Activity ID Activity Name Start Finish Original Duration Pump Station Improvement Program 01/11/2012 A 09/29/2020 3522 New EPS-1 08/01/2018 09/28/2020 790 100259 Pump Station 0010 Upgrade 08/01/2018 09/28/2020 790 Design 08/01/2018 06/29/2019 333 B1000 Design Phase 08/01/2018 06/29/2019 333 B1005 Prepare and Submit Design Package 08/01/2018 08/07/2018 7 B1010 Engage Design Consultant 08/08/2018 09/04/2018 28 B1012 TA Preparation 09/05/2018 09/18/2018 14 B1014 TA Approval 09/19/2018 10/28/2018 40 B1030 Issue Design NTP 10/29/2018 0 B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/29/2018 06/01/2019 216 30% Design 10/29/2018 01/16/2019 80 B1060 A/E Prepares 30% Construction Documents 10/29/2018 12/17/2018 50 B1100 30% CDs Submittal 12/17/2018 0 B1120 30% Review (MDWASD/PSIP Team) 12/18/2018 01/16/2019 30 60% Design 12/18/2018 01/30/2019 44 B1130 A/E Prepares 60% Construction Documents 12/18/2018 01/16/2019 30 B1140 60% CDs Submittal 01/16/2019 0 B1160 60% Review (MDWASD/PSIP Team) 01/17/2019 01/30/2019 14 90% Design 01/17/2019 06/01/2019 136 B1170 A/E Prepares 90% Construction Documents 01/17/2019 02/25/2019 40 B1180 90% CDs Submittal 02/25/2019 0 B1190 90% Review (MDWASD/PSIP Team) 02/26/2019 03/27/2019 30 B1200 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 03/28/2019 0 B1210 90% RER(DERM)/FDEP Permit Review (Pump Station) 03/28/2019 05/11/2019 45 B1220 90% RER (Building Dept Permit Submittal (Pump Station) 05/12/2019 0 B1230 90% RER (Building Dept) Permit Review (Pump Station) 05/12/2019 06/01/2019 21 B1240 90% PWWMD Permit Submittal (Pump Station) 05/12/2019 0 B1250 90% PWWMD Permit Review (Pump Station) 05/12/2019 06/01/2019 21 B1260 90% CD PM Comments Evaluation Completed 06/01/2019 0 100% Design 06/02/2019 06/29/2019 28 B1270 A/E Prepares 100% Construction Documents 06/02/2019 06/15/2019 14 B1280 100% CDs Submittal 06/15/2019 0 B1290 100% Review (MDWASD/PSIP Team) 06/16/2019 06/29/2019 14 B1300 Design Completed 06/29/2019 0 MDWASD Procurement 06/29/2019 10/11/2019 104 B1305 Procurement Phase 06/29/2019 10/11/2019 104 B1310 Submit CDs to MDWASD Procurement Division 06/29/2019 0 B1312 Bid Notice Preparation Period 06/30/2019 08/01/2019 33 B1314 Bid Notice 08/01/2019 0 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 2014 2015 2016 2017 2018 2019 2020 06/29/2019, Desi gn Design Phase Prepare and Submit Design Package Engage Design Consultant TA Preparation TA Approval Issue Design NTP Final Engineering Report Review & Ap 01/16/2019, 30% Desi gn A/E Prepares 30% Construction Documents 30% CDs Submittal 30% Review (MDWASD/PSIP Team) 01/30/2019, 60% Desi gn A/E Prepares 60% Construction Documents 60% CDs Submittal 60% Review (MDWASD/PSIP Team) 06/01/2019, 90% Desi gn A/E Prepares 90% Construction Documents 90% CDs Submittal 90% Review (MDWASD/PSIP Team) 90% RER(DERM)/FDEP Permit Submittal ( P 90% RER(DERM)/FDEP Permit Review 90% RER (Building Dept Permit Submi t 90% RER (Building Dept) Permit Revi e 90% PWWMD Permit Submittal (Pump 90% PWWMD Permit Review (Pump 90% CD PM Comments Evaluation C 06/29/2019, 100% Desi gn A/E Prepares 100% Construction D o 100% CDs Submittal 100% Review (MDWASD/PSIP Team Design Completed 10/11/2019, MDWASD Pr o Procurement Phase Submit CDs to MDWASD Procurem Bid Notice Preparation Period Bid Notice Miami Dade Water and Sewer Department Program and Construction Management Services for the Implementation of a Pump Station Improvement Program ISD Project No. E13-WASD-02R PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT Print Date: 08/15/2018 Data Date: 08/01/2018 Disclaimer: Dates subject to change as program is further developed Remaining Level of Effort Project Baseline Bar Actual Wor k Remaining Work Critical Remaining Work Baseline Milestone LOE Milestone Page 1 of 161 TASK filter: All Activities © Oracle Corporation

Upload: others

Post on 29-Sep-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

Pump StatioPump Station Improvement Program 01/11/2012 A 09/29/2020 3522

New EPS-New EPS-1 08/01/2018 09/28/2020 790

100259 Pu100259 Pump Station 0010 Upgrade 08/01/2018 09/28/2020 790DesignDesign 08/01/2018 06/29/2019 333

B1000 Design Phase 08/01/2018 06/29/2019 333B1005 Prepare and Submit Design Package 08/01/2018 08/07/2018 7B1010 Engage Design Consultant 08/08/2018 09/04/2018 28B1012 TA Preparation 09/05/2018 09/18/2018 14B1014 TA Approval 09/19/2018 10/28/2018 40B1030 Issue Design NTP 10/29/2018 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/29/2018 06/01/2019 216

30% Des30% Design 10/29/2018 01/16/2019 80B1060 A/E Prepares 30% Construction Documents 10/29/2018 12/17/2018 50

B1100 30% CDs Submittal 12/17/2018 0B1120 30% Review (MDWASD/PSIP Team) 12/18/2018 01/16/2019 30

60% Des60% Design 12/18/2018 01/30/2019 44B1130 A/E Prepares 60% Construction Documents 12/18/2018 01/16/2019 30B1140 60% CDs Submittal 01/16/2019 0B1160 60% Review (MDWASD/PSIP Team) 01/17/2019 01/30/2019 14

90% Des90% Design 01/17/2019 06/01/2019 136B1170 A/E Prepares 90% Construction Documents 01/17/2019 02/25/2019 40B1180 90% CDs Submittal 02/25/2019 0B1190 90% Review (MDWASD/PSIP Team) 02/26/2019 03/27/2019 30B1200 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 03/28/2019 0B1210 90% RER(DERM)/FDEP Permit Review (Pump Station) 03/28/2019 05/11/2019 45B1220 90% RER (Building Dept Permit Submittal (Pump Station) 05/12/2019 0B1230 90% RER (Building Dept) Permit Review (Pump Station) 05/12/2019 06/01/2019 21B1240 90% PWWMD Permit Submittal (Pump Station) 05/12/2019 0B1250 90% PWWMD Permit Review (Pump Station) 05/12/2019 06/01/2019 21B1260 90% CD PM Comments Evaluation Completed 06/01/2019 0

100% De100% Design 06/02/2019 06/29/2019 28B1270 A/E Prepares 100% Construction Documents 06/02/2019 06/15/2019 14B1280 100% CDs Submittal 06/15/2019 0B1290 100% Review (MDWASD/PSIP Team) 06/16/2019 06/29/2019 14B1300 Design Completed 06/29/2019 0

MDWASDMDWASD Procurement 06/29/2019 10/11/2019 104B1305 Procurement Phase 06/29/2019 10/11/2019 104B1310 Submit CDs to MDWASD Procurement Division 06/29/2019 0B1312 Bid Notice Preparation Period 06/30/2019 08/01/2019 33B1314 Bid Notice 08/01/2019 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

06/29/2019, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA ApprovalIssue Design NTP

Final Engineering Report Review & Ap01/16/2019, 30% Design

A/E Prepares 30% Construction Documents

30% CDs Submittal30% Review (MDWASD/PSIP Team)01/30/2019, 60% Design

A/E Prepares 60% Construction Documents60% CDs Submittal60% Review (MDWASD/PSIP Team)

06/01/2019, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)/FDEP Permit Submittal (P

90% RER(DERM)/FDEP Permit Review 90% RER (Building Dept Permit Submit

90% RER (Building Dept) Permit Revie90% PWWMD Permit Submittal (Pump

90% PWWMD Permit Review (Pump 90% CD PM Comments Evaluation C

06/29/2019, 100% Design

A/E Prepares 100% Construction Do100% CDs Submittal100% Review (MDWASD/PSIP TeamDesign Completed

10/11/2019, MDWASD Pro

Procurement PhaseSubmit CDs to MDWASD Procurem

Bid Notice Preparation PeriodBid Notice

Miami Dade Water and Sewer DepartmentProgram and Construction Management Services for theImplementation of a Pump Station Improvement Program

ISD Project No. E13-WASD-02R

PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORTPrint Date: 08/15/2018Data Date: 08/01/2018

Disclaimer: Dates subject to change as program is further developed

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 1 of 161 TASK filter: All Activities© Oracle Corporation

Page 2: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conferencce 08/02/2019 08/15/2019 14B1320 Pre-Bid Conference 08/16/2019 08/16/2019 1B1328 Bidders Prepare Bids for Submittal 08/17/2019 09/06/2019 21B1330 Bids Submittal 09/06/2019 0B1340 MDWASD/PSIP Team Bids Evaluation 09/07/2019 09/27/2019 21B1350 Recommendation for Award Letter 09/27/2019 0B1355 Contract Award (Purchase Order Approval) 09/28/2019 10/11/2019 14

ConstrucConstruction 08/16/2019 05/31/2020 290B1357 Construction Phase 08/16/2019 05/31/2020 290B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 09/28/2019 10/18/2019 21B1364 Pre-Construction Meeting 10/19/2019 10/19/2019 1B1366 WASD Issues NTP (Pre-Const to NTP) 10/20/2019 12/03/2019 45B1369 WASD Issues NTP (PO to NTP) 10/12/2019 12/03/2019 53B1370 Construction NTP 12/04/2019 0B1390 Construction Operations 12/04/2019 05/31/2020 180B1395 Substantial Completion 05/31/2020 0

DesignerDesigner Construction Support Services 08/16/2019 05/31/2020 290B1397 Designer Construction Support Services 08/16/2019 05/31/2020 290

Project CProject Closeout 05/31/2020 09/28/2020 120B1425 Closeout Phase 05/31/2020 09/28/2020 120B1430 Issue SAC Letter 05/31/2020 0B1450 Final Release of Retainage - Construction Contract 05/31/2020 0B1460 Administrative Closeout 06/01/2020 09/28/2020 120B1470 Project Closed 09/28/2020 0

Basin 0021Basin 0021 09/25/2014 A 10/31/2019 1857

100000 Ba100000 Basin 0021 Infiltration/Inflow Study and Repairs 09/25/2014 A 07/19/2016 A 632InfiltratioInfiltration/Inflow 09/25/2014 A 07/19/2016 A 624

B1000 Infiltration/Inflow Phase 09/25/2014 A 07/19/2016 A 624Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 10/23/2015 A 226

B1005 SSES Phase 09/25/2014 A 10/23/2015 A 226B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 03/04/2015 A 10/23/2015 A 30B1040 Video Review 04/24/2015 A 05/07/2015 A 30

CIPP RepCIPP Repairs 01/15/2016 A 05/06/2016 A 46B1065 CIPP Phase 01/15/2016 A 05/06/2016 A 46B1080 Issue NTP for CIPP Repairs 01/15/2016 A 0B1090 Conduct CIPP Repairs 03/21/2016 A 05/06/2016 A 20

ManholeManhole Repairs 01/15/2016 A 06/09/2016 A 20B1115 Manhole Phase 01/15/2016 A 06/09/2016 A 20B1132 Issue NTP for Manhole Repairs 01/15/2016 A 0B1140 Conduct Manhole Repairs 06/06/2016 A 06/09/2016 A 20

Dig & ReDig & Replace Repairs 11/20/2015 A 07/19/2016 A 45B1160 Dig & Replace Phase 11/20/2015 A 07/19/2016 A 45B1180 Issue NTP for Dig & Replace Repairs 11/20/2015 A 0B1190 Conduct Dig & Replace Repairs 07/13/2016 A 07/19/2016 A 45

Project CProject Closeout 06/10/2016 A 06/10/2016 A 0B1235 Closeout Phase 06/10/2016 A 06/10/2016 A 0B1260 Project Closed 06/10/2016 A 0

100001 Pu100001 Pump Station 0021 Upgrade 10/01/2014 A 03/17/2019 1629

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

MDWASD/PSIP Team Prepare Pre-Bid Conference

Bidders Prepare Bids for SubmBids Submittal

MDWASD/PSIP Team Bids ERecommendation for Award Contract Award (Purchase O

05/31/2

ConstruMDWASD/PSIP Team PrePre-Construction Meeting

WASD Issues NTP (PreWASD Issues NTP (POConstruction NTP

ConstruSubstan05/31/2

Designe

Issue SAFinal Re

10/31/2019, Basin 0021

07/19/2016 A, 100000 Basin 0021 Infiltration/Inflow Study and Repairs07/19/2016 A, Infiltration/Inflow

Infiltration/Inflow Phase10/23/2015 A, Sanitary Sewer Evaluation SurveySSES Phase

Issue NTP to SSES ContractorConduct SSES

Video Review05/06/2016 A, CIPP RepairsCIPP Phase

Issue NTP for CIPP RepairsConduct CIPP Repairs

06/09/2016 A, Manhole RepairsManhole Phase

Issue NTP for Manhole RepairsConduct Manhole Repairs

07/19/2016 A, Dig & Replace Repairs

Dig & Replace PhaseIssue NTP for Dig & Replace Repairs

Conduct Dig & Replace Repairs06/10/2016 A, Project CloseoutCloseout Phase

Project Closed03/17/2019, 100001 Pump Station 0021 U

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 2 of 161 TASK filter: All Activities© Oracle Corporation

Page 3: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

DesignDesign 10/01/2014 A 10/02/2017 A 1127B1000 Design Phase 10/01/2014 A 10/02/2017 A 1127B1010 WASD Overhead During Planning and Design 10/01/2014 A 10/02/2017 A 1127B1020 Prepare and Submit Design Package 10/01/2014 A 10/02/2014 A 5B1030 Engage Design Consultant 10/03/2014 A 11/04/2014 A 20B1035 TA Preparation 11/05/2014 A 11/05/2014 A 1B1037 TA Approval Process 11/06/2014 A 01/12/2015 A 20B1040 Issue Design NTP 02/02/2015 A 0B1042 WASD/PSIP Prepare Design / Permitting Accelerated Plan 03/23/2016 A 03/29/2016 A 5B1044 TA Rev 1 Preparation 03/30/2016 A 04/21/2016 A 1B1046 TA Rev 1 Approval Process 04/22/2016 A 10/14/2016 A 20B1060 Final Engineering Report Review & Approval (MDWASD/PSIP Te 02/02/2015 A 12/14/2016 A 85

30% Des30% Design 02/03/2015 A 08/29/2016 A 490B1070 A/E Prepares 30% Construction Documents 02/03/2015 A 03/03/2015 A 30B1080 Geotechnical Engineering Services 02/19/2015 A 03/03/2015 A 26B1090 Surveying Services 02/19/2015 A 03/03/2015 A 15B1110 30% CDs Submittal 03/03/2015 A 0B1130 30% Review (MDWASD/PSIP Team) 03/04/2015 A 05/01/2015 A 10B1132 A/E Prepares 30% Construction Documents (Re-Design) 03/23/2016 A 06/22/2016 A 43B1134 30% Review (MDWASD/PSIP Team) (Re-Design) 06/23/2016 A 08/29/2016 A 10

90% Des90% Design 04/20/2015 A 09/29/2017 A 881B1180 A/E Prepares 90% Construction Documents 04/20/2015 A 05/20/2015 A 20B1190 90% CDs Submittal 05/20/2015 A 0B1200 90% Review (MDWASD/PSIP Team) 05/21/2015 A 03/23/2016 A 15B1204 A/E Prepares 90% Construction Documents (Re-Design) 08/30/2016 A 11/02/2016 A 22B1206 90% Review (MDWASD/PSIP Team) (Re-Design) 11/03/2016 A 12/14/2016 A 30B1210 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 02/20/2017 A 0B1220 90% RER(DERM)/FDEP Permit Review (Pump Station) 02/20/2017 A 04/18/2017 A 45B1230 90% Miami - BD Permit Submittal (Pump Station) 04/18/2017 A 0B1240 90% Miami - BD Permit Review (Pump Station) 04/18/2017 A 09/29/2017 A 21B1250 90% Miami - PWD Permit Submittal (Pump Station) 04/18/2017 A 0B1260 90% Miami - PWD Permit Review (Pump Station) 04/18/2017 A 09/29/2017 A 21B1270 90% CD PM Comments Evaluation Completed 09/29/2017 A 0B1272 MDWASD Union Concurrence Process 02/27/2017 A 04/07/2017 A 30

100% De100% Design 09/30/2017 A 10/02/2017 A 31B1280 A/E Prepares 100% Construction Documents 09/30/2017 A 10/02/2017 A 14B1290 100% CDs Submittal 10/02/2017 A 0B1300 100% Review (MDWASD/PSIP Team) 10/02/2017 A 10/02/2017 A 14B1310 Design Completed 10/02/2017 A 0

MDWASDMDWASD Procurement 10/03/2017 A 03/23/2018 A 143B1315 Procurement Phase 10/03/2017 A 03/23/2018 A 143B1320 Submit CDs to MDWASD Procurement Division 10/03/2017 A 0B1323 Bid Notice Preparation Period 10/04/2017 A 10/16/2017 A 33B1325 Bid Notice 10/16/2017 A 0B1327 MDWASD/PSIP Team Prepare for Pre-Bid Conferencce 10/17/2017 A 10/25/2017 A 14B1330 Pre-Bid Conference 10/26/2017 A 10/26/2017 A 1B1335 Bidders Prepare Bids for Submittal 10/27/2017 A 12/10/2017 A 21B1336 Addendum #3 Issued to Changed Sub Trade to Primary Trade 12/11/2017 A 12/13/2017 A 3B1337 2nd Pre-Bid Conference Due to Sub Trade Changed to Primary 12/14/2017 A 12/14/2017 A 1

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

10/02/2017 A, Design

Design PhaseWASD Overhead During Planning and Design

Prepare and Submit Design PackageEngage Design ConsultantTA Preparation

TA Approval ProcessIssue Design NTP

WASD/PSIP Prepare Design / Permitting Accelerated PlanTA Rev 1 Preparation

TA Rev 1 Approval ProcessFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

08/29/2016 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services

30% CDs Submittal30% Review (MDWASD/PSIP Team)

A/E Prepares 30% Construction Documents (Re-Design)30% Review (MDWASD/PSIP Team) (Re-Design)

09/29/2017 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)A/E Prepares 90% Construction Documents (Re-Design)

90% Review (MDWASD/PSIP Team) (Re-Design)90% RER(DERM)/FDEP Permit Submittal (Pump Station)

90% RER(DERM)/FDEP Permit Review (Pump Station)90% Miami - BD Permit Submittal (Pump Station)

90% Miami - BD Permit Review (Pump Station)90% Miami - PWD Permit Submittal (Pump Station)

90% Miami - PWD Permit Review (Pump Station)90% CD PM Comments Evaluation Completed

MDWASD Union Concurrence Process10/02/2017 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal

100% Review (MDWASD/PSIP Team)Design Completed

03/23/2018 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation Period

Bid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferenccePre-Bid Conference

Bidders Prepare Bids for SubmittalAddendum #3 Issued to Changed Sub Trade to Primary Trade2nd Pre-Bid Conference Due to Sub Trade Changed to Primary Trade

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 3 of 161 TASK filter: All Activities© Oracle Corporation

Page 4: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1338 Bidders Prepare 2nd Bids for Submittal 12/15/2017 A 01/18/2018 A 35B1340 Bids Submittal 01/18/2018 A 0B1350 MDWASD/PSIP Team Bids Evaluation 01/19/2018 A 01/29/2018 A 21B1360 Recommendation for Award Letter 01/29/2018 A 0B1365 Contract Award (Purchase Order Approval) 01/30/2018 A 03/23/2018 A 14

ConstrucConstruction 10/26/2017 A 11/17/2018 419B1370 Construction Phase 10/26/2017 A 11/17/2018 419B1371 Construction Management - PSIP Team 10/26/2017 A 11/17/2018 419B1372 Construction Management - WASD 10/26/2017 A 11/17/2018 419B1373 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 01/30/2018 A 04/17/2018 A 21B1375 Pre-Construction Meeting 04/18/2018 A 04/18/2018 A 1B1376 WASD Issues NTP (Pre-Const to NTP) 04/19/2018 A 05/20/2018 A 45B1378 WASD Issues NTP (PO to NTP) 03/24/2018 A 05/20/2018 A 53B1380 Construction NTP 05/21/2018 A 0B1410 Construction Operations 05/21/2018 A 11/17/2018 179B1415 Substantial Completion 11/17/2018 0

DesignerDesigner Construction Support Services 10/26/2017 A 11/17/2018 388B1420 Designer Construction Support Services 10/26/2017 A 11/17/2018 388

Project CProject Closeout 11/17/2018 03/17/2019 120B1455 Closeout Phase 11/17/2018 03/17/2019 120B1460 Issue SAC Letter 11/17/2018 0B1480 Final Release of Retainage - Construction Contract 11/17/2018 0B1490 Administrative Closeout 11/18/2018 03/17/2019 120B1500 Project Closed 03/17/2019 0

100253 Pu100253 Pump Station 0021 Gravity Sewer 07/31/2017 A 10/31/2019 669DesignDesign 07/31/2017 A 04/17/2018 A 154

B1000 Design Phase 07/31/2017 A 04/17/2018 A 154B1010 WASD Overhead During Planning and Design 07/31/2017 A 04/17/2018 A 154

90% Des90% Design 07/31/2017 A 04/17/2018 A 154B1220 A/E Prepares Performance Specifications 07/31/2017 A 04/17/2018 A 154

MDWASDMDWASD Procurement 08/01/2018 11/12/2018 104B1305 Procurement Phase 08/01/2018 11/12/2018 104B1310 Submit CDs to MDWASD Procurement Division 08/01/2018 0B1312 Bid Notice Preparation Period 08/01/2018 09/02/2018 33B1314 Bid Notice 09/02/2018 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conferencce 09/03/2018 09/16/2018 14B1320 Pre-Bid Conference 09/17/2018 09/17/2018 1B1328 Bidders Prepare Bids for Submittal 09/18/2018 10/08/2018 21B1330 Bids Submittal 10/08/2018 0B1340 MDWASD/PSIP Team Bids Evaluation 10/09/2018 10/29/2018 21B1350 Recommendation for Award Letter 10/29/2018 0B1355 Contract Award (Purchase Order Approval) 10/30/2018 11/12/2018 14

ConstrucConstruction 09/17/2018 07/03/2019 290B1357 Construction Phase 09/17/2018 07/03/2019 290B1358 Construction Management - PSIP Team 09/17/2018 07/03/2019 290B1359 Construction Management - WASD 09/17/2018 07/03/2019 290B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 10/30/2018 11/19/2018 21B1364 Pre-Construction Meeting 11/20/2018 11/20/2018 1B1366 WASD Issues NTP (Pre-Const to NTP) 11/21/2018 01/04/2019 45

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Bidders Prepare 2nd Bids for Submittal

Bids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter

Contract Award (Purchase Order Approval)11/17/2018, Construction

Construction PhaseConstruction Management - PSIP TeamConstruction Management - WASD

MDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Construction NTPConstruction OperationsSubstantial Completion11/17/2018, Designer Construction Support Services

Designer Construction Support Services03/17/2019, Project Closeout

Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction Contract

Administrative CloseoutProject Closed

10/31/2019, 100253 Pum04/17/2018 A, DesignDesign PhaseWASD Overhead During Planning and Design04/17/2018 A, 90% DesignA/E Prepares Performance Specifications

11/12/2018, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferenccePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)

07/03/2019, Construction

Construction PhaseConstruction Management - PSIP TConstruction Management - WASD

MDWASD/PSIP Team Prepare for Pre-Construction MPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 4 of 161 TASK filter: All Activities© Oracle Corporation

Page 5: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1369 WASD Issues NTP (PO to NTP) 11/13/2018 01/04/2019 53B1370 Construction NTP 01/05/2019 0B1390 Construction Operations 01/05/2019 07/03/2019 180B1395 Substantial Completion 07/03/2019 0

DesignerDesigner Construction Support Services 09/17/2018 07/03/2019 290B1397 Designer Construction Support Services 09/17/2018 07/03/2019 290

Project CProject Closeout 07/03/2019 10/31/2019 120B1425 Closeout Phase 07/03/2019 10/31/2019 120B1450 Final Release of Retainage - Construction Contract 07/03/2019 0B1460 Administrative Closeout 07/04/2019 10/31/2019 120B1470 Project Closed 10/31/2019 0

Basin 0026Basin 0026 02/13/2015 A 11/29/2018 1267

100002 Ba100002 Basin 0026 Infiltration/Inflow Study and Repairs 05/22/2015 A 06/16/2016 A 289InfiltratioInfiltration/Inflow 05/22/2015 A 06/15/2016 A 281

B1000 Infiltration/Inflow Phase 05/22/2015 A 06/15/2016 A 281CIPP RepCIPP Repairs 05/22/2015 A 03/07/2016 A 20

B1065 CIPP Phase 05/22/2015 A 03/07/2016 A 20B1080 Issue NTP for CIPP Repairs 05/22/2015 A 0B1090 Conduct CIPP Repairs 07/09/2015 A 03/07/2016 A 20

ManholeManhole Repairs 03/25/2016 A 06/15/2016 A 112B1115 Manhole Phase 03/25/2016 A 06/15/2016 A 112B1130 Issue NTP for Manhole Repairs 03/25/2016 A 0B1140 Conduct Manhole Repairs 04/11/2016 A 06/15/2016 A 20

Dig & ReDig & Replace Repairs 06/26/2015 A 07/29/2015 A 30B1165 Dig & Replace Phase 06/26/2015 A 07/29/2015 A 30B1180 Issue NTP for Dig & Replace Repairs 06/26/2015 A 0B1190 Conduct Dig & Replace Repairs 07/20/2015 A 07/29/2015 A 30

Project CProject Closeout 06/16/2016 A 06/16/2016 A 0B1235 Closeout Phase 06/16/2016 A 06/16/2016 A 0B1260 Project Closed 06/16/2016 A 0

100240 Pu100240 Pump Station 0026 Upgrade 02/13/2015 A 11/29/2018 1267DesignDesign 02/13/2015 A 05/31/2017 A 783

B1000 Design Phase 02/13/2015 A 05/31/2017 A 783B1005 Prepare and Submit Design Package 02/13/2015 A 06/05/2015 A 5B1010 Engage Design Consultant 02/13/2015 A 06/05/2015 A 20B1020 TA Approval Process 06/19/2015 A 06/30/2015 A 20B1022 TA Rev 1 Approval Process 11/06/2015 A 12/11/2015 A 20B1030 Issue Design NTP 07/02/2015 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 07/02/2015 A 06/09/2016 A 85

30% Des30% Design 07/03/2015 A 09/28/2015 A 91B1060 A/E Prepares 30% Construction Documents 07/03/2015 A 09/11/2015 A 30B1070 Geotechnical Engineering Services 07/03/2015 A 09/11/2015 A 20B1080 Surveying Services 07/03/2015 A 09/11/2015 A 15B1100 30% CDs Submittal 09/14/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 09/15/2015 A 09/28/2015 A 10

90% Des90% Design 09/15/2015 A 04/17/2017 A 645B1170 A/E Prepares 90% Construction Documents 09/15/2015 A 03/24/2016 A 20B1180 90% CDs Submittal 03/24/2016 A 0B1190 90% Review (MDWASD/PSIP Team) 03/25/2016 A 06/09/2016 A 15

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

WASD Issues NTP (PO to NTP)

Construction NTPConstruction OperationsSubstantial Completion07/03/2019, Designer Construction

Designer Construction Support Ser10/31/2019, Project Close

Closeout PhaseFinal Release of Retainage - Const

Administrative CloseoutProject Closed

11/29/2018, Basin 0026

06/16/2016 A, 100002 Basin 0026 Infiltration/Inflow Study and Repairs06/15/2016 A, Infiltration/Inflow

Infiltration/Inflow Phase03/07/2016 A, CIPP RepairsCIPP Phase

Issue NTP for CIPP RepairsConduct CIPP Repairs

06/15/2016 A, Manhole RepairsManhole Phase

Issue NTP for Manhole RepairsConduct Manhole Repairs

07/29/2015 A, Dig & Replace RepairsDig & Replace Phase

Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs

06/16/2016 A, Project CloseoutCloseout Phase

Project Closed11/29/2018, 100240 Pump Station 0026 Upgrade

05/31/2017 A, Design

Design PhasePrepare and Submit Design PackageEngage Design Consultant

TA Approval ProcessTA Rev 1 Approval Process

Issue Design NTPFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

09/28/2015 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services

30% CDs Submittal30% Review (MDWASD/PSIP Team)

04/17/2017 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 5 of 161 TASK filter: All Activities© Oracle Corporation

Page 6: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1192 TA Rev 2 Approval Process 11/10/2016 A 12/21/2016 A 40B1194 A/E Prepares 90% Design for Flow Metter & Specialty Odor Con 11/10/2016 A 01/30/2017 A 40B1200 90% RER (DERM) FDEP Permit Submittal (Pump Station) 06/10/2016 A 0B1210 90% RER (DERM) FDEP Permit Review (Pump Station) 06/10/2016 A 02/24/2017 A 155B1220 90% RER (Building Department) Permit Submittal (Pump Statio 03/09/2017 A 0B1230 90% RER (Building Department) Permit Review (Pump Station) 03/09/2017 A 04/17/2017 A 21B1240 90% PWWMD Permit Submittal (Pump Station) 06/10/2016 A 0B1250 90% PWWMD Permit Review (Pump Station) 06/10/2016 A 02/24/2017 A 15B1260 90% CD PM Comments Evaluation Completed 04/17/2017 A 0B1262 MDWASD Union Concurrence Process 01/27/2017 A 03/07/2017 A 30

100% De100% Design 05/17/2017 A 05/31/2017 A 14B1270 A/E Prepares 100% Construction Documents 05/17/2017 A 05/30/2017 A 10B1280 100% CDs Submittal 05/30/2017 A 0B1290 100% Review (MDWASD/PSIP Team) 05/31/2017 A 05/31/2017 A 10B1300 Design Completed 05/31/2017 A 0

MDWASDMDWASD Procurement 06/01/2017 A 10/19/2017 A 101B1305 Procurement Phase 06/01/2017 A 10/19/2017 A 101B1310 Submit CDs to MDWASD Procurement Division 06/01/2017 A 0B1312 Bid Notice Preparation Period 06/02/2017 A 06/07/2017 A 23B1314 Bid Notice 06/07/2017 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 06/08/2017 A 06/20/2017 A 10B1320 Pre-Bid Conference 06/21/2017 A 06/21/2017 A 1B1328 Bidders Prepare Bids for Submittal 06/22/2017 A 07/24/2017 A 15B1330 Bids Submittal 07/24/2017 A 0B1340 Bids Evaluation (MDWASD/PSIP Team) 07/25/2017 A 08/31/2017 A 15B1350 Recommendation for Award Letter 08/31/2017 A 0B1352 Contract Award (Purchase Order Approval) 09/01/2017 A 10/19/2017 A 10

ConstrucConstruction 06/21/2017 A 08/01/2018 489B1355 Construction Phase 06/21/2017 A 08/01/2018 489B1357 MDAD/PSIP Team Prepare for Pre-Construction Meeting 09/01/2017 A 10/16/2017 A 21B1358 Pre-Construction Meeting 10/17/2017 A 10/17/2017 A 1B1359 WASD Issues NTP (Pre-Const to NTP) 10/18/2017 A 01/28/2018 A 45B1360 Construction NTP 01/29/2018 A 0B1361 WASD Issues NTP (PO to NTP) 10/20/2017 A 01/28/2018 A 53B1390 Construction Operations 01/29/2018 A 08/01/2018 149B1392 Substantial Completion 08/01/2018 0

DesignerDesigner Construction Support Services 06/21/2017 A 04/01/2018 A 274B1480 Designer Construction Support Services 06/21/2017 A 04/01/2018 A 820

Project CProject Closeout 10/31/2017 A 11/29/2018 394B1425 Closeout Phase 10/31/2017 A 11/29/2018 394B1430 Issue SAC Letter 10/31/2017 A 0B1450 Final Release of Retainage - Construction Contract 08/01/2018 0B1460 Administrative Closeout 08/02/2018 11/29/2018 120B1470 Project Closed 11/29/2018 0

Basin 0046Basin 0046 09/25/2014 A 09/28/2020 2031

100003 Ba100003 Basin 0046 Infiltration/Inflow Study and Repairs 09/25/2014 A 08/31/2016 A 723InfiltratioInfiltration/Inflow 09/25/2014 A 08/31/2016 A 723

B1000 Infiltration/Inflow Phase 09/25/2014 A 08/31/2016 A 723Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 06/18/2015 A 136

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

TA Rev 2 Approval ProcessA/E Prepares 90% Design for Flow Metter & Specialty Odor Control

90% RER (DERM) FDEP Permit Submittal (Pump Station)90% RER (DERM) FDEP Permit Review (Pump Station)90% RER (Building Department) Permit Submittal (Pump Station)

90% RER (Building Department) Permit Review (Pump Station)90% PWWMD Permit Submittal (Pump Station)

90% PWWMD Permit Review (Pump Station)90% CD PM Comments Evaluation Completed

MDWASD Union Concurrence Process05/31/2017 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal

100% Review (MDWASD/PSIP Team)Design Completed

10/19/2017 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid Notice

MDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

Bids Evaluation (MDWASD/PSIP Team)Recommendation for Award Letter

Contract Award (Purchase Order Approval)08/01/2018, Construction

Construction PhaseMDAD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)

Construction NTPWASD Issues NTP (PO to NTP)

Construction OperationsSubstantial Completion

04/01/2018 A, Designer Construction Support Services

Designer Construction Support Services11/29/2018, Project Closeout

Closeout PhaseIssue SAC Letter

Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed

08/31/2016 A, 100003 Basin 0046 Infiltration/Inflow Study and Repairs08/31/2016 A, Infiltration/Inflow

Infiltration/Inflow Phase06/18/2015 A, Sanitary Sewer Evaluation Survey

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 6 of 161 TASK filter: All Activities© Oracle Corporation

Page 7: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1005 SSES Phase 09/25/2014 A 06/18/2015 A 136B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 06/02/2015 A 06/11/2015 A 30B1040 Video Review 06/12/2015 A 06/18/2015 A 30

CIPP RepCIPP Repairs 01/15/2016 A 05/13/2016 A 28B1070 CIPP Phase 01/15/2016 A 05/13/2016 A 28B1090 Issue NTP for CIPP Repairs 01/15/2016 A 0B1100 Conduct CIPP Repairs 05/13/2016 A 05/13/2016 A 28

ManholeManhole Repairs 10/30/2015 A 02/11/2016 A 20B1115 Manhole Phase 10/30/2015 A 02/11/2016 A 20B1130 Issue NTP for Manhole Repairs 10/30/2015 A 0B1140 Conduct Manhole Repairs 01/06/2016 A 02/11/2016 A 20

Dig & ReDig & Replace Repairs 11/20/2015 A 08/31/2016 A 120B1165 Dig & Replace Phase 11/20/2015 A 08/31/2016 A 120B1180 Issue NTP for Dig & Replace Repairs 11/20/2015 A 0B1190 Conduct Dig & Replace Repairs 06/23/2016 A 08/31/2016 A 30

Project CProject Closeout 08/31/2016 A 08/31/2016 A 0B1235 Closeout Phase 08/31/2016 A 08/31/2016 A 0B1260 Project Closed 08/31/2016 A 0

100004 Pu100004 Pump Station 0046(AM) Upgrade 11/03/2015 A 07/26/2020 1700DesignDesign 11/03/2015 A 04/26/2019 1243

B1000 Design Phase 11/03/2015 A 04/26/2019 1243B1010 Prepare and Submit Design Package 11/03/2015 A 11/03/2015 A 5B1020 Engage Design Consultant 11/03/2015 A 11/11/2015 A 20B1021 SOW Received - I/I Repairs Pending To Resume Negotiations 11/12/2015 A 08/01/2018 20B1022 TA Preparation 08/02/2018 08/15/2018 14B1024 TA Approval Process 08/16/2018 09/24/2018 40B1030 Issue Design NTP 09/25/2018 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 09/25/2018 03/29/2019 186

30% Des30% Design 09/25/2018 12/13/2018 80B1060 A/E Prepares 30% Construction Documents 09/25/2018 11/13/2018 50B1100 30% CDs Submittal 11/13/2018 0B1120 30% Review (MDWASD/PSIP Team) 11/14/2018 12/13/2018 30

90% Des90% Design 11/14/2018 03/29/2019 136B1170 A/E Prepares 90% Construction Documents 11/14/2018 12/23/2018 40B1180 90% CDs Submittal 12/23/2018 0B1190 90% Review (MDWASD/PSIP Team) 12/24/2018 01/22/2019 30B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 01/23/2019 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 01/23/2019 03/08/2019 45B1220 90% Miami - BD Permit Submittal 03/09/2019 0B1230 90% Miami - BD Permit Review 03/09/2019 03/29/2019 21B1240 90% Miami - PWD Permit Submittal 03/09/2019 0B1250 90% Miami - PWD Permit Review 03/09/2019 03/29/2019 21B1260 90% CD PM Comments Evaluation Completed 03/29/2019 0

100% De100% Design 03/30/2019 04/26/2019 28B1270 A/E Prepares 100% Construction Documents 03/30/2019 04/12/2019 14B1280 100% CDs Submittal 04/12/2019 0B1290 100% Review (MDWASD/PSIP Team) 04/13/2019 04/26/2019 14B1300 Design Completed 04/26/2019 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

SSES Phase

Issue NTP to SSES ContractorConduct SSESVideo Review

05/13/2016 A, CIPP Repairs

CIPP PhaseIssue NTP for CIPP Repairs

Conduct CIPP Repairs02/11/2016 A, Manhole RepairsManhole Phase

Issue NTP for Manhole RepairsConduct Manhole Repairs

08/31/2016 A, Dig & Replace RepairsDig & Replace Phase

Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs08/31/2016 A, Project CloseoutCloseout Phase

Project Closed07/

04/26/2019, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantSOW Received - I/I Repairs Pending To Resume NegotiationsTA Preparation

TA Approval Process

Issue Design NTPFinal Engineering Report Review & Approva

12/13/2018, 30% Design

A/E Prepares 30% Construction Documents30% CDs Submittal

30% Review (MDWASD/PSIP Team)03/29/2019, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump

90% RER(DERM)FDEP Permit Review (Pum90% Miami - BD Permit Submittal

90% Miami - BD Permit Review90% Miami - PWD Permit Submittal

90% Miami - PWD Permit Review90% CD PM Comments Evaluation Comple

04/26/2019, 100% Design

A/E Prepares 100% Construction Docume100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 7 of 161 TASK filter: All Activities© Oracle Corporation

Page 8: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

MDWASDMDWASD Procurement 04/26/2019 08/08/2019 104B1305 Procurement Phase 04/26/2019 08/08/2019 104B1310 Submit CDs to MDWASD Procurement Division 04/26/2019 0B1312 Bid Notice Preparation Period 04/27/2019 05/29/2019 33B1314 Bid Notice 05/29/2019 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 05/30/2019 06/12/2019 14B1320 Pre-Bid Conference 06/13/2019 06/13/2019 1B1328 Bidders Prepare Bids for Submittal 06/14/2019 07/04/2019 21B1330 Bids Submittal 07/04/2019 0B1340 MDWASD/PSIP Team Bids Evaluation 07/05/2019 07/25/2019 21B1350 Recommendation for Award Letter 07/25/2019 0B1355 Contract Award (Purchase Order Approval) 07/26/2019 08/08/2019 14

ConstrucConstruction 06/13/2019 03/28/2020 290B1360 Construction Phase 06/13/2019 03/28/2020 290B1364 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 07/26/2019 08/15/2019 21B1366 Pre-Construction Meeting 08/16/2019 08/16/2019 1B1368 WASD Issues NTP (Pre-Const to NTP) 08/17/2019 09/30/2019 45B1370 Construction NTP 10/01/2019 0B1400 Construction Operations 10/01/2019 03/28/2020 180B1402 Substantial Completion 03/28/2020 0

DesignerDesigner Construction Support Services 06/13/2019 03/28/2020 290B1410 Designer Construction Support Services 06/13/2019 03/28/2020 290

Project CProject Closeout 03/28/2020 07/26/2020 120B1445 Closeout Phase 03/28/2020 07/26/2020 120B1450 Issue SAC Letter 03/28/2020 0B1470 Final Release of Retainage - Construction Contract 03/28/2020 0B1480 Administrative Closeout 03/29/2020 07/26/2020 120B1490 Project Closed 07/26/2020 0

100232 FM100232 FM for Pump Station 0046 08/01/2018 09/28/2020 790DesignDesign 08/01/2018 06/29/2019 333

B1000 Design Phase 08/01/2018 06/29/2019 333B1010 Prepare and Submit Design Package 08/01/2018 08/07/2018 7B1020 Engage Design Consultant 08/08/2018 09/04/2018 28B1022 TA Preparation 09/05/2018 09/18/2018 14B1024 TA Approval Process 09/19/2018 10/28/2018 40B1030 Issue Design NTP 10/29/2018 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/29/2018 06/01/2019 216

30% Des30% Design 10/29/2018 01/16/2019 80B1060 A/E Prepares 30% Construction Documents 10/29/2018 12/17/2018 50B1100 30% CDs Submittal 12/17/2018 0B1120 30% Review (MDWASD/PSIP Team) 12/18/2018 01/16/2019 30

60% Des60% Design 12/18/2018 01/30/2019 44B1140 A/E Prepares 60% Construction Documents 12/18/2018 01/16/2019 30B1150 60% CDs Submittal 01/16/2019 0B1170 60% Review (MDWASD/PSIP Team) 01/17/2019 01/30/2019 14

90% Des90% Design 01/17/2019 06/01/2019 136B1180 A/E Prepares 90% Construction Documents 01/17/2019 02/25/2019 40B1190 90% CDs Submittal 02/25/2019 0B1200 90% Review (MDWASD/PSIP Team) 02/26/2019 03/27/2019 30

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

08/08/2019, MDWASD ProcuremProcurement Phase

Submit CDs to MDWASD Procurement DBid Notice Preparation Period

Bid NoticeMDWASD/PSIP Team Prepare for Pr

Pre-Bid ConferenceBidders Prepare Bids for Submittal

Bids SubmittalMDWASD/PSIP Team Bids EvaluRecommendation for Award LetteContract Award (Purchase Order

03/28/2020,

Construction MDWASD/PSIP Team Prepare Pre-Construction Meeting

WASD Issues NTP (Pre-Con

Construction NTPConstruction Substantial C03/28/2020,

Designer Con07/Clo

Issue SAC LeFinal Release

AdmPro

06/29/2019, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval Process

Issue Design NTPFinal Engineering Report Review & Ap

01/16/2019, 30% Design

A/E Prepares 30% Construction Documents30% CDs Submittal

30% Review (MDWASD/PSIP Team)01/30/2019, 60% Design

A/E Prepares 60% Construction Documents60% CDs Submittal60% Review (MDWASD/PSIP Team)

06/01/2019, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 8 of 161 TASK filter: All Activities© Oracle Corporation

Page 9: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1210 90% PWWMD Permit Submittal (Force Main) 03/28/2019 0B1220 90% PWWMD Permit Review (Force Main) 03/28/2019 04/17/2019 21B1230 90% RER(DERM)FDEP Permit Submittal (Force Main) 03/28/2019 0B1240 90% RER(DERM)FDEP Permit Review (Force Main) 03/28/2019 05/11/2019 45B1250 90% Municipality Permit Submittal (Force Main) 05/12/2019 0B1260 90% Municipality Permit Review (Force Main) 05/12/2019 06/01/2019 21B1270 90% FDOT Permit Submittal (Force Main) 05/12/2019 0B1280 90% FDOT Permit Review (Force Main) 05/12/2019 06/01/2019 21B1290 90% CD PM Comments Evaluation Completed 06/01/2019 0

100% De100% Design 06/02/2019 06/29/2019 28B1300 A/E Prepares 100% Construction Documents 06/02/2019 06/15/2019 14B1310 100% CDs Submittal 06/15/2019 0B1320 100% Review (MDWASD/PSIP Team) 06/16/2019 06/29/2019 14B1330 Design Completed 06/29/2019 0

MDWASDMDWASD Procurement 06/29/2019 10/11/2019 104B1335 Procurement Phase 06/29/2019 10/11/2019 104B1340 Submit CDs to MDWASD Procurement Division 06/29/2019 0B1342 Bid Notice Preparation Period 06/30/2019 08/01/2019 33B1344 Bid Notice 08/01/2019 0B1346 MDWASD/PSIP Team Prepare for Pre-Bid Conference 08/02/2019 08/15/2019 14B1350 Pre-Bid Conference 08/16/2019 08/16/2019 1B1358 Bidders Prepare Bids for Submittal 08/17/2019 09/06/2019 21B1360 Bids Submittal 09/06/2019 0B1370 MDWASD/PSIP Bids Evaluation 09/07/2019 09/27/2019 21B1380 Recommendation for Award letter 09/27/2019 0B1385 Contract Award (Purchase Order Approval) 09/28/2019 10/11/2019 14

ConstrucConstruction 08/16/2019 06/01/2020 290B1390 Construction Phase 08/16/2019 06/01/2020 290B1394 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 09/28/2019 10/18/2019 21B1396 Pre-construction Meeting 10/19/2019 10/19/2019 1B1398 WASD Issues NTP (Pre-Const to NTP) 10/20/2019 12/03/2019 45B1400 Construction NTP 12/04/2019 0B1430 Construction Operations 12/04/2019 05/31/2020 180B1432 Substantial Completion 05/31/2020 0

DesignerDesigner Construction Support Services 08/16/2019 05/31/2020 290B1440 Designer Construction Support Services 08/16/2019 05/31/2020 290

Project CProject Closeout 05/31/2020 09/28/2020 120B1475 Closeout Phase 05/31/2020 09/28/2020 120B1500 Final Release of Retainage - Construction Contract 05/31/2020 0B1510 Administrative Closeout 06/01/2020 09/28/2020 120B1520 Project Closed 09/28/2020 0

Basin 0052Basin 0052 06/24/2016 A 08/05/2016 A 43

100254 Pu100254 Pump Station 0052 Upgrade 06/24/2016 A 08/05/2016 A 43Project CProject Closeout 06/24/2016 A 08/05/2016 A 43

B1425 Closeout Phase 06/24/2016 A 08/05/2016 A 43B1430 Issue SAC Letter 08/05/2016 A 0B1460 Administrative Closeout 06/24/2016 A 08/05/2016 A 31B1470 Project Closed 08/05/2016 A 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

90% PWWMD Permit Submittal (Force Mai90% PWWMD Permit Review (Force Main

90% RER(DERM)FDEP Permit Submittal (F90% RER(DERM)FDEP Permit Review (90% Municipality Permit Submittal (Forc

90% Municipality Permit Review (Forc90% FDOT Permit Submittal (Force Ma

90% FDOT Permit Review (Force Main90% CD PM Comments Evaluation C

06/29/2019, 100% Design

A/E Prepares 100% Construction Do100% CDs Submittal100% Review (MDWASD/PSIP TeamDesign Completed

10/11/2019, MDWASD ProProcurement Phase

Submit CDs to MDWASD ProcuremBid Notice Preparation Period

Bid NoticeMDWASD/PSIP Team Prepare

Pre-Bid ConferenceBidders Prepare Bids for Subm

Bids SubmittalMDWASD/PSIP Bids EvaluaRecommendation for Award Contract Award (Purchase O

06/01/2

ConstruMDWASD/PSIP Team PrePre-construction Meeting

WASD Issues NTP (Pre

Construction NTPConstruSubstan05/31/2

Designe

Final Re

08/05/2016 A, Basin 0052

08/05/2016 A, 100254 Pump Station 0052 Upgrade08/05/2016 A, Project Closeout

Closeout PhaseIssue SAC LetterAdministrative CloseoutProject Closed

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 9 of 161 TASK filter: All Activities© Oracle Corporation

Page 10: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

Basin 0057Basin 0057 06/13/2012 A 03/01/2020 1762

100005 Ba100005 Basin 0057 Infiltration/Inflow Study and Repairs 05/22/2015 A 10/07/2015 A 254InfiltratioInfiltration/Inflow 05/22/2015 A 10/06/2015 A 20

B1000 Infiltration/Inflow Phase 05/22/2015 A 10/06/2015 A 20CIPP RepCIPP Repairs 05/22/2015 A 10/06/2015 A 20

B1005 CIPP Phase 05/22/2015 A 10/06/2015 A 20B1020 Issue NTP for CIPP Repairs 05/22/2015 A 0B1030 Conduct CIPP Repairs 09/23/2015 A 10/06/2015 A 20

Project CProject Closeout 10/07/2015 A 10/07/2015 A 0B1175 Closeout Phase 10/07/2015 A 10/07/2015 A 0B1200 Project Closed 10/07/2015 A 0

100255 FM100255 FM for Pump Station 0057 08/01/2018 03/01/2020 579DesignDesign 08/01/2018 05/15/2019 288

A1170 Design Phase 08/01/2018 05/15/2019 288A1180 Prepare and Submit Design Package 08/01/2018 08/07/2018 7A1190 Engage Design Consultant 08/08/2018 09/04/2018 28A1193 TA Preparation 09/05/2018 09/18/2018 14A1195 TA Approval Process 09/19/2018 10/28/2018 40A1200 Issue Design NTP 10/29/2018 0A1220 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/29/2018 04/17/2019 171

30% Des30% Design 10/29/2018 01/16/2019 80A1230 A/E Prepares 30% Construction Documents 10/29/2018 12/17/2018 50A1240 30% CDs Submittal 12/17/2018 0A1260 30% Review (MDWASD/PSIP Team) 12/18/2018 01/16/2019 30

60% Des60% Design 12/18/2018 01/30/2019 44A1280 A/E Prepares 60% Construction Documents 12/18/2018 01/16/2019 30A1290 60% CDs Submittal 01/16/2019 0A1300 60% Review (MDWASD/PSIP Team) 01/17/2019 01/30/2019 14

90% Des90% Design 01/17/2019 04/17/2019 91A1310 A/E Prepares 90% Construction Documents 01/17/2019 02/25/2019 40A1320 90% CDs Submittal 02/25/2019 0A1330 90% Review (MDWASD/PSIP Team) 02/26/2019 03/27/2019 30A1345 90% RER (DERM) Permit Submittal (Force Main) 03/27/2019 0A1346 90% RER (DERM) Permit Review (Force Main) 03/28/2019 04/17/2019 21A1350 90% Other/Additional Permit Submittal (Force Main) 03/27/2019 0A1351 90% Other/Additional Permit Review (Force Main) 03/28/2019 04/17/2019 21A1385 90% CD PM Comments Evaluation Completed 04/17/2019 0

100% De100% Design 04/18/2019 05/15/2019 28A1390 A/E Prepares 100% Construction Documents 04/18/2019 05/01/2019 14A1400 100% CDs Submittal 05/01/2019 0A1410 100% Review (MDWASD/PSIP Team) 05/02/2019 05/15/2019 14A1420 Design Completed 05/15/2019 0

MDWASDMDWASD Procurement 05/15/2019 08/27/2019 104A1425 Procurement Phase 05/15/2019 08/27/2019 104A1430 Submit CDs to MDWASD Procurement Division 05/15/2019 0A1434 Bid Notice Preparation Period 05/16/2019 06/17/2019 33A1436 Bid Notice 06/17/2019 0A1438 MDWASD/PSIP Team Prepare for Pre-Bid Conference 06/18/2019 07/01/2019 14A1440 Pre-Bid Conference 07/02/2019 07/02/2019 1

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

03/01/2020, Ba

10/07/2015 A, 100005 Basin 0057 Infiltration/Inflow Study and Repairs10/06/2015 A, Infiltration/Inflow

Infiltration/Inflow Phase10/06/2015 A, CIPP RepairsCIPP Phase

Issue NTP for CIPP RepairsConduct CIPP Repairs10/07/2015 A, Project CloseoutCloseout Phase

Project Closed03/01/2020, 10

05/15/2019, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval ProcessIssue Design NTP

Final Engineering Report Review & Appro01/16/2019, 30% Design

A/E Prepares 30% Construction Documents30% CDs Submittal

30% Review (MDWASD/PSIP Team)01/30/2019, 60% Design

A/E Prepares 60% Construction Documents60% CDs Submittal60% Review (MDWASD/PSIP Team)

04/17/2019, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER (DERM) Permit Submittal (Force

90% RER (DERM) Permit Review (Force M90% Other/Additional Permit Submittal (For

90% Other/Additional Permit Review (Forc90% CD PM Comments Evaluation Comp

05/15/2019, 100% Design

A/E Prepares 100% Construction Docum100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed

08/27/2019, MDWASD Procure

Procurement PhaseSubmit CDs to MDWASD Procurement

Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for PPre-Bid Conference

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 10 of 161 TASK filter: All Activities© Oracle Corporation

Page 11: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

A1448 Bidders Prepare Bids for Submittal 07/03/2019 07/23/2019 21A1450 Bids Submittal 07/23/2019 0A1455 Bids Evaluation (MDWASD/PSIP Team) 07/24/2019 08/13/2019 21A1460 Recommendation for Award Letter 08/13/2019 0A1465 Contract Award (Purchase Order Approval) 08/14/2019 08/27/2019 14

ConstrucConstruction 07/02/2019 11/03/2019 124A1467 Construction Phase 07/02/2019 11/03/2019 124A1474 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 08/28/2019 09/17/2019 21A1476 Pre-Construction Meeting 09/18/2019 09/18/2019 1A1478 WASD Issues NTP (Pre-Const to NTP) 09/19/2019 11/02/2019 45A1479 WASD Issues NTP (PO to NTP) 08/28/2019 11/02/2019 67A1480 Construction NTP 11/03/2019 0A1500 Construction Operations 11/03/2019 11/03/2019 0A1502 Substantial Completion 11/03/2019 0

DesignerDesigner Construction Support Services 07/02/2019 11/02/2019 124A1508 Designer Construction Support Services 07/02/2019 11/02/2019 124

Project CProject Closeout 11/03/2019 03/01/2020 120A1535 Closeout Phase 11/03/2019 03/01/2020 120A1540 Issue SAC Letter 11/03/2019 0A1547 Final Release of Retainage - Construction Contract 11/03/2019 0A1548 Administrative Closeout 11/03/2019 03/01/2020 120A1550 Project Closed 03/01/2020 0

100256 Pu100256 Pump Station 0057 Upgrade * 06/13/2012 A 10/25/2018 790DesignDesign 06/13/2012 A 06/27/2018 A 7

B1000 Design Phase 06/13/2012 A 06/27/2018 A 7B1002 Remedial Action Plan to SAC Letter Issuance 06/13/2012 A 06/27/2018 A 7

Project CProject Closeout 06/27/2018 A 10/25/2018 673B1425 Closeout Phase 06/27/2018 A 10/25/2018 673B1430 Issue SAC Letter 06/27/2018 A 0B1460 Administrative Closeout 06/28/2018 A 10/25/2018 120B1470 Project Closed 10/25/2018 0

Basin 0065Basin 0065 06/30/2014 A 08/01/2018 1633

100007 Pu100007 Pump Station 0065 Upgrade 06/30/2014 A 08/01/2018 1054Pump StPump Station 0065 Upgrade 08/01/2018 08/01/2018 0

B1380 New Activity 08/01/2018 08/01/2018 0DesignDesign 06/30/2014 A 02/05/2015 A 236

B1495 Design Phase 06/30/2014 A 02/05/2015 A 236B1500 Prepare and Submit Design Package 06/30/2014 A 07/14/2014 A 5B1510 Engage Design Consultant 07/15/2014 A 09/22/2014 A 20B1520 Prepare and Issue TA 08/26/2014 A 09/22/2014 A 10B1530 Issue Design NTP 09/25/2014 A 0B1535 MDWASD MH-to-MH Calculation 10/20/2014 A 12/12/2014 A 10B1540 A/E Develops and Submits Final Engineering Report 09/25/2014 A 01/08/2015 A 41B1550 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/08/2014 A 01/15/2015 A 10

30% Des30% Design 09/26/2014 A 10/13/2014 A 26B1560 A/E Prepares 30% Construction Documents 09/26/2014 A 10/08/2014 A 10B1570 Geotechnical Engineering Services 09/26/2014 A 10/08/2014 A 20B1580 Surveying Services 09/26/2014 A 10/08/2014 A 15B1600 30% CDs Submittal 10/08/2014 A 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Bidders Prepare Bids for SubmittaBids Submittal

Bids Evaluation (MDWASD/PSIPRecommendation for Award LetContract Award (Purchase Orde

11/03/2019, Construction

Construction PhaseMDWASD/PSIP Team PrepaPre-Construction Meeting

WASD Issues NTP (Pre-CWASD Issues NTP (PO to

Construction NTPConstruction OperationsSubstantial Completion11/02/2019, Designer Co

Designer Construction Su03/01/2020, Pro

Closeout PhaseIssue SAC LetterFinal Release of Retainag

Administrative CProject Closed

10/25/2018, 100256 Pump Station 0057 Upgrade *06/27/2018 A, Design

Design PhaseRemedial Action Plan to SAC Letter Issuance

10/25/2018, Project Closeout

Closeout PhaseIssue SAC

Administrative CloseoutProject Closed

08/01/2018, Basin 0065

08/01/2018, 100007 Pump Station 0065 Upgrade08/01/2018, Pump Station 0065 UpgradeNew Activity

02/05/2015 A, DesignDesign Phase

Prepare and Submit Design PackageEngage Design ConsultantPrepare and Issue TA

Issue Design NTPMDWASD MH-to-MH Calculation

A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

10/13/2014 A, 30% DesignA/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services

30% CDs Submittal

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 11 of 161 TASK filter: All Activities© Oracle Corporation

Page 12: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1620 30% Review (MDWASD/PSIP Team) 10/09/2014 A 10/13/2014 A 1060% Des60% Design 10/09/2014 A 10/31/2014 A 54

B1630 A/E Prepares 60% Construction Documents 10/09/2014 A 10/23/2014 A 30B1640 60% CDs Submittal 10/23/2014 A 0B1660 60% Review (MDWASD/PSIP Team) 10/23/2014 A 10/31/2014 A 10

90% Des90% Design 10/24/2014 A 02/02/2015 A 106B1670 A/E Prepares 90% Construction Documents 10/24/2014 A 11/20/2014 A 20B1680 90% CDs Submittal 11/20/2014 A 0B1690 90% Review (MDWASD/PSIP Team) 11/21/2014 A 12/05/2014 A 15B1710 90% RER(DERM)FDEP Permit Submittal 01/16/2015 A 0B1720 90% RER(DERM)FDEP Permit Review 01/16/2015 A 01/22/2015 A 15B1750 90% Miami - BD Permit Submittal 01/26/2015 A 0B1760 90% Miami - BD Permit Review 01/26/2015 A 02/02/2015 A 15B1765 90% Miami - PWD Permit Submittal 01/26/2015 A 0B1766 90% Miami - PWD Permit Review 01/26/2015 A 02/02/2015 A 15B1770 90% CD PM Comments Evaluation Completed 02/02/2015 A 0

100% De100% Design 02/03/2015 A 02/05/2015 A 12B1780 A/E Prepares 100% Construction Documents 02/03/2015 A 02/04/2015 A 10B1790 100% CDs Submittal 02/04/2015 A 0B1800 100% Review (MDWASD/PSIP Team) 02/05/2015 A 02/05/2015 A 10B1810 Design Completed 02/05/2015 A 0

MDWASDMDWASD Procurement 02/20/2015 A 04/20/2015 A 105B1305 Procurement Phase 02/20/2015 A 04/20/2015 A 105B1310 Submit CDs to MDWASD Procurement Division 02/20/2015 A 0B1312 Bid Notice Preparation Period 02/20/2015 A 02/20/2015 A 33B1314 Bid Notice 02/20/2015 A 0B1316 MDWASD/PSIP Team Prepared for Pre-Bid Conference 02/21/2015 A 03/02/2015 A 14B1320 Pre-Bid Conference 03/03/2015 A 03/03/2015 A 1B1328 Bidders Prepare Bids for Submittal 03/04/2015 A 04/01/2015 A 21B1330 Bids Submittal 04/01/2015 A 0B1340 MDWASD/PSIP Team Bids Evaluation 04/02/2015 A 04/03/2015 A 21B1350 Recommendation for Award Letter 04/02/2015 A 0B1355 Contract Award (Purchase Order Approval) 04/06/2015 A 04/20/2015 A 14

ConstrucConstruction 03/03/2015 A 12/22/2015 A 1172B1360 Construction Phase 03/03/2015 A 12/22/2015 A 1172B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 04/03/2015 A 04/26/2015 A 33B1365 Preconstruction Meeting 04/27/2015 A 04/27/2015 A 1B1367 WASD Issues NTP (Pre-Const to NTP) 04/28/2015 A 05/31/2015 A 45B1368 WASD Issues NTP (PO to NTP) 04/20/2015 A 05/31/2015 A 45B1370 Construction NTP 06/01/2015 A 0B1400 Construction Operations 06/01/2015 A 12/16/2015 A 150B1400 Original Construction Duration 06/01/2015 A 10/29/2015 A 150B1400 Change Order #1 - Inspections 10/30/2015 A 11/20/2015 A 150B1400 Change Order #2 - FPL 11/21/2015 A 12/22/2015 A 150B1402 Substantial Completion 12/16/2015 A 0

DesignerDesigner Construction Support Services 03/03/2015 A 12/16/2015 A 37B1410 Designer Construction Support Services 03/03/2015 A 12/16/2015 A 109

Project CProject Closeout 12/17/2015 A 08/01/2018 944B1445 Closeout Phase 12/17/2015 A 08/01/2018 944

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

30% Review (MDWASD/PSIP Team)10/31/2014 A, 60% DesignA/E Prepares 60% Construction Documents

60% CDs Submittal60% Review (MDWASD/PSIP Team)

02/02/2015 A, 90% DesignA/E Prepares 90% Construction Documents

90% CDs Submittal90% Review (MDWASD/PSIP Team)

90% RER(DERM)FDEP Permit Submittal90% RER(DERM)FDEP Permit Review

90% Miami - BD Permit Submittal90% Miami - BD Permit Review

90% Miami - PWD Permit Submittal90% Miami - PWD Permit Review

90% CD PM Comments Evaluation Completed02/05/2015 A, 100% DesignA/E Prepares 100% Construction Documents

100% CDs Submittal100% Review (MDWASD/PSIP Team)

Design Completed04/20/2015 A, MDWASD ProcurementProcurement Phase

Submit CDs to MDWASD Procurement DivisionBid Notice Preparation Period

Bid NoticeMDWASD/PSIP Team Prepared for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for Submittal

Bids SubmittalMDWASD/PSIP Team Bids Evaluation

Recommendation for Award LetterContract Award (Purchase Order Approval)

12/22/2015 A, ConstructionConstruction Phase

MDWASD/PSIP Team Prepare for Pre-Construction MeetingPreconstruction Meeting

WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Construction NTPConstruction Operations

Original Construction DurationChange Order #1 - Inspections

Change Order #2 - FPL

Substantial Completion12/16/2015 A, Designer Construction Support ServicesDesigner Construction Support Services

08/01/2018, Project CloseoutCloseout Phase

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 12 of 161 TASK filter: All Activities© Oracle Corporation

Page 13: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1450 Issue SAC Letter 02/04/2016 A 0B1470 Final Release of Retainage - Construction Contract 04/12/2017 A 0B1480 Administrative Closeout 12/17/2015 A 08/01/2018 120B1490 Project Closed 08/01/2018 0

100006 Ba100006 Basin 0065 Infiltration/Inflow Study and Repairs 04/17/2015 A 06/16/2016 A 373InfiltratioInfiltration/Inflow 04/17/2015 A 06/15/2016 A 197

B1000 Infiltration/Inflow Phase 04/17/2015 A 06/15/2016 A 197CIPP RepCIPP Repairs 04/17/2015 A 06/11/2015 A 40

B1065 CIPP Phase 04/17/2015 A 06/11/2015 A 40B1080 Issue NTP for CIPP Repairs 04/17/2015 A 0B1090 Conduct CIPP Repairs 06/10/2015 A 06/11/2015 A 20

ManholeManhole Repairs 10/02/2015 A 06/15/2016 A 20B1115 Manhole Phase 10/02/2015 A 06/15/2016 A 20B1130 Issue NTP for Manhole Repairs 10/02/2015 A 0B1140 Conduct Manhole Repairs 10/13/2015 A 06/15/2016 A 20

Dig & ReDig & Replace Repairs 05/18/2015 A 10/02/2015 A 30B1165 Dig & Replace Phase 05/18/2015 A 10/02/2015 A 30B1180 Issue NTP for Dig & Replace Repairs 05/18/2015 A 0B1190 Conduct Dig & Replace Repairs 09/28/2015 A 10/02/2015 A 30

Project CProject Closeout 06/16/2016 A 06/16/2016 A 0B1235 Closeout Phase 06/16/2016 A 06/16/2016 A 0B1260 Project Closed 06/16/2016 A 0

100231 FM100231 FM for Pump Station 0065 Phase 1 07/14/2014 A 08/01/2018 1619DesignDesign 07/14/2014 A 02/12/2015 A 232

A1565 Design Phase 07/14/2014 A 02/12/2015 A 232A1570 Prepare and Submit Design Package 07/14/2014 A 07/18/2014 A 5A1580 Engage Design Consultant 07/21/2014 A 09/19/2014 A 20A1590 Prepare and Issue TA 09/11/2014 A 10/29/2014 A 20B1600 Issue Design NTP 10/30/2014 A 0B1610 A/E Develops and Submits Final Engineering Report 10/30/2014 A 02/12/2015 A 120B1620 Final Engineering Report Review & Approval (MDWASD/PSIP Te 01/21/2015 A 01/28/2015 A 0

30% Des30% Design 10/30/2014 A 11/10/2014 A 47B1630 A/E Prepares 30% Construction Documents 10/30/2014 A 11/05/2014 A 30B1640 Geotechnical Engineering Services 10/30/2014 A 11/05/2014 A 20B1650 Surveying Services 10/30/2014 A 11/05/2014 A 15B1670 30% CDs Submittal 11/05/2014 A 0B1690 30% Review (MDWASD/PSIP Team) 11/06/2014 A 11/10/2014 A 10

60% Des60% Design 11/07/2014 A 12/11/2014 A 42B1700 A/E Prepares 60% Construction Documents 11/07/2014 A 11/21/2014 A 30B1710 60% CDs Submittal 11/21/2014 A 0B1720 60% Legal Review (MDWASD) 11/24/2014 A 11/24/2014 A 15B1730 60% Review (MDWASD/PSIP Team) 11/24/2014 A 12/11/2014 A 10

90% Des90% Design 11/21/2014 A 02/12/2015 A 82B1740 A/E Prepares 90% Construction Documents 11/24/2014 A 12/22/2014 A 20B1750 90% CDs Submittal 12/22/2014 A 0B1760 90% Review (MDWASD/PSIP Team) 12/23/2014 A 01/02/2015 A 15B1770 90% Legal Review (MDWASD) 12/23/2014 A 12/23/2014 A 15B1780 90% RER(DERM)FDEP Permit Submittal (FM) 01/28/2015 A 0B1790 90% RER(DERM)FDEP Permit Review (FM) 01/28/2015 A 02/12/2015 A 1

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Issue SAC LetterFinal Release of Retainage - Construction Contract

Administrative Closeout

Project Closed06/16/2016 A, 100006 Basin 0065 Infiltration/Inflow Study and Repairs06/15/2016 A, Infiltration/Inflow

Infiltration/Inflow Phase06/11/2015 A, CIPP Repairs

CIPP PhaseIssue NTP for CIPP Repairs

Conduct CIPP Repairs06/15/2016 A, Manhole Repairs

Manhole PhaseIssue NTP for Manhole Repairs

Conduct Manhole Repairs10/02/2015 A, Dig & Replace Repairs

Dig & Replace PhaseIssue NTP for Dig & Replace Repairs

Conduct Dig & Replace Repairs06/16/2016 A, Project Closeout

Closeout PhaseProject Closed

08/01/2018, 100231 FM for Pump Station 0065 Phase 102/12/2015 A, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantPrepare and Issue TAIssue Design NTP

A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

11/10/2014 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services

30% CDs Submittal30% Review (MDWASD/PSIP Team)

12/11/2014 A, 60% Design

A/E Prepares 60% Construction Documents60% CDs Submittal60% Legal Review (MDWASD)60% Review (MDWASD/PSIP Team)

02/12/2015 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% Legal Review (MDWASD)90% RER(DERM)FDEP Permit Submittal (FM)90% RER(DERM)FDEP Permit Review (FM)

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 13 of 161 TASK filter: All Activities© Oracle Corporation

Page 14: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1820 90% Miami - PWD Permit Submittal (Force Main) 11/21/2014 A 0B1830 90% Miami - PWD Permit Review (Force Main) 11/21/2014 A 11/28/2014 A 5B1840 90% CD PM Comments Evaluation Completed 02/12/2015 A 0

100% De100% Design 02/12/2015 A 02/12/2015 A 0B1880 Design Completed 02/12/2015 A 0

MDWASDMDWASD Procurement 03/18/2015 A 06/01/2015 A 114B1425 Procurement Phase 03/18/2015 A 06/01/2015 A 114B1430 Submit CDs to MDWASD Procurement Division 03/18/2015 A 0B1440 Pre-Bid Conference 04/03/2015 A 0B1450 Bids Submittal 05/04/2015 A 0B1455 MDWASD/PSIP Team Bids Evaluation 05/05/2015 A 05/06/2015 A 20B1460 Contractor Selected 05/06/2015 A 0B1462 Contract Award (Purchase Order Approval) 05/07/2015 A 06/01/2015 A 10

ConstrucConstruction 05/15/2015 A 11/10/2015 A 1295B1465 Construction Phase 05/15/2015 A 11/10/2015 A 1295B1466 Pre Construction Meeting 06/04/2015 A 0B1468 MDWASD/PSIP prepare Notice to Proceed 06/05/2015 A 07/17/2015 A 10B1469 WASD Issues NTP (PO to NTP) 06/02/2015 A 07/19/2015 A 53B1470 Construction NTP 07/20/2015 A 0B1480 Mobilization 05/15/2015 A 07/20/2015 A 10B1490 Permit Approvals 05/15/2015 A 07/20/2015 A 20B1500 Construction Operations 07/20/2015 A 10/21/2015 A 86B1502 Substantial Completion 10/21/2015 A 0

DesignerDesigner Construction Support Services 07/20/2015 A 10/30/2015 A 96B1560 Designer Construction Support Services 07/20/2015 A 10/30/2015 A 96

ConstrucConstruction Close Out 10/22/2015 A 11/10/2015 A 31B1510 Commissioning 10/22/2015 A 11/10/2015 A 15B1520 Punch List 10/22/2015 A 11/10/2015 A 10

Project CProject Closeout 10/22/2015 A 08/01/2018 1004B1535 Closeout Phase 10/22/2015 A 08/01/2018 1004B1540 Issue SAC Letter 02/04/2016 A 0B1547 Final Release of Retainage - Construction Contract 08/04/2017 A 0B1548 Administrative Closeout 10/22/2015 A 08/01/2018 120B1550 Project Closed 08/01/2018 0

100237 FM100237 FM for Pump Station 0065 Phase 2 07/14/2014 A 08/01/2018 1619DesignDesign 07/14/2014 A 09/20/2016 A 817

B1485 Design Phase 07/14/2014 A 09/20/2016 A 817B1490 Prepare and Submit Design Package 07/14/2014 A 07/25/2014 A 5B1500 Engage Design Consultant 07/26/2014 A 04/03/2015 A 20B1510 Prepare and Issue TA 04/04/2015 A 05/01/2015 A 20B1520 Issue Design NTP 05/07/2015 A 0B1530 A/E Develops and Submits Final Engineering Report 05/07/2015 A 08/17/2016 A 160B1540 Final Engineering Report Review & Approval (MDWASD/PSIP Te 05/07/2015 A 06/08/2016 A 85

30% Des30% Design 05/08/2015 A 10/27/2015 A 134B1550 A/E Prepares 30% Construction Documents 05/08/2015 A 06/12/2015 A 60B1560 Geotechnical Engineering Services (Includes GPR) 05/08/2015 A 06/12/2015 A 30B1570 Surveying Services 05/08/2015 A 06/12/2015 A 30B1590 30% CDs Submittal 06/12/2015 A 0B1610 30% Review (MDWASD/PSIP Team) 06/15/2015 A 06/26/2015 A 10

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

90% Miami - PWD Permit Submittal (Force Main)90% Miami - PWD Permit Review (Force Main)90% CD PM Comments Evaluation Completed02/12/2015 A, 100% Design

Design Completed06/01/2015 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement DivisionPre-Bid Conference

Bids SubmittalMDWASD/PSIP Team Bids Evaluation

Contractor SelectedContract Award (Purchase Order Approval)

11/10/2015 A, Construction

Construction PhasePre Construction MeetingMDWASD/PSIP prepare Notice to ProceedWASD Issues NTP (PO to NTP)

Construction NTPMobilizationPermit Approvals

Construction OperationsSubstantial Completion

10/30/2015 A, Designer Construction Support Services

Designer Construction Support Services11/10/2015 A, Construction Close Out

CommissioningPunch List

08/01/2018, Project Closeout

Closeout PhaseIssue SAC Letter

Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed08/01/2018, 100237 FM for Pump Station 0065 Phase 2

09/20/2016 A, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantPrepare and Issue TAIssue Design NTP

A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

10/27/2015 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering Services (Includes GPR)Surveying Services

30% CDs Submittal30% Review (MDWASD/PSIP Team)

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 14 of 161 TASK filter: All Activities© Oracle Corporation

Page 15: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1612 TA Rev 1 Preparation (Deleted 60% Design) 06/29/2015 A 09/18/2015 A 40B1614 TA Rev 1 Approval Process (Deleted 60% Design) 09/21/2015 A 10/27/2015 A 40

90% Des90% Design 10/28/2015 A 08/17/2016 A 64B1660 A/E Prepares 90% Construction Documents 10/28/2015 A 05/27/2016 A 20B1670 90% CDs Submittal 05/27/2016 A 0

B1680 90% Review (MDWASD/PSIP Team) 05/30/2016 A 06/08/2016 A 15B1700 90% RER(DERM)FDEP Permit Submittal 06/09/2016 A 0B1710 90% RER(DERM)FDEP Permit Review 06/09/2016 A 06/17/2016 A 15B1720 90% FDOT Permit Submittal 06/10/2016 A 0B1730 90% FDOT Permit Review 06/10/2016 A 08/17/2016 A 15B1740 90% Miami - PWD Permit Submittal 06/01/2016 A 0B1750 90% Miami - PWD Permit Review 06/01/2016 A 06/06/2016 A 15B1752 90% Miami - MDT Permit Submittal 07/11/2016 A 0B1754 90% Miami - MDT Permit Review 07/11/2016 A 07/27/2016 A 15B1760 90% CD PM Comments Evaluation Completed 08/17/2016 A 0

100% De100% Design 08/18/2016 A 09/20/2016 A 67B1770 A/E Prepares 100% Construction Documents 08/18/2016 A 09/19/2016 A 10B1780 100% CDs Submittal 09/19/2016 A 0B1790 100% Review (MDWASD/PSIP Team) 09/20/2016 A 09/20/2016 A 5B1800 Design Completed 09/20/2016 A 0

MDWASDMDWASD Procurement 09/21/2016 A 03/15/2017 A 132B1305 Procurement Phase 09/21/2016 A 03/15/2017 A 132B1310 Submit CDs to MDWASD Procurement Division 09/21/2016 A 0B1311 Bid Notice Preparation Period 09/22/2016 A 10/20/2016 A 33B1312 Bid Notice 10/20/2016 A 0B1318 Preparation for Bid Conference 10/21/2016 A 11/09/2016 A 14B1320 Pre-Bid Conference 11/10/2016 A 11/10/2016 A 1B1328 Bidders Prepare Bids for Submittal 11/11/2016 A 12/14/2016 A 21B1330 Bids Submittal 12/14/2016 A 0B1340 MDWASD/PSIP Team Bids Evaluation 12/15/2016 A 01/24/2017 A 21B1350 Recommendation for Award Letter 01/24/2017 A 0B1352 Contract Award (Purchase Order Approval) 01/24/2017 A 03/15/2017 A 14

ConstrucConstruction 11/10/2016 A 02/15/2018 A 769B1355 Construction Phase 11/10/2016 A 01/25/2018 A 769B1356 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 01/25/2017 A 04/05/2017 A 21B1357 Pre-Construction Meeting 04/06/2017 A 04/06/2017 A 1B1359 WASD Issues NTP (Pre-Const to NTP) 04/07/2017 A 07/16/2017 A 45

B1360 Construction NTP 07/17/2017 A 0B1369 WASD Issues NTP (PO to NTP) 03/16/2017 A 07/16/2017 A 53B1390 Construction Operations 07/17/2017 A 01/25/2018 A 149B1390 Original Construction Duration 07/17/2017 A 12/14/2017 A 149B1390 Change Order #1 - Hurricane Irma Delay 12/15/2017 A 01/04/2018 A 149B1390 Change Order #2 - City of Miami Permit Delay 01/05/2018 A 02/15/2018 A 149B1392 Substantial Completion 01/25/2018 A 0

DesignerDesigner Construction Support Services 11/10/2016 A 01/25/2018 A 288B1480 Designer Construction Support Services 11/10/2016 A 01/25/2018 A 288

Project CProject Closeout 01/26/2018 A 08/01/2018 153B1425 Closeout Phase 01/26/2018 A 08/01/2018 153

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

TA Rev 1 Preparation (Deleted 60% Design)TA Rev 1 Approval Process (Deleted 60% Design)

08/17/2016 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal90% RER(DERM)FDEP Permit Review

90% FDOT Permit Submittal90% FDOT Permit Review

90% Miami - PWD Permit Submittal90% Miami - PWD Permit Review

90% Miami - MDT Permit Submittal90% Miami - MDT Permit Review

90% CD PM Comments Evaluation Completed09/20/2016 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal

100% Review (MDWASD/PSIP Team)Design Completed

03/15/2017 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid NoticePreparation for Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter

Contract Award (Purchase Order Approval)02/15/2018 A, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)

Construction NTPWASD Issues NTP (PO to NTP)

Construction OperationsOriginal Construction Duration

Change Order #1 - Hurricane Irma DelayChange Order #2 - City of Miami Permit Delay

Substantial Completion01/25/2018 A, Designer Construction Support Services

Designer Construction Support Services08/01/2018, Project Closeout

Closeout Phase

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 15 of 161 TASK filter: All Activities© Oracle Corporation

Page 16: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1450 Final Release of Retainage - Construction Contract 08/01/2018 0B1460 Administrative Closeout 01/26/2018 A 08/01/2018 120B1470 Project Closed 08/01/2018 0

Basin 0067Basin 0067 09/25/2014 A 08/01/2018 1535

100009 Pu100009 Pump Station 0067 Upgrade 12/15/2014 A 08/01/2018 1388DesignDesign 12/15/2014 A 09/30/2015 A 276

B1000 Design Phase 12/15/2014 A 09/30/2015 A 276B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 12/15/2014 A 12/17/2014 A 5B1020 Engage Design Consultant 12/18/2014 A 04/10/2015 A 20B1030 Issue Design NTP 04/13/2015 A 0B1040 A/E Develops and Submits Final Engineering Report 04/13/2015 A 09/11/2015 A 90B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 04/13/2015 A 08/20/2015 A 100

30% Des30% Design 04/13/2015 A 06/26/2015 A 46B1060 A/E Prepares 30% Construction Documents 04/13/2015 A 06/05/2015 A 30B1070 Geotechnical Engineering Services 04/15/2015 A 06/05/2015 A 20

B1080 Surveying Services 04/15/2015 A 06/05/2015 A 15B1100 30% CDs Submittal 06/05/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 06/09/2015 A 06/26/2015 A 10

90% Des90% Design 06/08/2015 A 09/11/2015 A 154B1130 A/E Prepares 90% Construction Documents 06/08/2015 A 07/23/2015 A 35B1140 90% CDs Submittal 07/23/2015 A 0B1150 90% Review (MDWASD/PSIP Team) 07/24/2015 A 08/20/2015 A 15B1160 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 08/21/2015 A 0B1170 90% RER(DERM)/FDEP Permit Review (Pump Station) 08/24/2015 A 08/28/2015 A 15B1180 90% Miami - BD Permit Submittal (Pump Station) 08/31/2015 A 0B1190 90% Miami - BD Permit Review (Pump Station) 08/31/2015 A 09/11/2015 A 15B1200 90% Miami - PWD Permit Submittal (Pump Station) 08/31/2015 A 0B1210 90% Miami - PWD Permit Review (Pump Station) 08/31/2015 A 09/11/2015 A 15B1220 90% CD PM Comments Evaluation Completed 09/11/2015 A 0

100% De100% Design 09/14/2015 A 09/30/2015 A 63B1230 A/E Prepares 100% Construction Documents 09/14/2015 A 09/21/2015 A 10B1240 100% CDs Submittal 09/22/2015 A 0B1250 100% Review (MDWASD/PSIP Team) 09/23/2015 A 09/30/2015 A 10B1260 Design Completed 09/30/2015 A 0

MDWASDMDWASD Procurement 10/02/2015 A 04/12/2016 A 72B1265 Procurement Phase 10/02/2015 A 04/12/2016 A 72B1270 Submit CDs to MDWASD Procurement Division 10/02/2015 A 0B1272 Bid Notice Preparation Period 10/05/2015 A 11/02/2015 A 23B1274 Bid Notice 11/03/2015 A 0B1276 MDWASD/PSIP Team Prepare for Pre-Bid Conference 11/04/2015 A 11/16/2015 A 10

B1280 Pre-Bid Conference 11/17/2015 A 11/17/2015 A 1B1288 Bidders Prepare Bids for Submittal 11/18/2015 A 12/16/2015 A 15B1290 Bids Submittal 12/17/2015 A 0B1300 MDWASD/PSIP Team Bids Evaluation 12/18/2015 A 01/05/2016 A 15B1310 Recommendation for Award Letter 01/05/2016 A 0B1315 Contract Award (Purchase Order Approval) 01/06/2016 A 04/12/2016 A 10

ConstrucConstruction 11/17/2015 A 07/18/2017 A 1128B1320 Construction Phase 11/17/2015 A 07/18/2017 A 1128

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed08/01/2018, Basin 0067

08/01/2018, 100009 Pump Station 0067 Upgrade09/30/2015 A, Design

Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book

Engage Design ConsultantIssue Design NTP

A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

06/26/2015 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering Services

Surveying Services30% CDs Submittal30% Review (MDWASD/PSIP Team)

09/11/2015 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)/FDEP Permit Submittal (Pump Station)90% RER(DERM)/FDEP Permit Review (Pump Station)

90% Miami - BD Permit Submittal (Pump Station)90% Miami - BD Permit Review (Pump Station)

90% Miami - PWD Permit Submittal (Pump Station)90% Miami - PWD Permit Review (Pump Station)

90% CD PM Comments Evaluation Completed09/30/2015 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal

100% Review (MDWASD/PSIP Team)Design Completed

04/12/2016 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid Conference

Pre-Bid ConferenceBidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter

Contract Award (Purchase Order Approval)07/18/2017 A, Construction

Construction Phase

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 16 of 161 TASK filter: All Activities© Oracle Corporation

Page 17: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1324 MDWASD/PSIP Team prepare for Pre-Construction Meeting 01/06/2016 A 01/13/2016 A 15B1325 Pre-Construction Meeting 01/14/2016 A 01/14/2016 A 1B1326 WASD Issues NTP (PO to NTP) 04/13/2016 A 01/02/2017 A 53

B1330 Construction NTP 01/03/2017 A 0B1360 Construction Operations 01/03/2017 A 07/10/2017 A 150B1360 Original Construction Duration 01/03/2017 A 06/02/2017 A 150B1360 Change Order #1 - FPL 06/03/2017 A 06/20/2017 A 150B1360 Change Order #2 - Wet Well Leak 06/21/2017 A 07/18/2017 A 150B1362 Substantial Completion 07/10/2017 A 0

DesignerDesigner Construction Support Services 11/17/2015 A 07/10/2017 A 270B1370 Designer Construction Support Services 11/17/2015 A 07/10/2017 A 270

Project CProject Closeout 07/11/2017 A 08/01/2018 365B1405 Closeout Phase 07/11/2017 A 08/01/2018 365

B1410 Issue SAC Letter 08/01/2018 0B1430 Final Release of Retainage - Construction Contract 08/01/2018 0B1440 Administrative Closeout 07/11/2017 A 08/01/2018 120B1450 Project Closed 08/01/2018 0

100008 Ba100008 Basin 0067 Infiltration/Inflow Study and Repairs 09/25/2014 A 07/30/2015 A 604InfiltratioInfiltration/Inflow 09/25/2014 A 07/29/2015 A 298

B1000 Infiltration/inflow Phase 09/25/2014 A 07/29/2015 A 298Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 07/29/2015 A 298

B1005 SSES Phase 09/25/2014 A 07/29/2015 A 298B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 07/10/2015 A 07/29/2015 A 30

Project CProject Closeout 07/30/2015 A 07/30/2015 A 0B1235 Closeout Phase 07/30/2015 A 07/30/2015 A 0B1260 Project Closed 07/30/2015 A 0

100210 FM100210 FM for Pump Station 0067 11/14/2014 A 08/01/2018 1469DesignDesign 11/14/2014 A 08/18/2015 A 329

B1000 Design Phase 11/14/2014 A 08/18/2015 A 329B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 11/14/2014 A 12/10/2014 A 5B1020 Engage Design Consultant 12/11/2014 A 03/12/2015 A 20B1030 Issue Design NTP 03/12/2015 A 0B1040 A/E Develops and Submits Final Engineering Report 03/12/2015 A 07/29/2015 A 98B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 03/12/2015 A 06/11/2015 A 65

30% Des30% Design 03/13/2015 A 04/22/2015 A 45B1060 A/E Prepares 30% Construction Documents 03/13/2015 A 04/13/2015 A 30B1070 Geotechnical Engineering Services 03/13/2015 A 04/13/2015 A 19B1080 Surveying Services 03/13/2015 A 04/14/2015 A 19B1100 30% CDs Submittal 04/13/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 04/14/2015 A 04/22/2015 A 0

60% Des60% Design 04/14/2015 A 05/19/2015 A 26B1140 A/E Prepares 60% Construction Documents 04/14/2015 A 05/13/2015 A 20B1150 60% CDs Submittal 05/12/2015 A 0

B1170 60% Review (MDWASD/PSIP Team) 05/13/2015 A 05/19/2015 A 790% Des90% Design 04/28/2015 A 07/29/2015 A 106

B1176 90% Miami - PWD Permit Submittal (Force Main) 04/28/2015 A 0B1178 90% Miami - PWD Permit Review (Force Main) 04/28/2015 A 04/28/2015 A 10B1180 A/E Prepares 90% Construction Documents 05/13/2015 A 06/05/2015 A 15

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

MDWASD/PSIP Team prepare for Pre-Construction MeetingPre-Construction Meeting

WASD Issues NTP (PO to NTP)

Construction NTPConstruction Operations

Original Construction DurationChange Order #1 - FPL

Change Order #2 - Wet Well Leak

Substantial Completion07/10/2017 A, Designer Construction Support Services

Designer Construction Support Services08/01/2018, Project Closeout

Closeout Phase

Issue SAC LetterFinal Release of Retainage - Construction ContractAdministrative CloseoutProject Closed

07/30/2015 A, 100008 Basin 0067 Infiltration/Inflow Study and Repairs07/29/2015 A, Infiltration/Inflow

Infiltration/inflow Phase07/29/2015 A, Sanitary Sewer Evaluation SurveySSES Phase

Issue NTP to SSES ContractorConduct SSES07/30/2015 A, Project CloseoutCloseout Phase

Project Closed08/01/2018, 100210 FM for Pump Station 0067

08/18/2015 A, Design

Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book

Engage Design ConsultantIssue Design NTP

A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

04/22/2015 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal

30% Review (MDWASD/PSIP Team)05/19/2015 A, 60% Design

A/E Prepares 60% Construction Documents60% CDs Submittal

60% Review (MDWASD/PSIP Team)07/29/2015 A, 90% Design

90% Miami - PWD Permit Submittal (Force Main)90% Miami - PWD Permit Review (Force Main)

A/E Prepares 90% Construction Documents

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 17 of 161 TASK filter: All Activities© Oracle Corporation

Page 18: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1190 90% CDs Submittal 06/05/2015 A 0B1200 90% Review (MDWASD/PSIP Team) 06/08/2015 A 07/15/2015 A 10B1230 90% RER(DERM)FDEP Permit Submittal (Force Main) 07/16/2015 A 0B1240 90% RER(DERM)FDEP Permit Review (Force Main) 07/16/2015 A 07/29/2015 A 15B1290 90% CD PM Comments Evaluation Completed 07/29/2015 A 0

100% De100% Design 07/30/2015 A 08/18/2015 A 15B1300 A/E Prepares 100% Construction Documents 07/30/2015 A 08/11/2015 A 5B1310 100% CDs Submittal 08/11/2015 A 0B1320 100% Review (MDWASD/PSIP Team) 08/12/2015 A 08/18/2015 A 5B1330 Design Completed 08/18/2015 A 0

MDWASDMDWASD Procurement 08/18/2015 A 01/29/2016 A 120B1335 Procurement Phase 08/18/2015 A 01/29/2016 A 120B1340 Submit CDs to MDWASD Procurement Division 08/18/2015 A 0B1342 Bid Notice Preparation Period 08/19/2015 A 09/24/2015 A 23B1344 Bid Notice 09/25/2015 A 0B1346 MDWASD/PSIP Team Prepare for Pre-Bid Conference 09/28/2015 A 10/06/2015 A 10B1350 Pre-Bid Conference 10/07/2015 A 10/07/2015 A 1B1352 Bidders Prepare Bids for Submittal 10/08/2015 A 11/05/2015 A 15B1360 Bids Submittal 11/06/2015 A 0B1370 MDWASD/PSIP Team Bids Evaluation 11/09/2015 A 12/16/2015 A 15B1380 Recommendation for Award Letter 12/17/2015 A 0B1385 Contract Award (Purchase Order Approval) 12/18/2015 A 01/29/2016 A 10

ConstrucConstruction 10/07/2015 A 09/30/2016 A 1169B1390 Construction Phase 10/07/2015 A 09/30/2016 A 1169B1394 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 12/18/2015 A 01/06/2016 A 15B1396 Pre- Construction Meeting 01/07/2016 A 01/07/2016 A 1B1398 WASD Issues NTP (PO to NTP) 01/30/2016 A 03/01/2016 A 53B1400 Construction NTP 03/02/2016 A 0B1430 Construction Operations 03/02/2016 A 05/20/2016 A 149B1432 Substantial Completion 05/20/2016 A 0

DesignerDesigner Construction Support Services 10/07/2015 A 09/30/2016 A 290B1440 Designer Construction Support Services 10/07/2015 A 09/30/2016 A 290

ConstrucConstruction Close Out 05/23/2016 A 09/30/2016 A 15B1450 Commissioning 05/23/2016 A 09/30/2016 A 15B1460 Punch List 05/23/2016 A 09/30/2016 A 10

Project CProject Closeout 05/23/2016 A 08/01/2018 731B1475 Closeout Phase 05/23/2016 A 08/01/2018 731B1500 Final Release of Retainage - Construction Contract 08/01/2018 0B1510 Administrative Closeout 05/23/2016 A 08/01/2018 120B1520 Project Closed 08/01/2018 0

Basin 0069Basin 0069 09/25/2014 A 12/18/2019 1861

100010 Pu100010 Pump Station 0069 Upgrade 11/14/2014 A 12/18/2019 1861DesignDesign 11/14/2014 A 09/18/2018 1405

B1000 Design Phase 11/14/2014 A 09/18/2018 1405B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 11/14/2014 A 12/19/2014 A 0B1020 Engage Design Consultant 12/22/2014 A 03/24/2015 A 20B1030 Issue Design NTP 03/24/2015 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 03/24/2015 A 08/21/2018 217

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

90% CDs Submittal90% Review (MDWASD/PSIP Team)

90% RER(DERM)FDEP Permit Submittal (Force Main)90% RER(DERM)FDEP Permit Review (Force Main)

90% CD PM Comments Evaluation Completed08/18/2015 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed

01/29/2016 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid Notice

MDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids SubmittalMDWASD/PSIP Team Bids Evaluation

Recommendation for Award LetterContract Award (Purchase Order Approval)

09/30/2016 A, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre- Construction Meeting

WASD Issues NTP (PO to NTP)Construction NTP

Construction OperationsSubstantial Completion

09/30/2016 A, Designer Construction Support Services

Designer Construction Support Services09/30/2016 A, Construction Close Out

CommissioningPunch List

08/01/2018, Project Closeout

Closeout PhaseFinal Release of Retainage - Construction ContractAdministrative CloseoutProject Closed

12/18/2019, Basin 00

12/18/2019, 100010 09/18/2018, Design

Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book

Engage Design ConsultantIssue Design NTP

Final Engineering Report Review & Approval (MDWASD/PSIP

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 18 of 161 TASK filter: All Activities© Oracle Corporation

Page 19: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

30% Des30% Design 03/25/2015 A 01/18/2018 A 1043B1060 A/E Prepares 30% Construction Documents (Suspended) 03/25/2015 A 06/16/2015 A 30B1070 Geotechnical Engineering Services 03/25/2016 A 06/16/2016 A 20B1080 Surveying Services 03/25/2015 A 05/11/2015 A 15B1082 MDWASD/PSIP Request Feasibility Study 06/17/2015 A 07/17/2015 A 30B1084 DC Prepare Feasibility Study, SOW & Fees for TA 007 Rev 1 07/20/2015 A 08/14/2015 A 30B1086 TA 007 Rev 1 Approval Process 08/14/2015 A 08/25/2015 A 30B1088 DC Prepares Feasibility Study 09/15/2015 A 03/30/2016 A 30B1089 Prepared and Submit Design Package for TA 019 Rev 0 04/01/2016 A 07/22/2016 A 5B1089 Engage Design Consultant for TA 019 Rev 0 07/25/2016 A 10/28/2016 A 20

B1089 TA 019 Rev 0 Preparation 10/31/2016 A 11/17/2016 A 1B1089 TA 019 Rev 0 Approval Process 11/18/2016 A 01/24/2017 A 40B1089 TA 007 Rev 2 Approval Process (Credit TA) 11/18/2016 A 01/24/2017 A 40

B1089 Issue Re-Design NTP 01/30/2017 A 0B1090 A/E Prepares 30% Construction Documents (Re-Design)(On-Ho 01/30/2017 A 03/08/2017 A 50B1092 30% CD On-Hold Until City of Miami - PW Approve Site Layout 03/09/2017 A 11/16/2017 A 50B1094 A/E Prepares 30% Construction Documents (Resume Re-Desig 11/17/2017 A 12/20/2017 A 50B1100 30% CDs Submittal 12/20/2017 A 0B1120 30% Review (MDWASD/PSIP Team) 12/21/2017 A 01/18/2018 A 30

90% Des90% Design 01/19/2018 A 08/21/2018 202B1170 A/E Prepares 90% Construction Documents 01/19/2018 A 03/19/2018 A 40B1180 90% CDs Submittal 03/19/2018 A 0B1190 90% Review (MDWASD/PSIP Team) 03/20/2018 A 04/12/2018 A 30

B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 04/13/2018 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 04/13/2018 A 07/13/2018 A 45B1220 90% Miami - BD Permit Submittal (Pump Station) 07/13/2018 A 0B1230 90% Miami - BD Permit Review (Pump Station) 07/13/2018 A 08/02/2018 21B1240 90% Miami - PWD Permit Submittal (Pump Station) 08/01/2018 0B1250 90% Miami - PWD Permit Review (Pump Station) 08/01/2018 08/21/2018 21B1260 90% CD PM Comments Evaluation Completed 08/21/2018 0

100% De100% Design 08/22/2018 09/18/2018 28B1270 A/E Prepares 100% Construction Documents 08/22/2018 09/04/2018 14B1280 100% CDs Submittal 09/04/2018 0

B1290 100% Review (MDWASD/PSIP Team) 09/05/2018 09/18/2018 14B1300 Design Completed 09/18/2018 0

