Providing Service toHigh-rise Condominiums
PresenterCharles L. Kahanek
SWEDE ConferenceHorseshoe Bay, TexasMay 2008
Houston High-rise Condominiums
Standard Service
• High Rise Building:– 6 Floors or more
• Dedicated Underground Area:– Automatic Transfer– Pad mount equipment at grade– Two Service Voltages
• Overhead / Underground Area:– Pad mount equipment at grade– Two Service Voltages
Modular Metering
• General Requirements:– Single Phase Meters Only– 2, 3, 4 or 5 high meter centers, 6 high approval based on overall height– All openings must have meter installed – no blanks– 120/240 or 120/208– Ring Type Enclosures– No Bypass Switches– Must be UL Approved
Providing Service toHigh-rise Condominiums
Continues to Change
MULTI-USE FACILITIES
• CONDOMINIUMS– Penthouses– Spa/Gym– Pool
• HOTEL– Banquet/Meeting Rooms– Food Service
• RETAIL• PARKING GARAGE