productivity improvement through planning way_3_r

Upload: vangatramani-naren

Post on 07-Apr-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/4/2019 Productivity Improvement Through Planning Way_3_R

    1/26

    PRODUCTIVITY IMPROVEMENTTHROUGH PLANNING WAY

    By VENGAT and ANANTH

  • 8/4/2019 Productivity Improvement Through Planning Way_3_R

    2/26

    What is Productivity

    Productivity is factor ofOutput Vs Input

    Here Output is the ProducedMinutes

    Have we ever calculated how much sewing

    time we have wasted every day? And why?

    Industry Research says that 20% to 40% of

    sewing time is wasted without any work

  • 8/4/2019 Productivity Improvement Through Planning Way_3_R

    3/26

    Factors affecting Productivity

    Delay due to Style Approval, Missing Fabric, Accessories

    Waiting due to Cut parts, Prints, Embellishments.

    Shortage of some Specific Machine. Etc

    These problems are avoidable as thy are caused by Poor Planning.

    Inadequate communication.

    Focus on all Resources Utilization, to reduce idle time

    The resources are 3M- Men, Machine, Material

    To do that Plan in Better Way

  • 8/4/2019 Productivity Improvement Through Planning Way_3_R

    4/26

    Current Scenario

    Many of us have invested on latestCutting, Sewing, Pressing machines toincrease productivity, indeed that alone

    would not ensure the productivity. Many of us not yet optimized productivity

    because we are looking only HALF part

    of entire process.

    Sewing faster alone not going to

    increase productivity

  • 8/4/2019 Productivity Improvement Through Planning Way_3_R

    5/26

    How to Increase Productivity ?

    The Answer is to Ensure - Planning Process

    Master Production Schedule

    Action Plan

    Material Requirement Plan

    Monitoring and closely reviewing the Feed Back

    Method Engineering (see Example)

    Industrial Engineering Practice ( Separate Presentation)

    Standard Operating Procedures

  • 8/4/2019 Productivity Improvement Through Planning Way_3_R

    6/26

    Planning Process

    Critical path ( see detailed presentation)

    Approvals

    Fabric

    Accessories

    Mid Process ( Embroidery, Printing , etc)

    Production

    Shipment

  • 8/4/2019 Productivity Improvement Through Planning Way_3_R

    7/26

    Variables to Plan Effectively

    System in place

    Capacity

    Lead time

    Material availability

    Monitoring

    Current production progress against Plan

  • 8/4/2019 Productivity Improvement Through Planning Way_3_R

    8/26

    Results of Effective Planning

    Meet - Customer order due dates Maximize - Resource Utilization

    Minimize - Idle time, Overtime, Step delays,Lead/Queue time, time in the System and WIP

    Monitoring

    Historical Data - Man, Machine, Material

    Work Flow

    Material Flow

    Work Demand

    Quality

  • 8/4/2019 Productivity Improvement Through Planning Way_3_R

    9/26

    Examples Method Engg

  • 8/4/2019 Productivity Improvement Through Planning Way_3_R

    10/26

    Example - System

    Activity Responsible From To

    Order Enquiry Merchandising Buyer Marketing

    Vailability for Production Merchandising Marketing PDM

    Confirmation from Samling forViability

    PDM PDM IE

    Verification by IE IE IE Planning / Marketing

    Process Sequence PDM/IE/ Merc IE Planning

    Tentative Booking in Planning Planning Planning Marketing

    Order Confirmation Merchandising Marketing Planning

    Booking Confirmation Planning Planning Marketing

    Set of Instruction & Ownership

  • 8/4/2019 Productivity Improvement Through Planning Way_3_R

    11/26

    Cont

    Monitoring

    Planning

    Execution

    Analyzing

    Feed Back

  • 8/4/2019 Productivity Improvement Through Planning Way_3_R

    12/264/13/2012 12

  • 8/4/2019 Productivity Improvement Through Planning Way_3_R

    13/26

    Objectives of MPS

    Short range Planning Horizon

    Finished Product Schedule

    Efficient Utilization

    4/13/2012 13

  • 8/4/2019 Productivity Improvement Through Planning Way_3_R

    14/26

    The MPS System Structure

    4/13/2012 14

    Front End

    Engine

    Back End

    Long-term,High uncertainty

    Short-term,

    Low uncertainty

  • 8/4/2019 Productivity Improvement Through Planning Way_3_R

    15/26

    The MPS System: Front End

    4/13/2012 15

    Resource

    Planning

    Production

    Planning

    Demand

    Management

    MarketInternal & External

    Customers

    Master Production Scheduling (MPS)

