design Phase 11/17/2015 A 06/26/2017 A 575B1010 Prepare and Submit Design Package 11/17/2015 A 11/17/2015 A 5B1020 Engage Design Consultant 11/17/2015 A 02/26/2016 A 20B1022 TA Preparation 02/29/2016 A 02/29/2016 A 1B1024 TA Approval Process 03/01/2016 A 03/25/2016 A 20B1030 Issue Design NTP 03/29/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 03/29/2016 A 12/08/2016 A 85
30% Des30% Design 03/29/2016 A 09/13/2016 A 146B1060 A/E Prepares 30% Construction Documents 03/29/2016 A 08/17/2016 A 30B1070 Geotechnical Engineering Services 03/29/2016 A 08/17/2016 A 20B1080 Surveying Services 03/29/2016 A 08/17/2016 A 15B1100 30% CDs Submittal 08/17/2016 A 0B1120 30% Review (MDWASD/PSIP Team) 08/18/2016 A 09/13/2016 A 10
90% Des90% Design 08/18/2016 A 05/02/2017 A 302B1170 A/E Prepares 90% Construction Documents 08/18/2016 A 11/07/2016 A 40B1180 90% CDs Submittal 11/07/2016 A 0B1190 90% Review (MDWASD/PSIP Team) 11/08/2016 A 12/08/2016 A 30B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 12/27/2016 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 12/27/2016 A 02/06/2017 A 45B1220 90% RER(Building Dept) Permit Submittal (Fire Dept. Municipal) 02/08/2017 A 0B1230 90% RER(Building Dept) Permit Review (Fire Dept. Municipal) 02/08/2017 A 05/02/2017 A 21B1240 90% Cutler Bay - BD Permit Submittal (Pump Station) 02/08/2017 A 0B1250 90% Cutler Bay - BD Permit Review (Pump Station) 02/08/2017 A 05/02/2017 A 15B1252 90% Cutler Bay - PWD Permit Submittal (Pump Station) 02/08/2017 A 0B1254 90% Cutler Bay - PWD Permit Review (Pump Station) 02/08/2017 A 05/02/2017 A 15B1260 90% CD PM Comments Evaluation Completed 05/02/2017 A 0B1262 MDWASD Union Concurrence Process 01/25/2017 A 02/22/2017 A 30
100% De100% Design 05/03/2017 A 06/26/2017 A 28
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Contract Award (Purchase Order Approval)04/04/2019, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Construction NTPConstruction OperationsSubstantial Completion04/04/2019, Designer Construction Suppo
Designer Construction Support Services08/02/2019, Project Closeout
Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction
Administrative CloseoutProject Closed
10/30/2018, Basin 1056
10/30/2018, 100172 Pump Station 1056 Upgrade06/26/2017 A, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval ProcessIssue Design NTP
Final Engineering Report Review & Approval (MDWASD/PSIP Team)09/13/2016 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal
30% Review (MDWASD/PSIP Team)05/02/2017 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)
90% RER(DERM)FDEP Permit Submittal (Pump Station)90% RER(DERM)FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Fire Dept. Municipal)
90% RER(Building Dept) Permit Review (Fire Dept. Municipal)90% Cutler Bay - BD Permit Submittal (Pump Station)
90% Cutler Bay - BD Permit Review (Pump Station)90% Cutler Bay - PWD Permit Submittal (Pump Station)
90% Cutler Bay - PWD Permit Review (Pump Station)90% CD PM Comments Evaluation Completed
MDWASD Union Concurrence Process06/26/2017 A, 100% Design
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 151 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1270 A/E Prepares 100% Construction Documents 05/03/2017 A 06/26/2017 A 10B1280 100% CDs Submittal 06/26/2017 A 0B1290 100% Review (MDWASD/PSIP Team) 06/26/2017 A 06/26/2017 A 10B1300 Design Completed 06/26/2017 A 0
MDWASDMDWASD Procurement 06/27/2017 A 12/01/2017 A 108B1305 Procurement Phase 06/27/2017 A 12/01/2017 A 108B1310 Submit CDs to MDWASD Procurement Division 06/27/2017 A 0B1312 Bid Notice Preparation Period 06/28/2017 A 07/27/2017 A 33B1314 Bid Notice 07/27/2017 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 07/28/2017 A 08/09/2017 A 14B1320 Pre-Bid Conference 08/10/2017 A 08/10/2017 A 1B1328 Bidders Prepare Bids for Submittal 08/11/2017 A 10/03/2017 A 21B1330 Bids Submittal 10/03/2017 A 0B1340 MDWASD/PSIP Team Bids Evaluation 10/04/2017 A 11/02/2017 A 21B1350 Recommendation for Award Letter 11/02/2017 A 0B1355 Contract Award (Purchase Order Approval) 11/03/2017 A 12/01/2017 A 14
ConstrucConstruction 08/10/2017 A 10/30/2018 446B1360 Construction Phase 08/10/2017 A 10/30/2018 446B1364 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 11/03/2017 A 12/17/2017 A 21B1366 Pre-Construction Meeting 12/18/2017 A 12/18/2017 A 1B1368 WASD Issues NTP (Pre-Const to NTP) 12/19/2017 A 07/01/2018 A 45B1369 WASD Issues NTP (PO to NTP) 12/02/2017 A 07/01/2018 A 57B1370 Construction NTP 07/02/2018 A 0B1400 Construction Operations 07/02/2018 A 10/30/2018 120B1402 Substantial Completion 10/30/2018 0
DesignerDesigner Construction Support Services 08/10/2017 A 10/30/2018 260B1410 Designer Construction Support Services 08/10/2017 A 10/30/2018 260
Project CProject Closeout 10/30/2018 10/30/2018 0B1445 Closeout Phase 10/30/2018 10/30/2018 0B1450 Issue SAC Letter 10/30/2018 0B1470 Final Release of Retainage - Construction Contract 10/30/2018 0B1480 Administrative Closeout 10/30/2018 0B1490 Project Closed 10/30/2018 0
Basin 1058Basin 1058 05/22/2015 A 11/29/2018 1288
100174 Pu100174 Pump Station 1058 Upgrade 12/17/2015 A 11/29/2018 990DesignDesign 12/17/2015 A 04/17/2017 A 441
