COMPANY PROFILE 2017 ش.ذ.م.م- ﺳﻴﻒ ﻓﻴﻮﺗﺸﺮ ﻟﻠﺨﺪﻣﺎت اﻟﻔﻨﻴﺔSAFEFUTURE TECHNICAL SERVICES - L.L.C www . safefuture . ae PRE-QUALIFICATION MANUAL PRE-QUALIFICATION MANUAL

Upload: ngokhanh

Post on 27-May-2018

234 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PRE-QUALIFICATION MANUAL - safefuture.cosafefuture.co/wp-content/uploads/Safe-Future-Company-Profile.pdf · Method of Statement ... calcium silicate, water & fire resistant gypsum

COMPANYPROFILEسيف فيوتشر للخدمات الفنية - ش.ذ.م.م2017

SAFEFUTURET E C H N I C A L S E R V I C E S - L . L . C

w w w . s a f e f u t u r e . a e

PRE-QUALIFICATIONMANUAL

PRE-QUALIFICATIONMANUAL

Page 2: PRE-QUALIFICATION MANUAL - safefuture.cosafefuture.co/wp-content/uploads/Safe-Future-Company-Profile.pdf · Method of Statement ... calcium silicate, water & fire resistant gypsum

TABLE OF CONTENTS

SAFEFUTURET E C H N I C A L S E R V I C E S - L . L . C

Contents

1 About Us

2

2.1

3

Method of Statement

Quality Policy Statement

Organization Chart

False ceilings and Partitioning

11 - 12

4 - 10

False ceilings and Partitioning Projects Profile

13 - 15 Safety Systems

16 - 17 Safety Systems Projects Profile

18 Security and Surveillance Systems

19 Security and Surveillance Systems Projects Profie

24 -32 Certificates

33 Contact Us

Page 3: PRE-QUALIFICATION MANUAL - safefuture.cosafefuture.co/wp-content/uploads/Safe-Future-Company-Profile.pdf · Method of Statement ... calcium silicate, water & fire resistant gypsum

سيف فيوتشر للخدمات الفنية - ش.ذ.م.م

SAFEFUTURET E C H N I C A L S E R V I C E S - L . L . C

Mission

Quality Policy

Why SafeFutureTo be recognized for the high quality finish of works that gives us pride by making a difference and change homes and offices.

Our experience team will always look to improve in design and quality of work which allows us to standing out in the market.

Professional Communication We believe that a healthy Communication with the customers is the key to understanding what they need. We maintain top of the class, two-way communication with all of our customers to ensure understanding and satisfaction.

Skilled Workers

We employ highly skilled and %100 dedicated labor to make sure that all the work is done in the most efficient way. We pride ourselves on the skills of our labor.

Timely Completion

We believe that timing is everything. During every single project, a great deal of attention is given on the timetables to make sure the punctuality stays intact. We have a proven record of always finishing our projects in time.

Customer Satisfaction

Our priority on the satisfaction of our customers. We are flexible, understanding and employ an excellent level of personalization in every project. If you are happy with the services, we are happy!

Trustworthy and Dependability

We take our work and our customer-relationship very seriously. We make sure that you are able to rely on us and we deliver perfect, user-tailored results. Our team of experts and top-notch services make sure that you can trust us and depend on us.

Our Philosophy Is to focus on prevention and every individu-al/team is committed to doing the right things from the first time every time. We believe Quality, Health, Safety and Environment protection is responsibility of everybody.

The company is committed to prioritizing the health and safety of every person involved in our cooperation as well as the protection of the environment where those operations take place. Through continual improvement we will keep meeting and exceeding the expectations of our customers, employees, contractors and third parties.

In order to achieve this goal we:

Provide services of the highest possible standards to satisfy our customers need, expectation of quality, reliability and service.Demonstrate commitment towards prevent of injury and ill health.Conserve and preserve the environment where we work and live.Ensure pollution prevent.Comply with all applicable legislations, regulations, and requirements of international standards and other requirements to which we subscribe.Ensure occupational health and safety risk of our personnel are identified and necessary control measures are taken.

Vision

SAFEFUTURE Technical ServicesGeneral Company Profile

Page No: 1

Page 4: PRE-QUALIFICATION MANUAL - safefuture.cosafefuture.co/wp-content/uploads/Safe-Future-Company-Profile.pdf · Method of Statement ... calcium silicate, water & fire resistant gypsum

Method of StatementIntroduction:

Program:

This method statement of SAFE FUTURE TECHNICAL L.L.C gives brief details of process flow right from the initiation of confirmed order to installation and handling over.

Immediately upon receipt of confirmation of order, based on require-ments followed by detailed discussion with the project manager of the main contractor the following program is chalked out by the contracts department.

Shop drawing submission and approvalsMiniature samples submission and approvalsMock-upMaterial procurement

Material:3

Materials mainly used is gypsum board, cement board, calcium silicate, water & fire resistant gypsum board.

Gypsum cast - Cornice - Columns - Arches - Domes - Ceiling RoseAll the above will be in accordance with contract specification and submitted forapproval before ordering. Any requirement will be incorporated duringmanufacturing.

1

2

a

b

c

3

Maintenance Work

Decoration Work

Manufactures

Ceiling Board:

Dry Wall Partition:

Ceiling Tile:

G.R.G 600x600 mm tileGypsum vinyl 600x600 mm tileAluminum 600x600 mm tileStainless steel 600x600 mm tile & any design

Installation:4

Installation will be done according to the specification and approved shop drawings by using advanced tools.

Installation will be done according to the submitted installation program which is based on the main contractor’s program.

All rubbish that is Packing and Protection material of WHITE CROWN will be removed to designated skip location provided by main contractor.

Any snagging given will be attended on top priority basis,

Prior to handling over, our own inspection team will be thoroughly check our work and attend to the snags if any.

