Proposal for Solar Energy Development Project Request for Information Prepared By: Gerard deLisser, VP Development Miller Bros 301 Alan Wood Rd I Conshohocken, PA 19428 Direct 610-832-1000 Mobil 917-687-2620 [email protected] March 13, 2015 Page 178 REQUEST FOR INFORMATION RESPONSES

Upload: others

Post on 16-Aug-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Proposal for Solar Energy Development Project …...Proposal for Solar Energy Development Project Request for Information Prepared By: Gerard deLisser, VP Development Miller Bros 301

Proposal for

Solar Energy Development Project

Request for Information

Prepared By: Gerard deLisser, VP Development

Miller Bros 301 Alan Wood Rd I Conshohocken, PA 19428

Direct 610-832-1000 Mobil 917-687-2620

[email protected]

March 13, 2015

Page 178REQUEST FOR INFORMATION RESPONSES

Page 2: Proposal for Solar Energy Development Project …...Proposal for Solar Energy Development Project Request for Information Prepared By: Gerard deLisser, VP Development Miller Bros 301

March 13, 2015 Alexandra Lauzon Virginia Office of Public-Private Partnerships 600 E. Main Street, Suite 2120 Richmond, VA 23219 [email protected] 804-786-0441

RFI RESPONSE: Solar Energy Development Project Alexandra: On behalf of our team including Marina Energy, LLC (a division of South Jersey Industries, SJI) and Miller Bros, we are pleased to submit our information to the Virginia Office of Public-Private Partnerships

in response to your RFI: Solar Energy Development Project. I trust you will find that Marina Energy, LLC will address your goal of a successful closing transaction in a timely fashion and thereby assist in obtaining renewable energy savings and land use in the most cost-effective, safe and reliable manner. Beyond our desire to offer the lowest possible cost of power, in considering our response to your solicitation we also identified further goals that we view as key to your efforts:

I. Choosing a partner with the financial strength, surety of execution and sophistication to close the transaction quickly and minimize the long-term risks to your stakeholders;

II. Selecting a team with the proven construction and engineering “know-how” to complete the project on time and minimize the risk that your program will fail to live up to its production and savings targets;

We hope that our proposal will best help you to achieve these objectives.

1. Financial Strength and Surety of Execution. Your Power Purchase Agreement (PPA) provider needs both the financial strength to enable it to perform its obligations to you and the financial sophistication to understand and optimize a transaction of this complexity. Marina Energy has successfully developed, financed, designed, installed, owns, operates and maintains over 150 commercial and municipal solar PPA projects. Marina Energy, LLC is a division of the public company South Jersey Industries (NYSE: SJI). Marina Energy professionals have decades of experience in municipal energy projects providing specific understanding of the complex legal, tax and regulatory issues associated with transactions, and to date have completed in excess of over 150 MW’s. And, have demonstrated their ability to execute PPA’s with public and private entities. Marina Energy agrees to fully comply with all applicable laws and codes if awarded the contract and further agrees to negotiate in good faith to craft a fair, reasonable and acceptable PPA.

Page 179REQUEST FOR INFORMATION RESPONSES

Page 3: Proposal for Solar Energy Development Project …...Proposal for Solar Energy Development Project Request for Information Prepared By: Gerard deLisser, VP Development Miller Bros 301

2. Construction and Engineering “Know-How”. Miller Brothers executes utility scale medium and high voltage, substation and transmission construction. Our proven utility construction model includes: construction project management expertise, full construction capabilities, 25+ years of audited financial statements, 200+ pieces of heavy equipment, $100+M bonding capacity. We are one of few utility contractors that can simultaneously self-perform multiple utility scale projects. Miller Bros. is experienced in all aspects of the utility construction industry including design, engineering and construction of large scale utility and renewable energy. Having completed over 100 MW’s of solar construction, Miller Brothers provides turnkey Engineering, Procurement & Construction (EPC) services, offering on-going back-end operations and maintenance support after project completion. Miller Brothers ensures a seamless integration throughout all project phases, resulting in an accelerated schedule, uncompromising cost control in a safe working environment.

