PRE-SUBMITTAL CONFERENCE REQUEST FOR INFORMATION (RFI) ENERGY INITIATIVES PROJECT at George Bush Intercontinental Airport (IAH) SOLICITATION NO. H37-EIPIAH-2017-018 Andre’ K. Morrow, C.P.M., CPPB Sr. Procurement Specialist Houston Airports Tuesday, February 14, 2017, 10:00 AM Supply Chain Management Office 18600 Lee Rd. Humble, TX 77338

Upload: others

Post on 23-Jan-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,

PRE-SUBMITTAL CONFERENCEREQUEST FOR INFORMATION (RFI)

ENERGY INITIATIVES PROJECTat George Bush Intercontinental Airport (IAH)

SOLICITATION NO. H37-EIPIAH-2017-018

Andre’ K. Morrow, C.P.M., CPPBSr. Procurement Specialist

Houston Airports

Tuesday, February 14, 2017, 10:00 AMSupply Chain Management Office

18600 Lee Rd.Humble, TX 77338

Page 2: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,

IAH Terminal Redevelopment Program

REQUEST FOR INFORMATION FOR ENERGY INITIATIVES PROJECT

at George Bush Intercontinental Airport (IAH)

SOLICITATION NO. H37-EIPIAH-2017-018

Page 3: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,

RFI Pre-Submittal Conference Agenda

3

ENERGY INITIATIVES PROJECT at George Bush Intercontinental Airport (IAH)

SOLICITATION NO. H37-EIPIAH-2017-018

I. Opening Remarks

II. Solicitation Overview

III. Project Scope and Overview

IV. Questions/Answers

Devon Tiner, P.E., PMP

Interim Procurement Officer

Andre’ Morrow, C.P.M., CPPB

Senior Procurement Specialist, HAS

Steven B. Cornell

EPM – Manager of Projects

Page 4: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,

IAH Terminal Redevelopment Program

SOLICITATION OVERVIEW

Andre’ Morrow, C.P.M., CPPBSenior Procurement Specialist, HAS

Page 5: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,

Solicitation Overview

SOLICITATION PURPOSE

The Houston Airport System (HAS) is requesting information and input for

innovative strategies and approaches to identify alternatives available to the

City in connection with its anticipated procurement of the Energy Initiatives

Project (Project) that will support George Bush Intercontinental Airport (IAH)

directly, and moreover, offers the possibility of providing energy for the City’s

electrical loads. The Project is intended to provide energy to meet a

demand at IAH in the order of 45-75MW, whereas an energy solution for the

City’s load could have a capacity in the range of 250MW.

5

ENERGY INITIATIVES PROJECT at George Bush Intercontinental Airport (IAH)

SOLICITATION NO. H37-EIPIAH-2017-018

Page 6: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,

Solicitation Overview

6

Submittals Due Date and Time:

March 21, 2017 @ 2:00 P.M., CST

Questions and Requests for Additional Information

Due Date:

February 17, 2017 @ 12:00 P.M. (Noon), CST must be

received electronically and directed via email to:

[email protected].

ENERGY INITIATIVES PROJECT at George Bush Intercontinental Airport (IAH)

SOLICITATION NO. H37-EIPIAH-2017-018

Page 7: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,

Additonal Information

And Specification Changes

7

Letters of Clarification (LOC):

Responses to questions received from potential

Respondent(s) and any changes to the Scope shall

be confirmed in writing and a LOC will be posted to

the Houston Airport System (HAS) website:

http://www.fly2houston.com prior to submittal due

date.

ENERGY INITIATIVES PROJECT at George Bush Intercontinental Airport (IAH)

SOLICITATION NO. H37-EIPIAH-2017-018

Page 8: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,

Submittal Procedures

8

One (1) original marked “original” signed in BLUE ink and ten

hard (6) copies of the submittals will be received at the address

below not later than 2 P.M. CST, March 21, 2017:

Houston Airport System

Supply Chain Management Office

Attn: Andre’ K. Morrow, Sr. Procurement Specialist

18600 Lee Road

Humble, Texas 77338

Please include the phrase “RFI No.: H37-EIPIAH-2017-018 , Energy Initiatives Project at George Bush Intercontinental

Airport (IAH)” in the subject line and provide all applicable

contact information.

ENERGY INITIATIVES PROJECT at George Bush Intercontinental Airport (IAH)

SOLICITATION NO. H37-EIPIAH-2017-018

Page 9: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,

Submittal Procedures

9

Each Submittal must be organized and follow the required

format as stated in section 6.0 of the RFI.

Each Section must be appropriately tabbed.

ENERGY INITIATIVES PROJECT at George Bush Intercontinental Airport (IAH)

SOLICITATION NO. H37-EIPIAH-2017-018

All recommendations and comments are welcomed and will

be reviewed and considered. All recommendation(s) of

good merit and clear business logic and methodology may

be used and incorporated into the final RFQ/P solicitation

document.

