professional forum...2009/06/16 · 16 june 2009 10 design principles for scl cross harbour section...
TRANSCRIPT
16 June 2009
Shatin to Central Link - Cross Harbour SectionProfessional Forum
216 June 2009
Agenda
Opening Speech (09:00)Presentation Part 1 Overriding Public Need and Constraints Presentation Part 2 Alignment Options without ReclamationQ&A
Tea Break (10:00)
Presentation Part 3 Other OptionsQ&AGroup DiscussionPlenary SessionOverall SummaryClosing Speech (12:20)
316 June 2009
SCL - History, Alignment, Station & Benefits
416 June 2009
History of Shatin to Central Link (SCL)
• Railway Development Strategy 2000 (RDS-2000) confirmed the policy objective of railways to form the backbone of the public transport system
• Recommended in RDS-2000 for priority implementation with a target completion in 2011
• MTRCL & KCRC were invited to submit proposals to Government for its implementation in 2001
• KCRC was awarded the project in 2002 – design carried out but affected in 2004 because of impending merger
• One of the 10 priority projects in 2007-2008 Policy Address
• Government invited MTRCL to continue with SCL planning and design in March 2008
• Government entrusted to MTRCL SCL design and site investigation works with Government funding
516 June 2009
Shatin to Central Link (SCL)Source:
LegCo Paper No. CB(1)1036/07-08(03) on 27 March 2008
CROSS HARBOUR SECTION
616 June 2009
East West CorridorKey Facts:
• Components:West Rail Line, Shatin to Central Link (Tai Wai to Hung Hom section),Ma On Shan Line
• Journey time:Wu Kai Sha to Tuen Mun69 mins
New Railway:
• 11 km
• 6 new stations
• 3 interchange stations
716 June 2009
North South CorridorKey Facts:
• Components:East Rail Line, Shatin to Central Link (Hung Hom to Admiralty section)
• Journey time: Lo Wu to Admiralty50 mins
HUNG HOM STATION
EXHIBITION STATION
ADMIRALTY STATION
CROSS HARBOUR SECTION
New Railway:
• 6 km
• 3 new stations
• All interchange stations
816 June 2009
Shatin to Central Link BenefitsBenefits:
• Increased area coverage
• 6 new interchange stations
• Significantly increased route choice
• Improved East-West connectivity
• Improved connection from New Territories to Urban Area
• Increased robustness of railway network
916 June 2009
Why are We Here Today?• Shatin to Central Link (SCL) needs to cross the harbour
• Cross Harbour Section may require ‘temporary’ or permanent reclamation
• The need for Compliance with Protection of Harbour Ordinance (PHO)
– Presumption against reclamation
– Overriding public need (as per Court of Final Appeal judgment) to rebut presumption
• To discuss alignment options for SCL Cross Harbour Section and review the extent of the proposed reclamation
1016 June 2009
Design Principles for SCL Cross Harbour Section• Acceptable railway design
– East Rail to cross harbour at Hung Hom Station
– Interchange with future North Island Line at Exhibition Station
• Feasible to construct
• No reclamation / minimum permanent reclamation
• Options requiring reclamation must satisfy the requirements of the PHO and the Court of Final Appeal Judgment (January 2004)
1116 June 2009
Public Consultation Programme for SCL Cross Harbour Section
Complete SCL Scheme supported by Cogent and Convincing Materials Report
September 2009
Public Forum & Follow-up DiscussionsAugust 2009
District ConsultationJuly / August 2009
Follow-up Discussions from Professional ForumFollow-up Discussions from Stakeholder Forum
June / July 2009
Stakeholder ForumJune/July 2009
Professional Forum16 June 2009
1216 June 2009
Current Programme for Shatin to Central Link
Completion of North South Section2019
Completion of East West Section2015
Commencement of ConstructionEnd 2010
Shatin to Central Link GazettalEnd 2009
1316 June 2009
PART IOVERRIDING PUBLIC NEEDS
AND CONSTRAINTS
1416 June 2009
Compliance with Protection of the Harbour Ordinance
1516 June 2009
Compliance with Protection of the Harbour Ordinance
• Statutory presumption against reclamation
• Presumption is rebuttable only by establishing an overriding public need for reclamation
Overriding Public Need
– Economic, environmental and social needs of the community
– Compelling
– Present
– Must have no reasonable alternative
1616 June 2009
The Overriding Public Need for SCL
1716 June 2009
To Relieve Congestion on Existing Rail Lines
SCL will redistribute railway passenger
flow to relieve congestion within existing
railway lines, some of which will be over
desirable capacity in near future.
