progress report test-production drilling program i' concerning...

34
PROGRESS REPORT TEST-PRODUCTION DRILLING PROGRAM CONCERNING R.W. PORTER'S PROPOSED KITLEY LAKE SUBDIVISION I ' / . Prepared for MR. R. LITTLE 105 - 650 Lexington Drive KELOWNA, e.c. viw 3e6 Prepared by PACIFIC HYDROLOGY CONSULTANTS LTD. 204 - 1929 West Broadway VANCOUVER, B.C. V6J 123 I JULY 2, 1991

Upload: others

Post on 09-May-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PROGRESS REPORT TEST-PRODUCTION DRILLING PROGRAM I' CONCERNING …a100.gov.bc.ca/appsdata/acat/documents/r7890/OK204_115713117… · W 1.0 SUMMARY AND CONCLUSIONS I. i b- The recent

PROGRESS REPORT

TEST-PRODUCTION DRILLING PROGRAM

CONCERNING R.W. PORTER'S PROPOSED KITLEY LAKE SUBDIVISION I ' / .

Prepared f o r

M R . R . LITTLE 105 - 650 Lexington Drive

KELOWNA, e . c . viw 3e6

Prepared by

PACIFIC H Y D R O L O G Y CONSULTANTS L T D . 204 - 1929 West Broadway V A N C O U V E R , B.C. V6J 123

I

JULY 2, 1991

Page 2: PROGRESS REPORT TEST-PRODUCTION DRILLING PROGRAM I' CONCERNING …a100.gov.bc.ca/appsdata/acat/documents/r7890/OK204_115713117… · W 1.0 SUMMARY AND CONCLUSIONS I. i b- The recent

E. LIVINGSTON. P. E N A. BADRY

U

PACIFIC HYDROLOGY CONSULTANTS LTD, CONSULTING GROUNDWATER GEOLOGISTS

' .

July 2 , 1991

Mr. R . L i t t l e 105 - 650 Lexington Drive KELOWNA, B.C. V 1 W 3B6

Subject: Progress Report Test-Production Drilling Program Concerning R.W. Porter's Proposed K i tl ey Lake Subdi vi si on

, e".-

Dear S i r :

204 - 1929 WEST BROADWAY VANCOUVER, B.C. V 6 J 123 TELEPHONE: (604) 738-9232

Enclosed herewith i s o u r report which discusses the r e su l t s o f the recent test-production d r i l l i n g car r ied out t o develop a source of groundwater f o r Mr . R . ( Bob) Porter Is proposed Kit 1 ey Lake Subdi v i s i on.

Please ca l l i f you wish t o discuss any aspect o f the contents of the report .

Yours t r u l y ,

P A C I F I C H Y D R O L O G Y CONSULTANTS LTD.

! i j i

1 -

E . L i v i n g s t o n , P. E n g . / -

Page 3: PROGRESS REPORT TEST-PRODUCTION DRILLING PROGRAM I' CONCERNING …a100.gov.bc.ca/appsdata/acat/documents/r7890/OK204_115713117… · W 1.0 SUMMARY AND CONCLUSIONS I. i b- The recent

PROGRESS REPORT

TEST-PRODUCTION DRILLING PROGRAM

CONCERNING R.W. PORTER'S PROPOSED KITLEY LAKE SUBDIVISION

TABLE OF CONTENTS

Sub .i ec t Page Section

i LETTER OF TRANSMITTAL

1 1 .o

2.0

3.0

4.0

SUMMARY AND CONCLUSIONS

3 RECOMMENDATIONS

4 INTRODUCTION

TEST-PRODUCTION DRILLING AND WELL CONSTRUCTION 5

5 5 6

4.1 General 4.2 Test Holes No. 1-1991 and No. 2-1991 4.3 Test Well No. 1-1991

7 PUMP TESTING 5.0

7 7

5.1 Test Procedure 5.2 Test Results

a a 8

6.0 WELL CAPACITY 6.1 Capacity of Test Well No. 1-1991 6.2 Aquifer Capacity

9 7.0

8.0

GROUNDWATER QUALITY

COURSE OF ACTION 10

Page 4: PROGRESS REPORT TEST-PRODUCTION DRILLING PROGRAM I' CONCERNING …a100.gov.bc.ca/appsdata/acat/documents/r7890/OK204_115713117… · W 1.0 SUMMARY AND CONCLUSIONS I. i b- The recent

i $-- L

E_=

1 .

, ; i

TABLE OF CONTENTS ( c o n t ' d )

APPENDICES

APPENDIX A AREA AND WELL LOCATION MAP

APPENDIX B LITHOLOGS, S I E V E ANALYSES AND WELL CONSTRUCTION DETAILS

APPENDIX C PUMPING TEST DATA AND PLOTS

APPENDIX D GROUNDWATER QUALITY . ._-

FIGURES

I *li

' Number T i t l e Page - F i g u r e 1 Area and Wel l L o c a t i o n Map - R.W. P o r t e r ' s K i t l e y

Lake Subdi v i s i on A - 1

F i g u r e 2 C o n s t r u c t i o n D e t a i l s o f R.W. P o r t e r ' s K i t l e y Lake T e s t Wel l No. 1-1991 B - 4

F i g u r e 3 S e m i - l o g a r i t h m i c P l o t o f Drawdown i n R.W, P o r t e r ' s T e s t Wel l No. 1-1991 c - 4

F i g u r e 4 S e m i - l o g a r i t h m i c P l o t o f Recovery o f Water Leve l - i n R.W. P o r t e r ' s T e s t Wel l No. 1-1991 c - 5

Page 5: PROGRESS REPORT TEST-PRODUCTION DRILLING PROGRAM I' CONCERNING …a100.gov.bc.ca/appsdata/acat/documents/r7890/OK204_115713117… · W 1.0 SUMMARY AND CONCLUSIONS I. i b- The recent

W

1.0 SUMMARY AND CONCLUSIONS

I .

i

b-

The recent t e s t d r i l l i n g program, which included the construction and preliminary pump tes t ing of a screened test-production well, on R.W. Por te r ' s Property on White Lake Road s o u t h of Kitley Lake, has shown the following:

1 . I n the area o f the intersect ion of White Lake Road and the Access Road t o the R.W. Porter Property, the overburden sediments are t h i n . Two t e s t holes were d r i l l e d t h r o u g h 2 .4 t o 3.0 m ( 8 t o 10 f t ) o f clay, compact gravel and t i l l . I n the f i r s t t e s t hole, a f r ac tu re zone between 4.3 and 6 .7 m (14 and 2 2 f t ) i n red-coloured bedrock yielded a b o u t 2.3 L/rnin ( 3 gpm). The second hole contained no water-bearing zone t o the t o t a l depth of 13.1 m (43 f t ) .

