GCT Canada Limited Partnership
April 23, 2019
Project Brief: GCT Deltaport Berth 4
CONFIDENTIAL
Prepared for: PCLC
GCT Canada Limited Partnership
Outline
2
1. About GCT
2. GCT Deltaport Expansion, Fourth Berth Project (DP4) overview and project status
3. GCT submission to CEAA RBT2 Panel – Why?
4. Comparative analysis
5. The Ask
GCT Canada Limited Partnership
ABOUT GCT GLOBAL CONTAINER TERMINALS INC.
3
1
GCT Canada Limited Partnership
GCT Global Container Terminals Inc.
4
HQ in Vancouver, 4 million TEUs at leading global gateways
GCT CANADA GCT Vanterm GCT Deltaport GCT Inc. HQ
GCT Bayonne GCT New York
GCT USA
GCT Canada Limited Partnership
GCT Global Container Terminals Inc.
5
• In 2007 GCT was acquired by Ontario Teacher’s Pension Plan (OTPP) who owned 100% of the equity
• December 2018, IFM Investors and BCI, British Columbia Investment Management joined OTPP as equity partners
• IFM Investors manages US$81B globally of institutional funds. HQ in Australia with North America offices in New York City
• BCI manages $135B globally. HQ in Victoria, BC
• GCT remains a majority Canadian-owned company with 3 exceptional shareholders who are leading infrastructure investors with significant experience in the ports sector
Canadian & International Institutional Investors
GCT Ownership
GCT Canada Limited Partnership
Sustainable Operator Investing in the communities in which we operate
6
DELTA VANCOUVER
Delta Chamber of Commerce BC Children’s Hospital
Delta Farmland & Wildlife Trust BC Lung Association
Delta Firefighters Greater Vancouver Board of Trade
Delta Hospital Foundation Hastings Community Policing
KidSport Delta Hastings Elementary School
North Delta Blue Jays Baseball Heart & Stroke Foundation
Operation Red Nose – Delta Society Mission Possible
Reach Child & Youth Development Ride to Conquer Cancer
Rotary Club of Tsawwassen UBC Supply Chain Program
Tour de Delta Union Gospel Mission
South Delta Secondary School Scholarship & Drama Program
Vancouver Maritime Museum
GCT Canada Limited Partnership
Sustainable Operator Investing in the communities in which we operate
7
GCT Canada Limited Partnership
Responsible Stewards of Roberts Bank
8
• GCT honoured with prestigious Clean50 Top 15 clean projects award
• As part of our initiative to set the standards for sustainability in the marine industry, all four GCT terminals are Green Marine certified earning “Excellence & Leadership” in nearly every category
• GCT Canada was recognized by CN EcoConnexions Sustainable Partner program for 2018
• GCT Canada was recognized by CN EcoConnexions program for 2018
Proven environmental performance
GCT Canada Limited Partnership
GCT DELTAPORT EXPANSION, FOURTH BERTH PROJECT (DP4)
9
2
GCT Canada Limited Partnership
Marketplace context Capture of U.S. destined discretionary cargo
10
COMPETING FOR U.S. DESTINED CARGO
35
GCT Canada Limited Partnership
Marketplace context
11
CARRIERS REQUIRE FEWER BUT LARGER TERMINALS IN EACH PORT
Source: Drewry, Future of Ports and Shipping, 2015
Ocean Carriers & Alliances
Terminals
Consolidation has occurred
Consolidation still needs to occur
“The dominance of the three alliances has
changed the character of that competition, as it
provides a lot of leverage to alliances. A port
with calls from the three alliances would ideally
have three or more competing terminals that
have exactly the right capacity to serve the calls
from the respective alliances. Needless to say,
this is rarely ever the case. Ports with three
terminals and calls from three alliances can
find themselves confronted with three alliances
that predominantly use two terminals. Other
ports might have two terminal operators that
will have to deal with cargo from three
alliances. Often the outcome of such dynamics
is a “winner takes all” phenomenon, where one
terminal is over-utilised whereas the competing
terminals will be underutilised.”
