Product Case HistoryPROJECT DESCRIPTION:Somerset Hydro Electric Stationcontains 8 gates measuring 2.44x 3.66 wide, which facilitate thegeneration of 4 megawatts of powerfrom the Somerset Lake (133,000hectares).
The gates & tunnel were completedsome 15 years ago by Altex and weredue for a maintenance repaint.
All products and equipment had to bebrought in along the en-trance tunnel,which is only approx. 2m high x1.5mwide and some 150m long.
COATING SELECTIONEXPLANATION:SYSTEM:
Gates: 2 x full coats of Carboguard690, with all bolts being brush applied.
Tunnel: 7.0m section steel coated withCarboguard 690
EXPOSURE:
One side of the gates immersed whenthe gates are closed. When the gatesare opened, the tunnel is immersed.
www.carboline.com December 2019
Somerset Dam - Sluice GatesLOCATION: Queensland, Australia
DATE OF APPLICATION: June 2017
MARKET: Water & Wastewater
PROJECT SIZE: 0 Square Meters
AREA COATED: Sluice Gates
SUBSTRATE: Steel
SURFACE PREP: SSPC-SP 10 (Near White Blast)
PRODUCTS: Carboguard 690
Somerset Dam - Sluice Gates
www.carboline.com December 2019
AREA COATED: Tunnel
SUBSTRATE: Steel
SURFACE PREP: SSPC-SP 10 (Near White Blast)
PRODUCTS: Carboguard 690
Somerset Dam - Sluice Gates
www.carboline.com December 2019
ADDITIONAL PHOTOS: