3/2/16 1 Advanced Techniques In Project Management Part 1: Technical Skills NK Shrivastava, PMP, RMP, ACP, CSM, SPC CEO/Consultant/Agile Coach - RefineM www.RefineM.com Agenda 1. What is Virtual Lunch & Learn 2. Your Expectations from this Webinar 3. Introduction – Myself 4. Advanced Techniques in Project Management Part 1: Technical Skills 5. Upcoming Learning Opportunities from RefineM 6. How to get 1 PDU for this Webinar? 7. Rewarding Our Star Attendees 8. Q&A

Upload: others

Post on 28-Jul-2020

6 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Project Management Consulting, Training, and Toolkits | RefineM … · 2016-03-02 · Project Management Part 1: Technical Skills NK Shrivastava, PMP, RMP, ACP, ... ∗ Project Management

3/2/16

1

Advanced Techniques In Project Management Part 1: Technical Skills

NK Shrivastava, PMP, RMP, ACP, CSM, SPCCEO/Consultant/Agile Coach - RefineM

www.RefineM.com

Agenda1. WhatisVirtualLunch&Learn2. YourExpectationsfromthisWebinar3. Introduction– Myself4. AdvancedTechniques inProjectManagement

Part1:TechnicalSkills

5. UpcomingLearningOpportunities fromRefineM6. Howtoget1PDUforthisWebinar?7. RewardingOurStarAttendees8. Q&A

Page 2: Project Management Consulting, Training, and Toolkits | RefineM … · 2016-03-02 · Project Management Part 1: Technical Skills NK Shrivastava, PMP, RMP, ACP, ... ∗ Project Management

3/2/16

2

www.RefineM.com

RefineM’s Virtual Lunch & LearnThisisamonthlywebinardeliveredduringthelunchhourinthefirstweek(Wednesdays)ofeverymonth.

It’sdesignedtohelpyoulearnwhileyoueatlunch,providingarelaxedenvironmenttoenhanceyourexperience.

ThemonthlywebinarswillcoveravarietyofProjectManagement/Agiletopics.

www.RefineM.com

Your Expectations

What are your expectations from this webinar?

Why are you here today?

Page 3: Project Management Consulting, Training, and Toolkits | RefineM … · 2016-03-02 · Project Management Part 1: Technical Skills NK Shrivastava, PMP, RMP, ACP, ... ∗ Project Management

3/2/16

3

www.RefineM.com

NK Shrivastava, PMP, RMP, ACP, CSM, SPC

∗ CEO/Consultant sinceDec2011∗ AgileCoaching/Adoption∗ ProjectManagement/ ProcessImprovement

ConsultingandTraining∗ ProjectManagementToolkits(forPMs,Executives

andAgilePractitioners)

Helping organizations turn their project management capability into a competitive advantage

Myprofessionaljourneyb/fRefineM ∗ 20+yearsofSuccessfulProject Leadership∗ Led100sofprojectsofallsizes,successfully∗ Recoveredmanyprojects,savedmillionsof$∗ Implementednumerousprocess

improvements∗ Coached/mentored100sofPMs,andsome

executives∗ BoardMember– SWMOPMIChapter(2008-

2014)

Advanced Techniques In Project Management

Part 1: Technical Skills§ OverviewofAdvancedTechniques§ WhoCanUseTheseTechniques?

Page 4: Project Management Consulting, Training, and Toolkits | RefineM … · 2016-03-02 · Project Management Part 1: Technical Skills NK Shrivastava, PMP, RMP, ACP, ... ∗ Project Management

3/2/16

4

www.RefineM.com

∗ Howdoprojectmanagersovercomeplateaus?

∗ Whatcantheyfocusontobemosteffective?

∗ Howcantheycontinuetomeetdemands oftheirjob?

Learnadvancedtechnicalandleadershipskills

Overview of Adv. Techniques

[email protected]

www.RefineM.com

Advanced Skills

[email protected]

TechnicalSkills LeadershipSkills1. AdvancedStakeholderManagement 1. DevelopingClarity

2. AdvancedScopeandChangeManagement 2. InspiringandMotivating

3. PerformanceMeasurementUsingEVM 3. CommunicatingEffectively

4. AdvancedRiskManagement 4. BuildingRelationships

5. DevelopingOthers

6. ManagingStressonProjects

Page 5: Project Management Consulting, Training, and Toolkits | RefineM … · 2016-03-02 · Project Management Part 1: Technical Skills NK Shrivastava, PMP, RMP, ACP, ... ∗ Project Management

3/2/16

5

www.RefineM.com

∗ Projectmanagerswhohavesomeexperience

∗ Theymayormaynothaveacertificationsuch asPMP®

∗ PMOLeads/Directors

∗ Projectmanagerslooking totakeonaleadershiprole

Who Can Use These Techniques?

