progress report on the test facility project, design and construction
DESCRIPTION
Progress report on the test facility project, design and construction. L. Serio on behalf of bldg. 180 test facility project team members (TE and EN departments). O utline. Introduction Project Plan Scope of work and implementation strategy Organization Action plan and schedule - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: Progress report on the test facility project, design and construction](https://reader035.vdocuments.mx/reader035/viewer/2022062410/56815769550346895dc50ebf/html5/thumbnails/1.jpg)
![Page 2: Progress report on the test facility project, design and construction](https://reader035.vdocuments.mx/reader035/viewer/2022062410/56815769550346895dc50ebf/html5/thumbnails/2.jpg)
Progress report on the test facility project, design and construction
L. Serio on behalf of bldg. 180 test facility project team members(TE and EN departments)
![Page 3: Progress report on the test facility project, design and construction](https://reader035.vdocuments.mx/reader035/viewer/2022062410/56815769550346895dc50ebf/html5/thumbnails/3.jpg)
L. Serio 3
Outline• Introduction• Project Plan
– Scope of work and implementation strategy– Organization– Action plan and schedule– Resources and cost– Financing
• Progress report– Test program and acceptance tests– Test benches scenarios– Design and construction activities
• ConclusionsCERN – GSI c.tte meeting 20140625
![Page 4: Progress report on the test facility project, design and construction](https://reader035.vdocuments.mx/reader035/viewer/2022062410/56815769550346895dc50ebf/html5/thumbnails/4.jpg)
Introduction
According to the last collaboration meeting we have proceeded with the review and optimisation of the test program and the internal / external interfaces in order to fix the requirements and develop a detailed project plan and resource loaded schedule.
Several meetings have taken place between CERN and FAIR personnel leading to the requirements, plans, resources and preliminary design reported hereafter.
Design and construction activities have started.
CERN – GSI c.tte meeting 20140625 L. Serio 4
![Page 5: Progress report on the test facility project, design and construction](https://reader035.vdocuments.mx/reader035/viewer/2022062410/56815769550346895dc50ebf/html5/thumbnails/5.jpg)
Outline• Introduction• Project Plan
– Scope of work and implementation strategy– Organization– Action plan and schedule– Resources and cost– Financing
• Progress report– Test program and acceptance tests– Test benches scenarios– Design and construction activities
• ConclusionsCERN – GSI c.tte meeting 20140625 L. Serio 5
![Page 6: Progress report on the test facility project, design and construction](https://reader035.vdocuments.mx/reader035/viewer/2022062410/56815769550346895dc50ebf/html5/thumbnails/6.jpg)
Implementation status• Scope of work – done; review of scope/financing required
• Fix the preliminary requirements with FAIR• Review the existing implementation constraints• Establish a preliminary test program and WBS
• Schedule- done; review required• Establish the test phases, sequence and overall testing rate• Establish the overall schedule and action plan
• Cost- done; review of scope/financing required• Establish the PBS and corresponding material and personnel budget
• Issue the Project Plan- done