MDWASDMDWASD Procurement 09/18/2018 12/30/2018 104B1305 Procurement Phase 09/18/2018 12/30/2018 104B1310 Submit CDs to MDWASD Procurement Division 09/18/2018* 0B1312 Bid Notice Preparation Period 09/18/2018 10/20/2018 33B1314 Bid Notice 10/20/2018 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 10/21/2018 11/03/2018 14B1320 Pre-Bid Conference 11/04/2018 11/04/2018 1B1328 Bidders Prepare Bids for Submittal 11/05/2018 11/25/2018 21B1330 Bids Submittal 11/25/2018 0

B1340 MDWASD/PSIP Team Bids Evaluation 11/26/2018 12/16/2018 21B1350 Recommendation for Award Letter 12/16/2018 0B1355 Contract Award (Purchase Order Approval) 12/17/2018 12/30/2018 14

ConstrucConstruction 11/04/2018 08/20/2019 290

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

01/18/2018 A, 30% Design

A/E Prepares 30% Construction Documents (Suspended)Geotechnical Engineering Services

Surveying ServicesMDWASD/PSIP Request Feasibility Study

DC Prepare Feasibility Study, SOW & Fees for TA 007 Rev 1TA 007 Rev 1 Approval Process

DC Prepares Feasibility StudyPrepared and Submit Design Package for TA 019 Rev 0

Engage Design Consultant for TA 019 Rev 0

TA 019 Rev 0 PreparationTA 019 Rev 0 Approval ProcessTA 007 Rev 2 Approval Process (Credit TA)

Issue Re-Design NTPA/E Prepares 30% Construction Documents (Re-Design)(On-Hold)

30% CD On-Hold Until City of Miami - PW Approve Site LayoutA/E Prepares 30% Construction Documents (Resume Re-Design)

30% CDs Submittal30% Review (MDWASD/PSIP Team)

08/21/2018, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)

90% RER(DERM)FDEP Permit Submittal (Pump Station)90% RER(DERM)FDEP Permit Review (Pump Station)90% Miami - BD Permit Submittal (Pump Station)

90% Miami - BD Permit Review (Pump Station)90% Miami - PWD Permit Submittal (Pump Station)

90% Miami - PWD Permit Review (Pump Station)90% CD PM Comments Evaluation Completed

09/18/2018, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal

100% Review (MDWASD/PSIP Team)Design Completed

12/30/2018, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)

08/20/2019, Construction

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 19 of 161 TASK filter: All Activities© Oracle Corporation

Page 20: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1360 Construction Phase 11/04/2018 08/20/2019 290B1362 MDWASD/PSIP Team prepare for Pre-Construction Meeting 12/17/2018 01/06/2019 21B1365 Pre-Construction Meeting 01/07/2019 01/07/2019 1B1366 WASD Issues NTP (Pre-Const to NTP) 01/08/2019 02/21/2019 45B1368 WASD Issues NTP (PO to NTP) 12/31/2018 02/21/2019 53B1370 Construction NTP 02/22/2019 0B1400 Construction Operations 02/22/2019 08/20/2019 180B1402 Substantial Completion 08/20/2019 0

DesignerDesigner Construction Support Services 11/04/2018 08/20/2019 290B1410 Designer Construction Support Services 11/04/2018 08/20/2019 290

Project CProject Closeout 08/20/2019 12/18/2019 120B1445 Closeout Phase 08/20/2019 12/18/2019 120B1450 Issue SAC Letter 08/20/2019 0B1470 Final Release of Retainage - Construction Contract 08/20/2019 0B1480 Administrative Closeout 08/21/2019 12/18/2019 120B1490 Project Closed 12/18/2019 0

100191 Ba100191 Basin 0069 Infiltration/Inflow Study and Repairs 09/25/2014 A 03/31/2016 A 397InfiltratioInfiltration/Inflow 09/25/2014 A 03/30/2016 A 396

B1000 Infiltration/Inflow Phase 09/25/2014 A 03/30/2016 A 396Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 07/21/2015 A 176

B1005 SSES Phase 09/25/2014 A 07/21/2015 A 176

B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 06/02/2015 A 06/25/2015 A 30B1040 Video Review 06/02/2015 A 07/21/2015 A 30

Dig & ReDig & Replace Repairs 11/20/2015 A 03/30/2016 A 142B1165 Dig & Replace Phase 11/20/2015 A 03/30/2016 A 142B1180 Issue NTP for Dig & Replace Repairs 11/20/2015 A 0B1190 Conduct Dig & Replace Repairs 03/30/2016 A 03/30/2016 A 30

Project CProject Closeout 03/31/2016 A 03/31/2016 A 0B1235 Closeout Phase 03/31/2016 A 03/31/2016 A 0B1260 Project Closed 03/31/2016 A 0

Basin 0076Basin 0076 07/30/2014 A 08/01/2018 1603

100011 Ba100011 Basin 0076 Infiltration/Inflow Study and Repairs 09/25/2014 A 03/09/2016 A 604InfiltratioInfiltration/Inflow 09/25/2014 A 03/08/2016 A 414

B1000 Infiltration/Inflow Phase 09/25/2014 A 03/08/2016 A 414Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 01/05/2015 A 262

B1005 SSES Phase 09/25/2014 A 01/05/2015 A 262B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 11/17/2014 A 12/18/2014 A 30B1031 Smoke Testing 11/17/2014 A 12/18/2014 A 10B1040 Video Review 12/18/2014 A 01/05/2015 A 21

CIPP RepCIPP Repairs 05/22/2015 A 03/08/2016 A 20B1065 CIPP Phase 05/22/2015 A 03/08/2016 A 20B1080 Issue NTP for CIPP Repairs 05/22/2015 A 0B1090 Conduct CIPP Repairs 07/09/2015 A 03/08/2016 A 20

ManholeManhole Repairs 10/02/2015 A 11/05/2015 A 20B1115 Manhole Phase 10/02/2015 A 11/05/2015 A 20B1130 Issue NTP for Manhole Repairs 10/02/2015 A 0B1140 Conduct Manhole Repairs 10/06/2015 A 11/05/2015 A 20

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Construction PhaseMDWASD/PSIP Team prepare for Pre-ConstructioPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Construction NTPConstruction OperationsSubstantial Completion08/20/2019, Designer Construc

Designer Construction Support 12/18/2019, Project C

Closeout PhaseIssue SAC LetterFinal Release of Retainage - Co

Administrative CloseoProject Closed

03/31/2016 A, 100191 Basin 0069 Infiltration/Inflow Study and Repairs03/30/2016 A, Infiltration/Inflow

Infiltration/Inflow Phase07/21/2015 A, Sanitary Sewer Evaluation SurveySSES Phase

Issue NTP to SSES ContractorConduct SSESVideo Review

03/30/2016 A, Dig & Replace RepairsDig & Replace Phase

Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs03/31/2016 A, Project CloseoutCloseout Phase

Project Closed08/01/2018, Basin 0076

03/09/2016 A, 100011 Basin 0076 Infiltration/Inflow Study and Repairs03/08/2016 A, Infiltration/Inflow

Infiltration/Inflow Phase01/05/2015 A, Sanitary Sewer Evaluation SurveySSES Phase

Issue NTP to SSES ContractorConduct SSESSmoke Testing

Video Review03/08/2016 A, CIPP RepairsCIPP Phase

Issue NTP for CIPP RepairsConduct CIPP Repairs

11/05/2015 A, Manhole RepairsManhole Phase

Issue NTP for Manhole RepairsConduct Manhole Repairs

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 20 of 161 TASK filter: All Activities© Oracle Corporation

Page 21: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

Dig & ReDig & Replace Repairs 05/18/2015 A 01/22/2016 A 30B1165 Dig & Replace Phase 05/18/2015 A 01/22/2016 A 30B1180 Issue NTP for Dig & Replace Repairs 05/18/2015 A 0B1190 Conduct Dig & Replace Repairs 07/06/2015 A 01/22/2016 A 30

Project CProject Closeout 03/09/2016 A 03/09/2016 A 0B1235 Closeout Phase 03/09/2016 A 03/09/2016 A 0B1260 Project Closed 03/09/2016 A 0

100013 Pu100013 Pump Station 0076 Upgrade 07/30/2014 A 08/01/2018 1603DesignDesign 07/30/2014 A 10/27/2015 A 483

B1000 Design Phase 07/30/2014 A 10/27/2015 A 483B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 07/30/2014 A 08/12/2014 A 5B1020 Engage Design Consultant 08/04/2014 A 11/19/2014 A 20B1030 Issue Design NTP 11/20/2014 A 0B1040 A/E Develops and Submits Final Engineering Report 11/20/2014 A 10/23/2015 A 218B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 11/20/2014 A 06/18/2015 A 85

30% Des30% Design 11/20/2014 A 01/16/2015 A 30B1060 A/E Prepares 30% Construction Documents 11/20/2014 A 12/24/2014 A 30B1070 Geotechnical Engineering Services 11/20/2014 A 12/24/2014 A 20B1080 Surveying Services 11/20/2014 A 12/24/2014 A 15B1100 30% CDs Submittal 12/24/2014 A 0B1120 30% Review (MDWASD/PSIP Team) 12/26/2014 A 01/16/2015 A 10

90% Des90% Design 12/26/2014 A 10/23/2015 A 262B1130 A/E Prepares 90% Construction Documents 12/26/2014 A 04/27/2015 A 20B1140 90% CDs Submittal 04/27/2015 A 0B1150 90% Review (MDWASD/PSIP Team) 04/27/2015 A 05/15/2015 A 15B1160 90% RER(DERM)FDEP Permit Submittal (Pump Station) 04/03/2015 A 0B1170 90% RER(DERM)FDEP Permit Review (Pump Station) 04/03/2015 A 05/04/2015 A 15B1180 90% Miami - BD Permit Submittal 05/18/2015 A 0B1190 90% Miami - BD Permit Review 05/18/2015 A 06/12/2015 A 15B1200 90% Miami - PWD Permit Submittal 05/18/2015 A 0B1210 90% Miami - PWD Permit Review 05/18/2015 A 06/12/2015 A 15B1220 90% CD PM Comments Evaluation Completed 06/12/2015 A 0B1221 TA Approval Process - Rev 1 06/09/2015 A 06/18/2015 A 20B1222 A/E Incorporates 90% Construction Documents Revisions 06/19/2015 A 08/25/2015 A 32

B1223 90% RER(DERM)FDEP Permit Reconciliation Period (Pump Sta 08/26/2015 A 10/22/2015 A 15B1224 90% RER(DERM)FDEP Permit Reconciled (Pump Station) 10/23/2015 A 0B1225 90% Miami - BD Permit Reconciliation Period 08/26/2015 A 10/22/2015 A 15B1226 90% Miami - BD Permit Reconciled 10/23/2015 A 0B1227 90% CD Permits Reconciliation Completed 10/23/2015 A 0

100% De100% Design 08/26/2015 A 10/27/2015 A 119B1230 A/E Prepares 100% Construction Documents 08/26/2015 A 10/23/2015 A 10B1240 100% CDs Submittal 10/26/2015 A 0B1250 100% Review (MDWASD/PSIP Team) 10/26/2015 A 10/26/2015 A 10B1260 Design Completed 10/27/2015 A 0

MDWASDMDWASD Procurement 10/28/2015 A 02/19/2016 A 79B1265 Procurement Phase 10/28/2015 A 02/19/2016 A 79B1270 Submit CDs to MDWASD Procurement Division 10/28/2015 A 0B1272 Bid Notice Preparation Period 10/29/2015 A 11/02/2015 A 23B1274 Bid Notice 11/03/2015 A 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

01/22/2016 A, Dig & Replace RepairsDig & Replace Phase

Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs

03/09/2016 A, Project CloseoutCloseout Phase

Project Closed08/01/2018, 100013 Pump Station 0076 Upgrade

10/27/2015 A, Design

Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book

Engage Design ConsultantIssue Design NTP

A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

01/16/2015 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services

30% CDs Submittal30% Review (MDWASD/PSIP Team)

10/23/2015 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)

90% RER(DERM)FDEP Permit Submittal (Pump Station)90% RER(DERM)FDEP Permit Review (Pump Station)90% Miami - BD Permit Submittal

90% Miami - BD Permit Review90% Miami - PWD Permit Submittal

90% Miami - PWD Permit Review90% CD PM Comments Evaluation Completed

TA Approval Process - Rev 1A/E Incorporates 90% Construction Documents Revisions

90% RER(DERM)FDEP Permit Reconciliation Period (Pump Station)90% RER(DERM)FDEP Permit Reconciled (Pump Station)

90% Miami - BD Permit Reconciliation Period90% Miami - BD Permit Reconciled90% CD Permits Reconciliation Completed10/27/2015 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed

02/19/2016 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation Period

Bid Notice

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 21 of 161 TASK filter: All Activities© Oracle Corporation

Page 22: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1278 MDWASD/PSIP Team Prepare for Pre-Bid Conference 11/04/2015 A 11/16/2015 A 10B1280 Pre-Bid Conference 11/17/2015 A 11/17/2015 A 1B1288 Bidders Prepare Bids for Submittal 11/18/2015 A 12/17/2015 A 15B1290 Bids Submittal 12/17/2015 A 0B1300 MDWASD/PSIP Team Bids Evaluation 12/18/2015 A 01/08/2016 A 15B1310 Recommendation for Award Letter 01/08/2016 A 0B1315 Contract Award (Purchase Order Approval) 01/11/2016 A 02/19/2016 A 10

ConstrucConstruction 11/17/2015 A 07/01/2018 A 1098B1320 Construction Phase 11/17/2015 A 07/01/2018 A 1098B1324 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 01/11/2016 A 01/20/2016 A 15B1326 Pre-Construction Meeting 01/21/2016 A 01/21/2016 A 1

B1328 WASD Issues NTP (PO to NTP) 02/20/2016 A 04/03/2016 A 53B1330 Construction NTP 04/04/2016 A 0B1360 Construction Operations 04/04/2016 A 12/21/2016 A 107B1360 Original Construction Duration 04/04/2016 A 09/01/2016 A 107B1360 Change Order #1 - Tree Permit 09/02/2016 A 12/23/2016 A 107B1362 Substantial Completion 12/21/2016 A 0

DesignerDesigner Construction Support Services 11/17/2015 A 07/01/2018 A 349B1370 Designer Construction Support Services 11/17/2015 A 07/01/2018 A 349

Project CProject Closeout 12/22/2016 A 08/01/2018 617B1405 Closeout Phase 12/22/2016 A 08/01/2018 617B1410 Issue SAC Letter 12/22/2016 A 10/31/2017 A 314B1430 Final Release of Retainage - Construction Contract 08/01/2018 0B1440 Administrative Closeout 12/22/2016 A 08/01/2018 120B1450 Project Closed 08/01/2018 0

Basin 0077Basin 0077 04/04/2018 A 04/04/2018 A 120

100015 Pu100015 Pump Station 0077 Upgrade 04/04/2018 A 04/04/2018 A 120DesignDesign 04/04/2018 A 04/04/2018 A 7

B1000 Design Phase 04/04/2018 A 04/04/2018 A 7

B1012 PS 0077 Swapped With PS 0319 04/04/2018 A 04/04/2018 A 7Project CProject Closeout 04/04/2018 A 04/04/2018 A 120

B1445 Closeout Phase 04/04/2018 A 04/04/2018 A 120B1480 Administrative Closeout 04/04/2018 A 04/04/2018 A 120B1490 Project Closed 04/04/2018 A 0

Basin 0081Basin 0081 12/01/2015 A 08/01/2018 974

100018 Pu100018 Pump Station 0081 Upgrade 12/01/2015 A 08/01/2018 974DesignDesign 12/01/2015 A 12/02/2016 A 249

B1000 Design Phase 12/01/2015 A 12/02/2016 A 249B1010 Prepare and Submit Design Package 12/01/2015 A 12/01/2015 A 5B1020 Engage Design Consultant 12/01/2015 A 12/31/2015 A 20B1022 TA Preparation 01/01/2016 A 01/20/2016 A 1B1024 TA Approval Process 01/21/2016 A 02/26/2016 A 20B1030 Issue Design NTP 03/11/2016 A 0B1040 A/E Develops and Submits Final Engineering Report 03/11/2016 A 07/21/2016 A 115B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 03/11/2016 A 07/21/2016 A 85

30% Des30% Design 03/11/2016 A 06/14/2016 A 63B1060 A/E Prepares 30% Construction Documents 03/11/2016 A 05/24/2016 A 30B1070 Geotechnical Engineering Services 03/11/2016 A 05/24/2016 A 20

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

MDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter

Contract Award (Purchase Order Approval)07/01/2018 A, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

WASD Issues NTP (PO to NTP)Construction NTP

Construction OperationsOriginal Construction Duration

Change Order #1 - Tree Permit

Substantial Completion07/01/2018 A, Designer Construction Support Services

Designer Construction Support Services08/01/2018, Project Closeout

Closeout PhaseIssue SAC Letter

Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed

04/04/2018 A, Basin 0077

04/04/2018 A, 100015 Pump Station 0077 Upgrade04/04/2018 A, Design

Design PhasePS 0077 Swapped With PS 031904/04/2018 A, Project CloseoutCloseout Phase

Administrative CloseoutProject Closed

08/01/2018, Basin 0081

08/01/2018, 100018 Pump Station 0081 Upgrade12/02/2016 A, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval ProcessIssue Design NTP

A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

06/14/2016 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering Services

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 22 of 161 TASK filter: All Activities© Oracle Corporation

Page 23: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1080 Surveying Services 03/11/2016 A 05/24/2016 A 15B1100 30% CDs Submittal 05/24/2016 A 0B1120 30% Review (MDWASD/PSIP Team) 05/25/2016 A 06/14/2016 A 10

90% Des90% Design 05/25/2016 A 12/02/2016 A 96B1170 A/E Prepares 90% Construction Documents (60% On-Board Re 05/25/2016 A 07/21/2016 A 20B1172 Pump Station Monitoring Period 07/22/2016 A 12/02/2016 A 96

Project CProject Closeout 12/02/2016 A 08/01/2018 609B1445 Closeout Phase 12/02/2016 A 08/01/2018 609B1450 Issue SAC Letter 12/02/2016 A 0B1480 Administrative Closeout 12/05/2016 A 08/01/2018 120B1490 Project Closed 08/01/2018 0

Basin 0102Basin 0102 05/22/2015 A 08/01/2018 1056

100019 Ba100019 Basin 0102 Infiltration/Inflow Study and Repairs 05/22/2015 A 03/18/2016 A 266InfiltratioInfiltration/Inflow 05/22/2015 A 03/17/2016 A 164

B1000 Infiltration/Inflow Phase 05/22/2015 A 03/17/2016 A 164CIPP RepCIPP Repairs 05/22/2015 A 03/10/2016 A 20

B1065 CIPP Phase 05/22/2015 A 03/10/2016 A 20B1080 Issue NTP for CIPP Repairs 05/22/2015 A 0B1090 Conduct CIPP Repairs 07/30/2015 A 03/10/2016 A 20

ManholeManhole Repairs 10/30/2015 A 03/17/2016 A 20B1115 Manhole Phase 10/30/2015 A 03/17/2016 A 20B1130 Issue NTP for Manhole Repairs 10/30/2015 A 0B1140 Conduct Manhole Repairs 02/08/2016 A 03/17/2016 A 20

Dig & ReDig & Replace Repairs 06/26/2015 A 03/10/2016 A 59B1165 Dig & Replace Phase 06/26/2015 A 03/10/2016 A 59B1180 Issue NTP for Dig & Replace Repairs 06/26/2015 A 0B1190 Conduct Dig & Replace Repairs 11/30/2015 A 03/10/2016 A 30

Project CProject Closeout 03/18/2016 A 03/18/2016 A 0B1235 Closeout Phase 03/18/2016 A 03/18/2016 A 0B1260 Project Closed 03/18/2016 A 0

100020 Pu100020 Pump Station 0102 Upgrade 01/15/2016 A 08/01/2018 912DesignDesign 01/15/2016 A 02/17/2017 A 122

B1000 Design Phase 01/15/2016 A 02/17/2017 A 122B1010 Prepare and Submit Design Package 01/15/2016 A 01/27/2016 A 5B1020 Engage Design Consultant 01/27/2016 A 03/24/2016 A 20B1022 TA Preparation 03/25/2016 A 03/25/2016 A 1B1024 TA Approval Process 03/28/2016 A 04/28/2016 A 20B1030 Issue Design NTP 05/16/2016 A 0

30% Des30% Design 05/16/2016 A 02/17/2017 A 30B1060 A/E Prepares 30% Construction Documents 05/16/2016 A 07/18/2016 A 30B1082 30% Design Documents Suspended and Project Cancelled 07/19/2016 A 02/17/2017 A 30

Project CProject Closeout 02/20/2017 A 08/01/2018 518B1445 Closeout Phase 02/20/2017 A 08/01/2018 518B1450 Issue SAC Letter 03/08/2017 A 0B1480 Administrative Closeout 02/20/2017 A 08/01/2018 30B1490 Project Closed 08/01/2018 0

Basin 0105Basin 0105 09/14/2015 A 08/01/2018 1218

100021 Pu100021 Pump Station 0105 Upgrade 09/14/2015 A 08/01/2018 1218

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Surveying Services30% CDs Submittal

30% Review (MDWASD/PSIP Team)12/02/2016 A, 90% Design

A/E Prepares 90% Construction Documents (60% On-Board Review)Pump Station Monitoring Period

08/01/2018, Project Closeout

Closeout PhaseIssue SAC Letter

Administrative CloseoutProject Closed08/01/2018, Basin 0102

03/18/2016 A, 100019 Basin 0102 Infiltration/Inflow Study and Repairs03/17/2016 A, Infiltration/Inflow

Infiltration/Inflow Phase03/10/2016 A, CIPP RepairsCIPP Phase

Issue NTP for CIPP RepairsConduct CIPP Repairs03/17/2016 A, Manhole RepairsManhole Phase

Issue NTP for Manhole RepairsConduct Manhole Repairs03/10/2016 A, Dig & Replace RepairsDig & Replace Phase

Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs03/18/2016 A, Project CloseoutCloseout Phase

Project Closed08/01/2018, 100020 Pump Station 0102 Upgrade

02/17/2017 A, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval ProcessIssue Design NTP

02/17/2017 A, 30% Design

A/E Prepares 30% Construction Documents30% Design Documents Suspended and Project Cancelled

08/01/2018, Project Closeout

Closeout PhaseIssue SAC Letter

Administrative CloseoutProject Closed08/01/2018, Basin 0105

08/01/2018, 100021 Pump Station 0105 Upgrade

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 23 of 161 TASK filter: All Activities© Oracle Corporation

Page 24: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

DesignDesign 09/14/2015 A 10/10/2016 A 436B1000 Design Phase 09/14/2015 A 10/10/2016 A 436B1010 Prepare and Submit Design Package 09/14/2015 A 09/21/2015 A 5B1020 Engage Design Consultant 09/22/2015 A 11/30/2015 A 20B1022 TA Preparation 12/01/2015 A 12/08/2015 A 1B1024 TA Approval Process 12/09/2015 A 01/28/2016 A 20B1030 Issue Design NTP 12/29/2015 A 0B1040 A/E Develops and Submits Final Engineering Report 12/29/2015 A 10/03/2016 A 110B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 12/29/2015 A 07/06/2016 A 85

30% Des30% Design 12/30/2015 A 03/30/2016 A 71B1060 A/E Prepares 30% Construction Documents 12/30/2015 A 03/15/2016 A 30B1070 Geotechnical Engineering Services 12/30/2015 A 03/15/2016 A 20B1080 Surveying Services 12/30/2015 A 03/15/2016 A 15B1100 30% CDs Submittal 03/15/2016 A 0B1120 30% Review (MDWASD/PSIP Team) 03/16/2016 A 03/30/2016 A 10

90% Des90% Design 03/16/2016 A 09/28/2016 A 182B1170 A/E Prepares 90% Construction Documents 03/16/2016 A 05/27/2016 A 20B1180 90% CDs Submittal 05/27/2016 A 0B1190 90% Review (MDWASD/PSIP Team) 05/31/2016 A 07/06/2016 A 15B1200 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 07/07/2016 A 0

B1210 90% RER(DERM)/FDEP Permit Review (Pump Station) 07/07/2016 A 09/08/2016 A 15B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 09/19/2016 A 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 09/19/2016 A 09/28/2016 A 15B1260 90% CD PM Comments Evaluation Completed 09/28/2016 A 0

100% De100% Design 09/29/2016 A 10/10/2016 A 31B1270 A/E Prepares 100% Construction Documents 09/29/2016 A 10/10/2016 A 10B1280 100% CDs Submittal 10/10/2016 A 0B1290 100% Review (MDWASD/PSIP Team) 09/29/2016 A 10/10/2016 A 10B1300 Design Completed 10/10/2016 A 0

MDWASDMDWASD Procurement 10/11/2016 A 04/06/2017 A 88B1305 Procurement Phase 10/11/2016 A 04/06/2017 A 88

B1310 Submit CDs to MDWASD Procurement Division 10/11/2016 A 0B1312 Bid Notice Preparation Period 10/12/2016 A 11/21/2016 A 23B1314 Bid Notice 11/21/2016 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 11/22/2016 A 12/13/2016 A 9B1320 Pre-Bid Conference 12/14/2016 A 12/14/2016 A 1B1328 Bidders Prepare Bids for Submittal 12/15/2016 A 01/12/2017 A 21B1330 Bids Submittal 01/12/2017 A 0B1340 MDWASD/PSIP Team Bids Evaluation 01/13/2017 A 02/07/2017 A 15B1350 Recommendation for Award Letter 02/07/2017 A 0B1355 Contract Award (Purchase Order Approval) 02/08/2017 A 04/06/2017 A 10

ConstrucConstruction 12/14/2016 A 12/29/2017 A 770B1360 Construction Phase 12/14/2016 A 12/29/2017 A 770B1364 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 02/08/2017 A 04/12/2017 A 15B1366 Pre-Construction Meeting 04/13/2017 A 04/13/2017 A 1B1368 WASD Issues NTP (Pre-Const to NTP) 04/14/2017 A 05/31/2017 A 26B1369 WASD Issues NTP (PO to NTP) 04/06/2017 A 05/31/2017 A 53

B1370 Construction NTP 06/01/2017 A 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

10/10/2016 A, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval ProcessIssue Design NTP

A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

03/30/2016 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal30% Review (MDWASD/PSIP Team)

09/28/2016 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)/FDEP Permit Submittal (Pump Station)

90% RER(DERM)/FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)90% RER(Building Dept) Permit Review (Pump Station)

90% CD PM Comments Evaluation Completed10/10/2016 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal

100% Review (MDWASD/PSIP Team)Design Completed

04/06/2017 A, MDWASD Procurement

Procurement Phase

Submit CDs to MDWASD Procurement DivisionBid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter

Contract Award (Purchase Order Approval)12/29/2017 A, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Construction NTP

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 24 of 161 TASK filter: All Activities© Oracle Corporation

Page 25: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1400 Construction Operations 06/01/2017 A 12/29/2017 A 151B1400 Original Construction Duration 06/01/2017 A 10/29/2017 A 151B1400 Change Order #1 - Hurricane Irma 10/30/2017 A 11/19/2017 A 151B1402 Substantial Completion 12/29/2017 A 0

DesignerDesigner Construction Support Services 12/14/2016 A 12/29/2017 A 262B1410 Designer Construction Support Services 12/14/2016 A 12/29/2017 A 262

Project CProject Closeout 12/30/2017 A 08/01/2018 243B1445 Closeout Phase 12/30/2017 A 08/01/2018 243B1450 Issue SAC Letter 05/22/2018 A 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 12/30/2017 A 08/01/2018 120B1490 Project Closed 08/01/2018 0

Basin 0109Basin 0109 03/12/2015 A 12/09/2018 1283

100023 Pu100023 Pump Station 0109 Upgrade 03/12/2015 A 12/09/2018 1283DesignDesign 03/12/2015 A 05/31/2017 A 732

B1000 Design Phase 03/12/2015 A 05/31/2017 A 732B1010 Prepare and Submit Design Package 03/12/2015 A 06/23/2015 A 5B1020 Engage Design Consultant 06/24/2015 A 09/16/2015 A 20B1022 TA Preparation 09/17/2015 A 09/17/2015 A 1B1025 TA Approval Process 09/18/2015 A 09/25/2015 A 20B1030 Issue Design NTP 10/01/2015 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/01/2015 A 07/14/2016 A 85

30% Des30% Design 10/01/2015 A 05/27/2016 A 210B1060 A/E Prepares 30% Construction Documents 10/01/2015 A 04/28/2016 A 30B1070 Geotechnical Engineering Services 10/01/2015 A 04/28/2016 A 20B1080 Surveying Services 10/01/2015 A 04/28/2016 A 15B1100 30% CDs Submittal 04/28/2016 A 0B1120 30% Review (MDWASD/PSIP Team) 04/29/2016 A 05/27/2016 A 10

90% Des90% Design 04/29/2016 A 05/12/2017 A 335B1170 A/E Prepares 90% Construction Documents 04/29/2016 A 06/30/2016 A 20B1180 90% CDs Submittal 06/30/2016 A 0B1190 90% Review (MDWASD/PSIP Team) 07/01/2016 A 07/14/2016 A 15B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 07/15/2016 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 07/15/2016 A 03/14/2017 A 45B1211 Flow Metter & Specialty Odor Control Evaluation Period 07/28/2016 A 11/15/2016 A 77B1212 TA Rev 1 Approval Process 11/15/2016 A 12/14/2016 A 40B1214 A/E Prepares 90% Design for Flow Metter & Specialty Odor Con 11/15/2016 A 02/06/2017 A 40B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 03/20/2017 A 0B1230 90% RER(Building Dept) Permit Submittal (Pump Station) 03/20/2017 A 05/12/2017 A 21B1260 90% CD PM Comments Evaluation Completed 05/12/2017 A 0B1262 MDWASD Union Concurrence Process 01/27/2017 A 03/07/2017 A 30

100% De100% Design 05/12/2017 A 05/31/2017 A 45B1270 A/E Prepares 100% Construction Documents 05/12/2017 A 05/30/2017 A 10B1280 100% CDs Submittal 05/30/2017 A 0B1290 100% Review (MDWASD/PSIP Team) 05/31/2017 A 05/31/2017 A 10B1300 Design Completed 05/31/2017 A 0

MDWASDMDWASD Procurement 06/01/2017 A 10/19/2017 A 133B1305 Procurement Phase 06/01/2017 A 10/19/2017 A 133

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Construction OperationsOriginal Construction Duration

Change Order #1 - Hurricane Irma

Substantial Completion12/29/2017 A, Designer Construction Support Services

Designer Construction Support Services08/01/2018, Project Closeout

Closeout PhaseIssue SAC Letter

Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed

12/09/2018, Basin 0109

12/09/2018, 100023 Pump Station 0109 Upgrade05/31/2017 A, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA PreparationTA Approval Process

Issue Design NTPFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

05/27/2016 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal

30% Review (MDWASD/PSIP Team)05/12/2017 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)

90% RER(DERM)FDEP Permit Submittal (Pump Station)90% RER(DERM)FDEP Permit Review (Pump Station)

Flow Metter & Specialty Odor Control Evaluation PeriodTA Rev 1 Approval Process

A/E Prepares 90% Design for Flow Metter & Specialty Odor Control

90% RER(Building Dept) Permit Submittal (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)90% CD PM Comments Evaluation Completed

MDWASD Union Concurrence Process

05/31/2017 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed

10/19/2017 A, MDWASD Procurement

Procurement Phase

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 25 of 161 TASK filter: All Activities© Oracle Corporation

Page 26: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1310 Submit CDs to MDWASD Procurement Division 06/01/2017 A 0B1314 Bid Notice Preparation Period 06/02/2017 A 06/07/2017 A 23B1316 Bid Notice 06/07/2017 A 0B1318 MDWASD/PSIP Team Prepare for Pre-Bid Conference 06/08/2017 A 06/20/2017 A 10B1320 Pre-Bid Conference 06/21/2017 A 06/21/2017 A 1B1328 Bidders Prepare Bids for Submittal 06/22/2017 A 07/24/2017 A 15B1330 Bids Submittal 07/24/2017 A 0

B1340 MDWASD/PSIP Team Bids Evaluation 07/25/2017 A 08/31/2017 A 15B1350 Recommendation for Award Letter 08/31/2017 A 0B1355 Contract Award (Purchase Order Approval) 09/01/2017 A 10/19/2017 A 10

ConstrucConstruction 06/21/2017 A 08/11/2018 532B1360 Construction Phase 06/21/2017 A 08/11/2018 532B1364 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 09/01/2017 A 10/16/2017 A 15B1366 Pre-Construction Meeting 10/17/2017 A 10/17/2017 A 1B1367 WASD Issues NTP (Pre-Const to NTP) 10/18/2017 A 02/11/2018 A 45B1369 WASD Issues NTP (PO to NTP) 10/20/2017 A 02/11/2018 A 53B1370 Construction NTP 02/12/2018 A 0B1400 Construction Operations 02/12/2018 A 08/11/2018 181B1402 Substantial Completion 08/11/2018 0

DesignerDesigner Construction Support Services 06/21/2017 A 08/11/2018 245B1410 Designer Construction Support Services 06/21/2017 A 08/11/2018 245

Project CProject Closeout 11/09/2017 A 12/09/2018 395B1445 Closeout Phase 11/09/2017 A 12/09/2018 395B1450 Issue SAC Letter 11/09/2017 A 0B1470 Final Release of Retainage - Construction Contract 08/11/2018 0B1480 Administrative Closeout 08/12/2018 12/09/2018 120B1490 Project Closed 12/09/2018 0

Basin 0113Basin 0113 08/01/2014 A 08/01/2018 1598

100024 Ba100024 Basin 0113 Infiltration/Inflow Study and Repairs 04/17/2015 A 10/15/2015 A 328InfiltratioInfiltration/Inflow 04/17/2015 A 10/14/2015 A 136

B1000 Infiltration/inflow Phase 04/17/2015 A 10/14/2015 A 136

CIPP RepCIPP Repairs 04/17/2015 A 07/21/2015 A 23B1005 CIPP Phase 04/17/2015 A 07/21/2015 A 23B1020 Issue NTP for CIPP Repairs 04/17/2015 A 0B1030 Conduct CIPP Repairs 07/21/2015 A 07/21/2015 A 20

ManholeManhole Repairs 10/02/2015 A 10/14/2015 A 20B1055 Manhole Phase 10/02/2015 A 10/14/2015 A 20B1070 Issue NTP for Manhole Repairs 10/02/2015 A 0B1080 Conduct Manhole Repairs 10/14/2015 A 10/14/2015 A 20

Dig & ReDig & Replace Repairs 05/18/2015 A 06/03/2015 A 52B1105 Dig & Replace Phase 05/18/2015 A 06/03/2015 A 52B1120 Issue NTP for Dig & Replace Repairs 05/18/2015 A 0B1130 Conduct Dig & Replace Repairs 06/01/2015 A 06/03/2015 A 30B1140 Punch List 06/03/2015 A 06/03/2015 A 10

Project CProject Closeout 10/15/2015 A 10/15/2015 A 0B1175 Closeout Phase 10/15/2015 A 10/15/2015 A 0B1200 Project Closed 10/15/2015 A 0

100025 Pu100025 Pump Station 0113 Upgrade 08/01/2014 A 08/01/2018 1598

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Submit CDs to MDWASD Procurement DivisionBid Notice Preparation Period

Bid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter

Contract Award (Purchase Order Approval)08/11/2018, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Construction NTPConstruction OperationsSubstantial Completion08/11/2018, Designer Construction Support Services

Designer Construction Support Services12/09/2018, Project Closeout

Closeout PhaseIssue SAC Letter

Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed

08/01/2018, Basin 0113

10/15/2015 A, 100024 Basin 0113 Infiltration/Inflow Study and Repairs10/14/2015 A, Infiltration/Inflow

Infiltration/inflow Phase07/21/2015 A, CIPP RepairsCIPP Phase

Issue NTP for CIPP RepairsConduct CIPP Repairs

10/14/2015 A, Manhole RepairsManhole Phase

Issue NTP for Manhole RepairsConduct Manhole Repairs

06/03/2015 A, Dig & Replace RepairsDig & Replace Phase

Issue NTP for Dig & Replace RepairsConduct Dig & Replace RepairsPunch List

10/15/2015 A, Project CloseoutCloseout Phase

Project Closed08/01/2018, 100025 Pump Station 0113 Upgrade

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 26 of 161 TASK filter: All Activities© Oracle Corporation

Page 27: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

DesignDesign 08/01/2014 A 06/02/2015 A 306B1000 Design Phase 08/01/2014 A 06/02/2015 A 306B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 08/01/2014 A 08/01/2014 A 5B1020 Engage Design Consultant 08/04/2014 A 11/19/2014 A 20B1030 Issue Design NTP 11/20/2014 A 0B1040 A/E Develops and Submits Final Engineering Report 11/20/2014 A 06/02/2015 A 20

B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 02/09/2015 A 03/26/2015 A 1030% Des30% Design 11/20/2014 A 01/29/2015 A 27

B1060 A/E Prepares 30% Construction Documents 11/20/2014 A 01/19/2015 A 25B1070 Geotechnical Engineering Services 12/03/2014 A 12/29/2014 A 20B1080 Surveying Services 12/03/2014 A 12/29/2014 A 15B1100 30% CDs Submittal 01/19/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 01/20/2015 A 01/29/2015 A 10

90% Des90% Design 01/20/2015 A 06/02/2015 A 98B1170 A/E Prepares 90% Construction Documents 01/20/2015 A 02/24/2015 A 20B1180 90% CDs Submittal 02/24/2015 A 0

B1190 90% Review (MDWASD/PSIP Team) 02/25/2015 A 03/10/2015 A 5B1195 Permit Package Modifications 03/11/2015 A 03/26/2015 A 5B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 03/27/2015 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 03/27/2015 A 04/22/2015 A 5B1220 90% RER (Building Dept) Permit Submittal 05/01/2015 A 0B1230 90% RER (Building Dept) Permit Review 05/01/2015 A 06/02/2015 A 10B1260 90% CD PM Comments Evaluation Completed 06/02/2015 A 0

100% De100% Design 03/11/2015 A 06/02/2015 A 4B1270 A/E Prepares 100% Construction Documents 03/11/2015 A 03/26/2015 A 2B1280 100% CDs Submittal 03/26/2015 A 0

B1290 100% Review (MDWASD/PSIP Team) 03/27/2015 A 05/27/2015 A 2B1300 Design Completed 06/02/2015 A 0

MDWASDMDWASD Procurement 05/05/2015 A 07/27/2015 A 77B1305 Procurement Phase 05/05/2015 A 07/27/2015 A 77B1310 Submit CDs to MDWASD Procurement Division 05/05/2015 A 0B1320 Pre-Bid Conference 05/15/2015 A 0B1322 Adddendum #2 06/11/2015 A 0B1330 Bids Submittal 06/19/2015 A 0B1340 MDWASD/PSIP Team Bids Evaluation 06/22/2015 A 06/29/2015 A 10B1350 Recommendation for Award Letter 06/29/2015 A 0B1355 Contract Award (Purchase Order Approval) 06/29/2015 A 07/27/2015 A 10

ConstrucConstruction 06/30/2015 A 03/29/2016 A 1267B1360 Construction Phase 06/30/2015 A 03/29/2016 A 1267B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 06/30/2015 A 07/10/2015 A 7B1365 Pre-Construction Meeting 07/13/2015 A 07/13/2015 A 1

B1369 WASD Issues NTP (PO to NTP) 07/27/2015 A 07/27/2015 A 53B1370 Construction NTP 07/27/2015 A 0B1400 Construction Operations 07/27/2015 A 02/19/2016 A 106B1400 Original Construction Duration 07/27/2015 A 12/24/2015 A 106B1400 Change Order #1 - Valve Vault, Top Slabs & Hatches Design Ch 12/25/2015 A 01/29/2016 A 106B1400 Change Order #2 - Hatches Design Change 01/30/2016 A 02/19/2016 A 106B1405 Substantial Completion 02/19/2016 A 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

06/02/2015 A, Design

Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book

Engage Design ConsultantIssue Design NTP

A/E Develops and Submits Final Engineering Report

Final Engineering Report Review & Approval (MDWASD/PSIP Team)01/29/2015 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services

30% CDs Submittal30% Review (MDWASD/PSIP Team)

06/02/2015 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)Permit Package Modifications90% RER(DERM)FDEP Permit Submittal (Pump Station)

90% RER(DERM)FDEP Permit Review (Pump Station)90% RER (Building Dept) Permit Submittal

90% RER (Building Dept) Permit Review90% CD PM Comments Evaluation Completed06/02/2015 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal

100% Review (MDWASD/PSIP Team)Design Completed

07/27/2015 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Pre-Bid ConferenceAdddendum #2Bids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter

Contract Award (Purchase Order Approval)03/29/2016 A, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction MeetingWASD Issues NTP (PO to NTP)

Construction NTPConstruction Operations

Original Construction DurationChange Order #1 - Valve Vault, Top Slabs & Hatches Design Change

Change Order #2 - Hatches Design Change

Substantial Completion

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 27 of 161 TASK filter: All Activities© Oracle Corporation

Page 28: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

DesignerDesigner Construction Support Services 07/13/2015 A 03/29/2016 A 177B1410 Designer Construction Support Services 07/13/2015 A 03/29/2016 A 177

ConstrucConstruction Close Out 02/22/2016 A 03/29/2016 A 15B1420 Commissioning 02/22/2016 A 02/26/2016 A 15

B1430 Punch List 02/22/2016 A 03/29/2016 A 10Project CProject Closeout 09/21/2015 A 08/01/2018 1045

B1445 Closeout Phase 09/21/2015 A 08/01/2018 1045B1450 Issue SAC Letter 09/21/2015 A 0B1470 Final Release of Retainage - Construction Contract 09/12/2016 A 0B1480 Administrative Closeout 02/22/2016 A 08/01/2018 120B1490 Project Closed 08/01/2018 0

Basin 0114Basin 0114 05/22/2015 A 11/29/2018 1228

100026 Ba100026 Basin 0114 Infiltration/Inflow Study and Repairs 05/22/2015 A 11/11/2015 A 68InfiltratioInfiltration/Inflow 05/22/2015 A 11/10/2015 A 20

B1000 Infiltration/Inflow Phase 05/22/2015 A 11/10/2015 A 20CIPP RepCIPP Repairs 05/22/2015 A 11/10/2015 A 20

B1065 CIPP Phase 05/22/2015 A 11/10/2015 A 20B1080 Issue NTP for CIPP Repairs 05/22/2015 A 0B1090 Conduct CIPP Repairs 10/23/2015 A 11/10/2015 A 20

Project CProject Closeout 11/11/2015 A 11/11/2015 A 0B1235 Closeout Phase 11/11/2015 A 11/11/2015 A 0B1260 Project Closed 11/11/2015 A 0

100027 Pu100027 Pump Station 0114 Upgrade 08/28/2015 A 11/29/2018 1228DesignDesign 08/28/2015 A 02/21/2017 A 515

B1000 Design Phase 08/28/2015 A 02/21/2017 A 515B1010 Prepare and Submit Design Package 08/28/2015 A 09/18/2015 A 5B1020 Engage Design Consultant 09/18/2015 A 09/21/2015 A 20

B1024 TA Preparation 09/22/2015 A 09/22/2015 A 1B1025 TA Approval Process 09/23/2015 A 10/08/2015 A 20B1030 Issue Design NTP 10/30/2015 A 0B1032 TA Rev 1 Approval Process 04/07/2016 A 05/02/2016 A 20B1034 Isue Design NTP - TA Rev 1 05/16/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/30/2015 A 08/19/2016 A 105

30% Des30% Design 10/30/2015 A 02/19/2016 A 53B1060 A/E Prepares 30% Construction Documents 10/30/2015 A 12/22/2015 A 30B1070 Geotechnical Engineering Services 10/30/2015 A 12/22/2015 A 20B1080 Surveying Services 10/30/2015 A 12/22/2015 A 15B1100 30% CDs Submittal 12/22/2015 A 0

B1120 30% Review (MDWASD/PSIP Team) 12/23/2015 A 02/19/2016 A 1060% Des60% Design 12/23/2015 A 05/26/2016 A 165

B1130 A/E Prepares 60% Construction Documents 12/23/2015 A 04/19/2016 A 20

B1140 60% CDs Submittal 04/19/2016 A 0B1160 60% Review (MDWASD/PSIP Team) 04/20/2016 A 05/26/2016 A 10

90% Des90% Design 04/19/2016 A 02/21/2017 A 260B1170 A/E Prepares 90% Construction Documents 04/19/2016 A 07/01/2016 A 20B1180 90% CDs Submittal 07/01/2016 A 0B1190 90% Review (MDWASD/PSIP Team) 07/04/2016 A 08/19/2016 A 15B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 09/14/2016 A 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

03/29/2016 A, Designer Construction Support Services

Designer Construction Support Services03/29/2016 A, Construction Close Out

Commissioning

Punch List08/01/2018, Project Closeout

Closeout PhaseIssue SAC Letter

Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed

11/29/2018, Basin 0114

11/11/2015 A, 100026 Basin 0114 Infiltration/Inflow Study and Repairs11/10/2015 A, Infiltration/Inflow

Infiltration/Inflow Phase11/10/2015 A, CIPP RepairsCIPP Phase

Issue NTP for CIPP RepairsConduct CIPP Repairs

11/11/2015 A, Project CloseoutCloseout Phase

Project Closed11/29/2018, 100027 Pump Station 0114 Upgrade

02/21/2017 A, Design

Design PhasePrepare and Submit Design Package

Engage Design Consultant

TA PreparationTA Approval Process

Issue Design NTPTA Rev 1 Approval ProcessIsue Design NTP - TA Rev 1

Final Engineering Report Review & Approval (MDWASD/PSIP Team)02/19/2016 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services

30% CDs Submittal

30% Review (MDWASD/PSIP Team)05/26/2016 A, 60% Design

A/E Prepares 60% Construction Documents

60% CDs Submittal60% Review (MDWASD/PSIP Team)

02/21/2017 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 28 of 161 TASK filter: All Activities© Oracle Corporation

Page 29: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 09/14/2016 A 11/17/2016 A 15

B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 11/18/2016 A 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 11/18/2016 A 01/12/2017 A 15B1240 90% RER (Class III) Permit Submittal (Pump Station) 09/14/2016 A 0B1250 90% RER (Class III) Permit Review (Pump Station) 09/14/2016 A 11/15/2016 A 15B1260 90% CD PM Comments Evaluation Completed 01/13/2017 A 0B1262 MDWASD Union Concurrence Process 01/20/2017 A 02/21/2017 A 30

100% De100% Design 01/19/2017 A 01/26/2017 A 28B1270 A/E Prepares 100% Construction Documents 01/19/2017 A 01/23/2017 A 10B1280 100% CDs Submittal 01/23/2017 A 0B1290 100% Review (MDWASD/PSIP Team) 01/23/2017 A 01/26/2017 A 10B1300 Design Completed 01/26/2017 A 0

MDWASDMDWASD Procurement 02/21/2017 A 05/22/2017 A 81B1305 Procurement Phase 02/21/2017 A 05/22/2017 A 81B1310 Submit CDs to MDWASD Procurement Division 02/21/2017 A 0B1312 Bid Notice Preparation Period 02/22/2017 A 02/23/2017 A 23B1314 Bid Notice 02/23/2017 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 02/24/2017 A 03/03/2017 A 10B1320 Pre-Bid Conference 03/06/2017 A 03/06/2017 A 1B1328 Bidders Prepare Bids for Submittal 03/07/2017 A 04/07/2017 A 15B1330 Bids Submittal 04/07/2017 A 0B1340 MDWASD/PSIP Team Bids Evaluation 04/10/2017 A 04/17/2017 A 15B1350 Recommendation for Award Letter 04/17/2017 A 0B1355 Contract Award (Purchase Order Approval) 04/18/2017 A 05/22/2017 A 10

ConstrucConstruction 03/06/2017 A 08/01/2018 697B1360 Construction Phase 03/06/2017 A 08/01/2018 697B1364 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 04/18/2017 A 05/24/2017 A 15B1366 Pre-Construction Meeting 05/25/2017 A 05/25/2017 A 1B1368 WASD Issues NTP (Pre-Const to NTP) 05/25/2017 A 08/27/2017 A 45

B1369 WASD Issues NTP (PO to NTP) 05/22/2017 A 08/27/2017 A 97B1370 Construction NTP 08/28/2017 A 0B1400 Construction Operations 08/28/2017 A 08/01/2018 150B1400 Original Construction Duration 08/28/2017 A 01/25/2018 A 150B1400 Change Order #1 - MDPW Permit 01/26/2018 A 06/14/2018 A 150B1402 Substantial Completion 08/01/2018 0

DesignerDesigner Construction Support Services 03/06/2017 A 08/01/2018 235B1410 Designer Construction Support Services 03/06/2017 A 08/01/2018 235

Project CProject Closeout 08/01/2018 11/29/2018 120B1445 Closeout Phase 08/01/2018 11/29/2018 120B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 08/02/2018 11/29/2018 120B1490 Project Closed 11/29/2018 0

Basin 0121Basin 0121 08/01/2018 09/28/2020 790

100029 Pu100029 Pump Station 0121 Upgrade * 08/01/2018 09/28/2020 790DesignDesign 08/01/2018 06/29/2019 333

B1000 Design Phase 08/01/2018 06/29/2019 333B1010 Prepare and Submit Design Package 08/01/2018 08/07/2018 7

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

90% RER(DERM)FDEP Permit Review (Pump Station)

90% RER(Building Dept) Permit Submittal (Pump Station)90% RER(Building Dept) Permit Review (Pump Station)

90% RER (Class III) Permit Submittal (Pump Station)90% RER (Class III) Permit Review (Pump Station)

90% CD PM Comments Evaluation CompletedMDWASD Union Concurrence Process

01/26/2017 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)

Design Completed05/22/2017 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter

Contract Award (Purchase Order Approval)08/01/2018, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Construction NTPConstruction Operations

Original Construction DurationChange Order #1 - MDPW Permit

Substantial Completion08/01/2018, Designer Construction Support Services

Designer Construction Support Services11/29/2018, Project Closeout

Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction Contract

Administrative CloseoutProject Closed

06/29/2019, Design

Design PhasePrepare and Submit Design Package

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 29 of 161 TASK filter: All Activities© Oracle Corporation

Page 30: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1020 Engage Design Consultant 08/08/2018 09/04/2018 28B1022 TA Preparation 09/05/2018 09/18/2018 14B1024 TA Approval Process 09/19/2018 10/28/2018 40B1030 Issue Design NTP 10/29/2018 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/29/2018 06/01/2019 216

30% Des30% Design 10/29/2018 01/16/2019 80B1060 A/E Prepares 30% Construction Documents 10/29/2018 12/17/2018 50B1100 30% CDs Submittal 12/17/2018 0

B1120 30% Review (MDWASD/PSIP Team) 12/18/2018 01/16/2019 3060% Des60% Design 12/18/2018 01/30/2019 44

B1130 A/E Prepares 60% Construction Documents 12/18/2018 01/16/2019 30B1140 60% CDs Submittal 01/16/2019 0B1160 60% Review (MDWASD/PSIP Team) 01/17/2019 01/30/2019 14

90% Des90% Design 01/17/2019 06/01/2019 136B1170 A/E Prepares 90% Construction Documents 01/17/2019 02/25/2019 40B1180 90% CDs Submittal 02/25/2019 0B1190 90% Review (MDWASD/PSIP Team) 02/26/2019 03/27/2019 30B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 03/28/2019 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 03/28/2019 05/11/2019 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 05/12/2019 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 05/12/2019 06/01/2019 21B1240 90% Municipality Permit Submittal (Pump Station) 05/12/2019 0B1250 90% Municipality Permit Review (Pump Station) 05/12/2019 06/01/2019 21

B1260 90% CD PM Comments Evaluation Completed 06/01/2019 0100% De100% Design 06/02/2019 06/29/2019 28

B1270 A/E Prepares 100% Construction Documents 06/02/2019 06/15/2019 14B1280 100% CDs Submittal 06/15/2019 0B1290 100% Review (MDWASD/PSIP Team) 06/16/2019 06/29/2019 14B1300 Design Completed 06/29/2019 0

MDWASDMDWASD Procurement 06/29/2019 10/11/2019 104B1305 Procurement Phase 06/29/2019 10/11/2019 104B1310 Submit CDs to MDWASD Procurement Division 06/29/2019 0B1312 Bid Notice Preparation Period 06/30/2019 08/01/2019 33B1314 Bid Notice 08/01/2019 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conferencce 08/02/2019 08/15/2019 14B1320 Pre-Bid Conference 08/16/2019 08/16/2019 1B1324 Bidders Prepare Bids for Submittal 08/17/2019 09/06/2019 21

B1330 Bids Submittal 09/06/2019 0B1340 MDWASD/PSIP Team Bids Evaluation 09/07/2019 09/27/2019 21B1350 Recommendation for Award Letter 09/27/2019 0B1355 Contract Award (Purchase Order Approval) 09/28/2019 10/11/2019 14

ConstrucConstruction 08/16/2019 05/31/2020 290B1360 Construction Phase 08/16/2019 05/31/2020 290B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 09/28/2019 10/18/2019 21B1364 Pre-Construction Meeting 10/19/2019 10/19/2019 1B1366 WASD Issues NTP (Pre-Const to NTP) 10/20/2019 12/03/2019 45B1369 WASD Issues NTP (PO to NTP) 10/12/2019 12/03/2019 53B1370 Construction NTP 12/04/2019 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Engage Design ConsultantTA Preparation

TA Approval Process

Issue Design NTPFinal Engineering Report Review & Ap

01/16/2019, 30% Design

A/E Prepares 30% Construction Documents30% CDs Submittal

30% Review (MDWASD/PSIP Team)01/30/2019, 60% Design

A/E Prepares 60% Construction Documents60% CDs Submittal60% Review (MDWASD/PSIP Team)

06/01/2019, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (P

90% RER(DERM)FDEP Permit Review (90% RER(Building Dept) Permit Submit

90% RER(Building Dept) Permit Revie90% Municipality Permit Submittal (Pum

90% Municipality Permit Review (Pum

90% CD PM Comments Evaluation C06/29/2019, 100% Design

A/E Prepares 100% Construction Do100% CDs Submittal100% Review (MDWASD/PSIP TeamDesign Completed

10/11/2019, MDWASD ProProcurement Phase

Submit CDs to MDWASD ProcuremBid Notice Preparation Period

Bid NoticeMDWASD/PSIP Team Prepare

Pre-Bid ConferenceBidders Prepare Bids for Subm

Bids SubmittalMDWASD/PSIP Team Bids ERecommendation for Award Contract Award (Purchase O

05/31/2

ConstruMDWASD/PSIP Team PrePre-Construction Meeting

WASD Issues NTP (PreWASD Issues NTP (PO

Construction NTP

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 30 of 161 TASK filter: All Activities© Oracle Corporation

Page 31: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1400 Construction Operations 12/04/2019 05/31/2020 180B1402 Substantial Completion 05/31/2020 0

DesignerDesigner Construction Support Services 08/16/2019 05/31/2020 290B1410 Designer Construction Support Services 08/16/2019 05/31/2020 290

Project CProject Closeout 05/31/2020 09/28/2020 120B1445 Closeout Phase 05/31/2020 09/28/2020 120B1450 Issue SAC Letter 05/31/2020 0B1470 Final Release of Retainage - Construction Contract 05/31/2020 0B1480 Administrative Closeout 06/01/2020 09/28/2020 120B1490 Project Closed 09/28/2020 0

Basin 0124Basin 0124 05/22/2015 A 12/02/2018 1244

100030 Ba100030 Basin 0124 Infiltration/Inflow Study and Repairs 05/22/2015 A 11/16/2015 A 212InfiltratioInfiltration/Inflow 05/22/2015 A 11/13/2015 A 20

B1000 Infiltration/Inflow Phase 05/22/2015 A 11/13/2015 A 20CIPP RepCIPP Repairs 05/22/2015 A 11/13/2015 A 20

B1005 CIPP Phase 05/22/2015 A 11/13/2015 A 20B1020 Issue NTP for CIPP Repairs 05/22/2015 A 0B1030 Conduct CIPP Repairs 10/22/2015 A 11/13/2015 A 20

Project CProject Closeout 11/16/2015 A 11/16/2015 A 0B1175 Closeout Phase 11/16/2015 A 11/16/2015 A 0B1200 Project Closed 11/16/2015 A 0

100031 Pu100031 Pump Station 0124 Upgrade 07/30/2015 A 12/02/2018 1244DesignDesign 07/30/2015 A 03/16/2017 A 620

B1000 Design Phase 07/30/2015 A 03/16/2017 A 620B1010 Prepare and Submit Design Package 07/30/2015 A 08/07/2015 A 5

B1020 Engage Design Consultant 08/10/2015 A 09/01/2015 A 15B1022 TA Preparation 09/02/2015 A 09/02/2015 A 1B1025 TA Approval Process 09/03/2015 A 09/25/2015 A 20B1030 Issue Design NTP 10/07/2015 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/07/2015 A 06/21/2016 A 85

30% Des30% Design 10/08/2015 A 01/07/2016 A 72B1060 A/E Prepares 30% Construction Documents 10/08/2015 A 12/03/2015 A 30B1100 30% CDs Submittal 12/03/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 12/04/2015 A 01/07/2016 A 10

60% Des60% Design 12/04/2015 A 05/02/2016 A 99B1130 A/E Prepares 60% Construction Documents 12/04/2015 A 02/09/2016 A 20B1140 60% CDs Submittal 02/09/2016 A 0B1160 60% Review (MDWASD/PSIP Team) 02/10/2016 A 05/02/2016 A 10

90% Des90% Design 02/10/2016 A 03/07/2017 A 387B1170 A/E Prepares 90% Construction Documents 02/10/2016 A 05/02/2016 A 20B1180 90% CDs Submittal 05/02/2016 A 0B1190 90% Review (MDWASD/PSIP Team) 05/03/2016 A 06/21/2016 A 15B1192 Pump Station Layout Under Evaluation 06/22/2016 A 09/12/2016 A 15B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 09/23/2016 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 09/23/2016 A 10/25/2016 A 15B1220 90% Doral - BD Permit Submittal 11/07/2016 A 0B1230 90% Doral - BD Permit Review 11/07/2016 A 01/25/2017 A 15B1240 90% Doral - PWD Permit Submittal 10/27/2016 A 0B1250 90% Doral - PWD Permit Review 10/27/2016 A 11/15/2016 A 15

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

ConstruSubstan05/31/2

Designe

Issue SAFinal Re

12/02/2018, Basin 0124

11/16/2015 A, 100030 Basin 0124 Infiltration/Inflow Study and Repairs11/13/2015 A, Infiltration/Inflow

Infiltration/Inflow Phase11/13/2015 A, CIPP RepairsCIPP Phase

Issue NTP for CIPP RepairsConduct CIPP Repairs11/16/2015 A, Project CloseoutCloseout Phase

Project Closed12/02/2018, 100031 Pump Station 0124 Upgrade

03/16/2017 A, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval ProcessIssue Design NTP

Final Engineering Report Review & Approval (MDWASD/PSIP Team)01/07/2016 A, 30% Design

A/E Prepares 30% Construction Documents30% CDs Submittal

30% Review (MDWASD/PSIP Team)05/02/2016 A, 60% Design

A/E Prepares 60% Construction Documents60% CDs Submittal

60% Review (MDWASD/PSIP Team)03/07/2017 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)Pump Station Layout Under Evaluation

90% RER(DERM)FDEP Permit Submittal (Pump Station)90% RER(DERM)FDEP Permit Review (Pump Station)

90% Doral - BD Permit Submittal90% Doral - BD Permit Review

90% Doral - PWD Permit Submittal90% Doral - PWD Permit Review

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 31 of 161 TASK filter: All Activities© Oracle Corporation

Page 32: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1260 90% CD PM Comments Evaluation Completed 11/16/2016 A 0B1262 MDWASD Union Concurrence Process 01/27/2017 A 03/07/2017 A 30

100% De100% Design 11/17/2016 A 03/16/2017 A 62B1270 A/E Prepares 100% Construction Documents 11/17/2016 A 01/31/2017 A 10B1280 100% CDs Submittal 01/31/2017 A 0B1290 100% Review (MDWASD/PSIP Team) 02/01/2017 A 03/16/2017 A 10B1300 Design Completed 03/16/2017 A 0

MDWASDMDWASD Procurement 03/16/2017 A 07/31/2017 A 115B1305 Procurement Phase 03/16/2017 A 07/31/2017 A 115B1310 Submit CDs to MDWASD Procurement Division 03/16/2017 A 0B1312 Bid Notice Preparation Period 03/17/2017 A 03/23/2017 A 23B1313 Bid Notice 03/23/2017 A 0B1315 Prepare For Pre-Bid Conference 03/24/2017 A 04/03/2017 A 10B1320 Pre-Bid Conference 04/04/2017 A 04/04/2017 A 1B1323 Bidders Prepare Bids For Submittal 04/05/2017 A 05/12/2017 A 15

B1330 Bids Submittal 05/12/2017 A 0B1340 Bids Evaluation (MDWASD/PSIP Team) 05/15/2017 A 05/22/2017 A 15B1350 Recommendation For Award Letter 05/22/2017 A 0B1355 Contract Award (Purchase Order Approval) 05/23/2017 A 07/31/2017 A 10

ConstrucConstruction 04/04/2017 A 08/05/2018 582B1360 Construction Phase 04/04/2017 A 08/04/2018 582B1364 MDWASD/PSIP Team Prepare For Pre-Construction Meeting 05/23/2017 A 07/28/2017 A 21B1366 Pre-Construction Meeting 07/31/2017 A 07/31/2017 A 1B1368 WASD Issues NTP (Pre-Const to NTP) 08/01/2017 A 12/17/2017 A 45B1369 WASD Issues NTP (PO to NTP) 08/01/2017 A 12/17/2017 A 53B1370 Construction NTP 12/18/2017 A 0

B1400 Construction Operations 12/18/2017 A 08/04/2018 150B1400 Original Construction Duration 12/18/2017 A 05/17/2018 A 150B1400 Change Order #1 - FM Shut Down 05/18/2018 A 06/03/2018 A 150B1400 Change Order #2 - FPL (Pending Approval) 06/04/2018 A 08/05/2018 A 150B1402 Substantial Completion 08/04/2018 0

DesignerDesigner Construction Support Services 04/04/2017 A 08/04/2018 274B1410 Designer Construction Support Services 04/04/2017 A 08/04/2018 274

Project CProject Closeout 08/04/2018 12/02/2018 120B1445 Closeout Phase 08/04/2018 12/02/2018 120B1450 Issue SAC Letter 08/04/2018 0

B1470 Final Release of Retainage - Construction Contract 08/04/2018 0B1480 Administrative Closeout 08/05/2018 12/02/2018 120B1490 Project Closed 12/02/2018 0

Basin 0142Basin 0142 09/25/2014 A 09/28/2020 2171

100032 Ba100032 Basin 0142 Infiltration/Inflow Study and Repairs 09/25/2014 A 09/09/2018 1003InfiltratioInfiltration/Inflow 09/25/2014 A 09/09/2018 1421

B1000 Infiltration/Inflow Phase 09/25/2014 A 09/09/2018 1421Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 09/09/2018 1421

B1005 SSES Phase 09/25/2014 A 09/09/2018 1421B1020 Issue NTP to SSES Contractor 09/25/2014 A 0

B1030 Conduct SSES 10/22/2014 A 12/17/2014 A 30B1031 Smoke Testing 10/27/2014 A 10/31/2014 A 10

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

90% CD PM Comments Evaluation CompletedMDWASD Union Concurrence Process03/16/2017 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal

100% Review (MDWASD/PSIP Team)Design Completed

07/31/2017 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation Period

Bid NoticePrepare For Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids For Submittal

Bids SubmittalBids Evaluation (MDWASD/PSIP Team)

Recommendation For Award LetterContract Award (Purchase Order Approval)

08/05/2018, Construction

Construction PhaseMDWASD/PSIP Team Prepare For Pre-Construction MeetingPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Construction NTP

Construction OperationsOriginal Construction DurationChange Order #1 - FM Shut Down

Change Order #2 - FPL (Pending Approval)

Substantial Completion08/04/2018, Designer Construction Support Services

Designer Construction Support Services12/02/2018, Project Closeout

Closeout PhaseIssue SAC Letter

Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed

09/09/2018, 100032 Basin 0142 Infiltration/Inflow Study a09/09/2018, Infiltration/Inflow

Infiltration/Inflow Phase09/09/2018, Sanitary Sewer Evaluation SurveySSES Phase

Issue NTP to SSES Contractor

Conduct SSESSmoke Testing

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 32 of 161 TASK filter: All Activities© Oracle Corporation

Page 33: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1040 Video Review 10/27/2014 A 01/30/2015 A 30B1290 Issue NTP to SSES Contractor (New I/I) 08/01/2018* 0B1300 Conduct SSES (New I/I) 08/01/2018 08/30/2018 30B1310 Smoke Testing (New I/I) 08/31/2018 09/09/2018 10B1320 Video Review (New I/I) 08/03/2018 09/01/2018 30

Dig & ReDig & Replace Repairs 06/26/2015 A 08/30/2018 1024B1165 Dig & Replace Phase 06/26/2015 A 08/30/2018 1024B1180 Issue NTP for Dig & Replace Repairs 06/26/2015 A 0B1190 Conduct Dig & Replace Repairs 08/17/2015 A 08/28/2015 A 30B1270 Issue NTP for Dig & Replace Repairs (New I/I) 08/01/2018* 0B1280 Conduct Dig & Replace Repairs (New I/I) 08/01/2018 08/30/2018 30

CIPP RepCIPP Repairs 08/01/2018 08/28/2018 20B1070 CIPP Phase 08/01/2018 08/28/2018 20B1090 Issue NTP for CIPP Repairs 08/01/2018* 0B1100 Conduct CIPP Repairs 08/01/2018 08/28/2018 20

ManholeManhole Repairs 08/01/2018 08/28/2018 20B1110 Manhole Phase 08/01/2018 08/28/2018 20B1130 Issue NTP for Manhole Repairs 08/01/2018* 0B1140 Conduct Manhole Repairs 08/01/2018 08/28/2018 20

Project CProject Closeout 08/28/2018 08/28/2018 0B1235 Closeout Phase 08/28/2018 08/28/2018 0B1260 Project Closed 08/28/2018 0

100033 Pu100033 Pump Station 0142 Upgrade * 08/01/2018 09/28/2020 790DesignDesign 08/01/2018 06/29/2019 333

B1000 Design Phase 08/01/2018 06/29/2019 333B1010 Prepare and Submit Design Package 08/01/2018 08/07/2018 7B1020 Engage Design Consultant 08/08/2018 09/04/2018 28B1022 TA Preparation 09/05/2018 09/18/2018 14B1024 TA Approval 09/19/2018 10/28/2018 40B1030 Issue Design NTP 10/29/2018 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/29/2018 06/01/2019 216

30% Des30% Design 10/29/2018 01/16/2019 80B1060 A/E Prepares 30% Construction Documents 10/29/2018 12/17/2018 50B1100 30% CDs Submittal 12/17/2018 0B1120 30% Review (MDWASD/PSIP Team) 12/18/2018 01/16/2019 30

60% Des60% Design 12/18/2018 01/30/2019 44B1130 A/E Prepares 60% Construction Documents 12/18/2018 01/16/2019 30B1140 60% CDs Submittal 01/16/2019 0B1160 60% Review (MDWASD/PSIP Team) 01/17/2019 01/30/2019 14

90% Des90% Design 01/17/2019 06/01/2019 136B1170 A/E Prepares 90% Construction Documents 01/17/2019 02/25/2019 40B1180 90% CDs Submittal 02/25/2019 0B1190 90% Review (MDWASD/PSIP Team) 02/26/2019 03/27/2019 30B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 03/28/2019 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 03/28/2019 05/11/2019 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 05/12/2019 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 05/12/2019 06/01/2019 21B1240 90% Municipality Permit Submittal (Pump Station) 05/12/2019 0B1250 90% Municipality Permit Review (Pump Station) 05/12/2019 06/01/2019 21

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Video ReviewIssue NTP to SSES Contractor (New I/I)

Conduct SSES (New I/I)Smoke Testing (New I/I)Video Review (New I/I)08/30/2018, Dig & Replace RepairsDig & Replace Phase

Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs

Issue NTP for Dig & Replace Repairs (New I/I)Conduct Dig & Replace Repairs (New I/I)08/28/2018, CIPP Repairs

CIPP PhaseIssue NTP for CIPP Repairs

Conduct CIPP Repairs08/28/2018, Manhole Repairs

Manhole PhaseIssue NTP for Manhole Repairs

Conduct Manhole Repairs08/28/2018, Project CloseoutCloseout Phase

Project Closed

06/29/2019, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval

Issue Design NTPFinal Engineering Report Review & Ap

01/16/2019, 30% Design

A/E Prepares 30% Construction Documents30% CDs Submittal

30% Review (MDWASD/PSIP Team)01/30/2019, 60% Design

A/E Prepares 60% Construction Documents60% CDs Submittal60% Review (MDWASD/PSIP Team)

06/01/2019, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (P

90% RER(DERM)FDEP Permit Review (90% RER(Building Dept) Permit Submit

90% RER(Building Dept) Permit Revie90% Municipality Permit Submittal (Pum

90% Municipality Permit Review (Pum

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 33 of 161 TASK filter: All Activities© Oracle Corporation

Page 34: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1260 90% CD PM Comments Evaluation Completed 06/01/2019 0100% De100% Design 06/02/2019 06/29/2019 28

B1270 A/E Prepares 100% Construction Documents 06/02/2019 06/15/2019 14B1280 100% CDs Submittal 06/15/2019 0B1290 100% Review (MDWASD/PSIP Team) 06/16/2019 06/29/2019 14B1300 Design Completed 06/29/2019 0

MDWASDMDWASD Procurement 06/29/2019 10/11/2019 104B1305 Procurement Phase 06/29/2019 10/11/2019 104B1310 Submit CDs to MDWASD Procurement Division 06/29/2019 0B1312 Bid Notice Preparation Period 06/30/2019 08/01/2019 33B1314 Bid Notice 08/01/2019 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conferencce 08/02/2019 08/15/2019 14B1320 Pre-Bid Conference 08/16/2019 08/16/2019 1B1328 Bidders Prepare Bids for Submittal 08/17/2019 09/06/2019 21B1330 Bids Submittal 09/06/2019 0B1340 MDWASD/PSIP Team Bids Evaluation 09/07/2019 09/27/2019 21B1350 Recommendation for Award Letter 09/27/2019 0B1355 Contract Award (Purchase Order Approval) 09/28/2019 10/11/2019 14

ConstrucConstruction 08/16/2019 05/31/2020 290B1360 Construction Phase 08/16/2019 05/31/2020 290B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 09/28/2019 10/18/2019 21B1364 Pre-Construction Meeting 10/19/2019 10/19/2019 1B1366 WASD Issues NTP (Pre-Const to NTP) 10/20/2019 12/03/2019 45B1369 WASD Issues NTP (PO to NTP) 10/12/2019 12/03/2019 53B1370 Construction NTP 12/04/2019 0B1400 Construction Operations 12/04/2019 05/31/2020 180B1402 Substantial Completion 05/31/2020 0

DesignerDesigner Construction Support Services 08/16/2019 05/31/2020 290B1410 Designer Construction Support Services 08/16/2019 05/31/2020 290

Project CProject Closeout 05/31/2020 09/28/2020 120B1445 Closeout Phase 05/31/2020 09/28/2020 120B1450 Issue SAC Letter 05/31/2020 0B1470 Final Release of Retainage - Construction Contract 05/31/2020 0B1480 Administrative Closeout 06/01/2020 09/28/2020 120B1490 Project Closed 09/28/2020 0

Basin 0144Basin 0144 08/01/2018 09/28/2020 790

100185 Pu100185 Pump Station 0144 Upgrade * 08/01/2018 09/28/2020 790DesignDesign 08/01/2018 06/29/2019 333

B1000 Design Phase 08/01/2018 06/29/2019 333B1010 Prepare and Submit Design Package 08/01/2018 08/07/2018 7B1020 Engage Design Consultant 08/08/2018 09/04/2018 28B1022 TA Preparation 09/05/2018 09/18/2018 14B1024 TA Approval 09/19/2018 10/28/2018 40B1030 Issue Design NTP 10/29/2018 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/29/2018 06/01/2019 216

30% Des30% Design 10/29/2018 01/16/2019 80B1060 A/E Prepares 30% Construction Documents 10/29/2018 12/17/2018 50B1100 30% CDs Submittal 12/17/2018 0B1120 30% Review (MDWASD/PSIP Team) 12/18/2018 01/16/2019 30

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

90% CD PM Comments Evaluation C06/29/2019, 100% Design

A/E Prepares 100% Construction Do100% CDs Submittal100% Review (MDWASD/PSIP TeamDesign Completed

10/11/2019, MDWASD ProProcurement Phase

Submit CDs to MDWASD ProcuremBid Notice Preparation Period

Bid NoticeMDWASD/PSIP Team Prepare

Pre-Bid ConferenceBidders Prepare Bids for Subm

Bids SubmittalMDWASD/PSIP Team Bids ERecommendation for Award Contract Award (Purchase O

05/31/2

ConstruMDWASD/PSIP Team PrePre-Construction Meeting

WASD Issues NTP (PreWASD Issues NTP (PO

Construction NTPConstruSubstan05/31/2

Designe

Issue SAFinal Re

06/29/2019, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval

Issue Design NTPFinal Engineering Report Review & Ap

01/16/2019, 30% Design

A/E Prepares 30% Construction Documents30% CDs Submittal

30% Review (MDWASD/PSIP Team)

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 34 of 161 TASK filter: All Activities© Oracle Corporation

Page 35: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

60% Des60% Design 12/18/2018 01/30/2019 44B1130 A/E Prepares 60% Construction Documents 12/18/2018 01/16/2019 30B1140 60% CDs Submittal 01/16/2019 0B1160 60% Review (MDWASD/PSIP Team) 01/17/2019 01/30/2019 14

90% Des90% Design 01/17/2019 06/01/2019 136B1170 A/E Prepares 90% Construction Documents 01/17/2019 02/25/2019 40B1180 90% CDs Submittal 02/25/2019 0B1190 90% Review (MDWASD/PSIP Team) 02/26/2019 03/27/2019 30B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 03/28/2019 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 03/28/2019 05/11/2019 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 05/12/2019 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 05/12/2019 06/01/2019 21B1240 90% Municipality Permit Submittal (Pump Station) 05/12/2019 0B1250 90% Municipality Permit Review (Pump Station) 05/12/2019 06/01/2019 21B1260 90% CD PM Comments Evaluation Completed 06/01/2019 0

100% De100% Design 06/02/2019 06/29/2019 28B1270 A/E Prepares 100% Construction Documents 06/02/2019 06/15/2019 14B1280 100% CDs Submittal 06/15/2019 0B1290 100% Review (MDWASD/PSIP Team) 06/16/2019 06/29/2019 14B1300 Design Completed 06/29/2019 0

MDWASDMDWASD Procurement 06/29/2019 10/11/2019 104B1305 Procurement Phase 06/29/2019 10/11/2019 104B1310 Submit CDs to MDWASD Procurement Division 06/29/2019 0B1312 Bid Notice Preparation Period 06/30/2019 08/01/2019 33B1314 Bid Notice 08/01/2019 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conferencce 08/02/2019 08/15/2019 14B1320 Pre-Bid Conference 08/16/2019 08/16/2019 1B1328 Bidders Prepare Bids for Submittal 08/17/2019 09/06/2019 21B1330 Bids Submittal 09/06/2019 0B1340 MDWASD/PSIP Team Bids Evaluation 09/07/2019 09/27/2019 21B1350 Recommendation for Award Letter 09/27/2019 0B1355 Contract Award (Purchase Order Approval) 09/28/2019 10/11/2019 14

ConstrucConstruction 08/16/2019 05/31/2020 290B1360 Construction Phase 08/16/2019 05/31/2020 290B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 09/28/2019 10/18/2019 21B1364 Pre-Construction Meeting 10/19/2019 10/19/2019 1B1366 WASD Issues NTP (Pre-Const to NTP) 10/20/2019 12/03/2019 45B1369 WASD Issues NTP (PO to NTP) 10/12/2019 12/03/2019 53B1370 Construction NTP 12/04/2019 0B1400 Construction Operations 12/04/2019 05/31/2020 180B1402 Substantial Completion 05/31/2020 0

DesignerDesigner Construction Support Services 08/16/2019 05/31/2020 290B1410 Designer Construction Support Services 08/16/2019 05/31/2020 290

Project CProject Closeout 05/31/2020 09/28/2020 120B1445 Closeout Phase 05/31/2020 09/28/2020 120B1450 Issue SAC Letter 05/31/2020 0B1470 Final Release of Retainage - Construction Contract 05/31/2020 0B1480 Administrative Closeout 06/01/2020 09/28/2020 120B1490 Project Closed 09/28/2020 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

01/30/2019, 60% Design

A/E Prepares 60% Construction Documents60% CDs Submittal60% Review (MDWASD/PSIP Team)

06/01/2019, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (P

90% RER(DERM)FDEP Permit Review 90% RER(Building Dept) Permit Submit

90% RER(Building Dept) Permit Revie90% Municipality Permit Submittal (Pum

90% Municipality Permit Review (Pum90% CD PM Comments Evaluation C

06/29/2019, 100% Design

A/E Prepares 100% Construction Do100% CDs Submittal100% Review (MDWASD/PSIP TeamDesign Completed

10/11/2019, MDWASD ProProcurement Phase

Submit CDs to MDWASD ProcuremBid Notice Preparation Period

Bid NoticeMDWASD/PSIP Team Prepare

Pre-Bid ConferenceBidders Prepare Bids for Subm

Bids SubmittalMDWASD/PSIP Team Bids ERecommendation for Award Contract Award (Purchase O

05/31/2

ConstruMDWASD/PSIP Team PrePre-Construction Meeting

WASD Issues NTP (PreWASD Issues NTP (PO

Construction NTPConstruSubstan05/31/2

Designe

Issue SAFinal Re

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 35 of 161 TASK filter: All Activities© Oracle Corporation

Page 36: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

Basin 0147Basin 0147 07/03/2014 A 08/01/2018 1630

100035 Ba100035 Basin 0147 Infiltration/Inflow Study and Repairs 05/18/2015 A 12/21/2015 A 541InfiltratioInfiltration/Inflow 05/18/2015 A 12/18/2015 A 417

B1000 Infiltration/Inflow Phase 05/18/2015 A 12/18/2015 A 417Sanitary Sanitary Sewer Evaluation Survey 08/19/2015 A 09/24/2015 A 30

B1001 SSES Phase 08/19/2015 A 09/24/2015 A 30B1003 Issue NTP to SSES Contractor 08/19/2015 A 0B1004 Conduct SSES 08/19/2015 A 09/24/2015 A 30

CIPP RepCIPP Repairs 09/17/2015 A 12/18/2015 A 28B1005 CIPP Phase 09/17/2015 A 12/18/2015 A 28B1020 Issue NTP for CIPP Repairs 09/17/2015 A 0B1030 Conduct CIPP Repairs 12/18/2015 A 12/18/2015 A 28

ManholeManhole Repairs 10/02/2015 A 11/11/2015 A 49B1055 Manhole Phase 10/02/2015 A 11/11/2015 A 49B1070 Issue NTP for Manhole Repairs 10/02/2015 A 0B1080 Conduct Manhole Repairs 11/09/2015 A 11/11/2015 A 20

Dig & ReDig & Replace Repairs 05/18/2015 A 12/09/2015 A 30B1105 Dig & Replace Phase 05/18/2015 A 12/09/2015 A 30B1120 Issue NTP for Dig & Replace Repairs 05/18/2015 A 0B1130 Conduct Dig & Replace Repairs 05/26/2015 A 12/09/2015 A 30

Project CProject Closeout 12/21/2015 A 12/21/2015 A 0B1175 Closeout Phase 12/21/2015 A 12/21/2015 A 0B1200 Project Closed 12/21/2015 A 0

100036 Pu100036 Pump Station 0147 Upgrade 07/03/2014 A 08/01/2018 1630DesignDesign 07/03/2014 A 04/27/2016 A 435

B1000 Design Phase 07/03/2014 A 04/27/2016 A 435B1010 Prepare Request for SOW, Fee, Schedule, and Project Book (D 07/03/2014 A 07/03/2014 A 5B1015 Engage Design Consultant (Draft PER) 07/07/2014 A 08/26/2014 A 20B1016 Prepare Request for SOW, Fee, Schedule, and Project Book (A 08/27/2014 A 08/27/2014 A 1B1017 Engage Design Consultant (Approved PER) 08/27/2014 A 11/05/2014 A 20B1020 Issue Design NTP 11/06/2014 A 0B1022 Engage Design Consultant for TA REV 1 07/28/2015 A 03/27/2016 A 20B1024 TA REV 1 Approval Process 03/28/2016 A 04/27/2016 A 20B1030 A/E Develops and Submits Final Engineering Report 11/06/2014 A 06/16/2015 A 20B1040 Final Engineering Report Review & Approval (MDWASD/PSIP Te 03/13/2015 A 03/26/2015 A 10

30% Des30% Design 11/06/2014 A 02/04/2015 A 80B1050 A/E Prepares 30% Construction Documents 11/06/2014 A 01/20/2015 A 30B1060 Geotechnical Engineering Services 11/24/2014 A 01/20/2015 A 25B1070 Surveying Services 11/24/2014 A 12/15/2014 A 15B1090 30% CDs Submittal 01/20/2015 A 0B1110 30% Review (MDWASD/PSIP Team) 01/21/2015 A 02/04/2015 A 10

90% Des90% Design 01/21/2015 A 06/16/2015 A 99B1160 A/E Prepares 90% Construction Documents 01/21/2015 A 03/12/2015 A 20B1170 90% CDs Submittal 03/12/2015 A 0B1180 90% Review (MDWASD/PSIP Team) 03/13/2015 A 03/26/2015 A 5B1190 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 04/06/2015 A 0B1200 90% RER(DERM)/FDEP Permit Review (Pump Station) 04/06/2015 A 05/04/2015 A 5B1210 90% RER (Building Department) Permit Submittal 05/12/2015 A 0B1220 90% RER (Building Department) Permit Review 05/12/2015 A 06/16/2015 A 10

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

08/01/2018, Basin 0147

12/21/2015 A, 100035 Basin 0147 Infiltration/Inflow Study and Repairs12/18/2015 A, Infiltration/Inflow

Infiltration/Inflow Phase09/24/2015 A, Sanitary Sewer Evaluation SurveySSES Phase

Issue NTP to SSES ContractorConduct SSES

12/18/2015 A, CIPP RepairsCIPP Phase

Issue NTP for CIPP RepairsConduct CIPP Repairs

11/11/2015 A, Manhole RepairsManhole Phase

Issue NTP for Manhole RepairsConduct Manhole Repairs

12/09/2015 A, Dig & Replace RepairsDig & Replace Phase

Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs12/21/2015 A, Project CloseoutCloseout Phase

Project Closed08/01/2018, 100036 Pump Station 0147 Upgrade

04/27/2016 A, Design

Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book (Draft PER)

Engage Design Consultant (Draft PER)Prepare Request for SOW, Fee, Schedule, and Project Book (Approved PER)

Engage Design Consultant (Approved PER)Issue Design NTP

Engage Design Consultant for TA REV 1TA REV 1 Approval Process

A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

02/04/2015 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering Services

Surveying Services30% CDs Submittal

30% Review (MDWASD/PSIP Team)06/16/2015 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)90% RER(DERM)/FDEP Permit Submittal (Pump Station)

90% RER(DERM)/FDEP Permit Review (Pump Station)90% RER (Building Department) Permit Submittal

90% RER (Building Department) Permit Review

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 36 of 161 TASK filter: All Activities© Oracle Corporation

Page 37: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1250 90% CD PM Comments Evaluation Completed 06/16/2015 A 0100% De100% Design 04/06/2015 A 04/08/2016 A 86

B1260 A/E Prepares 100% Construction Documents 04/06/2015 A 06/16/2015 A 10B1270 100% CDs Submittal 06/17/2015 A 0B1280 100% Review (MDWASD/PSIP Team) 05/12/2015 A 06/16/2015 A 10B1290 Design Completed 06/16/2015 A 0B1292 TA REV 1 - Design Modifications - Civil, Structural, Electrical & M 07/28/2015 A 04/08/2016 A 86

MDWASDMDWASD Procurement 04/28/2015 A 08/19/2015 A 258B1295 Procurement Phase 04/28/2015 A 08/19/2015 A 258B1300 Submit CDs to MDWASD Procurement Division 04/28/2015 A 0B1312 Bid Notice Preparation Period 04/29/2015 A 04/29/2015 A 33B1314 Bid Notice 04/30/2015 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conferencce 05/01/2015 A 05/05/2015 A 14B1318 Pre-Bid Conference 05/06/2015 A 05/06/2015 A 1B1319 Bidders Prepare Bids for Submittal 05/07/2015 A 06/18/2015 A 21B1320 Bids Submittal 06/18/2015 A 0B1330 MDWASD/PSIP Team Bids Evaluation 06/18/2015 A 07/10/2015 A 21B1340 Recommendation for Award Letter 07/10/2015 A 0B1345 Contract Award (Purchase Order Approval) 07/13/2015 A 08/19/2015 A 14

ConstrucConstruction 05/06/2015 A 03/31/2017 A 1226B1350 Construction Phase 05/06/2015 A 03/31/2017 A 1226B1354 MDWAS/PSIP Team Prepare for Pre-Construction Meeting 07/13/2015 A 07/24/2015 A 21B1356 Pre-Construction Meeting 07/27/2015 A 07/27/2015 A 1B1357 WASD Issues NTP (Pre-Const to NTP) 08/20/2015 A 06/19/2016 A 45B1358 WASD Issues NTP (PO to NTP) 08/20/2015 A 06/19/2016 A 53B1360 Construction NTP 06/20/2016 A 0B1390 Construction Operations 06/20/2016 A 01/30/2017 A 120B1390 Original Construction Duration 06/20/2016 A 10/18/2016 A 120B1390 Change Order #1 - Scriveners Error 10/19/2016 A 12/17/2016 A 120B1390 Change Order #2 - FPL 12/18/2016 A 01/19/2017 A 120B1390 Change Order #3 - Hurricane Mathew 01/20/2017 A 01/24/2017 A 120B1390 Change Order #4 - FPL 01/25/2017 A 02/22/2017 A 120B1392 Substantial Completion 01/30/2017 A 0

DesignerDesigner Construction Support Services 05/06/2015 A 03/31/2017 A 101B1400 Designer Construction Support Services 05/06/2015 A 03/31/2017 A 101

Project CProject Closeout 12/16/2015 A 08/01/2018 959B1435 Closeout Phase 12/16/2015 A 08/01/2018 959B1440 Issue SAC Letter 12/16/2015 A 0B1460 Final Release of Retainage - Construction Contract 08/01/2018 0B1470 Administrative Closeout 01/31/2017 A 08/01/2018 120B1480 Project Closed 08/01/2018 0

Basin 0149Basin 0149 05/22/2015 A 08/01/2018 1332

100037 Ba100037 Basin 0149 Infiltration/Inflow Study and Repairs 05/22/2015 A 05/16/2016 A 211InfiltratioInfiltration/Inflow 05/22/2015 A 05/13/2016 A 159

B1000 Infiltration/Inflow Phase 05/22/2015 A 05/13/2016 A 159CIPP RepCIPP Repairs 05/22/2015 A 05/13/2016 A 136

B1065 CIPP Phase 05/22/2015 A 05/13/2016 A 136B1080 Issue NTP for CIPP Repairs 05/22/2015 A 0B1090 Conduct CIPP Repairs 11/11/2015 A 05/13/2016 A 20

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

90% CD PM Comments Evaluation Completed04/08/2016 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed

TA REV 1 - Design Modifications - Civil, Structural, Electrical & Mechanical08/19/2015 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation Period

Bid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferenccePre-Bid Conference

Bidders Prepare Bids for Submittal

Bids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter

Contract Award (Purchase Order Approval)03/31/2017 A, Construction

Construction PhaseMDWAS/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)

WASD Issues NTP (PO to NTP)Construction NTP

Construction OperationsOriginal Construction Duration

Change Order #1 - Scriveners ErrorChange Order #2 - FPLChange Order #3 - Hurricane Mathew

Change Order #4 - FPL

Substantial Completion03/31/2017 A, Designer Construction Support Services

Designer Construction Support Services08/01/2018, Project Closeout

Closeout PhaseIssue SAC Letter

Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed08/01/2018, Basin 0149

05/16/2016 A, 100037 Basin 0149 Infiltration/Inflow Study and Repairs05/13/2016 A, Infiltration/Inflow

Infiltration/Inflow Phase05/13/2016 A, CIPP RepairsCIPP Phase

Issue NTP for CIPP RepairsConduct CIPP Repairs

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 37 of 161 TASK filter: All Activities© Oracle Corporation

Page 38: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

Dig & ReDig & Replace Repairs 09/25/2015 A 01/21/2016 A 30B1165 Dig & Replace Phase 09/25/2015 A 01/21/2016 A 30B1180 Issue NTP for Dig & Replace Repairs 09/25/2015 A 0B1190 Conduct Dig & Replace Repairs 01/21/2016 A 01/21/2016 A 30

Project CProject Closeout 05/16/2016 A 05/16/2016 A 0B1235 Closeout Phase 05/16/2016 A 05/16/2016 A 0B1260 Project Closed 05/16/2016 A 0

100038 Pu100038 Pump Station 0149(AM) Upgrade 10/12/2015 A 08/01/2018 1235DesignDesign 10/12/2015 A 07/31/2017 A 464

B1000 Design Phase 10/12/2015 A 07/31/2017 A 464B1010 Prepare and Submit Design Package 10/12/2015 A 10/12/2015 A 5B1012 Project SACed Evaluation Period 10/13/2015 A 07/31/2017 A 464

Project CProject Closeout 07/31/2017 A 08/01/2018 723B1445 Closeout Phase 07/31/2017 A 08/01/2018 723B1450 Issue SAC Letter 07/31/2017 A 0B1480 Administrative Closeout 08/01/2017 A 08/01/2018 120B1490 Project Closed 08/01/2018 0

Basin 0158Basin 0158 06/05/2015 A 08/01/2018 1297

100039 Ba100039 Basin 0158 Infiltration/Inflow Study and Repairs 11/20/2015 A 04/25/2016 A 92InfiltratioInfiltration/Inflow 11/20/2015 A 04/25/2016 A 20

B1000 Infiltration/Inflow Phase 11/20/2015 A 04/25/2016 A 20Dig & ReDig & Replace Repairs 11/20/2015 A 04/25/2016 A 20

B1105 Dig & Replace Phase 11/20/2015 A 04/25/2016 A 20B1120 Issue NTP for Dig & Replace Repairs 11/20/2015 A 0B1130 Conduct Dig & Replace Repairs 04/21/2016 A 04/25/2016 A 20

Project CProject Closeout 04/25/2016 A 04/25/2016 A 0B1175 Closeout Phase 04/25/2016 A 04/25/2016 A 0B1200 Project Closed 04/25/2016 A 0

100040 Pu100040 Pump Station 0158 Upgrade 06/05/2015 A 08/01/2018 1297DesignDesign 06/05/2015 A 11/18/2016 A 569

B1000 Design Phase 06/05/2015 A 11/18/2016 A 569B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 06/05/2015 A 06/19/2015 A 5B1020 Engage Design Consultant 06/19/2015 A 07/24/2015 A 15B1025 TA Approval Process 07/27/2015 A 08/07/2015 A 15B1030 Issue Design NTP 08/07/2015 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 08/07/2015 A 09/27/2016 A 94

30% Des30% Design 08/07/2015 A 12/01/2015 A 56B1060 A/E Prepares 30% Construction Documents 08/07/2015 A 10/21/2015 A 30B1100 30% CDs Submittal 10/22/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 10/23/2015 A 12/01/2015 A 10

90% Des90% Design 10/23/2015 A 09/27/2016 A 319B1170 A/E Prepares 90% Construction Documents 10/23/2015 A 01/21/2016 A 20B1180 90% CDs Submittal 01/21/2016 A 0B1190 90% Review (MDWASD/PSIP Team) 01/22/2016 A 05/05/2016 A 15B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 04/28/2016 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 04/28/2016 A 06/20/2016 A 15B1220 90% Doral - BD Permit Submittal 04/28/2016 A 0B1230 90% Doral - BD Permit Review 04/28/2016 A 09/27/2016 A 15B1260 90% CD PM Comments Evaluation Completed 09/27/2016 A 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

01/21/2016 A, Dig & Replace RepairsDig & Replace Phase

Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs

05/16/2016 A, Project CloseoutCloseout Phase

Project Closed08/01/2018, 100038 Pump Station 0149(AM) Upgrade

07/31/2017 A, Design

Design PhasePrepare and Submit Design Package

Project SACed Evaluation Period08/01/2018, Project Closeout

Closeout PhaseIssue SAC Letter

Administrative CloseoutProject Closed08/01/2018, Basin 0158

04/25/2016 A, 100039 Basin 0158 Infiltration/Inflow Study and Repairs04/25/2016 A, Infiltration/InflowInfiltration/Inflow Phase04/25/2016 A, Dig & Replace RepairsDig & Replace Phase

Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs04/25/2016 A, Project CloseoutCloseout Phase

Project Closed08/01/2018, 100040 Pump Station 0158 Upgrade

11/18/2016 A, Design

Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book

Engage Design ConsultantTA Approval ProcessIssue Design NTP

Final Engineering Report Review & Approval (MDWASD/PSIP Team)12/01/2015 A, 30% Design

A/E Prepares 30% Construction Documents30% CDs Submittal

30% Review (MDWASD/PSIP Team)09/27/2016 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)

90% RER(DERM)FDEP Permit Review (Pump Station)90% Doral - BD Permit Submittal

90% Doral - BD Permit Review90% CD PM Comments Evaluation Completed

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 38 of 161 TASK filter: All Activities© Oracle Corporation

Page 39: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

100% De100% Design 09/28/2016 A 11/18/2016 A 78B1270 A/E Prepares 100% Construction Documents 09/28/2016 A 11/18/2016 A 10B1280 100% CDs Submittal 11/18/2016 A 0B1290 100% Review (MDWASD/PSIP Team) 09/28/2016 A 11/18/2016 A 10B1300 Design Completed 11/18/2016 A 0

MDWASDMDWASD Procurement 05/10/2016 A 03/27/2017 A 254B1305 Procurement Phase 05/10/2016 A 03/27/2017 A 254B1310 Submit CDs to MDWASD Procurement Division 05/10/2016 A 0B1312 Bid Notice Preparation Period 05/11/2016 A 05/11/2016 A 23B1314 Bid Notice 05/11/2016 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 05/12/2016 A 05/31/2016 A 10B1320 Pre-Bid Conference 06/01/2016 A 06/01/2016 A 1B1324 Bidders Prepare Bids for Submittal 06/02/2016 A 12/20/2016 A 15B1330 Bids Submittal 12/20/2016 A 0B1340 MDWASD/PSIP Team Bids Evaluation 12/21/2016 A 01/30/2017 A 15B1350 Recommendation for Award Letter 01/30/2017 A 0B1355 Contract Award (Purchase Order Approval) 01/31/2017 A 03/27/2017 A 10

ConstrucConstruction 06/01/2016 A 12/26/2017 A 931B1360 Construction Phase 06/01/2016 A 12/26/2017 A 931B1363 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 01/31/2017 A 03/31/2017 A 21B1365 Pre-Construction Meeting 04/03/2017 A 04/03/2017 A 1B1367 WASD Issues NTP (Pre-Const to NTP) 04/04/2017 A 06/18/2017 A 53B1369 WASD Issues NTP (PO to NTP) 03/28/2017 A 06/18/2017 A 53B1370 Construction NTP 06/19/2017 A 0B1400 Construction Operations 06/19/2017 A 12/26/2017 A 150B1400 Original Construction Duration 06/19/2017 A 11/16/2017 A 150B1400 Change Order #1 - Hurricane Irma 11/17/2017 A 12/07/2017 A 150B1402 Substantial Completion 12/26/2017 A 0

DesignerDesigner Construction Support Services 06/01/2016 A 12/26/2017 A 301B1410 Designer Construction Support Services 06/01/2016 A 12/26/2017 A 301

Project CProject Closeout 12/27/2017 A 08/01/2018 212B1445 Closeout Phase 12/27/2017 A 08/01/2018 212B1450 Issue SAC Letter 07/05/2018 A 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 12/27/2017 A 08/01/2018 120B1490 Project Closed 08/01/2018 0

100239 FM100239 FM for Pump Station 0158 06/09/2015 A 08/01/2018 1283DesignDesign 06/09/2015 A 07/29/2016 A 425

B1000 Design Phase 06/09/2015 A 07/29/2016 A 425B1010 Prepare and Submit Design Package 06/09/2015 A 08/04/2015 A 5B1020 Engage Design Consultant 06/09/2015 A 07/29/2015 A 20B1030 TA Preparation 07/30/2015 A 07/30/2015 A 15B1032 TA Approval Process 07/31/2015 A 08/25/2015 A 20B1040 Issue Design NTP 09/15/2015 A 0B1050 A/E Develops and Submits Final Engineering Report 09/15/2015 A 05/13/2016 A 85B1060 Final Engineering Report Review & Approval (MDWASD/PSIP Te 09/15/2015 A 12/15/2015 A 75

