predim.column y vigas zapo
DESCRIPTION
Predimencionamiento de vigas, y columnasTRANSCRIPT
PREDIM.COLUMPREDIMENSIONAMIENTO DE COLUMNAS TIPICAS
TIPO C1ColumnaP = 1.1 x PG(Primeros pisos)interiorn =0.3TIPO C1ColumnaP = 1.1x PG(4 ltimos pisos superiores)interiorn =0.25TIPO C2 , C3ColumnaP = 1.25x PGextremasn =0.25TIPO C4ColumnaP = 1.50x PGesquinan =0.20Columnas C1:
1.- Metrado de Cargas:
P. de losa =280.00(kg/m2)P. de Tabiq =100.00(kg/m2)P. acabad. =100.00(kg/m2)P. viga =100.00(kg/m2)P. Columna =60.00(kg/m2)
CM =640.00(kg/m2)+CV =200.00(kg/m2)CT =840.00(kg/m2)
Luego:PG =88,704.00Kg
b*h =1548.80cm2
b*h =0.40 x 0.40
2.- Considerando el efecto de Cortante Basal:
Uso =ViviendaUbicacin =ChiclayoSuelo =Flexible y blandoZ =0.40U =1.00C =2.50S =1.40Area Edificada = 153.62f c (Kg/cm2) =210.00fy (Kg/cm2) =4200.00
y tambin:
Pe =774,244.80(Kg)
Vc =1,083,942.72(Kg)
h =39.19(cm)
b*h =0.40 x 0.40
Columnas C2:1.- Metrado de Cargas:
P. de losa =280.00(kg/m2)P. de Tabiq =100.00(kg/m2)P. acabad. =100.00(kg/m2)P. viga =100.00(kg/m2)P. Columna =60.00(kg/m2)
CM =640.00(kg/m2)+CV =200.00(kg/m2)CT =840.00(kg/m2)
Luego:PG =31,248.00Kg
b*h =744.00cm2
b*h =0.30 x 0.30
2.- Considerando el efecto de Cortante Basal:
Uso =ViviendaUbicacin =ChiclayoSuelo =Flexible y blandoZ =0.40U =1.00C =2.50S =1.40Area Edificada = 153.62f c (Kg/cm2) =210.00fy (Kg/cm2) =4200.00
y tambin:
Pe =645,204.00(Kg)
Vc =903,285.60(Kg)
h =38.56(cm)
b*h =0.40 x 0.40
Columnas C4:1.- Metrado de Cargas:
P. de losa =280.00(kg/m2)P. de Tabiq =100.00(kg/m2)P. acabad. =100.00(kg/m2)P. viga =100.00(kg/m2)P. Columna =60.00(kg/m2)
CM =640.00(kg/m2)+CV =200.00(kg/m2)CT =840.00(kg/m2)
Luego:PG =26,964.00Kg
b*h =963.00cm2
b*h =0.35 x 0.35
2.- Considerando el efecto de Cortante Basal:
Uso =ViviendaUbicacin =ChiclayoSuelo =Flexible y blandoZ =0.40U =1.00C =2.50S =1.40Area Edificada = 153.62f c (Kg/cm2) =210.00fy (Kg/cm2) =4200.00
y tambin:
Pe =645,204.00(Kg)
Vc =903,285.60(Kg)
h =38.56(cm)
b*h =0.40 x 0.40
PREDIM.VIGAS 1PREDIMENSIONAMIENTO DE VIGAS 1 PISOVIGAS (EJE X-X) :
VP - 101 :b = L/20 = 0.20, pero b mn :0.25cm
Losa :h = L/21 =0.19, entonces asumimos: h =0.20 cm
Por lo tanto :b (cm) =0.2525
1.- Metrado de Cargas:
(h = 0.20 m)P. de losa =300*3.981194.00(kg/m)P. de Tabiq =100*3.98398.00(kg/m)P. acabad. =100*3.98398.00(kg/m)
CM =1990.00(kg/m)
S/C =300*3.981194.00(kg/m)
CV =1194.00(kg/m)
Carga Amplificada =Wu =4815.80(kg/m)
2.- Altura de Viga :
Mo =9535.52(kg x m)
y M =6674.87(kg x m)
d =25.78(cm)
h =32.00
Pero :h = L/10h (cm) =39.80h = L/12h (cm) =33.17
Luego :h (cm) =35.00
Finalmente se asume:Seccin = 0.35 x 0.40
VIGAS (EJE Y-Y) :
VS :b = L/20 = 0.21, pero b mn :0.25cm
Por lo tanto :b (cm) =0.2525
