![Page 1: Project Information Session / Meet and Greet # 3hambjvteam.com/Content/UploadImages/636432362664361250...HKS, INC Fitzgerald Collaborative Group WalkerParkingConsultants Thornton Tomasetti](https://reader033.vdocuments.mx/reader033/viewer/2022042805/5f5fc83c02cb8c1e4e4d78b4/html5/thumbnails/1.jpg)
ATL WEST DECK COMPONENT
Holder-Austin-Moody-Bryson, a Joint VentureOctober 10th, 2017
Project Information Session / Meet and Greet # 3
![Page 2: Project Information Session / Meet and Greet # 3hambjvteam.com/Content/UploadImages/636432362664361250...HKS, INC Fitzgerald Collaborative Group WalkerParkingConsultants Thornton Tomasetti](https://reader033.vdocuments.mx/reader033/viewer/2022042805/5f5fc83c02cb8c1e4e4d78b4/html5/thumbnails/2.jpg)
Agenda
1. HAMB, a JV Company Overview
2. ATL – West Deck Project Description / Update
3. Trade Package Information
4. HAMB Prequalification Process
5. HAMB Procurement Process
6. Meet & Greet
![Page 3: Project Information Session / Meet and Greet # 3hambjvteam.com/Content/UploadImages/636432362664361250...HKS, INC Fitzgerald Collaborative Group WalkerParkingConsultants Thornton Tomasetti](https://reader033.vdocuments.mx/reader033/viewer/2022042805/5f5fc83c02cb8c1e4e4d78b4/html5/thumbnails/3.jpg)
» Holder Construction Company
» Austin Commercial
» C.D. Moody Construction
» Bryson Constructors
HAMB, JV Company Overview
Our Joint Venture – Construction Manager at Risk
![Page 4: Project Information Session / Meet and Greet # 3hambjvteam.com/Content/UploadImages/636432362664361250...HKS, INC Fitzgerald Collaborative Group WalkerParkingConsultants Thornton Tomasetti](https://reader033.vdocuments.mx/reader033/viewer/2022042805/5f5fc83c02cb8c1e4e4d78b4/html5/thumbnails/4.jpg)
» 7 Story, Cast-In-Place Parking Deck
» +/- 2,000,000 Total Square Feet
» Interior Courtyard at all levels
» +/- 5,700 Parking Spaces
» 3,000 SF interior office build-out
» New Elevated Pedestrian Bridge connecting to existing rail
» RCC Parkway – New Elevated Bridge / Intersection
» Project EBO Goals – 17.5% MBE & 13% FBE, 30.5% Total
» August 2017 – Start date
» Fall 2019 – Project Completion
ATL – West Deck
Project Overview
![Page 5: Project Information Session / Meet and Greet # 3hambjvteam.com/Content/UploadImages/636432362664361250...HKS, INC Fitzgerald Collaborative Group WalkerParkingConsultants Thornton Tomasetti](https://reader033.vdocuments.mx/reader033/viewer/2022042805/5f5fc83c02cb8c1e4e4d78b4/html5/thumbnails/5.jpg)
ATL – West Deck
Project Overview / Update – August 2017
![Page 6: Project Information Session / Meet and Greet # 3hambjvteam.com/Content/UploadImages/636432362664361250...HKS, INC Fitzgerald Collaborative Group WalkerParkingConsultants Thornton Tomasetti](https://reader033.vdocuments.mx/reader033/viewer/2022042805/5f5fc83c02cb8c1e4e4d78b4/html5/thumbnails/6.jpg)
ATL – West Deck
Project Overview / Update – September 2017
![Page 7: Project Information Session / Meet and Greet # 3hambjvteam.com/Content/UploadImages/636432362664361250...HKS, INC Fitzgerald Collaborative Group WalkerParkingConsultants Thornton Tomasetti](https://reader033.vdocuments.mx/reader033/viewer/2022042805/5f5fc83c02cb8c1e4e4d78b4/html5/thumbnails/7.jpg)
» INSERT IMAGE
ATL – West Deck
![Page 8: Project Information Session / Meet and Greet # 3hambjvteam.com/Content/UploadImages/636432362664361250...HKS, INC Fitzgerald Collaborative Group WalkerParkingConsultants Thornton Tomasetti](https://reader033.vdocuments.mx/reader033/viewer/2022042805/5f5fc83c02cb8c1e4e4d78b4/html5/thumbnails/8.jpg)
