pre feasibility - welcome to environmentenvironmentclearance.nic.in/.../tor/0_0_27_aug_2014... ·...
TRANSCRIPT
SAND/ BOULDER/ BAJRI MINING PROJECT OF RAMGADH RAU RIVER (AREA20.00 HA)
PRE-FEASIBILITY REPORT PAGE 1
TABLE OF CONTENTS
1.0. EXECUTIVE SUMMARY ________________________________________________________________________ 5
1.1. Salient Features Of The Project______________________________________________________________ 5
1.2. Proposed Planning ____________________________________________________________________________ 6
2.0. INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION ____________________ 6
2.1. Identification of Project Proponent _________________________________________________________ 6
2.2. Brief Description Of Nature Of The Project ________________________________________________ 7
2.3. Need For The Project And Its Importance To The Country And/or Region ___________ 7
2.4. Demand-Supply Gap ___________________________________________________________________________ 8
2.5. Imports vs. Indigenous production _________________________________________________________ 8
2.6. Export Possibility ______________________________________________________________________________ 8
2.7. Domestic/ Export Markets ___________________________________________________________________ 8
2.8. Employment Generation _____________________________________________________________________ 8
3.0. PROJECT DESCRIPTION _______________________________________________________________________ 9
3.1. Type Of Project Including Interlinked And Interdependent Projects, If Any _________ 9
3.2. Location (Map showing general location, specific Location, and project Boundary &
Project Site Layout) with Coordinates ______________________________________________________________ 9
3.3. Details Of Alternate Sites considered and the basis of selecting the proposed site,
particularly the environmental considerations gone into should be highlighted _________ 10
3.4. Size or Magnitude of Operation ___________________________________________________________ 11
3.4.1. Mineral Reserves During the Lease Period _____________________________________________ 11
3.4.2. Production Parameters ___________________________________________________________________ 11
3.5. Project Description With Process Details (a schematic diagram/ flow chart
showing the project layout, components of the project etc.) _________________________________ 12
3.5.1. method of mining _________________________________________________________________________ 12 3.5.2. Blasting ____________________________________________________________________________________ 13
3.6. Raw Material Required Along With Estimated Quantity, Likely Source, Marketing
Area Of Final Product/S, Mode Of Transport Of Raw Material And Finished Product ____ 13
3.7. Resource Optimization/ Recycling And Reuse __________________________________________ 14
3.8. Availability Of Water Its Source, Energy / Power Requirement & Source __________ 14
3.8.1. Water Requirement _______________________________________________________________________ 14 3.8.2. Power ______________________________________________________________________________________ 14
SAND/ BOULDER/ BAJRI MINING PROJECT OF RAMGADH RAU RIVER (AREA20.00 HA)
PRE-FEASIBILITY REPORT PAGE 2
3.9. Quantity Of Wastes To Be Generated (Liquid And Solid) And Scheme For Their
Management/ Disposal _____________________________________________________________________________ 15
3.9.1. Solid Waste Generation & its Disposal __________________________________________________ 15
3.9.2. Liquid Effluent ____________________________________________________________________________ 15
3.10. SCHEMATIC REPRESENTATIONS OF THE FEASIBILITY DRAWING WHICH GIVE
INFORMATION OF EIA PURPOSE __________________________________________________________________ 15
4.0. SITE ANALYSIS _______________________________________________________________________________ 17
4.1. Connectivity __________________________________________________________________________________ 17
4.2. Landform, Landuse And Land Ownership _______________________________________________ 17
4.2.1. Landform __________________________________________________________________________________ 17
4.2.2. Land Use ___________________________________________________________________________________ 17
4.2.3. Land Ownership __________________________________________________________________________ 17
4.3. Topography ___________________________________________________________________________________ 17
4.4. Existing Land Use Pattern __________________________________________________________________ 18
4.4.1. Environmental Sensitivity _______________________________________________________________ 18
4.5. Existing Infrastructure______________________________________________________________________ 19
4.6. Soil Classification ____________________________________________________________________________ 19
4.7. Climatic Data From Secondary Sources __________________________________________________ 19
4.8. Social Infrastructure ________________________________________________________________________ 21
5.0. PLANNING BRIEF _____________________________________________________________________________ 21
5.1. Planning Concept ____________________________________________________________________________ 21
5.2. Assessment Of Infrastructure Demand (Physical & Social) ___________________________ 21
5.3. Amenities/Facilities\ _______________________________________________________________________ 21
5.3.1. Mines Office, Workshop etc.______________________________________________________________ 21
5.3.2. Rest Shelter________________________________________________________________________________ 21
5.3.3. Water Supply ______________________________________________________________________________ 22
5.3.4. Power Supply _____________________________________________________________________________ 22
5.3.5. Transport of Men and Material __________________________________________________________ 22
5.3.6. Communication ___________________________________________________________________________ 22
5.3.7. Security Arrangements ___________________________________________________________________ 22
6.0. PROPOSED INFRASTRUCTURE _____________________________________________________________ 22
6.1. Industrial Area (Processing Area) ________________________________________________________ 22
6.2. Residential Area (Non Processing Area) _________________________________________________ 22
6.3. Green Belt _____________________________________________________________________________________ 22
6.4. Social Infrastructure ________________________________________________________________________ 23
