Production System Analysis & Italian Freight

Transport Companies

Page 2: Production System Analysis & Italian Transport Companies

Is it possible to use the method we use to analyze the production system for analyzing a transport company?

Page 3: Production System Analysis & Italian Transport Companies

Is it possible to assume a delivery good as a final Product (PF) of

Problem Tree?

Page 4: Production System Analysis & Italian Transport Companies

In addition, how about the Elementary Operations (EO),

Resources, Production Functions,

Agents, Information patterns

and Organizational Chart!

Page 5: Production System Analysis & Italian Transport Companies

I INVITE YOU TO VISIT: TRANSPORT AND LOGISTICS - BREAKING DOWN THE BARRIERS

Page 6: Production System Analysis & Italian Transport Companies

Assume that FP as satisfaction of client

by delivering good Pi to Ij

Page 7: Production System Analysis & Italian Transport Companies

OV

IVECO

dp

Page 8: Production System Analysis & Italian Transport Companies

The Problem Tree as a fundamental imagination

of what is happening in the production line

in our casefrom

NV = Non prepared vehicle

FP = Satisfaction of the client by delivering her goods Pi in Ij

Page 9: Production System Analysis & Italian Transport Companies

��

��

PF2 = Final unloading of goods

PF3 = Enter to the plant

��

�� � Doc. = Transport’s Documents has taken

� L = Goods has Loaded

FP = Satisfactory of client by delivering his goods Pi to Ij

GE = Goods has entered to Delivery Point

GA = Goods (vehicle) has arrived to the plant

PF5 = Driving

GA = Goods (vehicle) has exited from the plant

PF4 = Exit from the plant

PF6 = Documents has taken

PF1 = Loading operation

�� VA = Vehicle has arrived to the plant

�� VE = Vehicle has entered to client’s plant

PF3 = Enter to the plant

�� VX = Vehicle has exited from the plant

PF5 = Driving

��

VR = Vehicle is ready to start working

PF4 = Exit from the plant

NV = Non prepared vehicle for work

PF7 = Vehicle preparing

Sometime depends to

various situation,

here we will see a kind of

LOOP. Means that

vehicle have to exit of the

plant and enter in it

again. Maybe

because of different Point of

Loading or waiting for

receive Final Product that is not ready

yet etc.

Page 10: Production System Analysis & Italian Transport Companies

��

PF2 = Final unloading of goods

PF3 = Enter to the plant

��

�� � Doc. = Transport’s Documents has taken

� L = Goods has Loaded

FP = Satisfactory of client by delivering his goods Pi to Ij

GE = Goods has entered to Delivery Point

GA = Goods (vehicle) has arrived to the plant

PF5 = Driving

GA = Goods (vehicle) has exited from the plant

PF4 = Exit from the plant

PF6 = Documents has taken

PF1 = Loading operation

�� VA = Vehicle has arrived to the plant

�� VE = Vehicle has entered to client’s plant

PF3 = Enter to the plant

�� VX = Vehicle has exited from the plant

PF5 = Driving

VR = Vehicle is ready to start working

PF4 = Exit from the plant

NV = Non prepared vehicle for work

PF7 = Vehicle preparing

Sometime depends to

various situation,

here we will see a kind of

LOOP. Means that

vehicle have to exit of the

plant and enter in it

again. Maybe

because of different Point of

Loading or waiting for

receive Final Product that is not ready

yet etc.

Page 11: Production System Analysis & Italian Transport Companies

The table of Production functions

N Production Functions

1 Loading

2 Unloading

3 Entering to the plant

4 Exiting from the plant

5 Driving

6 Tack/release Documents

7 Preparing Vehicle

8 Control

9 PAC

Page 12: Production System Analysis & Italian Transport Companies

++PF7 PF4

PF4

PF5

PF5

PF3

PF3

PF1

PF6

PF2

Note that these functions are an

external resources.

PF

Page 13: Production System Analysis & Italian Transport Companies

The table of Resources

Resources Tasks

R1 Forklift

R2 Van

R3 Truck

R4 Trailer

R5 Trailer Trainer

R6 Drive

Page 14: Production System Analysis & Italian Transport Companies

The Graphical Table of Resources

R1 R2 R3 R4 R5 R6

Page 15: Production System Analysis & Italian Transport Companies
Page 16: Production System Analysis & Italian Transport Companies

The table of Agents

Agents Assigned production Functions Type Responsibility

onSubordinated

to

DM1 Loading&Unloading LO Storehouse STAFF

DM2 Driver LO Transport STAFF

DM3 Logistics Sub-Control LO Logistic Activities STAFF

DM4 Logistics Control STAFF P. Activity of System PAC

DM5 Company (Transport) Activity Control PAC System ——

Page 17: Production System Analysis & Italian Transport Companies

“CHI COMANDA QUI” ?!!!

Page 18: Production System Analysis & Italian Transport Companies

CHI COMANDA QUI ?!!!

LA MAMMA !!!

Page 19: Production System Analysis & Italian Transport Companies

List of the steps to resolve 1st Exercise!

1. Read the Problem Tree carefully!2. Graph of Components (that represent the Elementary Operations)!3. The Table of Paths to find the number of PHASES!4. Represent the diagram of EO’s!5. Identify the Production Functions!6. Represent the Work Sequence!7. Graph of Production Functions!8. Table and Graph of Resources!9. Scheme of Layout, evaluation of DM’s and Critical Points!!10. Information Pattern and Organizational Chart

- Study the table of Agents- Represent the type of connections according to the table of Agents

��

��

PF2 = Final unloading of goods

PF3 = Enter to the plant

��

�� � Doc. = Transport’s Documents has taken

� L = Goods has Loaded

FP = Satisfactory of client by delivering his goods Pi to Ij

GE = Goods has entered to Delivery Point

GA = Goods (vehicle) has arrived to the plant

PF5 = Driving

GA = Goods (vehicle) has exited from the plant

PF4 = Exit from the plant

PF6 = Documents has taken

PF1 = Loading operation

�� VA = Vehicle has arrived to the plant

�� VE = Vehicle has entered to client’s plant

PF3 = Enter to the plant

�� VX = Vehicle has exited from the plant

PF5 = Driving

��

VR = Vehicle is ready to start working

PF4 = Exit from the plant

NV = Non prepared vehicle for work

PF7 = Vehicle preparing

Sometime depends to

various situation,

here we will see a kind of

LOOP. Means that

vehicle have to exit of the

plant and enter in it

again. Maybe

because of different Point of

Loading or waiting for

receive Final Product that is not ready

yet etc.

Page 20: Production System Analysis & Italian Transport Companies

Graph of Components

NV VR VX VA VE L DO EX GA GE PF12345678910

Page 21: Production System Analysis & Italian Transport Companies

Table of Paths

NV VR VX VA VE L DOC. EX GA GE PF

10 PHASES

Page 22: Production System Analysis & Italian Transport Companies

Elementary Operations (EO’s) & Phases

10987654321

1° 2° 3° 4° 5° 6° 7° 8° 9° 10°

Page 23: Production System Analysis & Italian Transport Companies

PF’s & EO’s

PF’s \ EO’s 1 2 3 4 5 6 7 8 9 10

1 1

2 1

3 1 1

4 1 1

5 1 1

6 1

7 1

8

9

Page 24: Production System Analysis & Italian Transport Companies

Functions & Phases

7

6

5

4

3

2

1

F’s/P’s 1° 2° 3° 4° 5° 6° 7° 8° 9° 10°

Page 25: Production System Analysis & Italian Transport Companies

Graph of Production Functions

PF7 PF4 PF5 PF3 PF1 PF6 PF4 PF5 PF3 PF2 PFGEGAEXDOCLVEVAVXVRNV

Page 26: Production System Analysis & Italian Transport Companies

Graph of Resources

R’s \ PF’s 1 2 3 4 5 6 7 8 9

1 1 1

2

3

4 1

5 1

6 1 1 1 1 1

You see the mass traffic of production functions behind the Resource 6

Page 27: Production System Analysis & Italian Transport Companies

Do you remember who was responsible of 6th resource?

This means that the qualification of this resource is very important. So the manager or the controller should collaborate with the driver,

because efficiency and performance of this resource could seriously effect on the production line of transport & logistic system.

Page 28: Production System Analysis & Italian Transport Companies

Finally

we arrived to the destination!