30% Des30% Design 09/15/2015 A 12/15/2015 A 60B1070 A/E Prepares 30% Construction Documents 09/15/2015 A 10/15/2015 A 30B1080 Geotechnical Engineering Services 09/15/2015 A 10/15/2015 A 21

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

11/18/2016 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal

100% Review (MDWASD/PSIP Team)Design Completed

03/27/2017 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid Notice

MDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter

Contract Award (Purchase Order Approval)12/26/2017 A, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Construction NTPConstruction Operations

Original Construction DurationChange Order #1 - Hurricane Irma

Substantial Completion12/26/2017 A, Designer Construction Support Services

Designer Construction Support Services08/01/2018, Project Closeout

Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction ContractAdministrative CloseoutProject Closed08/01/2018, 100239 FM for Pump Station 0158

07/29/2016 A, Design

Design PhasePrepare and Submit Design PackageEngage Design ConsultantTA Preparation

TA Approval ProcessIssue Design NTP

A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)12/15/2015 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering Services

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 39 of 161 TASK filter: All Activities© Oracle Corporation

Page 40: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1090 Surveying Services 09/15/2015 A 10/15/2015 A 21B1100 30% CDs Submittal 10/16/2015 A 0B1110 30% Review (MDWASD/PSIP Team) 10/19/2015 A 12/15/2015 A 6

90% Des90% Design 10/19/2015 A 05/13/2016 A 224B1150 A/E Prepares 90% Construction Documents 10/19/2015 A 02/08/2016 A 20B1160 90% CDs Submittal 02/08/2016 A 0B1170 90% Review (MDWASD/PSIP Team) 02/09/2016 A 05/05/2016 A 15B1180 90% RER(DERM)/FDEP Permit Submittal (Force Main) 04/27/2016 A 0B1190 90% RER(DERM)/FDEP Permit Review (Force Main) 04/27/2016 A 05/12/2016 A 15B1200 90% Doral - PWD Permit Submittal (Force Main) 04/27/2016 A 0B1210 90% Doral - PWD Permit Review (Force Main) 04/27/2016 A 05/10/2016 A 15B1220 90% CD PM Comments Evaluation Completed 05/13/2016 A 0

100% De100% Design 05/16/2016 A 07/29/2016 A 31B1230 A/E Prepares 100% Construction Documents 05/16/2016 A 07/29/2016 A 10B1240 100% CDs Submittal 07/29/2016 A 0B1250 100% Review (MDWASD/PSIP Team) 05/16/2016 A 07/29/2016 A 10B1260 Design Completed 07/29/2016 A 0

MDWASDMDWASD Procurement 05/10/2016 A 08/16/2016 A 50B1270 Procurement Phase 05/10/2016 A 08/16/2016 A 50B1280 Submit CDs to MDWASD Procurement Division 05/10/2016 A 0B1282 Bid Notice Preparation Period 05/10/2016 A 05/10/2016 A 23B1284 Bid Notice 05/11/2016 A 0B1286 MDWASD/PSIP Team Prepare for Pre-Bid Conference 05/12/2016 A 05/31/2016 A 10B1290 Pre-Bid Conference 06/01/2016 A 06/01/2016 A 1B1298 Bidders Prepare Bids for Submittal 06/02/2016 A 06/14/2016 A 15B1300 Bids Submittal 07/08/2016 A 0B1310 Bids Evaluation (MDWASD/PSIP Team) 06/22/2016 A 07/07/2016 A 15B1320 Recommendation for Award Letter 07/07/2016 A 0B1330 Contract Award (Purchase Order Approval) 07/08/2016 A 08/16/2016 A 10

ConstrucConstruction 06/01/2016 A 12/30/2016 A 901B1340 Construction Phase 06/01/2016 A 12/30/2016 A 901B1344 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 07/08/2016 A 07/28/2016 A 15B1346 Pre-Construction Meeting 07/29/2016 A 07/29/2016 A 1B1348 WASD Issues NTP (PO to NTP) 08/17/2016 A 09/12/2016 A 53B1350 Construction NTP 09/13/2016 A 0B1380 Construction Operations 09/13/2016 A 12/09/2016 A 150B1382 Substantial Completion 12/09/2016 A 0

DesignerDesigner Construction Support Services 06/01/2016 A 12/30/2016 A 321B1480 Designer Construction Support Services 06/01/2016 A 12/30/2016 A 321

ConstrucConstruction Close Out 12/12/2016 A 12/30/2016 A 15B1390 Commissioning 12/12/2016 A 12/30/2016 A 15B1400 Punch List 12/12/2016 A 12/23/2016 A 10

Project CProject Closeout 12/12/2016 A 08/01/2018 598B1420 Closeout Phase 12/12/2016 A 08/01/2018 598B1430 Issue SAC Letter 12/20/2017 A 0B1450 Final Release of Retainage - Construction Contract 08/01/2018 0B1460 Administrative Closeout 12/12/2016 A 08/01/2018 30B1470 Project Closed 08/01/2018 0

Basin 0161Basin 0161 05/18/2015 A 05/18/2015 A 583

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Surveying Services30% CDs Submittal

30% Review (MDWASD/PSIP Team)05/13/2016 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)/FDEP Permit Submittal (Force Main)

90% RER(DERM)/FDEP Permit Review (Force Main)90% Doral - PWD Permit Submittal (Force Main)

90% Doral - PWD Permit Review (Force Main)90% CD PM Comments Evaluation Completed

07/29/2016 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed08/16/2016 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid Notice

MDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid ConferenceBidders Prepare Bids for Submittal

Bids SubmittalBids Evaluation (MDWASD/PSIP Team)Recommendation for Award Letter

Contract Award (Purchase Order Approval)12/30/2016 A, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

WASD Issues NTP (PO to NTP)

Construction NTPConstruction OperationsSubstantial Completion

12/30/2016 A, Designer Construction Support Services

Designer Construction Support Services12/30/2016 A, Construction Close Out

CommissioningPunch List

08/01/2018, Project Closeout

Closeout PhaseIssue SAC Letter

Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed

05/18/2015 A, Basin 0161

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 40 of 161 TASK filter: All Activities© Oracle Corporation

Page 41: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

100041 Pu100041 Pump Station 0161 Upgrade 05/18/2015 A 05/18/2015 A 583Project CProject Closeout 05/18/2015 A 05/18/2015 A 583

B1445 Closeout Phase 05/18/2015 A 05/18/2015 A 583B1450 Issue SAC Letter 05/18/2015 A 0B1480 Administrative Closeout 05/18/2015 A 05/18/2015 A 30B1490 Project Closed 05/18/2015 A 0

Basin 0163Basin 0163 09/10/2015 A 09/28/2020 1695

100042 Ba100042 Basin 0163 Infiltration/Inflow Study and Repairs 09/10/2015 A 09/25/2015 A 114InfiltratioInfiltration/Inflow 09/10/2015 A 09/24/2015 A 30

B1000 Infiltration/Inflow Phase 09/10/2015 A 09/24/2015 A 30Sanitary Sanitary Sewer Evaluation Survey 09/10/2015 A 09/24/2015 A 30

B1005 SSES Phase 09/10/2015 A 09/24/2015 A 30B1020 Issue NTP to SSES Contractor 09/10/2015 A 0B1030 Conduct SSES 09/10/2015 A 09/24/2015 A 30

Project CProject Closeout 09/25/2015 A 09/25/2015 A 0B1235 Closeout Phase 09/25/2015 A 09/25/2015 A 0B1260 Project Closed 09/25/2015 A 0

100043 Pu100043 Pump Station 0163 Upgrade * 08/01/2018 09/28/2020 790DesignDesign 08/01/2018 06/29/2019 333

B1000 Design Phase 08/01/2018 06/29/2019 333B1010 Prepare and Submit Design Package 08/01/2018 08/07/2018 7B1020 Engage Design Consultant 08/08/2018 09/04/2018 28B1022 TA Preparation 09/05/2018 09/18/2018 14B1024 TA Approval Process 09/19/2018 10/28/2018 40B1030 Issue Design NTP 10/29/2018 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/29/2018 06/01/2019 216

30% Des30% Design 10/29/2018 01/16/2019 80B1060 A/E Prepares 30% Construction Documents 10/29/2018 12/17/2018 50B1100 30% CDs Submittal 12/17/2018 0B1120 30% Review (MDWASD/PSIP Team) 12/18/2018 01/16/2019 30

60% Des60% Design 12/18/2018 01/30/2019 44B1130 A/E Prepares 60% Construction Documents 12/18/2018 01/16/2019 30B1140 60% CDs Submittal 01/16/2019 0B1160 60% Review (MDWASD/PSIP Team) 01/17/2019 01/30/2019 14

90% Des90% Design 01/17/2019 06/01/2019 136B1170 A/E Prepares 90% Construction Documents 01/17/2019 02/25/2019 40B1180 90% CDs Submittal 02/25/2019 0B1190 90% Review (MDWASD/PSIP Team) 02/26/2019 03/27/2019 30B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 03/28/2019 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 03/28/2019 05/11/2019 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 05/12/2019 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 05/12/2019 06/01/2019 21B1240 90% Municipality Permit Submittal (Pump Station) 05/12/2019 0B1250 90% Municipality Permit Review (Pump Station) 05/12/2019 06/01/2019 21B1260 90% CD PM Comments Evaluation Completed 06/01/2019 0

100% De100% Design 06/02/2019 06/29/2019 28B1270 A/E Prepares 100% Construction Documents 06/02/2019 06/15/2019 14B1280 100% CDs Submittal 06/15/2019 0B1290 100% Review (MDWASD/PSIP Team) 06/16/2019 06/29/2019 14

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

05/18/2015 A, 100041 Pump Station 0161 Upgrade05/18/2015 A, Project Closeout

Closeout PhaseIssue SAC Letter

Administrative CloseoutProject Closed

09/25/2015 A, 100042 Basin 0163 Infiltration/Inflow Study and Repairs09/24/2015 A, Infiltration/Inflow

Infiltration/Inflow Phase09/24/2015 A, Sanitary Sewer Evaluation SurveySSES Phase

Issue NTP to SSES ContractorConduct SSES09/25/2015 A, Project CloseoutCloseout Phase

Project Closed

06/29/2019, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval Process

Issue Design NTPFinal Engineering Report Review & Ap

01/16/2019, 30% Design

A/E Prepares 30% Construction Documents30% CDs Submittal

30% Review (MDWASD/PSIP Team)01/30/2019, 60% Design

A/E Prepares 60% Construction Documents60% CDs Submittal60% Review (MDWASD/PSIP Team)

06/01/2019, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (P

90% RER(DERM)FDEP Permit Review (90% RER(Building Dept) Permit Submit

90% RER(Building Dept) Permit Revie90% Municipality Permit Submittal (Pum

90% Municipality Permit Review (Pum90% CD PM Comments Evaluation C

06/29/2019, 100% Design

A/E Prepares 100% Construction Do100% CDs Submittal100% Review (MDWASD/PSIP Team

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 41 of 161 TASK filter: All Activities© Oracle Corporation

Page 42: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1300 Design Completed 06/29/2019 0MDWASDMDWASD Procurement 06/29/2019 10/11/2019 104

B1305 Procurement Phase 06/29/2019 10/11/2019 104B1310 Submit CDs to MDWASD Procurement Division 06/29/2019 0B1312 Bid Notice Preparation Period 06/30/2019 08/01/2019 33B1314 Bid Notice 08/01/2019 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 08/02/2019 08/15/2019 14B1320 Pre-Bid Conference 08/16/2019 08/16/2019 1B1322 Bidders Prepare Bids for Submittal 08/17/2019 09/06/2019 21B1330 Bids Submittal 09/06/2019 0B1340 MDWASD/PSIP Team Bids Evaluation 09/07/2019 09/27/2019 21B1350 Recommendation for Award Letter 09/27/2019 0B1355 Contract Award (Purchase Order Approval) 09/28/2019 10/11/2019 14

ConstrucConstruction 08/16/2019 05/31/2020 290B1360 Construction Phase 08/16/2019 05/31/2020 290B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 09/28/2019 10/18/2019 21B1364 Pre-Construction Meeting 10/19/2019 10/19/2019 1B1366 WASD Issues NTP (Pre-Const to NTP) 10/20/2019 12/03/2019 45B1369 WASD Issues NTP (PO to NTP) 10/12/2019 12/03/2019 53B1370 Construction NTP 12/04/2019 0B1400 Construction Operations 12/04/2019 05/31/2020 180B1402 Substantial Completion 05/31/2020 0

DesignerDesigner Construction Support Services 08/16/2019 05/31/2020 290B1410 Designer Construction Support Services 08/16/2019 05/31/2020 290

Project CProject Closeout 05/31/2020 09/28/2020 120B1445 Closeout Phase 05/31/2020 09/28/2020 120B1450 Issue SAC Letter 05/31/2020 0B1470 Final Release of Retainage - Construction Contract 05/31/2020 0B1480 Administrative Closeout 06/01/2020 09/28/2020 120B1490 Project Closed 09/28/2020 0

100235 FM100235 FM for Pump Station 0163 * 08/01/2017 A 11/20/2019 761DesignDesign 08/01/2017 A 08/20/2018 320

B1000 Design Phase 08/01/2017 A 08/20/2018 320B1010 Prepare and Submit Design Package 08/01/2017 A 08/01/2017 A 7B1020 Engage Design Consultant 08/02/2017 A 10/02/2017 A 28B1022 TA Preparation 10/03/2017 A 10/16/2017 A 14B1024 TA Approval Process 10/17/2017 A 12/20/2017 A 40B1030 Issue Design NTP 12/22/2017 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 12/22/2017 A 04/13/2018 A 186

30% Des30% Design 12/22/2017 A 02/15/2018 A 120B1060 A/E Prepares 30% Construction Documents 12/22/2017 A 02/05/2018 A 50B1100 30% CDs Submittal 02/05/2018 A 0B1120 30% Review (MDWASD/PSIP Team) 02/06/2018 A 02/15/2018 A 30

90% Des90% Design 02/02/2018 A 07/25/2018 A 174B1180 A/E Prepares 90% Construction Documents 02/06/2018 A 03/14/2018 A 40B1190 90% CDs Submittal 03/14/2018 A 0B1200 90% Review (MDWASD/PSIP Team) 03/15/2018 A 04/09/2018 A 30B1210 90% PWWMD Permit Submittal (Force Main) 02/02/2018 A 0B1220 90% PWWMD Permit Review (Force Main) 02/02/2018 A 02/06/2018 A 21

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Design Completed10/11/2019, MDWASD ProProcurement Phase

Submit CDs to MDWASD ProcuremBid Notice Preparation Period

Bid NoticeMDWASD/PSIP Team Prepare

Pre-Bid ConferenceBidders Prepare Bids for Subm

Bids SubmittalMDWASD/PSIP Team Bids ERecommendation for Award Contract Award (Purchase O

05/31/2

ConstruMDWASD/PSIP Team PrePre-Construction Meeting

WASD Issues NTP (PreWASD Issues NTP (PO

Construction NTPConstruSubstan05/31/2

Designe

Issue SAFinal Re

11/20/2019, 100235 FM08/20/2018, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval ProcessIssue Design NTP

Final Engineering Report Review & Approval (MDWASD/PSIP Team)02/15/2018 A, 30% Design

A/E Prepares 30% Construction Documents30% CDs Submittal

30% Review (MDWASD/PSIP Team)07/25/2018 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)

90% PWWMD Permit Submittal (Force Main)90% PWWMD Permit Review (Force Main)

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 42 of 161 TASK filter: All Activities© Oracle Corporation

Page 43: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1230 90% RER(DERM)FDEP Permit Submittal (Force Main) 04/16/2018 A 0B1240 90% RER(DERM)FDEP Permit Review (Force Main) 04/16/2018 A 07/25/2018 A 45B1290 90% CD PM Comments Evaluation Completed 04/13/2018 A 0

100% De100% Design 07/26/2018 A 08/20/2018 30B1300 A/E Prepares 100% Construction Documents 07/26/2018 A 08/06/2018 14B1310 100% CDs Submittal 08/06/2018 0B1320 100% Review (MDWASD/PSIP Team) 08/07/2018 08/20/2018 14B1330 Design Completed 08/20/2018 0

MDWASDMDWASD Procurement 08/20/2018 12/02/2018 104B1335 Procurement Phase 08/20/2018 12/02/2018 104B1340 Submit CDs to MDWASD Procurement Division 08/20/2018 0B1342 Bid Notice Preparation Period 08/21/2018 09/22/2018 33B1344 Bid Notice 09/22/2018 0B1346 MDWASD/PSIP Team Prepare for Pre-Bid Conference 09/23/2018 10/06/2018 14B1350 Pre-Bid Conference 10/07/2018 10/07/2018 1B1352 Bidders Prepare Bids for Submittal 10/08/2018 10/28/2018 21B1360 Bids Submittal 10/28/2018 0B1370 MDWASD/PSIP Team Bids Evaluation 10/29/2018 11/18/2018 21B1380 Recommendation for Award Letter 11/18/2018 0B1385 Contract Award (Purchase Order Approval) 11/19/2018 12/02/2018 14

ConstrucConstruction 10/07/2018 07/23/2019 290B1390 Construction Phase 10/07/2018 07/23/2019 290B1392 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 11/19/2018 12/09/2018 21B1394 Pre-Construction Meeting 12/10/2018 12/10/2018 1B1396 WASD Issues NTP (Pre-Const to NTP) 12/11/2018 01/24/2019 45B1398 WASD Issues NTP (PO to NTP) 12/03/2018 01/24/2019 53B1400 Construction NTP 01/25/2019 0B1430 Construction Operations 01/25/2019 07/23/2019 180B1432 Substantial Completion 07/23/2019 0

DesignerDesigner Construction Support Services 10/07/2018 07/23/2019 290B1440 Designer Construction Support Services 10/07/2018 07/23/2019 290

Project CProject Closeout 07/23/2019 11/20/2019 120B1475 Closeout Phase 07/23/2019 11/20/2019 120B1500 Final Release of Retainage - Construction Contract 07/23/2019 0B1510 Administrative Closeout 07/24/2019 11/20/2019 120B1520 Project Closed 11/20/2019 0

Basin 0167Basin 0167 01/14/2016 A 08/01/2018 1263

100044 Pu100044 Pump Station 0167 Upgrade 01/14/2016 A 08/01/2018 1263DesignDesign 01/14/2016 A 10/20/2017 A 625

B1000 Design Phase 01/14/2016 A 10/20/2017 A 625B1010 Prepare and Submit Design Package 01/14/2016 A 02/23/2016 A 5B1020 Engage Design Consultant 02/23/2016 A 09/14/2016 A 20B1022 TA Preparation 09/15/2016 A 09/15/2016 A 1B1024 TA Approval Process 09/16/2016 A 10/21/2016 A 20B1030 Issue Design NTP 10/26/2016 A 0

30% Des30% Design 10/26/2016 A 10/20/2017 A 386B1060 A/E Prepares 30% Construction Documents 10/26/2016 A 04/04/2017 A 50B1100 30% CDs Submittal 04/04/2017 A 0B1102 SAC Determination Period 04/05/2017 A 10/20/2017 A 198

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

90% RER(DERM)FDEP Permit Submittal (Force Main)90% RER(DERM)FDEP Permit Review (Force Main)

90% CD PM Comments Evaluation Completed08/20/2018, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed

12/02/2018, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)

07/23/2019, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction Pre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Construction NTPConstruction OperationsSubstantial Completion07/23/2019, Designer Constructio

Designer Construction Support Se11/20/2019, Project Clo

Closeout PhaseFinal Release of Retainage - Con

Administrative CloseoutProject Closed

08/01/2018, Basin 0167

08/01/2018, 100044 Pump Station 0167 Upgrade10/20/2017 A, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval ProcessIssue Design NTP

10/20/2017 A, 30% Design

A/E Prepares 30% Construction Documents30% CDs Submittal

SAC Determination Period

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 43 of 161 TASK filter: All Activities© Oracle Corporation

Page 44: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

Project CProject Closeout 10/20/2017 A 08/01/2018 664B1445 Closeout Phase 10/20/2017 A 08/01/2018 664B1450 Issue SAC Letter 10/20/2017 A 0B1480 Administrative Closeout 10/21/2017 A 08/01/2018 120B1490 Project Closed 08/01/2018 0

Basin 0173Basin 0173 09/25/2014 A 11/29/2019 1881

100045-2 B100045-2 Basin 0173 Infiltration/Inflow Study and Repairs 09/25/2014 A 07/22/2015 A 604InfiltratioInfiltration/Inflow 09/25/2014 A 07/21/2015 A 298

B1000 Infiltration/Inflow Phase 09/25/2014 A 07/21/2015 A 298Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 07/21/2015 A 298

B1005 SSES Phase 09/25/2014 A 07/21/2015 A 298B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 06/25/2015 A 07/21/2015 A 30

Project CProject Closeout 07/22/2015 A 07/22/2015 A 0B1235 Closeout Phase 07/22/2015 A 07/22/2015 A 0B1260 Project Closed 07/22/2015 A 0

100046 Pu100046 Pump Station 0173 Upgrade 04/20/2015 A 11/29/2019 1685DesignDesign 04/20/2015 A 08/29/2018 1228

B1000 Design Phase 04/20/2015 A 08/29/2018 1228B1010 Prepare and Submit Design Package 04/20/2015 A 04/24/2015 A 5B1020 Engage Design Consultant 04/27/2015 A 06/05/2015 A 20B1022 TA Preparation 06/18/2015 A 06/18/2015 A 1B1025 TA Approval Process 06/19/2015 A 06/25/2015 A 20B1030 Issue Design NTP 08/05/2015 A 0B1032 Prepare and Submit Design Package - Re-Design 03/21/2016 A 03/21/2016 A 5B1034 Engage Design Consultant - Re-Design 03/21/2016 A 04/28/2016 A 20B1036 TA Rev 1 Preparation - Re-Design 04/29/2016 A 09/22/2016 A 1B1038 TA Rev 1 Approval Process - Re-Design 09/26/2016 A 11/16/2016 A 20B1039 Issue Re-Design NTP 11/21/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 08/05/2015 A 08/01/2018 86

30% Des30% Design 08/05/2015 A 02/24/2017 A 558B1100 A/E Prepares 30% Construction Documents 08/05/2015 A 09/16/2015 A 30B1110 Geotechnical Engineering Services 08/05/2015 A 09/16/2015 A 20B1120 Surveying Services 08/05/2015 A 09/16/2015 A 15B1140 30% CDs Submittal 09/17/2015 A 0B1160 30% Review (MDWASD/PSIP Team) 09/18/2015 A 10/13/2015 A 10B1162 A/E Prepares 30% Construction Documents - Re-Design 11/21/2016 A 01/13/2017 A 36B1164 30% CDs Submittal - Re-Design 01/13/2017 A 0B1166 30% Review (MDWASD/PSIP Team) - Re-Design 01/13/2017 A 02/24/2017 A 10

90% Des90% Design 10/14/2015 A 08/01/2018 1003B1170 A/E Prepares 90% Construction Documents 10/14/2015 A 11/24/2015 A 20B1180 90% CDs Submittal 11/24/2015 A 0B1190 90% Review (MDWASD/PSIP Team) 11/25/2015 A 03/18/2016 A 15B1192 A/E Prepares 90% Construction Documents - Re-Design 02/27/2017 A 08/11/2017 A 40B1194 90% CDs Submittal - Re-Design 08/11/2017 A 0B1196 90% Review (MDWASD/PSIP Team) - Re-Design 08/14/2017 A 10/09/2017 A 30B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 11/20/2017 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 11/20/2017 A 03/13/2018 A 45B1220 90% Doral - BD Permit Submittal 03/26/2018 A 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

08/01/2018, Project Closeout

Closeout PhaseIssue SAC Letter

Administrative CloseoutProject Closed

11/29/2019, Basin 017

07/22/2015 A, 100045-2 Basin 0173 Infiltration/Inflow Study and Repairs07/21/2015 A, Infiltration/Inflow

Infiltration/Inflow Phase07/21/2015 A, Sanitary Sewer Evaluation SurveySSES Phase

Issue NTP to SSES ContractorConduct SSES07/22/2015 A, Project CloseoutCloseout Phase

Project Closed11/29/2019, 100046 P

08/29/2018, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA PreparationTA Approval Process

Issue Design NTPPrepare and Submit Design Package - Re-Design

Engage Design Consultant - Re-DesignTA Rev 1 Preparation - Re-Design

TA Rev 1 Approval Process - Re-DesignIssue Re-Design NTP

Final Engineering Report Review & Approval (MDWASD/PSIP 02/24/2017 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal

30% Review (MDWASD/PSIP Team)A/E Prepares 30% Construction Documents - Re-Design

30% CDs Submittal - Re-Design30% Review (MDWASD/PSIP Team) - Re-Design

08/01/2018, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)A/E Prepares 90% Construction Documents - Re-Design90% CDs Submittal - Re-Design

90% Review (MDWASD/PSIP Team) - Re-Design90% RER(DERM)FDEP Permit Submittal (Pump Station)

90% RER(DERM)FDEP Permit Review (Pump Station)90% Doral - BD Permit Submittal

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 44 of 161 TASK filter: All Activities© Oracle Corporation

Page 45: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1230 90% Doral - BD Permit Review 03/26/2018 A 08/01/2018 21B1240 90% Doral - PWD Permit Submittal 10/23/2015 A 0B1250 90% Doral - PWD Permit Review 10/23/2015 A 10/30/2015 A 15B1260 90% CD PM Comments Evaluation Completed 08/01/2018 0B1262 MDWASD Union Concurrence Process 08/25/2017 A 09/28/2017 A 30

100% De100% Design 08/02/2018 08/29/2018 28B1270 A/E Prepares 100% Construction Documents 08/02/2018 08/15/2018 14B1280 100% CDs Submittal 08/15/2018 0B1290 100% Review (MDWASD/PSIP Team) 08/16/2018 08/29/2018 14B1300 Design Completed 08/29/2018 0

MDWASDMDWASD Procurement 08/29/2018 12/11/2018 104B1305 Procurement Phase 08/29/2018 12/11/2018 104B1310 Submit CDs to MDWASD Procurement Division 08/29/2018 0B1312 Bid Notice Preparation Period 08/30/2018 10/01/2018 33B1314 Bid Notice 10/01/2018 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 10/02/2018 10/15/2018 14B1320 Pre-Bid Conference 10/16/2018 10/16/2018 1B1328 Bidders prepare Bids for Submittal 10/17/2018 11/06/2018 21B1330 Bids Submittal 11/06/2018 0B1340 MDWASD/PSIP Team Bids Evaluation 11/07/2018 11/27/2018 21B1350 Recommendation for Award Letter 11/27/2018 0B1355 Contract Award (Purchase Order Approval) 11/28/2018 12/11/2018 14

ConstrucConstruction 10/16/2018 08/01/2019 290B1360 Construction Phase 10/16/2018 08/01/2019 290B1364 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 11/28/2018 12/18/2018 21B1365 Pre-Construction Meeting 12/19/2018 12/19/2018 1B1367 WASD Issues NTP (Pre-Const to NTP) 12/20/2018 02/02/2019 45B1369 WASD Issues NTP (PO to NTP) 12/12/2018 02/02/2019 53B1370 Construction NTP 02/03/2019 0B1400 Construction Operations 02/03/2019 08/01/2019 180B1402 Substantial Completion 08/01/2019 0

DesignerDesigner Construction Support Services 10/16/2018 08/01/2019 290B1410 Designer Construction Support Services 10/16/2018 08/01/2019 290

Project CProject Closeout 08/01/2019 11/29/2019 120B1445 Closeout Phase 08/01/2019 11/29/2019 120B1450 Issue SAC Letter 08/01/2019 0B1470 Final Release of Retainage - Construction Contract 08/01/2019 0B1480 Administrative Closeout 08/02/2019 11/29/2019 120B1490 Project Closed 11/29/2019 0

Basin 0194Basin 0194 04/08/2015 A 04/08/2015 A 1499

100047 FM100047 FM for Pump Station 0194 04/08/2015 A 04/08/2015 A 1499Project CProject Closeout 04/08/2015 A 04/08/2015 A 1499

A1535 Closeout Phase 04/08/2015 A 04/08/2015 A 1499A1540 Issue SAC Letter 04/08/2015 A 0A1548 Administrative Closeout 04/08/2015 A 04/08/2015 A 15A1550 Project Closed 04/08/2015 A 04/08/2015 A 10

Basin 0196Basin 0196 05/22/2015 A 09/29/2020 1794

100048-2 B100048-2 Basin 0196 Infiltration/Inflow Study and Repairs 05/22/2015 A 03/14/2016 A 212InfiltratioInfiltration/Inflow 05/22/2015 A 03/11/2016 A 121

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

90% Doral - BD Permit Review90% Doral - PWD Permit Submittal90% Doral - PWD Permit Review

90% CD PM Comments Evaluation CompletedMDWASD Union Concurrence Process

08/29/2018, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed

12/11/2018, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)

08/01/2019, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-ConstructionPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Construction NTPConstruction OperationsSubstantial Completion08/01/2019, Designer Constructi

Designer Construction Support S11/29/2019, Project Clo

Closeout PhaseIssue SAC LetterFinal Release of Retainage - Con

Administrative CloseouProject Closed

04/08/2015 A, Basin 0194

04/08/2015 A, 100047 FM for Pump Station 019404/08/2015 A, Project Closeout

Closeout PhaseIssue SAC Letter

Administrative CloseoutProject Closed

03/14/2016 A, 100048-2 Basin 0196 Infiltration/Inflow Study and Repairs03/11/2016 A, Infiltration/Inflow

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 45 of 161 TASK filter: All Activities© Oracle Corporation

Page 46: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1000 Infiltration/Inflow Phase 05/22/2015 A 03/11/2016 A 121CIPP RepCIPP Repairs 05/22/2015 A 03/11/2016 A 20

B1005 CIPP Phase 05/22/2015 A 03/11/2016 A 20B1020 Issue NTP for CIPP Repairs 05/22/2015 A 0B1030 Conduct CIPP Repairs 07/22/2015 A 03/11/2016 A 20

Dig & ReDig & Replace Repairs 11/20/2015 A 02/23/2016 A 30B1105 Dig & Replace Phase 11/20/2015 A 02/23/2016 A 30B1120 Issue NTP for Dig & Replace Repairs 11/20/2015 A 0B1130 Conduct Dig & Replace Repairs 01/05/2016 A 02/23/2016 A 30

Project CProject Closeout 03/14/2016 A 03/14/2016 A 0B1175 Closeout Phase 03/14/2016 A 03/14/2016 A 0B1200 Project Closed 03/14/2016 A 0

100049 Pu100049 Pump Station 0196 Upgrade 08/01/2018 09/29/2020 791DesignDesign 08/01/2018 06/29/2019 333

B1000 Design Phase 08/01/2018 06/29/2019 333B1010 Prepare and Submit Design Package 08/01/2018 08/07/2018 7B1020 Engage Design Consultant 08/08/2018 09/04/2018 28B1022 TA Preparation 09/05/2018 09/18/2018 14B1024 TA Approval Process 09/19/2018 10/28/2018 40B1030 Issue Design NTP 10/29/2018 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/29/2018 06/01/2019 216

30% Des30% Design 10/29/2018 01/16/2019 80B1060 A/E Prepares 30% Construction Documents 10/29/2018 12/17/2018 50B1100 30% CDs Submittal 12/17/2018 0B1120 30% Review (MDWASD/PSIP Team) 12/18/2018 01/16/2019 30

60% Des60% Design 12/18/2018 01/30/2019 44B1130 A/E Prepares 60% Construction Documents 12/18/2018 01/16/2019 30B1140 60% CDs Submittal 01/16/2019 0B1160 60% Review (MDWASD/PSIP Team) 01/17/2019 01/30/2019 14

90% Des90% Design 01/17/2019 06/01/2019 136B1170 A/E Prepares 90% Construction Documents 01/17/2019 02/25/2019 40B1180 90% CDs Submittal 02/25/2019 0B1190 90% Review (MDWASD/PSIP Team) 02/26/2019 03/27/2019 30B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 03/28/2019 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 03/28/2019 05/11/2019 45B1220 90% RER (Building Department) Permit Submittal 05/12/2019 0B1230 90% RER (Building Department) Permit Review 05/12/2019 06/01/2019 21B1240 90% Municipality Permit Submittal (Pump Station) 05/12/2019 0B1250 90% Municipality Permit Review (Pump Station) 05/12/2019 06/01/2019 21B1260 90% CD PM Comments Evaluation Completed 06/01/2019 0

100% De100% Design 06/02/2019 06/29/2019 28B1270 A/E Prepares 100% Construction Documents 06/02/2019 06/15/2019 14B1280 100% CDs Submittal 06/15/2019 0B1290 100% Review (MDWASD/PSIP Team) 06/16/2019 06/29/2019 14B1300 Design Completed 06/29/2019 0

MDWASDMDWASD Procurement 06/30/2019 10/12/2019 104B1305 Procurement Phase 06/30/2019 10/12/2019 104B1310 Submit CDs to MDWASD Procurement Division 06/30/2019 0B1312 Bid Notice Preparation Period 07/01/2019 08/02/2019 33

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Infiltration/Inflow Phase03/11/2016 A, CIPP RepairsCIPP Phase

Issue NTP for CIPP RepairsConduct CIPP Repairs

02/23/2016 A, Dig & Replace RepairsDig & Replace Phase

Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs

03/14/2016 A, Project CloseoutCloseout Phase

Project Closed

06/29/2019, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval Process

Issue Design NTPFinal Engineering Report Review & Ap

01/16/2019, 30% Design

A/E Prepares 30% Construction Documents30% CDs Submittal

30% Review (MDWASD/PSIP Team)01/30/2019, 60% Design

A/E Prepares 60% Construction Documents60% CDs Submittal60% Review (MDWASD/PSIP Team)

06/01/2019, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (P

90% RER(DERM)FDEP Permit Review (90% RER (Building Department) Permit

90% RER (Building Department) Perm90% Municipality Permit Submittal (Pum

90% Municipality Permit Review (Pum90% CD PM Comments Evaluation C

06/29/2019, 100% Design

A/E Prepares 100% Construction Do100% CDs Submittal100% Review (MDWASD/PSIP TeamDesign Completed

10/12/2019, MDWASD ProProcurement Phase

Submit CDs to MDWASD ProcuremBid Notice Preparation Period

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 46 of 161 TASK filter: All Activities© Oracle Corporation

Page 47: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1314 Bid Notice 08/02/2019 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 08/03/2019 08/16/2019 14B1320 Pre-Bid Conference 08/17/2019 08/17/2019 1B1322 Bidders Prepare Bids for Submittal 08/18/2019 09/07/2019 21B1330 Bids Submittal 09/07/2019 0B1340 MDWASD/PSIP Team Bids Evaluation 09/08/2019 09/28/2019 21B1350 Recommendation for Award Letter 09/28/2019 0B1355 Contract Award (Purchase Order Approval) 09/29/2019 10/12/2019 14

ConstrucConstruction 08/17/2019 06/01/2020 290B1360 Construction Phase 08/17/2019 06/01/2020 290B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 09/29/2019 10/19/2019 21B1364 Pre-Construction Meeting 10/20/2019 10/20/2019 1B1366 WASD Issues NTP (Pre-Const to NTP) 10/21/2019 12/04/2019 45B1369 WASD Issues NTP (PO to NTP) 10/13/2019 12/04/2019 53B1370 Construction NTP 12/05/2019 0B1400 Construction Operations 12/05/2019 06/01/2020 180B1402 Substantial Completion 06/01/2020 0

DesignerDesigner Construction Support Services 08/17/2019 06/01/2020 290B1410 Designer Construction Support Services 08/17/2019 06/01/2020 290

Project CProject Closeout 06/01/2020 09/29/2020 120B1445 Closeout Phase 06/01/2020 09/29/2020 120B1450 Issue SAC Letter 06/01/2020 0B1470 Final Release of Retainage - Construction Contract 06/01/2020 0B1480 Administrative Closeout 06/02/2020 09/29/2020 120B1490 Project Closed 09/29/2020 0

Basin 0201Basin 0201 05/21/2014 A 08/01/2016 A 1535

100050-2 B100050-2 Basin 0201 Infiltration/Inflow Study and Repairs 09/25/2014 A 08/03/2015 A 604InfiltratioInfiltration/Inflow 09/25/2014 A 07/31/2015 A 466

B1000 Infiltration/Inflow Phase 09/25/2014 A 07/31/2015 A 466Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 05/15/2015 A 156

B1005 SSES Phase 09/25/2014 A 05/15/2015 A 156B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct Flow Isolation & SSES 10/28/2014 A 04/16/2015 A 30B1040 Video Review 12/05/2014 A 05/15/2015 A 30

CIPP RepCIPP Repairs 04/17/2015 A 07/30/2015 A 38B1065 CIPP Phase 04/17/2015 A 07/30/2015 A 38B1080 Issue NTP for CIPP Repairs 04/17/2015 A 0B1090 Conduct CIPP Repairs 05/26/2015 A 06/11/2015 A 20B1100 Punch List 06/12/2015 A 07/30/2015 A 10

Dig & ReDig & Replace Repairs 05/18/2015 A 07/31/2015 A 30B1165 Dig & Replace Phase 05/18/2015 A 07/31/2015 A 30B1180 Issue NTP for Dig & Replace Repairs 05/18/2015 A 0B1190 Conduct Dig & Replace Repairs 07/30/2015 A 07/31/2015 A 30

Project CProject Closeout 08/03/2015 A 08/03/2015 A 0B1235 Closeout Phase 08/03/2015 A 08/03/2015 A 0B1260 Project Closed 08/03/2015 A 0

100051 Pu100051 Pump Station 0201 Upgrade 05/21/2014 A 08/01/2016 A 1523100% De100% Design 09/02/2014 A 09/02/2014 A 0

B1260 Design Completed 09/02/2014 A 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Bid NoticeMDWASD/PSIP Team Prepare

Pre-Bid ConferenceBidders Prepare Bids for Subm

Bids SubmittalMDWASD/PSIP Team Bids ERecommendation for Award Contract Award (Purchase

06/01/2

ConstruMDWASD/PSIP Team PrePre-Construction Meeting

WASD Issues NTP (PreWASD Issues NTP (PO

Construction NTPConstruSubstan06/01/2

Designe

Issue SAFinal Re

08/01/2016 A, Basin 0201

08/03/2015 A, 100050-2 Basin 0201 Infiltration/Inflow Study and Repairs07/31/2015 A, Infiltration/Inflow

Infiltration/Inflow Phase05/15/2015 A, Sanitary Sewer Evaluation Survey

SSES PhaseIssue NTP to SSES Contractor

Conduct Flow Isolation & SSESVideo Review

07/30/2015 A, CIPP Repairs

CIPP PhaseIssue NTP for CIPP Repairs

Conduct CIPP RepairsPunch List07/31/2015 A, Dig & Replace Repairs

Dig & Replace PhaseIssue NTP for Dig & Replace Repairs

Conduct Dig & Replace Repairs08/03/2015 A, Project Closeout

Closeout PhaseProject Closed

08/01/2016 A, 100051 Pump Station 0201 Upgrade09/02/2014 A, 100% Design

Design Completed

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 47 of 161 TASK filter: All Activities© Oracle Corporation

Page 48: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

MDWASDMDWASD Procurement 05/21/2014 A 12/22/2014 A 346B1265 Procurement Phase 05/21/2014 A 12/22/2014 A 346B1270 Submit CDs to MDWASD Procurement Division 05/21/2014 A 0B1273 Bid Notice Preparation Period 05/22/2014 A 09/02/2014 A 23B1275 Bid Notice 09/03/2014 A 0B1277 MDWASD/PSIP Team Prepare for Pre-Bid Conferencce 09/04/2014 A 09/16/2014 A 10B1280 Pre-Bid Conference 09/17/2014 A 0B1285 Bidders Prepare Bids for Submittal 09/18/2014 A 10/06/2014 A 15B1290 Bids Submittal 10/07/2014 A 0B1300 MDWASD/PSIP Team Bids Evaluation 10/08/2014 A 11/05/2014 A 5B1310 Recommendation for Award Letter 11/06/2014 A 0B1312 Contract Award (Purchase Order Approval) 11/07/2014 A 12/22/2014 A 0

ConstrucConstruction 12/16/2014 A 09/05/2015 A 1381B1320 Construction Phase 12/16/2014 A 09/05/2015 A 1381B1323 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 12/23/2014 A 01/28/2015 A 15B1326 Pre-Construction Meeting 01/28/2015 A 0B1328 Permit Approvals 12/16/2014 A 03/27/2015 A 20B1329 WASD Issues NTP (PO to NTP) 12/23/2014 A 03/08/2015 A 53B1330 Construction NTP 03/09/2015 A 0B1340 Mobilization 03/09/2015 A 03/27/2015 A 30B1350 Construction Operations 03/09/2015 A 09/04/2015 A 121B1350 Original Construction Duration 03/09/2015 A 07/07/2015 A 121B1350 Change order #1 - Pump Delevery 07/08/2015 A 08/26/2015 A 121B1350 Change order #2 - Impeller Changes 08/27/2015 A 09/05/2015 A 121B1362 Substantial Completion 09/04/2015 A 0

DesignerDesigner Construction Support Services 03/09/2015 A 09/04/2015 A 140B1370 Designer Construction Support Services 03/09/2015 A 09/04/2015 A 140

ConstrucConstruction Close Out 08/06/2015 A 09/04/2015 A 15B1380 Commissioning 08/06/2015 A 09/04/2015 A 15B1390 Punch List 08/06/2015 A 09/04/2015 A 10

Project CProject Closeout 09/07/2015 A 08/01/2016 A 334B1405 Closeout Phase 09/07/2015 A 08/01/2016 A 334B1408 SAC Letter Issuance Period 09/07/2015 A 10/20/2015 A 30B1410 Issue SAC Letter 10/21/2015 A 0B1428 Final Release of Retainage Period 09/07/2015 A 05/06/2016 A 10B1430 Final Release of Retainage - Construction Contract 05/06/2016 A 0B1440 Administrative Closeout 09/07/2015 A 08/01/2016 A 30B1450 Project Closed 08/01/2016 A 0

Basin 0215Basin 0215 10/03/2017 A 12/05/2019 765

100052 Pu100052 Pump Station 0215 Upgrade 10/03/2017 A 12/05/2019 765DesignDesign 10/03/2017 A 09/04/2018 308

B1000 Design Phase 10/03/2017 A 09/04/2018 308B1010 Prepare and Submit Design Package 10/03/2017 A 10/03/2017 A 7B1020 Engage Design Consultant 10/04/2017 A 10/27/2017 A 28B1022 TA Preparation 10/28/2017 A 12/12/2017 A 14B1024 TA Approval Process 12/13/2017 A 02/02/2018 A 40B1030 Issue Design NTP 02/05/2018 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 02/05/2018 A 08/07/2018 186

30% Des30% Design 02/05/2018 A 04/23/2018 A 55

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

12/22/2014 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid Notice

MDWASD/PSIP Team Prepare for Pre-Bid ConferenccePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter

Contract Award (Purchase Order Approval)09/05/2015 A, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction Meeting

Pre-Construction MeetingPermit Approvals

WASD Issues NTP (PO to NTP)

Construction NTPMobilization

Construction OperationsOriginal Construction Duration

Change order #1 - Pump DeleveryChange order #2 - Impeller Changes

Substantial Completion09/04/2015 A, Designer Construction Support Services

Designer Construction Support Services09/04/2015 A, Construction Close Out

CommissioningPunch List

08/01/2016 A, Project Closeout

Closeout PhaseSAC Letter Issuance PeriodIssue SAC Letter

Final Release of Retainage Period

Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed

12/05/2019, Basin 021

12/05/2019, 100052 P09/04/2018, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval Process

Issue Design NTPFinal Engineering Report Review & Approval (MDWASD/PSIP

04/23/2018 A, 30% Design

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 48 of 161 TASK filter: All Activities© Oracle Corporation

Page 49: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1060 A/E Prepares 30% Construction Documents 02/05/2018 A 04/06/2018 A 50B1100 30% CDs Submittal 04/06/2018 A 0B1120 30% Review (MDWASD/PSIP Team) 04/07/2018 A 04/23/2018 A 18

90% Des90% Design 04/25/2018 A 08/07/2018 113B1170 A/E Prepares 90% Construction Documents 04/25/2018 A 05/22/2018 A 29B1180 90% CDs Submittal 05/22/2018 A 0B1190 90% Review (MDWASD/PSIP Team) 05/23/2018 A 06/05/2018 A 16B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 06/06/2018 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 06/06/2018 A 07/17/2018 A 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 07/18/2018 A 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 07/18/2018 A 08/07/2018 21B1260 90% CD PM Comments Evaluation Completed 08/07/2018 0

100% De100% Design 08/08/2018 09/04/2018 28B1270 A/E Prepares 100% Construction Documents 08/08/2018 08/21/2018 14B1280 100% CDs Submittal 08/21/2018 0B1290 100% Review (MDWASD/PSIP Team) 08/22/2018 09/04/2018 14B1300 Design Completed 09/04/2018 0

MDWASDMDWASD Procurement 09/04/2018 12/17/2018 104B1305 Procurement Phase 09/04/2018 12/17/2018 104B1310 Submit CDs to MDWASD Procurement Division 09/04/2018 0B1312 Bid Notice Preparation Period 09/05/2018 10/07/2018 33B1314 Bid Notice 10/07/2018 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 10/08/2018 10/21/2018 14B1320 Pre-Bid Conference 10/22/2018 10/22/2018 1B1322 Bidders Prepare Bids for Submittal 10/23/2018 11/12/2018 21B1330 Bids Submittal 11/12/2018 0B1340 MDWASD/PSIP Team Bids Evaluation 11/13/2018 12/03/2018 21B1350 Recommendation for Award Letter 12/03/2018 0B1355 Contract Award (Purchase Order Approval) 12/04/2018 12/17/2018 14

ConstrucConstruction 10/22/2018 08/07/2019 290B1360 Construction Phase 10/22/2018 08/07/2019 290B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 12/04/2018 12/24/2018 21B1364 Pre-Construction Meeting 12/25/2018 12/25/2018 1B1366 WASD Issues NTP (Pre-Const to NTP) 12/26/2018 02/08/2019 45B1368 WASD Issues NTP (PO to NTP) 12/18/2018 02/08/2019 53B1370 Construction NTP 02/09/2019 0B1400 Construction Operations 02/09/2019 08/07/2019 180B1402 Substantial Completion 08/07/2019 0

DesignerDesigner Construction Support Services 10/22/2018 08/07/2019 290B1410 Designer Construction Support Services 10/22/2018 08/07/2019 290

Project CProject Closeout 08/07/2019 12/05/2019 120B1445 Closeout Phase 08/07/2019 12/05/2019 120B1450 Issue SAC Letter 08/07/2019 0B1470 Final Release of Retainage - Construction Contract 08/07/2019 0B1480 Administrative Closeout 08/08/2019 12/05/2019 120B1490 Project Closed 12/05/2019 0

Basin 0309Basin 0309 01/11/2012 A 08/01/2018 1225

100053 Pu100053 Pump Station 0309 Upgrade 01/11/2012 A 08/01/2018 1225DesignDesign 01/11/2012 A 09/25/2017 A 1225

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

A/E Prepares 30% Construction Documents30% CDs Submittal

30% Review (MDWASD/PSIP Team)08/07/2018, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)

90% RER(DERM)FDEP Permit Submittal (Pump Station)90% RER(DERM)FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)90% RER(Building Dept) Permit Review (Pump Station)90% CD PM Comments Evaluation Completed

09/04/2018, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed

12/17/2018, MDWASD ProcurementProcurement Phase

Submit CDs to MDWASD Procurement DivisionBid Notice Preparation Period

Bid NoticeMDWASD/PSIP Team Prepare for Pre-Bid Conference

Pre-Bid ConferenceBidders Prepare Bids for Submittal

Bids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)

08/07/2019, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-ConstructionPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Construction NTPConstruction OperationsSubstantial Completion08/07/2019, Designer Construct

Designer Construction Support S12/05/2019, Project ClCloseout Phase

Issue SAC LetterFinal Release of Retainage - Co

Administrative CloseouProject Closed

08/01/2018, Basin 0309

08/01/2018, 100053 Pump Station 0309 Upgrade09/25/2017 A, Design

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 49 of 161 TASK filter: All Activities© Oracle Corporation

Page 50: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1000 Design Phase 01/11/2012 A 09/25/2017 A 1225B1028 Initial Moratorium 01/11/2012 A 05/19/2014 A 860B1030 Remedial Action Plan (RAP) 05/20/2014 A 09/25/2017 A 1225

Project CProject Closeout 11/12/2017 A 08/01/2018 489B1445 Closeout Phase 11/12/2017 A 08/01/2018 489B1450 Issue SAC Letter 11/12/2017 A 0B1480 Administrative Closeout 11/13/2017 A 08/01/2018 120B1490 Project Closed 08/01/2018 0

New EPS-New EPS-2 08/01/2018 09/28/2020 790

100260 Pu100260 Pump Station 0319 Upgrade 08/01/2018 09/28/2020 790DesignDesign 08/01/2018 06/29/2019 333

B1000 Design Phase 08/01/2018 06/29/2019 333B1005 Prepare and Submit Design Package 08/01/2018 08/07/2018 7B1010 Engage Design Consultant 08/08/2018 09/04/2018 28B1012 TA Preparation 09/05/2018 09/18/2018 14B1014 TA Approval 09/19/2018 10/28/2018 40B1030 Issue Design NTP 10/29/2018 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/29/2018 06/01/2019 216

30% Des30% Design 10/29/2018 01/16/2019 80B1060 A/E Prepares 30% Construction Documents 10/29/2018 12/17/2018 50B1100 30% CDs Submittal 12/17/2018 0B1120 30% Review (MDWASD/PSIP Team) 12/18/2018 01/16/2019 30

60% Des60% Design 12/18/2018 01/30/2019 44B1130 A/E Prepares 60% Construction Documents 12/18/2018 01/16/2019 30B1140 60% CDs Submittal 01/16/2019 0B1160 60% Review (MDWASD/PSIP Team) 01/17/2019 01/30/2019 14

90% Des90% Design 01/17/2019 06/01/2019 136B1170 A/E Prepares 90% Construction Documents 01/17/2019 02/25/2019 40B1180 90% CDs Submittal 02/25/2019 0B1190 90% Review (MDWASD/PSIP Team) 02/26/2019 03/27/2019 30B1200 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 03/28/2019 0B1210 90% RER(DERM)/FDEP Permit Review (Pump Station) 03/28/2019 05/11/2019 45B1220 90% RER (Building Dept Permit Submittal (Pump Station) 05/12/2019 0B1230 90% RER (Building Dept) Permit Review (Pump Station) 05/12/2019 06/01/2019 21B1240 90% PWWMD Permit Submittal (Pump Station) 05/12/2019 0B1250 90% PWWMD Permit Review (Pump Station) 05/12/2019 06/01/2019 21B1260 90% CD PM Comments Evaluation Completed 06/01/2019 0

100% De100% Design 06/02/2019 06/29/2019 28B1270 A/E Prepares 100% Construction Documents 06/02/2019 06/15/2019 14B1280 100% CDs Submittal 06/15/2019 0B1290 100% Review (MDWASD/PSIP Team) 06/16/2019 06/29/2019 14B1300 Design Completed 06/29/2019 0

MDWASDMDWASD Procurement 06/29/2019 10/11/2019 104B1305 Procurement Phase 06/29/2019 10/11/2019 104B1310 Submit CDs to MDWASD Procurement Division 06/29/2019 0B1312 Bid Notice Preparation Period 06/30/2019 08/01/2019 33B1314 Bid Notice 08/01/2019 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conferencce 08/02/2019 08/15/2019 14B1320 Pre-Bid Conference 08/16/2019 08/16/2019 1

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Design PhaseInitial Moratorium

Remedial Action Plan (RAP)08/01/2018, Project CloseoutCloseout Phase

Issue SAC LetterAdministrative CloseoutProject Closed

06/29/2019, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA ApprovalIssue Design NTP

Final Engineering Report Review & Ap01/16/2019, 30% Design

A/E Prepares 30% Construction Documents30% CDs Submittal

30% Review (MDWASD/PSIP Team)01/30/2019, 60% Design

A/E Prepares 60% Construction Documents60% CDs Submittal60% Review (MDWASD/PSIP Team)

06/01/2019, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)/FDEP Permit Submittal (P

90% RER(DERM)/FDEP Permit Review 90% RER (Building Dept Permit Submit

90% RER (Building Dept) Permit Revie90% PWWMD Permit Submittal (Pump

90% PWWMD Permit Review (Pump 90% CD PM Comments Evaluation C

06/29/2019, 100% Design

A/E Prepares 100% Construction Do100% CDs Submittal100% Review (MDWASD/PSIP TeamDesign Completed

10/11/2019, MDWASD Pro

Procurement PhaseSubmit CDs to MDWASD Procurem

Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare Pre-Bid Conference

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 50 of 161 TASK filter: All Activities© Oracle Corporation

Page 51: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1328 Bidders Prepare Bids for Submittal 08/17/2019 09/06/2019 21B1330 Bids Submittal 09/06/2019 0B1340 MDWASD/PSIP Team Bids Evaluation 09/07/2019 09/27/2019 21B1350 Recommendation for Award Letter 09/27/2019 0B1355 Contract Award (Purchase Order Approval) 09/28/2019 10/11/2019 14

ConstrucConstruction 08/16/2019 05/31/2020 290B1357 Construction Phase 08/16/2019 05/31/2020 290B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 09/28/2019 10/18/2019 21B1364 Pre-Construction Meeting 10/19/2019 10/19/2019 1B1366 WASD Issues NTP (Pre-Const to NTP) 10/20/2019 12/03/2019 45B1369 WASD Issues NTP (PO to NTP) 10/12/2019 12/03/2019 53B1370 Construction NTP 12/04/2019 0B1390 Construction Operations 12/04/2019 05/31/2020 180B1395 Substantial Completion 05/31/2020 0

DesignerDesigner Construction Support Services 08/16/2019 05/31/2020 290B1397 Designer Construction Support Services 08/16/2019 05/31/2020 290

Project CProject Closeout 05/31/2020 09/28/2020 120B1425 Closeout Phase 05/31/2020 09/28/2020 120B1430 Issue SAC Letter 05/31/2020 0B1450 Final Release of Retainage - Construction Contract 05/31/2020 0B1460 Administrative Closeout 06/01/2020 09/28/2020 120B1470 Project Closed 09/28/2020 0

Basin 0331Basin 0331 09/25/2014 A 08/01/2018 1521

100054-2 B100054-2 Basin 0331 Infiltration/Inflow Study and Repairs 09/25/2014 A 05/16/2016 A 632InfiltratioInfiltration/Inflow 09/25/2014 A 05/13/2016 A 518

B1000 Infiltration/Inflow Phase 09/25/2014 A 05/13/2016 A 518Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 06/19/2015 A 212

B1005 SSES Phase 09/25/2014 A 06/19/2015 A 212B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 03/20/2015 A 06/04/2015 A 30B1040 Video Review 06/05/2015 A 06/19/2015 A 30

CIPP RepCIPP Repairs 09/17/2015 A 05/13/2016 A 49B1065 CIPP Phase 09/17/2015 A 05/13/2016 A 49B1080 Issue NTP for CIPP Repairs 09/17/2015 A 0B1090 Conduct CIPP Repairs 11/23/2015 A 05/13/2016 A 20

ManholeManhole Repairs 10/30/2015 A 03/10/2016 A 47B1115 Manhole Phase 10/30/2015 A 03/10/2016 A 47B1130 Issue NTP for Manhole Repairs 10/30/2015 A 0B1140 Conduct Manhole Repairs 03/07/2016 A 03/10/2016 A 20

Project CProject Closeout 05/16/2016 A 05/16/2016 A 0B1235 Closeout Phase 05/16/2016 A 05/16/2016 A 0B1260 Project Closed 05/16/2016 A 0

100222 Pu100222 Pump Station 0331 Upgrade 10/08/2014 A 08/01/2018 1415DesignDesign 10/08/2014 A 06/17/2016 A 515

B1000 Design Phase 10/08/2014 A 06/17/2016 A 515B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 10/08/2014 A 10/08/2014 A 5B1020 Engage Design Consultant 10/09/2014 A 02/02/2015 A 20B1030 Issue Design NTP 02/03/2015 A 0B1032 TA Rev 1 Approval Process 03/21/2016 A 05/12/2016 A 20

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Bidders Prepare Bids for SubmBids Submittal

MDWASD/PSIP Team Bids ERecommendation for Award Contract Award (Purchase O

05/31/2

ConstruMDWASD/PSIP Team PrePre-Construction Meeting

WASD Issues NTP (PreWASD Issues NTP (POConstruction NTP

ConstruSubstan05/31/2

Designe

Issue SAFinal Re

08/01/2018, Basin 0331

05/16/2016 A, 100054-2 Basin 0331 Infiltration/Inflow Study and Repairs05/13/2016 A, Infiltration/Inflow

Infiltration/Inflow Phase06/19/2015 A, Sanitary Sewer Evaluation SurveySSES Phase

Issue NTP to SSES ContractorConduct SSESVideo Review

05/13/2016 A, CIPP RepairsCIPP Phase

Issue NTP for CIPP RepairsConduct CIPP Repairs

03/10/2016 A, Manhole RepairsManhole Phase

Issue NTP for Manhole RepairsConduct Manhole Repairs

05/16/2016 A, Project CloseoutCloseout Phase

Project Closed08/01/2018, 100222 Pump Station 0331 Upgrade

06/17/2016 A, Design

Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book

Engage Design ConsultantIssue Design NTP

TA Rev 1 Approval Process

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 51 of 161 TASK filter: All Activities© Oracle Corporation

Page 52: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1040 A/E Develops and Submits Final Engineering Report 02/03/2015 A 05/04/2016 A 125B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 02/03/2015 A 03/09/2016 A 85

30% Des30% Design 02/03/2015 A 10/27/2015 A 251B1060 A/E Prepares 30% Construction Documents 02/03/2015 A 03/19/2015 A 30B1070 Geotechnical Engineering Services 02/03/2015 A 03/31/2015 A 20B1080 Surveying Services 02/03/2015 A 03/31/2015 A 15B1082 A/E & MDWASD/PSIP Team and Town of Miami Lakes Easeme 03/23/2015 A 07/21/2015 A 20B1084 A/E Prepares 30% Construction Documents (Resume Design) 07/22/2015 A 09/25/2015 A 11B1100 30% CDs Submittal 09/28/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 09/29/2015 A 10/27/2015 A 10

90% Des90% Design 09/29/2015 A 05/04/2016 A 220B1170 A/E Prepares 90% Construction Documents 09/29/2015 A 12/23/2015 A 26B1180 90% CDs Submittal 12/23/2015 A 0B1190 90% Review (MDWASD/PSIP Team) 12/24/2015 A 03/09/2016 A 10B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 03/09/2016 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 03/09/2016 A 03/14/2016 A 15B1240 90% Miami Lakes - BD Permit Submittal (Pump Station) 03/23/2016 A 0B1250 90% Miami Lakes - BD Permit Review (Pump Station) 03/23/2016 A 05/04/2016 A 15B1260 90% CD PM Comments Evaluation Completed 05/04/2016 A 0

100% De100% Design 05/05/2016 A 06/17/2016 A 29B1270 A/E Prepares 100% Construction Documents 05/05/2016 A 06/17/2016 A 11B1280 100% CDs Submittal 06/17/2016 A 0B1290 100% Review (MDWASD/PSIP Team) 05/05/2016 A 06/17/2016 A 10B1300 Design Completed 06/17/2016 A 0

MDWASDMDWASD Procurement 04/05/2016 A 07/12/2016 A 77B1305 Procurement Phase 04/05/2016 A 07/12/2016 A 77B1310 Submit CDs to MDWASD Procurement Division 04/05/2016 A 0B1312 Bid Notice Preparation Period 04/06/2016 A 04/14/2016 A 23B1314 Bid Notice 04/15/2016 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 04/18/2016 A 04/21/2016 A 10B1320 Pre-Bid Conference 04/22/2016 A 04/22/2016 A 1B1328 Bidders Prepare Bids for Submittal 04/25/2016 A 05/26/2016 A 15B1330 Bids Submittal 05/27/2016 A 0B1340 MDWASD/PSIP Team Bids Evaluation 05/30/2016 A 06/08/2016 A 15B1350 Recommendation for Award Letter 06/08/2016 A 0B1355 Contract Award (Purchase Order Approval) 06/09/2016 A 07/12/2016 A 10

ConstrucConstruction 04/22/2016 A 11/17/2017 A 915B1360 Construction Phase 04/22/2016 A 11/17/2017 A 915B1364 MDAD/PSIP Team Prepare for Pre-Construction Meeting 06/09/2016 A 07/07/2016 A 15B1365 Pre-Construction Meeting 07/08/2016 A 07/08/2016 A 1B1369 WASD Issues NTP (PO to NTP) 07/13/2016 A 07/31/2016 A 53B1370 Construction NTP 08/01/2016 A 0B1400 Construction Operations 08/01/2016 A 11/17/2017 A 278B1400 Original Construction Duration 08/01/2016 A 12/29/2016 A 278B1400 Change Order #1 - FPL 12/30/2016 A 02/14/2017 A 278B1400 Change Order #2 - Diving Plan Approval & Hurricane Irma 02/15/2017 A 05/06/2017 A 278B1400 Change Order #3 - FPL 05/07/2017 A 10/11/2017 A 278B1402 Substantial Completion 11/17/2017 A 0

DesignerDesigner Construction Support Services 04/22/2016 A 11/17/2017 A 263

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

10/27/2015 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services

A/E & MDWASD/PSIP Team and Town of Miami Lakes Easement NegotiationsA/E Prepares 30% Construction Documents (Resume Design)30% CDs Submittal

30% Review (MDWASD/PSIP Team)05/04/2016 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)90% RER(DERM)FDEP Permit Review (Pump Station)90% Miami Lakes - BD Permit Submittal (Pump Station)

90% Miami Lakes - BD Permit Review (Pump Station)90% CD PM Comments Evaluation Completed

06/17/2016 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed

07/12/2016 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)

11/17/2017 A, Construction

Construction PhaseMDAD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction MeetingWASD Issues NTP (PO to NTP)

Construction NTPConstruction Operations

Original Construction DurationChange Order #1 - FPL

Change Order #2 - Diving Plan Approval & Hurricane IrmaChange Order #3 - FPL

Substantial Completion11/17/2017 A, Designer Construction Support Services

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 52 of 161 TASK filter: All Activities© Oracle Corporation

Page 53: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1410 Designer Construction Support Services 04/22/2016 A 11/17/2017 A 263Project CProject Closeout 11/18/2017 A 08/01/2018 212

B1445 Closeout Phase 11/18/2017 A 08/01/2018 212B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 11/18/2017 A 08/01/2018 120B1490 Project Closed 08/01/2018 0

Basin 0334Basin 0334 06/02/2014 A 08/01/2018 1646

100056 FM100056 FM for Pump Station 0334 06/23/2014 A 05/21/2015 A 386100% De100% Design 07/10/2014 A 07/10/2014 A 0

B1290 Design Completed 07/10/2014 A 0MDWASDMDWASD Procurement 06/23/2014 A 10/02/2014 A 167

B1295 Procurement Phase 06/23/2014 A 10/02/2014 A 167B1300 Submit CDs to MDWASD Procurement Division 06/23/2014 A 0B1310 Pre-Bid Conference 07/15/2014 A 0B1320 Bids Submittal 09/03/2014 A 0B1330 MDWASD Bids Evaluation 09/04/2014 A 10/02/2014 A 10B1340 Contractor Selected 09/04/2014 A 0

ConstrucConstruction 10/03/2014 A 05/21/2015 A 173B1350 Construction Phase 10/03/2014 A 05/21/2015 A 173B1360 Construction NTP 02/02/2015 A 0B1370 Mobilization 02/02/2015 A 02/09/2015 A 40B1380 Permit Approvals 10/03/2014 A 02/01/2015 A 20B1390 Construction Operations 02/02/2015 A 05/20/2015 A 128B1392 Substantial Completion 05/20/2015 A 0

DesignerDesigner Construction Services 02/02/2015 A 05/21/2015 A 130B1400 Designer Construction Support Services 02/02/2015 A 05/21/2015 A 130

ConstrucConstruction Close Out 05/21/2015 A 05/21/2015 A 10B1420 Punch List 05/21/2015 A 05/21/2015 A 10

100057 Pu100057 Pump Station 0334 Upgrade 06/02/2014 A 08/01/2018 1646DesignDesign 06/17/2014 A 06/17/2014 A 0

B1250 Design Phase 06/17/2014 A 06/17/2014 A 0100% De100% Design 06/17/2014 A 06/17/2014 A 0

B1260 Design Completed 06/17/2014 A 0MDWASDMDWASD Procurement 06/02/2014 A 10/07/2014 A 112

B1265 Procurement Phase 06/02/2014 A 10/07/2014 A 112B1270 Submit CDs to MDWASD Procurement Division 06/02/2014 A 0B1280 Pre-Bid Conference 07/02/2014 A 0B1290 Bids Submittal 07/10/2014 A 0B1300 MDWASD Bid Evaluation 07/11/2014 A 08/14/2014 A 10B1310 Recommendation for Award Letter 08/14/2014 A 0B1460 Contract Award (Purchase Order Approval) 08/14/2014 A 10/07/2014 A 0

ConstrucConstruction 08/15/2014 A 10/31/2016 A 1416B1320 Construction Phase 08/15/2014 A 10/31/2016 A 1416B1328 WASD Issues NTP (PO to NTP) 10/08/2014 A 02/04/2015 A 53B1330 Construction NTP 02/05/2015 A 0B1340 Mobilization 02/05/2015 A 02/26/2015 A 40B1350 Permit Approvals 08/15/2014 A 02/26/2015 A 20B1360 Construction Operations 02/06/2015 A 12/30/2015 A 126

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Designer Construction Support Services08/01/2018, Project Closeout

Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction ContractAdministrative CloseoutProject Closed08/01/2018, Basin 0334

05/21/2015 A, 100056 FM for Pump Station 033407/10/2014 A, 100% Design

Design Completed10/02/2014 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Pre-Bid ConferenceBids Submittal

MDWASD Bids EvaluationContractor Selected

05/21/2015 A, Construction

Construction PhaseConstruction NTP

MobilizationPermit Approvals

Construction OperationsSubstantial Completion

05/21/2015 A, Designer Construction Services

Designer Construction Support Services05/21/2015 A, Construction Close Out

Punch List08/01/2018, 100057 Pump Station 0334 Upgrade

06/17/2014 A, Design

Design Phase06/17/2014 A, 100% Design

Design Completed10/07/2014 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Pre-Bid ConferenceBids Submittal

MDWASD Bid EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)

10/31/2016 A, Construction

Construction PhaseWASD Issues NTP (PO to NTP)

Construction NTPMobilization

Permit ApprovalsConstruction Operations

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 53 of 161 TASK filter: All Activities© Oracle Corporation

Page 54: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1360 Original Construction Duration 02/06/2015 A 08/04/2015 A 126B1360 Change Order #1 - Shop Drawing Approval 08/05/2015 A 11/06/2015 A 126B1360 Change Order #2 - Sheet Pilling, FPL, Weather 11/07/2015 A 12/24/2015 A 126B1362 Substantial Completion 12/30/2015 A 0

DesignerDesigner Construction Support Services 02/05/2015 A 10/31/2016 A 130B1370 Designer Construction Support Services 02/05/2015 A 10/31/2016 A 130

ConstrucConstruction Close Out 12/31/2015 A 10/31/2016 A 15B1380 Commissioning 12/31/2015 A 02/29/2016 A 15B1390 Punch List 12/31/2015 A 10/31/2016 A 10

Project CProject Closeout 12/31/2015 A 08/01/2018 944B1405 Closeout Phase 12/31/2015 A 08/01/2018 944B1410 Issue SAC Letter 02/11/2016 A 0B1430 Final Release of Retainage - Construction Contract 08/01/2018 0B1440 Administrative Closeout 12/31/2015 A 08/01/2018 120B1450 Project Closed 08/01/2018 0

100055 Ba100055 Basin 0334 Infiltration/Inflow Study and Repairs 04/17/2015 A 11/12/2015 A 412InfiltratioInfiltration/Inflow 04/17/2015 A 11/11/2015 A 345

B1000 Infiltration/Inflow Phase 04/17/2015 A 11/11/2015 A 345CIPP RepCIPP Repairs 04/17/2015 A 07/22/2015 A 86

B1070 CIPP Phase 04/17/2015 A 07/22/2015 A 86B1090 Issue NTP for CIPP Repairs 04/17/2015 A 0B1100 Conduct CIPP Repairs 06/15/2015 A 07/22/2015 A 86

ManholeManhole Repairs 10/02/2015 A 11/11/2015 A 117B1110 Manhole Phase 10/02/2015 A 11/11/2015 A 117B1130 Issue NTP for Manhole Repairs 10/02/2015 A 0B1140 Conduct Manhole Repairs 11/11/2015 A 11/11/2015 A 117

Dig & ReDig & Replace Repairs 05/18/2015 A 10/07/2015 A 30B1160 Dig & Replace Phase 05/18/2015 A 10/07/2015 A 30B1180 Issue NTP for Dig & Replace Repairs 05/18/2015 A 0B1190 Conduct Dig & Replace Repairs 10/07/2015 A 10/07/2015 A 30

Project CProject Closeout 11/12/2015 A 11/12/2015 A 0B1250 Closeout Phase 11/12/2015 A 11/12/2015 A 0B1280 Project Closed 11/12/2015 A 0

New EPS-New EPS-3 08/01/2018 09/28/2020 790

100261 Pu100261 Pump Station 0335 Upgrade 08/01/2018 09/28/2020 790DesignDesign 08/01/2018 06/29/2019 333

B1000 Design Phase 08/01/2018 06/29/2019 333B1005 Prepare and Submit Design Package 08/01/2018 08/07/2018 7B1010 Engage Design Consultant 08/08/2018 09/04/2018 28B1012 TA Preparation 09/05/2018 09/18/2018 14B1014 TA Approval 09/19/2018 10/28/2018 40B1030 Issue Design NTP 10/29/2018 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/29/2018 06/01/2019 216

30% Des30% Design 10/29/2018 01/16/2019 80B1060 A/E Prepares 30% Construction Documents 10/29/2018 12/17/2018 50B1100 30% CDs Submittal 12/17/2018 0B1120 30% Review (MDWASD/PSIP Team) 12/18/2018 01/16/2019 30

60% Des60% Design 12/18/2018 01/30/2019 44B1130 A/E Prepares 60% Construction Documents 12/18/2018 01/16/2019 30

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Original Construction DurationChange Order #1 - Shop Drawing Approval

Change Order #2 - Sheet Pilling, FPL, Weather

Substantial Completion10/31/2016 A, Designer Construction Support Services

Designer Construction Support Services10/31/2016 A, Construction Close Out

CommissioningPunch List

08/01/2018, Project Closeout

Closeout PhaseIssue SAC Letter

Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed

11/12/2015 A, 100055 Basin 0334 Infiltration/Inflow Study and Repairs11/11/2015 A, Infiltration/InflowInfiltration/Inflow Phase

07/22/2015 A, CIPP RepairsCIPP Phase

Issue NTP for CIPP RepairsConduct CIPP Repairs

11/11/2015 A, Manhole RepairsManhole Phase

Issue NTP for Manhole RepairsConduct Manhole Repairs

10/07/2015 A, Dig & Replace RepairsDig & Replace Phase

Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs

11/12/2015 A, Project CloseoutCloseout Phase

Project Closed

06/29/2019, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA ApprovalIssue Design NTP

Final Engineering Report Review & Ap01/16/2019, 30% Design

A/E Prepares 30% Construction Documents30% CDs Submittal

30% Review (MDWASD/PSIP Team)01/30/2019, 60% Design

A/E Prepares 60% Construction Documents

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 54 of 161 TASK filter: All Activities© Oracle Corporation

Page 55: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1140 60% CDs Submittal 01/16/2019 0B1160 60% Review (MDWASD/PSIP Team) 01/17/2019 01/30/2019 14

90% Des90% Design 01/17/2019 06/01/2019 136B1170 A/E Prepares 90% Construction Documents 01/17/2019 02/25/2019 40B1180 90% CDs Submittal 02/25/2019 0B1190 90% Review (MDWASD/PSIP Team) 02/26/2019 03/27/2019 30B1200 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 03/28/2019 0B1210 90% RER(DERM)/FDEP Permit Review (Pump Station) 03/28/2019 05/11/2019 45B1220 90% RER (Building Dept Permit Submittal (Pump Station) 05/12/2019 0B1230 90% RER (Building Dept) Permit Review (Pump Station) 05/12/2019 06/01/2019 21B1240 90% PWWMD Permit Submittal (Pump Station) 05/12/2019 0B1250 90% PWWMD Permit Review (Pump Station) 05/12/2019 06/01/2019 21B1260 90% CD PM Comments Evaluation Completed 06/01/2019 0

100% De100% Design 06/02/2019 06/29/2019 28B1270 A/E Prepares 100% Construction Documents 06/02/2019 06/15/2019 14B1280 100% CDs Submittal 06/15/2019 0B1290 100% Review (MDWASD/PSIP Team) 06/16/2019 06/29/2019 14B1300 Design Completed 06/29/2019 0

MDWASDMDWASD Procurement 06/29/2019 10/11/2019 104B1305 Procurement Phase 06/29/2019 10/11/2019 104B1310 Submit CDs to MDWASD Procurement Division 06/29/2019 0B1312 Bid Notice Preparation Period 06/30/2019 08/01/2019 33B1314 Bid Notice 08/01/2019 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conferencce 08/02/2019 08/15/2019 14B1320 Pre-Bid Conference 08/16/2019 08/16/2019 1B1328 Bidders Prepare Bids for Submittal 08/17/2019 09/06/2019 21B1330 Bids Submittal 09/06/2019 0B1340 MDWASD/PSIP Team Bids Evaluation 09/07/2019 09/27/2019 21B1350 Recommendation for Award Letter 09/27/2019 0B1355 Contract Award (Purchase Order Approval) 09/28/2019 10/11/2019 14

ConstrucConstruction 08/16/2019 05/31/2020 290B1357 Construction Phase 08/16/2019 05/31/2020 290B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 09/28/2019 10/18/2019 21B1364 Pre-Construction Meeting 10/19/2019 10/19/2019 1B1366 WASD Issues NTP (Pre-Const to NTP) 10/20/2019 12/03/2019 45B1369 WASD Issues NTP (PO to NTP) 10/12/2019 12/03/2019 53B1370 Construction NTP 12/04/2019 0B1390 Construction Operations 12/04/2019 05/31/2020 180B1395 Substantial Completion 05/31/2020 0

DesignerDesigner Construction Support Services 08/16/2019 05/31/2020 290B1397 Designer Construction Support Services 08/16/2019 05/31/2020 290

Project CProject Closeout 05/31/2020 09/28/2020 120B1425 Closeout Phase 05/31/2020 09/28/2020 120B1430 Issue SAC Letter 05/31/2020 0B1450 Final Release of Retainage - Construction Contract 05/31/2020 0B1460 Administrative Closeout 06/01/2020 09/28/2020 120B1470 Project Closed 09/28/2020 0

Basin 0336Basin 0336 09/25/2014 A 01/11/2019 1322

100058 Pu100058 Pump Station 0336 Upgrade 01/11/2016 A 01/11/2019 1106

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

60% CDs Submittal60% Review (MDWASD/PSIP Team)

06/01/2019, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)/FDEP Permit Submittal (P

90% RER(DERM)/FDEP Permit Review 90% RER (Building Dept Permit Submit

90% RER (Building Dept) Permit Revie90% PWWMD Permit Submittal (Pump

90% PWWMD Permit Review (Pump 90% CD PM Comments Evaluation C

06/29/2019, 100% Design

A/E Prepares 100% Construction Do100% CDs Submittal100% Review (MDWASD/PSIP TeamDesign Completed

10/11/2019, MDWASD Pro

Procurement PhaseSubmit CDs to MDWASD Procurem

Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare Pre-Bid Conference

Bidders Prepare Bids for SubmBids Submittal

MDWASD/PSIP Team Bids ERecommendation for Award Contract Award (Purchase O

05/31/2

ConstruMDWASD/PSIP Team PrePre-Construction Meeting

WASD Issues NTP (PreWASD Issues NTP (POConstruction NTP

ConstruSubstan05/31/2

Designe

Issue SAFinal Re

01/11/2019, Basin 0336

01/11/2019, 100058 Pump Station 0336 Upgrad

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 55 of 161 TASK filter: All Activities© Oracle Corporation

Page 56: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

DesignDesign 01/11/2016 A 08/16/2017 A 591B1000 Design Phase 01/11/2016 A 08/16/2017 A 591B1010 Prepare and Submit Design Package 01/11/2016 A 01/11/2016 A 5B1020 Engage Design Consultant 01/11/2016 A 01/22/2016 A 20B1022 TA Preparation 01/25/2016 A 01/25/2016 A 1B1024 TA Approval Process 01/26/2016 A 04/04/2016 A 20B1030 Issue Design NTP 04/26/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 04/26/2016 A 11/07/2016 A 85

30% Des30% Design 04/27/2016 A 06/16/2016 A 46B1060 A/E Prepares 30% Construction Documents 04/27/2016 A 04/29/2016 A 30B1070 Geotechnical Engineering Services 04/27/2016 A 04/29/2016 A 20B1080 Surveying Services 04/27/2016 A 04/29/2016 A 15B1100 30% CDs Submittal 04/29/2016 A 0B1120 30% Review (MDWASD/PSIP Team) 05/02/2016 A 06/16/2016 A 10

90% Des90% Design 05/02/2016 A 06/28/2017 A 457B1170 A/E Prepares 90% Construction Documents 05/02/2016 A 09/19/2016 A 20B1180 90% CDs Submittal 09/19/2016 A 0B1190 90% Review (MDWASD/PSIP Team) 09/20/2016 A 11/07/2016 A 15B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 03/10/2017 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 03/01/2017 A 05/30/2017 A 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 05/30/2017 A 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 05/30/2017 A 05/31/2017 A 21B1240 90% Miami Lakes - BD Permit Submittal (Pump Station) 06/05/2017 A 0B1250 90% Miami Lakes - BD Permit Review (Pump Station) 06/05/2017 A 06/28/2017 A 21B1260 90% CD PM Comments Evaluation Completed 06/28/2017 A 0B1262 MDWASD Union Concurrence Process 04/26/2017 A 06/20/2017 A 30

100% De100% Design 06/29/2017 A 08/16/2017 A 44B1270 A/E Prepares 100% Construction Documents 06/29/2017 A 08/14/2017 A 10B1280 100% CDs Submittal 08/14/2017 A 0B1290 100% Review (MDWASD/PSIP Team) 08/14/2017 A 08/16/2017 A 10B1300 Design Completed 08/16/2017 A 0

MDWASDMDWASD Procurement 08/16/2017 A 12/19/2017 A 112B1305 Procurement Phase 08/16/2017 A 12/19/2017 A 112B1310 Submit CDs to MDWASD Procurement Division 08/16/2017 A 0B1312 Bid Notice Preparation Period 08/17/2017 A 08/23/2017 A 33B1314 Bid Notice 08/23/2017 A 0B1316 MDADWAD/PSIP Team Prepare for Pre-Bid Conference 08/24/2017 A 09/26/2017 A 14B1320 Pre-Bid Conference 09/27/2017 A 09/27/2017 A 1B1328 Bidders Prepare Bids for Submittal 09/28/2017 A 10/30/2017 A 21B1330 Bids Submittal 10/31/2017 A 0B1340 MDWASD/PSIP Team Bids Evaluation 11/01/2017 A 11/14/2017 A 21B1350 Recommendation for Award Letter 11/14/2017 A 0B1355 Contract Award (Purchase Order Approval) 11/15/2017 A 12/19/2017 A 14

ConstrucConstruction 09/27/2017 A 09/13/2018 468B1360 Construction Phase 09/27/2017 A 09/13/2018 468B1364 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 11/15/2017 A 01/18/2018 A 21B1366 Pre-Construction Meeting 01/19/2018 A 01/19/2018 A 1B1368 WASD Issues NTP (Pre-Const to NTP) 01/20/2018 A 04/15/2018 A 45B1369 WASD Issues NTP (PO to NTP) 12/19/2017 A 04/15/2018 A 53

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

08/16/2017 A, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval ProcessIssue Design NTP

Final Engineering Report Review & Approval (MDWASD/PSIP Team)06/16/2016 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services

30% CDs Submittal30% Review (MDWASD/PSIP Team)

06/28/2017 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)

90% RER(DERM)FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)90% RER(Building Dept) Permit Review (Pump Station)

90% Miami Lakes - BD Permit Submittal (Pump Station)90% Miami Lakes - BD Permit Review (Pump Station)

90% CD PM Comments Evaluation CompletedMDWASD Union Concurrence Process

08/16/2017 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal

100% Review (MDWASD/PSIP Team)Design Completed

12/19/2017 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation Period

Bid NoticeMDADWAD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter

Contract Award (Purchase Order Approval)09/13/2018, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 56 of 161 TASK filter: All Activities© Oracle Corporation

Page 57: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1370 Construction NTP 04/16/2018 A 0B1400 Construction Operations 04/16/2018 A 09/13/2018 149B1402 Substantial Completion 09/13/2018 0

DesignerDesigner Construction Support Services 09/27/2017 A 09/13/2018 290B1410 Designer Construction Support Services 09/27/2017 A 09/13/2018 290

Project CProject Closeout 11/13/2017 A 01/11/2019 162B1445 Closeout Phase 11/13/2017 A 01/11/2019 162B1450 Issue SAC Letter 11/13/2017 A 0B1470 Final Release of Retainage - Construction Contract 09/13/2018 0B1480 Administrative Closeout 09/14/2018 01/11/2019 120B1490 Project Closed 01/11/2019 0

100200 Ba100200 Basin 0336 Infiltration/Inflow Study and Repairs 09/25/2014 A 07/29/2015 A 336InfiltratioInfiltration/Inflow 09/25/2014 A 07/28/2015 A 61

B1000 Infiltration/Inflow Phase 09/25/2014 A 07/28/2015 A 61Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 07/28/2015 A 61

B1005 SSES Phase 09/25/2014 A 07/28/2015 A 61B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 07/10/2015 A 07/28/2015 A 30

Project CProject Closeout 07/29/2015 A 07/29/2015 A 0B1235 Closeout Phase 07/29/2015 A 07/29/2015 A 0B1260 Project Closed 07/29/2015 A 0

Basin 0356Basin 0356 09/05/2014 A 02/20/2019 1614

100219 Pu100219 Pump Station 0356 Upgrade 09/05/2014 A 02/20/2019 1614DesignDesign 09/05/2014 A 01/12/2016 A 378

B1000 Design Phase 09/05/2014 A 01/12/2016 A 378B1010 Prepare and Submit Design Package 09/05/2014 A 09/10/2014 A 5B1020 Engage Design Consultant 09/05/2014 A 11/04/2014 A 20B1022 TA Approval Process 11/05/2014 A 01/12/2015 A 20B1030 Issue Design NTP 02/02/2015 A 0B1032 Engage Design Consultant for TA Rev 1 07/03/2015 A 07/23/2015 A 20B1034 TA Rev 1 Approval Process 07/24/2015 A 07/31/2015 A 20B1036 Issue Design NTP for TA Rev 1 08/05/2015 A 0B1040 A/E Develops and Submits Final Engineering Report 02/02/2015 A 01/12/2016 A 125B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 02/02/2015 A 08/05/2015 A 85

30% Des30% Design 02/03/2015 A 06/01/2015 A 52B1060 A/E Prepares 30% Construction Documents 02/03/2015 A 03/02/2015 A 30B1070 Geotechnical Engineering Services 02/03/2015 A 02/18/2015 A 20B1080 Surveying Services 02/03/2015 A 02/18/2015 A 15B1100 30% CDs Submittal 03/02/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 03/03/2015 A 06/01/2015 A 10

90% Des90% Design 03/03/2015 A 01/12/2016 A 217B1170 A/E Prepares 90% Construction Documents 03/03/2015 A 07/02/2015 A 20B1180 90% CDs Submittal 07/02/2015 A 0B1190 90% Review (MDWASD/PSIP Team) 07/03/2015 A 10/16/2015 A 15B1192 A/E Incorporates TA Rev 1 - 30%, 90% & 100% Revisions 08/05/2015 A 10/16/2015 A 64B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 10/19/2015 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 10/20/2015 A 12/21/2015 A 15B1220 90% PWWMD Permit Submittal (Pump Station) 11/02/2015 A 0B1230 90% PWWMD Permit Review (Pump Station) 11/03/2015 A 11/03/2015 A 15

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Construction NTPConstruction OperationsSubstantial Completion09/13/2018, Designer Construction Support Services

Designer Construction Support Services01/11/2019, Project Closeout

Closeout PhaseIssue SAC Letter

Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed

07/29/2015 A, 100200 Basin 0336 Infiltration/Inflow Study and Repairs07/28/2015 A, Infiltration/Inflow

Infiltration/Inflow Phase07/28/2015 A, Sanitary Sewer Evaluation SurveySSES Phase

Issue NTP to SSES ContractorConduct SSES

07/29/2015 A, Project CloseoutCloseout Phase

Project Closed02/20/2019, Basin 0356

02/20/2019, 100219 Pump Station 0356 Upg01/12/2016 A, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Approval Process

Issue Design NTPEngage Design Consultant for TA Rev 1

TA Rev 1 Approval ProcessIssue Design NTP for TA Rev 1

A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

06/01/2015 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services

30% CDs Submittal30% Review (MDWASD/PSIP Team)

01/12/2016 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)A/E Incorporates TA Rev 1 - 30%, 90% & 100% Revisions

90% RER(DERM)FDEP Permit Submittal (Pump Station)90% RER(DERM)FDEP Permit Review (Pump Station)

90% PWWMD Permit Submittal (Pump Station)90% PWWMD Permit Review (Pump Station)

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 57 of 161 TASK filter: All Activities© Oracle Corporation

Page 58: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1240 90% RER (Building Dept) Permit Submittal (Pump Station) 12/29/2015 A 0B1250 90% RER (Building Dept) Permit Review (Pump Station) 12/30/2015 A 01/12/2016 A 15B1260 90% CD PM Comments Evaluation Completed 01/12/2016 A 0

100% De100% Design 01/08/2016 A 01/12/2016 A 24B1270 A/E Prepares 100% Construction Documents 01/12/2016 A 01/12/2016 A 10B1280 100% CDs Submittal 01/12/2016 A 0B1290 100% Review (MDWASD/PSIP Team) 01/12/2016 A 01/12/2016 A 10B1300 Design Completed 01/08/2016 A 0

MDWASDMDWASD Procurement 01/08/2016 A 12/28/2018 1051B1305 Procurement Phase 01/08/2016 A 12/28/2018 1051B1310 Submit CDs to MDWASD Procurement Division 01/08/2016 A 0B1312 Bid Notice Preparation Period 01/08/2016 A 01/08/2016 A 23B1314 Bid Notice 01/08/2016 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 01/11/2016 A 02/10/2016 A 10B1320 Pre-Bid Conference 02/11/2016 A 02/11/2016 A 1B1328 Bidders Prepare Bids for Submittal 02/12/2016 A 03/28/2016 A 15B1330 Bids Submittal 03/28/2016 A 0B1340 MDWASD/PSIP Team Bids Evaluation 03/29/2016 A 04/01/2016 A 15B1350 Recommendation for Award Letter 04/01/2016 A 0B1355 Contract Award (Purchase Order Approval) 04/04/2016 A 05/05/2016 A 10B1355 Submit CDs to MDWASD Procurement Division 09/15/2018 0B1355 Bid Notice Preparation Period 09/16/2018 10/18/2018 33B1355 Bid Notice 10/18/2018 0B1355 MDWASD/PSIP Team Prepare for Pre-Bid Conference 10/19/2018 11/01/2018 14B1355 Pre-Bid Conference 11/02/2018 11/02/2018 1B1355 Bidders Prepare Bids for Submittal 11/03/2018 11/23/2018 21B1355 Bids Submittal 11/23/2018 0B1355 MDWASD/PSIP Team Bids Evaluation 11/24/2018 12/14/2018 21B1355 Recommendation for Award Letter 12/14/2018 0B1355 Contract Award (Purchase Order Approval) 12/15/2018 12/28/2018 14

ConstrucConstruction 04/04/2016 A 02/20/2019 1144B1360 Construction Phase 04/04/2016 A 02/19/2019 1144B1364 MDAD/PSIP Team Prepare for Pre-Construction Meeting 04/04/2016 A 04/26/2016 A 15B1365 Pre-Construction Meeting 04/29/2016 A 04/29/2016 A 1B1370 Construction NTP 06/06/2016 A 0B1400 Construction Operations 06/06/2016 A 01/20/2017 A 186B1400 WASD Terminate Contract 01/20/2017 A 01/20/2017 A 1B1400 WASD/PSIP Team Re-Package Resolution Period 01/23/2017 A 08/29/2017 A 219B1400 Finalize Project Closeout with Maxon Groupe (Contractor) 08/30/2017 A 08/01/2018 275B1400 A/E Prepared SOW to Re-Package Contract Documents 08/30/2017 A 05/08/2018 A 215B1400 TA Approval Process 05/09/2018 A 08/01/2018 40B1400 A/E Re-Package Contract Documents 08/02/2018 09/15/2018 45B1400 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 12/15/2018 01/04/2019 21B1400 Pre-Construction Meeting 01/05/2019 01/05/2019 1B1400 WASD Issues NTP (Pre-Const to NTP) 01/06/2019 02/19/2019 45B1400 WASD Issues NTP (PO to NTP) 12/29/2018 02/19/2019 53B1400 Construction NTP 02/20/2019 0B1402 Substantial Completion 08/01/2018 0

DesignerDesigner Construction Support Services 06/06/2016 A 08/01/2018 180

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

90% RER (Building Dept) Permit Submittal (Pump Station)90% RER (Building Dept) Permit Review (Pump Station)90% CD PM Comments Evaluation Completed01/12/2016 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed

12/28/2018, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid Notice

MDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter

Contract Award (Purchase Order Approval)Submit CDs to MDWASD Procurement Division

Bid Notice Preparation Period

Bid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for Submittal

Bids SubmittalMDWASD/PSIP Team Bids Evaluation

Recommendation for Award LetterContract Award (Purchase Order Approval)

02/20/2019, Construction

Construction PhaseMDAD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

Construction NTPConstruction Operations

WASD Terminate ContractWASD/PSIP Team Re-Package Resolution Period

Finalize Project Closeout with Maxon Groupe (Contractor)A/E Prepared SOW to Re-Package Contract Documents

TA Approval ProcessA/E Re-Package Contract Documents

MDWASD/PSIP Team Prepare for Pre-ConstructioPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Construction NTPSubstantial Completion08/01/2018, Designer Construction Support Services

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 58 of 161 TASK filter: All Activities© Oracle Corporation

Page 59: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1410 Designer Construction Support Services 06/06/2016 A 08/01/2018 180Project CProject Closeout 08/01/2018 11/28/2018 120

B1445 Closeout Phase 08/01/2018 11/28/2018 120B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 08/01/2018 11/28/2018 120B1490 Project Closed 11/28/2018 0

Basin 0369Basin 0369 05/01/2014 A 04/28/2017 A 1095

100060 Pu100060 Pump Station 0369 Upgrade 05/01/2014 A 04/28/2017 A 1095PlanningPlanning 05/01/2014 A 01/09/2017 A 19

B0900 Planning Phase 05/01/2014 A 01/09/2017 A 19B0940 Develop Remedial Action Plan (RAP) 05/01/2014 A 05/19/2014 A 7B0950 Develop Preliminary Engineering Report (PER) 01/05/2015 A 10/26/2015 A 10B0960 Recommended Action Memo (RAM) 08/10/2016 A 01/09/2017 A 10

Project CProject Closeout 02/14/2017 A 04/28/2017 A 87B1445 Closeout Phase 02/14/2017 A 04/28/2017 A 87B1450 Issue SAC Letter 02/14/2017 A 0B1480 Administrative Closeout 04/03/2017 A 04/28/2017 A 30B1490 Project Closed 04/28/2017 A 0

Basin 0386Basin 0386 04/07/2014 A 04/28/2017 A 1085

100062 Pu100062 Pump Station 0386 Upgrade 04/07/2014 A 04/28/2017 A 1085PlanningPlanning 04/07/2014 A 01/09/2017 A 19

B0900 Planning Phase 04/07/2014 A 01/09/2017 A 19B0940 Develop Remedial Action Plan (RAP) 04/07/2014 A 05/20/2014 A 7B0960 Recommended Action Memo (RAM) 05/25/2016 A 01/09/2017 A 10

Project CProject Closeout 01/10/2017 A 04/28/2017 A 77B1445 Closeout Phase 01/10/2017 A 04/28/2017 A 77B1450 Issue SAC Letter 02/14/2017 A 0B1480 Administrative Closeout 01/10/2017 A 04/28/2017 A 30B1490 Project Closed 04/28/2017 A 0

Basin 0394Basin 0394 04/06/2015 A 08/01/2018 1247

100064 FM100064 FM for Pump Station 0394 04/06/2015 A 08/01/2018 1247DesignDesign 04/06/2015 A 06/21/2016 A 396

B1000 Design Phase 04/06/2015 A 06/21/2016 A 396B1010 Prepare and Submit Design Package 04/06/2015 A 04/08/2015 A 5B1020 Engage Design Consultant 04/09/2015 A 07/16/2015 A 20B1025 TA Approval Process 07/17/2015 A 08/07/2015 A 20B1030 Issue Design NTP 08/07/2015 A 0B1040 A/E Develops and Submits Final Engineering Report 08/07/2015 A 05/16/2016 A 125B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 08/07/2015 A 05/17/2016 A 125

30% Des30% Design 08/07/2015 A 02/12/2016 A 214B1060 A/E Prepares 30% Construction Documents 08/07/2015 A 02/01/2016 A 30B1070 Geotechnical Engineering Services 08/07/2015 A 11/20/2015 A 20B1080 Surveying Services 08/07/2015 A 11/20/2015 A 15B1100 30% CDs Submittal 02/01/2016 A 0B1120 30% Review (MDWASD/PSIP Team) 02/02/2016 A 02/12/2016 A 10

60% Des60% Design 02/02/2016 A 04/06/2016 A 29B1140 A/E Prepares 60% Construction Documents 02/02/2016 A 03/24/2016 A 20

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Designer Construction Support Services11/28/2018, Project Closeout

Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction Contract

Administrative CloseoutProject Closed

04/28/2017 A, Basin 0369

04/28/2017 A, 100060 Pump Station 0369 Upgrade01/09/2017 A, PlanningPlanning Phase

Develop Remedial Action Plan (RAP)Develop Preliminary Engineering Report (PER)

Recommended Action Memo (RAM)04/28/2017 A, Project CloseoutCloseout Phase

Issue SAC LetterAdministrative Closeout

Project Closed04/28/2017 A, Basin 0386

04/28/2017 A, 100062 Pump Station 0386 Upgrade01/09/2017 A, PlanningPlanning Phase

Develop Remedial Action Plan (RAP)Recommended Action Memo (RAM)

04/28/2017 A, Project CloseoutCloseout Phase

Issue SAC LetterAdministrative Closeout

Project Closed08/01/2018, Basin 0394

08/01/2018, 100064 FM for Pump Station 039406/21/2016 A, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Approval ProcessIssue Design NTP

A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

02/12/2016 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services

30% CDs Submittal30% Review (MDWASD/PSIP Team)

04/06/2016 A, 60% Design

A/E Prepares 60% Construction Documents

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 59 of 161 TASK filter: All Activities© Oracle Corporation

Page 60: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1150 60% CDs Submittal 03/24/2016 A 0B1170 60% Review (MDWASD/PSIP Team) 03/25/2016 A 04/06/2016 A 10

90% Des90% Design 03/25/2016 A 05/17/2016 A 82B1180 A/E Prepares 90% Construction Documents 03/25/2016 A 05/06/2016 A 20B1190 90% CDs Submittal 05/06/2016 A 0B1200 90% Review (MDWASD/PSIP Team) 05/09/2016 A 05/17/2016 A 15B1230 90% RER(DERM)FDEP Permit Submittal (Force Main) 04/07/2016 A 0B1240 90% RER(DERM)FDEP Permit Review (Force Main) 04/07/2016 A 05/16/2016 A 15B1242 90% PWWMD Permit Submittal (Force Main) 04/07/2016 A 0B1244 90% PWWMD Permit Review (Force Main) 04/07/2016 A 04/08/2016 A 15B1290 90% CD PM Comments Evaluation Completed 05/16/2016 A 0

