project overview “ egor-co2 ”
DESCRIPTION
CC Poland PlusProjects Review Meeting 11-12 April 2011. Project overview “ EGOR-CO2 ” „ Integration of CO 2 Sequestration with EGOR-CO2 technology (Enhanced Gas and Oil Recovery method). ” Speaker: Stanisław NAGY. Clean Coal Technologies. Project summary. Project summary. Contents. - PowerPoint PPT PresentationTRANSCRIPT
Project overview
“ EGOR-CO2”„Integration of CO2 Sequestration with EGOR-CO2 technology (Enhanced Gas and Oil
Recovery method).”
Speaker: Stanisław NAGY
1KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy
CC Poland PlusProjects Review Meeting11-12 April 2011
Clean Coal Technologies
Project summary
2KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy
MASTER DATA
Topical Area: CO2 sequestration
Project type: R&D
Project Duration: 3 years
Total Budget (K€) 1329,8
Total KIC request (K€) 308,6
PARTNERS DATACC Typology
(Rough) % TOTAL
budget splitPartners name Ger Pol Sw
eBen
Fra Ibe Res Uni Ind Oth
1 AGH
52%
2 LOTOS
8%
3 EDF KIC level partner
3%
4 PGNiG
13%
5 University of Stavanger
24%
Project summary
3KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy
1. Organisation of the project with workpackages.
2. Deliverables/products.
3. Timetable
4. Budget
5. Market analysis
6. Open issues
Contents
4KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy
55KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy
Organisation of work packages
WP3: Analysis of the possibilities to devise an inland transport of the CO2 to the potential injection zone, injection site infrastructure optimization and the assessment of the productivity. (PGNiG, AGH) budget: 85 k€
WP0: Preparation of market analysis and assessment of business opportunities.(PGNiG, LOTOS, AGH) budget: 11 k€
WP1: Data collection and construction of the static model of the Zalecze & Zuchlow gas field at basin and reservoir scale. (PGNiG, AGH); budget:
105 k€
WP2: Flow simulation and elements of geomechanics. Integrity analysis of the existing wells. (AGH, PGNiG), budget: 245 k€
6KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy
WP7: Feasibility study (LOTOS, AGH), budget: 57 k€
Organisation of work packages
WP8: Skarv field characterization and analysis of the EOR-CO2 implementation on oil productivity (Univ. Stavanger, AGH), budget: 760 k€
WP4: Construction of geological & numerical model of B3 oil field with history match (AGH), budget: 115 k€
WP5: Analysis of possibilities to increase the recovery factor with the CO2-EOR method (AGH, LOTOS, EDF), budget: 181,4 k€
WP6: CO2 Injection monitoring design (AGH, Lotos), cost: 79 k€
7KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy
Interdependences between packagesWP1
WP2
WP3
WP5
WP4
WP6
WP7
WP8
8KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy
Project description- expectations
•improvement of oil recovery efficiency: recovery of significant amount of oil which arises in a reservoir after finishing the primary & secondary exploitation;
•minimizing risk of geologic sequestration
•answering the technical questions necessary for EOR method introduction in the industry: features of the technology is an increase of mobility and change of viscosity
•Diagnosis of the EOR and EGR processes and their consequences
•confirmation of logistical solutions of CO2 transportation
9KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy
Project description – necessary workplan
10KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy
Project description
WORKPACKAGE No.1 (AGH, PGNiG)
Data collection and construction of the static model of the Zalecze & Zuchlow gas field at basin and reservoir scale
T1.2 Construction of the static model at basin and reservoir scale
WORKPACKAGE No.2 (AGH, PGNiG)
Flow simulation and elements of geomechanics. Integrity analysis of the existing wells
T2.1 Flow simulation and elements of geomechanics
T2.2 Integrity analysis of all existing wells
T1.1 Data collection and verification of the data quality
11KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy
Project description
WORKPACKAGE No.3 (PGNiG, AGH)
Analysis of the possibilities to devise an inland transport of the CO2 to the potential injection zone, injection site infrastructure optimization and the assessment of the productivity
T3.1 Elaboration of the most convenient and effective ways of transportation of the CO2
T3.2 Injection infrastructure optimization
T3.3 Influence of the miscibility zone appearance on productivity
12KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy
Project description
WORKPACKAGE No.4 (AGH)
Construction of geological & numerical model of B3 oil field with history match
T4.1 Data collection and analysis
T4.2 Geomechanical analysis of reservoir and caprock strata
T4.3 Construction of numerical model of B3 field
WORKPACKAGE No.5 (AGH, LOTOS, EDF)
Analysis of possibilities to increase the recovery factor with the CO2-EOR method
T5.1 Analysis of technical state of underground and surface infrastructure
T5.2 . Lab analysis with emphasis to sealing of structure after filling it with CO2 (chemical reaction/ long term laboratory work/simulation)
13KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy
Project description
WORKPACKAGE No.5 (AGH, LOTOS, EDF)
Analysis of possibilities to increase the recovery factor with the CO2-EOR method
T5.3 Infill drilling opportunities - analysis and new drilling projects
T5.4 Short & long Impact of CO2 injection on Sea and Air Environment