» INSERT IMAGE
ATL – West Deck
![Page 9: Project Information Session / Meet and Greet # 3hambjvteam.com/Content/UploadImages/636432362664361250...HKS, INC Fitzgerald Collaborative Group WalkerParkingConsultants Thornton Tomasetti](https://reader033.vdocuments.mx/reader033/viewer/2022042805/5f5fc83c02cb8c1e4e4d78b4/html5/thumbnails/9.jpg)
ATL – West Deck
![Page 10: Project Information Session / Meet and Greet # 3hambjvteam.com/Content/UploadImages/636432362664361250...HKS, INC Fitzgerald Collaborative Group WalkerParkingConsultants Thornton Tomasetti](https://reader033.vdocuments.mx/reader033/viewer/2022042805/5f5fc83c02cb8c1e4e4d78b4/html5/thumbnails/10.jpg)
ATL – West Deck
![Page 11: Project Information Session / Meet and Greet # 3hambjvteam.com/Content/UploadImages/636432362664361250...HKS, INC Fitzgerald Collaborative Group WalkerParkingConsultants Thornton Tomasetti](https://reader033.vdocuments.mx/reader033/viewer/2022042805/5f5fc83c02cb8c1e4e4d78b4/html5/thumbnails/11.jpg)
ATL – West Deck
![Page 12: Project Information Session / Meet and Greet # 3hambjvteam.com/Content/UploadImages/636432362664361250...HKS, INC Fitzgerald Collaborative Group WalkerParkingConsultants Thornton Tomasetti](https://reader033.vdocuments.mx/reader033/viewer/2022042805/5f5fc83c02cb8c1e4e4d78b4/html5/thumbnails/12.jpg)
» INSERT IMAGE
ATL – West Deck
![Page 13: Project Information Session / Meet and Greet # 3hambjvteam.com/Content/UploadImages/636432362664361250...HKS, INC Fitzgerald Collaborative Group WalkerParkingConsultants Thornton Tomasetti](https://reader033.vdocuments.mx/reader033/viewer/2022042805/5f5fc83c02cb8c1e4e4d78b4/html5/thumbnails/13.jpg)
Design Team / Document Release Information
- HFWT, A Joint Venture
HKS, INC
Fitzgerald Collaborative Group
Walker Parking Consultants
Thornton Tomasetti
- Bidding Documents – 95% “Construction Documents”
- Drawing Release Date – 10/19/2017
- 100% IFC Drawing Release Date - 11/16/2017
- Drawing Invites will be sent directly to each bidder via HelixProject on 10/20/17
ATL – West Deck
Trade Package Information
![Page 14: Project Information Session / Meet and Greet # 3hambjvteam.com/Content/UploadImages/636432362664361250...HKS, INC Fitzgerald Collaborative Group WalkerParkingConsultants Thornton Tomasetti](https://reader033.vdocuments.mx/reader033/viewer/2022042805/5f5fc83c02cb8c1e4e4d78b4/html5/thumbnails/14.jpg)
Roadway / Bridge Package (Turnkey)
Steel H-Piles
Roadway Utilities
MSE Walls
Bridge Extension
Site Walls / Paving
Signalization
Site Utilities (Remaining)
Water Utilities
Sanitary Utilities
ATL – West Deck
Trade Package Information
Structural / Misc. Steel
PED Bridge Steel Framing
Skin Steel Support
Steel Railings
Bollards
Misc. Framing / Support
Glass / Glazing
Office Windows
Curtainwall (Elevator Core Wall)
Glass Doors
![Page 15: Project Information Session / Meet and Greet # 3hambjvteam.com/Content/UploadImages/636432362664361250...HKS, INC Fitzgerald Collaborative Group WalkerParkingConsultants Thornton Tomasetti](https://reader033.vdocuments.mx/reader033/viewer/2022042805/5f5fc83c02cb8c1e4e4d78b4/html5/thumbnails/15.jpg)
Exterior Skin
Fabricoil Skin System
Artwork Framing
Canopy
ETFE Canopy
Steel Framing
Steel Wiring / Diagrid
ATL – West Deck
Trade Package Information
Metal Panels
Interior Deck Column Wraps
PED Bridge Insulated Panels
Architectural Louvers
Waterproofing
Fluid Applied Below Grade
Foundation Drains
