presentation 1
DESCRIPTION
PROGRESS OF CIVIL & MECHANICAL PROJECTS OF C &ESSTRANSCRIPT
C&ESS DEPARTMENT CONTRACT WORKS EFP-I
S No Name of WorkEstimated
Cost
Press Advertisem
ent dateDate of
Opening
Work Done by PartiesTarget
Completion Date Present StatusAFE Cost Lowest Cost
1
CONSTRUCTION OF FOUNDATION FOR REBOILER, CONDENSATE POTS & SOFTENING UNITS AT UCH#II, Distt: DheraBugti.
1.773 Million
22.08.2013At 1130 hrs 30 days
Work executed departmentally.
Tender cancelled.
2
Construction of Pre-Drilling Engineering Works for Zin PAB-2 (Zin#06), Distt. Dera Bughti, Balochistan
51.738 Millions
27.10.2013 11.11.2013 90 Days
work is in progress.
3
CONSTRUCTION OF PRE DRILLING CIVIL WORK AT LOTI DEEP # 01. DISTRICT DERA BUGHTI, BALUCHISTAN.
59.624 Millions
04.02.2014 21.02.2014 90 days
LOI issued. Contract agreement execution stage
4
CONSTRUCTIONS OF PRE DRILLING CIVIL WORK AT WELL LOCATION ZIN SML #04. DISTRICT DERA BUGTI BALOCHISTAN
54.031 millions
31.05.2014 16.06.2014 60 days
After retender. Bid advertised & opened on 16.06.2014.
S No Name of WorkEstimate
d Cost
Press Advertise
ment date
Date of Opening
Work Done by Parties
Target Completion
Date Present StatusAFE CostLowest
Cost
5
CONSTRUCTIONS OF PRE DRILLING CIVIL WORK AT LOTI WELL #19. DISTRICT DERA BUGHTI, BALUCHISTAN.
41.798 millions 04.04.201421.04.2014 60 days
LOI issued on 03.06.2014 and contract agreement to be executed.
6
CONSTRUCTIONS OF PRE DRILLING CIVIL WORK AT WELL LOCATION PIRKO DEEP #01. DISTRICT DERA BUGTI BALOCHISTAN.
54.406 millions
28.04.14 60 days
LOI issued on 03.06.2014 and contract agreement to be executed.
7
CONSTRUCTIONS OF PRE DRILLING CIVIL WORK AT LOTI#20. DISTRICT DERA BUGT BALOCHISTAN
41.798 millions 31.05.201420.06.2014 60 days
After retender. Bid advertised & opened on 20.06.2014.
9
CONSTRUCTIONS OF PRE DRILLING CIVIL WORK AT WELL LOCATION PIRKO #54. DISTRICT DERA BUGTI BALOCHISTAN.
44.762 millions
23.4.14 7.5.2014 60 days
Press advertised on 23.04.2014.opened on 7.5.14 and is under management approval.
C&ESS DEPARTMENT CONTRACT WORKS EFP-II
S No Name of WorkEstimate
d Cost
Press Advertise
ment date
Date of Opening
Work Done by Parties Target
Completion Date Present StatusAFE Cost
Lowest Cost
1
Engineering works for Sohniwala Well # 1 at Tehsil Ahmedpur Distt. Jhang
Rs.16 million
23.03.2013
07.04.2013 30 day Completed
2
Construction of Metalled Road, Boundary Wall & cement Concrete Stone Paving-additional works for Annxe at Regional Office Multan, District:Muzzafar Gahr. 2.64 M
03.09.2013
2/10/2013 30 days
Work Completed.
3
CONSTRUCTION OF PRE DRILLING CIVIL WORK AT KUP-I (KULCHAS E.L).DISTT: DERA BUGTI BALOCHISTAN
55 Million
31.08.2013
16.09.2013 45 days
Work is in Progress.
Watch Towers, culverts and cause under
progress.
C&ESS DEPARTMENT CONTRACT WORKS EFP-III
S No Name of WorkEstimated
Cost
Press Advertisem
ent dateDate of Opening
Work Done by Parties Target
Completion Date Present StatusAFE Cost Lowest Cost
1
Engineering works for Jand well # 1 Distt. Attock
Rs.20 millions 24.03.2013 09.04.2013 28.05.2013 Completed
2
Construction Of One R.C.C Underground Water Reservior At Water Source Near Mela #1 Water Point.Distt:Kohat 3.742 M 21.08.2013
06-09-2013At 1130 hrs 90 days Completed.
3
Construction of Pre Drilling Engineering Works At Rajian-8 District Chakwal Punjab 27 M 15.07.2013 15.08.2013 45 days Completed.
4
Supply of Utility Water (170,000 liters per day) to Nashpa Oil Plant and Camps including Rig N-2 at Nashpa Field 14.10 M 27.07.2013 22.08.2013 365 days Work in progress
5
Construction of Pre Drilling Engineering Works AT NASHPA-5 District Karak KPK
Rs:116.65 millions
04.02.14 45 days Work in progress
S No Name of Work
Estimated Cost
Press Advertisement date
Date of Opening
Work Done by Parties
Target Completion
Date Present StatusAFE Cost Lowest Cost
6
Construction of internal road at chanda plant, Distt: Kohat KPK.
3.364 Millions
01.11.2013
18.11.2013 45 Days Work in progress
7
Modification in new store shed at Dakhni Plant Well.
1.948 Millions
02.09.2013
26-09-2013 60 days Completed
8
Construction of Engineering Works Required For Workover Job At Rajian#2 District.
20.193 Millions
03.09.2013 16.09.13 30 Days Completed.
9
CONSTRUCTION OF FOUNDATION FOR INSTALLATION OF WEIGH BRIDGE NASHPA OIL FIELD 0.931 M
30.08.2013
19.09.2013 45 days Completed.
10
REPAIR OF (0.8KMS) ROAD AT RATTA MOHRA RAJIAN OIL FIELD, DISTRICT CHAKWAL.
2.232 Million
14.12.2013
30.12.2013 45 days Work in progress
S No Name of Work
Estimated Cost
Press Advertisem
ent dateDate of Opening
Work Done by PartiesTarget
Completion Date Present StatusAFE Cost Lowest Cost
11
CONSTRACTION OF RCC WALL (LENGTH 816.RM) AT NASHPA PLANT. DISTT:KARAK
14.387 Million 23.11.2013
10.12.2013 60 days
60 % Completed. Suspended due to land problem
12
CONSTRACTION OFFOUNDATION FORINSTALLATION OF WEIGHBRIDGE AT RAJIAN OIL FIELD.DISTRICT ATTOCK.