Given the diverse requirements to execute a solar project, we have brought together a team whose qualifications and experience are described in your RFI. Working together with these firms will enable us to complete your project on time and on budget, in a safe working environment. Sincerely,

John Spurlock Marina Energy, LLC One North White Horse Pike Hammonton, NJ 08037 609-568-9028 [email protected]

Gerard deLisser Miller Bros. 301 Alan Wood Rd Conshohocken, PA 19428 610-832-1000 [email protected]

Page 180REQUEST FOR INFORMATION RESPONSES

Page 4: Proposal for Solar Energy Development Project …...Proposal for Solar Energy Development Project Request for Information Prepared By: Gerard deLisser, VP Development Miller Bros 301

Page 181REQUEST FOR INFORMATION RESPONSES

Page 7: Proposal for Solar Energy Development Project …...Proposal for Solar Energy Development Project Request for Information Prepared By: Gerard deLisser, VP Development Miller Bros 301

Ted Pettinelli

General Manager, Operations

Solar Team

Fred Rohs

Manager, Solar Operations

Dan Streit

Construction Manager

Barry Miller

Manager of Contracts and Compliance

Freddy Tejeda

Supervisor, Solar Operations

Kyle Tress

Staff Engineer

Nancy Ricci

Billing, Invoicing

Jennifer Kinch

Accounting

Marina has a dedicated team for solar development and operations.

Page 184REQUEST FOR INFORMATION RESPONSES

Page 8: Proposal for Solar Energy Development Project …...Proposal for Solar Energy Development Project Request for Information Prepared By: Gerard deLisser, VP Development Miller Bros 301

Marina Finances

Solar Project

(ITC Credit goes

to Marina)

Solar Project Built

at Customers Location

(EPC Contractor)

Solar Array Generates

Power (SREC Retained

by Marina )

Marina Sells electricity to

Customer (PPA or Merchant)

Marina owns all of their solar sites and sells the electricity to host customers.

Page 185REQUEST FOR INFORMATION RESPONSES

Page 9: Proposal for Solar Energy Development Project …...Proposal for Solar Energy Development Project Request for Information Prepared By: Gerard deLisser, VP Development Miller Bros 301

Pre-Development

Development

Closed Project

O&M Contract

Compliance PMI

System

Monitoring

Marina is present during the entire project life span.

Development Team

Operations Team

Page 186REQUEST FOR INFORMATION RESPONSES

Page 10: Proposal for Solar Energy Development Project …...Proposal for Solar Energy Development Project Request for Information Prepared By: Gerard deLisser, VP Development Miller Bros 301

Bi-Monthly Production Reports

Daily Predicted Vs. Actual Reports

Dispatch Services Active Monitoring

PMI and Site Inspections

Marina performs all O&M and system evaluation of their solar fleet.

Page 187REQUEST FOR INFORMATION RESPONSES

Page 12: Proposal for Solar Energy Development Project …...Proposal for Solar Energy Development Project Request for Information Prepared By: Gerard deLisser, VP Development Miller Bros 301

Marina has made substantial financial investments into solar starting in 2009.

10

32

66

105

150

130

2009 2010 2011 2012 2013 2014

Millions of Dollars

Page 189REQUEST FOR INFORMATION RESPONSES

Page 13: Proposal for Solar Energy Development Project …...Proposal for Solar Energy Development Project Request for Information Prepared By: Gerard deLisser, VP Development Miller Bros 301

*2015 and 2016 continued growth

Marina is expected to continue its financial investments into solar.

10

32

66

105

150

130

2009 2010 2011 2012 2013 2014 2015* 2016*

Millions of Dollars

Page 190REQUEST FOR INFORMATION RESPONSES

Page 14: Proposal for Solar Energy Development Project …...Proposal for Solar Energy Development Project Request for Information Prepared By: Gerard deLisser, VP Development Miller Bros 301

1 7

23

49

97

149

2009 2010 2011 2012 2013 2014

MW Solar Installed

The size of the Marina solar fleet has grown and expanded since 2009.

Page 191REQUEST FOR INFORMATION RESPONSES

Page 15: Proposal for Solar Energy Development Project …...Proposal for Solar Energy Development Project Request for Information Prepared By: Gerard deLisser, VP Development Miller Bros 301

*2015 and 2016 continued growth

The size of the Marina solar fleet is expected to have continued growth.

1 7 23

49

97

149

2009 2010 2011 2012 2013 2014 2015* 2016*

MW Solar Installed

Page 192REQUEST FOR INFORMATION RESPONSES

Page 16: Proposal for Solar Energy Development Project …...Proposal for Solar Energy Development Project Request for Information Prepared By: Gerard deLisser, VP Development Miller Bros 301

Marina owns three different types of solar systems across their fleet.

