Enterprise Asset Management(eAM) – Preventive Maintenance
An Oracle White Paper December 2005
ii
eAM – Preventive Maintenance
EXECUTIVE SUMMARY ................................................................................................ 1 INTRODUCTION.............................................................................................................. 1 DESCRIPTION OF THE INITIAL SETUP ................................................................ 2 SET NAME........................................................................................................................... 2 METER .................................................................................................................................. 3 LAST SERVICE INFORMATION................................................................................. 4 PREVENTIVE MAINTENACE SCHEDULE............................................................ 5 Day Interval Rules............................................................................................................ 6 Scheduling Options.......................................................................................................... 6 Start to Start .................................................................................................................. 6 Forecast Work Order ............................................................................................. 6
Start to End................................................................................................................... 8 End to Start................................................................................................................... 8 Lead Time In Days ................................................................................................. 9
End to End ................................................................................................................. 10 Reschedule Manual Work Orders ...................................................................... 10
Runtime Rules................................................................................................................. 12 No Meter Readings.................................................................................................... 14 Usage Rate Not Recalculated................................................................................... 14 Usage Rate Recalculated ........................................................................................... 15 Work Order Completion – Change in Last service Information ...................... 17 Meter Reading Reset.................................................................................................. 18 “Schedule Based On”................................................................................................ 19
List Dates......................................................................................................................... 21 Generate Preventive Maintenance Work Orders program................................. 21
SUPPRESSION.................................................................................................................. 22 Tolerance In Days .......................................................................................................... 25
PREVENTIVE MAINTENANCE TEMPLATE....................................................... 26 CONCLUSION.................................................................................................................. 26 APPENDIX A: LOG FILE CREATED BY THE “GENERATE PREVENTIVE MAINTENACE WORK ORDER” CONCURRENT REQUEST ........................ 27
1 –eAM – Preventive Maintenance
eAM – Preventive Maintenance
EXECUTIVE SUMMARY
Maintenance activities are carried out on the assets in an organization, the details of
which are captured through work orders. The work orders can be generated either
manually or automatically. Maintenance activities can be scheduled periodically
based on time interval or based on the readings of meters associated to the asset or
based on predefined calendar dates. Enterprise Asset Management makes periodic
scheduling possible through Preventive Maintenance.
INTRODUCTION
Enterprise Asset Management (eAM) enables users to optimally plan and schedule
maintenance activities with minimal disruption to an organization’s operations or
production. By effectively monitoring an asset’s operating condition, effective
preventive maintenance strategies can be implemented. Preventive maintenance
activities reduce the probability of failure or degradation of the assets’ physical
conditions. Preventive maintenance helps to establish a maintenance strategy that
ensures minimal downtime.
It is possible to forecast the frequency at which preventive maintenance should be
performed. The frequency is decided based on meter readings, runtime intervals or
calendar dates. Meters are entered to measure any maintained number that needs to
be measured and periodically serviced, based on the measurement.
Preventive Maintenance Schedules(PM schedules) are defined for asset -activity
combinations. Multiple schedules can be defined for experimenting with different
maintenance strategies (simulation and what-if scenarios) but it is the default
schedule which is used for generating work orders. The work orders are generated
from the PM schedules either by running the ‘Generate Preventive Maintenance
Work Orders’ concurrent program or from the ‘Forecast Work Orders’ form.
This paper covers the basic setup and functionality of preventive maintenance.
Runtime Rules, Day Interval rules and List dates are covered in this paper .
Readers with an understanding of basic concepts of enterprise Asset management would be in a position to appreciate the entire gamut of this paper.
Note: The paper has been written with Oracle Application Release 11.5.9 in mind
The screen shots indicated pertain to 11.5.9 only.
2 –eAM – Preventive Maintenance
DESCRIPTION OF THE INITIAL SETUP
The maintenance organization used in this paper is EM1. “Cabs” is the Asset group
defined. The Asset numbers under this asset group are CAB001 to CAB006. There
are two maintenance activities carried out on each of the above mentioned assets :
• Cab Maintenance – this activity involves all the maintenance activities
carried out on the cab
• Cab Engine Overhaul – this activity is carried out only on the cab’s engine.
The routing for both the activities are the same. The first operation involves
department “Contract”. This department has one resource “OSP Res” and the
usage defined for this resource is 12 hours . The second operation is done in “F-
Maint” department and uses resource “Cab-Mech” for 12 hours. The total
duration for completing the activity is 24 hours.
SEQ Department Resource Assigned units Usage UOM
10 Contract OSP Res 1 12 HR
20 F-Maint Cab-Mech 1 12 HR
The resources “OSP Res” and “Cab-Mech” are available 24 hours. The calendar for
the organization is defined as all seven days in the week as working days and does
not include any exceptions.