WORKPACKAGE No.6 (AGH, LOTOS)
New CO2 Injection monitoring design
T6.1 Project of passive seismic monitoring
T6.2 Optic parameters permanent downhole measuring system
T 6.3 Water surface monitoring system
14KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy
Project description
WORKPACKAGE No.7 (AGH, LOTOS)Feasibility studyT 7.1 Standard monitoring of process
T 7.2 Analysis of transport opportunity from Lotos Refinary Plant
T 7.3 Multivariant final economic analysis
WORKPACKAGE No.8 (Univ. Stavanger, AGH)
Skarv field characterization and analysis of the EOR-CO2 implementation on oil productivity
T8.1 Methods of tight gas production at the Gro fieldA) Use of CO2 injection for the purpose of the fracturing process of
the tight gas field
T8.2 Carbon dioxide injection as a tool to increase oil/gas production
15KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy
Project description
WORKPACKAGE No.8 (Univ. Stavanger, AGH)
Skarv field characterization and analysis of the EOR-CO2 implementation on oil productivity
T8.1 Methods of tight gas production at the Gro fieldA) Use of CO2 injection for the purpose of the fracturing process of the
tight gas field
T8.2 Carbon dioxide injection as a tool to increase oil/gas production B) Comparison of advantages of the usage IOR/IGR vs EOR/EGR
T 8.3 Increase of oil recovery factor by means of natural gas injection at the Skarv field
C) Increase of oil recovery factor by means of CO2 injection at the Skarv field
16KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy
Deliverables
No. Deliverables
D 0.1. Portfolio of economic opportunities and internal development capabilities.
D 1.1 Static model data verification
D 1.2 Basin scale and reservoir static model
D 2.1 Flow dynamic and deformation of the storage complex based on thermo-hydraulic and geomechanical simulations
D 2.2 Integrity analysis of all existing wells
D 3.1 Transportation plan
D 3.2 Site infrastructure development project.
D 4.1 Geologic model of B3 oil field
D 6.1. New monitoring program.
D 7.1 Final report and efficiency of process estimation
D 7.2 Economic evaluation report
D 8.1. PhD and MSc programms
17KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy
KIC added value
• the introduction of innovative seismic monitoring system for industry purposes
• transportation plan
•site developement plan
•technology for increased exploitation of oil/gas (monograph, 3 papers)
•PhD and MSc programms considering recovery methods (1-2 PhD, 3 MSc)
18KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy
Timing/deliverables
19KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy
Budget
20KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy
Budget - financing
KIC level network partner KIC level network partner
Sources of Budget, in k€ AG
H
PGNiG Lot
os EDF
Univ.
Stavan
ger
TOTAL 2011 AG
H
PGNiG Lot
os EDF
Univ.
Stavan
ger
TOTAL REST
TOTAL PROJECT
Partner in-kind 30 30 23 83 60 70 16,8 146,8 229,8Partner in-cash 0 0 0EIT requested contribution 40 15 10 8 20 93 100 45 20 5,6 45 215,6 308,6National funding 85 85 115 115 200Regional funding 0 0 0European funding 38 25 63 90 65 155 218Other sources 87 90 177 275 230 505 682
Total 250 70 40 31 110 501 580 170 90 22,4 275 1137,4 1638,4
Poland Plus Poland Plus
21KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy
Budget
22KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy
Budget
23KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy
Market analysis (WP0) – PGNiG, Lotos
Title: Preparation of market analysis and assessment of business opportunities.
T0.1. External market analysis.a.Market analysis: the estimation of the current and future market size will be proceeded. The market capacity, potential demand and absorptivity of the new technology is going to be assessed. The prospective consumers and their motives will be determined, taking under consideration the distribution channels to the recipient.
b. Recognition of the competition structure will be performed and the risk evaluated, if new competitors are expected to appear. The value of project competitiveness will be underlined.
24KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy
Market analysis (WP0)
Title: Preparation of market analysis and assessment of business opportunities.
T0.2. Consortium's internal analysis.a.Assessment of material and immaterial resources capabilities of the partners partaking in the project (devices, materials, etc.), especially from among immaterial resources the importance of management capacity, institutions, reputation, etc.
b. The characteristics of the consortium's opportunities: recognition of strengths and weaknesses, which have an impact on chances of success depending on external circumstances, threats, formal legal issues risk.
c. The capabilities and outlook on generating new patents, recovered oil profit, extension of exploitation liveliness by developing new technology.
25KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy
Launching new products in a market
Questions: What- service/product? Who may be interested in? What for? How?
1. Creation and testing. Implementation for partner’s purpose.
2. Commercialization
• finding the discriminatory features
mainly energy companiesprofit, safety reasons
26KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy
Questions?
27KIC InnoEnergy | CC Poland Plus, Meeting, Cracow, 11Apr2011| Speaker:Stanisław Nagy
Thank you for your attention