1816 June 2009
To Support Cross Boundary Integration
SCL has immense significance to support
HK’s growing cross-boundary economic
activities & social integration with
Mainland China.
1916 June 2009
To Relieve Congestion of Cross Harbour Tunnel
SCL will be safe, reliable and
environmentally-friendly.
SCL will reduce road-based traffic and
alleviate traffic at the Cross Harbour
Tunnel.
2016 June 2009
To Relieve Traffic Congestion in Hong Kong
SCL will create the opportunity to relieve
traffic congestion in Kowloon and on
Hong Kong Island by providing an
alternative transport choice .
2116 June 2009
To Mitigate Deterioration of Road-side Air Quality
SCL is a sustainable solution to mitigate
deterioration of road-side air quality on
HK Island and Kowloon.
2216 June 2009
Benefits to the Community at Large
2316 June 2009
Social & Economic Benefits• Employment opportunities during SCL
construction – 11,000 jobs created
• Enhanced employment opportunities in areas along alignment – commercial / tourism related
• Passenger time savings worth HK$4.1 billion/year by 2021
• To catalyze rejuvenation of old urban districts
2416 June 2009
To Minimize Protracted Disruption to the Community
SCL will have to interface with Central
Wanchai Bypass and other major planned
projects along north shore of Hong Kong
Island.
Source: Highways Department
2516 June 2009
Summary
1. Overriding Public Need for SCL – PRESSING & IMMINENT
- To Relieve Congestion of Existing Rail Lines- To Support Cross-boundary Integration- To Relieve Traffic Congestion of Cross Harbour Tunnel- To Relieve Traffic Congestion in Hong Kong - To Mitigate Deterioration of Road-side Air Quality
2. Benefits to the Community at Large
- Social & Economic Benefits
3. Other Factors
- To Minimize Protracted Disruption to the Community
2616 June 2009
Constraints of Cross Harbour Section
2716 June 2009
Objective – extend East Rail across the harbour
EXHIBITIONSTATION
ADMIRALTYSTATION
TSUEN WAN LINE
ISLAND LINE
HUNG HOMSTATION
KOWLOON SOUTHERN LINK
EAST RAIL
PROPOSED NORTH ISLAND LINE
Hung Hom Station
Exhibition Station
Admiralty Station
2816 June 2009
Constraint –Hung Hom Interchange Station Location
HUNG HOMSTATION
EXHIBITIONSTATION
HUNG HOMSTATION
Constraints for Hung HomInterchange Station
horizontal & vertical constraints:
determine the location of the station andalignment of Cross Harbour Section
EXHIBITIONSTATION
ADMIRALTYSTATION
2916 June 2009
Hung Hom Bypass
IMC
Freight
ETS Portal
Freight Pier
E& M Plant Room
Existing East Rail/ West Rail/ Intercity Platforms
Hung Hom Interchange Station Horizontal Constraints
Freight with Metropolis Above
Cross Harbour Tunnel
A
A
Section A-AHK ColiseumMetropolis
(2) Existing foundation of Coliseum(3) Existing foundation of Metropolis
To PolyU
(1) Existing platforms
Stabling/Freight Yard
HK Coliseum
3016 June 2009
Constraint – Cross Harbour Tunnel (CHT)
EXHIBITIONSTATION
ADMIRALTYSTATION
HUNG HOMSTATION
ADMIRALTYSTATION
Cross Harbour Tunnel (CHT)
3116 June 2009
Constraint – Central Wanchai Bypass (CWB)
• CWB (the section within CBTS) will be constructed between 2010 & 2016
• CWB is a physical barrier to SCL alignment
