PROCESS OF MBA PROJECTS AT LUMS (Modified)
Groups finalization last week Aug
Project Proposals sent to Students Sep 1
st week
Groups Select Faculty Advisor Sep, 2014
Groups contact Client Orgn; DISCUSS project details Sep, 2014
Client assesses each Group; offers project to a Group Sep, 2014
Group ACCEPTS
Client Offer
NO
YES
Group starts working on Terms of Reference (TOR)
Submission of Draft TOR 3rd Oct, 2014
Presentation of TOR 17th Oct, 2014
Submission of FINAL TOR 24th Oct, 2014
Clients projects not taken up; regret letters 1st wk Nov 2014
Interim Presentations 30th Jan 2015
Printing of Brochure to Showcase MBA Projects 30th May 2015
Submission of Executive Summary to Showcase MBA Projects 15th May 2015
Final Report Submission 10th May, 2015
FINAL PRESENTATIONS 15th 30th Apr, 2015
Final Draft Report 1st week Apr 2015
Interim Report Submission 3rd Feb 2015