1.5 MILLION 09.01.2014
27.01.2014 45 days 80 % Completed.
13
CONSTRUCTION OF DYKE WALL AND P. C.C HARD STANDING FOR MELA CRUDE STORAGE TANK DISST:KOHAT, KPK.
1.854 Million 13.11.2013
28.11.2013 45 days
Work completed. Final bill payment is under process.
14
Construction of Engineering Works Required For Workover Job At Mela#1 District.Kohat KPK
25 Million 05.12.2013
21.12.2013 30 days
Well started flowing and tender was
annulled after approval for
award of work.
15
Construction of Permanent Wire Woven Mesh Fencing at Nashpa#1 Well.Distt:Karak
2.18 Million 22.3.2014
07.04.2014 30 days
Work order issued on
15.05.14. work in progress.
S No Name of Work
Estimated Cost
Press Advertisement date
Date of Opening
Work Done by PartiesTarget
Completion Date Present StatusAFE Cost Lowest Cost
16
Construction of Permanent Wire Woven Mesh Fencing at Nashpa #4 Well.Distt:Karak
2.62Million 22.03.20
1407.04.2014 30 days
Work order issued on 15.05.14. work in
progress.
17
CONSTRUCTION OF ENGINEERING WORKS REQUIRED FOR WORKOVER JOB AT CHAK NAURANG SOUTH # 1.DISTRICT CHAKWAL
12.23 Million
11.01.2014
23.01.2013 30 days Completed.
18
CONSTRUCTION OF UNDER GROUND WATER STORAGE TANK AT CHANDA PLANT DISST:KOHAT, KPK.
6.988 Million
09.01.2014
28.01.2014 45 days
Tender will be opened on 25-05-2014 at EFP-III. Under management approval.
19
Construction of Pre Drilling Engineering Works at Nashpa -6 District: karak, KPK
Rs:30.12
millions 30 DAYS
Case for contractor scope of work is being initiated for press advertisement from management.
S No Name of Work
Estimated Cost
Press Advertisemen
t dateDate of Opening
Work Done by Parties
Target Completion
Date Present StatusAFE CostLowest
Cost
20
HIRING OF DOZERS (D-8K/D-8N/KOMATTSU 155, MODEL 2000 & ABOVE) FOR NASHPA-6 WELL, DISTRICT KARAK, KPK.
Rs: 2.00 million 3 months
Case approved by management and LOI to be issued.
21
CONSTRUCTIONS OF PRE DRILLING CIVIL WORK AT DAKHNI DEEP WELL NO. 5 DISTRICT ATTOCK.
40.00 millions 03.04.2014 18.04.2014 45 days
Work order issued on 25.05.2014. problem in land acquisition.
22
CONSTRUCTION OF R.C.C HARD STANDING FOR INSTALLATION OF 20000 BPD CAPACITY NEW SEPARATION BATTERY AT NASHPA District: Karak, KPK
Rs:2.855 millions
05.04.2014 24.04.2014 45 days
Work order issued on _______ and work is under progress.
C&ESS DEPARTMENT CONTRACT WORKS EFP-IV
S No Name of WorkEstimated
Cost
Press Advertise
ment date
Date of Opening
Work Done by Parties Target
Completion Date Present StatusAFE Cost
Lowest Cost
1
Engineering works for Qadirpur HRL well # 7 Distt. Ghotki Sindh
Rs.18.00 millions
02.04.2013
18.04.2013
240 days after award Completed
2
Engineering works for Maru East Well # 1 at Distt. Ghotki Sindh
Rs.36.31 millions
30.04.2013
15.05.2013
45 days after award Completed.
3
Engineering works for Qadirpur Well # 50 at Distt. Ghotki Sindh
Rs.34.66 millions
05.06.2013
20.06.2013 30 days Completed
4
Construction of Pre-Drilling Engineering Works at QP-51 District Ghotki, Sindh. 30 Millions
07.09.2013
30.09.2013 30 days Completed
5
Construction of Pre-Drilling Engineering Works at HRL #08 District Ghotki, Sindh. 25 Millions
27.10.2013
12.11.2013 30 days Completed
S No Name of Work
Estimated Cost
Press Advertisem
ent date
Work Done by Parties
Date of Opening
Target Completio
n Date Present StatusAFE Cost Lowest Cost
6
Construction of Pre-Drilling Engineering Works at QP-52 District Ghotki, Sindh.
35.693 Millions 07.09.2013 07.10.2013 30 days Completed.
7
CONSTRUCTION OF CIVIL SYSTEM AT ERW PLATFORM (QP-42,43,44) FOR SCADA SYSTEM. DISTRICT GHOTKI, SINDH.
1.645 Million
17.11.2013 04.12.2013 30 days Completed
8
Construction of Pre Drilling Engineering Works at Well Location Sara West Well # 05.District Ghotk
Rs.63.153 millions
60 days
bids will be opened on 13.06.2014 agaist retendering.
9
Construction of Pre Drilling Engineering Works at Well Location, Reti # 02. District Ghotki.
Rs.42.44 millions
08.03.2014 26.03.2014 45 daysLOI issued on 30.05.14.
10 Construction of Pre Drilling Engineering Works at Qdir Pur Well # 53.. District Ghotki.
Rs.25.727 millions
03.04.2014 21.04.2014 30 days
Work order issued on 30.05.2014 and work in progress.
11
REPAIR / MAINTENANCE OF QADIRPUR INTERNAL ROAD.DISTRICT : GHOTKI, SINDH
Rs 14.231millions
24.05.2014 09.06.2014 90 DAYS
case sent on 10.06.2014 for management approval by EFP-IV.
C&ESS DEPARTMENT CONTRACT WORKS EFP-V
S No Name of WorkEstimated
Cost
Press Advertisem
ent dateDate of Opening
Work Done by Parties Target
Completion Date Present StatusAFE Cost Lowest Cost
1
Engineering works for Jakhro West Well # 1 at Distt. Sanghar Sindh
Rs.25.00 millions 20.04.2013
06.05.2013 120 days Completed
2
CONSTRUCTION OF PRE DRILLING CIVIL WORKS AT WELL KUNNAR DEEP#09.Distt: Hyderabad. 23.00 M 24.07.2013
13.08.2013 45 days Complted.