SET NAME
"Preventive Maintenance Set Name" gives users the option of creating multiple PM
schedules for one asset-activity association and provides ways of experimenting
with different maintenance strategies. A PM schedule for an Activity and a
Maintained Number or Maintained Group must uniquely belong to a Set Name.
Set names are defined in the "Set Name" window (Navigation : Preventive
Maintenance � Set Name Definition). The set names used in this paper are
“Cab_Main” and “Cab_Simulation”.
Some important points to note :
• “Main” is a seeded set
• PM schedule for the same Maintenance Number and activity combination
can be created across sets
• Each PM schedule will have a ‘set name’ field. It is a mandatory field
• Every PM set has an end date. Every PM schedule that belongs to the set
must have its effective-to date before the end date of the PM set.
• There can only be one default PM schedule per asset-activity association.
3 –eAM – Preventive Maintenance
Users will be able to set and unset a default PM schedule.
• Default PM schedules will be automatically picked up by the PM engine to
generate work orders.
• Non-default PM schedules will be mainly used for simulation and ‘What-If’
scenarios and they will never generate work orders
In the “Set Name” window, choose “Templates” to view or modify the PM schedule templates or choose “Schedules” to view or modify the PM schedules associated with the set name.
METER
Meters are associated with maintained numbers to measure a variable of the asset
or rebuildable item. Meters are entered to measure any Maintained Number that
needs to be measured and periodically serviced, based on the measurement.
Meters are defined using the meter definition screen.
• Enter a meter name ,description and a unit of measure (UOM) for the
meter. The meter defined here is OMCAB004_01 with a UOM of Hours.
• Choose whether the meter readings are ascending, descending or fluctuating.
• If the meter has to be used in scheduling, then mark the “Used In
Scheduling” check box. As soon as this is check marked, the “Rate (per
day)” and the “Number of Past Readings” fields are enabled.
• Enter the usage rate and the number of past readings (if “Used in
Scheduling” is marked) . The number of past readings designates how many
4 –eAM – Preventive Maintenance
readings prior the scheduler should go to for calculating the usage rate. If
there are an insufficient number of readings, then the usage rate defined
here is used. A usage rate of 20 and a number of past readings of 5 is
entered for the meter OMCAB004-01
• The initial meter reading and the effective dates are optional. For meter
OMCAB004-01 , an initial reading of 0 was entered on 15th Nov, 2004
The Meter defined can be associated with the asset number (Navigation : Meter �
Meter Association) . Meter OMCAB004-01 is associated with Asset number
CAB004.
Another way to define meters is through the Meter Template . In the Meter
Template definition, meter templates are associated with maintained groups .After
the association, whenever a new asset number is created under the maintained
group, a meter is created and attached to the new asset number automatically.
LAST SERVICE INFORMATION
The last service information captures details of the date and the reading when the
last maintenance activity is done on an asset.
Last service reading captures the meter reading when the activity was performed
most recently on the asset. The last service reading cannot be greater than the last
meter reading (in case of ascending meter) or less than the last meter reading (for
descending meters)
Similarly, last service date captures the date when the activity was performed most
recently on the asset . Last service start date captures the date when the activity
started and last service end date captures the date when the activity ended. Last
service start/end date serves as a starting point for rule based scheduling.
The last service information is usually updated from the work order completion. When a work order is completed, the last service start & end date will be updated with the work order’s actual start & end date and the last service meter readings will be entered. The last service information can be modified from the “Last Service Information” screen (Navigation : Preventive maintenance � Last Service Info)
5 –eAM – Preventive Maintenance
There is no meter associated with the asset number CAB001 so no meter details are seen in the screenshot provided above
PREVENTIVE MAINTENACE SCHEDULE
Preventive maintenance schedules are defined to create or forecast work orders
based on rules or based on a list of specific date. A preventive maintenance
schedule can be created on asset number –activity or asset route-activity
combination.
The PM schedule is defined in the “Preventive Maintenance (Schedule Definition)”
window ( Navigation : Preventive Maintenance � Schedule definition).
In the PM schedule definition window, enter the following details :
• Enter a unique “Schedule name”
• Choose the “Item type”. You could choose between Asset and rebuildable.
• Enter a valid set name. The set name must be defined in the “Set name”
definition window. Every Set Name has an end date. Every PM schedule
that belongs to the “Set Name” must have its effective-to date before the
end date of the PM Set Name.
• Select a “Maintained Number” . If the “Item Type” chosen is “Asset”, then
this field refers to the Asset number else it refers to the rebuildable number.
In the case of Non –serialized rebuildable item, then this field is not
required
• The maintained group is populated automatically as soon as a value is
entered for the maintained number field.
