preliminary method statement - sepa.org.uk · preliminary method statement timing ... this will...

1
Garraron hydro project page ( 2) 2166 Design statement. doc 03/ 07/ 2017 Preliminary Method statement Timing It is proposed to commence construction in May 2018 and complete the civil works in 4 months. This will utilise the driest months of the year for earthworks and avoid critical periods for spawning fish. The turbine and electrical works have a lead-in time of about 12 months and will be installed when available. Method of works Access – Existing tracks will be used as access to powerhouse site and up to the dam. Laydown area – it is proposed to utilise an area within the farmyard as a temporary laydown and storage area. Dam, intake and spillway– construction will involve excavation of soil, rock and gravel from within the reservoir and spillway areas, to be used as fill material in the embankment. Site investigations are to be carried out to identify potential borrow area locations. Placement of concrete will be carried out by helicopter. This will avoid the need for heavy duty tracks. Penstock – From the dam the penstock will follow a route along the eastern bank where all but the initial 140 m are to be buried beneath the access track. The penstock pipes will be transported via helicopter from a delivery area to intermediate points on the hill side where it can be welded into strings before being dragged into position. This minimises handling operations which could otherwise lead to more damage to the hillside vegetation. Powerhouse – construction will involve excavation and temporary stockpiling of topsoil and subsoil for construction of the concrete floor slab/foundation and of the building comprising blockwork walls and a profiled steel pitched roof. Equipment and machinery The earthwork, pipe laying and materials handling will be carried out by rubber tyres load handlers and 14T tracked excavators as appropriate. Concrete will be delivered to site as ready mix with helicopters used to transport concrete to the dam site. Standard precautions to prevent and contain fuel and oil spillage will be put in place. Operation and Maintenance The intake will require little routine maintenance other than periodic inspections. Floating debris such as leaves and grass, and any sediment greater than coarse sand in size will be swept over the spillway into the burn downstream. Periodic pigging of the pipelines will be required in order to dislodge an accumulation of peat slime on the inside walls of the pipes. The effect of this deposit varies from site to site but can lead to significant loss in power output if not dealt with. Pigging facilities are incorporated in the design of the intakes and powerhouse. Monitoring of abstracted flow volumes and energy generation will be done through the electronic control system of the turbine.

Upload: vokhanh

Post on 16-May-2018

238 views

Category:

Documents


2 download

TRANSCRIPT

Garraron hydro project page ( 2)

2166 Design statement. doc 03/07/2017

Preliminary Method statement

Timing

It is proposed to commence construction in May 2018 andcomplete the civil works in 4 months. This will utilise the driestmonths of the year for earthworks and avoid critical periods forspawning fish. The turbine and electrical works have a lead-intime of about 12 months and will be installed when available.

Method of works

Access – Existing tracks will be used as access topowerhouse site and up to the dam.

Laydown area – it is proposed to utilise an area within thefarmyard as a temporary laydown and storage area.

Dam, intake and spillway– construction will involveexcavation of soil, rock and gravel from within the reservoirand spillway areas, to be used as fill material in theembankment. Site investigations are to be carried out toidentify potential borrow area locations. Placement of concretewill be carried out by helicopter. This will avoid the need forheavy duty tracks.

Penstock – From the dam the penstock will follow a routealong the eastern bank where all but the initial 140 m are to beburied beneath the access track. The penstock pipes will betransported via helicopter from a delivery area to intermediatepoints on the hill side where it can be welded into stringsbefore being dragged into position. This minimises handlingoperations which could otherwise lead to more damage to thehillside vegetation.

Powerhouse – construction will involve excavation andtemporary stockpiling of topsoil and subsoil for construction ofthe concrete floor slab/foundation and of the buildingcomprising blockwork walls and a profiled steel pitched roof.

Equipment and machinery

The earthwork, pipe laying and materials handling will becarried out by rubber tyres load handlers and 14T trackedexcavators as appropriate. Concrete will be delivered to site asready mix with helicopters used to transport concrete to thedam site. Standard precautions to prevent and contain fuel andoil spillage will be put in place.

Operation and MaintenanceThe intake will require little routine maintenance other thanperiodic inspections. Floating debris such as leaves and grass, and any sediment greater than coarse sand in size will beswept over the spillway into the burn downstream. Periodicpigging of the pipelines will be required in order to dislodge anaccumulation of peat slime on the inside walls of the pipes.

The effect of this deposit varies from site to site but can lead tosignificant loss in power output if not dealt with. Piggingfacilities are incorporated in the design of the intakes andpowerhouse.

Monitoring of abstracted flow volumes and energy generationwill be done through the electronic control system of theturbine.