3
CONSTRUCTION OF PRE DRILLING CIVIL WORK AT WELL CHAK DIM5#3. 32.00 M 24.07.2013
13.08.2013 30 days Completed
4
Construction of Pre Drilling Engineering Works AT CHAK 25C-1, District Sanghar, Sindh. 32 Millions 13.08.2013
30.08.2013 30 Days Completed
5
Construction of Pre-Drilling Engineering works at Manna-1 (Tay X-2), Distt. Hyderabad, Sindh. 24 Millions 29.08.2013
13.09.2013 45 Days Completed
S No Name of WorkEstimated
Cost
Press Advertisem
ent dateDate of Opening
Work Done By PartiesTarget
Completion Date Present StatusAFE Cost
Lowest Cost
6
CONSTRUTION OF 550RFT LONG RCC SLUB CULVERT OVER BOBI & SINJORO PLANTS PIPE LINES DISTRICT SANGHAR SINDH.
3.645 Million 45 Days
Tender cancelled before Press
Advertisement
7
CONSTRUCTION OF WORK OVER JOB CIVI WORKS AT CHAK 66 NORTH EAST # 01, DISTRICT SHANGHER.
12.124 million 07.12.203
23.12.2013 30 days
Work order issued ______. 90 % Completed. Waiting for rig.
8
Construction of Pre Drilling Engineering Works at Goth Patafi Well # 01 (Hanif Siddiqui # 1 District Hyderabad
Rs.22.270 millions
21.12.201307.01.2014 30 days Completed
9
Construction of Pre Drilling Engineering Works at Pasaki Deep Well # 04 District Hyderabad
Rs.23.050 millions
21.12.201309.01.2014 30 days Completed
S No Name of WorkEstimate
d Cost
Press Advertisement date
Date of Opening
Work Done By Parties
Target Completion Date Present StatusAFE Cost
Lowest Cost
10
CONSTRUCTIONS OF PRE DRILLING CIVIL WORK AT WELL LOCATION SOUTH EAST X -01.(Pali Deep # 1) DISTRICT TANDO ALAHYAR, SINDH.
42.913 millions
27.03.2014
11.04.2014 45 days
LOI issued on 02.06.2014.
11
CONSTRUCTION OF PRE DRILLING CIVIL WORK AT WELL LOCATION, SAAND #02 DISTT: TANDO ALLAH YAR. 39.446
12.03.2014 26.03.14 45 days.
Work order issued on _______ work in progress.
12
CONSTRUCTION OF PRE DRILLING CIVIL WORK AT WELL LOCATION,KUNNER #09 DISTRICT : HYDERABAD., SINDH RS.31.205
15.05.2014
30.05.2014 30 days
Bids opened on 30.05.2014 and is under management approval.
C&ESS DEPARTMENT CONTRACT WORKS FGCP-I
S No Name of WorkEstimated
Cost
Press Advertisement date
Date of Opening
Work Done By Parties
Target Completion Date Present StatusAFE Cost
Lowest Cost
1
Hiring Services for Pipeline Construction work for Uch-II Development Project
Rs.68.826 millions
15.03.2013
30.03.2013
17.06.2013 (60 days) Completed
2
Civil & Mechanical Works for Installation of Well Head Assembilies and Flow Line for 09 wells at Uch Gas Field, Near Dera Murad Jamali, Distt. Bughti, Balochistan.
160 Millions
19.08.2013
04.09.2013 180 Days
55% work copmleted.
3
Electrical and Instrumentation Works for Well Head Facilities for 15 wells at Uch Gas Field, Near Dera Murad Jamali, Distt. Bughti, Balochistan.
80 Millions
19.08.2013
04.09.2013 90 Days
Work order is to be used.
C&ESS DEPARTMENT CONTRACT WORKS FGCP-I
S No Name of WorkEstimate
d Cost
Press Advertisement date Date of Opening
Work Done By Parties Target Completion
Date Present StatusAFE CostLowest
Cost
1
Hiring Services for Pipeline Construction work for Uch-II Development Project
Rs.68.826
millions15.03.20
13 30.03.201317.06.2013 (60 days) Completed
2
Civil & Mechanical Works for Installation of Well Head Assembilies and Flow Line for 09 wells at Uch Gas Field, Near Dera Murad Jamali, Distt. Bughti, Balochistan.
160 Millions
19.08.2013 04.09.2013 180 Days
55% work copmleted.
3
Electrical and Instrumentation Works for Well Head Facilities for 15 wells at Uch Gas Field, Near Dera Murad Jamali, Distt. Bughti, Balochistan.
80 Millions
19.08.2013 04.09.2013 90 Days
Work order is to be used.
C&ESS DEPARTMENT CONTRACT WORKS HEAD OFFICES No
Name of Work Estimated Cost
Press Advertisement date
Date of Opening
Work Done By Parties
Target Completion Date
Present Status
AFE CostLowest
Cost1 Construction of
Admin building, warehouses & security office building (Contract C-1), near Kunnar Oil Field Distt. Hyderabad Sindh
Rs.66.70 millions
08.09.2013
08.10.2013 240 days Management approval accorded and LOI issued by SCM department on 28.05.2014 .
2 Construction of workshop offices, MPE&I workshop, safety & Firefighting Building (Contract C-2), Laboratory near Kunnar Oil Field Distt. Hyderabad Sindh
Rs.48.40 millions
08.09.2013
08.10.2013 240 days Contract Agreement Execution Stage.
3 Construction of Officer's Houses (C-1) at Sinjhoro Plant Distt. Sanghar Sindh
Rs.89.619 millions
22.3.2014 26.03.2014 240 days Case deferred by Procurement Committee. Caravan as alternate option suggested by PC.
4 Construction of Assistant's Houses (C-II) at Sinjhoro Plant Distt. Sanghar Sindh
Rs.63.00 millions
11.05.2013
27.06.2013 240 days Case deferred by Procurement Committee. Caravan as alternate option suggested by PC.
S No
Name of Work Estimated Cost
Press Advertisement date
Date of Opening
Work Done By Parties
Target Completion Date
Present Status
AFE CostLowest
Cost5 Construction of
Officer's Houses (C-1) at Uch Gas Field for Uch-II
Rs.87.00 millions
08.09.2013
09.10.2013
365 days Annulled and Case for Caravans to be processed by Admin Deptt.
6 Construction of Boundary wall at Jhal Magsi Distt. Mera Murad Jamali
Rs.28.00 millions
08.08.2013
10.09.2013
120 days Word order issued on 08.04.2014 and contractor is to mobilize yet.
