PROJECT : SM LIGHT RESIDENCES LOCATION : BONI AVE. EDSA MANDALUYONG CITY SUBJECT : PRODUCTIVITY RATE SCOPE OF WORK : INTERIOR PAINTING OF UNITS FINISH : SEMI-GLOSS (2 COATS) PROCEDURE 1. SURFACE PREPARATION - Putty Works - Sanding 2. PRIMER - Application of Flat Latex - Spot putty and reapply Flat Latex 3. FIRST COAT - Application of Semi-Gloss 4. FINAL COAT - Application of Semi-Gloss PAINTING TO MASONRY WALL FLOOR : 17TH FLOOR UNIT NO. : 18 AREA : UNIT 46.9 m 2 CR 8.86 m 2 55.76 m 2 DATE MANPOWER ACTIVITY MANHOUR 6-Nov Painter Surface Preparation - Putty Works 5 Man-Hrs 7-Nov Painter Surface Preparation - Putty Works 7.5 Man-Hrs 7-Nov Painter Surface Preparation - Sanding 5 Man-Hrs 7-Nov Painter Primer - Application of Flat Latex 1 Man-Hrs 8-Nov Painter Primer - Application of Flat Latex 3.25 Man-Hrs 8-Nov Painter Primer - Spot Putty & Reapply Flat Latex 6.75 Man-Hrs 8-Nov Painter 1st Coat - Application of Semigloss 4.75 Man-Hrs 8-Nov Painter Final Coat - Application of Semigloss 4.5 Man-Hrs TOTAL 37.75 Man-Hrs PRODUCTIVITY (Man-hr/m 2 ) 0.6770 FLOOR : 17TH FLOOR UNIT NO. : 19 AREA : UNIT 46.9 m 2 CR 8.86 m 2 55.76 m 2 DATE MANPOWER ACTIVITY MANHOUR

Upload: louiemapuan

Post on 18-Dec-2015

2.022 views

Category:

Documents


155 download

DESCRIPTION

Labor Rate

TRANSCRIPT

  • PROJECT : SM LIGHT RESIDENCES

    LOCATION : BONI AVE. EDSA MANDALUYONG CITY

    SUBJECT : PRODUCTIVITY RATE

    SCOPE OF WORK : INTERIOR PAINTING OF UNITS

    FINISH : SEMI-GLOSS (2 COATS)

    PROCEDURE

    1. SURFACE PREPARATION

    - Putty Works

    - Sanding

    2. PRIMER

    - Application of Flat Latex

    - Spot putty and reapply Flat Latex

    3. FIRST COAT

    - Application of Semi-Gloss

    4. FINAL COAT

    - Application of Semi-Gloss

    PAINTING TO MASONRY WALL

    FLOOR : 17TH FLOOR

    UNIT NO. : 18

    AREA :

    UNIT 46.9 m2

    CR 8.86 m2

    55.76 m2

    DATE MANPOWER ACTIVITY MANHOUR

    6-Nov Painter Surface Preparation - Putty Works 5 Man-Hrs

    7-Nov Painter Surface Preparation - Putty Works 7.5 Man-Hrs

    7-Nov Painter Surface Preparation - Sanding 5 Man-Hrs

    7-Nov Painter Primer - Application of Flat Latex 1 Man-Hrs

    8-Nov Painter Primer - Application of Flat Latex 3.25 Man-Hrs

    8-Nov Painter Primer - Spot Putty & Reapply Flat Latex 6.75 Man-Hrs

    8-Nov Painter 1st Coat - Application of Semigloss 4.75 Man-Hrs

    8-Nov Painter Final Coat - Application of Semigloss 4.5 Man-Hrs

    TOTAL 37.75 Man-Hrs

    PRODUCTIVITY (Man-hr/m2) 0.6770

    FLOOR : 17TH FLOOR

    UNIT NO. : 19

    AREA :

    UNIT 46.9 m2

    CR 8.86 m2

    55.76 m2

    DATE MANPOWER ACTIVITY MANHOUR

  • 6-Nov Painter Surface Preparation - Putty Works 5 Man-Hrs

    7-Nov Painter Surface Preparation - Putty Works 7.5 Man-Hrs

    7-Nov Painter Surface Preparation - Sanding 5 Man-Hrs

    7-Nov Painter Primer - Application of Flat Latex 1 Man-Hrs

    8-Nov Painter Primer - Application of Flat Latex 4.25 Man-Hrs

    8-Nov Painter Primer - Spot Putty & Reapply Flat Latex 6.75 Man-Hrs

    8-Nov Painter 1st Coat - Application of Semigloss 3.75 Man-Hrs

    8-Nov Painter Final Coat - Application of Semigloss 4.5 Man-Hrs

    TOTAL 37.75 Man-Hrs

    PRODUCTIVITY (Man-hr/m2) 0.6770

    PAINTING TO MASONRY WALL

    FLOOR : 17TH FLOOR

    UNIT NO. : 37-38

    AREA :

    UNIT 93.8 m2

    CR 17.72 m2

    111.52 m2

    DATE MANPOWER ACTIVITY MANHOUR

    7-Nov Painter Surface Preparation - Putty Works 22 Man-Hrs

    8-Nov Painter Surface Preparation - Sanding 8.5 Man-Hrs

    8-Nov Painter Primer - Application of Flat Latex 4 Man-Hrs

    9-Nov Painter Primer - Application of Flat Latex 3 Man-Hrs

    10-Nov Painter Primer - Spot Putty & Reapply Flat Latex 5.5 Man-Hrs

    10-Nov Painter 1st Coat - Application of Semigloss 6 Man-Hrs

    13-Nov Painter Final Coat - Application of Semigloss 12 Man-Hrs

    TOTAL 61 Man-Hrs

    PRODUCTIVITY (Man-hr/m2) 0.5470

    PAINTING TO MASONRY WALL

    FLOOR : 8TH FLOOR

    UNIT NO. : 21-22

    AREA :

