Project Delivery Approaches:
“Which one is right for my facility?”
March 27, 2014
Jacob Gonzalez, P.E.
Brian Lozano, PMP
©
![Page 2: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore](https://reader034.vdocuments.mx/reader034/viewer/2022051314/55a566b71a28ab8e248b4611/html5/thumbnails/2.jpg)
AGENDA
INTRODUCTION
DESIGN BID BUILD
DESIGN BUILD
CONSTRUCTION MANAGEMENT AT RISK
INTEGRATED PROJECT DELIVERY
OPEN DISCUSSION
©
![Page 3: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore](https://reader034.vdocuments.mx/reader034/viewer/2022051314/55a566b71a28ab8e248b4611/html5/thumbnails/3.jpg)
Which project delivery approach was utilized?
Marq-E Entertainment Garage
Buffalo Niagara Medical Campus MiGo GarageWoodlands Waterway Square Garage
©
![Page 4: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore](https://reader034.vdocuments.mx/reader034/viewer/2022051314/55a566b71a28ab8e248b4611/html5/thumbnails/4.jpg)
DESIGN TEAM PROJECT MANAGER
©
![Page 5: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore](https://reader034.vdocuments.mx/reader034/viewer/2022051314/55a566b71a28ab8e248b4611/html5/thumbnails/5.jpg)
PROJECT MANAGER RESPONSIBILITIES
scope
budget schedule
©
![Page 6: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore](https://reader034.vdocuments.mx/reader034/viewer/2022051314/55a566b71a28ab8e248b4611/html5/thumbnails/6.jpg)
DESIGN TEAM PROJECT MANAGER RESPONSIBILITIES
Scope
Budget Schedule
Scope
Budget Schedule
Scope
Budget Schedule
Scope
Budget Schedule
Scope
Budget Schedule
Scope
Budget Schedule
Landscape
Architecture
MEP/IT
Civil
Traffic
Parking Design
Scope
Budget Schedule
Structural
©
![Page 7: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore](https://reader034.vdocuments.mx/reader034/viewer/2022051314/55a566b71a28ab8e248b4611/html5/thumbnails/7.jpg)
DESIGN TEAM CONSTRUCTION COST EXAMPLE
70.0%
15.0%
7.0%
5.0%
1.5%1.0% 0.5%
Structural
Architect
MEP/IT
Civil
Parking Consultant
Landscape
Traffic
©
![Page 8: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore](https://reader034.vdocuments.mx/reader034/viewer/2022051314/55a566b71a28ab8e248b4611/html5/thumbnails/8.jpg)
PROJECT ALIGNMENT
©
![Page 9: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore](https://reader034.vdocuments.mx/reader034/viewer/2022051314/55a566b71a28ab8e248b4611/html5/thumbnails/9.jpg)
PROJECT ALIGNMENT
DEFINE VISION AND GOALS
UNDERSTAND THE DELIVERY APPROACH
UNDERSTAND THE PROCUREMENT METHOD
PERFORM A SCOPE GAP ANALYSIS
PERFORM A PULL SCHEDULE
MAINTAIN ALIGNMENT THROUGHOUT
©
![Page 10: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore](https://reader034.vdocuments.mx/reader034/viewer/2022051314/55a566b71a28ab8e248b4611/html5/thumbnails/10.jpg)
DESIGN BID BUILD
Terminal E FIS Garage Phasing
Marq-E Entertainment Garage Harris County Parking Garage
©
![Page 11: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore](https://reader034.vdocuments.mx/reader034/viewer/2022051314/55a566b71a28ab8e248b4611/html5/thumbnails/11.jpg)
The Construction Management Association of America
DESIGN BID BUILD
©
![Page 12: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore](https://reader034.vdocuments.mx/reader034/viewer/2022051314/55a566b71a28ab8e248b4611/html5/thumbnails/12.jpg)
