PSB beam dump replacement project status. PSB LS1 coordination meeting Alba Sarri ó 04 -Dec-2013. Work planning. Preparation of the area: dismantling of beam line equipment (BT, BTY, BTM ) → 15/07/13 – 02/08/13 - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: PSB beam dump replacement project status](https://reader035.vdocuments.mx/reader035/viewer/2022062217/56813ac0550346895da2cf16/html5/thumbnails/1.jpg)
PSB beam dump replacement project status
PSB LS1 coordination meetingAlba Sarrió
04-Dec-2013
![Page 2: PSB beam dump replacement project status](https://reader035.vdocuments.mx/reader035/viewer/2022062217/56813ac0550346895da2cf16/html5/thumbnails/2.jpg)
Work planning• Preparation of the area: dismantling of beam line equipment
(BT, BTY, BTM) → 15/07/13 – 02/08/13• Disposal operations of existing dump and its shielding:
dismantling and storage in ISR → 05/08/13 – 29/08/13• Cleaning and decontamination of cavity → 30/08/13 –
19/09/13• Installation of new beam dump and its shielding → 30/09/13
– 08/10/13• Re-assembly of BTM beam line equipment → 21/10/13 –
01/11/13• Installation of BTY-QFO108 new support → 26/11/13
![Page 3: PSB beam dump replacement project status](https://reader035.vdocuments.mx/reader035/viewer/2022062217/56813ac0550346895da2cf16/html5/thumbnails/3.jpg)
Tasks to be done• Re-assembly BTY line elements:
– Adjustments in BTY-QFO108 new support: drilling holes, attach black plate (magnet support): 04/12/13
– Installation BTY magnets (BTY-QFO108 and BTY-QDE104) and stopper: 04/12/13 – 05/12/13
– Installation vacuum pipes in BTY line– Survey BTY line– Painting floor and walls
![Page 4: PSB beam dump replacement project status](https://reader035.vdocuments.mx/reader035/viewer/2022062217/56813ac0550346895da2cf16/html5/thumbnails/4.jpg)
Tasks to be done• Re-assembly BTY line elements:
– Installation cooling system: foreseen for 02/12/13 – 13/12/13, delayed until January, no confirmed date yet.
– Re-assembly stairs: a modification is also needed, no design provided yet.– Re-assembly cable rack– Re-assembly cupboard
![Page 5: PSB beam dump replacement project status](https://reader035.vdocuments.mx/reader035/viewer/2022062217/56813ac0550346895da2cf16/html5/thumbnails/5.jpg)
Tasks to be done
![Page 6: PSB beam dump replacement project status](https://reader035.vdocuments.mx/reader035/viewer/2022062217/56813ac0550346895da2cf16/html5/thumbnails/6.jpg)
Planning: tasks to be completed
![Page 7: PSB beam dump replacement project status](https://reader035.vdocuments.mx/reader035/viewer/2022062217/56813ac0550346895da2cf16/html5/thumbnails/7.jpg)
Thanks for your attention