B1000 Design Phase 12/17/2015 A 04/17/2017 A 441B1010 Prepare and Submit Design Package 12/17/2015 A 02/23/2016 A 5B1020 Engage Design Consultant 02/23/2016 A 04/13/2016 A 20B1022 TA Preparation 04/14/2016 A 04/14/2016 A 1B1024 TA Approval Process 04/15/2016 A 05/02/2016 A 20B1030 Issue Design NTP 05/16/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 05/16/2016 A 11/17/2016 A 85
30% Des30% Design 05/17/2016 A 09/02/2016 A 135B1060 A/E Prepares 30% Construction Documents 05/17/2016 A 08/05/2016 A 30B1070 Geotechnical Engineering Services 05/17/2016 A 08/05/2016 A 20B1080 Surveying Services 05/17/2016 A 08/05/2016 A 15B1100 30% CDs Submittal 08/05/2016 A 0B1120 30% Review (MDWASD/PSIP Team) 08/08/2016 A 09/02/2016 A 10
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
A/E Prepares 100% Construction Documents100% CDs Submittal
100% Review (MDWASD/PSIP Team)Design Completed
12/01/2017 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter
Contract Award (Purchase Order Approval)10/30/2018, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Construction NTPConstruction OperationsSubstantial Completion10/30/2018, Designer Construction Support Services
Designer Construction Support Services10/30/2018, Project Closeout
Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction ContractAdministrative CloseoutProject Closed
11/29/2018, Basin 1058
11/29/2018, 100174 Pump Station 1058 Upgrade04/17/2017 A, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval ProcessIssue Design NTP
Final Engineering Report Review & Approval (MDWASD/PSIP Team)09/02/2016 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services
30% CDs Submittal30% Review (MDWASD/PSIP Team)
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 152 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
90% Des90% Design 08/08/2016 A 04/17/2017 A 210B1170 A/E Prepares 90% Construction Documents 08/08/2016 A 10/19/2016 A 20B1180 90% CDs Submittal 10/19/2016 A 0B1190 90% Review (MDWASD/PSIP Team) 10/20/2016 A 11/17/2016 A 15B1200 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 12/28/2016 A 0B1210 90% RER(DERM)/FDEP Permit Review (Pump Station) 12/28/2016 A 01/13/2017 A 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 01/26/2017 A 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 01/26/2017 A 04/17/2017 A 21B1240 90% Cutler Bay - BD Permit Submittal (Pump Station) 01/26/2017 A 0B1250 90% Cutler Bay - BD Permit Review (Pump Station) 01/26/2017 A 04/17/2017 A 15B1252 90% Cutler Bay - PWD Permit Submittal (Pump Station) 01/26/2017 A 0B1254 90% Cutler Bay - PWD Permit Review (Pump Station) 01/26/2017 A 04/17/2017 A 15B1260 90% CD PM Comments Evaluation Completed 04/17/2017 A 0B1262 MDWASD/PSIP Concurrence Process 01/25/2017 A 02/22/2017 A 30
100% De100% Design 03/20/2017 A 04/06/2017 A 28B1270 A/E Prepares 100% Construction Documents 03/20/2017 A 03/31/2017 A 10B1280 100% CDs Submittal 03/31/2017 A 0B1290 100% Review (MDWASD/PSIP Team) 04/03/2017 A 04/06/2017 A 10B1300 Design Completed 04/06/2017 A 0
MDWASDMDWASD Procurement 04/06/2017 A 11/07/2017 A 78B1305 Procurement Phase 04/06/2017 A 11/07/2017 A 78B1310 Submit CDs to MDWASD Procurement Division 04/06/2017 A 0B1312 Bid Notice Preparation Period 04/07/2017 A 04/25/2017 A 23B1314 Bid Notice 04/25/2017 A 0B1316 MDWASAD/PSIP Team Prepare for Pre-Bid Conference 04/26/2017 A 05/22/2017 A 10B1320 Pre-Bid Conference 05/23/2017 A 05/23/2017 A 1B1322 Bidders Prepare Bids for Submittal 05/24/2017 A 06/21/2017 A 9B1330 Bids Submittal 06/21/2017 A 0B1340 MDWASD/PSIP Team Bids Evaluation 06/22/2017 A 07/20/2017 A 15B1350 Recommendation for Award Letter 07/20/2017 A 0B1355 Contract Award (Purchase Order Approval) 07/21/2017 A 11/07/2017 A 14
ConstrucConstruction 05/23/2017 A 08/01/2018 461B1360 Construction Phase 05/23/2017 A 08/01/2018 461B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 07/21/2017 A 08/29/2017 A 21B1364 Pre-Construction Meeting 08/30/2017 A 08/30/2017 A 1B1366 WASD Issues NTP (Pre-Const to NTP) 08/31/2017 A 01/07/2018 A 45B1368 WASD Issues NTP (PO to NTP) 11/07/2017 A 01/07/2018 A 57B1370 Construction NTP 01/08/2018 A 0B1400 Construction Operations 01/08/2018 A 08/01/2018 120B1402 Substantial Completion 08/01/2018 0
DesignerDesigner Construction Support Services 05/23/2017 A 08/01/2018 252B1410 Designer Construction Support Services 05/23/2017 A 08/01/2018 252
Project CProject Closeout 08/01/2018 11/29/2018 120B1445 Closeout Phase 08/01/2018 11/29/2018 120B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 08/02/2018 11/29/2018 120B1490 Project Closed 11/29/2018 0
100247 Ba100247 Basin 1058 Infiltration/Inflow Study and Repairs 05/22/2015 A 10/08/2015 A 376
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
04/17/2017 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)/FDEP Permit Submittal (Pump Station)90% RER(DERM)/FDEP Permit Review (Pump Station)
90% RER(Building Dept) Permit Submittal (Pump Station)90% RER(Building Dept) Permit Review (Pump Station)
90% Cutler Bay - BD Permit Submittal (Pump Station)90% Cutler Bay - BD Permit Review (Pump Station)
90% Cutler Bay - PWD Permit Submittal (Pump Station)90% Cutler Bay - PWD Permit Review (Pump Station)90% CD PM Comments Evaluation Completed
MDWASD/PSIP Concurrence Process04/06/2017 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal
100% Review (MDWASD/PSIP Team)Design Completed
11/07/2017 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid NoticeMDWASAD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter
Contract Award (Purchase Order Approval)08/01/2018, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Construction NTPConstruction OperationsSubstantial Completion08/01/2018, Designer Construction Support Services
Designer Construction Support Services11/29/2018, Project Closeout
Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction Contract
Administrative CloseoutProject Closed
10/08/2015 A, 100247 Basin 1058 Infiltration/Inflow Study and Repairs
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 153 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
InfiltratioInfiltration/Inflow 05/22/2015 A 10/07/2015 A 139B1000 Infiltration/Inflow Phase 05/22/2015 A 10/07/2015 A 139
CIPP RepCIPP Repairs 05/22/2015 A 10/07/2015 A 139B1070 CIPP Phase 05/22/2015 A 10/07/2015 A 139B1090 Issue NTP for CIPP Repairs 05/22/2015 A 0B1100 Conduct CIPP Repairs 10/07/2015 A 10/07/2015 A 1
Project CProject Closeout 10/08/2015 A 10/08/2015 A 0B1250 Closeout Phase 10/08/2015 A 10/08/2015 A 0B1280 Project Closed 10/08/2015 A 0
Basin 1065Basin 1065 07/01/2015 A 11/29/2019 1093
100175 Pu100175 Pump Station 1065 Upgrade 07/01/2015 A 11/29/2019 1093DesignDesign 07/01/2015 A 08/29/2018 636
B1000 Design Phase 07/01/2015 A 08/29/2018 636B1002 Prepare Request for SOW for Survey Only 07/01/2015 A 07/07/2015 A 5B1004 TA Approval Process (Survey Only) 07/08/2015 A 07/14/2015 A 20B1006 Waiting Period Prior to Design Package Preparation 07/15/2015 A 05/10/2016 A 5B1010 Prepare and Submit Design Package 05/11/2016 A 05/12/2016 A 5B1020 Engage Design Consultant 05/13/2016 A 11/18/2016 A 20B1022 TA Preparation 11/21/2016 A 11/21/2016 A 1B1024 TA Approval Process 11/22/2016 A 02/10/2017 A 20B1030 Issue Design NTP 02/16/2017 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 02/16/2017 A 08/01/2018 65
30% Des30% Design 07/14/2015 A 07/20/2017 A 241B1060 A/E Prepares 30% Construction Documents 02/16/2017 A 06/20/2017 A 50B1080 Surveying Services 07/14/2015 A 07/28/2015 A 19B1100 30% CDs Submittal 06/20/2017 A 0B1120 30% Review (MDWASD/PSIP Team) 06/21/2017 A 07/20/2017 A 30
90% Des90% Design 06/21/2017 A 08/01/2018 394B1170 A/E Prepares 90% Construction Documents 06/21/2017 A 12/04/2017 A 40B1180 90% CDs Submittal 12/04/2017 A 0B1190 90% Review (MDWASD/PSIP Team) 12/05/2017 A 01/03/2018 A 30B1200 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 02/06/2018 A 0B1210 90% RER(DERM)/FDEP Permit Review (Pump Station) 02/06/2018 A 04/17/2018 A 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 06/18/2018 A 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 06/18/2018 A 08/01/2018 21B1260 90% CD PM Comments Evaluation Completed 08/01/2018 0
100% De100% Design 08/02/2018 08/29/2018 28B1270 A/E Prepares 100% Construction Documents 08/02/2018 08/15/2018 14B1280 100% CDs Submittal 08/15/2018 0B1290 100% Review (MDWASD/PSIP Team) 08/16/2018 08/29/2018 14B1300 Design Completed 08/29/2018 0
MDWASDMDWASD Procurement 08/29/2018 12/11/2018 104B1305 Procurement Phase 08/29/2018 12/11/2018 104B1310 Submit CDs to MDWASD Procurement Division 08/29/2018 0B1312 Bid Notice preparation Period 08/30/2018 10/01/2018 33B1314 Bid Notice 10/01/2018 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 10/02/2018 10/15/2018 14B1320 Pre-Bid Conference 10/16/2018 10/16/2018 1B1328 Bidders Prepare Bids for Submittal 10/17/2018 11/06/2018 21
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
10/07/2015 A, Infiltration/Inflow
Infiltration/Inflow Phase10/07/2015 A, CIPP Repairs
CIPP PhaseIssue NTP for CIPP Repairs
Conduct CIPP Repairs10/08/2015 A, Project Closeout
Closeout PhaseProject Closed
11/29/2019, Basin 106
11/29/2019, 100175 P08/29/2018, Design
Design PhasePrepare Request for SOW for Survey Only
TA Approval Process (Survey Only)Waiting Period Prior to Design Package PreparationPrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval ProcessIssue Design NTP
Final Engineering Report Review & Approval (MDWASD/PSIP 07/20/2017 A, 30% Design
A/E Prepares 30% Construction DocumentsSurveying Services
30% CDs Submittal30% Review (MDWASD/PSIP Team)
08/01/2018, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)
90% RER(DERM)/FDEP Permit Submittal (Pump Station)90% RER(DERM)/FDEP Permit Review (Pump Station)
90% RER(Building Dept) Permit Submittal (Pump Station)90% RER(Building Dept) Permit Review (Pump Station)90% CD PM Comments Evaluation Completed
08/29/2018, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed
12/11/2018, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for Submittal
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 154 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1330 Bids Submittal 11/06/2018 0B1340 MDWASD/PSIP Team Bids Evaluation 11/07/2018 11/27/2018 21B1350 Recommendation for Award Letter 11/27/2018 0B1355 Contract Award (Purchase Order Approval) 11/28/2018 12/11/2018 14
ConstrucConstruction 10/16/2018 08/01/2019 290B1360 Construction Phase 10/16/2018 08/01/2019 290B1364 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 11/28/2018 12/18/2018 21B1366 Pre-Construction Meeting 12/19/2018 12/19/2018 1B1368 WASD Issues NTP (Pre-Const to NTP) 12/20/2018 02/02/2019 45B1369 WASD Issues NTP (PO to NTP) 12/12/2018 02/02/2019 53B1370 Construction NTP 02/03/2019 0B1400 Construction Operations 02/03/2019 08/01/2019 180B1402 Substantial Completion 08/01/2019 0