6.5. Connectivity __________________________________________________________________________________ 23
SAND/ BOULDER/ BAJRI MINING PROJECT OF RAMGADH RAU RIVER (AREA20.00 HA)
PRE-FEASIBILITY REPORT PAGE 3
6.6. Drinking Water Management ______________________________________________________________ 23
6.7. Sewerage System ____________________________________________________________________________ 23
6.8. Industrial Waste Management ____________________________________________________________ 23
6.9. Solid Waste Management ___________________________________________________________________ 23
6.10. Power Requirement & Supply/ Source ________________________________________________ 23
7.0. REHABILITATION AND RESETTLEMENT (R&R) PLAN _________________________________ 24
8.0. PROJECT SCHEDULE & COST ESTIMATES ________________________________________________ 24
8.1. Likely Date Of Start Of Construction And Likely Date Of Completion _______________ 24
8.2. Estimated Project Cost Along With Analysis In Terms Of Economic Viability Of The
Project _________________________________________________________________________________________________ 24
9.0. ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS) _______________________________ 25
9.1. Financial And Social Benefits With Special Emphasis On The Benefit To The Local
People Including Tribal Population, If Any, In The Area ______________________________________ 25
SAND/ BOULDER/ BAJRI MINING PROJECT OF RAMGADH RAU RIVER (AREA20.00 HA)
PRE-FEASIBILITY REPORT PAGE 4
LIST OF TABLE
Table 1: Salient feature of the project ...................................................................................................................... 5
Table 2 : Manpower requirement .............................................................................................................................. 9
Table 3 : Water Requirement with source of supply .......................................................................................14
Table 4: Environmental Sensitivity .........................................................................................................................18
Table 5: Soil types, district Dehradun ....................................................................................................................19
Table 6: Climatic data of district Dehradun .........................................................................................................20
Table 7: Operational cost of the project ................................................................................................................24
LIST OF FIGURE
Figure 1: General location of mine lease area .....................................................................................................10
Figure 2: Schematic flowchart of minor mineral mining process ..............................................................12
Figure 3 : Schematic flowchart of EIA process ...................................................................................................16
List of Annexure
Annexure Number Annexure title
Annexure1 : Letter of intent
Annexure 2 : Proposal for forest clearance
Annexure 3 : Joint Inspection report
Annexure 4 : Geographical corner coordinates of mine site
Annexure 5 : Environmental sensitivity map with 10 km radius map
SAND/ BOULDER/ BAJRI MINING PROJECT OF RAMGADH RAU RIVER (AREA20.00 HA)
PRE-FEASIBILITY REPORT PAGE 5
1.0. EXECUTIVE SUMMARY
The proposed project is for mining of Minor Minerals (sand, boulder and bajri) in an
area of 20 ha from the river bed of Ramgadh rau, located in Malhan reserved forest near
village- Ramgarh & Burpur, Tehsil- Vikasnagar, District-Dehradun, Uttarakhand. The
project site comes in Malhan Range under Dehradun Forest Division, Dehradun. The
river along its course brings huge quantity of material consisting of sand, boulder & bajri
during every monsoon. This material has to be removed every year in order to
channelize the river course to the middle and to prevent it from widening & thus causing
cutting of nearby habitation & forest land.
Uttarakhand Forest Development Corporation (UKFDC) is a statutory body constituted
by the Uttarakhand State Government, involved in collection and disposal of sand, bajri,
boulder from the rivers situated inside Malhan reserved forest areas. The project
proponent has been issued a letter of intent by the Geology & Mining Unit vides letter
no. 584/BHU. KHANI.I./2012-13 dated 19th January, 2013 Annexure-I.
As the Mine lease lies in the reserved forest hence Forest clearance under section-2 of
“Forest Conservation Act, 1980” has to be obtained from MOEF for which the
application has already been submitted (Copy enclosed as Annexure-II) for diversion
of 20.00 ha of forest land.
Proposed project will also required NBWL clearance due to presence of Rajaji National
park within 10 km radius of study area. Wild life clearance is under process
1.1. SALIENT FEATURES OF THE PROJECT
Table 1: Salient feature of the project
Project name Sand/Bajri/Boulder mining Ramgadh rau
River Bed
Location of mine Ramgadh rau riverbed
Village : Ramgarh & Burpur
Tehsil : Vikasnagar
District : Dehradun
State : Uttarakhand
Latitude 30°19'12.10"N to 30°18'25.20"N
Longitude 77°53'1090"E to 77°52'28.20"E
Topo sheet number 53F/4
Land use Forest land
Minerals of mine Sand/Bajri/Boulder
Life of mine Continuous, being replenished yearly
Proposed annual production of mine 1,80,000 tonnes
Method of mining Open-cast Manual
SAND/ BOULDER/ BAJRI MINING PROJECT OF RAMGADH RAU RIVER (AREA20.00 HA)
PRE-FEASIBILITY REPORT PAGE 6
No of working days in a year 270
Water demand 10 KLD
Sources of water Tanker water supply
Man power 100
Nearest railway station Dehradun, 14.38 km East
Nearest state highway/national highway NH-72,0.75km NE
Nearest air port Jolly Grant Airport-Dehradun, 31.87km SE
Seismic zone Zone-IV (As per 1893:2002)
1.2. PROPOSED PLANNING
Mining method : Open Cast Manual mining method
Project cost : Capital cost of Rs. 2 lacs
Production : Sand/Bajri/Boulder- 1, 80,000 TPA
2.0. INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION
The minor mineral mining lease, measuring 20 hectare (ha) is a forest land that falls in
Malhan Forest Range of Dehradun Forest Division near village- Ramgarh & Burpur,
Tehsil- Vikasnagar, District-Dehradun, Uttarakhand. As per EIA notification, 2006 and its
subsequent amendments later, the project activity has been categorized as Category- A
project due to presence of Uttara Pradesh – Uttarakhand interstate boundary of 3.50 km
being within 10 km radius of the project site. Proposed capacity of mine will be
production of sand, bajri & boulder at the rate of 1, 80,000 TPA.