2 . The sediments a t the s i t e of Test Well No. 1-1991, i n the central par t of the Kitley Valley, contain a coarse sand aquifer between 3.7 and 9.1 m ( 1 2 a n d 30 f t ) i n which a screen was s e t between 6.63 and 9.39 rn ( 2 1 . 7 5 a n d 30.8 f t ) ; the aquifer i s non-flow ar tes ian w i t h a confining layer o f c lay t o 2 . 4 m ( 8 f t ) a n d a s t a t i c water level close t o surface.

3. Test Well No. 1-1991 was pump tes ted a t a constant r a t e of 9.1 L/sec (120 igpm) f o r f ive hours, a t the end of which the pumping water level was i n the screen and was s t i l l drawing down. The capacity of Test Well No. 1-1991 i s c l ea r ly much less t h a n the t e s t r a t e of 9.1 L/sec.

4. Following the termination of p u m p i n g , the water level recovered f a i r l y rapidly, showing good recharge a t the time of the t e s t on June 14 . From the recovery d a t a , a moderate aquifer t ransmissivi ty of 337 m2/day (2 .26 x 104 igpd / f t ) i s calculated. Under the prevailing hydrogeoJogic conditions, aquifer transmissivity i s not considered t o be the control l ing fac tor insofar as aquifer a n d well capacity i s concerned; ra ther , the nature of aquifer recharge a t the end of the summer drought will ult imately determine the amoun t of groundwater which can be exploited by wells.

- 1 -

Page 6: PROGRESS REPORT TEST-PRODUCTION DRILLING PROGRAM I' CONCERNING …a100.gov.bc.ca/appsdata/acat/documents/r7890/OK204_115713117… · W 1.0 SUMMARY AND CONCLUSIONS I. i b- The recent

a

l i

5. Assuming that there is no significant seasonal decline in the water level in Test Well No. 1-1991 and, based on projected drawdown to 100 days of continuous pumping, a theoret ica l capacity of about 3.03 L/sec (40 igpm) is calculated for Test Well No. 1-1991.

6. A chemical analysis of a water sample collected from Test Well No. 1-1991 near the end of five hours of pumping shows a moderately highly mineralized water which is fairly hard and typical of groundwater quality in the B.C. Interior. The water quality shown by the analysis is certainly acceptable for domestic use; the analysis also showed the water to be free of iron.

-- 7 . Before finalizing subdivision plans, the capacity of the aquifer in the

Kitley Valley must be better evaluated at the time of minimum groundwater conditions, to ensure that recharge conditions are satisfactory at that time.

i I ' - 2 -

Page 7: PROGRESS REPORT TEST-PRODUCTION DRILLING PROGRAM I' CONCERNING …a100.gov.bc.ca/appsdata/acat/documents/r7890/OK204_115713117… · W 1.0 SUMMARY AND CONCLUSIONS I. i b- The recent

Irr

2.0 RECOMMENDATIONS

All things considered, before proceeding with additional t e s t d r i l l i n g or other work necessary t o "prove u p " a water supply source fo r R.W. Por t e r ' s proposed Kitley Lake Subdivision, i t i s obvious t h a t the aquifer encountered in Test Well No. 1-1991 should be be t te r evaluated as a long-term water supply source. We recommend the following:

1 . During the summer, monitor the water level in the well in an e f f o r t t o determine i f there i s a seasonal decline a n d , i f so, the amount of the decline. Semi-monthly water level observations would be sui table .

2 . A t the end of the summer, when groundwater conditions are minimum, a t the time of no recharge and high evapotranspiration, carry o u t an aquifer t e s t - i n p a r t i c u l a r , t o evaluate the aquifer recharge s i tua t ion .

3 . From the r e su l t s o f 1 . and 2., decide on whether additional t e s t d r i l l i n g should be carried o u t a n d , i f so, where.

- 3 -

Page 8: PROGRESS REPORT TEST-PRODUCTION DRILLING PROGRAM I' CONCERNING …a100.gov.bc.ca/appsdata/acat/documents/r7890/OK204_115713117… · W 1.0 SUMMARY AND CONCLUSIONS I. i b- The recent

3.0 INTRODUCTION

3 , J

i

I '

This report has been prepared to:

1. Describe the results of the test-production drilling at three sites on R.W. Porter's Property on the west side of White Lake Road south of Kitley Lake.

2 . Outline a program for completing an evaluation of the groundwater potential on R.W. Porter's Kitley Lake Property so that subdivision plans can be formulated based on the quantity of groundwater available.

~-... A "Concept Plan" for subdivision of R.W. Porter's Kitley Lake Property is given in a report by G.G. Runka Land Sense Ltd., dated September 1980, and i denti f i ed as "Overview Expl anatory Notes to accompany LAND RESOURCE MAP FOLIO". The subject Porter Property is legally described as a combination of:

Sb of N3, Sec. 10, Tp. 88, S.D.Y.D. (k135 acres/k54 hectares);

N$ of S3, Sec. 10, Tp. 88, S.D.Y.D. (k.145 acres/k59.5 hectares);

D.L. 2454s, except Plans 19670 and 20503 and Lot 1 of Plan 23864

Lot 2, Plan 23864, D.L. 2454, S.D.Y.D.