7 Construction of Officer's House & Infrastructure Works at Tando Alam Sindh
Rs.75.00 millions
28.07.2013
28.08.2012
21.07.2013 (365 days)
Annulled and Case for Caravans to be processed by Admin Deptt.
8 Construction of Govt. Rural Dispensary (Social Welfare Scheme), Village Dhayala, Teh. Dina, Distt. Jhelum, Punjab.
Rs.4.765 M
06.06.20113
10.07.2013
240 days Work under construction.
9 Construction of Waste Pit & Skimmer Tank at Kal Oil Field Distt. Chakwal
Rs.3.898 millions
06.06.2013
08.07.2013 60 days
Work order issued on 14.03.2014. Work under construction.
S No
Name of Work Estimated Cost
Press Advertisement date
Date of Opening
Work Done By Parties
Target Completion Date
Present Status
AFE CostLowest
Cost10 Construction of
Assistant's Houses (C-2) at Uch Gas Field Uch-II
Rs.87.00 millions
06.06.2013
09.07.2013
365 days
Annulled and Case for Caravans to be processed by Admin Deptt.
11 Construction of Worker's Houses (C-3) at Uch Gas Field Uch-II
Rs.87.00 millions
06.06.2013
09.07.2013
365 days
Annulled and Case for Caravans to be processed by Admin Deptt.
12 Up-gradation of Pasaki Facility Road from Hyderabad to Mirpur Khas main Road to new constructed Kunnar Plant Road
Rs.59.00 millions
06.06.2013
04.07.2013
180 days
Work order issued on 03.06.2014 Work is under construction.
13 Construction of Foundation for Dehydration Plant at Bobi
Rs.4.22 millions
06.06.2013
04.07.2013
30 days
Work order issued on 10.03.2014 and work is under construction.
14
Renovation of OGTI Hostel I-9 Islamabad
Rs.1.986 millions
27.07.2013
30-08-2013
60 days
After obtaining expenditure approval from ED(Petroserv) case submitted to SCM deptt on 28.01.2014 for further processing.
S No
Name of Work Estimated Cost
Press Advertisement date
Date of Opening
Work Done By Parties
Target Completion Date
Present Status
AFE Cost
Lowest Cost
15 Construction of PCC courtyard & fixing of Fiber Glass shed at Masjid Chanda Plant
Rs.1.26 millions
28.07.2013 27.08.2013 60 days
Sent for annullment on 14.03.14 due to expiry of bid validity.
16 Construction of Prefabricated worker houses at Sinjhoro (C-3) using SCIP
Rs.84.00 millions
28.07.2013
27.082013 240 days Case deferred by Procurement Committee. Caravan as alternate option suggested by PC.
17 Construction of Offices & other allied building at Bahu Well-2
Rs.10.03 millions
15.10.2013 21.11.2013 240 days
Deffered by Procurement Committee due low production life of Bahu.
18 Construction of new workshop shed at Dakhni Plant
Rs.15.51 millions
15.10.2013
25.11.2013 240 days Financial Evaluation done and uploaded on 02.06.2014.
19 Construction of Hard standing bath/wash room & canteen for ATA at Qadirpur
Rs.7.943 millions
15.10.2013
28.11.2013 90 days annulled on 15.04.14 due to no participation by bidders. Fresh case is being prepared.
S No
Name of Work Estimated Cost
Press Advertisement date
Date of Opening
Work Done By Parties
Target Completion Date
Present Status
AFE Cost
Lowest Cost
20 Repair of Road from Sohbatpur to Uch Plant
Rs.16.366 millions
28.07.2013 28.08.2013At 1130 hrs
90 days Work order issued on _______. Work is under construction.
21 Extension of Police Check Post (changla wall Maue Dariya) Near well No 3 at Dakhni field
1.663 M
15.10.2013 18.11.2013
60 days Contract Agreement prepared and submitted to SCM on 13.04.2014.
22 CONSTRUCTION OF REGIONAL COORDINATOR PRE FAB STRUCTURE OFFIC I/C SEWRAGE SYSTEM.DISTT: HYDERABAD.
8.103 M
240 days Pended.
23 Costruction of 12 rooms & 27 bathrooms at Qadir Pur Gas Field.Distt:Ghotki Sindh.
10.86 M 08.08.2013
09.09.2013 240 days
Annulled on 28.04.14 and fresh case to be intiated for re-tendering.
24 Construction of Permanent Wire Woven Mesh Fencing at Nashpa #3 Well.Distt:Karak
1.532 M 08.09.2013
07.10.2013At 1130 hrs 30 days
Annulled due to expiry of bid validity and case for approval through Field Tender is in process.
S No
Name of Work Estimated Cost
Press Advertisement date
Date of Opening
Work Done By Parties
Target Completion Date
Present Status
AFE Cost
Lowest Cost
25 Engineering Works for Bahu Wells #5,6,7 & 8 platform High Rising at Bahu Gas Field, Tehsil ahmad pur sial, Distt: Jhang.
209.713 M
08.09.2013
07.10.2013 365 days
Annulled on 11.04.14 due to expiry of bid validity and case is sent to user deptt to confirm if the requirement still exists.
26 Hiring of vehicles for Field Units of C&ESS department OGDCL, Islamabad
25.68 M 180 days
Case file lost at SCM deptt and sent again on 12.05.14 to SCM deptt for press advertisement.
27 CONSTRUCTION OF FOUNDATION FOR REBOILER, CONDENSATE POTS & SOFTENING UNITS AT UCH#II, Distt: DheraBugti.
1.773 Million
22.08.2013At 1130 hrs
30 days Work executed departmentally. Tender cancelled
28 CONSTRUCTION OF UNDER GROUND ROOM FOR HSD STORAGE TANK AT OGDCL HEAD OFFICE ISLAMABAD.
1.13 Millions
02.08.2013
20.08.2013 30 Days Work order issued on 14.05.14 and contractor mobilized but change in site is under consideration.
29 Construction of RCC water pond at Nashpa Plant
3.861 millions
15.10.2013
27.11.2013 90 Days Contract Agreement prepared and submitted to SCM on 13.04.2014.