    Engine

  • 8/4/2019 Productivity Improvement Through Planning Way_3_R

    16/26

    The MPS System: Engine

    4/13/2012 16

    Detailed Material Planning

    Time-Phased Requirement

    (MRP) Records

    Material & Capacity Plans

    Master Production

    Scheduling (MPS)

    Inventory

    Status

    Data

    Routing

    Order File

    BOM

  • 8/4/2019 Productivity Improvement Through Planning Way_3_R

    17/26

    MPS Techniques

    In response to seasonal sales a company may adopt:

    Level production MPS approach

    No hiring/firing of workers

    Buffering with inventory and backlog

    Chase production MPS approach

    Capacity adjustments from one period to another

    No inventory

    Hybrid strategy

    Uses elements of level and chase approaches

    4/13/2012 17

  • 8/4/2019 Productivity Improvement Through Planning Way_3_R

    18/26

    Conclusions

    The MPS System will be effective only if the TOPMANAGEMENTsATTITUIDE is right

    Common Systems facilitate effective scheduling in any

    business environment

    MPS should reflect the companys approach to the businessenvironment in which it operates

    Customer order promising should be closely linked to the

    MPS

    The MPS function should use the common MRP II, database

    Micro Planning has to derived from MPS

    Feedback System to be linked to Action Plan

    4/13/2012 18

  • 8/4/2019 Productivity Improvement Through Planning Way_3_R

    19/26

    The End

    4/13/2012 19

  • 8/4/2019 Productivity Improvement Through Planning Way_3_R

    20/26

  • 8/4/2019 Productivity Improvement Through Planning Way_3_R

    21/26

    Cont

    7. The master production scheduler must keep

    the sum of the parts (the MPS) equal to theoperations plan

    8. The MPS activity & the role of the masterproduction scheduler must be clearlydefined organizationally

    9. The MPS can be usefully considered as a setof firm planned orders

    10. The MPS should be evaluated with a formalperformance measurement system

    4/13/2012 21

  • 8/4/2019 Productivity Improvement Through Planning Way_3_R

    22/26

    Production Planning: Inputs

    A forecast of aggregate demand covering the

    selected planning horizon (6-18 months)

    The alternative means available to adjust short- tomedium-term capacity, to what extent each

    alternative could impact capacity and the relatedcosts

    The current status of the system in terms ofworkforce level, inventory level and production

    rate

    4/13/2012 22

  • 8/4/2019 Productivity Improvement Through Planning Way_3_R

    23/26

    Production Planning Output

    Fully load facilities and minimize overloadingand under loading

    Make sure enough capacity available to satisfy

    expected demand Plan for the orderly and systematic change of

    production capacity to meet the peaks andvalleys of expected customer demand

    Get the most output for the amount of resourcesavailable

    4/13/2012 23

  • 8/4/2019 Productivity Improvement Through Planning Way_3_R

    24/26

    Production Planning: Outputs

    A production plan: aggregate decisions foreach period in the planning horizon about workforce level

    inventory level

    production rate

    Projected costs if the production plan was

    implemented

    4/13/2012 24

  • 8/4/2019 Productivity Improvement Through Planning Way_3_R

    25/26

    Medium-Term Capacity

    Adjustments

    Workforce level adjustments Hire or layoff full-time workers

    Hire or layoff part-time workers

    Hire or layoff contract workers

    Utilizing existing work force Overtime

    Idle time (under time) Reduce hours worked

    4/13/2012 25

  • 8/4/2019 Productivity Improvement Through Planning Way_3_R

    26/26

    Medium-Term Capacity

    Adjustments

    Inventory level adjustments

    Finished goods inventory

    Backorders/lost sales

    Subcontracting

    4/13/2012 26