(kt-115 acres/k46.5 hectares);

Meetings in Penticton on March 25, 1991, at Century 21's Office, and later onsite at the Property, were held to discuss subdivision possibilities and groundwater exploration. Present at the office meeting were: Mr. Bob Porter, Property Owner; Mr. Bob Little, representative for the Owner; Mr. Len Fox, P. Eng., now of REMAX Penticton Realty; Mr. Keith Robbins of Robbins Water Well Drilling Ltd.; and Mr. Ed Livingston, P. Eng., of Pacific Hydrology Consultants Ltd. Except for Mr. Fox, all present at the office meeting subsequently were present at discussions in the field where three sites for test-production drilling were selected: two sites in the area of the intersection of the Property Access Road and White Lake Road, where there are presently two dug wells, and the third site in the Kitley Valley on the road which crosses the waterlogged area.

- 4 -

Page 9: PROGRESS REPORT TEST-PRODUCTION DRILLING PROGRAM I' CONCERNING …a100.gov.bc.ca/appsdata/acat/documents/r7890/OK204_115713117… · W 1.0 SUMMARY AND CONCLUSIONS I. i b- The recent

4.0 TEST-PRODUCTION DRILLING AND WELL CONSTRUCTION

4.1 General

, "

L

The test-producti on dri 11 i ng program was car r ied o u t by Robbi ns Water Well Dri l l ing L t d . u s i n g a cable tool d r i l l rig and 150 mrn (6") diameter casing. As i t turned out , the t e s t hole a t the t h i r d s i t e i n Kitley Valley was completed as a screened Test Well (No. 1-1991) . The approximate locations of the two Test Holes and the Test Well are shown on Figure 1 i n Appendix A . The d r i l l e r ' s l i thologs and other de t a i l s about the two Test Holes and the Test Well are contained i n Appendix B.

4.2 Test Holes No. 1-1991 and No. 2-1991

The f i r s t t e s t hole (No. 1-1991) was d r i l l e d a short distance s o u t h of the intersect ion of the Property Access Road w i t h White Lake Road. I t was d r i l l e d t h r o u g h 1 . 5 m ( 5 f t ) of so f t sandy clay over 1 .5 m ( 5 f t ) of compact sand and gravel where i t reached varicoloured volcanics of the Kitley Lake Member of the Marron Formation of ear ly Tert iary Age, which underlie the subject area. A t Mr. L i t t l e ' s ins t ruc t ion , d r i l l i n g was continued t o a depth of 20.4 m (67 f t ) i n the rock. A small f rac ture zone i n the interval 4.3 t o 6 . 7 m ( 1 4 t o 22 f t ) yielded a small amount of water, which was shown by bail t es t ing t o be a b o u t 2.3 L / m i n ( 3 gpm) . A t o p was welded on the 150 mm ( 6 " ) diameter casing, which was in s t a l l ed t h r o u g h the overburden t o a depth of 3.35 m ( 1 1 f t ) .

The second Test Hole (No. 2-1991) was d r i l l e d i n the same general area, on the south s ide of the Property Access Road i n d c lose t o White Lake Road, a t a s i t e between the two ponds. Test Hole No. .2-1991 encountered 2 .4 rn ( 8 f t ) of compact sediment over bedrock. A t t h i s s i t e , the casing was recovered.

- 5 -

Page 10: PROGRESS REPORT TEST-PRODUCTION DRILLING PROGRAM I' CONCERNING …a100.gov.bc.ca/appsdata/acat/documents/r7890/OK204_115713117… · W 1.0 SUMMARY AND CONCLUSIONS I. i b- The recent

U

4.3 T e s t Well No. 1-1991

The t e s t hole a t the th i rd s i t e i n the Kitley Valley encountered a sand and gravel aquifer between 2.4 and 9.1 rn ( 8 and 30 f t ) , overlain by clay and underlain by 0.9 m ( 3 f t ) of compact sediment, described by the d r i l l e r as " t i l l " , above so f t red bedrock.

Samples of aquifer sand and gravel i n the interval 4.3 t o 9.1 rn ( 1 4 t o 30 f t ) were shipped t o Pacific Hydrology and sieve analyses were carr ied out t o design a screen; the sieve analyses p lo ts a re included i n Appendix B. Based on these analyses, 2 . 4 rn ( 8 f t ) of 150 mm ( 6 " ) nominal diameter Johnson s t a in l e s s s tee l well screen, consisting of 1 . 2 rn ( 4 f t ) of 2.54 mm (0.100") s l o t over 1 . 2 m of 3.05 mm (0.120") s l o t was i n s t a l l ed between 6.63 and 9.39 m (21 .75 and 30.8 f t ) . Details of the construction o f Test Well No. 1-1991 are shown on Figure 2 in Appendix B (Page B - 4 ) .

Development o f Test Well No. 1-1991 was carr ied o u t by standard we1 1 development techniques of bai 1 i n g , surging and pumping, u n t i 1 the amount of sand t h a t could be brought in to the well was reduced t o an

'acceptable level .

- 6 -

Page 11: PROGRESS REPORT TEST-PRODUCTION DRILLING PROGRAM I' CONCERNING …a100.gov.bc.ca/appsdata/acat/documents/r7890/OK204_115713117… · W 1.0 SUMMARY AND CONCLUSIONS I. i b- The recent

5.0 PUMP TESTING

5.1 Test Procedure

i Following completion of the well development, Robbins Water Well

Dri l l ing L t d . carr ied out a constant-rate pumping t e s t fo r 300 minutes ( f i v e hours) a t a r a t e of 9.1 L/sec (120 igpm). Following the termination of pumping , the recovery of the water level was observed fo r 30 minutes.

5.2 Test Results

Data collected d u r i n g the pumping t e s t are included i n Appendix C , along w i t h s t a n d a r d s t r a igh t l i ne plots of the data on semi-logars-hmic g r a p h paper.

The plot of the drawdown d a t a (Figure 3, Page C - 4 ) shows t h a t :

1 . More t h a n half of the drawdown which occurred d u r i n g the 300 minutes of pumping took place in the f i r s t minute of pumping. However, since the residual drawdown i n the f i r s t minute a f t e r pumping stopped was only 1.00 m (3 .29 f t ) , compared t o 4 .78 m (15.67 f t ) i n the f i r s t minute of p u m p i n g , i t seems l ike ly t h a t an aquifer boundary was intercepted almost immediately a f t e r p u m p i n g s t a r t ed .

