prequalification process / subcontract lisa conomy construction counsel, osu lane beougher state...

51
Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Upload: eve-yellin

Post on 15-Jan-2016

218 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Prequalification Process / Subcontract

Lisa ConomyConstruction Counsel, OSU

Lane BeougherState Architect

Page 2: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Prequalification of Subcontractors

Presentation will cover:• Rule• Criteria• Process• Evaluation of Lower-Tier

Subcontractors• Self-Performed Work

Page 3: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Prequalification of Subcontractors

Rule• CMR or DB shall establish criteria

for pre-qualification of prospective subcontractors• Criteria shall be consistent with

rules adopted by DAS

Page 4: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Prequalification of Subcontractors

Rule• Criteria shall be subject to approval

of public authority involved in project (approved prequalification criteria will be used for any future bidder’s responsibility analysis)

Page 5: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Prequalification of Subcontractors

• CMR or DB will place the establishment of prequalification criteria on project schedule

• For each subcontract, CMR or DB shall identify at least 3 prospective bidders that are prequalified to bid

Page 6: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Prequalification of Subcontractors

• CMR or DB shall identify fewer than 3 (to satisfaction of public authority) if 3 prequalified bidders are not available

• Public authority shall verify that each prospective subcontractor meets the prequalification criteria

Page 7: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Prequalification of Subcontractors

• Once prospective subcontractors are prequalified & found acceptable, CMR or DB shall solicit proposals from each of these subcontractors

Page 8: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Prequalification of Subcontractors

• Solicitation & selection of a subcontractor shall be conducted under an “open book pricing method”

Page 9: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Prequalification of Subcontractors

• Open Book Pricing Method• CMR: same meaning as in ORC

9.33“method in which CMR provides the public authority, upon request, all books, records, documents, and other data pertaining to the bidding, pricing, or performance of a CM contract awarded to CMR”

Page 10: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Prequalification of Subcontractors

• Open Book Pricing Method (cont’d):• DB: same meaning as in ORC153.6

“method in which DB provides the public authority, upon request, all books, records, documents, contracts, subcontracts, purchase orders, and other data pertaining to the bidding, pricing, or performance of a contract for DB services awarded to DB”

Page 11: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Prequalification of Subcontractors

• Any self-performed work by CMR or DB, if allowed by public authority, shall have the same criteria as the other prospective subcontractors

Page 12: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Prequalification of Subcontractors

• CMR or DB shall not be required to award a subcontract to a low bid

• CMR or DB to use the subcontract form, prescribed by DAS, when entering into a subcontract

Page 13: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Prequalification Criteria

• Established criteria shall include the prospective bidders:• Experience • Financial condition• Conduct & performance on previous

contracts

Page 14: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Prequalification Criteria

• Established criteria (cont’d)• Management skills• Ability to execute subcontract

properly

Page 15: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Prequalification Criteria

• Established criteria shall also:• Further any goals set as part of an EDGE

or diversity and inclusion programs required by public authority or by applicable law

Page 16: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Prequalification Criteria

• Established criteria shall also (cont’d)• Require that prospective bidders have

not violated any affirmative action program during the last 5 years (per ORC 9.47, a prospective bidder may meet this requirement by submitting a valid certificate of compliance with affirmative action programs)

Page 17: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Prequalification Criteria

• Require prospective bidders to submit proof of current licenses to perform work as required by public authority or applicable law

• CM or DB to include any additional criteria for specific subcontracts required by public authority that are consistent with the scope and needs of project

Page 18: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Prequalification Process

• CMR or DB shall complete the subcontractor prequalification process for each subcontract no later than 30 days before the intent to solicit bids for that subcontract

Page 19: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Prequalification Process

• During the process, the CMR or DB shall develop “bidders” interest in project, including those prospective subcontractors the public authority asked the CM to contact.

Page 20: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Prequalification Process

• To reach prospective subcontractors, CMR or DB may place a notice on the official website of the public authority or other appropriate websites.

Page 21: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Prequalification Process

• During the process, the CMR or DB shall issue requests for qualifications to prospective subcontractors, and as appropriate forward any questions to the A/E or A/E of Record.

Page 22: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Prequalification Process

• CMR or DB shall accept for evaluation the qualifications timely submitted by any prospective bidder.

Page 23: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Prequalification Process

• CMR or DB shall evaluate all the qualifications that have been submitted and notify each of the prospective subcontractors of whether they are qualified

Page 24: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Prequalification Process

• CMR or DB shall submit names & qualifications of all the qualified prospective subcontractors to public authority (fewer than 3 names can be submitted if it is substantiated that fewer than 3 are available)

Page 25: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Prequalification Process

• Public authority, A/E and CMR or DB may meet to review qualifications of prospective subcontractors on list

• Public authority shall verify that prospective subcontractors on list do meet the prequalification criteria

Page 26: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Prequalification Process

• Public authority may eliminate any prospective subcontractor it determines is not qualified. CMR or DB shall notify the prospective subcontractor, in writing, of the decision to eliminate them

Page 27: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Prequalification Process

• If CMR or DB receives written objection from eliminated prospective subcontractor within 5 days after notification is received, CMR or DB shall deliver written objection to public authority. Public authority may respond to objection in writing through CMR or DB.