• Implement the Project Plan – started; review of scope/financing required
CERN – GSI c.tte meeting 20140625 L. Serio 6
![Page 7: Progress report on the test facility project, design and construction](https://reader035.vdocuments.mx/reader035/viewer/2022062410/56815769550346895dc50ebf/html5/thumbnails/7.jpg)
Project Plan: Scope of Work 1/2• Addendum n.2 to the 2010 Agreement K1727/DG between CERN
and GSI
• Testing of 3 prototypes and 52 series magnets: MULTIPLETS:
SHORT: 1 prototype and 7 series magnets LONG: 1 prototype and 22 series are magnets
DIPOLES: 1 prototype and 23 series magnets Schedule:
‒ prototypes 1.2016 – 6.2016‒ series testing 7.2016 – 1.2019
• Refurbishing and upgrade of the existing cryogenic test facility located in the test hall n. 180 at CERN - Meyrin
CERN – GSI c.tte meeting 20140625 L. Serio 7
![Page 8: Progress report on the test facility project, design and construction](https://reader035.vdocuments.mx/reader035/viewer/2022062410/56815769550346895dc50ebf/html5/thumbnails/8.jpg)
Project Plan: Scope of Work 2/2• Design a facility adequate for the testing of SFRS magnets
• Make extensive use of the existing CERN infrastructure– Refurbish the available equipment, within the existing limitations and space constraints
• Testing according to the magnet production schedule and optimised test program
• Design the facility according to the following magnets test phases:– Acceptance, preparation, installation and connection– Check electrical integrity of the magnet and its instrumentation at warm– Cool-down– Cold powering, magnetic field and heat-load measurements– Warm-up– Check electrical integrity of the magnet and its instrumentation at warm– De-mounting of magnet from test-bench– Storage of raw data, data analysis and report on magnet performance
CERN – GSI c.tte meeting 20140625 L. Serio 8
![Page 9: Progress report on the test facility project, design and construction](https://reader035.vdocuments.mx/reader035/viewer/2022062410/56815769550346895dc50ebf/html5/thumbnails/9.jpg)
Implementation strategy: WBSFAIR MAGNETS TEST FACILITY
1 PROJECT MANAGEMENT
2 CRYOGENIC SYSTEM
2.1 CRYOPLANT
2.2 CRYODISTRIBUTION
2.3 CONTROLS AND ELECTRICAL
3 MAGNETS TEST STAND
4 POWERING SYSTEM
5 ENERGY EXTRACTION SYSTEM
6 QUENCH PROTECTION SYSTEM
7 UTILITIES
7.1 CIVIL ENGINEERING
7.2 CONTROLS AND NETWORK
7.3 COOLING WATER AND VENTILATION
7.4 ELECTRICAL POWERING AND DISTRIBUTION
7.5 SURVEY SYSTEM
7.6 TRANSPORT AND HANDLING
CERN – GSI c.tte meeting 20140625 L. Serio 9
![Page 10: Progress report on the test facility project, design and construction](https://reader035.vdocuments.mx/reader035/viewer/2022062410/56815769550346895dc50ebf/html5/thumbnails/10.jpg)
Organization Chart
Nota: The construction of this facility has been grouped together with the upgrade of the SM18 test facility in a new project with Volker Mertens as Project Leader
CERN – GSI c.tte meeting 20140625 L. Serio 10
CERN – GSICollaboration Committee
F. Bordry, M. JimenezO. Kester, E. Fischer
CERNTechnical Coordinator
Luigi Serio
FAIR Technical Coordinator
Pierre Schnizer
Magnetic Measurements
Stephan Russenschuck
Test FacilityMarta Bajko
Electrical Power Rene Necca
Power ConvertersHugues Thiesen
CryogenicsAntonio Perin
Quench ProtectionReiner Denz
Cooling and Ventilation
Michele Battistin
SurveyDominique Missiaen
Cryogenic Testing at CERN of SUPER -FRS Magnets for FAIROrganization Chart
EN Dept.
TE Dept.