[email protected]

Advanced Technical Skills

§ AdvancedStakeholderManagement- NPS§ AdvancedScope/ChangeManagement- RTM§ PerformanceMeasurement - EVM§ AdvancedRiskManagement- ContingencyReserve

Page 6: Project Management Consulting, Training, and Toolkits | RefineM … · 2016-03-02 · Project Management Part 1: Technical Skills NK Shrivastava, PMP, RMP, ACP, ... ∗ Project Management

3/2/16

6

Advanced Stakeholder Management

§ OverviewofStakeholderManagement§ UsingNetPromoterScore(NPS)

www.RefineM.com

∗ EffectivestakeholdermanagementhelpsPMwinsupport

∗ Ineffective/nostakeholdermanagement:ü Causes communicationgaps/thingsslippingthroughcracksü Cancausestakeholderstobecomebarriers

∗ ManyPMsalreadydosomestakeholdermanagementü Stakeholderregisterandinfluence/interestgridü Stakeholderengagementmatrix(current,desiredlevels)

Howtogobeyond?

Stakeholder Management

[email protected]

Page 7: Project Management Consulting, Training, and Toolkits | RefineM … · 2016-03-02 · Project Management Part 1: Technical Skills NK Shrivastava, PMP, RMP, ACP, ... ∗ Project Management

3/2/16

7

www.RefineM.com

∗ NPSisacustomerloyaltymetric∗ NPSisbasedononequestion:

ü “Howstronglywillyourecommendusonascaleof1-10?”ü Thosescoring9-10arepromotersü 7-8arepassives/neutralsü 0-6aredetractors

Use Net Promoter Score (NPS)

[email protected]:https://en.wikipedia.org/wiki/Net_Promoter

Howdoyouapplythistoimprovestakeholderengagement?

Howaboutdoingasmallexercise?

Advanced Scope and Change Management

§ OverviewofScope/ChangeManagement§ RequirementsTraceabilityMatrix

§ Example

Page 8: Project Management Consulting, Training, and Toolkits | RefineM … · 2016-03-02 · Project Management Part 1: Technical Skills NK Shrivastava, PMP, RMP, ACP, ... ∗ Project Management

3/2/16

8

www.RefineM.com

∗ Scope/changemanagement iscriticaltoprojectsuccess

∗ Scopecreepcancause:ü Delaysü Costoverrunsü Customer dissatisfaction

∗ Basicscopeandchangemanagement startswith:ü WBSü Changecontrol system

Howtogobeyond?

Overview of Scope/Change Mgmt

[email protected]

www.RefineM.com

∗ Usedtotracerequirementsbacktotheirsource

∗ Cantierequirementsto:ü Businessandprojectobjectivesü Deliverablesü TestcasesüManyothers

∗ Benefitsprojectmanagersby:ü Bettertrackingofrequirementstomakesuretheygetcompletedü Betterintegrationofrequirementswithbusinessvalue

Requirements Traceability Matrix

[email protected]

Page 9: Project Management Consulting, Training, and Toolkits | RefineM … · 2016-03-02 · Project Management Part 1: Technical Skills NK Shrivastava, PMP, RMP, ACP, ... ∗ Project Management

3/2/16

9

www.RefineM.com

RTM Example

[email protected]

Project XYZ - Requirement Traceability Matrix (RTM)Id Requirements Deliverables Project Lead Estimated

Duration (Weeks)

Estimated Real Effort (Hours)

Date WBS Created

Date Schedule/MPP Created

Date Code Complete

Date Testing Complete

Date In Production

1 Requirements Set1

2 Requirements Set2

3 Requirements Set3

Performance Measurement Using Earned Value Management (EVM)

§ WhyUseEVM?§ EVMExample§ EVMMetrics

Page 10: Project Management Consulting, Training, and Toolkits | RefineM … · 2016-03-02 · Project Management Part 1: Technical Skills NK Shrivastava, PMP, RMP, ACP, ... ∗ Project Management

3/2/16

10

www.RefineM.com

∗ EVMisatoolthatmakesprojectmanagerspowerfulü Combinesscope,time,costmanagementinonemetric

∗ Canbesetupwiththefollowing:ü Valueofplannedwork(PV)ü Actualcostsincurred(AC)ü RulesforcalculatingEarnedValue(EV)

∗ Helpsprojectmanagers:ü Integratescope,schedule,andresourcesü Objectivelymeasureprojectperformanceü Effectivelyforecastfutureoutcomes

Why Use EVM?

