Prof. Awad Hanna Advantages of using Precedence Diagram: 1. No dummy activity are required. 2. A single number can be assigned to identify each activity. 3. Analytical solution is simpler.

Upload: sheena-hawkins

Post on 22-Dec-2015

217 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Prof. Awad Hanna Precedence Diagram Advantages of using Precedence Diagram: 1. No dummy activity are required. 2. A single number can be assigned to identify

Prof. Awad Hanna

Advantages of using Precedence Diagram:1. No dummy activity are required.2. A single number can be

assigned to identify each activity.3. Analytical solution is simpler.

Page 2: Prof. Awad Hanna Precedence Diagram Advantages of using Precedence Diagram: 1. No dummy activity are required. 2. A single number can be assigned to identify

Prof. Awad Hanna

20A

30B

30C

20A

30B

40C

(a) Incorrect Representation

(b) Correct Representation

Page 3: Prof. Awad Hanna Precedence Diagram Advantages of using Precedence Diagram: 1. No dummy activity are required. 2. A single number can be assigned to identify

Prof. Awad Hanna

A D

C E

B

(a) Incorrect Representation

A D

C E

(b) Correct Representation

Starting Dummy Finish DummyB

Page 4: Prof. Awad Hanna Precedence Diagram Advantages of using Precedence Diagram: 1. No dummy activity are required. 2. A single number can be assigned to identify

Prof. Awad Hanna

Wall 1

Wall 2

Footing 1

Footing 2

10Footing 1

40Wall 2

20Footing 2

30Wall 1

Page 5: Prof. Awad Hanna Precedence Diagram Advantages of using Precedence Diagram: 1. No dummy activity are required. 2. A single number can be assigned to identify

Prof. Awad Hanna

10A

25E

20C

30F

2

5Start

35Finish

15D

31 4

Page 6: Prof. Awad Hanna Precedence Diagram Advantages of using Precedence Diagram: 1. No dummy activity are required. 2. A single number can be assigned to identify

Prof. Awad Hanna

1. Create Activity list and eliminate redundancies.

2. Construct precedence diagramActivities with no dependency

arranged at the leftCreate dummy start if you have more

than one start “Contract Award”

3. Arrange activities in a sequential order