HSEAndre Henriques
FAIR Mirror Organization
ICEPhilippe Gayet
IntegrationY Muttoni
Energy ExtractionKnud Dahlerup-
Petersen
Handling and transport
Ingo Ruehl
Platforms and structures
M Willhelmson
Project Mgt. support
David Hay
![Page 11: Progress report on the test facility project, design and construction](https://reader035.vdocuments.mx/reader035/viewer/2022062410/56815769550346895dc50ebf/html5/thumbnails/11.jpg)
Baseline test sequencing installation & preparationcooling4 K testswarm upwarm tests and disconnect
closureshutdowninstallation & preparation 1 1 1 1 1 1 1cooling4 K tests . . . . . . .warm upwarm tests and disconnect 1 1 1 1 1 1 1 1 1
closureshutdowninstallation & preparation 1 1 1 1 1 1 1 1cooling4 K tests 3 3 3 3 3 3 . . . . . . . . . . . . . . 3 3warm upwarm tests and disconnect 1 1 1 1 1 1 1 1number of benches 0 0 0 1 1 2 2 3 3 4 4 5 4 5 4 5 4 5 4 . . . . . . . . . . . . . 5 4 4 4 3 2 2 1 1 0 0 0cooling power 4 K 0 0 0 0 0 4 2 6 4 6 4 6 4 6 4 6 4 . . . . . . . . . . . . . . . . 4 6 4 2 2 0 0 0 0 0 0cooling power 300 - 80 K 0 0 0 0 1 1 1 1 1 2 2 2 2 2 2 2 2 . . . . . . . . . . . . . . . . 2 2 1 1 1 1 1 0 0 0 0power supply 0 0 0 0 0 0 1 1 2 1 2 1 2 1 2 1 2 1 2 . . . . . . . . . . . . . . 2 1 2 1 1 0 0 0 0 0 0
available cooling 4 Kavailable cooling 300-80 Kavailable power supply 1
2 2 2 2 2
6 g/s2*10 kW
22 2
21
1015
14
number of magnets tested
number of magnets tested
2 2 2 2 2
2
23
2 2 23 3
52 weeks46 weeks (44 weeks cold)
3 3
2 2 2
2 22
3
23 3
3
52 weeks46 weeks (44 weeks cold)
10
53 days (44 working days - cryo also during non working days)
4
5
2 2
2 2 2 2 23 3 3
CERN – GSI c.tte meeting 20140625 L. Serio 11
![Page 12: Progress report on the test facility project, design and construction](https://reader035.vdocuments.mx/reader035/viewer/2022062410/56815769550346895dc50ebf/html5/thumbnails/12.jpg)
Baseline Action Plan and ScheduleCONSTRUCTION andOPERATIONSchedule
J F MA MJ J A S O N D J F MA MJ J A S O N D J F MA MJ J A S O N D J F MA MJ J A S O N D J F MA MJ J A S O N D J F MA MJ J A S O N DConceptual DesignPreliminary DesignFinal DesignProcurementManufacturingInstallationCommissioningMultiplet prototypeDipole prototypeSeries Magnets TestingPANDA testing
20192014 2015 2016 2017 2018
* If approved by CERN management
DIPOLES: 1 prototype, 23 series magnets, 2 spares cryostatMULTIPLETS: 2 prototypes (L and S), 22 (L) and 7 (S) series, 2 spares (L and S) 3 prototypes, 52 series magnets in total (plus 2 spares)
7.2016 7.2017 7.2018 7.2019 #24 24 4
15 days cold tests 14 14 14 10 52 3.75 years13 days cold tests 17 17 17 1 52 3 years
*
CERN – GSI c.tte meeting 20140625 L. Serio 12
![Page 13: Progress report on the test facility project, design and construction](https://reader035.vdocuments.mx/reader035/viewer/2022062410/56815769550346895dc50ebf/html5/thumbnails/13.jpg)
M+P estimate
CERN – GSI c.tte meeting 20140625 L. Serio 13
2013 2014 2015 2016 2017 2018 2019
BUDGET kCHF 348 1,011 8,238 1,070 1,120 1,120 1,120
0.1 5.9 7.3 3.1 3.1 3.1 3.1
0.0 2.3 7.6 3.5 3.5 3.5 3.5 9.9
2016-2019
4,430
12.2
13.8
2013-2015
9,596
13.3TOTAL
Cat 3+4 FTE-y
CONSTRUCTION OPERATION
Cat 2 FTE-y
TOT.CONSTRUCTION TOT.OPERATION
![Page 14: Progress report on the test facility project, design and construction](https://reader035.vdocuments.mx/reader035/viewer/2022062410/56815769550346895dc50ebf/html5/thumbnails/14.jpg)
Financing(Construction)
CERN – GSI c.tte meeting 20140625 L. Serio 14
CHF 6,000,000FAIR accepted extra contr CHF 1,200,000 pre-cooler