Page 10: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,

RFI SCHEDULE

10

ENERGY INITIATIVES PROJECT at George Bush Intercontinental Airport (IAH)

SOLICITATION NO. H37-EIPIAH-2017-018

Event * Date and Time

RFI Release Date February 3, 2017

Pre-Submittal Conference February 14, 2017 at 10:00 AM CST

Deadline to Submit Questions February 17, 2017 at 12:00 PM CST

RFI Response Due Date March 21, 2017 at 2:00 PM CST

* The City may release an RFQ/P after reviewing the responses to this RFI.

Page 11: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,

IAH Terminal Redevelopment Program 2015

Energy Initiatives Introduction – Bob Barker

11

Page 12: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,

IAH Terminal Redevelopment Program

IAH Introduction

12

Central Utility Plant

Central Terminal Area (CTA)

Greens Road

Substation

Intercontinental

Substation

Page 13: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,

IAH Terminal Redevelopment Program 2015

EI Purpose and Existing Conditions – Steve Cornell

13

Page 14: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,

IAH Terminal Redevelopment Program

ENERGY INITIATIVES PURPOSE

1. Improve Reliability of Electrical Supply and Distribution

2. Improve Electrical Supply and Distribution Systems Resilience

3. Provide Opportunities for More Sustainable and Diverse Energy Supply

4. Renew Aged Electrical Infrastructure

14

Page 15: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,

IAH Terminal Redevelopment Program

IAH Electrical System - Existing Challenges

Complexity

Each terminal is served by multiple service points and meters

Reliability

Multiple, aged terminal feeders operating at 50% load or higher

Manual throw over (MTO) switches installed at some terminals in lieu of Automatic throw over (ATO) switches

Ownership

Current distribution system prevents effective load aggregation by COH/HAS for alternative delivery strategies

15

Page 16: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,

IAH Terminal Redevelopment Program

Existing Electrical Substations and Feeders

Substations and Central

Terminal Area (CTA)

Distribution Owned and

Operated by CenterPoint

Energy

Infrastructure Cost and

O&M Recovered Through

Electric Service

Transmission & Distribution

(T&D) Cost Component of

Tariff Rate Structure

Each Facility has Individual

Service Point Entrance

with Dual Substation

Feeds, Transformers and

HAS-Owned Switchgear

IAH Substation

Greens Road Substation

IT Substation :

Feeders To CTA

GR Substation:

Feeders To CTA

Configuration For Illustration Purposes Only

Intercontinental Substation

16

Page 17: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,

IAH Terminal Redevelopment Program

CTA Electrical Distribution - Existing

17

IAH CTA Transformer and Meter Locations(does not include UAL)

West Central Terminal Area

East Central Terminal Area

Page 18: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,

IAH Terminal Redevelopment Program

IAH Electrical System - Solutions

Complexity: Simplify

Reconnect terminals to centralized distribution system (Utilidor + dedicated Electrical Power Station (EPS)

Reliability: Upgrade with New Feeders

Provide new feeder distribution pathways and conductors

Provide automatic throw over (ATO) via new centralized switching system

Ownership: HAS Ownership of Distribution

Aggregate CTA loads via new centralized distribution system to enable alternative Energy Infrastructure initiatives

18

Page 19: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,

IAH Terminal Redevelopment Program

• OPTION 1 - 138 kV Substation • OPTION 2 - CHP & 138 kV Substation• OPTION 3+ - Alternative Solutions

• Master Metering

• 12.47 kV Switches

• 12.47 kV Feeders

• Provides Pathway for Feeders• Also pathway for Other Utilities & IT

• Transformers• 480 Volt Terminal Services

FUTURE ENERGY DELIVERY SYSTEM

19

Page 20: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,

IAH Terminal Redevelopment Program

EUL and EI – Interface Overview

Electrical Utility Landside (EUL) Summary Objectives:

To provide a pathway to install electrical & fiber conduit, racks and innerduct with pullstrings for future conductors & fiber optic cables from Terminal A to MLIT. Fiber infrastructure to continue to old Tracon west of Terminal A.

Energy Infrastructure (EI) Summary Objectives:

To reduce operating load on existing 12.47kV feeders to less than 50% rated capacity to improve reliability

HAS acquire terminal distribution system ownership to support new Energy Infrastructure initiatives

Projected Demand:

Element A: IAH Loads

40MW projected aggregate demand for the IAH Central Terminal Area (CTA) – HAS Load

Min. 5MW UAL Load

Element B: Up to approx. 120MW CoH Loads (inclusive of HAS Loads)

20

Page 21: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,

IAH Terminal Redevelopment Program

Enabling Utilities Landside - Base Scope Project Overview

21

EI

On-Site

Option

Page 22: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,

IAH Terminal Redevelopment Program 2015

Energy Initiatives – Potential Solutions

22

Page 23: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,

IAH Terminal Redevelopment Program

Energy Initiatives Project - Option 1

Off-Site Energy Source

Feeds to 138kV/12.47kV

substation; to electrical power

station (EPS) and EUL

Infrastructure to CTA

Pros:

1. Increased Reliability of

Service - Feeder Loads

2. Reduces cost of Service,

eliminates T&D charges;

3. Supports HAS goal to

centralized CTA Power

distribution via Electrical

Power Station.

