procurement quality-management pjm400 mod2
TRANSCRIPT
![Page 1: Procurement quality-management PJM400 Mod2](https://reader034.vdocuments.mx/reader034/viewer/2022051515/557e7d06d8b42a03668b548f/html5/thumbnails/1.jpg)
1
Module 2Ken Hogan
Procurement Process In Construction Industrial Project
![Page 2: Procurement quality-management PJM400 Mod2](https://reader034.vdocuments.mx/reader034/viewer/2022051515/557e7d06d8b42a03668b548f/html5/thumbnails/2.jpg)
1. Definition 2. Objective 3. Procurement process 4. Performance indictor 5. Improvement 6. Benefits 7. Conclusion
2
![Page 3: Procurement quality-management PJM400 Mod2](https://reader034.vdocuments.mx/reader034/viewer/2022051515/557e7d06d8b42a03668b548f/html5/thumbnails/3.jpg)
Definition It is the process required to supply equipment , material , service and other resources needed to carry out a project that satisfy customer
3
![Page 4: Procurement quality-management PJM400 Mod2](https://reader034.vdocuments.mx/reader034/viewer/2022051515/557e7d06d8b42a03668b548f/html5/thumbnails/4.jpg)
Item Description Weight
1 Engineering 5%
22 Equipment / Material Equipment / Material 65%65%
33 Construction Construction 15%15%
4 Testing and Commissioning 10%
4
![Page 5: Procurement quality-management PJM400 Mod2](https://reader034.vdocuments.mx/reader034/viewer/2022051515/557e7d06d8b42a03668b548f/html5/thumbnails/5.jpg)
1-Setting procurement process requires to supply equipment , materials and other resources to carry out in constructing industrial project right the first time right the first time and every time.and every time.
2- Monitoring performance indictor to help
manager to prevent and reduce problem that can affect the procurement process.
5
![Page 6: Procurement quality-management PJM400 Mod2](https://reader034.vdocuments.mx/reader034/viewer/2022051515/557e7d06d8b42a03668b548f/html5/thumbnails/6.jpg)
1. Planning2. Documentation3. Product Evaluation4. Awarded 5. Administration 6. Inspection7. Delivery
6
![Page 7: Procurement quality-management PJM400 Mod2](https://reader034.vdocuments.mx/reader034/viewer/2022051515/557e7d06d8b42a03668b548f/html5/thumbnails/7.jpg)
7
Documentation
Product Evaluation
Awarded
Begin
Delivery
Planning
Inspection
![Page 8: Procurement quality-management PJM400 Mod2](https://reader034.vdocuments.mx/reader034/viewer/2022051515/557e7d06d8b42a03668b548f/html5/thumbnails/8.jpg)
Input 1. Scope of work2. Specification and drawings 3. Company resource4. Signature mandate 5. Product estimated value
8
![Page 9: Procurement quality-management PJM400 Mod2](https://reader034.vdocuments.mx/reader034/viewer/2022051515/557e7d06d8b42a03668b548f/html5/thumbnails/9.jpg)
Output1. Product list 2. Product supplier list3. Type of procurement contract
1. Sole source2. Single source3. Competitive bids
4. Estimated product value5. Approval to proceed with procurement
9
![Page 10: Procurement quality-management PJM400 Mod2](https://reader034.vdocuments.mx/reader034/viewer/2022051515/557e7d06d8b42a03668b548f/html5/thumbnails/10.jpg)
Tender documents Standardized forms
Inquiry Invitation letter Purchase order General terms and condition Filing system
10
![Page 11: Procurement quality-management PJM400 Mod2](https://reader034.vdocuments.mx/reader034/viewer/2022051515/557e7d06d8b42a03668b548f/html5/thumbnails/11.jpg)
1. Price 2. Delivery time3. Financial capability of supplier 4. Type of product 5. Historical of supplier6. Supplier approaches 7. Workload existing and anticipated 8. Customer feedback
Reference Approval
11
![Page 12: Procurement quality-management PJM400 Mod2](https://reader034.vdocuments.mx/reader034/viewer/2022051515/557e7d06d8b42a03668b548f/html5/thumbnails/12.jpg)
1. Notify successful tender and unsuccessfully tender of outcome
2. Compile contract documents3. Formally accepted tender offer
12
![Page 13: Procurement quality-management PJM400 Mod2](https://reader034.vdocuments.mx/reader034/viewer/2022051515/557e7d06d8b42a03668b548f/html5/thumbnails/13.jpg)