100% De100% Design 05/17/2016 A 06/21/2016 A 26B1300 A/E Prepares 100% Construction Documents 05/17/2016 A 05/18/2016 A 10B1310 100% CDs Submittal 05/19/2016 A 0B1320 100% Review (MDWASD/PSIP Team) 05/20/2016 A 06/20/2016 A 10B1330 Design Completed 06/21/2016 A 0

MDWASDMDWASD Procurement 05/18/2016 A 08/09/2016 A 54B1335 Procurement Phase 05/18/2016 A 08/09/2016 A 54B1340 Submit CDs to MDWASD Procurement Division 05/18/2016 A 0B1342 Bid Notice Preparation Period 05/19/2016 A 05/19/2016 A 23B1344 Bid Notice 05/19/2016 A 0B1346 MDWASD/PSIP Team Prepare for Pre-Bid Conference 05/20/2016 A 05/26/2016 A 10B1350 Pre-Bid Conference 05/27/2016 A 05/27/2016 A 1B1358 Bidders Prepare Bids for Submittal 05/30/2016 A 06/29/2016 A 15B1360 Bids Submittal 06/29/2016 A 0B1370 MDWASD/PSIP Team Bids Evaluation 06/30/2016 A 07/07/2016 A 15B1380 Recommendation for Award Letter 07/07/2016 A 0B1385 Contract Award (Purchase Order Approval) 07/08/2016 A 08/09/2016 A 10

ConstrucConstruction 05/27/2016 A 01/11/2017 A 897B1390 Construction Phase 05/27/2016 A 01/11/2017 A 897B1394 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 07/08/2016 A 07/18/2016 A 15B1396 Pre-Construction Meeting 07/19/2016 A 07/19/2016 A 1B1398 WASD Issues NTP (PO to NTP) 08/10/2016 A 08/28/2016 A 53B1400 Construction NTP 08/29/2016 A 0B1430 Construction Operations 08/29/2016 A 01/06/2017 A 99B1430 Original Construction Duration 08/29/2016 A 12/07/2016 A 99B1430 Change Order #1 - Hurricane Mathew Preparation 12/08/2016 A 12/12/2016 A 99B1430 Change Order #4 - Additional Scope 12/13/2016 A 01/11/2017 A 99B1432 Substantial Completion 01/06/2017 A 0

DesignerDesigner Construction Support Services 05/27/2016 A 01/06/2017 A 275B1440 Designer Construction Support Services 05/27/2016 A 01/06/2017 A 275

Project CProject Closeout 01/09/2017 A 08/01/2018 570B1475 Closeout Phase 01/09/2017 A 08/01/2018 570B1480 Issue SAC Letter 08/01/2018 0B1500 Final Release of Retainage - Construction Contract 08/01/2018 0B1510 Administrative Closeout 01/09/2017 A 08/01/2018 120B1520 Project Closed 08/01/2018 0

100065 Pu100065 Pump Station 0394(AM) Upgrade 09/02/2015 A 08/01/2018 1205DesignDesign 11/30/2015 A 11/30/2015 A 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

60% CDs Submittal60% Review (MDWASD/PSIP Team)

05/17/2016 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Force Main)90% RER(DERM)FDEP Permit Review (Force Main)

90% PWWMD Permit Submittal (Force Main)90% PWWMD Permit Review (Force Main)

90% CD PM Comments Evaluation Completed06/21/2016 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal

100% Review (MDWASD/PSIP Team)Design Completed08/09/2016 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid Notice

MDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter

Contract Award (Purchase Order Approval)01/11/2017 A, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

WASD Issues NTP (PO to NTP)Construction NTP

Construction OperationsOriginal Construction DurationChange Order #1 - Hurricane Mathew Preparation

Change Order #4 - Additional Scope

Substantial Completion01/06/2017 A, Designer Construction Support Services

Designer Construction Support Services08/01/2018, Project Closeout

Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction ContractAdministrative CloseoutProject Closed08/01/2018, 100065 Pump Station 0394(AM) Upgrade

11/30/2015 A, Design

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 60 of 161 TASK filter: All Activities© Oracle Corporation

Page 61: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1000 Design Phase 11/30/2015 A 11/30/2015 A 0100% De100% Design 11/30/2015 A 11/30/2015 A 0

B1260 Design Completed 11/30/2015 A 0MDWASDMDWASD Procurement 09/02/2015 A 12/09/2015 A 337

B1265 Procurement Phase 09/02/2015 A 12/09/2015 A 337B1270 Submit CDs to MDWASD Procurement Division 09/02/2015 A 0B1274 Bid Notice Preparation Period 09/02/2015 A 09/14/2015 A 23B1276 Bid Notice 09/15/2015 A 0B1278 MDWASD/PSIP Team Prepare for Pre-Bid Conference 09/16/2015 A 09/24/2015 A 10B1280 Pre-Bid Conference 09/25/2015 A 09/25/2015 A 1B1282 Bidders Prepare Bids for Submittal 09/28/2015 A 10/23/2015 A 15B1290 Bids Submittal 10/26/2015 A 0B1300 MDWASD/PSIP Team Bids Evaluation 10/26/2015 A 10/29/2015 A 15B1310 Recommendation for Award Letter 10/29/2015 A 0B1315 Contract Award (Purchase Order Approval) 10/30/2015 A 12/09/2015 A 10

ConstrucConstruction 09/25/2015 A 06/09/2016 A 1114B1320 Construction Phase 09/25/2015 A 06/09/2016 A 1114B1324 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 10/30/2015 A 01/07/2016 A 15B1326 Pre- Construction Meeting 01/08/2016 A 01/08/2016 A 1B1328 WASD Issues NTP (PO to NTP) 12/10/2015 A 01/10/2016 A 53B1330 Construction NTP 01/11/2016 A 0B1360 Construction Operations 01/11/2016 A 05/19/2016 A 120B1360 Original Construction Duration 01/11/2016 A 05/10/2016 A 120B1360 Change Order #1 - Rejected HOMA Pumps 05/11/2016 A 06/09/2016 A 120B1362 Substantial Completion 05/19/2016 A 0

DesignerDesigner Construction Support Services 09/25/2015 A 05/19/2016 A 192B1370 Designer Construction Support Services 09/25/2015 A 05/19/2016 A 192

ConstrucConstruction Close Out 05/19/2016 A 05/19/2016 A 21B1380 Commissioning 05/19/2016 A 05/19/2016 A 21B1390 Punch List 05/19/2016 A 05/19/2016 A 14

Project CProject Closeout 05/20/2016 A 08/01/2018 759B1405 Closeout Phase 05/20/2016 A 08/01/2018 759B1410 Issue SAC Letter 03/22/2017 A 0B1430 Final Release of Retainage - Construction Contract 02/18/2017 A 0B1440 Administrative Closeout 05/20/2016 A 08/01/2018 120B1450 Project Closed 08/01/2018 0

100248-2 B100248-2 Basin 0394 Infiltration/Inflow Study and Repairs 10/30/2015 A 03/15/2016 A 215InfiltratioInfiltration/Inflow 10/30/2015 A 03/14/2016 A 20

B1000 Infiltration/Inflow Phase 10/30/2015 A 03/14/2016 A 20ManholeManhole Repairs 10/30/2015 A 03/14/2016 A 20

B1110 Manhole Phase 10/30/2015 A 03/14/2016 A 20B1130 Issue NTP for Manhole Repairs 10/30/2015 A 0B1140 Conduct Manhole Repairs 03/14/2016 A 03/14/2016 A 20

Project CProject Closeout 03/15/2016 A 03/15/2016 A 0B1250 Closeout Phase 03/15/2016 A 03/15/2016 A 0B1280 Project Closed 03/15/2016 A 0

Basin 0399Basin 0399 06/12/2014 A 08/01/2018 1682

100066-2 B100066-2 Basin 0399 Infiltration/Inflow Study and Repairs 09/25/2014 A 06/10/2016 A 604InfiltratioInfiltration/Inflow 09/25/2014 A 06/09/2016 A 517

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Design Phase11/30/2015 A, 100% Design

Design Completed12/09/2015 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid Notice

MDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter

Contract Award (Purchase Order Approval)06/09/2016 A, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre- Construction Meeting

WASD Issues NTP (PO to NTP)

Construction NTPConstruction Operations

Original Construction DurationChange Order #1 - Rejected HOMA Pumps

Substantial Completion05/19/2016 A, Designer Construction Support Services

Designer Construction Support Services05/19/2016 A, Construction Close Out

CommissioningPunch List

08/01/2018, Project Closeout

Closeout PhaseIssue SAC Letter

Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed

03/15/2016 A, 100248-2 Basin 0394 Infiltration/Inflow Study and Repairs03/14/2016 A, Infiltration/Inflow

Infiltration/Inflow Phase03/14/2016 A, Manhole Repairs

Manhole PhaseIssue NTP for Manhole Repairs

Conduct Manhole Repairs03/15/2016 A, Project Closeout

Closeout PhaseProject Closed

08/01/2018, Basin 0399

06/10/2016 A, 100066-2 Basin 0399 Infiltration/Inflow Study and Repairs06/09/2016 A, Infiltration/Inflow

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 61 of 161 TASK filter: All Activities© Oracle Corporation

Page 62: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1000 Infiltration/Inflow Phase 09/25/2014 A 06/09/2016 A 517Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 05/14/2015 A 254

B1005 SSES Phase 09/25/2014 A 05/14/2015 A 254B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 03/02/2015 A 04/17/2015 A 30B1040 Video Review 04/07/2015 A 05/14/2015 A 30

CIPP RepCIPP Repairs 04/17/2015 A 07/27/2015 A 20B1065 CIPP Phase 04/17/2015 A 07/27/2015 A 20B1180 Issue NTP for CIPP Repairs 04/17/2015 A 0B1190 Conduct CIPP Repairs 06/08/2015 A 07/27/2015 A 20

ManholeManhole Repairs 10/02/2015 A 06/09/2016 A 104B1115 Manhole Phase 10/02/2015 A 06/09/2016 A 104B1130 Issue NTP for Manhole Repairs 10/02/2015 A 0B1140 Conduct Manhole Repairs 12/21/2015 A 06/09/2016 A 20

Project CProject Closeout 06/10/2016 A 06/10/2016 A 0B1235 Closeout Phase 06/10/2016 A 06/10/2016 A 0B1260 Project Closed 06/10/2016 A 0

100067 Pu100067 Pump Station 0399 Upgrade 06/12/2014 A 08/01/2018 1682DesignDesign 06/12/2014 A 04/29/2015 A 350

B1000 Design Phase 06/12/2014 A 04/29/2015 A 350B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 06/12/2014 A 06/17/2014 A 5B1020 Engage Design Consultant 06/18/2014 A 08/26/2014 A 20B1030 Issue Design NTP 09/17/2014 A 0B1040 A/E Develops and Submits Final Engineering Report 09/17/2014 A 04/29/2015 A 20B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 11/26/2014 A 01/26/2015 A 10

30% Des30% Design 09/18/2014 A 10/30/2014 A 54B1060 A/E Prepares 30% Construction Documents 09/18/2014 A 10/17/2014 A 30B1070 Geotechnical Engineering Services 10/03/2014 A 10/21/2014 A 31B1080 Surveying Services 10/03/2014 A 10/21/2014 A 21B1100 30% CDs Submittal 10/17/2014 A 0B1120 30% Review (MDWASD/PSIP Team) 10/17/2014 A 10/30/2014 A 10

90% Des90% Design 10/20/2014 A 04/29/2015 A 117B1170 A/E Prepares 90% Construction Documents 10/20/2014 A 11/25/2014 A 20B1180 90% CDs Submittal 11/25/2014 A 0B1190 90% Review (MDWASD/PSIP Team) 11/26/2014 A 01/06/2015 A 15B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 01/27/2015 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 01/27/2015 A 02/20/2015 A 15B1220 90% RER (Building Department) Permit Submittal 03/02/2015 A 0B1230 90% RER (Building Department) Permit Review 03/02/2015 A 04/29/2015 A 15B1260 90% CD PM Comments Evaluation Completed 04/29/2015 A 0

100% De100% Design 01/07/2015 A 03/26/2015 A 13B1270 A/E Prepares 100% Construction Documents 01/07/2015 A 03/24/2015 A 10B1280 100% CDs Submittal 03/24/2015 A 0B1290 100% Review (MDWASD/PSIP Team) 03/25/2015 A 03/26/2015 A 10B1300 Design Completed 03/26/2015 A 0

MDWASDMDWASD Procurement 04/01/2015 A 06/17/2015 A 113B1305 Procurement Phase 04/01/2015 A 06/17/2015 A 113B1310 Submit CDs to MDWASD Procurement Division 04/01/2015 A 0B1320 Pre-Bid Conference 04/09/2015 A 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Infiltration/Inflow Phase05/14/2015 A, Sanitary Sewer Evaluation SurveySSES Phase

Issue NTP to SSES ContractorConduct SSES

Video Review07/27/2015 A, CIPP RepairsCIPP Phase

Issue NTP for CIPP RepairsConduct CIPP Repairs

06/09/2016 A, Manhole RepairsManhole Phase

Issue NTP for Manhole RepairsConduct Manhole Repairs06/10/2016 A, Project CloseoutCloseout Phase

Project Closed08/01/2018, 100067 Pump Station 0399 Upgrade

04/29/2015 A, Design

Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book

Engage Design ConsultantIssue Design NTP

A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

10/30/2014 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services

30% CDs Submittal30% Review (MDWASD/PSIP Team)

04/29/2015 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)

90% RER(DERM)FDEP Permit Submittal (Pump Station)90% RER(DERM)FDEP Permit Review (Pump Station)90% RER (Building Department) Permit Submittal

90% RER (Building Department) Permit Review90% CD PM Comments Evaluation Completed

03/26/2015 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal

100% Review (MDWASD/PSIP Team)Design Completed

06/17/2015 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement DivisionPre-Bid Conference

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 62 of 161 TASK filter: All Activities© Oracle Corporation

Page 63: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1330 Bids Submittal 05/15/2015 A 0B1340 MDWASD/PSIP Team Bids Evaluation 05/18/2015 A 05/27/2015 A 30B1350 Recommendation for Award Letter 05/27/2015 A 0B1355 Contract Award (Purchase Order Approval) 05/28/2015 A 06/17/2015 A 15

ConstrucConstruction 04/09/2015 A 08/11/2016 A 1283B1360 Construction Phase 04/09/2015 A 08/11/2016 A 1283B1362 MDWASD/PSIP Team prepare for Pre-Construction meeting 05/29/2015 A 06/17/2015 A 15B1365 Pre-Construction Meeting 06/18/2015 A 06/18/2015 A 1B1369 WASD Issues NTP (PO to NTP) 06/18/2015 A 07/12/2015 A 53B1370 Construction NTP 07/13/2015 A 0B1400 Construction Operations 07/13/2015 A 12/18/2015 A 92B1400 Original Construction Duration 07/13/2015 A 11/20/2015 A 92B1400 Change Order #1 - FPL 11/21/2015 A 12/18/2015 A 92B1402 Substantial Completion 12/18/2015 A 0

DesignerDesigner Construction Support Services 04/09/2015 A 08/11/2016 A 95B1410 Designer Construction Support Services 04/09/2015 A 08/11/2016 A 95

ConstrucConstruction Close Out 12/21/2015 A 03/29/2016 A 15B1420 Commissioning 12/21/2015 A 03/29/2016 A 15B1430 Punch List 12/21/2015 A 03/29/2016 A 10

Project CProject Closeout 09/21/2015 A 08/01/2018 1045B1445 Closeout Phase 09/21/2015 A 08/01/2018 1045B1450 Issue SAC Letter 09/21/2015 A 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 12/21/2015 A 08/01/2018 120B1490 Project Closed 08/01/2018 0

Basin 0407Basin 0407 09/25/2014 A 01/05/2020 1883

100068 Pu100068 Pump Station 0407 Upgrade 12/29/2014 A 01/05/2020 1715DesignDesign 12/29/2014 A 10/04/2018 1257

B1000 Design Phase 12/29/2014 A 10/04/2018 1257B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 12/29/2014 A 01/05/2015 A 5B1020 Engage Design Consultant 01/06/2015 A 05/05/2015 A 20B1030 Issue Design NTP 05/05/2015 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 05/05/2015 A 09/14/2018 85

30% Des30% Design 05/06/2015 A 08/24/2015 A 95B1060 A/E Prepares 30% Construction Documents 05/06/2015 A 08/11/2015 A 30B1070 Geotechnical Engineering Services 05/06/2015 A 08/11/2015 A 20B1080 Surveying Services 05/06/2015 A 08/11/2015 A 15B1100 30% CDs Submittal 08/11/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 08/11/2015 A 08/24/2015 A 10

90% Des90% Design 08/11/2015 A 09/14/2018 1088B1170 A/E Prepares 90% Construction Documents 08/11/2015 A 10/30/2015 A 20B1172 90% CD On-Hold Until Pump Station Relocation Resolution 10/30/2015 A 08/01/2018 100B1180 90% CDs Submittal 08/01/2018 0B1190 90% Review (MDWASD/PSIP Team) 08/01/2018 08/15/2018 15B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 08/16/2018 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 08/16/2018 08/30/2018 15B1220 90% RER (Building Department) Permit Submittal 08/31/2018 0B1230 90% RER (Building Department) Permit Review 08/31/2018 09/14/2018 15B1260 90% CD PM Comments Evaluation Completed 09/14/2018 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Bids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)

08/11/2016 A, Construction

Construction PhaseMDWASD/PSIP Team prepare for Pre-Construction meetingPre-Construction Meeting

WASD Issues NTP (PO to NTP)

Construction NTPConstruction Operations

Original Construction DurationChange Order #1 - FPL

Substantial Completion08/11/2016 A, Designer Construction Support Services

Designer Construction Support Services03/29/2016 A, Construction Close Out

CommissioningPunch List

08/01/2018, Project Closeout

Closeout PhaseIssue SAC Letter

Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed

01/05/2020, Basin 0

01/05/2020, 10006810/04/2018, Design

Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book

Engage Design ConsultantIssue Design NTP

Final Engineering Report Review & Approval (MDWASD/PS08/24/2015 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal30% Review (MDWASD/PSIP Team)

09/14/2018, 90% Design

A/E Prepares 90% Construction Documents90% CD On-Hold Until Pump Station Relocation Resolution

90% CDs Submittal90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)90% RER(DERM)FDEP Permit Review (Pump Station)90% RER (Building Department) Permit Submittal90% RER (Building Department) Permit Review90% CD PM Comments Evaluation Completed

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 63 of 161 TASK filter: All Activities© Oracle Corporation

Page 64: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

100% De100% Design 09/15/2018 10/04/2018 20B1270 A/E Prepares 100% Construction Documents 09/15/2018 09/24/2018 10B1280 100% CDs Submittal 09/24/2018 0B1290 100% Review (MDWASD/PSIP Team) 09/25/2018 10/04/2018 10B1300 Design Completed 10/04/2018 0

MDWASDMDWASD Procurement 10/04/2018 01/15/2019 104B1305 Procurement Phase 10/04/2018 01/15/2019 104B1310 Submit CDs to MDWASD Procurement Division 10/04/2018 0B1312 Bid Notice Preparation Period 10/04/2018 11/05/2018 33B1314 Bid Notice 11/05/2018 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 11/06/2018 11/19/2018 14B1320 Pre-Bid Conference 11/20/2018 11/20/2018 1B1328 Bidders Prepare Bids for Submittal 11/21/2018 12/11/2018 21B1330 Bids Submittal 12/11/2018 0B1340 MDWASD/PSIP Team Bids Evaluation 12/12/2018 01/01/2019 21B1350 Recommendation for Award Letter 01/01/2019 0B1355 Contract Award (Purchase Order Approval) 01/02/2019 01/15/2019 14

ConstrucConstruction 11/20/2018 09/07/2019 292B1360 Construction Phase 11/20/2018 09/07/2019 292B1364 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 01/02/2019 01/24/2019 23B1366 Pre-Construction Meeting 01/25/2019 01/25/2019 1B1368 WASD Issues NTP (Pre-Const to NTP) 01/26/2019 03/11/2019 45B1369 WASD Issues NTP (PO to NTP) 01/16/2019 03/11/2019 55B1370 Construction NTP 03/12/2019 0B1400 Construction Operations 03/12/2019 09/07/2019 180B1402 Substantial Completion 09/07/2019 0

DesignerDesigner Construction Support Services 11/20/2018 09/07/2019 292B1410 Designer Construction Support Services 11/20/2018 09/07/2019 292

Project CProject Closeout 09/07/2019 01/05/2020 120B1445 Closeout Phase 09/07/2019 01/05/2020 120B1450 Issue SAC Letter 09/07/2019 0B1470 Final Release of Retainage - Construction Contract 09/07/2019 0B1480 Administrative Closeout 09/08/2019 01/05/2020 120B1490 Project Closed 01/05/2020 0

100190-2 B100190-2 Basin 0407 Infiltration/Inflow Study and Repairs 09/25/2014 A 07/28/2015 A 569InfiltratioInfiltration/Inflow 09/25/2014 A 07/27/2015 A 263

B1000 Infiltration/Inflow Phase 09/25/2014 A 07/27/2015 A 263Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 07/27/2015 A 263

B1005 SSES Phase 09/25/2014 A 07/27/2015 A 263B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 07/06/2015 A 07/27/2015 A 30

Project CProject Closeout 07/28/2015 A 07/28/2015 A 0B1235 Closeout Phase 07/28/2015 A 07/28/2015 A 0B1260 Project Closed 07/28/2015 A 0

100223 FM100223 FM for Pump Station 0407 12/29/2014 A 03/09/2019 1413DesignDesign 12/29/2014 A 09/10/2018 1233

B1000 Design Phase 12/29/2014 A 09/10/2018 1233B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 12/29/2014 A 01/05/2015 A 5B1020 Engage Design Consultant 01/06/2015 A 05/05/2015 A 20

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

10/04/2018, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed

01/15/2019, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)

09/07/2019, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-ConstructPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Construction NTPConstruction OperationsSubstantial Completion09/07/2019, Designer Constru

Designer Construction Suppo01/05/2020, Project

Closeout PhaseIssue SAC LetterFinal Release of Retainage - C

Administrative CloseProject Closed

07/28/2015 A, 100190-2 Basin 0407 Infiltration/Inflow Study and Repairs07/27/2015 A, Infiltration/Inflow

Infiltration/Inflow Phase07/27/2015 A, Sanitary Sewer Evaluation SurveySSES Phase

Issue NTP to SSES ContractorConduct SSES07/28/2015 A, Project CloseoutCloseout Phase

Project Closed03/09/2019, 100223 FM for Pump Station 0

09/10/2018, Design

Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book

Engage Design Consultant

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 64 of 161 TASK filter: All Activities© Oracle Corporation

Page 65: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1030 Issue Design NTP 05/05/2015 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 05/05/2015 A 10/30/2015 A 10

30% Des30% Design 05/06/2015 A 08/24/2015 A 107B1060 A/E Prepares 30% Construction Documents 05/06/2015 A 08/11/2015 A 30B1070 Geotechnical Engineering Services 05/06/2015 A 08/11/2015 A 20B1080 Surveying Services 05/06/2015 A 08/11/2015 A 15B1100 30% CDs Submittal 08/11/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 08/11/2015 A 08/24/2015 A 10

90% Des90% Design 08/11/2015 A 08/21/2018 1064B1180 A/E Prepares 90% Construction Documents 08/11/2015 A 10/22/2015 A 20B1190 90% CDs Submittal 10/22/2015 A 0B1200 90% Review (MDWASD/PSIP Team) 10/23/2015 A 10/30/2015 A 15B1202 90% Design Review On-Hold Until Pump Station Relocation Res 10/30/2015 A 08/01/2018 100B1230 90% RER(DERM)FDEP Permit Submittal (Force Main) 08/02/2018 0B1240 90% RER(DERM)FDEP Permit Review (Force Main) 08/02/2018 08/11/2018 10B1250 90% PWWMD Permit Submittal (Force Main) 08/12/2018 0B1260 90% PWWMD Permit Review (Force Main) 08/12/2018 08/21/2018 10B1290 90% CD PM Comments Evaluation Completed 08/21/2018 0

100% De100% Design 08/22/2018 09/10/2018 20B1300 A/E Prepares 100% Construction Documents 08/22/2018 08/31/2018 10B1310 100% CDs Submittal 08/31/2018 0B1320 100% Review (MDWASD/PSIP Team) 09/01/2018 09/10/2018 10B1330 Design Completed 09/10/2018 0

MDWASDMDWASD Procurement 09/10/2018 11/23/2018 74B1335 Procurement Phase 09/10/2018 11/23/2018 74B1340 Submit CDs to MDWASD Procurement Division 09/10/2018 0B1342 Bid Notice Preparation Period 09/11/2018 10/03/2018 23B1344 Bid Notice 10/03/2018 0B1346 MDWASD/PSIP Team Prepare for Pre-Bid Conference 10/04/2018 10/13/2018 10B1350 Pre-Bid Conference 10/14/2018 10/14/2018 1B1358 Bidders Prepare Bids for Submittal 10/15/2018 10/29/2018 15B1360 Bids Submittal 10/29/2018 0B1370 MDWASD/PSIP Team Bids Evaluation 10/30/2018 11/13/2018 15B1380 Recommendation for Award Letter 11/13/2018 0B1385 Contract Award (Purchase Order Approval) 11/14/2018 11/23/2018 10

ConstrucConstruction 10/14/2018 02/07/2019 117B1390 Construction Phase 10/14/2018 02/07/2019 117B1394 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 11/24/2018 12/08/2018 15B1396 Pre-Construction Meeting 12/09/2018 12/09/2018 1B1398 WASD Issues NTP (PO to NTP) 11/24/2018 12/09/2018 16B1400 Construction NTP 12/10/2018 0B1430 Construction Operations 12/10/2018 02/07/2019 60B1432 Substantial Completion 02/07/2019 0

DesignerDesigner Construction Support Services 10/14/2018 02/07/2019 117B1440 Designer Construction Support Services 10/14/2018 02/07/2019 117

Project CProject Closeout 02/07/2019 03/09/2019 30B1475 Closeout Phase 02/07/2019 03/09/2019 30B1480 Issue SAC Letter 02/07/2019 0B1500 Final Release of Retainage - Construction Contract 02/07/2019 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Issue Design NTPFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

08/24/2015 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal30% Review (MDWASD/PSIP Team)

08/21/2018, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)

90% Design Review On-Hold Until Pump Station Relocation Re

90% RER(DERM)FDEP Permit Submittal (Force Main)90% RER(DERM)FDEP Permit Review (Force Main)90% PWWMD Permit Submittal (Force Main)90% PWWMD Permit Review (Force Main)90% CD PM Comments Evaluation Completed

09/10/2018, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed

11/23/2018, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation Period

Bid NoticeMDWASD/PSIP Team Prepare for Pre-Bid Conference

Pre-Bid ConferenceBidders Prepare Bids for Submittal

Bids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)

02/07/2019, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction Pre-Construction MeetingWASD Issues NTP (PO to NTP)

Construction NTPConstruction OperationsSubstantial Completion02/07/2019, Designer Construction Support Se

Designer Construction Support Services03/09/2019, Project Closeout

Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction Cont

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 65 of 161 TASK filter: All Activities© Oracle Corporation

Page 66: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1510 Administrative Closeout 02/08/2019 03/09/2019 30B1520 Project Closed 03/09/2019 0

Basin 0408Basin 0408 09/25/2014 A 08/01/2018 1628

100070 Pu100070 Pump Station 0408(AM) Upgrade 01/12/2015 A 08/01/2018 1138DesignDesign 01/12/2015 A 05/19/2016 A 351

B1000 Design Phase 01/12/2015 A 05/19/2016 A 351B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 01/12/2015 A 03/04/2015 A 5B1020 Engage Design Consultant 03/05/2015 A 07/16/2015 A 15B1025 TA Approval Process 07/17/2015 A 08/07/2015 A 20B1030 Issue Design NTP 08/07/2015 A 0

30% Des30% Design 08/07/2015 A 10/30/2015 A 59B1060 A/E Prepares 30% Construction Documents 08/07/2015 A 10/22/2015 A 30B1070 Geotechnical Engineering Services 08/07/2015 A 10/22/2015 A 20B1080 Surveying Services 08/07/2015 A 10/22/2015 A 15B1100 30% CDs Submittal 10/22/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 10/23/2015 A 10/30/2015 A 10

60% Des60% Design 10/23/2015 A 05/19/2016 A 100B1130 A/E Prepares 60% Construction Documents 10/23/2015 A 10/30/2015 A 20B1132 60% CD On-Hold Until Pump Station Relocation Resolution 10/30/2015 A 05/19/2016 A 100

Project CProject Closeout 05/19/2016 A 08/01/2018 1157B1445 Closeout Phase 05/19/2016 A 08/01/2018 1157B1450 Issue SAC Letter 05/19/2016 A 0B1480 Administrative Closeout 05/20/2016 A 08/01/2018 120B1490 Project Closed 08/01/2018 0

100201-2 B100201-2 Basin 0408 Infiltration/Inflow Study and Repairs 09/25/2014 A 07/28/2015 A 336InfiltratioInfiltration/Inflow 09/25/2014 A 07/27/2015 A 111

B1000 Infiltration/Inflow Phase 09/25/2014 A 07/27/2015 A 111Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 07/27/2015 A 111

B1005 SSES Phase 09/25/2014 A 07/27/2015 A 111B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 07/06/2015 A 07/27/2015 A 30

Project CProject Closeout 07/28/2015 A 07/28/2015 A 0B1235 Closeout Phase 07/28/2015 A 07/28/2015 A 0B1260 Project Closed 07/28/2015 A 0

100063 FM100063 FM for Pump Station 0408 01/26/2015 A 08/01/2018 1275DesignDesign 01/26/2015 A 05/19/2016 A 331

B1000 Design Phase 01/26/2015 A 05/19/2016 A 331B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 01/26/2015 A 02/27/2015 A 5B1015 MDWASD to Issue PCTS Number to Project 03/03/2015 A 04/03/2015 A 21B1020 Engage Design Consultant 04/06/2015 A 07/16/2015 A 25B1030 Prepare and Issue TA 07/17/2015 A 08/06/2015 A 20B1040 Issue Design NTP 08/07/2015 A 0

30% Des30% Design 08/07/2015 A 05/19/2016 A 136B1070 A/E Prepares 30% Construction Documents 08/07/2015 A 10/30/2015 A 30B1080 Geotechnical Engineering Services 08/07/2015 A 10/30/2015 A 20B1090 Surveying Services 08/07/2015 A 10/30/2015 A 15B1092 30% CD On-Hold Until Pump Station Relocation Resolution 10/30/2015 A 05/19/2016 A 100

Project CProject Closeout 05/19/2016 A 08/01/2018 804B1420 Closeout Phase 05/19/2016 A 08/01/2018 804

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Administrative CloseoutProject Closed

08/01/2018, Basin 0408

08/01/2018, 100070 Pump Station 0408(AM) Upgrade05/19/2016 A, Design

Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book

Engage Design ConsultantTA Approval ProcessIssue Design NTP

10/30/2015 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal30% Review (MDWASD/PSIP Team)

05/19/2016 A, 60% Design

A/E Prepares 60% Construction Documents60% CD On-Hold Until Pump Station Relocation Resolution

08/01/2018, Project Closeout

Closeout PhaseIssue SAC Letter

Administrative CloseoutProject Closed

07/28/2015 A, 100201-2 Basin 0408 Infiltration/Inflow Study and Repairs07/27/2015 A, Infiltration/Inflow

Infiltration/Inflow Phase07/27/2015 A, Sanitary Sewer Evaluation SurveySSES Phase

Issue NTP to SSES ContractorConduct SSES

07/28/2015 A, Project CloseoutCloseout Phase

Project Closed08/01/2018, 100063 FM for Pump Station 0408

05/19/2016 A, Design

Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book

MDWASD to Issue PCTS Number to Project

Engage Design ConsultantPrepare and Issue TAIssue Design NTP

05/19/2016 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services

30% CD On-Hold Until Pump Station Relocation Resolution08/01/2018, Project Closeout

Closeout Phase

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 66 of 161 TASK filter: All Activities© Oracle Corporation

Page 67: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1430 Issue SAC Letter 05/19/2016 A 0B1460 Administrative Closeout 05/20/2016 A 08/01/2018 120B1470 Project Closed 08/01/2018 0

Basin 0431Basin 0431 04/15/2014 A 08/01/2018 1667

100072 Pu100072 Pump Station 0431 Upgrade 04/15/2014 A 08/01/2018 1667DesignDesign 04/15/2014 A 04/21/2016 A 400

B1000 Design Phase 04/15/2014 A 04/21/2016 A 400B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 04/15/2014 A 04/15/2014 A 5B1020 Engage Design Consultant 04/16/2014 A 09/17/2014 A 15B1022 TA Rev 1 - Approval Process 01/19/2016 A 04/21/2016 A 20B1030 Issue Design NTP 09/18/2014 A 0B1040 A/E Develops and Submits Final Engineering Report 09/19/2014 A 11/21/2014 A 20B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 11/24/2014 A 04/07/2015 A 10

30% Des30% Design 09/18/2014 A 10/30/2014 A 30B1060 A/E Prepares 30% Construction Documents 09/18/2014 A 10/20/2014 A 30B1070 Geotechnical Engineering Services 10/02/2014 A 10/16/2014 A 20B1080 Surveying Services 10/09/2014 A 10/16/2014 A 15B1090 30% CDs Submittal 10/20/2014 A 0B1100 30% Review (MDWASD/PSIP Team) 10/21/2014 A 10/30/2014 A 10

90% Des90% Design 10/21/2014 A 05/21/2015 A 210B1150 A/E Prepares 90% Construction Documents 10/21/2014 A 11/21/2014 A 20B1160 90% CDs Submittal 11/21/2014 A 0B1170 90% Review (MDWASD/PSIP Team) 11/24/2014 A 12/11/2014 A 15B1180 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 03/06/2015 A 0B1190 90% RER(DERM)/FDEP Permit Review (Pump Station) 03/06/2015 A 04/07/2015 A 15B1200 90% RER (Building Dept) Permit Submittal 04/22/2015 A 0B1210 90% RER (Building Dept) Permit Review 04/22/2015 A 05/21/2015 A 15B1240 90% CD PM Comments Evaluation Completed 05/21/2015 A 0

100% De100% Design 12/11/2014 A 05/21/2015 A 98B1250 A/E Prepares 100% Construction Documents 12/11/2014 A 01/23/2015 A 10B1260 100% CDs Submittal 01/23/2015 A 0B1270 100% Review (MDWASD/PSIP Team) 01/26/2015 A 03/05/2015 A 10B1280 Design Completed 05/21/2015 A 0

MDWASDMDWASD Procurement 04/24/2015 A 08/18/2015 A 202B1285 Procurement Phase 04/24/2015 A 08/18/2015 A 202B1290 Submit CDs to MDWASD Procurement Division 04/24/2015 A 0B1292 Bid Notice Preparation Period 04/27/2015 A 04/30/2015 A 23B1294 Bid Notice 04/30/2015 A 0B1296 MDWASD/PSIP Team Prepare for Pre-Bid Conference 05/01/2015 A 05/05/2015 A 10B1300 Pre-Bid Conference 05/06/2015 A 05/06/2015 A 1B1302 Bidders Prepare Bids for Submittal 05/07/2015 A 05/28/2015 A 15B1310 Bids Submittal 05/28/2015 A 0B1320 MDWASD/PSIP Team Bids Evaluation 05/29/2015 A 06/25/2015 A 15B1330 Recommendation for Award Letter 06/25/2015 A 0B1335 Contract Award (Purchase Order Approval) 06/26/2015 A 08/18/2015 A 10

ConstrucConstruction 05/06/2015 A 12/16/2016 A 1240B1340 Construction Phase 05/06/2015 A 12/16/2016 A 1240B1344 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 06/26/2015 A 07/27/2015 A 15B1346 Pre-Construction Meeting 07/28/2015 A 07/28/2015 A 1

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Issue SAC LetterAdministrative CloseoutProject Closed08/01/2018, Basin 0431

08/01/2018, 100072 Pump Station 0431 Upgrade04/21/2016 A, Design

Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book

Engage Design ConsultantTA Rev 1 - Approval Process

Issue Design NTPA/E Develops and Submits Final Engineering Report

Final Engineering Report Review & Approval (MDWASD/PSIP Team)10/30/2014 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services

30% CDs Submittal30% Review (MDWASD/PSIP Team)

05/21/2015 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)/FDEP Permit Submittal (Pump Station)

90% RER(DERM)/FDEP Permit Review (Pump Station)90% RER (Building Dept) Permit Submittal

90% RER (Building Dept) Permit Review90% CD PM Comments Evaluation Completed

05/21/2015 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)

Design Completed08/18/2015 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation Period

Bid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter

Contract Award (Purchase Order Approval)12/16/2016 A, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 67 of 161 TASK filter: All Activities© Oracle Corporation

Page 68: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1348 WASD Issues NTP (PO to NTP) 08/19/2015 A 09/01/2015 A 53B1350 Construction NTP 09/02/2015 A 0B1380 Construction Operations 09/02/2015 A 12/16/2016 A 105B1380 Original Construction Duration 09/02/2015 A 01/30/2016 A 105B1380 Change Order #1 - Shop Drawing Processing 01/31/2016 A 07/18/2016 A 105B1380 Change Order #2 - Contractor's Delays 07/19/2016 A 08/18/2016 A 105B1380 Change Order #3 - Multiple Issues 08/19/2016 A 11/28/2016 A 105B1382 Substantial Completion 12/16/2016 A 0

DesignerDesigner Construction Support Services 05/06/2015 A 12/16/2016 A 198B1390 Designer Construction Support Services 05/06/2015 A 12/16/2016 A 198

Project CProject Closeout 09/21/2015 A 08/01/2018 1045B1425 Closeout Phase 09/21/2015 A 08/01/2018 1045B1430 Issue SAC Letter 09/21/2015 A 0B1450 Final Release of Retainage - Construction Contract 08/01/2018 0B1460 Administrative Closeout 12/19/2016 A 08/01/2018 120B1470 Project Closed 08/01/2018 0

100202-2 B100202-2 Basin 0431 Infiltration/Inflow Study and Repairs 09/25/2014 A 01/29/2016 A 576InfiltratioInfiltration/Inflow 09/25/2014 A 01/28/2016 A 414

B1000 Infiltration/Inflow Phase 09/25/2014 A 01/28/2016 A 414Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 04/16/2015 A 234

B1005 SSES Phase 09/25/2014 A 04/16/2015 A 234B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct Flow Isolation & SSES 11/12/2014 A 03/02/2015 A 30B1031 Smoke Test 02/02/2015 A 02/05/2015 A 10B1040 Video Review 02/16/2015 A 04/16/2015 A 30

CIPP RepCIPP Repairs 11/30/2015 A 01/28/2016 A 20B1065 CIPP Phase 11/30/2015 A 01/28/2016 A 20B1080 Issue NTP for CIPP Repairs 11/30/2015 A 0B1090 Conduct CIPP Repairs 11/30/2015 A 01/28/2016 A 20

Project CProject Closeout 01/29/2016 A 01/29/2016 A 0B1235 Closeout Phase 01/29/2016 A 01/29/2016 A 0B1260 Project Closed 01/29/2016 A 0

100236 FM100236 FM for Pump Station 0431 07/14/2014 A 08/01/2018 1619DesignDesign 07/14/2014 A 05/07/2015 A 301

B1000 Design Phase 07/14/2014 A 05/07/2015 A 301B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 07/14/2014 A 07/18/2014 A 5B1020 Engage Design Consultant 07/21/2014 A 10/02/2014 A 20B1025 Prepare and Issue TA 09/19/2014 A 12/11/2014 A 10B1030 Issue Design NTP 12/11/2014 A 0B1040 A/E Develops and Submits Final Engineering Report 12/11/2014 A 05/05/2015 A 60B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 12/24/2014 A 04/08/2015 A 10

30% Des30% Design 12/12/2014 A 02/18/2015 A 73B1060 A/E Prepares 30% Construction Documents 12/12/2014 A 02/11/2015 A 20B1070 Geotechnical Engineering Services 12/12/2014 A 02/11/2015 A 15B1080 Surveying Services 12/12/2014 A 02/11/2015 A 15B1100 30% CDs Submittal 02/11/2015 A 0B1120 30% Review (MDWASD/PSIP Team ) 02/12/2015 A 02/18/2015 A 10

90% Des90% Design 02/12/2015 A 05/05/2015 A 84B1140 A/E Prepares 90% Construction Documents 02/12/2015 A 03/23/2015 A 15

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

WASD Issues NTP (PO to NTP)

Construction NTPConstruction Operations

Original Construction DurationChange Order #1 - Shop Drawing Processing

Change Order #2 - Contractor's DelaysChange Order #3 - Multiple Issues

Substantial Completion12/16/2016 A, Designer Construction Support Services

Designer Construction Support Services08/01/2018, Project Closeout

Closeout PhaseIssue SAC Letter

Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed

01/29/2016 A, 100202-2 Basin 0431 Infiltration/Inflow Study and Repairs01/28/2016 A, Infiltration/Inflow

Infiltration/Inflow Phase04/16/2015 A, Sanitary Sewer Evaluation SurveySSES Phase

Issue NTP to SSES ContractorConduct Flow Isolation & SSES

Smoke Test

Video Review01/28/2016 A, CIPP RepairsCIPP Phase

Issue NTP for CIPP RepairsConduct CIPP Repairs01/29/2016 A, Project CloseoutCloseout Phase

Project Closed08/01/2018, 100236 FM for Pump Station 0431

05/07/2015 A, Design

Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book

Engage Design ConsultantPrepare and Issue TAIssue Design NTP

A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

02/18/2015 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal30% Review (MDWASD/PSIP Team )

05/05/2015 A, 90% Design

A/E Prepares 90% Construction Documents

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 68 of 161 TASK filter: All Activities© Oracle Corporation

Page 69: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1150 90% CDs Submittal 03/23/2015 A 0B1160 90% Review (MDWASD/PSIP Team) 03/24/2015 A 04/08/2015 A 5B1170 90% RER(DERM)/FDEP Permit Submittal (Force Main) 04/21/2015 A 0B1180 90% RER(DERM)/FDEP Permit Review (Force Main) 04/21/2015 A 04/28/2015 A 5B1190 90% PWWMD Permit Submittal (Force Main) 04/22/2015 A 0B1200 90% PWWMD Permit Review (Force Main) 04/22/2015 A 05/05/2015 A 10B1250 90% CD PM Comments Evaluation Completed 05/05/2015 A 0

100% De100% Design 05/07/2015 A 05/07/2015 A 46B1260 A/E Prepares 100% Construction Documents 05/07/2015 A 05/07/2015 A 5B1270 100% CDs Submittal 05/07/2015 A 0B1280 100% Review (MDWASD/PSIP Team) 05/07/2015 A 05/07/2015 A 5B1290 Design Completed 05/07/2015 A 0

MDWASDMDWASD Procurement 05/01/2015 A 10/13/2015 A 178B1295 Procurement Phase 05/01/2015 A 10/13/2015 A 178B1300 Submit CDs to MDWASD Procurement Division 05/01/2015 A 0B1310 Pre-Bid Conference 05/27/2015 A 0B1320 Bids Submittal 06/18/2015 A 0B1330 Bids Evaluation (MDWASD/PSIP Team) 06/19/2015 A 08/10/2015 A 30B1332 MDWASD Issued Notice of Cancellation - Project To Be Re-Bid 08/11/2015 A 08/11/2015 A 30B1333 Re-Bid Notice Preparation Period 08/12/2015 A 08/12/2015 A 30B1334 Re-Bid Notice 08/12/2015 A 0B1335 MDWASD/PSIP Team Prepare for Re-Bid Conference 08/13/2015 A 08/25/2015 A 10B1336 Re-Bid Conference 08/26/2015 A 08/26/2015 A 1B1337 Bidders Prepare for Re-Bids Submittal 08/27/2015 A 09/15/2015 A 15B1338 Re-Bids Submittal 09/16/2015 A 0B1339 Re-Bids Evaluation (MDWASD/PSIP Team) 09/17/2015 A 09/18/2015 A 15B1340 Recommendation for Award Letter 09/21/2015 A 0B1345 Contract Award (Purchase Order Approval) 09/22/2015 A 10/13/2015 A 10

ConstrucConstruction 05/27/2015 A 07/29/2016 A 1175B1350 Construction Phase 05/27/2015 A 07/29/2016 A 1175B1354 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 09/22/2015 A 10/29/2015 A 15B1356 Pre-Construction Meeting 10/30/2015 A 10/30/2015 A 1B1357 WASD Issues NTP (Pre-Const to NTP) 11/02/2015 A 01/31/2016 A 15B1358 WASD Issues NTP (PO to NTP) 10/14/2015 A 01/31/2016 A 53B1360 Construction NTP 02/01/2016 A 0B1390 Construction Operations 02/01/2016 A 04/29/2016 A 63B1392 Substantial Completion 04/29/2016 A 0

DesignerDesigner Construction Services 05/27/2015 A 07/29/2016 A 152B1400 Designer Construction Support Services 05/27/2015 A 07/29/2016 A 152

ConstrucConstruction Close Out 05/02/2016 A 07/29/2016 A 10B1420 Punch List 05/02/2016 A 07/29/2016 A 10

Project CProject Closeout 05/02/2016 A 08/01/2018 792B1435 Closeout Phase 05/02/2016 A 08/01/2018 792B1460 Final Release of Retainage - Construction Contract 05/30/2017 A 0B1470 Administrative Closeout 05/02/2016 A 08/01/2018 120B1480 Project Closed 08/01/2018 0

Basin 0435Basin 0435 08/07/2014 A 08/01/2018 1651

100073 Pu100073 Pump Station 0435 Upgrade 08/07/2014 A 08/01/2018 1651DesignDesign 08/07/2014 A 09/30/2015 A 478

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

90% CDs Submittal90% Review (MDWASD/PSIP Team)90% RER(DERM)/FDEP Permit Submittal (Force Main)90% RER(DERM)/FDEP Permit Review (Force Main)90% PWWMD Permit Submittal (Force Main)90% PWWMD Permit Review (Force Main)90% CD PM Comments Evaluation Completed05/07/2015 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed

10/13/2015 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Pre-Bid ConferenceBids Submittal

Bids Evaluation (MDWASD/PSIP Team)MDWASD Issued Notice of Cancellation - Project To Be Re-BidRe-Bid Notice Preparation Period

Re-Bid NoticeMDWASD/PSIP Team Prepare for Re-Bid ConferenceRe-Bid Conference

Bidders Prepare for Re-Bids Submittal

Re-Bids SubmittalRe-Bids Evaluation (MDWASD/PSIP Team)

Recommendation for Award LetterContract Award (Purchase Order Approval)

07/29/2016 A, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Construction NTPConstruction OperationsSubstantial Completion

07/29/2016 A, Designer Construction Services

Designer Construction Support Services07/29/2016 A, Construction Close Out

Punch List08/01/2018, Project Closeout

Closeout PhaseFinal Release of Retainage - Construction Contract

Administrative CloseoutProject Closed08/01/2018, Basin 0435

08/01/2018, 100073 Pump Station 0435 Upgrade09/30/2015 A, Design

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 69 of 161 TASK filter: All Activities© Oracle Corporation

Page 70: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1000 Design Phase 08/07/2014 A 09/30/2015 A 478B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 08/07/2014 A 08/08/2014 A 5B1020 Engage Design Consultant 08/11/2014 A 01/15/2015 A 20B1030 Issue Design NTP 01/19/2015 A 0B1040 A/E Develops and Submits Final Engineering Report 01/16/2015 A 09/17/2015 A 175B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 01/16/2015 A 04/20/2015 A 85

30% Des30% Design 02/02/2015 A 04/24/2015 A 72B1060 A/E Prepares 30% Construction Documents 03/16/2015 A 04/24/2015 A 30B1070 Geotechnical Engineering Services 02/02/2015 A 03/06/2015 A 20B1080 Surveying Services 02/02/2015 A 03/06/2015 A 15B1100 30% CDs Submittal 03/06/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 03/09/2015 A 03/23/2015 A 7

90% Des90% Design 03/09/2015 A 09/17/2015 A 205B1170 A/E Prepares 90% Construction Documents 03/09/2015 A 04/13/2015 A 30B1180 90% CDs Submittal 04/13/2015 A 0B1190 90% Review (MDWASD/PSIP Team) 04/14/2015 A 04/20/2015 A 15B1200 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 06/25/2015 A 0B1210 90% RER(DERM)/FDEP Permit Review (Pump Station) 06/26/2015 A 08/20/2015 A 15B1236 90% RER (Building Dept) Permit Submittal (Pump Station) 08/25/2015 A 0B1238 90% RER (Building Dept) Permit Review (Pump Station) 08/25/2015 A 09/11/2015 A 15B1240 90% Aventura - BD Permit Submittal (Pump Station) 08/24/2015 A 0B1250 90% Aventura - BD Permit Review (Pump Station) 08/25/2015 A 09/17/2015 A 15B1260 90% CD PM Comments Evaluation Completed 09/17/2015 A 0

100% De100% Design 09/18/2015 A 09/30/2015 A 13B1270 A/E Prepares 100% Construction Documents 09/18/2015 A 09/28/2015 A 10B1280 100% CDs Submittal 09/29/2015 A 0B1290 100% Review (MDWASD/PSIP Team) 09/30/2015 A 09/30/2015 A 10B1300 Design Completed 09/30/2015 A 0

MDWASDMDWASD Procurement 09/30/2015 A 03/08/2016 A 85B1305 Procurement Phase 09/30/2015 A 03/08/2016 A 85B1310 Submit CDs to MDWASD Procurement Division 09/30/2015 A 0B1312 Bid Notice Preparation Period 09/30/2015 A 10/07/2015 A 23B1314 Bid Notice 10/08/2015 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 10/09/2015 A 10/19/2015 A 10B1320 Pre-Bid Conference 10/20/2015 A 10/20/2015 A 1B1328 Bidders Prepare Bids for Submittal 10/21/2015 A 11/19/2015 A 15B1330 Bids Submittal 11/19/2015 A 0B1340 MDWASD/PSIP Team Bids Evaluation 11/20/2015 A 12/07/2015 A 15B1350 Recommendation for Award Letter 12/07/2015 A 0B1355 Contract Award (Purchase Order Approval) 12/08/2015 A 03/08/2016 A 10

ConstrucConstruction 10/20/2015 A 10/31/2016 A 1182B1360 Construction Phase 10/20/2015 A 10/31/2016 A 1182B1364 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 12/08/2015 A 01/04/2016 A 15B1366 Pre-Construction Meeting 01/05/2016 A 01/05/2016 A 1B1368 WASD Issues NTP (PO to NTP) 03/09/2016 A 03/13/2016 A 55B1370 Construction NTP 03/14/2016 A 0B1400 Construction Operations 03/14/2016 A 06/21/2016 A 107B1402 Substantial Completion 06/21/2016 A 0

DesignerDesigner Construction Support Services 10/20/2015 A 10/31/2016 A 295

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book

Engage Design ConsultantIssue Design NTP

A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

04/24/2015 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services

30% CDs Submittal30% Review (MDWASD/PSIP Team)

09/17/2015 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)/FDEP Permit Submittal (Pump Station)

90% RER(DERM)/FDEP Permit Review (Pump Station)90% RER (Building Dept) Permit Submittal (Pump Station)90% RER (Building Dept) Permit Review (Pump Station)

90% Aventura - BD Permit Submittal (Pump Station)90% Aventura - BD Permit Review (Pump Station)90% CD PM Comments Evaluation Completed09/30/2015 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed

03/08/2016 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation Period

Bid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter

Contract Award (Purchase Order Approval)10/31/2016 A, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

WASD Issues NTP (PO to NTP)Construction NTP

Construction OperationsSubstantial Completion

10/31/2016 A, Designer Construction Support Services

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 70 of 161 TASK filter: All Activities© Oracle Corporation

Page 71: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1410 Designer Construction Support Services 10/20/2015 A 10/31/2016 A 295ConstrucConstruction Close Out 06/22/2016 A 10/31/2016 A 15

B1420 Commissioning 06/22/2016 A 10/31/2016 A 15B1430 Punch List 06/22/2016 A 08/22/2016 A 10

Project CProject Closeout 06/22/2016 A 08/01/2018 719B1445 Closeout Phase 06/22/2016 A 08/01/2018 719B1450 Issue SAC Letter 02/14/2017 A 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 06/22/2016 A 08/01/2018 120B1490 Project Closed 08/01/2018 0

Basin 0439Basin 0439 09/18/2014 A 08/01/2018 1535

100075 Pu100075 Pump Station 0439 Upgrade 09/18/2014 A 08/01/2018 1535DesignDesign 09/18/2014 A 07/18/2016 A 677

B1000 Design Phase 09/18/2014 A 07/18/2016 A 677B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 09/18/2014 A 09/19/2014 A 5B1020 Engage Design Consultant 10/07/2014 A 01/07/2015 A 20B1030 Issue Design NTP 01/07/2015 A 0B1040 A/E Develops and Submits Final Engineering Report 01/07/2015 A 06/08/2016 A 185B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 01/07/2015 A 03/18/2016 A 85

30% Des30% Design 01/08/2015 A 12/02/2015 A 312B1060 A/E Prepares 30% Construction Documents 01/08/2015 A 02/18/2015 A 30B1070 Geotechnical Engineering Services 01/08/2015 A 01/14/2015 A 20B1080 Surveying Services 01/08/2015 A 01/15/2015 A 15B1090 Engage VE Consultant 01/08/2015 A 01/08/2015 A 10B1100 30% CDs Submittal 02/18/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 02/19/2015 A 03/04/2015 A 10B1122 A/E Prepares 30% Construction Documents (Re-Design) 09/29/2015 A 11/05/2015 A 26B1124 30% CDs Submittal (Re-Design) 11/06/2015 A 0B1126 30% Review (MDWASD/PSIP Team) (Re-Design) 11/09/2015 A 12/02/2015 A 10

90% Des90% Design 02/19/2015 A 06/08/2016 A 487B1170 A/E Prepares 90% Construction Documents 02/19/2015 A 03/26/2015 A 20B1180 90% CDs Submittal 03/26/2015 A 0B1190 90% Review (MDWASD/PSIP Team) 03/27/2015 A 04/28/2015 A 15B1193 PSIP Revision to PER (VFD Removal/Pump Change) 04/29/2015 A 09/02/2015 A 15B1195 TA Rev 1 - Approval Process (VFD Removal/Pump Change) 09/03/2015 A 09/23/2015 A 20B1196 90% Plans Revision (VFD Removal/Pump Change) 11/09/2015 A 01/12/2016 A 26B1197 90% Plans Revision Review (MDWASD/PSIP Team) 01/13/2016 A 03/18/2016 A 15B1200 90% RER (DERM)FDEP Permit Submittal (Pump Station) 04/07/2016 A 0B1210 90% RER (DERM)FDEP Permit Review (Pump Station) 04/08/2016 A 05/16/2016 A 15B1212 90% RER (Building Dept) Permit Submittal (Pump Station) 05/23/2016 A 0B1214 90% RER (Building Dept) Permit Review (Pump Station) 05/23/2016 A 06/01/2016 A 15B1220 90% Aventura - BD Permit Submittal 05/20/2016 A 0B1230 90% Aventura - BD Permit Review 05/20/2016 A 06/08/2016 A 15B1260 90% CD PM Comments Evaluation Completed 06/08/2016 A 0

100% De100% Design 06/09/2016 A 07/18/2016 A 43B1270 A/E Prepares 100% Construction Documents 06/09/2016 A 07/18/2016 A 10B1280 100% CDs Submittal 07/18/2016 A 0B1290 100% Review (MDWASD/PSIP Team) 06/09/2016 A 07/18/2016 A 10B1300 Design Completed 07/18/2016 A 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Designer Construction Support Services10/31/2016 A, Construction Close Out

CommissioningPunch List

08/01/2018, Project Closeout

Closeout PhaseIssue SAC Letter

Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed08/01/2018, Basin 0439

08/01/2018, 100075 Pump Station 0439 Upgrade07/18/2016 A, Design

Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book

Engage Design ConsultantIssue Design NTP

A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

12/02/2015 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying ServicesEngage VE Consultant

30% CDs Submittal30% Review (MDWASD/PSIP Team)

A/E Prepares 30% Construction Documents (Re-Design)30% CDs Submittal (Re-Design)

30% Review (MDWASD/PSIP Team) (Re-Design)06/08/2016 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)PSIP Revision to PER (VFD Removal/Pump Change)

TA Rev 1 - Approval Process (VFD Removal/Pump Change)90% Plans Revision (VFD Removal/Pump Change)

90% Plans Revision Review (MDWASD/PSIP Team)90% RER (DERM)FDEP Permit Submittal (Pump Station)

90% RER (DERM)FDEP Permit Review (Pump Station)90% RER (Building Dept) Permit Submittal (Pump Station)90% RER (Building Dept) Permit Review (Pump Station)90% Aventura - BD Permit Submittal90% Aventura - BD Permit Review90% CD PM Comments Evaluation Completed

07/18/2016 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal

100% Review (MDWASD/PSIP Team)Design Completed

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 71 of 161 TASK filter: All Activities© Oracle Corporation

Page 72: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

MDWASDMDWASD Procurement 05/11/2016 A 08/19/2016 A 65B1305 Procurement Phase 05/11/2016 A 08/19/2016 A 65B1310 Submit CDs to MDWASD Procurement Division 05/11/2016 A 0B1312 Bid Notice Preparation Period 05/12/2016 A 05/24/2016 A 23B1314 Bid Notice 05/25/2016 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 05/26/2016 A 06/20/2016 A 10B1320 Pre-Bid Conference 06/21/2016 A 06/21/2016 A 1B1328 Bidders Prepare Bids for Submittal 06/22/2016 A 06/24/2016 A 15B1330 Bids Submittal 06/24/2016 A 0B1340 MDWASD/PSIP Team Bids Evaluation 06/27/2016 A 07/11/2016 A 15B1350 Recommendation for Award Letter 07/11/2016 A 0B1355 Contract Award (Purchase Order Approval) 07/12/2016 A 08/19/2016 A 10

ConstrucConstruction 06/21/2016 A 02/21/2017 A 930B1360 Construction Phase 06/21/2016 A 02/21/2017 A 930B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 07/12/2016 A 07/20/2016 A 15B1364 Pre-Construction Meeting 07/21/2016 A 07/21/2016 A 1B1369 WASD Issues NTP (PO to NTP) 08/20/2016 A 08/28/2016 A 53B1370 Construction NTP 08/29/2016 A 0B1400 Construction Operations 08/29/2016 A 02/21/2017 A 86B1400 Original Construction Duration 08/29/2016 A 12/27/2016 A 86B1400 Change Order #1 - Contractual Duration, Wet Well Hatcg Shopd 12/28/2016 A 02/16/2017 A 86B1402 Substantial Completion 02/21/2017 A 0

DesignerDesigner Construction Support Services 06/21/2016 A 02/21/2017 A 275B1410 Designer Construction Support Services 06/21/2016 A 02/21/2017 A 275

Project CProject Closeout 08/05/2016 A 08/01/2018 726B1445 Closeout Phase 08/05/2016 A 08/01/2018 726B1450 Issue SAC Leter 08/05/2016 A 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 02/22/2017 A 08/01/2018 120B1490 Project Closed 08/01/2018 0

Basin 0440Basin 0440 09/25/2014 A 03/21/2019 1445

100076-2 B100076-2 Basin 0440 Infiltration/Inflow Study and Repairs 09/25/2014 A 06/09/2016 A 463InfiltratioInfiltration/Inflow 09/25/2014 A 06/08/2016 A 451

B1000 Infiltration/Inflow Phase 09/25/2014 A 06/08/2016 A 451Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 10/23/2015 A 115

B1005 SSES Phase 09/25/2014 A 10/23/2015 A 115B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 06/22/2015 A 10/23/2015 A 30

Dig & ReDig & Replace Repairs 06/26/2015 A 06/08/2016 A 196B1165 Dig & Replace Phase 06/26/2015 A 06/08/2016 A 196B1180 Issue NTP for Dig & Replace Repairs 06/26/2015 A 0B1190 Conduct Dig & Replace Repairs 06/08/2016 A 06/08/2016 A 30

Project CProject Closeout 06/09/2016 A 06/09/2016 A 0B1235 Closeout Phase 06/09/2016 A 06/09/2016 A 0B1260 Project Closed 06/09/2016 A 0

100077 Pu100077 Pump Station 0440 Upgrade Phase 1 06/29/2015 A 08/01/2018 1128DesignDesign 06/29/2015 A 08/16/2016 A 381

B1000 Design Phase 06/29/2015 A 08/16/2016 A 381B1010 Prepare and Submit Design Package 06/29/2015 A 07/15/2015 A 5

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

08/19/2016 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid ConferenceBidders Prepare Bids for SubmittalBids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter

Contract Award (Purchase Order Approval)02/21/2017 A, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

WASD Issues NTP (PO to NTP)

Construction NTPConstruction Operations

Original Construction DurationChange Order #1 - Contractual Duration, Wet Well Hatcg Shopdrawing Approval

Substantial Completion02/21/2017 A, Designer Construction Support Services

Designer Construction Support Services08/01/2018, Project Closeout

Closeout PhaseIssue SAC Leter

Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed

03/21/2019, Basin 0440

06/09/2016 A, 100076-2 Basin 0440 Infiltration/Inflow Study and Repairs06/08/2016 A, Infiltration/Inflow

Infiltration/Inflow Phase10/23/2015 A, Sanitary Sewer Evaluation SurveySSES Phase

Issue NTP to SSES ContractorConduct SSES

06/08/2016 A, Dig & Replace RepairsDig & Replace Phase

Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs06/09/2016 A, Project CloseoutCloseout Phase

Project Closed08/01/2018, 100077 Pump Station 0440 Upgrade Phase 1

08/16/2016 A, Design

Design PhasePrepare and Submit Design Package

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 72 of 161 TASK filter: All Activities© Oracle Corporation

Page 73: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1020 Engage Design Consultant 06/29/2015 A 09/17/2015 A 20B1021 TA Preparation 09/18/2015 A 09/18/2015 A 1B1022 TA Approval Process 09/21/2015 A 09/25/2015 A 20B1030 Issue Design NTP 10/08/2015 A 0B1040 A/E Develops and Submits Final Engineering Report 10/08/2015 A 05/02/2016 A 101B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/08/2015 A 05/02/2016 A 86

30% Des30% Design 10/09/2015 A 12/23/2015 A 62B1060 A/E Prepares 30% Construction Documents 10/09/2015 A 12/09/2015 A 30B1070 Geotechnical Engineering Services 10/09/2015 A 12/09/2015 A 20B1080 Surveying Services 10/09/2015 A 12/09/2015 A 15B1100 30% CDs Submittal 12/09/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 12/10/2015 A 12/23/2015 A 10

90% Des90% Design 12/10/2015 A 08/16/2016 A 43B1170 A/E Prepares 90% Construction Documents 12/10/2015 A 04/06/2016 A 20B1180 90% CDs Submittal 04/06/2016 A 0B1190 90% Review (MDWASD/PSIP Team) 04/07/2016 A 05/02/2016 A 15B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 06/13/2016 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 06/13/2016 A 08/16/2016 A 15

Project CProject Closeout 09/09/2016 A 08/01/2018 762B1445 Closeout Phase 09/09/2016 A 08/01/2018 762B1448 Project Cancellation Approval Process 09/09/2016 A 09/20/2016 A 15B1480 Administrative Closeout 09/21/2016 A 08/01/2018 30B1490 Project Closed 08/01/2018 0

100245 Pu100245 Pump Station 0440 Upgrade Phase 2 10/30/2015 A 03/21/2019 1239Land AcqLand Acquisition 05/23/2016 A 05/04/2018 A 119

B0900 Land Acquisition Phase 05/23/2016 A 05/04/2018 A 119DesignDesign 10/30/2015 A 05/23/2018 A 946

B1000 Design Phase 10/30/2015 A 05/23/2018 A 946B1005 Prepare and Submit Design Package 10/30/2015 A 10/30/2015 A 5B1010 Engage Design Consultant 10/30/2015 A 01/27/2016 A 20B1018 TA Preparation 01/28/2016 A 01/28/2016 A 1B1020 TA Approval Process 01/29/2016 A 04/04/2016 A 20B1030 Issue Design NTP 04/14/2016 A 0B1031 WASD/PSIP Team Engage Design Consultant After 30% Subm 05/23/2016 A 12/01/2016 A 20B1032 TA Rev 1 Preparation 12/02/2016 A 12/02/2016 A 1B1034 TA Rev 1 Approval Process 12/05/2016 A 04/03/2017 A 40B1036 Issue 90% Design NTP 04/17/2017 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 04/14/2016 A 05/23/2018 A 85

30% Des30% Design 04/14/2016 A 06/20/2016 A 33B1060 A/E Prepares 30% Construction Documents 04/14/2016 A 05/20/2016 A 30B1070 Geotechnical Engineering Services 04/14/2016 A 05/20/2016 A 20B1080 Surveying Services 04/14/2016 A 05/20/2016 A 15B1100 30% CDs Submittal 05/20/2016 A 0B1120 30% Review (MDWASD/PSIP Team) 05/23/2016 A 06/20/2016 A 10

90% Des90% Design 04/17/2017 A 05/23/2018 A 424B1170 A/E Prepares 90% Construction Documents 04/17/2017 A 06/30/2017 A 40B1180 90% CDs Submittal 06/30/2017 A 0B1190 90% Review (MDWASD/PSIP Team) 07/03/2017 A 08/14/2017 A 30B1200 90% RER (DERM) FDEP Permit Submittal 10/02/2017 A 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Engage Design ConsultantTA PreparationTA Approval Process

Issue Design NTPA/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

12/23/2015 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal30% Review (MDWASD/PSIP Team)

08/16/2016 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)

90% RER(DERM)FDEP Permit Review (Pump Station)08/01/2018, Project Closeout

Closeout PhaseProject Cancellation Approval Process

Administrative CloseoutProject Closed

03/21/2019, 100245 Pump Station 0440 U05/04/2018 A, Land Acquisition

Land Acquisition Phase05/23/2018 A, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval ProcessIssue Design NTP

WASD/PSIP Team Engage Design Consultant After 30% SubmittalTA Rev 1 Preparation

TA Rev 1 Approval Process

Issue 90% Design NTPFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

06/20/2016 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal

30% Review (MDWASD/PSIP Team)05/23/2018 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER (DERM) FDEP Permit Submittal

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 73 of 161 TASK filter: All Activities© Oracle Corporation

Page 74: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1210 90% RER (DERM) FDEP Permit Review 10/02/2017 A 03/30/2018 A 45B1220 90% Miami Garden (Building Dept) Permit Submittal 04/04/2018 A 0B1230 90% Miami Garden (Building Dept) Permit Review 04/04/2018 A 05/23/2018 A 21B1260 90% CD PM Comments Evaluation Completed 05/23/2018 A 0B1262 MDWASD Union Concurrence Process 07/06/2017 A 07/31/2017 A 30

100% De100% Design 05/02/2018 A 05/04/2018 A 28B1270 A/E Prepares 100% Construction Documents 05/02/2018 A 05/04/2018 A 14B1280 100% CDs Submittal 05/04/2018 A 0B1290 100% Review (MDWASD/PSIP Team) 05/04/2018 A 05/04/2018 A 14B1300 Design Completed 05/04/2018 A 0

MDWASDMDWASD Procurement 06/08/2018 A 10/05/2018 127B1305 Procurement Phase 06/08/2018 A 10/05/2018 127B1310 Submit CDs to MDWASD Procurement Division 06/08/2018 A 0B1312 Bid Notice Preparation Period 06/09/2018 A 06/28/2018 A 33B1313 Bid Notice 06/28/2018 A 0B1315 MDWASD/PSIP Team Prepare for Pre-Bid Conferencce 06/29/2018 A 07/16/2018 A 14B1320 Pre-Bid Conference 07/17/2018 A 07/17/2018 A 1B1323 Bidders Prepare Bids for Submittal 07/18/2018 A 08/31/2018 21B1324 FPL Feeder Route Resolution 06/08/2018 A 08/31/2018 21B1330 Bids Submittal 08/31/2018 0B1340 MDWASD/PSIP Team Bids Evaluation 09/01/2018 09/21/2018 21B1350 Recommendation for Award Letter 09/21/2018 0B1355 Contract Award (Purchase Order Approval) 09/22/2018 10/05/2018 14B1480 Bidders Prepare Bids for Submittal 07/18/2018 A 08/17/2018 21

ConstrucConstruction 07/17/2018 A 11/22/2018 119B1357 Construction Phase 07/17/2018 A 11/22/2018 119B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 09/22/2018 10/06/2018 15B1365 Pre-Construction Meeting 10/07/2018 10/07/2018 1B1366 WASD Issues NTP (Pre-Const to NTP) 10/08/2018 11/21/2018 45B1368 WASD Issues NTP (PO to NTP) 10/06/2018 11/21/2018 47B1369 Construction NTP 11/22/2018 0B1390 Construction Operations 11/22/2018 11/22/2018 0B1395 Substantial Completion 11/22/2018 0

DesignerDesigner Construction Support Services 07/17/2018 A 11/21/2018 104B1397 Designer Construction Support Services 07/17/2018 A 11/21/2018 104

Project CProject Closeout 08/05/2016 A 03/21/2019 958B1425 Closeout Phase 08/05/2016 A 03/21/2019 958B1430 Issue SAC Letter 08/05/2016 A 0B1450 Final Release of Retainage - Construction Contract 11/22/2018 0B1460 Administrative Closeout 11/22/2018 03/21/2019 120B1470 Project Closed 03/21/2019 0

Basin 0442Basin 0442 04/19/2016 A 12/13/2019 1188

100078 Pu100078 Pump Station 0442 Upgrade 04/19/2016 A 12/13/2019 1188DesignDesign 04/19/2016 A 09/18/2018 737

B1000 Design Phase 04/19/2016 A 09/18/2018 737B1010 Prepare and Submit Design Package 04/19/2016 A 04/22/2016 A 5B1020 Engage Design Consultant 04/22/2016 A 09/13/2016 A 20B1022 TA Preparation 09/14/2016 A 09/14/2016 A 1B1024 TA Approval Process 09/15/2016 A 11/15/2016 A 20

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

90% RER (DERM) FDEP Permit Review90% Miami Garden (Building Dept) Permit Submittal

90% Miami Garden (Building Dept) Permit Review90% CD PM Comments Evaluation Completed

MDWASD Union Concurrence Process05/04/2018 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal

100% Review (MDWASD/PSIP Team)Design Completed

10/05/2018, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferenccePre-Bid Conference

Bidders Prepare Bids for SubmittalFPL Feeder Route Resolution

Bids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)

Bidders Prepare Bids for Submittal11/22/2018, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)

WASD Issues NTP (PO to NTP)Construction NTPConstruction OperationsSubstantial Completion11/21/2018, Designer Construction Support Services

Designer Construction Support Services03/21/2019, Project Closeout

Closeout PhaseIssue SAC Letter

Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed

12/13/2019, Basin 04

12/13/2019, 100078 09/18/2018, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval Process

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 74 of 161 TASK filter: All Activities© Oracle Corporation

Page 75: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1030 Issue Design NTP 11/18/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 11/18/2016 A 08/21/2018 65

30% Des30% Design 11/18/2016 A 05/08/2017 A 107B1060 A/E Prepares 30% Construction Documents 11/18/2016 A 02/09/2017 A 50B1100 30% CDs Submittal 02/09/2017 A 0B1120 30% Review (MDWASD/PSIP Team) 02/10/2017 A 05/08/2017 A 30

90% Des90% Design 02/10/2017 A 08/21/2018 567B1170 A/E Prepares 90% Construction Documents 02/10/2017 A 06/30/2017 A 40B1180 90% CDs Submittal 06/30/2017 A 0B1190 90% Review (MDWASD/PSIP Team) 07/03/2017 A 07/25/2017 A 30B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 08/28/2017 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 08/28/2017 A 02/22/2018 A 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 02/22/2018 A 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 02/22/2018 A 08/01/2018 21B1240 90% Miami Gardens - PWD Permit Submittal (Pump Station) 08/01/2018 0B1250 90% Miami Gardens - PWD Permit Review (Pump Station) 08/01/2018 08/21/2018 21B1252 90% Miami Gardens - BD Permit Submittal (Pump Station) 08/01/2018 0B1254 90% Miami Gardens - BD Permit Review (Pump Station) 08/01/2018 08/21/2018 21B1260 90% CD PM Comments Evaluation Completed 08/21/2018 0B1262 MDWASD Union Concurrence Process 07/06/2017 A 07/31/2017 A 30

100% De100% Design 08/22/2018 09/18/2018 28B1270 A/E Prepares 100% Construction Documents 08/22/2018 09/04/2018 14B1280 100% CDs Submittal 09/04/2018 0B1290 100% Review (MDWASD/PSIP Team) 09/05/2018 09/18/2018 14B1300 Design Completed 09/18/2018 0

MDWASDMDWASD Procurement 09/18/2018 12/31/2018 104B1305 Procurement Phase 09/18/2018 12/31/2018 104B1310 Submit CDs to MDWASD Procurement Division 09/18/2018 0B1312 Bid Notice Preparation Period 09/19/2018 10/21/2018 33B1314 Bid Notice 10/21/2018 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 10/22/2018 11/04/2018 14B1320 Pre-Bid Conference 11/05/2018 11/05/2018 1B1322 Bidders Prepare Bids for Submittal 11/06/2018 11/26/2018 21B1330 Bids Submittal 11/26/2018 0B1340 MDWASD/PSIP Team Bids Evaluation 11/27/2018 12/17/2018 21B1350 Recommendation for Award Letter 12/17/2018 0B1355 Contract Award (Purchase Order Approval) 12/18/2018 12/31/2018 14

ConstrucConstruction 11/05/2018 08/15/2019 284B1360 Construction Phase 11/05/2018 08/15/2019 284B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 12/18/2018 01/01/2019 15B1364 Pre-Construction Meeting 01/02/2019 01/02/2019 1B1366 WASD Issues NTP (Pre-Const to NTP) 01/03/2019 02/16/2019 45B1368 WASD Issues NTP (PO to NTP) 01/01/2019 02/16/2019 47B1370 Construction NTP 02/17/2019 0B1400 Construction Operations 02/17/2019 08/15/2019 180B1402 Substantial Completion 08/15/2019 0

DesignerDesigner Construction Support Services 11/05/2018 08/15/2019 284B1410 Designer Construction Support Services 11/05/2018 08/15/2019 284

Project CProject Closeout 08/15/2019 12/13/2019 120

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Issue Design NTPFinal Engineering Report Review & Approval (MDWASD/PSIP

05/08/2017 A, 30% Design

A/E Prepares 30% Construction Documents30% CDs Submittal

30% Review (MDWASD/PSIP Team)08/21/2018, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)

90% RER(DERM)FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)

90% RER(Building Dept) Permit Review (Pump Station)90% Miami Gardens - PWD Permit Submittal (Pump Station)

90% Miami Gardens - PWD Permit Review (Pump Station)90% Miami Gardens - BD Permit Submittal (Pump Station)

90% Miami Gardens - BD Permit Review (Pump Station)90% CD PM Comments Evaluation Completed

MDWASD Union Concurrence Process09/18/2018, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed

12/31/2018, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)

08/15/2019, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-ConstructioPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Construction NTPConstruction OperationsSubstantial Completion08/15/2019, Designer Construc

Designer Construction Support 12/13/2019, Project C

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 75 of 161 TASK filter: All Activities© Oracle Corporation

Page 76: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1445 Closeout Phase 08/15/2019 12/13/2019 120B1450 Issue SAC Letter 08/15/2019 0B1470 Final Release of Retainage - Construction Contract 08/15/2019 0B1480 Administrative Closeout 08/16/2019 12/13/2019 120B1490 Project Closed 12/13/2019 0

Basin 0449Basin 0449 05/14/2014 A 08/01/2018 1680

100082 Pu100082 Pump Station 0449 Upgrade (PS 460) 05/14/2014 A 01/05/2015 A 19PlanningPlanning 05/14/2014 A 01/05/2015 A 19

B0900 Planning Phase 05/14/2014 A 01/05/2015 A 19B0940 Develop Remedial Action Plan (RAP) 05/14/2014 A 05/22/2014 A 7B0950 Develop Preliminary Engineering Report (PER) 05/15/2014 A 01/05/2015 A 10

100080 FM100080 FM for Pump Station 0449 (PS 460) 05/14/2014 A 01/05/2015 A 19PlanningPlanning 05/14/2014 A 01/05/2015 A 19

B0900 Planning Phase 05/14/2014 A 01/05/2015 A 19B0940 Develop Remedial Action Plan (RAP) 05/14/2014 A 05/22/2014 A 7B0950 Develop Preliminary Engineering Report (PER) 05/23/2014 A 01/05/2015 A 10

100083 Pu100083 Pump Station 0449 Upgrade 07/30/2014 A 08/01/2018 1601DesignDesign 07/30/2014 A 05/26/2016 A 728

B1000 Design Phase 07/30/2014 A 05/26/2016 A 728B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 07/30/2014 A 08/07/2014 A 5B1020 Engage Design Consultant 08/08/2014 A 11/19/2014 A 20B1030 Issue Design NTP 11/20/2014 A 0B1040 A/E Develops and Submits Final Engineering Report 11/20/2014 A 05/09/2016 A 279B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 11/20/2014 A 11/27/2015 A 228

30% Des30% Design 11/20/2014 A 02/13/2015 A 56B1060 A/E Prepares 30% Construction Documents 11/20/2014 A 01/21/2015 A 30B1070 Geotechnical Engineering Services 11/20/2014 A 01/21/2015 A 20B1080 Surveying Services 11/20/2014 A 01/21/2015 A 15B1100 30% CDs Submittal 01/21/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 01/22/2015 A 02/13/2015 A 10

60% Des60% Design 01/22/2015 A 02/13/2015 A 24B1130 A/E Prepares 60% Construction Documents (Progress Set) 01/22/2015 A 02/13/2015 A 20B1140 60% CDs Submittal (Progress Set) 02/13/2015 A 0B1160 60% On-Board Review (Progress Set) 02/13/2015 A 02/13/2015 A 10

90% Des90% Design 02/16/2015 A 05/09/2016 A 487B1170 A/E Prepares 90% Construction Documents 02/16/2015 A 06/15/2015 A 20B1171 FM 0449 - TA Rev 1 Submission and Approval 02/18/2015 A 04/03/2015 A 20B1172 FM 0449 - Add FM to Project 04/06/2015 A 05/29/2015 A 20B1180 90% CDs Submittal 06/15/2015 A 0B1190 90% Review (MDWASD/PSIP Team) 06/15/2015 A 11/27/2015 A 15B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 11/30/2015 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 11/30/2015 A 03/01/2016 A 15B1220 90% Miami Gardens - BD Permit Submittal 03/02/2016 A 0B1230 90% Miami Gardens - BD Permit Review 03/02/2016 A 05/09/2016 A 15B1260 90% CD PM Comments Evaluation Completed 05/09/2016 A 0

100% De100% Design 05/10/2016 A 05/26/2016 A 28B1270 A/E Prepares 100% Construction Documents 05/10/2016 A 05/26/2016 A 10B1280 100% CDs Submittal 05/26/2016 A 0B1290 100% Review (MDWASD/PSIP Team) 05/10/2016 A 05/26/2016 A 10

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Closeout PhaseIssue SAC LetterFinal Release of Retainage - Co

Administrative CloseoProject Closed

08/01/2018, Basin 0449

01/05/2015 A, 100082 Pump Station 0449 Upgrade (PS 460)01/05/2015 A, PlanningPlanning Phase

Develop Remedial Action Plan (RAP)Develop Preliminary Engineering Report (PER)01/05/2015 A, 100080 FM for Pump Station 0449 (PS 460)01/05/2015 A, PlanningPlanning Phase

Develop Remedial Action Plan (RAP)Develop Preliminary Engineering Report (PER)

08/01/2018, 100083 Pump Station 0449 Upgrade05/26/2016 A, Design

Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book

Engage Design ConsultantIssue Design NTP

A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

02/13/2015 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services

30% CDs Submittal30% Review (MDWASD/PSIP Team)02/13/2015 A, 60% Design

A/E Prepares 60% Construction Documents (Progress Set)60% CDs Submittal (Progress Set)60% On-Board Review (Progress Set)

05/09/2016 A, 90% Design

A/E Prepares 90% Construction DocumentsFM 0449 - TA Rev 1 Submission and Approval

FM 0449 - Add FM to Project90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)

90% RER(DERM)FDEP Permit Review (Pump Station)90% Miami Gardens - BD Permit Submittal90% Miami Gardens - BD Permit Review

90% CD PM Comments Evaluation Completed05/26/2016 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal

100% Review (MDWASD/PSIP Team)

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 76 of 161 TASK filter: All Activities© Oracle Corporation

Page 77: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1300 Design Completed 05/26/2016 A 0MDWASDMDWASD Procurement 03/02/2016 A 07/06/2016 A 97

B1305 Procurement Phase 03/02/2016 A 07/06/2016 A 97B1310 Submit CDs to MDWASD Procurement Division 03/02/2016 A 0B1312 Bid Notice Preparation Period 03/03/2016 A 03/15/2016 A 23B1314 Bid Notice 03/15/2016 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 03/16/2016 A 04/05/2016 A 10B1320 Pre-Bid Conference 04/06/2016 A 04/06/2016 A 1B1322 Bidders Prepare Bids for Submittal 04/07/2016 A 05/13/2016 A 15B1330 Bids Submittal 05/16/2016 A 0B1340 MDWASD/PSIP Team Bids Evaluation 05/13/2016 A 05/24/2016 A 15B1350 Recommendation for Award Letter 05/25/2016 A 0B1355 Contract Award (Purchase Order Approval) 05/26/2016 A 07/06/2016 A 10

ConstrucConstruction 04/06/2016 A 01/18/2017 A 960B1360 Construction Phase 04/06/2016 A 01/18/2017 A 960B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 05/26/2016 A 07/06/2016 A 15B1365 Pre-Construction Meeting 07/07/2016 A 07/07/2016 A 1B1366 TA Rev 2 - Approval Process 07/11/2016 A 09/28/2016 A 20B1369 WASD Issues NTP (PO to NTP) 07/07/2016 A 07/31/2016 A 53B1370 Construction NTP 08/01/2016 A 0B1400 Construction Operations 08/01/2016 A 12/28/2016 A 107B1402 Substantial Completion 12/28/2016 A 0

DesignerDesigner Construction Support Services 04/06/2016 A 01/18/2017 A 275B1410 Designer Construction Support Services 04/06/2016 A 01/18/2017 A 275

ConstrucConstruction Close Out 12/29/2016 A 01/18/2017 A 15B1420 Commissioning 12/29/2016 A 01/18/2017 A 15B1430 Punch List 12/29/2016 A 01/11/2017 A 10

Project CProject Closeout 08/05/2016 A 08/01/2018 726B1445 Closeout Phase 08/05/2016 A 08/01/2018 726B1450 Issue SAC Letter 08/05/2016 A 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 12/29/2016 A 08/01/2018 120B1490 Project Closed 08/01/2018 0

Basin 0456Basin 0456 09/25/2014 A 02/02/2020 1946

100084 Pu100084 Pump Station 0456 Upgrade 01/08/2018 A 04/30/2019 485DesignDesign 01/08/2018 A 08/31/2018 243

B1000 Design Phase 01/08/2018 A 08/31/2018 243B1010 Prepare and Submit Design Package 01/08/2018 A 01/08/2018 A 7B1020 Engage Design Consultant 01/09/2018 A 02/05/2018 A 28B1022 TA Preparation 02/06/2018 A 02/07/2018 A 7B1024 TA Approval Process 02/08/2018 A 03/17/2018 A 20B1030 Issue Design NTP 03/26/2018 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 03/26/2018 A 08/17/2018 80

30% Des30% Design 03/26/2018 A 08/01/2018 149B1060 A/E Prepares 30% Construction Documents 03/26/2018 A 05/15/2018 A 21B1100 30% CDs Submittal 05/15/2018 A 0B1120 30% Review (MDWASD/PSIP Team) 08/01/2018 08/01/2018 1

90% Des90% Design 03/26/2018 A 08/17/2018 108B1170 A/E Prepares 90% Construction Documents 03/26/2018 A 05/15/2018 A 22

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Design Completed07/06/2016 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids SubmittalMDWASD/PSIP Team Bids Evaluation

Recommendation for Award LetterContract Award (Purchase Order Approval)

01/18/2017 A, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

TA Rev 2 - Approval ProcessWASD Issues NTP (PO to NTP)

Construction NTPConstruction OperationsSubstantial Completion

01/18/2017 A, Designer Construction Support Services

Designer Construction Support Services01/18/2017 A, Construction Close Out

CommissioningPunch List

08/01/2018, Project Closeout

Closeout PhaseIssue SAC Letter

Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed

02/02/2020, Basin

04/30/2019, 100084 Pump Station 04508/31/2018, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval Process

Issue Design NTPFinal Engineering Report Review & Approval (MDWASD/PSIP

08/01/2018, 30% Design

A/E Prepares 30% Construction Documents30% CDs Submittal

30% Review (MDWASD/PSIP Team)08/17/2018, 90% Design

A/E Prepares 90% Construction Documents

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 77 of 161 TASK filter: All Activities© Oracle Corporation

Page 78: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1180 90% CDs Submittal 05/15/2018 A 0B1190 90% Review (MDWASD/PSIP Team) 05/16/2018 A 06/14/2018 A 7B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 06/15/2018 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 06/15/2018 A 08/02/2018 15B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 08/03/2018 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 08/03/2018 08/17/2018 15B1260 90% CD PM Comments Evaluation Completed 08/17/2018 0

100% De100% Design 08/18/2018 08/31/2018 14B1270 A/E Prepares 100% Construction Documents 08/18/2018 08/24/2018 7B1280 100% CDs Submittal 08/24/2018 0B1290 100% Review (MDWASD/PSIP Team) 08/25/2018 08/31/2018 7B1300 Design Completed 08/31/2018 0

MDWASDMDWASD Procurement 08/31/2018 10/27/2018 57B1305 Procurement Phase 08/31/2018 10/27/2018 57B1310 Submit CDs to MDWASD Procurement Division 08/31/2018 0B1312 Bid Notice Preparation Period 09/01/2018 09/20/2018 20B1314 Bid Notice 09/20/2018 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conferencce 09/21/2018 09/27/2018 7B1320 Pre-Bid Conference 09/28/2018 09/28/2018 1B1328 Bidders Prepare Bids for Submittal 09/29/2018 10/13/2018 15B1330 Bids Submittal 10/13/2018 0B1340 MDWASD/PSIP Team Bids Evaluation 10/14/2018 10/20/2018 7B1350 Recommendation for Award Letter 10/20/2018 0B1355 Contract Award (Purchase Order Approval) 10/21/2018 10/27/2018 7

ConstrucConstruction 09/28/2018 12/31/2018 95B1360 Construction Phase 09/28/2018 12/31/2018 95B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 10/21/2018 11/10/2018 21B1364 Pre-Construction Meeting 11/11/2018 11/11/2018 1B1366 WASD Issues NTP (Pre-Const to NTP) 11/12/2018 11/25/2018 14B1368 WASD Issues NTP (PO to NTP) 10/28/2018 11/25/2018 29B1370 Construction NTP 11/26/2018 0B1400 Construction Operations 11/26/2018 12/31/2018 36B1402 Substantial Completion 12/31/2018 0

DesignerDesigner Construction Support Services 09/28/2018 12/31/2018 95B1410 Designer Construction Support Services 09/28/2018 12/31/2018 95

Project CProject Closeout 12/31/2018 04/30/2019 120B1445 Closeout Phase 12/31/2018 04/30/2019 120B1450 Issue SAC Letter 12/31/2018 0B1470 Final Release of Retainage - Construction Contract 12/31/2018 0B1480 Administrative Closeout 01/01/2019 04/30/2019 120B1490 Project Closed 04/30/2019 0

100085 Pu100085 Pump Station 0456 Upgrade (PS 0454 Generator) 12/14/2017 A 02/02/2020 780DesignDesign 08/01/2018 06/08/2019 312

B1000 Design Phase 08/01/2018 06/08/2019 312B1010 Prepare and Submit Design Package 08/01/2018* 08/05/2018 5B1020 Engage Design Consultant 08/06/2018 08/25/2018 20B1022 TA Preparation 08/26/2018 08/26/2018 1B1024 TA Approval Process 08/27/2018 10/05/2018 40B1030 Issue Design NTP 10/06/2018 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

90% CDs Submittal90% Review (MDWASD/PSIP Team)

90% RER(DERM)FDEP Permit Submittal (Pump Station)90% RER(DERM)FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)90% RER(Building Dept) Permit Review (Pump Station)90% CD PM Comments Evaluation Completed08/31/2018, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed

10/27/2018, MDWASD ProcurementProcurement Phase

Submit CDs to MDWASD Procurement DivisionBid Notice Preparation Period

Bid NoticeMDWASD/PSIP Team Prepare for Pre-Bid Conferencce

Pre-Bid ConferenceBidders Prepare Bids for Submittal

Bids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)

12/31/2018, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MPre-Construction MeetingWASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Construction NTPConstruction OperationsSubstantial Completion12/31/2018, Designer Construction Support Servic

Designer Construction Support Services04/30/2019, Project CloseoutCloseout Phase

Issue SAC LetterFinal Release of Retainage - Construction Contrac

Administrative CloseoutProject Closed

02/02/2020, 100006/08/2019, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval Process

Issue Design NTP

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 78 of 161 TASK filter: All Activities© Oracle Corporation

Page 79: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/06/2018 05/09/2019 21630% Des30% Design 10/06/2018 12/24/2018 80

B1060 A/E Prepares 30% Construction Documents 10/06/2018 11/24/2018 50B1090 30% CDs Submittal 11/24/2018 0B1100 30% Review (MDWASD/PSIP Team) 11/25/2018 12/24/2018 30

60% Des60% Design 11/25/2018 01/03/2019 40B1110 A/E Prepares 60% Construction Documents 11/25/2018 12/24/2018 30B1120 60% CDs Submittal 12/24/2018 0B1140 60% Review (MDWASD/PSIP Team) 12/25/2018 01/03/2019 10

90% Des90% Design 12/25/2018 06/08/2019 166B1150 A/E Prepares 90% Construction Documents 12/25/2018 02/02/2019 40B1160 90% CDs Submittal 02/02/2019 0B1170 90% Review (MDWASD/PSIP Team) 02/03/2019 03/04/2019 30B1180 90% RER(DERM)FDEP Permit Submittal (Pump Station) 03/05/2019 0B1190 90% RER(DERM)FDEP Permit Review (Pump Station) 03/05/2019 04/18/2019 45B1200 90% RER(Building Dept) Permit Submittal (Pump Station) 04/19/2019 0B1210 90% RER(Building Dept) Permit Review (Pump Station) 04/19/2019 05/09/2019 21B1220 90% Municipality Permit Submittal (Pump Station) 04/19/2019 0B1230 90% Municipality Permit Review (Pump Station) 04/19/2019 05/03/2019 15B1240 90% CD PM Comments Evaluation Completed 05/09/2019 0B1242 MDWASD Union Concurrence Process 05/10/2019 06/08/2019 30

100% De100% Design 05/10/2019 05/29/2019 20B1250 A/E Prepares 100% Construction Documents 05/10/2019 05/19/2019 10B1260 100% CDs Submittal 05/19/2019 0B1270 100% Review (MDWASD/PSIP Team) 05/20/2019 05/29/2019 10B1280 Design Completed 05/29/2019 0

MDWASDMDWASD Procurement 06/08/2019 08/21/2019 74B1285 Procurement Phase 06/08/2019 08/21/2019 74B1290 Submit CDs to MDWASD Procurement Division 06/08/2019 0B1292 Bid Notice Preparation Period 06/09/2019 07/01/2019 23B1294 Bid Notice 07/01/2019 0B1296 MDWASD/PSIP Team Prepare for Pre-Bid Conferencce 07/02/2019 07/11/2019 10B1300 Pre-Bid Conference 07/12/2019 07/12/2019 1B1302 Bidders Prepare Bids for Submittal 07/13/2019 07/27/2019 15B1310 Bids Submittal 07/27/2019 0B1320 MDWASD/PSIP Team Bids Evaluation 07/28/2019 08/11/2019 15B1330 Recommendation for Award Letter 08/11/2019 0B1335 Contract Award (Purchase Order Approval) 08/12/2019 08/21/2019 10

ConstrucConstruction 07/12/2019 01/13/2020 186B1340 Construction Phase 07/12/2019 01/13/2020 186B1342 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 08/12/2019 08/26/2019 15B1344 Pre-Construction Meeting 08/27/2019 08/27/2019 1B1350 Construction NTP 08/28/2019 0B1380 Construction Operations 08/28/2019 01/03/2020 129B1382 Substantial Completion 01/03/2020 0

DesignerDesigner Construction Support Services 07/12/2019 01/13/2020 186B1390 Designer Construction Support Services 07/12/2019 01/13/2020 186

ConstrucConstruction Close Out 01/04/2020 01/13/2020 10B1400 Commissioning 01/04/2020 01/08/2020 5

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Final Engineering Report Review & App12/24/2018, 30% Design

A/E Prepares 30% Construction Documents30% CDs Submittal

30% Review (MDWASD/PSIP Team)01/03/2019, 60% Design

A/E Prepares 60% Construction Documents60% CDs Submittal60% Review (MDWASD/PSIP Team)

06/08/2019, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pu

90% RER(DERM)FDEP Permit Review (P90% RER(Building Dept) Permit Submitta

90% RER(Building Dept) Permit Review 90% Municipality Permit Submittal (Pump90% Municipality Permit Review (Pump 90% CD PM Comments Evaluation Com

MDWASD Union Concurrence Proces05/29/2019, 100% Design

A/E Prepares 100% Construction Docu100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed

08/21/2019, MDWASD ProcureProcurement Phase

Submit CDs to MDWASD ProcuremeBid Notice Preparation Period

Bid NoticeMDWASD/PSIP Team Prepare for

Pre-Bid ConferenceBidders Prepare Bids for Submitt

Bids SubmittalMDWASD/PSIP Team Bids EvalRecommendation for Award LetContract Award (Purchase Orde

01/13/2020, Constr

Construction PhaseMDWASD/PSIP Team PreparePre-Construction Meeting

Construction NTPConstruction OperatSubstantial Complet01/13/2020, Design

Designer Construct01/13/2020, Constr

Commissioning

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 79 of 161 TASK filter: All Activities© Oracle Corporation

Page 80: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1410 Punch List 01/04/2020 01/13/2020 10Project CProject Closeout 12/14/2017 A 02/02/2020 780

B1425 Closeout Phase 12/14/2017 A 02/02/2020 780B1430 Issue SAC Letter 12/14/2017 A 0B1450 Final Release of Retainage - Construction Contract 01/13/2020 0B1460 Administrative Closeout 01/04/2020 02/02/2020 30B1470 Project Closed 02/02/2020 0

100187 Ba100187 Basin 0456 Infiltration/Inflow Study and Repairs 09/25/2014 A 09/04/2015 A 604InfiltratioInfiltration/Inflow 09/25/2014 A 09/03/2015 A 331

B1000 Infiltration/Inflow Phase 09/25/2014 A 09/03/2015 A 331Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 09/03/2015 A 331

B1005 SSES Phase 09/25/2014 A 09/03/2015 A 331B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 07/30/2015 A 09/03/2015 A 30

Project CProject Closeout 09/04/2015 A 09/04/2015 A 0B1235 Closeout Phase 09/04/2015 A 09/04/2015 A 0B1260 Project Closed 09/04/2015 A 0

Basin 0473Basin 0473 12/09/2015 A 08/01/2018 1067

100086 Pu100086 Pump Station 0473(AM) Upgrade 12/09/2015 A 08/01/2018 1067DesignDesign 12/09/2015 A 12/15/2016 A 393

B1000 Design Phase 12/09/2015 A 12/15/2016 A 393B1010 Prepare and Submit Design Package 12/09/2015 A 12/16/2015 A 5B1020 Engage Design Consultant 12/17/2015 A 12/28/2015 A 20B1022 TA Preparation 12/29/2015 A 12/29/2015 A 1B1024 TA Approval Process 12/30/2015 A 01/14/2016 A 20B1030 Issue Design NTP 01/27/2016 A 0B1040 A/E Develops and Submits Final Engineering Report 01/27/2016 A 12/07/2016 A 115B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 01/27/2016 A 08/25/2016 A 85

30% Des30% Design 01/27/2016 A 04/25/2016 A 52B1060 A/E Prepares 30% Construction Documents 01/27/2016 A 03/15/2016 A 30B1070 Geotechnical Engineering Services 01/27/2016 A 03/15/2016 A 20B1080 Surveying Services 01/27/2016 A 03/15/2016 A 15B1100 30% CDs Submittal 03/15/2016 A 0B1120 30% Review (MDWASD/PSIP Team) 03/15/2016 A 04/25/2016 A 10

