Page 1: PRE FEASIBILITY REPORT - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Project Site Location (Google Map) 17 • PLOT LAYOUT 8 LAYOUT OF PROPOSED

PRE FEASIBILITY REPORT

for

PROPOSED TREATMENT, STORAGE AND DISPOSAL FACILITY (TSDF)

of

M/s. NARODA ENVIRO PROJECTS LIMITED (NEPL)

Survey No. 124, 125, 125/p & 132, Village: Alva,

Taluka: Dhansura, Dist: Aravalli, Gujarat

Page 2: PRE FEASIBILITY REPORT - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Project Site Location (Google Map) 17 • PLOT LAYOUT 8 LAYOUT OF PROPOSED

CONTENTS

Sr. No. Description Page No.

1. Executive Summary 1

2. Introduction of the Project/Background information 3

3. Project Description 4

4. Site Analysis 11

5. Planning Brief 12

6. Proposed Infrastructure 13

7. Rehabilitation and resettlement (R & R) Plan 14

8. Project Schedule & Cost Estimates 14

9. Analysis of Proposal (Final Recommendations) 14

Page 3: PRE FEASIBILITY REPORT - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Project Site Location (Google Map) 17 • PLOT LAYOUT 8 LAYOUT OF PROPOSED

1

1.0 EXECUTIVE SUMMARY

1.1 Company Profile

Naroda Enviro Projects Ltd. (herein after referred as NEPL/Unit), is a company registered

under Section 25 of the Companies Act, 1956 and working on “No Profit No Loss” basis.

The Company is established in 1995, pursuant to landmark judgment given by Hon'ble

High Court of Gujarat under SCA No.770 of 1995. The Company is working as a Nodal

Agency between Industrial Units and various Government agencies. The Company has

two main Projects; the Common Effluent Treatment Plant (CETP) which is giving services

to the polluting industries of Naroda GIDC Estate and Treatment, Storage and Disposal

Facilities (TSDF), giving services to Industries of Gujarat to dispose their hazardous

waste in scientific manner.

The projects completed & successfully operational are summarized bellow…

• Naroda Eco Park/Paryavaran Mandir at TSDF Hazardous Waste on capped Pit I

• CETP with Multi Effect Evaporator(MEE) 6 stage (300 KLD)

• Wind Mill of 1.25 MW

• Estate Beautification & Greening Project

NEPL has successfully achieved National & International acclamations:

• Indo German Greentech Environment Excellence Award from 2001 to 2005

• Golden Peacock Environmental Management Award for Clean Technology – 2005

• Rajiv Gandhi Shiromani Award – 2009

• International Gold Award by Business Initiative Directions (BID) at New York –

2009

• Indira Gandhi Sadbhavana Award – 2010

• Award for Developing “Green Belt” in Gujarat at the August hands of Hon’ble

Chief Minister Shri Narendra Modi – 2010

• Platinum Technology Award for Quality and Best Trade Name from Otherways,

Switzerland – 2010

• International Diamond Category Award by Business Initiative Directions (BID) at

Geneva–2010

• 1st Category Award from Gujarat Horticulture Association for Consecutive 6 Years

till 2012

• Green Idol Award – 2012 given by leading Daily Newspaper Divyabhaskar

Page 4: PRE FEASIBILITY REPORT - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Project Site Location (Google Map) 17 • PLOT LAYOUT 8 LAYOUT OF PROPOSED

2

• In the year 2014 Bhamasha Award was received by Shri Shailesh I. Patwari at

the August hands of Petroleum Minister, GOI, Shri Dharmendra Pradhan and Shri

Murli Manohan Joshi at New Delhi

• Gauravvanta Gujarati Award by International Creative Art Society during the

month of June 2015 at the August hands of Hon’ble Mayor, Shrimati Minaxiben

Patel.

WAY AHEAD – NEPL future Vision and Mission

From the day first we are committed to use renewable energy by replacing thermal

energy/coal and in the process we have made up our mind to set up nearly 1 MW

Solar Park on capped landfill site at a cost of nearly Rs. 6 crores and likely to save

energy cost of Rs. 15 lacs per month from NEPL CETP, UGVCL charges.

The said Pit II is capped scientifically in May 2014 and nearly 12.5 MT hazardous waste

is collected and dumped scientifically in this pit. We have served all the industries of

Gujarat at a very very concessional rate.

We have supported GPCB to clear unauthorised dumping and collected waste in our site

without charging any cost. Till date more than Rs. 60 lacs of such unauthorised

dumping we have cleared as a CSR activity.

We are also encouraging the PPP model by imparting environmental knowledge amongst

the students of Schools and Technological Universities by holding Seminars and

Innovative Workshops.