(Source: pg.63, The Impact of Alliances in Container Shipping, International Transport Forum, OECD/ITF 2018)
GCT Canada Limited Partnership
Pacific Gateway Container Trade Historic Forecasts vs. Actual
12
GCT Canada Limited Partnership
BC West Coast Overview Capacity expansions vs. forecast
13
?
?
GCT Canada Limited Partnership
Long-Term Canadian Port Infrastructure Investor
14
History of GCT investment in Port of Vancouver
1997 + 2001 DP Commissioned + Expanded
2010 3rd Berth Expansion complete
CO
MP
LE
TE
D
2018 Yard Expansion & Densification
PL
AN
NE
D
Active plans Investment at GCT Vanterm
Future Investment at GCT Deltaport
$180M $300M
$160M ~$1B+
GCT Canada Limited Partnership
Informed by Robust and Advanced Environmental Studies
15
2014
2015
2016
2018
2019
Parsons Brinckerhoff
Amec Foster Wheeler
CPCS
PGL
Ausenco
DATE VENDOR DESCRIPTION
2017
Roberts Bank Container Terminal Capacity Enhancement alternatives
Conceptual Fisheries Offsetting Plans for the Proposed Deltaport Expansion Project
Assessment of Policy Options to Satisfy Canadian West Coast Container Port Capacity Needs
Preliminary Environmental Impacts Comparison: RBT2 & DP4
GCT Deltaport Expansion: Offsetting Outline and Approach
Analysis of Capacity Options on the West Coast of Canada Black Quay
• GCT independently engaged expert advisors, environmental and engineering consultants to examine capacity options for Canada’s West Coast. Based on their findings, we have concluded that incremental expansion of GCT Deltaport that would deliver up to 2 million TEUs of additional capacity in two construction stages is feasible. It may also have lower environmental impacts and deliver capacity at a lower all-in cost when compared to the proposed RBT2.
• GCT understands that GCT is not barred from submitting applications for regulatory approvals, including under the Fisheries Act (which has been significantly amended since 2003) and under CEAA 2012.
• In this case, the VFPA is GCT's regulator under several statues (CEAA 2012 and the Canada Marine Act). The VFPA’s PER process applies to activities proposed on lands and waters within its jurisdiction.
• After numerous engagements with VFPA, GCT has submitted the Preliminary Project Enquiry (PPE) to VFPA in February 2019.
GCT Canada Limited Partnership
Preliminary Project Enquiry GCT Deltaport Expansion, Fourth Berth Project (DP4)
16
GCT Canada Limited Partnership
DP4 Project Timeline
2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
17
Operations
Construction
Permitting
PER / Environmental Assessments
Indigenous & Stakeholder engagement and consultation
Pre-PER
Environmental approvals
*Determination of whether DP4 is a
designated project under CEAA / BC EAO =
EA Process
1
2
4
5
3
6
7
*The Canadian Environmental Assessment Act, 2012 designates projects that require a federal environmental assessment to determine whether the designated projects
have the potential to cause significant adverse environmental effects. New Federal legislation (Bill C-69) may change the federal environmental assessment process and its application to proposed activities. The BC Environmental Assessment Office may also be involved with the EA Process if reviewable under Provincial Assessment. The processes may be harmonized.