2 . A negative aquifer boundary was de f in i t e ly intercepted a t about 90 minutes a f t e r the s t a r t of p u m p i n g ; t h i s boundary i s ref lected i n a steepening of the drawdown p l o t .

The plot of the recovery o f the water level following the termination of pumping (Figure 4 , Page C - 5) sh6ws t h a t recharge conditions were cer ta in ly good a t the time of the t e s t on June 1 4 , a s ref lected i n rapid recovery of the water level t o the pre-pumping s t a t i c level . From the recovery p lo t , an aquifer t ransmissivi ty of 337 m2/day (2 .26 x lo4 igpd / f t ) i s calculated. This i s a moderate t ransmissivi ty showing good water-yielding capabi l i ty f o r the aquifer. However, under the prevail ing geologic conditions, the aquifer transmissivity i s n o t the constr ic t ion t o well capacity; ra ther the nature of recharge a t the end of the summer d r o u g h t w i l l be the main f ac to r determining well capacity.

- 7 -

Page 12: PROGRESS REPORT TEST-PRODUCTION DRILLING PROGRAM I' CONCERNING …a100.gov.bc.ca/appsdata/acat/documents/r7890/OK204_115713117… · W 1.0 SUMMARY AND CONCLUSIONS I. i b- The recent

6.0 WELL CAPACITY

6.1 Capac i t y o f Tes t Wel l No. 1-1991

9.1 te rm r a t e t e s t

Pump t e s t i n g o f Tes t Wel l No. 1-1991 f o r 300 minutes a t a r a t e of ./sec (120 igpm) drew t h e wa te r l e v e l down i n t o t h e screen and, a t t h e n a t i o n o f pumping, t h e water l e v e l was s t i l l d rawing down a t a cons tan t

Obvious ly , t h e c a p a c i t y o f t h e Wel l i s c o n s i d e r a b l y l e s s than t h e pumping r a t e o f 9.1 L/sec.

Under t h e p r e v a i 1 i ng c o n d i t i o n s , where drawdown was s t i 11 o c c u r r i n g when t e s t i n g was t e r m i n a t e d and where t e s t i n g was c a r r i e d o u t a t t h e t i m e o f maximum recharge, i t i s n o t p o s s i b l e t o e s t a b l i s h t h e c a p a c i t y o f t h e W e l l . I f t h e t r e n d o f t h e l a s t p a r t o f t h e drawdown p l o t i s p r o j e c t e d t o 100 days, a s p e c i f i c c a p a c i t y o f 0.7 L/sec/m (2.93 i g p m / f t ) i s c a l c u l a t e d . Then, based on such an assumed w e l l performance, a t h e o r e t i c a l w e l l c a p a c i t y i n t h e range 2.8 t o 3.3 L/sec (37 t o 434 igpm) i s c a l c u l a t e d . However, l ong d u r a t i o n pumping a t t h e t i m e o f minimum groundwater c o n d i t i o n s c o u l d show t h a t o t h e r p o s i t i v e o r n e g a t i v e a q u i f e r boundar ies a re i n t e r c e p t e d d u r i n g pumping which would r e s u l t i n an h i g h e r o r lower w e l l c a p a c i t y . F u r t h e r , i f t h e r e i s a s i g n i f i c a n t d e c l i n e i n t h e water t a b l e , t h e c a p a c i t y o f t h e Wel l would a l s o be l e s s because o f l e s s a v a i l a b l e drawdown.

6.2 A q u i f e r CaDaci tv

U n t i l a l o n g - d u r a t i o n pumping t e s t o f Tes t Well No. 1-1991 can be c a r r i e d o u t a t t h e t i m e o f minimum c o n d i t i o n s , t o b e t t e r e v a l u a t e recharge t o t h e a q u i f e r which y i e l d s wa te r t o t h e Wel l , i t i s n o t p o s s i b l e t o e s t i m a t e t h e c a p a c i t y o f t h e a q u i f e r ( s ) i n t h e K i t l e y Lake V a l l e y . A t t h i s t ime, t h e e x t e n t o f t h e a q u i f e r i s a l s o unknown. I f t h e a q u i f e r i s a l o c a l bounded pa tch o f permeable sediments con ta ined w i t h i n sediments o f much 1 ower permeabi 1 i ty, a d d i t i o n a l we1 1 s may n o t p r o v i de a d d i t i o n a l water . The encouraging p a r t i s t h a t Well No. 1-1991 i s l o c a t e d i n a permanent ly water logged area, i n d i c a t i n g con t inuous groundwater d i scha rge . Even so, t h e s c a l e o f , t h e groundwater f l o w system and t h e n a t u r e o f recharge t o t h e system a re t h e f a c t o r s which c o n t r o l t h e c a p a c i t y o f t h e a q u i f e r a t t h e end o f t h e p e r i o d o f no recharge.

- 8 -

Page 13: PROGRESS REPORT TEST-PRODUCTION DRILLING PROGRAM I' CONCERNING …a100.gov.bc.ca/appsdata/acat/documents/r7890/OK204_115713117… · W 1.0 SUMMARY AND CONCLUSIONS I. i b- The recent

7.0 GROUNDWATER QUALITY

A water sample was col lected near the end of the pumping t e s t and submitted t o Analytical Service Laboratories L t d . (ASL) for analysis. The report from ASL i s contained i n Appendix D.

The ASL analysis shows a groundwater typical of the B.C. In te r ior . The water i s hard and moderately highly mineralized. I t i s a calcium + magnesium/bicarbonate type water. The groundwater represented by the ASL analysis meets guidelines of B.C. Ministry of Health and Health and Welfare Canada fo r a l l parameters checked. The groundwater i s generally of good qua l i ty f o r domestic uses.