S No
Name of Work Estimated Cost
Press Advertisement date
Date of Opening
Work Done By Parties
Target Completion Date
Present Status
AFE Cost
Lowest Cost
30 Supply and fixing of geo membrane sheet 0.50 mm thick at effuluent water pits at Dakhni, Distt. Attock
10.856 Millions
15.10.2013 22.11.2013 30 days
Resubmitted to SCM Departement on 21.o5.2014for Retendering.
31 Construction of Civil Works for 09 Wells for Sinjhoro Gas field, Distt. Sanghar, Sindh.
12.542 Millions
15.10.2013
20.11.2013 90 Days After obtaining expenditure approval from ED(Petroserv) case submitted to M(S & FA) for AFE No.
32 Construction of Internal Road at Nashpa Plant, Distt. Karak, KPK
4.138 millions
04.01.2014
06.02.2014 45 Days Contract Agreement prepared and submitted to SCM on 13.04.2014.
33 Construction of Soldier Room, Toilet, Bath Kitchen For FC Post at Uch Dera Bugti Balochistan.
1.011 Millions
60 days Case returned to SCM on 22.05.2014 for retendering.
34 Hiring of Consultancy Services for Residential Camp at Nashpa
Nil 30.09.2013 75 days.Case returned to SCM on 30.09.2013. with soft copy of TOR
35 Pre-qualification / enlistment of contractors for PDEWs at different zones
Nil Nil Sent to GM (SCM) for on 25.11.2013.
S No Name of Work Estimated Cost
Press Advertisement date
Date of Opening
Work Done By Parties
Target Completion Date
Present Status
AFE Cost
Lowest Cost
36 Construction of BMP Posts in Tribal area Ranjanpur, Distt: Ranjanpur.
2.564 Million
45 days Completed departmental.
37 CONSTRUCTION OF REPAIR OF ROAD FROM JAND TO CHOWK SHAHEEDAN 4.3 KM AT DAKHNI FIELD
27.11.2013
26.12.2013 90 DAYS
Case approved by Procurement Committee on 10.06.2014.
87 Construction of BMP Posts in Trible area Ranjanpur, Distt: Ranjanpur.
Rs.2.564 60 days Completed through party resources.
39 CONSTRACTION/EXTENSION IN EXISTING SOCIAL WELFARE DISPENSERY AT RAJIAN OIL FIELD, Punjab
0.965 Million
26.01.2014
26.02.2014 30 days Financial Evaluation done and uploaded on 06.06.2014.
40 INSTALLATION OF UNDER GROUND POWER SUPPLY SYSTEM AT KOT SARANG Distt: Chakwal, Punjab
3.12 million
60 days Original case file lost. Bid documents prepared and approval is being sought again for execution.
S No
Name of Work Estimated Cost
Press Advertisement date
Date of Opening
Work Done By Parties
Target Completion Date
Present Status
AFE Cost
Lowest Cost
41 CONSTRUCTION OF SOCIAL WELFARE PUBLIC DOSPENSARY LPG PLANT AT BOBI OIL FIELD, DISTRICT SANGHAR SINDH.
12.983 Million
180 days
BOQ prepared and bid documents are under preparation.
42 EXTENSION OF EXISTING SOCIA WELFARE DISPENSARY AT KUUNAR OIL FEILD.
5.4 Million
26.01.2014
04.03.2014 180 days
Technical Evaluation done on 12.05.14 and sent to SCM for Financial opening / annullment.
43 CONSTRUCTION OF PRODUCED WATER PIT, BOUNDARY WALL AND ALLIED CIVIL WORKS OUTSIDE CHANDA PLANT PREMISES.
15.429 Million
26.01.2014
03.03.2014 120 days
Retendered on 07.05.2014 and will be opened on 29.06.14.
44 Raising & Strengthening of OGDC Bund at Qadirpur Gas Field District Ghotki Province Sindh.
171 million
04.01.2014
04.01.2014 120 days
To be presented in P & FC for approval of award on 11.06.2014
45 CONSTRACTION OF 10 NO. NEW ROOMS IN WORKER CAMP AT LOGISTIC CAP KOTSARANG
8.422 million
180 days
Sent to SCM Deptt for Press Advertisement
S No
Name of Work Estimated Cost
Press Advertisement date
Date of Opening
Work Done By Parties
Target Completion Date
Present Status
AFE Cost
Lowest Cost
46 IMPROVEMENT OF WATER SUPPLY SCHEME IN THE AREA OF KAL OIL FIELD.DISTRICT CHAKWAL, PUNJAB
Rs 0.65 millions
15.02.2014
21.03.2014 30 days To be done departmentally on quotation basis within PPRA limits.
47 CONSTRUCTION OF OH WATER TANK AND CAR PARKING AT CHANDA
PLANT.
5.267 Million
75 days Bid opened on 28.05.2014. Case awaited from SCM for Technical Evaluation.
48 CONSTRUCTION OF 02 NO.CLASS ROOMS WITH VERANDAH FOR GOVT.PRIMARY SCHOOL ALWARGI BANDA AT NASHPA .
1.125 Million
90 days Technical Evaluation done on 09.04.14 and sent to SCM for Financial opening.
49 CONSTRUCTION OF METALLED ROAD (45.657 Kms) FROM UCH PLANT TO UPL DERA MURAD JAMALI DISTRICT DERA BUGHTI, PROVINCE BALUCHISTAN.
868.27 million
22.02.2014
24.03.2014 18 months
Annulled due to poor response and case is being sent for press advertisement for retendering.
S No Name of Work Estimated Cost
Press Advertisement date
Date of Opening
Work Done By Parties
Target Completion Date
Present Status
AFE CostLowest
Cost509 CONSTRUCTION OF
REPAIR OF ROAD FROM TANDO MURREE TO TANDO ALAM # 15 BASE CAMP
Rs 2.45 millions
26.01.2014
28.02.2014 30 days Technical Evaluation done on 12.05.14 and sent to SCM for Financial opening.
51 Repair Maintenance of 01 km Road, Mohri Rajgan to Chak Tareda Under Social Welfare. Tehsil Sohawa.
1.297 Million
04.01.2014
10.02.2014 45 days Financial Evaluation done and uploaded on 06.06.2014.
52 SUPPLY & INSTALLATION & COMMISSIONING OF DOUBLE GATE SYSTEM, HYDRAULIC ROAD BLOCKER & HYDRAULIC BARRIER AT NASHPA DISTRICT KARAK KPK.
Rs 4.10millions
27.02.2014
03.04.2014 60 days Technical Evaluation done on 11.04.2014. letter to sent to bidder for withdrawal of exceptions / deviations. Financial opening awaited.
