progress status at pour 5,6 locations
DESCRIPTION
Progress Status aTRANSCRIPT
Progress Status at Podium LB 6,7 & UB 5 Locations
Status as on 24th Nov’15
30% staging works yet to be done at pour 5 UB location.
Retaining wall (Dependent activity ) not yet casted at pour 5 UB location
40% shuttering works yet to be done at pour 5 UB location.
Staircase columns not yet casted at pour 5 location.
20% shuttering work yet to be done at pour 6 location.
No manpower been deployed for reinforcement works at Pour 6 location.
Beam B34 bottom not yet initiated at pour 6 location.
Rain water tank bottom slab not yet casted at pour 6 location.
16 columns yet to be casted at pour 7 location .
Casting of starters not been initiated at pour 7 locations