60% Des60% Design 03/16/2016 A 06/20/2016 A 99B1130 A/E Prepares 60% Construction Documents 03/16/2016 A 05/24/2016 A 20B1140 60% CDs Submittal 05/24/2016 A 0B1160 60% Review (MDWASD/PSIP Team) 05/25/2016 A 06/20/2016 A 10

90% Des90% Design 05/25/2016 A 12/07/2016 A 190B1170 A/E Prepares 90% Construction Documents 05/25/2016 A 07/22/2016 A 20B1180 90% CDs Submittal 07/22/2016 A 0B1190 90% Review (MDWASD/PSIP Team) 07/25/2016 A 09/14/2016 A 15B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 09/26/2016 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 09/26/2016 A 11/30/2016 A 15B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 11/09/2016 A 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 11/09/2016 A 12/07/2016 A 15B1260 90% CD PM Comments Evaluation Completed 12/07/2016 A 0

100% De100% Design 12/08/2016 A 12/15/2016 A 28B1270 A/E Prepares 100% Construction Documents 12/08/2016 A 12/13/2016 A 10

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Punch List02/02/2020, ProjeCloseout Phase

Issue SAC LetterFinal Release of Re

Administrative CloProject Closed

09/04/2015 A, 100187 Basin 0456 Infiltration/Inflow Study and Repairs09/03/2015 A, Infiltration/Inflow

Infiltration/Inflow Phase09/03/2015 A, Sanitary Sewer Evaluation SurveySSES Phase

Issue NTP to SSES ContractorConduct SSES09/04/2015 A, Project CloseoutCloseout Phase

Project Closed08/01/2018, Basin 0473

08/01/2018, 100086 Pump Station 0473(AM) Upgrade12/15/2016 A, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval ProcessIssue Design NTP

A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

04/25/2016 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal

30% Review (MDWASD/PSIP Team)06/20/2016 A, 60% Design

A/E Prepares 60% Construction Documents60% CDs Submittal60% Review (MDWASD/PSIP Team)

12/07/2016 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)

90% RER(DERM)FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)

90% RER(Building Dept) Permit Review (Pump Station)90% CD PM Comments Evaluation Completed12/15/2016 A, 100% Design

A/E Prepares 100% Construction Documents

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 80 of 161 TASK filter: All Activities© Oracle Corporation

Page 81: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1280 100% CDs Submittal 12/13/2016 A 0B1290 100% Review (MDWASD/PSIP Team) 12/13/2016 A 12/15/2016 A 10B1300 Design Completed 12/15/2016 A 0

MDWASDMDWASD Procurement 12/15/2016 A 03/27/2017 A 57B1305 Procurement Phase 12/15/2016 A 03/27/2017 A 57B1310 Submit CDs to MDWASD Procurement Division 12/15/2016 A 0B1312 Bid Notice Preparation Period 12/16/2016 A 12/20/2016 A 23B1314 Bid Notice 12/20/2016 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 12/21/2016 A 01/09/2017 A 10B1320 Pre-Bid Conference 01/10/2017 A 01/10/2017 A 1B1328 Bidders Prepare Bids for Submittal 01/11/2017 A 01/30/2017 A 14B1330 Bids Submittal 01/30/2017 A 0B1340 MDWASD/PSIP Team Bids Evaluation 01/31/2017 A 02/16/2017 A 15B1350 Recommendation for Award Letter 02/17/2017 A 0B1355 Contract Award (Purchase Order Approval) 02/20/2017 A 03/27/2017 A 10

ConstrucConstruction 01/10/2017 A 01/18/2018 A 669B1360 Construction Phase 01/10/2017 A 01/18/2018 A 669B1364 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 02/20/2017 A 03/31/2017 A 15B1366 Pre-Construction Meeting 04/03/2017 A 04/03/2017 A 1B1368 WASD Issues NTP (Pre-Const to NTP) 04/03/2017 A 06/23/2017 A 59B1369 WASD Issues NTP (PO to NTP) 03/27/2017 A 06/23/2017 A 29B1370 Construction NTP 06/26/2017 A 0B1400 Construction Operations 06/26/2017 A 01/18/2018 A 108B1400 Original Construction Duration 06/26/2017 A 11/23/2017 A 108B1400 Change Order #1 - Hurricane Irma 11/24/2017 A 12/14/2017 A 108B1402 Substantial Completion 01/18/2018 A 0

DesignerDesigner Construction Support Services 01/10/2017 A 01/18/2018 A 253B1410 Designer Construction Support Services 01/10/2017 A 01/18/2018 A 253

Project CProject Closeout 12/14/2017 A 08/01/2018 230B1445 Closeout Phase 12/14/2017 A 08/01/2018 230B1450 Issue SAC Letter 12/14/2017 A 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 01/19/2018 A 08/01/2018 120B1490 Project Closed 08/01/2018 0

Basin 0480Basin 0480 11/05/2015 A 09/26/2019 1421

100087 Pu100087 Pump Station 0480 Upgrade 11/05/2015 A 09/26/2019 1421DesignDesign 11/05/2015 A 07/17/2018 A 1027

B1000 Design Phase 11/05/2015 A 07/17/2018 A 1027B1010 Prepare and Submit Design Package 11/05/2015 A 11/06/2015 A 5B1020 Engage Design Consultant 11/06/2015 A 03/18/2016 A 20B1022 TA Preparation 03/21/2016 A 03/21/2016 A 1B1024 TA Approval Process 03/22/2016 A 04/27/2016 A 20B1030 Issue Design NTP 05/13/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 05/13/2016 A 06/20/2018 A 65

30% Des30% Design 05/16/2016 A 08/17/2017 A 457B1060 A/E Prepares 30% Construction Documents 05/16/2016 A 07/05/2016 A 30B1070 Geotechnical Engineering Services 05/16/2016 A 07/05/2016 A 20B1080 Surveying Services 05/16/2016 A 07/05/2016 A 15B1100 30% CDs Submittal 07/05/2016 A 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

100% CDs Submittal100% Review (MDWASD/PSIP Team)

Design Completed03/27/2017 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid Notice

MDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter

Contract Award (Purchase Order Approval)01/18/2018 A, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Construction NTPConstruction Operations

Original Construction DurationChange Order #1 - Hurricane Irma

Substantial Completion01/18/2018 A, Designer Construction Support Services

Designer Construction Support Services08/01/2018, Project Closeout

Closeout PhaseIssue SAC Letter

Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed

09/26/2019, Basin 0480

09/26/2019, 100087 Pump07/17/2018 A, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval ProcessIssue Design NTP

Final Engineering Report Review & Approval (MDWASD/PSIP Tea08/17/2017 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 81 of 161 TASK filter: All Activities© Oracle Corporation

Page 82: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1120 30% Review (MDWASD/PSIP Team) 07/06/2016 A 09/09/2016 A 10B1122 Design Consultant Prepares SOW for New FDOT Requirement 09/12/2016 A 04/17/2017 A 20B1124 TA Rev 1 Preparation 04/18/2017 A 04/18/2017 A 1B1126 TA Rev 1 Approval Process 04/19/2017 A 05/17/2017 A 40B1128 A/E Prepares 30% Construction Documents (Re-Design) 06/02/2017 A 07/17/2017 A 22B1130 30% CDs Submittal (Re-Design) 07/17/2017 A 0B1132 30% Review (MDWASD/PSIP Team) (Re-Design) 07/18/2017 A 08/17/2017 A 30

90% Des90% Design 07/18/2017 A 06/20/2018 A 414B1170 A/E Prepares 90% Construction Documents 07/18/2017 A 10/02/2017 A 40B1180 90% CDs Submittal 10/02/2017 A 0B1190 90% Review (MDWASD/PSIP Team) 10/03/2017 A 10/30/2017 A 30B1200 90% RER(DERM)FDEP Permit Submittal 11/22/2017 A 0B1210 90% RER(DERM)FDEP Permit Review 11/22/2017 A 02/23/2018 A 45B1220 90% RER(Building Dept) Permit Submittal 03/27/2018 A 0B1230 90% RER(Building Dept) Permit Review 03/27/2018 A 04/11/2018 A 21B1240 90% Aventura - PWD Permit Submittal 03/26/2018 A 0B1250 90% Aventura - PWD Permit Review 03/26/2018 A 06/20/2018 A 21B1252 90% Aventura - BD Permit Submittal 03/26/2018 A 0B1254 90% Aventura - BD Permit Review 03/26/2018 A 03/27/2018 A 21B1256 90% FDOT Permit Submittal 12/19/2017 A 0B1258 90% FDOT Permit Review 12/19/2017 A 02/08/2018 A 21B1260 90% CD PM Comments Evaluation Completed 06/20/2018 A 0

100% De100% Design 06/20/2018 A 07/17/2018 A 28B1270 A/E Prepares 100% Construction Documents 06/20/2018 A 07/17/2018 A 14B1280 100% CDs Submittal 07/17/2018 A 0B1290 100% Review (MDWASD/PSIP Team) 07/13/2018 A 07/16/2018 A 14B1300 Design Completed 07/17/2018 A 0

MDWASDMDWASD Procurement 07/17/2018 A 10/08/2018 61B1305 Procurement Phase 07/17/2018 A 10/08/2018 61B1310 Submit CDs to MDWASD Procurement Division 07/17/2018 A 0B1312 Bid Notice Preparation Period 07/18/2018 A 07/30/2018 A 33B1314 Bid Notice 07/30/2018 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 07/31/2018 A 08/08/2018 14B1320 Pre-Bid Conference 08/09/2018 08/09/2018 1B1322 Bidders Prepare Bids for Submittal 08/10/2018 09/03/2018 25B1330 Bids Submittal 09/03/2018 0B1340 MDWASD/PSIP Team Bids Evaluation 09/04/2018 09/24/2018 21B1350 Recommendation for Award Letter 09/24/2018 0B1355 Contract Award (Purchase Order Approval) 09/25/2018 10/08/2018 14

ConstrucConstruction 08/09/2018 05/29/2019 294B1360 Construction Phase 08/09/2018 05/29/2019 294B1364 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 09/25/2018 10/15/2018 21B1366 Pre-Construction Meeting 10/16/2018 10/16/2018 1B1368 WASD Issues NTP (Pre-Const to NTP) 10/17/2018 11/30/2018 45B1369 WASD Issues NTP (PO to NTP) 10/09/2018 11/30/2018 53B1370 Construction NTP 12/01/2018 0B1400 Construction Operations 12/01/2018 05/29/2019 180B1402 Substantial Completion 05/29/2019 0

DesignerDesigner Construction Support Services 08/09/2018 05/29/2019 294

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

30% Review (MDWASD/PSIP Team)Design Consultant Prepares SOW for New FDOT RequirementTA Rev 1 Preparation

TA Rev 1 Approval ProcessA/E Prepares 30% Construction Documents (Re-Design)

30% CDs Submittal (Re-Design)30% Review (MDWASD/PSIP Team) (Re-Design)

06/20/2018 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal

90% RER(DERM)FDEP Permit Review90% RER(Building Dept) Permit Submittal90% RER(Building Dept) Permit Review

90% Aventura - PWD Permit Submittal90% Aventura - PWD Permit Review

90% Aventura - BD Permit Submittal90% Aventura - BD Permit Review

90% FDOT Permit Submittal90% FDOT Permit Review

90% CD PM Comments Evaluation Completed07/17/2018 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal

100% Review (MDWASD/PSIP Team)Design Completed

10/08/2018, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid Notice

MDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)

05/29/2019, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeePre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Construction NTPConstruction OperationsSubstantial Completion05/29/2019, Designer Construction Su

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 82 of 161 TASK filter: All Activities© Oracle Corporation

Page 83: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1410 Designer Construction Support Services 08/09/2018 05/29/2019 294Project CProject Closeout 05/29/2019 09/26/2019 120

B1445 Closeout Phase 05/29/2019 09/26/2019 120B1450 Issue SAC Letter 05/29/2019 0B1470 Final Release of Retainage - Construction Contract 05/29/2019 0B1480 Administrative Closeout 05/30/2019 09/26/2019 120B1490 Project Closed 09/26/2019 0

Basin 0487Basin 0487 05/02/2016 A 08/01/2018 822

100088 Pu100088 Pump Station 0487 Upgrade 05/02/2016 A 08/01/2018 822DesignDesign 05/02/2016 A 03/23/2017 A 376

B1000 Design Phase 05/02/2016 A 03/23/2017 A 376B1010 Prepare and Submit Design Package 05/02/2016 A 05/06/2016 A 5B1020 Engage Design Consultant 05/06/2016 A 09/29/2016 A 20B1022 TA Preparation 09/30/2016 A 09/30/2016 A 1B1024 TA Approval Process 10/03/2016 A 11/30/2016 A 40B1030 Issue Design NTP 12/09/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 12/09/2016 A 02/07/2017 A 65

30% Des30% Design 12/12/2016 A 03/23/2017 A 131B1060 A/E Prepares 30% Construction Documents 12/12/2016 A 02/07/2017 A 50B1062 Station Monitoring and SAC Process 02/08/2017 A 03/23/2017 A 40

Project CProject Closeout 03/23/2017 A 08/01/2018 496B1445 Closeout Phase 03/23/2017 A 08/01/2018 496B1450 Issue SAC Letter 03/23/2017 A 0B1480 Administrative Closeout 03/23/2017 A 08/01/2018 30B1490 Project Closed 08/01/2018 0

Basin 0494Basin 0494 01/14/2016 A 12/08/2018 1052

100090 Pu100090 Pump Station 0494 Upgrade 01/14/2016 A 12/08/2018 1052DesignDesign 01/14/2016 A 06/07/2017 A 548

B1000 Design Phase 01/14/2016 A 06/07/2017 A 548B1010 Prepare and Submit Design Package 01/14/2016 A 01/29/2016 A 5B1020 Engage Design Consultant 01/29/2016 A 04/26/2016 A 20B1022 TA Preparation 04/27/2016 A 04/27/2016 A 1B1024 TA Approval Process 04/28/2016 A 06/01/2016 A 20B1030 Issue Design NTP 06/13/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 06/13/2016 A 06/07/2017 A 65

30% Des30% Design 06/14/2016 A 09/29/2016 A 105B1060 A/E Prepares 30% Construction Documents 06/14/2016 A 09/01/2016 A 30B1100 30% CDs Submittal 09/01/2016 A 0B1120 30% Review (MDWASD/PSIP Team) 09/02/2016 A 09/29/2016 A 10

90% Des90% Design 09/05/2016 A 06/07/2017 A 331B1130 A/E Prepares 90% Construction Documents 09/05/2016 A 01/17/2017 A 40B1140 90% CDs Submittal 01/17/2017 A 0B1150 90% Review (MDWASD/PSIP Team) 01/18/2017 A 02/07/2017 A 30B1160 90% RER(DERM)FDEP Permit Submittal (Pump Station) 03/24/2017 A 0B1170 90% RER(DERM)FDEP Permit Review (Pump Station) 03/24/2017 A 04/04/2017 A 45B1180 90% RER(Building Dept) Permit Submittal (Pump Station) 05/15/2017 A 0B1190 90% RER(Building Dept) Permit Review (Pump Station) 05/15/2017 A 06/07/2017 A 21B1200 90% Golden Beach - BD Permit Submittal (Pump Station) 04/05/2017 A 0B1210 90% Golden Beach - BD Permit Review (Pump Station) 04/05/2017 A 05/23/2017 A 21

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Designer Construction Support Service09/26/2019, Project Closeou

Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construc

Administrative CloseoutProject Closed

08/01/2018, Basin 0487

08/01/2018, 100088 Pump Station 0487 Upgrade03/23/2017 A, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval ProcessIssue Design NTP

Final Engineering Report Review & Approval (MDWASD/PSIP Team)03/23/2017 A, 30% Design

A/E Prepares 30% Construction DocumentsStation Monitoring and SAC Process

08/01/2018, Project Closeout

Closeout PhaseIssue SAC Letter

Administrative CloseoutProject Closed

12/08/2018, Basin 0494

12/08/2018, 100090 Pump Station 0494 Upgrade06/07/2017 A, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval ProcessIssue Design NTP

Final Engineering Report Review & Approval (MDWASD/PSIP Team)09/29/2016 A, 30% Design

A/E Prepares 30% Construction Documents30% CDs Submittal

30% Review (MDWASD/PSIP Team)06/07/2017 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)90% RER(DERM)FDEP Permit Review (Pump Station)

90% RER(Building Dept) Permit Submittal (Pump Station)90% RER(Building Dept) Permit Review (Pump Station)90% Golden Beach - BD Permit Submittal (Pump Station)90% Golden Beach - BD Permit Review (Pump Station)

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 83 of 161 TASK filter: All Activities© Oracle Corporation

Page 84: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1212 90% Golden Beach - PWD Permit Submittal (Pump Station) 04/05/2017 A 0B1214 90% Golden Beach - PWD Permit Review (Pump Station) 04/05/2017 A 05/23/2017 A 21B1220 90% CD PM Comments Evaluation Completed 06/07/2017 A 0B1222 MDWASD Union Concurrence Process 03/07/2017 A 04/07/2017 A 30

100% De100% Design 04/07/2017 A 04/14/2017 A 26B1230 A/E Prepares 100% Construction Documents 04/07/2017 A 04/13/2017 A 10B1240 100% CDs Submittal 04/13/2017 A 0B1250 100% Review (MDWASD/PSIP Team) 04/14/2017 A 04/14/2017 A 10B1260 Design Completed 04/14/2017 A 0

MDWASDMDWASD Procurement 04/14/2017 A 08/14/2017 A 75B1265 Procurement Phase 04/14/2017 A 08/14/2017 A 75B1270 Submit CDs to MDWASD Procurement Division 04/14/2017 A 0B1272 Bid Notice Preparation Period 04/17/2017 A 05/10/2017 A 23B1274 Bid Notice 05/10/2017 A 0B1276 MDWASD/PSIP Team Prepare for Pre-Bid Conference 05/11/2017 A 05/22/2017 A 10B1280 Pre-Bid Conference 05/23/2017 A 05/23/2017 A 1B1282 Bidders Prepare Bids for Submittal 05/24/2017 A 06/20/2017 A 15B1290 Bids Submittal 06/20/2017 A 0B1300 MDWASD/PSIP Team Bids Evaluation 06/21/2017 A 07/24/2017 A 15B1310 Recommendation for Award Letter 07/24/2017 A 0B1315 Contract Award (Purchase Order Approval) 07/25/2017 A 08/14/2017 A 10

ConstrucConstruction 05/23/2017 A 08/10/2018 551B1320 Construction Phase 05/23/2017 A 08/10/2018 551B1322 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 07/25/2017 A 08/21/2017 A 15B1324 Pre-Construction Meeting 08/22/2017 A 08/22/2017 A 1B1326 WASD Issues NTP (Pre-Const to NTP) 08/23/2017 A 03/11/2018 A 132B1328 WASD Issues NTP (PO to NTP) 08/15/2017 A 03/11/2018 A 53B1330 Construction NTP 03/12/2018 A 0B1360 Construction Operations 03/12/2018 A 08/10/2018 119B1362 Substantial Completion 08/10/2018 0

DesignerDesigner Construction Support Services 05/23/2017 A 08/10/2018 260B1370 Designer Construction Support Services 05/23/2017 A 08/10/2018 260

Project CProject Closeout 08/10/2018 12/08/2018 120B1405 Closeout Phase 08/10/2018 12/08/2018 120B1410 Issue SAC Letter 08/10/2018 0B1430 Final Release of Retainage - Construction Contract 08/10/2018 0B1440 Administrative Closeout 08/11/2018 12/08/2018 120B1450 Project Closed 12/08/2018 0

Basin 0495Basin 0495 06/16/2014 A 08/01/2018 1696

100091 Pu100091 Pump Station 0495 Upgrade 06/16/2014 A 08/01/2018 1198DesignDesign 06/16/2014 A 08/01/2016 A 333

B1000 Design Phase 06/16/2014 A 08/01/2016 A 333B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 06/16/2014 A 06/19/2014 A 5B1020 Engage Design Consultant 06/20/2014 A 09/16/2014 A 15B1030 Issue Design NTP 09/17/2014 A 0B1032 TA Rev 2 - Approval Process 06/02/2016 A 08/01/2016 A 15B1040 A/E Develops and Submits Final Engineering Report 09/17/2014 A 04/23/2015 A 20B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 09/17/2014 A 01/07/2015 A 0

30% Des30% Design 09/18/2014 A 10/30/2014 A 30

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

90% Golden Beach - PWD Permit Submittal (Pump Station)90% Golden Beach - PWD Permit Review (Pump Station)

90% CD PM Comments Evaluation CompletedMDWASD Union Concurrence Process04/14/2017 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal

100% Review (MDWASD/PSIP Team)Design Completed08/14/2017 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid Notice

MDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)

08/10/2018, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Construction NTPConstruction OperationsSubstantial Completion08/10/2018, Designer Construction Support Services

Designer Construction Support Services12/08/2018, Project Closeout

Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction Contract

Administrative CloseoutProject Closed

08/01/2018, Basin 0495

08/01/2018, 100091 Pump Station 0495 Upgrade08/01/2016 A, Design

Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book

Engage Design ConsultantIssue Design NTP

TA Rev 2 - Approval Process

A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

10/30/2014 A, 30% Design

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 84 of 161 TASK filter: All Activities© Oracle Corporation

Page 85: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1060 A/E Prepares 30% Construction Documents 09/18/2014 A 10/16/2014 A 30B1070 Geotechnical Engineering Services 10/03/2014 A 10/16/2014 A 30B1080 Surveying Services 10/03/2014 A 10/23/2014 A 23B1100 30% CDs Submittal 10/17/2014 A 0B1120 30% Review (MDWASD/PSIP Team) 10/17/2014 A 10/30/2014 A 10

90% Des90% Design 10/17/2014 A 04/23/2015 A 144B1170 A/E Prepares 90% Construction Documents 10/17/2014 A 11/25/2014 A 20B1180 90% CDs Submittal 11/25/2014 A 0B1190 90% Review (MDWASD/PSIP Team) 11/26/2014 A 01/07/2015 A 15B1195 Revision - FPL Issues 01/26/2015 A 02/11/2015 A 5B1200 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 02/12/2015 A 0B1210 90% RER(DERM)/FDEP Permit Review (Pump Station) 02/12/2015 A 03/11/2015 A 15B1220 90% Golden Beach - BD Permit Submittal 03/03/2015 A 0B1230 90% Golden Beach - BD Permit Review 03/03/2015 A 04/23/2015 A 15B1240 90% Golden Beach - PWD Permit Submittal 03/03/2015 A 0B1250 90% Golden Beach - PWD Permit Review 03/03/2015 A 04/23/2015 A 15B1260 90% CD PM Comments Evaluation Completed 04/23/2015 A 0

100% De100% Design 02/12/2015 A 04/30/2015 A 25B1270 A/E Prepares 100% Construction Documents 02/12/2015 A 03/30/2015 A 10B1280 100% CDs Submittal 03/30/2015 A 0B1290 100% Review (MDWASD/PSIP Team) 03/30/2015 A 04/30/2015 A 10B1300 Design Completed 04/30/2015 A 0

MDWASDMDWASD Procurement 04/07/2015 A 07/14/2015 A 98B1305 Procurement Phase 04/07/2015 A 07/14/2015 A 98B1310 Submit CDs to MDWASD Procurement Division 04/07/2015 A 0B1312 Bid Notice Preparation Period 04/08/2015 A 04/27/2015 A 23B1314 Bid Notice 04/28/2015 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 04/29/2015 A 05/11/2015 A 10B1320 Pre-Bid Conference 05/12/2015 A 05/12/2015 A 1B1322 Bidders Prepare Bids for Submittal 05/13/2015 A 06/09/2015 A 15B1330 Bids Submittal 06/10/2015 A 0B1340 MDWASD/PSIP Team Bids Evaluation 06/11/2015 A 06/16/2015 A 15B1350 Recommendation for Award Letter 06/17/2015 A 0B1355 Contract Award (Purchase Order Approval) 06/18/2015 A 07/14/2015 A 10

ConstrucConstruction 05/12/2015 A 09/30/2016 A 1301B1360 Construction Phase 05/12/2015 A 09/30/2016 A 1301B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 06/18/2015 A 07/08/2015 A 15B1365 Pre-Construction Meeting 07/09/2015 A 07/09/2015 A 1B1368 WASD Issues NTP (PO to NTP) 07/14/2015 A 07/14/2015 A 53B1370 Construction NTP 07/14/2015 A 0B1400 Construction Operations 07/14/2015 A 11/17/2015 A 85B1400 Original Construction Duration 07/14/2015 A 11/11/2015 A 85B1400 Change Order #1 - FPL 11/12/2015 A 11/28/2015 A 85B1402 Substantial Completion 11/17/2015 A 0

DesignerDesigner Construction Support Services 05/12/2015 A 09/30/2016 A 143B1410 Designer Construction Support Services 05/12/2015 A 09/30/2016 A 143

ConstrucConstruction Close Out 11/18/2015 A 06/27/2016 A 15B1420 Commissioning 11/18/2015 A 12/10/2015 A 15B1430 Punch List 11/18/2015 A 06/27/2016 A 10

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services

30% CDs Submittal30% Review (MDWASD/PSIP Team)

04/23/2015 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)Revision - FPL Issues90% RER(DERM)/FDEP Permit Submittal (Pump Station)

90% RER(DERM)/FDEP Permit Review (Pump Station)90% Golden Beach - BD Permit Submittal

90% Golden Beach - BD Permit Review90% Golden Beach - PWD Permit Submittal

90% Golden Beach - PWD Permit Review90% CD PM Comments Evaluation Completed04/30/2015 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal

100% Review (MDWASD/PSIP Team)Design Completed

07/14/2015 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid Notice

MDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter

Contract Award (Purchase Order Approval)09/30/2016 A, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction MeetingWASD Issues NTP (PO to NTP)Construction NTP

Construction OperationsOriginal Construction DurationChange Order #1 - FPL

Substantial Completion09/30/2016 A, Designer Construction Support Services

Designer Construction Support Services06/27/2016 A, Construction Close Out

CommissioningPunch List

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 85 of 161 TASK filter: All Activities© Oracle Corporation

Page 86: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

Project CProject Closeout 11/18/2015 A 08/01/2018 678B1445 Closeout Phase 11/18/2015 A 08/01/2018 952B1450 Issue SAC Letter 12/23/2015 A 0B1470 Final Release of Retainage - Construction Contract 11/21/2016 A 0B1480 Administrative Closeout 11/18/2015 A 08/01/2018 120B1490 Project Closed 08/01/2018 0

100188-2 B100188-2 Basin 0495 Infiltration/Inflow Study and Repairs 04/17/2015 A 11/26/2015 A 390InfiltratioInfiltration/Inflow 04/17/2015 A 11/25/2015 A 173

B1000 Infiltration/Inflow Phase 04/17/2015 A 11/25/2015 A 173CIPP RepCIPP Repairs 04/17/2015 A 07/27/2015 A 107

B1065 CIPP Phase 04/17/2015 A 07/27/2015 A 107B1080 Issue NTP for CIPP Repairs 04/17/2015 A 0B1090 Conduct CIPP Repairs 07/27/2015 A 07/27/2015 A 20

ManholeManhole Repairs 10/02/2015 A 11/25/2015 A 20B1115 Manhole Phase 10/02/2015 A 11/25/2015 A 20B1130 Issue NTP for Manhole Repairs 10/02/2015 A 0B1140 Conduct Manhole Repairs 10/14/2015 A 11/25/2015 A 20

Project CProject Closeout 11/26/2015 A 11/26/2015 A 0B1235 Closeout Phase 11/26/2015 A 11/26/2015 A 0B1260 Project Closed 11/26/2015 A 0

Basin 0500Basin 0500 07/02/2014 A 08/01/2018 1631

100093 Pu100093 Pump Station 0500 Upgrade 07/02/2014 A 08/01/2018 1631DesignDesign 07/02/2014 A 04/30/2015 A 303

B1000 Design Phase 07/02/2014 A 04/30/2015 A 303B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 07/02/2014 A 07/28/2014 A 5B1020 Engage Design Consultant 07/29/2014 A 10/23/2014 A 15B1030 Issue Design NTP 10/24/2014 A 0B1040 A/E Develops and Submits Final Engineering Report 10/27/2014 A 01/14/2015 A 20B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 12/29/2014 A 02/11/2015 A 1

30% Des30% Design 10/27/2014 A 12/02/2014 A 57B1060 A/E Prepares 30% Construction Documents 10/27/2014 A 11/11/2014 A 30B1070 Geotechnical Engineering Services 10/27/2014 A 11/11/2014 A 20B1080 Surveying Services 10/27/2014 A 11/11/2014 A 15B1100 30% CDs Submittal 11/11/2014 A 0B1120 30% Review (MDWASD/PSIP Team) 11/12/2014 A 12/02/2014 A 10

90% Des90% Design 11/12/2014 A 04/30/2015 A 99B1170 A/E Prepares 90% Construction Documents 11/12/2014 A 12/26/2014 A 20B1180 90% CDs Submittal 12/26/2014 A 0B1190 90% Review (MDWASD/PSIP Team) 12/29/2014 A 01/14/2015 A 15B1200 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 02/17/2015 A 0B1210 90% RER(DERM)/FDEP Permit Review (Pump Station) 02/17/2015 A 03/12/2015 A 5B1220 90% RER (Building Dept) Permit Submittal 03/20/2015 A 0B1230 90% RER (Building Dept) Permit Review 03/20/2015 A 04/30/2015 A 5B1240 90% PWWMD Permit Submittal (Pump Station) 11/14/2014 A 0B1250 90% PWWMD Permit Review (Pump Station) 11/12/2014 A 11/20/2014 A 5B1260 90% CD PM Comments Evaluation Completed 04/30/2015 A 0

100% De100% Design 01/15/2015 A 04/30/2015 A 64B1270 A/E Prepares 100% Construction Documents 01/15/2015 A 01/23/2015 A 10B1280 100% CDs Submittal 01/23/2015 A 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

08/01/2018, Project Closeout

Closeout PhaseIssue SAC Letter

Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed

11/26/2015 A, 100188-2 Basin 0495 Infiltration/Inflow Study and Repairs11/25/2015 A, Infiltration/Inflow

Infiltration/Inflow Phase07/27/2015 A, CIPP RepairsCIPP Phase

Issue NTP for CIPP RepairsConduct CIPP Repairs

11/25/2015 A, Manhole RepairsManhole Phase

Issue NTP for Manhole RepairsConduct Manhole Repairs11/26/2015 A, Project CloseoutCloseout Phase

Project Closed08/01/2018, Basin 0500

08/01/2018, 100093 Pump Station 0500 Upgrade04/30/2015 A, Design

Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book

Engage Design ConsultantIssue Design NTP

A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

12/02/2014 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services

30% CDs Submittal30% Review (MDWASD/PSIP Team)

04/30/2015 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)

90% RER(DERM)/FDEP Permit Submittal (Pump Station)90% RER(DERM)/FDEP Permit Review (Pump Station)

90% RER (Building Dept) Permit Submittal90% RER (Building Dept) Permit Review

90% PWWMD Permit Submittal (Pump Station)90% PWWMD Permit Review (Pump Station)

90% CD PM Comments Evaluation Completed04/30/2015 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 86 of 161 TASK filter: All Activities© Oracle Corporation

Page 87: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1290 100% Review (MDWASD/PSIP Team) 01/24/2015 A 02/11/2015 A 5B1300 Design Completed 04/30/2015 A 0

MDWASDMDWASD Procurement 03/18/2015 A 07/23/2015 A 109B1305 Procurement Phase 03/18/2015 A 07/23/2015 A 109B1310 Submit CDs to MDWASD Procurement Division 03/18/2015 A 0B1320 Pre-Bid Conference 04/07/2015 A 04/07/2015 A 1B1330 Bids Submittal 05/05/2015 A 0B1340 MDWASD/PSIP Team Bids Evaluation 05/06/2015 A 05/14/2015 A 30B1350 Recommendation for Award Letter 05/15/2015 A 0B1355 Contract Award (Purchase Order Approval) 05/18/2015 A 07/23/2015 A 15

ConstrucConstruction 04/07/2015 A 07/08/2016 A 1290B1360 Construction Phase 04/07/2015 A 07/08/2016 A 1290B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 05/18/2015 A 06/09/2015 A 0B1365 Pre-Construction Meeting 06/10/2015 A 06/10/2015 A 1B1368 WASD Issues NTP (PO to NTP) 07/24/2015 A 07/26/2015 A 53B1369 Permits / Shop Drawings / Material Orders 06/11/2015 A 11/20/2015 A 15B1370 Construction NTP 07/27/2015 A 0B1400 Construction Operations 07/27/2015 A 12/23/2015 A 106B1402 Substantial Completion 12/23/2015 A 0

DesignerDesigner Construction Support Services 04/07/2015 A 07/08/2016 A 160B1410 Designer Construction Support Services 04/07/2015 A 07/08/2016 A 160

ConstrucConstruction Close Out 12/24/2015 A 02/29/2016 A 15B1420 Commissioning 12/24/2015 A 02/29/2016 A 15B1430 Punch List 12/24/2015 A 02/29/2016 A 10

Project CProject Closeout 12/24/2015 A 08/01/2018 944B1445 Closeout Phase 12/24/2015 A 08/01/2018 944B1450 Issue SAC Letter 01/26/2016 A 0B1470 Final Release of Retainage - Construction Contract 12/23/2016 A 0B1480 Administrative Closeout 12/24/2015 A 08/01/2018 120B1490 Project Closed 08/01/2018 0

100092-2 B100092-2 Basin 0500 Infiltration/Inflow Study and Repairs 09/25/2014 A 09/04/2015 A 609InfiltratioInfiltration/Inflow 09/25/2014 A 09/03/2015 A 338

B1260 Infiltration/Inflow Phase 09/25/2014 A 09/03/2015 A 338Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 12/31/2014 A 274

B0995 SSES Phase 09/25/2014 A 12/31/2014 A 274B1010 Issue NTP to SSES Contractor 09/25/2014 A 0B1020 Conduct SSES 09/29/2014 A 10/17/2014 A 30B1021 Suspect Laterals/Smoke Test Defect Investigations 10/16/2014 A 10/17/2014 A 10B1030 Video Review 10/20/2014 A 12/31/2014 A 30

CIPP RepCIPP Repairs 04/17/2015 A 07/20/2015 A 33B1055 CIPP Phase 04/17/2015 A 07/20/2015 A 33B1070 Issue NTP for CIPP Repairs 04/17/2015 A 0B1080 Conduct CIPP Repairs 06/18/2015 A 07/20/2015 A 20

ManholeManhole Repairs 07/14/2015 A 09/03/2015 A 20B1005 Manhole Phase 07/14/2015 A 09/03/2015 A 20B1120 Issue NTP for Manhole Repairs 07/14/2015 A 0B1130 Conduct Manhole Repairs 08/17/2015 A 09/03/2015 A 20

Dig & ReDig & Replace Repairs 05/18/2015 A 07/01/2015 A 30B1155 Dig & Replace Phase 05/18/2015 A 07/01/2015 A 30

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

100% Review (MDWASD/PSIP Team)Design Completed

07/23/2015 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Pre-Bid ConferenceBids SubmittalMDWASD/PSIP Team Bids Evaluation

Recommendation for Award LetterContract Award (Purchase Order Approval)

07/08/2016 A, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

WASD Issues NTP (PO to NTP)

Permits / Shop Drawings / Material OrdersConstruction NTP

Construction OperationsSubstantial Completion

07/08/2016 A, Designer Construction Support Services

Designer Construction Support Services02/29/2016 A, Construction Close Out

CommissioningPunch List

08/01/2018, Project Closeout

Closeout PhaseIssue SAC Letter

Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed

09/04/2015 A, 100092-2 Basin 0500 Infiltration/Inflow Study and Repairs09/03/2015 A, Infiltration/Inflow

Infiltration/Inflow Phase12/31/2014 A, Sanitary Sewer Evaluation SurveySSES Phase

Issue NTP to SSES ContractorConduct SSESSuspect Laterals/Smoke Test Defect Investigations

Video Review07/20/2015 A, CIPP RepairsCIPP Phase

Issue NTP for CIPP RepairsConduct CIPP Repairs

09/03/2015 A, Manhole RepairsManhole Phase

Issue NTP for Manhole RepairsConduct Manhole Repairs

07/01/2015 A, Dig & Replace RepairsDig & Replace Phase

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 87 of 161 TASK filter: All Activities© Oracle Corporation

Page 88: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1170 Issue NTP for Dig & Replace Repairs 05/18/2015 A 0B1180 Conduct Dig & Replace Repairs 06/22/2015 A 07/01/2015 A 30

Project CProject Closeout 09/04/2015 A 09/04/2015 A 0B1225 Closeout Phase 09/04/2015 A 09/04/2015 A 0B1250 Project Closed 09/04/2015 A 0

100213 FM100213 FM for Pump Station 0500 07/02/2014 A 07/17/2017 A 1631DesignDesign 07/02/2014 A 03/24/2015 A 283

B1000 Design Phase 07/02/2014 A 03/24/2015 A 283B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 07/02/2014 A 08/01/2014 A 5B1020 Engage Design Consultant 08/04/2014 A 11/05/2014 A 20B1030 Issue Design NTP 11/05/2014 A 0B1040 A/E Develops and Submits Final Engineering Report 11/06/2014 A 01/26/2015 A 20B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 01/27/2015 A 01/30/2015 A 2

30% Des30% Design 11/06/2014 A 12/04/2014 A 97B1060 A/E Prepares 30% Construction Documents 11/06/2014 A 11/24/2014 A 30B1070 Geotechnical Engineering Services 11/06/2014 A 11/24/2014 A 20B1080 Surveying Services 11/06/2014 A 11/24/2014 A 15B1100 30% CDs Submittal 11/24/2014 A 0B1120 30% Review (MDWASD/PSIP Team) 11/24/2014 A 12/04/2014 A 10

90% Des90% Design 11/25/2014 A 03/13/2015 A 66B1180 A/E Prepares 90% Construction Documents 12/16/2014 A 01/30/2015 A 15B1190 90% CDs Submittal 01/30/2015 A 0B1200 90% Review (MDWASD/PSIP Team) 02/02/2015 A 02/13/2015 A 15B1230 90% RER(DERM)FDEP Permit Submittal (Force Main) 03/06/2015 A 0B1240 90% RER(DERM)FDEP Permit Review (Force Main) 03/06/2015 A 03/11/2015 A 5B1250 90% PWWMD Permit Submittal (Force Main) 11/25/2014 A 0B1260 90% PWWMD Permit Review (Force Main) 11/25/2014 A 12/02/2014 A 5B1290 90% CD PM Comments Evaluation Completed 03/13/2015 A 0

100% De100% Design 02/14/2015 A 03/24/2015 A 37B1300 A/E Prepares 100% Construction Documents 02/14/2015 A 03/20/2015 A 2B1310 100% CDs Submittal 03/20/2015 A 0B1320 100% Review (MDWASD/PSIP Team) 03/23/2015 A 03/24/2015 A 4B1330 Design Completed 03/24/2015 A 0

MDWASDMDWASD Procurement 03/25/2015 A 07/14/2015 A 95B1335 Procurement Phase 03/25/2015 A 07/14/2015 A 95B1340 Submit CDs to MDWASD Procurement Division 03/25/2015 A 0B1350 Pre-Bid Conference 04/14/2015 A 04/14/2015 A 1B1360 Bids Submittal 05/18/2015 A 0B1370 MDWASD/PSIP Team Bids Evaluation 05/19/2015 A 05/22/2015 A 20B1380 Recommendation for Award Letter 05/22/2015 A 0B1385 Contract Award (Purchase Order Approval) 05/22/2015 A 07/14/2015 A 15

ConstrucConstruction 04/14/2015 A 02/06/2017 A 1276B1390 Construction Phase 04/14/2015 A 02/06/2017 A 1276B1394 MDWASD/PSIP Prepare for Pre-Construction Meeting 05/25/2015 A 06/17/2015 A 30B1396 Pre-Construction Meeting 06/18/2015 A 06/18/2015 A 1B1398 Permits / Shop Drawings / Material Orders 06/19/2015 A 11/20/2015 A 30B1399 WASD Issues NTP (PO to NTP) 07/15/2015 A 08/31/2015 A 53B1400 Construction NTP 09/01/2015 A 0B1430 Construction Operations 09/01/2015 A 12/17/2015 A 85

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs

09/04/2015 A, Project CloseoutCloseout Phase

Project Closed07/17/2017 A, 100213 FM for Pump Station 0500

03/24/2015 A, Design

Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book

Engage Design ConsultantIssue Design NTP

A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

12/04/2014 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services

30% CDs Submittal30% Review (MDWASD/PSIP Team)

03/13/2015 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)

90% RER(DERM)FDEP Permit Submittal (Force Main)90% RER(DERM)FDEP Permit Review (Force Main)

90% PWWMD Permit Submittal (Force Main)90% PWWMD Permit Review (Force Main)

90% CD PM Comments Evaluation Completed03/24/2015 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed

07/14/2015 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement DivisionPre-Bid Conference

Bids SubmittalMDWASD/PSIP Team Bids Evaluation

Recommendation for Award LetterContract Award (Purchase Order Approval)

02/06/2017 A, Construction

Construction PhaseMDWASD/PSIP Prepare for Pre-Construction MeetingPre-Construction Meeting

Permits / Shop Drawings / Material OrdersWASD Issues NTP (PO to NTP)

Construction NTPConstruction Operations

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 88 of 161 TASK filter: All Activities© Oracle Corporation

Page 89: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1432 Substantial Completion 12/17/2015 A 0DesignerDesigner Construction Support Services 04/14/2015 A 02/06/2017 A 128

B1440 Designer Construction Support Services 04/14/2015 A 02/06/2017 A 128ConstrucConstruction Close Out 12/18/2015 A 02/29/2016 A 15

B1450 Commissioning 12/18/2015 A 12/31/2015 A 15B1460 Punch List 12/18/2015 A 02/29/2016 A 10

Project CProject Closeout 12/17/2015 A 07/17/2017 A 550B1475 Closeout Phase 12/17/2015 A 07/17/2017 A 550B1478 SAC Letter Issuance Period 12/17/2015 A 01/26/2016 A 26B1480 Issue SAC Letter 01/26/2016 A 0B1500 Final Release of Retainage - Construction Contract 05/27/2016 A 0B1510 Administrative Closeout 12/18/2015 A 07/17/2017 A 30B1520 Project Closed 07/17/2017 A 0

Basin 0502Basin 0502 09/25/2014 A 08/01/2018 1506

100094 Pu100094 Pump Station 0502 Upgrade 10/10/2014 A 08/01/2018 1437DesignDesign 10/10/2014 A 06/22/2015 A 179

B1000 Design Phase 10/10/2014 A 06/22/2015 A 179B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 10/10/2014 A 10/13/2014 A 5B1020 Engage Design Consultant 10/14/2014 A 01/08/2015 A 20B1030 Issue Design NTP 01/08/2015 A 0B1040 A/E Develops and Submits Final Engineering Report 01/08/2015 A 05/29/2015 A 20B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 04/30/2015 A 05/14/2015 A 10

30% Des30% Design 01/09/2015 A 02/24/2015 A 72B1060 A/E Prepares 30% Construction Documents 01/09/2015 A 02/12/2015 A 30B1070 Geotechnical Engineering Services 01/26/2015 A 02/12/2015 A 20B1080 Surveying Services 01/26/2015 A 02/12/2015 A 15B1100 30% CDs Submittal 02/12/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 02/13/2015 A 02/24/2015 A 10

90% Des90% Design 02/13/2015 A 06/12/2015 A 124B1170 A/E Prepares 90% Construction Documents 02/13/2015 A 04/29/2015 A 35B1180 90% CDs Submittal 04/29/2015 A 0B1190 90% Review (MDWASD/PSIP Team) 04/30/2015 A 05/14/2015 A 10B1200 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 05/29/2015 A 0B1210 90% RER(DERM)/FDEP Permit Review (Pump Station) 05/20/2015 A 06/04/2015 A 5B1220 90% RER (Building Dept) Permit Submittal 06/10/2015 A 0B1230 90% RER (Building Dept) Permit Review 06/11/2015 A 06/12/2015 A 10B1260 90% CD PM Comments Evaluation Completed 06/12/2015 A 0

100% De100% Design 05/30/2015 A 06/22/2015 A 11B1270 A/E Prepares 100% Construction Documents 05/30/2015 A 06/22/2015 A 5B1280 100% CDs Submittal 06/22/2015 A 0B1290 100% Review (MDWASD/PSIP Team) 06/22/2015 A 06/22/2015 A 5B1300 Design Completed 06/22/2015 A 0

MDWASDMDWASD Procurement 06/23/2015 A 08/05/2015 A 64B1305 Procurement Phase 06/23/2015 A 08/05/2015 A 64B1310 Submit CDs to MDWASD Procurement Division 06/23/2015 A 0B1312 Bid Notice Preparation Period 06/23/2015 A 06/23/2015 A 23B1314 Bid Notice 06/23/2015 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 06/24/2015 A 06/29/2015 A 10B1320 Pre-Bid Conference 06/30/2015 A 06/30/2015 A 1

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Substantial Completion02/06/2017 A, Designer Construction Support Services

Designer Construction Support Services02/29/2016 A, Construction Close Out

CommissioningPunch List

07/17/2017 A, Project Closeout

Closeout PhaseSAC Letter Issuance Period

Issue SAC LetterFinal Release of Retainage - Construction Contract

Administrative CloseoutProject Closed

08/01/2018, Basin 0502

08/01/2018, 100094 Pump Station 0502 Upgrade06/22/2015 A, Design

Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book

Engage Design ConsultantIssue Design NTP

A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

02/24/2015 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services

30% CDs Submittal30% Review (MDWASD/PSIP Team)06/12/2015 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)/FDEP Permit Submittal (Pump Station)

90% RER(DERM)/FDEP Permit Review (Pump Station)90% RER (Building Dept) Permit Submittal

90% RER (Building Dept) Permit Review90% CD PM Comments Evaluation Completed06/22/2015 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal

100% Review (MDWASD/PSIP Team)Design Completed

08/05/2015 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation Period

Bid NoticeMDWASD/PSIP Team Prepare for Pre-Bid Conference

Pre-Bid Conference

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 89 of 161 TASK filter: All Activities© Oracle Corporation

Page 90: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1322 Bidders Prepare Bids for Submittal 07/01/2015 A 07/20/2015 A 15B1330 Bids Submittal 07/21/2015 A 0B1340 MDWASD/PSIP Team Bids Evaluation 07/22/2015 A 07/22/2015 A 15B1350 Recommendation for Award Letter 07/22/2015 A 0B1355 Contract Award (Purchase Order Approval) 07/23/2015 A 08/05/2015 A 10

ConstrucConstruction 06/30/2015 A 04/28/2017 A 1226B1360 Construction Phase 06/30/2015 A 04/28/2017 A 1226B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 07/23/2015 A 09/09/2015 A 15B1365 Pre-Construction Meeting 09/10/2015 A 09/10/2015 A 1B1366 WASD Issues NTP (Pre-Const to NTP) 09/11/2015 A 04/10/2016 A 15B1368 WASD Issues NTP (PO to NTP) 08/06/2015 A 04/10/2016 A 53B1370 Construction NTP 04/11/2016 A 0B1400 Construction Operations 04/11/2016 A 03/02/2017 A 108B1400 Original Construction Duration 04/11/2016 A 09/08/2016 A 108B1400 Change Order #1 - FPL 09/09/2016 A 09/30/2016 A 108B1400 Change Order #2 - Hurricane Mathew 10/01/2016 A 10/05/2016 A 108B1400 Change Order #3 - Bypass, Sheet Pilling Contractor, FPL 10/06/2016 A 12/13/2016 A 108B1400 Change Order #4 - Contractual Duration Discrepancy 12/14/2016 A 03/02/2017 A 108B1402 Substantial Completion 03/09/2017 A 0

DesignerDesigner Construction Support Services 06/30/2015 A 04/28/2017 A 217B1410 Designer Construction Support Services 06/30/2015 A 04/28/2017 A 217

ConstrucConstruction Close Out 03/09/2017 A 04/28/2017 A 10B1420 Commissioning 03/09/2017 A 03/09/2017 A 5B1430 Punch List 03/10/2017 A 04/28/2017 A 10

Project CProject Closeout 03/10/2017 A 08/01/2018 518B1445 Closeout Phase 03/10/2017 A 08/01/2018 518B1450 Issue SAC Letter 05/16/2018 A 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 03/10/2017 A 08/01/2018 120B1490 Project Closed 08/01/2018 0

100189-2 B100189-2 Basin 0502 Infiltration/Inflow Study and Repairs 09/25/2014 A 02/24/2016 A 575InfiltratioInfiltration/Inflow 09/25/2014 A 02/23/2016 A 486

B1000 Infiltration/Inflow Phase 09/25/2014 A 02/23/2016 A 486Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 04/01/2015 A 233

B1005 SSES Phase 09/25/2014 A 04/01/2015 A 233B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 01/20/2015 A 02/27/2015 A 30B1031 Suspect Lateral/Smoke Test Defect Investigations 01/20/2015 A 01/23/2015 A 10B1040 Video Review 02/20/2015 A 04/01/2015 A 30

CIPP RepCIPP Repairs 05/22/2015 A 08/05/2015 A 20B1065 CIPP Phase 05/22/2015 A 08/05/2015 A 20B1080 Issue NTP for CIPP Repairs 05/22/2015 A 0B1090 Conduct CIPP Repairs 07/29/2015 A 08/05/2015 A 20

Dig & ReDig & Replace Repairs 11/20/2015 A 02/23/2016 A 30B1165 Dig & Replace Phase 11/20/2015 A 02/23/2016 A 30B1180 Issue NTP for Dig & Replace Repairs 11/20/2015 A 0B1190 Conduct Dig & Replace Repairs 02/18/2016 A 02/23/2016 A 30

Project CProject Closeout 02/24/2016 A 02/24/2016 A 0B1235 Closeout Phase 02/24/2016 A 02/24/2016 A 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Bidders Prepare Bids for Submittal

Bids SubmittalMDWASD/PSIP Team Bids Evaluation

Recommendation for Award LetterContract Award (Purchase Order Approval)

04/28/2017 A, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)

WASD Issues NTP (PO to NTP)Construction NTP

Construction OperationsOriginal Construction Duration

Change Order #1 - FPLChange Order #2 - Hurricane Mathew

Change Order #3 - Bypass, Sheet Pilling Contractor, FPLChange Order #4 - Contractual Duration Discrepancy

Substantial Completion04/28/2017 A, Designer Construction Support Services

Designer Construction Support Services04/28/2017 A, Construction Close Out

CommissioningPunch List

08/01/2018, Project Closeout

Closeout PhaseIssue SAC Letter

Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed

02/24/2016 A, 100189-2 Basin 0502 Infiltration/Inflow Study and Repairs02/23/2016 A, Infiltration/Inflow

Infiltration/Inflow Phase04/01/2015 A, Sanitary Sewer Evaluation SurveySSES Phase

Issue NTP to SSES ContractorConduct SSES

Suspect Lateral/Smoke Test Defect Investigations

Video Review08/05/2015 A, CIPP RepairsCIPP Phase

Issue NTP for CIPP RepairsConduct CIPP Repairs

02/23/2016 A, Dig & Replace RepairsDig & Replace Phase

Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs02/24/2016 A, Project CloseoutCloseout Phase

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 90 of 161 TASK filter: All Activities© Oracle Corporation

Page 91: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1260 Project Closed 02/24/2016 A 0

Basin 0503Basin 0503 09/25/2014 A 09/18/2015 A 921

100095-3 B100095-3 Basin 0503 Infiltration/Inflow Study and Repairs 09/25/2014 A 07/24/2015 A 541InfiltratioInfiltration/Inflow 09/25/2014 A 07/23/2015 A 275

B1000 Infiltration/Inflow Phase 09/25/2014 A 07/23/2015 A 275Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 05/25/2015 A 30

B1005 SSES Phase 09/25/2014 A 05/25/2015 A 30B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 04/26/2015 A 05/25/2015 A 30

Dig & ReDig & Replace Repairs 05/18/2015 A 07/23/2015 A 30B1165 Dig & Replace Phase 05/18/2015 A 07/23/2015 A 30B1180 Issue NTP for Dig & Replace Repairs 05/18/2015 A 0B1190 Conduct Dig & Replace Repairs 07/21/2015 A 07/23/2015 A 30

Project CProject Closeout 07/24/2015 A 07/24/2015 A 0B1235 Closeout Phase 07/24/2015 A 07/24/2015 A 0B1260 Project Closed 07/24/2015 A 0

100225 Pu100225 Pump Station 0503 Upgrade 09/18/2015 A 09/18/2015 A 636Project CProject Closeout 09/18/2015 A 09/18/2015 A 636

B1445 Closeout Phase 09/18/2015 A 09/18/2015 A 636B1450 Issue SAC Letter 09/18/2015 A 0B1480 Administrative Closeout 09/18/2015 A 09/18/2015 A 5B1490 Project Closed 09/18/2015 A 0

Basin 0506Basin 0506 01/05/2016 A 11/08/2018 1057

100096 Pu100096 Pump Station 0506 Upgrade 01/05/2016 A 11/08/2018 1057DesignDesign 01/05/2016 A 03/06/2017 A 428

B1000 Design Phase 01/05/2016 A 03/06/2017 A 428B1010 Prepare and Submit Design Package 01/05/2016 A 01/05/2016 A 5B1020 Engage Design Consultant 01/05/2016 A 02/26/2016 A 20B1022 TA Preparation 02/29/2016 A 02/29/2016 A 1B1024 TA Approval Process 03/01/2016 A 03/16/2016 A 20B1030 Issue Design NTP 03/28/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 03/28/2016 A 11/02/2016 A 85

30% Des30% Design 03/28/2016 A 07/15/2016 A 104B1060 A/E Prepares 30% Construction Documents 03/28/2016 A 06/28/2016 A 30B1070 Geotechnical Engineering Services 03/28/2016 A 06/28/2016 A 20B1080 Surveying Services 03/28/2016 A 06/28/2016 A 15B1100 30% CDs Submittal 06/28/2016 A 0B1120 30% Review (MDWASD/PSIP Team) 06/29/2016 A 07/15/2016 A 10

90% Des90% Design 06/29/2016 A 02/21/2017 A 275B1170 A/E Prepares 90% Construction Documents 06/29/2016 A 09/26/2016 A 40B1180 90% CDs Submittal 09/26/2016 A 0B1190 90% Review (MDWASD/PSIP Team) 09/27/2016 A 11/02/2016 A 30B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 11/03/2016 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 11/03/2016 A 12/13/2016 A 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 01/04/2017 A 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 01/04/2017 A 01/24/2017 A 21B1260 90% CD PM Comments Evaluation Completed 01/25/2017 A 0B1262 MDWASD Union Concurrence Process 01/25/2017 A 02/21/2017 A 30

100% De100% Design 01/26/2017 A 03/06/2017 A 10

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Project Closed09/18/2015 A, Basin 0503

07/24/2015 A, 100095-3 Basin 0503 Infiltration/Inflow Study and Repairs07/23/2015 A, Infiltration/Inflow

Infiltration/Inflow Phase05/25/2015 A, Sanitary Sewer Evaluation SurveySSES Phase

Issue NTP to SSES ContractorConduct SSES

07/23/2015 A, Dig & Replace RepairsDig & Replace Phase

Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs

07/24/2015 A, Project CloseoutCloseout Phase

Project Closed09/18/2015 A, 100225 Pump Station 0503 Upgrade09/18/2015 A, Project Closeout

Closeout PhaseIssue SAC Letter

Administrative CloseoutProject Closed

11/08/2018, Basin 0506

11/08/2018, 100096 Pump Station 0506 Upgrade03/06/2017 A, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA PreparationTA Approval ProcessIssue Design NTP

Final Engineering Report Review & Approval (MDWASD/PSIP Team)07/15/2016 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal30% Review (MDWASD/PSIP Team)

02/21/2017 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)

90% RER(DERM)FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)

90% RER(Building Dept) Permit Review (Pump Station)90% CD PM Comments Evaluation Completed

MDWASD Union Concurrence Process03/06/2017 A, 100% Design

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 91 of 161 TASK filter: All Activities© Oracle Corporation

Page 92: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1270 A/E Prepares 100% Construction Documents 01/26/2017 A 03/01/2017 A 10B1280 100% CDs Submittal 03/01/2017 A 0B1290 100% Review (MDWASD/PSIP Team) 03/02/2017 A 03/06/2017 A 2B1300 Design Completed 03/06/2017 A 0

MDWASDMDWASD Procurement 03/07/2017 A 05/31/2017 A 79B1305 Procurement Phase 03/07/2017 A 05/31/2017 A 79B1310 Submit CDs to MDWASD Procurement Division 03/07/2017 A 0B1312 Bid Notice Preparation Period 03/08/2017 A 03/16/2017 A 23B1314 Bid Notice 03/16/2017 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 03/17/2017 A 03/22/2017 A 10B1320 Pre-Bid Conference 03/23/2017 A 03/23/2017 A 1B1328 Bidders Prepare Bids for Submittal 03/24/2017 A 04/20/2017 A 15B1330 Bids Submittal 04/20/2017 A 0B1340 MDWASD/PSIP Team Bids Evaluation 04/21/2017 A 04/26/2017 A 15B1350 Recommendation for Award Letter 04/26/2017 A 0B1355 Contract Award (Purchase Order Approval) 04/27/2017 A 05/31/2017 A 10

ConstrucConstruction 03/23/2017 A 07/11/2018 A 639B1360 Construction Phase 03/23/2017 A 07/11/2018 A 639B1364 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 04/27/2017 A 06/09/2017 A 15B1366 Pre-Construction Meeting 06/12/2017 A 06/12/2017 A 1B1368 WASD Issues NTP (Pre-Const to NTP) 06/13/2017 A 08/27/2017 A 24B1369 WASD Issues NTP (PO to NTP) 06/01/2017 A 08/27/2017 A 53B1370 Construction NTP 08/28/2017 A 0B1400 Construction Operations 08/28/2017 A 07/11/2018 A 150B1402 Substantial Completion 07/11/2018 A 0

DesignerDesigner Construction Support Services 03/23/2017 A 07/11/2018 A 260B1410 Designer Construction Support Services 03/23/2017 A 07/11/2018 A 778

Project CProject Closeout 07/12/2018 A 11/08/2018 120B1445 Closeout Phase 07/12/2018 A 11/08/2018 120B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 07/12/2018 A 11/08/2018 120B1490 Project Closed 11/08/2018 0

Basin 0527Basin 0527 09/21/2015 A 09/21/2015 A 838

100226 Pu100226 Pump Station 0527 Upgrade 09/21/2015 A 09/21/2015 A 838Project CProject Closeout 09/21/2015 A 09/21/2015 A 838

B1445 Closeout Phase 09/21/2015 A 09/21/2015 A 838B1450 Issue SAC Letter 09/21/2015 A 0B1480 Administrative Closeout 09/21/2015 A 09/21/2015 A 5B1490 Project Closed 09/21/2015 A 09/21/2015 A 10

Basin 0530Basin 0530 04/29/2016 A 11/30/2018 996

100098 Pu100098 Pump Station 0530 Upgrade 04/29/2016 A 11/30/2018 996DesignDesign 04/29/2016 A 07/17/2017 A 464

B1000 Design Phase 04/29/2016 A 07/17/2017 A 464B1010 Prepare and Submit Design Package 04/29/2016 A 05/10/2016 A 5B1020 Engage Design Consultant 05/10/2016 A 07/15/2016 A 20B1022 TA Preparation 07/18/2016 A 07/18/2016 A 1B1024 TA Approval Process 07/19/2016 A 10/21/2016 A 40

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed

05/31/2017 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation Period

Bid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter

Contract Award (Purchase Order Approval)07/11/2018 A, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Construction NTPConstruction OperationsSubstantial Completion07/11/2018 A, Designer Construction Support Services

Designer Construction Support Services11/08/2018, Project Closeout

Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction Contract

Administrative CloseoutProject Closed

09/21/2015 A, Basin 0527

09/21/2015 A, 100226 Pump Station 0527 Upgrade09/21/2015 A, Project Closeout

Closeout PhaseIssue SAC Letter

Administrative CloseoutProject Closed

11/30/2018, Basin 0530

11/30/2018, 100098 Pump Station 0530 Upgrade07/17/2017 A, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval Process

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 92 of 161 TASK filter: All Activities© Oracle Corporation

Page 93: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1030 Issue Design NTP 11/03/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 11/03/2016 A 06/26/2017 A 65

30% Des30% Design 11/03/2016 A 02/13/2017 A 100B1060 A/E Prepares 30% Construction Documents 11/03/2016 A 01/30/2017 A 50B1100 30% CDs Submittal 01/30/2017 A 0B1120 30% Review (MDWASD/PSIP Team) 01/31/2017 A 02/13/2017 A 30

90% Des90% Design 01/31/2017 A 06/26/2017 A 209B1170 A/E Prepares 90% Construction Documents 01/31/2017 A 03/24/2017 A 40B1180 90% CDs Submittal 03/24/2017 A 0B1190 90% Review (MDWASD/PSIP Team) 03/27/2017 A 05/05/2017 A 30B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 05/15/2017 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 05/15/2017 A 06/09/2017 A 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 06/12/2017 A 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 06/12/2017 A 06/26/2017 A 21B1260 90% CD PM Comments Evaluation Completed 06/26/2017 A 0B1262 MDWASD Union Concurrence Process 04/26/2017 A 06/20/2017 A 30

100% De100% Design 06/27/2017 A 07/17/2017 A 14B1270 A/E Prepares 100% Construction Documents 06/27/2017 A 07/10/2017 A 10B1280 100% CDs Submittal 07/10/2017 A 0B1290 100% Review (MDWASD/PSIP Team) 07/11/2017 A 07/17/2017 A 10B1300 Design Completed 07/17/2017 A 0

MDWASDMDWASD Procurement 07/18/2017 A 11/16/2017 A 118B1305 Procurement Phase 07/18/2017 A 11/16/2017 A 118B1310 Submit CDs to MDWASD Procurement Division 07/18/2017 A 0B1312 Bid Notice Preparation Period 07/19/2017 A 08/10/2017 A 33B1313 Bid Notice 08/10/2017 A 0B1315 MDWASD/PSIP Team Prepare for Pre-Bid Conferencce 08/11/2017 A 08/21/2017 A 14B1320 Pre-Bid Conference 08/22/2017 A 08/22/2017 A 1B1323 Bidders Prepare Bids for Submittal 08/23/2017 A 10/19/2017 A 21B1330 Bids Submittal 10/19/2017 A 0B1340 MDWASD/PSIP Team Bids Evaluation 10/20/2017 A 10/31/2017 A 21B1350 Recommendation for Award Letter 10/31/2017 A 0B1355 Contract Award (Purchase Order Approval) 11/01/2017 A 11/16/2017 A 14

ConstrucConstruction 08/22/2017 A 08/02/2018 506B1360 Construction Phase 08/22/2017 A 08/02/2018 506B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 11/01/2017 A 11/30/2017 A 21B1365 Pre-Construction Meeting 12/01/2017 A 12/01/2017 A 1B1366 WASD Issues NTP (Pre-Const to NTP) 12/02/2017 A 03/04/2018 A 45B1369 WASD Issues NTP (PO to NTP) 11/17/2017 A 03/04/2018 A 53B1370 Construction NTP 03/05/2018 A 0B1400 Construction Operations 03/05/2018 A 08/02/2018 151B1402 Substantial Completion 08/02/2018 0

DesignerDesigner Construction Support Services 08/22/2017 A 08/02/2018 260B1410 Designer Construction Support Services 08/22/2017 A 08/02/2018 260

Project CProject Closeout 08/01/2018 11/30/2018 122B1445 Closeout Phase 08/01/2018 11/30/2018 122B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 08/02/2018 0B1480 Administrative Closeout 08/03/2018 11/30/2018 120

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Issue Design NTPFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

02/13/2017 A, 30% Design

A/E Prepares 30% Construction Documents30% CDs Submittal30% Review (MDWASD/PSIP Team)

06/26/2017 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)90% RER(DERM)FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)90% RER(Building Dept) Permit Review (Pump Station)90% CD PM Comments Evaluation Completed

MDWASD Union Concurrence Process07/17/2017 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed

11/16/2017 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid Notice

MDWASD/PSIP Team Prepare for Pre-Bid ConferenccePre-Bid Conference

Bidders Prepare Bids for SubmittalBids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)

08/02/2018, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Construction NTPConstruction OperationsSubstantial Completion08/02/2018, Designer Construction Support Services

Designer Construction Support Services11/30/2018, Project Closeout

Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction Contract

Administrative Closeout

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 93 of 161 TASK filter: All Activities© Oracle Corporation

Page 94: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1490 Project Closed 11/30/2018 0

Basin 0542Basin 0542 11/10/2015 A 08/03/2018 1135

100100 Pu100100 Pump Station 0542 Upgrade 11/10/2015 A 08/03/2018 1135DesignDesign 11/10/2015 A 02/24/2017 A 571

B1000 Design Phase 11/10/2015 A 02/24/2017 A 571B1010 Prepare and Submit Design Package 11/10/2015 A 11/10/2015 A 5B1020 Engage Design Consultant 11/10/2015 A 12/25/2015 A 20B1022 TA Preparation 12/28/2015 A 12/28/2015 A 1B1024 TA Approval Process 12/29/2015 A 01/15/2016 A 20B1030 Issue Design NTP 01/15/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 01/15/2016 A 01/20/2017 A 65

30% Des30% Design 01/18/2016 A 05/24/2016 A 52B1060 A/E Prepares 30% Construction Documents 01/18/2016 A 05/04/2016 A 30B1070 Geotechnical Engineering Services 01/18/2016 A 05/04/2016 A 20B1080 Surveying Services 01/18/2016 A 05/04/2016 A 15B1100 30% CDs Submittal 05/04/2016 A 0B1120 30% Review (MDWASD/PSIP Team) 05/05/2016 A 05/24/2016 A 10

90% Des90% Design 05/05/2016 A 02/22/2017 A 365B1170 A/E Prepares 90% Construction Documents 05/05/2016 A 06/24/2016 A 20B1180 90% CDs Submittal 06/24/2016 A 0B1190 90% Review (MDWASD/PSIP Team) 06/27/2016 A 11/07/2016 A 15B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 01/09/2017 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 01/09/2017 A 01/11/2017 A 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 01/04/2017 A 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 01/04/2017 A 01/19/2017 A 21B1260 90% CD PM Comments Evaluation Completed 01/20/2017 A 0B1262 MDWASD Union Concurrence Process 01/25/2017 A 02/22/2017 A 30

100% De100% Design 01/23/2017 A 02/24/2017 A 28B1270 A/E Prepares 100% Construction Documents 01/23/2017 A 02/24/2017 A 10B1280 100% CDs Submittal 02/24/2017 A 0B1290 100% Review (MDWASD/PSIP Team) 02/24/2017 A 02/24/2017 A 10B1300 Design Completed 02/24/2017 A 0

MDWASDMDWASD Procurement 02/24/2017 A 06/08/2017 A 75B1305 Procurement Phase 02/24/2017 A 06/08/2017 A 75B1310 Submit CDs to MDWASD Procurement Division 02/24/2017 A 0B1312 Bid Notice Preparation Period 02/27/2017 A 03/06/2017 A 23B1314 Bid Notice 03/06/2017 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 03/07/2017 A 03/13/2017 A 10B1320 Pre-Bid Conference 03/14/2017 A 03/14/2017 A 1B1328 Bidders Prepare Bids for Submittal 03/15/2017 A 04/25/2017 A 15B1330 Bids Submittal 04/25/2017 A 0B1340 MDWASD/PSIP Team Bids Evaluation 04/26/2017 A 05/10/2017 A 15B1350 Recommendation for Award Letter 05/10/2017 A 0B1355 Contract Award (Purchase Order Approval) 05/11/2017 A 06/08/2017 A 10

ConstrucConstruction 03/14/2017 A 04/13/2018 A 615B1360 Construction Phase 03/14/2017 A 04/05/2018 A 615B1364 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 05/11/2017 A 07/12/2017 A 15B1366 Pre-Construction Meeting 07/13/2017 A 07/13/2017 A 1B1368 WASD Issues NTP (Pre-Const to NTP) 07/14/2017 A 08/27/2017 A 1

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Project Closed08/03/2018, Basin 0542

08/03/2018, 100100 Pump Station 0542 Upgrade02/24/2017 A, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval ProcessIssue Design NTP

Final Engineering Report Review & Approval (MDWASD/PSIP Team)05/24/2016 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services

30% CDs Submittal30% Review (MDWASD/PSIP Team)

02/22/2017 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)

90% RER(DERM)FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)

90% RER(Building Dept) Permit Review (Pump Station)90% CD PM Comments Evaluation Completed

MDWASD Union Concurrence Process02/24/2017 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal

100% Review (MDWASD/PSIP Team)Design Completed

06/08/2017 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid Notice

MDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids SubmittalMDWASD/PSIP Team Bids Evaluation

Recommendation for Award LetterContract Award (Purchase Order Approval)

04/13/2018 A, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 94 of 161 TASK filter: All Activities© Oracle Corporation

Page 95: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1369 WASD Issues NTP (PO to NTP) 06/09/2017 A 08/27/2017 A 53B1370 Construction NTP 08/28/2017 A 0B1400 Construction Operations 08/28/2017 A 04/05/2018 A 149B1400 Original Construction Duration 08/28/2017 A 01/25/2018 A 149B1400 Change Order #1 - Hurricane Irma 01/26/2018 A 02/15/2018 A 149B1400 Change Order #2 - FPL 02/16/2018 A 04/13/2018 A 149B1402 Substantial Completion 04/05/2018 A 0

DesignerDesigner Construction Support Services 03/14/2017 A 04/05/2018 A 260B1410 Designer Construction Support Services 03/14/2017 A 04/05/2018 A 778

Project CProject Closeout 04/06/2018 A 08/03/2018 124B1445 Closeout Phase 04/06/2018 A 08/03/2018 124B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 04/06/2018 A 08/03/2018 120B1490 Project Closed 08/03/2018 0

Basin 0560Basin 0560 11/06/2015 A 08/18/2019 1382

100101 Pu100101 Pump Station 0560 Upgrade 11/06/2015 A 08/18/2019 1382DesignDesign 11/06/2015 A 12/23/2016 A 434

B1000 Design Phase 11/06/2015 A 12/23/2016 A 434B1010 Prepare and Submit Design Package 11/06/2015 A 11/19/2015 A 5B1020 Engage Design Consultant 11/20/2015 A 12/28/2015 A 20B1022 TA Preparation 12/29/2015 A 12/29/2015 A 1B1024 TA Approval Process 12/14/2015 A 01/15/2016 A 20B1030 Issue Design NTP 01/20/2016 A 0B1040 A/E Develops and Submits Final Engineering Report 01/20/2016 A 12/15/2016 A 115B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 01/20/2016 A 08/25/2016 A 85

30% Des30% Design 01/20/2016 A 04/19/2016 A 87B1060 A/E Prepares 30% Construction Documents 01/20/2016 A 03/07/2016 A 30B1070 Geotechnical Engineering Services 01/20/2016 A 03/07/2016 A 20B1080 Surveying Services 01/20/2016 A 03/07/2016 A 15B1100 30% CDs Submittal 03/07/2016 A 0B1120 30% Review (MDWASD/PSIP Team) 03/08/2016 A 04/19/2016 A 10

60% Des60% Design 03/08/2016 A 06/23/2016 A 69B1130 A/E Prepares 60% Construction Documents 03/08/2016 A 05/24/2016 A 20B1140 60% CDs Submittal 05/24/2016 A 0B1160 60% Review (MDWASD/PSIP Team) 05/25/2016 A 06/23/2016 A 10

90% Des90% Design 05/25/2016 A 12/15/2016 A 197B1170 A/E Prepares 90% Construction Documents 05/25/2016 A 07/29/2016 A 20B1180 90% CDs Submittal 07/29/2016 A 0B1190 90% Review (MDWASD/PSIP Team) 08/01/2016 A 09/14/2016 A 30B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 09/26/2016 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 09/26/2016 A 11/02/2016 A 15B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 11/09/2016 A 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 11/09/2016 A 12/15/2016 A 15B1260 90% CD PM Comments Evaluation Completed 12/15/2016 A 0

100% De100% Design 12/16/2016 A 12/23/2016 A 28B1270 A/E Prepares 100% Construction Documents 12/16/2016 A 12/22/2016 A 10B1280 100% CDs Submittal 12/22/2016 A 0B1290 100% Review (MDWASD/PSIP Team) 12/22/2016 A 12/23/2016 A 10

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

WASD Issues NTP (PO to NTP)

Construction NTPConstruction Operations

Original Construction DurationChange Order #1 - Hurricane Irma

Change Order #2 - FPL

Substantial Completion04/05/2018 A, Designer Construction Support Services

Designer Construction Support Services08/03/2018, Project Closeout

Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction ContractAdministrative CloseoutProject Closed

08/18/2019, Basin 0560

08/18/2019, 100101 Pump Sta12/23/2016 A, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA PreparationTA Approval ProcessIssue Design NTP

A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

04/19/2016 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services

30% CDs Submittal30% Review (MDWASD/PSIP Team)

06/23/2016 A, 60% Design

A/E Prepares 60% Construction Documents60% CDs Submittal

60% Review (MDWASD/PSIP Team)12/15/2016 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)

90% RER(DERM)FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)

90% RER(Building Dept) Permit Review (Pump Station)90% CD PM Comments Evaluation Completed12/23/2016 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 95 of 161 TASK filter: All Activities© Oracle Corporation

Page 96: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1300 Design Completed 12/23/2016 A 0MDWASDMDWASD Procurement 12/23/2016 A 08/30/2018 596

B1305 Procurement Phase 12/23/2016 A 08/30/2018 596B1310 Submit CDs to MDWASD Procurement Division 12/23/2016 A 0B1312 Bid Notice Preparation Period 12/26/2016 A 01/24/2017 A 23B1314 Bid Notice 01/24/2017 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 01/25/2017 A 02/01/2017 A 10B1320 Pre-Bid Conference 02/02/2017 A 02/02/2017 A 1B1328 Bidders Prepare Bids for Submittal 02/03/2017 A 02/28/2017 A 15B1330 Bids Submittal 02/28/2017 A 0B1340 MDWASD/PSIP Team Bids Evaluation 03/01/2017 A 03/08/2017 A 6B1350 Recommendation for Award Letter 03/08/2017 A 0B1355 Contract Award (Purchase Order Approval) 03/09/2017 A 04/07/2017 A 10B1355 Submit CDs to MDWASD Procurement Division 05/18/2018 A 0B1355 Bid Notice Preparation Period 05/19/2018 A 06/13/2018 A 33B1355 Bid Notice 06/13/2018 A 0B1355 MDWASD/PSIP Team Prepare for Pre-Bid Conference 06/14/2018 A 06/25/2018 A 14B1355 Pre-Bid Conference 06/26/2018 A 06/26/2018 A 1B1355 Bidders Prepare Bids for Submittal 06/27/2018 A 07/26/2018 A 21B1355 Bids Submittal 07/26/2018 A 0B1355 MDWASD/PSIP Team Bids Evaluation 07/27/2018 A 08/16/2018 21B1355 Recommendation for Award Letter 08/16/2018 0B1355 Contract Award (Purchase Order Approval) 08/17/2018 08/30/2018 14

ConstrucConstruction 03/09/2017 A 04/20/2019 808B1360 Construction Phase 03/09/2017 A 04/20/2019 808B1364 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 03/09/2017 A 04/11/2017 A 15B1366 Pre-Construction Meeting 04/12/2017 A 04/12/2017 A 1B1368 WASD Issues NTP Period 04/13/2017 A 05/19/2017 A 45B1370 Construction NTP 05/22/2017 A 0B1400 Construction Operations 05/22/2017 A 08/09/2017 A 151B1400 WASD Terminate Contract 08/10/2017 A 08/10/2017 A 1B1400 WASD/PSIP Team Re-Package Resolution Period 08/11/2017 A 08/29/2017 A 160B1400 Finalize Project Closeout with A Green World (Contractor) 08/30/2017 A 08/01/2018 275B1400 A/E Prepared SOW to Re-Package Contract Documents 08/30/2017 A 03/15/2018 A 198B1400 TA Approval Process 03/16/2018 A 05/08/2018 A 40B1400 A/E Re-Package Contract Documents 05/09/2018 A 05/18/2018 A 10B1400 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 08/17/2018 09/06/2018 21B1400 Pre-Construction Meeting 09/07/2018 09/07/2018 1B1400 WASD Issues NTP (Pre-Const to NTP) 09/08/2018 10/22/2018 45B1400 WASD Issues NTP (PO to NTP) 08/31/2018 10/22/2018 53B1400 Construction NTP 10/23/2018 0B1400 Construction Operations 10/23/2018 04/20/2019 180B1402 Substantial Completion 04/20/2019 0

DesignerDesigner Construction Support Services 05/22/2017 A 04/20/2019 267B1410 Designer Construction Support Services 05/22/2017 A 04/20/2019 267

Project CProject Closeout 08/01/2018 08/18/2019 383B1445 Closeout Phase 08/01/2018 08/18/2019 383B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 04/20/2019 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Design Completed08/30/2018, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter

Contract Award (Purchase Order Approval)Submit CDs to MDWASD Procurement Division

Bid Notice Preparation Period

Bid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for Submittal

Bids SubmittalMDWASD/PSIP Team Bids Evaluation

Recommendation for Award LetterContract Award (Purchase Order Approval)

04/20/2019, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

WASD Issues NTP PeriodConstruction NTP

Construction OperationsWASD Terminate Contract

WASD/PSIP Team Re-Package Resolution PeriodFinalize Project Closeout with A Green World (Contractor)

A/E Prepared SOW to Re-Package Contract DocumentsTA Approval ProcessA/E Re-Package Contract Documents

MDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Construction NTPConstruction Operations

Substantial Completion04/20/2019, Designer Construction Supp

Designer Construction Support Services08/18/2019, Project Closeout

Closeout PhaseIssue SAC Letter

Final Release of Retainage - Construction

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 96 of 161 TASK filter: All Activities© Oracle Corporation

Page 97: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1480 Administrative Closeout 04/21/2019 08/18/2019 120B1490 Project Closed 08/18/2019 0

Basin 0592Basin 0592 09/17/2012 A 08/03/2018 2938

100103 FM100103 FM for Pump Station 0592 09/18/2015 A 08/01/2018 1143DesignDesign 09/18/2015 A 11/01/2016 A 607

B1000 Design Phase 09/18/2015 A 11/01/2016 A 607B1010 Prepare and Submit Design Package 09/18/2015 A 10/19/2015 A 5B1020 Engage Design Consultant 10/20/2015 A 11/12/2015 A 20B1022 TA Preparation 11/12/2015 A 11/12/2015 A 1B1024 TA Approval Provess 11/13/2015 A 12/11/2015 A 20B1030 Issue Design NTP 12/30/2015 A 0B1040 A/E Develops and Submits Final Engineering Report 12/30/2015 A 10/24/2016 A 105B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 12/30/2015 A 08/09/2016 A 85

30% Des30% Design 12/30/2015 A 02/25/2016 A 69B1060 A/E Prepares 30% Construction Documents 12/31/2015 A 02/08/2016 A 30B1070 Geotechnical Engineering Services 12/30/2015 A 02/08/2016 A 20B1080 Surveying Services 12/30/2015 A 02/08/2016 A 15B1100 30% CDs Submittal 02/08/2016 A 0B1120 30% Review (MDWASD/PSIP Team) 02/09/2016 A 02/25/2016 A 10

60% Des60% Design 02/09/2016 A 04/04/2016 A 44B1140 A/E Prepares 60% Construction Documents 02/09/2016 A 03/28/2016 A 20B1150 60% CDs Submittal 03/28/2016 A 0B1170 60% Review (MDWASD/PSIP Team) 03/29/2016 A 04/04/2016 A 10

90% Des90% Design 03/29/2016 A 10/24/2016 A 225B1180 A/E Prepares 90% Construction Documents 03/29/2016 A 06/27/2016 A 20B1190 90% CDs Submittal 06/27/2016 A 0B1200 90% Review (MDWASD/PSIP Team) 06/28/2016 A 08/09/2016 A 15B1202 90% CSX Permit Submittal (Force Main) 06/28/2016 A 0B1204 90% CSX Permit Review (Force Main) 06/28/2016 A 10/03/2016 A 15B1210 90% PWWMD Permit Submittal (Force Main) 07/13/2016 A 0B1220 90% PWWMD Permit Review (Force Main) 07/13/2016 A 07/29/2016 A 15B1230 90% RER(DERM)FDEP Permit Submittal (Force Main) 09/15/2016 A 0B1240 90% RER(DERM)FDEP Permit Review (Force Main) 09/15/2016 A 10/24/2016 A 15B1290 90% CD PM Comments Evaluation Completed 10/24/2016 A 0

100% De100% Design 10/25/2016 A 11/01/2016 A 57B1300 A/E Prepares 100% Construction Documents 10/25/2016 A 11/01/2016 A 10B1310 100% CDs Submittal 11/01/2016 A 0B1320 100% Review (MDWASD/PSIP Team) 10/25/2016 A 11/01/2016 A 10B1330 Design Completed 11/01/2016 A 0

MDWASDMDWASD Procurement 11/08/2016 A 03/17/2017 A 103B1335 Procurement Phase 11/08/2016 A 03/17/2017 A 103B1340 Submit CDs to MDWASD Procurement Division 11/08/2016 A 0B1342 Bid Notice Preparation Period 11/09/2016 A 11/17/2016 A 33B1344 Bid Notice 11/17/2016 A 0B1346 MDWASD/PSIP Prepare for Pre-Bid Conference 11/18/2016 A 11/28/2016 A 14B1350 Pre-Bid Conference 11/29/2016 A 11/29/2016 A 1B1358 Bidders Prepare Bids for Submittal 11/30/2016 A 01/13/2017 A 21B1360 Bids Submittal 01/13/2017 A 0B1370 MDWASD/PSIP Team Bids Evaluation 01/16/2017 A 02/17/2017 A 21

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Administrative CloseoutProject Closed

08/03/2018, Basin 0592

08/01/2018, 100103 FM for Pump Station 059211/01/2016 A, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval ProvessIssue Design NTP

A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

02/25/2016 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal30% Review (MDWASD/PSIP Team)

04/04/2016 A, 60% Design

A/E Prepares 60% Construction Documents60% CDs Submittal60% Review (MDWASD/PSIP Team)

10/24/2016 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% CSX Permit Submittal (Force Main)

90% CSX Permit Review (Force Main)90% PWWMD Permit Submittal (Force Main)90% PWWMD Permit Review (Force Main)

90% RER(DERM)FDEP Permit Submittal (Force Main)90% RER(DERM)FDEP Permit Review (Force Main)90% CD PM Comments Evaluation Completed11/01/2016 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal

100% Review (MDWASD/PSIP Team)Design Completed

03/17/2017 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation Period

Bid NoticeMDWASD/PSIP Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids Evaluation

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 97 of 161 TASK filter: All Activities© Oracle Corporation

Page 98: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1380 Recommendation for Award Letter 02/17/2017 A 0B1385 Contract Award (Purchase Order Approval) 02/20/2017 A 03/17/2017 A 14

ConstrucConstruction 11/29/2016 A 01/30/2018 A 747B1390 Construction Phase 11/29/2016 A 01/30/2018 A 747B1394 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 02/20/2017 A 04/04/2017 A 21B1396 Pre-Construction meeting 04/05/2017 A 04/05/2017 A 1B1398 WASD Issues NTP (Pre-Const to NTP) 04/05/2017 A 06/18/2017 A 45B1399 WASD Issues NTP (PO to NTP) 03/18/2017 A 06/18/2017 A 53B1400 Construction NTP 06/19/2017 A 0B1430 Construction Operations 06/19/2017 A 01/30/2018 A 241B1432 Substantial Completion 01/30/2018 A 0

DesignerDesigner Construction Support Services 11/29/2016 A 01/30/2018 A 277B1440 Designer Construction Support Services 11/29/2016 A 01/30/2018 A 277

Project CProject Closeout 01/31/2018 A 08/01/2018 201B1475 Closeout Phase 01/31/2018 A 08/01/2018 201B1500 Final Release of Retainage - Construction Contract 08/01/2018 0B1510 Administrative Closeout 01/31/2018 A 08/01/2018 120B1520 Project Closed 08/01/2018 0

100227 Pu100227 Pump Station 0592 Upgrade 09/17/2012 A 08/03/2018 2057DesignDesign 09/17/2012 A 04/05/2018 A 2027

B1000 Design Phase 09/17/2012 A 04/05/2018 A 2027B1012 Remedial Action Plan to SAC Issuance Letter 09/17/2012 A 04/05/2018 A 2027

ConstrucConstruction 08/01/2018 08/01/2018 0B1360 Construction Phase 08/01/2018 08/01/2018 0

Project CProject Closeout 04/05/2018 A 08/03/2018 820B1445 Closeout Phase 04/05/2018 A 08/03/2018 820B1450 Issue SAC Letter 04/05/2018 A 0B1480 Administrative Closeout 04/06/2018 A 08/03/2018 120B1490 Project Closed 08/03/2018 0

Basin 0596Basin 0596 05/11/2016 A 11/29/2019 1398

100104 Pu100104 Pump Station 0596 Upgrade 05/11/2016 A 11/29/2019 1398DesignDesign 05/11/2016 A 08/29/2018 941

B1000 Design Phase 05/11/2016 A 08/29/2018 941B1010 Prepare and Submit Design Package 05/11/2016 A 05/17/2016 A 7B1020 Engage Design Consultant 05/18/2016 A 07/19/2017 A 20B1022 TA Preparation 06/20/2017 A 06/20/2017 A 1B1024 TA Approval Process 06/21/2017 A 08/09/2017 A 40B1030 Issue Design NTP 09/21/2017 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 09/21/2017 A 08/01/2018 186

30% Des30% Design 09/22/2017 A 01/26/2018 A 102B1060 A/E Prepares 30% Construction Documents 09/22/2017 A 01/11/2018 A 50B1100 30% CDs Submittal 01/11/2018 A 0B1120 30% Review (MDWASD/PSIP Team) 01/12/2018 A 01/26/2018 A 30

90% Des90% Design 01/29/2018 A 08/01/2018 154B1170 A/E Prepares 90% Construction Documents 01/29/2018 A 03/22/2018 A 40B1180 90% CDs Submittal 03/22/2018 A 0B1190 90% Review (MDWASD/PSIP Team) 03/23/2018 A 05/18/2018 A 30B1200 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 05/21/2018 A 0B1210 90% RER(DERM)/FDEP Permit Review (Pump Station) 05/21/2018 A 06/25/2018 A 45

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Recommendation for Award LetterContract Award (Purchase Order Approval)

01/30/2018 A, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction meeting

WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Construction NTPConstruction OperationsSubstantial Completion01/30/2018 A, Designer Construction Support Services

Designer Construction Support Services08/01/2018, Project Closeout

Closeout PhaseFinal Release of Retainage - Construction ContractAdministrative CloseoutProject Closed08/03/2018, 100227 Pump Station 0592 Upgrade

04/05/2018 A, Design

Design PhaseRemedial Action Plan to SAC Issuance Letter

08/01/2018, Construction

Construction Phase08/03/2018, Project CloseoutCloseout Phase

Issue SAC LetterAdministrative Closeout

Project Closed11/29/2019, Basin 059

11/29/2019, 100104 P08/29/2018, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval ProcessIssue Design NTP

Final Engineering Report Review & Approval (MDWASD/PSIP 01/26/2018 A, 30% Design

A/E Prepares 30% Construction Documents30% CDs Submittal30% Review (MDWASD/PSIP Team)

08/01/2018, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)/FDEP Permit Submittal (Pump Station)

90% RER(DERM)/FDEP Permit Review (Pump Station)

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 98 of 161 TASK filter: All Activities© Oracle Corporation

Page 99: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 06/28/2018 A 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 06/28/2018 A 08/01/2018 21B1260 90% CD PM Comments Evaluation Completed 08/01/2018 0

100% De100% Design 08/02/2018 08/29/2018 28B1270 A/E Prepares 100% Construction Documents 08/02/2018 08/15/2018 14B1280 100% CDs Submittal 08/15/2018 0B1290 100% Review (MDWASD/PSIP Team) 08/16/2018 08/29/2018 14B1300 Design Completed 08/29/2018 0

MDWASDMDWASD Procurement 08/29/2018 12/11/2018 104B1305 Procurement Phase 08/29/2018 12/11/2018 104B1310 Submit CDs to MDWASD Procurement Division 08/29/2018* 0B1312 Bid Notice Preparation Period 08/30/2018 10/01/2018 33B1314 Bid Notice 10/01/2018 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 10/02/2018 10/15/2018 14B1320 Pre-Bid Conference 10/16/2018 10/16/2018 1B1322 Bidders Prepare Bids for Submittal 10/17/2018 11/06/2018 21B1330 Bids Submittal 11/06/2018 0B1340 MDWASD/PSIP Team Bids Evaluation 11/07/2018 11/27/2018 21B1350 Recommendation for Award Letter 11/27/2018 0B1355 Contract Award (Purchase Order Approval) 11/28/2018 12/11/2018 14

ConstrucConstruction 10/16/2018 08/01/2019 290B1360 Construction Phase 10/16/2018 08/01/2019 290B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 11/28/2018 12/18/2018 21B1364 Pre-Construction Meeting 12/19/2018 12/19/2018 1B1366 WASD Issues NTP (Pre-Const to NTP) 12/20/2018 02/02/2019 45B1369 WASD Issues NTP (PO to NTP) 12/12/2018 02/02/2019 53B1370 Construction NTP 02/03/2019 0B1400 Construction Operations 02/03/2019 08/01/2019 180B1402 Substantial Completion 08/01/2019 0

DesignerDesigner Construction Support Services 10/16/2018 08/01/2019 290B1410 Designer Construction Support Services 10/16/2018 08/01/2019 290

Project CProject Closeout 08/01/2018 11/29/2019 486B1445 Closeout Phase 08/01/2018 11/29/2019 486B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 08/01/2019 0B1480 Administrative Closeout 08/02/2019 11/29/2019 120B1490 Project Closed 11/29/2019 0

Basin 0604Basin 0604 07/07/2014 A 08/01/2018 1658

100106 FM100106 FM for Pump Station 0604 07/16/2014 A 08/01/2018 1615DesignDesign 07/16/2014 A 05/18/2015 A 326

B1000 Design Phase 07/16/2014 A 05/18/2015 A 326B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 07/16/2014 A 07/23/2014 A 5B1020 Engage Design Consultant 07/24/2014 A 11/05/2014 A 20B1030 Issue Design NTP 11/05/2014 A 0B1040 A/E Develops and Submits Final Engineering Report 11/05/2014 A 05/05/2015 A 20B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 03/23/2015 A 04/08/2015 A 10

30% Des30% Design 11/06/2014 A 02/18/2015 A 61B1060 A/E Prepares 30% Construction Documents 11/06/2014 A 02/11/2015 A 30B1070 Geotechnical Engineering Services 11/06/2014 A 02/11/2015 A 20

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

90% RER(Building Dept) Permit Submittal (Pump Station)90% RER(Building Dept) Permit Review (Pump Station)90% CD PM Comments Evaluation Completed

08/29/2018, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed

12/11/2018, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)

08/01/2019, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-ConstructionPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Construction NTPConstruction OperationsSubstantial Completion08/01/2019, Designer Constructi

Designer Construction Support S11/29/2019, Project CloCloseout Phase

Issue SAC LetterFinal Release of Retainage - Con

Administrative CloseouProject Closed

08/01/2018, Basin 0604

08/01/2018, 100106 FM for Pump Station 060405/18/2015 A, Design

Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book

Engage Design ConsultantIssue Design NTP

A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

02/18/2015 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering Services

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 99 of 161 TASK filter: All Activities© Oracle Corporation

Page 100: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1080 Surveying Services 11/06/2014 A 02/11/2015 A 15B1100 30% CDs Submittal 02/11/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 02/12/2015 A 02/18/2015 A 10

90% Des90% Design 02/12/2015 A 05/05/2015 A 85B1140 A/E Prepares 90% Construction Documents 02/12/2015 A 03/23/2015 A 20B1150 90% CDs Submittal 03/23/2015 A 0B1160 90% Review (MDWASD/PSIP Team) 03/24/2015 A 04/08/2015 A 5B1170 90% PWWMD Permit Submittal 04/22/2015 A 0B1180 90% PWWMD Permit Review 04/22/2015 A 05/05/2015 A 10B1190 90% RER(DERM)FDEP Permit Submittal (Force Main) 04/10/2015 A 0B1200 90% RER(DERM)FDEP Permit Review (Force Main) 04/10/2015 A 04/29/2015 A 5B1250 90% CD PM Comments Evaluation Completed 05/05/2015 A 0

100% De100% Design 05/06/2015 A 05/18/2015 A 14B1260 A/E Prepares 100% Construction Documents 05/06/2015 A 05/13/2015 A 5B1270 100% CDs Submittal 05/13/2015 A 0B1280 100% Review (MDWASD/PSIP Team) 05/14/2015 A 05/18/2015 A 5B1290 Design Completed 05/18/2015 A 0

MDWASDMDWASD Procurement 04/23/2015 A 07/27/2015 A 111B1295 Procurement Phase 04/23/2015 A 07/27/2015 A 111B1300 Submit CDs to MDWASD Procurement Division 04/23/2015 A 0B1310 Pre-Bid Conference 05/12/2015 A 0B1320 Bids Submittal 06/15/2015 A 0B1330 MDWASD/PSIP Team Bids Evaluation 06/16/2015 A 06/19/2015 A 20B1340 Recommendation for Award Letter 06/19/2015 A 0B1345 Contract Award (Purchase Order Approval) 06/22/2015 A 07/27/2015 A 10

ConstrucConstruction 05/12/2015 A 12/15/2015 A 1226B1350 Construction Phase 05/12/2015 A 12/15/2015 A 1226B1354 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 06/22/2015 A 07/24/2015 A 15B1356 Pre-Construction Meeting 07/27/2015 A 07/27/2015 A 1B1358 Permits / Shop Drawings / Material Orders 07/27/2015 A 11/20/2015 A 15B1359 WASD Issues NTP (PO to NTP) 07/28/2015 A 08/09/2015 A 53B1360 Construction NTP 08/10/2015 A 0B1390 Construction Operations 08/10/2015 A 12/15/2015 A 100B1392 Substantial Completion 12/15/2015 A 0

DesignerDesigner Construction Services 05/12/2015 A 12/15/2015 A 175B1400 Designer Construction Support Services 05/12/2015 A 12/15/2015 A 175

ConstrucConstruction Close Out 12/01/2015 A 12/15/2015 A 15B1410 Commissioning 12/01/2015 A 12/15/2015 A 15B1420 Punch List 12/01/2015 A 12/15/2015 A 10

Project CProject Closeout 12/16/2015 A 08/01/2018 944B1435 Closeout Phase 12/16/2015 A 08/01/2018 944B1460 Final Release of Retainage - Construction Contract 03/07/2017 A 0B1470 Administrative Closeout 12/16/2015 A 08/01/2018 120B1480 Project Closed 08/01/2018 0

100105-2 B100105-2 Basin 0604 Infiltration/Inflow Study and Repairs 09/25/2014 A 10/06/2015 A 609InfiltratioInfiltration/Inflow 09/25/2014 A 10/05/2015 A 429

B1000 Infiltration/Inflow Phase 09/25/2014 A 10/05/2015 A 429Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 12/19/2014 A 274

B1005 SSES Phase 09/25/2014 A 12/19/2014 A 274

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Surveying Services30% CDs Submittal

30% Review (MDWASD/PSIP Team)05/05/2015 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)

90% PWWMD Permit Submittal90% PWWMD Permit Review

90% RER(DERM)FDEP Permit Submittal (Force Main)90% RER(DERM)FDEP Permit Review (Force Main)90% CD PM Comments Evaluation Completed05/18/2015 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal

100% Review (MDWASD/PSIP Team)Design Completed

07/27/2015 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement DivisionPre-Bid Conference

Bids SubmittalMDWASD/PSIP Team Bids Evaluation

Recommendation for Award LetterContract Award (Purchase Order Approval)

12/15/2015 A, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

Permits / Shop Drawings / Material OrdersWASD Issues NTP (PO to NTP)

Construction NTPConstruction OperationsSubstantial Completion

12/15/2015 A, Designer Construction Services

Designer Construction Support Services12/15/2015 A, Construction Close Out

CommissioningPunch List

08/01/2018, Project Closeout

Closeout PhaseFinal Release of Retainage - Construction Contract

Administrative CloseoutProject Closed

10/06/2015 A, 100105-2 Basin 0604 Infiltration/Inflow Study and Repairs10/05/2015 A, Infiltration/Inflow

Infiltration/Inflow Phase12/19/2014 A, Sanitary Sewer Evaluation SurveySSES Phase

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 100 of 161 TASK filter: All Activities© Oracle Corporation