Timing of Project Schedule may vary and will ultimately be determined by regulatory process timelines, business case and market conditions
GCT Canada Limited Partnership
Studies informing the DP4 project rationale Engineering Studies
18
Navigational Memo -Ausenco, Capt. J. Swann
Engineering Studies (Project Design, Wharf Structure, Mooring Arrangements) - Ausenco
Roberts Bank Terminal Capacity Enhancement Alternatives -Parsons Brinckerhoff
GCT Canada Limited Partnership
Studies informing the DP4 project rationale Environmental
19
GCT Canada Limited Partnership
Studies informing the DP4 project rationale Environmental
20
Potentially lower environmental impacts
Infill = 56 ha Dredging = 43 ha Total = 99 ha Eelgrass 71% of total footprint (~70 ha)
Key Point: Overall lower environment impacts expected from smaller footprint, and in particular lower impacts to crabs and crabbing area are expected which is of significant importance to the Tsawwassen First Nation
GCT Canada Limited Partnership
GCT Deltaport Berth 4 Project
Project rendering
Short Sea Shipping Berth
Expanded Rail Yard
Expanded Container Yard
Tsawwassen First Nation Marina & Tug Basin
21
GCT Canada Limited Partnership
Deltaport Berth 4 Project
22
Aerial Photograph with existing and proposed use
GCT Canada Limited Partnership
Habitat Survey 2013
Fill Area
Dredge Area
23
Fill
GCT Canada Limited Partnership
GCT Collaboration with First Nations
• TFN is a self-governing First Nation who has implemented the first urban treaty in Canadian history
• GCT/TFN 2010 Memorandum of Understanding that sets out the framework for respectful collaboration in a number of areas for the mutual benefit and future prosperity of both organizations and GCT maintains active dialogue with the TFN Executive Council and administrative officials
• Based on TFN input GCT commissioned the PGL report - a comparative summary of RBT2 and early GCT Deltaport expansion concept effects
• Collaborative engagement continues to explore options and interests for sustainable growth of container handling capacity while preserving the responsible stewardship and co-management of Roberts Bank
• Excerpt from TFN CEAA submission on RBT2
• “TFN is not satisfied that the full range of alternative means have been sufficiently analysed, including the use of uplands adjacent to the existing terminals to construct a facility for container storage and sorting that would reduce the project footprint in the intertidal zone.”
• “ In the end, it is our view that, so far, the Proponent has not provided sufficient information for the purpose of proceeding to a public hearing.”
24
GCT Deltaport is located next to Tsawwassen First Nation (TFN)
GCT Canada Limited Partnership
Transformational Change through collaboration: Labour, Clean Growth & Timely Capacity
• DP4 will be a semi-automated expansion incorporating the newest approach to green infrastructure, taking into consideration climate impacts, community benefits and building on GCT’s collaboration with local First Nations
25
Quote from the Senate Committee on Transportation (March 21, 2018)
• DP4 will be built in consultation with labour, using innovation and new technologies while supporting quality well-paying jobs and middle-class growth
• DP4 can be brought on-line in a cost-effective staged manner by densifying an existing terminal, making it responsive to changes in the ocean shipping industry and aligning it with capacity demands
Rob Ashton, President ILWU Canada
“Now what the Port Of Vancouver is saying is, “We’re going to
utilize your money to work against you, and by the way, you can’t
have any ability to run the terminal, so we’re going to send it out
to another corporation. Some other company, an investment bank
or whatever it is”
“Then what happens is they create a fully automated terminal or
mostly automated terminal, which then drives the current
tenants either out of business or forces them to automate their
terminals, which then drives workers out of jobs.”
“With GCT at Deltaport, there has been some automation there.
That automation has happened through discussions and
negotiations with the labour unions that are represented there.”
GCT Canada Limited Partnership
DP4 Project Rationale
26
• GCT is uniquely positioned to provide the needed container terminal capacity on the Canadian West coast in the most timely, economic and sustainable way
Summary
Provides needed port capacity at the right time
Environmentally responsible based on updated scientific studies and current environmental policy
Brownfield investment reduces footprint, cost and impact per TEU of capacity provided
GCT has decades of experience operating at Roberts Bank with longstanding relationships with supply chain partners, community stakeholders, first nations and labour
Leverages public and private investments into trade corridor with three Class 1 rail infrastructure already in place
Structure in place to attract even more investment from large Canadian and international investors.
GCT Canada Limited Partnership
VFPA Project & Environmental Review Process (PER)
Total Fill Area- 56 ha. Total Dredged Area- 43 ha.
Berth #4
27
GCT Canada Limited Partnership
VFPA Project & Environmental Review Process Denial to review the application
28
At Roberts Bank, expanding the existing Deltaport container terminal is not an option for two main reasons. First, Fisheries and Oceans Canada has prohibited further land reclamation
inland from Deltaport, due to environmental sensitivity.
