Project PlanningMclean Farms Pvt. Ltd.
![Page 2: Project Planning TJ 23 June](https://reader035.vdocuments.mx/reader035/viewer/2022081514/587590191a28ab901c8b6c43/html5/thumbnails/2.jpg)
Upcoming ProjectsUpcoming Projects
1. MF Labelling System2. Moba Integration
Moba Client Data Import to PFMS Database Import Cracked, Dirt and licker data to PFMS
Database Off grade Alert & tracking system
3. Supervisor’s Performance Tracking System
![Page 3: Project Planning TJ 23 June](https://reader035.vdocuments.mx/reader035/viewer/2022081514/587590191a28ab901c8b6c43/html5/thumbnails/3.jpg)
MF Labelling SystemMF Labelling System
1. TUN Labelling System2. Pallet tag Labeling System
Regular Pallet tag Promo Pallet tag 1st/2nd grade Pallet tag Pulp vats Pallet tag
3. Settings Printer Settings Barcode detail settings
![Page 4: Project Planning TJ 23 June](https://reader035.vdocuments.mx/reader035/viewer/2022081514/587590191a28ab901c8b6c43/html5/thumbnails/4.jpg)
1. TUN Labelling System1. TUN Labelling System
Task Duration (7Hr/Day) Team member Roughly Design Planning 1 Day Rosemary and Tejas
Design Specification 1 Days Rosemary and Tejas
Approval 1 Day Rosemary
Development 5 Days Rosemary & TJ
Testing 1 Day Tejas & Rosemary
Create User Guide 1 Day Tejas
Total Estimate Time 10 DaysLive Environment: Install Application on Front Room PC
Training 5 Day Tejas and Supervisors
Total Project time including Training: 15 Days (3 Weeks)
Project Estimate TimeProject Estimate Time
![Page 5: Project Planning TJ 23 June](https://reader035.vdocuments.mx/reader035/viewer/2022081514/587590191a28ab901c8b6c43/html5/thumbnails/5.jpg)
2. Pallet tag labelling System2. Pallet tag labelling System
TASK DURATION in Days (7Hr/Day) Total Working
Days
Team Member
sREGULAR
PROMO 2ND RADE
PULP VATS
Settings
Roughly Design Planning
1 1 1/2 1/2 1 4 RG, TJ, Byron
Design Specification
1 1 1 1 1 4 RG & TJ
Approval 1 12 1/2 1/2 1/2 3 RG
Development
10 8 3 3 5 29 RG & TJ
Testing 1 1 1 1 1 5 RG & TJ
User Guide
1 1 1 1 1 5 TJ
Total Estimate Time: 50 Working Days
Training 5 5 5 5 20 RG & TJ
Total estimate Project time including Training: 70 Working Days (3 Month + 2 Weeks)
Project Estimate TimeProject Estimate Time
![Page 6: Project Planning TJ 23 June](https://reader035.vdocuments.mx/reader035/viewer/2022081514/587590191a28ab901c8b6c43/html5/thumbnails/6.jpg)
2. MOBA Integration
![Page 7: Project Planning TJ 23 June](https://reader035.vdocuments.mx/reader035/viewer/2022081514/587590191a28ab901c8b6c43/html5/thumbnails/7.jpg)
Off Grade Tracking & Alert SystemOff Grade Tracking & Alert System
• What is Off grade eggs? If MOBA system detects eggs with …..
Cracked Blood Dirt
called Off grade eggs.
Machine Speed: Nearly 3 Dozen per Second (36 Eggs)
![Page 8: Project Planning TJ 23 June](https://reader035.vdocuments.mx/reader035/viewer/2022081514/587590191a28ab901c8b6c43/html5/thumbnails/8.jpg)
Off Grade Track & Alert SystemOff Grade Track & Alert System
Task Duration (7Hr/Day) Team member Roughly Design Planning 1 Day Rosemary, Byron and
Tejas
Design Specification 1 Days Rosemary and Tejas
Approval 1 Day Rosemary
Development 10 Days Rosemary & Tejas
Testing 1 Day Rosemary & Tejas
Create User Guide 1 Day TejasTotal Estimate Time 15 Days
Live Environment: Install Application on Spare TV (PC) on PF
Training 5 Day Tejas and Maintenance
Total Project time including Training: 20 Days (4 Weeks)
Project Estimate TimeProject Estimate Time
![Page 9: Project Planning TJ 23 June](https://reader035.vdocuments.mx/reader035/viewer/2022081514/587590191a28ab901c8b6c43/html5/thumbnails/9.jpg)
3. Performance Tracking System
Task Duration (7Hr/Day) Team member Roughly Design Planning 1 Day Rosemary, Byron and
Tejas
Design Specification 1 Days Rosemary and Tejas
Approval 1 Day Rosemary
Development 20 Days Rosemary & Tejas
Testing 1 Day Rosemary & Tejas
Create User Guide 1 Day Tejas
Total Estimate Time 25 DaysLive Environment: Install Application on Byron’s PC
Training 1 Day Tejas
Total Project time including Training: 26 Days (5 Weeks)
Project Estimate TimeProject Estimate Time
![Page 10: Project Planning TJ 23 June](https://reader035.vdocuments.mx/reader035/viewer/2022081514/587590191a28ab901c8b6c43/html5/thumbnails/10.jpg)
SummarySummary
Projects DurationMF Labelling System 17 Weeks (4 Months + 1 Week)
MOBA: Off grade Tracking & Alert System 04 Weeks (1 Month)
Performance Tracking system 05 Weeks (1 Month + 1 Week)
Total Estimate Development time: 6 Month + 2 Weeks (910 Hours)