Page 5: PRE FEASIBILITY REPORT - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Project Site Location (Google Map) 17 • PLOT LAYOUT 8 LAYOUT OF PROPOSED

3

1.2 Project Details

Sr. No. Facility Capacity

1 Secured Landfill facility (TSDF) for Hazardous waste 27,50,000 MT

1.3 Material Requirement

Not Applicable

1.4 Water Requirement

Total water requirement will be 111 m3/day and shall be met through rain water

harvesting/Tankers (surface water).

1.5 Air Pollution Source and Control Management

There will be emission from D.G. Set -250 KVA x 2 nos. (used during emergency only).

1.6 Hazardous Waste

Not Applicable

1.7 Green Belt

Total 1,07,577.4745 sq. meter land area is available at site; out of this area approximately

20,000 sq. meter area will be allotted for tree plantation and other forms of greenery.

1.8 Power & Fuel Requirements

Electricity Connection: UGVCL

Electricity Requirement: 500 KVA.

D. G. set : 250 KVA x 2 nos. (Stand by).

Coal/Wood briquette= 6 T/Hr. &

HSD at rate of 2 KL/Hr. will be used as fuel in D.G. Sets.

Page 6: PRE FEASIBILITY REPORT - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Project Site Location (Google Map) 17 • PLOT LAYOUT 8 LAYOUT OF PROPOSED

4

2.0 INTRODUCTION OF THE PROJECT/BACKGROUND INFORMATION

2.1 Identification of the project and project proponent. In case of mining project, a copy

of mining lease/letter of intent should be given.

Identification of the project

M/s. Naroda Enviro Projects Limited (NEPL) proposes to develop TSDF site at Survey No. 124,

125, 125/p & 132, Village: Alva, Taluka: Dhansura, Dist: Aravalli, Gujarat.

Identification of the project proponent

M/s. Naroda Enviro Projects Ltd, a company is promoted by various industries in

Ahmedabad.

2.2 Brief description of nature of the Project

Development of Secured Landfill facility (TSDF) for Hazardous waste

2.3 Need for the project and its importance to the country and or region

As per the hazardous waste (Management, Handling and Transboundary Movement) Third

Amendment Rules, 2010 of Environment Protection Act, 1986, hazardous waste generated

by industries has to be collected, transported, treated and disposed in a properly designed

TSDF Facility. The aforesaid rules and its amendments lay down a procedure for collection,

storage, transportation and disposal of hazardous wastes. The scientific disposal of

hazarded waste can be done at a secured landfill, which wills an engineered operation,

design and operation according to acceptable standards. Secured landfill is considered as a

method of disposing waste on land without creating nuisance or hazard to public health or

safety. The landfill facility of NEPL having proposed capacity of 27,50,000 MT.

2.4 Employment Generation (Direct and Indirect) due to project.

M/s. NECL will give direct employment to local people based on qualification and

requirement. In addition to direct employment, indirect employment shall generate

ancillary business to some extent for the local population.

3.0 PROJECT DESCRIPTION

Development of Secured Landfill facility (TSDF) for Hazardous waste.

Page 7: PRE FEASIBILITY REPORT - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Project Site Location (Google Map) 17 • PLOT LAYOUT 8 LAYOUT OF PROPOSED

5

3.1 Type of Project including interlinked and interdependent projects, if any.

No interlinked project has been submitted.

3.2 Location (map showing general location, specific location and project boundary &

project site layout) with coordinates.

• Map showing general location

• Specific location and project boundary

Page 8: PRE FEASIBILITY REPORT - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Project Site Location (Google Map) 17 • PLOT LAYOUT 8 LAYOUT OF PROPOSED

6

Project Site Location (Google Map)

Page 9: PRE FEASIBILITY REPORT - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Project Site Location (Google Map) 17 • PLOT LAYOUT 8 LAYOUT OF PROPOSED

17

• PLOT LAYOUT

Page 10: PRE FEASIBILITY REPORT - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Project Site Location (Google Map) 17 • PLOT LAYOUT 8 LAYOUT OF PROPOSED

8

LAYOUT OF PROPOSED CELL FOR LAND FILLING SITE

Page 11: PRE FEASIBILITY REPORT - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Project Site Location (Google Map) 17 • PLOT LAYOUT 8 LAYOUT OF PROPOSED

9

3.3 Details of alternate sites considered and the basis of selecting the proposed site,

particularly the environmental considerations gone into should be highlighted.

Hazardous waste landfills preferred located in areas of low population density, low

alternative land use value, low ground water contamination potential and at sites having

high clay contain in the subsoil.

Hazardous waste landfill site selected by following the guidelines published by MoEF. The

step by step procedure as follows.

1. Earmarking a “search area” taking into account the location of the waste generation

units and a “search radius” (Typically 5 to 250 Km). The search area is chosen that it

minimizes the number of HW landfills in any region or state.