The laboratory conductivity, a general measure o f the mineralization of a water o f 443 microsiemens, i s i n c lose agreement w i t h the conductivity of 400 microsiemens of the outflow of Kitley Lake, measured w i t h a f i e l d meter conductivity a t the time o f the f i e l d investigation of March 25, 1991.

- 9 -

Page 14: PROGRESS REPORT TEST-PRODUCTION DRILLING PROGRAM I' CONCERNING …a100.gov.bc.ca/appsdata/acat/documents/r7890/OK204_115713117… · W 1.0 SUMMARY AND CONCLUSIONS I. i b- The recent

8.0 COURSE OF ACTION

f 'I

Under the prevailing circumstances, i t i s obvious t h a t careful pump t e s t ing of Test Well No. 1-1991 m u s t be carr ied o u t a t the end of the d r o u g h t period t o provide a r e a l i s t i c basis for evaluating the capacity of the aquifer in the Kitley Lake Valley. Depending on the outcome of such t e s t i n g , i t may also be advisable t o continue the groundwater exploration program. If the aquifer which y ie lds water t o Test Well No. 1-1991 i s a local isolated p a t c h and n o t par t of a continuous aquifer f i l l i n g the Valley, i t may be possible t o construct other s imilar wells in other patches o f aquifer . On the other h a n d , i f there i s one continuous aquifer f i l l i n g the valley t o Kitley Lake, which receives only limited recharge, additional wells may n o t y ie ld more water.

As mentioned previously, the amount o f seasonal f luctuat ion in the water t a b l e w i l l give some clues a s t o the scale of groundwater f l o w system and thus t o the nature o f recharge. This knowledge, combined with a careful p u m p i n g t e s t of l e s t Well No. 1-1991 a t the end of the summer d r o u g h t , will e i t he r provide a basis for establishing the groundwater potential on R.W. Po r t e r ' s Kitley Lake Property or for defining w h a t i s necessary t o be t te r evaluate the groundwater potent ia l .

All things considered, the following course o f action i s recommended:

1 .

2.

3.

Monitor the water level in l e s t Well No. 1-1991 on a semi-monthly basis throughout the summer.

A t the end of the summer d r o u g h t , ca r ry o u t a long-duration pumping t e s t o f l e s t Well No. 1-1991, ensuring t h a t the discharge water from the t e s t i s conveyed o u t of the Kitley Lake basin by direct ing i t over the ridge t o the eas t .

A t the end of the long-duration pumping t e s t , co l l ec t a water sample and obtain a par t ia l analysis t o determine whether there are s ign i f icant seasonal changes in groundwater q u a l i t y .

- 10 -

Page 15: PROGRESS REPORT TEST-PRODUCTION DRILLING PROGRAM I' CONCERNING …a100.gov.bc.ca/appsdata/acat/documents/r7890/OK204_115713117… · W 1.0 SUMMARY AND CONCLUSIONS I. i b- The recent

APPENDIX A

AREA AND WELL LOCATION MAP

Page 16: PROGRESS REPORT TEST-PRODUCTION DRILLING PROGRAM I' CONCERNING …a100.gov.bc.ca/appsdata/acat/documents/r7890/OK204_115713117… · W 1.0 SUMMARY AND CONCLUSIONS I. i b- The recent