• Select the “Activity”. Only the activities associated with the asset number /
rebuildable is available in the list of values.
• Choose the Schedule type. The options available are “Rule Based” and “List
Dates”. The “Day Interval Rules” tab and the “Runtime Rules” tab are
enabled if you choose “Rule Based” schedule type . The “List dates” tab
becomes enabled when the schedule type chosen is “List dates”
• The Effective date defaults from the activity chosen. The “Effective from”
and “Effective To” dates can be updated
• Run to failure items are those whose items costs are cheaper than the
maintenance cost of the item. If the “Run To Failure” check box is selected,
the PM Scheduler will not automatically schedule the maintained number
and Activity association, however manual Work Orders can still be created.
• The “Default” check box, if marked, indicates that the PM schedule is the
default schedule for the maintained number–activity combination. Work
orders will be generated only based on the default PM schedules
6 –eAM – Preventive Maintenance
Day Interval Rules
The day interval rule specifies the time span in days, between the creation of each
work order . This is based on the last service information.
For information on the “last service start date & end date”, pls refer to the Last
Service Information described above
The above PM schedule will be used to explain the Scheduling options
Scheduling Options
The “Scheduling Options” controls the way the work order dates are calculated by
the PM scheduler. This decided whether forward scheduling or backward
scheduling must be used by the PM Process.
Start to Start
This is a Forward Scheduling Method. The PM scheduler uses the base point as the “Last Service START date” and calculates the START dates for the scheduled work orders.
Forecast Work Order
In the Maintenance Workbench (Navigation : Work Order planning � Maintenance Workbench), choose the Asset number CAB001. In the work order form, Press on the “Forecast Work” button to get the “Forecast Work Order” form. In the “Forecast Work Order” form :
• The Start date would default to current date
• Enter the cutoff date. The Cutoff Date decides the date till which you would
like the Work Orders to be created from the suggested dates.
7 –eAM – Preventive Maintenance
• The horizon is the difference between the start and cutoff date. If the
horizon is changed, then the cut off date gets recalculated
• Optionally enter a Set name. If a set name is entered then the “Simulate”
button gets enabled and the “Run” and “Implement” button grays out. On
the other hand if no set name is chosen, then the “Simulate” button is
grayed out and the “Run” and “Implement” buttons are enabled. . No PM
schedule will be picked up for the asset/activity association if there is no
simulation PM schedule with the set name existing.
• When ‘Combine with Default’ is checked, the default PM schedules gets
picked up in the cases where no PM schedules with the specified set name
exist. When ‘Combine with Default’ is not checked, only PM schedules with
the set name specified will be picked up by the PM engine.
For the asset CAB001 (schedule attached to this asset number is CAB001_CM), when the “Forecast Work Order” is run from the Maintenance Workbench, the following work orders are suggested .
The last service start date was 24th Nov, 2004. With a day interval of 30, the first
work order’s START date is suggested on 24th Dec, 2004 and the consecutive work
orders are created with a difference of 30 days.
The “Implement” button could be chosen to convert the forecasted schedules into work orders. Implementing the third line in the above schedule, would create work order with the start date as 22-Feb-2005 and completion date as 23-Feb-2005.
8 –eAM – Preventive Maintenance
Start to End
This is a Backward Scheduling Method. The base point here is the “Last Service
START date” and using the base point, the PM process calculates the END dates
for the scheduled work orders.
For the PM schedule, CAB001_CM, change the Scheduling option to Start to
End.. The screenshot below shows the forecasted schedule for the asset number
CAB001 for the “Start to End” option
The last service START date was 24th Nov, 2004. With a day interval of 30, the first
work order’s END date is suggested on 24th Dec, 2004 and the consecutive work
orders are created with a difference of 30 days.
Implementing the third line in the above schedule, would create work order with
the start date as 21-Feb-2005 and completion date as 22-Feb-2005.
End to Start
This is a forward scheduling method . Here the PM scheduler uses the last service
END date to calculate the START dates for the scheduled work orders.
Changed the Scheduling option to End to Start for the schedule CAB001_CM and
forecasted the work orders. The last service end date was 26th Nov, 2004. With a
day interval of 30, the first work order’s START date is suggested on 26-Dec-2004
and the consecutive work orders are created with a difference of 30 days. The
suggested work orders are shown in the next screen shot.
9 –eAM – Preventive Maintenance
Lead Time In Days
The Preventive Maintenance process suggests work orders to be created or
scheduled in the horizon between the forecast start date to the cut-off date
specified while running the process. Lead Time In Days specifies the work orders
for those extra days beyond the cut-off date mentioned. To illustrate this example,
for the schedule CAB001_CM, a value of 25 is entered against the “Lead Time In
Days” field.