سيف فيوتشر للخدمات الفنية - ش.ذ.م.م

SAFEFUTURET E C H N I C A L S E R V I C E S - L . L . C

Method of Statement

1

2

SAFEFUTURE Technical ServicesGeneral Company Profile

Page No: 2

Page 5: PRE-QUALIFICATION MANUAL - safefuture.cosafefuture.co/wp-content/uploads/Safe-Future-Company-Profile.pdf · Method of Statement ... calcium silicate, water & fire resistant gypsum

SAFEFUTURE Technical ServicesGeneral Company Profile

Page No: 2.1

سيف فيوتشر للخدمات الفنية - ش.ذ.م.م

SAFEFUTURET E C H N I C A L S E R V I C E S - L . L . C Quality Policy Statement

All SAFE FUTURE TECHNICAL SERVICES LLC employees are guided by SAFE FUTURE TECHNICAL SERVICES LLC Quality Policy in all decisions and actions on daily basis. Our goal is to provide the following:

The SAFE FUTURE TECHNICAL SERVICES LLC management realizes that success in the future depends upon achieving these goals by:

SAFE FUTURE TECHNICAL SERVICES LLC will not compromise the integrity of our services in an attempt to satisfy short-term goals. We are committed to long term growth, profitability and employment for our personnel and will achieve this by utilizing a business approach that takes into account the needs of all our stakeholders (e.g. employees, partners, suppliers, customers and the environment) and which encompasses an attitude of “Quality First”.

A product and service solution which meets our customer’s expectation.

A highly trustworthy and ethical work environment that provides long-term employment, development, and growth for all employees.

Continual improvement in all that we perform.

Promoting a work ethic which is predicated upon quality, health, safety and environment.

Providing all employees with the training and tools necessary to perform their job in the most efficient and effective manner possible.

Providing the necessary resources and personal support required for successful implementation of ISO 9001:2015 Quality Management System and Quality Objectives.

General ManagerSFT-QSF-MGT-F01

Page 6: PRE-QUALIFICATION MANUAL - safefuture.cosafefuture.co/wp-content/uploads/Safe-Future-Company-Profile.pdf · Method of Statement ... calcium silicate, water & fire resistant gypsum

.م.م

.ذش

نيلف

ت اما

خد لل

شروت

فيف

سي

SAFE

FUTU

RET

EC

HN

ICA

L S

ER

VIC

ES

- L

.L.C

CHA

IRM

AN

Eng.

Kha

lid A

l Lith

y

AC

CO

UNTS

DEP

ART

MEN

T

SEC

URITY

SYS

TEM

S

DEP

ART

MEN

T

SAFE

TY S

YSTE

MS

DEP

ART

MEN

T

CEI

LIN

G &

PA

RTIO

NIN

G

DEP

ART

MEN

T

MEP

DEP

ART

MEN

T

MA

INTE

NA

NC

E

DEP

ART

MEN

T

BUS.

DEV

ELO

PMEN

T

DEP

ART

MEN

T

ESTIM

ATIO

N

DEP

ART

MEN

T

CO

MM

ERC

IAL

DEP

ART

MEN

T

PLA

NN

ING

DEP

ART

MEN

T

HR &

AD

MIN

DEP

ART

MEN

T

MA

NA

GIN

G D

IREC

TOR

BOA

RD M

EMBE

RM

r. G

amal

Osm

an

GEN

ERA

L M

AN

AG

ERBO

ARD

MEM

BER

Eng

Tare

k O

sman

SAFE

FUTU

RE T

echn

ical

Ser

vice

sG

en

era

l C

om

pa

ny

Pro

file

Pag

e N

o:

3

Page 7: PRE-QUALIFICATION MANUAL - safefuture.cosafefuture.co/wp-content/uploads/Safe-Future-Company-Profile.pdf · Method of Statement ... calcium silicate, water & fire resistant gypsum

Our Services

سيف فيوتشر للخدمات الفنية - ش.ذ.م.م

SAFEFUTURET E C H N I C A L S E R V I C E S - L . L . C

False ceilings and Partitioning

Fire Alarm & Fire Fighting Safety Equipment

Security & Surveillance System

Page 8: PRE-QUALIFICATION MANUAL - safefuture.cosafefuture.co/wp-content/uploads/Safe-Future-Company-Profile.pdf · Method of Statement ... calcium silicate, water & fire resistant gypsum

سيف فيوتشر للخدمات الفنية - ش.ذ.م.م

SAFEFUTURET E C H N I C A L S E R V I C E S - L . L . C

Our Services

False ceilings and Partitioning

Types of False Ceiling:False ceilings can be differentiated into many types based on their uses, material used and appearance and visibility.

The major classification based on materials used are listed briefly below:

With years of experience in this sector, we are one of the leading businesses in GCC for all your false ceiling and partition related requirements. Our range of products includes all gypsum related material, including innovative products like BoardeX, which can be used for outside as well as internal places where there is a problem with humidity and moisture, and CoreX, our ultra light gypsum board. Our works also consist of designer finishing false ceilings & dry-wall partitions that can be altered to any need you might have (being humidity issues to fire rated partitions)

We also have a vast choice of designer ceiling tiles that can be used for providing acoustical insulation. The various types of insulation we stock include those that do not need any dismantling of your current ceiling, but simply adding on, with minimal disruption. We also offer the regular ceiling tiles found in various locations like school buildings, studios, hospitals, labs, etc, offering the specifications your need for your business.

At Safe Future we also offer various partitioning solutions, with a choice of double glazing windows, different colored blinds and aluminum frames, as well as door frames and sliding doors for your company needs.

Gypsum false ceiling is a hydrated sulfate of calcium. This type of false ceiling are lightweight, sound insulated, fire resistance, soft and thermally insulated.