OWNER
DTPM CONTRACTOR
SUB CONTRACTORSDESIGN TEAM
contractual obligation,
direct communication
& collaboration
Indirect communication
& minimal collaboration
DESIGN BID BUILD
STRUCTURE
©
![Page 13: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore](https://reader034.vdocuments.mx/reader034/viewer/2022051314/55a566b71a28ab8e248b4611/html5/thumbnails/13.jpg)
PROJECT SCHEDULE
DESIGN-BID-BUILD: 25 MONTHS
RFP Design Permit Procure Construction
2 5 2 142
©
![Page 14: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore](https://reader034.vdocuments.mx/reader034/viewer/2022051314/55a566b71a28ab8e248b4611/html5/thumbnails/14.jpg)
DESIGN BID BUILD ADVANTAGES/DISADVANTAGES
• LONGER DURATION
• MORE RISK FOR OWNER
• CHANGE ORDERS
• OPEN COMMUNICATION
BETWEEN OWNERS AND
DESIGNERS
• DESIGN CONTROL
• COMPETITIVE PRICING
X
©
![Page 15: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore](https://reader034.vdocuments.mx/reader034/viewer/2022051314/55a566b71a28ab8e248b4611/html5/thumbnails/15.jpg)
DESIGN BID BUILD PROJECT EXAMPLE
Rusk Garage Ramp Reconfiguration
©
![Page 16: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore](https://reader034.vdocuments.mx/reader034/viewer/2022051314/55a566b71a28ab8e248b4611/html5/thumbnails/16.jpg)
DESIGN BUILD
500 South Main Garage, Las Vegas, NV
Buffalo Niagara Medical Campus MiGo Garage UTMDACC Braeswood Garage
©
![Page 17: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore](https://reader034.vdocuments.mx/reader034/viewer/2022051314/55a566b71a28ab8e248b4611/html5/thumbnails/17.jpg)
DESIGN BUILD DEFINITION
The Construction Management Association of America
©
![Page 18: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore](https://reader034.vdocuments.mx/reader034/viewer/2022051314/55a566b71a28ab8e248b4611/html5/thumbnails/18.jpg)
OWNER
DESIGN
BUILDER
SUB CONTRACTORSDTPM / DESIGN TEAM
direct communication
& collaboration
contractual obligation, direct communication
& collaboration
DESIGN BUILD
STRUCTURE
©
![Page 19: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore](https://reader034.vdocuments.mx/reader034/viewer/2022051314/55a566b71a28ab8e248b4611/html5/thumbnails/19.jpg)
PROJECT SCHEDULE
DESIGN-BID-BUILD: 25 MONTHS
DESIGN-BUILD: 21 MONTHS
RFP Design Permit Construction
ConstructionRFP Design PermitBridging
Documents
2 5 2 14
122 22 3
2
Procure
©
![Page 20: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore](https://reader034.vdocuments.mx/reader034/viewer/2022051314/55a566b71a28ab8e248b4611/html5/thumbnails/20.jpg)
DESIGN BUILD ADVANTAGES/DISADVANTAGES
• LESS DESIGN CONTROL
• DESIGN BUILDER CONTROLS
COMMUNICATION
• QUALITY OF MATERIALS
DICTATED BY DESIGN BUILDER
• RISK BY DESIGN BUILDER
• FASTER SCHEDULE
• LOWER COST
X
©
![Page 21: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore](https://reader034.vdocuments.mx/reader034/viewer/2022051314/55a566b71a28ab8e248b4611/html5/thumbnails/21.jpg)
DESIGN BUILD PROJECT EXAMPLE
500 South Main Garage, Las Vegas, NV
©
![Page 22: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore](https://reader034.vdocuments.mx/reader034/viewer/2022051314/55a566b71a28ab8e248b4611/html5/thumbnails/22.jpg)
CONSTRUCTION MANAGEMENT AT RISK
Texas Medical Center Garage 19