U U

AREA AND WELL LOCATION MAP - R.W. PORTER'S KITLEY LAKE SUBDIVISION

FIGURE 1

~~~~ ~

Notes:

1. The base map is 1:50,000 s c a l e topographic map N.T.S. 82E/5, Penticton, en la rged t o an approximate s c a l e o f 1:23,500.

2 .

3.

Boundary of R.W. P o r t e r Property.

Approximate (unsurveyed) l o c a t i o n of a Test Hole or Test Well, a s i d e n t i f i e d . 0 + A - I

Page 17: PROGRESS REPORT TEST-PRODUCTION DRILLING PROGRAM I' CONCERNING …a100.gov.bc.ca/appsdata/acat/documents/r7890/OK204_115713117… · W 1.0 SUMMARY AND CONCLUSIONS I. i b- The recent

APPENDIX B

LITHOLOGS, SIEVE ANALYSES AND WELL CONSTRUCTION DETAILS

i

Page 18: PROGRESS REPORT TEST-PRODUCTION DRILLING PROGRAM I' CONCERNING …a100.gov.bc.ca/appsdata/acat/documents/r7890/OK204_115713117… · W 1.0 SUMMARY AND CONCLUSIONS I. i b- The recent

'y: w

TEST HOLE NO. 1-1991 ON R . PORTER'S PROPOSED KITLEY LAKE SUBDIVISION

Locat ion: West of White Lake Road nea r P rope r ty Ent rance .

Date o f d r i l l i n g : May 1991

Con t rac to r : Robbins Water Well D r i l l i n g L t d .

L i tho1 og :

0 - 1 .5 m ( 0 - 5 f t ) 1 .5 - 2.1 m ( 5 - 7 f t ) 2.1 - 3.0 rn ( 7 - 10 f t ) 3.0 - 4 . 3 m ( 1 0 - 14 f t ) 4.3 - 6.7 m (14 - 22 f t )

6.7 - 11.0 m ( 2 2 - 36 f t ) 11.0 - 12.8 m ( 3 6 - 42 f t ) 12.8 - 16.2 m (42 - 53 f t ) 16.2 - 20.4 m ( 5 3 - 67 f t )

Diameter: 150 mm 20.4 m

S t a t i c water 1 eve1

s o f t sandy c l a y brown sand and g r a v e l ; t i g h t l a r g e and small s h a r p g rave l red bedrock; very s o f t red rock w i t h a small f r a c t u r e c o n t a i n i n g

some water dark brown rock b l ack rock s o f t brown rock dark r ed rock .

( 6 " ) c a s i n g t o 3.4 rn (11 f t ) and 150 mm rock h o l e t o 67 f t ) .

unknown.

Remarks: A b a i l t e s t i n d i c a t e d a c a p a c i t y about 2 .3 L / m i n (4 igpm).

S t a t u s : S t e e l p l a t e welded on c a s i n g .

B - 1

Page 19: PROGRESS REPORT TEST-PRODUCTION DRILLING PROGRAM I' CONCERNING …a100.gov.bc.ca/appsdata/acat/documents/r7890/OK204_115713117… · W 1.0 SUMMARY AND CONCLUSIONS I. i b- The recent

U W

TEST HOLE NO. 2-1991 ON R . PORTER'S PROPOSED KITLEY LAKE SUBDIVISION

L o c a t i o n : On t h e south s i d e o f t h e Access Road, south o f t h e o l d shed, between t h e two ponds.

Date o f d r i l l i n g : May 1991.

C o n t r a c t o r : Robbins Water Wel l D r i l l i n g L t d .

L i t h o l o g s :

0 - 1.8 m ( 0 - 6 f t ) g r e y sandy loam 1 .8 - 2 . 4 rn ( 6 - 8 f t ) t i g h t sandy till 2.4 - 4.3 rn ( 8 - 14 f t ) soft r e d r o c k 4.3 - 6.1 m (14 - 20 ft) r e d d i s h brown r o c k 6.1 - 9.8 rn (20 - 32 f t ) dark brown r o c k 9.8 - 13.1 rn (32 - 43 f t ) b l a c k r o c k .

I..

Diameter: 150 mm ( 6 " ) c a s i n g t o 2.4 rn ( 8 f t ) w i t h 150 mm r o c k h o l e t o 13.1 rn (43 f t ) .

S t a t u s : C a s i n g recovered, h o l e b a c k f i l l e d and s i t e abandoned.

B - 2

Page 20: PROGRESS REPORT TEST-PRODUCTION DRILLING PROGRAM I' CONCERNING …a100.gov.bc.ca/appsdata/acat/documents/r7890/OK204_115713117… · W 1.0 SUMMARY AND CONCLUSIONS I. i b- The recent

TEST WELL NO. 1-1991 ON R. PORTER'S PROPOSED KITLEY LAKE SUBDIVISION

Locat ion: I n the water logged a r e a i n t h e v a l l e y south of K i t l e y Lake.

3

Date of c o n s t r u c t i o n : May 1391.

C o n t r a c t o r : Robbins Water Well D r i l l i n g L t d .

L i tho1 og :

0 - 0.15 rn ( 0 - h f t ) 0.15 - 1 . 8 m ( $ - 6 f t ) 1 . 8 - 2.4 m ( 6 - 8 f t ) 2 .3 - 3.0 rn ( 8 - 70 f t ) 3.0 - 3.7 m ( 1 0 - 12 f t )

3.7 - 4 . 3 m (12 - 14 f t ) 4.3 - 7.3 m (14 - 24 f t ) 7 . 3 - 7.9 m (24 - 26 f t ) 7.9 - 9.1 m (26 - 30 f t ) 9.1 - 9.8 m (30 - 32 f t ) 9 .8 - 76.8 rn (32 - 55 f t )

Diameter: 150 rnm ( 6 " ) .

black o r g a n i c s o i l brown sandy c l a y brown c l ay brown sand dark brown sand and small g rave l becoming

c l e a n e r brown c o a r s e sand w i t h c o b b l e s brown c o a r s e sand , c l e a n e r a t bottom c l e a n c o a r s e sand w i t h c o b b l e s brown c o a r s e sand w i t h s h a r p s t o n e s sand w i t h c l a y ; t i g h t e r b u t making water red s o f t bedrock.

S t a t i c water l e v e l : On June 14, 1991, 0.165 rn (0 .54 f t ) below the wel l c a s i n g s t ickup c u t o f f a lmost a t ground s u r f a c e .

Compl e t i on :

Test-Product ion Well ,No. 1-1991 i s completed w i t h t he f o l l o w i n g assembly of 150 mm ( 6 " ) nominal s ize Johnson s t a i n l e s s s t e e l wel l s c r e e n :

a t t o p a t 6.63 m (21.75 f t ) 1.2 m ( 4 f t ) of 2.54 mrn (0 .100") s l o t sc reen 1.2 rn ( 4 f t ) of 3.05 mrn (0 .120") s l o t s c r e e n a t bottom a t 9.39 m ( 3 0 . 8 f t ) f l a t bottom.

Measurements a r e below the well c a s i n g .

t y p e K packer

Well performance: O n June 14 , 1991, a f t e r c o n s t a n t r a t e of 9.1 L/sec was 7.343 m (24.085 f t ) 1.24 L/sec/m ( 4 . 9 8 igpm/f t