53 CONSTRUCTION OF 03 NOS PICKETS WITH ATTACH BATH, KITCHEN & TOILETS FOR PHASE-II FC PICKETS AT UCH-II GAS FIELD.DISTRICT DERA BUGTI BALUCHISTAN
Rs 2.518millions
45 days Financial Evaluation done on 13.05.14 and case is with SCM for further processing.
S No
Name of Work Estimated Cost
Press Advertisement date
Date of Opening
Work Done By Parties
Target Completion Date
Present Status
AFE Cost
Lowest Cost
48 CONSTRACTION OF P.C.C HARD STANDING FOR STOCK MATERIALS AT NASHPA DISTRICT KARAK,KPK.
Rs 0.716millions
26.01.2014
27.02.2014
30 days Expenditure approval obtianed and AFE No alloted on 13.05.14. Financial evaluation done and uploaded on web 30.05.14.
56 Construction Of Police Picket At Sinjhoro Plant Gate District Sanghar.
Rs 1.602millions
09.04.2014
09.05.2014
45 days Technical Evaluation done and Financial opening is on 16.06.2014.
54 Raising of Sales Gas ROW at Nashpa (1.5 km)\Distric karak, kpk.
Rs 4.45millions
45 days Technical Evaluation done and uploaded on 09.06.2014.
51 EARTH FILLING, CONSTRUCTION OF ONE WAY ROAD AND PARKING SHED AT NASHPA PLANT. DISTT: KARAK, KPK
Rs 19.106millions
15.02.2014
20.03.2014
120 days Received for endorsement of Executive Summary on 11.06.2014.
55 CONSTRUCTION OF COMPUTER ROOM FOR WEIGHING BRIDGE AT NASHPA PLANT. DISTT: KARAK, KPK
Rs 0.934millions
60 days work in progress as an additional work through the same contractor for weigh bridge.
S No
Name of Work Estimated Cost
Press Advertisement date
Date of Opening
Work Done By Parties
Target Completion Date
Present Status
AFE Cost
Lowest Cost
56 CONSTRUCTION OF HARD STANDING FOUNDATION AREA OF LOGISTIC WORKSHOP AT LOGISTIC CAMP KOTSARANG.DIST: CHAKWAL, PUNJAB
Rs 16.06millions
22.02.2014
25.03.2014 30 days Technical Evaluation done on 07.04.2014 and case sent to SCM for Financial Opening.
57 CONSTRUCTION OF WATER TANK FOR DRINKING PURPOSE FOR LOCALS AT TANDO ALAM OIL COMPLEX
Rs 0.816millions
09.04.2014
08.05.2014 60 days Technical Evaluation done on 21.05.2014 and sent to SCM deptt for Financial Evaluation.
58 Feasibility Study Of Existing Ogdcl Office Building Office Building Masood Mansion At F-8 Markaz For Addition Of New Floors For Gymnasium And Design/Consultancy Services For The Improvement Measures And Proposed Gymnasium Thereof millions
16.04.2014
16.05.2014 90 days Received on 28.05.14 for Technical Evaluation.
S No
Name of Work Estimated Cost
Press Advertisement date
Date of Opening
Work Done By Parties
Target Completion Date
Present Status
AFE Cost
Lowest Cost
59 CONSTRUCTION OF ROW 31.05 KM FOR JAKHRO WELL-1 DISTRIC: KHAIRPUR ,SINDH
30.953 million
45 days Press advertised.Bid will be opened on 23.06.2014.
60 CONSTRUCTION OF 02 NOS. PRODUCTION STORAGE SHED & HARD STANDING AT NASHPA PLANT. DISTT: KARAK, KPK
45.68 million
240 days
Sent to PTO (Mech) on 06.06.14 for Budget allocation.
61 CONSTRUCTION OF CIVIL WORKS FOR FIELD DEVELOPMENT AT WELL LOCATION DACHRA PUR # 02 .DISTT: HYDERABAD, SINDH.
2.41 million
30 days Technical Evaluation done on 02.06.2014 and sent for Financial Opening.
62 REPAIR/MAINTENANCE OF ROAD FROM REHMAT GAS FIELD TURN TO ANWAR ABAD. DISTT: GHOTKI
Rs 25.327millions
60 days Sent to SCM Deptt on 08.05.14 for Press Advertisement.
63 CONSTRUCTION OF GEO-MEMBRANE LINING FOR PRODUCED WATER PIT AT QADIR PUR PLANT..
2.445 million
30 days Bid documents are being prepared.
S No
Name of Work Estimated Cost
Press Advertisement date
Date of Opening
Work Done By Parties
Target Completion Date
Present Status
AFE CostLowest
Cost64 RAISING OF APPROACH
ROAD AT QADIRPUR#35.DISTRICT : GHOTKI, SINDH
2.969 45 days Bid documents prepared. Budget allocated by QP JV and file received in (E.O) South Section on 05.05.14. Case is to be sent to SCM for press advertisement.
65 CONSTRUCTION OF RAISED PLATFORM AT HRL-2. DISTRICT GHOTKI, SINDH
27.56 million 90 days
Press advertised. Bids will be opened on 24.06.2014.
66 CONSTRUCTION OF RAISED PLATFORM AT HRL-7. DISTRICT GHOTKI, SINDH
27.55 million 90 days
Bid opened on 10.06.2014 and case awiated from SCM deptt for Technical Evaluation.
67 RAISING OF APPROACH ROAD AT QADIRPUR#48.DISTRICT : GHOTKI, SINDH
5.11 million
45 days Bid documents prepared. Budget allocated by QP JV and file received in (E.O) South Section on 05.05.14. Case is to be sent to SCM for press advertisement.
68 CONSTRUCTION OF ROAD FROM DISPENSARY TO WELL NO.6 (ABOUT 7 KM) AT DAKHNI PLANT WELL.DISTRICT: ATTOCK.
35.088 150 days
Press advertised on 16.05.2014 and bids will opened on 25.06.2014.
S No
Name of Work Estimated Cost
Press Advertisement date
Date of Opening
Work Done By Parties
Target Completion Date
Present Status
AFE CostLowest
Cost69 CONSTRUCTION OF
RAISED PLATFORM AT QADIRPUR#50.DISTRICT : GHOTKI, SINDH
27.56 million
45 days Bid documents prepared. Budget allocated by QP JV and file received in (E.O) South Section on 05.05.14. Case is to be sent to SCM for press advertisement.
