presentation plan introduction national electricity network review of electricity operations...
TRANSCRIPT
Presentation Plan
• INTRODUCTION
• NATIONAL ELECTRICITY NETWORK
• REVIEW OF ELECTRICITY OPERATIONS
• COMMERCIALISATION AND FINANCIAL SITUATION
•THE ROLE OF ELECTRICITY PREPAYMENT
Angolan Map
Introduction
Angola covers an area of 1,246,700 km2.
It borders the Republic of Congo and the DRC to the north, the DRC and Zambia to the east,
Namibia to the south and the Atlantic Ocean to the west.
Physiography varies from the lowland coastal areas, up to 300 m to an intermediate sub-
plateau zone and inland plateau with altitudes between 1,200 and 1,700m.
Cont.
Angolan population is estimated at 14 million inhabitants.
Social and economic conditions up to 2002 due to disruptions occurring during the transition period
from independence in 1975, followed by the implementation of inadequate macro-economic
policies.
This situation was aggravated by civil war, which resulted in a state of insecurity and destruction of
vital economic infrastructure.
Cont.
Cumulative inflation rate reached 1,838% in 1993, 3,784% in 1995 and 1,650% in 1996. Since 2003,
the social and economic situation has been improving slowly and a reduction of the inflation
rate to 34.01% was registered in 2004.
The electricity sector infrastructure is one of those that suffered the most from destruction during the
civil war.
Production and Transmission Rehabilitation Plan 1997
Uige
Luquixe
Hydro
GTG
G Diesel
Line 220kV
Line 100kVLine 60kV
Substation RT
Substationj.CH
Cabinda
Malongo
Cacongo
MabubasQuibaxe
Kifangondo
LuandaViana
Porto Amboim
Umbe
Gabela
Cambambe
N’Dalatando
Cacuso
Northern System
Malanje
Cunje
Kuito
CENTRAL SYSTEM
Production and Transmission Rehabilitation Plan 1997
Line 30kVG Diesel
Hydro
GTG
Line 150kV
Line 60kVSubstation RT
Substation CH
Baia farta
Chinguar
Benguela
Catumbela
Katchiungo
Quileva
Cavaco
Lobito
Huambo
Biópio (T)
Lomaum aaaumuum
A.Catumbela
Biópio (H)
Oral presentation layout
Substation H
.Hydro
.Hydraulic
Line 150KV
Line 60KV
Substation TGTG
G Diesel
Tchamutete
MatalaLubango
Namibe
Jamba
Tombwa
Saco
Gove
Production centres, such as hydro dams and thermal turbines, HV and MV transmission lines
and transformation points were partially or totally destroyed.
The Angolan Government is engaged in a large program of reconstruction and rehabilitation.
We believe that the large sums of money invested in reconstruction and rehabilitation should take advantage of the new, modern hi-tech options
Program of Reconstruction
National Electricity Network
About 93% of electricity production and consumption is from three independent systems:
● North System: 93%● Centre System: 5%● South System: 1.5%● Isolated Systems: 0.5%
Review of electricity operations
PRODUCTIONTotal installed capacity, including the Capanda
hydro plant, is 901.9 MW.
Only 69.2% (623.9 MW) is available.
Breakdown is:● 61.1% hydro (433.1 MW)● 38.9% thermal (190.85 MW)
Transmission/distribution
ENE has 2,118 km of transmission and distribution lines –53.1% (1124.65 km) available.
MV operating voltages are 6.3, 6.6, 15 kV.
More than 54% of substations need to be rehabilitated, expanded or modernised
Distribution network is almost 30 years old and no longer able to cope with increase in demand. Consequently the operation and distribution
charges are very high.
EDEL
EDEL receives power from ENE through the 60 kV HV network at the Cuca, Golf and Zango
substations.
EDEL has 6 substations with capacity 330 MVA.
EDEL’s primary network is a 15 kV MV and includes 20 distribution points. There are 837
transformation points, of which 440 are public and 397 private.
Line60kV(km)
15kV(km)
0.4kV(km)
Air 2 42
Underground 23 382.4
Total 25 424.4 2180
EDEL NETWORK EXTENSION
Highest peak reached by EDEL is 182 MW, registered 22 December 2003 at 20 hours.
Line extensions are as follows:
Failures
Year Failures of network
60kV 15kV 0.4kV Total
2001 7 289 2839 3135
2002 11 273 3763 4047
2003 13 245 3630 3888
Main causes of failure, especially LV, are● cables and equipment due to illegal, unauthorised connections● inadequate supply in high populated areas and newly emerging suburban zones
ACTIVITY 2002 2003 2004
Total power supply (GWh) 1781 1997 2243
Supply from NamPower 6.4 7.2 8.3
Total power billed (GWh) 1345.1 1541.9 1636
Power billed to EDEL (GWh) 919.89 978.9 1353
Power billed to EDEL/total (%) 68.39 63.49 82.7
Indices of Power billed/paid from EDEL (%) 33.7 21.8
Power billed to other clients(GWh) 425.2 563.04
Indices of billed /paid from others customers (%) 59.4 63.8
ENE has 110,801 customers (835 in Luanda).The situation was as follows:
Commercialisation and Financial Situation
ENE not able to bill all the power it produces - commercial losses were 38% in 2004.
Edel
EDEL covers 7 of 9 municipalities of Luanda – coverage about 9% of the settled area and 111,131 clients.
If the average family size is 6 and the total population of Luanda 4.5 million, then 15% of Luanda population are legally serviced by EDEL. The number of illegal connections is estimated at 40,000 to 50,000.
Commercial Situation 2004
Number of Customers112,378
Meters out of service 5,289
Customers without metering 33,865
Power received (GWh) 1,103.99
Power sales (GWh) 768.10
Commercial losses (GWh) 170.25
Rate of metering done (%) 55
Rate of estimated metering (%) 45
Installed pre-payment Meters 0
Nr.of main public institution Debtors 10
Total debt to EDEL (million USD) > 20
Customers satisfied 89,092
Unsatisfied customers 22,476
Commercial Situation 2004
It is obvious that EDEL has major difficulties in undertaking the metering of consumption.
Accumulated debt of EDEL to ENE up to 2004 is estimated at Kz5549 97 million
(USD61.6 million).
The Role of Electricity Prepayment
ENE has more than one reason to think of installing a prepaid metering system.
For ENE to become viable, the basic principle has to be institutionalised that:
Power supplied must be paid for.
EDEL must find ways to come up with the debt and ENE can assist by forcing EDEL through the
installation of prepayment meters in EDEL’s three reception substations.
Cont.
ENE could do the same for all the big consumers, i.e. factories, public illumination, etc., which are
directly supplied by ENE.
On the other hand, EDEL can’t become viable if it is unable to meter, bill and collect the money from
the consumers. The tariff is irrelevant if the payment issue is not solved.
Installing prepayment meters to all big consumers, both private and public, will assist with starting the
process.
Cont.
Up to now, there has been little incentive for ENE and EDEL to show interest in launching appropriate conservation initiatives. Given the normalisation of the political situation and the cut off of government subventions, ENE and EDEL will soon have to bring about effective billing and collection of electricity charges and later on the reduction of commercial losses.
Conclusion
Opting for prepayment metering will enable both ENE and EDEL to emerge from their unfavourable financial predicaments.
In addition prepayment metering will enable EDEL to bring about effective reduction of technical losses through modernisation of the distribution network.
Thank you
Questions?