CHF 410,000 survey and EECHF 4,179,000
CHF 11,789,000CHF 12,171,771
CHF 959,577-CHF 1,342,348-CHF 2,952,348
Total FUNDINGBudget total M+P
Missing budgetMissing agreed budget FAIR
GSI contribution
FAIR extra activitiesFunding CERN
Contingency
![Page 15: Progress report on the test facility project, design and construction](https://reader035.vdocuments.mx/reader035/viewer/2022062410/56815769550346895dc50ebf/html5/thumbnails/15.jpg)
Options according to financing availabilities
CERN – GSI c.tte meeting 20140625 L. Serio 15
9596960800
177760004179
13132 10179 -2953
7090709800
158060004179
10179 10179 0
GSI contributionCERN contribution
ContingencyMaterial
staff (16 FTE-y but 1/3 for constr)non staff (15.8 FTE-y)
Costing 2 test benches & 1 precooler - Construction
Costing 3 test benches & 2 precooler - ConstructionMaterial
staff (16 FTE-y but 1/3 for constr)non staff (17.8 FTE-y)GSI contributionCERN contribution
Contingency
![Page 16: Progress report on the test facility project, design and construction](https://reader035.vdocuments.mx/reader035/viewer/2022062410/56815769550346895dc50ebf/html5/thumbnails/16.jpg)
2 versus 3 test facilities• Presently agreed budget allows only for two TBs• Implications of 2 versus 3 test benches analyzed• Main WPs affected:
– Cryo, Platforms&Supports, Test Stand
CERN – GSI c.tte meeting 20140625 L. Serio 16
cost breakdown 3rd bench (option)kCHF1200
EE and survey 410200200100100290200253
1343
resourcescontingencyTOTAL
utilities
precooler
cryolinessatellite valve boxesone test benchelectrical, instrumentation & control
![Page 17: Progress report on the test facility project, design and construction](https://reader035.vdocuments.mx/reader035/viewer/2022062410/56815769550346895dc50ebf/html5/thumbnails/17.jpg)
Project PlanTable of Contents https://edms.cern.ch/document/1370663/2
status
a. Note
b. Scope of Work
c. Project Requirements
d. Organization Chart
e. PBS
f. WBS
g. RASCI
h. Schedule and Action Plan
i. Summary M+P
j. Graphs
k. Resources Operation
l. Resources Construction
m. Risk Matrix
n. Financing
o. Documentation Management
p. Annexes
Individual groups resource estimates and WBS/PBS
CERN – GSI c.tte meeting 20140625 L. Serio 17
![Page 18: Progress report on the test facility project, design and construction](https://reader035.vdocuments.mx/reader035/viewer/2022062410/56815769550346895dc50ebf/html5/thumbnails/18.jpg)
Outline• Introduction• Project Plan
– Scope of work and implementation strategy– Organization– Action plan and schedule– Resources and cost– Financing
• Progress report– Test program and acceptance tests– Test benches scenarios– Design and construction activities
• ConclusionsCERN – GSI c.tte meeting 20140625 L. Serio 18
![Page 19: Progress report on the test facility project, design and construction](https://reader035.vdocuments.mx/reader035/viewer/2022062410/56815769550346895dc50ebf/html5/thumbnails/19.jpg)
Reviewed test program and time
CERN – GSI c.tte meeting 20140625 L. Serio 19
Reception at CERN 0.75 days 0.75 daysUnloading 1 day 1 dayReception test 1.25 days 1.25 daysInstallation from temporary storage to Test Bench 1.75 days 1.5 daysConnection to the test bench 3 days 2.5 daysTest at Room Temperature 2.38 days 2 days in //DAQ system preparation 2 days 2 days in //Leak test 1.5 days 1.5 days in //Purging 2 days 2 days in //Cooling 300 - 80 K 12 days 8 days 8Cooling 80 - 4 K 2 days 1 days 1Filling Lhe 2 days 1 days 1Leak test if cooling indicates a problem 2 days not considered 0Preparation Work at 4 K 2 days 2 days inDAQ system at 4 K 2 days 2 days in //Protection system set up 1 day 1 day inPowering the magnet at 4 K 3.25 days 3 days 1.5Magnetic measurements at 4 K 11 days 10 days 10