    UNIT 93.8 m2

    CR 17.72 m2

    111.52 m2

    DATE MANPOWER ACTIVITY MANHOUR

    7-Nov Painter Surface Preparation - Putty Works 14 Man-Hrs

    8-Nov Painter Surface Preparation - Putty Works 10 Man-Hrs

    8-Nov Painter Surface Preparation - Sanding 7.5 Man-Hrs

    9-Nov Painter Primer - Application of Flat Latex 6 Man-Hrs

    10-Nov Painter Primer - Spot Putty & Reapply Flat Latex 13 Man-Hrs

  • 10-Nov Painter 1st Coat - Application of Semigloss 6 Man-Hrs

    Painter Final Coat - Application of Semigloss 12 Man-Hrs

    TOTAL 68.5 Man-Hrs

    PRODUCTIVITY (Man-hr/m2) 0.6142

    AVERAGE PRODUCTIVITY (Man-hr/m2) 0.6288

    FINISH : FLAT FINISH

    PROCEDURE

    1. SURFACE PREPARATION

    - Putty Works

    - Sanding

    2. PRIMER

    - Application of Flat Latex

    - Spot putty and reapply Flat Latex

    3. FINAL COAT

    - Final application of flat latex

    PAINTING TO CONCRETE CEILING

    FLOOR : 17TH FLOOR

    UNIT NO. : 18

    AREA :

    UNIT 12.8 m2

    12.8 m2

    DATE MANPOWER ACTIVITY MANHOUR

    6-Nov Painter Surface Preparation - Putty Works 3 Man-Hrs

    7-Nov Painter Surface Preparation - Putty Works 3 Man-Hrs

    7-Nov Painter Surface Preparation - Sanding 2 Man-Hrs

    8-Nov Painter Primer - Application of Flat Latex 0.75 Man-Hrs

    7-Nov Painter Primer - Application of Flat Latex 1 Man-Hrs

    8-Nov Painter Primer - Spot Putty & Reapply Flat Latex 0.5 Man-Hrs

    8-Nov Painter Final Coat - Application of flat latex 1.25 Man-Hrs

    TOTAL 11.5 Man-Hrs

    PRODUCTIVITY (Man-hr/m2) 0.8984

    FLOOR : 17TH FLOOR

    UNIT NO. : 19

    AREA :

    UNIT 12.8 m2

    12.8 m2

    DATE MANPOWER ACTIVITY MANHOUR

    6-Nov Painter 1 Surface Preparation - Putty Works 3 Man-Hrs

    7-Nov Painter 1 Surface Preparation - Putty Works 3 Man-Hrs

    7-Nov Painter 1 Surface Preparation - Sanding 2 Man-Hrs

  • 7-Nov Painter 1 Primer - Application of Flat Latex 1 Man-Hrs

    8-Nov Painter 2 Primer - Application of Flat Latex 0.75 Man-Hrs

    8-Nov Painter 1 Primer - Spot Putty & Reapply Flat Latex 0.5 Man-Hrs

    8-Nov Painter 1 Final Coat - Application of flat latex 1.25 Man-Hrs

    TOTAL 11.5 Man-Hrs

    PRODUCTIVITY (Man-hr/m2) 0.8984

    FLOOR : 17TH FLOOR

    UNIT NO. : 37-38

    AREA :

    UNIT 25.6 m2

    25.6 m2

    DATE MANPOWER ACTIVITY MANHOUR

    7-Nov Painter 1 Surface Preparation - Putty Works 5.5 Man-Hrs

    8-Nov Painter 1 Surface Preparation - Sanding 6 Man-Hrs

    9-Nov Painter 1 Primer - Application of Flat Latex 2.5 Man-Hrs

    9-Nov Painter 1 Primer - Spot Putty & Reapply Flat Latex 2.5 Man-Hrs

    10-Nov Painter 1 Final Coat - Application of flat latex 3 Man-Hrs

    TOTAL 19.5 Man-Hrs

    PRODUCTIVITY (Man-hr/m2) 0.7617

    FLOOR : 8TH FLOOR

    UNIT NO. : 21-22

    AREA :

    UNIT 25.6 m2

    25.6 m2

    DATE MANPOWER ACTIVITY MANHOUR

    7-Nov Painter 1 Surface Preparation - Putty Works 9 Man-Hrs

    8-Nov Painter 1 Surface Preparation - Sanding 4 Man-Hrs

    9-Nov Painter 1 Primer - Application of Flat Latex 2.5 Man-Hrs

    9-Nov Painter 1 Primer - Spot Putty & Reapply Flat Latex 2.5 Man-Hrs

    10-Nov Painter 1 Final Coat - Application of flat latex 3 Man-Hrs

    TOTAL 21 Man-Hrs

    PRODUCTIVITY (Man-hr/m2) 0.8203

    AVERAGE PRODUCTIVITY (Man-hr/m2) 0.8447

  • 210 972.625

    105 69.47321 0.330825

    5 1 43.69

    6 2

    7 2

    8 3

    9 4

    10 5

    11 6