pre-submittal conference · pre-submittal conference february 14, 2017 at 10:00 am cst deadline to...
TRANSCRIPT
![Page 1: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,](https://reader033.vdocuments.mx/reader033/viewer/2022041621/5e3ef6a295f5a91eed20603e/html5/thumbnails/1.jpg)
PRE-SUBMITTAL CONFERENCEREQUEST FOR INFORMATION (RFI)
ENERGY INITIATIVES PROJECTat George Bush Intercontinental Airport (IAH)
SOLICITATION NO. H37-EIPIAH-2017-018
Andre’ K. Morrow, C.P.M., CPPBSr. Procurement Specialist
Houston Airports
Tuesday, February 14, 2017, 10:00 AMSupply Chain Management Office
18600 Lee Rd.Humble, TX 77338
![Page 2: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,](https://reader033.vdocuments.mx/reader033/viewer/2022041621/5e3ef6a295f5a91eed20603e/html5/thumbnails/2.jpg)
IAH Terminal Redevelopment Program
REQUEST FOR INFORMATION FOR ENERGY INITIATIVES PROJECT
at George Bush Intercontinental Airport (IAH)
SOLICITATION NO. H37-EIPIAH-2017-018
![Page 3: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,](https://reader033.vdocuments.mx/reader033/viewer/2022041621/5e3ef6a295f5a91eed20603e/html5/thumbnails/3.jpg)
RFI Pre-Submittal Conference Agenda
3
ENERGY INITIATIVES PROJECT at George Bush Intercontinental Airport (IAH)
SOLICITATION NO. H37-EIPIAH-2017-018
I. Opening Remarks
II. Solicitation Overview
III. Project Scope and Overview
IV. Questions/Answers
Devon Tiner, P.E., PMP
Interim Procurement Officer
Andre’ Morrow, C.P.M., CPPB
Senior Procurement Specialist, HAS
Steven B. Cornell
EPM – Manager of Projects
![Page 4: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,](https://reader033.vdocuments.mx/reader033/viewer/2022041621/5e3ef6a295f5a91eed20603e/html5/thumbnails/4.jpg)
IAH Terminal Redevelopment Program
SOLICITATION OVERVIEW
Andre’ Morrow, C.P.M., CPPBSenior Procurement Specialist, HAS
![Page 5: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,](https://reader033.vdocuments.mx/reader033/viewer/2022041621/5e3ef6a295f5a91eed20603e/html5/thumbnails/5.jpg)
Solicitation Overview
SOLICITATION PURPOSE
The Houston Airport System (HAS) is requesting information and input for
innovative strategies and approaches to identify alternatives available to the
City in connection with its anticipated procurement of the Energy Initiatives
Project (Project) that will support George Bush Intercontinental Airport (IAH)
directly, and moreover, offers the possibility of providing energy for the City’s
electrical loads. The Project is intended to provide energy to meet a
demand at IAH in the order of 45-75MW, whereas an energy solution for the
City’s load could have a capacity in the range of 250MW.
5
ENERGY INITIATIVES PROJECT at George Bush Intercontinental Airport (IAH)
SOLICITATION NO. H37-EIPIAH-2017-018
![Page 6: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,](https://reader033.vdocuments.mx/reader033/viewer/2022041621/5e3ef6a295f5a91eed20603e/html5/thumbnails/6.jpg)
Solicitation Overview
6
Submittals Due Date and Time:
March 21, 2017 @ 2:00 P.M., CST
Questions and Requests for Additional Information
Due Date:
February 17, 2017 @ 12:00 P.M. (Noon), CST must be
received electronically and directed via email to:
ENERGY INITIATIVES PROJECT at George Bush Intercontinental Airport (IAH)
SOLICITATION NO. H37-EIPIAH-2017-018
![Page 7: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,](https://reader033.vdocuments.mx/reader033/viewer/2022041621/5e3ef6a295f5a91eed20603e/html5/thumbnails/7.jpg)
Additonal Information
And Specification Changes
7
Letters of Clarification (LOC):
Responses to questions received from potential
Respondent(s) and any changes to the Scope shall
be confirmed in writing and a LOC will be posted to
the Houston Airport System (HAS) website:
http://www.fly2houston.com prior to submittal due
date.