The PM process was run with a cutoff date as 01st May, 2005. The lead time of 25 days was taken into the picture while running the PM process so a work order was also forecasted for 25th May 2005.
10 –eAM – Preventive Maintenance
End to End
The PM scheduler uses the base point as the “Last Service END date” and
calculates the END dates for the scheduled work orders. This is a Backward
Scheduling Method.
Note : The “Lead Time In Days” is set to zero for the following simulations
Reschedule Manual Work Orders
In the PM schedule, mark the “Reschedule Manual Work Orders” check box. If the
box is checked, the unreleased manual work orders will be taken into account
during PM rescheduling, else not. PM engine will not reschedule firmed or released
work orders.
Another change introduced in the PM schedule, CAM001_CM, is the Multiple
Rules defined for the day interval rule. The interval between the scheduled work
orders is 30 days between 24-Nov- 2004 and 28-Feb-2005 . From 01-Mar-2005 to
15-Aug-2005 , the day interval specified is 45 days.
The details of the 3 work orders already existing for the asset CAB001 is shown
below
Sl Work Order
Number
Scheduled Start date Scheduled
Completion date
Status
1 EM182073 14-Jan-2005 05:31:00 15-Jan-2005 05:31:00 Unreleased
2 EM182074 10-Feb-2005 13:17:00 11-Feb-2005 13:17:00 Unreleased
3 EM181973 23-Jun-2005 00:00:00 24-jun-2005 00:00:00 Released
11 –eAM – Preventive Maintenance
When the PM engine is run, the schedule shown below is proposed
Line 1, 2 ,4 and 5 in the above forecast corresponds to the interval rule of 30 days.
After 26th Mar, 2005, the interval rule of 45 days is added to get the next effective
date of 10th May ,2005. The next expected schedule must be with the schedule end
date of 24th Jun, 2005 but as there is already a work order on the 24th June, no work
order is suggested by the PM engine.
Also note that for the released work order EM181973, the action column contains
a value of “No Action”. For work order EM182073, the check box is marked
meaning that the work order will be rescheduled to the expected end date. For
12 –eAM – Preventive Maintenance
work order EM182074, the check box is not marked so the work order will not be
rescheduled.
Implementing the forecasted work orders would provide the following work orders
The work orders forecasted for this schedule is shown below
Runtime Rules
Runtime rules are based on meters. The interval between the work orders is
calculated based on the interval divided by the usage rate.
Ensure that the following setup is complete before defining a runtime PM schedule
• Activity Definition
• Maintained Number or maintained Group - Activity Association
• Meter Definition
• Meter/Asset Association
• Maintained Group (Non-Serialized Rebuildable) or Asset or Maintained
• Number/Activity Association
The Runtime rule will be explained using asset number CAB004. Meter
OMCAB004-01 is defined and attached to the asset CAB004 (refer Meter
definition explained before). Schedule CAB004_CM is defined for the asset
CAB004 as shown in the next screen shot:
13 –eAM – Preventive Maintenance
The interval defined for the meter OMCAB004-01 in schedule CAB004_CM is 300
KM. Usage rate defined for the meter is 20 KM
The last service information can be entered from the PM Schedule screen by
pressing on the “Last Service Info” button. The service start and end date is on
15th November , 2004 and the last service reading is 0 KM
14 –eAM – Preventive Maintenance
No Meter Readings
No meter readings are entered. When running the PM engine from the “Forecast
Work Order” screen, the following work orders are forecasted :
The usage rate is 20 KM and the interval is 300 Km so the work orders are
scheduled at a gap of 15 days. The current meter reading date is 15th Nov,2004 so
the first work order is created on 30th Nov, 2004 and thereafter a work order is
created every 15th day.
Usage Rate Not Recalculated
Meter readings are now entered in the meter reading screen(Meters � Meter
Reading). The reading history shows the following :
The number of past readings is 5 whereas only two entries have been made so the usage rate is 20 (defined in the meter definition form). The system uses the Life To Date meter reading to calculate the Usage Rate.