• SCL either passes above or below CWB
• To minimize impacts to the community and Causeway Bay Typhoon Shelter, SCL has to coordinate with CWB
EXHIBITIONSTATION
ADMIRALTYSTATION
HUNG HOMSTATION
Central Wanchai Bypass(CWB)
3216 June 2009
Constraint – Causeway Bay Typhoon Shelter (CBTS)
• CBTS users demand for minimum disruption
• Construction of CWB in CBTS require re-arrangement of anchorage area and moorings
EXHIBITIONSTATION
ADMIRALTYSTATION
HUNG HOMSTATION
Causeway Bay Typhoon
Shelter (CBTS)
3316 June 2009
Constraint – Typical Vertical Constraints
Central Wanchai Bypass Tunnel
Existing Breakwater
Alluvium
Rock
Marine Deposits
Corestones
Seabed approx -20mPD
Scour Area -local depression in seabed
Existing Cross Harbour Tunnel HUNG HOMSTATION
Fairway
Fairway
Typical Geological Plan and Section for Cross Harbour Section
3416 June 2009
• Minimum radius curve – 300m
• Maximum gradient – 3%
• Large ventilation ducts for each tunnel tube
• Cross passages between tunnel tubes at 250m intervals
• Ventilation building / fireman’s access / emergency evacuation point as close to landfall as practical
• Flood gate buildings on alignment on both sides at landing points
Constraint – Operational Requirements
3516 June 2009
Summary of Constraints
HUNG HOMSTATION
EXHIBITIONSTATION
11 Hung Hom Interchange Station
(horizontal & vertical constraints)
2 Cross Harbour Tunnel (CHT)
3 Central Wanchai Bypass (CWB)
4 Causeway Bay Typhoon Shelter (CBTS)
5 Typical Vertical Constraints
6 Operational Requirements
7 Hung Hom Bypass & Fender Piles
8 Seawall
9 Freight Pier
10 Fairway
11 Buoy
12 Gas Main
13 Breakwater
14 CHT Portal & Existing Seawall
15 Buildings & Infrastructure Projects
2
3
4
5
6
7
8
9
10
11
12
13
14
15
3616 June 2009
Potential Alignment Options
3716 June 2009
Alignment Corridor
• All alignment options fall within the envelope shown
• Some alignment options may require reclamation
• Details to be discussed in Part 2 and 3
HUNG HOMSTATION
EXHIBITIONSTATION
Existing Cross H
arbour Tunnel
Centra
l Wan
chai
Bypas
s
Envelope for Alignment Options
3816 June 2009
PART 2ALIGNMENT OPTION WITHOUT RECLAMATION
3916 June 2009
Cross Harbour Bridge
Characteristics• Bridge piers in the harbour are regarded as reclamation• Bridge deck should be high enough to allow passage of vessels• Require extensive approaches at both ends. Approach ramps would extend almost to Admiralty Station.
Implications• Require extensive land resumption for bridge piers and foundations• Massive approach ramps would cut off harbourfront• Interchanges not practical. • Visual impact of Victoria Harbour
NOT A REASONABLE OPTION
‘No Reclamation’ Options
4016 June 2009
Tunnel in Mixed Ground Under the Harbour
Diameter Dictated by• structure gauge• ventilation
Vertical Alignment• Minimum ground cover to maintain ground
stability• Desirable cover – 2 diameters• Geological conditions
can only be constructed by tunnel boringmachine (TBM)
Minimum 1~2 diameter of tunnel
approx. 10m
diameter
air duct
4116 June 2009
Due to vertical alignment constraints, tunnels have to pass through mixed ground, i.e.through soft and rock strata.
