Project Management

LectureNetwork Analysis

Introduction Project planning

Gantt chart and WBS

Project planning Network analysis I

Project planning Network analysis II

Introduction Project planning

Gantt chart and WBS

Project planning Network analysis I

Plan Project planning

Resource analysis Risk management Quality Budgets and cost

control Project teams

Plan

Monitor & Review

Plan

Iterative Process The plan will evolve as the project evolves The plan is reviewed and updated as more

information becomes available and uncertainties become less uncertain

Plan

Monitor & Review

Plan

Monitor & Review

Plan

Plan

PBS Example

Project

Design Deliverables

Database Deliverables

GUI Deliverables

Functional Deliverables

Project Management Deliverables

Produce Class Diagrams

Produce Use Cases

Produce Activity Diagrams

Use Case Describes a unit of functionality from

a users perspective May be text or diagram

Therefore they provide a good tool for Project Task Planning

They also can determine the nature of the project process How many development iterations?

Place Order

Send Payment

Retailer

Dispatch Order

Send Invioce

Raise Purchase Order

Make Payment

Staff

Priority 1

Priority 2

Use Case Example – Big John’s

Use Case Example – Big John’s Each Use Case Shown can be shown

as activities in the PBS The prioritisation can be used to

describe the activities for two development iterations

This will be significantly different to the process if only one iteration was used

Gantt Chart ExampleRepresent the following on a Gantt chart

Task Start (wk no) Duration (wks) %CompleteA 1 5 100B 2 3 100C 1 8 75D 3 4 100E 5 5 60F 2 4 25G 10 6 0H 6 6 100I 7 2 50J 8 6 50

Assume this information was taken at the end of week 8

Gantt Chart ExampleWeek

Task 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16ABCDEFGHIJ

Scheduled Completion

Actual Completion

Under-fulfilled tasks: C, E, F, IOver-fulfilled tasks H, J

Gantt chart disadvantages Not ideal for showing inter-

relationships Locating an activity requires three

simultaneous decisions: Method Time Resources

Complexity Number of tasks? Number of people? Size of Budget? Number/Nature of constraints Dependencies between tasks

Why Network Diagrams? Splits up the decision making process

into Method/logic - the order in which tasks

have to be completed Time – estimates for the time to

completion can be added to each task Resources – these can be added and then

analysis carried out

Two Methods Activity on Arrow

Traditionally the preferred method Activity on Node

More popular these days Supported by most Project Management

software tools (i.e. MS Project)

A B

C

D

Activity on Arrow Arrows are used to represent an activity Circles are used to represent the points

where activities meet i.e. the dependency between activities

A B

C

D

Activity on Node Activities are

represented by boxes

Dependencies are represented by arrows joining the boxes

Task A

Task D

Task C

Task B

Comparison

A B

C

D

Task A

Task D

Task C

Task B

Task B cannot start until Task A is complete

Activity on Node

Activity on Arrow

Dependency Example Task B cannot start until Task A is

complete

Activity on Node

Task A Task B

Task A Task B

More complex example Four activities/tasks:

A, B, K, L Activity K is dependent on activity A Activity L is dependent on activities A and B

Task A

Task L Task B

Task K

The same example in AoA

The same example in AoA

A K

The problem with AoA A K

L B

A K

L B

dummy activity

Wrong…

Right

Activity K is dependent on activity AActivity L is dependent on activities A and B

Exercise 1 Draw the following:

Activity K is dependant on Activity A Activity L is dependent on Activity B Activity M is dependent on Activity A and

B

Exercise 2 Draw the following:

Activity K is dependent on activities A and B

Activity L is dependent on activities B and C

Activity is dependent on activity B

Drawing the network Direction

The flow of work is from left to right Identifying Tasks

Each task is given a unique ID number ID number is often given in WBS

Scale Diagram is not drawn to scale Length and size do not matter

They have no meaning

What’s in the box?

Earliest Start

Estimated Duration

Earliest Finish

Activity NumberActivity Description

Latest Start

FloatLatest Finish

Project Exercise 1Project 1: Verification of a computer systemThe followng table shows the activities required for this project.

Activity ID Activity Immediate Predecessor

Duration (Days)

1 Test Module A none 42 Test Module B Test Module A 63 Test Module C none 74 Test Combined Modules Test Module B, Test Module C 45 Check User Documents Test Combined Modules 56 Print User Documents Check User Documents 27 Final Systems Check Test Combined Modules 98 Prepare Invoice Final Systems Check 19 Ship to Customer Print User Documents, Final

Systems Check2

Errors in Logic Looping

Due to a mistake in drawing or to errors in identifying dependent activities

P Q

R

Errors in Logic Dangling

Usually occur when activities are added as an afterthought

Can be avoided by using a single finish node

K L

M

K L

M

Finish

Project Exercise 2Project 2: A presentationThe followng table shows the activities required for this project.

Activity ID Activity Immediate Predecessor

Duration (Days)

1 Book Search none 122 Journal Search Book Search 63 Internet Search none 154 Produce Outline Journal Search, Internet Search 105 Prepare Handouts Produce Outline 76 Print Handouts Prepare Handouts 27 Produce Visual Aids Produce Outline 128 Write Speech Notes Produce Outline 49 Rehearse Speech Write Speech Notes 10

10 Give Presentation Print Handouts, Produce Visual Aids, Rehearse Speech

1

Introduction Project planning

Gantt chart and WBS

Project planning Network analysis I

Project planning Network analysis II

Project planning Network analysis I

Project planning Network analysis II

Plan Project planning

Resource analysis Risk management Quality Budgets and cost

control Project teams