TRANSCRIPT

Page 1: Preferred Alternative Presentation

Hampton Avenue Capital Improvement Project

Danée McGee, P.E. Project Manager: Charlotte Storm Water Services

Cliff Nelson, P.E.Project Manager: Baker Engineering, Inc.

October 11, 2012

Baker Engineering

Page 2: Preferred Alternative Presentation

Project Team & Meeting Purpose

Charlotte Storm Water Services: Project Management

Baker Engineering: Design Consultant

Explanation of Storm Water Program: Why Are We Here?

Obtain Public Input:Your Part in the Process…

Provide Project Overview: What Are We Doing?

Explanation of Next Steps:What is Coming Next…

Baker Engineering

Page 3: Preferred Alternative Presentation

Charlotte’s Storm Water Program

Water Quality

Maintenance

Capital Improvements

Baker Engineering

Page 4: Preferred Alternative Presentation

During the project:

Public Input

– Mailers Every Four Months – Website Updates: http://Stormwater.Charmeck.Org

– Public Meetings

– Questionnaires and Property Owner Surveys

– Email and Phone Contact as Needed

Baker Engineering

Page 5: Preferred Alternative Presentation

Project Phases

1. Planning

2. Design

3. Permitting (401/404)

4. Easement Acquisition

5. Bid & Construction

– Public Involvement Throughout

Baker Engineering

Page 6: Preferred Alternative Presentation

Drainage Conditions in The Neighborhood

Baker Engineering

Page 7: Preferred Alternative Presentation

Hampton Avenue CIP Area

Baker Engineering

Page 8: Preferred Alternative Presentation

Preferred Alternative for Design

Cost/Benefit: $$

Alleviate Structure Flooding:addresses

Alleviate Intersection Flooding: intersections

Repair Aging/Failing Infrastructure:where

Baker Engineering

Page 9: Preferred Alternative Presentation

Final Project Phases - How things Work:

Next Steps

– Design Phase

– 401/404 Permitting

– Easement Acquisition

– Bid and Construction

Baker Engineering

Page 10: Preferred Alternative Presentation

Questions &

Comments