• Implications: - requires frequent (daily) intervention for maintenance & repair of cutterhead due to serious wearing in mixed ground
- interventions require work under pressure to maintain face stability
• Problems: - required to work under pressure > 3.45 bar for up to 1,800 m
EXHIBITIONSTATION
HUNG HOMSTATION
Rock
Soft
Breakwater Hung Hom Bypass
DeepFlood Gate
SCL Bored Tunnel
3.45 bar limit
DeeperStation
Central Wanchai Bypass
DeepVentilation
Building
Bored Tunnel in Mixed Ground Under the Harbour
4216 June 2009
Face Interventions• For frequent face interventions at these pressures in mixed ground conditions, special
techniques such as saturation diving would be required
• Saturation diving only used on one completed project in the world (completed in 2002). Different circumstances, due to ground conditions, as only 6 interventions made.
• ‘Last resort’ technique.
SPACE TO BE PRESSURISED TO KEEP WATER OUT
AND TO STOP GROUND COLLAPSING ON WORKERS
SEABED
4316 June 2009
• Conclusions: - Risk to health, life and project too high to be acceptable- Not a reasonable option
• Problems: - Factories and Industrial Undertakings Ordinance (Cap.59M) allows working up to maximum pressure of 3.45 bar
- All bored tunnel options will require regular intervention for maintenance and repair work in excess of 3.45 bar
Bored Tunnel in Mixed Ground Under the Harbour
4416 June 2009
Tunnel Deep in RockCharacteristics• Alignment will be significantly lowered
Implications• East Rail would need to be depressed from north of Mong Kok East Station• Interchange at Hung Hom and Exhibition Station either not practical or inconvenient• Cannot provide required level of service
• NOT A REASONABLE OPTION
‘No Reclamation’ Options
EXHIBITIONSTATION
HUNG HOMSTATION
Rock
Soft
Breakwater Hung Hom Bypass
DeeperFlood Gate
DeeperInterchange
StationDeeper
InterchangeStation
Central Wanchai Bypass
DeeperVentilation
Building
SCL Tunnel Deep in RockFurther deepening of building required
approx. 80m
approx. 40m approx. 53m
4516 June 2009
• The following “No Reclamation” Options have been considered:
– Cross Harbour Bridge
– Bored Tunnel in Mixed Ground
– Tunnel Deep in Rock
• None of the above are considered to be reasonable.
‘No Reclamation’ Options
4616 June 2009
Q&A SESSION
4716 June 2009
TEA BREAK
4816 June 2009
PART 3OTHER OPTIONS
4916 June 2009
Other Options
• Immersed Tube Tunnel
• Cut & Cover Tunnel
• Combination of the above
Previous cross harbour tunnels have been constructed by Immersed Tube Tunnel with Cut & Cover sections at each landfall.
5016 June 2009
Immersed Tube Tunnel
• Proven method
• Installation of pre-cast units into trench in seabed
(1) Trench dredging (2) Lower immersed tube units (3) BackfillingLay barge
Sea bed Sea bed Sea bed
5116 June 2009
Immersed Tube Tunnel – Alignment Envelope
Central Alignment –
Constrained by CWB slip road
Exis
ting
Cro
ss H
arbo
ur T
unne
l
HUNG HOMSTATION
EXHIBITIONSTATION
Envelope for Cross Harbour Tunnel Options
Centra
l Wan
chai
Bypas
s
(CWB)
EASTERN CORRIDOR
WESTERN CORRIDOR
SLIP ROAD NO.8
5216 June 2009
1. Immersed Tube Tunnel (IMT) –IMT unit partly above existing seabed
2. Hung Hom Landfall – Cut & Cover Tunnel
3. Reinstatement of Hung Hum Bypass Fender Piles
4. Reinstatement of Freight Pier
Common Alignment Issues
Exis
ting
Cro
ss H
arbo
ur T
unne
l
HUNG HOMSTATION
EXHIBITIONSTATION
Centra
l Wan
chai
Bypas
s
(CWB)
1
2
4
3
5. Cofferdam for Demolition and Reinstatement of Causeway Bay Typhoon Shelter (CBTS) Existing Breakwater
6. Temporary Reclamation in CBTS
5
6
5316 June 2009
1. Immersed Tube Tunnel (IMT) –IMT units partly above existing seabed
• Any permanent reclamation? No– Raising sea bed is not reclamation
