ROY HILL BULK EARTHWORKS & CONCRETE PACKAGE CLIENT Samsung C&T PROJECT Roy Hill Concrete and Earthworks LOCATION Pilbara, Western Australia VALUE AU $200 million COMMENCED April 2014 COMPLETED Scheduled for June 2015 PROJECT SUMMARY The proposed scope of works includes Concrete and detailed Earthworks for the Iron Ore Processing Plant, Stockyard, Overland Conveyors and Crushing areas. Specific works to be undertaken include: 53,000cm of structural concrete 800,000cm of backfill/excavations 15km of underground piping 5km of Rail works for the Stackers and Reclaimers. The project has a duration of twelve months commencing in April 2014 with manning on site estimated to peak at 660 personnel. PFS-C077 Current

Upload: damian-brandon

Post on 22-Jan-2018

27 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: Project - Roy Hill Bulk Earthworks and Concrete Package

ROY HILL BULK EARTHWORKS & CONCRETE PACKAGE

CLIENTSamsung C&T

PROJECT Roy Hill Concrete and Earthworks

LOCATIONPilbara, Western Australia

VALUEAU $200 million

COMMENCEDApril 2014

COMPLETEDScheduled for June 2015

PROJECT SUMMARY

The proposed scope of works includes Concrete and detailed Earthworks for the Iron Ore Processing Plant, Stockyard, Overland Conveyors and Crushing areas.

Specific works to be undertaken include:

• 53,000cm of structural concrete• 800,000cm of backfill/excavations• 15km of underground piping• 5km of Rail works for the Stackers and Reclaimers.

The project has a duration of twelve months commencing in April 2014 with manning on site estimated to peak at 660 personnel.