Progress report June 2017
![Page 2: Progress report June 2017 - hazelproject.inhazelproject.in/wp-content/themes/twentyfourteen/images/blocks/... · • Meter panel inspection completed for D & E Block , delivery of](https://reader033.vdocuments.mx/reader033/viewer/2022052101/603ab81e3f5d0114bd2257eb/html5/thumbnails/2.jpg)
BLOCK – E
![Page 3: Progress report June 2017 - hazelproject.inhazelproject.in/wp-content/themes/twentyfourteen/images/blocks/... · • Meter panel inspection completed for D & E Block , delivery of](https://reader033.vdocuments.mx/reader033/viewer/2022052101/603ab81e3f5d0114bd2257eb/html5/thumbnails/3.jpg)
BLOCK – E UPDATES• External Block work completed till 14th Floor
• Internal Block work in 11th, 12th,13th & 14th floor work is in progress.
• Lintel work in progress for 10th Floor.
• Door Frame installation work in progress.
• Plumbing work in progress.
• Internal plastering work completed till 3rd Floor.
• 4th Floor Plastering work is in progress.
• Electrical conducting work in progress.
• Ceiling plastering and Bathroom Rough Plastering work is in
progress at 7th Floor.
• Block work for Electrical panel room in stilt floor completed and
plastering work is in progress.
• Meter panel inspection completed for D & E Block , delivery of the
panels are expected shortly.
![Page 4: Progress report June 2017 - hazelproject.inhazelproject.in/wp-content/themes/twentyfourteen/images/blocks/... · • Meter panel inspection completed for D & E Block , delivery of](https://reader033.vdocuments.mx/reader033/viewer/2022052101/603ab81e3f5d0114bd2257eb/html5/thumbnails/4.jpg)
BLOCK – E UPDATES
Lintel works is in progress
![Page 5: Progress report June 2017 - hazelproject.inhazelproject.in/wp-content/themes/twentyfourteen/images/blocks/... · • Meter panel inspection completed for D & E Block , delivery of](https://reader033.vdocuments.mx/reader033/viewer/2022052101/603ab81e3f5d0114bd2257eb/html5/thumbnails/5.jpg)
BLOCK – E UPDATES
Internal Block works is in progress
![Page 6: Progress report June 2017 - hazelproject.inhazelproject.in/wp-content/themes/twentyfourteen/images/blocks/... · • Meter panel inspection completed for D & E Block , delivery of](https://reader033.vdocuments.mx/reader033/viewer/2022052101/603ab81e3f5d0114bd2257eb/html5/thumbnails/6.jpg)
BLOCK – E UPDATES
Bathroom rough plastering & Electrical room plastering work is in progress