productivity rate - interior painting
DESCRIPTION
Labor RateTRANSCRIPT
-
PROJECT : SM LIGHT RESIDENCES
LOCATION : BONI AVE. EDSA MANDALUYONG CITY
SUBJECT : PRODUCTIVITY RATE
SCOPE OF WORK : INTERIOR PAINTING OF UNITS
FINISH : SEMI-GLOSS (2 COATS)
PROCEDURE
1. SURFACE PREPARATION
- Putty Works
- Sanding
2. PRIMER
- Application of Flat Latex
- Spot putty and reapply Flat Latex
3. FIRST COAT
- Application of Semi-Gloss
4. FINAL COAT
- Application of Semi-Gloss
PAINTING TO MASONRY WALL
FLOOR : 17TH FLOOR
UNIT NO. : 18
AREA :
UNIT 46.9 m2
CR 8.86 m2
55.76 m2
DATE MANPOWER ACTIVITY MANHOUR
6-Nov Painter Surface Preparation - Putty Works 5 Man-Hrs
7-Nov Painter Surface Preparation - Putty Works 7.5 Man-Hrs
7-Nov Painter Surface Preparation - Sanding 5 Man-Hrs
7-Nov Painter Primer - Application of Flat Latex 1 Man-Hrs
8-Nov Painter Primer - Application of Flat Latex 3.25 Man-Hrs
8-Nov Painter Primer - Spot Putty & Reapply Flat Latex 6.75 Man-Hrs
8-Nov Painter 1st Coat - Application of Semigloss 4.75 Man-Hrs
8-Nov Painter Final Coat - Application of Semigloss 4.5 Man-Hrs
TOTAL 37.75 Man-Hrs
PRODUCTIVITY (Man-hr/m2) 0.6770
FLOOR : 17TH FLOOR
UNIT NO. : 19
AREA :
UNIT 46.9 m2
CR 8.86 m2
55.76 m2
DATE MANPOWER ACTIVITY MANHOUR
-
6-Nov Painter Surface Preparation - Putty Works 5 Man-Hrs
7-Nov Painter Surface Preparation - Putty Works 7.5 Man-Hrs
7-Nov Painter Surface Preparation - Sanding 5 Man-Hrs
7-Nov Painter Primer - Application of Flat Latex 1 Man-Hrs
8-Nov Painter Primer - Application of Flat Latex 4.25 Man-Hrs
8-Nov Painter Primer - Spot Putty & Reapply Flat Latex 6.75 Man-Hrs
8-Nov Painter 1st Coat - Application of Semigloss 3.75 Man-Hrs
8-Nov Painter Final Coat - Application of Semigloss 4.5 Man-Hrs
TOTAL 37.75 Man-Hrs
PRODUCTIVITY (Man-hr/m2) 0.6770
PAINTING TO MASONRY WALL
FLOOR : 17TH FLOOR
UNIT NO. : 37-38
AREA :
UNIT 93.8 m2
CR 17.72 m2
111.52 m2
DATE MANPOWER ACTIVITY MANHOUR
7-Nov Painter Surface Preparation - Putty Works 22 Man-Hrs
8-Nov Painter Surface Preparation - Sanding 8.5 Man-Hrs
8-Nov Painter Primer - Application of Flat Latex 4 Man-Hrs
9-Nov Painter Primer - Application of Flat Latex 3 Man-Hrs
10-Nov Painter Primer - Spot Putty & Reapply Flat Latex 5.5 Man-Hrs
10-Nov Painter 1st Coat - Application of Semigloss 6 Man-Hrs
13-Nov Painter Final Coat - Application of Semigloss 12 Man-Hrs
TOTAL 61 Man-Hrs
PRODUCTIVITY (Man-hr/m2) 0.5470
PAINTING TO MASONRY WALL
FLOOR : 8TH FLOOR
UNIT NO. : 21-22
AREA :
UNIT 93.8 m2
CR 17.72 m2
111.52 m2
DATE MANPOWER ACTIVITY MANHOUR
7-Nov Painter Surface Preparation - Putty Works 14 Man-Hrs
8-Nov Painter Surface Preparation - Putty Works 10 Man-Hrs
8-Nov Painter Surface Preparation - Sanding 7.5 Man-Hrs