1.- Metrado de Cargas:
P. de losa =300*4.231269.00(kg/m)P. de Tabiq =100*4.23423.00(kg/m)P. acabad. =100*4.23423.00(kg/m)
CM =2115.00(kg/m)
S/C =300*1.451269.00(kg/m)
CV =1269.00(kg/m)
Carga Amplificada =Wu =5118.30(kg/m)
2.- Altura de Viga :
Mo =11447.65(kg x m)
y M =8013.36(kg x m)
d =28.25(cm)
h =34.47
Pero :h = L/10h (cm) =34.00h = L/12h (cm) =28.33
Luego :h (cm) =35.00
Finalmente se asume:Seccin = 0.30 x 0.35
PREDIM.VIGAS MEZANINEPREDIMENSIONAMIENTO DE VIGAS MEZANINEVIGAS (EJE X-X) :
VP - 101 :b = L/20 = 0.20, pero b mn :0.25cm
Losa :h = L/21 =0.19, entonces asumimos: h =0.20 cm
Por lo tanto :b (cm) =0.2525
1.- Metrado de Cargas:
(h = 0.20 m)P. de losa =300*3.981194.00(kg/m)P. de Tabiq =100*3.98398.00(kg/m)P. acabad. =100*3.98398.00(kg/m)
CM =1990.00(kg/m)
S/C =200*3.98796.00(kg/m)
CV =796.00(kg/m)
Carga Amplificada =Wu =4139.20(kg/m)
2.- Altura de Viga :
Mo =8195.82(kg x m)
y M =5737.08(kg x m)
d =23.90(cm)
h =30.12
Pero :h = L/10h (cm) =39.80h = L/12h (cm) =33.17
Luego :h (cm) =35.00
Finalmente se asume: Seccin = 0.35 x 0.40
VIGAS (EJE Y-Y) :
VS :b = L/20 = 0.21, pero b mn :0.25cm
Por lo tanto :b (cm) =0.2525
1.- Metrado de Cargas:
P. de losa =300*4.231269.00(kg/m)P. de Tabiq =100*4.23423.00(kg/m)P. acabad. =100*4.23423.00(kg/m)
CM =2115.00(kg/m)
S/C =200*1.45846.00(kg/m)
CV =846.00(kg/m)
Carga Amplificada =Wu =4399.20(kg/m)
2.- Altura de Viga :
Mo =9839.31(kg x m)
y M =6887.51(kg x m)
d =26.19(cm)
h =32.41
Pero :h = L/10h (cm) =34.00h = L/12h (cm) =28.33
Luego :h (cm) =35.00
Finalmente se asume: Seccin = 0.30 x 0.35
PREDIM.VIGAS 2 AL 5 PISOPREDIMENSIONAMIENTO DE VIGAS 2 al 5 PISOVIGAS (EJE X-X) :
VP - 101 :b = L/20 = 0.20, pero b mn :0.25cm
Losa :h = L/21 =0.19, entonces asumimos: h =0.20 cm
Por lo tanto :b (cm) =0.2525
1.- Metrado de Cargas:
(h = 0.20 m)P. de losa =300*3.981194.00(kg/m)P. de Tabiq =100*3.98398.00(kg/m)P. acabad. =100*3.98398.00(kg/m)
CM =1990.00(kg/m)
S/C =200*3.98796.00(kg/m)
CV =796.00(kg/m)
Carga Amplificada =Wu =4139.20(kg/m)
2.- Altura de Viga :
Mo =8195.82(kg x m)
y M =5737.08(kg x m)
d =23.90(cm)
h =30.12
Pero :h = L/10h (cm) =39.80h = L/12h (cm) =33.17
Luego :h (cm) =35.00
Finalmente se asume:Seccin = 0.35 x 0.40
VIGAS (EJE Y-Y) :
VS :b = L/20 = 0.21, pero b mn :0.25cm
Por lo tanto :b (cm) =0.2525
1.- Metrado de Cargas:
P. de losa =300*4.231269.00(kg/m)P. de Tabiq =100*4.23423.00(kg/m)P. acabad. =100*4.23423.00(kg/m)
CM =2115.00(kg/m)
S/C =200*1.45846.00(kg/m)
CV =846.00(kg/m)
Carga Amplificada =Wu =4399.20(kg/m)
2.- Altura de Viga :
Mo =9839.31(kg x m)
y M =6887.51(kg x m)
d =26.19(cm)
h =32.41
Pero :h = L/10h (cm) =34.00h = L/12h (cm) =28.33
Luego :h (cm) =35.00
Finalmente se asume: Seccin = 0.30 x 0.35