70 CONSTRUCTION OF RAISED PLATFORM AT QADIRPUR#45.DISTRICT : GHOTKI, SINDH
27.56 45 days Bid documents prepared. Budget allocated by QP JV and file received in C&ESS on 06.05.14. Case is to be sent to SCM for press advertisement.
71 CONSTRUCTION OF RAISING OF APPROCH ROAD AT QADIRPUR#50.DISTRICT : GHOTKI, SINDH
3.39 million
45 days Bid documents prepared. Case is with (E.O)South Section for budget arrangement.
72 CONSTRUCTION OF RAISING OF APPROACH ROAD AT QADIRPUR#31.DISTRICT : GHOTKI, SINDH
6.10 million
45 days Bid documents prepared. File is with (E.O)South section and is being sent to JV Accounts for budget allocation.
S No
Name of Work Estimated Cost
Press Advertisement date
Date of Opening
Work Done By Parties
Target Completion Date
Present Status
AFE Cost
Lowest Cost
73 CONSTRUCTION OF STORE SHED FROM RETERIEVED MATERIAL OF TOOT AT DAKHNI PLANT DISTRICT ATTOCK, PUNJAB.
4.56 million 90 days
Bids opened on 06.06.2014 and case awaited from SCM deptt for Technical Evaluation.
74 CONSTRUCTION OF METTALED ROAD FROM BASIC HEALTH UNIT TO AYUB LAKHAN TO GOVERNAMENT HIGH SCHOOL AYUB LAKHAN.
1.337 million
60 days Sent to SCM Deptt on 22.05.14 for Press Advertisement.
75 CONSTRACTION OF RAISING OF APPROCH ROAD AT QADIRPUR#41.DISTRICT : GHOTKI, SINDH
4.18 million
45 days Bid documents prepared. File is with (E.O)South section and is being sent to JV Accounts for budget allocation.
76 Construction of Foundation and Dyke Walls for Crude Storage Tanks at Rajian Well # 05
1.25 05.05.2014
02.06.2014 Bids opened on 02.06.2014 and case awaited from SCM deptt for Technical Evaluation.
77 CONSTRACTION OF RAISED PLAT FORM AT QADIRPUR#38/39.DISTRICT : GHOTKI, SINDH
37.67 million
45 days Confirmation of Budget allocation is in Process
S No
Name of Work Estimated Cost
Press Advertisement date
Date of Opening
Work Done By Parties
Target Completion Date
Present Status
AFE Cost
Lowest Cost
78 RAISING OF APPROACH ROAD AT QADIRPUR# 11.DISTRICT : GHOTKI, SINDH
1.55 million
45 days Confirmation of Buget allocation is in Process
79 RAISING OF APPROACH ROAD AT QADIRPUR DEEP#1 .DISTRICT : GHOTKI, SINDH
14.87 million
45 days Sent to SCM deptt on 06.06.2014 for Press advertisement.
80 RAISING OF APPROACH ROAD AT QADIRPUR# 45.DISTRICT : GHOTKI, SINDH
6.19 million
45 days Sent to SCM deptt on 06.06.2014 for Press advertisement.
81 CONSTRACTION OF RAISED PLAT FORM AT QADIRPUR DEEP #01.DISTRICT : GHOTKI, SINDH
27.79 million
45 days Sent to SCM deptt on 06.06.2014 for Press advertisement.
S No Name of Work Estimated Cost
Press Advertisement date
Date of Opening
Work Done By Parties
Target Completion Date
Present Status
AFE Cost
Lowest Cost
86
CONSTRACTION OF RAISED PLAT FORM AT QADIRPUR#48.DISTRICT : GHOTKI, SINDH 27.56
million 45 days
Bid documents prepared. Budget allocated by QP JV and file received in (E.O) South Section on 05.05.14. Case is to be sent to SCM for press advertisement.
87 CONSTRACTION OF RAISED PLAT FORM AT QADIRPUR#46.DISTRICT : GHOTKI, SINDH
Rs 27.56millions
45 days Budget allocated by QP JV department. Case is with (E.O)South Section.
PRE-DRILLING ENGINEERING WORKS AT EFP-3 DURING JUNE 2013 TO JUNE 2014
S.No Description Approved Cost
EFP-3 inputRemarks
Earh Work Water Supply System Misc.Works
Approach
Road
Preparation of Well
location
Mud Pit Additional Mud Pit
Establishmen
t
Water required for
drilling Operation
Electrical
Works
Plumbing &
Sanitary Works
Total amount
MRs MRs MRs MRs MRs MRs MRs MRs MRs MRs
1 PDCW at Jund-1 53.959 2.00 3.50 3.00 4.00 2.00 22.50 0 0 37.00
2 PDCW at Soghari-1 22.557 1.00 2.00 3.00 4.00 1.00 13.50 0.5 0.2 25.20
3 PDCW at Mela-4 39.856 4.00 5.00 4.00 3.00 1.00 22.50 0.5 0.2 40.20
4 PDCW at Rajian-7 23.505 1.50 3.00 4.00 3.00 1.00 13.50 0.5 0.2 26.70
5 PDCW at Rajian-8 60.100 2.00 4.00 4.00 5.00 0.00 18.00 33.00
6
Work over job at Rajian-2 20.193 3.00 0.00 0.00 7.00 10.00
7 PDCW at Nashpa-5 99.850 12.00 24.00 2.00 0.00 0.00 0.00 0 0 38.00
8
PDCW at Surqamar-1 25.00 25.00
9 PDCW at Kurrum-1 28.555 1.00 1.00 3.00 0.00 0.50 13.50 19.00
WATER SUPPLY SYSTEM FOR PLANT/ FIELD OPERATED BY EFP-3 DURING JUNE 2013 TO JUNE 2014
S.No Fields/ Plants Water Source Water required for Operational activities of Plants/ Fields Remarks
Million Rupees
1Chanda Plant/
Mela Plant
Mela Water Point situated in hilly area ≈25 km away from Chanda
Plant 28.640
2Missa Kaswall
Fieldfrom local near by Nallah
4.091 3 Rajian Oil Field from Chohan Nallah 12.274
4 Sadqal Oil FieldSadqal Water Point situated at