Page 28: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Subcontract Bidding Process

• CMR or DB shall create a bid package for each subcontract & solicit bids from the qualified prospective subcontractors in accordance with construction schedule but no later than 60 days before work under that bid package is scheduled to begin

Page 29: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Subcontract Bidding Process

• During the process, the CMR or DB shall issue bidding documents, conduct pre-bid conferences, forward appropriate questions to A/E, assist A/E with preparation of addenda, receive all bids, prepare bid analysis, conduct pre-award conferences & report information to public authority

Page 30: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Subcontract Bidding Process

• At completion of process for each subcontract & no later than 25 days before work is scheduled to begin, the CMR or DB & public authority will meet to review bids and determine to which subcontractor(s) an award will be made

Page 31: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Subcontract Bidding Process

• During review meeting, public authority may reject a proposed subcontractor as non-responsible

Page 32: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Subcontract Bidding Process

• Each subcontractor being considered for an award shall be qualified to perform the subcontracted work and have submitted a bid which conforms to the requirements of the contract documents

Page 33: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Subcontract Bidding Process

• If no proposed subcontractor is rejected, CMR or DB shall enter into the subcontract with accepted subcontractor

Page 34: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Subcontract Bidding Process

• CMR or DB shall prepare all Subcontracts which shall incorporate the General Conditions & be on the Subcontract Form prescribed in OAC 153:1-03-02

Page 35: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Subcontract Bidding Process

• CMR or DB shall prepare all Subcontracts which shall incorporate the General Conditions & be on the Subcontract Form prescribed in OAC 153:1-03-02

• All Subcontracts will be between CMR or DB and the respective Subcontractors

Page 36: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect
Page 37: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Subcontract Bidding Process

• No less than 10 days before work is to begin, CMR or DB shall submit a Subcontractor & Material Supplier Declaration form for approval

• If a proposed subcontractor is rejected, CMR or DB shall propose another subcontractor

Page 38: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Subcontract Bidding Process

• CMR or DB shall not be entitled to any adjustment of contract sum, contract time, or both on account of public authority’s rejection of a proposed subcontractor as non-responsible

Page 39: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Evaluation of Lower-Tier Subcontractors

• Lower-Tier Subcontractor is defined as any subcontractor not in privity with the CMR or DB

• No less than 10 days before work is to begin by any lower-tier subcontractor, CMR shall submit to A/E a Subcontractor and Material Supplier Declaration form (DB shall submit to public authority)

Page 40: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Evaluation of Lower-Tier Subcontractors

• A/E shall verify completeness of form and forward to public authority

• If public authority rejects any proposed lower-tier subcontractor, CMR or DB shall propose a replacement at no additional cost

Page 41: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Self-Performed Work

• CMR or DB (or affiliated entity) can bid to perform Work with its own employees subject to the following:

• Notify public authority of their intent to bid on portion of work

Page 42: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Self-Performed Work

• Public authority shall review that Work & agree on its scope before finalization of subcontracting plan

• At least 14 days before issuing bid documents for the Work, seek public authority’s permission to bid

Page 43: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Self-Performed Work

• If public authority grants permission, the following applies:

• CMR or DB shall meet, in all respects, the bidder pre-qualification criteria

Page 44: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Self-Performed Work

• Bidding documents shall specifically state that a self-perform bid my be submitted

• CMR or DB shall ensure strict separation of personnel involved in bidding from project personnel. Communication between these groups is prohibited until after bid is opened

Page 45: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Self-Performed Work

• General conditions apply to self-performed work no different than other subcontracted work

• All requirements applicable to other subcontractors apply to self-performed work

Page 46: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Self-Performed Work

• Sealed Bid for self-performed work shall be submitted to public authority no less than 48 hours before the deadline for all other bids for same work are submitted to CMR or DB

Page 47: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Self-Performed Work

• If self-performed bid is submitted and less than 2 other bids are received, public authority may require a rebid

Page 48: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Self-Performed Work

• If self-performed work is awarded, CMR or DB may not use CM Contingency for that work. This prohibition applies specifically, but not exclusively, to using contingency to make-up for underestimation of that scope of work by CMR or DB

Page 49: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Self-Performed Work

• Self-Performed work will be considered a subcontract and will be on same subcontract form as all other subcontracts

Page 50: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Prequalification Process/Subcontract

Questions:

Lisa ConomyConstruction [email protected]

Lane J. BeougherState Architect

[email protected]

Page 51: Prequalification Process / Subcontract Lisa Conomy Construction Counsel, OSU Lane Beougher State Architect

Academy Wrap Up

Craig WeiseConstruction Reform Program Director