project scheduling: pert-cpm. pert (program evaluation and review technique) and cpm (critical path...

32
Project Scheduling: PERT- CPM

Upload: jade-burgamy

Post on 31-Mar-2015

237 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: Project Scheduling: PERT-CPM. PERT (Program evaluation and review technique) and CPM (Critical Path Method) makes a managerial technique to help planning

Project Scheduling: PERT-CPM

Page 2: Project Scheduling: PERT-CPM. PERT (Program evaluation and review technique) and CPM (Critical Path Method) makes a managerial technique to help planning

PERT (Program evaluation and review

technique) and CPM (Critical Path Method)

makes a managerial technique to help

planning and displaying the coordination of

all the activities.

Page 3: Project Scheduling: PERT-CPM. PERT (Program evaluation and review technique) and CPM (Critical Path Method) makes a managerial technique to help planning

ActivityActivity

DescriptionImmediate

PredecessorsEstimated

TimeABCDEFGHIJKLMN

-ABCCED

E,GCF,IJJH

K,L

2 weeks4 weeks

10 weeks6 weeks4 weeks5 weeks7 weeks9 weeks7 weeks8 weeks4 weeks5 weeks2 weeks6 weeks

ExcavateLay the foundationPut up the rough wallPut up the roofInstall the exterior plumbingInstall the interior plumbingPut up the exterior sidingDo the exterior paintingDo the electrical workPut up the wallboardInstall the flooringDo the interior paintingInstall the exterior fixturesInstall the interior fixtures

Page 4: Project Scheduling: PERT-CPM. PERT (Program evaluation and review technique) and CPM (Critical Path Method) makes a managerial technique to help planning

Immediate predecessors:

For any given activity, its immediate predecessors are the activities that must be completed by no later than the starting time of the given activity.

Page 5: Project Scheduling: PERT-CPM. PERT (Program evaluation and review technique) and CPM (Critical Path Method) makes a managerial technique to help planning

AOA (Activity-on-Arc):

Each activity is represented by an arc.

The arcs are used to show the precedence relationships between the activities.

Page 6: Project Scheduling: PERT-CPM. PERT (Program evaluation and review technique) and CPM (Critical Path Method) makes a managerial technique to help planning

AB

C

E

M N

START

FINISH

H

G

D

J

I

F

LK

410

4 76

7

9

8

54

62

nodearc

5

0

0(Estimated)Time

2

Page 7: Project Scheduling: PERT-CPM. PERT (Program evaluation and review technique) and CPM (Critical Path Method) makes a managerial technique to help planning

START A B C D G H M FINISH

2 + 4 + 10 + 6 + 7 + 9 + 2 = 40 weeks

START A B C E F J K N FINISH

2 + 4 + 10 + 4 + 5 + 8 + 4 + 6 = 43 weeks

START A B C E F J L N FINISH

2 + 4 + 10 + 4 + 5 + 8 + 5 + 6 = 44 weeks

Path and Length

Critical Path

Page 8: Project Scheduling: PERT-CPM. PERT (Program evaluation and review technique) and CPM (Critical Path Method) makes a managerial technique to help planning

Critical Path:

A project time equals the length of the longest path through a project network. The longest path is called “critical path”.

Activities on a critical path are the critical bottleneck activities where any delay in their completion must be avoided to prevent delaying project completion.

Page 9: Project Scheduling: PERT-CPM. PERT (Program evaluation and review technique) and CPM (Critical Path Method) makes a managerial technique to help planning

ES :

Earliest Start time for a particular activity

EF :

Earliest Finish time for a particular activity

Page 10: Project Scheduling: PERT-CPM. PERT (Program evaluation and review technique) and CPM (Critical Path Method) makes a managerial technique to help planning

AB

C

E

MN

START

FINISH

H

G

D

J

I

F

LK

4

10

4 76

7

98

54

62

5

0

0

2ES=0EF=2

ES=2EF=6ES=6

EF=16

ES=16EF=20

ES=16EF=23

ES=16EF=22ES=22EF=29

ES=20EF=25

Page 11: Project Scheduling: PERT-CPM. PERT (Program evaluation and review technique) and CPM (Critical Path Method) makes a managerial technique to help planning

If an activity has only a single immediate

predecessor, then ES = EF for the

immediate predecessor.

Earliest Start Time Rule:The earliest start time of an activity is equal to the largest of the earliest finish times of its immediate predecessors.

ES = largest EF of the immediate predecessors.