9-Nov Painter Primer - Application of Flat Latex 6 Man-Hrs
10-Nov Painter Primer - Spot Putty & Reapply Flat Latex 13 Man-Hrs
-
10-Nov Painter 1st Coat - Application of Semigloss 6 Man-Hrs
Painter Final Coat - Application of Semigloss 12 Man-Hrs
TOTAL 68.5 Man-Hrs
PRODUCTIVITY (Man-hr/m2) 0.6142
AVERAGE PRODUCTIVITY (Man-hr/m2) 0.6288
FINISH : FLAT FINISH
PROCEDURE
1. SURFACE PREPARATION
- Putty Works
- Sanding
2. PRIMER
- Application of Flat Latex
- Spot putty and reapply Flat Latex
3. FINAL COAT
- Final application of flat latex
PAINTING TO CONCRETE CEILING
FLOOR : 17TH FLOOR
UNIT NO. : 18
AREA :
UNIT 12.8 m2
12.8 m2
DATE MANPOWER ACTIVITY MANHOUR
6-Nov Painter Surface Preparation - Putty Works 3 Man-Hrs
7-Nov Painter Surface Preparation - Putty Works 3 Man-Hrs
7-Nov Painter Surface Preparation - Sanding 2 Man-Hrs
8-Nov Painter Primer - Application of Flat Latex 0.75 Man-Hrs
7-Nov Painter Primer - Application of Flat Latex 1 Man-Hrs
8-Nov Painter Primer - Spot Putty & Reapply Flat Latex 0.5 Man-Hrs
8-Nov Painter Final Coat - Application of flat latex 1.25 Man-Hrs
TOTAL 11.5 Man-Hrs
PRODUCTIVITY (Man-hr/m2) 0.8984
FLOOR : 17TH FLOOR
UNIT NO. : 19
AREA :
UNIT 12.8 m2
12.8 m2
DATE MANPOWER ACTIVITY MANHOUR
6-Nov Painter 1 Surface Preparation - Putty Works 3 Man-Hrs
7-Nov Painter 1 Surface Preparation - Putty Works 3 Man-Hrs
7-Nov Painter 1 Surface Preparation - Sanding 2 Man-Hrs
-
7-Nov Painter 1 Primer - Application of Flat Latex 1 Man-Hrs
8-Nov Painter 2 Primer - Application of Flat Latex 0.75 Man-Hrs
8-Nov Painter 1 Primer - Spot Putty & Reapply Flat Latex 0.5 Man-Hrs
8-Nov Painter 1 Final Coat - Application of flat latex 1.25 Man-Hrs
TOTAL 11.5 Man-Hrs
PRODUCTIVITY (Man-hr/m2) 0.8984
FLOOR : 17TH FLOOR
UNIT NO. : 37-38
AREA :
UNIT 25.6 m2
25.6 m2
DATE MANPOWER ACTIVITY MANHOUR
7-Nov Painter 1 Surface Preparation - Putty Works 5.5 Man-Hrs
8-Nov Painter 1 Surface Preparation - Sanding 6 Man-Hrs
9-Nov Painter 1 Primer - Application of Flat Latex 2.5 Man-Hrs
9-Nov Painter 1 Primer - Spot Putty & Reapply Flat Latex 2.5 Man-Hrs
10-Nov Painter 1 Final Coat - Application of flat latex 3 Man-Hrs
TOTAL 19.5 Man-Hrs
PRODUCTIVITY (Man-hr/m2) 0.7617
FLOOR : 8TH FLOOR
UNIT NO. : 21-22
AREA :
UNIT 25.6 m2
25.6 m2
DATE MANPOWER ACTIVITY MANHOUR
7-Nov Painter 1 Surface Preparation - Putty Works 9 Man-Hrs
8-Nov Painter 1 Surface Preparation - Sanding 4 Man-Hrs
9-Nov Painter 1 Primer - Application of Flat Latex 2.5 Man-Hrs
9-Nov Painter 1 Primer - Spot Putty & Reapply Flat Latex 2.5 Man-Hrs
10-Nov Painter 1 Final Coat - Application of flat latex 3 Man-Hrs
TOTAL 21 Man-Hrs
PRODUCTIVITY (Man-hr/m2) 0.8203
AVERAGE PRODUCTIVITY (Man-hr/m2) 0.8447
-