f i v e hours of pumping a t a (120 igpm), t he to ta l .d rawdown f o r a s p e c i f i c c a p a c i t y of

B - 3

Page 21: PROGRESS REPORT TEST-PRODUCTION DRILLING PROGRAM I' CONCERNING …a100.gov.bc.ca/appsdata/acat/documents/r7890/OK204_115713117… · W 1.0 SUMMARY AND CONCLUSIONS I. i b- The recent

b

i

\V//\.fl/

v - - - -

-.

- .-, 150 mn ( 6 " ) diameter well c a s i n g a p p r o x i m t e l y a t su r f ace .

''e/& e'//,

S t a t i c water level on June 14, 1991 = 0.165 m (0.54 f t ) .

U CONSTRUCTION DETAILS OF R.W. PORTER'S

KI'I'LEY L m TEST WELL NO. 1-1991 FIGURE 2

Notes:

1. The ske tch is no t t o s c a l e . 2. 3.

The sc reen is 150 mm (6") nominal d iameter Johnson s t a i n l e s s steel. A l l measurements a r e below t h e top o f t h e 150 mn diameter well cas ing .

Page 22: PROGRESS REPORT TEST-PRODUCTION DRILLING PROGRAM I' CONCERNING …a100.gov.bc.ca/appsdata/acat/documents/r7890/OK204_115713117… · W 1.0 SUMMARY AND CONCLUSIONS I. i b- The recent

SIEVE ANkeYSIS

i

i

100

90

80

fi 70 2 - a k 60 K

t- E 50 0

K W 40 n

2 30 W

c a

I 20

A 3

3 0

10

0

100

90

80

7 0

60

50

4 0

'30

Z20

10

0 - 20 4 0 - 80 110 120 140 1&0 180 200 220 240 260

SLOT OPENING AND GRAIN S I Z E - I N THOUSANDTHS OF AN INCH

12 I .066 I 1.68 1 381 I 73 I 373 I 48 I 325 I 58 047 1 7.19 1 442 1 371 I 66

100 ,006 0.15 200 ,003 0.08

T O T A L 524 780 564 200 1 ,003 I 0.08 I 1

T O T A L I I 1 524 I I 780 I I 564 I

B - 5

Page 23: PROGRESS REPORT TEST-PRODUCTION DRILLING PROGRAM I' CONCERNING …a100.gov.bc.ca/appsdata/acat/documents/r7890/OK204_115713117… · W 1.0 SUMMARY AND CONCLUSIONS I. i b- The recent

U S S/€Vf$ SIEVE OPENING CUMULATIVE % RETAINED REMARKS

ESTIMATED OVERSIZE 10 15 30 NO IINCHES I MM G I

3 I .265 [ 6.73 65 12 45 8 78 134

----- 1

50 60

100 200

TOTAL

B - 6

.012 0.30 ,010 0.25 ,006 0.15 .003 0.08

91 545 94 499 92 51 5 --_.__--

540 564 577

Page 24: PROGRESS REPORT TEST-PRODUCTION DRILLING PROGRAM I' CONCERNING …a100.gov.bc.ca/appsdata/acat/documents/r7890/OK204_115713117… · W 1.0 SUMMARY AND CONCLUSIONS I. i b- The recent

SIEVE A N M Y S I S

B - 7

Page 25: PROGRESS REPORT TEST-PRODUCTION DRILLING PROGRAM I' CONCERNING …a100.gov.bc.ca/appsdata/acat/documents/r7890/OK204_115713117… · W 1.0 SUMMARY AND CONCLUSIONS I. i b- The recent

APPENDIX C

PUMPING TEST DATA AND PLOTS

Page 26: PROGRESS REPORT TEST-PRODUCTION DRILLING PROGRAM I' CONCERNING …a100.gov.bc.ca/appsdata/acat/documents/r7890/OK204_115713117… · W 1.0 SUMMARY AND CONCLUSIONS I. i b- The recent

U PUMP TEST - DRAWDOWN DATA

ELAPSED DISTANCE PUMPING

RATE TIME TIME T O DRAWDOWN

( f t ) WATER HR. M I N . t (MIN. ) 0.54 ( i ~ p m )

1 16.21 15.67

2 17.21 16.67

3 17.92 17.36

4 18.04 17.50

5 16.27 17.73

6 16.46 17.92

7 16.54 18.00

18.11

9 16.61 16.2'7

70 16.675 16.335

15 19.40 16.66

20 19.54 19.00

25 19.79 19.25

30 20.04 19.50

35 20.29 79.75

40 20.46 19.92

45 20.56 20.04

50 20.73 20.19

55 20.90 20.36

60 21.04 20.50

70 21.25 20.71

80 21 .so 20.96

90 21.71 21.17

105 21.90 21.36

120 22.15 21.61

150 22.71 22.17

180 23.08 22.54

I -

--- I 6 18.65

-

------

c - 1

PAGE- 1 OF __ 3

REMARKS

S t a t i c l e v e l ; s t a r t .

-

-

CONTRACTOR Robbins Water Well D r i l l i n q Ltd .

PROJECT R.U. - K n E Y LAKE SUBDIVISION

O n Access Road ac ross waterlogged a rea i n Valley south of Location K i t l e y Lake

well Test Well No. 7-1991 pumping Rate (0) Constant a t 120 iqpm (9.1 L/sec)

Datum Point

Static Water Level

Top o f wel l ca s ing Elevation of Datum point

screen Location

Approximately a t ground s u r f a c e

0.54 f t (0.165 m) 21.75 t o 30.8 f t (6.63 t o 9.39 m)

Page 27: PROGRESS REPORT TEST-PRODUCTION DRILLING PROGRAM I' CONCERNING …a100.gov.bc.ca/appsdata/acat/documents/r7890/OK204_115713117… · W 1.0 SUMMARY AND CONCLUSIONS I. i b- The recent

U U PUMP TEST - DRAWDOWN DATA

&

3 P A G E 2 OF -

ELAPSED DISTANCE PUMPING REMARKS T I M E T O DRAWDOWN T IME

WATER ( f t ) RATE HR. M I N . t (MIN.)

( igpm) 21 0 23 58 23.04

240 23.875 23.335 120

270 24.375 23.835

300 24.625 24.085 Stop PunPo

-

-

_ _

c - 2

Page 28: PROGRESS REPORT TEST-PRODUCTION DRILLING PROGRAM I' CONCERNING …a100.gov.bc.ca/appsdata/acat/documents/r7890/OK204_115713117… · W 1.0 SUMMARY AND CONCLUSIONS I. i b- The recent

U JJMP TEST - RECOVERY D A T A

ELAPSED E LAPSED T IME SINCE T I M E SINCE

PUMPING PUMPING STARTED STOPPED

TIME

3 3 PAGE - OF ___

RATIO ( t l t ' )

Datum point

Static Water Level

Top o f well casing

0.54 f t (0.165 m)

24.625

3.83

24.085 stop pmp.

3.29 300

301 1 301

2.83

REMARKS RESIDUAL

DRAWDOWN TO

WATER (ft)

2.29 302 2 151

303 3 101

!

2.54

2.33

2.17

2.04

1 .875

1 .a1

c - 3

2.00

1.79 - 1.63-'

1 .SO

1.335

1.27

1.67

1.58

1.375

1.125

1 .oo

0.92

1 .I3

1.04

0.835

0.585

0.46