Page 12: Project Scheduling: PERT-CPM. PERT (Program evaluation and review technique) and CPM (Critical Path Method) makes a managerial technique to help planning

AB

C

E

MN

START

FINISH

H

G

D

J

I

F

LK

4

10

4 76

7

98

54

62

5

0

0

2ES=0EF=2

ES=2EF=6

ES=6EF=1

ES=16EF=20

ES=16EF=23

ES=16EF=22ES=22EF=29

ES=20EF=25 ES=25

EF=33ES=33EF=37

ES=33EF=38

ES=38EF=44

ES=29EF=38

ES=38EF=40

ES=44EF=44

Page 13: Project Scheduling: PERT-CPM. PERT (Program evaluation and review technique) and CPM (Critical Path Method) makes a managerial technique to help planning

Latest Finish Time Rule:The latest finish time of an activity is equal to the smallest of the latest finish times of its immediate successors.

LF = the smallest LS of immediate successors.

LS:

Latest Start time for a particular activity

LF:

Latest Finish time for a particular activity

Page 14: Project Scheduling: PERT-CPM. PERT (Program evaluation and review technique) and CPM (Critical Path Method) makes a managerial technique to help planning

AB

C

E

MN

START

FINISH

H

G

D

J

I

F

LK

4

10

4 76

7

98

54

62

5

0

0

2

LS=0LF=0

LS=0LF=2

LS=2LF=6

LS=6LF=16

LS=16LF=20

LS=20LF=25

LS=25LF=33

LS=18LF=25

LS=34LF=38

LS=33LF=38

LS=38LF=44

LS=33LF=42

LS=42LF=44

LS=26LF=33

LS=20LF=26

LS=44LF=44

Page 15: Project Scheduling: PERT-CPM. PERT (Program evaluation and review technique) and CPM (Critical Path Method) makes a managerial technique to help planning

Latest

Start Time

Earliest

Start Time

S=( 2, 2 )F=( 6, 6 )

Latest

Finish Time

Earliest

Finish Time

Page 16: Project Scheduling: PERT-CPM. PERT (Program evaluation and review technique) and CPM (Critical Path Method) makes a managerial technique to help planning

S=(20,20)F=(25,25)

AB

C

E

MN

START

FINISH

H

G

D

J

I

LK

4

10

4 76

7

9

8

54

62

5

0

0

2

S=(0,0)F=(0,0)S=(0,0)

F=(2,2) S=(2,2)F=(6,6)

S=(16,16)F=(20,20)

S=(25,25)F=(33,33)

S=(16,18)F=(23,25)

S=(33,34)F=(37,38)

S=(33,33)F=(38,38)

S=(38,38)F=(44,44)

S=(29,33)F=(38,42)

S=(38,42)F=(40,44)

S=(22,26)F=(29,33)

S=(16,20)F=(22,26)

S=(44,44)F=(44,44)

F

S=(6,6)F=(16,16)

Critical Path

Page 17: Project Scheduling: PERT-CPM. PERT (Program evaluation and review technique) and CPM (Critical Path Method) makes a managerial technique to help planning

Slack:

A difference between the latest finish time and

the earliest finish time.

Slack = LF - EF

Each activity with zero slack is on a critical

path.

Any delay along this path delays a whole

project completion.

Page 18: Project Scheduling: PERT-CPM. PERT (Program evaluation and review technique) and CPM (Critical Path Method) makes a managerial technique to help planning

Three-Estimates

Most likely Estimate (m)

= an estimate of the most likely value of time.

Optimistic Estimate (o)

= an estimate of time under the most favorable

conditions.

Pessimistic Estimate (p)

= an estimate of time under the most

unfavorable conditions.

Page 19: Project Scheduling: PERT-CPM. PERT (Program evaluation and review technique) and CPM (Critical Path Method) makes a managerial technique to help planning

22

6

4

op

pmo

o pmo

Beta distribution

Mean :

Variance:

Page 20: Project Scheduling: PERT-CPM. PERT (Program evaluation and review technique) and CPM (Critical Path Method) makes a managerial technique to help planning

Mean critical path:A path through the project network becomes the critical path if each activity time equals its mean.