(even if it were, there is overriding public need)– Fairway not affected
• Any temporary reclamation? No
• Any impact to the use and enjoyment of harbour?Temporary marine traffic diversion
Typical Cross Section above Seabed
Future Sea Bed Level
Existing Sea Bed Level
Typical Cross Section at Deeper Section of IMT
Future Sea Bed Level
Existing Sea Bed Level
Section A
Section B
Typical Cross Section at Two Ends of IMT
Future Sea Bed Level
Existing Sea Bed Level
EXHIBITIONSTATION
Central –Wanchai Bypass
Ventilation Building
HUNG HOMSTATION
Rock
Soft
BreakwaterHung Hom
BypassFlood Gate
SCL Immersed Tube Tunnel
Hung Hom Fairway
B
A
A
B
5416 June 2009
2. Hung Hom Landfall – Cut & Cover Tunnel
Temporary works area
Cut-and-cover tunnel
Immersed tube tunnel
International Mail Centre
To Hung Hom Station
Freight Pier
Hung Hom Bypass
5516 June 2009
• Any permanent reclamation? No
• Any temporary reclamation? approx. 1 ha– Temporary works area– Temporary cofferdam
• Any impact to the use and enjoyment of harbour?– No impact to use of the harbour by the public
2. Hung Hom Landfall – Cut & Cover Tunnel
Cut & Cover Tunnel
Temporary Works Area
Temporary Cofferdam
Temporary Works Area
5616 June 2009
3. Reinstatement Hung Hom Bypass Fender Piles
Existing fender piles to be removed for construction of cut-and-cover tunnels and reinstated in a different location and form.
• Any permanent reclamation? Yesthe reinstated fender piles
• Any temporary reclamation? No
• Any impact to the use and enjoyment of harbour?No impact to use of the harbour by the public
5716 June 2009
• Part of the pier structure has to be demolished to make way for the trench excavation for the immersed tube
• Pier may not require reinstatement depending on operational requirements
• Any permanent reclamation? YesIf reinstatement of pier is required
• Any temporary reclamation? No
• Any impact to the use and enjoyment of harbour?No impact to use of the harbour by the public
4. Reinstatement of Existing Freight Pier
International Mail Centre
To Hung Hom Station
Freight Pier
Hung Hom Bypass
Part of freight pier to be demolished
5816 June 2009
5. Cofferdam for Demolition & Reinstatement of CBTS Existing Breakwater
• Temporary seawall and reclamation provided on harbour
• Temporary seawall and reclamation formed before removing existing breakwater for SCL tunnel construction
• Breakwater reinstated prior to removal of temporary seawall
• Any permanent reclamation? No
• Any temporary reclamation? YesIncorporated with those for Cut and Cover tunnel in CBTS
• Any impact to the use and enjoyment of harbour?Some moorings inside the CBTS will be affected
temporary breakwater
existing breakwater removed after temporary breakwater constructed
5916 June 2009
Central Wanchai Bypass (CWB)
• Project authorized by ExCo in May 2009
• Construction work in CBTS from 2010 to 2016
• Temporary reclamation in CBTS will be carried out in 4 main stages to facilitate construction of the road tunnels
6. Temporary Reclamation in Causeway Bay Typhoon Shelter (CBTS)
6016 June 2009(extracted from CWB CCM process)
CWB Works in Causeway Bay Typhoon Shelter (CBTS) Temporary Reclamation Phasing
6116 June 2009
Causeway Bay Typhoon Shelter
Private Mooring Area(about 4.4 ha, about 150 vessels)
RHKYC Mooring Area(about 3 ha , about 150
vessels)
Note: vessels counting carried out in April 2008
Anchorage Area(about 2.6 ha, about 200 vessels)
OFF-SITE
CWB Works in Causeway Bay Typhoon Shelter (CBTS) Mooring Re-provisioning
6216 June 2009
• SCL work has no permanent reclamation inside CBTS
• In addition to the economic, environmental and social implications, cost as well as the time and delay should temporary reclamation also be judged in terms of
– Area?
– Duration?