Expansion Joints
PED Walkway Traffic Coatings
Misc. Sealants / Caulking
![Page 16: Project Information Session / Meet and Greet # 3hambjvteam.com/Content/UploadImages/636432362664361250...HKS, INC Fitzgerald Collaborative Group WalkerParkingConsultants Thornton Tomasetti](https://reader033.vdocuments.mx/reader033/viewer/2022042805/5f5fc83c02cb8c1e4e4d78b4/html5/thumbnails/16.jpg)
Masonry
Office Walls
IDF/Electrical Closet Walls
Door Frame Install
Drywall
Office Walls
Office Ceilings
Wall Insulation
Wall Framing
ATL – West Deck
Trade Package Information
Paint
Office Areas
Edge Paint Conditions
Interior Elevator Core Walls
Misc. Paint
Frames / Doors
Doors / Frames / Hardware
Office Doors / Frames / Hardware
IDF / Electrical Room D/F/H
Hardware for Glass Sliding Doors
Door Installation
![Page 17: Project Information Session / Meet and Greet # 3hambjvteam.com/Content/UploadImages/636432362664361250...HKS, INC Fitzgerald Collaborative Group WalkerParkingConsultants Thornton Tomasetti](https://reader033.vdocuments.mx/reader033/viewer/2022042805/5f5fc83c02cb8c1e4e4d78b4/html5/thumbnails/17.jpg)
Specialties
Restroom Partitions
Restroom Accessories
Fire Extinguishers / AED Units
Parking Controls
Cameras / License Plate Readers
Access Control / Monitoring
Entrance / Exit Lanes
Space Availability (Red/Green)
Hardware for Systems
Entrance Security Booths
ATL – West Deck
Trade Package Information
Asphalt Paving / Striping / Curb
Perimeter Fire Lane Paving/Curbs
Exterior Flatwork / Paving Adjustments
Space Striping (5,700 spaces)
Custom Striping
Directional Striping
Hardscape / Landscape
Site Walls
Site Heavy Duty Paving
Trees / Shrubs / Sod
Site Amenities
Special Systems
Fiber / Security / Low Voltage
![Page 18: Project Information Session / Meet and Greet # 3hambjvteam.com/Content/UploadImages/636432362664361250...HKS, INC Fitzgerald Collaborative Group WalkerParkingConsultants Thornton Tomasetti](https://reader033.vdocuments.mx/reader033/viewer/2022042805/5f5fc83c02cb8c1e4e4d78b4/html5/thumbnails/18.jpg)
Signage Code Required Signage
West Deck Signage
Wayfinding Signage
Fire ProtectionDeck / PED Bridge Dry System
Office Sprinkler System
RoofingRoofing at Stair Enclosures
Roofing at Elevator Cores
Loading Dock EquipmentCorner Guards / Edge Angles
ATL – West Deck
Trade Package Information
Millwork
Office Area Millwork
Site Security / Fencing
Permanent Fencing
Access Gates
Flooring
Carpet / Tile / Resilient / Base
![Page 19: Project Information Session / Meet and Greet # 3hambjvteam.com/Content/UploadImages/636432362664361250...HKS, INC Fitzgerald Collaborative Group WalkerParkingConsultants Thornton Tomasetti](https://reader033.vdocuments.mx/reader033/viewer/2022042805/5f5fc83c02cb8c1e4e4d78b4/html5/thumbnails/19.jpg)
» Visit www.hambjvteam.com
» Click on Prequalification Tab
» Download, Complete and Return the Prequalification Form to
Doretha Smith ([email protected])
» HAMB will review Prequalification results for each package
» All contracts over $5,000,000 must be a Joint Venture
» Joint Venture must be with business owner of different race
and/or gender
» Prequalification letters will be issued by Package
» Prime Subcontractor
» Sub-Prime Subcontractor
ATL – West Deck
Prequalification Process
![Page 20: Project Information Session / Meet and Greet # 3hambjvteam.com/Content/UploadImages/636432362664361250...HKS, INC Fitzgerald Collaborative Group WalkerParkingConsultants Thornton Tomasetti](https://reader033.vdocuments.mx/reader033/viewer/2022042805/5f5fc83c02cb8c1e4e4d78b4/html5/thumbnails/20.jpg)