Texas Medical Center Garage 18Woodlands Waterway Square Garage
©
![Page 23: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore](https://reader034.vdocuments.mx/reader034/viewer/2022051314/55a566b71a28ab8e248b4611/html5/thumbnails/23.jpg)
OWNER
DTPM CONTRACTOR
SUB CONTRACTORSDESIGN TEAM
contractual obligation, direct communication
& collaboration
direct communication
& collaboration
CONSTRUCTION MANAGEMENT AT RISK STRUCTURE
©
![Page 24: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore](https://reader034.vdocuments.mx/reader034/viewer/2022051314/55a566b71a28ab8e248b4611/html5/thumbnails/24.jpg)
PROJECT SCHEDULE
DESIGN-BID-BUILD: 25 MONTHS
DESIGN-BUILD: 21 MONTHS
CM@RISK: 21 MONTHS
RFP Design Permit Construction
Construction
Construction
RFP
RFP
Design
Design
Permit
Permit
Bridging
Documents
2 5 2 14
12
12
2 5 2
2 22 3
2
Procure
©
![Page 25: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore](https://reader034.vdocuments.mx/reader034/viewer/2022051314/55a566b71a28ab8e248b4611/html5/thumbnails/25.jpg)
CMAR ADVANTAGES/DISADVANTAGES
• ADDITIONAL FEES PAID FOR CM
SERVICES
• ESTIMATES CARRY LARGER
CONTINGENCY
• REQUIRES STRONG PRECON
TEAM FROM CONTRACTOR
• MORE CONTROL OVER DESIGN
• CAN ESTABLISH GMP SOONER
• OPEN COMMUNICATION
BETWEEN ALL TEAM MEMBER
X
©
![Page 26: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore](https://reader034.vdocuments.mx/reader034/viewer/2022051314/55a566b71a28ab8e248b4611/html5/thumbnails/26.jpg)
CMAR PROJECT EXAMPLE
Texas Medical Center Garage 19
©
![Page 27: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore](https://reader034.vdocuments.mx/reader034/viewer/2022051314/55a566b71a28ab8e248b4611/html5/thumbnails/27.jpg)
George Washington University Hospital Renovations
INTEGRATED PROJECT DELIVERY
©
![Page 28: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore](https://reader034.vdocuments.mx/reader034/viewer/2022051314/55a566b71a28ab8e248b4611/html5/thumbnails/28.jpg)
INTEGRATED PROJECT DELIVERY
-The Construction Management Association of America
©
![Page 29: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore](https://reader034.vdocuments.mx/reader034/viewer/2022051314/55a566b71a28ab8e248b4611/html5/thumbnails/29.jpg)
OWNER
INTEGRATED PROJECT DELIVERY
DTPM CONTRACTOR
SUB CONTRACTORSDESIGN TEAM
Contractual obligation,
direct communication
& collaboration
©
![Page 30: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore](https://reader034.vdocuments.mx/reader034/viewer/2022051314/55a566b71a28ab8e248b4611/html5/thumbnails/30.jpg)
IPD ADVANTAGES/DISADVANTAGES
• TEAM SHOULD HAVE LONG
HISTORY OF WORKING
TOGETHER
• OWNER SACRIFICES FINANCIAL
STAKE IF TARGETS NOT MET
• BETTER FOR COMPLEX
PROJECTS
• REQUIRES STRONG
LEADERSHIP OR FACILITATORS
• INCENTIVE CONTRACTS
• RISK SHARED EQUALLY BY ALL
PARTIES
• HIGHLY COLLABORATIVE
• FASTER SCHEDULE
• LOWER COST
X
©
![Page 31: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore](https://reader034.vdocuments.mx/reader034/viewer/2022051314/55a566b71a28ab8e248b4611/html5/thumbnails/31.jpg)
OPEN DISCUSSION
©
![Page 32: Project Delivery Approaches: "Which one is right for my Parking Facility?" Walter P Moore](https://reader034.vdocuments.mx/reader034/viewer/2022051314/55a566b71a28ab8e248b4611/html5/thumbnails/32.jpg)