[email protected]

www.RefineM.com

EVM Example

[email protected]

Page 11: Project Management Consulting, Training, and Toolkits | RefineM … · 2016-03-02 · Project Management Part 1: Technical Skills NK Shrivastava, PMP, RMP, ACP, ... ∗ Project Management

3/2/16

11

www.RefineM.com

EVM Formulas∗ Variances- apositive#isbetter

ü AlwaysinvolvesEVminussomethingü ScheduleVariance(SV)=EV-PV ü CostVariance(CV) =EV-AC

∗ PerformanceIndices– a#morethan1isbetterü AlwaysinvolvesEVdividedbysomethingü SchedulePerformanceIndex(SPI)=EV/PV

• Foreachdayspent,howmuchisprojectearning?

ü CostPerformanceIndex(CPI)=EV/AC• Foreachdollarspent,howmuchisprojectearning?

Source: PMI’s Practice Standard for Earned Value Management (Second Edition), 2011, Project Management Ins titute.

www.RefineM.com

EVM Metrics for Past PerformanceMetric Description

Planned Value(PV) Valueplannedforworktobeperformed

EarnedValue(EV) Valueearned forworkperformed

ActualCost(AC) Cost ofworkperformed

CostVariance(CV) Differencebetweenearnedvalue, actual cost

CostPerformanceIndex(CPI) Valueearned perdollarspent

ScheduleVariance(SV) Differencebetweenplanned, earnedvalue

SchedulePerformanceIndex(SPI) Valueearnedperdayspent

Page 12: Project Management Consulting, Training, and Toolkits | RefineM … · 2016-03-02 · Project Management Part 1: Technical Skills NK Shrivastava, PMP, RMP, ACP, ... ∗ Project Management

3/2/16

12

www.RefineM.com

EVM Exercise

Activity % Complete Cost

Side1 100% 1200

Side2 100% 1000

Side3 75% 750

Side4 50% 500

Side5 0% 0

Side6 0% 0

YouaretheProjectManagerforasmallproject.Youneedtobuild astructurewith6sidesin6days.Eachside shouldcost$1000.00.Todayistheendofday3.

Thefollowing isanextractfromtheSiteManager’sReport.

Solvethefollowing:

www.RefineM.com

Parameter Calculation Result

PVEVACBACCVCPISVSPI

EVMExerciseAnswers

$1,000 + $1,000 + $1,000 $3,000$1,000 + $1,000 + $750 + $500 $3,250$1,200 + $1,000 + $750 + $500 $3,450

$1,000 + $1,000 + $1,000 + $1,000 + $1,000 + $1,000 $6,000$3,250 - $3,450 ($200)$3,250 / $3,450 .94$3,250 - $3,000 $250$3,250 / $3,000 1.08

Page 13: Project Management Consulting, Training, and Toolkits | RefineM … · 2016-03-02 · Project Management Part 1: Technical Skills NK Shrivastava, PMP, RMP, ACP, ... ∗ Project Management

3/2/16

13

Advanced Risk Management§ OverviewofRiskManagement§ BasicQuantitativeAnalysis§ RiskContingencyReserve

www.RefineM.com

∗ Riskmanagement iscriticaltoprojectsuccess

∗ Withoutit,projectmanagerscanexpect:ü Lotofsurprisesand“ohno”momentsduetothingsmissedü CostlydelaysandoverrunsüMissedopportunities

∗ Basicriskmanagement startswith:ü Riskregisterü Identifyingresponsestrategiesü Basicqualitativeanalysis

Howtogobeyond?

Overview of Risk Management

[email protected]

Page 14: Project Management Consulting, Training, and Toolkits | RefineM … · 2016-03-02 · Project Management Part 1: Technical Skills NK Shrivastava, PMP, RMP, ACP, ... ∗ Project Management

3/2/16

14

www.RefineM.com

∗ ExpectedMonetaryValue(EMV)isoneexampleü Probabilityofriskoccurrencetimesimpactofoccurrence

∗ Example:Computersgodown,costis$5,000toreplace.ü Theprobabilityofcomputersgoingdownis20%üWhatistheEMV?ü EMV=$5,000x20%=$1,000

∗ BenefitsofEMVü Exposetherealimpactofariskü Setupriskcontingencyreserve

Basic Quantitative Analysis

[email protected]

www.RefineM.com

∗ Timeorcostsetasidetomanageidentified risks

∗ ContingencyReservecovers“knownunknowns”