2. Identification of a list of potential site of on the basis of

a) Availability of Land

b) Collection of preliminary data

c) Restrictions listed in the locational criteria

• The location of the all necessary infrastructural facilities such as power,

transportation, water supply and manpower are easily available.

Project is determined by the following consideration:

• The site is located on Bayad –Dhansura state highway No-59.

• Identified area for landfill does not fall under coastal area, forest and grazing land,

high rainfall area or area with high water table as mentioned in criteria for

hazardous waste landfill by CPCB.

3.4 Size or Magnitude of Operation

Please refer Section-1.2, Page No.2.

3.5 Project Description with process details (a schematic diagram/flow chart showing the

project layout, components of the project, etc. should be given)

Page 12: PRE FEASIBILITY REPORT - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Project Site Location (Google Map) 17 • PLOT LAYOUT 8 LAYOUT OF PROPOSED

10

3.6 Raw Material required along with estimated quantity, likely source, marketing area of

final product/s, mode of transport of raw material and Finished product.

Not Applicable

3.7 Resource optimization/recycling and reuse envisaged in the project, if any, should be

briefly outlined.

After set up of unit, every effort will put to recycle/reuse the water.

3.8 Availability of water its source, energy/power requirement and source should be

given.

Water Source

Total water requirement shall meet through rain water or surface water.

Power & Fuel Requirement

Energy:

Electricity Connection: UGVCL

Electricity Requirement: 500 KVA.

D. G. Set: 250 KVA x 2 nos. (Stand by)

Coal/Wood briquette= 6 T/Hr. &

Fuel : HSD @ 2 KL/Hr.

3.9 Quantity of wastes to be generated (liquid and solid) and scheme for their

management/disposal.

No Waste will be generated from proposed TSDF Facility.

Page 13: PRE FEASIBILITY REPORT - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Project Site Location (Google Map) 17 • PLOT LAYOUT 8 LAYOUT OF PROPOSED

11

3.10 Schematic representations of the feasibility drawing which give information of EIA

purpose.

RECONNAISSANCE SURVEY OF EXISTING PLANT ANNUAL REPORT

MARKET ASSESSMENT

FINANCIAL REPORT

PROJECT REPORT

INTRODUCTION

MONITORING OF AIR, WATER & SOIL QUALITY & NOISE

LEVELS. DATA ON METEOROLOGY SOCIO-ECONOMIC STATUS

& BASIC AMENITIES. SITE VISITS BY AND INTERVIEWS WITH

LOCALS

BASELINE

ENVIRONMENTAL

STATUS

ENVIRONMENTAL INFORMATION CENTRE

CENTRAL GROUND WATER BOARD

GUJARAT POLLUTION CONTROL BOARD (GPCB)

PUBLIC HEALTH ENGINEERING DEPT.

AGRICULTURE DEPARTMENT

FOREST DEPARTMENT

IRRIGATION DEPARTMENT

EMPLOYMENT EXCHANGE

HEALTH CENTER

CENSUS DEPT.

INDIAN METEOROLOGICAL DEPT.

SOCIOECONOMIC

STATUS &

INFRASTRUCTURE

EXISTING

PLANT

FACILITY DESCRIPTION

IMPACTS

METHODOLOGY OF

IMPACT

ASSESSMENT

IDENTIFICATION & ASSESSMENT OF IMPACTS

EVALUATION OF IMPACTS BY MATRIX METHOD

SOURCE OF INFORMATION OVERVIEW OF

E. I. A. STUDIES

ACTIVITIES

ENVIRONMENTAL

MANAGEMENT PLAN

DESCRIPTION OF EFFLUENT TREATMENT PLAN, AIR

POLLUTION CONTROL, HAZARDOUS WASTE MANAGEMENT,

GREEN BELT DEVELOPMENT MONITORING PROGRAM

RISK ANALYSIS

STUDIES &

DISASTER

MANAGEMENT PLAN

SAFETY, HEALTH & ENVIRONMENTAL POLICY, GUIDELINES BY

DIRECTOR GENERAL OF FACTORY SAFETY, MINISTRY OF LABOR. CONSEQUENCE ANALYSIS

PREPARATION OF DISASTER MANAGEMENT PLAN

Page 14: PRE FEASIBILITY REPORT - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Project Site Location (Google Map) 17 • PLOT LAYOUT 8 LAYOUT OF PROPOSED

12

4.0 SITE ANALYSIS

4.1 Connectivity

• Site is very well connected by road

• Availability of water, power, etc.

4.2 Land Form, Land Use and Land Ownership

The detail will be incorporated in EIA study Report.