Cons:

1. Capital expense,

2. Complexity

3. Long lead time to design

and construct new 138 kV

feeders.

Costs:

To be determined

Intercontinental

Substation

GR Substation:

Feeders to CTA

Energy Initiatives Project to Source Power from Energy Provider and Deliver to CTA on EUL Project Built Infrastructure

IT Substation

(12.47kV) Feeds to

CTA Eliminated

New138kV

Dual Service to

138kV/12.47kV

Substation and

Feed to EPS

Configuration For Illustration Purposes Only

Substation /

Electrical

Power Station

23

IT Substation :

Feeders To CTA

Greens Road

Substation

Greens Road

Substation (12.47kV)

Feeds to CTA

Eliminated

Page 24: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,

IAH Terminal Redevelopment Program

■ Renewable - Alternative Energy Sources - Off-Site

■ Photo-voltaic (PV) energy supplier

■ Wind energy supplier

■ Bio-gas (e.g., sewage treatment)

■ Hydro-electric energy supplier

■ Supplemental Benefits

■ Chilled Water Storage

■ Ice Storage

■ Waste Heat Reuse

Energy Initiatives Project - Option 1 Considerations

24

Page 25: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,

IAH Terminal Redevelopment Program

Energy Initiatives Project - Option 2

On-Site CHP (“COGEN”) plant;

Feeds to12.47kV electrical

power station (EPS) and EUL

Infrastructure to CTA

Pros:

1. Increased Reliability of

Service - Feeder Loads;

2. Reduces cost of Service,

eliminates distribution retail

pricing;

3. Reduction in regional air

emissions.

4. Planned CUP equipment

replacement cost offset.

Cons:

1. Potential contracting

complexity.

Costs:

To be determinedGR Substation:

Feeders To CTA

Energy Initiatives Project to Source Power from On-Site Generation Facility and Deliver to CTA on EUL Project Built Infrastructure

Configuration For Illustration Purposes Only

CHP Plant

Electrical

Power Station

25

IT Substation :

Feeders To CTA

Greens Road

Substation (12.47kV)

Feeds to CTA

Eliminated

IT Substation

(12.47kV) Feeds to

CTA Eliminated

New138kV

Dual Service to

138kV/12.47kV

Substation and

Feed to EPS

Substation

Intercontinental

Substation

Greens Road

Substation

Page 26: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,

IAH Terminal Redevelopment Program

Project Delivery Method Considerations

■ A Project Delivery Method is the contractual structure (exclusive of the

financial arrangements) of how the final project is delivered to the Owner. The

various project delivery methods are often consolidated into four (4) basic

approaches:

■ Design-Bid-Build (DBB) - the traditional project delivery method, which involves three sequential project phases: design, procurement, and construction

■ Construction Manager at Risk (CMAR) – a project delivery method in which the construction manager acts as a consultant to the owner in the development and design phases, but assumes the responsibility for construction performance as the equivalent of a general contractor holding all trade subcontracts during the construction phase

■ Design-Build (DB) – a project delivery method that combines design services with construction performance under one contract

■ Design-Build-Operate-Maintain (DBOM) – a project delivery method that combines design services with construction performance under one contract plus follow-on performance of operation and maintenance of built facilities

■ Project Delivery Method w/ Financing

■ DBOMF / Public Private Partnership is a delivery method whereby a public entity partners with a private entity for the purpose of delivering public infrastructure.

26

Page 27: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,

IAH Terminal Redevelopment Program

Next Steps

■ Receive responses to Request for Information(RFI) 21 March 2017

■ Review responses and select delivery option(s)

■ Proceed with procurement via public bidding process – 2nd – 3rd Quarter 2017

■ Prepare and issue Two-Step RFQ package

■ Receive & evaluate respondent’s Statement of Qualifications (SOQ)

■ Establish short list to receive Technical Proposals

■ Receive & evaluate respondents’ Technical & Financial proposals

■ Award Energy Infrastructure Contract 4th Quarter 2017 (estimated)

27

Page 28: PRE-SUBMITTAL CONFERENCE · Pre-Submittal Conference February 14, 2017 at 10:00 AM CST Deadline to Submit Questions February 17, 2017 at 12:00 PM CST RFI Response Due Date March 21,

IAH Terminal Redevelopment Program 2015

Questions & Answers

28

Questions and Requests for Additional Information must be received

electronically and directed via email to: [email protected].