DesignerDesigner Construction Support Services 10/16/2018 08/01/2019 290B1410 Designer Construction Support Services 10/16/2018 08/01/2019 290
Project CProject Closeout 08/01/2019 11/29/2019 120B1445 Closeout Phase 08/01/2019 11/29/2019 120B1450 Issue SAC Letter 08/01/2019 0B1470 Final Release of Retainage - Construction Contract 08/01/2019 0B1480 Administrative Closeout 08/02/2019 11/29/2019 120B1490 Project Closed 11/29/2019 0
Basin 1067Basin 1067 10/01/2014 A 08/31/2018 1428
100178 Pu100178 Pump Station 1067 Upgrade 10/01/2014 A 08/31/2018 1428DesignDesign 10/01/2014 A 06/23/2016 A 616
B1000 Design Phase 10/01/2014 A 06/23/2016 A 616B1010 Prepare and Submit Design Package 10/01/2014 A 10/07/2014 A 5B1020 Engage Design Consultant 10/08/2014 A 02/04/2015 A 20B1022 TA Approval Process 02/05/2015 A 03/11/2015 A 20B1024 TA Approval Process (Survey) 02/16/2015 A 03/19/2015 A 20B1030 Issue Design NTP 03/16/2015 A 0B1031 Issue Survey NTP 03/24/2015 A 0B1040 A/E Develops and Submits Final Engineering Report 03/16/2015 A 04/07/2016 A 125B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 03/16/2015 A 11/18/2015 A 80
30% Des30% Design 03/17/2015 A 06/19/2015 A 77B1060 A/E Prepares 30% Construction Documents 03/17/2015 A 05/19/2015 A 30B1070 Geotechnical Engineering Services 03/17/2015 A 05/19/2015 A 20B1080 Surveying Services 03/25/2015 A 05/19/2015 A 19B1100 30% CDs Submittal 05/19/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 05/20/2015 A 06/19/2015 A 10
60% Des60% Design 05/20/2015 A 08/21/2015 A 106B1130 A/E Prepares 60% Construction Documents 05/20/2015 A 08/14/2015 A 20B1140 60% CDs Submittal 08/14/2015 A 0B1160 60% Review (MDWASD/PSIP Team) 08/17/2015 A 08/21/2015 A 10
90% Des90% Design 08/17/2015 A 04/07/2016 A 244B1170 A/E Prepares 90% Construction Documents 08/17/2015 A 09/02/2015 A 20B1180 90% CDs Submittal 09/03/2015 A 0B1190 90% Review (MDWASD/PSIP Team) 09/04/2015 A 11/18/2015 A 15B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 11/19/2015 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 11/20/2015 A 12/29/2015 A 15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Bids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)
08/01/2019, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-ConstructionPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Construction NTPConstruction OperationsSubstantial Completion08/01/2019, Designer Constructi
Designer Construction Support S11/29/2019, Project Clo
Closeout PhaseIssue SAC LetterFinal Release of Retainage - Con
Administrative CloseouProject Closed
08/31/2018, Basin 1067
08/31/2018, 100178 Pump Station 1067 Upgrade06/23/2016 A, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Approval ProcessTA Approval Process (Survey)Issue Design NTPIssue Survey NTP
A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)
06/19/2015 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal
30% Review (MDWASD/PSIP Team)08/21/2015 A, 60% Design
A/E Prepares 60% Construction Documents60% CDs Submittal
60% Review (MDWASD/PSIP Team)04/07/2016 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)
90% RER(DERM)FDEP Permit Review (Pump Station)
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 155 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1222 90% Miami - BD Permit Submittal (Pump Station) 02/16/2016 A 0B1224 90% Miami - BD Permit Review (Pump Station) 02/16/2016 A 02/25/2016 A 15B1226 90% Miami - PWD Permit Submittal (Pump Station) 02/11/2016 A 0B1228 90% Miami - PWD Permit Review (Pump Station) 02/11/2016 A 04/07/2016 A 15B1260 90% CD PM Comments Evaluation Completed 04/07/2016 A 0
100% De100% Design 04/28/2016 A 06/23/2016 A 44B1270 A/E Prepares 100% Construction Documents 04/28/2016 A 06/22/2016 A 10B1280 100% CDs Submittal 06/23/2016 A 0B1290 100% Review (MDWASD/PSIP Team) 06/23/2016 A 06/23/2016 A 10B1300 Design Completed 06/23/2016 A 0
MDWASDMDWASD Procurement 03/01/2016 A 06/13/2016 A 97B1305 Procurement Phase 03/01/2016 A 06/13/2016 A 97B1310 Submit CDs to MDWASD Procurement Division 03/01/2016 A 0B1312 Bid Notice Preparation Period 03/02/2016 A 03/15/2016 A 23B1314 Bid Notice 03/15/2016 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 03/16/2016 A 04/05/2016 A 10B1320 Pre-Bid Conference 04/06/2016 A 04/06/2016 A 1B1328 Bidders Prepare Bids for Submittal 04/07/2016 A 04/27/2016 A 15B1330 Bids Submittal 04/27/2016 A 0B1340 MDWASD/PSIP Team Bids Evaluation 04/28/2016 A 05/05/2016 A 15B1350 Recommendation for Award Letter 05/05/2016 A 0B1355 Contract Award (Purchase Order Approval) 05/06/2016 A 06/13/2016 A 10
ConstrucConstruction 04/06/2016 A 08/01/2018 827B1360 Construction Phase 04/06/2016 A 08/01/2018 827B1364 MDWASD/PSIP Team Prepare for Pre-construction Meeting 05/06/2016 A 06/23/2016 A 15B1366 Pre-Construction Meeting 06/24/2016 A 06/24/2016 A 1B1368 WASD Issues NTP (PO to NTP) 06/13/2016 A 07/25/2016 A 57B1370 Construction NTP 07/25/2016 A 0B1400 Construction Operations 07/25/2016 A 08/01/2018 140B1400 Original Construction Duration 07/25/2016 A 12/12/2016 A 140B1400 Change Order #1 - Unforeseen ATT 12/13/2016 A 04/20/2017 A 140B1400 Change Order #2 - Hurricane Irma 04/21/2017 A 05/11/2017 A 140B1400 Change Order #3 - FPL and Guy Wire Change 05/12/2017 A 11/04/2017 A 140B1402 Substantial Completion 08/01/2018 0