4.3 Existing land use pattern (agriculture, non-agriculture, forest, water bodies (including

area under CRZ)), shortest distances from the periphery of the project to periphery of the

forests, national park, wild life sanctuary, eco sensitive areas, water bodies (distance from

HFL of the river), CRZ. In case of the notified industrial area, a copy of the Gazette

notification should be given.

The detail will be incorporated in EIA study Report.

4.4 Existing Infrastructure

The proposed project activity will be developed on exhausted mining (Black Trap) Sites so

now there is only open land.

4.5 Soil Classification

The detail will be incorporated in EIA study Report.

4.6 Climatic data from secondary sources.

4.6.1 Temperature Detail

4.6.2 Relative Humidity (RH)

4.6.3 Rainfall

4.6.4 Wind Speed

The detail will be incorporated in EIA study Report.

4.7Social infrastructure available.

The detail will be incorporated in EIA study Report.

Page 15: PRE FEASIBILITY REPORT - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Project Site Location (Google Map) 17 • PLOT LAYOUT 8 LAYOUT OF PROPOSED

13

5.0 PLANNING BRIEF

5.1 Planning Concept (type of industries, facilities, transportation, etc) Town and Country

planning/Development authority classification.

Type of Industry: Proposed TSDF site.

5.2 Population Projection

The detail will be incorporated in EIA study Report.

5.3 Land use planning (breakup along with green belt etc.)

Total Plot Area: 1,07,577.4745 m2

Green Belt Area (Approximately): 20,000 m2

5.4 Assessment of Infrastructure Demand (Physical & Social)

• Employment would be as per prevailing norms of state government for skilled and

unskilled people for the proposed project activity.

• Social Welfare

• Cordial relation with the neighbouring villages shall be established and representation

shall be made to villagers for help for creation of facilities related to health, education,

etc.

5.5 Amenities/Facilities

Details of amenities available in study area

The detail will be incorporated in EIA study Report.

Page 16: PRE FEASIBILITY REPORT - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Project Site Location (Google Map) 17 • PLOT LAYOUT 8 LAYOUT OF PROPOSED

14

6.0 PROPOSED INFRASTRUCTURE

6.1 Industrial Area (Processing Area)

Total Area: 1,07,577.4745 m2

6.2 Residential Area (Non Processing Area)

Processing Area (Green belt area and open area)

Non Processing Area: 37,000 m2

6.3 Green Belt

Green Belt Area (Approximately): 20,000 m2

6.4 Social Infrastructure

6.5 Connectivity (Traffic and Transportation Road/ Rail/Metro/ Water ways etc)

Major factors involved in the selection of site are listed below:

• Site is very well connected by road and rail

• Proximity to Haz. Waste generators

• Availability of sufficient land free from cultivation

• Availability of power evacuation facilities

• Availability of water for industrial use

6.6 Drinking water Management (Source & Supply of water)

Total water requirement shall meet through rain water or surface water.

6.7 Sewerage System

Sewage will be disposed in Septic Tank & soak pit.

6.8 Solid Waste Management

Apart from sewage, there will not be any kind of solid waste generation.

6.9 Power Requirement & Supply/Source

Electricity Connection: UGVCL

Electricity Requirement: 500 KVA

D. G. set : 250 KVA x 2 nos. (Stand by)

Page 17: PRE FEASIBILITY REPORT - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Project Site Location (Google Map) 17 • PLOT LAYOUT 8 LAYOUT OF PROPOSED

15

7.0 REHABILITATION AND RESETTLEMENT (R & R) PLAN

7.1 Policy to be adopted (central/state) in respect of the project affected including home

oustees, land oustees and landless laborers (a brief outline to be given)

There is no habitation on the proposed project activity area and it is barren land which is

purchased for development of facility, so R & R policy is not applicable to this project.

There shall not be displacement of any population in project area. Any major activity that

may lead to resettlement of the people is considered as permanent impact. Hence, there is

no permanent impact on this account. The increasing industrial activity will boost the

commercial and economical status of the locality up to some extent.

8. PROJECT SCHEDULE & COST ESTIMATES

8.1 Likely date of start of construction and likely date of completion (Time schedule for

the project to be given).

Construction work will be started after getting Environment Clearance & CTE & operation of

TSDF will be started after applying for CC&A.

8.2 Estimated Project cost along with analysis in terms of economic viability of the

project.

Total Project cost for proposed project activity is Rs. 45 Crores.

9. ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS)

9.1 Financial and social benefits with special emphasis on the benefit to be local people

including tribal population, if any, in the area.

• Employment would be as per prevailing norms of state government for skilled and

unskilled people for the proposed project.

• Social Welfare shall be done.

• Cordial relation with the neighbouring villages shall be established and representation

shall be made to villagers for help for creation of facilities related to health, education,