TANK, ABU DHABI, U.A.E Project Description: PROJECT: REPAIR AND WATERPROOFING OF IRRIGATION T C M Corrotech Construction Chemicals, P. O. Box 8344, Dubai, U.A.E.; Tel: +971 4 8112100; Fax: +971 4 8112101; www.mctuae.com page 1 of 1 / 27-CCCrefPUA-8 ISO 9000:2001 certified company The Abu Dhabi Municipality has been searching for a waterproofing system after an excessive leakage of product from irrigation tanks for several years. Various systems have been applied but have already failed after a short time frame. Based on the original construction of a concrete base in combination with steel walls, the interface areas showed severe corrosion problems caused by the leakage. Corrocoat PUA SG was tested on steel plates. After the exceptional performance of Corrocoat PUA system for flexibility and adhesion the system was approved and specified as the preferred internal tank lining system. The application took place in 6 steps: 1. All substrates were high pressure washed. 2. Steel walls were grit blasted to SA 2.5 cleanliness and to a minimum 75 μm profile. 3. Concrete base was sweep blasted to prepare concrete substrate for further overcoating. 4. Corroprime EP SF primer was applied to steel substrate to enhance bonding. 5. Irregularities in concrete surface were repaired with Corromortar FC, after which concrete was primed. 6. Corrocoat PUA SG was applied to a thickness of 2.5 mm by high pressure application. The complete process of surface-preparation, application of base coat and top coat was successfully completed in 25 days despite difficult access, extreme ambient and working conditions. Client Location Construction Contractor Coating Contractor Consultant Project Product Area Date of application : Abu Dhabi Municipality : Abu Dhabi, UAE : Bin Ham : Anticor LLC, Dubai : Dorsch Group Abu Dhabi : Irrigation Tank - Abu Dhabi, UAE : Corroprime EP SF, Corromortar FC, Corrocoat PUA SG : app. 800m² : September 2011 Project Information

Upload: vuongkhue

Post on 12-Dec-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PROJECT: REPAIR AND WATERPROOFING OF IRRIGATION … · Based on the original construction of a concrete base in combination with steel walls, the interface areas showed severe corrosion

TANK, ABU DHABI, U.A.E

Project Description:

PROJECT: REPAIR AND WATERPROOFING OF IRRIGATION

TCM

Corrotech Construction Chemicals, P. O. Box 8344, Dubai, U.A.E.; Tel: +971 4 8112100; Fax: +971 4 8112101; www.mctuae.com

page 1 of 1 / 27-CCCrefPUA-8

ISO 9000:2001 certified company

The Abu Dhabi Municipality has been searching for a waterproofing system after an excessive leakage of product from irrigation tanks for several years.Various systems have been applied but have already failed after a short time frame.Based on the original construction of a concrete base in combination with steel walls, the interface areas showed severe corrosion problems caused by the leakage.Corrocoat PUA SG was tested on steel plates. After theexceptional performance of Corrocoat PUA system for flexibility and adhesion the system was approved and specified as the preferred internal tank lining system.

The application took place in 6 steps:1. All substrates were high pressure washed.2. Steel walls were grit blasted to SA 2.5 cleanliness and to a minimum 75 µm profile.3. Concrete base was sweep blasted to prepare concrete substrate for further overcoating.4. Corroprime EP SF primer was applied to steel substrate to enhance bonding.5. Irregularities in concrete surface were repaired with Corromortar FC, after which concrete was primed.6. Corrocoat PUA SG was applied to a thickness of 2.5 mm by high pressure application.

The complete process of surface-preparation, application of base coat and top coat was successfully completed in 25 days despite difficult access, extreme ambient and working conditions.

Client

Location

Construction Contractor

Coating Contractor

Consultant

Project

Product

Area

Date of application

: Abu Dhabi Municipality

: Abu Dhabi, UAE

: Bin Ham

: Anticor LLC, Dubai

: Dorsch Group Abu Dhabi

: Irrigation Tank - Abu Dhabi, UAE

: Corroprime EP SF, Corromortar FC, Corrocoat PUA SG

: app. 800m²

: September 2011