Stationary loss measurements 3 days3 days overnight for static losses and no AC losses
0
Warm up 12 days 10 days 10Test at Room Temperature 1.88 days 1.88 days 2Disconnection from test bench 2 days 2 days Electrical disconnection 1 day 1 day Hydraulic disconnection 1 day 1 dayInstallation from test bench to temporary storage 1.25 days 1.25 daysLoading 4 hrs 4 hrs
67 41
rece
ption
ar
ea
3 3
occu
patio
n of
the
test
ben
ches
67
4
1.5
2
rece
ption
are
a
1.5 1.5
![Page 20: Progress report on the test facility project, design and construction](https://reader035.vdocuments.mx/reader035/viewer/2022062410/56815769550346895dc50ebf/html5/thumbnails/20.jpg)
Reviewed overall duration(3 test benches and 2 precoolers)
installation & preparationcooling4 K testswarm upwarm tests and disconnect
installation & preparationcooling4 K testswarm upwarm tests and disconnect
1013
446 days (41 working days - cryo also during non working days)
410
number of magnets tested per year
or 1.35 magnets per month16with 3 test benches and 13 days cold magnetic
CERN – GSI c.tte meeting 20140625 L. Serio 20
![Page 21: Progress report on the test facility project, design and construction](https://reader035.vdocuments.mx/reader035/viewer/2022062410/56815769550346895dc50ebf/html5/thumbnails/21.jpg)
Optimal overall duration(3 test benches and 2 precoolers)
installation & preparationcooling4 K testswarm upwarm tests and disconnect
closureshutdown 2 2 number of magnets tested per yearinstallation & preparation 1 1 1 1 1 1 1 1 1cooling or 2 magnets per month testing rate4 K tests . . . . . . . . . . . . .warm upwarm tests and disconnect 1 1 1 1 1 1 1 1number of benches 0 0 0 1 1 2 2 3 3 3 3 3 3 3 3 3 3 3 3 . . . . . . . . . . . . . 3 3 3 3 3 2 2 1 1 0 0 0cooling power 4 K 0 0 0 2 2 4 4 4 4 4 4 4 4 4 4 4 4 . . . . . . . . . . . . . . . . 4 4 4 4 4 2 2 0 0 0 0cooling power 300 - 80 K 0 0 1 1 1 1 2 2 2 2 2 2 2 2 2 2 2 . . . . . . . . . . . . . . . . 2 2 2 2 2 1 1 1 1 0 0power supply 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 . . . . . . . . . . . . . . 1 1 1 1 1 0 0 0 0 0 0
available cooling 4 Kavailable cooling 300-80 Kavailable power supply
42 days (37 working days - cryo also during non working days)4
22 2 2 2 2
21
52 weeks46 weeks (42 weeks cold)
2 2
with 3 test benches and 2 weeks cold magnetic measurements
1010
103
2 2 2 2 2 222 22 22 2 2 2 2 2
2
6 g/s2*10 kW
1
CERN – GSI c.tte meeting 20140625 L. Serio 21
![Page 22: Progress report on the test facility project, design and construction](https://reader035.vdocuments.mx/reader035/viewer/2022062410/56815769550346895dc50ebf/html5/thumbnails/22.jpg)
Series tests duration comparison
CERN – GSI c.tte meeting 20140625 L. Serio 22
Test duration15 days cold tests - 3TB2PC optimised13 days cold tests - 3TB2PC no margin10 days cold tests - 3TB2PC unfeasible 5 days cold tests - 2TB2PC no MM13 days cold tests - 2TB2PC no margin13 days cold tests - 2TB1PC no redund
year 1 year 2 year 3 year 4 year 5 year 6 note
![Page 23: Progress report on the test facility project, design and construction](https://reader035.vdocuments.mx/reader035/viewer/2022062410/56815769550346895dc50ebf/html5/thumbnails/23.jpg)
Schedule updateUPDATE Planning 6.2014