Second, expanding Deltaport would mean one terminal operator would control a significant majority of the market for container terminal services, Healthy competition is necessary to ensure users continue to pay reasonable rates for reliable service.
Taking all of the above factors into consideration, we will not be processing your Enquiry through our project and environmental review process at this time.
The RBT2 Project is our preferred project for achieving the expansion of capacity to meet projected increases in demand.
GCT Canada Limited Partnership
Original RBT2 proposed locations Related to 2003 DFO responses
29
GCT Canada Limited Partnership
3 GCT SUBMISSION TO CEAA RBT2 PANEL
GCT Canada Limited Partnership
GCT Submission to CEAA RBT2 Panel
31
? ?
?
GCT Canada Limited Partnership
GCT Submission to CEAA RBT2 Panel Why?
• GCT previously commented on the RBT2 project in 2014 (CEAR Document No. 111).
In reviewing the information provided by the Proponent (VFPA) and those additional from government departments and agencies with oversight, to date there have not been responses to the information requested outlined in the letter.
• The VFPA’s RBT2 project that was originally proposed in 2003 and then again in 2013 is now outmoded and, GCT submits, no longer viable given changes in a number of market factors.
It is GCT’s view that the long-term sustainability of Canada's western trade gateway is only achievable through careful terminal design that reflects a modern, innovative, and a more sustainable approach to planning and constructing such an expansion.
• As such, GCT’s submission to CEAA regarding the Proponent’s sufficiency of information focuses on gaps in three key areas:
1. Project Rationale;
2. Alternative Means Assessment; and
3. Environmental Impact Statement.
32
GCT Canada Limited Partnership
DP4 AND RBT2 COMPARATIVE ANALYSIS
4
GCT Canada Limited Partnership
Comparison between DP4 and RBT2
34
DP4 RBT2*
Cost/Capacity
• Lower cost (overall and $/TEU basis)
• Currently estimated at C$1.0 – $1.6 billion
• 2.0 million TEU of additional capacity
• More expensive (overall and $/TEU basis)
• Currently estimated at C$2.5 - $3.0 billion
• 2.4 million TEU of additional capacity
Subsidy • No taxpayer subsidy required • Significant subsidy likely to be required
Staged Construction
• Yes – Capex can be spent as demand requires
• ~3-4 yrs. IAA Process, 4-5 years construction
• Capacity available ~ 2029-2030
• No – Majority of capex needs to be spent upfront to establish the terminal Island footprint and expansion of the existing causeway
• Capacity available ~2029
Commercial Structure
• Simple development agreement & lease amendment
• No complex interface issues
• Complex interface between Infrastructure Developer and Terminal Operator
• More complex structure may lead to more disputes
Investor Commitment
• Fully committed Canadian Container Terminal Operator (CTO) with existing volumes
• CTO required to commit to future lease payments without any existing Gateway volume experience
Project Participation
• GCT Owners are committed to the project
• No publicly-confirmed commitment by CTO or Infrastructure Builder
• Project has already been abandoned once (2008)
Environmental • Both projects face environmental impacts, however DP4 is expected to have a smaller footprint and therefore
expected to have less environmental impacts.
Union Support • Support indicated by key longshore and foremen union
(ILWU) • ILWU recently issued a statement questioning the
project
First Nations • GCT has and is committed to meaningful consultation
and engagement at each stage of the process
• VFPA is proceeding to public hearing without responding to substantial outstanding information requests and concerns expressed by Indigenous communities
* The statements on T2 above are based on GCT’s internal analysis and should not be relied upon by the reader without further verification and analysis
GCT Canada Limited Partnership
ASK AND NEXT STEPS
35
5
GCT Canada Limited Partnership
The Ask and discussion
GCT is asking for fair, transparent, timely and equal footing regulatory process for private sector project proponents where the local Port Authority is a proponent of a competing project
GCT has informed government of need for comprehensive analysis of preferred container capacity growth options for West Coast of Canada
GCT is supportive of the Port Modernization Review in order to decouple current conflicted governance model of Port Authorities
36
GCT Canada Limited Partnership 37