2.1. IDENTIFICATION OF PROJECT PROPONENT
Uttarakhand Forest Development Corporation (UKFDC) is a statutory body constituted
by the State Government of Uttarakhand. The Corporation was formed for the better
preservation, supervision and development of forest also for better exploitation of forest
produce within the State and for matters connected there with.
The Corporation has been progressing forward not only in its financial aspect but also
has taken a big leap in the direction of diversification of its activities.
The Corporation has added the collection and disposal of minor minerals from the rivers
situated inside reserved forest areas, collection and marketing of medicinal plants and
Eco tourism in its works apart from the removal of dead, dying and uprooted trees as
allotted by the Forest department.
Collection and marketing of sand, boulder and Bajri from the river beds of reserved
forest areas has been undertaken in order to protect the forest lands, agricultural crops,
inhabitations from the havoc of floods. The collection and marketing system is being
converted from volume base to weight basis for the disposal of sand, bajri, boulder in
SAND/ BOULDER/ BAJRI MINING PROJECT OF RAMGADH RAU RIVER (AREA20.00 HA)
PRE-FEASIBILITY REPORT PAGE 7
the Gaula, Sharda, Nandhaur, Kosi, Dabka, Ganga, Yamuna, Song and Gunna rivers of the
State. The implementation of advanced computerized technique of minor mineral
weighing system is a step towards advancement and use of new technology.
2.2. BRIEF DESCRIPTION OF NATURE OF THE PROJECT
The project has been proposed for an annual production of 1,80,000 tonnes of
Sand/Bajri/Boulder by open cast manual extraction method in river bed. The lease area
is totally under the forest land. The total lease area is 20 ha is mineable as per approved
Site inspection committee report comprising of officer from UKFDC, SDM Dehradun
Regional officer Dehradun, Tehsil office Vikasnagar Dehradun, Forest Ranger Jhajra
Forest Range of Dehradun dated 29.04.2013. Site inspection report attached as
Annexure II.
There is practically no soil cover on top profile of river bed section proposed for mining,
however, if some soil is available it will be removed and carefully stored for use in
plantation purpose.
No solid waste other than negligible quantity of silt/silty clay, which gets deposited as
crust material on the bed profile, shall be scrapped and carefully stored for depositing
into the mine pits in the river bed or for plantation purpose.
During monsoon season, when the river reaches high stage, Ramgarh Rau River has
significant catchment area and it transports bed load material and sediments which gets
aggraded at such stretch which has wider river width and has concave banks. The mined
out area gets replenished annually after monsoon, thus it does not require any
backfilling. The rehabilitation/reclamation of such lease area which has been secluded
for mining being closure to the bank in the form of upper terraces will be done by way of
tree plantation along lease boundary. Green barriers will be created by plantation as per
CPCB Guidelines.
2.3. NEED FOR THE PROJECT AND ITS IMPORTANCE TO THE COUNTRY AND/OR REGION
During monsoon due to heavy rainfall & flooding annually in the recent past years, a
large amount of minor minerals (sand, bajri, boulder) has been deposited in the bed of
river Ramgarh Rau which has widened the course of river and in-turn is responsible for
cutting of nearby agricultural and forest land causing heavy degradation in the form of
soil erosion and loss of vegetation along the river course. Keeping in view the
environmental consideration for the ecosystem of the river it is essential to remove
sand, Bajri, Boulder from the river bed.
SAND/ BOULDER/ BAJRI MINING PROJECT OF RAMGADH RAU RIVER (AREA20.00 HA)
PRE-FEASIBILITY REPORT PAGE 8
Therefore, in order to avoid widening of river, channelize the river course, prevention of
floods and land cutting from nearby agricultural fields & forests; this project has been
proposed to collect minor minerals from an area of 20 ha. It will not only benefit in
meeting the huge demand of construction material like coarse and fine aggregate
required in building construction & infrastructure works, road material for construction
& maintenance of roads/highway, elastic ballast material for rail tracks in the state of
Uttarakhand and nearby cities and towns of Uttar Pradesh as minor minerals of
Ramgadh river at river bed quarry site has been found suitable from techno-economic
consideration, but also provide direct employment to about 100 persons including
skilled, semi-skilled & unskilled laborers. Additional jobs are created by way of
transportation.
2.4. DEMAND-SUPPLY GAP
Due to ban on illegal mining and with increase in infrastructure industries demand of
sand bajri & boulder (construction material) has increased by almost 50 % hence the
excavation of river bed material will not only help in saving the river from diversion and
viding of its course but will also cater increased demand of river bed material in
construction activities like building, infrastructure facilities, construction and expansion
of existing road and highways etc
2.5. IMPORTS VS. INDIGENOUS PRODUCTION
Import does not apply in the present case as minor mineral is indigenously available at
number of mines under operation in Uttarakhand.
2.6. EXPORT POSSIBILITY
Export possibility is neither plausible nor there is any such demand.
2.7. DOMESTIC/ EXPORT MARKETS
The proposed mining activity is for obtaining Sand/Bajri/Boulder for indigenous
consumption and also for sale to nearby cities and towns located in the state of
Uttarakhand as well as Uttar Pradesh.
2.8. EMPLOYMENT GENERATION
About 300 workers including skilled, semi-skilled & unskilled labors shall be engaged
SAND/ BOULDER/ BAJRI MINING PROJECT OF RAMGADH RAU RIVER (AREA20.00 HA)
PRE-FEASIBILITY REPORT PAGE 9
through project proponent for extraction of minor mineral and loading and handling of
mineral in mining area, besides, watch and ward and plantation activity with proper
maintenance.