Page 101: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 10/10/2014 A 12/05/2014 A 30B1031 Smoke Testing 10/21/2014 A 10/21/2014 A 10B1040 Video Review 12/08/2014 A 12/19/2014 A 30

CIPP RepCIPP Repairs 04/17/2015 A 06/17/2015 A 33B1065 CIPP Phase 04/17/2015 A 06/17/2015 A 33B1080 Issue NTP for CIPP Repairs 04/17/2015 A 0B1090 Conduct CIPP Repairs 06/17/2015 A 06/17/2015 A 20

ManholeManhole Repairs 07/15/2015 A 10/05/2015 A 20B1115 Manhole Phase 07/15/2015 A 10/05/2015 A 20B1130 Issue NTP for Manhole Repairs 07/15/2015 A 0B1140 Conduct Manhole Repairs 09/30/2015 A 10/05/2015 A 20

Dig & ReDig & Replace Repairs 06/26/2015 A 09/18/2015 A 30B1165 Dig & Replace Phase 06/26/2015 A 09/18/2015 A 30B1180 Issue NTP for Dig & Replace Repairs 06/26/2015 A 0B1190 Conduct Dig & Replace Repairs 09/14/2015 A 09/18/2015 A 30

Project CProject Closeout 10/06/2015 A 10/06/2015 A 0B1235 Closeout Phase 10/06/2015 A 10/06/2015 A 0B1260 Project Closed 10/06/2015 A 0

100107 Pu100107 Pump Station 0604 Upgrade 07/07/2014 A 08/01/2018 1658DesignDesign 07/07/2014 A 04/21/2016 A 403

B1000 Design Phase 07/07/2014 A 04/21/2016 A 403B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 07/07/2014 A 07/14/2014 A 5B1020 Engage Design Consultant 07/14/2014 A 10/08/2014 A 20B1030 Issue Design NTP 10/08/2014 A 0B1032 TA Rev 1 - Approval Process 01/19/2016 A 04/21/2016 A 20B1040 A/E Develops and Submits Final Engineering Report 10/08/2014 A 07/28/2015 A 20B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/08/2014 A 02/17/2015 A 10

30% Des30% Design 09/10/2014 A 11/26/2014 A 45B1060 A/E Prepares 30% Construction Documents 09/10/2014 A 11/17/2014 A 30B1070 Geotechnical Engineering Services 10/20/2014 A 10/24/2014 A 20B1080 Surveying Services 10/17/2014 A 11/14/2014 A 15B1100 30% CDs Submittal 11/17/2014 A 0B1120 30% Review (MDWASD/PSIP Team) 11/18/2014 A 11/26/2014 A 10

90% Des90% Design 11/18/2014 A 07/28/2015 A 189B1170 A/E Prepares 90% Construction Documents 11/18/2014 A 01/28/2015 A 20B1180 90% CDs Submittal 01/28/2015 A 0B1190 90% Review (MDWASD/PSIP Team) 01/29/2015 A 02/17/2015 A 15B1191 Design Consultant Preparing Permit Packages 02/23/2015 A 03/04/2015 A 10B1200 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 03/06/2015 A 0B1210 90% RER(DERM)/FDEP Permit Review (Pump Station) 03/06/2015 A 06/24/2015 A 15B1220 90% RER (Building Dept) Permit Submittal 06/25/2015 A 0B1230 90% RER (Building Dept) Permit Review 06/25/2015 A 07/28/2015 A 15B1260 90% CD PM Comments Evaluation Completed 07/28/2015 A 0

100% De100% Design 07/29/2015 A 08/07/2015 A 18B1270 A/E Prepares 100% Construction Documents 07/29/2015 A 08/07/2015 A 10B1280 100% CDs Submittal 08/07/2015 A 0B1290 100% Review (MDWASD/PSIP Team) 08/07/2015 A 08/07/2015 A 10B1300 Design Completed 08/07/2015 A 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Issue NTP to SSES ContractorConduct SSES

Smoke Testing

Video Review06/17/2015 A, CIPP RepairsCIPP Phase

Issue NTP for CIPP RepairsConduct CIPP Repairs

10/05/2015 A, Manhole RepairsManhole Phase

Issue NTP for Manhole RepairsConduct Manhole Repairs

09/18/2015 A, Dig & Replace RepairsDig & Replace Phase

Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs10/06/2015 A, Project CloseoutCloseout Phase

Project Closed08/01/2018, 100107 Pump Station 0604 Upgrade

04/21/2016 A, Design

Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book

Engage Design ConsultantIssue Design NTP

TA Rev 1 - Approval Process

A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

11/26/2014 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering Services

Surveying Services30% CDs Submittal

30% Review (MDWASD/PSIP Team)07/28/2015 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)Design Consultant Preparing Permit Packages90% RER(DERM)/FDEP Permit Submittal (Pump Station)

90% RER(DERM)/FDEP Permit Review (Pump Station)90% RER (Building Dept) Permit Submittal

90% RER (Building Dept) Permit Review90% CD PM Comments Evaluation Completed08/07/2015 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 101 of 161 TASK filter: All Activities© Oracle Corporation

Page 102: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

MDWASDMDWASD Procurement 04/28/2015 A 08/11/2015 A 204B1305 Procurement Phase 04/28/2015 A 08/11/2015 A 204B1310 Submit CDs to MDWASD Procurement Division 04/28/2015 A 0B1312 Bid Notice Preparation Period 04/29/2015 A 05/05/2015 A 23B1314 Bid Notice 05/06/2015 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conferencce 05/07/2015 A 05/14/2015 A 10B1320 Pre-Bid Conference 05/15/2015 A 05/15/2015 A 1B1328 Bidders Prepare Bids for Submittal 05/18/2015 A 07/16/2015 A 15B1330 Bids Submittal 07/17/2015 A 0B1340 MDWASD/PSIP Team Bids Evaluation 07/20/2015 A 07/22/2015 A 15B1350 Recommendation for Award Letter 07/22/2015 A 0B1355 Contract Award (Purchase Order Approval) 07/23/2015 A 08/11/2015 A 10

ConstrucConstruction 05/15/2015 A 01/24/2017 A 1258B1360 Construction Phase 05/15/2015 A 01/24/2017 A 1258B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 07/23/2015 A 07/27/2015 A 15B1365 Pre-Construction Meeting 07/28/2015 A 07/28/2015 A 1B1369 WASD Issues NTP (PO to NTP) 08/12/2015 A 08/16/2015 A 53B1370 Construction NTP 08/17/2015 A 0B1400 Construction Operations 08/17/2015 A 03/02/2016 A 104B1400 Original Construction Duration 08/17/2015 A 01/09/2016 A 104B1400 Change Order #1 - Electrical Revisions, Shopdrawing Approval 01/10/2016 A 02/26/2016 A 104B1400 Change Order #2 - FPL 02/27/2016 A 03/02/2016 A 104B1402 Substantial Completion 03/02/2016 A 0

DesignerDesigner Construction Support Services 05/15/2015 A 01/24/2017 A 114B1410 Designer Construction Support Services 05/15/2015 A 01/24/2017 A 114

ConstrucConstruction Close Out 03/03/2016 A 08/31/2016 A 15B1420 Commissioning 03/03/2016 A 08/31/2016 A 15B1430 Punch List 03/03/2016 A 06/30/2016 A 10

Project CProject Closeout 03/03/2016 A 08/01/2018 853B1445 Closeout Phase 03/03/2016 A 08/01/2018 853B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 08/23/2016 A 0B1480 Administrative Closeout 03/03/2016 A 08/01/2018 30B1490 Project Closed 08/01/2018 0

Basin 0607Basin 0607 05/19/2014 A 05/31/2017 A 1637

100109 Pu100109 Pump Station 0607 Upgrade 05/19/2014 A 05/31/2017 A 1637100% De100% Design 06/23/2014 A 06/23/2014 A 0

B1300 Design Completed 06/23/2014 A 0MDWASDMDWASD Procurement 05/19/2014 A 09/24/2014 A 173

B1305 Procurement Phase 05/19/2014 A 09/24/2014 A 173B1310 Submit CDs to MDWASD Procurement Division 05/19/2014 A 0B1312 Bid Notice Preparation Period 05/20/2014 A 06/30/2014 A 23B1313 Bid Notice 06/30/2014 A 0B1315 MDWASD/PSIP Team Prepare for Pre-Bid Conferencce 07/01/2014 A 07/16/2014 A 10B1320 Pre-Bid Conference 07/16/2014 A 0B1323 Bidders Prepare Bids for Submittal 07/17/2014 A 07/24/2014 A 15B1330 Bids Submittal 07/24/2014 A 0B1340 MDWASD/PSIP Team Bids Evaluation 07/25/2014 A 08/13/2014 A 10B1350 Recommendation for Award Letter 08/14/2014 A 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

08/11/2015 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation Period

Bid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferenccePre-Bid Conference

Bidders Prepare Bids for SubmittalBids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)

01/24/2017 A, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

WASD Issues NTP (PO to NTP)

Construction NTPConstruction Operations

Original Construction DurationChange Order #1 - Electrical Revisions, Shopdrawing ApprovalChange Order #2 - FPL

Substantial Completion01/24/2017 A, Designer Construction Support Services

Designer Construction Support Services08/31/2016 A, Construction Close Out

CommissioningPunch List

08/01/2018, Project Closeout

Closeout PhaseIssue SAC Letter

Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed

05/31/2017 A, Basin 0607

05/31/2017 A, 100109 Pump Station 0607 Upgrade06/23/2014 A, 100% Design

Design Completed09/24/2014 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferenccePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 102 of 161 TASK filter: All Activities© Oracle Corporation

Page 103: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1352 Contract Award (Purchase Order Approval) 08/15/2014 A 09/24/2014 A 10ConstrucConstruction 09/24/2014 A 11/30/2015 A 1523

B1360 Construction Phase 09/24/2014 A 11/30/2015 A 1523B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 09/25/2014 A 10/07/2014 A 15B1365 Pre-Construction Meeting 10/07/2014 A 0B1369 WASD Issues NTP (PO to NTP) 09/25/2014 A 12/07/2014 A 53B1370 Construction NTP 12/08/2014 A 0B1380 Mobilization 01/12/2015 A 05/22/2015 A 40B1390 Permit Approvals 09/24/2014 A 12/07/2014 A 20B1400 Construction Operations 12/08/2014 A 10/14/2015 A 249B1400 Original Construction Duration 12/08/2014 A 06/06/2015 A 249B1400 Change Order #1 - Re-Design of Pipe Diameter 06/07/2015 A 08/13/2015 A 249B1400 Change Order #2 - Additional Wet Well Repairs, Tropical Stor W 08/14/2015 A 10/14/2015 A 249B1402 Substantial Completion 10/14/2015 A 0

DesignerDesigner Construction Support Services 12/08/2014 A 11/30/2015 A 140B1410 Designer Construction Support Services 12/08/2014 A 11/30/2015 A 140

ConstrucConstruction Close Out 10/15/2015 A 11/30/2015 A 15B1420 Commissioning 10/15/2015 A 11/30/2015 A 15B1430 Punch List 10/15/2015 A 11/30/2015 A 10

Project CProject Closeout 10/15/2015 A 05/31/2017 A 853B1445 Closeout Phase 10/15/2015 A 05/31/2017 A 853B1450 Issue SAC Letter 11/30/2015 A 0B1470 Final Release of Retainage - Construction Contract 10/31/2016 A 0B1480 Administrative Closeout 10/15/2015 A 05/31/2017 A 120B1490 Project Closed 05/31/2017 A 0

100108-2 B100108-2 Basin 0607 Infiltration/Inflow Study and Repairs 09/25/2014 A 03/10/2016 A 609InfiltratioInfiltration/Inflow 09/25/2014 A 03/09/2016 A 431

B1000 Infiltration/Inflow Phase 09/25/2014 A 03/09/2016 A 431Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 12/31/2014 A 267

B1005 SSES Phase 09/25/2014 A 12/31/2014 A 267B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 10/15/2014 A 12/18/2014 A 30B1031 Smoke Testing 11/06/2014 A 11/12/2014 A 10B1040 Video Review 11/03/2014 A 12/31/2014 A 30

CIPP RepCIPP Repairs 04/17/2015 A 03/09/2016 A 34B1065 CIPP Phase 04/17/2015 A 03/09/2016 A 34B1080 Issue NTP for CIPP Repairs 04/17/2015 A 0B1090 Conduct CIPP Repairs 05/27/2015 A 03/09/2016 A 20

ManholeManhole Repairs 07/15/2015 A 11/09/2015 A 111B1115 Manhole Phase 07/15/2015 A 11/09/2015 A 111B1130 Issue NTP for Manhole Repairs 07/15/2015 A 0B1140 Conduct Manhole Repairs 08/26/2015 A 11/09/2015 A 20

Dig & ReDig & Replace Repairs 05/18/2015 A 06/19/2015 A 30B1165 Dig & Replace Phase 05/18/2015 A 06/19/2015 A 30B1180 Issue NTP for Dig & Replace Repairs 05/18/2015 A 0B1190 Conduct Dig & Replace Repairs 06/11/2015 A 06/19/2015 A 30

Project CProject Closeout 03/10/2016 A 03/10/2016 A 0B1235 Closeout Phase 03/10/2016 A 03/10/2016 A 0B1260 Project Closed 03/10/2016 A 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Contract Award (Purchase Order Approval)11/30/2015 A, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

WASD Issues NTP (PO to NTP)

Construction NTPMobilization

Permit ApprovalsConstruction Operations

Original Construction DurationChange Order #1 - Re-Design of Pipe Diameter

Change Order #2 - Additional Wet Well Repairs, Tropical Stor Weather Preparation

Substantial Completion11/30/2015 A, Designer Construction Support Services

Designer Construction Support Services11/30/2015 A, Construction Close Out

CommissioningPunch List

05/31/2017 A, Project Closeout

Closeout PhaseIssue SAC Letter

Final Release of Retainage - Construction ContractAdministrative Closeout

Project Closed03/10/2016 A, 100108-2 Basin 0607 Infiltration/Inflow Study and Repairs03/09/2016 A, Infiltration/Inflow

Infiltration/Inflow Phase12/31/2014 A, Sanitary Sewer Evaluation Survey

SSES PhaseIssue NTP to SSES Contractor

Conduct SSESSmoke Testing

Video Review03/09/2016 A, CIPP Repairs

CIPP PhaseIssue NTP for CIPP Repairs

Conduct CIPP Repairs11/09/2015 A, Manhole Repairs

Manhole PhaseIssue NTP for Manhole Repairs

Conduct Manhole Repairs06/19/2015 A, Dig & Replace Repairs

Dig & Replace PhaseIssue NTP for Dig & Replace Repairs

Conduct Dig & Replace Repairs03/10/2016 A, Project Closeout

Closeout PhaseProject Closed

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 103 of 161 TASK filter: All Activities© Oracle Corporation

Page 104: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

Basin 0609Basin 0609 03/28/2014 A 08/01/2018 1759

100111 FM100111 FM for Pump Station 0609 03/28/2014 A 11/25/2014 A 24PlanningPlanning 03/28/2014 A 11/25/2014 A 24

B0900 Planning Phase 03/28/2014 A 11/25/2014 A 24B0940 Develop Remedial Action Plan (RAP) 03/28/2014 A 05/22/2014 A 10B0950 Develop Preliminary Engineering Report (PER) 05/23/2014 A 11/25/2014 A 10

100110-2 B100110-2 Basin 0609 Infiltration/Inflow Study and Repairs 04/17/2015 A 10/01/2015 A 372InfiltratioInfiltration/Inflow 04/17/2015 A 09/30/2015 A 209

B1000 Infiltration/Inflow Phase 04/17/2015 A 09/30/2015 A 209CIPP RepCIPP Repairs 04/17/2015 A 07/20/2015 A 40

B1005 CIPP Phase 04/17/2015 A 07/20/2015 A 40B1020 Issue NTP for CIPP Repairs 04/17/2015 A 0B1030 Conduct CIPP Repairs 06/19/2015 A 07/20/2015 A 20

ManholeManhole Repairs 07/15/2015 A 09/30/2015 A 140B1055 Manhole Phase 07/15/2015 A 09/30/2015 A 140B1070 Issue NTP for Manhole Repairs 07/15/2015 A 0B1080 Conduct Manhole Repairs 09/30/2015 A 09/30/2015 A 20

Dig & ReDig & Replace Repairs 05/18/2015 A 06/19/2015 A 30B1105 Dig & Replace Phase 05/18/2015 A 06/19/2015 A 30B1120 Issue NTP for Dig & Replace Repairs 05/18/2015 A 0B1130 Conduct Dig & Replace Repairs 06/03/2015 A 06/19/2015 A 30

Project CProject Closeout 10/01/2015 A 10/01/2015 A 0B1175 Closeout Phase 10/01/2015 A 10/01/2015 A 0B1200 Project Closed 10/01/2015 A 0

100228 Pu100228 Pump Station 0609 Upgrade 08/28/2014 A 08/01/2018 1606DesignDesign 08/28/2014 A 05/28/2015 A 307

B1000 Design Phase 08/28/2014 A 05/28/2015 A 307B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 08/28/2014 A 09/02/2014 A 5B1020 Engage Design Consultant 09/03/2014 A 11/05/2014 A 20B1030 Issue Design NTP 11/06/2014 A 0B1040 A/E Develops and Submits Final Engineering Report 11/06/2014 A 05/04/2015 A 20B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 02/26/2015 A 04/06/2015 A 10

30% Des30% Design 11/06/2014 A 01/23/2015 A 80B1060 A/E Prepares 30% Construction Documents 11/06/2014 A 01/08/2015 A 30B1070 Geotechnical Engineering Services 11/19/2014 A 01/08/2015 A 20B1080 Surveying Services 11/19/2014 A 12/08/2014 A 15B1100 30% CDs Submittal 01/08/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 01/09/2015 A 01/23/2015 A 10

90% Des90% Design 01/09/2015 A 05/22/2015 A 127B1170 A/E Prepares 90% Construction Documents 01/09/2015 A 02/25/2015 A 20B1180 90% CDs Submittal 02/25/2015 A 0B1190 90% Review (MDWASD/PSIP Team) 02/26/2015 A 03/05/2015 A 15B1200 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 03/06/2015 A 0B1210 90% RER(DERM)/FDEP Permit Review (Pump Station) 03/06/2015 A 04/06/2015 A 15B1220 90% Cutler Bay - BD Permit Submittal 04/10/2015 A 0B1230 90% Cutller Bay - BD Permit Review 04/10/2015 A 05/22/2015 A 15B1240 90% RER (Building Dept) Permit Submittal 04/21/2015 A 0B1250 90% RER (Building Dept) Permit Review 04/21/2015 A 05/04/2015 A 15B1260 90% CD PM Comments Evaluation Completed 05/04/2015 A 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

08/01/2018, Basin 0609

11/25/2014 A, 100111 FM for Pump Station 060911/25/2014 A, Planning

Planning PhaseDevelop Remedial Action Plan (RAP)

Develop Preliminary Engineering Report (PER)10/01/2015 A, 100110-2 Basin 0609 Infiltration/Inflow Study and Repairs09/30/2015 A, Infiltration/Inflow

Infiltration/Inflow Phase07/20/2015 A, CIPP RepairsCIPP Phase

Issue NTP for CIPP RepairsConduct CIPP Repairs

09/30/2015 A, Manhole RepairsManhole Phase

Issue NTP for Manhole RepairsConduct Manhole Repairs

06/19/2015 A, Dig & Replace RepairsDig & Replace Phase

Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs

10/01/2015 A, Project CloseoutCloseout Phase

Project Closed08/01/2018, 100228 Pump Station 0609 Upgrade

05/28/2015 A, Design

Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book

Engage Design ConsultantIssue Design NTP

A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

01/23/2015 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering Services

Surveying Services30% CDs Submittal

30% Review (MDWASD/PSIP Team)05/22/2015 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)90% RER(DERM)/FDEP Permit Submittal (Pump Station)

90% RER(DERM)/FDEP Permit Review (Pump Station)90% Cutler Bay - BD Permit Submittal

90% Cutller Bay - BD Permit Review90% RER (Building Dept) Permit Submittal

90% RER (Building Dept) Permit Review90% CD PM Comments Evaluation Completed

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 104 of 161 TASK filter: All Activities© Oracle Corporation

Page 105: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

100% De100% Design 03/06/2015 A 05/28/2015 A 12B1270 A/E Prepares 100% Construction Documents 03/06/2015 A 05/22/2015 A 10B1280 100% CDs Submittal 05/22/2015 A 0B1290 100% Review (MDWASD/PSIP Team) 05/23/2015 A 05/28/2015 A 10B1300 Design Completed 05/28/2015 A 0

MDWASDMDWASD Procurement 04/28/2015 A 08/26/2015 A 117B1305 Procurement Phase 04/28/2015 A 08/26/2015 A 117B1310 Submit CDs to MDWASD Procurement Division 04/28/2015 A 0B1320 Pre-Bid Conference 05/06/2015 A 05/06/2015 A 1B1330 Bids Submittal 05/28/2015 A 0B1340 MDWASD/PSIP Team Bids Evaluation 05/29/2015 A 07/09/2015 A 15B1350 Recommendation for Award Letter 07/09/2015 A 0B1355 Contract Award (Purchase Order Approval) 07/10/2015 A 08/26/2015 A 10

ConstrucConstruction 05/06/2015 A 10/03/2016 A 1258B1360 Construction Phase 05/06/2015 A 10/03/2016 A 1258B1364 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 07/10/2015 A 07/27/2015 A 15B1366 Pre-Construction Meeting 07/28/2015 A 07/28/2015 A 1B1369 WASD Issues NTP (PO to NTP) 08/27/2015 A 09/01/2015 A 53B1370 Construction NTP 09/02/2015 A 0B1400 Construction Operations 09/02/2015 A 01/19/2016 A 71B1402 Substantial Completion 01/19/2016 A 0

DesignerDesigner Construction Support Services 05/06/2015 A 10/03/2016 A 127B1410 Designer Construction Support Services 05/06/2015 A 10/03/2016 A 127

ConstrucConstruction Close Out 01/19/2016 A 08/31/2016 A 15B1420 Commissioning 01/19/2016 A 01/28/2016 A 15B1430 Punch List 01/20/2016 A 08/31/2016 A 10

Project CProject Closeout 09/21/2015 A 08/01/2018 1045B1445 Closeout Phase 09/21/2015 A 08/01/2018 1045B1450 Issue SAC Letter 09/21/2015 A 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 01/20/2016 A 08/01/2018 30B1490 Project Closed 08/01/2018 0

Basin 0613Basin 0613 05/12/2014 A 08/01/2018 1901

100113 Pu100113 Pump Station 0613 Upgrade 05/12/2014 A 08/01/2018 1106DesignDesign 05/12/2014 A 12/04/2015 A 47

B1000 Design Phase 05/12/2014 A 12/04/2015 A 47B1002 RAP - Remedial Action Plan 05/12/2014 A 05/12/2014 A 1B1004 PER - Preliminary Engineer Report 10/19/2015 A 12/04/2015 A 47

Project CProject Closeout 12/05/2015 A 08/01/2018 1106B1445 Closeout Phase 12/05/2015 A 08/01/2018 1106B1447 SAC Letter Execution Period 12/05/2015 A 08/28/2017 A 616B1450 Issue SAC Letter 08/28/2017 A 0B1480 Administrative Closeout 08/29/2017 A 08/01/2018 120B1490 Project Closed 08/01/2018 0

100112 FM100112 FM for Pump Station 0613 05/12/2014 A 08/01/2018 911DesignDesign 05/12/2014 A 12/04/2015 A 47

B1000 Design Phase 05/12/2014 A 12/04/2015 A 47B1002 RAP - Remedial Action Plan 05/12/2014 A 05/12/2014 A 1B1004 PER - Preliminary Engineer Report 10/19/2015 A 12/04/2015 A 47

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

05/28/2015 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed

08/26/2015 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement DivisionPre-Bid Conference

Bids SubmittalMDWASD/PSIP Team Bids Evaluation

Recommendation for Award LetterContract Award (Purchase Order Approval)

10/03/2016 A, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

WASD Issues NTP (PO to NTP)

Construction NTPConstruction OperationsSubstantial Completion

10/03/2016 A, Designer Construction Support Services

Designer Construction Support Services08/31/2016 A, Construction Close Out

CommissioningPunch List

08/01/2018, Project Closeout

Closeout PhaseIssue SAC Letter

Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed08/01/2018, Basin 0613

08/01/2018, 100113 Pump Station 0613 Upgrade12/04/2015 A, Design

Design PhaseRAP - Remedial Action Plan

PER - Preliminary Engineer Report08/01/2018, Project CloseoutCloseout Phase

SAC Letter Execution Period

Issue SAC LetterAdministrative CloseoutProject Closed08/01/2018, 100112 FM for Pump Station 0613

12/04/2015 A, Design

Design PhaseRAP - Remedial Action Plan

PER - Preliminary Engineer Report

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 105 of 161 TASK filter: All Activities© Oracle Corporation

Page 106: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

Project CProject Closeout 08/29/2017 A 08/01/2018 667B1475 Closeout Phase 08/29/2017 A 08/01/2018 667B1510 Administrative Closeout 08/29/2017 A 08/01/2018 120B1520 Project Closed 08/01/2018 0

100249-2 B100249-2 Basin 0613 Infiltration/Inflow Study and Repairs 06/26/2015 A 03/03/2016 A 43InfiltratioInfiltration/Inflow 06/26/2015 A 03/02/2016 A 30

B1000 Infiltration/Inflow Phase 06/26/2015 A 03/02/2016 A 30Dig & ReDig & Replace Repairs 06/26/2015 A 03/02/2016 A 30

B1160 Dig & Replace Phase 06/26/2015 A 03/02/2016 A 30B1180 Issue NTP for Dig & Replace Repairs 06/26/2015 A 0B1190 Conduct Dig & Replace Repairs 03/02/2016 A 03/02/2016 A 30

Project CProject Closeout 03/03/2016 A 03/03/2016 A 0B1250 Closeout Phase 03/03/2016 A 03/03/2016 A 0B1280 Project Closed 03/03/2016 A 0

Basin 0614Basin 0614 09/25/2014 A 08/01/2018 1455

100114 Pu100114 Pump Station 0614 Upgrade 10/07/2014 A 08/01/2018 1455DesignDesign 10/07/2014 A 06/08/2016 A 1028

B1000 Design Phase 10/07/2014 A 06/08/2016 A 1028B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 10/07/2014 A 10/08/2014 A 5B1020 Engage Design Consultant 10/09/2014 A 01/22/2015 A 20B1030 Issue Design NTP 01/23/2015 A 0B1040 A/E Develops and Submits Final Engineering Report 01/23/2015 A 05/10/2016 A 20B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 01/23/2015 A 06/05/2015 A 10

30% Des30% Design 01/23/2015 A 03/26/2015 A 58B1060 A/E Prepares 30% Construction Documents 01/23/2015 A 02/20/2015 A 30B1070 Geotechnical Engineering Services 01/23/2015 A 02/06/2015 A 20B1080 Surveying Services 01/23/2015 A 02/06/2015 A 15B1100 30% CDs Submittal 02/20/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 02/23/2015 A 03/26/2015 A 10

90% Des90% Design 02/23/2015 A 05/10/2016 A 418B1170 A/E Prepares 90% Construction Documents 02/23/2015 A 04/08/2015 A 20B1180 90% CDs Submittal 04/08/2015 A 0B1190 90% Review (MDWASD/PSIP Team) 04/09/2015 A 10/16/2015 A 15B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 10/19/2015 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 10/20/2015 A 03/18/2016 A 15B1220 90% RER (Building Department) Permit Submittal 01/07/2016 A 0B1230 90% RER (Building Department) Permit Review 01/08/2016 A 05/10/2016 A 15B1240 90% PWWMD Permit Submittal 11/02/2015 A 0B1250 90% PWWMD Permit Review 11/03/2015 A 11/04/2015 A 15B1260 90% CD PM Comments Evaluation Completed 05/10/2016 A 0

100% De100% Design 05/11/2016 A 06/08/2016 A 26B1270 A/E Prepares 100% Construction Documents 05/11/2016 A 06/08/2016 A 10B1280 100% CDs Submittal 06/08/2016 A 0B1290 100% Review (MDWASD/PSIP Team) 05/11/2016 A 06/08/2016 A 10B1300 Design Completed 06/08/2016 A 0

MDWASDMDWASD Procurement 01/08/2016 A 07/07/2016 A 180B1305 Procurement Phase 01/08/2016 A 07/07/2016 A 180B1310 Submit CDs to MDWASD Procurement Division 01/08/2016 A 0B1312 Bid Notice Preparation Period 01/08/2016 A 01/08/2016 A 23

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

08/01/2018, Project CloseoutCloseout Phase

Administrative CloseoutProject Closed

03/03/2016 A, 100249-2 Basin 0613 Infiltration/Inflow Study and Repairs03/02/2016 A, Infiltration/Inflow

Infiltration/Inflow Phase03/02/2016 A, Dig & Replace Repairs

Dig & Replace PhaseIssue NTP for Dig & Replace Repairs

Conduct Dig & Replace Repairs03/03/2016 A, Project Closeout

Closeout PhaseProject Closed

08/01/2018, Basin 0614

08/01/2018, 100114 Pump Station 0614 Upgrade06/08/2016 A, Design

Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book

Engage Design ConsultantIssue Design NTP

A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

03/26/2015 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal

30% Review (MDWASD/PSIP Team)05/10/2016 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)

90% RER(DERM)FDEP Permit Review (Pump Station)90% RER (Building Department) Permit Submittal

90% RER (Building Department) Permit Review90% PWWMD Permit Submittal

90% PWWMD Permit Review90% CD PM Comments Evaluation Completed06/08/2016 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal

100% Review (MDWASD/PSIP Team)Design Completed07/07/2016 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation Period

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 106 of 161 TASK filter: All Activities© Oracle Corporation

Page 107: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1314 Bid Notice 01/08/2016 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 01/11/2016 A 02/10/2016 A 10B1320 Pre-Bid Conference 02/11/2016 A 02/11/2016 A 1B1322 Bidders Prepare Bids for Submittal 02/12/2016 A 03/09/2016 A 15B1330 Bids Submittal 03/10/2016 A 0B1340 MDWASD/PSIP Team Bids Evaluation 03/11/2016 A 05/23/2016 A 15B1350 Recommendation for Award Letter 05/23/2016 A 0B1355 Contract Award (Purchase Order Approval) 05/24/2016 A 07/07/2016 A 10

ConstrucConstruction 02/11/2016 A 09/21/2017 A 935B1360 Construction Phase 02/11/2016 A 09/21/2017 A 935B1364 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 05/24/2016 A 06/07/2016 A 15B1366 Pre-Construction Meeting 06/08/2016 A 06/08/2016 A 1B1369 WASD Issues NTP (PO to NTP) 07/08/2016 A 08/28/2016 A 53B1370 Construction NTP 08/29/2016 A 0B1400 Construction Operations 08/29/2016 A 05/20/2017 A 107B1400 Original Construction Duration 08/29/2016 A 01/26/2017 A 107B1400 Change Order #? - Unidentifiable Time Extension 01/27/2017 A 05/16/2017 A 107B1400 Change Order #1 - PW Permit & FPL 05/17/2017 A 09/21/2017 A 107B1402 Substantial Completion 05/20/2017 A 0

DesignerDesigner Construction Support Services 02/11/2016 A 06/30/2017 A 189B1410 Designer Construction Support Services 02/11/2016 A 06/30/2017 A 189

ConstrucConstruction Close Out 05/10/2017 A 06/30/2017 A 10B1420 Commissioning 05/10/2017 A 05/13/2017 A 5B1430 Punch List 05/22/2017 A 06/30/2017 A 10

Project CProject Closeout 05/22/2017 A 08/01/2018 395B1445 Closeout Phase 05/22/2017 A 08/01/2018 395B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 05/22/2017 A 08/01/2018 120B1490 Project Closed 08/01/2018 0

100205-2 B100205-2 Basin 0614 Infiltration/Inflow Study and Repairs 09/25/2014 A 07/15/2015 A 352InfiltratioInfiltration/Inflow 09/25/2014 A 07/14/2015 A 112

B1000 Infiltration/Inflow Phase 09/25/2014 A 07/14/2015 A 112Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 07/14/2015 A 112

B1005 SSES Phase 09/25/2014 A 07/14/2015 A 112B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 06/17/2015 A 06/19/2015 A 30B1040 Video Review 06/17/2015 A 07/14/2015 A 30

Project CProject Closeout 07/15/2015 A 07/15/2015 A 0B1235 Closeout Phase 07/15/2015 A 07/15/2015 A 0B1260 Project Closed 07/15/2015 A 0

Basin 0638Basin 0638 11/20/2015 A 12/20/2019 1390

100115 Pu100115 Pump Station 0638 Upgrade 07/17/2017 A 12/20/2019 810DesignDesign 07/17/2017 A 09/19/2018 353

B1000 Design Phase 07/17/2017 A 09/19/2018 353B1010 Prepare and Submit Design Package 07/17/2017 A 07/17/2017 A 7B1020 Engage Design Consultant 07/18/2017 A 10/09/2017 A 28B1022 TA Preparation 10/10/2017 A 10/10/2017 A 14B1024 TA Approval Process 10/11/2017 A 01/16/2018 A 40

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Bid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)

09/21/2017 A, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

WASD Issues NTP (PO to NTP)

Construction NTPConstruction Operations

Original Construction DurationChange Order #? - Unidentifiable Time Extension

Change Order #1 - PW Permit & FPL

Substantial Completion06/30/2017 A, Designer Construction Support Services

Designer Construction Support Services06/30/2017 A, Construction Close Out

CommissioningPunch List

08/01/2018, Project Closeout

Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction ContractAdministrative CloseoutProject Closed

07/15/2015 A, 100205-2 Basin 0614 Infiltration/Inflow Study and Repairs07/14/2015 A, Infiltration/Inflow

Infiltration/Inflow Phase07/14/2015 A, Sanitary Sewer Evaluation SurveySSES Phase

Issue NTP to SSES ContractorConduct SSESVideo Review

07/15/2015 A, Project CloseoutCloseout Phase

Project Closed12/20/2019, Basin 06

12/20/2019, 100115 09/19/2018, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval Process

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 107 of 161 TASK filter: All Activities© Oracle Corporation

Page 108: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1030 Issue Design NTP 01/16/2018 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 01/16/2018 A 08/22/2018 186

30% Des30% Design 10/11/2017 A 02/16/2018 A 95B1060 A/E Prepares 30% Construction Documents 10/11/2017 A 01/05/2018 A 50B1100 30% CDs Submittal 01/05/2018 A 0B1120 30% Review (MDWASD/PSIP Team) 01/06/2018 A 02/16/2018 A 30

90% Des90% Design 02/17/2018 A 08/22/2018 168B1170 A/E Prepares 90% Construction Documents 02/17/2018 A 03/30/2018 A 40B1180 90% CDs Submittal 03/30/2018 A 0B1190 90% Review (MDWASD/PSIP Team) 03/31/2018 A 05/31/2018 A 30B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 06/04/2018 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 06/04/2018 A 08/01/2018 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 08/02/2018 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 08/02/2018 08/22/2018 21B1260 90% CD PM Comments Evaluation Completed 08/22/2018 0

100% De100% Design 08/23/2018 09/19/2018 28B1270 A/E Prepares 100% Construction Documents 08/23/2018 09/05/2018 14B1280 100% CDs Submittal 09/05/2018 0B1290 100% Review (MDWASD/PSIP Team) 09/06/2018 09/19/2018 14B1300 Design Completed 09/19/2018 0

MDWASDMDWASD Procurement 09/19/2018 01/01/2019 104B1305 Procurement Phase 09/19/2018 01/01/2019 104B1310 Submit CDs to MDWASD Procurement Division 09/19/2018 0B1312 Bid Notice Preparation Period 09/20/2018 10/22/2018 33B1314 Bid Notice 10/22/2018 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 10/23/2018 11/05/2018 14B1320 Pre-Bid Conference 11/06/2018 11/06/2018 1B1322 Bidders Prepare Bids for Submittal 11/07/2018 11/27/2018 21B1330 Bids Submittal 11/27/2018 0B1340 MDWASD/PSIP Team Bids Evaluation 11/28/2018 12/18/2018 21B1350 Recommendation for Award Letter 12/18/2018 0B1355 Contract Award (Purchase Order Approval) 12/19/2018 01/01/2019 14

ConstrucConstruction 11/06/2018 08/22/2019 290B1360 Construction Phase 11/06/2018 08/22/2019 290B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 12/19/2018 01/08/2019 21B1364 Pre-Construction Meeting 01/09/2019 01/09/2019 1B1366 WASD Issues NTP (Pre-Const to NTP) 01/10/2019 02/23/2019 45B1369 WASD Issues NTP (PO to NTP) 01/02/2019 02/23/2019 53B1370 Construction NTP 02/24/2019 0B1400 Construction Operations 02/24/2019 08/22/2019 180B1402 Substantial Completion 08/22/2019 0

DesignerDesigner Construction Support Services 11/06/2018 08/22/2019 290B1410 Designer Construction Support Services 11/06/2018 08/22/2019 290

Project CProject Closeout 08/01/2018 12/20/2019 507B1445 Closeout Phase 08/01/2018 12/20/2019 507B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 08/22/2019 0B1480 Administrative Closeout 08/23/2019 12/20/2019 120B1490 Project Closed 12/20/2019 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Issue Design NTPFinal Engineering Report Review & Approval (MDWASD/PSIP

02/16/2018 A, 30% Design

A/E Prepares 30% Construction Documents30% CDs Submittal

30% Review (MDWASD/PSIP Team)08/22/2018, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)

90% RER(DERM)FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)

90% RER(Building Dept) Permit Review (Pump Station)90% CD PM Comments Evaluation Completed

09/19/2018, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed

01/01/2019, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)

08/22/2019, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-ConstructioPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Construction NTPConstruction OperationsSubstantial Completion08/22/2019, Designer Construc

Designer Construction Support 12/20/2019, Project C

Closeout PhaseIssue SAC Letter

Final Release of Retainage - CAdministrative CloseoProject Closed

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 108 of 161 TASK filter: All Activities© Oracle Corporation

Page 109: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

100206-2 B100206-2 Basin 0638 Infiltration/Inflow Study and Repairs 11/20/2015 A 03/08/2016 A 92InfiltratioInfiltration/Inflow 11/20/2015 A 03/07/2016 A 43

B1000 Infiltration/Inflow Phase 11/20/2015 A 03/07/2016 A 43Dig & ReDig & Replace Repairs 11/20/2015 A 03/07/2016 A 43

B1165 Dig & Replace Phase 11/20/2015 A 03/07/2016 A 43B1180 Issue NTP for Dig & Replace Repairs 11/20/2015 A 0B1190 Conduct Dig & Replace Repairs 03/04/2016 A 03/07/2016 A 30

Project CProject Closeout 03/08/2016 A 03/08/2016 A 0B1235 Closeout Phase 03/08/2016 A 03/08/2016 A 0B1260 Project Closed 03/08/2016 A 0

Basin 0645Basin 0645 09/18/2012 A 08/01/2018 1987

100117 Pu100117 Pump Station 0645 Upgrade 09/18/2012 A 08/01/2018 1987DesignDesign 09/18/2012 A 02/25/2018 A 1987

B1000 Design Phase 09/18/2012 A 02/25/2018 A 1987B1005 Remedial Action Plan to SAC Letter Issuance 09/18/2012 A 02/25/2018 A 1987

Project CProject Closeout 02/26/2018 A 08/01/2018 667B1445 Closeout Phase 02/26/2018 A 08/01/2018 667B1450 Issue SAC Letter 02/26/2018 A 0B1480 Administrative Closeout 02/26/2018 A 08/01/2018 120B1490 Project Closed 08/01/2018 0

Basin 0648Basin 0648 09/25/2014 A 08/01/2018 1836

100118 Ba100118 Basin 0648 Infiltration/Inflow Study and Repairs 09/25/2014 A 06/18/2015 A 563InfiltratioInfiltration/Inflow 09/25/2014 A 06/17/2015 A 241

B1000 Infiltration/Inflow Phase 09/25/2014 A 06/17/2015 A 241Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 06/17/2015 A 241

B1005 SSES Phase 09/25/2014 A 06/17/2015 A 241B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 05/26/2015 A 06/03/2015 A 30B1040 Video Review 06/04/2015 A 06/17/2015 A 30

Project CProject Closeout 06/18/2015 A 06/18/2015 A 0B1235 Closeout Phase 06/18/2015 A 06/18/2015 A 0B1260 Project Closed 06/18/2015 A 0

100119 Pu100119 Pump Station 0648 Upgrade 06/27/2016 A 08/01/2018 1196DesignDesign 06/27/2016 A 11/17/2017 A 240

B1000 Design Phase 06/27/2016 A 11/17/2017 A 240B1010 Prepare and Submit Design Package 06/27/2016 A 08/17/2016 A 5B1020 Engage Design Consultant 08/18/2016 A 11/10/2016 A 20B1021 SAC Determination Period 11/11/2016 A 11/17/2017 A 166

Project CProject Closeout 11/17/2017 A 08/01/2018 739B1445 Closeout Phase 11/17/2017 A 08/01/2018 739B1450 Issue SAC Letter 11/17/2017 A 0B1480 Administrative Closeout 11/18/2017 A 08/01/2018 120B1490 Project Closed 08/01/2018 0

Basin 0669Basin 0669 11/20/2015 A 09/27/2020 1694

100120 Ba100120 Basin 0669 Infiltration/Inflow Study and Repairs 11/20/2015 A 06/14/2016 A 144InfiltratioInfiltration/Inflow 11/20/2015 A 06/13/2016 A 144

B1000 Infiltration/Inflow Phase 11/20/2015 A 06/13/2016 A 144CIPP RepCIPP Repairs 01/15/2016 A 05/04/2016 A 113

B1065 CIPP Phase 01/15/2016 A 05/04/2016 A 113

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

03/08/2016 A, 100206-2 Basin 0638 Infiltration/Inflow Study and Repairs03/07/2016 A, Infiltration/Inflow

Infiltration/Inflow Phase03/07/2016 A, Dig & Replace RepairsDig & Replace Phase

Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs03/08/2016 A, Project CloseoutCloseout Phase

Project Closed08/01/2018, Basin 0645

08/01/2018, 100117 Pump Station 0645 Upgrade02/25/2018 A, Design

Design PhaseRemedial Action Plan to SAC Letter Issuance

08/01/2018, Project CloseoutCloseout Phase

Issue SAC LetterAdministrative CloseoutProject Closed08/01/2018, Basin 0648

06/18/2015 A, 100118 Basin 0648 Infiltration/Inflow Study and Repairs06/17/2015 A, Infiltration/Inflow

Infiltration/Inflow Phase06/17/2015 A, Sanitary Sewer Evaluation SurveySSES Phase

Issue NTP to SSES ContractorConduct SSESVideo Review06/18/2015 A, Project CloseoutCloseout Phase

Project Closed08/01/2018, 100119 Pump Station 0648 Upgrade

11/17/2017 A, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantSAC Determination Period

08/01/2018, Project Closeout

Closeout PhaseIssue SAC Letter

Administrative CloseoutProject Closed

06/14/2016 A, 100120 Basin 0669 Infiltration/Inflow Study and Repairs06/13/2016 A, Infiltration/Inflow

Infiltration/Inflow Phase05/04/2016 A, CIPP RepairsCIPP Phase

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 109 of 161 TASK filter: All Activities© Oracle Corporation

Page 110: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1080 Issue NTP for CIPP Repairs 01/15/2016 A 0B1090 Conduct CIPP Repairs 05/04/2016 A 05/04/2016 A 28

ManholeManhole Repairs 03/25/2016 A 06/13/2016 A 105B1115 Manhole Phase 03/25/2016 A 06/13/2016 A 105B1130 Issue NTP for Manhole Repairs 03/25/2016 A 0B1140 Conduct Manhole Repairs 04/18/2016 A 06/13/2016 A 20

Dig & ReDig & Replace Repairs 11/20/2015 A 04/07/2016 A 144B1165 Dig & Replace Phase 11/20/2015 A 04/07/2016 A 144B1180 Issue NTP for Dig & Replace Repairs 11/20/2015 A 0B1190 Conduct Dig & Replace Repairs 03/16/2016 A 04/07/2016 A 30

Project CProject Closeout 06/14/2016 A 06/14/2016 A 0B1235 Closeout Phase 06/14/2016 A 06/14/2016 A 0B1260 Project Closed 06/14/2016 A 0

100121 Pu100121 Pump Station 0669 Upgrade * 08/01/2018 09/27/2020 789DesignDesign 08/01/2018 06/29/2019 333

B1000 Design Phase 08/01/2018 06/29/2019 333B1010 Prepare and Submit Design Package 08/01/2018 08/07/2018 7B1020 Engage Design Consultant 08/08/2018 09/04/2018 28B1022 TA Preparation 09/05/2018 09/18/2018 14B1024 TA Approval Process 09/19/2018 10/28/2018 40B1030 Issue Design NTP 10/29/2018 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/29/2018 06/01/2019 216

30% Des30% Design 10/29/2018 01/16/2019 80B1060 A/E Prepares 30% Construction Documents 10/29/2018 12/17/2018 50B1100 30% CDs Submittal 12/17/2018 0B1120 30% Review (MDWASD/PSIP Team) 12/18/2018 01/16/2019 30

60% Des60% Design 12/18/2018 01/30/2019 44B1130 A/E Prepares 60% Construction Documents 12/18/2018 01/16/2019 30B1140 60% CDs Submittal 01/16/2019 0B1160 60% Review (MDWASD/PSIP Team) 01/17/2019 01/30/2019 14

90% Des90% Design 01/17/2019 06/01/2019 136B1170 A/E Prepares 90% Construction Documents 01/17/2019 02/25/2019 40B1180 90% CDs Submittal 02/25/2019 0B1190 90% Review (MDWASD/PSIP Team) 02/26/2019 03/27/2019 30B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 03/28/2019 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 03/28/2019 05/11/2019 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 05/12/2019 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 05/12/2019 06/01/2019 21B1240 90% Municipality Permit Submittal (Pump Station) 05/12/2019 0B1250 90% Municipality Permit Review (Pump Station) 05/12/2019 06/01/2019 21B1260 90% CD PM Comments Evaluation Completed 06/01/2019 0

100% De100% Design 06/02/2019 06/29/2019 28B1270 A/E Prepares 100% Construction Documents 06/02/2019 06/15/2019 14B1280 100% CDs Submittal 06/15/2019 0B1290 100% Review (MDWASD/PSIP Team) 06/16/2019 06/29/2019 14B1300 Design Completed 06/29/2019 0

MDWASDMDWASD Procurement 06/29/2019 10/10/2019 104B1305 Procurement Phase 06/29/2019 10/10/2019 104B1310 Submit CDs to MDWASD Procurement Division 06/29/2019 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Issue NTP for CIPP RepairsConduct CIPP Repairs

06/13/2016 A, Manhole RepairsManhole Phase

Issue NTP for Manhole RepairsConduct Manhole Repairs

04/07/2016 A, Dig & Replace RepairsDig & Replace Phase

Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs

06/14/2016 A, Project CloseoutCloseout Phase

Project Closed

06/29/2019, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval Process

Issue Design NTPFinal Engineering Report Review & Ap

01/16/2019, 30% Design

A/E Prepares 30% Construction Documents30% CDs Submittal

30% Review (MDWASD/PSIP Team)01/30/2019, 60% Design

A/E Prepares 60% Construction Documents60% CDs Submittal60% Review (MDWASD/PSIP Team)

06/01/2019, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (P

90% RER(DERM)FDEP Permit Review (90% RER(Building Dept) Permit Submit

90% RER(Building Dept) Permit Revie90% Municipality Permit Submittal (Pum

90% Municipality Permit Review (Pum90% CD PM Comments Evaluation C

06/29/2019, 100% Design

A/E Prepares 100% Construction Do100% CDs Submittal100% Review (MDWASD/PSIP TeamDesign Completed

10/10/2019, MDWASD ProProcurement Phase

Submit CDs to MDWASD Procurem

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 110 of 161 TASK filter: All Activities© Oracle Corporation

Page 111: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1312 Bid Notice Preparation period 06/29/2019 07/31/2019 33B1314 Bid Notice 07/31/2019 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 08/01/2019 08/14/2019 14B1320 Pre-Bid Conference 08/15/2019 08/15/2019 1B1322 Bidders Prepare Bids for Submittal 08/16/2019 09/05/2019 21B1330 Bids Submittal 09/05/2019 0B1340 MDWASD/PSIP Team Bids Evaluation 09/06/2019 09/26/2019 21B1350 Recommendation for Award Letter 09/26/2019 0B1355 Contract Award (Purchase Order Approval) 09/27/2019 10/10/2019 14

ConstrucConstruction 08/15/2019 05/30/2020 290B1360 Construction Phase 08/15/2019 05/30/2020 290B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 09/27/2019 10/17/2019 21B1364 Pre-Construction Meeting 10/18/2019 10/18/2019 1B1366 WASD Issues NTP (Pre-Const to NTP) 10/19/2019 12/02/2019 45B1369 WASD Issues NTP (PO to NTP) 10/11/2019 12/02/2019 53B1370 Construction NTP 12/03/2019 0B1400 Construction Operations 12/03/2019 05/30/2020 180B1402 Substantial Completion 05/30/2020 0

DesignerDesigner Construction Support Services 08/15/2019 05/30/2020 290B1410 Designer Construction Support Services 08/15/2019 05/30/2020 290

Project CProject Closeout 08/01/2018 09/27/2020 789B1445 Closeout Phase 08/01/2018 09/27/2020 789B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 05/30/2020 0B1480 Administrative Closeout 05/31/2020 09/27/2020 120B1490 Project Closed 09/27/2020 0

Basin 0672Basin 0672 12/07/2015 A 02/22/2019 1177

100122 Pu100122 Pump Station 0672 Upgrade 12/07/2015 A 02/22/2019 1177DesignDesign 12/07/2015 A 07/14/2017 A 620

B1000 Design Phase 12/07/2015 A 07/14/2017 A 620B1010 Prepare and Submit Design Package 12/07/2015 A 12/07/2015 A 5B1020 Engage Design Consultant 12/07/2015 A 01/12/2016 A 20B1022 TA Preparation 01/13/2016 A 01/13/2016 A 1B1024 TA Approval Process 01/14/2016 A 04/04/2016 A 20B1030 Issue Design NTP 04/14/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 04/14/2016 A 09/29/2016 A 85

30% Des30% Design 04/14/2016 A 05/18/2016 A 52B1060 A/E Prepares 30% Construction Documents 04/14/2016 A 04/27/2016 A 30B1070 Geotechnical Engineering Services 04/14/2016 A 04/27/2016 A 20B1080 Surveying Services 04/14/2016 A 04/27/2016 A 15B1100 30% CDs Submittal 04/27/2016 A 0B1120 30% Review (MDWASD/PSIP Team) 04/28/2016 A 05/18/2016 A 10

90% Des90% Design 04/28/2016 A 05/30/2017 A 417B1170 A/E Prepares 90% Construction Documents 04/28/2016 A 08/17/2016 A 20B1180 90% CDs Submittal 08/17/2016 A 0B1190 90% Review (MDWASD/PSIP Team) 08/18/2016 A 09/29/2016 A 15B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 12/06/2016 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 12/06/2016 A 04/04/2017 A 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 04/18/2017 A 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Bid Notice Preparation period

Bid NoticeMDWASD/PSIP Team Prepare

Pre-Bid ConferenceBidders Prepare Bids for Subm

Bids SubmittalMDWASD/PSIP Team Bids ERecommendation for Award Contract Award (Purchase O

05/30/20

ConstrucMDWASD/PSIP Team PrePre-Construction Meeting

WASD Issues NTP (PreWASD Issues NTP (PO

Construction NTPConstrucSubstan05/30/20

Designe

Issue SAC LetterFinal Re

02/22/2019, Basin 0672

02/22/2019, 100122 Pump Station 0672 Upg07/14/2017 A, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval ProcessIssue Design NTP

Final Engineering Report Review & Approval (MDWASD/PSIP Team)05/18/2016 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services

30% CDs Submittal30% Review (MDWASD/PSIP Team)

05/30/2017 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)

90% RER(DERM)FDEP Permit Submittal (Pump Station)90% RER(DERM)FDEP Permit Review (Pump Station)

90% RER(Building Dept) Permit Submittal (Pump Station)

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 111 of 161 TASK filter: All Activities© Oracle Corporation

Page 112: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1230 90% RER(Building Dept) Permit Review (Pump Station) 04/18/2017 A 05/12/2017 A 21B1240 90% PWWMD Permit Submittal (Pump Station) 05/22/2017 A 0B1250 90% PWWMD Permit Review (Pump Station) 05/22/2017 A 05/30/2017 A 21B1260 90% CD PM Comments Evaluation Completed 05/30/2017 A 0B1262 MDWASD Union Concurrence Process 02/27/2017 A 04/07/2017 A 30

100% De100% Design 05/31/2017 A 07/14/2017 A 75B1270 A/E Prepares 100% Construction Documents 05/31/2017 A 07/14/2017 A 10B1280 100% CDs Submittal 07/14/2017 A 0B1290 100% Review (MDWASD/PSIP Team) 07/14/2017 A 07/14/2017 A 10B1300 Design Completed 07/14/2017 A 0

MDWASDMDWASD Procurement 07/14/2017 A 01/02/2018 A 101B1305 Procurement Phase 07/14/2017 A 01/02/2018 A 101B1310 Submit CDs to MDWASD Procurement Division 07/14/2017 A 0B1312 Bid Notice Preparation Period 07/17/2017 A 08/10/2017 A 33B1314 Bid Notice 08/10/2017 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 08/11/2017 A 08/21/2017 A 14B1320 Pre-Bid Conference 08/22/2017 A 08/22/2017 A 1B1328 Bidders Prepare Bids for Submittal 09/25/2017 A 10/19/2017 A 21B1330 Bids Submittal 10/19/2017 A 0B1340 MDWASD/PSIP Team Bids Evaluation 10/20/2017 A 11/17/2017 A 21B1350 Recommendation for Award letter 11/17/2017 A 0B1355 Contract Award (Purchase Order Approval) 11/18/2017 A 01/02/2018 A 14

ConstrucConstruction 08/22/2017 A 10/25/2018 507B1360 Construction Phase 08/22/2017 A 10/25/2018 507B1364 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 11/18/2017 A 01/21/2018 A 21B1366 Pre-Construction Meeting 01/22/2018 A 01/22/2018 A 1B1368 WASD Issues NTP (Pre-Const to NTP) 01/23/2018 A 05/27/2018 A 45B1369 WASD Issues NTP (PO to NTP) 01/03/2018 A 05/27/2018 A 53B1370 Construction NTP 05/28/2018 A 0B1400 Construction Operations 05/28/2018 A 10/25/2018 151B1402 Substantial Completion 10/25/2018 0

DesignerDesigner Construction Support Services 08/22/2017 A 10/25/2018 246B1410 Designer Construction Support Services 08/22/2017 A 10/25/2018 246

Project CProject Closeout 08/01/2018 02/22/2019 206B1445 Closeout Phase 08/01/2018 02/22/2019 206B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 10/25/2018 0B1480 Administrative Closeout 10/26/2018 02/22/2019 120B1490 Project Closed 02/22/2019 0

Basin 0675Basin 0675 09/25/2014 A 11/01/2019 1646

100123 Pu100123 Pump Station 0675 Upgrade 01/14/2016 A 11/01/2019 1369DesignDesign 01/14/2016 A 08/01/2018 912

B1000 Design Phase 01/14/2016 A 08/01/2018 912B1010 Prepare and Submit Design Package 01/14/2016 A 01/14/2016 A 5B1020 Engage Design Consultant 01/14/2016 A 04/01/2016 A 20B1022 TA Preparation 04/04/2016 A 04/15/2016 A 1B1024 TA Approval Process 04/18/2016 A 01/10/2017 A 40B1030 Issue Design NTP 01/13/2017 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 01/13/2017 A 01/26/2018 A 65

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

90% RER(Building Dept) Permit Review (Pump Station)90% PWWMD Permit Submittal (Pump Station)

90% PWWMD Permit Review (Pump Station)90% CD PM Comments Evaluation Completed

MDWASD Union Concurrence Process07/14/2017 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal

100% Review (MDWASD/PSIP Team)Design Completed

01/02/2018 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award letter

Contract Award (Purchase Order Approval)10/25/2018, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Construction NTPConstruction OperationsSubstantial Completion10/25/2018, Designer Construction Support Services

Designer Construction Support Services02/22/2019, Project Closeout

Closeout PhaseIssue SAC Letter

Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed

11/01/2019, Basin 0675

11/01/2019, 100123 Pum08/01/2018, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval ProcessIssue Design NTP

Final Engineering Report Review & Approval (MDWASD/PSIP Team)

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 112 of 161 TASK filter: All Activities© Oracle Corporation

Page 113: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

30% Des30% Design 01/13/2017 A 06/07/2017 A 151B1060 A/E Prepares 30% Construction Documents 01/13/2017 A 05/04/2017 A 50B1100 30% CDs Submittal 05/04/2017 A 0B1120 30% Review (MDWASD/PSIP Team) 05/05/2017 A 05/05/2017 A 30B1122 Project On-Hold Until Property Limits/Easments Have Been Esta 05/05/2017 A 06/07/2017 A 30

90% Des90% Design 06/08/2017 A 01/26/2018 A 200B1170 A/E Prepares 90% Construction Documents 06/08/2017 A 07/05/2017 A 40B1180 90% CDs Submittal 07/05/2017 A 0B1190 90% Review (MDWASD/PSIP Team) 07/06/2017 A 07/26/2017 A 30B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 08/29/2017 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 08/29/2017 A 11/29/2017 A 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 11/30/2017 A 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 11/30/2017 A 01/26/2018 A 21B1260 90% CD PM Comments Evaluation Completed 01/26/2018 A 0B1262 MDWASD Union Concurrence Process 07/06/2017 A 07/31/2017 A 30

100% De100% Design 01/29/2018 A 08/01/2018 212B1270 A/E Prepares 100% Construction Documents 01/29/2018 A 02/22/2018 A 14B1280 100% CDs Submittal 02/22/2018 A 0B1282 TA Rev 2 Preparation 02/23/2018 A 05/08/2018 A 14B1284 TA Rev 2 Approval Process 05/09/2018 A 06/20/2018 A 40B1290 100% Review (MDWASD/PSIP Team) 06/21/2018 A 08/01/2018 14B1300 Design Completed 08/01/2018 0

MDWASDMDWASD Procurement 08/01/2018 11/13/2018 104B1305 Procurement Phase 08/01/2018 11/13/2018 104B1310 Submit CDs to MDWASD Procurement Division 08/01/2018 0B1312 Bid Notice Preparation Period 08/02/2018 09/03/2018 33B1314 Bid Notice 09/03/2018 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 09/04/2018 09/17/2018 14B1320 Pre-Bid Conference 09/18/2018 09/18/2018 1B1322 Bidders Prepare Bids for Submittal 09/19/2018 10/09/2018 21B1330 Bids Submittal 10/09/2018 0B1340 MDWASD/PSIP Team Bids Evaluation 10/10/2018 10/30/2018 21B1350 Recommendation for Award Letter 10/30/2018 0B1355 Contract Award (Purchase Order Approval) 10/31/2018 11/13/2018 14

ConstrucConstruction 09/18/2018 07/05/2019 290B1360 Construction Phase 09/18/2018 07/05/2019 290B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 10/31/2018 11/20/2018 21B1364 Pre-Construction Meeting 11/21/2018 11/21/2018 1B1366 WASD Issues NTP (Pre-Const to NTP) 11/22/2018 01/05/2019 45B1369 WASD Issues NTP (PO to NTP) 11/14/2018 01/05/2019 53B1370 Construction NTP 01/06/2019 0B1400 Construction Operations 01/06/2019 07/04/2019 180B1402 Substantial Completion 07/04/2019 0

DesignerDesigner Construction Support Services 09/18/2018 07/04/2019 290B1410 Designer Construction Support Services 09/18/2018 07/04/2019 290

Project CProject Closeout 08/01/2018 11/01/2019 458B1445 Closeout Phase 08/01/2018 11/01/2019 458B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 07/04/2019 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

06/07/2017 A, 30% Design

A/E Prepares 30% Construction Documents30% CDs Submittal

30% Review (MDWASD/PSIP Team)Project On-Hold Until Property Limits/Easments Have Been Established

01/26/2018 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)

90% RER(DERM)FDEP Permit Submittal (Pump Station)90% RER(DERM)FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)

90% RER(Building Dept) Permit Review (Pump Station)90% CD PM Comments Evaluation Completed

MDWASD Union Concurrence Process08/01/2018, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal

TA Rev 2 PreparationTA Rev 2 Approval Process

100% Review (MDWASD/PSIP Team)Design Completed

11/13/2018, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)

07/05/2019, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Construction NTPConstruction OperationsSubstantial Completion07/04/2019, Designer Construction

Designer Construction Support Ser11/01/2019, Project Close

Closeout PhaseIssue SAC Letter

Final Release of Retainage - Const

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 113 of 161 TASK filter: All Activities© Oracle Corporation

Page 114: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1480 Administrative Closeout 07/05/2019 11/01/2019 120B1490 Project Closed 11/01/2019 0

100193 Ba100193 Basin 0675 Infiltration/Inflow Study and Repairs 09/25/2014 A 05/27/2015 A 397InfiltratioInfiltration/Inflow 09/25/2014 A 05/26/2015 A 38

B1000 Infiltration/Inflow Phase 09/25/2014 A 05/26/2015 A 38Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 05/26/2015 A 38

B1005 SSES Phase 09/25/2014 A 05/26/2015 A 38B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 04/10/2015 A 04/30/2015 A 30B1040 Video Review 05/12/2015 A 05/26/2015 A 30

Project CProject Closeout 05/27/2015 A 05/27/2015 A 0B1235 Closeout Phase 05/27/2015 A 05/27/2015 A 0B1260 Project Closed 05/27/2015 A 0

Basin 0688Basin 0688 11/10/2014 A 08/01/2018 1444

100125 Pu100125 Pump Station 0688 Upgrade 11/10/2014 A 08/01/2018 1444DesignDesign 11/10/2014 A 04/25/2016 A 529

B1000 Design Phase 11/10/2014 A 04/25/2016 A 529B1010 Prepare and Submit Design Package 11/10/2014 A 11/24/2014 A 5B1020 Engage Design Consultant 11/25/2014 A 03/23/2015 A 20B1022 TA Approval Process 03/24/2015 A 04/30/2015 A 20B1030 Issue Design NTP 05/07/2015 A 0B1040 A/E Develops and Submits Final Engineering Report 05/07/2015 A 03/30/2016 A 125B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 05/07/2015 A 11/18/2015 A 10

30% Des30% Design 05/08/2015 A 07/28/2015 A 74B1060 A/E Prepares 30% Construction Documents 05/08/2015 A 07/13/2015 A 30B1070 Geotechnical Engineering Services 05/08/2015 A 07/13/2015 A 20B1080 Surveying Services 05/08/2015 A 07/13/2015 A 15B1100 30% CDs Submittal 07/13/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 07/14/2015 A 07/28/2015 A 10

60% Des60% Design 07/14/2015 A 09/08/2015 A 84B1130 A/E Prepares 60% Construction Documents 07/14/2015 A 08/07/2015 A 20B1140 60% CDs Submittal 08/07/2015 A 0B1160 60% Review (MDWASD/PSIP Team) 08/11/2015 A 09/08/2015 A 10

90% Des90% Design 08/11/2015 A 03/30/2016 A 218B1170 A/E Prepares 90% Construction Documents 08/11/2015 A 10/23/2015 A 20B1180 90% CDs Submittal 10/23/2015 A 0B1190 90% Review (MDWASD/PSIP Team) 10/26/2015 A 11/18/2015 A 15B1200 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 01/27/2016 A 0B1210 90% RER(DERM)/FDEP Permit Review (Pump Station) 01/27/2016 A 03/25/2016 A 15B1220 90% RER (Building Dept) Permit Submittal 03/15/2016 A 0B1230 90% RER (Building Dept) Permit Review 03/15/2016 A 03/30/2016 A 15B1260 90% CD PM Comments Evaluation Completed 03/30/2016 A 0

100% De100% Design 03/30/2016 A 04/25/2016 A 74B1270 A/E Prepares 100% Construction Documents 03/30/2016 A 04/25/2016 A 10B1280 100% CDs Submittal 04/25/2016 A 0B1290 100% Review (MDWASD/PSIP Team) 03/30/2016 A 04/25/2016 A 10B1300 Design Completed 04/25/2016 A 0

MDWASDMDWASD Procurement 03/02/2016 A 05/02/2016 A 55B1305 Procurement Phase 03/02/2016 A 05/02/2016 A 55

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Administrative CloseoutProject Closed

05/27/2015 A, 100193 Basin 0675 Infiltration/Inflow Study and Repairs05/26/2015 A, Infiltration/Inflow

Infiltration/Inflow Phase05/26/2015 A, Sanitary Sewer Evaluation SurveySSES Phase

Issue NTP to SSES ContractorConduct SSESVideo Review

05/27/2015 A, Project CloseoutCloseout Phase

Project Closed08/01/2018, Basin 0688

08/01/2018, 100125 Pump Station 0688 Upgrade04/25/2016 A, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Approval Process

Issue Design NTPA/E Develops and Submits Final Engineering Report

Final Engineering Report Review & Approval (MDWASD/PSIP Team)07/28/2015 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal30% Review (MDWASD/PSIP Team)

09/08/2015 A, 60% Design

A/E Prepares 60% Construction Documents60% CDs Submittal

60% Review (MDWASD/PSIP Team)03/30/2016 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)/FDEP Permit Submittal (Pump Station)90% RER(DERM)/FDEP Permit Review (Pump Station)

90% RER (Building Dept) Permit Submittal90% RER (Building Dept) Permit Review90% CD PM Comments Evaluation Completed

04/25/2016 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal

100% Review (MDWASD/PSIP Team)Design Completed

05/02/2016 A, MDWASD Procurement

Procurement Phase

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 114 of 161 TASK filter: All Activities© Oracle Corporation

Page 115: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1310 Submit CDs to MDWASD Procurement Division 03/02/2016 A 0B1312 Bid Notice Preparation Period 03/03/2016 A 03/07/2016 A 23B1314 Bid Notice 03/07/2016 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 03/08/2016 A 03/16/2016 A 10B1320 Pre-Bid Conference 03/17/2016 A 03/17/2016 A 1B1328 Bidders Prepare Bids for Submittal 03/21/2016 A 04/05/2016 A 15B1330 Bids Submittal 04/06/2016 A 0B1340 MDWASD/PSIP Team Bids Evaluation 04/07/2016 A 04/12/2016 A 15B1350 Recommendation for Award Letter 04/12/2016 A 0B1355 Contract Award (Purchase Order Approval) 04/13/2016 A 05/02/2016 A 10

ConstrucConstruction 03/17/2016 A 02/28/2017 A 936B1360 Construction Phase 03/17/2016 A 02/28/2017 A 936B1364 MDWASD/PSIP Team Prepare for Pre-Construction meeting 04/13/2016 A 04/22/2016 A 15B1366 Pre-Construction Meeting 04/25/2016 A 04/25/2016 A 1B1369 WASD Issues NTP (PO to NTP) 05/03/2016 A 07/19/2016 A 53B1370 Construction NTP 07/20/2016 A 0B1400 Construction Operations 07/20/2016 A 12/28/2016 A 180B1402 Substantial Completion 12/28/2016 A 0

DesignerDesigner Construction Support Services 03/17/2016 A 02/28/2017 A 249B1410 Designer Construction Support Services 03/17/2016 A 02/28/2017 A 249

ConstrucConstruction Close Out 12/29/2016 A 02/28/2017 A 10B1420 Commissioning 12/29/2016 A 01/05/2017 A 5B1430 Punch List 12/29/2016 A 02/28/2017 A 10

Project CProject Closeout 12/29/2016 A 08/01/2018 562B1445 Closeout Phase 12/29/2016 A 08/01/2018 562B1448 SAC Letter Issuance Period 12/29/2016 A 06/14/2017 A 167B1450 Issue SAC Letter 06/22/2017 A 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 12/29/2016 A 08/01/2018 120B1490 Project Closed 08/01/2018 0

100246 Ba100246 Basin 0688 Infiltration/Inflow Study and Repairs 05/22/2015 A 10/23/2015 A 376InfiltratioInfiltration/Inflow 05/22/2015 A 10/22/2015 A 154

B1000 Infiltration/Inflow Phase 05/22/2015 A 10/22/2015 A 154CIPP RepCIPP Repairs 05/22/2015 A 10/22/2015 A 154

B1070 CIPP Phase 05/22/2015 A 10/22/2015 A 154B1090 Issue NTP for CIPP Repairs 05/22/2015 A 0B1100 Conduct CIPP Repairs 10/21/2015 A 10/22/2015 A 2

Project CProject Closeout 10/23/2015 A 10/23/2015 A 0B1250 Closeout Phase 10/23/2015 A 10/23/2015 A 0B1280 Project Closed 10/23/2015 A 0

Basin 0698Basin 0698 09/25/2014 A 05/19/2019 1620

100126 Ba100126 Basin 0698 Infiltration/Inflow Study and Repairs 09/25/2014 A 06/02/2016 A 567InfiltratioInfiltration/Inflow 09/25/2014 A 06/01/2016 A 439

B1000 Infiltration/Inflow Phase 09/25/2014 A 06/01/2016 A 439Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 10/23/2015 A 235

B1005 SSES Phase 09/25/2014 A 10/23/2015 A 235B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 12/15/2014 A 10/23/2015 A 30

CIPP RepCIPP Repairs 01/15/2016 A 06/01/2016 A 20

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Submit CDs to MDWASD Procurement DivisionBid Notice Preparation Period

Bid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter

Contract Award (Purchase Order Approval)02/28/2017 A, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction meetingPre-Construction Meeting

WASD Issues NTP (PO to NTP)

Construction NTPConstruction Operations

Substantial Completion02/28/2017 A, Designer Construction Support Services

Designer Construction Support Services02/28/2017 A, Construction Close Out

CommissioningPunch List

08/01/2018, Project Closeout

Closeout PhaseSAC Letter Issuance Period

Issue SAC LetterFinal Release of Retainage - Construction ContractAdministrative CloseoutProject Closed

10/23/2015 A, 100246 Basin 0688 Infiltration/Inflow Study and Repairs10/22/2015 A, Infiltration/Inflow

Infiltration/Inflow Phase10/22/2015 A, CIPP Repairs

CIPP PhaseIssue NTP for CIPP Repairs

Conduct CIPP Repairs10/23/2015 A, Project Closeout

Closeout PhaseProject Closed

05/19/2019, Basin 0698

06/02/2016 A, 100126 Basin 0698 Infiltration/Inflow Study and Repairs06/01/2016 A, Infiltration/Inflow

Infiltration/Inflow Phase10/23/2015 A, Sanitary Sewer Evaluation SurveySSES Phase

Issue NTP to SSES ContractorConduct SSES

06/01/2016 A, CIPP Repairs

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 115 of 161 TASK filter: All Activities© Oracle Corporation

Page 116: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1065 CIPP Phase 01/15/2016 A 06/01/2016 A 20B1080 Issue NTP for CIPP Repairs 01/15/2016 A 0B1090 Conduct CIPP Repairs 02/19/2016 A 06/01/2016 A 20

ManholeManhole Repairs 10/30/2015 A 03/24/2016 A 20B1115 Manhole Phase 10/30/2015 A 03/24/2016 A 20B1130 Issue NTP for Manhole Repairs 10/30/2015 A 0B1140 Conduct Manhole Repairs 11/16/2015 A 03/24/2016 A 20

Dig & ReDig & Replace Repairs 09/25/2015 A 02/26/2016 A 30B1165 Dig & Replace Phase 09/25/2015 A 02/26/2016 A 30B1180 Issue NTP for Dig & Replace Repairs 09/25/2015 A 0B1190 Conduct Dig & Replace Repairs 10/05/2015 A 02/26/2016 A 30

Project CProject Closeout 06/02/2016 A 06/02/2016 A 0B1235 Closeout Phase 06/02/2016 A 06/02/2016 A 0B1260 Project Closed 06/02/2016 A 0

100128 Pu100128 Pump Station 0698(AM) Upgrade 10/10/2014 A 05/19/2019 1519DesignDesign 10/10/2014 A 12/13/2017 A 1013

B1000 Design Phase 10/10/2014 A 12/13/2017 A 1013B1010 Prepare and Submit Design Package 10/10/2014 A 10/13/2014 A 5B1020 Engage Design Consultant 10/14/2014 A 03/24/2015 A 20B1030 Issue Design NTP 03/24/2015 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 03/24/2015 A 11/30/2017 A 209

30% Des30% Design 03/25/2015 A 07/13/2016 A 441B1060 A/E Prepares 30% Construction Documents 03/25/2015 A 06/08/2015 A 30B1070 Geotechnical Engineering Services 03/25/2015 A 06/08/2015 A 20B1080 Surveying Services 03/25/2015 A 06/08/2015 A 15B1100 30% CDs Submittal 06/08/2015 A 0B1102 PSIP Prepare PER to Re-Design 30% CDs 06/09/2015 A 10/14/2015 A 10B1104 Prepare Request for SOW, Fee to Re-Design 30% CDs 10/15/2015 A 12/15/2015 A 10B1106 TA Rev 1 Approval Process to Re-Design 30% CDs 12/16/2015 A 01/20/2016 A 10B1108 A/E Re-Design 30% Contract Documents 01/28/2016 A 04/28/2016 A 30B1120 30% Re-Design Review (MDWASD/PSIP Team) 04/29/2016 A 07/13/2016 A 10

60% Des60% Design 04/29/2016 A 03/23/2017 A 72B1128 TA Rev 2 Approval Process 12/19/2016 A 02/01/2017 A 40B1130 A/E Prepares 60% Construction Documents 04/29/2016 A 02/01/2017 A 30B1140 60% CDs Submittal 02/01/2017 A 0B1160 60% Review (MDWASD/PSIP Team) 02/02/2017 A 03/23/2017 A 10

90% Des90% Design 03/24/2017 A 11/30/2017 A 208B1170 A/E Prepares 90% Construction Documents 03/24/2017 A 06/27/2017 A 40B1180 90% CDs Submittal 06/27/2017 A 0B1190 90% Review (MDWASD/PSIP Team) 06/28/2017 A 08/11/2017 A 30B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 08/14/2017 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 08/14/2017 A 09/28/2017 A 45B1220 90% RER (Building Dept) Permit Submittal 10/20/2017 A 0B1230 90% RER (Building Dept) Permit Review 10/20/2017 A 11/30/2017 A 21B1260 90% CD PM Comments Evaluation Completed 11/30/2017 A 0B1262 MDWASD Union Concurrence Process 06/28/2017 A 07/17/2017 A 30

100% De100% Design 12/01/2017 A 12/13/2017 A 28B1270 A/E Prepares 100% Construction Documents 12/01/2017 A 12/13/2017 A 14B1280 100% CDs Submittal 12/13/2017 A 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

CIPP Phase

Issue NTP for CIPP RepairsConduct CIPP Repairs

03/24/2016 A, Manhole RepairsManhole Phase

Issue NTP for Manhole RepairsConduct Manhole Repairs

02/26/2016 A, Dig & Replace RepairsDig & Replace Phase

Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs

06/02/2016 A, Project CloseoutCloseout Phase

Project Closed05/19/2019, 100128 Pump Station 06

12/13/2017 A, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantIssue Design NTP

Final Engineering Report Review & Approval (MDWASD/PSIP Team)07/13/2016 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services

30% CDs SubmittalPSIP Prepare PER to Re-Design 30% CDs

Prepare Request for SOW, Fee to Re-Design 30% CDsTA Rev 1 Approval Process to Re-Design 30% CDs

A/E Re-Design 30% Contract Documents30% Re-Design Review (MDWASD/PSIP Team)

03/23/2017 A, 60% DesignTA Rev 2 Approval Process

A/E Prepares 60% Construction Documents60% CDs Submittal

60% Review (MDWASD/PSIP Team)11/30/2017 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)

90% RER(DERM)FDEP Permit Review (Pump Station)90% RER (Building Dept) Permit Submittal

90% RER (Building Dept) Permit Review90% CD PM Comments Evaluation Completed

MDWASD Union Concurrence Process12/13/2017 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 116 of 161 TASK filter: All Activities© Oracle Corporation

Page 117: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1290 100% Review (MDWASD/PSIP Team) 12/13/2017 A 12/13/2017 A 14B1300 Design Completed 12/13/2017 A 0

MDWASDMDWASD Procurement 12/13/2017 A 04/13/2018 A 88B1305 Procurement Phase 12/13/2017 A 04/13/2018 A 88B1310 Submit CDs to MDWASD Procurement Division 12/13/2017 A 0B1312 Bid Notice Preparation Period 12/14/2017 A 12/18/2017 A 33B1314 Bid Notice 12/18/2017 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 12/19/2017 A 01/11/2018 A 14B1320 Pre-Bid Conference 01/12/2018 A 01/12/2018 A 1B1328 Bidders Prepare Bids for Submittal 01/13/2018 A 02/20/2018 A 21B1330 Bids Submittal 02/20/2018 A 0B1340 MDWASD/PSIP Team Bids Evaluation 02/21/2018 A 03/12/2018 A 21B1350 Recommendation for Award Letter 03/12/2018 A 0B1355 Contract Award (Purchase Order Approval) 03/13/2018 A 04/13/2018 A 14

ConstrucConstruction 01/12/2018 A 01/19/2019 382B1360 Construction Phase 01/12/2018 A 01/19/2019 382B1364 MDWASD/PSIP Team Prepare for Pre-Construction meeting 03/13/2018 A 05/09/2018 A 21B1365 Pre-Construction Meeting 05/10/2018 A 05/10/2018 A 1B1366 WASD Issues NTP (Pre-Const to NTP) 05/11/2018 A 07/22/2018 A 45B1369 WASD Issues NTP (PO to NTP) 04/13/2018 A 07/22/2018 A 53B1370 Construction NTP 07/23/2018 A 0B1400 Construction Operations 07/23/2018 A 01/19/2019 181B1402 Substantial Completion 01/19/2019 0

DesignerDesigner Construction Support Services 01/12/2018 A 01/19/2019 290B1410 Designer Construction Support Services 01/12/2018 A 01/19/2019 290

Project CProject Closeout 07/05/2018 A 05/19/2019 323B1445 Closeout Phase 07/05/2018 A 05/19/2019 323B1450 Issue SAC Letter 07/05/2018 A 0B1470 Final Release of Retainage - Construction Contract 01/19/2019 0B1480 Administrative Closeout 01/20/2019 05/19/2019 120B1490 Project Closed 05/19/2019 0

Basin 0700Basin 0700 02/12/2013 A 08/01/2018 1808

100129 Pu100129 Pump Station 0700 Upgrade 02/12/2013 A 08/01/2018 1808DesignDesign 02/12/2013 A 01/24/2018 A 1808

B1000 Design Phase 02/12/2013 A 01/24/2018 A 1808B1005 Remedial Action Plan Submittal to SAC Letter Issuance 02/12/2013 A 01/24/2018 A 1808

Project CProject Closeout 01/24/2018 A 08/01/2018 642B1445 Closeout Phase 01/24/2018 A 08/01/2018 642B1450 Issue SAC Letter 01/24/2018 A 0B1480 Administrative Closeout 01/25/2018 A 08/01/2018 120B1490 Project Closed 08/01/2018 0

Basin 0723Basin 0723 01/14/2016 A 08/17/2018 1083

100130 Pu100130 Pump Station 0723 Upgrade 01/14/2016 A 08/17/2018 1083DesignDesign 01/14/2016 A 03/27/2017 A 452

B1000 Design Phase 01/14/2016 A 03/27/2017 A 452B1010 Prepare and Submit Design Package 01/14/2016 A 01/15/2016 A 5B1020 Engage Design Consultant 01/15/2016 A 02/17/2016 A 20B1022 TA Preparation 02/22/2016 A 02/22/2016 A 1B1024 TA Approval Process 03/08/2016 A 04/21/2016 A 20

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

100% Review (MDWASD/PSIP Team)Design Completed

04/13/2018 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter

Contract Award (Purchase Order Approval)01/19/2019, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction meetingPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Construction NTPConstruction OperationsSubstantial Completion01/19/2019, Designer Construction Support Serv

Designer Construction Support Services05/19/2019, Project Closeout

Closeout PhaseIssue SAC Letter

Final Release of Retainage - Construction ContraAdministrative CloseoutProject Closed

08/01/2018, Basin 0700

08/01/2018, 100129 Pump Station 0700 Upgrade01/24/2018 A, Design

Design PhaseRemedial Action Plan Submittal to SAC Letter Issuance

08/01/2018, Project CloseoutCloseout Phase

Issue SAC LetterAdministrative Closeout

Project Closed08/17/2018, Basin 0723

08/17/2018, 100130 Pump Station 0723 Upgrade03/27/2017 A, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval Process

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 117 of 161 TASK filter: All Activities© Oracle Corporation

Page 118: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1030 Issue Design NTP 04/25/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 04/25/2016 A 03/14/2017 A 85

30% Des30% Design 04/25/2016 A 07/11/2016 A 42B1060 A/E Prepares 30% Construction Documents 04/25/2016 A 06/08/2016 A 30B1070 Geotechnical Engineering Services 05/04/2016 A 06/08/2016 A 20B1080 Surveying Services 05/04/2016 A 06/08/2016 A 15B1100 30% CDs Submittal 06/08/2016 A 0B1120 30% Review (MDWASD/PSIP Team) 06/08/2016 A 07/11/2016 A 10

60% Des60% Design 06/09/2016 A 09/02/2016 A 72B1130 A/E Prepares 60% Construction Documents 06/09/2016 A 08/08/2016 A 20B1140 60% CDs Submittal 08/08/2016 A 0B1160 60% Review (MDWASD/PSIP Team) 08/09/2016 A 09/02/2016 A 10

90% Des90% Design 06/09/2016 A 03/14/2017 A 214B1170 A/E Prepares 90% Construction Documents 08/09/2016 A 09/30/2016 A 20B1180 90% CDs Submittal 09/30/2016 A 0B1190 90% Review (MDWASD/PSIP Team) 10/03/2016 A 10/26/2016 A 15B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 11/21/2016 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 11/21/2016 A 01/31/2017 A 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 02/07/2017 A 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 02/07/2017 A 03/14/2017 A 21B1240 90% PWWMD Permit Submittal (Pump Station) 06/09/2016 A 0B1250 90% PWWMD Permit Review (Pump Station) 06/09/2016 A 07/06/2016 A 15B1260 90% CD PM Comments Evaluation Completed 03/14/2017 A 0B1262 MDWASD Union Concurrence Process 01/27/2017 A 03/07/2017 A 30

100% De100% Design 03/14/2017 A 03/27/2017 A 26B1270 A/E Prepares 100% Construction Documents 03/14/2017 A 03/27/2017 A 10B1280 100% CDs Submittal 03/27/2017 A 0B1290 100% Review (MDWASD/PSIP Team) 03/27/2017 A 03/27/2017 A 10B1300 Design Completed 03/27/2017 A 0

MDWASDMDWASD Procurement 03/27/2017 A 08/09/2017 A 66B1305 Procurement Phase 03/27/2017 A 08/09/2017 A 66B1310 Submit CDs to MDWASD Procurement Division 03/27/2017 A 0B1312 Bid Notice Preparation Period 03/28/2017 A 03/31/2017 A 23B1314 Bid Notice 03/31/2017 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Confefence 04/03/2017 A 04/03/2017 A 10B1320 Pre-Bid Conference 04/04/2017 A 04/04/2017 A 1B1322 Bidders Prepare Bids for Submittal 04/05/2017 A 05/02/2017 A 15B1330 Bids Submittal 05/02/2017 A 0B1340 MDWASD/PSIP Team Bids Evaluation 05/03/2017 A 05/23/2017 A 15B1350 Recommendation for Award Letter 05/23/2017 A 0B1355 Contract Award (Purchase Order Approval) 05/24/2017 A 08/09/2017 A 10

ConstrucConstruction 04/04/2017 A 04/19/2018 A 618B1360 Construction Phase 04/04/2017 A 04/19/2018 A 618B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 05/24/2017 A 08/22/2017 A 15B1364 Pre-Construction Meeting 08/23/2017 A 08/23/2017 A 1B1366 WASD Issues NTP (Pre-Const to NTP) 08/24/2017 A 09/01/2017 A 12B1369 WASD Issues NTP (PO to NTP) 08/10/2017 A 09/03/2017 A 53B1370 Construction NTP 09/04/2017 A 0B1400 Construction Operations 09/04/2017 A 04/19/2018 A 150

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Issue Design NTPFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

07/11/2016 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal

30% Review (MDWASD/PSIP Team)09/02/2016 A, 60% Design

A/E Prepares 60% Construction Documents60% CDs Submittal60% Review (MDWASD/PSIP Team)

03/14/2017 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)

90% RER(DERM)FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)

90% RER(Building Dept) Permit Review (Pump Station)90% PWWMD Permit Submittal (Pump Station)

90% PWWMD Permit Review (Pump Station)90% CD PM Comments Evaluation Completed

MDWASD Union Concurrence Process03/27/2017 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal

100% Review (MDWASD/PSIP Team)Design Completed

08/09/2017 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid Notice

MDWASD/PSIP Team Prepare for Pre-Bid ConfefencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter

Contract Award (Purchase Order Approval)04/19/2018 A, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction MeetingWASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Construction NTPConstruction Operations

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 118 of 161 TASK filter: All Activities© Oracle Corporation

Page 119: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1400 Original Construction Duration 09/04/2017 A 02/01/2018 A 150B1400 Change Order #1 - Hurricane Irma 02/02/2018 A 02/22/2018 A 150B1402 Substantial Completion 04/19/2018 A 0

DesignerDesigner Construction Support Services 04/04/2017 A 04/19/2018 A 260B1410 Designer Construction Support Services 04/04/2017 A 04/19/2018 A 778

Project CProject Closeout 04/20/2018 A 08/17/2018 120B1445 Closeout Phase 04/20/2018 A 08/17/2018 120B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 04/20/2018 A 08/17/2018 120B1490 Project Closed 08/17/2018 0

Basin 0724Basin 0724 09/25/2014 A 09/28/2020 2136

100131 Ba100131 Basin 0724 Infiltration/Inflow Study and Repairs 09/25/2014 A 05/13/2016 A 647InfiltratioInfiltration/Inflow 09/25/2014 A 05/13/2016 A 615

B1000 Infiltration/Inflow Phase 09/25/2014 A 05/13/2016 A 615Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 10/23/2015 A 213

B1005 SSES Phase 09/25/2014 A 10/23/2015 A 213B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 04/24/2015 A 10/23/2015 A 30

Dig & ReDig & Replace Repairs 11/20/2015 A 05/13/2016 A 30B1165 Dig & Replace Phase 11/20/2015 A 05/13/2016 A 30B1180 Issue NTP for Dig & Replace Repairs 11/20/2015 A 0B1190 Conduct Dig & Replace Repairs 04/14/2016 A 05/13/2016 A 30

Project CProject Closeout 05/13/2016 A 05/13/2016 A 0B1235 Closeout Phase 05/13/2016 A 05/13/2016 A 0B1260 Project Closed 05/13/2016 A 0

100132 Pu100132 Pump Station 0724 Upgrade * 08/01/2018 09/28/2020 564DesignDesign 08/01/2018 06/29/2019 333

B1000 Design Phase 08/01/2018 06/29/2019 333B1010 Prepare and Submit Design Package 08/01/2018 08/07/2018 7B1020 Engage Design Consultant 08/08/2018 09/04/2018 28B1022 TA Preparation 09/05/2018 09/18/2018 14B1024 TA Approval Process 09/19/2018 10/28/2018 40B1030 Issue Design NTP 10/29/2018 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/29/2018 06/01/2019 216

30% Des30% Design 10/29/2018 01/16/2019 80B1060 A/E Prepares 30% Construction Documents 10/29/2018 12/17/2018 50B1100 30% CDs Submittal 12/17/2018 0B1120 30% Review (MDWASD/PSIP Team) 12/18/2018 01/16/2019 30

60% Des60% Design 12/18/2018 01/30/2019 44B1130 A/E Prepares 60% Construction Documents 12/18/2018 01/16/2019 30B1140 60% CDs Submittal 01/16/2019 0B1160 60% Review (MDWASD/PSIP Team) 01/17/2019 01/30/2019 14

90% Des90% Design 01/17/2019 06/01/2019 136B1170 A/E Prepares 90% Construction Documents 01/17/2019 02/25/2019 40B1180 90% CDs Submittal 02/25/2019 0B1190 90% Review (MDWASD/PSIP Team) 02/26/2019 03/27/2019 30B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 03/28/2019 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 03/28/2019 05/11/2019 45

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Original Construction DurationChange Order #1 - Hurricane Irma

Substantial Completion04/19/2018 A, Designer Construction Support Services

Designer Construction Support Services08/17/2018, Project Closeout

Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction ContractAdministrative CloseoutProject Closed

05/13/2016 A, 100131 Basin 0724 Infiltration/Inflow Study and Repairs05/13/2016 A, Infiltration/Inflow

Infiltration/Inflow Phase10/23/2015 A, Sanitary Sewer Evaluation SurveySSES Phase

Issue NTP to SSES ContractorConduct SSES

05/13/2016 A, Dig & Replace RepairsDig & Replace Phase

Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs05/13/2016 A, Project CloseoutCloseout Phase

Project Closed

06/29/2019, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval Process

Issue Design NTPFinal Engineering Report Review & Ap

01/16/2019, 30% Design

A/E Prepares 30% Construction Documents30% CDs Submittal

30% Review (MDWASD/PSIP Team)01/30/2019, 60% Design

A/E Prepares 60% Construction Documents60% CDs Submittal60% Review (MDWASD/PSIP Team)

06/01/2019, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (P

90% RER(DERM)FDEP Permit Review (

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 119 of 161 TASK filter: All Activities© Oracle Corporation

Page 120: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 05/12/2019 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 05/12/2019 06/01/2019 21B1240 90% Municipality Permit Submittal (Pump Station) 05/12/2019 0B1250 90% Municipality Permit Review (Pump Station) 05/12/2019 06/01/2019 21B1260 90% CD PM Comments Evaluation Completed 06/01/2019 0

100% De100% Design 06/02/2019 06/29/2019 28B1270 A/E Prepares 100% Construction Documents 06/02/2019 06/15/2019 14B1280 100% CDs Submittal 06/15/2019 0B1290 100% Review (MDWASD/PSIP Team) 06/16/2019 06/29/2019 14B1300 Design Completed 06/29/2019 0

MDWASDMDWASD Procurement 06/29/2019 10/11/2019 104B1305 Procurement Phase 06/29/2019 10/11/2019 104B1310 Submit CDs to MDWASD Procurement Division 06/29/2019 0B1312 Bid Notice Preparation Period 06/30/2019 08/01/2019 33B1314 Bid Notice 08/01/2019 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 08/02/2019 08/15/2019 14B1320 Pre-Bid Conference 08/16/2019 08/16/2019 1B1322 Bidders Prepare Bids for Submittal 08/17/2019 09/06/2019 21B1330 Bids Submittal 09/06/2019 0B1340 MDWASD/PSIP Team Bids Evaluation 09/07/2019 09/27/2019 21B1350 Recommendation for Award Letter 09/27/2019 0B1355 Contract Award (Purchase Order Approval) 09/28/2019 10/11/2019 14

ConstrucConstruction 08/16/2019 05/31/2020 290B1360 Construction Phase 08/16/2019 05/31/2020 290B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 09/28/2019 10/18/2019 21B1364 Pre-Construction Meeting 10/19/2019 10/19/2019 1B1366 WASD Issues NTP (Pre-Const to NTP) 10/20/2019 12/03/2019 45B1369 WASD Issues NTP (PO to NTP) 10/12/2019 12/03/2019 53B1370 Construction NTP 12/04/2019 0B1400 Construction Operations 12/04/2019 05/31/2020 180B1402 Substantial Completion 05/31/2020 0

DesignerDesigner Construction Support Services 08/16/2019 05/31/2020 290B1410 Designer Construction Support Services 08/16/2019 05/31/2020 290

Project CProject Closeout 08/01/2018 09/28/2020 564B1445 Closeout Phase 08/01/2018 09/28/2020 790B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 05/31/2020 0B1480 Administrative Closeout 06/01/2020 09/28/2020 120B1490 Project Closed 09/28/2020 0

Basin 0742Basin 0742 11/20/2015 A 08/18/2019 1294

100133 Ba100133 Basin 0742 Infiltration/Inflow Study and Repairs 11/20/2015 A 05/11/2016 A 156InfiltratioInfiltration/Inflow 11/20/2015 A 05/10/2016 A 144

B1000 Infiltration/Inflow Phase 11/20/2015 A 05/10/2016 A 144Dig & ReDig & Replace Repairs 11/20/2015 A 05/10/2016 A 144

B1165 Dig & Replace Phase 11/20/2015 A 05/10/2016 A 144B1180 Issue NTP for Dig & Replace Repairs 11/20/2015 A 0B1190 Conduct Dig & Replace Repairs 04/08/2016 A 05/10/2016 A 30

Project CProject Closeout 05/11/2016 A 05/11/2016 A 0B1235 Closeout Phase 05/11/2016 A 05/11/2016 A 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

90% RER(Building Dept) Permit Submit90% RER(Building Dept) Permit Revie

90% Municipality Permit Submittal (Pum90% Municipality Permit Review (Pum90% CD PM Comments Evaluation C

06/29/2019, 100% Design

A/E Prepares 100% Construction Do100% CDs Submittal100% Review (MDWASD/PSIP TeamDesign Completed

10/11/2019, MDWASD ProProcurement Phase

Submit CDs to MDWASD ProcuremBid Notice Preparation Period

Bid NoticeMDWASD/PSIP Team Prepare

Pre-Bid ConferenceBidders Prepare Bids for Subm

Bids SubmittalMDWASD/PSIP Team Bids ERecommendation for Award Contract Award (Purchase O

05/31/2

ConstruMDWASD/PSIP Team PrePre-Construction Meeting

WASD Issues NTP (PreWASD Issues NTP (PO

Construction NTPConstruSubstan05/31/2

Designe

Issue SAC LetterFinal Re

08/18/2019, Basin 0742

05/11/2016 A, 100133 Basin 0742 Infiltration/Inflow Study and Repairs05/10/2016 A, Infiltration/InflowInfiltration/Inflow Phase05/10/2016 A, Dig & Replace RepairsDig & Replace Phase

Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs05/11/2016 A, Project CloseoutCloseout Phase

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 120 of 161 TASK filter: All Activities© Oracle Corporation

Page 121: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1260 Project Closed 05/11/2016 A 0

100134 Pu100134 Pump Station 0742 Upgrade 01/14/2016 A 08/18/2019 1294DesignDesign 01/14/2016 A 04/23/2018 A 819

B1000 Design Phase 01/14/2016 A 04/23/2018 A 819B1010 Prepare and Submit Design Package 01/14/2016 A 01/14/2016 A 5B1020 Engage Design Consultant 01/14/2016 A 04/01/2016 A 20B1022 TA Preparation 04/04/2016 A 04/15/2016 A 1B1024 TA Approval Process 04/18/2016 A 09/28/2016 A 20B1030 Issue Design NTP 09/30/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 09/30/2016 A 03/30/2018 A 85

30% Des30% Design 09/30/2016 A 06/13/2017 A 170B1060 A/E Prepares 30% Construction Documents 09/30/2016 A 01/17/2017 A 50B1100 30% CDs Submittal 01/17/2017 A 0B1120 30% Review (MDWASD/PSIP Team) 01/18/2017 A 03/17/2017 A 30B1122 Project On-Hold, Pending Construction Staging Area Approval 03/17/2017 A 06/13/2017 A 63

90% Des90% Design 06/13/2017 A 03/30/2018 A 282B1170 A/E Prepares 90% Construction Documents 06/13/2017 A 07/14/2017 A 40B1180 90% CDs Submittal 07/14/2017 A 0B1190 90% Review (MDWASD/PSIP Team) 07/17/2017 A 10/09/2017 A 30B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 11/22/2017 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 11/22/2017 A 02/21/2018 A 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 02/22/2018 A 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 02/22/2018 A 03/30/2018 A 21B1260 90% CD PM Comments Evaluation Completed 03/30/2018 A 0B1262 MDWASD Union Concurrence Process 07/27/2017 A 08/17/2017 A 30

100% De100% Design 04/01/2018 A 04/23/2018 A 30B1270 A/E Prepares 100% Construction Documents 04/01/2018 A 04/13/2018 A 14B1280 100% CDs Submittal 04/13/2018 A 0B1290 100% Review (MDWASD/PSIP Team) 04/15/2018 A 04/23/2018 A 14B1300 Design Completed 04/23/2018 A 0