Gypsum false ceiling comes in the shape of square boards that are hung with the help of iron framework. The finishing work on these boards like paints, laminates, wallpapers and texture finish gives good look.

Plaster Ceiling is the majorly used material in the construction of false ceiling. POP is obtained when gypsum is heated to a certain degree. It gives the both aesthetical and functional help.

Plaster Ceiling false ceiling are attractive, almost no mainte-nance and has a long life span. They are very excellent insula-tors or heat and cold.

These types of false ceiling don’t only hide the ugly members of structure, ventilation ducts and conduits but also give smooth finish to the ceiling.

SAFEFUTURE Technical ServicesGeneral Company Profile

Page No: 4

1. Gypsum False Ceiling:

2. Plaster Ceiling:

Page 9: PRE-QUALIFICATION MANUAL - safefuture.cosafefuture.co/wp-content/uploads/Safe-Future-Company-Profile.pdf · Method of Statement ... calcium silicate, water & fire resistant gypsum

One of the type of false ceiling used in construction are of glass. It is a non-crystalline material with the property of brittle and transparent. But this can be altered to make it non brittle and non-transparent using some admixtures.

As glass is a good insulator of heat, it can be used for false ceiling. This type of false ceiling improves aesthetical appear-ance of the building.

As metal is a hard and durable material, it is used extensively in the false ceiling. When the metal surface is polished it gives a shiny surface which is a treat for eyes.

The metals used in this are galvanized iron and aluminum. The cost of this ceiling are low as they are easy to install and access. The hidden members of the structure are easily accessed as the panels are easily removable and reattached. The construc-tion cost becomes less as the installation, fixing and maintained is low.

Fiber false ceiling are in high demand for the construction of false ceiling due to low cost and east installation. The material used to manufacture fiber ceiling panels are man made by synthetic and natural minerals. As these are man-made they come in many shapes and sizes.

سيف فيوتشر للخدمات الفنية - ش.ذ.م.م

SAFEFUTURET E C H N I C A L S E R V I C E S - L . L . C

False Ceiling

Wooden false ceiling is used due to its natural textures and pattern. Nowadays this types of false ceiling are used commonly as it gives a pleasant look to the eyes.

Wooden false ceiling being costly, is not used in malls and hospi-tals but can be installed in residential buildings. They can be given various finishes, or painted to get the right look.

Wooden false ceiling has many disadvantages, majorly which are:

Prone to thermite attack. Prone to warping. The room should be thermally controlled.

3. Fiber False Ceiling: 5. Glass False Ceiling:

4. Wooden False Ceiling

6. Metal False Ceiling

SAFEFUTURE Technical ServicesGeneral Company Profile

Page No: 5

Page 10: PRE-QUALIFICATION MANUAL - safefuture.cosafefuture.co/wp-content/uploads/Safe-Future-Company-Profile.pdf · Method of Statement ... calcium silicate, water & fire resistant gypsum

سيف فيوتشر للخدمات الفنية - ش.ذ.م.م

SAFEFUTURET E C H N I C A L S E R V I C E S - L . L . C

False Ceiling

Ceiling Panels

Clip in - PlainClip in System is charecterized by a concealed grid, which gives the ceilinga monolithic appearance. The panels are especially suitable for buildings where smooth and washable surface are required for hygiene reasons.

Dimension:(Complete range of sizes) 600x600 mm600x1200 mm

Thickness:0.6 & 0.7 mm

LAY IN - PlainLAY IN system is characterized by a exposed grid system allow to create ceilings of easy installation providing total access.

Dimension:(Complete range of sizes) 600x600 mm600x1200 mm

Thickness:0.6 & 0.7 mm

Clip in - Perforated

Lay-in - Perforated

Lay in Ceiling PanelsClip in Ceiling Panels

SAFEFUTURE Technical ServicesGeneral Company Profile

Page No: 9

Page 11: PRE-QUALIFICATION MANUAL - safefuture.cosafefuture.co/wp-content/uploads/Safe-Future-Company-Profile.pdf · Method of Statement ... calcium silicate, water & fire resistant gypsum

Description

paper backing on premium quality gypsum board which is best quality.

Water Resistance Tiles

Gypsum Tiles are water resistant and suitable to use in areas like

OYB

ISLAMIC FISSURED FLORAL FLEXFOIL

PETALS YELLOW-FERN PINK-FERN DIAMOND CHAIN

Fire Resistance Tiles

Conform to BSI-British Standard as follows: BS 1230:part 1-1985 & BS 476:part 8-1972

DIAMOND SAFARI FIBER

Gypsum Tiles

TC-66 600 x 600 7,8,9,12 10

Reference Dimensions Thickness Qty / Box

Note: All dimensions are in mm.

سيف فيوتشر للخدمات الفنية - ش.ذ.م.م

SAFEFUTURET E C H N I C A L S E R V I C E S - L . L . C

SAFEFUTURE Technical ServicesGeneral Company Profile

Page No: 6

Page 12: PRE-QUALIFICATION MANUAL - safefuture.cosafefuture.co/wp-content/uploads/Safe-Future-Company-Profile.pdf · Method of Statement ... calcium silicate, water & fire resistant gypsum

TEE 15/24-Grid Main Suspension

Cross Tee

Note: All dimensions are in mm.

Reference Dimensions Length Material Piece / Box

CT15-0.6 25 15 600 Galvanized 75 CT15-1.2 25 15 1200 Galvanized 50 CT24-0.6 25 24 600 Galvanized 75 CT24-1.2 25 24 1200 Galvanized 50

H W

Main Tee

Reference Dimensions Length Material Piece / Box

MT15 38 15 3600 Galvanized 25 MT24 38 24 3600 Galvanized 25

Note: All dimensions are in mm.