Breakup of manpower is given as follows:
Table 2 : Manpower requirement
S. No. Type of Manpower Number
1 Skilled 4
2 Semi-skilled 10
3 Unskilled Labourers 86
Total 100
3.0. PROJECT DESCRIPTION
3.1. TYPE OF PROJECT INCLUDING INTERLINKED AND INTERDEPENDENT PROJECTS, IF ANY
The project has been proposed for an annual production of 1, 80,000 TPA of sand,
boulder & bajri by open cast manual extraction method in river bed. The lease area (20
ha) is a forest land. The project has no other interlinked project. Minor minerals form
the site will be transported to different vendors of crusher units for further activities.
3.2. LOCATION (MAP SHOWING GENERAL LOCATION, SPECIFIC LOCATION, AND PROJECT BOUNDARY &
PROJECT SITE LAYOUT) WITH COORDINATES
The minor mineral mining lease, measuring 20 ha is a forest land and falls in Malhan
Forest Range of Dehradun Forest Division Dehradun. Mine site is located near village–
Burpur, Tehsil-Vikasnagar, District-Dehradun Uttarakhand. General location of the mine
site is given in Figure 1.
Geographical location of mine stretch is given below:
Latitude 30°19'12.10"N to 30°18'25.20"N
Longitude 77°53'1090"E to 77°52'28.20"E
Project boundary with site layout and geographical corner coordinates along the mine
site is shown in satellite image attached as Annexure-III.
SAND/ BOULDER/ BAJRI M
PRE-FEASIBILITY REPORT
Figure 1: General
3.3. DETAILS OF ALTERNATE SITES CONSIDERED AND
PARTICULARLY THE ENVIRONMENTAL CONSIDERA
The proposed site shall be mined for the purpose of preventing
heavy rainfall and floods
Examination for alternative sites was not required as it is mandated for the above
mentioned purpose only.
Besides this any other alternative other than river bed mining like mining of rock in
quarry shall result in exorbitant cost, result in comparatively higher land degradation
and cause more environmental impacts.
MINING PROJECT OF RAMGADH RAU RIVER (AREA20
EPORT
: General location of mine lease area
ITES CONSIDERED AND THE BASIS OF SELECTING THE PROPOSED SITE
IRONMENTAL CONSIDERATIONS GONE INTO SHOULD BE HIGHLIGHTED
he proposed site shall be mined for the purpose of preventing land cutting during
heavy rainfall and floods and also to channelize the river course to the middle
Examination for alternative sites was not required as it is mandated for the above
Besides this any other alternative other than river bed mining like mining of rock in
quarry shall result in exorbitant cost, result in comparatively higher land degradation
and cause more environmental impacts.
20.00 HA)
PAGE 10
NG THE PROPOSED SITE,
LD BE HIGHLIGHTED
land cutting during
and also to channelize the river course to the middle.
Examination for alternative sites was not required as it is mandated for the above
Besides this any other alternative other than river bed mining like mining of rock in-situ
quarry shall result in exorbitant cost, result in comparatively higher land degradation
SAND/ BOULDER/ BAJRI MINING PROJECT OF RAMGADH RAU RIVER (AREA20.00 HA)
PRE-FEASIBILITY REPORT PAGE 11
3.4. SIZE OR MAGNITUDE OF OPERATION
Total available area of the river is 20 ha, which falls under Dehradun Forest Division,
Uttarakhand. The collection of minor minerals will be carried out from the 50% of the
total area i.e. approximately 8 ha, leaving 25% area on either side of the river bank for
better channelization of the water during monsoon. Hence, Total capacity of mine is
estimated at 1, 80,000 tonnes per annum.
3.4.1. MINERAL RESERVES DURING THE LEASE PERIOD
The total & mineable reserve considered up to depth of 1.0m almost 1, 80,000 tonnes
mineral is available. The total estimated reserve for next ten years is 18,00,000 tonnes.
The stretches of the river, where the aggradations of bed load/ suspended load takes
place, are well defined within the river section and such areas get replenished annually
in variable quantum depending upon the flood events and the duration of floods within
the rainy season. If this river bed material is not removed from the stream channel to
the desired depth the ensuing year influx of river bed material is bound to deposit in the
mid stream and divert the flash floods to the bank inundating river site locales
3.4.2. PRODUCTION PARAMETERS
Leaving 25% area on both the banks of the river along with 200 feet each upstream and
downstream for any road /bridge crossing the river, thereby collecting the minor
mineral in almost 50% of the total area along the centre of river channel; yearly
production of mine is estimated as 50% of the total reserve available per year i.e.
@1,80,000 tonnes per year.
The mine will be worked in the day shift only. The average number of working days in
the year would be 270.
The proposed annual target production has been worked out on the basis of mineable
area with maximum mining depth of 1m. On the basis of the nature of RBM (River Borne
Material) in the boulder reach of the river, the matrix comprises of the bed load, mainly
comprising of boulder, pebble, cobble, bajri and sand. The river originates from non-
glaciated areas of Inner Himalayas and is basically spring fed river with discharges
throughout the year. During monsoon season, the high intensity and duration of rain fall
result into high floods and sometime the flash flood also. The banks of the river in the
upper reaches are made-up of friable material, which is easily eroded. The river bed
material and the suspended solids material mainly constitutes of stone, bajri and sand,
SAND/ BOULDER/ BAJRI M
PRE-FEASIBILITY REPORT
which gets settled into the beds with depressed elevation and into such pockets formed
during the mining in pre-monsoon season. Viewing the
traction force generated during period of high discharges the bed load material, viz.
boulder, shingle and sand gets aggraded annually and it is essential that the silviculture
purposes and to save the nearby habitation, th
river course is not diverted. The annual target production is likely to be achieved during
the year of normal rainfall in the catchment of Ramgarh Ro River.