DesignerDesigner Construction Support Services 04/06/2016 A 08/01/2018 304B1410 Designer Construction Support Services 04/06/2016 A 08/01/2018 304
Project CProject Closeout 08/05/2016 A 08/31/2018 756B1445 Closeout Phase 08/05/2016 A 08/31/2018 756B1450 Issue SAC Letter 08/05/2016 A 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 08/02/2018 08/31/2018 30B1490 Project Closed 08/31/2018 0
100251 Ba100251 Basin 1067 Infiltration/Inflow Study and Repairs 10/30/2015 A 06/15/2016 A 246InfiltratioInfiltration/Inflow 10/30/2015 A 06/14/2016 A 20
B1000 Infiltration/Inflow Phase 10/30/2015 A 06/14/2016 A 20ManholeManhole Repairs 10/30/2015 A 06/14/2016 A 20
B1110 Manhole Phase 10/30/2015 A 06/14/2016 A 20B1130 Issue NTP for Manhole Repairs 10/30/2015 A 0B1140 Conduct Manhole Repairs 03/14/2016 A 06/14/2016 A 20
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
90% Miami - BD Permit Submittal (Pump Station)90% Miami - BD Permit Review (Pump Station)
90% Miami - PWD Permit Submittal (Pump Station)90% Miami - PWD Permit Review (Pump Station)
90% CD PM Comments Evaluation Completed06/23/2016 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed
06/13/2016 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)
08/01/2018, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-construction MeetingPre-Construction Meeting
WASD Issues NTP (PO to NTP)Construction NTP
Construction OperationsOriginal Construction Duration
Change Order #1 - Unforeseen ATTChange Order #2 - Hurricane Irma
Change Order #3 - FPL and Guy Wire Change
Substantial Completion08/01/2018, Designer Construction Support Services
Designer Construction Support Services08/31/2018, Project Closeout
Closeout PhaseIssue SAC Letter
Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed
06/15/2016 A, 100251 Basin 1067 Infiltration/Inflow Study and Repairs06/14/2016 A, Infiltration/Inflow
Infiltration/Inflow Phase06/14/2016 A, Manhole Repairs
Manhole PhaseIssue NTP for Manhole Repairs
Conduct Manhole Repairs
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 156 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
Project CProject Closeout 06/15/2016 A 06/15/2016 A 0B1250 Closeout Phase 06/15/2016 A 06/15/2016 A 0B1280 Project Closed 06/15/2016 A 0
Basin 1068Basin 1068 04/22/2015 A 08/01/2018 1224
100179 Pu100179 Pump Station 1068 Upgrade 04/22/2015 A 08/01/2018 1224DesignDesign 04/22/2015 A 07/20/2016 A 925
B1000 Design Phase 04/22/2015 A 07/20/2016 A 925B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 04/22/2015 A 04/29/2015 A 5B1020 Engage Design Consultant 04/30/2015 A 06/19/2015 A 20B1025 TA Approval Process 07/08/2015 A 07/16/2015 A 15B1030 Issue Design NTP 07/30/2015 A 0B1040 A/E Develops and Submits Final Engineering Report 07/30/2015 A 06/07/2016 A 120B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 07/30/2015 A 04/12/2016 A 95
30% Des30% Design 07/30/2015 A 12/01/2015 A 69B1060 A/E Prepares 30% Construction Documents 07/30/2015 A 10/09/2015 A 30B1070 Geotechnical Engineering Services 07/30/2015 A 10/09/2015 A 20B1080 Surveying Services 07/30/2015 A 10/09/2015 A 21B1100 30% CDs Submittal 10/09/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 10/13/2015 A 12/01/2015 A 10
60% Des60% Design 10/13/2015 A 02/16/2016 A 40B1130 A/E Prepares 60% Construction Documents 10/13/2015 A 12/28/2015 A 20B1140 60% CDs Submittal 12/28/2015 A 0B1160 60% Review (MDWASD/PSIP Team) 12/29/2015 A 02/16/2016 A 10
90% Des90% Design 12/29/2015 A 06/07/2016 A 198B1170 A/E Prepares 90% Construction Documents 12/29/2015 A 03/28/2016 A 20B1180 90% CDs Submittal 03/28/2016 A 0B1190 90% Review (MDWASD/PSIP Team) 03/28/2016 A 04/12/2016 A 15B1200 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 04/22/2016 A 0B1210 90% RER(DERM)/FDEP Permit Review (Pump Station) 04/22/2016 A 05/18/2016 A 15B1220 90% RER (Building Dept) Permit Submittal 05/27/2016 A 0B1230 90% RER (Building Department) Permit Review 05/27/2016 A 06/07/2016 A 15B1240 90% PWWMD Permit Submittal (Pump Station) 04/22/2016 A 0B1250 90% PWWMD Permit Review (Pump Station) 04/22/2016 A 05/18/2016 A 15B1260 90% CD PM Comments Evaluation Completed 06/07/2016 A 0
100% De100% Design 05/25/2016 A 07/20/2016 A 45B1270 A/E Prepares 100% Construction Documents 05/25/2016 A 07/20/2016 A 10B1280 100% CDs Submittal 07/20/2016 A 0B1290 100% Review (MDWASD/PSIP Team) 05/25/2016 A 07/20/2016 A 10B1300 Design Completed 07/20/2016 A 0
MDWASDMDWASD Procurement 05/04/2016 A 08/04/2016 A 73B1305 Procurement Phase 05/04/2016 A 08/04/2016 A 73B1310 Submit CDs to MDWASD Procurement Division 05/04/2016 A 0B1312 Bid Notice Preparation Period 05/04/2016 A 05/24/2016 A 23B1314 Bid Notice 05/25/2016 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 05/26/2016 A 06/01/2016 A 10B1320 Pre-Bid Conference 06/02/2016 A 06/02/2016 A 1B1328 Bidders Prepare Bids for Submittal 06/03/2016 A 06/24/2016 A 15B1330 Bids Submittal 06/24/2016 A 0B1340 MDWASD/PSIP Team Bids Evaluation 06/27/2016 A 07/11/2016 A 15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
06/15/2016 A, Project Closeout
Closeout PhaseProject Closed
08/01/2018, Basin 1068
08/01/2018, 100179 Pump Station 1068 Upgrade07/20/2016 A, Design
Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book
Engage Design ConsultantTA Approval Process
Issue Design NTPA/E Develops and Submits Final Engineering Report