0.38

Page 29: PROGRESS REPORT TEST-PRODUCTION DRILLING PROGRAM I' CONCERNING …a100.gov.bc.ca/appsdata/acat/documents/r7890/OK204_115713117… · W 1.0 SUMMARY AND CONCLUSIONS I. i b- The recent

N 1.)

! , . t

I

1 . !

i I

. I -

i :.i

f 11 I

1 ! I i ' j

r : l., I

7 7

I

n . . 8 , . _ _

.... ....... I / #

I

. . . . . . _ . _ . ! . . . . - . . , . . . . . . . . . . . L ~ . -. .. - _ _ . . . . < . . . - . * . 1

... - , . . .

'I .

j . - . . . . . . . t 18 .. .- ....

. . i i o I $ k

20 j I . . . . .

I I ... ...

! . . - .......... 5 - /-

E . .

CI 15 , l-

4 I I

. .

. . . . . . I

. I .

I . , ! c . .

.. -. - . .-

. I ,

. . .

' I

. . , . :

. 4 . . I

...

. . . . . .

. . 1 . . ! . . I . I / i I

I i i !

-. ..... : e ' - ~ _ - . J . . . . . . . ... , . . . . . r-' -. . . . . . . . .

I I , .... .- . . . .

I

.-.-I ......

. . . . , . . .

i Time i n ,minut+ s ince . .

1 10

Page 30: PROGRESS REPORT TEST-PRODUCTION DRILLING PROGRAM I' CONCERNING …a100.gov.bc.ca/appsdata/acat/documents/r7890/OK204_115713117… · W 1.0 SUMMARY AND CONCLUSIONS I. i b- The recent
Page 31: PROGRESS REPORT TEST-PRODUCTION DRILLING PROGRAM I' CONCERNING …a100.gov.bc.ca/appsdata/acat/documents/r7890/OK204_115713117… · W 1.0 SUMMARY AND CONCLUSIONS I. i b- The recent

APPENDIX D

GROUNDWATER QUALITY

Page 32: PROGRESS REPORT TEST-PRODUCTION DRILLING PROGRAM I' CONCERNING …a100.gov.bc.ca/appsdata/acat/documents/r7890/OK204_115713117… · W 1.0 SUMMARY AND CONCLUSIONS I. i b- The recent

Date: Jun. 07, 1991

I t

I I ASL P i l e No. 6433B

Report On: Water Analysis

R e p o r t To: Pacific Hydrology Consultants #204 - 1929 W. Broadway Vancouver, BC V 6 J 123

Attention: Ms. Anne Badry

Date Received: May. 29, 1991 I-.-

METHODOLOGY

Conventional Parameters

These analyses are carried out in accordance with procedures described in "Standard Methods for the Examination of Water and Wastewater" 17th Ed. published by the American Public Health Association, 1989. Further details are available on request.

Metals

These analyses were carried out in accordance with procedures described in "Standard Methods for the Examination of Water and Wastewater" 17th Edition published by the American Public Health Association, 1989. The procedures involve a variety of instrumental analyses involving inductively coupled plasma (ICP) and atomic absorption spectrophotometry (AA) to obtain the . required detection limit for each element. Specific details are available on request.

analytical service laboratories Itd. 1988 Triumph Street, Vancouver, B.C. V5L 1K5 Fax (604) 253-6700 Telephone (604) 253-4188

Page 33: PROGRESS REPORT TEST-PRODUCTION DRILLING PROGRAM I' CONCERNING …a100.gov.bc.ca/appsdata/acat/documents/r7890/OK204_115713117… · W 1.0 SUMMARY AND CONCLUSIONS I. i b- The recent

REMARKS

ASL Pile No. 64338 Page 2

Remarks

The water as represented by the sample Porter Water can be characterized as moderately high with respect to dissolved mineralization. The water sample met Canadian and British Columbia drinking water guidelines for all parameters analysed.

ASL ANALYTICAL SERVICE LABORATORIES LTD.

i

I . . f + . .

Eda Parreno B.Sc. Project Chemist

Page 34: PROGRESS REPORT TEST-PRODUCTION DRILLING PROGRAM I' CONCERNING …a100.gov.bc.ca/appsdata/acat/documents/r7890/OK204_115713117… · W 1.0 SUMMARY AND CONCLUSIONS I. i b- The recent

b'

w RESULTS OF ANALYSIS - Water

Paranmter

ASL Pile No. 6 4 3 3 B Page 3

Porter Drinking *I Water Water Sample Guidelines

Phy6iCal T e s t s Colour cu Conductivity umhos/cm Total Dissolved Solids Hardness CaC03 PH Total Suspended Solids Turbidity NTU

D i e s o l v e d Anions Alkalinity CaC03 Chloride c1 Fluoride F Silicate s io2 Sulphate SO4

Hut rient e Nitrite/Nitrate Nitrogen

Total Metale Arsenic Barium Cadmium Ca 1 c ium Chromium Copper iron

Lead Magnesium Manganese Potassium Sodium Zinc

T-As T-Ba

T-Ca T-Cr

T-Fe

T-Cd

T-CU

T-Pb T-Mg T-Mn

T-Na T-2n

T-K

< 5 . 0 15. ( A ) 443 - 389 500. ( A ) 213 - '2 (A) 7.93 6.5-8.5 (A) 5 - 0.73 5. (A)

236 - 3.3 250. ( A ) 0.81 1.5 (H&A) 17.8 - 19.6 500. (H&A)

N 0.054 10.0 (H)

0.0007 0.05 (H) 0.021 1.0 (H) <0.0002 0.005 (H) 60.3 - C0.015 0.05 (H) <0.010 1.0 (H) 0.078 0.30 (A)

<o. 001 0.01 (H) 14.9 - <O. 005 0.05 (A) 0.40 - 19.4 - <O. 005 5.0 ( A )

< = Less than A = Aesthetic reasons H = Health Considerations Results expressed a8 milligrams per litre except f o r pH, Conductivity (pmhoe/cm), Colour (CU), Turbidity (NTU) and Coliform Bacteria (colonies/100 ml) *1

* 2

*3

"Maximum acceptable concentration" as published by Health C

Maximum level not established - water suppliea with a hardness exceeding 200 mg/L are considered poor but will be tolerated. Maximum level not established - of concern to consumers with sodium restricted diet. Levels exceeding 20 mg/L may be of concern in this circumstance.

Welfare Canada,. 1989