3.5. PROJECT DESCRIPTION WITH
SHOWING THE PROJECT LAYOUT
3.5.1. METHOD OF MINING
As per Environmental Impact Assessment Guidance Manual for
released by MoEF - the project is a surface mining. The typical opera
surface mining is shown in the figure given below:
Figure 2: Schematic flowchart of minor mineral mining process
MINING PROJECT OF RAMGADH RAU RIVER (AREA20
EPORT
which gets settled into the beds with depressed elevation and into such pockets formed
monsoon season. Viewing the competence of the river and the
traction force generated during period of high discharges the bed load material, viz.
boulder, shingle and sand gets aggraded annually and it is essential that the silviculture
purposes and to save the nearby habitation, the removal of sand is essential, so that, the
river course is not diverted. The annual target production is likely to be achieved during
the year of normal rainfall in the catchment of Ramgarh Ro River.
ITH PROCESS DETAILS (A SCHEMATIC DIAGRAM/
LAYOUT, COMPONENTS OF THE PROJECT ETC.)
As per Environmental Impact Assessment Guidance Manual for - Mining of Minerals
the project is a surface mining. The typical operations involved in a
surface mining is shown in the figure given below:
: Schematic flowchart of minor mineral mining process
Site Preparation
Extraction of minor mineral (by manual opencast method)
Loading of mineral
Haulage & Transportation
Transportation of mineral to the destined places
20.00 HA)
PAGE 12
which gets settled into the beds with depressed elevation and into such pockets formed
competence of the river and the
traction force generated during period of high discharges the bed load material, viz.
boulder, shingle and sand gets aggraded annually and it is essential that the silviculture
e removal of sand is essential, so that, the
river course is not diverted. The annual target production is likely to be achieved during
FLOW CHART
Mining of Minerals
tions involved in a
: Schematic flowchart of minor mineral mining process
SAND/ BOULDER/ BAJRI MINING PROJECT OF RAMGADH RAU RIVER (AREA20.00 HA)
PRE-FEASIBILITY REPORT PAGE 13
� The project will be accomplished by fully manual open cast method of mining
that does not involve any processes such as overburden removal, drilling,
blasting and beneficiation.
� The extraction of river bed material from the bed of the river will be made by
leaving 25% width on either side of river
� The mining process involves collection of material by simple hand tool such as
shovel, pans and sieves.
� This will be followed by sorting and manual picking, stacking and loading into
trucks/ tractor–trolley for transporting.
� The pits from where the material is picked are not deeper than 1.5 meter and
shall follow the normal channel direction of the river. These get replenished
during monsoon.
� The only waste is silt/clay which will be added back to the pits.
� The material is transported through tipper (9.0-10.2 MT Capacity), Tractor
trolley small (3MT capacity) Tractor trolley big (6 MT capacity) to the destined
users/places outside mining lease
Mining will be carried out only during the day time. Extraction of sand, stone and bajri
material will be completely stopped during the monsoon season.
The implements for mining are arranged by project proponent who are also responsible
for administrative control of labours as well as for carrying out mining operations in the
sanctioned/demarcated lease area within the ambit of the conditions set-forth in the
order for execution of mine by the competent authority and also the
instructions/guideline issued by the Khanan Vibhag, Uttarakhand.
3.5.2. BLASTING
No blasting is proposed to be done.
3.6. RAW MATERIAL REQUIRED ALONG WITH ESTIMATED QUANTITY, LIKELY SOURCE, MARKETING
AREA OF FINAL PRODUCT/S, MODE OF TRANSPORT OF RAW MATERIAL AND FINISHED
PRODUCT
No raw material is required for extraction of minerals.
SAND/ BOULDER/ BAJRI MINING PROJECT OF RAMGADH RAU RIVER (AREA20.00 HA)
PRE-FEASIBILITY REPORT PAGE 14
3.7. RESOURCE OPTIMIZATION/ RECYCLING AND REUSE
Not applicable in the present case as all size of minerals will be extracted and
transported to various crusher units outside the mine lease area for sorting & grading
purpose.
3.8. AVAILABILITY OF WATER ITS SOURCE, ENERGY / POWER REQUIREMENT & SOURCE
3.8.1. WATER REQUIREMENT
Water requirement for human consumption, plantation and dust suppression is 10 KLD,
which shall be met from tanker supply. The water required for domestic purpose
includes drinking purpose and toilet needs of workers for which toilet with septic tank
will be provided at site. The water is further required for sprinkling on haulage road
which is done twice a day in morning and evening using water tanker supply. Breakup of
water requirements is as given below:
Table 3 : Water Requirement with source of supply
S. No. Description of requirement Water requirement
(KLD)
Source
1. Drinking 3.00 Tanker water supply
3. Dust Suppression 2.00
4. Green Belt Development 5.00
TOTAL REQUIREMENT 10 KLD
3.8.2. POWER
No electrical power shall be required for operations as the mining will be worked out
during day time only minimal power required for office shall be taken from general
electric supply of area.
SAND/ BOULDER/ BAJRI MINING PROJECT OF RAMGADH RAU RIVER (AREA20.00 HA)
PRE-FEASIBILITY REPORT PAGE 15
3.9. QUANTITY OF WASTES TO BE GENERATED (LIQUID AND SOLID) AND SCHEME FOR THEIR
MANAGEMENT/ DISPOSAL
3.9.1. SOLID WASTE GENERATION & ITS DISPOSAL
No solid waste other than negligible quantity of silt/silty clay, which gets deposited as
crust material on the bed profile, shall be scrapped and deposited into the mine pits or
in the upper terraces earmarked for plantation.
3.9.2. LIQUID EFFLUENT
There will be no waste water generation from mining activities.