3 test benches, 2 CWUs12 days cold testing J F MA MJ J A S O N D J F MA MJ J A S O N D J F MA MJ J A S O N D J F MA MJ J A S O N D J F MA MJ J A S O N D J F MA MJ J A S O N D J F MA MJ J A S O N DConceptual DesignPreliminary DesignFinal DesignProcurementManufacturingInstallationCommissioningProto magnets testingSeries Magnets TestingShort Multiplets Proto . . . . .Long Multiplet Proto . . . . .Dipole Proto . . . . .First Series Short MultipletFirst Series Long MultipletFirst Series DipoleFirst Energy Buncher ?Last Energy Buncher ?PANDA testing ?
3 test benches, 2 precooler, 13 days cold testingmagnet testing rate1.35 magnets modules/month
0.8 multiplets/months0.55 dipoles/month
2019 20202014 2015 2016 2017 2018
Fix layout interfaces
LLI launch procur. commissioning
CERN – GSI c.tte meeting 20140625 L. Serio 23
LS2
![Page 24: Progress report on the test facility project, design and construction](https://reader035.vdocuments.mx/reader035/viewer/2022062410/56815769550346895dc50ebf/html5/thumbnails/24.jpg)
Alternative scenarios (2TB-2PC with a later upgrade to 3TB-2PC)
2/3 test benches, 2 CWUs12 days cold testing J F MA MJ J A S O N D J F MA MJ J A S O N D J F MA MJ J A S O N D J F MA MJ J A S O N D J F MA MJ J A S O N D J F MA MJ J A S O N D J F MA MJ J A S O N D J F A J J A S O N DConceptual DesignPreliminary DesignFinal DesignProcurementManufacturingInstallationCommissioningUPGRADEProto magnets testingSeries Magnets TestingShort Multiplets Proto . . .Long Multiplet Proto . . . .Dipole Proto . . . . .First Series Short MultipletFirst Series Long MultipletFirst Series DipoleFirst Energy BuncherLast Energy BuncherPANDA testing ?
3 test benches, 2 precooler, 13 days cold testingmagnet testing rate1.35 magnets modules/month
0.8 multiplets/months0.55 dipoles/month
2014 2015 2016 2017 2018 2019 2020 2021
Nota: a. Delayed decision / financingb. Increased overall costc. Reduced testing capabilities and time for prototypes
CERN – GSI c.tte meeting 20140625 L. Serio 24
![Page 25: Progress report on the test facility project, design and construction](https://reader035.vdocuments.mx/reader035/viewer/2022062410/56815769550346895dc50ebf/html5/thumbnails/25.jpg)
Outline• Introduction• Project Plan
– Scope of work and implementation strategy– Organization– Action plan and schedule– Resources and cost– Financing
• Progress report– Test program and acceptance tests– Test benches scenarios– Design and construction activities
• ConclusionsCERN – GSI c.tte meeting 20140625 L. Serio 25
![Page 26: Progress report on the test facility project, design and construction](https://reader035.vdocuments.mx/reader035/viewer/2022062410/56815769550346895dc50ebf/html5/thumbnails/26.jpg)
WP: all
DONE• Overall scope, WBS, resources, budget and schedule
reviewed and agreed
IN WORK• Detailed PBS, WBS and resource loaded schedule• RASCI
DELAYED• Interface documents (ext and int) – September 2014• EVM based project reporting – October 2014CERN – GSI c.tte meeting 20140625 L. Serio 26
![Page 27: Progress report on the test facility project, design and construction](https://reader035.vdocuments.mx/reader035/viewer/2022062410/56815769550346895dc50ebf/html5/thumbnails/27.jpg)
WP: CryogenicsDONE• CERN-GSI agreed design and main specifications parameters for the cryogenic
components (pre-cooler) - https://edms.cern.ch/document/1355497/1• Preparation of bldg 279 and galleries sites (cleaning)• Updated naming, database, PFDs, P&IDs, controls specifications of the helium
refrigerators
IN WORK• Writing of the pre-cooler technical specification• Review and approval of final PFDs and P&IDs