ENERGY INITIATIVES PROJECT at George Bush Intercontinental Airport (IAH)
SOLICITATION NO. H37-EIPIAH-2017-018
![Page 8: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,](https://reader033.vdocuments.mx/reader033/viewer/2022041621/5e3ef6a295f5a91eed20603e/html5/thumbnails/8.jpg)
Submittal Procedures
8
One (1) original marked “original” signed in BLUE ink and ten
hard (6) copies of the submittals will be received at the address
below not later than 2 P.M. CST, March 21, 2017:
Houston Airport System
Supply Chain Management Office
Attn: Andre’ K. Morrow, Sr. Procurement Specialist
18600 Lee Road
Humble, Texas 77338
Please include the phrase “RFI No.: H37-EIPIAH-2017-018 , Energy Initiatives Project at George Bush Intercontinental
Airport (IAH)” in the subject line and provide all applicable
contact information.
ENERGY INITIATIVES PROJECT at George Bush Intercontinental Airport (IAH)
SOLICITATION NO. H37-EIPIAH-2017-018
![Page 9: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,](https://reader033.vdocuments.mx/reader033/viewer/2022041621/5e3ef6a295f5a91eed20603e/html5/thumbnails/9.jpg)
Submittal Procedures
9
Each Submittal must be organized and follow the required
format as stated in section 6.0 of the RFI.
Each Section must be appropriately tabbed.
ENERGY INITIATIVES PROJECT at George Bush Intercontinental Airport (IAH)
SOLICITATION NO. H37-EIPIAH-2017-018
All recommendations and comments are welcomed and will
be reviewed and considered. All recommendation(s) of
good merit and clear business logic and methodology may
be used and incorporated into the final RFQ/P solicitation
document.
![Page 10: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,](https://reader033.vdocuments.mx/reader033/viewer/2022041621/5e3ef6a295f5a91eed20603e/html5/thumbnails/10.jpg)
RFI SCHEDULE
10
ENERGY INITIATIVES PROJECT at George Bush Intercontinental Airport (IAH)
SOLICITATION NO. H37-EIPIAH-2017-018
Event * Date and Time
RFI Release Date February 3, 2017
Pre-Submittal Conference February 14, 2017 at 10:00 AM CST
Deadline to Submit Questions February 17, 2017 at 12:00 PM CST
RFI Response Due Date March 21, 2017 at 2:00 PM CST
* The City may release an RFQ/P after reviewing the responses to this RFI.
![Page 11: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,](https://reader033.vdocuments.mx/reader033/viewer/2022041621/5e3ef6a295f5a91eed20603e/html5/thumbnails/11.jpg)
IAH Terminal Redevelopment Program 2015
Energy Initiatives Introduction – Bob Barker
11
![Page 12: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,](https://reader033.vdocuments.mx/reader033/viewer/2022041621/5e3ef6a295f5a91eed20603e/html5/thumbnails/12.jpg)
IAH Terminal Redevelopment Program
IAH Introduction
12
Central Utility Plant
Central Terminal Area (CTA)
Greens Road
Substation
Intercontinental
Substation
![Page 13: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,](https://reader033.vdocuments.mx/reader033/viewer/2022041621/5e3ef6a295f5a91eed20603e/html5/thumbnails/13.jpg)
IAH Terminal Redevelopment Program 2015
EI Purpose and Existing Conditions – Steve Cornell
13
![Page 14: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,](https://reader033.vdocuments.mx/reader033/viewer/2022041621/5e3ef6a295f5a91eed20603e/html5/thumbnails/14.jpg)
IAH Terminal Redevelopment Program
ENERGY INITIATIVES PURPOSE
1. Improve Reliability of Electrical Supply and Distribution
2. Improve Electrical Supply and Distribution Systems Resilience
3. Provide Opportunities for More Sustainable and Diverse Energy Supply
4. Renew Aged Electrical Infrastructure
14
![Page 15: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,](https://reader033.vdocuments.mx/reader033/viewer/2022041621/5e3ef6a295f5a91eed20603e/html5/thumbnails/15.jpg)
IAH Terminal Redevelopment Program
IAH Electrical System - Existing Challenges
Complexity
Each terminal is served by multiple service points and meters
Reliability
Multiple, aged terminal feeders operating at 50% load or higher
Manual throw over (MTO) switches installed at some terminals in lieu of Automatic throw over (ATO) switches
Ownership
Current distribution system prevents effective load aggregation by COH/HAS for alternative delivery strategies
15
![Page 16: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,](https://reader033.vdocuments.mx/reader033/viewer/2022041621/5e3ef6a295f5a91eed20603e/html5/thumbnails/16.jpg)