– Disturbance?
– Combinations of all these?
Objective is to minimize the temporary reclamation taking all of these factors into account.
6. Temporary Reclamation in Causeway Bay Typhoon Shelter (CBTS)
6316 June 2009
• Option 1: Easterly Alignment
SCL Alignment Option in CBTS
6416 June 2009
Easterly Alignment – Option 1A (SCL below CWB) Permanent Reclamation: No
Temporary Reclamation: Approximate additional area = 0.6 ha
Temporary reclamation for CWB at CBTS will need to be extended by approx. 3 years
Prolonged disruption to CBTS
Features: SCL to be built underneath CWB as a combined structure
Excavation in CBTS will be deeper and will increase construction complexity,
risk, cost and duration
Railway Operation: Cross platform interchange at Exhibition Station cannot be provided
SCL SCL
CWB CWB
EXHIBITIONSTATION
Temporary reclamation
Station 8m deeper. No cross platform interchange
Deeper tunnel, work in CBTS prolonged by approx. 3 years
CBTS
SCL TunnelCWB Tunnel
Challenging, risky construction under CHT
6516 June 2009
Permanent Reclamation: Yes
CWB and SCL alignments need to shifted northward for about 3m to avoid clashes with existing structures
Temporary Reclamation: Required at CBTS & near Island Eastern Corridor
Approximate additional area = 1.4 ha
Prolonged disruption to CBTS due to impacts on cooling water intakes
CWB completion will be delayed by approx. 3 years
Features: Only part of SCL to run underneath CWB to avoid construction complexity in Option 1A particularly at CHT
Railway Operation: Cross platform interchange at Exhibition Station can be provided
Easterly Alignment – Option 1B (SCL partly below CWB)
SCL SCL
CWB CWB
CBTS
SCL TunnelCWB Tunnel
EXHIBITIONSTATION
Temporary reclamation
Clashes with CWB tunnels; to be moved north,
permanent reclamation required
HEC SubStation
6616 June 2009
Permanent Reclamation: No
Temporary Reclamation: Required (additional area within CBTS) & near Island Eastern Corridor
& prolonged disruption to CBTS (due to deeper tunnel under CBTS and not possible
to have concurrent SCL and CWB construction due to impacts on sea water intakes)
Approximate additional area = 1.4 ha
CWB completion will be delayed by approx. 3 years
Features: Similar to Option 1B but follow more inland alignment towards Exhibition Station
Railway Design: Cross platform interchange at Exhibition Station cannot be provided
Easterly Alignment – Option 1C (SCL partly below CWB)
Temporary reclamation
SCL SCL
CWB CWB
CBTS
SCL TunnelCWB Tunnel
EXHIBITIONSTATION
No cross platform interchange
Deeper tunnel, work in CBTS prolonged by approx. 3 years
Temporary reclamation
6716 June 2009
CROSS HARBOUR TUNNELCAUSEWAY BAY TYPHOON SHELTER
(CBTS)SEABED
SCL TUNNELS PROTRUDE ABOVE SEABED
SCL TUNNELS CLASH WITH CWB SLIP ROAD NO.8
SCL Tunnel
CWB Tunnel
Easterly Alignment – Option 1D (SCL above CWB)
6816 June 2009
Easterly Alignment – Option 1D (SCL above CWB)Permanent Reclamation: 10 ha near North Point (6.7 ha more than CWB original scheme)
Temporary Reclamation: Required at CBTS & near Island Eastern Corridor
Approximate additional area = 0.6 ha
Prolonged disruption to CBTS due to construction complexity
Features: CWB vertical profile lowered to accommodate SCL
SCL to be built above CWB as a separate structure
Excavation in CBTS will be deeper and will increase construction complexity,
risk, cost and duration
SCL SCL
CWB CWB
6916 June 2009
SCL Alignment Option in CBTS• Option 1: Easterly Alignment
• Option 2: Westerly Alignment
7016 June 2009
Permanent Reclamation: No
Temporary Reclamation: Required at CBTS
Approximate additional area = 2.2 ha
Features: Alignment crossing CWB at the west of CBTSShortest distance
