prioritetna metoda primer

2
Prioritetna metoda Aktivnost Prethodna aktivnost Tip veze Trajanje t j (dan) A / / 4 B A PP2 2 C B KP 4 D B KP2 12 E D PP2 14 F E KP 4 G F PP2 10 H G PP4 12 I H PP2 4 J C KP10 2 K I,J KP,KP 2 L K KP 4 M K KP2 4 N L KP 2 O M PP2 6 P O KP2 2 R N KP 8 S P,R PP,PP 2 T S KP 6 U T KP 2

Upload: evilbelgrade

Post on 07-Sep-2015

2 views

Category:

Documents


0 download

DESCRIPTION

fon

TRANSCRIPT

  • Prioritetna metoda

    Aktivnost Prethodna aktivnost Tip veze

    Trajanje tj (dan)

    A / / 4 B A PP2 2 C B KP 4 D B KP2 12 E D PP2 14 F E KP 4 G F PP2 10 H G PP4 12 I H PP2 4 J C KP10 2 K I,J KP,KP 2 L K KP 4 M K KP2 4 N L KP 2 O M PP2 6 P O KP2 2 R N KP 8 S P,R PP,PP 2 T S KP 6 U T KP 2

  • Kritian put : A-B-D-E-F-G-H-I-K-M-O-P-S-T-U Trajanje projekta : 58 dana

    Sc= 14 Sj = 14 Sl = 6 Sn = 6 Sr = 6