H W

L-Angle Reference Dimensions Length Material Piece / Box

ET-L20 20 20 3000 GS Prepainted 25 ET-L25 25 25 3000 GS Prepainted 25

Note: All dimensions are in mm.

Cross Tee 1.2

600mm1200mm

Cross Tee 0.6

600mm

3600mm

A B

Galvanized Steel Prepainted Polyester Coating

tiles.

Consist of Galvanized Steel with Pre-painted Polyester Coating Aluminium or P.P.G.I. Capping.

Consist of Galvanized Steel with Pre-painted Polyester Coating Aluminium or P.P.G.I. Capping.

3000mm

سيف فيوتشر للخدمات الفنية - ش.ذ.م.م

SAFEFUTURET E C H N I C A L S E R V I C E S - L . L . C

SAFEFUTURE Technical ServicesGeneral Company Profile

Page No: 7

Page 13: PRE-QUALIFICATION MANUAL - safefuture.cosafefuture.co/wp-content/uploads/Safe-Future-Company-Profile.pdf · Method of Statement ... calcium silicate, water & fire resistant gypsum

Cross Tee

Note: All dimensions are in mm.

Reference Dimensions Length Material Piece / Box

FCT15-0.6 41 15 600 GS Prepainted 50 FCT15-1.2 41 15 1200 GS Prepainted 50

H W

Main Tee Reference Dimensions Length Material Piece / Box

FMT15 41 15 3600 GS Prepainted 20

Note: All dimensions are in mm.

H W

L-Angle Reference Dimensions Length Material Piece / Box

FT-L20 20 20 3000 GS Prepainted 50FT-L24 24 24 3000 GS Prepainted 40

FINE Grid Main Suspension

A B

Cross Tee 1.241mm

1200mm

Cross Tee 0.641mm

600mm

41mm

300mm 600mm

3600mm

Note: All dimensions are in mm.

Galvanized Steel Prepainted Polyester Coating

tiles.

3000mm

سيف فيوتشر للخدمات الفنية - ش.ذ.م.م

SAFEFUTURET E C H N I C A L S E R V I C E S - L . L . C

SAFEFUTURE Technical ServicesGeneral Company Profile

Page No: 8

Page 14: PRE-QUALIFICATION MANUAL - safefuture.cosafefuture.co/wp-content/uploads/Safe-Future-Company-Profile.pdf · Method of Statement ... calcium silicate, water & fire resistant gypsum

The Classic Panel provides protected openings in ceilings and walls for access to building

can be over painted to blend with the surrounding surface. The Classic Panel is a high quality robust solution suitable for everyday use with all the discrete advantages the client demands of an access panel. Each panel is made to suit the individual tile and combination of tiles being used. This ensures no unsightly tile cuts or visible frames to

door sag to a minimum, thus avoiding chipped tiles caused by the door dropping as it is opened. Whether it is push open or sliding type, TMI is ready to make the access panel as per the client’s request. The Access Panel frame consists of powder coated aluminium frame with Regular, Fire Resistant or Moisture Resistant Gypsum Board with a thickness ranging from 12mm up to 15mm.

Access Panels Most Popular SizesThe most popular sizes of access panels, however, ready to make any size as per the customer and site requirements.

Additional Products

Access Panels

سيف فيوتشر للخدمات الفنية - ش.ذ.م.م

SAFEFUTURET E C H N I C A L S E R V I C E S - L . L . C

SAFEFUTURE Technical ServicesGeneral Company Profile

Page No: 10

Page 15: PRE-QUALIFICATION MANUAL - safefuture.cosafefuture.co/wp-content/uploads/Safe-Future-Company-Profile.pdf · Method of Statement ... calcium silicate, water & fire resistant gypsum

سيف فيوتشر للخدمات الفنية - ش.ذ.م.م

SAFEFUTURET E C H N I C A L S E R V I C E S - L . L . C

Projects Profile

1 Dubai BUILDING G+12AT AL B ARSHA 765,000 COMPLETED GYPSUM WORK

2 Dubai 850,000 COMPLETED GYPSUM WORKBUILDING G+16 AT TECOM BOUTIQUE 7 HOTEL & SUITES

3 Dubai 1,750,000 COMPLETED GYPSUM WORKMARGHAM CONSERVATION MAJLISPOOL & GYMNSIUM

4 Dubai 225,000 COMPLETED GYPSUM &PARTITIONWORK

BUILDING G+4 AT AL KARAMA

5 Dubai 187,000 COMPLETED GYPSUM WORKG+1 FLOOR VILLA AT AL KHAWANEEJFOR MS.KHAWLA AL GHURAIR

6 Dubai 189,000 COMPLETED GYPSUM WORKG+1 FLOOR VILLA AT AL KHAWANEEJFOR MR.NABEEL GERGASH

7 Dubai 478,000 COMPLETED GYPSUM WORKG+1 FLOOR 4 BUILDING AT ABO HAIL FOR MR. KHALAF AL HABTOOR

8 Dubai 789,000 COMPLETED GYPSUM WORKG+1 FLOOR 10 VILLAS AT JUMAIRAH FOR MR. KHALED AL NABOODAH

9 Dubai 674,000 COMPLETED GYPSUM WORKBUILDING G+9 AT DUBAI LAND

10 Dubai 456,000 COMPLETED GYPSUM WORKBUILDING G+9 AT DIB

11 Dubai 238,000 COMPLETED GYPSUM WORK &PARTITION WORK

BUILDING G + MEZZ + 3 + R FORH.H SHEIKHA SHEIKHA ALMAKTOOM AT AL BUTAIN

12 Dubai 260,000 COMPLETED GYPSUM WORKBUILDING G + 3 TYPICAL FOR H.H SHEIKHA SHEIKHA AL MAKTOOM AT AL BADA

13

14

Dubai

Dubai

225,000

365,000

COMPLETED

COMPLETED

GYPSUM WORK

GYPSUM WORK

G + 1 FLOOR VILLA FOR H.HSHEIKHA SHEIKHA BINT SAEED AL MAKTOOM UM SUQEIM

B+G+2 Residentail(Umm Al sheif)