∗ BenefitsofContingencyReserveü Improvespredictabilityofoutcomesü Effectivecommunicationtoolforrisks

Risk Contingency Reserve

[email protected]

Page 15: Project Management Consulting, Training, and Toolkits | RefineM … · 2016-03-02 · Project Management Part 1: Technical Skills NK Shrivastava, PMP, RMP, ACP, ... ∗ Project Management

3/2/16

15

www.RefineM.com

Risk Impact on the Project

www.RefineM.com

∗ MasterthefollowingtoovercomeyourPMplateau

Conclusion

[email protected]

Page 16: Project Management Consulting, Training, and Toolkits | RefineM … · 2016-03-02 · Project Management Part 1: Technical Skills NK Shrivastava, PMP, RMP, ACP, ... ∗ Project Management

3/2/16

16

www.RefineM.com

∗ Nextmonthwewilldiscuss stakeholdermanagement

∗ Inthemeantime,findwaystopracticetheskills

∗ Regularpracticewillhelp youdeveloptheseskills

Withtheseskillsyoucanmanageanyproject

Evenalargeandcomplexproject

What’s next?

[email protected]

www.RefineM.com

Please visit https://refinem.com/training/ for more details.

More Training Opportunities From RefineM

[email protected]

Training Title Springfield Kansas City St. Louis Instructor-Led Online

Tips/TricksforStakeholderEngagement Mar14

First-TimeManager Mar16 Mar30 Jun01

LeadershipSkillsforProjectManagers Mar17 Mar31 Jun02

Adv.TechniquesinRiskManagement Mar21

IsQualityReally Important? Mar23 May02 Apr07

Lean 101 Mar30 May03 Apr08

ChangeManagement Apr04 May04 Apr09

AgileFundamentals/Agile101 Apr07 May04-05 Apr04-05

PMI-ACP®ExamPrep May04-06

PMP®ExamPrep May09-12

Risk ManagementforProjects Nov14 Jun01

Page 17: Project Management Consulting, Training, and Toolkits | RefineM … · 2016-03-02 · Project Management Part 1: Technical Skills NK Shrivastava, PMP, RMP, ACP, ... ∗ Project Management

3/2/16

17

www.RefineM.com

We also offer customized trainings, On-site & Virtual

Topics include ∗ Agile, ∗ Project Management, ∗ Process Improvement, ∗ Leadership and ∗ PMI & SAFe Certifications.

RefineM Customized Training

More info at https://refinem.com/training/

Contact us at [email protected]

[email protected]

www.RefineM.com

∗ Adv.TechniquesInPM:StakeholderManagementüHowdoyougobeyondstakeholdermanagementbasics?üHowcanyoumaximizestakeholdercommunication?

∗ Wednesday,April6,12:00-1:00PMCentral

RegisterToday- Don’twaitforthelastMinute

Next Lunch and Learn

[email protected]

Page 18: Project Management Consulting, Training, and Toolkits | RefineM … · 2016-03-02 · Project Management Part 1: Technical Skills NK Shrivastava, PMP, RMP, ACP, ... ∗ Project Management

3/2/16

18

www.RefineM.com

∗ PDU Category – B, Continuing Education∗ Program Title – Webinar on “Advanced Techniques in

Project Management Part 1: Technical Skills”∗ Talent Triangle – 1.00 Technical ∗ Date Started – Today’s date∗ Date Completed – Today’s date∗ Hours Completed – 1.00∗ Provider

ü Name – RefineMü Phone # 417-763-6762ü Email – [email protected]

∗ PDUs Claimed – 1.00 Technical

How to Claim 1 PDU for this Webinar?

[email protected]

www.RefineM.com

Rewarding Our Star Attendees

∗ Anyonewhoattends3LunchandLearnWebinarsinarowisaStarAttendeeandiseligibleforaprizedrawingfora$10Amazongiftcard.

There are no Star Attendees this month.Stay tuned for our next drawing in April.

[email protected]

Page 19: Project Management Consulting, Training, and Toolkits | RefineM … · 2016-03-02 · Project Management Part 1: Technical Skills NK Shrivastava, PMP, RMP, ACP, ... ∗ Project Management

3/2/16

19

www.RefineM.com

__________________________________________________________________

NK Shrivastava, MBA, PMP, RMP, ACP, CSM, SPCCEO/Consultant, RefineMNixa, MO 65714, [email protected], www.refinem.com

http://www.linkedin.com/in/nkshrivastava @jujustrightpm

Questions?