Final Engineering Report Review & Approval (MDWASD/PSIP Team)12/01/2015 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal
30% Review (MDWASD/PSIP Team)02/16/2016 A, 60% Design
A/E Prepares 60% Construction Documents60% CDs Submittal
60% Review (MDWASD/PSIP Team)06/07/2016 A, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)
90% RER(DERM)/FDEP Permit Submittal (Pump Station)90% RER(DERM)/FDEP Permit Review (Pump Station)90% RER (Building Dept) Permit Submittal90% RER (Building Department) Permit Review90% PWWMD Permit Submittal (Pump Station)
90% PWWMD Permit Review (Pump Station)90% CD PM Comments Evaluation Completed
07/20/2016 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal
100% Review (MDWASD/PSIP Team)Design Completed08/04/2016 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids Evaluation
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 157 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1350 Recommendation for Award Letter 07/11/2016 A 0B1355 Contract Award (Purchase Order Approval) 07/12/2016 A 08/04/2016 A 10
ConstrucConstruction 06/02/2016 A 06/19/2017 A 826B1360 Construction Phase 06/02/2016 A 06/19/2017 A 826B1364 MDWASD/PSIP Team Prepare for Pre-construction Meeting 07/12/2016 A 07/20/2016 A 15B1365 Pre-Construction Meeting 07/21/2016 A 07/21/2016 A 1B1368 WASD Issues NTP (PO to NTP) 08/04/2016 A 11/28/2016 A 57B1370 Construction NTP 11/28/2016 A 0B1400 Construction Operations 11/28/2016 A 06/19/2017 A 100B1402 Substantial Completion 06/19/2017 A 0
DesignerDesigner Construction Support Services 06/02/2016 A 06/19/2017 A 259B1410 Designer Construction Support Services 06/02/2016 A 06/19/2017 A 259
Project CProject Closeout 08/05/2016 A 08/01/2018 726B1445 Closeout Phase 08/05/2016 A 08/01/2018 726B1450 Issue SAC Letter 08/05/2016 A 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 06/20/2017 A 08/01/2018 120B1490 Project Closed 08/01/2018 0
Basin 1201Basin 1201 08/26/2016 A 12/19/2019 1205
100181 Pu100181 Pump Station 1201 Upgrade 08/26/2016 A 12/19/2019 1205DesignDesign 08/26/2016 A 09/18/2018 748
B1000 Design Phase 08/26/2016 A 09/18/2018 748B1010 Prepare and Submit Design Package 08/26/2016 A 08/26/2016 A 5B1020 Engage Design Consultant 08/26/2016 A 10/07/2016 A 20B1022 TA Preparation 10/10/2016 A 10/10/2016 A 1B1024 TA Approval Process 10/11/2016 A 11/08/2016 A 20B1030 Issue Design NTP 11/10/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 11/10/2016 A 08/21/2018 65
30% Des30% Design 11/10/2016 A 01/29/2018 A 449B1060 A/E Prepares 30% Construction Documents 11/10/2016 A 02/13/2017 A 50B1100 30% CDs Submittal 02/13/2017 A 0B1120 30% Review (MDWASD/PSIP Team) 02/14/2017 A 03/21/2017 A 30B1122 SOW for Demo Exist. Generator Bldg., Odor Control System & N 03/22/2017 A 06/20/2017 A 30B1124 TA Rev 1 Preparation 06/21/2017 A 06/21/2017 A 1B1126 TA Rev 1 Approval Process 06/22/2017 A 08/17/2017 A 57B1128 A/E Prepares 30% Construction Documents (Re-Design) 09/21/2017 A 12/27/2017 A 64B1130 30% CDs Submittal (Re-Design) 12/27/2017 A 0B1132 30% Review (MDWASD/PSIP Team) (Re-Design) 12/28/2017 A 01/29/2018 A 30
90% Des90% Design 01/30/2018 A 08/21/2018 226B1170 A/E Prepares 90% Construction Documents 01/30/2018 A 02/26/2018 A 36B1180 90% CDs Submittal 02/26/2018 A 0B1190 90% Review (MDWASD/PSIP Team) 02/27/2018 A 03/30/2018 A 30B1200 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 05/03/2018 A 0B1210 90% RER(DERM)/FDEP Permit Review (Pump Station) 05/03/2018 A 07/16/2018 A 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 08/01/2018 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 08/01/2018 08/21/2018 21B1240 90% Doral - BD Permit Submittal (Pump Station) 07/17/2018 A 0B1250 90% Doral - BD Permit Review (Pump Station) 07/17/2018 A 08/06/2018 21B1260 90% CD PM Comments Evaluation Completed 08/21/2018 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
Recommendation for Award LetterContract Award (Purchase Order Approval)
06/19/2017 A, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-construction MeetingPre-Construction Meeting
WASD Issues NTP (PO to NTP)Construction NTP
Construction OperationsSubstantial Completion
06/19/2017 A, Designer Construction Support Services
Designer Construction Support Services08/01/2018, Project Closeout
Closeout PhaseIssue SAC Letter
Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed
12/19/2019, Basin 12
12/19/2019, 100181 09/18/2018, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval ProcessIssue Design NTP
Final Engineering Report Review & Approval (MDWASD/PSIP01/29/2018 A, 30% Design
A/E Prepares 30% Construction Documents30% CDs Submittal
30% Review (MDWASD/PSIP Team)SOW for Demo Exist. Generator Bldg., Odor Control System & New GeneratorTA Rev 1 Preparation
TA Rev 1 Approval ProcessA/E Prepares 30% Construction Documents (Re-Design)
30% CDs Submittal (Re-Design)30% Review (MDWASD/PSIP Team) (Re-Design)
08/21/2018, 90% Design
A/E Prepares 90% Construction Documents90% CDs Submittal
90% Review (MDWASD/PSIP Team)90% RER(DERM)/FDEP Permit Submittal (Pump Station)
90% RER(DERM)/FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)
90% RER(Building Dept) Permit Review (Pump Station)90% Doral - BD Permit Submittal (Pump Station)90% Doral - BD Permit Review (Pump Station)90% CD PM Comments Evaluation Completed
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 158 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