15 Dubai 250,000 GYPSUM WORKB+G+8+H.C. Residential(DUBAI LAND)

16 Dubai 6,500,000 COMPLETED

COMPLETED

GYPSUM WORKB+G+8+ROOF (8 Building) (Dubai Investment Park)

17 Dubai 2,500,000 COMPLETED GYPSUM WORK60 Compound Villas (Ned Al Shiba Third)

No Place Project Name(AED)

Status Type

ProjectVaue

SAFEFUTURE Technical ServicesGeneral Company Profile

Page No: 11

Page 16: PRE-QUALIFICATION MANUAL - safefuture.cosafefuture.co/wp-content/uploads/Safe-Future-Company-Profile.pdf · Method of Statement ... calcium silicate, water & fire resistant gypsum

No Place Project Name Value

(AED)

Project

StatusType

1 SHARJAHB+7P+H.C+30 TYPICAL FLOOR(EMIRATES SAIL) 1.284,000 COMPLETED GYPSUM WORK

2 SHARJAH 685,000 COMPLETED GYPSUM WORKB+3P+H.C+22 TYPICAL FLOOR(AL MAWARED TOWER)

3 SHARJAH 176,000 COMPLETED GYPSUM WORKG+1 FLOOR VILLA AT SHRQAN FOR MR, TAREQ AL SAADY

4 SHARJAH 1.500,000 COMPLETED GYPSUM WORKSHARJAH UNIVERSITY STAFF ACCOMOCATION

5 SHARJAH 214,000 COMPLETED GYPSUM WORKG+1 FLOOR VILLA FOR MR.AWNY AL SAWAN

6 SHARJAH 122,000 COMPLETED GYPSUM WORKG+1 FLOOR VILLA FOR MR HILAL AL DHAHERT

7 SHARJAH 462,000 COMPLETED GYPSUM WORKG+1 FLOOR VILLA FOR MS.AISHA EBRAHEEM

8 SHARJAH 208,000 COMPLETED GYPSUM WORKG+1 FLOOR 10 VILLAS AT JUMAIRAH FOR MR. KHALED AL NABOODAH

9 SHARJAH 1.185,000 COMPLETED GYPSUM WORKB+7P+H.C+42 TYPICAL FLOOR(AL SAREH)

10 SHARJAH 175,000 COMPLETED GYPSUM WORKB+3P+H.C+12 TYPICAL FLOOR(AL KAWTHER BUILDING)

سيف فيوتشر للخدمات الفنية - ش.ذ.م.م

SAFEFUTURET E C H N I C A L S E R V I C E S - L . L . C

Projects Profile

Projects Profile

SAFEFUTURE Technical ServicesGeneral Company Profile

Page No: 12

Page 17: PRE-QUALIFICATION MANUAL - safefuture.cosafefuture.co/wp-content/uploads/Safe-Future-Company-Profile.pdf · Method of Statement ... calcium silicate, water & fire resistant gypsum

Safety SystemsWe are able to supply/install best known product for conventional as well as Analog Addressable Fire Alarm/Fire Fighting Systems & Security systems. All these systems are delivered in accordance with requirements from authorities like Architects, Consultants & Electrical Contractors as well as directly by clients in compliance with standards. A complete team of field service technicians are available for on-site service and maintenance of Fire Alarm, Sprinkler and Fire Fighting System.

EXTERNAL HYDRANT SYSTEM

External fire hydrants are located throughout residential and industrial areas and are supplied by either public or private service underground piping distribution mains. These networks are connected to suitable water storage facilities which utilize fire pumps to distribute water to hydrants.

Due to the high operating pressures and flows discharged thru hose and nozzles, the hydrants must be manually operated by trained personnel i.e. Civil Defense firefighters. The hydrants are also provided with a facility to connect fire hoses direct from Civil Defense fire water storage tankers should the distribution mains be unable to provide adequate water supply or pressure

WATER SPRAY DELUGE SYSTEMS

Water spray deluge systems comprise a distribution of piping and nozzles arranged to provide specific types of protection to identified hazardous equipment e.g. oil storage tanks, transformers etc. Types of protection provided include for effective fire control, extinguish-ment, prevention, or exposure protection.

Water supply to the piping and ‘open type’ nozzles is controlled via automatic or manually operated deluge control valves. Calculations determine appropriate water ‘density application rates’ to provide the type fire protection system required to be installed

Our Major Activities & Services:

Analysis and evaluation of Fire & Security Risks.Free survey of premises, which are to be protected, advice and assistance on all types of Fire and Security requirements.We are specialized in Supply, Installation, and Maintenance of:All types of Fire ExtinguishersDry & Wet stand pipe systemsFire Hydrants (all types)All types of valvesAll kinds of Piping & Related Fittings (G.I, PVC etc.)Sprinkler SystemsFM 200 fire suppression systemFire alarm system (both Conventional and Addressable)Firefighting pumps (UL and non UL listed)Emergency lighting systemProviding training to Security Staff for operation of systems and preventing further losses.After Installation/Service, during contract period, to keep the systems functional to its fullest capacity.Four times site visit during the annual contract period and free emergency call out service.