Monitor supplier progress Inspection Shipment and delivery Payment Check compliance with quality
13
![Page 14: Procurement quality-management PJM400 Mod2](https://reader034.vdocuments.mx/reader034/viewer/2022051515/557e7d06d8b42a03668b548f/html5/thumbnails/14.jpg)
1. Cycle times The different activities within PP
2. Milestone events Issuing R.Q - PO Approval of drawings Inspection Customs clearance Delivery
3. Management Project police Project Organization
14
![Page 15: Procurement quality-management PJM400 Mod2](https://reader034.vdocuments.mx/reader034/viewer/2022051515/557e7d06d8b42a03668b548f/html5/thumbnails/15.jpg)
4. Cost Indicator No of days in warehouse No of days in customs No of days correction / repair No of changes to air transportation Time from arrival till installation
5. Referential values Amount of PO No and amount of change orders Delivery / invoicing
15
![Page 16: Procurement quality-management PJM400 Mod2](https://reader034.vdocuments.mx/reader034/viewer/2022051515/557e7d06d8b42a03668b548f/html5/thumbnails/16.jpg)
16
![Page 17: Procurement quality-management PJM400 Mod2](https://reader034.vdocuments.mx/reader034/viewer/2022051515/557e7d06d8b42a03668b548f/html5/thumbnails/17.jpg)
1. Shortage of materials2. Out of specification 3. Incomplete delivery 4. Excess of materials 5. Damage and defective
17
![Page 18: Procurement quality-management PJM400 Mod2](https://reader034.vdocuments.mx/reader034/viewer/2022051515/557e7d06d8b42a03668b548f/html5/thumbnails/18.jpg)
18
![Page 19: Procurement quality-management PJM400 Mod2](https://reader034.vdocuments.mx/reader034/viewer/2022051515/557e7d06d8b42a03668b548f/html5/thumbnails/19.jpg)
Whether the procurement satisfied the stated objective
Whether needs and expectation have be meets
Whether the procurement process should be improve
How external factors such regulation , standard component have change
Whether the process improve cost saving
19
![Page 20: Procurement quality-management PJM400 Mod2](https://reader034.vdocuments.mx/reader034/viewer/2022051515/557e7d06d8b42a03668b548f/html5/thumbnails/20.jpg)
Review of performance indicator Review non conformity report Effect analysis regarding delays Costs and time cycles
20
![Page 21: Procurement quality-management PJM400 Mod2](https://reader034.vdocuments.mx/reader034/viewer/2022051515/557e7d06d8b42a03668b548f/html5/thumbnails/21.jpg)
21
![Page 22: Procurement quality-management PJM400 Mod2](https://reader034.vdocuments.mx/reader034/viewer/2022051515/557e7d06d8b42a03668b548f/html5/thumbnails/22.jpg)
1. Improve company and project reputation name 2. Achieving customer satisfaction and increase
market share 3. Reduce rework and mistake 4. Standardized forms 5. Reduce warranty period 6. Increase profit7. Lower insurance cost8. Improve cash follow
22
![Page 23: Procurement quality-management PJM400 Mod2](https://reader034.vdocuments.mx/reader034/viewer/2022051515/557e7d06d8b42a03668b548f/html5/thumbnails/23.jpg)
The problem present on procurement are of different types and origins. The most detected problem :
Planning Delay on issuing specification for quotation Delay on informing supplier
Supplier To many obstacles and clauses delay
negotiations Poor explanation about items Later purchase makes system expensive , air
freight and urgent
23
![Page 24: Procurement quality-management PJM400 Mod2](https://reader034.vdocuments.mx/reader034/viewer/2022051515/557e7d06d8b42a03668b548f/html5/thumbnails/24.jpg)
1. Delay at delivery2. Delay on ordering3. Delay on engineering drawings ( errors) 4. Repair and replacement at job site 5. Poorly planned inspection6. Lack of information on site about arrival for some supplier 7. Changes to air transportation to make faster delivery
Using PP indicator and periodical report is tools to monitor and prevent delays
Using IT ( email , scheduling etc ) will help in reducing delay and closely monitor the product progress for necessary action .