MDWASDMDWASD Procurement 04/08/2018 A 08/30/2018 91B1305 Procurement Phase 04/08/2018 A 08/30/2018 91B1310 Submit CDs to MDWASD Procurement Division 05/07/2018 A 0B1312 Bid Notice Preparation Period 04/08/2018 A 05/15/2018 A 33B1314 Bid Notice 05/15/2018 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 05/16/2018 A 05/28/2018 A 14B1320 Pre-Bid Conference 05/29/2018 A 05/29/2018 A 1B1322 Bidders Prepare Bids for Submittal 05/30/2018 A 07/26/2018 A 21B1330 Bids Submittal 07/26/2018 A 0B1340 MDWASD/PSIP Team Bids Evaluation 07/27/2018 A 08/16/2018 21B1350 Recommendation for Award Letter 08/16/2018 0B1355 Contract Award (Purchase Order Approval) 08/17/2018 08/30/2018 14

ConstrucConstruction 05/29/2018 A 04/20/2019 290B1360 Construction Phase 05/29/2018 A 04/20/2019 290B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 08/17/2018 09/06/2018 21B1364 Pre-Construction Meeting 09/07/2018 09/07/2018 1B1366 WASD Issues NTP (Pre-Const to NTP) 09/08/2018 10/22/2018 45B1369 WASD Issues NTP (PO to NTP) 08/31/2018 10/22/2018 53B1370 Construction NTP 10/23/2018 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Project Closed08/18/2019, 100134 Pump Sta

04/23/2018 A, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval ProcessIssue Design NTP

Final Engineering Report Review & Approval (MDWASD/PSIP Team)06/13/2017 A, 30% Design

A/E Prepares 30% Construction Documents30% CDs Submittal

30% Review (MDWASD/PSIP Team)Project On-Hold, Pending Construction Staging Area Approval

03/30/2018 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)

90% RER(DERM)FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)

90% RER(Building Dept) Permit Review (Pump Station)90% CD PM Comments Evaluation Completed

MDWASD Union Concurrence Process04/23/2018 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed

08/30/2018, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid Notice

MDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)

04/20/2019, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Construction NTP

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 121 of 161 TASK filter: All Activities© Oracle Corporation

Page 122: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1400 Construction Operations 10/23/2018 04/20/2019 180B1402 Substantial Completion 04/20/2019 0

DesignerDesigner Construction Support Services 05/29/2018 A 04/20/2019 290B1410 Designer Construction Support Services 05/29/2018 A 04/20/2019 290

Project CProject Closeout 08/01/2018 08/18/2019 383B1445 Closeout Phase 08/01/2018 08/18/2019 383B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 04/20/2019 0B1480 Administrative Closeout 04/21/2019 08/18/2019 120B1490 Project Closed 08/18/2019 0

Basin 0743Basin 0743 08/04/2014 A 08/01/2018 1554

100135 Ba100135 Basin 0743 Infiltration/Inflow Study and Repairs 05/22/2015 A 05/06/2016 A 297InfiltratioInfiltration/Inflow 05/22/2015 A 05/05/2016 A 237

B1000 Infiltration/Inflow Phase 05/22/2015 A 05/05/2016 A 237CIPP RepCIPP Repairs 05/22/2015 A 07/28/2015 A 20

B1065 CIPP Phase 05/22/2015 A 07/28/2015 A 20B1080 Issue NTP for CIPP Repairs 05/22/2015 A 0B1090 Conduct CIPP Repairs 07/27/2015 A 07/28/2015 A 20

ManholeManhole Repairs 10/30/2015 A 03/17/2016 A 20B1115 Manhole Phase 10/30/2015 A 03/17/2016 A 20B1130 Issue NTP for Manhole Repairs 10/30/2015 A 0B1140 Conduct Manhole Repairs 03/17/2016 A 03/17/2016 A 20

Dig & ReDig & Replace Repairs 06/26/2015 A 05/05/2016 A 30B1165 Dig & Replace Phase 06/26/2015 A 05/05/2016 A 30B1180 Issue NTP for Dig & Replace Repairs 06/26/2015 A 0B1190 Conduct Dig & Replace Repairs 08/04/2015 A 05/05/2016 A 30

Project CProject Closeout 05/06/2016 A 05/06/2016 A 0B1235 Closeout Phase 05/06/2016 A 05/06/2016 A 0B1260 Project Closed 05/06/2016 A 0

100218 Pu100218 Pump Station 0743(AM) Upgrade 08/04/2014 A 08/01/2018 1479DesignDesign 08/04/2014 A 07/10/2015 A 496

B1000 Design Phase 08/04/2014 A 07/10/2015 A 496B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 08/04/2014 A 08/06/2014 A 5B1020 Engage Design Consultant 08/07/2014 A 11/04/2014 A 20B1030 Issue Design NTP 11/05/2014 A 0B1040 A/E Develops and Submits Final Engineering Report 11/05/2014 A 07/10/2015 A 17B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 11/05/2014 A 02/27/2015 A 10

30% Des30% Design 11/05/2014 A 01/08/2015 A 30B1060 A/E Prepares 30% Construction Documents 11/05/2014 A 12/24/2014 A 30B1070 Geotechnical Engineering Services 11/05/2014 A 12/24/2014 A 20B1080 Surveying Services 11/05/2014 A 12/24/2014 A 15B1100 30% CDs Submittal 12/24/2014 A 0B1120 30% Review (MDWASD/PSIP Team) 12/26/2014 A 01/08/2015 A 10

90% Des90% Design 12/26/2014 A 07/10/2015 A 135B1170 A/E Prepares 90% Construction Documents 12/26/2014 A 02/18/2015 A 20B1180 90% CDs Submittal 02/18/2015 A 0B1190 90% Review (MDWASD/PSIP Team) 02/18/2015 A 02/27/2015 A 15B1195 Permit Set Modifications 03/02/2015 A 03/05/2015 A 10B1200 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 03/06/2015 A 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Construction OperationsSubstantial Completion04/20/2019, Designer Construction Supp

Designer Construction Support Services08/18/2019, Project Closeout

Closeout PhaseIssue SAC Letter

Final Release of Retainage - ConstructionAdministrative CloseoutProject Closed

08/01/2018, Basin 0743

05/06/2016 A, 100135 Basin 0743 Infiltration/Inflow Study and Repairs05/05/2016 A, Infiltration/Inflow

Infiltration/Inflow Phase07/28/2015 A, CIPP RepairsCIPP Phase

Issue NTP for CIPP RepairsConduct CIPP Repairs

03/17/2016 A, Manhole RepairsManhole Phase

Issue NTP for Manhole RepairsConduct Manhole Repairs

05/05/2016 A, Dig & Replace RepairsDig & Replace Phase

Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs05/06/2016 A, Project CloseoutCloseout Phase

Project Closed08/01/2018, 100218 Pump Station 0743(AM) Upgrade

07/10/2015 A, Design

Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book

Engage Design ConsultantIssue Design NTP

A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

01/08/2015 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services

30% CDs Submittal30% Review (MDWASD/PSIP Team)

07/10/2015 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)Permit Set Modifications

90% RER(DERM)/FDEP Permit Submittal (Pump Station)

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 122 of 161 TASK filter: All Activities© Oracle Corporation

Page 123: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1210 90% RER(DERM)/FDEP Permit Review (Pump Station) 03/06/2015 A 04/07/2015 A 5B1220 90% RER (Building Dept) Permit Submittal 04/22/2015 A 0B1230 90% RER (Building Dept) Permit Review 04/22/2015 A 06/09/2015 A 10B1240 90% PWWMD Permit Submittal 07/01/2015 A 0B1250 90% PWWMD Permit Review 07/01/2015 A 07/10/2015 A 5B1260 90% CD PM Comments Evaluation Completed 07/10/2015 A 0

100% De100% Design 07/10/2015 A 07/10/2015 A 43B1270 A/E Prepares 100% Construction Documents 07/10/2015 A 07/10/2015 A 5B1280 100% CDs Submittal 07/10/2015 A 0B1290 100% Review (MDWASD/PSIP Team) 07/10/2015 A 07/10/2015 A 5B1300 Design Completed 07/10/2015 A 0

MDWASDMDWASD Procurement 04/17/2015 A 10/07/2015 A 123B1305 Procurement Phase 04/17/2015 A 10/07/2015 A 123B1310 Submit CDs to MDWASD Procurement Division 04/17/2015 A 0B1312 Bid Notice Preparation Period 04/20/2015 A 04/29/2015 A 0B1314 Bid Notice 04/30/2015 A 0B1316 MDWASD/PSIP Team Prepared for Pre-Bid Conference 05/01/2015 A 05/05/2015 A 0B1320 Pre-Bid Conference 05/06/2015 A 05/06/2015 A 0B1322 Bidders Prepare Bids for Submittal 05/07/2015 A 07/01/2015 A 0B1330 Bids Submittal 07/02/2015 A 0B1340 MDWASD/PSIP Team Bids Evaluation 07/03/2015 A 07/17/2015 A 15B1350 Recommendation for Award Letter 07/17/2015 A 0B1355 Contract Award (Purchase Order Approval) 07/20/2015 A 10/07/2015 A 10

ConstrucConstruction 05/06/2015 A 03/03/2017 A 1219B1360 Construction Phase 05/06/2015 A 03/03/2017 A 1219B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 07/20/2015 A 08/18/2015 A 15B1365 Pre-Construction Meeting 08/19/2015 A 0B1366 Awaiting Resolution of FPL Issues & MDWASD Electrtical Stand 08/19/2015 A 01/22/2016 A 15B1369 WASD Issues NTP (PO to NTP) 10/08/2015 A 01/24/2016 A 53B1370 Construction NTP 01/25/2016 A 0B1400 Construction Operations 01/25/2016 A 11/15/2016 A 107B1400 Original Construction Duration 01/25/2016 A 06/23/2016 A 107B1400 Change Order #1 - FPL 06/24/2016 A 08/31/2016 A 107B1400 Change Order #2 - Contractual Duration Discrepancies 09/01/2016 A 11/15/2016 A 107B1402 Substantial Completion 11/15/2016 A 0

DesignerDesigner Construction Support Services 05/06/2015 A 03/03/2017 A 226B1410 Designer Construction Support Services 05/06/2015 A 03/03/2017 A 226

ConstrucConstruction Close Out 11/16/2016 A 03/03/2017 A 10B1420 Commissioning 11/16/2016 A 03/03/2017 A 5B1430 Punch List 11/16/2016 A 03/03/2017 A 10

Project CProject Closeout 11/16/2016 A 08/01/2018 624B1445 Closeout Phase 11/16/2016 A 08/01/2018 624B1450 Issue SAC Letter 03/20/2018 A 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 11/16/2016 A 08/01/2018 120B1490 Project Closed 08/01/2018 0

100214 FM100214 FM for Pump Station 0743 08/18/2014 A 08/01/2018 1554DesignDesign 08/18/2014 A 07/23/2015 A 549

B1000 Design Phase 08/18/2014 A 07/23/2015 A 549

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

90% RER(DERM)/FDEP Permit Review (Pump Station)90% RER (Building Dept) Permit Submittal

90% RER (Building Dept) Permit Review90% PWWMD Permit Submittal90% PWWMD Permit Review90% CD PM Comments Evaluation Completed07/10/2015 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal

100% Review (MDWASD/PSIP Team)Design Completed

10/07/2015 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation Period

Bid NoticeMDWASD/PSIP Team Prepared for Pre-Bid Conference

Pre-Bid ConferenceBidders Prepare Bids for Submittal

Bids SubmittalMDWASD/PSIP Team Bids Evaluation

Recommendation for Award LetterContract Award (Purchase Order Approval)

03/03/2017 A, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction Meeting

Pre-Construction MeetingAwaiting Resolution of FPL Issues & MDWASD Electrtical StandardWASD Issues NTP (PO to NTP)

Construction NTPConstruction Operations

Original Construction DurationChange Order #1 - FPL

Change Order #2 - Contractual Duration Discrepancies

Substantial Completion03/03/2017 A, Designer Construction Support Services

Designer Construction Support Services03/03/2017 A, Construction Close Out

CommissioningPunch List

08/01/2018, Project Closeout

Closeout PhaseIssue SAC Letter

Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed08/01/2018, 100214 FM for Pump Station 0743

07/23/2015 A, Design

Design Phase

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 123 of 161 TASK filter: All Activities© Oracle Corporation

Page 124: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 08/18/2014 A 09/05/2014 A 5B1020 Engage Design Consultant 09/08/2014 A 12/05/2014 A 20B1030 Issue Design NTP 12/05/2014 A 0B1040 A/E Develops and Submits Final Engineering Report 12/05/2014 A 07/23/2015 A 20B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 12/05/2014 A 03/30/2015 A 10

30% Des30% Design 12/08/2014 A 03/25/2015 A 30B1060 A/E Prepares 30% Construction Documents 12/08/2014 A 02/17/2015 A 30B1070 Geotechnical Engineering Services 12/08/2014 A 02/17/2015 A 20B1080 Surveying Services 12/08/2014 A 02/17/2015 A 15B1100 30% CDs Submittal 02/17/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 02/18/2015 A 03/25/2015 A 0

60% Des60% Design 02/18/2015 A 03/04/2015 A 15B1140 A/E Prepares 60% Construction Documents (Progress Set) 02/18/2015 A 03/04/2015 A 15B1150 60% CDs Submittal (Progress Set) 03/04/2015 A 0B1170 60% Review (On-Board Review) 03/04/2015 A 03/04/2015 A 1

90% Des90% Design 03/05/2015 A 07/23/2015 A 116B1180 A/E Prepares 90% Construction Documents 03/05/2015 A 03/27/2015 A 0B1190 90% CDs Submittal 03/27/2015 A 0B1200 90% Review (MDWASD/PSIP Team) 03/25/2015 A 03/30/2015 A 5B1230 90% RER(DERM)FDEP Permit Submittal (Force Main) 07/14/2015 A 0B1240 90% RER(DERM)FDEP Permit Review (Force Main) 07/14/2015 A 07/22/2015 A 5B1250 90% PWWMD Permit Submittal (Force Main) 07/16/2015 A 0B1260 90% PWWMD Permit Review (Force Main) 07/16/2015 A 07/23/2015 A 10B1290 90% CD PM Comments Evaluation Completed 07/23/2015 A 0

100% De100% Design 03/31/2015 A 07/22/2015 A 123B1300 A/E Prepares 100% Construction Documents 03/31/2015 A 07/22/2015 A 5B1310 100% CDs Submittal 07/22/2015 A 0B1320 100% Review (MDWASD/PSIP Team) 07/22/2015 A 07/22/2015 A 5B1330 Design Completed 07/22/2015 A 0

MDWASDMDWASD Procurement 08/13/2015 A 03/04/2016 A 109B1335 Procurement Phase 08/13/2015 A 03/04/2016 A 109B1340 Submit CDs to MDWASD Procurement Division 08/13/2015 A 0B1342 Bid Notice Preparation Period 08/14/2015 A 09/18/2015 A 23B1344 Bid Notice 09/21/2015 A 0B1346 MDWASD/PSIP Team Preparation for Pre-Bid Conference 09/22/2015 A 10/07/2015 A 10B1350 Pre-Bid Conference 10/08/2015 A 10/08/2015 A 1B1358 Bidders Prepare Bids for Submittal 10/09/2015 A 10/27/2015 A 15B1360 Bids Submittal 10/28/2015 A 0B1370 MDWASD/PSIP Team Bids Evaluation 10/29/2015 A 12/08/2015 A 15B1380 Recommendation for Award Letter 12/08/2015 A 0B1385 Contract Award (Purchase Order Approval) 12/09/2015 A 03/04/2016 A 10

ConstrucConstruction 10/08/2015 A 02/02/2017 A 1160B1390 Construction Phase 10/08/2015 A 12/04/2016 A 1160B1392 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 12/09/2015 A 01/06/2016 A 15B1394 Pre-Construction Meeting 01/07/2016 A 01/07/2016 A 1B1396 WASD Issues NTP (PO to NTP) 03/05/2016 A 03/13/2016 A 53B1400 Construction NTP 03/14/2016 A 0B1430 Construction Operations 03/14/2016 A 11/04/2016 A 104B1430 Original Contruction Duration 03/14/2016 A 08/07/2016 A 104

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Prepare Request for SOW, Fee, Schedule, and Project BookEngage Design ConsultantIssue Design NTP

A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)03/25/2015 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal

30% Review (MDWASD/PSIP Team)03/04/2015 A, 60% Design

A/E Prepares 60% Construction Documents (Progress Set)60% CDs Submittal (Progress Set)

60% Review (On-Board Review)07/23/2015 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)

90% RER(DERM)FDEP Permit Submittal (Force Main)90% RER(DERM)FDEP Permit Review (Force Main)90% PWWMD Permit Submittal (Force Main)90% PWWMD Permit Review (Force Main)90% CD PM Comments Evaluation Completed07/22/2015 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal

100% Review (MDWASD/PSIP Team)Design Completed

03/04/2016 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Preparation for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter

Contract Award (Purchase Order Approval)02/02/2017 A, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

WASD Issues NTP (PO to NTP)Construction NTP

Construction OperationsOriginal Contruction Duration

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 124 of 161 TASK filter: All Activities© Oracle Corporation

Page 125: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1430 Change Order #1 - Pipe & Roadway Restoration 08/08/2016 A 11/05/2016 A 104B1432 Substantial Completion 02/02/2017 A 0

DesignerDesigner Construction Support Services 10/08/2015 A 12/04/2016 A 267B1440 Designer Construction Support Services 10/08/2015 A 12/04/2016 A 267

ConstrucConstruction Close Out 11/07/2016 A 12/04/2016 A 10B1460 Punch List 11/07/2016 A 12/04/2016 A 10

Project CProject Closeout 11/07/2016 A 08/01/2018 547B1475 Closeout Phase 11/07/2016 A 08/01/2018 547B1500 Final Release of Retainage - Construction Contract 11/07/2017 A 0B1510 Administrative Closeout 11/07/2016 A 08/01/2018 120B1520 Project Closed 08/01/2018 0

Basin 0773Basin 0773 12/17/2012 A 08/01/2018 1901

100137 Pu100137 Pump Station 0773 Upgrade 12/17/2012 A 08/01/2018 1901DesignDesign 12/17/2012 A 03/02/2018 A 1901

B1000 Design Phase 12/17/2012 A 03/02/2018 A 1901B1005 Remedial Action Plan to SAC Letter Issuance 12/17/2012 A 03/02/2018 A 1901

Project CProject Closeout 03/02/2018 A 08/01/2018 152B1445 Closeout Phase 03/02/2018 A 08/01/2018 152B1450 Issue SAC Letter 03/02/2018 A 0B1480 Administrative Closeout 03/03/2018 A 08/01/2018 120B1490 Project Closed 08/01/2018 0

100229 FM100229 FM for Pump Station 0773 12/17/2012 A 08/01/2018 1901DesignDesign 12/17/2012 A 03/02/2018 A 1901

B1000 Design Phase 12/17/2012 A 03/02/2018 A 1901B1005 Remedial Action Plan to SAC Letter Issuance 12/17/2012 A 03/02/2018 A 1901

Project CProject Closeout 03/03/2018 A 08/01/2018 697B1475 Closeout Phase 03/03/2018 A 08/01/2018 697B1510 Administrative Closeout 03/03/2018 A 08/01/2018 120B1520 Project Closed 08/01/2018 0

Basin 0785Basin 0785 06/26/2015 A 01/22/2016 A 1000

100138 Ba100138 Basin 0785 Infiltration/Inflow Study and Repairs 06/26/2015 A 01/22/2016 A 246InfiltratioInfiltration/Inflow 06/26/2015 A 01/21/2016 A 30

B1000 Infiltration/Inflow Phase 06/26/2015 A 01/21/2016 A 30Dig & ReDig & Replace Repairs 06/26/2015 A 01/21/2016 A 30

B1165 Dig & Replace Phase 06/26/2015 A 01/21/2016 A 30B1180 Issue NTP for Dig & Replace Repairs 06/26/2015 A 0B1190 Conduct Dig & Replace Repairs 07/09/2015 A 01/21/2016 A 30

Project CProject Closeout 01/22/2016 A 01/22/2016 A 0B1235 Closeout Phase 01/22/2016 A 01/22/2016 A 0B1260 Project Closed 01/22/2016 A 0

100139 Pu100139 Pump Station 0785 Upgrade 07/02/2015 A 07/02/2015 A 1000Project CProject Closeout 07/02/2015 A 07/02/2015 A 1000

B1445 Closeout Phase 07/02/2015 A 07/02/2015 A 1000B1450 Issue SAC Letter 07/02/2015 A 0B1480 Administrative Closeout 07/02/2015 A 07/02/2015 A 5B1490 Project Closed 07/02/2015 A 07/02/2015 A 10

Basin 0794Basin 0794 09/25/2014 A 08/01/2018 1477

100140 Ba100140 Basin 0794 Infiltration/Inflow Study and Repairs 09/25/2014 A 07/13/2015 A 546InfiltratioInfiltration/Inflow 09/25/2014 A 07/10/2015 A 240

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Change Order #1 - Pipe & Roadway Restoration

Substantial Completion12/04/2016 A, Designer Construction Support Services

Designer Construction Support Services12/04/2016 A, Construction Close Out

Punch List08/01/2018, Project Closeout

Closeout PhaseFinal Release of Retainage - Construction Contract

Administrative CloseoutProject Closed08/01/2018, Basin 0773

08/01/2018, 100137 Pump Station 0773 Upgrade03/02/2018 A, Design

Design PhaseRemedial Action Plan to SAC Letter Issuance

08/01/2018, Project CloseoutCloseout Phase

Issue SAC LetterAdministrative CloseoutProject Closed08/01/2018, 100229 FM for Pump Station 0773

03/02/2018 A, Design

Design PhaseRemedial Action Plan to SAC Letter Issuance

08/01/2018, Project CloseoutCloseout Phase

Administrative CloseoutProject Closed

01/22/2016 A, Basin 0785

01/22/2016 A, 100138 Basin 0785 Infiltration/Inflow Study and Repairs01/21/2016 A, Infiltration/Inflow

Infiltration/Inflow Phase01/21/2016 A, Dig & Replace RepairsDig & Replace Phase

Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs01/22/2016 A, Project CloseoutCloseout Phase

Project Closed07/02/2015 A, 100139 Pump Station 0785 Upgrade07/02/2015 A, Project Closeout

Closeout PhaseIssue SAC Letter

Administrative CloseoutProject Closed

08/01/2018, Basin 0794

07/13/2015 A, 100140 Basin 0794 Infiltration/Inflow Study and Repairs07/10/2015 A, Infiltration/Inflow

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 125 of 161 TASK filter: All Activities© Oracle Corporation

Page 126: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1000 Infiltration/Inflow Phase 09/25/2014 A 07/10/2015 A 240Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 07/10/2015 A 240

B1005 SSES Phase 09/25/2014 A 07/10/2015 A 240B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 06/22/2015 A 07/10/2015 A 30

Project CProject Closeout 07/13/2015 A 07/13/2015 A 0B1235 Closeout Phase 07/13/2015 A 07/13/2015 A 0B1260 Project Closed 07/13/2015 A 0

100141 Pu100141 Pump Station 0794(AM) Upgrade 12/31/2014 A 08/01/2018 1440DesignDesign 12/31/2014 A 07/28/2016 A 662

B1000 Design Phase 12/31/2014 A 07/28/2016 A 662B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 12/31/2014 A 01/07/2015 A 5B1020 Engage Design Consultant 01/08/2015 A 04/14/2015 A 20B1030 Issue Design NTP 04/15/2015 A 0B1040 A/E Develops and Submits Final Engineering Report 04/15/2015 A 07/20/2016 A 73B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 04/15/2015 A 03/30/2016 A 32B1052 TA Rev 1 - Preparation of FPL and WASD Easements 06/30/2015 A 07/29/2015 A 20B1054 TA Rev 1 - FPL and WASD Easements Approval Process 07/30/2015 A 08/14/2015 A 20

30% Des30% Design 04/15/2015 A 06/08/2016 A 73B1060 A/E Prepares 30% Construction Documents 04/15/2015 A 06/08/2015 A 30B1070 Geotechnical Engineering Services 04/15/2015 A 06/08/2015 A 15B1080 Surveying Services 04/15/2015 A 06/08/2015 A 15B1100 30% CDs Submittal 06/12/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 06/15/2015 A 06/26/2015 A 10B1122 DC Prepares Legal Description & Location of FPL & MDWASD E 08/17/2015 A 08/31/2015 A 20B1124 Approval and Recording of FPL & MDWASD Easements 09/01/2015 A 06/08/2016 A 20

90% Des90% Design 02/09/2016 A 07/20/2016 A 181B1170 A/E Prepares 90% Construction Documents 02/09/2016 A 02/23/2016 A 20B1180 90% CDs Submittal 02/23/2016 A 0B1190 90% Review (MDWASD/PSIP Team) 02/24/2016 A 03/30/2016 A 15B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 04/19/2016 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 04/19/2016 A 06/20/2016 A 15B1220 90% RER (Building Department) Permit Submittal 06/24/2016 A 0B1230 90% RER (Building Department) Permit Review 06/24/2016 A 07/20/2016 A 15B1240 90% PWWMD Permit Submittal 03/07/2016 A 0B1250 90% PWWMD Permit Review 03/07/2016 A 03/30/2016 A 15B1260 90% CD PM Comments Evaluation Completed 07/20/2016 A 0

100% De100% Design 07/21/2016 A 07/28/2016 A 92B1270 A/E Prepares 100% Construction Documents 07/21/2016 A 07/28/2016 A 10B1280 100% CDs Submittal 07/28/2016 A 0B1290 100% Review (MDWASD/PSIP Team) 07/21/2016 A 07/28/2016 A 10B1300 Design Completed 07/28/2016 A 0

MDWASDMDWASD Procurement 07/29/2016 A 11/07/2016 A 59B1305 Procurement Phase 07/29/2016 A 11/07/2016 A 59B1310 Submit CDs to MDWASD Procurement Division 07/29/2016 A 0B1312 Bid Notice Preparation Period 07/29/2016 A 08/02/2016 A 23B1314 Bid Notice 08/02/2016 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 08/03/2016 A 08/11/2016 A 7B1320 Pre-Bid Conference 08/12/2016 A 08/12/2016 A 1

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Infiltration/Inflow Phase07/10/2015 A, Sanitary Sewer Evaluation SurveySSES Phase

Issue NTP to SSES ContractorConduct SSES07/13/2015 A, Project CloseoutCloseout Phase

Project Closed08/01/2018, 100141 Pump Station 0794(AM) Upgrade

07/28/2016 A, Design

Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book

Engage Design ConsultantIssue Design NTP

A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

TA Rev 1 - Preparation of FPL and WASD EasementsTA Rev 1 - FPL and WASD Easements Approval Process

06/08/2016 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal30% Review (MDWASD/PSIP Team)

DC Prepares Legal Description & Location of FPL & MDWASD Easement.Approval and Recording of FPL & MDWASD Easements

07/20/2016 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)

90% RER(DERM)FDEP Permit Review (Pump Station)90% RER (Building Department) Permit Submittal

90% RER (Building Department) Permit Review90% PWWMD Permit Submittal

90% PWWMD Permit Review90% CD PM Comments Evaluation Completed07/28/2016 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal

100% Review (MDWASD/PSIP Team)Design Completed11/07/2016 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 126 of 161 TASK filter: All Activities© Oracle Corporation

Page 127: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1328 Bidders Prepare Bids for Submittal 08/15/2016 A 08/30/2016 A 12B1330 Bids Submittal 08/30/2016 A 0B1340 MDWASD/PSIP Team Bids Evaluation 08/31/2016 A 09/08/2016 A 15B1350 Recommendation for Award Letter 09/08/2016 A 0B1355 Contract Award (Purchase Order Approval) 09/09/2016 A 11/07/2016 A 10

ConstrucConstruction 08/12/2016 A 03/15/2018 A 859B1360 Construction Phase 08/12/2016 A 03/15/2018 A 859B1362 MDWASD/PSIP Team Prepare for Pre-Construction meeting 09/09/2016 A 11/14/2016 A 15B1364 Pre-Construction Meeting 11/15/2016 A 11/15/2016 A 1B1369 WASD Issues NTP (PO to NTP) 11/08/2016 A 11/27/2016 A 53B1370 Construction NTP 11/28/2016 A 0B1400 Construction Operations 11/28/2016 A 03/15/2018 A 150B1400 Original Constrcution Duration 11/28/2016 A 04/27/2017 A 150B1400 Change Order #1 - FPL 04/28/2017 A 07/26/2017 A 150B1400 Change Order #2 - Hurricane Irma 07/27/2017 A 08/16/2017 A 150B1400 Change Order #3 - FPL 08/17/2017 A 02/16/2018 A 150B1402 Substantial Completion 03/15/2018 A 0

DesignerDesigner Construction Support Services 08/12/2016 A 03/15/2018 A 272B1410 Designer Construction Support Services 08/12/2016 A 03/15/2018 A 814

Project CProject Closeout 03/16/2018 A 08/01/2018 120B1445 Closeout Phase 03/16/2018 A 08/01/2018 120B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 03/16/2018 A 08/01/2018 120B1490 Project Closed 08/01/2018 0

100074 FM100074 FM for Pump Station 0794 01/12/2015 A 08/01/2018 1437DesignDesign 01/12/2015 A 10/16/2015 A 333

B1005 Design Phase 01/12/2015 A 10/16/2015 A 333B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 01/12/2015 A 01/16/2015 A 5B1020 Engage Design Consultant 01/19/2015 A 04/08/2015 A 30B1030 TA Approval Process 04/09/2015 A 04/30/2015 A 20B1040 Issue Design NTP 05/01/2015 A 0B1050 A/E Develops and Submits Final Engineering Report 05/01/2015 A 09/29/2015 A 86B1060 Final Engineering Report Review & Approval (MDWASD/PSIP Te 05/14/2015 A 09/29/2015 A 10

30% Des30% Design 05/01/2015 A 06/19/2015 A 54B1070 A/E Prepares 30% Construction Documents 05/01/2015 A 06/09/2015 A 25B1080 Geotechnical Engineering Services 05/01/2015 A 06/09/2015 A 15B1090 Surveying Services 05/01/2015 A 06/09/2015 A 15B1100 30% CDs Submittal 06/09/2015 A 0B1110 30% Review (MDWASD/PSIP Team) 06/10/2015 A 06/19/2015 A 6

90% Des90% Design 06/09/2015 A 10/08/2015 A 113B1150 A/E Prepares 90% Construction Documents 06/09/2015 A 06/29/2015 A 15B1152 90% Construction Documents Awaiting MDWASD/FPL Easemen 06/30/2015 A 07/28/2015 A 15B1154 A/E Prepares 90% Construction Documents (Resume Design) 07/29/2015 A 08/20/2015 A 15B1160 90% CDs Submittal 08/20/2015 A 0B1170 90% Review (MDWASD/PSIP Team) 08/21/2015 A 09/29/2015 A 15B1180 90% RER(DERM)FDEP Permit Submittal (Force Main) 09/29/2015 A 0B1190 90% RER(DERM)FDEP Permit Review (Force Main) 09/29/2015 A 10/08/2015 A 5B1200 90% PWWMD Permit Submittal (Force Main) 07/27/2015 A 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Bidders Prepare Bids for SubmittalBids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter

Contract Award (Purchase Order Approval)03/15/2018 A, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction meetingPre-Construction MeetingWASD Issues NTP (PO to NTP)

Construction NTPConstruction Operations

Original Constrcution DurationChange Order #1 - FPL

Change Order #2 - Hurricane IrmaChange Order #3 - FPL

Substantial Completion03/15/2018 A, Designer Construction Support Services

Designer Construction Support Services08/01/2018, Project Closeout

Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction ContractAdministrative CloseoutProject Closed08/01/2018, 100074 FM for Pump Station 0794

10/16/2015 A, Design

Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book

Engage Design ConsultantTA Approval ProcessIssue Design NTP

A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

06/19/2015 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal30% Review (MDWASD/PSIP Team)

10/08/2015 A, 90% Design

A/E Prepares 90% Construction Documents90% Construction Documents Awaiting MDWASD/FPL Easement ResolutionA/E Prepares 90% Construction Documents (Resume Design)

90% CDs Submittal90% Review (MDWASD/PSIP Team)

90% RER(DERM)FDEP Permit Submittal (Force Main)90% RER(DERM)FDEP Permit Review (Force Main)90% PWWMD Permit Submittal (Force Main)

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 127 of 161 TASK filter: All Activities© Oracle Corporation

Page 128: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1210 90% PWWMD Permit Review (Force Main) 07/27/2015 A 08/12/2015 A 15B1220 90% CD PM Comments Evaluation Completed 09/29/2015 A 0

100% De100% Design 09/30/2015 A 10/16/2015 A 17B1230 A/E Prepares 100% Construction Documents 09/30/2015 A 10/15/2015 A 6B1240 100% CDs Submittal 10/15/2015 A 0B1250 100% Review (MDWASD/PSIP Team) 10/15/2015 A 10/16/2015 A 5B1260 Design Completed 10/16/2015 A 0

MDWASDMDWASD Procurement 10/16/2015 A 03/07/2016 A 84B1270 Procurement Phase 10/16/2015 A 03/07/2016 A 84B1280 Submit CDs to MDWASD Procurement Division 10/16/2015 A 0B1282 Bid Notice Preparation Period 10/19/2015 A 11/17/2015 A 23B1284 Bid Notice 11/17/2015 A 0B1286 MDWASD/PSIP Team Prepare for Pre-Bid Conference 11/18/2015 A 12/02/2015 A 10B1290 Pre-Bid Conference 12/03/2015 A 12/03/2015 A 1B1298 Bidders Prepare Bids for Submittal 12/04/2015 A 12/17/2015 A 15B1300 Bids Submittal 12/17/2015 A 0B1310 Bids Evaluation (MDWASD/PSIP Team) 12/18/2015 A 01/29/2016 A 15B1320 Recommendation for Award Letter 01/29/2016 A 0B1330 Contract Award (Purchase Order Approval) 02/01/2016 A 03/07/2016 A 10

ConstrucConstruction 12/03/2015 A 07/26/2016 A 1112B1340 Construction Phase 12/03/2015 A 07/26/2016 A 1112B1342 MDWASD/PSIP Team Prepare for Pre-Construction meeting 02/01/2016 A 02/25/2016 A 15B1344 Pre-Construction Meeting 02/26/2016 A 02/26/2016 A 1B1346 WASD Issues NTP (PO to NTP) 03/08/2016 A 03/27/2016 A 53B1350 Construction NTP 03/28/2016 A 0B1380 Construction Operations 03/28/2016 A 06/03/2016 A 120B1382 Substantial Completion 06/03/2016 A 0

DesignerDesigner Construction Support Services 12/03/2015 A 07/26/2016 A 272B1480 Designer Construction Support Services 12/03/2015 A 07/26/2016 A 272

ConstrucConstruction Close Out 06/06/2016 A 06/24/2016 A 15B1390 Commissioning 06/06/2016 A 06/24/2016 A 15B1400 Punch List 06/06/2016 A 06/24/2016 A 10

Project CProject Closeout 06/06/2016 A 08/01/2018 737B1420 Closeout Phase 06/06/2016 A 08/01/2018 737B1450 Final Release of Retainage - Construction Contract 05/30/2017 A 0B1460 Administrative Closeout 06/06/2016 A 08/01/2018 30B1470 Project Closed 08/01/2018 0

Basin 0815Basin 0815 05/01/2014 A 08/01/2018 1541

100142 Ba100142 Basin 0815 Infiltration/Inflow Study and Repairs 09/25/2014 A 05/27/2015 A 542InfiltratioInfiltration/Inflow 09/25/2014 A 05/26/2015 A 193

B1000 Infiltration/Inflow Phase 09/25/2014 A 05/26/2015 A 193Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 05/26/2015 A 193

B1005 SSES Phase 09/25/2014 A 05/26/2015 A 193B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 04/22/2015 A 05/15/2015 A 30B1040 Video Review 05/12/2015 A 05/26/2015 A 30

Project CProject Closeout 05/27/2015 A 05/27/2015 A 0B1235 Closeout Phase 05/27/2015 A 05/27/2015 A 0B1260 Project Closed 05/27/2015 A 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

90% PWWMD Permit Review (Force Main)90% CD PM Comments Evaluation Completed

10/16/2015 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed

03/07/2016 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid ConferenceBidders Prepare Bids for SubmittalBids Submittal

Bids Evaluation (MDWASD/PSIP Team)Recommendation for Award Letter

Contract Award (Purchase Order Approval)07/26/2016 A, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction meeting

Pre-Construction MeetingWASD Issues NTP (PO to NTP)

Construction NTPConstruction OperationsSubstantial Completion07/26/2016 A, Designer Construction Support Services

Designer Construction Support Services06/24/2016 A, Construction Close Out

CommissioningPunch List

08/01/2018, Project Closeout

Closeout PhaseFinal Release of Retainage - Construction Contract

Administrative CloseoutProject Closed08/01/2018, Basin 0815

05/27/2015 A, 100142 Basin 0815 Infiltration/Inflow Study and Repairs05/26/2015 A, Infiltration/Inflow

Infiltration/Inflow Phase05/26/2015 A, Sanitary Sewer Evaluation SurveySSES Phase

Issue NTP to SSES ContractorConduct SSESVideo Review05/27/2015 A, Project CloseoutCloseout Phase

Project Closed

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 128 of 161 TASK filter: All Activities© Oracle Corporation

Page 129: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

100143 Pu100143 Pump Station 0815 Upgrade 05/01/2014 A 08/01/2018 1541PlanningPlanning 05/01/2014 A 01/09/2017 A 19

B0900 Planning Phase 05/01/2014 A 01/09/2017 A 19B0940 Develop Remedial Action Plan (RAP) 05/01/2014 A 05/19/2014 A 7B0950 Develop Preliminary Engineering Report (PER) 05/22/2014 A 01/04/2016 A 10B0960 Recommended Action Memo (RAM) 02/03/2016 A 01/09/2017 A 10

Project CProject Closeout 02/15/2017 A 08/01/2018 532B1445 Closeout Phase 02/15/2017 A 08/01/2018 532B1450 Issue SAC Letter 02/15/2017 A 0B1480 Administrative Closeout 02/16/2017 A 08/01/2018 30B1490 Project Closed 08/01/2018 0

Basin 0819Basin 0819 08/11/2014 A 08/01/2018 1458

100145 Pu100145 Pump Station 0819 Upgrade 08/11/2014 A 08/01/2018 1458DesignDesign 08/11/2014 A 02/09/2016 A 438

B1000 Design Phase 08/11/2014 A 02/09/2016 A 438B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 08/11/2014 A 08/15/2014 A 5B1020 Engage Design Consultant 08/15/2014 A 01/07/2015 A 35B1022 TA Rev 00 - Approval Process 11/24/2014 A 12/30/2014 A 20B1024 TA Rev 01 - Approval Process 05/19/2015 A 05/27/2015 A 20B1026 TA Rev 02 - Approval Process 12/09/2015 A 01/20/2016 A 20B1030 Issue Design NTP 01/07/2015 A 0B1040 A/E Develops and Submits Final Engineering Report 01/07/2015 A 01/21/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 01/07/2015 A 07/01/2015 A 10

30% Des30% Design 01/08/2015 A 03/12/2015 A 48B1060 A/E Prepares 30% Construction Documents 01/08/2015 A 02/20/2015 A 30B1070 Geotechnical Engineering Services 01/08/2015 A 02/20/2015 A 20B1080 Surveying Services 01/08/2015 A 02/20/2015 A 15B1100 30% CDs Submittal 02/20/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 02/20/2015 A 03/12/2015 A 10

60% Des60% Design 02/20/2015 A 04/29/2015 A 42B1130 A/E Prepares 60% Construction Documents 02/20/2015 A 04/10/2015 A 30B1140 60% CDs Submittal 04/10/2015 A 0B1160 60% Review (MDWASD/PSIP Team) 04/13/2015 A 04/29/2015 A 10

90% Des90% Design 04/14/2015 A 01/20/2016 A 309B1170 A/E Prepares 90% Construction Documents 04/14/2015 A 06/15/2015 A 20B1180 90% CDs Submittal 06/15/2015 A 0B1190 90% Review (MDWASD/PSIP Team) 06/16/2015 A 10/19/2015 A 15B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 10/20/2015 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 10/21/2015 A 11/10/2015 A 15B1220 90% RER (Building Dept) Permit Submittal 11/25/2015 A 0B1230 90% RER (Building Dept) Permit Review 11/26/2015 A 01/19/2016 A 15B1260 90% CD PM Comments Evaluation Completed 01/20/2016 A 0

100% De100% Design 01/22/2016 A 02/09/2016 A 24B1270 A/E Prepares 100% Construction Documents 01/22/2016 A 02/09/2016 A 10B1280 100% CDs Submittal 02/09/2016 A 0B1290 100% Review (MDWASD/PSIP Team) 02/09/2016 A 02/09/2016 A 1B1300 Design Completed 02/09/2016 A 0

MDWASDMDWASD Procurement 02/09/2016 A 04/25/2016 A 125B1305 Procurement Phase 02/09/2016 A 04/25/2016 A 125

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

08/01/2018, 100143 Pump Station 0815 Upgrade01/09/2017 A, PlanningPlanning Phase

Develop Remedial Action Plan (RAP)Develop Preliminary Engineering Report (PER)

Recommended Action Memo (RAM)08/01/2018, Project CloseoutCloseout Phase

Issue SAC LetterAdministrative Closeout

Project Closed08/01/2018, Basin 0819

08/01/2018, 100145 Pump Station 0819 Upgrade02/09/2016 A, Design

Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book

Engage Design ConsultantTA Rev 00 - Approval Process

TA Rev 01 - Approval ProcessTA Rev 02 - Approval Process

Issue Design NTPA/E Develops and Submits Final Engineering Report

Final Engineering Report Review & Approval (MDWASD/PSIP Team)03/12/2015 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services

30% CDs Submittal30% Review (MDWASD/PSIP Team)04/29/2015 A, 60% Design

A/E Prepares 60% Construction Documents60% CDs Submittal

60% Review (MDWASD/PSIP Team)01/20/2016 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)90% RER(DERM)FDEP Permit Review (Pump Station)90% RER (Building Dept) Permit Submittal

90% RER (Building Dept) Permit Review90% CD PM Comments Evaluation Completed

02/09/2016 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed

04/25/2016 A, MDWASD Procurement

Procurement Phase

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 129 of 161 TASK filter: All Activities© Oracle Corporation

Page 130: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1310 Submit CDs to MDWASD Procurement Division 02/09/2016 A 0B1312 Bid Notice Preparation Period 02/09/2016 A 02/17/2016 A 23B1314 Bid Notice 02/17/2016 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 02/18/2016 A 02/22/2016 A 10B1320 Pre-Bid Conference 02/23/2016 A 02/23/2016 A 1B1328 Bidders Prepare Bids for Submittal 02/24/2016 A 03/28/2016 A 15B1330 Bids Submittal 03/28/2016 A 0B1340 MDWASD/PSIP Team Bids Evaluation 03/29/2016 A 04/01/2016 A 15B1350 Recommendation for Award Letter 04/01/2016 A 0B1355 Contract Award (Purchase Order Approval) 04/04/2016 A 04/25/2016 A 10

ConstrucConstruction 02/23/2016 A 10/26/2017 A 999B1360 Construction Phase 02/23/2016 A 10/26/2017 A 999B1362 MDWASD/PSIP Team Prepare for Pre-Construction meeting 04/04/2016 A 04/21/2016 A 15B1364 Pre-Construction Meeting 04/22/2016 A 04/22/2016 A 1B1369 WASD Issues NTP (PO to NTP) 04/26/2016 A 06/19/2016 A 53B1370 Construction NTP 06/20/2016 A 0B1400 Construction Operations 06/20/2016 A 10/26/2017 A 150B1400 Original Construction Duration 06/20/2016 A 11/17/2016 A 150B1400 Change Order #1 - Miami Dade Bldg. Dept. Re-Permitting 11/18/2016 A 02/11/2017 A 150B1400 Change Order #2 - WASD Shut Down FM & FPL 02/12/2017 A 04/20/2017 A 150B1400 Change Order #3 - Hurricane Irma 04/21/2017 A 05/11/2017 A 150B1402 Substantial Completion 10/26/2017 A 0

DesignerDesigner Construction Support Services 02/23/2016 A 10/26/2017 A 291B1410 Designer Construction Support Services 02/23/2016 A 10/26/2017 A 291

Project CProject Closeout 10/27/2017 A 08/01/2018 273B1445 Closeout Phase 10/27/2017 A 08/01/2018 273B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 10/27/2017 A 08/01/2018 120B1490 Project Closed 08/01/2018 0

100250 Ba100250 Basin 0819 Infiltration/Inflow Study and Repairs 05/22/2015 A 10/13/2015 A 29InfiltratioInfiltration/Inflow 05/22/2015 A 10/12/2015 A 20

B1000 Infiltration/Inflow Phase 05/22/2015 A 10/12/2015 A 20CIPP RepCIPP Repairs 05/22/2015 A 10/12/2015 A 20

B1070 CIPP Phase 05/22/2015 A 10/12/2015 A 20B1090 Issue NTP for CIPP Repairs 05/22/2015 A 0B1100 Conduct CIPP Repairs 10/12/2015 A 10/12/2015 A 20

Project CProject Closeout 10/13/2015 A 10/13/2015 A 0B1250 Closeout Phase 10/13/2015 A 10/13/2015 A 0B1280 Project Closed 10/13/2015 A 0

Basin 0836Basin 0836 10/02/2015 A 08/01/2018 1035

100146 Pu100146 Pump Station 0836 Upgrade 10/02/2015 A 08/01/2018 1035DesignDesign 10/02/2015 A 11/11/2016 A 458

B1000 Design Phase 10/02/2015 A 11/11/2016 A 458B1010 Prepare & Submit Design Package 10/02/2015 A 11/04/2015 A 5B1020 Engage Design Consultant 11/05/2015 A 12/04/2015 A 20B1022 TA Preparation 12/07/2015 A 12/07/2015 A 1B1024 TA Approval Process 12/08/2015 A 12/18/2015 A 20B1030 Issue Design NTP 01/06/2016 A 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Submit CDs to MDWASD Procurement DivisionBid Notice Preparation Period

Bid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter

Contract Award (Purchase Order Approval)10/26/2017 A, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction meetingPre-Construction Meeting

WASD Issues NTP (PO to NTP)

Construction NTPConstruction Operations

Original Construction DurationChange Order #1 - Miami Dade Bldg. Dept. Re-Permitting

Change Order #2 - WASD Shut Down FM & FPLChange Order #3 - Hurricane Irma

Substantial Completion10/26/2017 A, Designer Construction Support Services

Designer Construction Support Services08/01/2018, Project Closeout

Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction ContractAdministrative CloseoutProject Closed

10/13/2015 A, 100250 Basin 0819 Infiltration/Inflow Study and Repairs10/12/2015 A, Infiltration/Inflow

Infiltration/Inflow Phase10/12/2015 A, CIPP Repairs

CIPP PhaseIssue NTP for CIPP Repairs

Conduct CIPP Repairs10/13/2015 A, Project Closeout

Closeout PhaseProject Closed

08/01/2018, Basin 0836

08/01/2018, 100146 Pump Station 0836 Upgrade11/11/2016 A, Design

Design PhasePrepare & Submit Design Package

Engage Design ConsultantTA PreparationTA Approval Process

Issue Design NTP

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 130 of 161 TASK filter: All Activities© Oracle Corporation

Page 131: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1040 A/E Develops and Submits Final Engineering Report 01/06/2016 A 11/11/2016 A 110B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 01/06/2016 A 06/23/2016 A 85

30% Des30% Design 01/06/2016 A 04/08/2016 A 66B1060 A/E Prepares 30% Construction Documents 01/06/2016 A 03/25/2016 A 30B1080 Surveying Services 01/06/2016 A 02/11/2016 A 15B1100 30% CDs Submittal 03/25/2016 A 0B1120 30% Review (MDWASD/PSIP Team) 03/28/2016 A 04/08/2016 A 10

90% Des90% Design 03/28/2016 A 10/26/2016 A 138B1170 A/E Prepares 90% Construction Documents 03/28/2016 A 06/14/2016 A 20B1180 90% CDs Submittal 06/14/2016 A 0B1190 90% Review (MDWASD/PSIP Team) 06/15/2016 A 07/14/2016 A 15B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 07/15/2016 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 07/15/2016 A 09/30/2016 A 15B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 10/18/2016 A 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 10/18/2016 A 10/26/2016 A 15B1260 90% CD PM Comments Evaluation Completed 10/26/2016 A 0

100% De100% Design 10/27/2016 A 11/09/2016 A 32B1270 A/E Prepares 100% Construction Documents 10/27/2016 A 11/09/2016 A 10B1280 100% CDs Submittal 11/09/2016 A 0B1290 100% Review (MDWASD/PSIP Team) 10/27/2016 A 11/09/2016 A 10B1300 Design Completed 11/09/2016 A 0

MDWASDMDWASD Procurement 11/14/2016 A 04/06/2017 A 88B1305 Procurement Phase 11/14/2016 A 04/06/2017 A 88B1310 Submit CDs to MDWASD Procurement Division 11/14/2016 A 0B1312 Bid Notice Preparation Period 11/15/2016 A 11/29/2016 A 11B1314 Bid Notice 11/29/2016 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 11/30/2016 A 12/13/2016 A 10B1320 Pre-Bid Conference 12/14/2016 A 12/14/2016 A 1B1322 Bidders Prepare Bids for Submittal 12/15/2016 A 01/12/2017 A 21B1330 Bids Submittal 01/12/2017 A 0B1340 MDWASD/PSIP Team Bids Evaluation 01/13/2017 A 01/31/2017 A 15B1350 Recommendation for Award Letter 01/31/2017 A 0B1355 Contract Award (Purchase Order Approval) 02/01/2017 A 04/06/2017 A 10

ConstrucConstruction 12/14/2016 A 12/27/2017 A 375B1360 Construction Phase 12/14/2016 A 12/27/2017 A 375B1364 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 02/01/2017 A 03/14/2017 A 15B1366 Pre-Construction Meeting 03/15/2017 A 03/15/2017 A 1B1368 WASD Issues NTP (Pre-Const to NTP) 03/16/2017 A 07/21/2017 A 91B1369 WASD Issues NTP (PO to NTP) 04/06/2017 A 07/21/2017 A 91B1370 Construction NTP 07/24/2017 A 0B1400 Construction Operations 07/24/2017 A 12/27/2017 A 153B1402 Substantial Completion 12/27/2017 A 0

DesignerDesigner Construction Support Services 12/14/2016 A 12/26/2017 A 262B1410 Designer Construction Support Services 12/14/2016 A 12/26/2017 A 262

Project CProject Closeout 12/28/2017 A 08/01/2018 202B1445 Closeout Phase 12/28/2017 A 08/01/2018 202B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 12/28/2017 A 08/01/2018 120

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

04/08/2016 A, 30% Design

A/E Prepares 30% Construction DocumentsSurveying Services

30% CDs Submittal30% Review (MDWASD/PSIP Team)

10/26/2016 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)

90% RER(DERM)FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)90% RER(Building Dept) Permit Review (Pump Station)90% CD PM Comments Evaluation Completed11/09/2016 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal

100% Review (MDWASD/PSIP Team)Design Completed

04/06/2017 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter

Contract Award (Purchase Order Approval)12/27/2017 A, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Construction NTPConstruction OperationsSubstantial Completion

12/26/2017 A, Designer Construction Support Services

Designer Construction Support Services08/01/2018, Project Closeout

Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction ContractAdministrative Closeout

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 131 of 161 TASK filter: All Activities© Oracle Corporation

Page 132: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1490 Project Closed 08/01/2018 0

Basin 0840Basin 0840 05/04/2016 A 11/29/2018 929

100147 Pu100147 Pump Station 0840 (AM) Upgrade 05/04/2016 A 11/29/2018 929DesignDesign 05/04/2016 A 12/18/2017 A 601

B1000 Design Phase 05/04/2016 A 12/18/2017 A 601B1010 Prepare and Submit Design Package 05/04/2016 A 05/04/2016 A 5B1020 Engage Design Consultant 05/04/2016 A 06/28/2016 A 20B1022 TA Preparation 06/29/2016 A 07/14/2016 A 1B1024 TA Approval Process 07/15/2016 A 09/21/2016 A 20B1030 Issue Design NTP 09/27/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 09/27/2016 A 11/22/2017 A 103

30% Des30% Design 09/27/2016 A 01/19/2017 A 121B1060 A/E Prepares 30% Construction Documents 09/27/2016 A 12/20/2016 A 50B1100 30% CDs Submittal 12/20/2016 A 0B1120 30% Review (MDWASD/PSIP Team) 12/21/2016 A 01/19/2017 A 30

90% Des90% Design 12/21/2016 A 11/22/2017 A 364B1170 A/E Prepares 90% Construction Documents 12/21/2016 A 05/01/2017 A 62B1180 90% CDs Submittal 05/01/2017 A 0B1190 90% Review (MDWASD/PSIP Team) 05/02/2017 A 05/22/2017 A 30B1191 PSIP Prepared Memorandum with Recommendation for WASD 03/29/2017 A 04/16/2017 A 60B1192 TA Rev 1 Preparation 04/17/2017 A 04/17/2017 A 1B1193 TA Rev 1 Approval Process 04/18/2017 A 05/31/2017 A 40B1200 90% RER(DERM)/FDEP Permit Submittal (Force Main) 07/17/2017 A 0B1210 90% RER(DERM)/FDEP Permit Review (Force Main) 07/17/2017 A 11/22/2017 A 45B1260 90% CD PM Comments Evaluation Completed 11/22/2017 A 0B1262 MDWASD Union Concurrence Process 06/28/2017 A 07/17/2017 A 30

100% De100% Design 11/23/2017 A 12/18/2017 A 24B1270 A/E Prepares 100% Construction Documents 11/23/2017 A 12/18/2017 A 14B1280 100% CDs Submittal 12/18/2017 A 0B1290 100% Review (MDWASD/PSIP Team) 12/18/2017 A 12/18/2017 A 14B1300 Design Completed 12/18/2017 A 0

MDWASDMDWASD Procurement 12/19/2017 A 05/15/2018 A 96B1305 Procurement Phase 12/19/2017 A 05/15/2018 A 96B1310 Submit CDs to MDWASD Procurement Division 12/19/2017 A 0B1312 Bid Notice Preparation Period 12/20/2017 A 01/18/2018 A 33B1314 Bid Notice 01/18/2018 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conferencce 01/19/2018 A 01/29/2018 A 14B1320 Pre-Bid Conference 01/30/2018 A 01/30/2018 A 1B1324 Bidders Prepare Bids for Submittal 01/31/2018 A 03/02/2018 A 21B1330 Bids Submittal 03/02/2018 A 0B1340 MDWASD/PSIP Team Bids Evaluation 03/03/2018 A 03/29/2018 A 21B1350 Recommendation for Award Letter 03/29/2018 A 0B1355 Contract Award (Purchase Order Approval) 03/30/2018 A 05/15/2018 A 14

ConstrucConstruction 01/30/2018 A 08/02/2018 317B1360 Construction Phase 01/30/2018 A 08/02/2018 317B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 03/30/2018 A 05/09/2018 A 33B1365 Pre-Construction Meeting 05/10/2018 A 05/10/2018 A 1B1366 WASD Issues NTP (Pre-Const to NTP) 05/11/2018 A 08/01/2018 38B1369 WASD Issues NTP (PO to NTP) 05/15/2018 A 08/01/2018 53

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Project Closed11/29/2018, Basin 0840

11/29/2018, 100147 Pump Station 0840 (AM) Upgr12/18/2017 A, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval ProcessIssue Design NTP

Final Engineering Report Review & Approval (MDWASD/PSIP Team)01/19/2017 A, 30% Design

A/E Prepares 30% Construction Documents30% CDs Submittal

30% Review (MDWASD/PSIP Team)11/22/2017 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)PSIP Prepared Memorandum with Recommendation for WASD ApprovalTA Rev 1 Preparation

TA Rev 1 Approval Process

90% RER(DERM)/FDEP Permit Submittal (Force Main)90% RER(DERM)/FDEP Permit Review (Force Main)

90% CD PM Comments Evaluation CompletedMDWASD Union Concurrence Process

12/18/2017 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal

100% Review (MDWASD/PSIP Team)Design Completed

05/15/2018 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferenccePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter

Contract Award (Purchase Order Approval)08/02/2018, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 132 of 161 TASK filter: All Activities© Oracle Corporation

Page 133: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1370 Construction NTP 08/02/2018 0B1400 Construction Operations 08/02/2018 08/02/2018 0B1402 Substantial Completion 08/02/2018 0

DesignerDesigner Construction Support Services 01/30/2018 A 08/01/2018 302B1410 Designer Construction Support Services 01/30/2018 A 08/01/2018 302

Project CProject Closeout 08/02/2018 11/29/2018 120B1445 Closeout Phase 08/02/2018 11/29/2018 120B1450 Issue SAC Letter 08/02/2018 0B1470 Final Release of Retainage - Construction Contract 08/02/2018 0B1480 Administrative Closeout 08/02/2018 11/29/2018 120B1490 Project Closed 11/29/2018 0

Basin 0842Basin 0842 04/02/2014 A 08/01/2018 1682

100149 Pu100149 Pump Station 0842 Upgrade 04/02/2014 A 08/01/2018 1682DesignDesign 04/02/2014 A 06/12/2015 A 411

B1000 Design Phase 04/02/2014 A 06/12/2015 A 411B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 04/02/2014 A 04/02/2014 A 5B1020 Engage Design Consultant 04/03/2014 A 11/19/2014 A 20B1030 Issue Design NTP 11/20/2014 A 0B1040 A/E Develops and Submits Final Engineering Report 11/20/2014 A 05/29/2015 A 20B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 11/20/2014 A 03/25/2015 A 5

30% Des30% Design 11/20/2014 A 01/23/2015 A 128B1060 A/E Prepares 30% Construction Documents 11/20/2014 A 01/14/2015 A 30B1070 Geotechnical Engineering Services 11/20/2014 A 12/16/2014 A 20B1080 Surveying Services 11/20/2014 A 12/17/2014 A 15B1090 30% CDs Submittal 01/14/2015 A 0B1100 30% Review (MDWASD/PSIP Team) 01/15/2015 A 01/23/2015 A 10

90% Des90% Design 01/15/2015 A 06/05/2015 A 86B1110 A/E Prepares 90% Construction Documents 01/15/2015 A 03/06/2015 A 20B1120 90% CDs Submittal 03/06/2015 A 0B1130 90% Review (MDWASD/PSIP Team) 03/09/2015 A 03/25/2015 A 15B1131 Permit Set Revisions 03/26/2015 A 04/10/2015 A 5B1140 90% RER(DERM)FDEP Permit Submittal (Pump Station) 04/13/2015 A 0B1150 90% RER(DERM)FDEP Permit Review (Pump Station) 04/13/2015 A 04/20/2015 A 15B1160 90% RER (Building Department) Permit Submittal 04/23/2015 A 0B1170 90% RER (Building Department) Permit Review 04/23/2015 A 06/05/2015 A 15B1200 90% CD PM Comments Evaluation Completed 06/05/2015 A 0

100% De100% Design 03/26/2015 A 06/12/2015 A 12B1210 A/E Prepares 100% Construction Documents 03/26/2015 A 04/10/2015 A 10B1220 100% CDs Submittal 04/10/2015 A 0B1230 100% Review (MDWASD/PSIP Team) 04/13/2015 A 04/24/2015 A 10B1240 Design Completed 06/12/2015 A 0

MDWASDMDWASD Procurement 05/01/2015 A 07/24/2015 A 64B1245 Procurement Phase 05/01/2015 A 07/24/2015 A 64B1250 Submit CDs to MDWASD Procurement Division 05/01/2015 A 0B1260 Pre-Bid Conference 05/15/2015 A 0B1270 Bids Submittal 06/19/2015 A 0B1280 MDWASD/PSIP Team Bids Evaluation 06/22/2015 A 06/23/2015 A 15B1290 Recommendation for Award Letter 06/23/2015 A 0B1295 Contract Award (Purchase Order Approval) 06/23/2015 A 07/24/2015 A 10

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Construction NTPConstruction OperationsSubstantial Completion08/01/2018, Designer Construction Support Services

Designer Construction Support Services11/29/2018, Project CloseoutCloseout Phase

Issue SAC LetterFinal Release of Retainage - Construction Contract

Administrative CloseoutProject Closed

08/01/2018, Basin 0842

08/01/2018, 100149 Pump Station 0842 Upgrade06/12/2015 A, Design

Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book

Engage Design ConsultantIssue Design NTP

A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

01/23/2015 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services

30% CDs Submittal30% Review (MDWASD/PSIP Team)

06/05/2015 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)Permit Set Revisions90% RER(DERM)FDEP Permit Submittal (Pump Station)90% RER(DERM)FDEP Permit Review (Pump Station)90% RER (Building Department) Permit Submittal

90% RER (Building Department) Permit Review90% CD PM Comments Evaluation Completed06/12/2015 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal

100% Review (MDWASD/PSIP Team)Design Completed

07/24/2015 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Pre-Bid ConferenceBids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter

Contract Award (Purchase Order Approval)

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 133 of 161 TASK filter: All Activities© Oracle Corporation

Page 134: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

ConstrucConstruction 05/15/2015 A 08/19/2016 A 1251B1300 Construction Phase 05/15/2015 A 08/19/2016 A 1251B1302 MDWASD / PSIP Team Prepare for Pre-Construction Meeting 06/24/2015 A 07/10/2015 A 15B1304 Pre-Construction Meeting 07/13/2015 A 07/13/2015 A 1B1306 Permits / Shop Drawings / Material Orders 07/14/2015 A 11/20/2015 A 15B1308 WASD Issues NTP (PO to NTP) 07/25/2015 A 08/02/2015 A 53B1310 Construction NTP 08/03/2015 A 0B1340 Construction Operations 08/03/2015 A 02/05/2016 A 107B1340 Original Construction Duration 08/03/2015 A 12/31/2015 A 107B1340 Change Order #1 - Utility Conflict Impeding Wet Well Installation 01/01/2016 A 01/21/2016 A 107B1342 Substantial Completion 02/05/2016 A 0

DesignerDesigner Construction Services 05/15/2015 A 08/19/2016 A 146B1350 Designer Construction Support Services 05/15/2015 A 08/19/2016 A 146

ConstrucConstruction Close Out 02/08/2016 A 07/21/2016 A 15B1360 Commissioning 02/08/2016 A 07/21/2016 A 15B1370 Punch List 02/08/2016 A 07/21/2016 A 10

Project CProject Closeout 09/23/2015 A 08/01/2018 1043B1385 Closeout Phase 09/23/2015 A 08/01/2018 1043B1390 Issue SAC Letter 09/23/2015 A 0B1392 Contracctor Prepare Remedial Action Plan - Property Encroachm 02/08/2016 A 07/21/2016 A 30B1420 Final Release of Retainage - Construction Contract 02/23/2017 A 0B1422 Administrative Closeout 02/08/2016 A 08/01/2018 120B1430 Project Closed 08/01/2018 0

100243 Ba100243 Basin 0842 Infiltration/Inflow Study and Repairs 05/22/2015 A 07/28/2015 A 29InfiltratioInfiltration/Inflow 05/22/2015 A 07/28/2015 A 29

B1000 Infiltration/Inflow Phase 05/22/2015 A 07/28/2015 A 29CIPP RepCIPP Repairs 05/22/2015 A 07/28/2015 A 29

B1070 CIPP Phase 05/22/2015 A 07/28/2015 A 29B1090 Issue NTP for CIPP Repairs 05/22/2015 A 0B1100 Conduct CIPP Repairs 07/28/2015 A 07/28/2015 A 29

Project CProject Closeout 07/28/2015 A 07/28/2015 A 0B1250 Closeout Phase 07/28/2015 A 07/28/2015 A 0B1280 Project Closed 07/28/2015 A 0

Basin 0843Basin 0843 01/14/2016 A 08/31/2018 942

100150 Pu100150 Pump Station 0843 Upgrade 01/14/2016 A 08/31/2018 942DesignDesign 01/14/2016 A 05/02/2017 A 487

B1000 Design Phase 01/14/2016 A 05/02/2017 A 487B1010 Prepare and Submit Design Package 01/14/2016 A 01/14/2016 A 5B1020 Engage Design Consultant 01/15/2016 A 04/22/2016 A 20B1022 TA Preparation 04/25/2016 A 04/25/2016 A 1B1024 TA Approval Process 04/26/2016 A 06/01/2016 A 20B1030 Issue Design NTP 06/07/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 06/07/2016 A 04/21/2017 A 85

30% Des30% Design 06/07/2016 A 09/29/2016 A 134B1060 A/E Prepares 30% Construction Documents 06/08/2016 A 08/17/2016 A 30B1070 Geotechnical Engineering Services 06/07/2016 A 08/17/2016 A 20B1080 Surveying Services 06/08/2016 A 08/17/2016 A 15B1100 30% CDs Submittal 08/18/2016 A 0B1120 30% Review (MDWASD/PSIP Team) 08/19/2016 A 09/29/2016 A 10

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

08/19/2016 A, Construction

Construction PhaseMDWASD / PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

Permits / Shop Drawings / Material OrdersWASD Issues NTP (PO to NTP)

Construction NTPConstruction Operations

Original Construction DurationChange Order #1 - Utility Conflict Impeding Wet Well Installation

Substantial Completion08/19/2016 A, Designer Construction Services

Designer Construction Support Services07/21/2016 A, Construction Close Out

CommissioningPunch List

08/01/2018, Project Closeout

Closeout PhaseIssue SAC Letter

Contracctor Prepare Remedial Action Plan - Property Encroachment

Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed

07/28/2015 A, 100243 Basin 0842 Infiltration/Inflow Study and Repairs07/28/2015 A, Infiltration/InflowInfiltration/Inflow Phase07/28/2015 A, CIPP Repairs

CIPP PhaseIssue NTP for CIPP Repairs

Conduct CIPP Repairs07/28/2015 A, Project Closeout

Closeout PhaseProject Closed

08/31/2018, Basin 0843

08/31/2018, 100150 Pump Station 0843 Upgrade05/02/2017 A, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval ProcessIssue Design NTP

Final Engineering Report Review & Approval (MDWASD/PSIP Team)09/29/2016 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services

30% CDs Submittal30% Review (MDWASD/PSIP Team)

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 134 of 161 TASK filter: All Activities© Oracle Corporation

Page 135: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

60% Des60% Design 09/30/2016 A 11/08/2016 A 34B1130 A/E Prepares 60% Construction Documents 09/30/2016 A 10/21/2016 A 20B1140 60% CDs Submittal 10/21/2016 A 0B1160 60% Review (MDWASD/PSIP Team) 10/24/2016 A 11/08/2016 A 10

90% Des90% Design 10/24/2016 A 04/21/2017 A 214B1170 A/E Prepares 90% Construction Documents 10/24/2016 A 11/30/2016 A 20B1180 90% CDs Submittal 11/30/2016 A 0B1190 90% Review (MDWASD/PSIP Team) 12/01/2016 A 12/23/2016 A 15B1200 90% RER(DERM)FDEP Permit Submittal 01/31/2017 A 0B1210 90% RER(DERM)FDEP Permit Review 01/31/2017 A 04/07/2017 A 45B1220 90% RER(Building Dept) Permit Submittal 04/12/2017 A 0B1230 90% RER(Building Dept) Permit Review 04/12/2017 A 04/21/2017 A 21B1260 90% CD PM Comments Evaluation Completed 04/21/2017 A 0B1262 MDWASD Union Concurrence Process 01/27/2017 A 03/07/2017 A 30

100% De100% Design 04/24/2017 A 05/02/2017 A 30B1270 A/E Prepares 100% Construction Documents 04/24/2017 A 05/01/2017 A 10B1280 100% CDs Submittal 05/01/2017 A 0B1290 100% Review (MDWASD/PSIP Team) 05/02/2017 A 05/02/2017 A 1B1300 Design Completed 05/02/2017 A 0

MDWASDMDWASD Procurement 05/02/2017 A 08/24/2017 A 55B1305 Procurement Phase 05/02/2017 A 08/24/2017 A 55B1310 Submit CDs to MDWASD Procurement Division 05/02/2017 A 0B1312 Bid Notice Preparation Period 05/03/2017 A 05/11/2017 A 23B1314 Bid Notice 05/11/2017 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 05/12/2017 A 05/22/2017 A 10B1320 Pre-Bid Conference 05/23/2017 A 05/23/2017 A 1B1322 Bidders Prepare Bids for Submittal 05/24/2017 A 06/23/2017 A 15B1330 Bids Submittal 06/23/2017 A 0B1340 MDWASD/PSIP Team Bids Evaluation 06/26/2017 A 07/17/2017 A 15B1350 Recommendation for Award Letter 07/17/2017 A 0B1355 Contract Award (Purchase Order Approval) 07/18/2017 A 08/24/2017 A 10

ConstrucConstruction 05/23/2017 A 08/01/2018 426B1360 Construction Phase 05/23/2017 A 08/01/2018 426B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 07/18/2017 A 10/10/2017 A 15B1364 Pre-Construction Meeting 10/11/2017 A 10/11/2017 A 1B1366 WASD Issues NTP (Pre-Const to NTP) 10/12/2017 A 01/01/2018 A 45B1368 WASD Issues NTP (PO to NTP) 08/24/2017 A 01/01/2018 A 45B1370 Construction NTP 01/02/2018 A 0B1400 Construction Operations 01/02/2018 A 08/01/2018 190B1402 Substantial Completion 08/01/2018 0

DesignerDesigner Construction Support Services 05/23/2017 A 08/01/2018 260B1410 Designer Construction Support Services 05/23/2017 A 08/01/2018 260

Project CProject Closeout 08/01/2018 08/31/2018 31B1445 Closeout Phase 08/01/2018 08/31/2018 31B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 08/02/2018 08/31/2018 30B1490 Project Closed 08/31/2018 0

Basin 0853Basin 0853 03/19/2014 A 08/01/2018 1581

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

11/08/2016 A, 60% Design

A/E Prepares 60% Construction Documents60% CDs Submittal60% Review (MDWASD/PSIP Team)

04/21/2017 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal

90% RER(DERM)FDEP Permit Review90% RER(Building Dept) Permit Submittal90% RER(Building Dept) Permit Review90% CD PM Comments Evaluation Completed

MDWASD Union Concurrence Process05/02/2017 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal

100% Review (MDWASD/PSIP Team)Design Completed

08/24/2017 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid Notice

MDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter

Contract Award (Purchase Order Approval)08/01/2018, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Construction NTPConstruction OperationsSubstantial Completion08/01/2018, Designer Construction Support Services

Designer Construction Support Services08/31/2018, Project Closeout

Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction Contract

Administrative CloseoutProject Closed

08/01/2018, Basin 0853

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 135 of 161 TASK filter: All Activities© Oracle Corporation

Page 136: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

100151 Ba100151 Basin 0853 Infiltration/Inflow Study and Repairs 06/26/2015 A 11/25/2015 A 240InfiltratioInfiltration/Inflow 06/26/2015 A 11/24/2015 A 30

B1000 Infiltration/Inflow Phase 06/26/2015 A 11/24/2015 A 30Dig & ReDig & Replace Repairs 06/26/2015 A 11/24/2015 A 30

B1165 Dig & Replace Phase 06/26/2015 A 11/24/2015 A 30B1180 Issue NTP for Dig & Replace Repairs 06/26/2015 A 0B1190 Conduct Dig & Replace Repairs 11/24/2015 A 11/24/2015 A 30

Project CProject Closeout 11/25/2015 A 11/25/2015 A 0B1235 Closeout Phase 11/25/2015 A 11/25/2015 A 0B1260 Project Closed 11/25/2015 A 0

100152 Pu100152 Pump Station 0853 Upgrade 03/19/2014 A 08/01/2018 792DesignDesign 03/19/2014 A 12/04/2017 A 63

B1000 Design Phase 03/19/2014 A 12/04/2017 A 63B1012 RAP - Remedial Action Plan 03/19/2014 A 05/20/2014 A 63B1014 SAC Period 05/21/2014 A 12/04/2017 A 63

Project CProject Closeout 12/06/2017 A 08/01/2018 792B1445 Closeout Phase 12/06/2017 A 08/01/2018 792B1450 Issue SAC Letter 12/29/2017 A 0B1480 Administrative Closeout 12/06/2017 A 08/01/2018 120B1490 Project Closed 08/01/2018 0

Basin 0860Basin 0860 09/25/2014 A 08/01/2018 1535

100153 Ba100153 Basin 0860 Infiltration/Inflow Study and Repairs 09/25/2014 A 04/22/2016 A 632InfiltratioInfiltration/Inflow 09/25/2014 A 04/21/2016 A 624

B1000 Infiltration/Inflow Phase 09/25/2014 A 04/21/2016 A 624Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 07/16/2015 A 282

B1005 SSES Phase 09/25/2014 A 07/16/2015 A 282B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 06/17/2015 A 07/16/2015 A 30

ManholeManhole Repairs 03/25/2016 A 04/21/2016 A 112B1115 Manhole Phase 03/25/2016 A 04/21/2016 A 112B1130 Issue NTP for Manhole Repairs 03/25/2016 A 0B1140 Conduct Manhole Repairs 04/13/2016 A 04/21/2016 A 20

Project CProject Closeout 04/22/2016 A 04/22/2016 A 0B1235 Closeout Phase 04/22/2016 A 04/22/2016 A 0B1260 Project Closed 04/22/2016 A 0

100154 Pu100154 Pump Station 0860 Upgrade 12/08/2014 A 08/01/2018 1458DesignDesign 12/08/2014 A 02/09/2016 A 456

B1000 Design Phase 12/08/2014 A 02/09/2016 A 456B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 12/08/2014 A 12/19/2014 A 5B1020 Engage Design Consultant 12/22/2014 A 03/24/2015 A 20B1030 Issue Design NTP 03/24/2015 A 0B1040 A/E Develops and Submits Final Engineering Report 03/24/2015 A 02/02/2016 A 125B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 03/24/2015 A 12/21/2015 A 10

30% Des30% Design 03/25/2015 A 06/15/2015 A 87B1060 A/E Prepares 30% Construction Documents 03/25/2015 A 06/08/2015 A 30B1070 Geotechnical Engineering Services 03/25/2015 A 06/08/2015 A 20B1080 Surveying Services 03/25/2015 A 06/08/2015 A 15B1100 30% CDs Submittal 06/08/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 06/09/2015 A 06/15/2015 A 10

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

11/25/2015 A, 100151 Basin 0853 Infiltration/Inflow Study and Repairs11/24/2015 A, Infiltration/Inflow

Infiltration/Inflow Phase11/24/2015 A, Dig & Replace RepairsDig & Replace Phase

Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs11/25/2015 A, Project CloseoutCloseout Phase

Project Closed08/01/2018, 100152 Pump Station 0853 Upgrade

12/04/2017 A, Design

Design PhaseRAP - Remedial Action Plan

SAC Period08/01/2018, Project CloseoutCloseout Phase

Issue SAC LetterAdministrative CloseoutProject Closed08/01/2018, Basin 0860

04/22/2016 A, 100153 Basin 0860 Infiltration/Inflow Study and Repairs04/21/2016 A, Infiltration/Inflow

Infiltration/Inflow Phase07/16/2015 A, Sanitary Sewer Evaluation SurveySSES Phase

Issue NTP to SSES ContractorConduct SSES

04/21/2016 A, Manhole RepairsManhole Phase

Issue NTP for Manhole RepairsConduct Manhole Repairs04/22/2016 A, Project CloseoutCloseout Phase

Project Closed08/01/2018, 100154 Pump Station 0860 Upgrade

02/09/2016 A, Design

Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book

Engage Design ConsultantIssue Design NTP

A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

06/15/2015 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal30% Review (MDWASD/PSIP Team)

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 136 of 161 TASK filter: All Activities© Oracle Corporation

Page 137: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

90% Des90% Design 06/09/2015 A 02/02/2016 A 253B1170 A/E Prepares 90% Construction Documents 06/09/2015 A 09/24/2015 A 20B1180 90% CDs Submittal 09/25/2015 A 0B1190 90% Review (MDWASD/PSIP Team) 09/28/2015 A 12/21/2015 A 15B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 12/22/2015 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 12/23/2015 A 01/07/2016 A 15B1220 90% RER (Building Dept) Permit Submittal 01/08/2016 A 0B1230 90% RER (Building Dept) Permit Review 01/08/2016 A 02/02/2016 A 15B1260 90% CD PM Comments Evaluation Completed 02/02/2016 A 0

100% De100% Design 02/03/2016 A 02/09/2016 A 28B1270 A/E Prepares 100% Construction Documents 02/03/2016 A 02/05/2016 A 10B1280 100% CDs Submittal 02/05/2016 A 0B1290 100% Review (MDWASD/PSIP Team) 02/08/2016 A 02/09/2016 A 10B1300 Design Completed 02/09/2016 A 0

MDWASDMDWASD Procurement 02/10/2016 A 06/21/2016 A 111B1305 Procurement Phase 02/10/2016 A 06/21/2016 A 111B1310 Submit CDs to MDWASD Procurement Division 02/10/2016 A 0B1312 Bid Notice Preparation Period 02/11/2016 A 03/11/2016 A 23B1314 Bid Notice 03/11/2016 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 03/14/2016 A 03/22/2016 A 10B1320 Pre-Bid Conference 03/22/2016 A 03/22/2016 A 1B1328 Bidders Prepare Bids for Submittal 03/23/2016 A 04/08/2016 A 15B1330 Bids Submittal 04/11/2016 A 0B1340 MDWASD/PSIP Team Bids Evaluation 04/12/2016 A 04/22/2016 A 15B1350 Recommendation for Award Letter 04/22/2016 A 0B1355 Contract Award (Purchase Order Approval) 04/25/2016 A 06/21/2016 A 10

ConstrucConstruction 03/22/2016 A 07/11/2017 A 995B1360 Construction Phase 03/22/2016 A 07/11/2017 A 995B1362 MDWASD/PSIP Team Prepare for Pre-Construction meeting 04/25/2016 A 05/04/2016 A 15B1364 Pre-Construction Meeting 05/05/2016 A 05/05/2016 A 1B1369 WASD Issues NTP (PO to NTP) 06/22/2016 A 08/21/2016 A 53B1370 Construction NTP 08/22/2016 A 0B1400 Construction Operations 08/22/2016 A 07/11/2017 A 120B1400 Original Construction Duration 08/22/2016 A 12/20/2016 A 120B1400 Change Order #1 - Bid Plans Error Relocating FPL Equipment 12/21/2016 A 04/19/2017 A 120B1400 Change Order #2 - Use of Commercial Diving Company 04/20/2017 A 05/03/2017 A 120B1400 Change Order #3 - Unforeseen FPL Utility 05/04/2017 A 05/08/2017 A 120B1400 Change Order #4 - Inoperable Pump Station Plug Valve 05/09/2017 A 05/29/2017 A 120B1400 Change Order #5 - FPL 05/30/2017 A 07/02/2017 A 120B1400 Change Order #6 - Unforeseen Weather Condition 07/03/2017 A 07/09/2017 A 120B1402 Substantial Completion 07/11/2017 A 0

DesignerDesigner Construction Support Services 03/22/2016 A 07/11/2017 A 275B1410 Designer Construction Support Services 03/22/2016 A 07/11/2017 A 275

Project CProject Closeout 07/12/2017 A 08/01/2018 366B1445 Closeout Phase 07/12/2017 A 08/01/2018 366B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 07/12/2017 A 08/01/2018 120B1490 Project Closed 08/01/2018 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

02/02/2016 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)90% RER(DERM)FDEP Permit Review (Pump Station)

90% RER (Building Dept) Permit Submittal90% RER (Building Dept) Permit Review

90% CD PM Comments Evaluation Completed02/09/2016 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal

100% Review (MDWASD/PSIP Team)Design Completed

06/21/2016 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)

07/11/2017 A, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction meetingPre-Construction Meeting

WASD Issues NTP (PO to NTP)

Construction NTPConstruction Operations

Original Construction DurationChange Order #1 - Bid Plans Error Relocating FPL EquipmentChange Order #2 - Use of Commercial Diving CompanyChange Order #3 - Unforeseen FPL Utility

Change Order #4 - Inoperable Pump Station Plug ValveChange Order #5 - FPLChange Order #6 - Unforeseen Weather Condition

Substantial Completion07/11/2017 A, Designer Construction Support Services

Designer Construction Support Services08/01/2018, Project Closeout

Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction ContractAdministrative CloseoutProject Closed

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 137 of 161 TASK filter: All Activities© Oracle Corporation

Page 138: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

Basin 0870Basin 0870 07/06/2015 A 10/24/2018 1178

100155 Pu100155 Pump Station 0870 Upgrade 07/06/2015 A 10/24/2018 1178DesignDesign 07/06/2015 A 02/22/2017 A 555

B1000 Design Phase 07/06/2015 A 02/22/2017 A 555B1010 Prepare and Submit Design Package 07/06/2015 A 07/06/2015 A 5B1020 Engage Design Consultant 07/06/2015 A 09/21/2015 A 20B1022 TA Preparation 09/22/2015 A 09/22/2015 A 1B1024 TA Approval Process 09/23/2015 A 10/27/2015 A 20B1030 Issue Design NTP 10/30/2015 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/30/2015 A 08/25/2016 A 110

30% Des30% Design 10/30/2015 A 01/04/2016 A 52B1060 A/E Prepares 30% Construction Documents 10/30/2015 A 12/21/2015 A 30B1070 Geotechnical Engineering Services 10/30/2015 A 12/21/2015 A 29B1080 Surveying Services 10/30/2015 A 12/21/2015 A 18B1100 30% CDs Submittal 12/21/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 12/22/2015 A 01/04/2016 A 10

60% Des60% Design 12/22/2015 A 03/30/2016 A 105B1130 A/E Prepares 60% Construction Documents 12/22/2015 A 03/04/2016 A 20B1140 60% CDs Submittal 03/04/2016 A 0B1160 60% Review (MDWASD/PSIP Team) 03/07/2016 A 03/30/2016 A 10

90% Des90% Design 03/07/2016 A 02/22/2017 A 311B1170 A/E Prepares 90% Construction Documents 03/07/2016 A 07/29/2016 A 20B1180 90% CDs Submittal 07/29/2016 A 0B1190 90% Review (MDWASD/PSIP Team) 07/29/2016 A 08/25/2016 A 15B1200 90% RER(DERM)FDEP Permit Submittal 10/11/2016 A 0B1210 90% RER(DERM)FDEP Permit Review 10/11/2016 A 11/22/2016 A 15B1220 90% RER(Building Dept) Permit Submittal 12/01/2016 A 0B1230 90% RER(Building Dept) Permit Review 12/01/2016 A 12/16/2016 A 15B1240 90% PWWMD Permit Submittal 12/16/2016 A 0B1250 90% PWWMD Permit Review 12/16/2016 A 01/09/2017 A 15B1260 90% CD PM Comments Evaluation Completed 01/09/2017 A 0B1262 MDWASD Union Concurrence Process 01/10/2017 A 02/22/2017 A 30

100% De100% Design 01/10/2017 A 01/11/2017 A 2B1270 A/E Prepares 100% Construction Documents 01/10/2017 A 01/10/2017 A 1B1280 100% CDs Submittal 01/10/2017 A 0B1290 100% Review (MDWASD/PSIP Team) 01/11/2017 A 01/11/2017 A 1B1300 Design Completed 01/11/2017 A 0

MDWASDMDWASD Procurement 02/22/2017 A 07/25/2017 A 116B1305 Procurement Phase 02/22/2017 A 07/25/2017 A 116B1310 Submit CDs to MDWASD Procurement Division 02/22/2017 A 0B1312 Bid Notice Preparation Period 02/23/2017 A 03/02/2017 A 23B1314 Bid Notice 03/02/2017 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 03/03/2017 A 03/08/2017 A 10B1320 Pre-Bid Conference 03/09/2017 A 03/09/2017 A 1B1328 Bidders Prepare Bids for Submittal 03/10/2017 A 04/06/2017 A 15B1330 Bids Submittal 04/06/2017 A 0B1340 MDWASD/PSIP Team Bids Evaluation 04/07/2017 A 04/25/2017 A 15B1350 Recommendation for Award Letter 04/25/2017 A 0B1355 Contract Award (Purchase Order Approval) 04/26/2017 A 07/25/2017 A 10

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

10/24/2018, Basin 0870

10/24/2018, 100155 Pump Station 0870 Upgrade02/22/2017 A, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval ProcessIssue Design NTP

Final Engineering Report Review & Approval (MDWASD/PSIP Team)01/04/2016 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services

30% CDs Submittal30% Review (MDWASD/PSIP Team)03/30/2016 A, 60% Design

A/E Prepares 60% Construction Documents60% CDs Submittal

60% Review (MDWASD/PSIP Team)02/22/2017 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal

90% RER(DERM)FDEP Permit Review90% RER(Building Dept) Permit Submittal90% RER(Building Dept) Permit Review90% PWWMD Permit Submittal

90% PWWMD Permit Review90% CD PM Comments Evaluation Completed

MDWASD Union Concurrence Process01/11/2017 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed

07/25/2017 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation Period

Bid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter

Contract Award (Purchase Order Approval)

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 138 of 161 TASK filter: All Activities© Oracle Corporation

Page 139: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

ConstrucConstruction 03/09/2017 A 06/26/2018 A 417B1360 Construction Phase 03/09/2017 A 06/26/2018 A 417B1364 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 04/26/2017 A 06/23/2017 A 15B1366 Pre-Construction Meeting 06/27/2017 A 06/27/2017 A 1B1368 WASD Issues NTP (Pre-Const to NTP) 06/27/2017 A 07/28/2017 A 4B1369 WASD Issues NTP (PO to NTP) 07/25/2017 A 07/28/2017 A 45B1370 Construction NTP 07/31/2017 A 0B1400 Construction Operations 07/31/2017 A 06/26/2018 A 150B1400 Original Construction Duration 07/31/2017 A 12/28/2017 A 150B1400 Change order #1 - Hurricane Irma and FPL 12/29/2017 A 03/01/2018 A 150B1400 Change order #2 - Miami Dade Public Work Dept. MOT Permit A 03/02/2018 A 05/24/2018 A 150B1402 Substantial Completion 06/26/2018 A 0

DesignerDesigner Construction Support Services 03/09/2017 A 06/26/2018 A 260B1410 Designer Construction Support Services 03/09/2017 A 06/26/2018 A 260

Project CProject Closeout 11/12/2017 A 10/24/2018 145B1445 Closeout Phase 11/12/2017 A 10/24/2018 145B1450 Issue SAC Letter 11/12/2017 A 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 06/27/2018 A 10/24/2018 120B1490 Project Closed 10/24/2018 0

Basin 0871Basin 0871 09/18/2015 A 09/18/2015 A 1277

100157 Pu100157 Pump Station 0871 Upgrade 09/18/2015 A 09/18/2015 A 1277Project CProject Closeout 09/18/2015 A 09/18/2015 A 1277

B1445 Closeout Phase 09/18/2015 A 09/18/2015 A 1277B1450 Issue SAC Letter 09/18/2015 A 0B1480 Administrative Closeout 09/18/2015 A 09/18/2015 A 5B1490 Project Closed 09/18/2015 A 0

Basin 0877Basin 0877 08/15/2012 A 08/01/2018 2791

100158 Ba100158 Basin 0877 Infiltration/Inflow Study and Repairs 11/20/2015 A 06/01/2016 A 163InfiltratioInfiltration/Inflow 11/20/2015 A 05/31/2016 A 151

B1000 Infiltration/Inflow Phase 11/20/2015 A 05/31/2016 A 151Dig & ReDig & Replace Repairs 11/20/2015 A 05/31/2016 A 151

B1165 Dig & Replace Phase 11/20/2015 A 05/31/2016 A 151B1180 Issue NTP for Dig & Replace Repairs 11/20/2015 A 0B1190 Conduct Dig & Replace Repairs 04/21/2016 A 05/31/2016 A 30

Project CProject Closeout 06/01/2016 A 06/01/2016 A 0B1235 Closeout Phase 06/01/2016 A 06/01/2016 A 0B1260 Project Closed 06/01/2016 A 0

100159 Pu100159 Pump Station 0877 Upgrade 08/15/2012 A 08/01/2018 2032DesignDesign 08/15/2012 A 03/21/2018 A 2032

B1000 Design Phase 08/15/2012 A 03/21/2018 A 2032B1005 Remedial Action Plan to SAC Letter Issuance 08/15/2012 A 03/21/2018 A 2032

Project CProject Closeout 03/21/2018 A 08/01/2018 146B1445 Closeout Phase 03/21/2018 A 08/01/2018 146B1450 Issue SAC Letter 03/21/2018 A 0B1480 Administrative Closeout 03/22/2018 A 08/01/2018 120B1490 Project Closed 08/01/2018 0

Basin 0897Basin 0897 09/25/2014 A 08/01/2018 1402

100160 Ba100160 Basin 0897 Infiltration/Inflow Study and Repairs 09/25/2014 A 06/12/2015 A 372

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

06/26/2018 A, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Construction NTPConstruction Operations

Original Construction DurationChange order #1 - Hurricane Irma and FPL

Change order #2 - Miami Dade Public Work Dept. MOT Permit Appr

Substantial Completion06/26/2018 A, Designer Construction Support Services

Designer Construction Support Services10/24/2018, Project Closeout

Closeout PhaseIssue SAC Letter

Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed

09/18/2015 A, Basin 0871

09/18/2015 A, 100157 Pump Station 0871 Upgrade09/18/2015 A, Project Closeout

Closeout PhaseIssue SAC Letter

Administrative CloseoutProject Closed

08/01/2018, Basin 0877

06/01/2016 A, 100158 Basin 0877 Infiltration/Inflow Study and Repairs05/31/2016 A, Infiltration/InflowInfiltration/Inflow Phase05/31/2016 A, Dig & Replace RepairsDig & Replace Phase

Issue NTP for Dig & Replace RepairsConduct Dig & Replace Repairs06/01/2016 A, Project CloseoutCloseout Phase

Project Closed08/01/2018, 100159 Pump Station 0877 Upgrade

03/21/2018 A, Design

Design PhaseRemedial Action Plan to SAC Letter Issuance

08/01/2018, Project CloseoutCloseout Phase

Issue SAC LetterAdministrative CloseoutProject Closed08/01/2018, Basin 0897

06/12/2015 A, 100160 Basin 0897 Infiltration/Inflow Study and Repairs

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 139 of 161 TASK filter: All Activities© Oracle Corporation

Page 140: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

InfiltratioInfiltration/Inflow 09/25/2014 A 06/11/2015 A 223B1000 Infiltration/Inflow Phase 09/25/2014 A 06/11/2015 A 223

Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 06/11/2015 A 223B1005 SSES Phase 09/25/2014 A 06/11/2015 A 223B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 05/15/2015 A 05/27/2015 A 30B1040 Video Review 05/28/2015 A 06/11/2015 A 30

Project CProject Closeout 06/12/2015 A 06/12/2015 A 0B1235 Closeout Phase 06/12/2015 A 06/12/2015 A 0B1260 Project Closed 06/12/2015 A 0

100162 Pu100162 Pump Station 0897 Upgrade 02/16/2015 A 08/01/2018 1395DesignDesign 02/16/2015 A 05/31/2016 A 859

B1000 Design Phase 02/16/2015 A 05/31/2016 A 859B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 02/16/2015 A 02/20/2015 A 5B1020 Engage Design Consultant 02/23/2015 A 05/01/2015 A 20B1030 Issue Design NTP 05/05/2015 A 0B1040 A/E Develops and Submits Final Engineering Report 05/05/2015 A 10/28/2015 A 125B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 05/05/2015 A 10/19/2015 A 103

30% Des30% Design 05/05/2015 A 08/28/2015 A 95B1060 A/E Prepares 30% Construction Documents 05/06/2015 A 08/10/2015 A 30B1070 Geotechnical Engineering Services 05/05/2015 A 05/26/2015 A 20B1080 Surveying Services 05/05/2015 A 06/03/2015 A 15B1100 30% CDs Submittal 08/10/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 08/11/2015 A 08/28/2015 A 10

90% Des90% Design 08/11/2015 A 01/29/2016 A 161B1170 A/E Prepares 90% Construction Documents 08/11/2015 A 09/23/2015 A 20B1180 90% CDs Submittal 09/24/2015 A 0B1190 90% Review (MDWASD/PSIP Team) 09/25/2015 A 11/25/2015 A 15B1200 90% RER (DERM)FDEP Permit Submittal (Pump Station) 12/10/2015 A 0B1210 90% RER (DERM)FDEP Permit Review (Pump Station) 12/10/2015 A 01/13/2016 A 15B1220 90% RER (Building Dept.) Permit Submittal (Pump Station) 01/22/2016 A 0B1230 90% RER (Building Dept.) Permit Review (Pump Station) 01/22/2016 A 01/29/2016 A 15B1240 90% PWWMD Permit Submittal (Pump Station) 09/21/2015 A 0B1250 90% PWWMD Permit Review (Pump Station) 09/21/2015 A 10/05/2015 A 15B1260 90% CD PM Comments Evaluation Completed 01/29/2016 A 0

100% De100% Design 01/29/2016 A 05/31/2016 A 136B1270 A/E Prepares 100% Construction Documents 01/29/2016 A 05/31/2016 A 10B1280 100% CDs Submittal 05/31/2016 A 0B1290 100% Review (MDWASD/PSIP Team) 02/08/2016 A 05/31/2016 A 10B1300 Design Completed 05/31/2016 A 0

MDWASDMDWASD Procurement 02/08/2016 A 07/01/2016 A 110B1305 Procurement Phase 02/08/2016 A 07/01/2016 A 110B1310 Submit CDs to MDWASD Procurement Division 02/08/2016 A 0B1312 Bid Notice Preparation Period 02/09/2016 A 03/11/2016 A 23B1314 Bid Notice 03/11/2016 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 03/14/2016 A 03/21/2016 A 10B1320 Pre-Bid Conference 03/22/2016 A 03/22/2016 A 1B1322 Bidders Prepare Bids for Submittal 03/23/2016 A 04/18/2016 A 15B1330 Bids Submittal 04/18/2016 A 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

06/11/2015 A, Infiltration/Inflow

Infiltration/Inflow Phase06/11/2015 A, Sanitary Sewer Evaluation SurveySSES Phase

Issue NTP to SSES ContractorConduct SSESVideo Review

06/12/2015 A, Project CloseoutCloseout Phase

Project Closed08/01/2018, 100162 Pump Station 0897 Upgrade

05/31/2016 A, Design

Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book

Engage Design ConsultantIssue Design NTP

A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

08/28/2015 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services

30% CDs Submittal30% Review (MDWASD/PSIP Team)

01/29/2016 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER (DERM)FDEP Permit Submittal (Pump Station)

90% RER (DERM)FDEP Permit Review (Pump Station)90% RER (Building Dept.) Permit Submittal (Pump Station)90% RER (Building Dept.) Permit Review (Pump Station)

90% PWWMD Permit Submittal (Pump Station)90% PWWMD Permit Review (Pump Station)

90% CD PM Comments Evaluation Completed05/31/2016 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal

100% Review (MDWASD/PSIP Team)Design Completed07/01/2016 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 140 of 161 TASK filter: All Activities© Oracle Corporation

Page 141: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1340 MDWASD/PSIP Team Bids Evaluation 04/19/2016 A 05/31/2016 A 15B1350 Recommendation for Award Letter 05/31/2016 A 0B1355 Contract Award (Purchase Order Approval) 06/01/2016 A 07/01/2016 A 10

ConstrucConstruction 03/22/2016 A 03/30/2017 A 994B1360 Construction Phase 03/22/2016 A 03/30/2017 A 994B1364 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 06/01/2016 A 06/14/2016 A 15B1366 Pre-Construction Meeting 06/15/2016 A 06/15/2016 A 1B1368 WASD Issues NTP (PO to NTP) 07/02/2016 A 11/13/2016 A 53B1369 FPL De-Energizes Overhead Lines 07/04/2016 A 11/08/2016 A 15B1370 Construction NTP 11/14/2016 A 0B1400 Construction Operations 11/14/2016 A 03/30/2017 A 129B1402 Substantial Completion 03/30/2017 A 0

DesignerDesigner Construction Support Services 03/22/2016 A 03/30/2017 A 275B1410 Designer Construction Support Services 03/22/2016 A 03/30/2017 A 275

Project CProject Closeout 03/31/2017 A 08/01/2018 394B1445 Closeout Phase 03/31/2017 A 08/01/2018 394B1450 Issue SAC Letter 05/09/2018 A 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 03/31/2017 A 08/01/2018 120B1490 Project Closed 08/01/2018 0

100161 FM100161 FM for Pump Station 0897 02/16/2015 A 08/01/2018 1402DesignDesign 02/16/2015 A 12/02/2015 A 298

B1000 Design Phase 02/16/2015 A 12/02/2015 A 298B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 02/16/2015 A 02/20/2015 A 5B1020 Engage Design Consultant 02/23/2015 A 05/20/2015 A 20B1025 TA Approval Process 05/21/2015 A 06/08/2015 A 20B1030 Issue Design NTP 06/11/2015 A 0B1040 A/E Develops and Submits Final Engineering Report 06/11/2015 A 10/28/2015 A 125B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 06/11/2015 A 10/02/2015 A 10

30% Des30% Design 06/11/2015 A 08/12/2015 A 80B1060 A/E Prepares 30% Construction Documents 06/11/2015 A 07/16/2015 A 30B1070 Geotechnical Engineering Services 06/11/2015 A 07/01/2015 A 29B1080 Surveying Services 06/11/2015 A 07/01/2015 A 22B1100 30% CDs Submittal 07/17/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 07/20/2015 A 07/24/2015 A 10B1130 30% Public Works Dry-Run Permit Submittal (Force Main) 07/27/2015 A 08/12/2015 A 30

90% Des90% Design 07/20/2015 A 10/28/2015 A 43B1180 A/E Prepares 90% Construction Documents 07/20/2015 A 08/17/2015 A 20B1190 90% CDs Submittal 08/18/2015 A 0B1200 90% Review (MDWASD/PSIP Team) 08/19/2015 A 10/02/2015 A 15B1210 90% PWWMD Permit Submittal (Force Main) 07/27/2015 A 0B1220 90% PWWMD Permit Review (Force Main) 07/27/2015 A 08/12/2015 A 15B1230 90% RER(DERM)FDEP Permit Submittal (Force Main) 10/05/2015 A 0B1240 90% RER(DERM)FDEP Permit Review (Force Main) 10/05/2015 A 10/28/2015 A 15B1290 90% CD PM Comments Evaluation Completed 10/28/2015 A 0

100% De100% Design 10/28/2015 A 12/02/2015 A 25B1300 A/E Prepares 100% Construction Documents 10/28/2015 A 11/30/2015 A 10B1310 100% CDs Submittal 11/30/2015 A 0B1320 100% Review (MDWASD/PSIP Team) 12/01/2015 A 12/02/2015 A 10

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter

Contract Award (Purchase Order Approval)03/30/2017 A, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

WASD Issues NTP (PO to NTP)FPL De-Energizes Overhead Lines

Construction NTPConstruction Operations

Substantial Completion03/30/2017 A, Designer Construction Support Services

Designer Construction Support Services08/01/2018, Project Closeout

Closeout PhaseIssue SAC Letter

Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed08/01/2018, 100161 FM for Pump Station 0897

12/02/2015 A, Design

Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book

Engage Design ConsultantTA Approval ProcessIssue Design NTP

A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

08/12/2015 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services

30% CDs Submittal30% Review (MDWASD/PSIP Team)

30% Public Works Dry-Run Permit Submittal (Force Main)10/28/2015 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% PWWMD Permit Submittal (Force Main)

90% PWWMD Permit Review (Force Main)90% RER(DERM)FDEP Permit Submittal (Force Main)90% RER(DERM)FDEP Permit Review (Force Main)90% CD PM Comments Evaluation Completed

12/02/2015 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 141 of 161 TASK filter: All Activities© Oracle Corporation

Page 142: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1330 Design Completed 12/02/2015 A 0MDWASDMDWASD Procurement 12/03/2015 A 06/21/2016 A 111

B1335 Procurement Phase 12/03/2015 A 06/21/2016 A 111B1340 Submit CDs to MDWASD Procurement Division 12/03/2015 A 0B1344 Bid Notice Preparation Period 12/04/2015 A 12/17/2015 A 23B1346 Bid Notice 12/17/2015 A 0B1348 MDWASD/PSIP Team Prepare for Pre-Bid Conference 12/17/2015 A 01/20/2016 A 10B1350 Pre-Bid Conference 01/21/2016 A 01/21/2016 A 1B1358 Bidders Prepare Bids for Submittal 01/22/2016 A 02/17/2016 A 15B1360 Bids Submittal 02/17/2016 A 0B1370 MDWASD/PSIP Team Bids Evaluation 02/18/2016 A 03/01/2016 A 15B1380 Recommendation for Award Letter 03/01/2016 A 0B1385 Contract Award (Purchase Order Approval) 03/02/2016 A 06/21/2016 A 10

ConstrucConstruction 01/21/2016 A 10/03/2016 A 992B1390 Construction Phase 01/21/2016 A 10/03/2016 A 992B1394 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 03/02/2016 A 04/11/2016 A 15B1396 Pre-Construction Meeting 04/12/2016 A 04/12/2016 A 1B1398 WASD Issues NTP (PO to NTP) 06/21/2016 A 06/22/2016 A 53B1400 Construction NTP 06/22/2016 A 0B1430 Construction Operations 06/22/2016 A 08/28/2016 A 107B1432 Substantial Completion 08/28/2016 A 0

DesignerDesigner Construction Support Services 01/21/2016 A 10/03/2016 A 141B1440 Designer Construction Support Services 01/21/2016 A 10/03/2016 A 141

ConstrucConstruction Close Out 08/15/2016 A 08/31/2016 A 15B1450 Commissioning 08/15/2016 A 08/31/2016 A 15B1460 Punch List 08/15/2016 A 08/31/2016 A 10

Project CProject Closeout 08/15/2016 A 08/01/2018 622B1475 Closeout Phase 08/15/2016 A 08/01/2018 622B1500 Final Release of Retainage - Construction Contract 04/12/2017 A 0B1510 Administrative Closeout 08/15/2016 A 08/01/2018 120B1520 Project Closed 08/01/2018 0

Basin 0898Basin 0898 09/18/2012 A 08/01/2018 1736

100164 Pu100164 Pump Station 0898 Upgrade 09/18/2012 A 08/01/2018 1736DesignDesign 09/18/2012 A 12/18/2017 A 1723

B1000 Design Phase 09/18/2012 A 12/18/2017 A 1723B1012 RAP Submittal 09/18/2012 A 0B1014 I/I Repairs and Monitoring Period 04/01/2013 A 12/18/2017 A 1723

Project CProject Closeout 12/19/2017 A 08/01/2018 802B1445 Closeout Phase 12/19/2017 A 08/01/2018 802B1450 Issue SAC Letter 12/19/2017 A 0B1480 Administrative Closeout 12/20/2017 A 08/01/2018 120B1490 Project Closed 08/01/2018 0

Basin 1002Basin 1002 09/25/2014 A 01/23/2020 1662

100165 Pu100165 Pump Station 1002 Upgrade 12/17/2015 A 01/23/2020 1452DesignDesign 12/17/2015 A 10/23/2018 995

B1000 Design Phase 12/17/2015 A 10/23/2018 995B1010 Prepare and Submit Design Package 12/17/2015 A 12/28/2015 A 5B1020 Engage Design Consultant 12/28/2015 A 04/01/2016 A 20B1022 TA Preparation 04/04/2016 A 04/15/2016 A 1

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Design Completed06/21/2016 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation Period

Bid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter

Contract Award (Purchase Order Approval)10/03/2016 A, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

WASD Issues NTP (PO to NTP)Construction NTP

Construction OperationsSubstantial Completion

10/03/2016 A, Designer Construction Support Services

Designer Construction Support Services08/31/2016 A, Construction Close Out

CommissioningPunch List

08/01/2018, Project Closeout

Closeout PhaseFinal Release of Retainage - Construction Contract

Administrative CloseoutProject Closed08/01/2018, Basin 0898

08/01/2018, 100164 Pump Station 0898 Upgrade12/18/2017 A, Design

Design PhaseRAP Submittal

I/I Repairs and Monitoring Period08/01/2018, Project CloseoutCloseout Phase

Issue SAC LetterAdministrative CloseoutProject Closed

01/23/2020, Basin

01/23/2020, 1001610/23/2018, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 142 of 161 TASK filter: All Activities© Oracle Corporation

Page 143: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1024 TA Approval Process 04/18/2016 A 09/21/2016 A 20B1030 Issue Design NTP 09/28/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 09/28/2016 A 10/09/2018 85

30% Des30% Design 09/28/2016 A 09/04/2018 702B1060 A/E Prepares 30% Construction Documents 09/28/2016 A 01/24/2017 A 50B1100 30% CDs Submittal 01/24/2017 A 0B1102 Project On-Hold Due to Re-Design 01/25/2017 A 03/17/2017 A 52B1104 Engage Design Consultant (Re-Design) 03/20/2017 A 08/14/2017 A 28B1106 TA-Rev 1 Preparation 08/15/2017 A 08/15/2017 A 14B1108 TA-Rev 1 Approval Process 08/16/2017 A 11/29/2017 A 40B1109 WASD/PSIP/Design Consultant in Consultation for easement E 11/30/2017 A 05/21/2018 A 50B1110 A/E Prepares 30% Construction Documents (Re-Design) 05/22/2018 A 07/18/2018 A 50B1112 30% CDs Submittal (Re-Design) 07/18/2018 A 0B1114 TA-Rev 2 Approval Process 07/27/2018 A 09/04/2018 40B1120 30% Review (MDWASD/PSIP Team) (Re-Design) 07/19/2018 A 08/10/2018 10

90% Des90% Design 08/11/2018 10/09/2018 60B1170 A/E Prepares 90% Construction Documents 08/11/2018 08/25/2018 15B1180 90% CDs Submittal 08/25/2018 0B1190 90% Review (MDWASD/PSIP Team) 08/26/2018 09/09/2018 15B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 09/10/2018 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 09/10/2018 09/24/2018 15B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 09/25/2018 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 09/25/2018 10/09/2018 15B1260 90% CD PM Comments Evaluation Completed 10/09/2018 0

100% De100% Design 10/10/2018 10/23/2018 14B1270 A/E Prepares 100% Construction Documents 10/10/2018 10/16/2018 7B1280 100% CDs Submittal 10/16/2018 0B1290 100% Review (MDWASD/PSIP Team) 10/17/2018 10/23/2018 7B1300 Design Completed 10/23/2018 0

MDWASDMDWASD Procurement 10/23/2018 02/04/2019 104B1305 Procurement Phase 10/23/2018 02/04/2019 104B1310 Submit CDs to MDWASD Procurement Division 10/23/2018 0B1312 Bid Notice Preparation Period 10/24/2018 11/25/2018 33B1314 Bid Notice 11/25/2018 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 11/26/2018 12/09/2018 14B1320 Pre-Bid Conference 12/10/2018 12/10/2018 1B1328 Bidders Prepare Bids for Submittal 12/11/2018 12/31/2018 21B1330 Bids Submittal 12/31/2018 0B1340 MDWASD/PSIP Team Bids Evaluation 01/01/2019 01/21/2019 21B1350 Recommendation for Award Letter 01/21/2019 0B1355 Contract Award (Purchase Order Approval) 01/22/2019 02/04/2019 14

ConstrucConstruction 12/10/2018 09/25/2019 290B1360 Construction Phase 12/10/2018 09/25/2019 290B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 01/22/2019 02/11/2019 21B1364 Pre-Construction Meeting 02/12/2019 02/12/2019 1B1366 WASD Issues NTP (Pre-Const to NTP) 02/13/2019 03/29/2019 45B1368 WASD Issues NTP (PO to NTP) 02/05/2019 03/29/2019 53B1370 Construction NTP 03/30/2019 0B1400 Construction Operations 03/30/2019 09/25/2019 180

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

TA Approval ProcessIssue Design NTP

Final Engineering Report Review & Approval (MDWASD/P09/04/2018, 30% Design

A/E Prepares 30% Construction Documents30% CDs Submittal

Project On-Hold Due to Re-DesignEngage Design Consultant (Re-Design)TA-Rev 1 Preparation

TA-Rev 1 Approval ProcessWASD/PSIP/Design Consultant in Consultation for easement Encroa

A/E Prepares 30% Construction Documents (Re-Design)30% CDs Submittal (Re-Design)

TA-Rev 2 Approval Process

30% Review (MDWASD/PSIP Team) (Re-Design)10/09/2018, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)90% RER(DERM)FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)90% RER(Building Dept) Permit Review (Pump Station)90% CD PM Comments Evaluation Completed10/23/2018, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed

02/04/2019, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferenPre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)

09/25/2019, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-ConstruPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Construction NTPConstruction Operations

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 143 of 161 TASK filter: All Activities© Oracle Corporation

Page 144: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1402 Substantial Completion 09/25/2019 0DesignerDesigner Construction Support Services 12/10/2018 09/25/2019 290

B1410 Designer Construction Support Services 12/10/2018 09/25/2019 290Project CProject Closeout 09/25/2019 01/23/2020 120

B1445 Closeout Phase 09/25/2019 01/23/2020 120B1450 Issue SAC Letter 09/25/2019 0B1470 Final Release of Retainage - Construction Contract 09/25/2019 0B1480 Administrative Closeout 09/26/2019 01/23/2020 120B1490 Project Closed 01/23/2020 0

100196 Ba100196 Basin 1002 Infiltration/Inflow Study and Repairs 09/25/2014 A 10/26/2015 A 330InfiltratioInfiltration/Inflow 09/25/2014 A 10/23/2015 A 57

B1000 Infiltration/Inflow Phase 09/25/2014 A 10/23/2015 A 57Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 10/23/2015 A 57

B1005 SSES Phase 09/25/2014 A 10/23/2015 A 57B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 07/30/2015 A 10/23/2015 A 30

Project CProject Closeout 10/26/2015 A 10/26/2015 A 0B1235 Closeout Phase 10/26/2015 A 10/26/2015 A 0B1260 Project Closed 10/26/2015 A 0

Basin 1004Basin 1004 04/22/2015 A 04/22/2015 A 933

100234 FM100234 FM for Pump Station 1004 04/22/2015 A 04/22/2015 A 933Project CProject Closeout 04/22/2015 A 04/22/2015 A 933

B1475 Closeout Phase 04/22/2015 A 04/22/2015 A 933B1480 Issue SAC Letter 04/22/2015 A 0B1510 Administrative Closeout 04/22/2015 A 04/22/2015 A 15B1520 Project Closed 04/22/2015 A 04/22/2015 A 10

Basin 1008Basin 1008 07/27/2017 A 12/20/2019 802

100167 Pu100167 Pump Station 1008 Upgrade 07/27/2017 A 12/20/2019 802DesignDesign 07/27/2017 A 09/19/2018 345

B1000 Design Phase 07/27/2017 A 09/19/2018 345B1010 Prepare and Submit Design Package 07/27/2017 A 07/27/2017 A 7B1020 Engage Design Consultant 07/28/2017 A 10/09/2017 A 28B1022 TA Preparation 10/10/2017 A 10/10/2017 A 14B1024 TA Approval Process 10/11/2017 A 12/20/2017 A 40B1030 Issue Design NTP 12/22/2017 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 12/22/2017 A 08/22/2018 186

30% Des30% Design 12/22/2017 A 02/12/2018 A 100B1060 A/E Prepares 30% Construction Documents 12/22/2017 A 01/11/2018 A 50B1100 30% CDs Submittal 01/11/2018 A 0B1120 30% Review (MDWASD/PSIP Team) 01/12/2018 A 02/12/2018 A 30

90% Des90% Design 01/12/2018 A 08/22/2018 175B1170 A/E Prepares 90% Construction Documents 01/12/2018 A 03/26/2018 A 40B1180 90% CDs Submittal 03/26/2018 A 0B1190 90% Review (MDWASD/PSIP Team) 03/27/2018 A 04/24/2018 A 30B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 06/12/2018 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 06/12/2018 A 08/01/2018 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 08/02/2018 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 08/02/2018 08/22/2018 21B1260 90% CD PM Comments Evaluation Completed 08/22/2018 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Substantial Completion09/25/2019, Designer Const

Designer Construction Supp01/23/2020, Projec

Closeout PhaseIssue SAC LetterFinal Release of Retainage -

Administrative ClosProject Closed

10/26/2015 A, 100196 Basin 1002 Infiltration/Inflow Study and Repairs10/23/2015 A, Infiltration/Inflow

Infiltration/Inflow Phase10/23/2015 A, Sanitary Sewer Evaluation SurveySSES Phase

Issue NTP to SSES ContractorConduct SSES10/26/2015 A, Project CloseoutCloseout Phase

Project Closed04/22/2015 A, Basin 1004

04/22/2015 A, 100234 FM for Pump Station 100404/22/2015 A, Project Closeout

Closeout PhaseIssue SAC Letter

Administrative CloseoutProject Closed

12/20/2019, Basin 10

12/20/2019, 100167 09/19/2018, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval ProcessIssue Design NTP

Final Engineering Report Review & Approval (MDWASD/PSIP02/12/2018 A, 30% Design

A/E Prepares 30% Construction Documents30% CDs Submittal30% Review (MDWASD/PSIP Team)

08/22/2018, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)

90% RER(DERM)FDEP Permit Submittal (Pump Station)90% RER(DERM)FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)

90% RER(Building Dept) Permit Review (Pump Station)90% CD PM Comments Evaluation Completed

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 144 of 161 TASK filter: All Activities© Oracle Corporation

Page 145: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

100% De100% Design 08/23/2018 09/19/2018 28B1270 A/E Prepares 100% Construction Documents 08/23/2018 09/05/2018 14B1280 100% CDs Submittal 09/05/2018 0B1290 100% Review (MDWASD/PSIP Team) 09/06/2018 09/19/2018 14B1300 Design Completed 09/19/2018 0

MDWASDMDWASD Procurement 09/19/2018 01/01/2019 104B1305 Procurement Phase 09/19/2018 01/01/2019 104B1310 Submit CDs to MDWASD Procurement Division 09/19/2018 0B1312 Bid Notice Preparation Period 09/20/2018 10/22/2018 33B1314 Bid Notice 10/22/2018 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conferencce 10/23/2018 11/05/2018 14B1320 Pre-Bid Conference 11/06/2018 11/06/2018 1B1328 Bidders Prepare Bids for Submittal 11/07/2018 11/27/2018 21B1330 Bids Submittal 11/27/2018 0B1340 MDWASD/PSIP Team Bids Evaluation 11/28/2018 12/18/2018 21B1350 Recommendation for Award Letter 12/18/2018 0B1355 Contract Award (Purchase Order Approval) 12/19/2018 01/01/2019 14

ConstrucConstruction 11/06/2018 08/22/2019 290B1360 Construction Phase 11/06/2018 08/22/2019 290B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 12/19/2018 01/08/2019 21B1364 Pre-Construction Meeting 01/09/2019 01/09/2019 1B1366 WASD Issues NTP (Pre-Const to NTP) 01/10/2019 02/23/2019 45B1368 WASD Issues NTP (PO to NTP) 01/02/2019 02/23/2019 53B1370 Construction NTP 02/24/2019 0B1400 Construction Operations 02/24/2019 08/22/2019 180B1402 Substantial Completion 08/22/2019 0

DesignerDesigner Construction Support Services 11/06/2018 08/22/2019 290B1410 Designer Construction Support Services 11/06/2018 08/22/2019 290

Project CProject Closeout 08/22/2019 12/20/2019 120B1445 Closeout Phase 08/22/2019 12/20/2019 120B1450 Issue SAC Letter 08/22/2019 0B1470 Final Release of Retainage - Construction Contract 08/22/2019 0B1480 Administrative Closeout 08/23/2019 12/20/2019 120B1490 Project Closed 12/20/2019 0

Basin 1020Basin 1020 05/29/2015 A 12/28/2019 1854

100168 Pu100168 Pump Station 1020 Upgrade 06/04/2018 A 12/28/2019 576DesignDesign 06/04/2018 A 11/26/2018 179

B1000 Design Phase 06/04/2018 A 11/26/2018 179B1010 Prepare and Submit Design Package 06/04/2018 A 06/04/2018 A 7B1020 Engage Design Consultant 06/05/2018 A 06/23/2018 A 28B1022 TA Preparation 06/24/2018 A 06/24/2018 A 14B1024 TA Approval Process 06/25/2018 A 08/01/2018 40B1030 Issue Design NTP 08/02/2018 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 08/02/2018 11/12/2018 103

30% Des30% Design 08/02/2018 08/23/2018 22B1060 A/E Prepares 30% Construction Documents 08/02/2018 08/16/2018 15B1100 30% CDs Submittal 08/16/2018 0B1120 30% Review (MDWASD/PSIP Team) 08/17/2018 08/23/2018 7

90% Des90% Design 08/17/2018 11/12/2018 88

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

09/19/2018, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed

01/01/2019, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferenccePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)

08/22/2019, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-ConstructioPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Construction NTPConstruction OperationsSubstantial Completion08/22/2019, Designer Construc

Designer Construction Support 12/20/2019, Project C

Closeout PhaseIssue SAC LetterFinal Release of Retainage - C

Administrative CloseoProject Closed12/28/2019, Basin 1

12/28/2019, 10016811/26/2018, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval Process

Issue Design NTPFinal Engineering Report Review & Approval (MDWAS

08/23/2018, 30% Design

A/E Prepares 30% Construction Documents30% CDs Submittal30% Review (MDWASD/PSIP Team)

11/12/2018, 90% Design

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 145 of 161 TASK filter: All Activities© Oracle Corporation

Page 146: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1170 A/E Prepares 90% Construction Documents 08/17/2018 08/31/2018 15B1180 90% CDs Submittal 08/31/2018 0B1190 90% Review (MDWASD/PSIP Team) 09/01/2018 09/07/2018 7B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 09/08/2018 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 09/08/2018 10/22/2018 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 10/23/2018 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 10/23/2018 11/12/2018 21B1260 90% CD PM Comments Evaluation Completed 11/12/2018 0

100% De100% Design 11/13/2018 11/26/2018 14B1270 A/E Prepares 100% Construction Documents 11/13/2018 11/19/2018 7B1280 100% CDs Submittal 11/19/2018 0B1290 100% Review (MDWASD/PSIP Team) 11/20/2018 11/26/2018 7B1300 Design Completed 11/26/2018 0

MDWASDMDWASD Procurement 11/26/2018 03/10/2019 104B1305 Procurement Phase 11/26/2018 03/10/2019 104B1310 Submit CDs to MDWASD Procurement Division 11/26/2018 0B1312 Bid Notice Preparation Period 11/27/2018 12/29/2018 33B1314 Bid Notice 12/29/2018 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conferencce 12/30/2018 01/12/2019 14B1320 Pre-Bid Conference 01/13/2019 01/13/2019 1B1328 Bidders Prepare Bids for Submittal 01/14/2019 02/03/2019 21B1330 Bids Submittal 02/03/2019 0B1340 MDWASD/PSIP Team Bids Evaluation 02/04/2019 02/24/2019 21B1350 Recommendation for Award Letter 02/24/2019 0B1355 Contract Award (Purchase Order Approval) 02/25/2019 03/10/2019 14

ConstrucConstruction 01/13/2019 08/30/2019 230B1360 Construction Phase 01/13/2019 08/30/2019 230B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 02/25/2019 03/17/2019 21B1364 Pre-Construction Meeting 03/18/2019 03/18/2019 1B1366 WASD Issues NTP (Pre-Const to NTP) 03/19/2019 05/02/2019 45B1368 WASD Issues NTP (PO to NTP) 03/11/2019 05/02/2019 53B1370 Construction NTP 05/03/2019 0B1400 Construction Operations 05/03/2019 08/30/2019 120B1402 Substantial Completion 08/30/2019 0

DesignerDesigner Construction Support Services 01/13/2019 08/30/2019 230B1410 Designer Construction Support Services 01/13/2019 08/30/2019 230

Project CProject Closeout 08/30/2019 12/28/2019 120B1445 Closeout Phase 08/30/2019 12/28/2019 120B1450 Issue SAC Letter 08/30/2019 0B1470 Final Release of Retainage - Construction Contract 08/30/2019 0B1480 Administrative Closeout 08/31/2019 12/28/2019 120B1490 Project Closed 12/28/2019 0

100198 Ba100198 Basin 1020 Infiltration/Inflow Study and Repairs 05/29/2015 A 06/17/2016 A 548InfiltratioInfiltration/Inflow 05/29/2015 A 06/16/2016 A 275

B1000 Infiltration/Inflow Phase 05/29/2015 A 06/16/2016 A 275Sanitary Sanitary Sewer Evaluation Survey 05/29/2015 A 08/13/2015 A 30

B1005 SSES Phase 05/29/2015 A 08/13/2015 A 30B1020 Issue NTP to SSES Contractor 05/29/2015 A 0B1030 Conduct SSES 05/29/2015 A 08/13/2015 A 30

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)

90% RER(DERM)FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Statio

90% RER(Building Dept) Permit Review (Pump Station90% CD PM Comments Evaluation Completed11/26/2018, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed

03/10/2019, MDWASD ProcurementProcurement Phase

Submit CDs to MDWASD Procurement DivisionBid Notice Preparation Period

Bid NoticeMDWASD/PSIP Team Prepare for Pre-Bid Confer

Pre-Bid ConferenceBidders Prepare Bids for Submittal

Bids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)

08/30/2019, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-ConsPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Construction NTPConstruction OperationsSubstantial Completion08/30/2019, Designer Constru

Designer Construction Suppor12/28/2019, Project Closeout Phase

Issue SAC LetterFinal Release of Retainage - C

Administrative CloseProject Closed

06/17/2016 A, 100198 Basin 1020 Infiltration/Inflow Study and Repairs06/16/2016 A, Infiltration/Inflow

Infiltration/Inflow Phase08/13/2015 A, Sanitary Sewer Evaluation SurveySSES Phase

Issue NTP to SSES ContractorConduct SSES

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 146 of 161 TASK filter: All Activities© Oracle Corporation

Page 147: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

Dig & ReDig & Replace Repairs 11/20/2015 A 06/16/2016 A 30B1160 Dig & Replace Phase 11/20/2015 A 06/16/2016 A 30B1180 Issue NTP for Dig & Replace Repairs 11/20/2015 A 0B1190 Conduct Dig & Replace Repairs 06/16/2016 A 06/16/2016 A 30

Project CProject Closeout 06/17/2016 A 06/17/2016 A 0B1235 Closeout Phase 06/17/2016 A 06/17/2016 A 0B1260 Project Closed 06/17/2016 A 0

Basin 1021Basin 1021 08/15/2012 A 09/28/2020 905

100238 FM100238 FM for Pump Station 1021 08/01/2018 09/28/2020 790DesignDesign 08/01/2018 06/29/2019 333

B1000 Design Phase 08/01/2018 06/29/2019 333B1010 Prepare and Submit Design Package 08/01/2018 08/07/2018 7B1020 Engage Design Consultant 08/08/2018 09/04/2018 28B1030 TA Preparation 09/05/2018 09/18/2018 14B1032 TA Approval Process 09/19/2018 10/28/2018 40B1040 Issue Design NTP 10/29/2018 0B1060 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/29/2018 06/01/2019 216

30% Des30% Design 10/29/2018 01/16/2019 80B1070 A/E Prepares 30% Construction Documents 10/29/2018 12/17/2018 50B1110 30% CDs Submittal 12/17/2018 0B1130 30% Review (MDWASD/PSIP Team) 12/18/2018 01/16/2019 30

60% Des60% Design 12/18/2018 01/30/2019 44B1150 A/E Prepares 60% Construction Documents 12/18/2018 01/16/2019 30B1160 60% CDs Submittal 01/16/2019 0B1180 60% Review (MDWASD/PSIP Team) 01/17/2019 01/30/2019 14

90% Des90% Design 01/17/2019 06/01/2019 136B1190 A/E Prepares 90% Construction Documents 01/17/2019 02/25/2019 40B1200 90% CDs Submittal 02/25/2019 0B1210 90% Review (MDWASD/PSIP Team) 02/26/2019 03/27/2019 30B1220 90% PWWMD Permit Submittal (Force Main) 03/28/2019 0B1230 90% PWWMD Permit Review (Force Main) 03/28/2019 04/17/2019 21B1240 90% RER(DERM)/FDEP Permit Submittal (Force Main) 03/28/2019 0B1250 90% RER(DERM)/FDEP Permit Review (Force Main) 03/28/2019 05/11/2019 45B1260 90% Municipality Permit Submittal (Force Main) 05/12/2019 0B1270 90% Municipality Permit Review (Force Main) 05/12/2019 06/01/2019 21B1280 90% FDOT Permit Submittal (Force Main) 05/12/2019 0B1290 90% FDOT Permit Review (Force Main) 05/12/2019 06/01/2019 21B1300 90% CD PM Comments Evaluation Completed 06/01/2019 0

100% De100% Design 06/02/2019 06/29/2019 28B1310 A/E Prepares 100% Construction Documents 06/02/2019 06/15/2019 14B1320 100% CDs Submittal 06/15/2019 0B1330 100% Review (MDWASD/PSIP Team) 06/16/2019 06/29/2019 14B1340 Design Completed 06/29/2019 0

MDWASDMDWASD Procurement 06/29/2019 10/11/2019 104B1345 Procurement Phase 06/29/2019 10/11/2019 104B1350 Submit CDs to MDWASD Procurement Division 06/29/2019 0B1356 Bid Notice Preparation Period 06/30/2019 08/01/2019 33B1357 Bid Notice 08/01/2019 0B1358 MDWASD/PSIP Team Prepare for Pre-Bid Conferencce 08/02/2019 08/15/2019 14

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

06/16/2016 A, Dig & Replace Repairs

Dig & Replace PhaseIssue NTP for Dig & Replace Repairs

Conduct Dig & Replace Repairs06/17/2016 A, Project CloseoutCloseout Phase

Project Closed

06/29/2019, DesignDesign Phase

Prepare and Submit Design PackageEngage Design ConsultantTA Preparation

TA Approval Process

Issue Design NTPFinal Engineering Report Review & Ap

01/16/2019, 30% DesignA/E Prepares 30% Construction Documents

30% CDs Submittal30% Review (MDWASD/PSIP Team)01/30/2019, 60% Design

A/E Prepares 60% Construction Documents

60% CDs Submittal60% Review (MDWASD/PSIP Team)

06/01/2019, 90% DesignA/E Prepares 90% Construction Documents

90% CDs Submittal90% Review (MDWASD/PSIP Team)

90% PWWMD Permit Submittal (Force Mai90% PWWMD Permit Review (Force Main

90% RER(DERM)/FDEP Permit Submittal (F90% RER(DERM)/FDEP Permit Review

90% Municipality Permit Submittal (Forc90% Municipality Permit Review (Forc

90% FDOT Permit Submittal (Force Ma90% FDOT Permit Review (Force Main

90% CD PM Comments Evaluation C06/29/2019, 100% Design

A/E Prepares 100% Construction Do

100% CDs Submittal100% Review (MDWASD/PSIP Team

Design Completed10/11/2019, MDWASD ProProcurement Phase

Submit CDs to MDWASD ProcuremBid Notice Preparation Period

Bid NoticeMDWASD/PSIP Team Prepare

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 147 of 161 TASK filter: All Activities© Oracle Corporation

Page 148: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1360 Pre-Bid Conference 08/16/2019 08/16/2019 1B1362 Bidders Prepare Bids for Submittal 08/17/2019 09/06/2019 21B1370 Bids Submittal 09/06/2019 0B1380 MDWASD/PSIP Team Bids Evaluation 09/07/2019 09/27/2019 21B1390 Recommendation for Award Letter 09/27/2019 0B1392 Contract Award (Purchase Order Approval) 09/28/2019 10/11/2019 14

ConstrucConstruction 08/16/2019 05/31/2020 290B1395 Construction Phase 08/16/2019 05/31/2020 290B1396 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 09/28/2019 10/18/2019 21B1397 Pre-Construction Meeting 10/19/2019 10/19/2019 1B1398 WASD Issues NTP (Pre-Const to NTP) 10/20/2019 12/03/2019 45B1399 WASD Issues NTP (PO to NTP) 10/12/2019 12/03/2019 53B1400 Construction NTP 12/04/2019 0B1430 Construction Operations 12/04/2019 05/31/2020 180B1432 Substantial Completion 05/31/2020 0

DesignerDesigner Construction Support Services 08/16/2019 05/31/2020 290B1440 Designer Construction Support Services 08/16/2019 05/31/2020 290

Project CProject Closeout 05/31/2020 09/28/2020 120B1475 Closeout Phase 05/31/2020 09/28/2020 120B1500 Final Release of Retainage - Construction Contract 05/31/2020 0B1510 Administrative Closeout 06/01/2020 09/28/2020 120B1520 Project Closed 09/28/2020 0

100258 Pu100258 Pump Station 1021 Upgrade 08/15/2012 A 08/03/2018 783DesignDesign 08/15/2012 A 04/05/2018 A 28

B1000 Design Phase 08/15/2012 A 04/05/2018 A 28B1016 Remedial Action Plan to SAC Letter Issuance 08/15/2012 A 04/05/2018 A 28

Project CProject Closeout 04/05/2018 A 08/03/2018 665B1425 Closeout Phase 04/05/2018 A 08/03/2018 665B1430 Issue SAC Letter 04/05/2018 A 0B1460 Administrative Closeout 04/06/2018 A 08/03/2018 120B1470 Project Closed 08/03/2018 0

Basin 1022Basin 1022 04/22/2014 A 01/12/2020 1718

100170 Pu100170 Pump Station 1022(AM) Upgrade 03/14/2016 A 01/12/2020 1399DesignDesign 03/14/2016 A 10/12/2018 942

B1000 Design Phase 03/14/2016 A 10/12/2018 942B1010 Prepare and Submit Design Package 03/14/2016 A 03/14/2016 A 5B1020 Engage Design Consultant 03/14/2016 A 08/10/2016 A 20B1020 FPL/WASD Easements Negotiation Period (Approved PER) 08/11/2016 A 02/01/2017 A 60B1020 Engage Design Consultant (Design TA) 02/01/2017 A 02/28/2017 A 20B1022 TA Preparation 02/28/2017 A 02/28/2017 A 1B1024 TA Approval Process 02/28/2017 A 04/03/2017 A 40B1030 Issue Design NTP 04/06/2017 A 0B1032 Surveying Services for Easements - Recording - Conceptual De 04/06/2017 A 11/02/2017 A 110B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 08/01/2018 09/14/2018 45

30% Des30% Design 11/03/2017 A 01/22/2018 A 80B1060 A/E Prepares 30% Construction Documents 11/03/2017 A 12/11/2017 A 50B1100 30% CDs Submittal 12/11/2017 A 0B1120 30% Review (MDWASD/PSIP Team) 12/12/2017 A 01/22/2018 A 30

90% Des90% Design 01/23/2018 A 09/14/2018 226

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Pre-Bid ConferenceBidders Prepare Bids for Subm

Bids SubmittalMDWASD/PSIP Team Bids E

Recommendation for Award Contract Award (Purchase O

05/31/2Constru

MDWASD/PSIP Team PrePre-Construction Meeting

WASD Issues NTP (PreWASD Issues NTP (PO

Construction NTPConstru

Substan05/31/2Designe

Final Re

08/03/2018, 100258 Pump Station 1021 Upgrade04/05/2018 A, Design

Design PhaseRemedial Action Plan to SAC Letter Issuance

08/03/2018, Project Closeout

Closeout PhaseIssue SAC Letter

Administrative CProject Closed

01/12/2020, Basin

01/12/2020, 1001710/12/2018, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantFPL/WASD Easements Negotiation Period (Approved PER)

Engage Design Consultant (Design TA)TA Preparation

TA Approval ProcessIssue Design NTP

Surveying Services for Easements - Recording - Conceptual DesignFinal Engineering Report Review & Approval (MDWASD/PS

01/22/2018 A, 30% Design

A/E Prepares 30% Construction Documents30% CDs Submittal

30% Review (MDWASD/PSIP Team)09/14/2018, 90% Design

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 148 of 161 TASK filter: All Activities© Oracle Corporation

Page 149: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1170 A/E Prepares 90% Construction Documents 01/23/2018 A 03/21/2018 A 40B1180 90% CDs Submittal 03/21/2018 A 0B1190 90% Review (MDWASD/PSIP Team) 03/22/2018 A 07/10/2018 A 30B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 07/11/2018 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 07/11/2018 A 08/24/2018 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 08/25/2018 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 08/25/2018 09/14/2018 21B1260 90% CD PM Comments Evaluation Completed 09/14/2018 0

100% De100% Design 09/15/2018 10/12/2018 28B1270 A/E Prepares 100% Construction Documents 09/15/2018 09/28/2018 14B1280 100% CDs Submittal 09/28/2018 0B1290 100% Review (MDWASD/PSIP Team) 09/29/2018 10/12/2018 14B1300 Design Completed 10/12/2018 0

MDWASDMDWASD Procurement 10/12/2018 01/24/2019 104B1305 Procurement Phase 10/12/2018 01/24/2019 104B1310 Submit CDs to MDWASD Procurement Division 10/12/2018 0B1312 Bid Notice Preparation Period 10/13/2018 11/14/2018 33B1314 Bid Notice 11/14/2018 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 11/15/2018 11/28/2018 14B1320 Pre-Bid Conference 11/29/2018 11/29/2018 1B1322 Bidders Prepare Bids for Submittal 11/30/2018 12/20/2018 21B1330 Bids Submittal 12/20/2018 0B1340 MDWASD/PSIP Team Bids Evaluation 12/21/2018 01/10/2019 21B1350 Recommendation for Award Letter 01/10/2019 0B1355 Contract Award (Purchase Order Approval) 01/11/2019 01/24/2019 14

ConstrucConstruction 11/29/2018 09/14/2019 290B1360 Construction Phase 11/29/2018 09/14/2019 290B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 01/11/2019 01/31/2019 21B1364 Pre-Construction Meeting 02/01/2019 02/01/2019 1B1366 WASD Issues NTP (Pre-Const to NTP) 02/02/2019 03/18/2019 45B1368 WASD Issues NTP (PO to NTP) 01/25/2019 03/18/2019 53B1370 Construction NTP 03/19/2019 0B1400 Construction Operations 03/19/2019 09/14/2019 180B1402 Substantial Completion 09/14/2019 0

DesignerDesigner Construction Support Services 11/29/2018 09/14/2019 290B1410 Designer Construction Support Services 11/29/2018 09/14/2019 290

Project CProject Closeout 09/14/2019 01/12/2020 120B1445 Closeout Phase 09/14/2019 01/12/2020 120B1450 Issue SAC Letter 09/14/2019 0B1470 Final Release of Retainage - Construction Contract 09/14/2019 0B1480 Administrative Closeout 09/15/2019 01/12/2020 120B1490 Project Closed 01/12/2020 0

100169 FM100169 FM for Pump Station 1022 04/22/2014 A 06/08/2016 A 12PlanningPlanning 04/22/2014 A 06/08/2016 A 12

B0900 Planning Phase 04/22/2014 A 06/08/2016 A 12B0940 Develop Remedial Action Plan (RAP) 04/22/2014 A 05/22/2014 A 5B0950 Develop Preliminary Engineer Report (PER) 09/08/2015 A 06/08/2016 A 5

100199 Ba100199 Basin 1022 Infiltration/Inflow Study and Repairs 09/25/2014 A 05/20/2015 A 397InfiltratioInfiltration/Inflow 09/25/2014 A 05/19/2015 A 109

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)

90% RER(DERM)FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)

90% RER(Building Dept) Permit Review (Pump Station)90% CD PM Comments Evaluation Completed

10/12/2018, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed

01/24/2019, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencPre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)

09/14/2019, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-ConstrucPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Construction NTPConstruction OperationsSubstantial Completion09/14/2019, Designer Constr

Designer Construction Suppo01/12/2020, Projec

Closeout PhaseIssue SAC LetterFinal Release of Retainage -

Administrative CloseProject Closed

06/08/2016 A, 100169 FM for Pump Station 102206/08/2016 A, PlanningPlanning Phase

Develop Remedial Action Plan (RAP)Develop Preliminary Engineer Report (PER)

05/20/2015 A, 100199 Basin 1022 Infiltration/Inflow Study and Repairs05/19/2015 A, Infiltration/Inflow

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 149 of 161 TASK filter: All Activities© Oracle Corporation

Page 150: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1000 Infiltration/Inflow Phase 09/25/2014 A 05/19/2015 A 109Sanitary Sanitary Sewer Evaluation Survey 09/25/2014 A 05/19/2015 A 109

B1005 SSES Phase 09/25/2014 A 05/19/2015 A 109B1020 Issue NTP to SSES Contractor 09/25/2014 A 0B1030 Conduct SSES 04/17/2015 A 05/06/2015 A 30B1040 Video Review 05/05/2015 A 05/19/2015 A 30

Project CProject Closeout 05/20/2015 A 05/20/2015 A 0B1235 Closeout Phase 05/20/2015 A 05/20/2015 A 0B1260 Project Closed 05/20/2015 A 0

Basin 1026Basin 1026 01/14/2016 A 08/02/2019 1261

100171 Pu100171 Pump Station 1026 Upgrade 01/14/2016 A 08/02/2019 1261DesignDesign 01/14/2016 A 03/25/2018 A 770

B1000 Design Phase 01/14/2016 A 03/25/2018 A 770B1010 Prepare and Submit Design Package 01/14/2016 A 02/19/2016 A 5B1020 Engage Design Consultant 02/19/2016 A 05/16/2016 A 20B1022 TA Preparation 05/17/2016 A 05/17/2016 A 1B1024 TA Approval Process 05/18/2016 A 11/08/2016 A 20B1030 Issue Design NTP 11/15/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 11/15/2016 A 02/15/2018 A 85

30% Des30% Design 11/15/2016 A 02/17/2017 A 115B1060 A/E Prepares 30% Construction Documents 11/15/2016 A 01/19/2017 A 50B1100 30% CDs Submittal 01/19/2017 A 0B1120 30% Review (MDWASD/PSIP Team) 01/20/2017 A 02/17/2017 A 30

90% Des90% Design 02/20/2017 A 02/15/2018 A 393B1170 A/E Prepares 90% Construction Documents 02/20/2017 A 07/14/2017 A 40B1180 90% CDs Submittal 07/14/2017 A 0B1190 90% Review (MDWASD/PSIP Team) 07/17/2017 A 08/10/2017 A 30B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 10/11/2017 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 10/11/2017 A 12/19/2017 A 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 12/27/2017 A 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 12/27/2017 A 02/15/2018 A 21B1260 90% CD PM Comments Evaluation Completed 02/15/2018 A 0B1262 MDWASD Union Concurrence Process 07/27/2017 A 08/17/2017 A 30

100% De100% Design 02/16/2018 A 03/25/2018 A 28B1270 A/E Prepares 100% Construction Documents 02/16/2018 A 03/15/2018 A 14B1280 100% CDs Submittal 03/15/2018 A 0B1290 100% Review (MDWASD/PSIP Team) 03/16/2018 A 03/25/2018 A 14B1300 Design Completed 03/25/2018 A 0

MDWASDMDWASD Procurement 03/26/2018 A 08/01/2018 108B1305 Procurement Phase 03/26/2018 A 08/01/2018 108B1310 Submit CDs to MDWASD Procurement Division 03/26/2018 A 0B1312 Bid Notice Preparation Period 03/27/2018 A 04/06/2018 A 33B1314 Bid Notice 04/06/2018 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 04/07/2018 A 05/15/2018 A 21B1320 Pre-Bid Conference 04/16/2018 A 04/16/2018 A 1B1322 Bidders Prepare Bids for Submittal 04/17/2018 A 05/31/2018 A 21B1330 Bids Submittal 05/31/2018 A 0B1340 MDWASD/PSIP Team Bids Evaluation 06/01/2018 A 06/26/2018 A 21B1350 Recommendation for Award Letter 06/26/2018 A 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Infiltration/Inflow Phase05/19/2015 A, Sanitary Sewer Evaluation SurveySSES Phase

Issue NTP to SSES ContractorConduct SSESVideo Review

05/20/2015 A, Project CloseoutCloseout Phase

Project Closed08/02/2019, Basin 1026

08/02/2019, 100171 Pump Stat03/25/2018 A, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval ProcessIssue Design NTP

Final Engineering Report Review & Approval (MDWASD/PSIP Team)02/17/2017 A, 30% Design

A/E Prepares 30% Construction Documents30% CDs Submittal30% Review (MDWASD/PSIP Team)

02/15/2018 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)

90% RER(DERM)FDEP Permit Submittal (Pump Station)90% RER(DERM)FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)

90% RER(Building Dept) Permit Review (Pump Station)90% CD PM Comments Evaluation Completed

MDWASD Union Concurrence Process03/25/2018 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed

08/01/2018, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation Period

Bid NoticeMDWASD/PSIP Team Prepare for Pre-Bid Conference

Pre-Bid ConferenceBidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 150 of 161 TASK filter: All Activities© Oracle Corporation

Page 151: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1355 Contract Award (Purchase Order Approval) 06/27/2018 A 08/01/2018 14ConstrucConstruction 04/16/2018 A 04/04/2019 327

B1360 Construction Phase 04/16/2018 A 04/04/2019 327B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 08/01/2018 08/21/2018 21B1364 Pre-Construction Meeting 08/22/2018 08/22/2018 1B1366 WASD Issues NTP (Pre-Const to NTP) 08/23/2018 10/06/2018 45B1368 WASD Issues NTP (PO to NTP) 08/02/2018 10/06/2018 66B1370 Construction NTP 10/07/2018 0B1400 Construction Operations 10/07/2018 04/04/2019 180B1402 Substantial Completion 04/04/2019 0

DesignerDesigner Construction Support Services 04/16/2018 A 04/04/2019 290B1410 Designer Construction Support Services 04/16/2018 A 04/04/2019 290

Project CProject Closeout 04/04/2019 08/02/2019 120B1445 Closeout Phase 04/04/2019 08/02/2019 120B1450 Issue SAC Letter 04/04/2019 0B1470 Final Release of Retainage - Construction Contract 04/04/2019 0B1480 Administrative Closeout 04/05/2019 08/02/2019 120B1490 Project Closed 08/02/2019 0

Basin 1056Basin 1056 11/17/2015 A 10/30/2018 1002

100172 Pu100172 Pump Station 1056 Upgrade 11/17/2015 A 10/30/2018 1002DesignDesign 11/17/2015 A 06/26/2017 A 575

B1000 Design Phase 11/17/2015 A 06/26/2017 A 575B1010 Prepare and Submit Design Package 11/17/2015 A 11/17/2015 A 5B1020 Engage Design Consultant 11/17/2015 A 02/26/2016 A 20B1022 TA Preparation 02/29/2016 A 02/29/2016 A 1B1024 TA Approval Process 03/01/2016 A 03/25/2016 A 20B1030 Issue Design NTP 03/29/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 03/29/2016 A 12/08/2016 A 85

30% Des30% Design 03/29/2016 A 09/13/2016 A 146B1060 A/E Prepares 30% Construction Documents 03/29/2016 A 08/17/2016 A 30B1070 Geotechnical Engineering Services 03/29/2016 A 08/17/2016 A 20B1080 Surveying Services 03/29/2016 A 08/17/2016 A 15B1100 30% CDs Submittal 08/17/2016 A 0B1120 30% Review (MDWASD/PSIP Team) 08/18/2016 A 09/13/2016 A 10

90% Des90% Design 08/18/2016 A 05/02/2017 A 302B1170 A/E Prepares 90% Construction Documents 08/18/2016 A 11/07/2016 A 40B1180 90% CDs Submittal 11/07/2016 A 0B1190 90% Review (MDWASD/PSIP Team) 11/08/2016 A 12/08/2016 A 30B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 12/27/2016 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 12/27/2016 A 02/06/2017 A 45B1220 90% RER(Building Dept) Permit Submittal (Fire Dept. Municipal) 02/08/2017 A 0B1230 90% RER(Building Dept) Permit Review (Fire Dept. Municipal) 02/08/2017 A 05/02/2017 A 21B1240 90% Cutler Bay - BD Permit Submittal (Pump Station) 02/08/2017 A 0B1250 90% Cutler Bay - BD Permit Review (Pump Station) 02/08/2017 A 05/02/2017 A 15B1252 90% Cutler Bay - PWD Permit Submittal (Pump Station) 02/08/2017 A 0B1254 90% Cutler Bay - PWD Permit Review (Pump Station) 02/08/2017 A 05/02/2017 A 15B1260 90% CD PM Comments Evaluation Completed 05/02/2017 A 0B1262 MDWASD Union Concurrence Process 01/25/2017 A 02/22/2017 A 30

100% De100% Design 05/03/2017 A 06/26/2017 A 28

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Contract Award (Purchase Order Approval)04/04/2019, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Construction NTPConstruction OperationsSubstantial Completion04/04/2019, Designer Construction Suppo

Designer Construction Support Services08/02/2019, Project Closeout

Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction

Administrative CloseoutProject Closed

10/30/2018, Basin 1056

10/30/2018, 100172 Pump Station 1056 Upgrade06/26/2017 A, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval ProcessIssue Design NTP

Final Engineering Report Review & Approval (MDWASD/PSIP Team)09/13/2016 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal

30% Review (MDWASD/PSIP Team)05/02/2017 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)

90% RER(DERM)FDEP Permit Submittal (Pump Station)90% RER(DERM)FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Fire Dept. Municipal)

90% RER(Building Dept) Permit Review (Fire Dept. Municipal)90% Cutler Bay - BD Permit Submittal (Pump Station)

90% Cutler Bay - BD Permit Review (Pump Station)90% Cutler Bay - PWD Permit Submittal (Pump Station)

90% Cutler Bay - PWD Permit Review (Pump Station)90% CD PM Comments Evaluation Completed

MDWASD Union Concurrence Process06/26/2017 A, 100% Design

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 151 of 161 TASK filter: All Activities© Oracle Corporation

Page 152: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1270 A/E Prepares 100% Construction Documents 05/03/2017 A 06/26/2017 A 10B1280 100% CDs Submittal 06/26/2017 A 0B1290 100% Review (MDWASD/PSIP Team) 06/26/2017 A 06/26/2017 A 10B1300 Design Completed 06/26/2017 A 0

MDWASDMDWASD Procurement 06/27/2017 A 12/01/2017 A 108B1305 Procurement Phase 06/27/2017 A 12/01/2017 A 108B1310 Submit CDs to MDWASD Procurement Division 06/27/2017 A 0B1312 Bid Notice Preparation Period 06/28/2017 A 07/27/2017 A 33B1314 Bid Notice 07/27/2017 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 07/28/2017 A 08/09/2017 A 14B1320 Pre-Bid Conference 08/10/2017 A 08/10/2017 A 1B1328 Bidders Prepare Bids for Submittal 08/11/2017 A 10/03/2017 A 21B1330 Bids Submittal 10/03/2017 A 0B1340 MDWASD/PSIP Team Bids Evaluation 10/04/2017 A 11/02/2017 A 21B1350 Recommendation for Award Letter 11/02/2017 A 0B1355 Contract Award (Purchase Order Approval) 11/03/2017 A 12/01/2017 A 14

ConstrucConstruction 08/10/2017 A 10/30/2018 446B1360 Construction Phase 08/10/2017 A 10/30/2018 446B1364 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 11/03/2017 A 12/17/2017 A 21B1366 Pre-Construction Meeting 12/18/2017 A 12/18/2017 A 1B1368 WASD Issues NTP (Pre-Const to NTP) 12/19/2017 A 07/01/2018 A 45B1369 WASD Issues NTP (PO to NTP) 12/02/2017 A 07/01/2018 A 57B1370 Construction NTP 07/02/2018 A 0B1400 Construction Operations 07/02/2018 A 10/30/2018 120B1402 Substantial Completion 10/30/2018 0

DesignerDesigner Construction Support Services 08/10/2017 A 10/30/2018 260B1410 Designer Construction Support Services 08/10/2017 A 10/30/2018 260

Project CProject Closeout 10/30/2018 10/30/2018 0B1445 Closeout Phase 10/30/2018 10/30/2018 0B1450 Issue SAC Letter 10/30/2018 0B1470 Final Release of Retainage - Construction Contract 10/30/2018 0B1480 Administrative Closeout 10/30/2018 0B1490 Project Closed 10/30/2018 0

Basin 1058Basin 1058 05/22/2015 A 11/29/2018 1288

100174 Pu100174 Pump Station 1058 Upgrade 12/17/2015 A 11/29/2018 990DesignDesign 12/17/2015 A 04/17/2017 A 441

B1000 Design Phase 12/17/2015 A 04/17/2017 A 441B1010 Prepare and Submit Design Package 12/17/2015 A 02/23/2016 A 5B1020 Engage Design Consultant 02/23/2016 A 04/13/2016 A 20B1022 TA Preparation 04/14/2016 A 04/14/2016 A 1B1024 TA Approval Process 04/15/2016 A 05/02/2016 A 20B1030 Issue Design NTP 05/16/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 05/16/2016 A 11/17/2016 A 85

30% Des30% Design 05/17/2016 A 09/02/2016 A 135B1060 A/E Prepares 30% Construction Documents 05/17/2016 A 08/05/2016 A 30B1070 Geotechnical Engineering Services 05/17/2016 A 08/05/2016 A 20B1080 Surveying Services 05/17/2016 A 08/05/2016 A 15B1100 30% CDs Submittal 08/05/2016 A 0B1120 30% Review (MDWASD/PSIP Team) 08/08/2016 A 09/02/2016 A 10

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

A/E Prepares 100% Construction Documents100% CDs Submittal

100% Review (MDWASD/PSIP Team)Design Completed

12/01/2017 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement DivisionBid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter

Contract Award (Purchase Order Approval)10/30/2018, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Construction NTPConstruction OperationsSubstantial Completion10/30/2018, Designer Construction Support Services

Designer Construction Support Services10/30/2018, Project Closeout

Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction ContractAdministrative CloseoutProject Closed

11/29/2018, Basin 1058

11/29/2018, 100174 Pump Station 1058 Upgrade04/17/2017 A, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval ProcessIssue Design NTP

Final Engineering Report Review & Approval (MDWASD/PSIP Team)09/02/2016 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services

30% CDs Submittal30% Review (MDWASD/PSIP Team)

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 152 of 161 TASK filter: All Activities© Oracle Corporation

Page 153: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

90% Des90% Design 08/08/2016 A 04/17/2017 A 210B1170 A/E Prepares 90% Construction Documents 08/08/2016 A 10/19/2016 A 20B1180 90% CDs Submittal 10/19/2016 A 0B1190 90% Review (MDWASD/PSIP Team) 10/20/2016 A 11/17/2016 A 15B1200 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 12/28/2016 A 0B1210 90% RER(DERM)/FDEP Permit Review (Pump Station) 12/28/2016 A 01/13/2017 A 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 01/26/2017 A 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 01/26/2017 A 04/17/2017 A 21B1240 90% Cutler Bay - BD Permit Submittal (Pump Station) 01/26/2017 A 0B1250 90% Cutler Bay - BD Permit Review (Pump Station) 01/26/2017 A 04/17/2017 A 15B1252 90% Cutler Bay - PWD Permit Submittal (Pump Station) 01/26/2017 A 0B1254 90% Cutler Bay - PWD Permit Review (Pump Station) 01/26/2017 A 04/17/2017 A 15B1260 90% CD PM Comments Evaluation Completed 04/17/2017 A 0B1262 MDWASD/PSIP Concurrence Process 01/25/2017 A 02/22/2017 A 30

100% De100% Design 03/20/2017 A 04/06/2017 A 28B1270 A/E Prepares 100% Construction Documents 03/20/2017 A 03/31/2017 A 10B1280 100% CDs Submittal 03/31/2017 A 0B1290 100% Review (MDWASD/PSIP Team) 04/03/2017 A 04/06/2017 A 10B1300 Design Completed 04/06/2017 A 0

MDWASDMDWASD Procurement 04/06/2017 A 11/07/2017 A 78B1305 Procurement Phase 04/06/2017 A 11/07/2017 A 78B1310 Submit CDs to MDWASD Procurement Division 04/06/2017 A 0B1312 Bid Notice Preparation Period 04/07/2017 A 04/25/2017 A 23B1314 Bid Notice 04/25/2017 A 0B1316 MDWASAD/PSIP Team Prepare for Pre-Bid Conference 04/26/2017 A 05/22/2017 A 10B1320 Pre-Bid Conference 05/23/2017 A 05/23/2017 A 1B1322 Bidders Prepare Bids for Submittal 05/24/2017 A 06/21/2017 A 9B1330 Bids Submittal 06/21/2017 A 0B1340 MDWASD/PSIP Team Bids Evaluation 06/22/2017 A 07/20/2017 A 15B1350 Recommendation for Award Letter 07/20/2017 A 0B1355 Contract Award (Purchase Order Approval) 07/21/2017 A 11/07/2017 A 14

ConstrucConstruction 05/23/2017 A 08/01/2018 461B1360 Construction Phase 05/23/2017 A 08/01/2018 461B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 07/21/2017 A 08/29/2017 A 21B1364 Pre-Construction Meeting 08/30/2017 A 08/30/2017 A 1B1366 WASD Issues NTP (Pre-Const to NTP) 08/31/2017 A 01/07/2018 A 45B1368 WASD Issues NTP (PO to NTP) 11/07/2017 A 01/07/2018 A 57B1370 Construction NTP 01/08/2018 A 0B1400 Construction Operations 01/08/2018 A 08/01/2018 120B1402 Substantial Completion 08/01/2018 0

DesignerDesigner Construction Support Services 05/23/2017 A 08/01/2018 252B1410 Designer Construction Support Services 05/23/2017 A 08/01/2018 252

Project CProject Closeout 08/01/2018 11/29/2018 120B1445 Closeout Phase 08/01/2018 11/29/2018 120B1450 Issue SAC Letter 08/01/2018 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 08/02/2018 11/29/2018 120B1490 Project Closed 11/29/2018 0

100247 Ba100247 Basin 1058 Infiltration/Inflow Study and Repairs 05/22/2015 A 10/08/2015 A 376

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

04/17/2017 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)/FDEP Permit Submittal (Pump Station)90% RER(DERM)/FDEP Permit Review (Pump Station)

90% RER(Building Dept) Permit Submittal (Pump Station)90% RER(Building Dept) Permit Review (Pump Station)

90% Cutler Bay - BD Permit Submittal (Pump Station)90% Cutler Bay - BD Permit Review (Pump Station)

90% Cutler Bay - PWD Permit Submittal (Pump Station)90% Cutler Bay - PWD Permit Review (Pump Station)90% CD PM Comments Evaluation Completed

MDWASD/PSIP Concurrence Process04/06/2017 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal

100% Review (MDWASD/PSIP Team)Design Completed

11/07/2017 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid NoticeMDWASAD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award Letter

Contract Award (Purchase Order Approval)08/01/2018, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Construction NTPConstruction OperationsSubstantial Completion08/01/2018, Designer Construction Support Services

Designer Construction Support Services11/29/2018, Project Closeout

Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction Contract

Administrative CloseoutProject Closed

10/08/2015 A, 100247 Basin 1058 Infiltration/Inflow Study and Repairs

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 153 of 161 TASK filter: All Activities© Oracle Corporation

Page 154: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

InfiltratioInfiltration/Inflow 05/22/2015 A 10/07/2015 A 139B1000 Infiltration/Inflow Phase 05/22/2015 A 10/07/2015 A 139

CIPP RepCIPP Repairs 05/22/2015 A 10/07/2015 A 139B1070 CIPP Phase 05/22/2015 A 10/07/2015 A 139B1090 Issue NTP for CIPP Repairs 05/22/2015 A 0B1100 Conduct CIPP Repairs 10/07/2015 A 10/07/2015 A 1

Project CProject Closeout 10/08/2015 A 10/08/2015 A 0B1250 Closeout Phase 10/08/2015 A 10/08/2015 A 0B1280 Project Closed 10/08/2015 A 0

Basin 1065Basin 1065 07/01/2015 A 11/29/2019 1093

100175 Pu100175 Pump Station 1065 Upgrade 07/01/2015 A 11/29/2019 1093DesignDesign 07/01/2015 A 08/29/2018 636

B1000 Design Phase 07/01/2015 A 08/29/2018 636B1002 Prepare Request for SOW for Survey Only 07/01/2015 A 07/07/2015 A 5B1004 TA Approval Process (Survey Only) 07/08/2015 A 07/14/2015 A 20B1006 Waiting Period Prior to Design Package Preparation 07/15/2015 A 05/10/2016 A 5B1010 Prepare and Submit Design Package 05/11/2016 A 05/12/2016 A 5B1020 Engage Design Consultant 05/13/2016 A 11/18/2016 A 20B1022 TA Preparation 11/21/2016 A 11/21/2016 A 1B1024 TA Approval Process 11/22/2016 A 02/10/2017 A 20B1030 Issue Design NTP 02/16/2017 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 02/16/2017 A 08/01/2018 65

30% Des30% Design 07/14/2015 A 07/20/2017 A 241B1060 A/E Prepares 30% Construction Documents 02/16/2017 A 06/20/2017 A 50B1080 Surveying Services 07/14/2015 A 07/28/2015 A 19B1100 30% CDs Submittal 06/20/2017 A 0B1120 30% Review (MDWASD/PSIP Team) 06/21/2017 A 07/20/2017 A 30

90% Des90% Design 06/21/2017 A 08/01/2018 394B1170 A/E Prepares 90% Construction Documents 06/21/2017 A 12/04/2017 A 40B1180 90% CDs Submittal 12/04/2017 A 0B1190 90% Review (MDWASD/PSIP Team) 12/05/2017 A 01/03/2018 A 30B1200 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 02/06/2018 A 0B1210 90% RER(DERM)/FDEP Permit Review (Pump Station) 02/06/2018 A 04/17/2018 A 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 06/18/2018 A 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 06/18/2018 A 08/01/2018 21B1260 90% CD PM Comments Evaluation Completed 08/01/2018 0

100% De100% Design 08/02/2018 08/29/2018 28B1270 A/E Prepares 100% Construction Documents 08/02/2018 08/15/2018 14B1280 100% CDs Submittal 08/15/2018 0B1290 100% Review (MDWASD/PSIP Team) 08/16/2018 08/29/2018 14B1300 Design Completed 08/29/2018 0

MDWASDMDWASD Procurement 08/29/2018 12/11/2018 104B1305 Procurement Phase 08/29/2018 12/11/2018 104B1310 Submit CDs to MDWASD Procurement Division 08/29/2018 0B1312 Bid Notice preparation Period 08/30/2018 10/01/2018 33B1314 Bid Notice 10/01/2018 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 10/02/2018 10/15/2018 14B1320 Pre-Bid Conference 10/16/2018 10/16/2018 1B1328 Bidders Prepare Bids for Submittal 10/17/2018 11/06/2018 21

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

10/07/2015 A, Infiltration/Inflow

Infiltration/Inflow Phase10/07/2015 A, CIPP Repairs

CIPP PhaseIssue NTP for CIPP Repairs

Conduct CIPP Repairs10/08/2015 A, Project Closeout

Closeout PhaseProject Closed

11/29/2019, Basin 106

11/29/2019, 100175 P08/29/2018, Design

Design PhasePrepare Request for SOW for Survey Only

TA Approval Process (Survey Only)Waiting Period Prior to Design Package PreparationPrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval ProcessIssue Design NTP

Final Engineering Report Review & Approval (MDWASD/PSIP 07/20/2017 A, 30% Design

A/E Prepares 30% Construction DocumentsSurveying Services

30% CDs Submittal30% Review (MDWASD/PSIP Team)

08/01/2018, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)

90% RER(DERM)/FDEP Permit Submittal (Pump Station)90% RER(DERM)/FDEP Permit Review (Pump Station)

90% RER(Building Dept) Permit Submittal (Pump Station)90% RER(Building Dept) Permit Review (Pump Station)90% CD PM Comments Evaluation Completed

08/29/2018, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed

12/11/2018, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for Submittal

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 154 of 161 TASK filter: All Activities© Oracle Corporation

Page 155: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1330 Bids Submittal 11/06/2018 0B1340 MDWASD/PSIP Team Bids Evaluation 11/07/2018 11/27/2018 21B1350 Recommendation for Award Letter 11/27/2018 0B1355 Contract Award (Purchase Order Approval) 11/28/2018 12/11/2018 14

ConstrucConstruction 10/16/2018 08/01/2019 290B1360 Construction Phase 10/16/2018 08/01/2019 290B1364 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 11/28/2018 12/18/2018 21B1366 Pre-Construction Meeting 12/19/2018 12/19/2018 1B1368 WASD Issues NTP (Pre-Const to NTP) 12/20/2018 02/02/2019 45B1369 WASD Issues NTP (PO to NTP) 12/12/2018 02/02/2019 53B1370 Construction NTP 02/03/2019 0B1400 Construction Operations 02/03/2019 08/01/2019 180B1402 Substantial Completion 08/01/2019 0

DesignerDesigner Construction Support Services 10/16/2018 08/01/2019 290B1410 Designer Construction Support Services 10/16/2018 08/01/2019 290

Project CProject Closeout 08/01/2019 11/29/2019 120B1445 Closeout Phase 08/01/2019 11/29/2019 120B1450 Issue SAC Letter 08/01/2019 0B1470 Final Release of Retainage - Construction Contract 08/01/2019 0B1480 Administrative Closeout 08/02/2019 11/29/2019 120B1490 Project Closed 11/29/2019 0

Basin 1067Basin 1067 10/01/2014 A 08/31/2018 1428

100178 Pu100178 Pump Station 1067 Upgrade 10/01/2014 A 08/31/2018 1428DesignDesign 10/01/2014 A 06/23/2016 A 616

B1000 Design Phase 10/01/2014 A 06/23/2016 A 616B1010 Prepare and Submit Design Package 10/01/2014 A 10/07/2014 A 5B1020 Engage Design Consultant 10/08/2014 A 02/04/2015 A 20B1022 TA Approval Process 02/05/2015 A 03/11/2015 A 20B1024 TA Approval Process (Survey) 02/16/2015 A 03/19/2015 A 20B1030 Issue Design NTP 03/16/2015 A 0B1031 Issue Survey NTP 03/24/2015 A 0B1040 A/E Develops and Submits Final Engineering Report 03/16/2015 A 04/07/2016 A 125B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 03/16/2015 A 11/18/2015 A 80

30% Des30% Design 03/17/2015 A 06/19/2015 A 77B1060 A/E Prepares 30% Construction Documents 03/17/2015 A 05/19/2015 A 30B1070 Geotechnical Engineering Services 03/17/2015 A 05/19/2015 A 20B1080 Surveying Services 03/25/2015 A 05/19/2015 A 19B1100 30% CDs Submittal 05/19/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 05/20/2015 A 06/19/2015 A 10

60% Des60% Design 05/20/2015 A 08/21/2015 A 106B1130 A/E Prepares 60% Construction Documents 05/20/2015 A 08/14/2015 A 20B1140 60% CDs Submittal 08/14/2015 A 0B1160 60% Review (MDWASD/PSIP Team) 08/17/2015 A 08/21/2015 A 10

90% Des90% Design 08/17/2015 A 04/07/2016 A 244B1170 A/E Prepares 90% Construction Documents 08/17/2015 A 09/02/2015 A 20B1180 90% CDs Submittal 09/03/2015 A 0B1190 90% Review (MDWASD/PSIP Team) 09/04/2015 A 11/18/2015 A 15B1200 90% RER(DERM)FDEP Permit Submittal (Pump Station) 11/19/2015 A 0B1210 90% RER(DERM)FDEP Permit Review (Pump Station) 11/20/2015 A 12/29/2015 A 15

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Bids SubmittalMDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)

08/01/2019, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-ConstructionPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Construction NTPConstruction OperationsSubstantial Completion08/01/2019, Designer Constructi

Designer Construction Support S11/29/2019, Project Clo

Closeout PhaseIssue SAC LetterFinal Release of Retainage - Con

Administrative CloseouProject Closed

08/31/2018, Basin 1067

08/31/2018, 100178 Pump Station 1067 Upgrade06/23/2016 A, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Approval ProcessTA Approval Process (Survey)Issue Design NTPIssue Survey NTP

A/E Develops and Submits Final Engineering ReportFinal Engineering Report Review & Approval (MDWASD/PSIP Team)

06/19/2015 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal

30% Review (MDWASD/PSIP Team)08/21/2015 A, 60% Design

A/E Prepares 60% Construction Documents60% CDs Submittal

60% Review (MDWASD/PSIP Team)04/07/2016 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)FDEP Permit Submittal (Pump Station)

90% RER(DERM)FDEP Permit Review (Pump Station)

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 155 of 161 TASK filter: All Activities© Oracle Corporation

Page 156: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1222 90% Miami - BD Permit Submittal (Pump Station) 02/16/2016 A 0B1224 90% Miami - BD Permit Review (Pump Station) 02/16/2016 A 02/25/2016 A 15B1226 90% Miami - PWD Permit Submittal (Pump Station) 02/11/2016 A 0B1228 90% Miami - PWD Permit Review (Pump Station) 02/11/2016 A 04/07/2016 A 15B1260 90% CD PM Comments Evaluation Completed 04/07/2016 A 0

100% De100% Design 04/28/2016 A 06/23/2016 A 44B1270 A/E Prepares 100% Construction Documents 04/28/2016 A 06/22/2016 A 10B1280 100% CDs Submittal 06/23/2016 A 0B1290 100% Review (MDWASD/PSIP Team) 06/23/2016 A 06/23/2016 A 10B1300 Design Completed 06/23/2016 A 0

MDWASDMDWASD Procurement 03/01/2016 A 06/13/2016 A 97B1305 Procurement Phase 03/01/2016 A 06/13/2016 A 97B1310 Submit CDs to MDWASD Procurement Division 03/01/2016 A 0B1312 Bid Notice Preparation Period 03/02/2016 A 03/15/2016 A 23B1314 Bid Notice 03/15/2016 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 03/16/2016 A 04/05/2016 A 10B1320 Pre-Bid Conference 04/06/2016 A 04/06/2016 A 1B1328 Bidders Prepare Bids for Submittal 04/07/2016 A 04/27/2016 A 15B1330 Bids Submittal 04/27/2016 A 0B1340 MDWASD/PSIP Team Bids Evaluation 04/28/2016 A 05/05/2016 A 15B1350 Recommendation for Award Letter 05/05/2016 A 0B1355 Contract Award (Purchase Order Approval) 05/06/2016 A 06/13/2016 A 10

ConstrucConstruction 04/06/2016 A 08/01/2018 827B1360 Construction Phase 04/06/2016 A 08/01/2018 827B1364 MDWASD/PSIP Team Prepare for Pre-construction Meeting 05/06/2016 A 06/23/2016 A 15B1366 Pre-Construction Meeting 06/24/2016 A 06/24/2016 A 1B1368 WASD Issues NTP (PO to NTP) 06/13/2016 A 07/25/2016 A 57B1370 Construction NTP 07/25/2016 A 0B1400 Construction Operations 07/25/2016 A 08/01/2018 140B1400 Original Construction Duration 07/25/2016 A 12/12/2016 A 140B1400 Change Order #1 - Unforeseen ATT 12/13/2016 A 04/20/2017 A 140B1400 Change Order #2 - Hurricane Irma 04/21/2017 A 05/11/2017 A 140B1400 Change Order #3 - FPL and Guy Wire Change 05/12/2017 A 11/04/2017 A 140B1402 Substantial Completion 08/01/2018 0

DesignerDesigner Construction Support Services 04/06/2016 A 08/01/2018 304B1410 Designer Construction Support Services 04/06/2016 A 08/01/2018 304

Project CProject Closeout 08/05/2016 A 08/31/2018 756B1445 Closeout Phase 08/05/2016 A 08/31/2018 756B1450 Issue SAC Letter 08/05/2016 A 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 08/02/2018 08/31/2018 30B1490 Project Closed 08/31/2018 0

100251 Ba100251 Basin 1067 Infiltration/Inflow Study and Repairs 10/30/2015 A 06/15/2016 A 246InfiltratioInfiltration/Inflow 10/30/2015 A 06/14/2016 A 20

B1000 Infiltration/Inflow Phase 10/30/2015 A 06/14/2016 A 20ManholeManhole Repairs 10/30/2015 A 06/14/2016 A 20

B1110 Manhole Phase 10/30/2015 A 06/14/2016 A 20B1130 Issue NTP for Manhole Repairs 10/30/2015 A 0B1140 Conduct Manhole Repairs 03/14/2016 A 06/14/2016 A 20

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

90% Miami - BD Permit Submittal (Pump Station)90% Miami - BD Permit Review (Pump Station)

90% Miami - PWD Permit Submittal (Pump Station)90% Miami - PWD Permit Review (Pump Station)

90% CD PM Comments Evaluation Completed06/23/2016 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Team)Design Completed

06/13/2016 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)

08/01/2018, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-construction MeetingPre-Construction Meeting

WASD Issues NTP (PO to NTP)Construction NTP

Construction OperationsOriginal Construction Duration

Change Order #1 - Unforeseen ATTChange Order #2 - Hurricane Irma

Change Order #3 - FPL and Guy Wire Change

Substantial Completion08/01/2018, Designer Construction Support Services

Designer Construction Support Services08/31/2018, Project Closeout

Closeout PhaseIssue SAC Letter

Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed

06/15/2016 A, 100251 Basin 1067 Infiltration/Inflow Study and Repairs06/14/2016 A, Infiltration/Inflow

Infiltration/Inflow Phase06/14/2016 A, Manhole Repairs

Manhole PhaseIssue NTP for Manhole Repairs

Conduct Manhole Repairs

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 156 of 161 TASK filter: All Activities© Oracle Corporation

Page 157: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

Project CProject Closeout 06/15/2016 A 06/15/2016 A 0B1250 Closeout Phase 06/15/2016 A 06/15/2016 A 0B1280 Project Closed 06/15/2016 A 0

Basin 1068Basin 1068 04/22/2015 A 08/01/2018 1224

100179 Pu100179 Pump Station 1068 Upgrade 04/22/2015 A 08/01/2018 1224DesignDesign 04/22/2015 A 07/20/2016 A 925

B1000 Design Phase 04/22/2015 A 07/20/2016 A 925B1010 Prepare Request for SOW, Fee, Schedule, and Project Book 04/22/2015 A 04/29/2015 A 5B1020 Engage Design Consultant 04/30/2015 A 06/19/2015 A 20B1025 TA Approval Process 07/08/2015 A 07/16/2015 A 15B1030 Issue Design NTP 07/30/2015 A 0B1040 A/E Develops and Submits Final Engineering Report 07/30/2015 A 06/07/2016 A 120B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 07/30/2015 A 04/12/2016 A 95

30% Des30% Design 07/30/2015 A 12/01/2015 A 69B1060 A/E Prepares 30% Construction Documents 07/30/2015 A 10/09/2015 A 30B1070 Geotechnical Engineering Services 07/30/2015 A 10/09/2015 A 20B1080 Surveying Services 07/30/2015 A 10/09/2015 A 21B1100 30% CDs Submittal 10/09/2015 A 0B1120 30% Review (MDWASD/PSIP Team) 10/13/2015 A 12/01/2015 A 10

60% Des60% Design 10/13/2015 A 02/16/2016 A 40B1130 A/E Prepares 60% Construction Documents 10/13/2015 A 12/28/2015 A 20B1140 60% CDs Submittal 12/28/2015 A 0B1160 60% Review (MDWASD/PSIP Team) 12/29/2015 A 02/16/2016 A 10

90% Des90% Design 12/29/2015 A 06/07/2016 A 198B1170 A/E Prepares 90% Construction Documents 12/29/2015 A 03/28/2016 A 20B1180 90% CDs Submittal 03/28/2016 A 0B1190 90% Review (MDWASD/PSIP Team) 03/28/2016 A 04/12/2016 A 15B1200 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 04/22/2016 A 0B1210 90% RER(DERM)/FDEP Permit Review (Pump Station) 04/22/2016 A 05/18/2016 A 15B1220 90% RER (Building Dept) Permit Submittal 05/27/2016 A 0B1230 90% RER (Building Department) Permit Review 05/27/2016 A 06/07/2016 A 15B1240 90% PWWMD Permit Submittal (Pump Station) 04/22/2016 A 0B1250 90% PWWMD Permit Review (Pump Station) 04/22/2016 A 05/18/2016 A 15B1260 90% CD PM Comments Evaluation Completed 06/07/2016 A 0

100% De100% Design 05/25/2016 A 07/20/2016 A 45B1270 A/E Prepares 100% Construction Documents 05/25/2016 A 07/20/2016 A 10B1280 100% CDs Submittal 07/20/2016 A 0B1290 100% Review (MDWASD/PSIP Team) 05/25/2016 A 07/20/2016 A 10B1300 Design Completed 07/20/2016 A 0

MDWASDMDWASD Procurement 05/04/2016 A 08/04/2016 A 73B1305 Procurement Phase 05/04/2016 A 08/04/2016 A 73B1310 Submit CDs to MDWASD Procurement Division 05/04/2016 A 0B1312 Bid Notice Preparation Period 05/04/2016 A 05/24/2016 A 23B1314 Bid Notice 05/25/2016 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 05/26/2016 A 06/01/2016 A 10B1320 Pre-Bid Conference 06/02/2016 A 06/02/2016 A 1B1328 Bidders Prepare Bids for Submittal 06/03/2016 A 06/24/2016 A 15B1330 Bids Submittal 06/24/2016 A 0B1340 MDWASD/PSIP Team Bids Evaluation 06/27/2016 A 07/11/2016 A 15

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

06/15/2016 A, Project Closeout

Closeout PhaseProject Closed

08/01/2018, Basin 1068

08/01/2018, 100179 Pump Station 1068 Upgrade07/20/2016 A, Design

Design PhasePrepare Request for SOW, Fee, Schedule, and Project Book

Engage Design ConsultantTA Approval Process

Issue Design NTPA/E Develops and Submits Final Engineering Report

Final Engineering Report Review & Approval (MDWASD/PSIP Team)12/01/2015 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services30% CDs Submittal

30% Review (MDWASD/PSIP Team)02/16/2016 A, 60% Design

A/E Prepares 60% Construction Documents60% CDs Submittal

60% Review (MDWASD/PSIP Team)06/07/2016 A, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)

90% RER(DERM)/FDEP Permit Submittal (Pump Station)90% RER(DERM)/FDEP Permit Review (Pump Station)90% RER (Building Dept) Permit Submittal90% RER (Building Department) Permit Review90% PWWMD Permit Submittal (Pump Station)

90% PWWMD Permit Review (Pump Station)90% CD PM Comments Evaluation Completed

07/20/2016 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal

100% Review (MDWASD/PSIP Team)Design Completed08/04/2016 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids Evaluation

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 157 of 161 TASK filter: All Activities© Oracle Corporation

Page 158: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1350 Recommendation for Award Letter 07/11/2016 A 0B1355 Contract Award (Purchase Order Approval) 07/12/2016 A 08/04/2016 A 10

ConstrucConstruction 06/02/2016 A 06/19/2017 A 826B1360 Construction Phase 06/02/2016 A 06/19/2017 A 826B1364 MDWASD/PSIP Team Prepare for Pre-construction Meeting 07/12/2016 A 07/20/2016 A 15B1365 Pre-Construction Meeting 07/21/2016 A 07/21/2016 A 1B1368 WASD Issues NTP (PO to NTP) 08/04/2016 A 11/28/2016 A 57B1370 Construction NTP 11/28/2016 A 0B1400 Construction Operations 11/28/2016 A 06/19/2017 A 100B1402 Substantial Completion 06/19/2017 A 0

DesignerDesigner Construction Support Services 06/02/2016 A 06/19/2017 A 259B1410 Designer Construction Support Services 06/02/2016 A 06/19/2017 A 259

Project CProject Closeout 08/05/2016 A 08/01/2018 726B1445 Closeout Phase 08/05/2016 A 08/01/2018 726B1450 Issue SAC Letter 08/05/2016 A 0B1470 Final Release of Retainage - Construction Contract 08/01/2018 0B1480 Administrative Closeout 06/20/2017 A 08/01/2018 120B1490 Project Closed 08/01/2018 0

Basin 1201Basin 1201 08/26/2016 A 12/19/2019 1205

100181 Pu100181 Pump Station 1201 Upgrade 08/26/2016 A 12/19/2019 1205DesignDesign 08/26/2016 A 09/18/2018 748

B1000 Design Phase 08/26/2016 A 09/18/2018 748B1010 Prepare and Submit Design Package 08/26/2016 A 08/26/2016 A 5B1020 Engage Design Consultant 08/26/2016 A 10/07/2016 A 20B1022 TA Preparation 10/10/2016 A 10/10/2016 A 1B1024 TA Approval Process 10/11/2016 A 11/08/2016 A 20B1030 Issue Design NTP 11/10/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 11/10/2016 A 08/21/2018 65

30% Des30% Design 11/10/2016 A 01/29/2018 A 449B1060 A/E Prepares 30% Construction Documents 11/10/2016 A 02/13/2017 A 50B1100 30% CDs Submittal 02/13/2017 A 0B1120 30% Review (MDWASD/PSIP Team) 02/14/2017 A 03/21/2017 A 30B1122 SOW for Demo Exist. Generator Bldg., Odor Control System & N 03/22/2017 A 06/20/2017 A 30B1124 TA Rev 1 Preparation 06/21/2017 A 06/21/2017 A 1B1126 TA Rev 1 Approval Process 06/22/2017 A 08/17/2017 A 57B1128 A/E Prepares 30% Construction Documents (Re-Design) 09/21/2017 A 12/27/2017 A 64B1130 30% CDs Submittal (Re-Design) 12/27/2017 A 0B1132 30% Review (MDWASD/PSIP Team) (Re-Design) 12/28/2017 A 01/29/2018 A 30

90% Des90% Design 01/30/2018 A 08/21/2018 226B1170 A/E Prepares 90% Construction Documents 01/30/2018 A 02/26/2018 A 36B1180 90% CDs Submittal 02/26/2018 A 0B1190 90% Review (MDWASD/PSIP Team) 02/27/2018 A 03/30/2018 A 30B1200 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 05/03/2018 A 0B1210 90% RER(DERM)/FDEP Permit Review (Pump Station) 05/03/2018 A 07/16/2018 A 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 08/01/2018 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 08/01/2018 08/21/2018 21B1240 90% Doral - BD Permit Submittal (Pump Station) 07/17/2018 A 0B1250 90% Doral - BD Permit Review (Pump Station) 07/17/2018 A 08/06/2018 21B1260 90% CD PM Comments Evaluation Completed 08/21/2018 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

Recommendation for Award LetterContract Award (Purchase Order Approval)

06/19/2017 A, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-construction MeetingPre-Construction Meeting

WASD Issues NTP (PO to NTP)Construction NTP

Construction OperationsSubstantial Completion

06/19/2017 A, Designer Construction Support Services

Designer Construction Support Services08/01/2018, Project Closeout

Closeout PhaseIssue SAC Letter

Final Release of Retainage - Construction ContractAdministrative CloseoutProject Closed

12/19/2019, Basin 12

12/19/2019, 100181 09/18/2018, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval ProcessIssue Design NTP

Final Engineering Report Review & Approval (MDWASD/PSIP01/29/2018 A, 30% Design

A/E Prepares 30% Construction Documents30% CDs Submittal

30% Review (MDWASD/PSIP Team)SOW for Demo Exist. Generator Bldg., Odor Control System & New GeneratorTA Rev 1 Preparation

TA Rev 1 Approval ProcessA/E Prepares 30% Construction Documents (Re-Design)

30% CDs Submittal (Re-Design)30% Review (MDWASD/PSIP Team) (Re-Design)

08/21/2018, 90% Design

A/E Prepares 90% Construction Documents90% CDs Submittal

90% Review (MDWASD/PSIP Team)90% RER(DERM)/FDEP Permit Submittal (Pump Station)

90% RER(DERM)/FDEP Permit Review (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)

90% RER(Building Dept) Permit Review (Pump Station)90% Doral - BD Permit Submittal (Pump Station)90% Doral - BD Permit Review (Pump Station)90% CD PM Comments Evaluation Completed

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 158 of 161 TASK filter: All Activities© Oracle Corporation

Page 159: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

100% De100% Design 08/22/2018 09/18/2018 28B1270 A/E Prepares 100% Construction Documents 08/22/2018 09/04/2018 14B1280 100% CDs Submittal 09/04/2018 0B1290 100% Review (MDWASD/PSIP Teama) 09/05/2018 09/18/2018 14B1300 Design Completed 09/18/2018 0

MDWASDMDWASD Procurement 09/18/2018 12/31/2018 104B1305 Procurement Phase 09/18/2018 12/31/2018 104B1310 Submit CDs to MDWASD Procurement Division 09/18/2018* 0B1312 Bid Notice Preparation Period 09/19/2018 10/21/2018 33B1314 Bid Notice 10/21/2018 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conference 10/22/2018 11/04/2018 14B1320 Pre-Bid Conference 11/05/2018 11/05/2018 1B1328 Bidders Prepare Bids for Submittal 11/06/2018 11/26/2018 21B1330 Bids Submittal 11/26/2018 0B1340 MDWASD/PSIP Team Bids Evaluation 11/27/2018 12/17/2018 21B1350 Recommendation for Award Letter 12/17/2018 0B1355 Contract Award (Purchase Order Approval) 12/18/2018 12/31/2018 14

ConstrucConstruction 11/05/2018 08/21/2019 290B1360 Construction Phase 11/05/2018 08/21/2019 290B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 12/18/2018 01/07/2019 21B1364 Pre-Construction Meeting 01/08/2019 01/08/2019 1B1366 WASD Issues NTP (Pre-Const to NTP) 01/09/2019 02/22/2019 45B1369 WASD Issues NTP (PO to NTP) 01/01/2019 02/22/2019 53B1370 Construction NTP 02/23/2019 0B1400 Construction Operations 02/23/2019 08/21/2019 180B1402 Substantial Completion 08/21/2019 0

DesignerDesigner Construction Support Services 11/05/2018 08/21/2019 290B1410 Designer Construction Support Services 11/05/2018 08/21/2019 290

Project CProject Closeout 08/21/2019 12/19/2019 120B1445 Closeout Phase 08/21/2019 12/19/2019 120B1450 Issue SAC Letter 08/21/2019 0B1470 Final Release of Retainage - Construction Contract 08/21/2019 0B1480 Administrative Closeout 08/22/2019 12/19/2019 120B1490 Project Closed 12/19/2019 0

Basin 1306Basin 1306 05/09/2016 A 03/29/2019 1031

100182 Pu100182 Pump Station 1306(AM) Upgrade 05/09/2016 A 03/29/2019 1031DesignDesign 05/09/2016 A 07/28/2017 A 474

B1000 Design Phase 05/09/2016 A 07/28/2017 A 474B1010 Prepare and Submit Design Package 05/09/2016 A 05/11/2016 A 5B1020 Engage Design Consultant 05/11/2016 A 07/05/2016 A 20B1022 TA Preparation 07/06/2016 A 07/07/2016 A 1B1024 TA Approval Process 07/07/2016 A 09/12/2016 A 20B1030 Issue Design NTP 10/18/2016 A 0B1050 Final Engineering Report Review & Approval (MDWASD/PSIP Te 10/18/2016 A 06/30/2017 A 65

30% Des30% Design 10/18/2016 A 12/08/2016 A 55B1060 A/E Prepares 30% Construction Documents 10/18/2016 A 11/03/2016 A 30B1070 Geotechnical Engineering Services 10/18/2016 A 11/03/2016 A 20B1080 Surveying Services 10/18/2016 A 11/03/2016 A 15B1100 30% CDs Submittal 11/03/2016 A 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

09/18/2018, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal100% Review (MDWASD/PSIP Teama)Design Completed

12/31/2018, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferencePre-Bid Conference

Bidders Prepare Bids for SubmittalBids Submittal

MDWASD/PSIP Team Bids EvaluationRecommendation for Award LetterContract Award (Purchase Order Approval)

08/21/2019, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-ConstructioPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Construction NTPConstruction OperationsSubstantial Completion08/21/2019, Designer Construc

Designer Construction Support 12/19/2019, Project C

Closeout PhaseIssue SAC LetterFinal Release of Retainage - Co

Administrative CloseoProject Closed

03/29/2019, Basin 1306

03/29/2019, 100182 Pump Station 1306(A07/28/2017 A, Design

Design PhasePrepare and Submit Design Package

Engage Design ConsultantTA Preparation

TA Approval ProcessIssue Design NTP

Final Engineering Report Review & Approval (MDWASD/PSIP Team)12/08/2016 A, 30% Design

A/E Prepares 30% Construction DocumentsGeotechnical Engineering ServicesSurveying Services

30% CDs Submittal

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 159 of 161 TASK filter: All Activities© Oracle Corporation

Page 160: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

B1120 30% Review (MDWASD/PSIP Team) 11/07/2016 A 12/08/2016 A 1090% Des90% Design 11/07/2016 A 06/30/2017 A 264

B1170 A/E Prepares 90% Construction Documents 11/07/2016 A 01/04/2017 A 40B1172 90% Construction Documents Placed On-Hold 01/05/2017 A 01/24/2017 A 14B1174 A/E Prepares (Resumed) 90% Construction Documents 01/25/2017 A 02/28/2017 A 40B1180 90% CDs Submittal 02/28/2017 A 0B1190 90% Review (MDWASD/PSIP Team) 02/28/2017 A 03/15/2017 A 30B1200 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 04/19/2017 A 0B1210 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 04/19/2017 A 06/09/2017 A 45B1220 90% RER(Building Dept) Permit Submittal (Pump Station) 06/12/2017 A 0B1230 90% RER(Building Dept) Permit Review (Pump Station) 06/12/2017 A 06/30/2017 A 21B1260 90% CD PM Comments Evaluation Completed 06/30/2017 A 0B1262 MDWASD Union Concurrence Process 04/11/2017 A 05/01/2017 A 30

100% De100% Design 07/03/2017 A 07/28/2017 A 28B1270 A/E Prepares 100% Construction Documents 07/03/2017 A 07/28/2017 A 10B1280 100% CDs Submittal 07/28/2017 A 0B1290 100% Review (MDWASD/PSIP Team) 07/28/2017 A 07/28/2017 A 10B1300 Design Completed 07/28/2017 A 0

MDWASDMDWASD Procurement 07/28/2017 A 10/25/2017 A 76B1305 Procurement Phase 07/28/2017 A 10/25/2017 A 76B1310 Submit CDs to MDWASD Procurement Division 07/28/2017 A 0B1312 Bid Notice Preparation Period 07/31/2017 A 08/14/2017 A 33B1314 Bid Notice 08/14/2017 A 0B1316 MDWASD/PSIP Team Prepare for Pre-Bid Conferencce 08/15/2017 A 08/21/2017 A 14B1320 Pre-Bid Conference 08/22/2017 A 08/22/2017 A 1B1328 Bidders Prepare Bids for Submittal 08/23/2017 A 09/14/2017 A 21B1330 Bids Submittal 09/14/2017 A 0B1340 MDWASD/PSIP Team Bids Evaluation 09/15/2017 A 10/03/2017 A 21B1350 Recommendation for Award Letter 10/03/2017 A 0B1355 Contract Award (Purchase Order Approval) 10/04/2017 A 10/25/2017 A 14

ConstrucConstruction 08/22/2017 A 11/29/2018 442B1360 Construction Phase 08/22/2017 A 11/29/2018 442B1362 MDWASD/PSIP Team Prepare for Pre-Construction Meeting 10/04/2017 A 11/08/2017 A 21B1365 Pre-Construction Meeting 11/09/2017 A 11/09/2017 A 1B1366 WASD Issues NTP (Pre-Const to NTP) 11/10/2017 A 07/01/2018 A 45B1368 WASD Issues NTP (PO to NTP) 10/26/2017 A 07/01/2018 A 57B1370 Construction NTP 07/02/2018 A 0B1400 Construction Operations 07/02/2018 A 11/29/2018 151B1402 Substantial Completion 11/29/2018 0

DesignerDesigner Construction Support Services 08/22/2017 A 11/29/2018 246B1410 Designer Construction Support Services 08/22/2017 A 11/29/2018 246

Project CProject Closeout 11/29/2018 03/29/2019 120B1445 Closeout Phase 11/29/2018 03/29/2019 120B1450 Issue SAC Letter 11/29/2018 0B1470 Final Release of Retainage - Construction Contract 11/29/2018 0B1480 Administrative Closeout 11/30/2018 03/29/2019 120B1490 Project Closed 03/29/2019 0

Basin 1311Basin 1311 09/01/2015 A 03/31/2017 A 913

100183 Pu100183 Pump Station 1311 Upgrade 09/01/2015 A 03/31/2017 A 913

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

30% Review (MDWASD/PSIP Team)06/30/2017 A, 90% Design

A/E Prepares 90% Construction Documents90% Construction Documents Placed On-Hold

A/E Prepares (Resumed) 90% Construction Documents90% CDs Submittal90% Review (MDWASD/PSIP Team)

90% RER(DERM)/FDEP Permit Submittal (Pump Station)90% RER(DERM)/FDEP Permit Submittal (Pump Station)90% RER(Building Dept) Permit Submittal (Pump Station)90% RER(Building Dept) Permit Review (Pump Station)

90% CD PM Comments Evaluation CompletedMDWASD Union Concurrence Process

07/28/2017 A, 100% Design

A/E Prepares 100% Construction Documents100% CDs Submittal

100% Review (MDWASD/PSIP Team)Design Completed

10/25/2017 A, MDWASD Procurement

Procurement PhaseSubmit CDs to MDWASD Procurement Division

Bid Notice Preparation PeriodBid NoticeMDWASD/PSIP Team Prepare for Pre-Bid ConferenccePre-Bid Conference

Bidders Prepare Bids for SubmittalBids SubmittalMDWASD/PSIP Team Bids Evaluation

Recommendation for Award LetterContract Award (Purchase Order Approval)

11/29/2018, Construction

Construction PhaseMDWASD/PSIP Team Prepare for Pre-Construction MeetingPre-Construction Meeting

WASD Issues NTP (Pre-Const to NTP)WASD Issues NTP (PO to NTP)

Construction NTPConstruction OperationsSubstantial Completion11/29/2018, Designer Construction Support Services

Designer Construction Support Services03/29/2019, Project Closeout

Closeout PhaseIssue SAC LetterFinal Release of Retainage - Construction Contract

Administrative CloseoutProject Closed

03/31/2017 A, Basin 1311

03/31/2017 A, 100183 Pump Station 1311 Upgrade

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 160 of 161 TASK filter: All Activities© Oracle Corporation

Page 161: PSIP PROJECTS DETAILED SCHEDULE PROGRESS REPORT …Design 08/01/2018 06/29/2019 333 B1000Design Phase 08/01/2018 06/29/2019 333 B1005Prepare and Submit Design Package 08/01/2018 08/07/2018

Activity ID Activity Name Start Finish OriginalDuration

DesignDesign 02/01/2016 A 10/25/2016 A 166B1000 Design Phase 02/01/2016 A 10/25/2016 A 166B1040 A/E Develops and Submits Final Engineering Report 02/01/2016 A 04/20/2016 A 11B1050 Final Engineering Report Review & Approval (PSIP Team) 04/21/2016 A 06/24/2016 A 5

90% Des90% Design 07/22/2016 A 10/25/2016 A 15B1160 90% RER(DERM)/FDEP Permit Submittal (Pump Station) 07/22/2016 A 0B1170 90% RER(DERM)/FDEP Permit Review (Pump Station) 07/22/2016 A 10/25/2016 A 15

MDWASDMDWASD Procurement 09/01/2015 A 01/19/2016 A 99B1265 Procurement Phase 09/01/2015 A 01/19/2016 A 99B1285 Bidders Prepare Bids for Submittal 09/01/2015 A 09/01/2015 A 3B1290 Bids Submittal 09/01/2015 A 0B1310 Recommendation for Award Letter 09/02/2015 A 0B1315 Contract Award (Purchase Order Approval) 09/02/2015 A 09/02/2015 A 1B1317 Pumps Manufacturing and Delivery 09/02/2015 A 01/19/2016 A 99

ConstrucConstruction 10/26/2016 A 11/23/2016 A 31B1320 Construction Phase 10/26/2016 A 11/23/2016 A 31B1330 Construction NTP 10/26/2016 A 0B1360 Construction Operations 10/26/2016 A 11/23/2016 A 11B1365 Substantial Completion 11/23/2016 A 0

Project CProject Closeout 11/24/2016 A 03/31/2017 A 577B1405 Closeout Phase 11/24/2016 A 03/31/2017 A 577B1410 Issue SAC Letter 02/16/2017 A 0B1440 Administrative Closeout 11/24/2016 A 03/31/2017 A 30B1450 Project Closed 03/31/2017 A 0

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q32014 2015 2016 2017 2018 2019 2020

10/25/2016 A, Design

Design PhaseA/E Develops and Submits Final Engineering Report

Final Engineering Report Review & Approval (PSIP Team)10/25/2016 A, 90% Design

90% RER(DERM)/FDEP Permit Submittal (Pump Station)90% RER(DERM)/FDEP Permit Review (Pump Station)

01/19/2016 A, MDWASD Procurement

Procurement PhaseBidders Prepare Bids for Submittal

Bids SubmittalRecommendation for Award Letter

Contract Award (Purchase Order Approval)Pumps Manufacturing and Delivery

11/23/2016 A, Construction

Construction PhaseConstruction NTP

Construction OperationsSubstantial Completion

03/31/2017 A, Project Closeout

Closeout PhaseIssue SAC Letter

Administrative CloseoutProject Closed

Remaining Level of EffortProject Baseline Bar

Actual WorkRemaining Work

Critical Remaining WorkBaseline Milestone

LOEMilestone

Page 161 of 161 TASK filter: All Activities© Oracle Corporation