SAFEFUTURE Technical ServicesGeneral Company Profile

Page No: 13

Our ServicesSafety Systms

سيف فيوتشر للخدمات الفنية - ش.ذ.م.م

SAFEFUTURET E C H N I C A L S E R V I C E S - L . L . C

Page 18: PRE-QUALIFICATION MANUAL - safefuture.cosafefuture.co/wp-content/uploads/Safe-Future-Company-Profile.pdf · Method of Statement ... calcium silicate, water & fire resistant gypsum

Foam Systems

Selection of system protection to be installed is dependent upon identification of either Class A or Class B type fire. Generally foam / water deluge systems are designed to extinguish flammable liquid hazards, e.g. within bund areas containing oil storage tanks. Selection of suitable discharge devices provide various options to distribute either externally or internally, e.g. foam pourers at top of large capacity vertical oil storage tanks

FIRE SUPPRESSION SYSTEM

We are leaders in suppression system. We design, test commis-sion, service and maintain wide range of fire Suppression system such as FM200, NOVEC, Argonite, HPCO2, LPCO2, High Pressure Water Mist, Dry Chemical and Fire PASS system. Our factory trained & Certified engineer carryout in house Design, Drawings & Calculations in accordance with the requirements of International Standards & using latest softwares.

Fire & Gas Detection System

Fully integrated fire & gas detection solutions for the industrial segment are carried out by our highly experienced and trained engineers, Flame detection, gas detection coupied with sophisticated control and annunciation system are provided to protect assets and save human lives.

Sprinkler Systems

Automatic Operated Wet Pipe Sprinkler Systems comprise distribu-tion piping layout, temperature rated frangible bulb sprinklers, Alarm Check Valves c/w trim assembly, OS&Y System Isolation Gate Valves, Zone Control Valve arrangements c/w Butterfly Isolation Valve, Water Flow Detector, Test & Drain Valve

Water within the sprinkler distribution piping, which utilizes sealed temperature rated sprinkler bulbs, is maintained at a suitable pressure. Should a fire condition occur, which generates heat in excess of the temperature rated sprinkler bulbs one or more sprinkler(s) operate and water is immediate-ly discharged from the open sprinkler(s) downwards toward the fire hazard.

Selection of suitable types of sprinkler protection is dependent upon the identified types of commodities and classification of occupancy and associated hazards.

High expansion foam concentrates also provide capability to discharge a ‘foam blanket’ over large floor areas, e.g. aircraft hangers providing containment and extinguishing protection

SAFEFUTURE Technical ServicesGeneral Company Profile

Page No: 14

سيف فيوتشر للخدمات الفنية - ش.ذ.م.م

SAFEFUTURET E C H N I C A L S E R V I C E S - L . L . C

Our ServicesSafety Systms

Page 19: PRE-QUALIFICATION MANUAL - safefuture.cosafefuture.co/wp-content/uploads/Safe-Future-Company-Profile.pdf · Method of Statement ... calcium silicate, water & fire resistant gypsum

FIRE HOSE REEL & STANDPIPE SYSTEMS

Wet riser pipe systems comprise manually operated fire hose reels and landing valves which are strategically located for unobstruct-ed access should a fire condition occur. The fire hose reel should only be operated by occupants who are competent / trained in their use however; due to higher operating pressures and flows discharged thru hose and nozzles, landing valves must only be operated by the trained fire department personnel.

Dry riser pipe systems comprise landing valves which are usually located within building stairwells. The systems require external fire hose connections direct from Civil Defense fire water storage tankers to provide adequate water supply or pressure and must only be operated by the trained fire department personnel.

Gate Valve System

Gate valves are multi-purpose bi-directional shutoff valves for controlling firewater supply between the water storage facility via fire pumps and piping distribution networks. Their operation status is either ‘fully open’ or ‘fully closed’. Operation-al status is achieved by moving the wedge in an up/down direction inside the valve body. They can be installed in horizontal, vertical or inclined positions.

Novec Clean Agent System

Novec1230 gas is a waterless fire suppressant and extinguishes a fire by removing the heat element of the fire triangle (Oxygen, Heat and Fuel). It does not remove or reduce oxygen levels within the protected area.

Due to the low concentration levels of Novec1230 fire suppres-sion, this means that less storage space for Novec 1230 storage cylinders is required, making the storage footprint for the fire suppression agent relatively small by comparison to other Clean Agent fire suppression systems.

Typical Novec1230 fire suppression applications:

Computer Data Centers Communication Rooms Telecommunication facilities UPS Rooms Medical facilities

EMERGENCY EXIT LIGHT

Exit signags, bulkhead, high output and twinlight emergency luminaries, most fittings are available as either non-maintained or maintained version.

Bin Touq Fire and Safety also offers a full range of central battery systems available as

Switch trippers AC systems DC systems

SAFEFUTURE Technical ServicesGeneral Company Profile

Page No: 15

سيف فيوتشر للخدمات الفنية - ش.ذ.م.م

SAFEFUTURET E C H N I C A L S E R V I C E S - L . L . C

Our Services

Page 20: PRE-QUALIFICATION MANUAL - safefuture.cosafefuture.co/wp-content/uploads/Safe-Future-Company-Profile.pdf · Method of Statement ... calcium silicate, water & fire resistant gypsum

Safety Systems Projects Profile:

No Place Project NameProject Status Type

Dubai1 1B+G3+POD19+ Typ. Plot noBB.B01.062

Completed Fire Alarm, EmergencyLighting

DubaiJebel Ali Free Zone

2 Completed Fire Alarm, EmergencyLighting

Hyundai JAFZA warehouse on plot S60108 at

DubaiSportsCity

3 Completed Fire Alarm, EmergencyLighting

B+G2+ School & G3+ Hostel Buildingon Plot. 1483-682

Dubai4 Completed Fire Alarm, EmergencyLighting

Supply Material forB+G+M5+P28+F+SF+HPCommercial/Residential

Dubai5 Completed Fire Alarm, EmergencyLighting

G + 5P + 15 plot no 135 Al Nahdah

Sharjah6 Completed Fire Alarm, EmergencyLighting

GR.8+P.+H.C.-2+ OFF19+-TYP3+PH+ROOF+HELIPADPlot No:752

Sharjah7 Completed Fire Alarm, EmergencyLighting

G5+P+H.C14+ Typ+Pent-house on Plot. 306

SharjahMuweilah

8 Completed Fire Alarm, EmergencyLighting

G1+P5+ Story Residential Building on Plot. no. 696-107

DubaiNad AlShiba

9 Completed Fire Alarm, EmergencyLighting

G8+ Typ. Plot no 021-12

DubaiRas Al Khor

10 Completed Fire Alarm, EmergencyLighting

G1+ Residential Bldg. on Plot. 6130758

11 Completed Fire Alarm, EmergencyLighting

Proposed G+P5+ Typ on Plot. 696-30 Gov. 2930

SharjahMuweilah

12 Completed Fire Alarm, EmergencyLighting

Proposed G+P5+ plot no Mulk 152- 696

SharjahMuweilah

SAFEFUTURET E C H N I C A L S E R V I C E S - L . L . C

Projects Profile

SAFEFUTURE Technical ServicesGeneral Company Profile

Page No: 16

Safety Systms

Page 21: PRE-QUALIFICATION MANUAL - safefuture.cosafefuture.co/wp-content/uploads/Safe-Future-Company-Profile.pdf · Method of Statement ... calcium silicate, water & fire resistant gypsum

SAFEFUTURET E C H N I C A L S E R V I C E S

Safety Systems Projects Profile:

No Place Project NameProject Status Type

13 Completed

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Fire Alarm, EmergencyLighting

SharjahAl Khan

14 Fire Alarm, EmergencyLighting

G + 3P16+ plot 141 Al Khan

Proposed G+P5+ plot no Mulk 29 - 696

Ajman15 Fire Alarm, EmergencyLighting

G2+P3+ Typ. pl.no. 9-43-42

16 Fire Alarm, EmergencyLighting

B+G6+ typ. On plot no 969 / 6 mulk

17 Fire Alarm, EmergencyLighting

(G3+P15+) on Plot 428

DubaiAl Warqa First

18 Fire Alarm, EmergencyLighting

B+G+6+R plot no 4210196

DubaiJabel Ali

19 Fire Alarm, EmergencyLightingPlot. No.34B, 8B & 34BH

SharjahMuweilah

SharjahMuweilah

SharjahMuweilah

SharjahAbu Shehara

20 Fire Alarm, EmergencyLighting

Proposesd B+G2+ shoping centre At Plot no 392

DubaiAl Hamriya

21 Fire Alarm, EmergencyLighting

3B+G3+Typ Floors+Gym on Plot. no.405-313

DubaiDIP

22 Fire Alarm, EmergencyLighting

Sheds at Dubai

SAFEFUTURE Technical ServicesGeneral Company Profile

Page No: 17

SAFEFUTURET E C H N I C A L S E R V I C E S - L . L . C

Projects Profile

Safety Systms

Page 22: PRE-QUALIFICATION MANUAL - safefuture.cosafefuture.co/wp-content/uploads/Safe-Future-Company-Profile.pdf · Method of Statement ... calcium silicate, water & fire resistant gypsum

������ ������� ������ ���

SAFEFUTURET E C H N I C A L S E R V I C E S

������ ������� ������ ���

SAFEFUTURET E C H N I C A L S E R V I C E S

General Maintenance Plan Tasks

Customer Support from our 24 hour support engineers. Availability of our Technicians 24 hours a day, 365 days a year.Monthly and annual maintenance Inspections. Equipment and programming adjustments during inspection. Annual assessment of your business security requirementsFixed price for the term of the agreementAll work carried out on site or remotely (for configuration manage-ment), the Service engineer will also note down any deficiencies in the system and recommend work required to maintain, full, trouble free operation.A secure web address to access your surveillance system remotely

Full System Inspection and Testing

Check whether staff have experienced any problems with the system.Carry out a visual inspection of all major components (including cabling and connections where accessible) for signs of deterioration or damage and rectify as necessary.

Cameras

1. Cameras are well connected and are configured for maximum and optimal coverage. Angles are appropriate for your site and lens zooming is in accordance with the camera specifications.2. Examine supporting brackets and towers for signs of corrosion and damage.3. Check physical condition of cameras and housings for signs of deterioration due to rain, dust and dirt.4. Check that field of view is correct.5. Check that all camera bracket fittings and clamping bolts are tight.6. Check that lenses are correctly focused.7. Check operation of auto-iris lenses as appropriate.8. Clean housing windows as necessary.9. Check that washer bottles are full, refilling if necessary.10. Check operation, blade condition and parking position of wiper unit, adjusting stop position if necessary.11. Check condition of pan / tilt unit, adjusting position of end stops and presets where applicable.12. Check operation of infrared units.

Monitors

1. Check physical condition and cable connections.2. Check operation of controls and adjust for best picture.

Controls

1. Wiring is well shielded and protected. Visual inspection of all major components (including cabling and connections) for signs of deteriora-tion or damage and rectify as necessary.2. Check physical condition and cable connections.3. Check operation of switchers and multiplex controllers including external alarm interfaces when fitted.4. Check time / date settings and adjust if necessary.