3.10. SCHEMATIC REPRESENTATIONS OF THE FEASIBILITY DRAWING WHICH GIVE
INFORMATION OF EIA PURPOSE
As the project is categorized in category-A of Schedule under item 1(a) in the EIA
notification, 2006 and its subsequent amendments; it shall be taken up at the Expert
Appraisal Committee (MOEF) for the purpose of obtaining Environment Clearance.
Schematic representation for EIA purpose is given below:
SAND/ BOULDER/ BAJRI MINING PROJECT OF RAMGADH RAU RIVER (AREA20.00 HA)
PRE-FEASIBILITY REPORT PAGE 16
Figure 3 : Schematic flowchart of EIA process
SAND/ BOULDER/ BAJRI MINING PROJECT OF RAMGADH RAU RIVER (AREA20.00 HA)
PRE-FEASIBILITY REPORT PAGE 17
4.0. SITE ANALYSIS
4.1. CONNECTIVITY
The mining site is well connected through rail & road network.
� Mine site at Ramgadh rau River Malhan Range, Vikasnagar is approachable by
Peterson road which is connected to NH-72 at a distance of 0.75 km in north
direction
� Dehradun railway station is located at a distance of 14.38 km.
� The nearest airport is Jolly Grant (Dehradun) around 31.87 km away from the
mining area.
4.2. LANDFORM, LANDUSE AND LAND OWNERSHIP
4.2.1. LANDFORM
The mine lease area is in river bed of Ramgadh rau River, Malhan Forest Range of
Dehradun Forest Division.
4.2.2. LAND USE
The land use of the mine lease area is river body classified as forest land.
4.2.3. LAND OWNERSHIP
The designated mine area is forest land and belongs to Malhan Forest range of Dehradun
forest division and has been allotted to UKFDC for the purpose of mining.
4.3. TOPOGRAPHY
The mine lease area lies in the river bed and is a part of foothills of Siwalik range region
of Uttarakhand. Highest and lowest elevation in the area is 586 m AMSL and 544 m
AMSL creating a level difference of 42 m. Due to difference in elevation it is considered
lesser hilly region.
The residual hills are mostly formed by erosion and are the remnants of post Upper
Siwalik deposits. These are called Older Doon Gravels or Langha Boulder Beds. Boulder
beds, shales and red clay represent this unit. The residual hills are present in Doiwala
and Vikasnagar blocks.
Dehradun can be divided into 2 distinct tracts i.e. the montrane tract and the sub-
montrane tract. The mine lease area lies in the sub-montrane tract which is the famous
SAND/ BOULDER/ BAJRI MINING PROJECT OF RAMGADH RAU RIVER (AREA20.00 HA)
PRE-FEASIBILITY REPORT PAGE 18
Doon Valley, surrounded by Siwalik Hills in the South and outer scrap of Himalayas in
the North.
Topography will not change during running of mine and on its abandonment at the end
of the proposed mining, due to digging of shallow pits and consequent annual deposition
during high floods. Map showing study area with 10 km radius around the mine lease
boundary is attached as Annexure- IV.
4.4. EXISTING LAND USE PATTERN
The existing land use pattern of mine lease area belongs to landuse category “River
body” in reserved forest area and shall continue to be so even after the current mining
project is over.
4.4.1. ENVIRONMENTAL SENSITIVITY
Table 4: Environmental Sensitivity
S.No. Sensitive Ecological Features Name Aerial Distance
(in km.) from
Mine Lease
boundary
1. National Park/Wildlife Sanctuary Rajaji National Park Adjacent to mine
lease area
2. Tiger Reserve/Elephant Reserve
/ Turtle Nesting Ground
- -
3. Core Zone of Biosphere Reserve None -
4. Habitat for migratory birds None -
5. Lakes/Reservoir/Dams No -
6. Stream/Rivers Mine is located in the bed
of Ramgadh rau river
-
7. Estuary/Sea None -
8. Mangroves None -
9. Mountains/Hills Project lies in the
foothills of Siwalik range
-
10. Notified Archaeological sites None -
11. Industries/Thermal Power Plants None -
12. Defense Installation Indian Military Academy 8.14 km E
13. Airports Jolly Grant 31.87km SE
14. Railway Lines Dehradun 14.38 km SE
15. National / State Highways NH-72 0.75 km NE
16. Important worship place Jama Masjid 12.18km
SAND/ BOULDER/ BAJRI MINING PROJECT OF RAMGADH RAU RIVER (AREA20.00 HA)
PRE-FEASIBILITY REPORT PAGE 19
4.5. EXISTING INFRASTRUCTURE
The mine lease area is a forest land which lies in the Ramgadh rau river basin and gets
deposition of sand, bajri & boulder carried along the river course with the flow of river
during monsoon. There is no existing infrastructure, however during mining temporary
rest shelters for workers will be provided.
4.6. SOIL CLASSIFICATION
The nature and soil type play an important role in agriculture and have direct relation
with groundwater recharge. Physiography, climate, drainage and geology of the area are
the factors responsible for the nature and type of soil and soil cover. The soil type also
depends upon the slope and rate of erosion. The soil types of district Dehradun are given
in Table 5:
Table 5: Soil types, district Dehradun
Physioraphy Characteristics Taxonomic Classification
Mountains Moderately deep, well-drained, thermic
coarse loamy soils on steep slopes, strong,
stoniness, associated with shallow
excessively drained, loamy skeletal soil.
Loamy skeletal. Dystric
Eutrochrepts. Fine loamy
lithic and typic Hapludolls-
Loamy skeletal typic Udrothants
Soils on Upper
piedmont plains
Deep, well-drained, coarse loamy cover,
fragmental soils on heavy gentle slope with
loamy surface and slight erosion.
