WESTERN TURNER SYNCLINE CONCRETE WORKS CLIENT Rio Tinto Iron Ore PROJECT Western Turner Syncline Concrete Works LOCATION Tom Price, Western Australia VALUE AU $94 million COMMENCED May 2012 COMPLETED November 2013 PROJECT SUMMARY NRW undertook the concrete and civil works at Western Turner Syncline Mine. The scope of works included the installation of approximately 21,000 cubic metres of concrete for the following areas: Primary crusher Overland conveyor Plant utilities The Project also included the erection of a corrugated steel arch, structural earthworks, fill around the primary crusher, fencing and bollards. The Project ran for approximately 82 weeks and had a peak workforce of 225 personnel. PFS-C048 Completed

Upload: damian-brandon

Post on 12-Apr-2017

14 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Project - WTS Concrete

WESTERN TURNERSYNCLINE CONCRETE WORKS

CLIENTRio Tinto Iron Ore

PROJECT Western Turner Syncline Concrete Works

LOCATIONTom Price, Western Australia

VALUEAU $94 million

COMMENCEDMay 2012

COMPLETEDNovember 2013

PROJECT SUMMARY

NRW undertook the concrete and civil works at Western Turner Syncline Mine. The scope of works included the installation of approximately 21,000 cubic metres of concrete for the following areas:

• Primary crusher• Overland conveyor • Plant utilities

The Project also included the erection of a corrugated steel arch, structural earthworks, fill around the primary crusher, fencing and bollards.

The Project ran for approximately 82 weeks and had a peak workforce of 225 personnel.