15 –eAM – Preventive Maintenance
The PM schedule forecasts the following schedules
The first Scheduled date is not 30th Nov, 2004 00:00:00 but it is 28th Nov, 2004
15:36:00. This is calculated using the following logic :
Current Meter reading = 67 Current Meter reading Date = 17-Nov-2004
For the PM Schedule,
Last Service Date = 15-Nov-2004 Target Meter Reading = 300
Due date for next service = Current Meter reading date + (target meter reading -
Current reading)/rate
= 17-Nov-2004 + (300 - 67)/20
= 17-Nov-2004 + 11.65 � 28-Nov-2004 15:36:00
The work orders after 28-Nov-2004 15:36:00 are spaced at an interval of 15 days
Usage Rate Recalculated
A few more meter readings are entered as shown below
16 –eAM – Preventive Maintenance
“The number of past readings” defined for the meter is 5. The number of readings available for the meter OMCAB004-01 is more than the required number so the usage rate is recalculated using the last 4 meter readings. The readings seen in the above screen shot is Life to date reading. The actual readings entered is given below
DATE Actual Value Life to date
15th Nov, 2004 0 0
16th Nov, 2004 35 35
17th Nov, 2004 32 67
18th Nov, 2004 33 100
19th Nov, 2004 30 130
20th Nov, 2004 25 155
The usage rate is calculated as the total of the meter readings value changes,
divided by the total of the meter reading date intervals
= (Total of meter Reading value changes)/ (Total of reading date intervals) = (155-35)/(20th Nov- 16th Nov) = 120/ 4 � 30
The first date is calculated using the logic :
Current Meter reading = 155 Current Meter reading Date = 20-Nov-2004
For the PM Schedule, Usage Rate = 30
Last Service Date = 15-Nov-2004 Target Meter Reading = 300
Due date for next service = Current Meter reading date + (target meter reading -
Current reading)/rate
= 20-Nov-2004 + (300 - 155)/30
= 20-Nov-2004 + 4.833 � 24-Nov-2004 20:00:00
The work orders after 20-Nov-2004 20:00:00 are spaced at an interval of 10 days
(interval/usage rate � 300/30). Now when the PM engine is run, the following
work orders are forecasted
17 –eAM – Preventive Maintenance
Work Order Completion – Change in Last service Information
A work order is created for asset CAB004 for activity cab maintenance. The
scheduled start date is 20-Nov-2004 00:00:00 and completion date is 21-Nov-2004
00:00:00. The work order was completed and the actual start and end dates of the
work orders are the same as the scheduled dates. While completing the work order ,
a meter reading of 179 was entered. The last service information of the CAB004-
cab maintenance is shown below :
One more reading is entered on the 22nd November ,2004. the meter readings
history is shown in the table below :
DATE Actual Value Life to date
15th Nov, 2004 0 0
16th Nov, 2004 35 35
17th Nov, 2004 32 67
18th Nov, 2004 33 100
19th Nov, 2004 30 130
20th Nov, 2004 25 155
21st Nov, 2004 24 179
22nd Nov, 2004 21 200
The usage rate now recalculates to 25 ( (200-100)/4 �25). When the work orders
are forecasted, the following schedule is proposed
18 –eAM – Preventive Maintenance
The logic behind this :
Current Meter reading = 200 Current Meter reading Date = 22-Nov-2004
Usage Rate = 25
For the PM Schedule, Last Service Date = 20-Nov-2004
Target Meter Reading = 479 (last service reading of 179 +interval of 300)
Due date for next service = Current Meter reading date + (target meter reading -
Current reading)/rate
= 22-Nov-2004 + (479 - 200)/25
= 22-Nov-2004 + 11.16 � 03-Dec-2004 03:50:24
The work orders after 03-Dec-2004 03:50:24 are spaced at an interval of 12 days
(interval/usage rate � 300/25)
Meter Reading Reset
The meter OMCAB001-04 is reset to zero on 24th Nov, 2004 00:00:00. The value
before Reset was 200. The forecasted orders are shown below :
19 –eAM – Preventive Maintenance
The usage rate remains at 25 and the logic of calculation remains the same as
shown under work order completion except that now the last meter reading is on
24th Nov, 2004 (for the work order completion calculation it was 22nd Nov, 2004)
so the first work order is suggested on 05th Dec, 2004 03:50:24.
Disabled meter readings are not considered by the PM schedule.
“Schedule Based On”
PM Schedule CAB005_CM will be used to understand the functionality of the
“schedule based on” option. The screenshot of the schedule definition is posted
below:
The schedule, CAB005_CM, is based on Runtime Rules and has two meters
OMCAB005-01 and OMCAB005-02 attached to it. The usage rate for meter
OMCAB005-01 is 25 KM /day and the interval defined for this meter is 100 KM.
The second meter OMCAB005-02 has a usage rate of 50 KMs and an interval of
250 KM.
Common information about meter OMCAB005-01 and OMCAB005-02 :
Number of past reading is 3. Last service start and end date is 30-Nov-2004 and the
last service reading is Zero.
20 –eAM – Preventive Maintenance
With a start date of 30-Nov-2004 and a cutoff date of 01st Jan, 2005, the work
orders created for meters independently are shown below.