3%

37% 60%

Canopy

Roof

Ground

Page 193REQUEST FOR INFORMATION RESPONSES

Page 17: Proposal for Solar Energy Development Project …...Proposal for Solar Energy Development Project Request for Information Prepared By: Gerard deLisser, VP Development Miller Bros 301

87%

11%

1%

NJ

MA

VT

State MW

Installed

NJ

130 MW

MA 17 MW

VT 2 MW

Marina is financially invested in three different solar markets.

Page 194REQUEST FOR INFORMATION RESPONSES

Page 18: Proposal for Solar Energy Development Project …...Proposal for Solar Energy Development Project Request for Information Prepared By: Gerard deLisser, VP Development Miller Bros 301

New Jersey Portfolio

Marina has expanded outward and has solar sites across NJ, MA, and VT.

Page 195REQUEST FOR INFORMATION RESPONSES

Page 19: Proposal for Solar Energy Development Project …...Proposal for Solar Energy Development Project Request for Information Prepared By: Gerard deLisser, VP Development Miller Bros 301

Massachusetts and Vermont Portfolio

Marina has expanded outward and has solar sites across NJ, MA, and VT.

Page 196REQUEST FOR INFORMATION RESPONSES

Page 20: Proposal for Solar Energy Development Project …...Proposal for Solar Energy Development Project Request for Information Prepared By: Gerard deLisser, VP Development Miller Bros 301

46%

36%

13%

5%

Commercial

Education

Municipalities

Merchant Plants

By number of customers

Marina supplies a wide variety of customers with solar energy.

Page 197REQUEST FOR INFORMATION RESPONSES

Page 21: Proposal for Solar Energy Development Project …...Proposal for Solar Energy Development Project Request for Information Prepared By: Gerard deLisser, VP Development Miller Bros 301

47%

20%

13%

20%

Commercial

Education

Municipalities

Merchant Plants

By Size (MW)

Marina supplies a wide variety of customers with solar energy.

Page 198REQUEST FOR INFORMATION RESPONSES

Page 22: Proposal for Solar Energy Development Project …...Proposal for Solar Energy Development Project Request for Information Prepared By: Gerard deLisser, VP Development Miller Bros 301

Marina has helped customers meet their sustainability goals with solar.

Page 199REQUEST FOR INFORMATION RESPONSES

Page 23: Proposal for Solar Energy Development Project …...Proposal for Solar Energy Development Project Request for Information Prepared By: Gerard deLisser, VP Development Miller Bros 301

Page 200REQUEST FOR INFORMATION RESPONSES

Page 24: Proposal for Solar Energy Development Project …...Proposal for Solar Energy Development Project Request for Information Prepared By: Gerard deLisser, VP Development Miller Bros 301

ACCC 2MW

Page 201REQUEST FOR INFORMATION RESPONSES

Page 25: Proposal for Solar Energy Development Project …...Proposal for Solar Energy Development Project Request for Information Prepared By: Gerard deLisser, VP Development Miller Bros 301

Frankford 10 MW

Page 202REQUEST FOR INFORMATION RESPONSES

Page 26: Proposal for Solar Energy Development Project …...Proposal for Solar Energy Development Project Request for Information Prepared By: Gerard deLisser, VP Development Miller Bros 301

GCIT 638 kW

Page 203REQUEST FOR INFORMATION RESPONSES

Page 27: Proposal for Solar Energy Development Project …...Proposal for Solar Energy Development Project Request for Information Prepared By: Gerard deLisser, VP Development Miller Bros 301

Holland 3.5 MW

Page 204REQUEST FOR INFORMATION RESPONSES

Page 28: Proposal for Solar Energy Development Project …...Proposal for Solar Energy Development Project Request for Information Prepared By: Gerard deLisser, VP Development Miller Bros 301

NFI 994 kW

Page 205REQUEST FOR INFORMATION RESPONSES

Page 29: Proposal for Solar Energy Development Project …...Proposal for Solar Energy Development Project Request for Information Prepared By: Gerard deLisser, VP Development Miller Bros 301

Brickyard 2 MW

Page 206REQUEST FOR INFORMATION RESPONSES

Page 30: Proposal for Solar Energy Development Project …...Proposal for Solar Energy Development Project Request for Information Prepared By: Gerard deLisser, VP Development Miller Bros 301

Rockland 2 MW

Page 207REQUEST FOR INFORMATION RESPONSES