Video / (DVR) Digital Video Recording Devices

1. DVR system monitoring (checks for system errors, video loss, network connection failure, and other system alerts)2. DVRs are well connected and configured for optimal recording experience. Configure motion based or continuous recording options. Data is recorded and stacked so that new data is never overwritten.3. Check hours run indicator and recommend for removal for service as appropriate.4. Check condition and operation controls as necessary.5. Check time / date settings and adjust accordingly

سيف فيوتشر للخدمات الفنية - ش.ذ.م.م

SAFEFUTURET E C H N I C A L S E R V I C E S - L . L . C

Our Services

Security Systems

SAFEFUTURE Technical ServicesGeneral Company Profile

Page No: 18

Security & Surveillance System

Page 23: PRE-QUALIFICATION MANUAL - safefuture.cosafefuture.co/wp-content/uploads/Safe-Future-Company-Profile.pdf · Method of Statement ... calcium silicate, water & fire resistant gypsum

CCTV Projects:We are here to endeavor the best in the industry services and features pertaining to CCTV Installations and Maintenance. We are providing the services with full customer satisfaction among all the CCTV companies in Dubai. As we are based in Dubai and manages our operation from Dubai to all over the UAE.

1 BUIDING G+4+R Completed

Completed

Completed

Completed

Completed

Completed

CompletedCompleted

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Completed

ALQUSAIS CCTV

CCTV

CCTV

CCTV

CCTV

CCTV

CCTV

CCTV

CCTV

CCTV

CCTV

CCTV

CCTV

CCTV

CCTV

CCTV

CCTV

CCTV

CCTV

CCTV

CCTVCCTV

CCTV

CCTVCCTVCCTV

CCTV

CCTVCCTV

2 BUIDING G+4+RWARSAN 3

3 LABOUR CAMP G+4JEBEL ALI IND 1

4 LABOUR CAMP G+3JEBEL ALI IND 1

5 LABOUR CAMP G+2ALMUHAISNAH 2

6 LABOUR CAMP G+2ALMUHAISNAH 2

7 LABOUR CAMP G+1ALMUHAISNAH2

8 LABOUR CAMP G+1ALMUHAISNAH2

9 LABOUR CAMP G+2ALMUHAISNAH210 RESTAURANTDEIRA

11

12

13

14

RESTAURANTDEIRA

15

RESTAURANTDEIRA

16

RESTAURANTDEIRA

17

RESTAURANTALBARSHA

18

RESTAURANTALBARSHA

19

RESTAURANTALBARSHA

20

RESTAURANTALBARSHA

21

RESTAURANTSILICON OASIS

22

RESTAURANTALBARSHA

LABOUR CAMP G+2ALMUHAISNAH 2

LABOUR CAMP G+3WARSAN 3LABOUR CAMP G+2ALMUHAISNAH 2

No Place Project NameProject Status Type

SAFEFUTURET E C H N I C A L S E R V I C E S - L . L . C

Our ServicesSecurity Systms

SAFEFUTURE Technical ServicesGeneral Company Profile

Page No: 19

Page 24: PRE-QUALIFICATION MANUAL - safefuture.cosafefuture.co/wp-content/uploads/Safe-Future-Company-Profile.pdf · Method of Statement ... calcium silicate, water & fire resistant gypsum

Certificates

Page 25: PRE-QUALIFICATION MANUAL - safefuture.cosafefuture.co/wp-content/uploads/Safe-Future-Company-Profile.pdf · Method of Statement ... calcium silicate, water & fire resistant gypsum

SAFEFUTURE Technical ServicesGeneral Company Profile

Page No: 20

Certificates

Page 26: PRE-QUALIFICATION MANUAL - safefuture.cosafefuture.co/wp-content/uploads/Safe-Future-Company-Profile.pdf · Method of Statement ... calcium silicate, water & fire resistant gypsum

Certificates

SAFEFUTURE Technical ServicesGeneral Company Profile

Page No: 21

Page 27: PRE-QUALIFICATION MANUAL - safefuture.cosafefuture.co/wp-content/uploads/Safe-Future-Company-Profile.pdf · Method of Statement ... calcium silicate, water & fire resistant gypsum

SAFEFUTURE Technical ServicesGeneral Company Profile

Page No: 22

Certificates

Page 28: PRE-QUALIFICATION MANUAL - safefuture.cosafefuture.co/wp-content/uploads/Safe-Future-Company-Profile.pdf · Method of Statement ... calcium silicate, water & fire resistant gypsum

Certificates

SAFEFUTURE Technical ServicesGeneral Company Profile

Page No: 23

Page 29: PRE-QUALIFICATION MANUAL - safefuture.cosafefuture.co/wp-content/uploads/Safe-Future-Company-Profile.pdf · Method of Statement ... calcium silicate, water & fire resistant gypsum

Certificates

SAFEFUTURE Technical ServicesGeneral Company Profile

Page No: 25

Page 30: PRE-QUALIFICATION MANUAL - safefuture.cosafefuture.co/wp-content/uploads/Safe-Future-Company-Profile.pdf · Method of Statement ... calcium silicate, water & fire resistant gypsum

Certificates

SAFEFUTURE Technical ServicesGeneral Company Profile

Page No: 26

Page 31: PRE-QUALIFICATION MANUAL - safefuture.cosafefuture.co/wp-content/uploads/Safe-Future-Company-Profile.pdf · Method of Statement ... calcium silicate, water & fire resistant gypsum

Certificates

SAFEFUTURE Technical ServicesGeneral Company Profile

Page No: 27

Page 32: PRE-QUALIFICATION MANUAL - safefuture.cosafefuture.co/wp-content/uploads/Safe-Future-Company-Profile.pdf · Method of Statement ... calcium silicate, water & fire resistant gypsum

Certificates

SAFEFUTURE Technical ServicesGeneral Company Profile

Page No: 28

Page 33: PRE-QUALIFICATION MANUAL - safefuture.cosafefuture.co/wp-content/uploads/Safe-Future-Company-Profile.pdf · Method of Statement ... calcium silicate, water & fire resistant gypsum

Eng. Tarek OsmanSafe Future Technical Services L.L.CAl Mamzar | AB Plaza 8 Building Office 103 Dubai , UAE92252 , Al Mamzar, Dubai, UAE+971 4 266 1231+971 4 266 8700+971 50 940 [email protected]