Shah pur Dam 10.229
REPAIR/ MAINTANENCE OF APPROACH ROAD FROM PLANT TO WELL LOCATION DURING JUNE2013 TO JUNE 2014
S.No Approach Road Maintenance by EFP-3 Remarks MRs
1From Well
Nashpa-1,2,3,42.50
2From Well Mela-
1,2,3,43.00
3Road near
Tharraly Bridge0.50
EARTH WORK REQUIRED FOR ROW,WASTE PITS AND LEVELING BY EFP-3 DURING JUNE2013 TO JUNE 2014
S.No DESCRIPTIONEarth Work
RemarksMRs
1ROW for SNGPL Gas Pipe line
from Nashpa Plant 1.500
2Restoration of Mud Waste Pit
at Nashpa-21.000
3Restoration of Mud Waste Pit
at Nashpa-31.000
4
Leveling of Hilly area at Plant for Loading Gantry and double
Road
15.00
5Effulent Water Pits (3No) at
Dakhni Plant0.900
6Leveling of Store Area at
Dakhni Plant0.500
PRE-DRILLING ENGINEERING WORKS AT EFP-1 DURING JUNE 2013 TO JUNE 2014
S.No Description Approved Cost
EFP-31inputRemarks
Earh Work Water Supply System Misc.Works
Approach
Road
Preparation of Well
location
Mud Pit Additional Mud Pit
Establishmen
t
Water required for
drilling Operation
Electrical
Works
Plumbing &
Sanitary Works
Total amount
MRs MRs MRs MRs MRs MRs MRs MRs MRs MRs
1
2
3
4
5
6
7
8
9
WATER SUPPLY SYSTEM FOR PLANT/ FIELD OPERATED BY EFP-1 DURING JUNE 2013 TO JUNE 2014
S.No Fields/ Plants Water Source Water required for Operational activities of Plants/ Fields Remarks
Million Rupees
1
2
3
4
REPAIR/ MAINTANENCE OF APPROACH ROAD FROM PLANT TO WELL LOCATION DURING JUNE2013 TO JUNE 2014
S.No Approach Road Maintenance by EFP-1 Remarks MRs
1
2
3
EARTH WORK REQUIRED FOR ROW,WASTE PITS AND LEVELING BY EFP-1 DURING JUNE2013 TO JUNE 2014
S.No DESCRIPTIONEarth Work
RemarksMRs
1
2
3
4
5
6
PRE-DRILLING ENGINEERING WORKS AT EFP-2 DURING JUNE 2013 TO JUNE 2014
S.No Description Approved Cost
EFP-2 inputRemarks
Earh Work Water Supply System Misc.Works
Approach
Road
Preparation of Well
location
Mud Pit Additional Mud Pit
Establishmen
t
Water required for
drilling Operation
Electrical
Works
Plumbing &
Sanitary Works
Total amount
MRs MRs MRs MRs MRs MRs MRs MRs MRs MRs
1
2
3
4
5
6
7
8
9
WATER SUPPLY SYSTEM FOR PLANT/ FIELD OPERATED BY EFP-2 DURING JUNE 2013 TO JUNE 2014
S.No Fields/ Plants Water Source Water required for Operational activities of Plants/ Fields Remarks
Million Rupees
1
2
3
4
REPAIR/ MAINTANENCE OF APPROACH ROAD FROM PLANT TO WELL LOCATION DURING JUNE2013 TO JUNE 2014
S.No Approach Road Maintenance by EFP-2 Remarks MRs
1
2
3
EARTH WORK REQUIRED FOR ROW,WASTE PITS AND LEVELING BY EFP-2 DURING JUNE2013 TO JUNE 2014
S.No DESCRIPTIONEarth Work
RemarksMRs
1
2
3
4
5
6
PRE-DRILLING ENGINEERING WORKS AT EFP-4 DURING JUNE 2013 TO JUNE 2014
S.No Description Approved Cost
EFP-4 inputRemarks
Earh Work Water Supply System Misc.Works
Approach
Road
Preparation of Well
location
Mud Pit Additional Mud Pit
Establishmen
t
Water required for
drilling Operation
Electrical
Works
Plumbing &
Sanitary Works
Total amount
MRs MRs MRs MRs MRs MRs MRs MRs MRs MRs
1
2
3
4
5
6
7
8
9
WATER SUPPLY SYSTEM FOR PLANT/ FIELD OPERATED BY EFP-4 DURING JUNE 2013 TO JUNE 2014
S.No Fields/ Plants Water Source Water required for Operational activities of Plants/ Fields Remarks
Million Rupees
1
2
3
4
REPAIR/ MAINTANENCE OF APPROACH ROAD FROM PLANT TO WELL LOCATION DURING JUNE2013 TO JUNE 2014
S.No Approach Road Maintenance by EFP-4 Remarks MRs
1
2
3
EARTH WORK REQUIRED FOR ROW,WASTE PITS AND LEVELING BY EFP-4 DURING JUNE2013 TO JUNE 2014
S.No DESCRIPTIONEarth Work
RemarksMRs
1
2
3
4
5
6
PRE-DRILLING ENGINEERING WORKS AT EFP-5 DURING JUNE 2013 TO JUNE 2014
S.No Description Approved Cost
EFP-5 inputRemarks
Earh Work Water Supply System Misc.Works
Approach
Road
Preparation of Well
location
Mud Pit Additional Mud Pit
Establishmen
t
Water required for
drilling Operation
Electrical
Works
Plumbing &
Sanitary Works
Total amount
MRs MRs MRs MRs MRs MRs MRs MRs MRs MRs
1
2
3
4
5
6
7
8
9
WATER SUPPLY SYSTEM FOR PLANT/ FIELD OPERATED BY EFP-5 DURING JUNE 2013 TO JUNE 2014
S.No Fields/ Plants Water Source Water required for Operational activities of Plants/ Fields Remarks
Million Rupees
1
2
3
4
REPAIR/ MAINTANENCE OF APPROACH ROAD FROM PLANT TO WELL LOCATION DURING JUNE2013 TO JUNE 2014
S.No Approach Road Maintenance by EFP-5 Remarks MRs
1
2
3
EARTH WORK REQUIRED FOR ROW,WASTE PITS AND LEVELING BY EFP-5 DURING JUNE2013 TO JUNE 2014
S.No DESCRIPTIONEarth Work
RemarksMRs
1
2
3
4
5
6
Financially Highlight of- Total Works Done, EFP’s
FY 2013-14
1 EFP-I
2 EFP-II PAK Rs. 300.o1 Million
3 EFP-III PAK Rs. 347.83 Million
4 EFP-IV
5 EFP-V
6 FGCP-I
7 FGCP-II