OMCAB005-01
1 04th Dec, 2004
2 08th Dec, 2004
3 12th Dec, 2004
4 16th Dec, 2004
5 20th Dec, 2004
6 24th Dec, 2004
7 28h Dec, 2004
For OMCAB005-01, the work order will be scheduled every fourth day (interval = 100, usage rate =25) and for meter OMCAB005-02, work orders will be scheduled on every fifth day (interval =250, usage rate =50). When the “Schedule Based on” is set to “First Due Date”, then the due date is set to the due date of the first due date of all the rules. The work orders forecasted for CAB005_CM for the First due date option is shown below :
When the schedule based on is the “Last Due date” , then the due date is set to
the last due date of all rules. The scheduled work orders for schedule CAB005_CM
is shown in the next screenshot
OMCAB005-02
1 05h Dec, 2004
2 10th Dec, 2004
3 15th Dec, 2004
4 20th Dec, 2004
5 25th Dec, 2004
6 30th Dec, 2004
21 –eAM – Preventive Maintenance
List Dates
The list dates provides users the flexibility to define a PM schedule by listing all the
specific due dates on which the work orders should occur, instead of defining rules
in the PM schedule. The PM engine then generates work orders on these list dates.
List dates and day/runtime interval are mutually exclusive.
PM Schedule CAB003_CM is defined for asset CAB003. The Schedule type is List
dates and under the “List Dates” tab , the dates on which the work orders are
required are listed out.
Generate Preventive Maintenance Work Orders program
In the previous simulations, the “Forecast Work order” form was used to forecast
and implement the work orders. The advantage in the “Forecast Work order” form
is the possibility of viewing the scheduled orders before implementing them.
Another way to create work orders using the PM schedule is to launch the
“Generate Preventive Maintenance Work Orders” concurrent program (
Navigation : Preventive Maintenance � Generate Work orders). This program
considers only the Default PM schedule for generating the work orders and does
not consider any other PM schedule.
The mandatory parameter passed to this program is the cutoff date. Area, asset
Category, item type (Asset or Rebuildable), maintained group and Maintained
number are other filters that could be passed here.
22 –eAM – Preventive Maintenance
After the “Generate Preventive Maintenance Work Orders” concurrent request
completes, the “WIP Mass Load” program is launched to generate the work orders
forecast by the “Generate Preventive Maintenance Work Orders” request.
The work orders generated for the Asset CAB003 is shown below :
SUPPRESSION
Other Activities can be suppressed with the current Activity in the scheduling
definition. You can enter suppression activities for a Maintained Number/Activity
combination.
To illustrate this functionality, asset CAB006 and activities “Cab maintenance” and
“Cab Engine Overhaul” is used. Here the simulation set is “Cab_Simulation” and
the “Default” check box is not marked. The schedule definitions are shown below :
23 –eAM – Preventive Maintenance
Schedule CAB006_CS is defined for the CAB006- Cab maintenance combination.
The Day interval defined for this schedule is 5 days.
Schedule CAB006_CEO_CS is defined for the CAB006-Cab Engine Overhaul
combination. The Day interval defined for this schedule is 4 days.
24 –eAM – Preventive Maintenance
CASE I : No Suppression defined
When no suppression is defined, the work orders forecasted for the asset CAB006
are :
Cab maintenance Activity
Schedule Start Date
1 06-DEC-2004
2 11-DEC-2004
3 16-DEC-2004
4 21-DEC-2004
5 26-DEC-2004
CASE II: Suppression Defined
Suppression is defined to suppress “Cab Engine Overhaul” Activity by “Cab
maintenance” activity (Navigation : Preventive Maintenance �Suppression)
When the forecast Work order is run , the following work orders are forecasted:
Cab Engine Overhaul
Activity
Schedule Start Date
1 05-DEC-2004
2 09-DEC-2004
3 13-DEC-2004
4 17-DEC-2004
5 21-DEC-2004
6 25-DEC-2004
7 29-DEC-2004
Cab Engine Overhaul Activity
Schedule Start Date
1 05-DEC-2004
2 10-DEC-2004
3 15-DEC-2004
4 20-DEC-2004
5 25-DEC-2004
6 30-DEC-2004
Cab maintenance Activity
Schedule Start Date
1 06-DEC-2004
2 11-DEC-2004
3 16-DEC-2004
4 21-DEC-2004
5 26-DEC-2004
25 –eAM – Preventive Maintenance
The second work order forecasted under the “Cab Engine Overhaul” activity is on
10th Dec, 2004 and not on 9th December. This is because when a parent activity
suppresses a child activity, it means that the child activity will be performed when
the parent activity is done, i.e., the “cab Maintenance” activity performed on the
cab also includes “Cab engine Overhaul” activity.
Keeping the above in mind, the “Cab Engine Overhaul” activity is done on the 05th
Dec, 2004 but a “Cab Maintenance” activity is done on 6th Dec, 2004 which also
includes the “Cab Engine Overhaul” activity. The next work order for “Cab Engine
Overhaul” is scheduled 4 days from 06th Dec, 2004 , i.e., 10th Dec, 2004. The same
logic holds good for the other work orders forecasted under the “cab Engine
Overhaul” activity.