Associated with excessively cairned soils
with loamy surface and slight to moderate
erosion. Deep, well-drained, fine to coarse loamy
surface and slight to moderate erosion.
Udifiuventic
Ustochrepts
Typic Usipsammens
Udic Ustorchrepts
Soils on Lower
piedmont plains
Deep, well-drained, coarse loamy cover over
fragmental soils on nearly level plains with
loamy surface.
Associated with deep, well drained, fine loamy soil with loamy surface.
Deep well drained, fine silty soil on very
gentle slopes with loamy surface and slight
erosion. Deep well drained fine to coarse loamy
surface and slight to moderate erosion, silty
soil with loamy surface.
Udifluventic
Ustochreps
Udic Ustochrepts
Udic Haplustolls
Udic Ustochrepts
*(source: CGWB 2011 report on Dehradun)
4.7. CLIMATIC DATA FROM SECONDARY SOURCES
The district has within its limits lofty peaks of the Outer Himalayas as well as the Dun
Valley with climatic conditions nearly similar to those in the plains.
SAND/ BOULDER/ BAJRI MINING PROJECT OF RAMGADH RAU RIVER (AREA20.00 HA)
PRE-FEASIBILITY REPORT PAGE 20
� Climate: The climate of the district, in general, is temperate. The temperature
depends on the elevation. In the Doon Valley, the heat is often intense. The
temperature drops below freezing point during the winters. The summer starts
by March and lasts up to mid of June when the monsoon sets in. Generally, the
month of May and early part of June is hottest. Winter starts from November and
continue upto February.
� Temperature: The temperature depends on the elevation. Mean temperature
shoots upto 36.20c at Dehradun during summers and the maximum temperature
rises to over 420C. The mean daily maximum temperature during winter is
19.10C and the mean daily minimum temperature in January is 6.1
0C. The highest
maximum temperature recorded at Dehradun was 43.90C on June 4, 1902 and
the lowest minimum temperature during winter was - 1.10C, on February 1st,
1905 and January 1945.
� Rainfall: The district receives an average annual rainfall of 2073.3 mm. Most of
the rainfall is received during the period from June to September, July and
August being the wettest months. The region around Raipur gets the maximum
rainfall, while the southern part receives the least rainfall in the district. About
87% of the annual rainfall is received during the period June to September.
The climatic data of Doon Valley is summarized in Table 6.
Table 6: Climatic data of district Dehradun
Month
Normal
Rainfall(mm)
Relative
Humidity
%
Temperature (0C)
Maximu
m Minimum Average
January 57.9 91 19.3 3.6 10.9
February 66.8 83 22.4 5.6 13.3
March 37.9 69 26.2 91. 17.5
April 19.6 53 32 13.3 22.7
May 35.8 49 35.3 16.8 25.4
June 184.4 65 34.4 29.4 27.1
July 655.6 86 30.5 22.6 25.1
August 713.0 89 29.7 22.3 25.3
September 304.5 83 29.8 19.7 24.2
October 41.9 74 28.5 13.3 20.5
November 7.6 82 24.8 7.6 15.7
December 24.9 89 21.9 4.0 12.0
Annual
2149.9 76 27.8 13.3 20.0
Normal
Average
*(source: CGWB 2011 report on Dehradun)
SAND/ BOULDER/ BAJRI MINING PROJECT OF RAMGADH RAU RIVER (AREA20.00 HA)
PRE-FEASIBILITY REPORT PAGE 21
4.8. SOCIAL INFRASTRUCTURE
The social infrastructure like educational facilities (primary and higher secondary
schools, degree college), drinking water supply, post and telegraph, public
transportation and hospitals are by and large are available in the study area.
5.0. PLANNING BRIEF
5.1. PLANNING CONCEPT
Open cast manual mining method will be adopted for Sand/Bajri/Boulder mining.
Project will annually produce Sand/Bajri/Boulder @ 1,80,000 tonnes, which will be
used for meeting the huge demand of construction material like coarse and fine
aggregate required in building construction and infrastructure works, road material for
construction and maintenance of roads/highway; elastic ballast material for rail tracks
in the state of Uttarakhand and nearby cities and towns of Uttar Pradesh.
5.2. ASSESSMENT OF INFRASTRUCTURE DEMAND (PHYSICAL & SOCIAL)
Adequate infrastructure facilities are available in the vicinity of mine lease area and due
to the mining activities; no extra infrastructure over and above the existing
infrastructure is required.
5.3. AMENITIES/FACILITIES\
Adequate infrastructure facilities are available in the vicinity of mine lease area and due
to the mining activities; no extra infrastructure over and above the existing
infrastructure is required.
5.3.1. MINES OFFICE, WORKSHOP ETC.
Proper site services such as First Aid, Rest Shelter, and Drinking Water will be provided
to the mine workers.
5.3.2. REST SHELTER
Rest shelter along with first-aid station complying with all the provisions of Mines Rules
shall be provided by project proponent outside lease area
SAND/ BOULDER/ BAJRI MINING PROJECT OF RAMGADH RAU RIVER (AREA20.00 HA)
PRE-FEASIBILITY REPORT PAGE 22
5.3.3. WATER SUPPLY
A total of 10 KLD Water will be required for the purpose of human consumption, dust
suppression and plantation. Water shall be supplied by tanker supply from authorized
vendor.
5.3.4. POWER SUPPLY
The mining work will be done in day time only, so no lighting arrangement will be
required.
5.3.5. TRANSPORT OF MEN AND MATERIAL
By and large only local personnel shall be deployed for mining. Either by foot or with the
help of bicycle, they will reach the site. During operation phase, trucks/tractors shall be
used for the transportation of river bed material from the site to destined locations.