100% De100% Design 08/22/2018 09/18/2018 28B1270 A/E Prepares 100% Construction Documents 08/22/2018 09/04/2018 14B1280 100% CDs Submittal 09/04/2018 0B1290 100% Review (MDWASD/PSIP Teama) 09/05/2018 09/18/2018 14B1300 Design Completed 09/18/2018 0
MDWASDMDWASD Procurement 09/18/2018 12/31/2018 104B1305 Procurement Phase 09/18/2018 12/31/2018 104B1310 Submit CDs to MDWASD Procurement Division 09/18/2018* 0B1312 Bid Notice Preparation Period 09/19/2018 10/21/2018 33B1314 Bid Notice 10/21/2018 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 10/22/2018 11/04/2018 14B1320 Pre-Bid Conference 11/05/2018 11/05/2018 1B1328 Bidders Prepare Bids for Submittal 11/06/2018 11/26/2018 21B1330 Bids Submittal 11/26/2018 0B1340 MDWASD/PSIP Team Bids Evaluation 11/27/2018 12/17/2018 21B1350 Recommendation for Award Letter 12/17/2018 0B1355 Contract Award (Purchase Order Approval) 12/18/2018 12/31/2018 14
ConstrucConstruction 11/05/2018 08/21/2019 290B1360 Construction Phase 11/05/2018 08/21/2019 290B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 12/18/2018 01/07/2019 21B1364 Pre-Construction Meeting 01/08/2019 01/08/2019 1B1366 WASD Issues NTP (Pre-Const to NTP) 01/09/2019 02/22/2019 45B1369 WASD Issues NTP (PO to NTP) 01/01/2019 02/22/2019 53B1370 Construction NTP 02/23/2019 0B1400 Construction Operations 02/23/2019 08/21/2019 180B1402 Substantial Completion 08/21/2019 0
DesignerDesigner Construction Support Services 11/05/2018 08/21/2019 290B1410 Designer Construction Support Services 11/05/2018 08/21/2019 290
Project CProject Closeout 08/21/2019 12/19/2019 120B1445 Closeout Phase 08/21/2019 12/19/2019 120B1450 Issue SAC Letter 08/21/2019 0B1470 Final Release of Retainage - Construction Contract 08/21/2019 0B1480 Administrative Closeout 08/22/2019 12/19/2019 120B1490 Project Closed 12/19/2019 0
Basin 1306Basin 1306 05/09/2016 A 03/29/2019 1031
100182 Pu100182 Pump Station 1306(AM) Upgrade 05/09/2016 A 03/29/2019 1031DesignDesign 05/09/2016 A 07/28/2017 A 474
B1000 Design Phase 05/09/2016 A 07/28/2017 A 474B1010 Prepare and Submit Design Package 05/09/2016 A 05/11/2016 A 5B1020 Engage Design Consultant 05/11/2016 A 07/05/2016 A 20B1022 TA Preparation 07/06/2016 A 07/07/2016 A 1B1024 TA Approval Process 07/07/2016 A 09/12/2016 A 20B1030 Issue Design NTP 10/18/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/18/2016 A 06/30/2017 A 65
30% Des30% Design 10/18/2016 A 12/08/2016 A 55B1060 A/E Prepares 30% Construction Documents 10/18/2016 A 11/03/2016 A 30B1070 Geotechnical Engineering Services 10/18/2016 A 11/03/2016 A 20B1080 Surveying Services 10/18/2016 A 11/03/2016 A 15B1100 30% CDs Submittal 11/03/2016 A 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
09/18/2018, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Teama)Design Completed
12/31/2018, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference
Bidders Prepare Bids for SubmittalBids Submittal
MDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)
08/21/2019, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-ConstructioPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Construction NTPConstruction OperationsSubstantial Completion08/21/2019, Designer Construc
Designer Construction Support 12/19/2019, Project C
Closeout PhaseIssue SAC LetterFinal Release of Retainage - Co
Administrative CloseoProject Closed
03/29/2019, Basin 1306
03/29/2019, 100182 Pump Station 1306(A07/28/2017 A, Design
Design PhasePrepare and Submit Design Package
Engage Design ConsultantTA Preparation
TA Approval ProcessIssue Design NTP
Final Engineering Report Review & Approval (MDWASD/PSIP Team)12/08/2016 A, 30% Design
A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services
30% CDs Submittal
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 159 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
B1120 30% Review (MDWASD/PSIP Team) 11/07/2016 A 12/08/2016 A 1090% Des90% Design 11/07/2016 A 06/30/2017 A 264
B1170 A/E Prepares 90% Construction Documents 11/07/2016 A 01/04/2017 A 40B1172 90% Construction Documents Placed On-Hold 01/05/2017 A 01/24/2017 A 14B1174 A/E Prepares (Resumed) 90% Construction Documents 01/25/2017 A 02/28/2017 A 40B1180 90% CDs Submittal 02/28/2017 A 0B1190 90% Review (MDWASD/PSIP Team) 02/28/2017 A 03/15/2017 A 30B1200 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 04/19/2017 A 0B1210 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 04/19/2017 A 06/09/2017 A 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 06/12/2017 A 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 06/12/2017 A 06/30/2017 A 21B1260 90% CD PM Comments Evaluation Completed 06/30/2017 A 0B1262 MDWASD Union Concurrence Process 04/11/2017 A 05/01/2017 A 30
100% De100% Design 07/03/2017 A 07/28/2017 A 28B1270 A/E Prepares 100% Construction Documents 07/03/2017 A 07/28/2017 A 10B1280 100% CDs Submittal 07/28/2017 A 0B1290 100% Review (MDWASD/PSIP Team) 07/28/2017 A 07/28/2017 A 10B1300 Design Completed 07/28/2017 A 0