Tolerance In Days
“Tolerance In Days” is mentioned in the scheduling window to define the
minimum interval in days that suggested Work Orders’ dates are spaced from each
other.
The tolerance considers suppression.
CASE III: Suppression defined in Case II and a tolerance of 2 days set in CAB006_ CS schedule and null tolerance set in CAB006_CEO_CS schedule
When the work orders are forecasted, the suggested dates is the same as in Case II
CASE IV : Suppression defined as in Case II and a tolerance of null days set in CAB006_ CS schedule and 2 days tolerance set in CAB006_CEO_CS schedule
The work orders forecasted for this case is shown below
26 –eAM – Preventive Maintenance
Work orders forecasted for “Cab Maintenance” activity are
06 DEC-2004
11-DEC-2004
16-DEC-2004
21-DEC-2004
26-DEC-2004
Work order forecasted for “Cab Engine Overhaul” activity is
30-DEC-2004
No other work order is forecasted for “Cab Engine Overhaul” activity as work
orders exist for the parent activity ,“Cab Maintenance”
The CAB006_CS and the CAB006_CEO_CS schedules were set as default and the
“Generate Preventive Maintenance Work Orders” concurrent request was
submitted. The log file generated by the request is provided in Appendix A
PREVENTIVE MAINTENANCE TEMPLATE
The previous schedules were created individually using the “Preventive
Maintenance (Schedule Definition)” window. The other way to define schedule is
to use the “Preventive Maintenance (Template definition)” window. A PM
Template is a schedule, defined for a Maintained Group (Asset Group or
Rebuildable Item)/Activity association. When the PM template functionality is
used, a new PM Schedule is automatically created for a newly created Maintained
Number (asset or rebuildable) for the Maintained Group. All PM Template
attributes are copied over to the PM Schedule for the Instance.
The steps used to create the PM template are the same as mentioned under the PM
schedule definition.
CONCLUSION
This paper covers the setup and functionality of preventive maintenance using a
hypothetical business scenario and test cases. The work orders were forecasted or
created after ensuring that no work orders exist in the system for the asset-activity
combination for the forecasted period.
27 –eAM – Preventive Maintenance
APPENDIX A: LOG FILE CREATED BY THE “GENERATE PREVENTIVE
MAINTENACE WORK ORDER” CONCURRENT REQUEST
Parameters passed to “Generate Preventive Maintenance Work Orders” � Cut off
date : 31-Dec-2004, "Item Type" : Asset and "Maintained Number" : CAB006. Log
file generated is posted below:
+---------------------------------------------------------------------------+
Oracle Enterprise Asset Management: Version : 11.5.0 - Development
Copyright (c) 1979, 1999, Oracle Corporation. All rights reserved.
EAMPMSDU module: Generate Preventive Maintenance Work Orders
+---------------------------------------------------------------------------+
Current system time is 04-DEC-2004 09:36:44
+---------------------------------------------------------------------------+
**Starts**04-DEC-2004 09:36:45
**Ends**04-DEC-2004 09:36:50
Start of log messages from FND_FILE
+---------------------------------------------------------------------------+
Starting my log at Sat Dec 04 09:36:48 MST 2004
select msn.inventory_item_id, msn.serial_number
from mtl_serial_numbers msn, mtl_system_items msi
where msn.current_organization_id = msi.organization_id
and msn.inventory_item_id = msi.inventory_item_id
and msi.organization_id = ? and msi.eam_item_type = 1 and
msn.current_status != 4
and msn.maintainable_flag = 'Y' and msn.serial_number = ?
found a serial ...
&&&&&&&&&&&&&&&&&&&&&&&&&&&&
Initializing PMSchedule ...
&&&&&&&&&&&&&&&&&&&&&&&&&&&&
* The last service start and end dates are: 2004-12-01 00:00:00.0, 2004-12-
01 00:00:00.0
ruleType == PMConstants.DAY_INTERVAL_RULE
---- putting in the node: pm with id: 542---
&&&&&&&&&&&&&&&&&&&&&&&&&&&&
Initializing PMSchedule ...