The Work sequence

and

the layout of the system

Page 29: Production System Analysis & Italian Transport Companies

PF 1 PF 2

DM5

DM4

DM3

DM2 DM1

PF 7 PF 4

PF 5PF 3 PF 6

PF 4 PF 5

PF 3

R6R6

THEOF THERESOURCES (PRODUCT FUNCTIONS (AND DECISION MAKERS (

Page 30: Production System Analysis & Italian Transport Companies

DM4

DM3 DM2

DM1

DM5

Information Pattern

Page 31: Production System Analysis & Italian Transport Companies

PAC

STAFF LO

LO LO LO LO

Organization ChartLA MAMMA !!!

Page 32: Production System Analysis & Italian Transport Companies

KPI ?!!

MSWhat can not be measured CAN NOT be represent!

Page 33: Production System Analysis & Italian Transport Companies

SOME CONSTRAINTS ABOUT HOURS OF WORKS AND DRIVE

• Total Daily hour of driving ⥴ 9 hours (2 times 10 h)

• Total Daily hour of all kind of work ⥴ 15 hours

• Total Weekly hour of working ⥴ 56 hours

• Total hour of work in two weeks ⥴ 90 hours

Page 34: Production System Analysis & Italian Transport Companies

• Obligated daily hours of rest ⥲ 11 hours - max 3 times per week ( 9 + 3)

• Obligated daily break time ⥲ 45 min - after 4.5 hours of driving

• Obligated weekly hours of rest ⥲ 45 hours - once minimum 24 hours

SOME CONSTRAINTS ABOUT HOURS OF RESTING

Page 35: Production System Analysis & Italian Transport Companies

HOW HOURS OF DRIVING AND WORKING COULD BE MEASURED ?!

Page 36: Production System Analysis & Italian Transport Companies

• Analog

• Digital

CRONOTACHIGRAFO

Page 37: Production System Analysis & Italian Transport Companies

• Analog • Setup time

++

• S ij ≠ S ji

PF7

Page 38: Production System Analysis & Italian Transport Companies

• Digital • Setup time •S ij = S ji

Page 39: Production System Analysis & Italian Transport Companies

SOME CONSTRAINTS ABOUT TRAFFIC

• Max speed in city center 50 km/h BUT most of the time maximum 30 km/h

• Max speed in regional ways 70 km/h

• Max speed in highways 80 km/h

Page 40: Production System Analysis & Italian Transport Companies

• In addition, many specific traffic signs such as:

Page 41: Production System Analysis & Italian Transport Companies

CONSTRAINTS ABOUT WEIGHT AND DIMENSION

MAXIMUM TOTAL WEIGHT

40 TONS

40 = +14 26

“FQ” BATCH

Page 42: Production System Analysis & Italian Transport Companies

CONSTRAINTS ABOUT TRAFFIC POLICY AND CONTROL

Page 43: Production System Analysis & Italian Transport Companies

SOME OTHER CONSTRAINTS ABOUT GENRE AND KIND OF GOODS OR MATERIAL

Page 45: Production System Analysis & Italian Transport Companies

ADR

•S ij ≠ S ji

Page 46: Production System Analysis & Italian Transport Companies

KPI

MS

SO AFTER THAT SHORT INTRODUCTION ABOUT THE VARIES KIND OF CONSTRAINTS, THAT WE FACE THEM EVERY DAYS IN THE WORLD OF TRANSPORT & LOGISTICS LETS COME BACK AGAIN TO THE KPI CONCEPT:

7 th Scheduling problem,

Series Res.

Page 47: Production System Analysis & Italian Transport Companies

Statistic analysis based on calculating time to reach the customers, time to loading, necessary time to drive the distance between the customer and delivery point etc.

Page 48: Production System Analysis & Italian Transport Companies

MS & Standard Transport Time

Page 49: Production System Analysis & Italian Transport Companies

KPI = MS

4%10%

22%

23%

11%

24%

6%

Reach Customer Driving Wait for LoadingWait for Unloading L + tack doc. UL + tack doc.etc.

Page 50: Production System Analysis & Italian Transport Companies

KPI = Compare your system with Competitor

Page 51: Production System Analysis & Italian Transport Companies

Organized transport companies, those are familiar to benefit form modern navigating systems (Real-time Optimization System),

have a Core Transport Network and an efficient work sequence cycles.

Page 52: Production System Analysis & Italian Transport Companies