5.3.6. COMMUNICATION
Mobile phones & walky talky shall be used for communication.
5.3.7. SECURITY ARRANGEMENTS
Mine lease being a part of reserve forest required appropriate security which shall be
provided by UKFDC along with Forest Department.
6.0. PROPOSED INFRASTRUCTURE
6.1. INDUSTRIAL AREA (PROCESSING AREA)
Temporary arrangements like site office, rest shelters & approach roads etc shall be
provided. No permanent infrastructure is proposed.
6.2. RESIDENTIAL AREA (NON PROCESSING AREA)
As the local person shall be employed, no residential building/housing are proposed.
6.3. GREEN BELT
As the mine site is a part of forest land, hence the project proponent i.e. UKFDC shall
carry out compensatory afforestation as mentioned in the Forest Clearance conditions.
Apart from compensatory afforestation green belt shall also be developed along the road
side after consultation with concerned authority and village panchaya.
SAND/ BOULDER/ BAJRI MINING PROJECT OF RAMGADH RAU RIVER (AREA20.00 HA)
PRE-FEASIBILITY REPORT PAGE 23
6.4. SOCIAL INFRASTRUCTURE
As per primary survey & secondary data available, by & large all the social infrastructure
facilities are available in the vicinity of mine site in the study area. However, in-line with
the Social Responsibility Activities at other operational sites, relevant developmental
assistance shall be rendered depending on the local needs identified through EIA studies
with consultation of Gram Panchayat.
6.5. CONNECTIVITY
Site is well connected to existing road and rail network. There is no proposal to develop
new road and rail links.
6.6. DRINKING WATER MANAGEMENT
Water requirement for drinking and other operations will be 10.0 KLD, which will be
met from nearby underground water source and tanker supply.
6.7. SEWERAGE SYSTEM
Domestic sewage shall be disposed off into septic tank followed by soak pits.
6.8. INDUSTRIAL WASTE MANAGEMENT
Not applicable, as the mining activity will not be generating any overburden or waste
water.
6.9. SOLID WASTE MANAGEMENT
Solid waste need not to be treated because the debris (solid waste) generated during
excavation is likely to be the dust, soil and slurry. Those can be left/ dumped at the site
as they are likely to have the same characteristic as the river bed material has. Separate
bins shall be provided for solid waste generated by daily human activities i.e. wrappers,
aluminium foils, leftover food materials etc.
6.10. POWER REQUIREMENT & SUPPLY/ SOURCE
The mining shall be carried out manually with the help of hand implements during day
time hence, power requirement is not needed.
SAND/ BOULDER/ BAJRI MINING PROJECT OF RAMGADH RAU RIVER (AREA20.00 HA)
PRE-FEASIBILITY REPORT PAGE 24
7.0. REHABILITATION AND RESETTLEMENT (R&R) PLAN
As per the primary site survey & latest census data available, the mine lease area is
designated as river bed in reserve forest has no habitation & therefore displacement of
population is not applicable therefore no Rehabilitation & Resettlement is envisaged.
However a detailed analysis on socio-economic aspects of the study area is proposed to
be carried out during EIA study of the proposed mine.
8.0. PROJECT SCHEDULE & COST ESTIMATES
8.1. LIKELY DATE OF START OF CONSTRUCTION AND LIKELY DATE OF COMPLETION
No construction activity is involved under the project activity. The mining operations
shall commence after getting all the regulatory compliance including environmental
clearance as applicable
8.2. ESTIMATED PROJECT COST ALONG WITH ANALYSIS IN TERMS OF ECONOMIC VIABILITY OF THE
PROJECT
The Proposed project is a new mine and capital cost of the project includes cost of
machinery and equipments. Breakup of operational cost calculated on the basis of per
tonne of mineral produced is as given below:
Table 7: Operational cost of the project
S. No. Particulars Cost per tonne
(Rs.)
1. Mining cost (inclusive of salaries & wages of
employees & workmen, Stores consumables,
machineries Repairing & maintenance
depreciation & over expenditures)
4720
2. Socioeconomic developments 310
3. Occupational Health & safety 200
4. Environmental management 1818
Total cost per tonne 7048
Selling rate of Sand, Bajri & Boulder varies and the average comes out to be Rs. 13450
per tonne approximately. Hence the project is economically feasible.
SAND/ BOULDER/ BAJRI MINING PROJECT OF RAMGADH RAU RIVER (AREA20.00 HA)
PRE-FEASIBILITY REPORT PAGE 25
9.0. ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS)
9.1. FINANCIAL AND SOCIAL BENEFITS WITH SPECIAL EMPHASIS ON THE BENEFIT TO THE LOCAL
PEOPLE INCLUDING TRIBAL POPULATION, IF ANY, IN THE AREA
The proposed project is found to have both financial and social benefits as listed below:
• The project will provide direct & indirect employment to local people in
different activities such as mining, sizing (sieving) transportation and plantation
activities.
• This project will provide protection to the nearby habitation from submergence
which is cause due to flood in monsoon season.
• The revenue generated from the production and sale of mineral will also add to
the exchequer of government, which in turn will help in the growth of state
economy.
• As the proposed mine area lies in the flood plain, hence the removal of extracted
material will minimize the chances of flood disaster in the area.
• With the emergence of fast growing construction industry of Uttarakhand and
other nearby states Excavated material will also cater the huge increasing
demand of mineral to be used as raw material for construction.
The project is not expected to have any major adverse impact on the environment and
whatever impacts are anticipated during the EIA study will be minimized with the help
of suitable mitigation measures. Hence it is concluded that the project is economically
feasible and financially beneficial to the local people as well as to the country.
************