28 –eAM – Preventive Maintenance
* The last service start and end dates are: 2004-12-01 00:00:00.0, 2004-12-
01 00:00:00.0
ruleType == PMConstants.DAY_INTERVAL_RULE
---- putting in the node: pm with id: 463---
--- This PM's parentPM's Suggestions: ---
* The Day interval is: 5.0
************************
* The dueDate is :2004-12-06 00:00:00.0
* The Day interval is: 5.0
************************
* The dueDate is :2004-12-11 00:00:00.0
* The Day interval is: 5.0
************************
* The dueDate is :2004-12-16 00:00:00.0
* The Day interval is: 5.0
************************
* The dueDate is :2004-12-21 00:00:00.0
* The Day interval is: 5.0
************************
* The dueDate is :2004-12-26 00:00:00.0
* The Day interval is: 5.0
************************
* The dueDate is :2004-12-31 00:00:00.0
******** PM Schedule Details ******************
PM: 463 association ID : 2636
leadTime : 0.0 reschedulingPoint : 1
nonScheduled : falseDay Interval Rule: Every [5.0]
********** Work Order Suggestions for PM 463**********
associationID: 2636
Create new work order
The timestamp is: 2004-12-06 00:00:00.0
associationID: 2636
Create new work order
The timestamp is: 2004-12-11 00:00:00.0
29 –eAM – Preventive Maintenance
associationID: 2636
Create new work order
The timestamp is: 2004-12-16 00:00:00.0
associationID: 2636
Create new work order
The timestamp is: 2004-12-21 00:00:00.0
associationID: 2636
Create new work order
The timestamp is: 2004-12-26 00:00:00.0
--- This PM's parentPM's Suggestions: ---
associationID: 2636
Create new work order
The timestamp is: 2004-12-06 00:00:00.0
associationID: 2636
Create new work order
The timestamp is: 2004-12-11 00:00:00.0
associationID: 2636
Create new work order
The timestamp is: 2004-12-16 00:00:00.0
associationID: 2636
Create new work order
The timestamp is: 2004-12-21 00:00:00.0
associationID: 2636
Create new work order
The timestamp is: 2004-12-26 00:00:00.0
--------------------------
* The Day interval is: 4.0
************************
30 –eAM – Preventive Maintenance
* The dueDate is :2004-12-05 00:00:00.0
* The Day interval is: 4.0
************************
* The dueDate is :2004-12-10 00:00:00.0
* The Day interval is: 4.0
************************
* The dueDate is :2004-12-15 00:00:00.0
* The Day interval is: 4.0
************************
* The dueDate is :2004-12-20 00:00:00.0
* The Day interval is: 4.0
************************
* The dueDate is :2004-12-25 00:00:00.0
* The Day interval is: 4.0
************************
* The dueDate is :2004-12-30 00:00:00.0
* The Day interval is: 4.0
************************
* The dueDate is :2005-01-03 00:00:00.0
******** PM Schedule Details ******************
PM: 542 association ID : 2635
leadTime : 0.0 reschedulingPoint : 1
nonScheduled : false Day Interval Rule: Every [4.0]
********** Work Order Suggestions for PM 542**********
PARENT's suggestion...
associationID: 2635
Create new work order
The timestamp is: 2004-12-06 00:00:00.0
PARENT's suggestion...
associationID: 2635
Create new work order
The timestamp is: 2004-12-11 00:00:00.0
PARENT's suggestion...
31 –eAM – Preventive Maintenance
associationID: 2635
Create new work order
The timestamp is: 2004-12-16 00:00:00.0
PARENT's suggestion...
associationID: 2635
Create new work order
The timestamp is: 2004-12-21 00:00:00.0
PARENT's suggestion...
associationID: 2635
Create new work order
The timestamp is: 2004-12-26 00:00:00.0
associationID: 2635
Create new work order
The timestamp is: 2004-12-30 00:00:00.0
Begin to try to reschedule existing work orders for PM 463
End of trying to reschedule existing work orders for PM 463
Begin to try to reschedule existing work orders for PM 542
End of trying to reschedule existing work orders for PM 542
+---------------------------------------------------------------------------+
End of log messages from FND_FILE
+---------------------------------------------------------------------------+
Executing request completion options...
Printing output file.
Request ID : 2540122
Number of copies : 0
Printer : noprint
Finished executing request completion options.
+---------------------------------------------------------------------------+
Concurrent request completed successfully
Current system time is 04-DEC-2004 09:36:50
+---------------------------------------------------------------------------+
Enterprise Asset Management (eAM) – Preventive Maintenance December 2005 Author: Arockiaraj Irudayasamy, Karthikeyan Balasubramaniam Co-Author : Vinay Srinath Contributing Authors: N/A Oracle Corporation World Headquarters 500 Oracle Parkway Redwood Shores, CA 94065 U.S.A. Worldwide Inquiries: Phone: +1.650.506.7000 Fax: +1.650.506.7200 www.oracle.com Oracle Corporation provides the software that powers the Internet. Oracle is a registered trademark of Oracle Corporation. Various product and service names referenced herein may be trademarks of Oracle Corporation. All other product and service names mentioned may be trademarks of their respective owners. Copyright © 2002 Oracle Corporation All rights reserved.