IAH Terminal Redevelopment Program
Existing Electrical Substations and Feeders
Substations and Central
Terminal Area (CTA)
Distribution Owned and
Operated by CenterPoint
Energy
Infrastructure Cost and
O&M Recovered Through
Electric Service
Transmission & Distribution
(T&D) Cost Component of
Tariff Rate Structure
Each Facility has Individual
Service Point Entrance
with Dual Substation
Feeds, Transformers and
HAS-Owned Switchgear
IAH Substation
Greens Road Substation
IT Substation :
Feeders To CTA
GR Substation:
Feeders To CTA
Configuration For Illustration Purposes Only
Intercontinental Substation
16
![Page 17: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,](https://reader033.vdocuments.mx/reader033/viewer/2022041621/5e3ef6a295f5a91eed20603e/html5/thumbnails/17.jpg)
IAH Terminal Redevelopment Program
CTA Electrical Distribution - Existing
17
IAH CTA Transformer and Meter Locations(does not include UAL)
West Central Terminal Area
East Central Terminal Area
![Page 18: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,](https://reader033.vdocuments.mx/reader033/viewer/2022041621/5e3ef6a295f5a91eed20603e/html5/thumbnails/18.jpg)
IAH Terminal Redevelopment Program
IAH Electrical System - Solutions
Complexity: Simplify
Reconnect terminals to centralized distribution system (Utilidor + dedicated Electrical Power Station (EPS)
Reliability: Upgrade with New Feeders
Provide new feeder distribution pathways and conductors
Provide automatic throw over (ATO) via new centralized switching system
Ownership: HAS Ownership of Distribution
Aggregate CTA loads via new centralized distribution system to enable alternative Energy Infrastructure initiatives
18
![Page 19: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,](https://reader033.vdocuments.mx/reader033/viewer/2022041621/5e3ef6a295f5a91eed20603e/html5/thumbnails/19.jpg)
IAH Terminal Redevelopment Program
• OPTION 1 - 138 kV Substation • OPTION 2 - CHP & 138 kV Substation• OPTION 3+ - Alternative Solutions
• Master Metering
• 12.47 kV Switches
• 12.47 kV Feeders
• Provides Pathway for Feeders• Also pathway for Other Utilities & IT
• Transformers• 480 Volt Terminal Services
FUTURE ENERGY DELIVERY SYSTEM
19
![Page 20: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,](https://reader033.vdocuments.mx/reader033/viewer/2022041621/5e3ef6a295f5a91eed20603e/html5/thumbnails/20.jpg)
IAH Terminal Redevelopment Program
EUL and EI – Interface Overview
Electrical Utility Landside (EUL) Summary Objectives:
To provide a pathway to install electrical & fiber conduit, racks and innerduct with pullstrings for future conductors & fiber optic cables from Terminal A to MLIT. Fiber infrastructure to continue to old Tracon west of Terminal A.
Energy Infrastructure (EI) Summary Objectives:
To reduce operating load on existing 12.47kV feeders to less than 50% rated capacity to improve reliability
HAS acquire terminal distribution system ownership to support new Energy Infrastructure initiatives
Projected Demand:
Element A: IAH Loads
40MW projected aggregate demand for the IAH Central Terminal Area (CTA) – HAS Load
Min. 5MW UAL Load
Element B: Up to approx. 120MW CoH Loads (inclusive of HAS Loads)
20
![Page 21: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,](https://reader033.vdocuments.mx/reader033/viewer/2022041621/5e3ef6a295f5a91eed20603e/html5/thumbnails/21.jpg)
IAH Terminal Redevelopment Program
Enabling Utilities Landside - Base Scope Project Overview
21
EI
On-Site
Option
![Page 22: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,](https://reader033.vdocuments.mx/reader033/viewer/2022041621/5e3ef6a295f5a91eed20603e/html5/thumbnails/22.jpg)
IAH Terminal Redevelopment Program 2015
Energy Initiatives – Potential Solutions
22
![Page 23: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,](https://reader033.vdocuments.mx/reader033/viewer/2022041621/5e3ef6a295f5a91eed20603e/html5/thumbnails/23.jpg)
IAH Terminal Redevelopment Program
Energy Initiatives Project - Option 1
Off-Site Energy Source
Feeds to 138kV/12.47kV
substation; to electrical power
station (EPS) and EUL
Infrastructure to CTA
Pros:
1. Increased Reliability of
Service - Feeder Loads
2. Reduces cost of Service,
eliminates T&D charges;
3. Supports HAS goal to
centralized CTA Power
distribution via Electrical
Power Station.
Cons:
1. Capital expense,
2. Complexity
3. Long lead time to design
and construct new 138 kV
feeders.