DELAYED• Finalised interface documents (requirements) – September 2014• Market survey LLI– October 2014• Procurement documents – December 2014
CERN – GSI c.tte meeting 20140625 L. Serio 27
![Page 28: Progress report on the test facility project, design and construction](https://reader035.vdocuments.mx/reader035/viewer/2022062410/56815769550346895dc50ebf/html5/thumbnails/28.jpg)
WP: Magnetic MeasurementsDONE• Magnet tests database definition• Review of magnet test program, time and tools requirements
IN WORK• Development on the fluxmeter and rotating coils (challenging precision
measurements, high cost of industrially available instruments)• Measurement strategy within the boundary constrains being reviewed
in order to streamline tests, analysis, time
DELAYED• Review of finalised magnet database and required test data –
September 2014 in order to launch the required development and procurements
CERN – GSI c.tte meeting 20140625 L. Serio 28
![Page 29: Progress report on the test facility project, design and construction](https://reader035.vdocuments.mx/reader035/viewer/2022062410/56815769550346895dc50ebf/html5/thumbnails/29.jpg)
WP: TF and ICE
DONE• Facility test program and optimised activities
duration in collaboration with FAIR
IN WORK• Specifications for DAQ and signals exchange
being prepared
CERN – GSI c.tte meeting 20140625 L. Serio 29
![Page 30: Progress report on the test facility project, design and construction](https://reader035.vdocuments.mx/reader035/viewer/2022062410/56815769550346895dc50ebf/html5/thumbnails/30.jpg)
WP: Power Converters
DONE• Procurement of Power Converters launched
(PCs expected at CERN mid-2015)
IN WORK• Definition of detailed requirements and
interface specifications (in particular Energy Extraction system)
CERN – GSI c.tte meeting 20140625 L. Serio 30
![Page 31: Progress report on the test facility project, design and construction](https://reader035.vdocuments.mx/reader035/viewer/2022062410/56815769550346895dc50ebf/html5/thumbnails/31.jpg)
WP: Cooling and VentilationDONE• Conceptual Design and preliminary interface data
IN WORK• Layout and implementation• Measurement strategy within the boundary constrains being
reviewed in order to streamline tests, analysis, time
DELAYED• Finalised interface documents (requirements) – September 2014• Market survey LLI– October 2014• Procurement documents – December 2014
CERN – GSI c.tte meeting 20140625 L. Serio 31
![Page 32: Progress report on the test facility project, design and construction](https://reader035.vdocuments.mx/reader035/viewer/2022062410/56815769550346895dc50ebf/html5/thumbnails/32.jpg)
WP: Cooling and VentilationDONE• Conceptual Design and preliminary interface data
IN WORK• Equipment layout and general integration
DELAYED• Finalised interface documents (requirements) – September
2014• Market survey LLI– October 2014• Procurement documents – December 2014CERN – GSI c.tte meeting 20140625 L. Serio 32
![Page 33: Progress report on the test facility project, design and construction](https://reader035.vdocuments.mx/reader035/viewer/2022062410/56815769550346895dc50ebf/html5/thumbnails/33.jpg)
WP: Platforms and Structure
DONE• General layout and concept• Interfaces with magnets
IN WORK• Freezing of magnets interfaces• Detailed design and cost optimisation
CERN – GSI c.tte meeting 20140625 L. Serio 33
![Page 34: Progress report on the test facility project, design and construction](https://reader035.vdocuments.mx/reader035/viewer/2022062410/56815769550346895dc50ebf/html5/thumbnails/34.jpg)
Platform review and optimization