Activity OE M PE Mean Variance

A

B

C

2

13

2

9

1

2

6

3

8

18

2

4

10

9

1

4

1

OE: Optimistic EstimateM : Most Likely EstimatePE: Pessimistic Estimate

Page 21: Project Scheduling: PERT-CPM. PERT (Program evaluation and review technique) and CPM (Critical Path Method) makes a managerial technique to help planning

Activities on Mean Critical Path Mean Variance

A

B

C

E

F

J

L

N

2

4

10

4

5

8

5

6

1

4

1

1

1

91

Project Time 44p 92 p

94

94

Page 22: Project Scheduling: PERT-CPM. PERT (Program evaluation and review technique) and CPM (Critical Path Method) makes a managerial technique to help planning

Approximating Probability of Meeting Deadline

T = a project time has a normal distribution

with mean and ,

d = a deadline for the project = 47 weeks.

44p 92 p

13

4447

p

pdK

Assumption:A probability distribution of project time is a normal distribution.

Page 23: Project Scheduling: PERT-CPM. PERT (Program evaluation and review technique) and CPM (Critical Path Method) makes a managerial technique to help planning

Using a table for a standard normal distribution,

the probability of meeting the deadline is

P ( T d ) = P ( standard normal )

= 1 - P( standard normal )

= 1 - 0.1587

0.84.

K

K

Page 24: Project Scheduling: PERT-CPM. PERT (Program evaluation and review technique) and CPM (Critical Path Method) makes a managerial technique to help planning

Time - Cost Trade - OffsCrashing an activity refers to taking special costly measures to reduce the time of an activity below its normal value.

Crash

Normal

Crashtime

Normaltime

Crash cost

Normal cost

Activitycost

Activitytime

Page 25: Project Scheduling: PERT-CPM. PERT (Program evaluation and review technique) and CPM (Critical Path Method) makes a managerial technique to help planning

Activity J:

Normal point: time = 8 weeks, cost = $430,000.

Crash point: time = 6 weeks, cost = $490,000.

Maximum reduction in time = 8 - 6 = 2 weeks.

Crash cost per week saved =

= $30,000.

2

000,430$000,490$

Page 26: Project Scheduling: PERT-CPM. PERT (Program evaluation and review technique) and CPM (Critical Path Method) makes a managerial technique to help planning

Cost($1,000)

Crash Costper Week

Saved

A

B

J

$100

$ 50

$ 30

Activity

Time(week)

MaximumReduction

in Time(week)N NC C

1

2

2

$180

$320

$430

$280

$420

$490

2

4

8

1

2

6

N: Normal C: Crash

Page 27: Project Scheduling: PERT-CPM. PERT (Program evaluation and review technique) and CPM (Critical Path Method) makes a managerial technique to help planning

Using LP to Make Crashing Decisions

Let Z be the total cost of crashing activities.

A problem is to minimize Z, subject to the

constraint that its project duration must be less

than or equal to the time desired by a project

manager.

Page 28: Project Scheduling: PERT-CPM. PERT (Program evaluation and review technique) and CPM (Critical Path Method) makes a managerial technique to help planning

= the reduction in the time of activity j

by crashing it

= the project time for the FINISH node

jx

.000,60000,50000,100 NBA xxxZ

40FINISHy

FINISHy

Page 29: Project Scheduling: PERT-CPM. PERT (Program evaluation and review technique) and CPM (Critical Path Method) makes a managerial technique to help planning

= the start time of activity j

Duration of activity j = its normal time

Immediate predecessor of activity F:

Activity E, which has duration =

Relationship between these activities:

iy

ix

Ex4

.4 EEF xyy

Page 30: Project Scheduling: PERT-CPM. PERT (Program evaluation and review technique) and CPM (Critical Path Method) makes a managerial technique to help planning

Immediate predecessor of activity J:

Activity F, which has time =

Activity I, which has time =

Relationship between these activities:

Fx5

Ix7

IIJ

FFJ

xyy

xyy

7

5

Page 31: Project Scheduling: PERT-CPM. PERT (Program evaluation and review technique) and CPM (Critical Path Method) makes a managerial technique to help planning

.000,60000,50000,100 NBA xxxZ

Minimize

.3,,2,1 NBA xxx

.0,0,,0,0

0,,0,0

FINISHNCB

NBA

yyyy

xxx

The Complete linear programming model

Page 32: Project Scheduling: PERT-CPM. PERT (Program evaluation and review technique) and CPM (Critical Path Method) makes a managerial technique to help planning

.40FINISHy

CCD

BBC

AB

xyy

xyy

xy

10

4

20

HHM xyy 9

One Immediate

Predecessor

Two ImmediatePredecessors

EEH

GGH

xyy

xyy

4

7

NNFINISH

MMFINISH

xyy

xyy

6

2

Finish Time = 40

Total Cost = $4,690,000