Costs:
To be determined
Intercontinental
Substation
GR Substation:
Feeders to CTA
Energy Initiatives Project to Source Power from Energy Provider and Deliver to CTA on EUL Project Built Infrastructure
IT Substation
(12.47kV) Feeds to
CTA Eliminated
New138kV
Dual Service to
138kV/12.47kV
Substation and
Feed to EPS
℗
Configuration For Illustration Purposes Only
Substation /
Electrical
Power Station
23
IT Substation :
Feeders To CTA
Greens Road
Substation
Greens Road
Substation (12.47kV)
Feeds to CTA
Eliminated
![Page 24: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,](https://reader033.vdocuments.mx/reader033/viewer/2022041621/5e3ef6a295f5a91eed20603e/html5/thumbnails/24.jpg)
IAH Terminal Redevelopment Program
■ Renewable - Alternative Energy Sources - Off-Site
■ Photo-voltaic (PV) energy supplier
■ Wind energy supplier
■ Bio-gas (e.g., sewage treatment)
■ Hydro-electric energy supplier
■ Supplemental Benefits
■ Chilled Water Storage
■ Ice Storage
■ Waste Heat Reuse
Energy Initiatives Project - Option 1 Considerations
24
![Page 25: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,](https://reader033.vdocuments.mx/reader033/viewer/2022041621/5e3ef6a295f5a91eed20603e/html5/thumbnails/25.jpg)
IAH Terminal Redevelopment Program
Energy Initiatives Project - Option 2
On-Site CHP (“COGEN”) plant;
Feeds to12.47kV electrical
power station (EPS) and EUL
Infrastructure to CTA
Pros:
1. Increased Reliability of
Service - Feeder Loads;
2. Reduces cost of Service,
eliminates distribution retail
pricing;
3. Reduction in regional air
emissions.
4. Planned CUP equipment
replacement cost offset.
Cons:
1. Potential contracting
complexity.
Costs:
To be determinedGR Substation:
Feeders To CTA
Energy Initiatives Project to Source Power from On-Site Generation Facility and Deliver to CTA on EUL Project Built Infrastructure
Configuration For Illustration Purposes Only
CHP Plant
Electrical
Power Station
25
IT Substation :
Feeders To CTA
Greens Road
Substation (12.47kV)
Feeds to CTA
Eliminated
IT Substation
(12.47kV) Feeds to
CTA Eliminated
New138kV
Dual Service to
138kV/12.47kV
Substation and
Feed to EPS
Substation
Intercontinental
Substation
Greens Road
Substation
![Page 26: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,](https://reader033.vdocuments.mx/reader033/viewer/2022041621/5e3ef6a295f5a91eed20603e/html5/thumbnails/26.jpg)
IAH Terminal Redevelopment Program
Project Delivery Method Considerations
■ A Project Delivery Method is the contractual structure (exclusive of the
financial arrangements) of how the final project is delivered to the Owner. The
various project delivery methods are often consolidated into four (4) basic
approaches:
■ Design-Bid-Build (DBB) - the traditional project delivery method, which involves three sequential project phases: design, procurement, and construction
■ Construction Manager at Risk (CMAR) – a project delivery method in which the construction manager acts as a consultant to the owner in the development and design phases, but assumes the responsibility for construction performance as the equivalent of a general contractor holding all trade subcontracts during the construction phase
■ Design-Build (DB) – a project delivery method that combines design services with construction performance under one contract
■ Design-Build-Operate-Maintain (DBOM) – a project delivery method that combines design services with construction performance under one contract plus follow-on performance of operation and maintenance of built facilities
■ Project Delivery Method w/ Financing
■ DBOMF / Public Private Partnership is a delivery method whereby a public entity partners with a private entity for the purpose of delivering public infrastructure.
26
![Page 27: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,](https://reader033.vdocuments.mx/reader033/viewer/2022041621/5e3ef6a295f5a91eed20603e/html5/thumbnails/27.jpg)
IAH Terminal Redevelopment Program
Next Steps
■ Receive responses to Request for Information(RFI) 21 March 2017
■ Review responses and select delivery option(s)
■ Proceed with procurement via public bidding process – 2nd – 3rd Quarter 2017
■ Prepare and issue Two-Step RFQ package
■ Receive & evaluate respondent’s Statement of Qualifications (SOQ)
■ Establish short list to receive Technical Proposals
■ Receive & evaluate respondents’ Technical & Financial proposals
■ Award Energy Infrastructure Contract 4th Quarter 2017 (estimated)
27
![Page 28: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,](https://reader033.vdocuments.mx/reader033/viewer/2022041621/5e3ef6a295f5a91eed20603e/html5/thumbnails/28.jpg)
IAH Terminal Redevelopment Program 2015
Questions & Answers
28
Questions and Requests for Additional Information must be received
electronically and directed via email to: [email protected].
Helpful Links:
IAH Terminal Redevelopment Program (ITRP) and Energy Infrastructure Industry Day Power Point Presentation and Sign-In Sheets.
http://www.houstonairports.biz/0/3921886/0/94600D95659/