CERN – GSI c.tte meeting 20140625 L. Serio 34
![Page 35: Progress report on the test facility project, design and construction](https://reader035.vdocuments.mx/reader035/viewer/2022062410/56815769550346895dc50ebf/html5/thumbnails/35.jpg)
WP: Integration
DONE• General layout and concept• PANDA space sharing agreement
IN WORK• Review and freezing of individual system
routings and layout
CERN – GSI c.tte meeting 20140625 L. Serio 35
![Page 36: Progress report on the test facility project, design and construction](https://reader035.vdocuments.mx/reader035/viewer/2022062410/56815769550346895dc50ebf/html5/thumbnails/36.jpg)
FAIR and PANDA layoutPanda assembly and testing area
CERN – GSI c.tte meeting 20140625 L. Serio 36
![Page 37: Progress report on the test facility project, design and construction](https://reader035.vdocuments.mx/reader035/viewer/2022062410/56815769550346895dc50ebf/html5/thumbnails/37.jpg)
WP: Handling and Transport
DONE• Modifications for coupling of two existing
cranes
IN WORK• Industrial survey for the procurement of
interface lifting spreader (coupling) and dedicated magnets lifting spreaders (to be decided if procured directly by FAIR or via CERN)
CERN – GSI c.tte meeting 20140625 L. Serio 37
![Page 38: Progress report on the test facility project, design and construction](https://reader035.vdocuments.mx/reader035/viewer/2022062410/56815769550346895dc50ebf/html5/thumbnails/38.jpg)
Outline• Introduction• Project Plan
– Scope of work and implementation strategy– Organization– Action plan and schedule– Resources and cost– Financing
• Progress report– Test program and acceptance tests– Test benches scenarios– Design and construction activities
• ConclusionsCERN – GSI c.tte meeting 20140625 L. Serio 38
![Page 39: Progress report on the test facility project, design and construction](https://reader035.vdocuments.mx/reader035/viewer/2022062410/56815769550346895dc50ebf/html5/thumbnails/39.jpg)
Conclusions 1/2• Conceptual design, project plan, financing and
resources (limited to two test benches) agreed upon • Financing issues (choice of 2 or 3 test benches) and
possible staging option analysed• Test program optimised and finalised• Launch Safety Agreement prepared and issued
– GSI to review and accept safety requirements• Cryogenic layout and precooler requirements agreed
to proceed with Specification and Tendering phase• PANDA issues solved but no synergy implemented yet
CERN – GSI c.tte meeting 20140625 L. Serio 39
![Page 40: Progress report on the test facility project, design and construction](https://reader035.vdocuments.mx/reader035/viewer/2022062410/56815769550346895dc50ebf/html5/thumbnails/40.jpg)
Conclusions 2/2
• September 2014 freezing of interface requirements (internal &external) to launch final design phase and procurement
• Formal agreement (technical reached) on cryogenic layout and components (with financing for second pre-cooler) required asap in order not to delay the project (LLI)
CERN – GSI c.tte meeting 20140625 L. Serio 40
![Page 41: Progress report on the test facility project, design and construction](https://reader035.vdocuments.mx/reader035/viewer/2022062410/56815769550346895dc50ebf/html5/thumbnails/41.jpg)
References
• Project Plan (contains all up to date information): – EDMS: https://
edms.cern.ch/document/1370663/3
• Technical coordination meetings and reviewed interface parameters:– EDMS:
https://edms.cern.ch/nav/P:FAIR-000001263:V0/P:FAIR-000002500:V0/TAB3
CERN – GSI c.tte meeting 20140625 L. Serio 41