Westerly Alignment
CBTS
SCL Tunnel
LONGITUDINAL SECTION ALONG CWB
CWB TunnelCWB Slip Road
SCL Temporary Reclamation
Breakwater
CWB
7116 June 2009
Within the limit of the gazetted CWB scheme and CCM, the extent of SCL protection work allowed is as shown
Westerly Alignment – CWB authorized, SCL not yet authorized
7216 June 2009
The following considerations have to be taken into account in developing a reasonable construction sequence:
• Area of temporary reclamation
• Duration of temporary reclamation
• Disturbance to the moorings and activities
• Various other factors in line with Court of Final Appeal Judgment
Westerly Alignment – SCL authorized
7316 June 2009
Westerly Alignment – Option 2
Additional Protection Works by CWB
Original TS4 to be extended
Minimum extentLimit preferably
moved further North
7416 June 2009
Westerly Alignment – Option 2
TS3(E) & TS3 (W)
Completed Tunnel
Tunnel Structure
SCL 2
Completion of SCL from SVB
7516 June 2009
TS3(E) & TS3 (W)
Completed Tunnel
To be completed after CWB construction
Tunnel Structure
Westerly Alignment – Option 2
7616 June 2009
TS3(E) & TS3 (W)
Completed Tunnel
Tunnel Structure
Westerly Alignment – Further Opportunities for Earlier Completion
Can works in this area be completed earlier?
7716 June 2009
Requirements for Earlier Completion
– Need to provide sufficient navigation channel and work space in CBTS
– Proposed revised temporary reclamation and mooring arrangement have to be accepted by concerned stakeholders
– Some additional moorings (compared to CWB) may need to be relocated outside CBTS
– Timely authorization of SCL
Westerly Alignment – Further Opportunities for Earlier Completion
7816 June 2009
Option 2 –Westerly
Alignment
Option 1 – Easterly Alignment
LowMediumMediumMediumHighConstruction Complexity & Risk
Min. length;X-platform int’geok
Longer;X-platform int’genot ok
Longer;X-platform int’ge not ok
Longer;X-platform int’ge ok
Longer;X-platform int’ge not ok
Railway operation
Limited moorings affected
Prolonged occupation of moorings
Prolonged occupation of moorings
Prolonged occupation of moorings
Prolonged occupation of moorings
Disturbance
+ 1.5 years+ 3 years and delay to CWB
+ 3 years and delay to CWB
+ 3 years and delay to CWB
+ 3 years and delay to CWB
Extended Duration of Works in CBTS
2.2 ha0.6 ha2 ha2 ha0.6 haTemporary reclamation
NilAdditional 6.7 ha for CWB
NilTo be determined
NilPermanent reclamation
Option 1DOption 1COption 1BOption 1A
Summary of Options with Reclamation
7916 June 2009
Issues to be AddressedYour views on:
• Are you satisfied that there is overriding need for SCL?
• There is no reasonable ‘no reclamation’ option.
• Which of the two IMT alignment corridors (easterly or westerly) is the better option?
• Should the extent of protection work in CWB be increased to avoid repeated temporary reclamation in CBTS?
• What additional work should MTRCL and Government undertake to maximize the integration of the construction work in CBTS to achieve minimum reclamation?
8016 June 2009
Q&A
8116 June 2009
GROUP DISCUSSION
8216 June 2009
PLENARY SESSION
8316 June 2009
OVERALL SUMMARY
8416 June 2009
Next Step
Complete SCL Scheme supported by Cogent and Convincing Materials Report
September 2009
Public Forum & Follow-up DiscussionsAugust 2009
District ConsultationJuly / August 2009
Follow-up Discussions from Professional ForumFollow-up Discussions from Stakeholder Forum
June / July 2009
Stakeholder ForumJune/July 2009
Professional Forum16 June 2009
Completion of North South Section2019
Completion of East West Section2015
Commencement of ConstructionEnd 2010
Shatin to Central Link GazettalEnd 2009
SCL Programme
Public Consultation Programme