MDWASDMDWASD Procurement 07/28/2017 A 10/25/2017 A 76B1305 Procurement Phase 07/28/2017 A 10/25/2017 A 76B1310 Submit CDs to MDWASD Procurement Division 07/28/2017 A 0B1312 Bid Notice Preparation Period 07/31/2017 A 08/14/2017 A 33B1314 Bid Notice 08/14/2017 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conferencce 08/15/2017 A 08/21/2017 A 14B1320 Pre-Bid Conference 08/22/2017 A 08/22/2017 A 1B1328 Bidders Prepare Bids for Submittal 08/23/2017 A 09/14/2017 A 21B1330 Bids Submittal 09/14/2017 A 0B1340 MDWASD/PSIP Team Bids Evaluation 09/15/2017 A 10/03/2017 A 21B1350 Recommendation for Award Letter 10/03/2017 A 0B1355 Contract Award (Purchase Order Approval) 10/04/2017 A 10/25/2017 A 14
ConstrucConstruction 08/22/2017 A 11/29/2018 442B1360 Construction Phase 08/22/2017 A 11/29/2018 442B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 10/04/2017 A 11/08/2017 A 21B1365 Pre-Construction Meeting 11/09/2017 A 11/09/2017 A 1B1366 WASD Issues NTP (Pre-Const to NTP) 11/10/2017 A 07/01/2018 A 45B1368 WASD Issues NTP (PO to NTP) 10/26/2017 A 07/01/2018 A 57B1370 Construction NTP 07/02/2018 A 0B1400 Construction Operations 07/02/2018 A 11/29/2018 151B1402 Substantial Completion 11/29/2018 0
DesignerDesigner Construction Support Services 08/22/2017 A 11/29/2018 246B1410 Designer Construction Support Services 08/22/2017 A 11/29/2018 246
Project CProject Closeout 11/29/2018 03/29/2019 120B1445 Closeout Phase 11/29/2018 03/29/2019 120B1450 Issue SAC Letter 11/29/2018 0B1470 Final Release of Retainage - Construction Contract 11/29/2018 0B1480 Administrative Closeout 11/30/2018 03/29/2019 120B1490 Project Closed 03/29/2019 0
Basin 1311Basin 1311 09/01/2015 A 03/31/2017 A 913
100183 Pu100183 Pump Station 1311 Upgrade 09/01/2015 A 03/31/2017 A 913
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
30% Review (MDWASD/PSIP Team)06/30/2017 A, 90% Design
A/E Prepares 90% Construction Documents90% Construction Documents Placed On-Hold
A/E Prepares (Resumed) 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)
90% RER(DERM)/FDEP Permit Submittal (Pump Station)90% RER(DERM)/FDEP Permit Submittal (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)90% RER(Building Dept) Permit Review (Pump Station)
90% CD PM Comments Evaluation CompletedMDWASD Union Concurrence Process
07/28/2017 A, 100% Design
A/E Prepares 100% Construction Documents100% CDs Submittal
100% Review (MDWASD/PSIP Team)Design Completed
10/25/2017 A, MDWASD Procurement
Procurement PhaseSubmit CDs to MDWASD Procurement Division
Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferenccePre-Bid Conference
Bidders Prepare Bids for SubmittalBids SubmittalMDWASD/PSIP Team Bids Evaluation
Recommendation for Award LetterContract Award (Purchase Order Approval)
11/29/2018, Construction
Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting
WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)
Construction NTPConstruction OperationsSubstantial Completion11/29/2018, Designer Construction Support Services
Designer Construction Support Services03/29/2019, Project Closeout
Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction Contract
Administrative CloseoutProject Closed
03/31/2017 A, Basin 1311
03/31/2017 A, 100183 Pump Station 1311 Upgrade
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 160 of 161 TASK filter: All Activities© Oracle Corporation
Activity ID Activity Name Start Finish OriginalDuration
DesignDesign 02/01/2016 A 10/25/2016 A 166B1000 Design Phase 02/01/2016 A 10/25/2016 A 166B1040 A/E Develops and Submits Final Engineering Report 02/01/2016 A 04/20/2016 A 11B1050 Final Engineering Report Review & Approval (PSIP Team) 04/21/2016 A 06/24/2016 A 5
90% Des90% Design 07/22/2016 A 10/25/2016 A 15B1160 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 07/22/2016 A 0B1170 90% RER(DERM)/FDEP Permit Review (Pump Station) 07/22/2016 A 10/25/2016 A 15
MDWASDMDWASD Procurement 09/01/2015 A 01/19/2016 A 99B1265 Procurement Phase 09/01/2015 A 01/19/2016 A 99B1285 Bidders Prepare Bids for Submittal 09/01/2015 A 09/01/2015 A 3B1290 Bids Submittal 09/01/2015 A 0B1310 Recommendation for Award Letter 09/02/2015 A 0B1315 Contract Award (Purchase Order Approval) 09/02/2015 A 09/02/2015 A 1B1317 Pumps Manufacturing and Delivery 09/02/2015 A 01/19/2016 A 99
ConstrucConstruction 10/26/2016 A 11/23/2016 A 31B1320 Construction Phase 10/26/2016 A 11/23/2016 A 31B1330 Construction NTP 10/26/2016 A 0B1360 Construction Operations 10/26/2016 A 11/23/2016 A 11B1365 Substantial Completion 11/23/2016 A 0
Project CProject Closeout 11/24/2016 A 03/31/2017 A 577B1405 Closeout Phase 11/24/2016 A 03/31/2017 A 577B1410 Issue SAC Letter 02/16/2017 A 0B1440 Administrative Closeout 11/24/2016 A 03/31/2017 A 30B1450 Project Closed 03/31/2017 A 0
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020
10/25/2016 A, Design
Design PhaseA/E Develops and Submits Final Engineering Report
Final Engineering Report Review & Approval (PSIP Team)10/25/2016 A, 90% Design
90% RER(DERM)/FDEP Permit Submittal (Pump Station)90% RER(DERM)/FDEP Permit Review (Pump Station)
01/19/2016 A, MDWASD Procurement
Procurement PhaseBidders Prepare Bids for Submittal
Bids SubmittalRecommendation for Award Letter
Contract Award (Purchase Order Approval)Pumps Manufacturing and Delivery
11/23/2016 A, Construction
Construction PhaseConstruction NTP
Construction OperationsSubstantial Completion
03/31/2017 A, Project Closeout
Closeout PhaseIssue SAC Letter
Administrative CloseoutProject Closed
Remaining Level of EffortProject Baseline Bar
Actual WorkRemaining Work
Critical Remaining WorkBaseline Milestone
LOEMilestone
Page 161 of 161 TASK filter: All Activities© Oracle Corporation