Prequalification Process
![Page 21: Project Information Session / Meet and Greet # 3hambjvteam.com/Content/UploadImages/636432362664361250...HKS, INC Fitzgerald Collaborative Group WalkerParkingConsultants Thornton Tomasetti](https://reader033.vdocuments.mx/reader033/viewer/2022042805/5f5fc83c02cb8c1e4e4d78b4/html5/thumbnails/21.jpg)
Prequalification Process
![Page 22: Project Information Session / Meet and Greet # 3hambjvteam.com/Content/UploadImages/636432362664361250...HKS, INC Fitzgerald Collaborative Group WalkerParkingConsultants Thornton Tomasetti](https://reader033.vdocuments.mx/reader033/viewer/2022042805/5f5fc83c02cb8c1e4e4d78b4/html5/thumbnails/22.jpg)
Prequalification Process
![Page 23: Project Information Session / Meet and Greet # 3hambjvteam.com/Content/UploadImages/636432362664361250...HKS, INC Fitzgerald Collaborative Group WalkerParkingConsultants Thornton Tomasetti](https://reader033.vdocuments.mx/reader033/viewer/2022042805/5f5fc83c02cb8c1e4e4d78b4/html5/thumbnails/23.jpg)
ATL – West Deck
Procurement Process
» Basis of Evaluation
» Pricing
» Completion of “Scope Checklist”
» Plan to Execute the Work
» EBO Participation Plan
» Workforce Development Plan
» Project Team
» Schedule
» Unit Prices
Bid Due Dates – 11/10/17, 3 weeks after drawings released*Based on size / scope, certain bid package due dates may extend past 3 weeks
![Page 24: Project Information Session / Meet and Greet # 3hambjvteam.com/Content/UploadImages/636432362664361250...HKS, INC Fitzgerald Collaborative Group WalkerParkingConsultants Thornton Tomasetti](https://reader033.vdocuments.mx/reader033/viewer/2022042805/5f5fc83c02cb8c1e4e4d78b4/html5/thumbnails/24.jpg)
Prequalification Process
![Page 25: Project Information Session / Meet and Greet # 3hambjvteam.com/Content/UploadImages/636432362664361250...HKS, INC Fitzgerald Collaborative Group WalkerParkingConsultants Thornton Tomasetti](https://reader033.vdocuments.mx/reader033/viewer/2022042805/5f5fc83c02cb8c1e4e4d78b4/html5/thumbnails/25.jpg)
Advertisements
Outreach
Prequalification
Subs Notified of Status
RFP Issued to Subs
Pre-Proposal Meeting
Proposal Submission
Scope Meetings
Final Bid Evaluation
Owner Approval
Subcontract Award
Issue Subcontract
Request for Qualifications
Information Sessions, Association Meetings, Industry Events
Subs Complete Prequalification Statements and Return to HAMB
Available Status: Prime Subcontractors, Sub-Prime Subcontractors
HAMB Forms of Agreement
Discuss Project Scope, Prime Subs and Sub-Prime Subs Network
Sealed Envelope to HAMB
Scope Review with Each Firm that Submits
Final Bid Evaluation Presented to COA,DOA
Owner Approval of Subcontract Award
HAMB Awards the Work to Successful Proponent
HAMB Issues Subcontract to Successful Proponent
![Page 26: Project Information Session / Meet and Greet # 3hambjvteam.com/Content/UploadImages/636432362664361250...HKS, INC Fitzgerald Collaborative Group WalkerParkingConsultants Thornton Tomasetti](https://reader033.vdocuments.mx/reader033/viewer/2022042805/5f5fc83c02cb8c1e4e4d78b4/html5/thumbnails/26.jpg)
ATL – West Deck
Scope Checklist Format
![Page 27: Project Information Session / Meet and Greet # 3hambjvteam.com/Content/UploadImages/636432362664361250...HKS, INC Fitzgerald Collaborative Group WalkerParkingConsultants Thornton Tomasetti](https://reader033.vdocuments.mx/reader033/viewer/2022042805/5f5fc83c02cb8c1e4e4d78b4/html5/thumbnails/27.jpg)